Using Earned Value Management to Manage Risk & Monitor Contract Performance
|
|
- Silas Willis
- 7 years ago
- Views:
Transcription
1
2 Using Earned Value Management to Manage Risk & Monitor Contract Performance Breakout Session # B14 Stephen J. Yuter, CPCM, CFCM, PMP, Fellow Acting Director & Head of the Contracting Activity DHHS/Indian Health Service Date: July 28, 2014 Time: 2:30 p.m. 3:45 p.m.
3 OVERVIEW Definition & Principles of EVM EVM Process & Key Questions Traditional Management Systems vs. EVM Performance Measurements FAR & Agency EVM Requirements Contractor s Requirements and Validation Process for EVM Contracting Officer s Responsibilities for EVM 2 2
4 WHY IS THERE A NEED FOR EVM? Need for accurate and consistent status information Numerous complex (and interrelated) projects 70% of projects are over budget and behind schedule 52% of all projects finish at 189% of their initial budget 3 3
5 WHAT IS EVM? A Set of Business Practices integrate scope, schedule, and cost objectives establish a baseline plan for accomplishment of project or program objectives employ earned value techniques for performance management Compares where the project is now with: (1) previous work accomplished and (2) where the project was planned to be Early warning system to detect deficient or endangered progress 4 4
6 EVM DEFINED Earned value is the value of the work that has been completed it represents the amount of the overall project budget that has been earned based on the percentage of the work that has been accomplished EVM enables both the government and the contractor to have clear visibility into technical, cost and schedule planning, performance, and progress on their contracts EVM requires that each element of work be budgeted as each element is completed with clearly defined deliverables, its budgeted costs are earned by placing a cost value on status, a project's performance can be evaluated and communicated 5 5
7 ANSI/EIA-748 STANDARDS Prescribes 32 criteria in five categories: Organization - assign responsibilities for all WBS elements Planning, Scheduling, and Budgeting - measure performance against the integrated performance baseline Accounting Considerations - record project costs as consumed or incurred Analysis and Management Reports - analyze actual performance against the authorized baseline Revisions and Data Maintenance - provide timely approval/rejection of all change requests 6 6
8 Approaches to EVM: ANSI/EIA-748 COMPLIANCE All 32 ANSI Standard criteria apply (OMB full compliance) Criteria are scalable and can be adapted, based on a project s size, complexity, risk, etc. ( Tailored EVM) Selected criteria are applied and additional ones can be added, based on a project s size, complexity, risk, etc. (EVM Lite ) 7 7
9 BRIEF HISTORY OF EVM 1960s 1970s 1980s DoD adopted Cost/Schedule Control Systems Criteria (C/SCSC) as an objective measure of progress Continued use in DoD as a means to offset cost/schedule risk in cost-plus contracts Policy moved Earned Value into all Federal agencies OMB Circular A OMB began enforcement in all civilian agencies 8 8
10 BASIC PRINCIPLES OF EVM Proper use of EVM can provide early warning (forecasting) of impending problems, leaving ample time for corrective action EVM DOES NOT determine a course of action; instead, it simply isolates the cause of project problems or confirms that tasks are progressing as planned EVM is normally not appropriate for contracts that are not performancebased (e.g. FFP or T&M) or where the nature of the work is not measurable (e.g. level of effort, and/or in steady state operations and support); optimal for services contracts providing development & integration Applying EVM principles properly can provide for better control of program/project performance, along with greater accountability and a reduction in risk 9 9
11 BASIC PRINCIPLES OF EVM (CONT D.) Break down the work scope into discrete, measurable elements and assign responsibility Plan and integrate the scope, schedule, and cost into a timephased plan and control changes to the plan Provides the ability to examine detailed schedule information, critical program and technical milestones, and cost data Objectively assess progress and accomplishments Use actual costs, use information to manage Analyze variances from the plan 10 10
12 KEY ATTRIBUTES OF EVM 11 11
13 THE EARNED VALUE PROCESS Define the Work Plan the Work Work the Plan Collect Results Change Control Measure Performance External Changes Analyze Deviations Take Corrective Action 12
14 WHY USE EARNED VALUE MANAGEMENT? Ensures a clear definition of work prior to beginning that work Presents a logical plan for accomplishing the work Provides an objective measure of accomplishments Early and accurate identification of trends and problems Accurate picture of contract status - cost, schedule, and technical Basis for course correction Supports mutual goals of contractor and customer - bring project in on schedule and cost 13 13
15 EVM MEASURES PROGRESS Progress = movement towards a goal to measure progress, there must be a standard against which the movement may be compared EVM establishes that standard as the Performance Measurement Baseline and measures progress against that baseline 14 14
16 PERFORMANCE MEASUREMENT BASELINE Fundamental to earned value management Includes the undistributed budget, all summary level planning package budgets, and all control account budgets not include management reserve) Establishes the contract level timed phased baseline against which contract level earned value metrics are computed Establishes the performance targets for the program 15 15
17 WHAT DO WE MEASURE PROGRESS AGAINST? Performance measurement baseline: integrates three key measurements budget is spread over... time, to accomplish the scope of work against which progress can be measured compares the PLANNED amount of work with what has actually been COMPLETED, to determine if COST, SCHEDULE, and WORK ACCOMPLISHED are progressing as planned work is earned or credited as it is completed (expressed in dollar or hours); the value earned is the WBS budgeted cost of the activity completed to date 16 16
18 KEY QUESTIONS EVM ANSWERS We analyze past performance to help us control the future PAST PRESENT FUTURE Are we on schedule? Are we on cost? What are the significant variances? Why do we have variances? Who is responsible? What is the trend to date? When will we finish? What will it cost at the end? How can we control the trend? The Two Key Questions 1. Did we get what we wanted for what we spent? 2. At the end of the project, is it likely that the cost will be less than or equal to the original estimate? 17 17
19 WAYS OF EARNING VALUE Should be quantitative and discrete whenever possible Discrete = tangible end product e.g. delivery of a specification, vendor parts contract awarded, foundation completed Should be integrated with success criteria or technical measures e.g., successful completion of clean-up, a specific test, reliability growth curve 18 18
20 TRADITIONAL MANAGEMENT SYSTEMS In these systems, you budget work and then record actual expenditures. Example: I budget 5 widgets at 100 hrs. per widget. At the end of the month 400 hrs. had been expended. But what does this mean? Is this really the true status of work? What did I accomplish? GREAT! I'm 100hrs under budget Budget vs. Actual Variance = 19 19
21 MANAGEMENT SYSTEMS MEASUREMENT OF EXPENDITURES Well, I ve spent 400 hrs, does that mean I ve accomplished 400 hrs of work? Actual Cost is not an indication of work progress, only an indication of hours/money spent
22 MANAGEMENT USING EARNED VALUE Earned Value is an objective measure of how much work has been accomplished Example: I plan to build 5 widgets this month Each widget should take 100hrs I will measure Earned Value based on # widgets completed At Month End Budget Plan 500 Earned Value 300 (3 Widgets * 100 hrs.) Actual
23 EARNED VALUE ADDS A NEW DIMENSION TO TRADITIONAL TRACKING SYSTEMS Budget Plan 500hrs Earned Value 300hrs Cost Variance Schedule Variance (200) (100) Actual 400hrs I better figure out what is going on. I ve got 200 hours worth of work to catch up on, and I ve already overspent by 100 hours
24 USING PERFORMANCE DATA FOR DECISION-MAKING Behind Schedule How critical is schedule? Can I afford to work overtime to recover? Can I do tasks concurrently? Are there technical innovations which could speed up the process? Am I gold plating instead of just meeting requirements? Should I do a schedule risk assessment to project impact to program? Over Cost Can I reschedule tasks? (time phasing) Is there a less costly facility I can use? Are there tasks which can be deleted? Should the element be added to my risk management profile? 23 23
25 FIVE BASIC PERFORMANCE QUESTIONS & ANSWERS IN EVM Question Answer Acronym How much work did we plan to do? How much work got done? How much did the completed work cost? What was the total job supposed to cost? What do we now expect the total job to cost? Budgeted Cost for Work Scheduled Budgeted Cost for Work Performed Actual Cost of Work Performed Budget at Completion Estimate At Completion BCWS = PV BCWP = EV ACWP = AC BAC EAC 24 24
26 VARIANCE CALCULATIONS IN EVM Schedule Variance (SV) = EV PV the difference between Earned Value (EV) and Planned Value (PV) Schedule Performance Index (SPI) = EV/PV SPI<1 means project is behind schedule Cost Variance (CV) = EV - AC the difference between EV and Actual Cost (AC) Cost Performance Index (CPI) = EV/AC CPI<1 means project is over budget 25 25
27 MAKING PROJECTIONS WITH EVM Cost Schedule Index (CSI) = CPI x SPI the further CSI is from 1.0, the less likely project recovery becomes Once a project is 10% complete, the overrun at completion will not be less than the current overrun Once a project is 20% complete, the CPI does not vary from its current value by more than 10% The CPI and SPI are statistically accurate indicators of final cost results 26 26
28 CONTRACTOR S VARIANCE ANALYSIS Should address significant variances: Separate discussion of cost and schedule variances Clear description of reason for variance Quantity variances (e.g., price vs. usage) Be specific, not general Include corrective action Technical, schedule, and cost impacts Impact to estimate at completion Should be analyzed by the individual controlling the work 27 27
29 USING EVM PERFORMANCE DATA TO VALIDATE ESTIMATES New estimates at completion take on more meaning when you employ performance information To recover from a CPI of.5, the project would have to work at an efficiency > 1 The Estimate At Completion (EAC) can be predicted by the performance index: EAC = BAC = $20,000 = $40,000 CPI.5 The overrun will never be less than it is at the 15% complete point! 28 28
30 THE NEED FOR ACCURATE EACs New EACs take on more meaning when you employ performance information the EAC can be predicted by the performance index analysis of EAC realism what are the drivers? What can we do about them? Variance at Completion vs. Contractor Loss Positive VAC: EAC < BAC underrun contractor gain Negative VAC: EAC > BAC share area contractor partial loss EAC > ceiling overrun contractor loss (100%) Government develops top-level EAC for comparison: Government should limit progress payments if EAC is greater than contract ceiling Government needs accurate forecast of fund requirements 29 29
31 EARNED VALUE PROBLEM INDICATORS GOAL: to verify that effective variance analysis processes are applied to identify, correct, and report problems Potential Problem Indicators: Zero variances Monthly trends turning negative or downward Schedule variances generally indicate cost will follow Actuals > Latest Revised Estimates (LRE) BCWP increases with no increase in ACWP Negative data elements 30 30
32 STATUTES RELATED TO EVM The requirement for EVM as it is practiced today can be traced to three public laws: Government Performance and Results Act of 1993 (GPRA) Establish performance standards for Federal budget Federal Acquisition Streamlining Act, Title V of 1994 (FASA V) Report cost, schedule, and performance goals and evaluate progress Information Technology Management Reform Act of 1996/ Clinger-Cohen Act (ITMRA/Clinger-Cohen) Report performance information systems acquisition 31 31
33 EVM REQUIREMENTS OMB Circular A-11, Part 7 requires the use of EVM in the performance management of major investments and major systems in development, modernization, or enhancement (DME) or in mixed life-cycle "Agencies must use a performance-based acquisition management system to measure the achievement of cost, schedule, and performance goals, and achieve (on average), 90% of those goals Contractors Earned Value Management System (EVMS) must comply with the guidelines set forth in the American National Standards Institute (ANSI)/Electronic Industries Alliance (EIA)-748 Standard FAR (Pre-IRB), (Post-IRB), and (EVMS) Federal agencies requires its use on major programs (i.e. IT and non-it investments $100M or greater) and on their associated contracts with a contract price of $20M or greater; continued surveillance to ensure compliance 32 32
34 EVM REQUIREMENTS (CONT D.) Contract Total Value EVM Compliance CWBS & IMS CPR (monthly) CFSR (quarterly) $50M and greater $20M and greater but less than $50M Required Required Required Required Required Required Required Required Less than $20M Optional (at discretion of PM) Required if PM requires EVM Required if PM requires EVM Required 33 33
35 INTEGRATED BASELINE REVIEW (IBR) Determines that the Performance Measurement Baseline is responsive to the scope of work required Joint assessment of Coverage of SOW Scheduling of work Resource allocation Earned Value methodologies Technical content of PMB Realism and Risks Should be conducted pre-award but no later than 180 days post-award 34 34
36 THE CONTRACTOR S EVMS Describes system in sufficient detail to determine compliance Includes prior Certification/Acceptance If no EVMS is in place, Contractor must submit a comprehensive plan for compliance System description Necessary modifications Compliance map Process descriptions Recent evaluation or self-assessment results Identify major subcontracts for application of criteria Verify baseline integrity is maintained Contains plan and procedures for surveillance and self assessment 35 35
37 THE CONTRACTOR S EVMS (CONT D.) Surveillance Plan Methods and techniques Inclusion of new scope Customer coordination Schedule Analysis Ensure that reliable and timely cost, schedule, and technical performance information is generated Baseline Budget Control Accounts Baseline Schedule Work Measurement by Control Account Work-hours, dollars, units, etc
38 EVM VALIDATION Required for all companies with a EVMS cost-plus contract over $50M Validation is achieved by conducting a formal review of the processes defined and used by the contractor to comply with the EVMS guidelines in ANSI/EIA-748 Determines that the contractor is using the system as one of its primary program management processes has properly implemented the system on the contract is using the data from its system in reports to the government Single validation required for each company resulting in a compliant EVMS Note: an EVMS Compliance Review is the same as a Validation Review 37 37
39 EVM VALIDATION PROCESS A formal recognition of certification by an independent party that company s EVMS meets the guidelines in ANSI/EIA-748 A formal Government review conducted at a contractor s facility to assess the contractor s proposed EVMS compliance with ANSI/EIA-748 A recurring process by an independent party (normally DCMA) assessing the continuing compliance of the company s EVMS with ANSI/EIA-748 and the company s written system documentation n independent party (normally DCMA) assessing the continuing compliance of the company s EVMS with ANSI/EIA-748 and the company s written system documentation 38 38
40 Objectives: EVM VALIDATION REVIEW Evaluate management system capabilities against ANSI/EIA-748 Assess the description of the management system to determine if it adequately describes the management processes demonstrated during the review Evaluate the application of the management system on the contract being reviewed Validation Process: begins as soon as practicable following the implementation of the EVMS and IBR review system documentation reviews, data traces, and interviews with contractor personnel organized to follow the system approach taken by the contractor 39 39
41 FAILING THE VALIDATION Potential of extra withholding on payments that could be as much as 10% additional Disadvantage in bidding future EVM contracts Potential for additional oversight on existing EVM contracts Brings in question a company s ability to control and manage multi-million dollar programs Notable examples: Lockheed Martin & Bell Helicopter 40 40
42 EVMS IS IMPORTANT TO EFFECTIVE CONTRACT ADMINISTRATION EVMS gives early warning of potential problems As a Contract Specialist or Contracting Officer, you are a member of the Integrated Project Team (IPT) It is your job as the CS/CO to protect the Government s rights if performance does not show satisfactory progress! You must work with the other IPT members and the Contractor to avoid or mitigate performance problems 41 41
43 WHAT ARE THE CO S RESPONSIBILITIES REGARDING EVMS? Contracting Officer s Pre-Award Responsibilities as a Member of the IPT: Identify application of the Earned Value Management System in acquisition plans, solicitations and contracts Define reporting and electronic submission requirements Define evaluation criteria for source selections Factor EVMS into contract management planning 42 42
44 WHAT ARE THE CO S RESPONSIBILITIES REGARDING EVMS? (CONT D.) Contracting Officer s Post-Award Responsibilities as a Member of the IPT: Integrate performance monitoring with EVMS into Award/Incentive plans Monitor performance with IPT using the EVMS Act when performance is at risk (communication with contractor, show cause and cure notices, etc.) Evaluate the Contractor s EVMS implementation plan Evaluate the Contractor s EVM systems for compliance with the standard Conduct Integrated Baseline Reviews to ensure all the work scope is included in the baseline 43 43
45 EVM IMPACT ON MISSION By utilizing EVM properly, an agency can improve its ability to track and report on investment cost, schedule, and performance variances (agency projects must stay within a 10% variance) allow PMs and project team members to optimize resources and deliver capital investment projects on-time, on-budget, and within scope operate by tracking its programs health beyond pure financials ensure its customers requirements are satisfied 44 44
46 LIMITATIONS OF EVM Quantifying/measuring work progress can be difficult Time required for data measurement, input, and manipulation can be considerable EVM becomes problematic when Inadequate requirements definition Incomplete WBS Accounting systems that cannot address the WBS Lack of management attention to project progress Failure to respond to warning signs Failure to reconcile baseline to funding shortfalls (re-baseline) 45 45
47 EVM IS SUCCESSFUL When management embraces it When the program uses it to manage When all program levels understand how it works 46 46
48 SUMMARY EVM helps reduce the guesswork in: measuring performance forecasting Aids in getting beyond misleading measures of progress - provides a common denominator for work scope, schedule, and resources Reasons to use EVM: Good project management practices OMB/FAR requirement Should be incorporated into contracts for major acquisitions (cost-reimbursement) 47 47
49 EVM RESOURCES Practice Standard for Earned Value Management DoD Earned Value Management ANSI/EIA-748 Guide EIA748.pdf 48 48
50 Q & A 49 49
Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1
Earned Value Valerie Colber, MBA, PMP, SCPM Not for duplication nor distribution 1 Where did Earned Value Management come from? In 1967 the Department of Defense (DoD) established the Cost/Schedule Control
More informationAn introduction to Earned Value Analysis
An introduction to Earned Value Analysis Prepared by: Suketu Nagrecha, MBA, PMP, CNA March 16, 2002 Earned Value Analysis - 2 Abstract Earned value analysis is a method of performance measurement. Many
More informationAppendix D Glossary Of Terms
Appendix D Glossary Of Terms The notational style used in this glossary is to begin the definition of each defined term with a new paragraph beginning with the term in UPPERCASE. Any word or phrase used
More informationGovernment Contracting and Earned Value Management (EVM)
Government Contracting and Earned Value Management (EVM) Ida Davis, EVP, PMP, MBA Earned Value Manager DynPort Vaccine Company LLC, A CSC Company Note: This presentation is the property of DynPort Vaccine
More informationEarned Value Management and the Government Program Office. Blair Alan Knapp Jr. MSPM PMP
Earned Value Management and the Government Program Office Blair Alan Knapp Jr. MSPM PMP Agenda EVM Information Alignment OMB Exhibit 300 and Funding Government Program Office Challenges Government Program
More informationBasic Concepts of Earned Value Management (EVM)
Basic Concepts of Earned Value Management (EVM) This article provides an introduction to the basic concepts of earned value management (EVM), from initial project planning through execution including data
More informationEarned Value Management Systems Application Guide
National Defense Industrial Association Integrated Program Management Division Earned Value Management Systems Application Guide January 27, 2015 Revision 2 National Defense Industrial Association (NDIA)
More informationIT Baseline Management Policy. Table of Contents
Table of Contents 1. INTRODUCTION... 1 1.1 Purpose... 2 1.2 Scope and Applicability... 2 1.3 Compliance, Enforcement, and Exceptions... 3 1.4 Authority... 3 2. ROLES, RESPONSIBILITIES, AND GOVERNANCE...
More informationEarned Value Management Systems Application Guide
National Defense Industrial Association Integrated Program Management Division Earned Value Management Systems Application Guide May 4, 2011 Revision 1* National Defense Industrial Association (NDIA) 2111
More informationA Gentle Introduction to Earned Value Management Systems
A Gentle Introduction to Earned Value Management Systems Good metrics let us see if we are doing the right things and doing them well." Niwot Ridge Consulting 4347 Pebble Beach Niwot, Colorao www.niwotridge.com
More informationPredicting progress on your project
www.nonsuch.co info@nonsuch.co Predicting progress on your project - using Lego bricks to understand Earned Value September 4 PM Conference 2015 Presented by Youssef Mourra Director, Principal Consultant
More informationTHE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH
THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH By Nghi M. Nguyen, Ph.D., PE, PMP. * INTRODUCTION The management of engineering projects
More informationINSE 6230 Total Quality Project Management
Lecture 5 Project Cost Management Project cost management introduction Estimating costs and budgeting Earned Value Management (EVM) 2 IT projects have a poor track record for meeting budget goals Cost
More informationEarned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition.
Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition. Errata for Chapter 7 (Replacement pages provided) Deleted up to a given point in time from the description
More informationWhat Does the Government Want from Project Management? DC PMI Chapter Executive Breakfast Series January 16, 2008
What Does the Government Want from Project Management? DC PMI Chapter Executive Breakfast Series January 16, 2008 The Government Wants from Project Management A project management process and culture in
More informationDATA ITEM DESCRIPTION Title: Integrated Program Management Report (IPMR) Number: DI-MGMT-81861 Approval Date: 20120620
DATA ITEM DESCRIPTION Title: Integrated Program Management Report (IPMR) Number: DI-MGMT-81861 Approval Date: 20120620 AMSC Number: D7549 Limitation: DTIC Applicable: No GIDEP Applicable: No Preparing
More informationEarned Value Management Tutorial Module 1: Introduction to Earned Value Management. Prepared by:
Earned Value Management Tutorial Module 1: Introduction to Earned Value Management Prepared by: Module1: Introduction to Earned Value Welcome to Module 1. The objective of this module is to introduce you
More information700 Analysis and Reporting
Jefferson Science Associates, LLC 700 Analysis and Reporting Project Control System Manual Revision 7-50 - 700 Analysis and Reporting This chapter of the JSA Project Control System Manual explains how
More informationEarned Value Management Tutorial Module 8: Reporting. Prepared by:
Earned Value Management Tutorial Module 8: Reporting Prepared by: Module 8: Government Required Reports Welcome to Module 8. The objective of this module is to introduce you to Government required reports.
More informationJuly 6, 2015 11(1) CHAPTER 11
July 6, 2015 11(1) CHAPTER 11 Table of Contents Paragraph Page 11-000 Audit of Contractor Compliance with Contract Financial Management Requirements 11-001 Scope of Chapter... 1101 11-100 Section 1 ---
More informationEarned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance.
About the Tutorial Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance. This is a brief tutorial that acquaints
More informationAACE International Recommended Practice No. 86R 14
AACE International Recommended Practice No. 86R 14 VARIANCE ANALYSIS AND REPORTING TCM Framework: 9.1 Project Cost Accounting 9.2 Progress and Performance Measurement 10.1 Project Performance Assessment
More informationSimple Earned Value (Using MS Project 2010)
Simple Earned Value (Using MS Project 2010) This document outlines a Simple Earned Value technique, a technique which sticks to a simple 0/100% Milestone approach with some Level of effort tasks maintained
More informationIST 302 : Project Cost Management
IST 302 : Project Cost Management Project Cost Management : Why do we care? 1 Cost and Cost Management Cost: Cost Management: Project Cost Management Processes Cost Estimating Developing an estimate of
More informationL10: Budgeting and Cost Control. Olivier de Weck
ESD.36 System Project Management + L10: Budgeting and Cost Control Instructor(s) Olivier de Weck Lecture 10 Oct. 11, 2012 System Project Management ESD.36 Framework Project Preparation Enterprise has chosen
More informationDCMA DCMA-EA PAM 200.1. October 2012
DCMA Earned Value Management System (EVMS) Program Analysis Pamphlet (PAP) DCMA-EA PAM 200.1 October 2012 THE DCMA ENGINEERING AND ANALYSIS EXECUTIVE DIRECTOR IS RESPONSIBLE FOR ISSUANCE AND MAINTENANCE
More informationThis EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts.
This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts. To begin, how does the Prime integrate the subcontractor
More informationEarned Value Formulae
Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from http://www.mosaicprojects.com.au/techniques.html#earnedvalue
More informationBrainstorm. What is Cost and Project Cost Management?
Brainstorm Suppose you need to create a network from scratch in your organization's headquarter. Your project is named HQ Network. Your major deliverables includes: LAN, WAN, server room, workstations,
More informationEarned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting. Prepared by:
Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting Prepared by: Module 6: Metrics, Performance Measurements and Forecasting Welcome to Module 6. The objective
More informationPROJECT MANAGEMENT AND THE ACQUISITION OF MAJOR SYSTEMS
PROJECT MANAGEMENT AND THE ACQUISITION OF MAJOR SYSTEMS Guiding Principle: Sound planning and management of DOE s contracts for the acquisition of projects are essential to the success of the Department
More informationFERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT. Head, Office of Project Management Oversight
SUBJECT: FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT NUMBER: 12.PM-006 RESPONSIBILITY: Office of Project Management Oversight REVISION: 54 APPROVED BY: TITLE DRAFT FOR DISCUSSION Head, Office
More informationRules on using templates. MECH 896 Professional Development for MEng Students. Assignment #6A: Questions. Homework Discussion
MECH 896 Professional Development for MEng Students Mohamed Hefny and Brian Surgenor (hefny@cs.queensu.ca and surgenor@me.queensu.ca) Rules on using templates 1) Must reference the template used 2) Use
More informationIntroduction to earn value management in Civil Engineering
3 rd World Conference on Applied Sciences, Engineering & Technology 27-29 September 2014, Kathmandu, Nepal Introduction to earn value management in Civil Engineering S. K. KAMANE, S. A. MAHADIK, A. C.
More informationEarned Value Management Best Practices
Division of Information Technology Investment Management Enterprise Architecture & Strategy Group Office of Information Services Earned Value Management Best Practices Version 2.2 Last Modified: 19 November
More informationHow To Write Ansi/Eia Evm System Acceptanceance Guide
National Defense Industrial Association (NDIA) Program Management Systems Committee (PMSC) ANSI/EIA 748 Earned Value Management System Acceptance Guide Working Release For User Comment January 23, 2006
More informationHow To Manage A Project
Project Management Institute Practice Standard for EARNED VALUE MANAGEMENT Global Project Management Institute Practice Standard for Earned Value Management Practice Standard for Earned Value Management
More informationProject Management System Description (PMSD)
Project Management System Description (PMSD) Revision 3 Project Management System Description (PMSD) Revision 3 February 2016 Prepared by: Date: Steve Langish Planning & Control Division Approved by: Date:
More informationUsing Earned Value Management for Improving Processes. By Cynthia K. West
Using Earned Value Management for Improving Processes By Cynthia K. West Summary: This article explains earned value management and explores how the metric can be used to improve project and business processes.
More informationChapter 7. (PMBOK Guide)
Chapter 7 Project Cost Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: marajabi@ut.ac.irac ir Homepage:
More informationEarned Value Management System Description
LCLS Project Management Document # 1.1-015 Project Management Revision 3.0 Earned Value Management System Description Patricia Mast (LCLS Project Controls Manager) Signature Date Mark Reichanadter (LCLS
More informationEarned Value and Agile Reporting
Earned Value and Agile Reporting Anthony Cabri, Mike Griffiths Quadrus Development Inc. Abstract This paper reviews the concepts of Earned Value Management established in traditional project management,
More informationEarned Value Management Guidelines
Effective Date: April 21, 2009 Status: Revision 1 Supersedes: NA Document Owner: Director, Environmental and Engineering Program Introduction This paper provides guidance and recommendations for the application
More informationChapter 7: Project Cost Management. Munawar moenawar@gmail.com
Chapter 7: Project Cost Management Munawar moenawar@gmail.com Learning Objectives Understand the importance of project cost management. Explain basic project cost management principles, concepts, and terms.
More informationEstimating Cost at Completion - Judgment & EV Information
Page 1 of 10 Estimating Cost at Completion - Judgment & EV Information Cost estimating is often called a "black art" and, too often, estimates are structured to fit some predetermined idea of a number
More informationTracking Budgets and Schedules
Tracking Budgets and Schedules David V. Tennant, PE, PMP One of the simplest questions you are likely to encounter as an engineering or project manager is: Are we on budget and schedule? While this is
More informationEARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS
14 EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS Dr. P.B.G. Dissanayake 1 1 Department of Civil Engineering, Faculty of Engineering, University of Peradeniya
More informationEARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT
EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT Assoc. Prof. Anca Mehedintu Ph. D University of Craiova Faculty of Economics and Business Administration Craiova, Romania Prof. Cerasela Pirvu
More informationYoung Hoon Kwak Associate Professor School of Business The George Washington University
Project Management in Government: An Introduction to Earned Value Management (EVM) Improving Performance Series Young Hoon Kwak Associate Professor School of Business The George Washington University Frank
More informationInternal Surveillance
Page 1 of 18 Internal Surveillance A contract having Earned Value Management System (EVMS) requires the contractor to maintain an effective management control system consistent with EVM industry standards
More informationSUCCESSFULLY INTEGRATING AGILE WITH EARNED VALUE MANAGEMENT
1 PMSC Quarterly Meeting, February 1 2, 2011, Fort Worth, Texas SUCCESSFULLY INTEGRATING AGILE WITH EARNED VALUE MANAGEMENT Increasing the Probability Program of Success (PoPS)by Connect the dots between
More informationUsing Earned Value Management Concepts to Improve Commercial Project Performance
Using Earned Value Management Concepts to Improve Commercial Project Performance R. Scott Brunton, PMP, PMI-RMP/SP, EVP Principal Solutions Consultant Lewis Fowler, LLC www.lewisfowler.com Welcome to the
More informationEssential Views of the Integrated Program Management Reports. Thomas J. Coonce Glen B. Alleman
Essential Views of the Integrated Program Management Reports Thomas J. Coonce Glen B. Alleman Agenda Background Twenty-five metrics are proposed Twelve are demonstrated with tasserted value to the government
More informationProject Cost Management
Project Cost Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points To Note Please
More informationEarned Value Management System (EVMS) and. Project Analysis Standard Operating Procedure (EPASOP)
Earned Value Management System (EVMS) and Project Analysis Standard Operating Procedure (EPASOP) Issued by Office of Acquisition and Project Management MA-63 March 12, 2014 DEPARTMENT OF ENERGY Office
More informationSelftestengine..PMI-SP.270 questions PMI-SP. PMI Scheduling Professional
Selftestengine..PMI-SP.270 questions Number: PMI-SP Passing Score: 800 Time Limit: 120 min File Version: 5.1 PMI-SP PMI Scheduling Professional This study guides are so comprehensible that anyone can understand
More informationSoaDssPm: A new Service-Oriented Architecture of the decision support system for the Project Management.
SoaDssPm: A new Service-Oriented Architecture of the decision support system for the Project Management. Fatima Boumahdi, Rachid Chalal Abstract This paper presents an architecture for the Project Management,
More informationtechnical tips and tricks
technical tips and tricks Earned Value Analysis Overview Document author: Produced by: Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the smart
More informationCONVERTING TO PHYSICAL % COMPLETE METHOD OF EARNED VALUE IN MICROSOFT PROJECT
CONVERTING TO PHYSICAL % COMPLETE METHOD OF EARNED VALUE IN MICROSOFT PROJECT PREPARED BY James E Aksel, PMP jim@projectpmo.com http://www.msprojectdblog.com http://www.projectpmo.com Page 1 of 19 Table
More informationProject Management Using Earned Value
Project Management Using Earned Value Third Edition Gary C. Humphreys Earned Value Management Consulting Training 2002, 2011, 2014 Gary C. Humphreys Humphreys & Associates, Inc. All rights reserved. No
More informationEarned Value Management and Professional Services Automation
Earned Value Management and Professional Services Automation Prepared by: Frances B. Craig Unanet Technologies www.unanet.com 1 of 5 Earned Value Management and Professional Services Automation Earned
More informationGPMCEP GLOBAL PROJECT MANAGEMENT, LLC C O U R S E
C O U R S E C E GPMCEP GLOBAL PROJECT MANAGEMENT, LLC Project Management Professional (PMP) Certification Exam Prep Global Project Management, LLC is a Global Registered Education Provider (R.E.P.) of
More informationEarned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP
Earned Value Exercise 1 Running head: Earned Value Exercise Earned Value Exercise SuCheng Wu MET AD 644: Project Risk, and Cost Management Paul B. Cook, PhD PMP Earned Value Exercise 2 Case 1: Background:
More informationAgile Project Management Controls
0 Agile Project Management Controls Issues with EVM and a Viable Alternative: Agile Project Management (PM) Tool ICEAA Conference, June 2015 San Diego, CA Blaze Smallwood, Booz Allen Hamilton Omar Mahmoud,
More informationProject Management: Tracking Progress and Earned Value with MS Project 2003
Project Management: Tracking Progress and Earned Value with MS Project 2003 Project Planning Suppose you have been assigned a project to construct a website in a certain time frame and given a certain
More informationInformation Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu
Management, Sixth Edition Note: See the text itself for full citations. More courses at cie-wc.edu Understand the importance of project cost management Explain basic project cost management principles,
More informationOver Target Baseline and Over Target Schedule Guide
Over Target Baseline and Over Target Schedule Guide OUSD AT&L (PARCA) December 5, 2012 1 Table of Contents Section Page No. Introduction 4 Chapter 1. What is Formal Reprogramming? 5 1.1 Formal Reprogramming
More informationBrief Introduction to Earned Value Management (EVM)
Brief Introduction to Earned Value Management (EVM) 12/25/06 EVM Introduction 1 12/25/06 EVM Introduction 1 Outline Introduction to the basic rationale and elements of EVM Issues of actually implementing
More informationUnit 5: Cost Management (PMBOK Guide, Chapter 7)
(PMBOK Guide, Chapter 7) The questions on this topic have historically been more difficult than average for some exam takers because of unfamiliarity with some of the math. You will be responsible for
More informationIQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques
IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques Kym Henderson Former Education Director, PMI Sydney Chapter March 2003 to March 2007 Kym.Henderson@froggy.com.au
More informationFRA s Earned Value Management System Overview for Self Assessment Surveillance March 07-09, 2011
FRA s Earned Value Management System Overview for Self Assessment Surveillance March 07-09, 2011 Dean Hoffer Head, Office of Project Management Oversight Outline EVMS History at the Lab FRA EVMS Documents
More informationDefense Logistics Agency INSTRUCTION
Defense Logistics Agency INSTRUCTION DLAI 2105 Effective May 13, 2013 SUBJECT: Earned Value Management (EVM) Systems Performance, Oversight, and Governance Referenses: (a) DLA Instruction 2105, Earned
More informationThe Two Most Useful Earned Value Metrics: the CPI and the TCPI
PM WORLD TODAY SECOND EDITIONS JUNE 2009 Editor s note: Second Editions are papers that have been previously published that have continued relevance and deserve additional visibility. The paper below was
More informationAnalysis and Application of Earned Value Management in Software Development
Analysis and Application of Earned Value Management in Software Development Frank Tsui School of Computing and Software Engineering Southern Polytechnic State University, Marietta, Georgia, USA 30060 Abstract
More informationProject Management. ZEUS Student Seminar on 14 th November 2003 by Riko Wichmann. Riko Wichmann, MPY Zeus Student Seminar - PM, 14.11.
Project Management ZEUS Student Seminar on 14 th November 2003 by Riko Wichmann Riko Wichmann, MPY Zeus Student Seminar - PM, 14.11.2003 1 Project Management - Training Program - Project Scope Management
More informationPortfolio Management through Capital Planning and Investment Control: Program Planning Best Practice Agency Level (for the US Department of State)
Portfolio Management through Capital Planning and Investment Control: Program Planning Best Practice Agency Level (for the US Department of State) Robert A. Horrigan, PMP Knowledge Exchange Forum Moderator
More informationOrange County Convention Center Orlando, Florida June 3-5, 2014. Using SAP PS Earned Value to Manage IT Projects Michael Kim (michael.kim@prpx.
Orange County Convention Center Orlando, Florida June 3-5, 2014 Using SAP PS Earned Value to Manage IT Projects Michael Kim (michael.kim@prpx.com) AGENDA What is a typical problem with IT projects? What
More informationEARNED VALUE MANAGEMENT SYSTEMS (EVMS)
NOT MEASUREMENT SENSITIVE DOE G 413.3-10 XX-XX-08 EARNED VALUE MANAGEMENT SYSTEMS (EVMS) [This Guide describes suggested nonmandatory approaches for meeting requirements. Guides are not requirements documents
More informationNASA/SP-2012-599 Earned Value Management (EVM) Implementation Handbook
NASA/SP-2012-599 Earned Value Management (EVM) Implementation Handbook National Aeronautics and Space Administration NASA Headquarters Washington, D.C. 20546 February 2013 NASA STI Program... in Profile
More informationPERFORMANCE AND QUALITY IN PROJECTS Project Management and Leadership 2016D, PhD, PMP
PERFORMANCE AND QUALITY IN PROJECTS Project Management and Leadership 2016D, PhD, PMP PROJECTS PROGRESS WELL UNTIL 70% Quick progress until 60-70% complete. Then we discover the project is in distress.
More informationPune, MH, India. 2 P.G. Student, Imperial College of Engineering & Research, Wagholi, Pune, MH, India. wit.vaishnavi@gmail.com
COST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHOD Dr. Arun Dhawale 1 Vaishnavi Tuljapurkar 2 1 Head of Department, Associate Professor, Department of Civil Engineering, Imperial College of
More information300 Scheduling and Budgeting
Jefferson Science Associates, LLC 300 Scheduling and Budgeting Project Control System Manual Revision 7-16 - 300 Scheduling and Budgeting This chapter of the JSA Project Control System Manual describes
More informationTowards a Complete Earned Value Analysis. Sam Sharp and Peter Hall. Paper # 166
Towards a Complete Earned Value Analysis Sam Sharp and Peter Hall Paper # 166 Planned vs Actual A purely accounting approach to project tracking involves the monitoring of status by simply comparing actual
More informationDCMA EVMS COMPLIANCE REPORT I LOCKHEED MARTIN AERONAUTICS CO.
POST ACCEPTANCE REVIEW FOR CAUSE COMPLIANCE REPORT FOR THE LOCKHEED MARTIN AERONAUTICS COMPANY FORT WORTH, TEXAS PREPARED BY: DEFENSE CONTRACT MANAGEMENT AGENCY (DCMA) EARNED VALUE MANAGEMENT (EVM) CENTER
More informationTraining Seminars. Description. Core Courses: The core courses consist of the following:
Training Seminars Description The POI consists of training courses known as core. The purpose of the core courses is to provide a principles or foundation knowledge baseline to the student in the fundamentals
More informationServices Contracts and Earned Value Management (EVM)
Services Contracts and Earned Value Management (EVM) National Defense Industrial Association 2111 Wils on Blvd, Suite 400 Arlington, VA 22201 www.ndia.org February 17, 2010 www.ndia.org 2010 National Defense
More informationPEP TALK. Policy EVMS - PARS. Department of Energy Acquisition and Project Management Workshop Federal Stewardship Providing the Value Proposition
2015 Department of Energy Acquisition and Project Management Workshop Federal Stewardship Providing the Value Proposition PEP TALK Policy EVMS - PARS Melvin Frank Chief, Project Systems Division/MA-632
More informationBasics of Cost and Schedule Control
Basics of Cost and Schedule Control Topics Monitoring and Scheduling: Two Parts of a Feedback System. Definitions Schedule Updates from Monitoring Components of Effective Monitoring Cost Control As A Management
More informationRisk Mitigation and Subcontract Management
Risk Mitigation and Subcontract Management Breakout Session # C13 Danielle Carr, MSM Program Acquisitions, HMS Technologies Stacey B. Dey-Foy Director Suspension & Debarment, EPA July 28, 2014 @ 4:00pm
More informationProject Control with ProTrack
Project Control with ProTrack 1.0 (last update: 11/11/08) 1 Project Control with ProTrack by Mario Vanhoucke Professor at Ghent University and Vlerick Leuven Gent Management School (Belgium) Partner OR-AS
More informationQUALITY AND PERFORMANCE IN PROJECTS. Project Management and Leadership 2015D, PhD, PMP
QUALITY AND PERFORMANCE IN PROJECTS Project Management and Leadership 2015D, PhD, PMP Our PROGRAMME: 1. INTRODUCTION TO PROJECT MANAGEMENT 2. STARTING A PROJECT 3. WORK MOTIVATION 4. COMMUNICATION 5: TEAMS
More informationMTAT.03.244 Software Economics. Lecture 6: Software Cost Estimation (part II)
MTAT.03.244 Software Economics Lecture 6: Software Cost Estimation (part II) Marlon Dumas marlon.dumas ät ut. ee Outline Review of Effort Estimation Homework Discussion on book chapter by Caper Jones Earned
More informationExhibit 300: Capital Asset Plan and Business Case Summary PART I: SUMMARY INFORMATION AND JUSTIFICATION (All Capital Assets)
Exhibit 300: Capital Asset Plan and Business Case Summary PART I: SUMMARY INFORMATION AND JUSTIFICATION (All Capital Assets) Section A: Overview (All Capital Assets) 1. Date of Submission: 09/08/2006 2.
More informationWhat is the Health of my Project?
WHITE PAPER What is the Health of my Project? The Use and Benefits of Earned Value Table of Contents How s My Project Doing?...1 Need a Solution? Earned Value to the Rescue!...1 My actual costs are less
More informationLEADING EDGE FORUM CSC PAPERS 2012 EARNED SCHEDULE: FROM EMERGING PRACTICE TO PRACTICAL APPLICATION
LEADING EDGE FORUM CSC PAPERS 2012 EARNED SCHEDULE: FROM EMERGING PRACTICE TO PRACTICAL APPLICATION Author Bill Mowery MPM, PMP Keywords Earned Value Management, Earned Schedule, Project Management, Cost
More informationtechnical tips and tricks
technical tips and tricks Applying Earned Value Analysis Document author: Produced by: Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the smart
More informationChapter 7: Project Cost Management. Information Technology Project Management, Fourth Edition
Chapter 7: Project Cost Management Information Technology Project Management, Fourth Edition Learning Objectives Understand the importance of project cost management. Explain basic project cost management
More informationProject Reviews Lessons Learned Presented by: Kellie Cloud, PMP, PMI SP, PMI RMP, EVP
Project Reviews Lessons Learned Presented by: Kellie Cloud, PMP, PMI SP, PMI RMP, EVP Project Management Institute WDC Chapter Chantilly Luncheon 10 March 2011 Topics of Discussioni Best Practices and
More informationPMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION
PMP SAMPLE QUESTIONS http://www.tutorialspoint.com/pmp-exams/pmp_sample_questions.htm Copyright tutorialspoint.com BASED ON PMBOK 5TH EDITION Here are 200 more objective type sample questions and their
More informationProject Cost Management
Project Cost Management Guide to Mathematical Questions PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Present
More information