Key Steps To Profitable Foundation Drilling

Size: px
Start display at page:

Download "Key Steps To Profitable Foundation Drilling"

Transcription

1 Key Steps To Profitable Foundation Drilling

2 KEY STEPS TO PROFITABLE FOUNDATION DRILLING Unlike geothermal and water well drilling operators, a foundation drilling contractor is a small cog in a large wheel. Whether it is civil construction or bridge construction, foundation drillers work with the prime contractors and perform within the confines of the design parameters of the larger project. The activities the foundation drillers perform, such as anchored earth retention, pile construction and drilled shaft foundations, are all determined by the factors that govern the engineering project they are part of. This necessitates a closer partnership between foundation drillers and prime contractors. A lot of issues determine the profitability of foundation drilling operations and the contractors must remain vigilant of poor bidding practices, delays, changeorders, budget overruns, distrust, disputes, and technical challenges to make sure that the drilling job is completed safely, soundly and profitably. This white paper discusses some of the key steps foundation drilling contractors need to take to keep their jobs profitable. 1. Thoroughly Study the Site Construction Report When a foundation drilling contractor is called in by a prime contractor, in most cases, some kind of preliminary work is already done on the project. The prime contractor will have access to site investigation reports performed on the project site before he or she bid for the project. These site investigation reports are a good source of information which every drilling contractor should study before bidding any work. The site investigation reports usually have a series of test borings or core borings done on site to check the soil properties and other geological information. A careful analysis of these reports will provide the drilling contractor with a lot of information critical to understanding the scope of the work such as; the type, size, quantity and the structural details of the piles that need to be constructed; site specific information about the structural nature of the overburden and rock layers (e.g. clays, glacial till, shale rock etc.) will be detailed in the bore logs on these reports. 1

3 There are different types of deep foundation piles such as end bearing piles, skin friction piles, settlement reducing piles, tension piles, laterally loaded piles, etc., but end bearing and friction piles are the two most commonly used construction techniques. End bearing piles are deep foundations which terminate in hard, relatively impenetrable material such as rock or very dense sand, gravel and sometimes limestone. They derive most of their load bearing capacity from the resistance of the stratum at the base of the pile. This requires foundation drillers to drill down through all the soft soil layers and drill into the bed rock and construct the pile. Drillers need to case the pile all the way down to the bed rock and drill further into the bed rock. Once the hole is drilled and cased common practice is to pressure fill the cavity with concrete. The pre-constructed steel pile is then lowered into the hole. Upon curing of the concrete the casing is removed leaving a constructed pile. This construction technique displaces the load on the pile into the solid bed rock. Friction piles obtain a greater part of their carrying capacity by skin friction or adhesion. This tends to occur when piles do not reach an impenetrable stratum but are driven for some distance into a penetrable soil. Their carrying capacity is derived partly from end bearing and partly from skin friction between the embedded surface of the soil and the surrounding soil. Foundation drillers employ pile driving machines to drive the casing down into the ground, beating it until it doesn t go any further. They drill down through the casing; drill underneath the casing and then pressure fill the hole with concrete. The casing is sometimes lifted as the hole is pressure-filled or removed after the concrete has cured. The concrete being forced into the hole under pressure swells out underneath the casing. As the casing is removed the bond between the concrete and the soil layers creates a friction on which the load of the pile is handled. Your site investigation report will help you choose the correct type of the pile method that should be employed. It also helps you to arrive at better informed decisions regarding pile bearing capacity and the methods of verification being used on site; specification of structural materials. 2

4 2. Understand Your Capabilities Every foundation drilling contractor needs to have a thorough and realistic understanding of their firm s capabilities in handling the size and scope of the drilling operations. The foundation drilling industry is littered with examples of when a contractor has embarked on a project exceeding his or her capabilities and has to call in external assistance half-way through the job; incurring expenses and compromising the profitability of the contract. You need to understand the capabilities in terms of your expertise and experience and then the capabilities of the equipment you employ in foundation jobs. Both are very important to be able to sail through drilling assignments smoothly. A mismatch between your capabilities and the requirements of the project may set you on a very huge and expensive learning curve. Capabilities of equipment are something foundation drillers should focus on. If their inventory consists of smaller rigs then their machinery is best suited for micro pile work in 5-1/2 inch OD, 6-5/8 inch OD, 7 inch OD, and 7-7/8 inch OD slots. These are the standard casing sizes used in foundation drilling industry. Since most projects build piles according to the standard casing sizes available in the industry, the smaller rigs have the capability to handle such micro pile and tie back work. Such rigs are also capable of building slanted piles in some bridge construction work. If a wall needs to be built at an angle of 70 or 80 degrees, a number of holes can be drilled from the side and anchors can be pushed into the bed rock so that walls can be attached firmly to these anchors dug deep into the solid rock. When foundation drillers try to employ the same machinery in drilling holes of large diameter, such as 20 inch or 24 inch, there is a serious mismatch between the available and the required capabilities. Smaller rigs just don t have the required torque needed and in most cases will not have the pullback capability to extract tooling safely. One way to solve this problem is to seek outside resources from specialists who have the experience in handling such large diameter works. By outsourcing or subcontracting different parts of your job to different specialists you can avoid an expensive learning curve and you can actually capitalize on their expertise and keep your foundation drilling job profitable. 3

5 3. Bid Your Projects Effectively While it s a foregone conclusion that it s impossible to predict how things will turn out in a drilling job, it is important prior to bidding of any job to thoroughly examine the project requirements. The size, scope, construction method and the quantity of the piles; geotechnical considerations; delivery of supplies to the site; your machineries capabilities; and the way payments are processed all affect the profitability of foundation drilling. Proper site investigation should show the geological conditions that the job will need to be performed in. However it is not uncomm0n to encounter conditions that vary from what the site investigation shows. As part of the bidding process the construction process that the drilling contractor will use is specified. If this needs to be changed during the job due to such a change in geology it is important that this is addressed in the bid, and responsibility for the additional costs identified. Foundation drillers should ask for specific performance criteria, such as permissible movements of structures, as part of pre-bid questioning so that the driller can identify suitable drilling and grouting procedures to effectively meet the project goals. There are many ways drillers are paid by the prime such as per pile accepted by the engineer, per pile placed with access tubes for down-hole integrity testing accepted by the engineer, per pile for integrity testing on a production pile, per pile for rapid load test on a production pile, per pile for dynamic load test on a production pile, and lump sum for pre-production test program as approved by the engineer. The contractor should have a clear-cut understanding of payment mechanism of the prime contractor and this should ideally be included in the bid and final agreement. 4

6 4. Plan Your Deliveries In the foundation drilling industry, the manufacturing timelines for much hardware especially the specialty tooling can take about 5 or 6 months. Such long manufacturing lead times have the potential to shut down operations due to down time. It is important for drilling contractors to understand how these delivery schedules affect the progress of their work and plan things accordingly. A clear definition of the scope of the work of the drilling contractor, the size and scale of the drilling operations, and a meticulous understanding of what is needed to effectively do the work helps you correctly assess the material requirements, their manufacturing timelines and scheduling of the entire job operations. The driller needs to understand the human resource requirements, plant and machinery requirements, construction materials requirements, coordination requirements, materials delivery scheduling, traffic management, and then plan labour, plant, equipment and tools, and construction materials in an effective way. 5. Adhere Strictly to Drilling Rules and Regulations As in water well drilling, the rules and regulations related to foundation drilling vary from state to state and country to country. As a foundation drilling contractor you have a requirement to understand these regulations. Should you accept a job in another province or country, it is very important that you acquaint yourself with all the statutory rules and regulations and strictly adhere to them. Some local authorities recognize only certain types of piles and restrict construction of other types. Some drilling practices, which are safe and legal under a different authority, might be banned in some places due to safety or geological considerations. For example, in the state of New York, a contractor is not allowed to advance the inner drill bit in front of the casing due to concerns about hole cavitation. 5

7 Usual regulations such as having your piling construction plans authorized by the local authority; details of monitoring requirements for the adjacent and nearby buildings, structures, land, streets and services arising from the proposed piling works; the contingency measures taken to avoid any calamity; pre-design ground investigations; pre-drilling studies; post construction proof drilling; rules regarding ground-borne vibrations and ground settlements arising from pile driving and similar operations; quality supervision; and on-time submission of piling record plans and reports must all be followed strictly. Not adhering to the rules and regulations related to drilling and not working within the specified parameters in an area may put you on the wrong side of the law and you may get fined or worse, an on-site inspector might shut the job site down. Apart from the above mentioned job-specific regulations, drillers need to respond in an appropriate manner to safety standards or regulations, which affect the operations. They should place the safety and well-being of their workers first, and be honest in the pursuit of safety standards. Drillers should regularly review and periodically update the safety requirements for the installation of piles, anchored earth retention systems, drilled shafts, and micro piles. Adequate education and training for the safe installation of deep foundations must be provided to your crew. 6. Build an Effective Relationship with the Prime Contractor The relationship between the prime contractor and subcontractor is an extremely important one. To this both the parties should do everything possible to manage this relationship as being as productive and positive as possible. Delays in deliveries, additional costs, changes in projects, and timely release of payments are some common irritants in the relationship between the prime contractor and subcontractors. It helps to clearly define how payments shall be made and on what basis they are made in a written agreement. It is not uncommon for a prime contractor to request that certain changes are made during the completion of the project. In such a case the subcontractor should ensure that all such requests are in writing. Revised completion schedules and additional costs if any should be defined also. 6

8 Contracting arrangements are usually framed so as to ensure that not only are subcontractors fairly managed, but also that prime contractors are able to hold subcontractors to account for poor performance and, where necessary, terminate agreements with subcontractors who are not performing to agreed standards. Understand that success in this profession depends on effective relationships between prime contractors and subcontractors. 7. Effective Production Management is the Key Unlike geothermal well drilling or water wells, foundation drilling assignments are not stand-alone jobs; they are a small cog in a large wheel. What drillers can do and when they can are subject to the requirements of the larger construction project they are part of. A significant part of their operations are beyond their control. Foundation drillers have to operate within this window and parameters. To effectively meet these challenges, foundation drillers need to excel in production management. They need to mobilise all the resources they need the tooling, the rig, the compressor, the concrete, and other supplies - on site to complete the job on time. Suspending work because some material has to be delivered on site reflects poorly on the contractor s professionalism. A superior knowledge of the requirements, procedures and materials that are needed to undertake drilling operations is necessary. Experience, either your own or of outside collaborators, in implementing appropriate procedures and techniques for the safe, effective and efficient achievement of the required drilling operations is important. Back-up plans should be ready to handle various frequently encountered problems during drilling operations such as keeping the hole open to carry out pile construction, equipment failure, drill string bogging, controlling drill hole direction, control of hydrostatic pressures, disposal of waste material and drilling in difficult ground. As in any other construction-related activity, successful production management involves careful planning, daily production meetings, job box meetings, midcourse corrections and working with others to plan, prepare and execute proper effective drilling operations. 7

9 8. Your Job is Not Done Till it is Approved To have your work approved you need to work with different kinds of inspectors, especially geotechnical engineers. Once the piles are built they will be subjected to load tests, side load, proof tests on foundation and other tests to check their integrity. Alternative procedures and acceptance criteria, or methods other than test loading or core-drilling, which can demonstrate the performance of the foundation under loads or verify the integrity and the load-response interaction between the foundation unit and the bearing stratum may also be performed by the inspectors. The construction is certified only after satisfactory piling records have been submitted; the required proof tests have been satisfactorily carried out; and all relevant imposed conditions including materials testing requirement have been complied with. Since drillers can t get their money unless their work is certified, they need to work closely with inspectors and assist them in assessing and certifying drilling work by providing them all the necessary information. Conclusion As you can see there are a number of factors to consider when planning and executing Foundation Drilling projects. By following these steps and taking action you can significantly improve the profitability of your contracts. I m sure like most foundation drilling contractors you have a wealth of knowledge and a lot of these steps will not be totally new to you. However it is worth taking a step back from your business sometimes and asking yourself if hand on heart you do actually follow all of these steps. 8

10 About Mincon International Mincon International was established in Shannon, Ireland in 1977 and has grown into a global business with a presence across 6 continents. Mincon produce a range of high quality DTH hammers and bits for a wide variety of drilling applications. With three state of the art manufacturing facilities in Shannon, Ireland, Benton, Illinois, USA and Perth, Australia, Mincon can supply its products worldwide. If you need specific advice on your next drilling project or would like to arrange a site trial with our hammers and bits then get in touch with your local office today: 9

PILE FOUNDATIONS FM 5-134

PILE FOUNDATIONS FM 5-134 C H A P T E R 6 PILE FOUNDATIONS Section I. GROUP BEHAVIOR 6-1. Group action. Piles are most effective when combined in groups or clusters. Combining piles in a group complicates analysis since the characteristics

More information

DESIGNING STRUCTURES IN EXPANSIVE CLAY

DESIGNING STRUCTURES IN EXPANSIVE CLAY DESIGNING STRUCTURES IN EXPANSIVE CLAY A GUIDE FOR A RCHITECTS AND E NGINEERS Table of Contents 1. Introduction Page 1 2. Common Foundation Systems Page 2 3. Drilled Piers Page 3 a. Skin Friction Piers

More information

High Strain Dynamic Load Testing of Drilled Shafts

High Strain Dynamic Load Testing of Drilled Shafts Supplemental Technical Specification for High Strain Dynamic Load Testing of Drilled Shafts SCDOT Designation: SC-M-712 (9/15) September 3, 2015 1.0 GENERAL This work shall consist of performing high-strain

More information

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS July 14, 2015 1.0 GENERAL BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS This work shall consist of furnishing all materials, equipment, labor, and incidentals necessary for conducting bi-directional

More information

Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. The Leading Edge.

Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. The Leading Edge. TM TM Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. SM The Leading Edge. 10 One Major Causes of foundation settlement or more conditions may

More information

New construction Repairing failed or old foundations Retrofit foundations Permanent battered piers Machinery/equipment foundations

New construction Repairing failed or old foundations Retrofit foundations Permanent battered piers Machinery/equipment foundations from New construction foundations don t have to be a headache. The CHANCE Helical Pier Foundation System gives you the performance of concrete without the drawbacks and liabilities of driven piles and

More information

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS Page 1 of 9 SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS 1. GENERAL REQUIREMENTS 1. Description of Work: This work consists of furnishing all materials, equipment and

More information

INSITU TESTS! Shear Vanes! Shear Vanes! Shear Vane Test! Sensitive Soils! Insitu testing is used for two reasons:!

INSITU TESTS! Shear Vanes! Shear Vanes! Shear Vane Test! Sensitive Soils! Insitu testing is used for two reasons:! In-situ Testing! Insitu Testing! Insitu testing is used for two reasons:! To allow the determination of shear strength or penetration resistance or permeability of soils that would be difficult or impossible

More information

System. Stability. Security. Integrity. 150 Helical Anchor

System. Stability. Security. Integrity. 150 Helical Anchor Model 150 HELICAL ANCHOR System PN #MBHAT Stability. Security. Integrity. 150 Helical Anchor System About Foundation Supportworks is a network of the most experienced and knowledgeable foundation repair

More information

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Jeff R. Hill, P.E. Hayward Baker Inc. 111 W. Port Plaza Drive Suite 600 St. Louis, MO 63146 314-542-3040 JRHill@HaywardBaker.com

More information

Design and Construction of Auger Cast Piles

Design and Construction of Auger Cast Piles Design and Construction of Auger Cast Piles 101 th Annual Road School 2015 3/11/2015 Malek Smadi, Ph.D., P.E. Principal Engineer - GEOTILL - Fishers, IN msmadi@geotill.com - www.geotill.com CONTENTS 1.

More information

How to Estimate the Cost of Support of Excavation for Foundation Installation. CPE Candidate No. 0113013. May 15, 2013

How to Estimate the Cost of Support of Excavation for Foundation Installation. CPE Candidate No. 0113013. May 15, 2013 How to Estimate the Cost of Support of Excavation for Foundation Installation CPE Candidate No. 0113013 May 15, 2013 1 How to Estimate the Cost of Support of Excavation for Foundation Installation Table

More information

DIRECTIONAL DRILLING

DIRECTIONAL DRILLING DIRECTIONAL DRILLING 1. General. Installation of pipelines through the levee embankment using directional drilling technology is prohibited. Installation of pipelines through a flood control project foundation

More information

ALLOWABLE LOADS ON A SINGLE PILE

ALLOWABLE LOADS ON A SINGLE PILE C H A P T E R 5 ALLOWABLE LOADS ON A SINGLE PILE Section I. BASICS 5-1. Considerations. For safe, economical pile foundations in military construction, it is necessary to determine the allowable load capacity

More information

METHOD OF STATEMENT FOR STATIC LOADING TEST

METHOD OF STATEMENT FOR STATIC LOADING TEST Compression Test, METHOD OF STATEMENT FOR STATIC LOADING TEST Tension Test and Lateral Test According to the American Standards ASTM D1143 07, ASTM D3689 07, ASTM D3966 07 and Euro Codes EC7 Table of Contents

More information

ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT

ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT Description: This work shall consist of furnishing all materials, equipment and labor necessary for conducting an Osterberg Cell (O-Cell) Load

More information

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling Engineering and Construction Services Division Standard Specifications for Sewers and Watermains TS 415 April 2013 Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation

More information

GUIDELINES FOR GEOTECHNICAL INVESTIGATION OF BRIDGE STRUCTURES. Materials Engineering Report No. 2009-8M (Supersedes Report No.

GUIDELINES FOR GEOTECHNICAL INVESTIGATION OF BRIDGE STRUCTURES. Materials Engineering Report No. 2009-8M (Supersedes Report No. GUIDELINES FOR GEOTECHNICAL INVESTIGATION OF BRIDGE STRUCTURES Materials Engineering Report No. 2009-8M (Supersedes Report No. 21) F CHOWDHURY GEOMECHANICS AND STRUCTURAL MATERIALS ENGINEER S REHMAN GEOTECHNICAL

More information

Tunnelling & Underground. Specialists

Tunnelling & Underground. Specialists Tunnelling & Underground Specialists Mined Tunnels Excavation at Ayer Rajah Avenue, Singapore Introduction Amberg & TTI Engineering Pte Ltd (AETTI) was established in Singapore in 2002 by Amberg Engineering

More information

Pro-Lift Steel Pile Foundation Repair

Pro-Lift Steel Pile Foundation Repair Pro-Lift Steel Pile Foundation Repair Pro-Lift Steel Pile Foundation Repair System Pro-lift steel piles are designed for the stresses of Texas soils. They can have multiple steel walls, depending on the

More information

1 Mobilisation and demobilisation 1 Deep boring sum 2 Cone penetration tests sum 3 Miscellenous tests sum

1 Mobilisation and demobilisation 1 Deep boring sum 2 Cone penetration tests sum 3 Miscellenous tests sum Malaysian Civil Engineering Standard Method of Measurement (MyCESMM) CLASS D: SITE INVESTIGATION WORK Measurement covered under other classes: Excavation not carried out for the purpose of soil investigation

More information

Ground-borne Vibrations and Ground Settlements Arising from Pile Driving and Similar Operations

Ground-borne Vibrations and Ground Settlements Arising from Pile Driving and Similar Operations Buildings Department Practice Note for Authorized Persons, Registered Structural Engineers and Registered Geotechnical Engineers APP-137 Ground-borne Vibrations and Ground Settlements Arising from Pile

More information

Comprehensive Design Example 2: Foundations for Bulk Storage Facility

Comprehensive Design Example 2: Foundations for Bulk Storage Facility Comprehensive Design Example 2: Foundations for Bulk Storage Facility Problem The project consists of building several dry product storage silos near an existing rail siding in an open field presently

More information

Geotechnical Measurements and Explorations Prof. Nihar Ranjan Patra Department of Civil Engineering Indian Institute of Technology, Kanpur

Geotechnical Measurements and Explorations Prof. Nihar Ranjan Patra Department of Civil Engineering Indian Institute of Technology, Kanpur Geotechnical Measurements and Explorations Prof. Nihar Ranjan Patra Department of Civil Engineering Indian Institute of Technology, Kanpur Lecture No. # 13 (Refer Slide Time: 00:18) So last class, it was

More information

ATLAS RESISTANCE Pier Foundation Systems

ATLAS RESISTANCE Pier Foundation Systems ATLAS RESISTANCE Pier Foundation Systems Foundation Repair Systems for Civil Construction Applications: Residential, Commercial, Industrial Atlas Resistance Piers have been used to restore and/or stabilize

More information

Local Authority Building Control Technical Information Note 3 Driven and In-situ Piled Foundations

Local Authority Building Control Technical Information Note 3 Driven and In-situ Piled Foundations Local Authority Building Control Technical Information Note 3 Driven and In-situ Piled Foundations Cambridge City Council - East Cambridgeshire District Council - Fenland District Council, Huntingdonshire

More information

The Stabilizer TM. Benefits. www.griptite.com. Supplemental support system for sagging beams and floor joists within a crawl space

The Stabilizer TM. Benefits. www.griptite.com. Supplemental support system for sagging beams and floor joists within a crawl space The Stabilizer TM Supplemental support system for sagging beams and floor joists within a crawl space Pre-drilled holes in steel plate allow for connection to beam or floor joists. Benefits Levels and

More information

Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing

Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing Brussels, 18-20 February 2008 Dissemination of information workshop 1 Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing Dr.-Ing. Bernd Schuppener, Federal Waterways Engineering

More information

LEGACY REPORT ER-5110. www.icc-es.org. ICC Evaluation Service, Inc. Reissued November 1, 2003. Legacy report on the 1997 Uniform Building Code

LEGACY REPORT ER-5110. www.icc-es.org. ICC Evaluation Service, Inc. Reissued November 1, 2003. Legacy report on the 1997 Uniform Building Code LEGACY REPORT Reissued November 1, 2003 ICC Evaluation Service, Inc. www.icc-es.org Business/Regional Office # 5360 Workman Mill Road, Whittier, California 90601 # (562) 699-0543 Regional Office # 900

More information

Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS

Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS 1 Proposal & Plans Received? 2 Review Proposal, highlight important facts. Know proposal well to be able to find answers quickly.

More information

Guidelines for Earthquake Bracing Residential Water Heaters

Guidelines for Earthquake Bracing Residential Water Heaters Guidelines for Earthquake Bracing Residential Water Heaters Department of General Services Division of the State Architect In accordance with the Health and Safety Code Section 19215, the Division of the

More information

Transmission Foundations. helical piles and guy anchors for transmission structures. www.hubbellpowersystems.com

Transmission Foundations. helical piles and guy anchors for transmission structures. www.hubbellpowersystems.com Transmission Foundations helical piles and guy anchors for transmission structures www.hubbellpowersystems.com Grid locked on your transmission job? Instant Foundation helical piles go places concrete

More information

Lymon C. Reese & Associates LCR&A Consulting Services Tests of Piles Under Axial Load

Lymon C. Reese & Associates LCR&A Consulting Services Tests of Piles Under Axial Load Lymon C. Reese & Associates LCR&A Consulting Services Tests of Piles Under Axial Load Nature of Services The company has a long history of performance of tests of piles and pile groups under a variety

More information

THE PROVISIONAL CENTRAL PRODUCT CLASSIFICATION

THE PROVISIONAL CENTRAL PRODUCT CLASSIFICATION THE PROVISIONAL CENTRAL PRODUCT CLASSIFICATION GROUP 867 ARCHITECTURAL, ENGINEERING AND OTHER TECHNICAL SERVICES Excerpt from CPCprov-en-Publication.doc - United Nation Statistic Division Group Class Subclass

More information

High Capacity Helical Piles Limited Access Projects

High Capacity Helical Piles Limited Access Projects High Capacity Helical Piles Limited Access Projects Tel 403 228-1767 Canada, USA, Russia Brendan ODonoghue 519 830-6113 Presentation Summary 1. Helical piles Background on large diameter shafts and helices

More information

Guidelines for Earthquake Bracing of Residential Water Heaters

Guidelines for Earthquake Bracing of Residential Water Heaters Guidelines for Earthquake Bracing of Residential Water Heaters Department of General Services Division of the State Architect 1102 Q Street, Suite 5100 Sacramento, CA 95814 Phone: (916) 324-7099 Fax: (916)

More information

Moving Small Mountains Vesuvius Dam Rehab

Moving Small Mountains Vesuvius Dam Rehab Moving Small Mountains Vesuvius Dam Rehab Susan L. Peterson, P.E., regional dams engineer, Eastern Region, Bedford, IN Note: The following article, Moving Small Mountains Vesuvius Dam Rehab, by Sue Peterson,

More information

Engineering Council of South Africa

Engineering Council of South Africa Government Gazette No. 26180, 2 April 2004 Page 1 of 30 Board Notice 42 of 2004 Engineering Council of South Africa Guideline Scope of Services and Tariff of Fees for Persons Registered in terms of the

More information

Figure A-1. Figure A-2. continued on next page... HPM-1. Grout Reservoir. Neat Cement Grout (Very Flowable) Extension Displacement Plate

Figure A-1. Figure A-2. continued on next page... HPM-1. Grout Reservoir. Neat Cement Grout (Very Flowable) Extension Displacement Plate Addendum HELICAL PULLDOWN Micropile (HPM) Introduction The HPM is a system for constructing a grout column around the shaft of a standard Helical Screw Foundation (see Figure A1). To begin the process,

More information

SERVICES 2015 ISO 18001

SERVICES 2015 ISO 18001 SERVICES 2015 A family business with a solid foundation of experience, we handle all aspects of site investigation.... Phase 1 Environmental Studies Phase 2 Intrusive Investigations Phase 3 Remediation

More information

Safe & Sound Bridge Terminology

Safe & Sound Bridge Terminology Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries

More information

SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT

SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT 1.0 SOIL IMPROVEMENT 1.1 General Soil Investigation Information are provided in Part B1 annex as a guide to the Contractor for his consideration

More information

Attachment G-1: Pit Latrine Diagram. Fig E.1a: Pit Latrine. Fig E.1b: Plan View of Twin Pits

Attachment G-1: Pit Latrine Diagram. Fig E.1a: Pit Latrine. Fig E.1b: Plan View of Twin Pits Attachment G-1: Pit Latrine Diagram Fig E.1a: Pit Latrine Fig E.1b: Plan View of Twin Pits Fig E.1c: Section of a water-sealed pan Fig E.1d: 3D view of Overflow Pipe Fig E.1e: 2D view of Overflow Pipe

More information

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations Nathan A. Ingraffea, P.E., S.E. Associate, KPFF Consulting Engineers, Portland, Oregon, USA Abstract The use of steel sheet

More information

Federation of Piling Specialists Testing Datasheet No 1

Federation of Piling Specialists Testing Datasheet No 1 Testing Datasheet No 1 Guidance for the Principal Contractor It is an essential requirement that the specialist testing contractor is allowed to work in a safe way and fully in accordance with their own

More information

How To Prepare A Geotechnical Study For A Trunk Sewer Project In Lincoln, Nebraska

How To Prepare A Geotechnical Study For A Trunk Sewer Project In Lincoln, Nebraska APPENDIX B Geotechnical Engineering Report GEOTECHNICAL ENGINEERING REPORT Preliminary Geotechnical Study Upper Southeast Salt Creek Sanitary Trunk Sewer Lincoln Wastewater System Lincoln, Nebraska PREPARED

More information

COSMOS 2012: Earthquakes in Action COSMOS 2012

COSMOS 2012: Earthquakes in Action COSMOS 2012 COSMOS 2012 What is SFSI and why is it important? Soil issues in Earthquakes Structures where SFSI important Retaining structures (lateral earth pressure) Foundations (spread and pile footings, bearing

More information

PROPOSED RESIDENTIAL DEVELOPMENT LAND OFF MACCLESFIELD OLD ROAD, BUXTON. Construction Management Plan

PROPOSED RESIDENTIAL DEVELOPMENT LAND OFF MACCLESFIELD OLD ROAD, BUXTON. Construction Management Plan PROPOSED RESIDENTIAL DEVELOPMENT LAND OFF MACCLESFIELD OLD ROAD, BUXTON Construction Management Plan May 2013 CONTENTS Page No: 1.0 INTRODUCTION 1 2.0 PROJECT ORGANISATION AND RESPONSIBILITIES 2 2.1 Client

More information

SECTION 10 WATER WELL SUPPLY 10.01 SCOPE OF WORK

SECTION 10 WATER WELL SUPPLY 10.01 SCOPE OF WORK 10.01 SCOPE OF WORK The work covered by this section of the specifications consists in furnishing all labor, equipment and material necessary to perform the installation of a Type I water supply well per

More information

Geotechnical Investigation Test Report

Geotechnical Investigation Test Report Geotechnical Investigation Test Report Report No. htsc/rcd/ 3457 Dated: - 20/03/2010 Asphalt Standard Penetration Test as per IS 2131 ------------- IS 6403 Soil Job Card No - 1649 Cement Client/Department

More information

Work Type Definition and Submittal Requirements

Work Type Definition and Submittal Requirements Work Type: Geotechnical Studies Soils Analysis & Recommendations The first section, Work Type Definition, provides a detailed explanation of the work type. The second section, Work Type Submittal Requirements,

More information

PART E SPECIFICATIONS

PART E SPECIFICATIONS PART E SPECIFICATIONS Page 1 of 5 PART E - SPECIFICATIONS GENERAL E1. APPLICABLE SPECIFICATIONS, STANDARD DETAILS AND DRAWINGS E1.1 The City of Winnipeg Works and Operations Division Standard Construction

More information

USE OF MICROPILES IN TEXAS BRIDGES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch

USE OF MICROPILES IN TEXAS BRIDGES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch USE OF MICROPILES IN TEXAS BRIDGES by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch DEFINITION OF A MICROPILE A micropile is a small diameter (typically less than 12 in.), drilled and

More information

and the design of construction working platforms

and the design of construction working platforms Federation A presentation to the Australian Geomechanics Society Victoria i Branch 11 August 2010 Dr Stephen Buttling Piling rig bearing pressures and the design of construction working platforms 1 The

More information

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL. STRUCTURES 1. General. Critical structures may impact the integrity of a flood control project in several manners such as the excavation for construction of the structure, the type of foundation, backfill

More information

Policy on Water Heater Installations Policy No. UPC 510-1-94 Effective: September 1, 1995 Revised: February 10, 1996

Policy on Water Heater Installations Policy No. UPC 510-1-94 Effective: September 1, 1995 Revised: February 10, 1996 CITY OF SAN JOSE BUILDING DIVISION POLICY Policy on Water Heater Installations Policy No. UPC 510-1-94 Effective: September 1, 1995 Revised: February 10, 1996 All new and replacement water heaters installed

More information

FUTURE SLAB. PENETRATIONS and. DEMOLITION of POST-TENSIONED FLOORS

FUTURE SLAB. PENETRATIONS and. DEMOLITION of POST-TENSIONED FLOORS FUTURE SLAB PENETRATIONS and DEMOLITION of POST-TENSIONED FLOORS 1.0 INTRODUCTION Post-tensioned floor slabs in Australia and South East Asia are now universally regarded as the most cost effective form

More information

Designed and Engineered to Perform

Designed and Engineered to Perform History EARTH CONTACT PRODUCTS, L.L.C., is a family owned company, based in Olathe, Kansas. This company was built upon Don May s U.S. Patented fourth-generation Steel Piering System that has led to the

More information

PDCA Driven-Pile Terms and Definitions

PDCA Driven-Pile Terms and Definitions PDCA Driven-Pile Terms and Definitions This document is available for free download at piledrivers.org. Preferred terms are descriptively defined. Potentially synonymous (but not preferred) terms are identified

More information

INTERNAL CONTROL MATRIX FOR AUDIT OF ESTIMATING SYSTEM CONTROLS Version No. 3.2 June 2006. 31-d Page 1 of 7

INTERNAL CONTROL MATRIX FOR AUDIT OF ESTIMATING SYSTEM CONTROLS Version No. 3.2 June 2006. 31-d Page 1 of 7 INTERNAL CONTROL MATRIX FOR AUDIT OF ESTIMATING SYSTEM CONTROLS Version No. 3.2 June 2006 Control Objectives Example Control Activities Audit Procedures 1. INTERNAL AUDITS Management should periodically

More information

How To Design A Foundation

How To Design A Foundation The Islamic university - Gaza Faculty of Engineering Civil Engineering Department CHAPTER (2) SITE INVESTIGATION Instructor : Dr. Jehad Hamad Definition The process of determining the layers of natural

More information

SikaProof A Technology

SikaProof A Technology SikaProof A Technology The fully bonded waterproofing system Keep your basements durably and securely watertight What is SikaProof A? How does it work? Where can it be used? What are the advantages of

More information

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS Vince Luongo Petrifond Foundation Co., Ltd. PROJECT DESCRIPTION The York Durham Sanitary System (YDSS) Interceptor in the Town of Richmond Hill located

More information

Page B-1 Hubbell Power Systems, Inc. All Rights Reserved Copyright 2014 LOAD TESTS

Page B-1 Hubbell Power Systems, Inc. All Rights Reserved Copyright 2014 LOAD TESTS Page B-1 Hubbell Power Systems, Inc. All Rights Reserved Copyright 2014 Appendix B CONTENTS STATIC (TIEBACKS)... B-3 STATIC AXIAL (COMPRESSION/TENSION)... B-6 STATIC (LATERAL)... B-9 CAPACITY VERIFICATION

More information

ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING

ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING 1.0 General 1.1 The work covered by this section consists of providing all labor, equipment, material and supplies, insurance, accessories, tools, transportation,

More information

Geotechnical Investigation Reports and Foundation Recommendations - Scope for Improvement - Examples

Geotechnical Investigation Reports and Foundation Recommendations - Scope for Improvement - Examples Geotechnical Investigation Reports and Foundation Recommendations - Scope for Improvement - Examples Prof. V.S.Raju (Formerly: Director, IIT Delhi & Professor and Dean, IIT Madras) Email: rajuvs_b@yahoo.com

More information

BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM

BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM Swaminathan Srinivasan, P.E., M.ASCE H.C. Nutting/Terracon David Tomley, P.E., M.ASCE KZF Design Delivering Success for

More information

BUTE Department of Construction Management and Technology

BUTE Department of Construction Management and Technology BUTE Department of Construction Management and Technology 02.10.2012 Definition 1: Foundation: The structure, that transmits the load of the building to the soil Definition 2: Load bearing soil (strata):

More information

Step 11 Static Load Testing

Step 11 Static Load Testing Step 11 Static Load Testing Test loading is the most definitive method of determining load capacity of a pile. Testing a pile to failure provides valuable information to the design engineer and is recommended

More information

Helical Piles. A Practical Guide to Design and Installation

Helical Piles. A Practical Guide to Design and Installation Brochure More information from http://www.researchandmarkets.com/reports/2216946/ Helical Piles. A Practical Guide to Design and Installation Description: An unbiased, comprehensive review of helical pile

More information

INDIRECT METHODS SOUNDING OR PENETRATION TESTS. Dr. K. M. Kouzer, Associate Professor in Civil Engineering, GEC Kozhikode

INDIRECT METHODS SOUNDING OR PENETRATION TESTS. Dr. K. M. Kouzer, Associate Professor in Civil Engineering, GEC Kozhikode INDIRECT METHODS SOUNDING OR PENETRATION TESTS STANDARD PENETRATION TEST (SPT) Reference can be made to IS 2131 1981 for details on SPT. It is a field edtest to estimate e the penetration e resistance

More information

A Solid Foundation Solution for Homeowners. from. Our products are made with 90% Recycled Material Down. Right. Solid. GREEN.

A Solid Foundation Solution for Homeowners. from. Our products are made with 90% Recycled Material Down. Right. Solid. GREEN. A Solid Foundation Solution for Homeowners from Our products are made with 90% Recycled Material Down. Right. Solid. GREEN. Stop the damaging effects of foundation settling... Sinking foundations, cracked

More information

A study on the Effect of Distorted Sampler Shoe on Standard Penetration Test Result in Cohesionless soil

A study on the Effect of Distorted Sampler Shoe on Standard Penetration Test Result in Cohesionless soil ISSN: 319-53 (An ISO 39: 00 Certified Organization) A study on the Effect of Distorted Sampler Shoe on Standard Penetration Test Result in Cohesionless soil Utpal Kumar Das Associate Professor, Department

More information

Single Project Professional Indemnity Insurance Proposal Form. Note: This is a proposal form for a claims made policy

Single Project Professional Indemnity Insurance Proposal Form. Note: This is a proposal form for a claims made policy Single Project Professional Indemnity Insurance Proposal Form Note: This is a proposal form for a claims made policy Please provide any necessary explanations or additional details by attaching separate

More information

SECTION 02200 SUPPORT OF EXCAVATION

SECTION 02200 SUPPORT OF EXCAVATION SECTION 02200 PART 1 GENERAL 1.01 DESCRIPTION A. Section including specifications for design and installation of excavation support. B. Section also includes specifications for excavation support systems

More information

SECTION 1 GENERAL REQUIREMENTS

SECTION 1 GENERAL REQUIREMENTS Page 1 of 6 SECTION 1 GENERAL REQUIREMENTS 1. SCOPE OF WORK: The work to be performed under the provisions of these documents and the contract based thereon includes furnishing all labor, equipment, materials,

More information

Caltrans Geotechnical Manual

Caltrans Geotechnical Manual Cone Penetration Test The cone penetration test (CPT) is an in-situ sounding that pushes an electronic penetrometer into soil and records multiple measurements continuously with depth. Compared with rotary

More information

CONSTRUCTION COST ESTIMATES

CONSTRUCTION COST ESTIMATES Chapter 8 CONSTRUCTION COST ESTIMATES SCDOT BRIDGE DESIGN MANUAL April 2006 Table of Contents Section Page 8.1 PROGRAMMING ESTIMATES...8-1 8.1.1 Bridge Replacement Projects...8-1 8.1.2 Other Projects...8-1

More information

The FIDIC Suite of Contracts

The FIDIC Suite of Contracts Less well know FIDIC contracts are also available such as the Turquoise Book for Dredging and Reclamation Works published in January 2006 and the White Book model services agreement published in October

More information

Trench Rescue by Buddy Martinette

Trench Rescue by Buddy Martinette Trench Rescue by Buddy Martinette SOIL TYPE AND TESTING It is imperative that rescue personnel understand soil types and testing procedures if the want to be competent at trench rescue operations. Determining

More information

CHAPTER 2 QUANTITY TAKE-OFF

CHAPTER 2 QUANTITY TAKE-OFF CHAPTER 2 QUANTITY TAKEOFF The quantity takeoff is an important part of the cost estimate. It must be as accurate as possible and should be based on all available engineering and design data. Use of appropriate

More information

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0

More information

2010-2011 Contractor of the Year

2010-2011 Contractor of the Year U.S. Army Corps of Engineers: Little Calumet River Stage VII Steel Sheet Piling Installation Hammond, Indiana Thatcher worked two rigs concurrently one on the north side and one on the south. The United

More information

TECHNICAL SPECIFICATIONS CEMENT-BENTONITE SLURRY TRENCH CUTOFF WALL

TECHNICAL SPECIFICATIONS CEMENT-BENTONITE SLURRY TRENCH CUTOFF WALL TECHNICAL SPECIFICATIONS CEMENT-BENTONITE SLURRY TRENCH CUTOFF WALL SCOPE This section of the specifications includes requirements for the Slurry Trench Cutoff Wall and related work as indicated on the

More information

Determination of Thermal Conductivity of Coarse and Fine Sand Soils

Determination of Thermal Conductivity of Coarse and Fine Sand Soils Proceedings World Geothermal Congress Bali, Indonesia, - April Determination of Thermal Conductivity of Coarse and Fine Sand Soils Indra Noer Hamdhan 1 and Barry G. Clarke 2 1 Bandung National of Institute

More information

North American Development Bank. Prequalification of Contractors

North American Development Bank. Prequalification of Contractors North American Development Bank Prequalification of Contractors PREQUALIFICATION NOTE This note is prepared for the exclusive use of the borrower (the purchaser in this document) and should not be included

More information

Dr. Jesús Gómez, P.E. 36th Annual Conference on Deep Foundations, Boston, MA

Dr. Jesús Gómez, P.E. 36th Annual Conference on Deep Foundations, Boston, MA FHWA Hollow Bar Soil Nail (HBSN) Test Program Dr. Jesús Gómez, P.E. 36th Annual Conference on Deep Foundations, Boston, MA Outline Introduction and motivation Installation methods for testing Testing and

More information

ENCE 4610 Foundation Analysis and Design

ENCE 4610 Foundation Analysis and Design This image cannot currently be displayed. ENCE 4610 Foundation Analysis and Design Shallow Foundations Total and Differential Settlement Schmertmann s Method This image cannot currently be displayed. Strength

More information

vulcanhammer.net This document downloaded from

vulcanhammer.net This document downloaded from This document downloaded from vulcanhammer.net since 1997, your source for engineering information for the deep foundation and marine construction industries, and the historical site for Vulcan Iron Works

More information

National Electric Power Regulatory Authority

National Electric Power Regulatory Authority National Electric Power Regulatory Authority MECHANISM FOR DETERMINATION OF TARIFF FOR HYDROPOWER PROJECTS Preamble Conservative estimates show total hydroelectric potential in the country to be 45000

More information

Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils

Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils Stephen W. Lacz 1, M. ASCE, P.E. and Richard C. Wells 2, F. ASCE, P.E. 1 Senior Professional, Trigon Kleinfelder, Inc., 313 Gallimore

More information

CIVL451. Soil Exploration and Characterization

CIVL451. Soil Exploration and Characterization CIVL451 Soil Exploration and Characterization 1 Definition The process of determining the layers of natural soil deposits that will underlie a proposed structure and their physical properties is generally

More information

Exploration for natural gas

Exploration for natural gas FACT SHEET NO. 42 Exploration for natural gas Quick facts QGC holds licences from the Queensland Government called Authorities to Prospect that allow us to explore in areas known as tenements We work with

More information

Residential Foundations and Basements

Residential Foundations and Basements Residential Foundations and Basements Disclaimer All of the following information is based on the 2006 International Residential Code with Kentucky Amendments. As some information is paraphrased, article

More information

Buildings Department Practice Note for Registered Contractors 38. Registration of General Building Contractors and Specialist Contractors

Buildings Department Practice Note for Registered Contractors 38. Registration of General Building Contractors and Specialist Contractors Buildings Department Practice Note for Registered Contractors 38 Registration of General Building Contractors and Specialist Contractors This practice note covers solely the registration of general building

More information

Anirudhan I.V. Geotechnical Solutions, Chennai

Anirudhan I.V. Geotechnical Solutions, Chennai Anirudhan I.V. Geotechnical Solutions, Chennai Often inadequate In some cases, excess In some cases, disoriented Bad investigation Once in a while good ones Depends on one type of investigation, often

More information

Site Auditing for Building Works. This practice note provides details of the strategy on auditing building works by the Buildings Department (BD).

Site Auditing for Building Works. This practice note provides details of the strategy on auditing building works by the Buildings Department (BD). Buildings Department Practice te for Authorized Persons, Registered Structural Engineers and Registered Geotechnical Engineers ADM-18 Site Auditing for Building Works Introduction This practice note provides

More information

TYPES OF PIERS USED IN NORTH AND EAST TEXAS RESIDENTIAL FOUNDATION REPAIR

TYPES OF PIERS USED IN NORTH AND EAST TEXAS RESIDENTIAL FOUNDATION REPAIR TYPES OF PIERS USED IN NORTH AND EAST TEXAS RESIDENTIAL FOUNDATION REPAIR If you listen to the hype, it sounds like there must be 20 or 30 different types of piers out there. Company A says they have an

More information

DESIGN IS GOOD BUSINESS

DESIGN IS GOOD BUSINESS COMPENSATING YOUR ARCHITECT The creature comforts are one thing, but for a house to become a home it s got to be elevated to the point that it s about raising one s spirits as well. SAMUEL MOCKBEE Building

More information

ENGINEERED FOUNDATIONS. Department of Public Works Jeff Hill, PE

ENGINEERED FOUNDATIONS. Department of Public Works Jeff Hill, PE ENGINEERED FOUNDATIONS Department of Public Works Jeff Hill, PE What is an engineered foundation. A Foundation Design Developed by a Trained Professional (Engineer) Types of Foundations (All of which can

More information