Using Earned Value Management to Manage Risk & Monitor Contract Performance

Size: px
Start display at page:

Download "Using Earned Value Management to Manage Risk & Monitor Contract Performance"

Transcription

1

2 Using Earned Value Management to Manage Risk & Monitor Contract Performance Breakout Session # B14 Stephen J. Yuter, CPCM, CFCM, PMP, Fellow Acting Director & Head of the Contracting Activity DHHS/Indian Health Service Date: July 28, 2014 Time: 2:30 p.m. 3:45 p.m.

3 OVERVIEW Definition & Principles of EVM EVM Process & Key Questions Traditional Management Systems vs. EVM Performance Measurements FAR & Agency EVM Requirements Contractor s Requirements and Validation Process for EVM Contracting Officer s Responsibilities for EVM 2 2

4 WHY IS THERE A NEED FOR EVM? Need for accurate and consistent status information Numerous complex (and interrelated) projects 70% of projects are over budget and behind schedule 52% of all projects finish at 189% of their initial budget 3 3

5 WHAT IS EVM? A Set of Business Practices integrate scope, schedule, and cost objectives establish a baseline plan for accomplishment of project or program objectives employ earned value techniques for performance management Compares where the project is now with: (1) previous work accomplished and (2) where the project was planned to be Early warning system to detect deficient or endangered progress 4 4

6 EVM DEFINED Earned value is the value of the work that has been completed it represents the amount of the overall project budget that has been earned based on the percentage of the work that has been accomplished EVM enables both the government and the contractor to have clear visibility into technical, cost and schedule planning, performance, and progress on their contracts EVM requires that each element of work be budgeted as each element is completed with clearly defined deliverables, its budgeted costs are earned by placing a cost value on status, a project's performance can be evaluated and communicated 5 5

7 ANSI/EIA-748 STANDARDS Prescribes 32 criteria in five categories: Organization - assign responsibilities for all WBS elements Planning, Scheduling, and Budgeting - measure performance against the integrated performance baseline Accounting Considerations - record project costs as consumed or incurred Analysis and Management Reports - analyze actual performance against the authorized baseline Revisions and Data Maintenance - provide timely approval/rejection of all change requests 6 6

8 Approaches to EVM: ANSI/EIA-748 COMPLIANCE All 32 ANSI Standard criteria apply (OMB full compliance) Criteria are scalable and can be adapted, based on a project s size, complexity, risk, etc. ( Tailored EVM) Selected criteria are applied and additional ones can be added, based on a project s size, complexity, risk, etc. (EVM Lite ) 7 7

9 BRIEF HISTORY OF EVM 1960s 1970s 1980s DoD adopted Cost/Schedule Control Systems Criteria (C/SCSC) as an objective measure of progress Continued use in DoD as a means to offset cost/schedule risk in cost-plus contracts Policy moved Earned Value into all Federal agencies OMB Circular A OMB began enforcement in all civilian agencies 8 8

10 BASIC PRINCIPLES OF EVM Proper use of EVM can provide early warning (forecasting) of impending problems, leaving ample time for corrective action EVM DOES NOT determine a course of action; instead, it simply isolates the cause of project problems or confirms that tasks are progressing as planned EVM is normally not appropriate for contracts that are not performancebased (e.g. FFP or T&M) or where the nature of the work is not measurable (e.g. level of effort, and/or in steady state operations and support); optimal for services contracts providing development & integration Applying EVM principles properly can provide for better control of program/project performance, along with greater accountability and a reduction in risk 9 9

11 BASIC PRINCIPLES OF EVM (CONT D.) Break down the work scope into discrete, measurable elements and assign responsibility Plan and integrate the scope, schedule, and cost into a timephased plan and control changes to the plan Provides the ability to examine detailed schedule information, critical program and technical milestones, and cost data Objectively assess progress and accomplishments Use actual costs, use information to manage Analyze variances from the plan 10 10

12 KEY ATTRIBUTES OF EVM 11 11

13 THE EARNED VALUE PROCESS Define the Work Plan the Work Work the Plan Collect Results Change Control Measure Performance External Changes Analyze Deviations Take Corrective Action 12

14 WHY USE EARNED VALUE MANAGEMENT? Ensures a clear definition of work prior to beginning that work Presents a logical plan for accomplishing the work Provides an objective measure of accomplishments Early and accurate identification of trends and problems Accurate picture of contract status - cost, schedule, and technical Basis for course correction Supports mutual goals of contractor and customer - bring project in on schedule and cost 13 13

15 EVM MEASURES PROGRESS Progress = movement towards a goal to measure progress, there must be a standard against which the movement may be compared EVM establishes that standard as the Performance Measurement Baseline and measures progress against that baseline 14 14

16 PERFORMANCE MEASUREMENT BASELINE Fundamental to earned value management Includes the undistributed budget, all summary level planning package budgets, and all control account budgets not include management reserve) Establishes the contract level timed phased baseline against which contract level earned value metrics are computed Establishes the performance targets for the program 15 15

17 WHAT DO WE MEASURE PROGRESS AGAINST? Performance measurement baseline: integrates three key measurements budget is spread over... time, to accomplish the scope of work against which progress can be measured compares the PLANNED amount of work with what has actually been COMPLETED, to determine if COST, SCHEDULE, and WORK ACCOMPLISHED are progressing as planned work is earned or credited as it is completed (expressed in dollar or hours); the value earned is the WBS budgeted cost of the activity completed to date 16 16

18 KEY QUESTIONS EVM ANSWERS We analyze past performance to help us control the future PAST PRESENT FUTURE Are we on schedule? Are we on cost? What are the significant variances? Why do we have variances? Who is responsible? What is the trend to date? When will we finish? What will it cost at the end? How can we control the trend? The Two Key Questions 1. Did we get what we wanted for what we spent? 2. At the end of the project, is it likely that the cost will be less than or equal to the original estimate? 17 17

19 WAYS OF EARNING VALUE Should be quantitative and discrete whenever possible Discrete = tangible end product e.g. delivery of a specification, vendor parts contract awarded, foundation completed Should be integrated with success criteria or technical measures e.g., successful completion of clean-up, a specific test, reliability growth curve 18 18

20 TRADITIONAL MANAGEMENT SYSTEMS In these systems, you budget work and then record actual expenditures. Example: I budget 5 widgets at 100 hrs. per widget. At the end of the month 400 hrs. had been expended. But what does this mean? Is this really the true status of work? What did I accomplish? GREAT! I'm 100hrs under budget Budget vs. Actual Variance = 19 19

21 MANAGEMENT SYSTEMS MEASUREMENT OF EXPENDITURES Well, I ve spent 400 hrs, does that mean I ve accomplished 400 hrs of work? Actual Cost is not an indication of work progress, only an indication of hours/money spent

22 MANAGEMENT USING EARNED VALUE Earned Value is an objective measure of how much work has been accomplished Example: I plan to build 5 widgets this month Each widget should take 100hrs I will measure Earned Value based on # widgets completed At Month End Budget Plan 500 Earned Value 300 (3 Widgets * 100 hrs.) Actual

23 EARNED VALUE ADDS A NEW DIMENSION TO TRADITIONAL TRACKING SYSTEMS Budget Plan 500hrs Earned Value 300hrs Cost Variance Schedule Variance (200) (100) Actual 400hrs I better figure out what is going on. I ve got 200 hours worth of work to catch up on, and I ve already overspent by 100 hours

24 USING PERFORMANCE DATA FOR DECISION-MAKING Behind Schedule How critical is schedule? Can I afford to work overtime to recover? Can I do tasks concurrently? Are there technical innovations which could speed up the process? Am I gold plating instead of just meeting requirements? Should I do a schedule risk assessment to project impact to program? Over Cost Can I reschedule tasks? (time phasing) Is there a less costly facility I can use? Are there tasks which can be deleted? Should the element be added to my risk management profile? 23 23

25 FIVE BASIC PERFORMANCE QUESTIONS & ANSWERS IN EVM Question Answer Acronym How much work did we plan to do? How much work got done? How much did the completed work cost? What was the total job supposed to cost? What do we now expect the total job to cost? Budgeted Cost for Work Scheduled Budgeted Cost for Work Performed Actual Cost of Work Performed Budget at Completion Estimate At Completion BCWS = PV BCWP = EV ACWP = AC BAC EAC 24 24

26 VARIANCE CALCULATIONS IN EVM Schedule Variance (SV) = EV PV the difference between Earned Value (EV) and Planned Value (PV) Schedule Performance Index (SPI) = EV/PV SPI<1 means project is behind schedule Cost Variance (CV) = EV - AC the difference between EV and Actual Cost (AC) Cost Performance Index (CPI) = EV/AC CPI<1 means project is over budget 25 25

27 MAKING PROJECTIONS WITH EVM Cost Schedule Index (CSI) = CPI x SPI the further CSI is from 1.0, the less likely project recovery becomes Once a project is 10% complete, the overrun at completion will not be less than the current overrun Once a project is 20% complete, the CPI does not vary from its current value by more than 10% The CPI and SPI are statistically accurate indicators of final cost results 26 26

28 CONTRACTOR S VARIANCE ANALYSIS Should address significant variances: Separate discussion of cost and schedule variances Clear description of reason for variance Quantity variances (e.g., price vs. usage) Be specific, not general Include corrective action Technical, schedule, and cost impacts Impact to estimate at completion Should be analyzed by the individual controlling the work 27 27

29 USING EVM PERFORMANCE DATA TO VALIDATE ESTIMATES New estimates at completion take on more meaning when you employ performance information To recover from a CPI of.5, the project would have to work at an efficiency > 1 The Estimate At Completion (EAC) can be predicted by the performance index: EAC = BAC = $20,000 = $40,000 CPI.5 The overrun will never be less than it is at the 15% complete point! 28 28

30 THE NEED FOR ACCURATE EACs New EACs take on more meaning when you employ performance information the EAC can be predicted by the performance index analysis of EAC realism what are the drivers? What can we do about them? Variance at Completion vs. Contractor Loss Positive VAC: EAC < BAC underrun contractor gain Negative VAC: EAC > BAC share area contractor partial loss EAC > ceiling overrun contractor loss (100%) Government develops top-level EAC for comparison: Government should limit progress payments if EAC is greater than contract ceiling Government needs accurate forecast of fund requirements 29 29

31 EARNED VALUE PROBLEM INDICATORS GOAL: to verify that effective variance analysis processes are applied to identify, correct, and report problems Potential Problem Indicators: Zero variances Monthly trends turning negative or downward Schedule variances generally indicate cost will follow Actuals > Latest Revised Estimates (LRE) BCWP increases with no increase in ACWP Negative data elements 30 30

32 STATUTES RELATED TO EVM The requirement for EVM as it is practiced today can be traced to three public laws: Government Performance and Results Act of 1993 (GPRA) Establish performance standards for Federal budget Federal Acquisition Streamlining Act, Title V of 1994 (FASA V) Report cost, schedule, and performance goals and evaluate progress Information Technology Management Reform Act of 1996/ Clinger-Cohen Act (ITMRA/Clinger-Cohen) Report performance information systems acquisition 31 31

33 EVM REQUIREMENTS OMB Circular A-11, Part 7 requires the use of EVM in the performance management of major investments and major systems in development, modernization, or enhancement (DME) or in mixed life-cycle "Agencies must use a performance-based acquisition management system to measure the achievement of cost, schedule, and performance goals, and achieve (on average), 90% of those goals Contractors Earned Value Management System (EVMS) must comply with the guidelines set forth in the American National Standards Institute (ANSI)/Electronic Industries Alliance (EIA)-748 Standard FAR (Pre-IRB), (Post-IRB), and (EVMS) Federal agencies requires its use on major programs (i.e. IT and non-it investments $100M or greater) and on their associated contracts with a contract price of $20M or greater; continued surveillance to ensure compliance 32 32

34 EVM REQUIREMENTS (CONT D.) Contract Total Value EVM Compliance CWBS & IMS CPR (monthly) CFSR (quarterly) $50M and greater $20M and greater but less than $50M Required Required Required Required Required Required Required Required Less than $20M Optional (at discretion of PM) Required if PM requires EVM Required if PM requires EVM Required 33 33

35 INTEGRATED BASELINE REVIEW (IBR) Determines that the Performance Measurement Baseline is responsive to the scope of work required Joint assessment of Coverage of SOW Scheduling of work Resource allocation Earned Value methodologies Technical content of PMB Realism and Risks Should be conducted pre-award but no later than 180 days post-award 34 34

36 THE CONTRACTOR S EVMS Describes system in sufficient detail to determine compliance Includes prior Certification/Acceptance If no EVMS is in place, Contractor must submit a comprehensive plan for compliance System description Necessary modifications Compliance map Process descriptions Recent evaluation or self-assessment results Identify major subcontracts for application of criteria Verify baseline integrity is maintained Contains plan and procedures for surveillance and self assessment 35 35

37 THE CONTRACTOR S EVMS (CONT D.) Surveillance Plan Methods and techniques Inclusion of new scope Customer coordination Schedule Analysis Ensure that reliable and timely cost, schedule, and technical performance information is generated Baseline Budget Control Accounts Baseline Schedule Work Measurement by Control Account Work-hours, dollars, units, etc

38 EVM VALIDATION Required for all companies with a EVMS cost-plus contract over $50M Validation is achieved by conducting a formal review of the processes defined and used by the contractor to comply with the EVMS guidelines in ANSI/EIA-748 Determines that the contractor is using the system as one of its primary program management processes has properly implemented the system on the contract is using the data from its system in reports to the government Single validation required for each company resulting in a compliant EVMS Note: an EVMS Compliance Review is the same as a Validation Review 37 37

39 EVM VALIDATION PROCESS A formal recognition of certification by an independent party that company s EVMS meets the guidelines in ANSI/EIA-748 A formal Government review conducted at a contractor s facility to assess the contractor s proposed EVMS compliance with ANSI/EIA-748 A recurring process by an independent party (normally DCMA) assessing the continuing compliance of the company s EVMS with ANSI/EIA-748 and the company s written system documentation n independent party (normally DCMA) assessing the continuing compliance of the company s EVMS with ANSI/EIA-748 and the company s written system documentation 38 38

40 Objectives: EVM VALIDATION REVIEW Evaluate management system capabilities against ANSI/EIA-748 Assess the description of the management system to determine if it adequately describes the management processes demonstrated during the review Evaluate the application of the management system on the contract being reviewed Validation Process: begins as soon as practicable following the implementation of the EVMS and IBR review system documentation reviews, data traces, and interviews with contractor personnel organized to follow the system approach taken by the contractor 39 39

41 FAILING THE VALIDATION Potential of extra withholding on payments that could be as much as 10% additional Disadvantage in bidding future EVM contracts Potential for additional oversight on existing EVM contracts Brings in question a company s ability to control and manage multi-million dollar programs Notable examples: Lockheed Martin & Bell Helicopter 40 40

42 EVMS IS IMPORTANT TO EFFECTIVE CONTRACT ADMINISTRATION EVMS gives early warning of potential problems As a Contract Specialist or Contracting Officer, you are a member of the Integrated Project Team (IPT) It is your job as the CS/CO to protect the Government s rights if performance does not show satisfactory progress! You must work with the other IPT members and the Contractor to avoid or mitigate performance problems 41 41

43 WHAT ARE THE CO S RESPONSIBILITIES REGARDING EVMS? Contracting Officer s Pre-Award Responsibilities as a Member of the IPT: Identify application of the Earned Value Management System in acquisition plans, solicitations and contracts Define reporting and electronic submission requirements Define evaluation criteria for source selections Factor EVMS into contract management planning 42 42

44 WHAT ARE THE CO S RESPONSIBILITIES REGARDING EVMS? (CONT D.) Contracting Officer s Post-Award Responsibilities as a Member of the IPT: Integrate performance monitoring with EVMS into Award/Incentive plans Monitor performance with IPT using the EVMS Act when performance is at risk (communication with contractor, show cause and cure notices, etc.) Evaluate the Contractor s EVMS implementation plan Evaluate the Contractor s EVM systems for compliance with the standard Conduct Integrated Baseline Reviews to ensure all the work scope is included in the baseline 43 43

45 EVM IMPACT ON MISSION By utilizing EVM properly, an agency can improve its ability to track and report on investment cost, schedule, and performance variances (agency projects must stay within a 10% variance) allow PMs and project team members to optimize resources and deliver capital investment projects on-time, on-budget, and within scope operate by tracking its programs health beyond pure financials ensure its customers requirements are satisfied 44 44

46 LIMITATIONS OF EVM Quantifying/measuring work progress can be difficult Time required for data measurement, input, and manipulation can be considerable EVM becomes problematic when Inadequate requirements definition Incomplete WBS Accounting systems that cannot address the WBS Lack of management attention to project progress Failure to respond to warning signs Failure to reconcile baseline to funding shortfalls (re-baseline) 45 45

47 EVM IS SUCCESSFUL When management embraces it When the program uses it to manage When all program levels understand how it works 46 46

48 SUMMARY EVM helps reduce the guesswork in: measuring performance forecasting Aids in getting beyond misleading measures of progress - provides a common denominator for work scope, schedule, and resources Reasons to use EVM: Good project management practices OMB/FAR requirement Should be incorporated into contracts for major acquisitions (cost-reimbursement) 47 47

49 EVM RESOURCES Practice Standard for Earned Value Management DoD Earned Value Management ANSI/EIA-748 Guide EIA748.pdf 48 48

50 Q & A 49 49

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1 Earned Value Valerie Colber, MBA, PMP, SCPM Not for duplication nor distribution 1 Where did Earned Value Management come from? In 1967 the Department of Defense (DoD) established the Cost/Schedule Control

More information

An introduction to Earned Value Analysis

An introduction to Earned Value Analysis An introduction to Earned Value Analysis Prepared by: Suketu Nagrecha, MBA, PMP, CNA March 16, 2002 Earned Value Analysis - 2 Abstract Earned value analysis is a method of performance measurement. Many

More information

Appendix D Glossary Of Terms

Appendix D Glossary Of Terms Appendix D Glossary Of Terms The notational style used in this glossary is to begin the definition of each defined term with a new paragraph beginning with the term in UPPERCASE. Any word or phrase used

More information

Government Contracting and Earned Value Management (EVM)

Government Contracting and Earned Value Management (EVM) Government Contracting and Earned Value Management (EVM) Ida Davis, EVP, PMP, MBA Earned Value Manager DynPort Vaccine Company LLC, A CSC Company Note: This presentation is the property of DynPort Vaccine

More information

Earned Value Management and the Government Program Office. Blair Alan Knapp Jr. MSPM PMP

Earned Value Management and the Government Program Office. Blair Alan Knapp Jr. MSPM PMP Earned Value Management and the Government Program Office Blair Alan Knapp Jr. MSPM PMP Agenda EVM Information Alignment OMB Exhibit 300 and Funding Government Program Office Challenges Government Program

More information

Basic Concepts of Earned Value Management (EVM)

Basic Concepts of Earned Value Management (EVM) Basic Concepts of Earned Value Management (EVM) This article provides an introduction to the basic concepts of earned value management (EVM), from initial project planning through execution including data

More information

Earned Value Management Systems Application Guide

Earned Value Management Systems Application Guide National Defense Industrial Association Integrated Program Management Division Earned Value Management Systems Application Guide January 27, 2015 Revision 2 National Defense Industrial Association (NDIA)

More information

IT Baseline Management Policy. Table of Contents

IT Baseline Management Policy. Table of Contents Table of Contents 1. INTRODUCTION... 1 1.1 Purpose... 2 1.2 Scope and Applicability... 2 1.3 Compliance, Enforcement, and Exceptions... 3 1.4 Authority... 3 2. ROLES, RESPONSIBILITIES, AND GOVERNANCE...

More information

Earned Value Management Systems Application Guide

Earned Value Management Systems Application Guide National Defense Industrial Association Integrated Program Management Division Earned Value Management Systems Application Guide May 4, 2011 Revision 1* National Defense Industrial Association (NDIA) 2111

More information

A Gentle Introduction to Earned Value Management Systems

A Gentle Introduction to Earned Value Management Systems A Gentle Introduction to Earned Value Management Systems Good metrics let us see if we are doing the right things and doing them well." Niwot Ridge Consulting 4347 Pebble Beach Niwot, Colorao www.niwotridge.com

More information

Predicting progress on your project

Predicting progress on your project www.nonsuch.co info@nonsuch.co Predicting progress on your project - using Lego bricks to understand Earned Value September 4 PM Conference 2015 Presented by Youssef Mourra Director, Principal Consultant

More information

THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH

THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH By Nghi M. Nguyen, Ph.D., PE, PMP. * INTRODUCTION The management of engineering projects

More information

INSE 6230 Total Quality Project Management

INSE 6230 Total Quality Project Management Lecture 5 Project Cost Management Project cost management introduction Estimating costs and budgeting Earned Value Management (EVM) 2 IT projects have a poor track record for meeting budget goals Cost

More information

Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition.

Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition. Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition. Errata for Chapter 7 (Replacement pages provided) Deleted up to a given point in time from the description

More information

What Does the Government Want from Project Management? DC PMI Chapter Executive Breakfast Series January 16, 2008

What Does the Government Want from Project Management? DC PMI Chapter Executive Breakfast Series January 16, 2008 What Does the Government Want from Project Management? DC PMI Chapter Executive Breakfast Series January 16, 2008 The Government Wants from Project Management A project management process and culture in

More information

DATA ITEM DESCRIPTION Title: Integrated Program Management Report (IPMR) Number: DI-MGMT-81861 Approval Date: 20120620

DATA ITEM DESCRIPTION Title: Integrated Program Management Report (IPMR) Number: DI-MGMT-81861 Approval Date: 20120620 DATA ITEM DESCRIPTION Title: Integrated Program Management Report (IPMR) Number: DI-MGMT-81861 Approval Date: 20120620 AMSC Number: D7549 Limitation: DTIC Applicable: No GIDEP Applicable: No Preparing

More information

Earned Value Management Tutorial Module 1: Introduction to Earned Value Management. Prepared by:

Earned Value Management Tutorial Module 1: Introduction to Earned Value Management. Prepared by: Earned Value Management Tutorial Module 1: Introduction to Earned Value Management Prepared by: Module1: Introduction to Earned Value Welcome to Module 1. The objective of this module is to introduce you

More information

700 Analysis and Reporting

700 Analysis and Reporting Jefferson Science Associates, LLC 700 Analysis and Reporting Project Control System Manual Revision 7-50 - 700 Analysis and Reporting This chapter of the JSA Project Control System Manual explains how

More information

Earned Value Management Tutorial Module 8: Reporting. Prepared by:

Earned Value Management Tutorial Module 8: Reporting. Prepared by: Earned Value Management Tutorial Module 8: Reporting Prepared by: Module 8: Government Required Reports Welcome to Module 8. The objective of this module is to introduce you to Government required reports.

More information

July 6, 2015 11(1) CHAPTER 11

July 6, 2015 11(1) CHAPTER 11 July 6, 2015 11(1) CHAPTER 11 Table of Contents Paragraph Page 11-000 Audit of Contractor Compliance with Contract Financial Management Requirements 11-001 Scope of Chapter... 1101 11-100 Section 1 ---

More information

Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance.

Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance. About the Tutorial Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance. This is a brief tutorial that acquaints

More information

AACE International Recommended Practice No. 86R 14

AACE International Recommended Practice No. 86R 14 AACE International Recommended Practice No. 86R 14 VARIANCE ANALYSIS AND REPORTING TCM Framework: 9.1 Project Cost Accounting 9.2 Progress and Performance Measurement 10.1 Project Performance Assessment

More information

Simple Earned Value (Using MS Project 2010)

Simple Earned Value (Using MS Project 2010) Simple Earned Value (Using MS Project 2010) This document outlines a Simple Earned Value technique, a technique which sticks to a simple 0/100% Milestone approach with some Level of effort tasks maintained

More information

IST 302 : Project Cost Management

IST 302 : Project Cost Management IST 302 : Project Cost Management Project Cost Management : Why do we care? 1 Cost and Cost Management Cost: Cost Management: Project Cost Management Processes Cost Estimating Developing an estimate of

More information

L10: Budgeting and Cost Control. Olivier de Weck

L10: Budgeting and Cost Control. Olivier de Weck ESD.36 System Project Management + L10: Budgeting and Cost Control Instructor(s) Olivier de Weck Lecture 10 Oct. 11, 2012 System Project Management ESD.36 Framework Project Preparation Enterprise has chosen

More information

DCMA DCMA-EA PAM 200.1. October 2012

DCMA DCMA-EA PAM 200.1. October 2012 DCMA Earned Value Management System (EVMS) Program Analysis Pamphlet (PAP) DCMA-EA PAM 200.1 October 2012 THE DCMA ENGINEERING AND ANALYSIS EXECUTIVE DIRECTOR IS RESPONSIBLE FOR ISSUANCE AND MAINTENANCE

More information

This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts.

This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts. This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts. To begin, how does the Prime integrate the subcontractor

More information

Earned Value Formulae

Earned Value Formulae Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from http://www.mosaicprojects.com.au/techniques.html#earnedvalue

More information

Brainstorm. What is Cost and Project Cost Management?

Brainstorm. What is Cost and Project Cost Management? Brainstorm Suppose you need to create a network from scratch in your organization's headquarter. Your project is named HQ Network. Your major deliverables includes: LAN, WAN, server room, workstations,

More information

Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting. Prepared by:

Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting. Prepared by: Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting Prepared by: Module 6: Metrics, Performance Measurements and Forecasting Welcome to Module 6. The objective

More information

PROJECT MANAGEMENT AND THE ACQUISITION OF MAJOR SYSTEMS

PROJECT MANAGEMENT AND THE ACQUISITION OF MAJOR SYSTEMS PROJECT MANAGEMENT AND THE ACQUISITION OF MAJOR SYSTEMS Guiding Principle: Sound planning and management of DOE s contracts for the acquisition of projects are essential to the success of the Department

More information

FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT. Head, Office of Project Management Oversight

FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT. Head, Office of Project Management Oversight SUBJECT: FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT NUMBER: 12.PM-006 RESPONSIBILITY: Office of Project Management Oversight REVISION: 54 APPROVED BY: TITLE DRAFT FOR DISCUSSION Head, Office

More information

Rules on using templates. MECH 896 Professional Development for MEng Students. Assignment #6A: Questions. Homework Discussion

Rules on using templates. MECH 896 Professional Development for MEng Students. Assignment #6A: Questions. Homework Discussion MECH 896 Professional Development for MEng Students Mohamed Hefny and Brian Surgenor (hefny@cs.queensu.ca and surgenor@me.queensu.ca) Rules on using templates 1) Must reference the template used 2) Use

More information

Introduction to earn value management in Civil Engineering

Introduction to earn value management in Civil Engineering 3 rd World Conference on Applied Sciences, Engineering & Technology 27-29 September 2014, Kathmandu, Nepal Introduction to earn value management in Civil Engineering S. K. KAMANE, S. A. MAHADIK, A. C.

More information

Earned Value Management Best Practices

Earned Value Management Best Practices Division of Information Technology Investment Management Enterprise Architecture & Strategy Group Office of Information Services Earned Value Management Best Practices Version 2.2 Last Modified: 19 November

More information

How To Write Ansi/Eia Evm System Acceptanceance Guide

How To Write Ansi/Eia Evm System Acceptanceance Guide National Defense Industrial Association (NDIA) Program Management Systems Committee (PMSC) ANSI/EIA 748 Earned Value Management System Acceptance Guide Working Release For User Comment January 23, 2006

More information

How To Manage A Project

How To Manage A Project Project Management Institute Practice Standard for EARNED VALUE MANAGEMENT Global Project Management Institute Practice Standard for Earned Value Management Practice Standard for Earned Value Management

More information

Project Management System Description (PMSD)

Project Management System Description (PMSD) Project Management System Description (PMSD) Revision 3 Project Management System Description (PMSD) Revision 3 February 2016 Prepared by: Date: Steve Langish Planning & Control Division Approved by: Date:

More information

Using Earned Value Management for Improving Processes. By Cynthia K. West

Using Earned Value Management for Improving Processes. By Cynthia K. West Using Earned Value Management for Improving Processes By Cynthia K. West Summary: This article explains earned value management and explores how the metric can be used to improve project and business processes.

More information

Chapter 7. (PMBOK Guide)

Chapter 7. (PMBOK Guide) Chapter 7 Project Cost Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: marajabi@ut.ac.irac ir Homepage:

More information

Earned Value Management System Description

Earned Value Management System Description LCLS Project Management Document # 1.1-015 Project Management Revision 3.0 Earned Value Management System Description Patricia Mast (LCLS Project Controls Manager) Signature Date Mark Reichanadter (LCLS

More information

Earned Value and Agile Reporting

Earned Value and Agile Reporting Earned Value and Agile Reporting Anthony Cabri, Mike Griffiths Quadrus Development Inc. Abstract This paper reviews the concepts of Earned Value Management established in traditional project management,

More information

Earned Value Management Guidelines

Earned Value Management Guidelines Effective Date: April 21, 2009 Status: Revision 1 Supersedes: NA Document Owner: Director, Environmental and Engineering Program Introduction This paper provides guidance and recommendations for the application

More information

Chapter 7: Project Cost Management. Munawar moenawar@gmail.com

Chapter 7: Project Cost Management. Munawar moenawar@gmail.com Chapter 7: Project Cost Management Munawar moenawar@gmail.com Learning Objectives Understand the importance of project cost management. Explain basic project cost management principles, concepts, and terms.

More information

Estimating Cost at Completion - Judgment & EV Information

Estimating Cost at Completion - Judgment & EV Information Page 1 of 10 Estimating Cost at Completion - Judgment & EV Information Cost estimating is often called a "black art" and, too often, estimates are structured to fit some predetermined idea of a number

More information

Tracking Budgets and Schedules

Tracking Budgets and Schedules Tracking Budgets and Schedules David V. Tennant, PE, PMP One of the simplest questions you are likely to encounter as an engineering or project manager is: Are we on budget and schedule? While this is

More information

EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS

EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS 14 EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS Dr. P.B.G. Dissanayake 1 1 Department of Civil Engineering, Faculty of Engineering, University of Peradeniya

More information

EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT

EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT Assoc. Prof. Anca Mehedintu Ph. D University of Craiova Faculty of Economics and Business Administration Craiova, Romania Prof. Cerasela Pirvu

More information

Young Hoon Kwak Associate Professor School of Business The George Washington University

Young Hoon Kwak Associate Professor School of Business The George Washington University Project Management in Government: An Introduction to Earned Value Management (EVM) Improving Performance Series Young Hoon Kwak Associate Professor School of Business The George Washington University Frank

More information

Internal Surveillance

Internal Surveillance Page 1 of 18 Internal Surveillance A contract having Earned Value Management System (EVMS) requires the contractor to maintain an effective management control system consistent with EVM industry standards

More information

SUCCESSFULLY INTEGRATING AGILE WITH EARNED VALUE MANAGEMENT

SUCCESSFULLY INTEGRATING AGILE WITH EARNED VALUE MANAGEMENT 1 PMSC Quarterly Meeting, February 1 2, 2011, Fort Worth, Texas SUCCESSFULLY INTEGRATING AGILE WITH EARNED VALUE MANAGEMENT Increasing the Probability Program of Success (PoPS)by Connect the dots between

More information

Using Earned Value Management Concepts to Improve Commercial Project Performance

Using Earned Value Management Concepts to Improve Commercial Project Performance Using Earned Value Management Concepts to Improve Commercial Project Performance R. Scott Brunton, PMP, PMI-RMP/SP, EVP Principal Solutions Consultant Lewis Fowler, LLC www.lewisfowler.com Welcome to the

More information

Essential Views of the Integrated Program Management Reports. Thomas J. Coonce Glen B. Alleman

Essential Views of the Integrated Program Management Reports. Thomas J. Coonce Glen B. Alleman Essential Views of the Integrated Program Management Reports Thomas J. Coonce Glen B. Alleman Agenda Background Twenty-five metrics are proposed Twelve are demonstrated with tasserted value to the government

More information

Project Cost Management

Project Cost Management Project Cost Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points To Note Please

More information

Earned Value Management System (EVMS) and. Project Analysis Standard Operating Procedure (EPASOP)

Earned Value Management System (EVMS) and. Project Analysis Standard Operating Procedure (EPASOP) Earned Value Management System (EVMS) and Project Analysis Standard Operating Procedure (EPASOP) Issued by Office of Acquisition and Project Management MA-63 March 12, 2014 DEPARTMENT OF ENERGY Office

More information

Selftestengine..PMI-SP.270 questions PMI-SP. PMI Scheduling Professional

Selftestengine..PMI-SP.270 questions PMI-SP. PMI Scheduling Professional Selftestengine..PMI-SP.270 questions Number: PMI-SP Passing Score: 800 Time Limit: 120 min File Version: 5.1 PMI-SP PMI Scheduling Professional This study guides are so comprehensible that anyone can understand

More information

SoaDssPm: A new Service-Oriented Architecture of the decision support system for the Project Management.

SoaDssPm: A new Service-Oriented Architecture of the decision support system for the Project Management. SoaDssPm: A new Service-Oriented Architecture of the decision support system for the Project Management. Fatima Boumahdi, Rachid Chalal Abstract This paper presents an architecture for the Project Management,

More information

technical tips and tricks

technical tips and tricks technical tips and tricks Earned Value Analysis Overview Document author: Produced by: Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the smart

More information

CONVERTING TO PHYSICAL % COMPLETE METHOD OF EARNED VALUE IN MICROSOFT PROJECT

CONVERTING TO PHYSICAL % COMPLETE METHOD OF EARNED VALUE IN MICROSOFT PROJECT CONVERTING TO PHYSICAL % COMPLETE METHOD OF EARNED VALUE IN MICROSOFT PROJECT PREPARED BY James E Aksel, PMP jim@projectpmo.com http://www.msprojectdblog.com http://www.projectpmo.com Page 1 of 19 Table

More information

Project Management Using Earned Value

Project Management Using Earned Value Project Management Using Earned Value Third Edition Gary C. Humphreys Earned Value Management Consulting Training 2002, 2011, 2014 Gary C. Humphreys Humphreys & Associates, Inc. All rights reserved. No

More information

Earned Value Management and Professional Services Automation

Earned Value Management and Professional Services Automation Earned Value Management and Professional Services Automation Prepared by: Frances B. Craig Unanet Technologies www.unanet.com 1 of 5 Earned Value Management and Professional Services Automation Earned

More information

GPMCEP GLOBAL PROJECT MANAGEMENT, LLC C O U R S E

GPMCEP GLOBAL PROJECT MANAGEMENT, LLC C O U R S E C O U R S E C E GPMCEP GLOBAL PROJECT MANAGEMENT, LLC Project Management Professional (PMP) Certification Exam Prep Global Project Management, LLC is a Global Registered Education Provider (R.E.P.) of

More information

Earned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP

Earned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP Earned Value Exercise 1 Running head: Earned Value Exercise Earned Value Exercise SuCheng Wu MET AD 644: Project Risk, and Cost Management Paul B. Cook, PhD PMP Earned Value Exercise 2 Case 1: Background:

More information

Agile Project Management Controls

Agile Project Management Controls 0 Agile Project Management Controls Issues with EVM and a Viable Alternative: Agile Project Management (PM) Tool ICEAA Conference, June 2015 San Diego, CA Blaze Smallwood, Booz Allen Hamilton Omar Mahmoud,

More information

Project Management: Tracking Progress and Earned Value with MS Project 2003

Project Management: Tracking Progress and Earned Value with MS Project 2003 Project Management: Tracking Progress and Earned Value with MS Project 2003 Project Planning Suppose you have been assigned a project to construct a website in a certain time frame and given a certain

More information

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu Management, Sixth Edition Note: See the text itself for full citations. More courses at cie-wc.edu Understand the importance of project cost management Explain basic project cost management principles,

More information

Over Target Baseline and Over Target Schedule Guide

Over Target Baseline and Over Target Schedule Guide Over Target Baseline and Over Target Schedule Guide OUSD AT&L (PARCA) December 5, 2012 1 Table of Contents Section Page No. Introduction 4 Chapter 1. What is Formal Reprogramming? 5 1.1 Formal Reprogramming

More information

Brief Introduction to Earned Value Management (EVM)

Brief Introduction to Earned Value Management (EVM) Brief Introduction to Earned Value Management (EVM) 12/25/06 EVM Introduction 1 12/25/06 EVM Introduction 1 Outline Introduction to the basic rationale and elements of EVM Issues of actually implementing

More information

Unit 5: Cost Management (PMBOK Guide, Chapter 7)

Unit 5: Cost Management (PMBOK Guide, Chapter 7) (PMBOK Guide, Chapter 7) The questions on this topic have historically been more difficult than average for some exam takers because of unfamiliarity with some of the math. You will be responsible for

More information

IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques

IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques Kym Henderson Former Education Director, PMI Sydney Chapter March 2003 to March 2007 Kym.Henderson@froggy.com.au

More information

FRA s Earned Value Management System Overview for Self Assessment Surveillance March 07-09, 2011

FRA s Earned Value Management System Overview for Self Assessment Surveillance March 07-09, 2011 FRA s Earned Value Management System Overview for Self Assessment Surveillance March 07-09, 2011 Dean Hoffer Head, Office of Project Management Oversight Outline EVMS History at the Lab FRA EVMS Documents

More information

Defense Logistics Agency INSTRUCTION

Defense Logistics Agency INSTRUCTION Defense Logistics Agency INSTRUCTION DLAI 2105 Effective May 13, 2013 SUBJECT: Earned Value Management (EVM) Systems Performance, Oversight, and Governance Referenses: (a) DLA Instruction 2105, Earned

More information

The Two Most Useful Earned Value Metrics: the CPI and the TCPI

The Two Most Useful Earned Value Metrics: the CPI and the TCPI PM WORLD TODAY SECOND EDITIONS JUNE 2009 Editor s note: Second Editions are papers that have been previously published that have continued relevance and deserve additional visibility. The paper below was

More information

Analysis and Application of Earned Value Management in Software Development

Analysis and Application of Earned Value Management in Software Development Analysis and Application of Earned Value Management in Software Development Frank Tsui School of Computing and Software Engineering Southern Polytechnic State University, Marietta, Georgia, USA 30060 Abstract

More information

Project Management. ZEUS Student Seminar on 14 th November 2003 by Riko Wichmann. Riko Wichmann, MPY Zeus Student Seminar - PM, 14.11.

Project Management. ZEUS Student Seminar on 14 th November 2003 by Riko Wichmann. Riko Wichmann, MPY Zeus Student Seminar - PM, 14.11. Project Management ZEUS Student Seminar on 14 th November 2003 by Riko Wichmann Riko Wichmann, MPY Zeus Student Seminar - PM, 14.11.2003 1 Project Management - Training Program - Project Scope Management

More information

Portfolio Management through Capital Planning and Investment Control: Program Planning Best Practice Agency Level (for the US Department of State)

Portfolio Management through Capital Planning and Investment Control: Program Planning Best Practice Agency Level (for the US Department of State) Portfolio Management through Capital Planning and Investment Control: Program Planning Best Practice Agency Level (for the US Department of State) Robert A. Horrigan, PMP Knowledge Exchange Forum Moderator

More information

Orange County Convention Center Orlando, Florida June 3-5, 2014. Using SAP PS Earned Value to Manage IT Projects Michael Kim (michael.kim@prpx.

Orange County Convention Center Orlando, Florida June 3-5, 2014. Using SAP PS Earned Value to Manage IT Projects Michael Kim (michael.kim@prpx. Orange County Convention Center Orlando, Florida June 3-5, 2014 Using SAP PS Earned Value to Manage IT Projects Michael Kim (michael.kim@prpx.com) AGENDA What is a typical problem with IT projects? What

More information

EARNED VALUE MANAGEMENT SYSTEMS (EVMS)

EARNED VALUE MANAGEMENT SYSTEMS (EVMS) NOT MEASUREMENT SENSITIVE DOE G 413.3-10 XX-XX-08 EARNED VALUE MANAGEMENT SYSTEMS (EVMS) [This Guide describes suggested nonmandatory approaches for meeting requirements. Guides are not requirements documents

More information

NASA/SP-2012-599 Earned Value Management (EVM) Implementation Handbook

NASA/SP-2012-599 Earned Value Management (EVM) Implementation Handbook NASA/SP-2012-599 Earned Value Management (EVM) Implementation Handbook National Aeronautics and Space Administration NASA Headquarters Washington, D.C. 20546 February 2013 NASA STI Program... in Profile

More information

PERFORMANCE AND QUALITY IN PROJECTS Project Management and Leadership 2016D, PhD, PMP

PERFORMANCE AND QUALITY IN PROJECTS Project Management and Leadership 2016D, PhD, PMP PERFORMANCE AND QUALITY IN PROJECTS Project Management and Leadership 2016D, PhD, PMP PROJECTS PROGRESS WELL UNTIL 70% Quick progress until 60-70% complete. Then we discover the project is in distress.

More information

Pune, MH, India. 2 P.G. Student, Imperial College of Engineering & Research, Wagholi, Pune, MH, India. wit.vaishnavi@gmail.com

Pune, MH, India. 2 P.G. Student, Imperial College of Engineering & Research, Wagholi, Pune, MH, India. wit.vaishnavi@gmail.com COST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHOD Dr. Arun Dhawale 1 Vaishnavi Tuljapurkar 2 1 Head of Department, Associate Professor, Department of Civil Engineering, Imperial College of

More information

300 Scheduling and Budgeting

300 Scheduling and Budgeting Jefferson Science Associates, LLC 300 Scheduling and Budgeting Project Control System Manual Revision 7-16 - 300 Scheduling and Budgeting This chapter of the JSA Project Control System Manual describes

More information

Towards a Complete Earned Value Analysis. Sam Sharp and Peter Hall. Paper # 166

Towards a Complete Earned Value Analysis. Sam Sharp and Peter Hall. Paper # 166 Towards a Complete Earned Value Analysis Sam Sharp and Peter Hall Paper # 166 Planned vs Actual A purely accounting approach to project tracking involves the monitoring of status by simply comparing actual

More information

DCMA EVMS COMPLIANCE REPORT I LOCKHEED MARTIN AERONAUTICS CO.

DCMA EVMS COMPLIANCE REPORT I LOCKHEED MARTIN AERONAUTICS CO. POST ACCEPTANCE REVIEW FOR CAUSE COMPLIANCE REPORT FOR THE LOCKHEED MARTIN AERONAUTICS COMPANY FORT WORTH, TEXAS PREPARED BY: DEFENSE CONTRACT MANAGEMENT AGENCY (DCMA) EARNED VALUE MANAGEMENT (EVM) CENTER

More information

Training Seminars. Description. Core Courses: The core courses consist of the following:

Training Seminars. Description. Core Courses: The core courses consist of the following: Training Seminars Description The POI consists of training courses known as core. The purpose of the core courses is to provide a principles or foundation knowledge baseline to the student in the fundamentals

More information

Services Contracts and Earned Value Management (EVM)

Services Contracts and Earned Value Management (EVM) Services Contracts and Earned Value Management (EVM) National Defense Industrial Association 2111 Wils on Blvd, Suite 400 Arlington, VA 22201 www.ndia.org February 17, 2010 www.ndia.org 2010 National Defense

More information

PEP TALK. Policy EVMS - PARS. Department of Energy Acquisition and Project Management Workshop Federal Stewardship Providing the Value Proposition

PEP TALK. Policy EVMS - PARS. Department of Energy Acquisition and Project Management Workshop Federal Stewardship Providing the Value Proposition 2015 Department of Energy Acquisition and Project Management Workshop Federal Stewardship Providing the Value Proposition PEP TALK Policy EVMS - PARS Melvin Frank Chief, Project Systems Division/MA-632

More information

Basics of Cost and Schedule Control

Basics of Cost and Schedule Control Basics of Cost and Schedule Control Topics Monitoring and Scheduling: Two Parts of a Feedback System. Definitions Schedule Updates from Monitoring Components of Effective Monitoring Cost Control As A Management

More information

Risk Mitigation and Subcontract Management

Risk Mitigation and Subcontract Management Risk Mitigation and Subcontract Management Breakout Session # C13 Danielle Carr, MSM Program Acquisitions, HMS Technologies Stacey B. Dey-Foy Director Suspension & Debarment, EPA July 28, 2014 @ 4:00pm

More information

Project Control with ProTrack

Project Control with ProTrack Project Control with ProTrack 1.0 (last update: 11/11/08) 1 Project Control with ProTrack by Mario Vanhoucke Professor at Ghent University and Vlerick Leuven Gent Management School (Belgium) Partner OR-AS

More information

QUALITY AND PERFORMANCE IN PROJECTS. Project Management and Leadership 2015D, PhD, PMP

QUALITY AND PERFORMANCE IN PROJECTS. Project Management and Leadership 2015D, PhD, PMP QUALITY AND PERFORMANCE IN PROJECTS Project Management and Leadership 2015D, PhD, PMP Our PROGRAMME: 1. INTRODUCTION TO PROJECT MANAGEMENT 2. STARTING A PROJECT 3. WORK MOTIVATION 4. COMMUNICATION 5: TEAMS

More information

MTAT.03.244 Software Economics. Lecture 6: Software Cost Estimation (part II)

MTAT.03.244 Software Economics. Lecture 6: Software Cost Estimation (part II) MTAT.03.244 Software Economics Lecture 6: Software Cost Estimation (part II) Marlon Dumas marlon.dumas ät ut. ee Outline Review of Effort Estimation Homework Discussion on book chapter by Caper Jones Earned

More information

Exhibit 300: Capital Asset Plan and Business Case Summary PART I: SUMMARY INFORMATION AND JUSTIFICATION (All Capital Assets)

Exhibit 300: Capital Asset Plan and Business Case Summary PART I: SUMMARY INFORMATION AND JUSTIFICATION (All Capital Assets) Exhibit 300: Capital Asset Plan and Business Case Summary PART I: SUMMARY INFORMATION AND JUSTIFICATION (All Capital Assets) Section A: Overview (All Capital Assets) 1. Date of Submission: 09/08/2006 2.

More information

What is the Health of my Project?

What is the Health of my Project? WHITE PAPER What is the Health of my Project? The Use and Benefits of Earned Value Table of Contents How s My Project Doing?...1 Need a Solution? Earned Value to the Rescue!...1 My actual costs are less

More information

LEADING EDGE FORUM CSC PAPERS 2012 EARNED SCHEDULE: FROM EMERGING PRACTICE TO PRACTICAL APPLICATION

LEADING EDGE FORUM CSC PAPERS 2012 EARNED SCHEDULE: FROM EMERGING PRACTICE TO PRACTICAL APPLICATION LEADING EDGE FORUM CSC PAPERS 2012 EARNED SCHEDULE: FROM EMERGING PRACTICE TO PRACTICAL APPLICATION Author Bill Mowery MPM, PMP Keywords Earned Value Management, Earned Schedule, Project Management, Cost

More information

technical tips and tricks

technical tips and tricks technical tips and tricks Applying Earned Value Analysis Document author: Produced by: Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the smart

More information

Chapter 7: Project Cost Management. Information Technology Project Management, Fourth Edition

Chapter 7: Project Cost Management. Information Technology Project Management, Fourth Edition Chapter 7: Project Cost Management Information Technology Project Management, Fourth Edition Learning Objectives Understand the importance of project cost management. Explain basic project cost management

More information

Project Reviews Lessons Learned Presented by: Kellie Cloud, PMP, PMI SP, PMI RMP, EVP

Project Reviews Lessons Learned Presented by: Kellie Cloud, PMP, PMI SP, PMI RMP, EVP Project Reviews Lessons Learned Presented by: Kellie Cloud, PMP, PMI SP, PMI RMP, EVP Project Management Institute WDC Chapter Chantilly Luncheon 10 March 2011 Topics of Discussioni Best Practices and

More information

PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION

PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION PMP SAMPLE QUESTIONS http://www.tutorialspoint.com/pmp-exams/pmp_sample_questions.htm Copyright tutorialspoint.com BASED ON PMBOK 5TH EDITION Here are 200 more objective type sample questions and their

More information

Project Cost Management

Project Cost Management Project Cost Management Guide to Mathematical Questions PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Present

More information