Understand Earned Value in Under an Hour! Wayne Brantley, MS Ed, PMP, ACP, CSM, CSPO, ITIL, CRP, CPLP Associate VP of Professional Education
|
|
- Allyson Pierce
- 7 years ago
- Views:
Transcription
1 Understand Earned Value in Under an Hour! Wayne Brantley, MS Ed, PMP, ACP, CSM, CSPO, ITIL, CRP, CPLP Associate VP of Professional Education
2 Villanova University 100% online courses in critical certifications: Agile Management Project Management Six Sigma Business Analysis Contract Management Business Intelligence Business Process Management Leadership HR Management Cyber Security S/W Testing ITIL
3 Overview Establish the link between the requirements and the performance measurement baseline Understand what the Earned Value calculations are measuring Explain Earned Value as an easy to use tool for project performance measurement
4 Earned Value and The DaVinci Code
5 Earned Value and The DaVinci Code
6 Why Do We Need Earned Value? 1994 The Chaos Report Approximately 70% of projects are: o Over budget o Behind schedule 52% of all projects finish at 189% of their initial budget *Standish Group: Chaos Report
7 How do your projects perform today? Do you have projects that are over budget? Do you have projects that are late? Do you have projects that have scope creep?
8
9
10 How do your projects perform?
11 Why don t we want to measure? No one wants to know they have an ugly baby!
12 Variance Analysis is the Great Lie Planned Actuals You planned to do $100k of work in one month You spent $110k Variance = -$10k Now tell me how much of the work is completed?
13 What is Earned Value Management? Earned Value Analysis is: An industry standard way to: o Measure a project s progress o Forecast it s completion date and final cost o Provide schedule and budget variances along the way
14 What is Earned Value Management? EV compares: The PLANNED amount of work (PV) that has actually been COMPLETED (EV) and how much the work ACTUALLY COST (AC)
15 What EV Tells You Where you are on schedule Where you are on budget Where you are on work accomplished
16 Why you should know Earned Value 1. So you can say you are an EVM expert 2. Because there are some questions on the PMP exam 3. Because you need to control project delays and overruns 4. Government legislation requires it 5. RFP requires it
17 Earned Value Management Thresholds in the Government Federal Agency EVM Threshold EVMS Threshold DoD, NASA $20-$50 million EVMS required DoD, NASA Greater than $50 million EVMS implementation & process must be verified GSA Greater than $20 million EVMS required; implementation & process must be verified DoE Greater than $20 million EVMS required EPA Greater than $5 million EVMS required FAA Greater than $10 million EVMS required
18 Six Essential Elements to Implementing an Earned Value Management System Good requirements A detailed WBS Good estimates for durations Good estimates for budgets A good schedule A performance measurement baseline
19 How is learning Earned Value like eating an elephant? One bite at a time
20 What You Need to Know to do Earned Value Scope, Requirements, and the WBS Understand the link between requirements and the WBS Scheduling Understand the development of a schedule and time estimates Budgeting Understand how cost estimates are developed Earned Value Identify how earned value calculations are accomplished Reporting Know how earned value (EV) can be used to measure project progress
21 Understand the link between requirements and the WBS
22 Understanding the link between requirements and the WBS Where do we start in order to gather requirements? Request for Proposal Statement of Work Contract Project Charter Any others?
23 The Project Charter What should be in a Project Charter? 1. Sponsor authorization and signs-off 2. Project Manager assigned Other considerations? o Requirements o Business need o Project purpose o Milestones o Stakeholder influences o Functional organizations o Assumptions and constraints o Summary budget
24
25 Obtaining Good Requirements Why are good requirements essential? SCOPE
26 Obtaining Good Requirements How do you obtain good requirements? Take time to do it Ask the right people the right questions Draw a picture Build a model Build a little Check and re-check (CYA)
27 Obtaining Good Requirements How do you obtain good requirements? Take time to do it Ask the right people the right questions Draw a picture Build a model Build a little Check and re-check (Cover Your Activities)
28 Dilbert s view on requirements gathering
29
30
31
32
33
34
35
36
37 Understanding the link between requirements and the WBS What is a WBS? A deliverable-oriented hierarchical decomposition of the work to be executed by the project team to accomplish the project objectives and create the required deliverables.
38 Understanding the link between requirements and the WBS Why is a WBS so important? How low do you go? Project (1.0) odeliverables (1.1, 1.2, 1.3,..) Tasks (1.1.1, 1.1.2, 1.1.3,.) Activities ( , ,.) Why an 80 - hour rule?
39
40 Thou shalt not have work packages over 80 hours
41 Scheduling - Understand the Development of a Schedule
42 42 Dilbert Looks at Scheduling
43 Scheduling What do we have at this point? Requirements WBS Who would you go to determine what must be done and in what order? What tools are available for scheduling?
44 The Most Powerful Scheduling Tool
45 Scheduling What do we have at this point? Requirements WBS Who would you go to determine what must be done and in what order? What tools are available for scheduling? What do scheduling and a game of chess have in common?
46 46
47 Scheduling 101 Critical scheduling questions What comes first? What comes second? Any restrictions? Any constraints?
48 The Gantt Chart View Task Days Days Days Days Days Days Days Days 16 - End Days
49 Budgeting - Understand how cost estimates are developed
50 Budgeting What do you have at this point? Requirements WBS Schedule Where do your cost estimates come from? Where should they come from? What are the differences?
51 The Gantt Chart View - Cost at $10,000/day per task Task Days Days Days Days Days Days Days Days 16 - End Days
52 Building the cumulative cost curve $10,000/day each task
53 - The Cumulative Cost Curve - S Curve - - Performance Measurement Baseline -
54 BAC = $290k PV = $200k
55 Earned Value Identify how earned value calculations are accomplished
56 Spending Rates Budget at completion is $290k Why at day 9 (half of 18 days) are we at $200k and not $145k (half of $290k)? Why is the cost curve not linear? How does this correlate to EV? Spending Rates?
57 Tying in the Cumulative Cost Curve and EV Planned Value (PV) = Planned costs for the planned work to be done at a particular time (BCWS) Earned Value (EV) = The percentage of the planned work that was accomplished (BCWP) Actual Costs (AC) = Amount spent on the work that was accomplished (ACWP) Budget At Completion (BAC) = Total of all planned costs
58 Tying in the Cumulative Cost Curve and EV BAC = $290k is the total costs of all work to be done PV (BCWS) = $200k is amount spent through Day 9 EV (BCWP) = The % assessed of the work completed AC (ACWP) = The actual costs spent on the work done
59 Why People Hate Earned Value The Math Who has had Calculus 3 or Differential Equations?
60
61 Earned Value Formulas Variance Analysis = subtraction formulas Cost Variance (CV) = Earned Value (EV) Actual Costs (AC) (EV-AC) Schedule Variance (SV) = Earned Value Planned Value (PV) (EV-PV) Performance Indices = division formulas Cost Performance Index (CPI) = Earned Value / Actual Costs (EV/AC) Schedule Performance Index (SPI) = Earned Value / Planned Value (EV/PV)
62 How to create the EV formulas on test day EV PV AC
63 How to create the EV formulas on test day EV PV AC SV = SPI = CV = CPI =
64 How to create the EV formulas on test day EV PV AC SV = SPI = EV EV CV = EV CPI = EV
65 How to create the EV formulas on test day EV PV AC SV = SPI = EV EV - / CV = EV - CPI = EV /
66 How to create the EV formulas on test day EV PV AC SV = SPI = EV EV - / CV = EV - AC CPI = EV / AC
67 How to create the EV formulas on test day EV PV AC SV = SPI = EV EV - / PV PV CV = EV - AC CPI = EV / AC
68 How to create the EV formulas on test day EV PV AC SV = SPI = EV EV - / PV PV EAC = CV = EV - AC CPI = EV / AC
69 How to create the EV formulas on test day EV PV AC SV = SPI = EV EV - / PV PV EAC = BAC/CPI CV = EV - AC CPI = EV / AC
70 How to create the EV formulas on test day EV PV AC SV = SPI = EV EV - / PV PV EAC = BAC/CPI CV = EV - AC = AC + (BAC-EV) = AC +[BAC-EV)/ CPI = EV / AC (CPIXSPI)]
71 How to create the EV formulas on test day EV PV AC SV = SPI = EV EV - / PV PV EAC = BAC/CPI CV = EV - AC CPI = EV / AC
72 How to create the EV formulas on test day Notice all formulas are dependent on EV Typical variance analysis is planned actual dollars spent or in earned value language PV AC We are determining the percent of the work that was completed (= EV) based on what we planned to do (= PV) EV shows you what you did versus what you said you would do
73 Reporting Know how earned value (EV) can be used to measure project progress
74 Dilbert Looks at EV Meetings 74
75 Dilbert Looks at EV Meetings Earned Value 75
76 Earned Value Calculations Time to do the Math! We know the following: BAC = $290k Day 9 PV what is it? o Planned Value (PV) to spend is $200k If at day 9 we have accomplished 80% of the scheduled work we can calculate the EV. What is it? Earned Value (EV) is $160k = 80% of PV ($200k) Accounting tells us we have spent $175,000 what does this tell us? The Actual Cost (AC) is $175k
77 Earned Value Calculations PV, EV, AC CV CPI SV SPI EAC
78 Earned Value Calculations - Costs PV = $200k EV = $160k AC = $175k CV = EV - AC 160k-175k = -$15k (Over Budget) Rule of thumb = negative is BAD! CPI = EV / AC 160k/175k = $.91 or 91%
79 How are we doing? It depends What was an acceptable variance? +/- 15%
80 Earned Value Calculations - Schedule PV = $200k EV = $160k AC = $175k SV = EV - PV 160k - 200k = -$40k (Behind Schedule) SPI = EV / PV 160k / 200k = $.80 or 80% How are we doing? +/-15% How about as compared to CPI?
81 Earned Value Calculations - EAC The CPI?.91 BAC? $290k Now you can calculate the EAC = BAC/CPI $290k/.91 = $318k
82 Forecasting - Where are you trending? EAC = $318k BAC = $290k
83 Forecasting calculations EAC = BAC / CPI = $290k /.91 = $318k ETC = EAC EV = $318k - $160k = $158K VAC = BAC EAC = $290k - $318k = -$28k TCPI = (BAC EV) / (BAC AC) = $290k - $160k / $290k - $175k $130k / $115k = 1.13
84 Did you see what happened? G.I.G.O.
85 Summary Establish the link between the requirements and the performance measurement baseline Understand what the Earned Value calculations are measuring Explain Earned Value as an easy to use tool for project performance measurement
Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance.
About the Tutorial Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance. This is a brief tutorial that acquaints
More informationINSE 6230 Total Quality Project Management
Lecture 5 Project Cost Management Project cost management introduction Estimating costs and budgeting Earned Value Management (EVM) 2 IT projects have a poor track record for meeting budget goals Cost
More informationEarned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP
Earned Value Exercise 1 Running head: Earned Value Exercise Earned Value Exercise SuCheng Wu MET AD 644: Project Risk, and Cost Management Paul B. Cook, PhD PMP Earned Value Exercise 2 Case 1: Background:
More informationRules on using templates. MECH 896 Professional Development for MEng Students. Assignment #6A: Questions. Homework Discussion
MECH 896 Professional Development for MEng Students Mohamed Hefny and Brian Surgenor (hefny@cs.queensu.ca and surgenor@me.queensu.ca) Rules on using templates 1) Must reference the template used 2) Use
More informationA Gentle Introduction to Earned Value Management Systems
A Gentle Introduction to Earned Value Management Systems Good metrics let us see if we are doing the right things and doing them well." Niwot Ridge Consulting 4347 Pebble Beach Niwot, Colorao www.niwotridge.com
More informationEarned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1
Earned Value Valerie Colber, MBA, PMP, SCPM Not for duplication nor distribution 1 Where did Earned Value Management come from? In 1967 the Department of Defense (DoD) established the Cost/Schedule Control
More informationAn introduction to Earned Value Analysis
An introduction to Earned Value Analysis Prepared by: Suketu Nagrecha, MBA, PMP, CNA March 16, 2002 Earned Value Analysis - 2 Abstract Earned value analysis is a method of performance measurement. Many
More informationProject Cost Management
Project Cost Management Guide to Mathematical Questions PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Present
More informationEarned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition.
Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition. Errata for Chapter 7 (Replacement pages provided) Deleted up to a given point in time from the description
More informationBrainstorm. What is Cost and Project Cost Management?
Brainstorm Suppose you need to create a network from scratch in your organization's headquarter. Your project is named HQ Network. Your major deliverables includes: LAN, WAN, server room, workstations,
More informationEarned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting. Prepared by:
Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting Prepared by: Module 6: Metrics, Performance Measurements and Forecasting Welcome to Module 6. The objective
More informationEarned Value Formulae
Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from http://www.mosaicprojects.com.au/techniques.html#earnedvalue
More informationIntroduction to earn value management in Civil Engineering
3 rd World Conference on Applied Sciences, Engineering & Technology 27-29 September 2014, Kathmandu, Nepal Introduction to earn value management in Civil Engineering S. K. KAMANE, S. A. MAHADIK, A. C.
More informationGPMCEP GLOBAL PROJECT MANAGEMENT, LLC C O U R S E
C O U R S E C E GPMCEP GLOBAL PROJECT MANAGEMENT, LLC Project Management Professional (PMP) Certification Exam Prep Global Project Management, LLC is a Global Registered Education Provider (R.E.P.) of
More informationEARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT
EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT Assoc. Prof. Anca Mehedintu Ph. D University of Craiova Faculty of Economics and Business Administration Craiova, Romania Prof. Cerasela Pirvu
More informationEstimating Cost at Completion - Judgment & EV Information
Page 1 of 10 Estimating Cost at Completion - Judgment & EV Information Cost estimating is often called a "black art" and, too often, estimates are structured to fit some predetermined idea of a number
More informationIST 302 : Project Cost Management
IST 302 : Project Cost Management Project Cost Management : Why do we care? 1 Cost and Cost Management Cost: Cost Management: Project Cost Management Processes Cost Estimating Developing an estimate of
More informationSimple Earned Value (Using MS Project 2010)
Simple Earned Value (Using MS Project 2010) This document outlines a Simple Earned Value technique, a technique which sticks to a simple 0/100% Milestone approach with some Level of effort tasks maintained
More information700 Analysis and Reporting
Jefferson Science Associates, LLC 700 Analysis and Reporting Project Control System Manual Revision 7-50 - 700 Analysis and Reporting This chapter of the JSA Project Control System Manual explains how
More informationChapter 7. (PMBOK Guide)
Chapter 7 Project Cost Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: marajabi@ut.ac.irac ir Homepage:
More informationAACE International Recommended Practice No. 86R 14
AACE International Recommended Practice No. 86R 14 VARIANCE ANALYSIS AND REPORTING TCM Framework: 9.1 Project Cost Accounting 9.2 Progress and Performance Measurement 10.1 Project Performance Assessment
More informationCPM -100: Principles of Project Management
CPM -100: Principles of Project Management Lesson B: Time and Cost Management Presented by Bruce R. Shaw, P.E., PMP starshaw@starpower.net Ph: 703-922-2772 Presented at the PMI-CPM 2002 Fall Conference
More informationHow To Manage A Project
Project Management Institute Practice Standard for EARNED VALUE MANAGEMENT Global Project Management Institute Practice Standard for Earned Value Management Practice Standard for Earned Value Management
More informationTHE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH
THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH By Nghi M. Nguyen, Ph.D., PE, PMP. * INTRODUCTION The management of engineering projects
More informationUsing Earned Value Management for Improving Processes. By Cynthia K. West
Using Earned Value Management for Improving Processes By Cynthia K. West Summary: This article explains earned value management and explores how the metric can be used to improve project and business processes.
More informationEarned Value and Agile Reporting
Earned Value and Agile Reporting Anthony Cabri, Mike Griffiths Quadrus Development Inc. Abstract This paper reviews the concepts of Earned Value Management established in traditional project management,
More informationL10: Budgeting and Cost Control. Olivier de Weck
ESD.36 System Project Management + L10: Budgeting and Cost Control Instructor(s) Olivier de Weck Lecture 10 Oct. 11, 2012 System Project Management ESD.36 Framework Project Preparation Enterprise has chosen
More informationSelftestengine..PMI-SP.270 questions PMI-SP. PMI Scheduling Professional
Selftestengine..PMI-SP.270 questions Number: PMI-SP Passing Score: 800 Time Limit: 120 min File Version: 5.1 PMI-SP PMI Scheduling Professional This study guides are so comprehensible that anyone can understand
More informationModule 5 Cost Management PMP Exam Questions
Module 5 Cost Management PMP Exam Questions PMP, PMBOK and the Registered Education Provider logo are registered marks of the Project Management Institute, Inc Question 1 A company, which provides professional
More informationCOINS EVA Earned Value Analysis
COINS EVA Earned Value Analysis Nigel Cope July 2006 Earned Value Analysis The most widely used method for performance measurement of projects Combines scope, cost and schedule patterns Informs project
More informationChapter 7: Project Cost Management. Munawar moenawar@gmail.com
Chapter 7: Project Cost Management Munawar moenawar@gmail.com Learning Objectives Understand the importance of project cost management. Explain basic project cost management principles, concepts, and terms.
More informationtechnical tips and tricks
technical tips and tricks Applying Earned Value Analysis Document author: Produced by: Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the smart
More informationProject Cost Management
Project Cost Management Martin Pazderka martin.pazderka@inso.tuwien.ac.at INSO - Industrial Software Institut für Rechnergestützte Automation Fakultät für Informatik Technische Universität Wien Agenda
More informationEVM.01. Earned Value Analysis Why it Doesn't Work
EVM.01 Earned Value Analysis Why it Doesn't Work Mr. Joseph A Lukas, PE CCE F or many companies looking to improve project performance, earned value analysis (EVA) seems a logical technique to use on projects
More informationBasic Concepts of Earned Value Management (EVM)
Basic Concepts of Earned Value Management (EVM) This article provides an introduction to the basic concepts of earned value management (EVM), from initial project planning through execution including data
More informationPredicting progress on your project
www.nonsuch.co info@nonsuch.co Predicting progress on your project - using Lego bricks to understand Earned Value September 4 PM Conference 2015 Presented by Youssef Mourra Director, Principal Consultant
More informationAdjust MS Project default settings to meet the needs of your project. Loading Analysis is an iterative process. Where are you overloaded?
Resource Loading: who and/or what needed where and when. Adjust MS Project default settings to meet the needs of your project. Loading Analysis is an iterative process. Where are you overloaded? Resource
More informationUnit 5: Cost Management (PMBOK Guide, Chapter 7)
(PMBOK Guide, Chapter 7) The questions on this topic have historically been more difficult than average for some exam takers because of unfamiliarity with some of the math. You will be responsible for
More informationProfesor: Francisco Javier Sanz Pérez. by fjspsv, 2011. PMP Test C07_01
PMP Test C07_01 01. One common way to compute estimate at completion (EAC) is to take the budget at completion (BAC) and: A. Divide by SPI. B. Multiply by SPI. C. Multiply by CPI. D. Divide by CPI. 02.
More informationEarned Value Analysis Exercise
Earned Value Analysis Exercise www.spmbook.com Author: Adolfo Villafiorita Revision: 2 (205-02-06) Given the following project plan: ID Task Immediate Predecessor (*) Expected Duration (days) Budget ($)
More informationProject Management. ZEUS Student Seminar on 14 th November 2003 by Riko Wichmann. Riko Wichmann, MPY Zeus Student Seminar - PM, 14.11.
Project Management ZEUS Student Seminar on 14 th November 2003 by Riko Wichmann Riko Wichmann, MPY Zeus Student Seminar - PM, 14.11.2003 1 Project Management - Training Program - Project Scope Management
More informationEarned Value Management and the Government Program Office. Blair Alan Knapp Jr. MSPM PMP
Earned Value Management and the Government Program Office Blair Alan Knapp Jr. MSPM PMP Agenda EVM Information Alignment OMB Exhibit 300 and Funding Government Program Office Challenges Government Program
More informationVIII. Project Management Glossary
https://www.wrike.com/project-management-guide/glossary/ VIII. Project Management Glossary Project management, like any other industry, has its share of unique terms. Don t be overwhelmed. Here is our
More informationIQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques
IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques Kym Henderson Former Education Director, PMI Sydney Chapter March 2003 to March 2007 Kym.Henderson@froggy.com.au
More informationApplied Project Management ( APM )
Applied Project Management Applied Project Management ( APM ) TRAINING PROGRAM Page 1 Of 7 APPLIED PROJECT MANAGEMENT PRO PROGRAM OVERVIEW This course provides in-depth Project Management Training and
More informationtechnical tips and tricks
technical tips and tricks Earned Value Analysis Overview Document author: Produced by: Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the smart
More informationCertification Exam Objectives: PK0-003
Certification Exam Objectives: PK0-003 INTRODUCTION The CompTIA Project + examination is designed for business professionals involved with projects. This exam will certify that the successful candidate
More informationSoaDssPm: A new Service-Oriented Architecture of the decision support system for the Project Management.
SoaDssPm: A new Service-Oriented Architecture of the decision support system for the Project Management. Fatima Boumahdi, Rachid Chalal Abstract This paper presents an architecture for the Project Management,
More informationManaging Project Budgets with MS Project. Sonja Streuber, PMP, SSBB
Managing Project Budgets with MS Project Sonja Streuber, PMP, SSBB Sonja Streuber Project Mgmt & Engineering, Six Sigma, Risk Mgmt & Risk Analysis: 2000 2003 Agilent Technologies 2003 2009 Lockheed Martin
More informationPune, MH, India. 2 P.G. Student, Imperial College of Engineering & Research, Wagholi, Pune, MH, India. wit.vaishnavi@gmail.com
COST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHOD Dr. Arun Dhawale 1 Vaishnavi Tuljapurkar 2 1 Head of Department, Associate Professor, Department of Civil Engineering, Imperial College of
More informationThe Two Most Useful Earned Value Metrics: the CPI and the TCPI
PM WORLD TODAY SECOND EDITIONS JUNE 2009 Editor s note: Second Editions are papers that have been previously published that have continued relevance and deserve additional visibility. The paper below was
More informationProcurement Management S# What? Formula Additional Notes CPPC CPFF CPAF CPIF T&M FPEPA FPAF FPIF FFP
PMP Formulae & Tips Cheat Sheet P a g e Integration Management Develop Project Charter process Project Selection Methods (>> Benefit Measurement Methods >> Economic Models -7) Present Value (PV) FV The
More informationChapter 3: Project Cost Management
Chapter 3: Project Cost Management Learning Objectives o Understand the importance of project cost management. o Explain basic project cost management principles, concepts, and terms. o Discuss different
More informationAppendix D Glossary Of Terms
Appendix D Glossary Of Terms The notational style used in this glossary is to begin the definition of each defined term with a new paragraph beginning with the term in UPPERCASE. Any word or phrase used
More informationExpert Reference Series of White Papers. Importance of Schedule and Cost Control
Expert Reference Series of White Papers Importance of Schedule and Cost Control 1-800-COURSES www.globalknowledge.com Importance of Schedule and Cost Control Bill Scott, PE, PMP, PgMP Outline I. Project
More informationInformation Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu
Management, Sixth Edition Note: See the text itself for full citations. More courses at cie-wc.edu Understand the importance of project cost management Explain basic project cost management principles,
More informationPMI Lexicon of Project Management Terms
Project Management Institute PMI Lexicon of Project Management Terms Version 3.0 Published by: Project Management Institute, Inc. 14 Campus Boulevard Newtown Square, Pennsylvania 19073-3299 USA Phone:
More informationProject Management: Tracking Progress and Earned Value with MS Project 2003
Project Management: Tracking Progress and Earned Value with MS Project 2003 Project Planning Suppose you have been assigned a project to construct a website in a certain time frame and given a certain
More informationProject Management Institute (PMBOK 2000) PMP Preparation Worksheet
Project Integration Management Processes required to ensure that the various elements of the project are properly coordinated to meet / exceed stakeholder expectations. Project Plan Development Other ning
More informationTracking Budgets and Schedules
Tracking Budgets and Schedules David V. Tennant, PE, PMP One of the simplest questions you are likely to encounter as an engineering or project manager is: Are we on budget and schedule? While this is
More informationLecture Slides for Managing and Leading Software Projects. Chapter 8: Measuring and Controlling Work Processes
Lecture Slides for Managing and Leading Software Projects Chapter 8: Measuring and Controlling Work Processes developed by Richard E. (Dick) Fairley, Ph.D. to accompany the tet Managing and Leading Software
More informationChapter 7: Project Cost Management. Information Technology Project Management, Fourth Edition
Chapter 7: Project Cost Management Information Technology Project Management, Fourth Edition Learning Objectives Understand the importance of project cost management. Explain basic project cost management
More informationpm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS
pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development
More informationCVR/IT Consulting LLC
2011 CVR/IT Consulting LLC All Rights Reserved 1 www.cvr-it.com info@cvr-it.com Overview Easy Earned Value CVR/IT Consulting LLC 2011 CVR/IT Consulting LLC All Rights Reserved 2 Introduction Earned Value
More informationEarned Value Management Guidelines
Effective Date: April 21, 2009 Status: Revision 1 Supersedes: NA Document Owner: Director, Environmental and Engineering Program Introduction This paper provides guidance and recommendations for the application
More informationPROJECTS SCHEDULING AND COST CONTROLS
Professional Development Day September 27th, 2014 PROJECTS SCHEDULING AND COST CONTROLS Why do we need to Control Time and Cost? Plans are nothing; Planning is everything. Dwight D. Eisenhower Back to
More informationPMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION
PMP SAMPLE QUESTIONS http://www.tutorialspoint.com/pmp-exams/pmp_sample_questions_set2.htm Copyright tutorialspoint.com BASED ON PMBOK 5TH EDITION Here are 200 more objective type sample questions and
More informationProject Control with ProTrack
Project Control with ProTrack 1.0 (last update: 11/11/08) 1 Project Control with ProTrack by Mario Vanhoucke Professor at Ghent University and Vlerick Leuven Gent Management School (Belgium) Partner OR-AS
More informationWhat is the Health of my Project?
WHITE PAPER What is the Health of my Project? The Use and Benefits of Earned Value Table of Contents How s My Project Doing?...1 Need a Solution? Earned Value to the Rescue!...1 My actual costs are less
More informationProject Cost Management
Project Cost Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points To Note Please
More informationPROJECT MONITORING AND CONTROL USING BURNDOWN CHARTS
The 4 th edition of the Interdisciplinarity in Engineering International Conference Petru Maior University of Tîrgu Mureş, Romania, 2009 PROJECT MOITORIG AD COTROL USIG BURDOW CHARTS Attila Vajda Sysgenic
More informationPERFORMANCE AND QUALITY IN PROJECTS Project Management and Leadership 2016D, PhD, PMP
PERFORMANCE AND QUALITY IN PROJECTS Project Management and Leadership 2016D, PhD, PMP PROJECTS PROGRESS WELL UNTIL 70% Quick progress until 60-70% complete. Then we discover the project is in distress.
More informationText. Key Performance Measures in a Lean Agile Program. Thomas Blackburn 2/19/2015
Text Key Performance Measures in a Lean Agile Program Thomas Blackburn 2/19/2015 Goal and Objectives Discussion on Current Performance Measurement in Agile Shared understanding of measures that can drive
More informationPMP PREP QUICK STUDY GUIDE BY THE PERSIMMON GROUP
PMP PREP QUICK STUDY GUIDE BY THE PERSIMMON GROUP Frequently Asked Questions What is the PMP credential? The PMP (Project Management Professional) credential is a globally recognized certification for
More informationPMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION
PMP SAMPLE QUESTIONS http://www.tutorialspoint.com/pmp-exams/pmp_sample_questions.htm Copyright tutorialspoint.com BASED ON PMBOK 5TH EDITION Here are 200 more objective type sample questions and their
More informationChapter 5: Project Cost Management
Chapter 5: Project Cost Management 1 Learning Objectives Understand the importance of good project cost management Explain basic project cost management principles, concepts, and terms Describe how resource
More informationQUALITY AND PERFORMANCE IN PROJECTS. Project Management and Leadership 2015D, PhD, PMP
QUALITY AND PERFORMANCE IN PROJECTS Project Management and Leadership 2015D, PhD, PMP Our PROGRAMME: 1. INTRODUCTION TO PROJECT MANAGEMENT 2. STARTING A PROJECT 3. WORK MOTIVATION 4. COMMUNICATION 5: TEAMS
More informationBEYOND EARNED VALUE: A Better Practice for Monitoring Project Performance 2012 Dr. Kenneth F. Smith, PMP ; Project Management Consultant
BEYOND EARNED VALUE: A Better Practice for Monitoring Project Performance 2012 Dr. Kenneth F. Smith, PMP ; Project Management Consultant Introduction Earned Value (EV) has been around since the 1960 s
More informationForecasting Project Schedule Completion by Using Earned Value Metrics
Forecasting Project Schedule Completion by Using Earned Value Metrics Ing. Stephan Vandevoorde Sr. Project Manager Fabricom Airport Systems svv@fabricom.be 1 Agenda Introduction Schedule performance indicators
More information10.1 Communications Planning 10.2 Information Distribution Figure 10 1 10.3 Performance Reporting 10.1 Communications Planning 10.
PROJECT 10 COMMUNICATIONS MANAGEMENT Project Communications Management includes the processes required to ensure timely and appropriate generation, collection, dissemination, storage, and ultimate disposition
More informationAssignment 2: Microsoft Project Toolset. Eric Palmer & Mahindra Bheodari. Kennesaw State University. IS 8100 Spring 2015
Assignment 2: Microsoft Project Toolset 1 Assignment 2: Microsoft Project Toolset Eric Palmer & Mahindra Bheodari Kennesaw State University IS 8100 Spring 2015 Assignment 2: Microsoft Project Toolset 2
More informationCONVERTING TO PHYSICAL % COMPLETE METHOD OF EARNED VALUE IN MICROSOFT PROJECT
CONVERTING TO PHYSICAL % COMPLETE METHOD OF EARNED VALUE IN MICROSOFT PROJECT PREPARED BY James E Aksel, PMP jim@projectpmo.com http://www.msprojectdblog.com http://www.projectpmo.com Page 1 of 19 Table
More informationLEADING EDGE FORUM CSC PAPERS 2012 EARNED SCHEDULE: FROM EMERGING PRACTICE TO PRACTICAL APPLICATION
LEADING EDGE FORUM CSC PAPERS 2012 EARNED SCHEDULE: FROM EMERGING PRACTICE TO PRACTICAL APPLICATION Author Bill Mowery MPM, PMP Keywords Earned Value Management, Earned Schedule, Project Management, Cost
More informationperformance management system that is based on Earned Schedule Management.
The aim of this presentation is to share lessons learned from using a project performance management system that is based on Earned Schedule Management. Earned Schedule Management is a new method created
More informationAnalysis and Application of Earned Value Management in Software Development
Analysis and Application of Earned Value Management in Software Development Frank Tsui School of Computing and Software Engineering Southern Polytechnic State University, Marietta, Georgia, USA 30060 Abstract
More informationProject Management Glossary
Project Management Glossary THE VOCABULARY OF ACHIEVEMENT RON BLACK THE MENTOR GROUP WWW.RONBLACK.COM 800-381-8686 This glossary is an excerpt from Ron Black s book, The Complete Idiot s Guide to Project
More informationPROJECT COST MANAGEMENT
PROJECT COST MANAGEMENT http://www.tutorialspoint.com/pmp-exams/project_cost_management.htm Copyright tutorialspoint.com Here is a list of sample questions which would help you to understand the pattern
More informationTowards a Multi-Dimensional Framework for Assessing the Value of. Software Projects
Towards a Multi-Dimensional Framework for Assessing the Value of Software Projects by John Richard Kopp Submitted in partial fulfillment of the requirements for the Master s degree in Software Development
More informationIntegration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects. Abstract. Introduction
Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects Puian Masudifar, Deputy CEO, VIRA Consulting Engineers Fereydoun Fardad, Aryana Project Management
More informationTracking Software Development Progress with Earned Value and Use Case Point
ISBN 978-952-5726-06-0 Proceedings of the 2009 International Workshop on Information Security and Application (IWISA 2009) Qingdao, China, November 21-22, 2009 Tracking Software Development Progress with
More informationGuided Process across Project Management; Preliminary phase: Contract Preparation
Electronics Technology Department FINAL PROJECT Guided Process across Project Management; Preliminary phase: Contract Preparation Author: Mª Pilar Albertos Mesonero Director: Bernardo Delicado Trapero
More informationPROJECT MANAGEMENT PLAN CHECKLIST
PROJECT MANAGEMENT PLAN CHECKLIST The project management plan is a comprehensive document that defines each area of your project. The final document will contain all the required plans you need to manage,
More informationDCMA DCMA-EA PAM 200.1. October 2012
DCMA Earned Value Management System (EVMS) Program Analysis Pamphlet (PAP) DCMA-EA PAM 200.1 October 2012 THE DCMA ENGINEERING AND ANALYSIS EXECUTIVE DIRECTOR IS RESPONSIBLE FOR ISSUANCE AND MAINTENANCE
More informationExpert Reference Series of White Papers. Tips and Techniques to Pass the PMP Exam
Expert Reference Series of White Papers Tips and Techniques to Pass the PMP Exam 1-800-COURSES www.globalknowledge.com Tips and Techniques to Pass the PMP Exam Dan Stober, PMP Introduction Passing the
More informationIT Project Management Methodology. Project Scope Management Support Guide
NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA IT Project Management Methodology Project Scope Management Support Guide Version 0.3 Version Date Author Change Description 0.1 23 rd Mar, 2013 Gerald
More informationEarned Value Management Tutorial Module 8: Reporting. Prepared by:
Earned Value Management Tutorial Module 8: Reporting Prepared by: Module 8: Government Required Reports Welcome to Module 8. The objective of this module is to introduce you to Government required reports.
More informationPMP Exam Preparation Answer Key
Chapter 2 Answers 1) d) They are all of equal importance unless otherwise stated The Triple Constraint of Project Management is that Scope, Time, and Cost are all equal unless otherwise defined as such.
More informationEarned Value Probabilistic Forecasting Using Monte Carlo Simulation
Earned Value Probabilistic Forecasting Using Monte Carlo Simulation Ricardo Viana Vargas, MSc, PMP Professor Getulio Vargas Foundation - Brazil Chair - Grupo A&C Brasil ricardo.vargas@uol.com.br ou rvargas@aec.com.br
More informationProject Cost Management. Richard Boser
Project Cost Management Richard Boser Project Cost Management Introduction Course Objectives Upon completing today s activities you will be knowledgeable of tools and techniques to: Allocate overall costs
More information