GC-208 Preparing for the CPSR A Practical Guide. Christine Williamson, Member, Watkins Meegan LLC Rich Wilkinson, Director, Watkins Meegan LLC
|
|
- Phyllis Pearson
- 7 years ago
- Views:
Transcription
1 GC-208 Preparing for the CPSR A Practical Guide Christine Williamson, Member, Watkins Meegan LLC Rich Wilkinson, Director, Watkins Meegan LLC
2 Session Content Background Where to Start (And, It s Not Where You Think) Procurement Policies and Procedures The Process A Look Forward Questions
3 Background
4 Background The Contractor Purchasing System Review (CPSR) has been around since the early days of DCAA DCMA has had primary responsibility for the review at Major Contractors (>$50M of ADV) since 1990 (DCAA did the smaller firms if and when they were reviewed) DCMA now has sole responsibility for the CPSR under the final DFARS Business Systems Rule (Feb 2012) DCAA may assist at the request of DCMA Purchasing System adequacy determination is the sole purview of the Administrative Contracting Officer (ACO)
5 The Business Systems Rule DFARS defines six (6) contractor systems subject to determination of adequacy (subject to applicability) Three are audited by DCAA Accounting (1) Estimating (1) Material Management Accounting System (MMAS) (2) The remaining three are reviewed (not audited) by DCMA Purchasing (3) Government Property (2) Earned Value Management (2) (1) Always applicable (2) Applicable only when system is required (3) Applicable, but reviewed only above a threshold or on request
6 More on Business Systems Authority for adequacy determinations vested solely in the ACO DCAA issues findings and can recommend, but not determine DCAA will report findings in subsequent reports as if it was making a determination nearly the same effect Threshold for Purchasing System review currently set at $25M in ADV (administrative and subject to revision without notice) Review on request (by PCO) very common in recent experience
7 Where to Start
8 The Adequacy Criteria The Business Systems Rule sets forth 24 system criteria that must be present in all contractor purchasing systems in order for a purchasing system to be acceptable (see DFARS (a)) DCMA CPSR checklist contains 55 items to be examined (specific policies) with space to indicate presence (or absence) and adequacy The system criteria of the DFARS and the review checklist have NOT YET BEEN RECONCILED
9 General Company Policies Organization plan that establishes clear lines of authority and responsibility; Policy to ensure that all purchases are based on authorized requisitions and include documentary support for vendor selected, price paid, and files which are subject to Government review; Internal audits or reviews, training, and policies for the purchasing department to ensure the integrity of the system
10 General Procurement Policies System description including policies, procedures, and purchasing practices that comply with the requirements of the FAR and DFARS Organizational and administrative structure to ensure effective and efficient procurement of requirements at the best value from responsible and reliable sources
11 Procurement Policies and Procedures
12 Adequacy Criteria Deep Dive Procurement Planning/Market Research (2 Criteria) Conflict of Interest/Misconduct (1 Criterion) Competition (2 Criteria) Negotiated Procurement (1 Criterion) Cost or Pricing Data and Price Reasonableness (5 Criteria) Source Selection (3 Criteria) Contract Formation and Content (3 Criteria) Foreign Purchasing and Performance (3 Criteria) Procurement Administration (4 Criteria)
13 Procurement Planning/Market Research Apply a consistent make-or-buy policy that is in the best interest of the Government Ensure proper type of contract selection and prohibit issuance of cost-plus-a-percentage-of-cost subcontracts
14 Conflict of Interest/Misconduct Enforce adequate policies on conflict of interest, gifts, and gratuities, including the requirements of the Anti-Kickback Act
15 Competition Use competitive sourcing to the maximum extent practicable, and ensure debarred or suspended contractors are properly excluded from contract award Require management level justification and adequate cost or price analysis, as applicable, for any sole or single source award
16 Negotiated Procurement A practice of documenting negotiations in accordance with the FAR requirements for negotiation memoranda
17 Cost or Pricing Data and Price Reasonableness Evaluate price, quality, delivery, technical, and financial capabilities of competing vendors to ensure fair and reasonable prices Perform cost or price analysis and technical evaluation for each proposal or quote to ensure fair and reasonable subcontract prices Document negotiations in accordance with FAR Take discounts, including cash discounts, trade discounts, quantity discounts, rebates, freight allowances, and companywide volume discounts Establish and maintain procedures to ensure performance of adequate price or cost analysis on purchasing actions
18 Source Selection Use competitive sourcing to the maximum extent practicable, and ensure debarred or suspended contractors are properly excluded from contract award Evaluate price, quality, delivery, technical capabilities, and financial capabilities of competing vendors to ensure fair and reasonable prices Establish and maintain selection processes to ensure the most responsive and responsible sources and to promote competitive sourcing so that purchases are reasonably priced and from sources that meet quality requirements
19 Contract Formation and Content Ensure purchase orders and subcontracts contain all flowdown clauses, including terms and conditions, and any other clauses needed to carry out the requirements of the prime contract Notify the Government of the award of all subcontracts that contain flowdown clauses that allow for Government audit of subcontracts, and ensure the performance of audits of those subcontracts Ensure purchase orders and subcontracts contain mandatory and applicable flowdown clauses, as required by the FAR and DFARS
20 Foreign Purchasing and Performance Ensure compliance with all relevant domestic preference requirements Ensure compliance with export control regulations Ensure agreements are not executed with prohibited parties
21 Procurement Administration Maintain subcontract surveillance to ensure timely delivery and procedures to notify the Government of potential subcontract problems that may impact delivery, quantity, or price Document and justify reasons for subcontract changes that affect cost or price Ensure that proper types of subcontracts are selected, and that there are controls over subcontracting, including oversight and surveillance of subcontracted effort Establish and maintain procedures to timely notify the Contracting Officer, in writing, of excessive pass-through concerns
22 The Process
23 Process Basics Begins with a request by the ACO to perform a review Should ALWAYS be scheduled, never unannounced Should be reasonably convenient for both parties Unless you KNOW you are well prepared, get as much lead time as you can Plan on one to two weeks on-site (your facility) for two or more people (based on recent experience) One of the participants is often from DCAA
24
25
26
27
28 Process Results Draft report to the ACO on findings Report is a DCMA document, NOT DCAA Does NOT come under the DCAA Rules of Engagement DCMA usually cooperative on getting contractor input No set time frame for issuance of determination by ACO Often issued first as a formal draft report with a request for a reponse ACO will sometimes permit follow-up review before issuing final Once issued, DFARS Business Systems Rule controls clocks for the process No one passes on the first try
29 A Look Forward
30 Near Term Outlook DCMA has undertaken a large number of CPSRs in 2012 DCAA is participating heavily, but may not continue given agency workload DCMA current backlog estimated at more than one year
31 Longer Term Outlook Purchasing System status now tracked by DCMA in Business Systems database Contractors meeting threshold for review will be shown with a (purchasing) system status of Unassessed if Never reviewed Last adequacy determination more than 3 years old Status of unassessed may adversely affect eligibility for contracts that require an approved purchasing system Growing backlog of CPSRs may put many contractors in exactly that position
32 Resources CPSR Flowchart (Word) DCMA CPSR Checklist (Excel) or Procurement Policies Checklist (Excel) CPSR Review Guide or
33 Questions? 33 10/2/2 012 CONFIDENTIAL 2011 Deltek, Inc. All Rights Reserved
34 Call to Action / Contact Us 34 10/2/2 012 CONFIDENTIAL 2011 Deltek, Inc. All Rights Reserved
35 Call to Action / Contact Us 8000 Towers Crescent Drive Tysons Corner, VA Christine Williamson, Member (703) Christine.Williamson@WatkinsMeegan.com Rich Wilkinson, Director (703) Rich.Wilkinson@WatkinsMeegan.com
Contractor Purchasing System Review (CPSR)
Contractor Purchasing System Review (CPSR) Presentation References FAR 44.3 and DFARS 244.3 -- Contractors Purchasing Systems Reviews Consent to Subcontract FAR 44.2 2 What is a CPSR Contractor purchasing
More informationContractor Purchasing System Review (CPSR) Guidebook
DEPARTMENT OF DEFENSE (DOD) Contractor Purchasing System Review (CPSR) Guidebook November 02, 2015 DEFENSE CONTRACT MANAGEMENT AGENCY (DCMA) This revision supersedes all previous versions. Table of Contents
More informationDOECAA Spring Conference Presentation. Cost Reimbursement Contracting Issues - DOE Proposed Business System Rule
DOECAA Spring Conference Presentation Cost Reimbursement Contracting Issues - DOE Proposed Business System Rule Mary Karen Wills, CPA Director/Leader, BRG Government Contracts 2014 Berkeley Research Group
More informationContractor Purchasing System Reviews (CPSRs)
Contractor Purchasing System Reviews (CPSRs) San Diego Chapter on February 17, 2010 Panel members: Carl DeWoody Dan Kearney Lil Smith Jim Southerland Facilitator: Maurice Caskey 1 Outline Introduction
More informationCONTACT: 1. Proposed rule BDO GOVERNMENT CONTRACTING PRACTICE GUIDANCE ON THE PROPOSED DOE BUSINESS SYSTEM RULE
BDO GOVERNMENT CONTRACTING PRACTICE GUIDANCE ON THE PROPOSED DOE BUSINESS SYSTEM RULE By Eric Sobota, Kelley Doran and Barron Avery Contractors that work for the Department of Energy (DOE) under agreements
More informationClick to edit Master title style
Click to edit Master title style Click The to Business edit Master title style Operations Center and CPSRs Breakout Third Session level # D08 Andrew C. Obermeyer, Director, DCMA Business Operations Center
More informationDCAA Our Role. Laura Cloyd-Hall, CPA, MBA John D. Mollohan II, CPA, CFE. Page 1. DCAA 1965-2015: Celebrating 50 Years of Excellence
DCAA Our Role Laura Cloyd-Hall, CPA, MBA John D. Mollohan II, CPA, CFE DCAA 1965-2015: Celebrating 50 Years of Excellence Page 1 Topics About DCAA Typical DCAA Audits for Small Businesses Basic Roles of
More informationAudit Issues In Government Subcontracting
Audit Issues In Government Subcontracting Breakout Session E Brent A. Calhoon, CPA, Partner, Baker Tilly Virchow Krause, LLP Janie L. Maddox, CPCM, Fellow, Thursday, March 27 1:30pm 2:45pm Agenda 1. Introductions
More informationStrategic Implications of the New DFARS Business System Rule Co-presented by Venable LLP and Argy, Wiltse & Robinson June 12, 2012
Strategic Implications of the New DFARS Business System Rule Co-presented by Venable LLP and Argy, Wiltse & Robinson June 12, 2012 1 Panelists Robert A. ( Rob ) Burton, Partner, Venable LLP A 30-year veteran
More informationGC-217 SBA s Rules of Affiliation and How They Impact Small Businesses
GC-217 SBA s Rules of Affiliation and How They Impact Small Businesses Rich Wilkinson, Director, Watkins Meegan LLC Keith Romanowski, Senior Manager, Watkins Meegan LLC Session Content Background Why Affiliation
More informationINTERNAL CONTROL MATRIX FOR AUDIT OF ESTIMATING SYSTEM CONTROLS Version No. 3.2 June 2006. 31-d Page 1 of 7
INTERNAL CONTROL MATRIX FOR AUDIT OF ESTIMATING SYSTEM CONTROLS Version No. 3.2 June 2006 Control Objectives Example Control Activities Audit Procedures 1. INTERNAL AUDITS Management should periodically
More informationAF Life Cycle Management Center
AF Life Cycle Management Center Subcontract Pricing Shannon Prince AFLCMC/PZF Wright-Patterson AFB 24 March 2014 Overview Intro to Subcontracts Pertinent Thresholds PCO & Prime Responsibilities Prime Analysis
More informationConflicts of Interest
Conflicts of Interest Presented By: Rich Wilkinson, Director Watkins Meegan LLC Rebecca Kehoe, Manager Watkins Meegan LLC Conflicts of Interest (COIs) Conflicts of Interests (COIs) can prevent you from
More informationOMB Uniform Guidance Procurement Standards Pilot Worthy?
Federal Demonstration Partnership May 13, 2014 OMB Uniform Guidance Procurement Standards Pilot Worthy? Prepared by: Office of Naval Research Debbie Rafi, Director, University Business Affairs Abe Sabbag,
More informationDOD's Business Systems Rule: The Challenge Measuring Government Contractor Compliance Against Subjective Criteria and Perceived Risks
DOD's Business Systems Rule: The Challenge Measuring Government Contractor Compliance Against Subjective Criteria and Perceived Risks Breakout Session #: B04 Presented by: Michael E. Steen, CPA Date: July
More informationDCAA Perspective: Key Subcontracting Practices for Maintaining Approved Business Systems Accounting System and Estimating System
DCAA Perspective: Key Subcontracting Practices for Maintaining Approved Business Systems Accounting System and Estimating System Breakout Session A Alfred J. Massey, Western Region, Special Programs Manager,
More informationCurrent Initiatives May 2015
DHG 20 th Annual Government Contracting Update Current Initiatives May 2015 Mr. Ken Saccoccia Deputy Director Page 1 One Agency One Mission DCAA Overview Priorities and Better Buying Power Small Business
More informationWhat Exactly is an Acceptable Accounting System?
What Exactly is an Acceptable Accounting System? Kristen Soles, CPA Member Stephanie Widzinski, CPA Senior Manager September 27, 2012 Agenda Review DFARS Business System Rule What Agency is Responsible
More informationA Guide to Sub-recipient Monitoring
A Guide to Sub-recipient Monitoring 1 SPONSORED PROJECTS OFFICE UNIVERSITY OF CALIFORNIA, BERKELEY PAM MILLER, DIRECTOR SPO WOULD BE HAPPY TO BRING THIS PRESENTATION TO INDIVIDUAL UNITS. CONTACT PAM MILLER
More informationMaster Document Audit Program. Version 7.4, dated November 2006 B-1 Planning Considerations. Purpose and Scope
Activity Code 24010 B-1 Planning Considerations Estimating System Survey (ICR) Purpose and Scope The major objectives of this audit are to: Evaluate the adequacy of and the contractor s compliance with
More informationAttachment II FLOW-DOWN CLAUSES APPLICABLE TO PURCHASE ORDERS INVOLVING FUNDS FROM A FEDERAL GOVERNMENT CONTRACT OR GRANT
Attachment II FLOW-DOWN CLAUSES APPLICABLE TO PURCHASE ORDERS INVOLVING FUNDS FROM A FEDERAL GOVERNMENT CONTRACT OR GRANT If the Order involves funds from a Federal government contract or funds from a
More informationGeneral Terms and Conditions of Purchase
General Terms and Conditions of Purchase Supplement 1 Federal Acquisition Regulation (FAR) Government Contract Provisions 1. When the materials or products furnished are for use in connection with a U.S.
More informationDCMA Perspective: Key Subcontracting Practices for Maintaining Approved Business Systems
DCMA Perspective: Key Subcontracting Practices for Maintaining Approved Business Systems Breakout Session I Andrew Obermeyer, CPCM, Fellow Director, Business Operations Center, Defense Contract Management
More informationDEFENSE CONTRACT AUDIT AGENCY DEPARTMENT OF DEFENSE 8725 JOHN J. KINGMAN ROAD, SUITE 2135 FORT BELVOIR, VA 22060-6219
DEFENSE CONTRACT AUDIT AGENCY DEPARTMENT OF DEFENSE 8725 JOHN J. KINGMAN ROAD, SUITE 2135 FORT BELVOIR, VA 22060-6219 IN REPLY REFER TO PSP 730.8.B.1/2010-003 February 18, 2011 11-PSP-003(R) MEMORANDUM
More information10/30/2015. Procurement Under the New Requirements. Why This Session Is Needed. Lesson Overview & Module Objectives. Changes to conflict of interest
Requirements Procurement under the New Requirements 1 1 Why This Session Is Needed New provisions in Uniform Guidance Changes to conflict of interest requirements in Uniform Guidance Distinctions between
More informationQuick Guide to Cost and Price Analysis for HUD Grantees and Funding Recipients
Quick Guide to Cost and Price Analysis for HUD Grantees and Funding Recipients Who is this guide for? This guide is for all HUD grantees and funding recipients that contract for services and/or supplies
More informationDEPARTMENT OF DEFENSE Defense Contract Management Agency INSTRUCTION. Small Business Process
DEPARTMENT OF DEFENSE Defense Contract Management Agency INSTRUCTION Small Business Process Contracts Directorate DCMA-INST 119 OPR: DCMA-AQS 1. PURPOSE. This Instruction: a. Reissues and updates DCMA
More informationSupplement 1 Federal Acquisition Regulation (FAR) Government Contract Provisions
General Terms and Conditions of Purchase Supplement 1 Federal Acquisition Regulation (FAR) Government Contract Provisions 1. When the products or services furnished are for use in connection with a U.S.
More informationBid Protests: When, Where, Why, and Can You Win?
Bid Protests: When, Where, Why, and Can You Win? What is a bid protest? A written objection by an interested party to a federal government procurement activity. This could be issuance or cancelation of
More informationFood Service Management Companies Table of Contents
Food Service Management Companies Table of Contents Food Service Management Companies 22.1 Procedures for Competitive Bidding/Competitive Proposal 22.1 for a Food Service Management Company (FSMC) Procedures
More informationEvaluation of Defense Contract Management Agency Actions on Reported DoD Contractor Business System Deficiencies
Inspector General U.S. Department of Defense Report No. DODIG-2016-001 OCTOBER 1, 2015 Evaluation of Defense Contract Management Agency Actions on Reported DoD Contractor Business System Deficiencies INTEGRITY
More informationSTOC II Draft RFP (W900KK-08-R-0001) Questions & Answers
STOC II Draft RFP (W900KK-08-R-0001) Questions & Answers Answers to questions submitted, but not included in this set of Q&As,will be provided in a subsequent posting of Q&As in the near future. As the
More informationGovernment Contracting and Earned Value Management (EVM)
Government Contracting and Earned Value Management (EVM) Ida Davis, EVP, PMP, MBA Earned Value Manager DynPort Vaccine Company LLC, A CSC Company Note: This presentation is the property of DynPort Vaccine
More informationDefense Contract Audit Agency: What Do They Do and How Does It Affect ME as a Resource Manager? (Breakout #63)
Defense Contract Audit Agency: What Do They Do and How Does It Affect ME as a Resource Manager? (Breakout #63) Pat Fitzgerald Director Defense Contract Audit Agency The views expressed in this presentation
More informationADMINISTRATIVE REGULATION Milwaukee Area Technical College Title: CONSTRUCTION-RELATED PROCUREMENTS Code: BB0801
General Information for Procuring Construction Materials and Services The Construction Services Department (CSD) is responsible for the orderly and economical procurement of construction-related goods
More informationJuly 6, 2015 11(1) CHAPTER 11
July 6, 2015 11(1) CHAPTER 11 Table of Contents Paragraph Page 11-000 Audit of Contractor Compliance with Contract Financial Management Requirements 11-001 Scope of Chapter... 1101 11-100 Section 1 ---
More informationInside The Proposed DFARS Business Systems Rule
Portfolio Media. Inc. 860 Broadway, 6th Floor New York, NY 10003 www.law360.com Phone: +1 646 783 7100 Fax: +1 646 783 7161 customerservice@law360.com Inside The Proposed DFARS Business s Rule Law360,
More informationCGI Federal Ethics and Compliance Program
CGI Federal Ethics and Compliance Program CGI Federal is committed to maintaining the highest standard of ethical conduct and compliance with all applicable federal, state and local laws, and rules and
More informationTC-UPDATE (11/10) 52.222-39 252.204-7009. 12. Requirements Regarding Potential Access to Export-Controlled Items
TC-UPDATE (11/10) The following updates reflect changes to various provisions and clauses of U.S. Government acquisition regulations, including the Federal Acquisition Regulations (FAR) and the Department
More informationLawrence University Procurement Policy for Federally Sponsored Projects
Lawrence University Procurement Policy for Federally Sponsored Projects PURPOSE Federal grants are taxpayer dollars entrusted to Lawrence University for the advancement of public good. It is incumbent
More informationMonitoring Subcontracts. The views expressed in this presentation are DCAA's views and not necessarily the views of other DoD organizations
Monitoring Subcontracts The views expressed in this presentation are DCAA's views and not necessarily the views of other DoD organizations Subcontracts What should a contractor know about subcontracting:
More informationJanuary 2004 5(1) CHAPTER 5. Table of Contents
January 2004 5(1) Paragraph CHAPTER 5 Table of Contents 5-000 Audit of Policies, Procedures, and Internal Controls Relative to Accounting and Management Systems Page 5-001 Scope of Chapter... 501 5-100
More informationPURCHASING POLICY & PROCEDURES. Table of Contents
Table of Contents I. Purpose...3 II.Objective... 3 III.Scope... 3 IV.Policy Statement....3 V.When Does The Purchasing Staff Need To Be Involved... 3 VI.Who is Authorized to Legally Commit Morehouse School
More informationGOVERNMENT CONTRACTING MICROSOFT DYNAMICS AX AND
GOVERNMENT CONTRACTING AND MICROSOFT DYNAMICS AX White paper on Government Contracting requirements and considerations in planning for a Dynamics AX implementation. 1 Government Contracting and Microsoft
More informationOverview 1) Grantee s procurement requirements must be in conformance with the appropriate applicable Federal, State, and local laws.
The award of Federal funds does not exempt the Grantee organization from compliance with State, and local requirements. When similar requirements exist at all levels, the rule of thumb is that the most
More informationProcurement Standards 2 CFR 200.317-326
2 CFR 200 Uniform Guidance Procurement Standards Kris Rhodes, Director Sponsored Project Services 1 Procurement Standards 2 CFR 200.317-326 200.317 Procurement by states 200.318 General procurement standards
More informationDEPARTMENT OF DEFENSE Defense Contract Management Agency INSTRUCTION. Novation, Change-of-Name, and Business Combination (Restructuring) Agreements
DEPARTMENT OF DEFENSE Defense Contract Management Agency INSTRUCTION Novation, Change-of-Name, and Business Combination (Restructuring) Agreements Contracts Directorate DCMA-INST 132 CPR: DCMA-AQ 1. PURPOSE.
More informationAccounting System Requirements
Accounting System Requirements Further information is available in the Information for Contractors Manual under Enclosure 2 The views expressed in this presentation are DCAA's views and not necessarily
More informationAddendum 529 (5/13) Page 1 of 5
Additional Terms and Conditions E-2D Full Rate Production (FRP) Lot 2 (Prime Contract No. N00019-13-C-9999) All of the additional terms and conditions set forth below are incorporated in and made part
More informationGovernment Contractor Business Systems and Overview of System Assessments
Government Contractor Business Systems and Overview of System Assessments Agenda Overview of business systems rules and environment today 3 rd party assessments Practical solutions Contractor perspective
More informationCertificate of Accounting, Billing and Property System Adequacy
Certificate of Accounting, Billing and Property System Adequacy This certifies that, to the best of my knowledge and belief, Contractor s Accounting, Billing and/or Property System and related internal
More informationDCAA / DCMA: Progress or Status Quo? Presented By: Christine Williamson, CPA, Member Kristen Soles, CPA, Member
DCAA / DCMA: Progress or Status Quo? Presented By: Christine Williamson, CPA, Member Kristen Soles, CPA, Member Agenda State of the Agencies DCAA/DCMA What does GAO have to say? What does DOD IG have to
More informationOpen competition for each procurement Master state contract Task orders Multiple agency procurement vehicles Sole source, single source Interagency
Procurements Procurement Models Federal Procurement Standards Procurement Practices Prior Approval Considerations Exemptions, Request for Waiver, and Exceptions Acquisition Checklist Prior Approval Process
More informationAppendix 1 CJC CONTRACT MANAGEMENT POLICIES AND PROCEDURES. Criminal Justice Commission Contract Management Policies and Procedures
CJC CONTRACT MANAGEMENT POLICIES AND PROCEDURES SNYOPSIS: The CJC was created by a Palm Beach County ordinance in 1988. It has 21 public sector members representing local, state, and federal criminal justice
More informationDCAA Initiatives/Current Issues
Defense Contract Audit Agency DCAA Initiatives/Current Issues Maryland Association of CPAs 2010 Government Contractors' Conference September 21, 2010 Kenneth J. Saccoccia Assistant Director Policy and
More informationLEGAL SERVICES CORPORATION OFFICE OF INSPECTOR GENERAL FINAL REPORT ON SELECTED INTERNAL CONTROLS RHODE ISLAND LEGAL SERVICES, INC.
LEGAL SERVICES CORPORATION OFFICE OF INSPECTOR GENERAL FINAL REPORT ON SELECTED INTERNAL CONTROLS RHODE ISLAND LEGAL SERVICES, INC. RNO 140000 Report No. AU 16-05 March 2016 www.oig.lsc.gov TABLE OF CONTENTS
More informationSociety of American Engineers Joint Engineer Training Conference St. Louis, Missouri. Building your Small Business for the Federal Marketplace
Society of American Engineers Joint Engineer Training Conference St. Louis, Missouri Building your Small Business for the Federal Marketplace Michael Zambrana, FSAME www.pangea-group.com Linda Shapiro,
More informationInternal Surveillance
Page 1 of 18 Internal Surveillance A contract having Earned Value Management System (EVMS) requires the contractor to maintain an effective management control system consistent with EVM industry standards
More informationDCAA Guidelines. How the SBIR firm can work effectively with the Defense Contract Audit Agency
DCAA Guidelines How the SBIR firm can work effectively with the Defense Contract Audit Agency Today s Presenters OUTLINE Presenter Introduction DCAA & DCMA DCAA Overview Types of DCAA Audits What it takes
More informationPost Award Accounting System Audit at Nonmajor Contractors
Activity Code 17741 Version 3.1, dated November 2015 B-01 Planning Considerations Post Award Accounting System Audit at Nonmajor Contractors Audit Specific Independence Determination Members of the audit
More informationUnderstanding the Rate Cycle. Presented By: Rich Wilkinson, VP Client Services
Understanding the Rate Cycle Presented By: Rich Wilkinson, VP Client Services The Rate Cycle and Related Trivia Basics of Indirect Rates The Traditional Structures Developing Rates Prospective Rate Submissions
More informationAudit Expectations for Small Businesses
Audit Expectations for Small Businesses DEFENSE CONTRACT CONSULTING Joseph A. Dalton, CGFM/CFE/CAP Over 31 Years -Supervisory/Auditor Service- DCAA Retired Captain, U. S. Naval Reserve 1996 BUSINESS NO.
More informationTime s Up: DCAA s Renewed Focus on Incurred Cost Submissions
Time s Up: DCAA s Renewed Focus on Incurred Cost Submissions Nicole Mitchell, CPA Donna Dominguez Aronson LLC May 1, 2013 2013 All Rights Reserved 805 King Farm Boulevard Suite 300 Rockville, Maryland
More informationReasons for Change Orders
T E X A S D E PA R T M E N T O F T R A N S P O R TAT I O N A change order is defined in the 2004 Standard Specification Book as a written order to the Contractor detailing changes to the specified work,
More informationPreaward and Post Award Accounting System Audits. November 17, 2011 Pikes Peak NCMA Roland Wick
Preaward and Post Award Accounting System Audits November 17, 2011 Pikes Peak NCMA Roland Wick OVERVIEW This presentation will provide: 1. The basic criteria for the Preaward and Post Award accounting
More informationPARTNERSHIP AGREEMENT Between The U.S. Small Business Administration And The Commodity Futures Trading Commission
PARTNERSHIP AGREEMENT Between The U.S. Small Business Administration And The Commodity Futures Trading Commission Sections 7(j) and 8(a) of the Small Business Act (the Act) (15 U.S.C. 636 (j) and 637(a))
More informationOctober 14, 2015 5(1)
October 14, 2015 5(1) Paragraph CHAPTER 5 Table of Contents 5-000 Audit of Policies, Procedures, and Internal Controls Relative to Accounting and Management Systems Page 5-001 Scope of Chapter... 501 5-100
More informationProperty Management System (GPMS)
Property Management System (GPMS) Business System Overview Sep 20, 2013 Marcia D. Whitson, CPPM, CF NPMA National President DFARS 252.242-7005 Contractor Business Systems DoD Business Systems Rule - Clarifies
More informationPurchase Requisition & Purchase Order Policy
Purchase Requisition & Purchase Order Policy Effective Date: July 9, 2012 Policy Statement The following provides policy guidance to faculty, staff, students and others with respect to the use of a Purchase
More informationIncurred Cost Submissions - It's Not Too Early!
Incurred Cost Submissions - It's Not Too Early! March 28, 2013 David Eck and Todd W. Bishop Dixon Hughes Goodman LLP Agenda Treat Incurred Cost Submissions like a Project Why an Incurred Cost Submission?
More informationVOLUME 11A, CHAPTER 18: NON-ECONOMY ACT ORDERS SUMMARY OF MAJOR CHANGES. All changes are denoted by blue font.
VOLUME 11A, CHAPTER 18: NON-ECONOMY ACT ORDERS SUMMARY OF MAJOR CHANGES All changes are denoted by blue font. Substantive revisions are denoted by an * symbol preceding the section, paragraph, table, or
More informationSMALL BUSINESS INNOVATION RESEARCH DESK REFERENCE FOR CONTRACTING AND PAYMENT
U.S. DEPARTMENT OF DEFENSE SMALL BUSINESS INNOVATION RESEARCH DESK REFERENCE FOR CONTRACTING AND PAYMENT U.S. Department of Defense SBIR Program Office Washington, DC 20301 DESK REFERENCE 8ED. 2 TABLE
More information3 Terms and definitions 3.5 client organization whose management system is being audited for certification purposes
3 Terms and definitions 3.4 third-party certification audit audit carried out by an auditing organization independent of the client and the user, for the purpose of certifying the client's management system
More informationFederal Government Ethics Compliance Training. Federal Acquisition Regulation
Federal Government Ethics Compliance Training Federal Acquisition Regulation Presentation Overview Historical overview of Federal Acquisition Regulation Compliance and requirements Code of Ethics Ethical
More information24 CFR PART 85 85.36 Procurement. States. Procurement standards.
85.36 Procurement. (a) States. When procuring property and services under a grant, a State will follow the same policies and procedures it uses for procurements from its non-federal funds. The State will
More informationFinancial Management Guide for Government Contractors
Financial Management Guide for Government Contractors Overview You are a Government Contractor or wish to be a Government Contractor. Congratulations. It is important you know that the challenges facing
More informationFAR UPDATE 52.216-7, Allowable Cost and Payment (Jun 2013)
FAR UPDATE 52.216-7, Allowable Cost and Payment (Jun 2013) "It's never too early to prepare for your incurred cost submission (A webinar sponsored by Pleasant Valley Business Solutions) 1 Objective Know
More informationThe Devil is in the Details Compliance with the Business Systems Rule
Metropolitan Area Corporate Counsel Association WMACCA Conference on Ethics and Compliance for Government Contractors The Devil is in the Details Compliance with the Business Systems Rule April 1, 2014
More informationPage 1 of 7. Corporate Form CC009 Rev 13, Dated 31 Jan 2015
1. When the materials or products furnished are for use in connection with a U.S. Government contract or subcontract, in addition to the L-3 General Terms and Conditions (Corp Form CC008), the following
More informationa. Buyer may require Seller to transfer title and deliver to Buyer, as directed by Buyer, any (i) completed Goods, and (ii) any partially completed
a. Buyer may require Seller to transfer title and deliver to Buyer, as directed by Buyer, any (i) completed Goods, and (ii) any partially completed Goods and materials, parts, tools, dies, jigs, fixtures,
More informationMEMORANDUM OF UNDERSTANDING Between Defense Contract Audit Agency and Department of Homeland Security
MEMORANDUM OF UNDERSTANDING Between Defense Contract Audit Agency and Department of Homeland Security 1. PURPOSE This memorandum sets forth an understanding of contract audit coverage and related audit
More informationSPECIAL INSPECTOR GENERAL FOR IRAQ RECONSTRUCTION LETTER FOR DIRECTOR, DEFENSE CONTRACT MANAGEMENT AGENCY DIRECTOR, DEFENSE CONTRACT AUDIT AGENCY
SPECIAL INSPECTOR GENERAL FOR IRAQ RECONSTRUCTION LETTER FOR DIRECTOR, DEFENSE CONTRACT MANAGEMENT AGENCY DIRECTOR, DEFENSE CONTRACT AUDIT AGENCY July 30, 2012 SUBJECT: Gaps in Business System Reviews
More informationAn organization which employs, or is about to employ, any of the above, has a financial or other interest in the firm selected for award.
85.36 Procurement (a) States. When procuring property and services under a grant, a State will follow the same policies and procedures it uses for procurements from its non-federal funds. The State will
More informationAttachment 32c THE FOLLOWING PROVISIONS APPLY: Applies to orders of any amount
Attachment 32c FEDERAL PROVISIONS APPLICABLE WHEN SUBCONTRACTOR (COMMERCIAL ENTITY) IS IN POSSESSION OF GOVERNMENT PROPERTY GOVERNMENT SUBCONTRACT PROVISIONS INCORPORATED IN ALL SUBCONTRACTS/PURCHASE ORDERS
More informationADMINISTRATIVE PRACTICE LETTER
Page 1 of 9 Index Purpose of Guidelines Policy Who is Responsible Definitions and Terms Responsibilities and Procedures o Audit Requirements o For-profit Recipients and Audit Requirements o Roles and Responsibilities
More informationUNIT 34: COST ACCOUNTING STANDARDS
UNIT CERTIFICATION Statement of Completion has satisfactorily completed training in the duty of this Unit under the conditions described below and in accordance with the overall standard(s) for this Unit.
More informationFederal Acquisition Regulation Subcontract Flowdown Provisions
Federal Acquisition Regulation Subcontract Flowdown Provisions Clause Title Title Applicability 52.203-6, Alt 1 Restrictions on Subcontractor Sales to the (if subcontract over $150,000) Government (SEP
More informationINTERNAL CONTROL MATRIX FOR AUDIT OF BILLING SYSTEM CONTROLS Version No. 4.2 August 2006
INTERNAL CONTROL MATRIX FOR AUDIT OF BILLING SYSTEM CONTROLS Version No. 4.2 August 2006 1. MANAGEMENT REVIEWS The contractor should have policies and procedures for periodic monitoring of the billing
More informationGENERAL SERVICES ADMINISTRATION
GENERAL SERVICES ADMINISTRATION Auditing and Financial Services & Information Technology Services CONTRACT # GS-00F-0031M Schedule Title: (00 Corp) The Consolidated Schedule (formerly Corporate Contract
More informationThe Changing Government Contractor Environment
The Changing Government Contractor Environment 1 Federal Government Contracting DCAA FY 2014 Report to Congress DCAA Audit Guidance Business systems Federal regulatory rule changes State Contracting (Dept.
More informationGAO DEFENSE CONTRACTING INTEGRITY. Opportunities Exist to Improve DOD s Oversight of Contractor Ethics Programs. Report to Congressional Committees
GAO United States Government Accountability Office Report to Congressional Committees September 2009 DEFENSE CONTRACTING INTEGRITY Opportunities Exist to Improve DOD s Oversight of Contractor Ethics Programs
More information1. STATEMENT OF POLICY:
LOYOLA MARYMOUNT UNIVERSITY POLICIES AND PROCEDURES MANUAL DEPARTMENT: CONTROLLER S OFFICE SUBJECT: UNIVERSITY PURCHASING CARD (P-CARD) POLICY Page 1 of 6 Policy Number: B&F Supersedes: April 2005 Effective
More informationReview of Audits Issued by the Defense Contract Audit Agency in FY 2012 and FY 2013
Report No. DODIG-2014-109 Inspector General U.S. Department of Defense SEPTEMBER 8, 2014 Review of Audits Issued by the Defense Contract Audit Agency in FY 2012 and FY 2013 INTEGRITY EFFICIENCY ACCOUNTABILITY
More informationBusiness Systems: Update on Proposed Rules
Business Systems: Update on Proposed Rules Presented By: Mark Burroughs, Partner Topics Review of Business System requirements Observations on areas of focus by the government Enforcement of significant
More informationBell Standard Purchase Order Terms and Conditions - FAR/DFARS Clause Flow-Downs in Fulfillment of a U.S. Government Contract
Section I FEDERAL ACQUISITION REGULATION (A) Seller agrees to negotiate with Buyer to incorporate additional provisions herein or to change provisions as Buyer reasonably deems necessary to comply with
More informationMEMORANDUM OF UNDERSTANDING Between Defense Contract Audit Agency and Department of Homeland Security
MEMORANDUM OF UNDERSTANDING Between Defense Contract Audit Agency and Department of Homeland Security 1. PURPOSE This memorandum sets forth an understanding of contract audit coverage and related audit
More informationSUBRECIPIENT CERTIFICATION FORM
Our records indicate that your organization is currently being considered for receipt of a subaward under sponsored project funds awarded to the University of Washington. Please check all applicable Certifications
More informationHow To Audit A Government Contractor
Activity Code 17740 Version 6.11, dated November 2015 B-1 Planning Considerations Preaward Survey of Prospective Contractor Accounting System Audit Specific Independence Determination Members of the audit
More informationCHAPTER 8. Table of Contents
July 29, 2015 8(1) Paragraph CHAPTER 8 Table of Contents 8-000 Cost Accounting Standards Page 8-001 Scope of Chapter... 801 8-100 Section 1 --- Overview - Cost Accounting Standards Board (CASB) Rules and
More informationTOPIC 12 CONTRACT COST AND PRICE ANALYSIS
CONTRACT AUDIT GUIDE FRAMEWORK TOPIC 12 CONTRACT COST AND PRICE ANALYSIS Objective To determine whether the agency effectively conducts cost or price analysis to arrive at fair and reasonable prices for
More information