HNC/D Project Management

Size: px
Start display at page:

Download "HNC/D Project Management"

Transcription

1 Session 8 - Monitoring cost and slippage in progress Monitoring the project cost The normal accounting systems used in a business are rarely adequate for monitoring project costs. (An exception to this are those businesses whose main function is to undertake projects, such as engineering contractors.) In most businesses the material and labour expenses are not usually recorded in precisely attributable way that is required for project control, and often the reports from the accounting system are available too late for the manager to exercise a control. Furthermore, it is rare for a non-project business to record alongside the expenditure the value of the work achieved by that expenditure. Measurement of expenditure alone is almost useless: it is essential to know what has been achieved as a result of this expenditure. The consequence of these deficiencies is that many project managers have to their own system for monitoring and controlling project costs and achievement The system that is described here is called an earned value system, so called because it seeks to show the manager not only the cost of the work performed so far but the value earned by that work. Such systems are now quite common among performing organisations. Some clients may insist on the use of such a system. The earned value of the work performed on a project is the value that the estimator attached to that work when the project budget was defined. Another term for which is rather more explicit is budgeted cost of work performed, or BCWP. the term we shall employ in this course but it is interchangeable with earned value. The budgeted cost of work performed at any stage during the project can be calculated by adding up the component values of the elements of work that contribute to the project, taking account of the fractional completion of each element. Suppose the budgeted values in a project are as shown in Table 1.

2 Table 1 Calculating BCWP for a new plant project If milestones have been passed corresponding to 50% completion of the site preparation and equipment procurement then the BCWP is calculated in Table 1 as Although no breakdown has been shown for these packages assume that milestones have been defined to allow satisfactory estimates of` percentage completion to be made. A more complete version of Table 1 show each work package subdivided into work elements, most of which either 0% or 100% complete, leaving the partial progress on only a minority elements to be assessed. * Estimating the cost at completion As the project progresses the actual cost of work performed (ACWP) can be monitored by collecting data on the costs of the labour and materials used by the project. The ACWP can then be compared to the BCWP as shown in Figure 1. The cost variance (CV) is the difference between ACWP and BCWP: CV = ACWP BCWP CV represents the expenditure over budget for the work performed so far. At the end of the project BCWP will reach the agreed budgeted cost at completion, the project budget, PB. The cost variance at that time will be the cost over-run of the project. (Here we make no distinction between inflation and other causes of escalation. Inflation could be factored out.) The estimated cost at completion will depend on what assumption the project manager chooses to make about the cost of work still to be performed. One assumption that could be made is that the work still to be performed will be done at the budgeted cost, the original estimate. In this case the estimated cost at completion (ECAC) will be given by:

3 ECAC = PB + CV Assumption 1 A more realistic assumption may be that the remaining work will suffer the same cost inflation factor that has been observed in the work performed so far. In that case the estimated cost at completion will be given by: ECAC = (ACWP/BCWP) PB Assumption 2 The ratio BCWP/ACWP is sometimes called the performance index, PI. Early in the project, when the fraction of work completed is small, the performance index may be an unreliable guide to the costs of the rest of the project because it is based on too little data, so it is probably better to use Assumption 1 until at least 30% of the work has been done. Later on, it is probably more appropriate to use Assumption 2. As the project approaches 100% completion the two estimates approach each other so it then does not matter which assumption is used. Another term frequently required in a monthly cost report is the cost to complete (CTC). The cost to complete (as opposed to the cost at completion) is the estimated cost of the work still to be done. Since the cost so far is ACWP, the relationship between the cost to complete and the estimated cost at completion is: CTC = ECAC ACWP

4 The value of CTC is the relevant figure if you had to decide whether to continue with a project or to cut your losses and cancel it. Other costs are water under the bridge, called sunk costs, but CTC is the money still to be spent. A number of cost control terms have now been introduced and it may be useful to see a summary of them, together with some others that have not yet been mentioned, as shown in Table 2 TABLE 3.3 Cost control terms Table 2 Summary of cost control terms ** Monitoring the achievement against the schedule Although this section is primarily about monitoring cost it is convenient to anticipate the next section, on monitoring the achievement against schedule, by introducing here the budgeted cost of work scheduled, BCWS. You have already met BCWP, the budgeted cost of work performed, which represents the achievement. BCWS represents the planned achievement. Although both BCWP

5 and BCWS are measured in terms of cash they are really measurements of quantities of work (or achievement) expressed for the sake of compatibility in cash terms. BCWS represents the scheduled work while BCWP represents the performed work. The graph of BCWS against time can be plotted at the outset of the project once the cost of each activity has been estimated and a schedule of the activities has been prepared. To calculate BCWS we need to know the budgeted cost of each activity and the time at which that activity is scheduled to be performed. This can be found from the bar chart once each activity has been given a scheduled start time. It is necessary to assume the expenditure profile of each activity, the simplest assumption being that the rate of expenditure is constant during the activity. This will usually be accurate enough. For example, in the new plant project we might assume that the installation activity starts at week 20 and finishes at week 25 and that the cost will be spent at f per week as shown in Figure 2. By adding together the rates of expenditure of all the activities each week, the total rate of expenditure on the whole project can be predicted for each week. These can be accumulated to give a scheduled cumulative cost, the budgeted cost of work scheduled (BCWS) as shown in Figure 3. A further elaboration is possible. The bar chart used as the basis for the BCWS calculation will usually include activities that have float. To obtain a BCWS curve it is necessary to fix the start time of each of these activities, usually the earliest start time. However, for planning purposes it is possible to calculate two extreme BCWS curves, one assuming earliest starts and one assuming latest starts, as shown in Figure 4. These two extremes show the limits between which any actual BCWS curve must lie. ***

6 Schedule variance The schedule variance (SV) may be rather difficult to understand when you first meet it. It is the apparent underspending on the project so far because the work has not progressed as far as scheduled, an apparent saving due to delay: SV = BCWS BCWP The schedule variance is not a true cost saving; it is simply the effect on the current cash balance if expenditure on the project is delayed. In an extreme case, for example, you might have planned to spend f 1 million by June but in fact you have not yet started, and have spent nothing, so the schedule variance is 1 million. A more realistic situation is shown in Figure 5 where all three curves, BCWS, BCWP and ACWP, are plotted. FIGURE 5 Performance on atypical project The state of the project shown in Figure 5 is typical of many projects. The BCWS is shown as an S-shaped curve, representing the planned accumulated expenditure. It reaches the project budget at the scheduled completion date. The next lower curve is the actual cost of work performed. In the example illustrated it is lower than the budgeted cost of work scheduled, not because of actual under-expenditure, but simply due to delay in the project. This can be seen from the third curve, BCWP, which is even lower than ACWP. The cost variance (CV) is positive, showing that the work performed has actually cost more than planned. The work is well behind schedule, causing a large schedule variance (SV). ****

7 We will be returning to the subject of the schedule variance and the interpretation of the BCWS and BCWP curves in the next section, which is concerned with maintaining the schedule. Controlling the project cost Controlling cost is much more difficult than monitoring cost and it is almost impossible to prescribe how it should be done. There are numerous books on cost control which, in spite of optimistic-sounding titles, are really mostly about techniques for cost monitoring. Cost monitoring is of course an essential prerequisite for cost control because without it the project manager is left in the position of one who can only exhort the team to do their best, but does not know whether to praise them or blame them for their past performance. It comes back to the project control loop. The status measurement is essential for control. One axiom should be stated at the outset: you cannot control the cost of an item when the money has already been spent or irrevocably committed. A consequence of this axiom is that cost control is all about controlling future commitments, not about controlling the past expenditure. So the main element of cost control is the authorization to spend money, which will be discussed below. This being so, what then is the point of cost monitoring-gathering and reporting the costs of historical spending? It may be argued that such monitoring is done purely to satisfy the accountants about where the money has gone. Perhaps cost monitoring is useless as a tool for controlling cost? How does it help? The answer to this is three-fold. First, there is the effect upon the attitude of the project staff towards spending. The fact that the project manager is cost conscious must be strongly communicated to the project team so that their attitude towards expenditure reflects this. This attitude can be either fostered or neglected according to the mechanisms which are instituted by the project manager for authorizing expenditure and for calling staff to account for their spending. Second, the cost monitoring system gives feedback so that the project manager knows whether the authorization controls are working. Third, if costs do over-run, it gives the project manager advance warning to seek more funds before the cash runs out.

8 Authorisation During the execution of the project the control of cost is mainly exercised by authorising only those commitments which are detailed in the project budget breakdown with some margin, perhaps 10%, to allow for inaccuracies in the estimate. In some companies each order for external expenditure will carry a cost code so detailed that it can be checked against the estimate for that individual item before the official order is placed. More commonly the cost code embraces a number of component orders because the cost account is set at a higher level in the work breakdown structure (WBS) than the component level. Even so the engineer responsible for initiating the order will be expected to ensure that the cost of all the components within the cost account does not exceed the estimate by more than the tolerable error. Similar control is required for the expenditure on labour. For close control a system is required in which every unit of time is booked against a cost code, representing an activity within the WBS. Authority to book against a given code has to be given in advance. The only difference from the system of monitoring commitments for equipment is that the units of measurement are usually days or hours rather than pounds. The translation of time to cost charged against the project is usually based on some formula according to the grade of the employee, and includes a factor to cover all the overheads, such as the provision of office accommodation, heating, lighting and phones. Timing The project manager's power to influence the final cost diminishes as the project progresses. The most effective time in the project at which to exercise control is at the conceptual stage when the scope of the project is being defined. At each successive stage as the project progresses, the scope for exercising control diminishes, until at the finishing stages the project manager is almost powerless to affect the outcome. At the conceptual stage there has as yet been little expenditure on the project and it is still possible, by cancelling the project, to save nearly 100% of the project budget. Although this may seem to express a rather pessimistic attitude there is no doubt that it would have saved a great deal of money for many project sponsors if some projects had been aborted at an early stage. Of course this is easier to see with hindsight, but it shows the importance of getting the concept right. If a project is to he aborted it is cheapest to do it early.

9 The next most effective stage at which to save money is at scope definition. Perhaps some parts of the project are less valuable than others. The cost of each function needs to be carefully estimated to ensure that each piece of the project is worthwhile. The specification may need pruning to get the best value for money. (Very occasionally the reverse is true: the scope needs to be expanded to achieve better returns.) Once the scope has been defined the most important of all documents for cost control can be produced: the project budget breakdown. This budget will give a detailed breakdown of the cost of the project showing the budgeted cost of every item to be ordered and every task to be performed down to the lowest level of detail that it is economically possible to achieve, given the knowledge available at that stage. Calculating slippage from earned value S-curves You have seen in the previous section how an earned value system can be used to calculate the slippage of costs. The same system, using the same data and the same curves, can be used to estimate the overall slippage of the schedule. The scheduled rate of completion of the project is represented by the BCWS curve, the budgeted cost of work scheduled. Remember that the term 'budgeted cost' is really a measurement of work, but is presented in cost terms in order to have a standard unit of measurement. So BCWS represents the accumulated value of the work which should be achieved at any date if all is performed to schedule. However, we also have available, through the earned value system, a measurement of the budgeted cost of work performed (BCWP) which measures the work actually done, in the same cost units. So the time lag of one curve behind the other at any date in the project is a measure of the slippage. Figure 6 shows a typical situation. At the end of June the value of BCWP has reached the value scheduled at the end of May. The current slippage is therefore one month. It is important to appreciate that, as BCWS and BCWP are both budgeted costs, not actual costs, there is no need to take any account of cost escalation in making this calculation. This has been taken care of by using budgeted cost in both curves. To extrapolate to the end of the project assumptions about the rate of progress on the remaining work must be made similar to those made earlier for cost predictions.

10 Figure 6 Earned value S curve for a typical project ***** The effect on the projected completion date of making different assumptions is shown in Figure 7. If it is assumed that all remaining work is performed at the scheduled rate, then the projected completion date will be one month behind the original scheduled completion date. If, however, it is assumed that the time scale for the outstanding work has to be inflated by the same factor as for work performed so far then the projected slippage is much greater. The work scheduled to be done in 5 months has taken 6 months, so the time scale inflation factor is 1.2. The scheduled 1-year project will take 1.2 x 12 months, i.e months. The projected slippage is 2.4 months. As the effect of different assumptions is so large how can you, as project manager, choose between them? You must decide whether the factors that have affected progress so far are likely to persist or whether they are factors that belong only to the past. You must exercise your judgement according to the apparent cause of the previous slippage.

11 Figure 7 Alternative assumptions for predicted achievement Significance of S-curve slippage The slippage estimated by the time difference between BCWS and BCWP is a measure of the delay in the overall rate of work on the project. If the slip between the two curves is one month it cannot necessarily be inferred that each activity is now one month behind schedule. The aggregation of all the components that make up the earned value means that we may have reached this earned value by being ahead on some parts of the work and behind on others so that the total achievement is as reported. The value represented by BCWP is an overall measure of work done and does not distinguish between work that it is critical to perform to reach the final target and work that is less critical. To understand this distinction it is necessary to look at the project network. You will be taught networking theory in the business module in semester 2.

technical tips and tricks

technical tips and tricks technical tips and tricks Earned Value Analysis Overview Document author: Produced by: Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the smart

More information

Project Control. 1. Schedule Updating

Project Control. 1. Schedule Updating Project Control During the execution of a project, procedures for project control and record keeping become indispensable tools to managers and other participants in the construction process. These tools

More information

Estimating Cost at Completion - Judgment & EV Information

Estimating Cost at Completion - Judgment & EV Information Page 1 of 10 Estimating Cost at Completion - Judgment & EV Information Cost estimating is often called a "black art" and, too often, estimates are structured to fit some predetermined idea of a number

More information

Basic Concepts of Earned Value Management (EVM)

Basic Concepts of Earned Value Management (EVM) Basic Concepts of Earned Value Management (EVM) This article provides an introduction to the basic concepts of earned value management (EVM), from initial project planning through execution including data

More information

technical tips and tricks

technical tips and tricks technical tips and tricks Applying Earned Value Analysis Document author: Produced by: Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the smart

More information

Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance.

Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance. About the Tutorial Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance. This is a brief tutorial that acquaints

More information

Chapter 7: Project Cost Management. Munawar moenawar@gmail.com

Chapter 7: Project Cost Management. Munawar moenawar@gmail.com Chapter 7: Project Cost Management Munawar moenawar@gmail.com Learning Objectives Understand the importance of project cost management. Explain basic project cost management principles, concepts, and terms.

More information

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1 Earned Value Valerie Colber, MBA, PMP, SCPM Not for duplication nor distribution 1 Where did Earned Value Management come from? In 1967 the Department of Defense (DoD) established the Cost/Schedule Control

More information

EVA (C/SCSC) and Basics of Project Control. Nathaniel Osgood 4/7/2004

EVA (C/SCSC) and Basics of Project Control. Nathaniel Osgood 4/7/2004 EVA (C/SCSC) and Basics of Project Control Nathaniel Osgood 4/7/2004 Topics Monitoring cont d EVA (C/SCSC) Definitions and examples Forecasting Project Control General Performance-adjustments adjustments

More information

A Gentle Introduction to Earned Value Management Systems

A Gentle Introduction to Earned Value Management Systems A Gentle Introduction to Earned Value Management Systems Good metrics let us see if we are doing the right things and doing them well." Niwot Ridge Consulting 4347 Pebble Beach Niwot, Colorao www.niwotridge.com

More information

PERCEPTION. Tracking Progress & EAC

PERCEPTION. Tracking Progress & EAC PERCEPTION Tracking Progress & EAC 1 Maximize Efficiency Shipyards that know their true costs are more likely to be profitable and are in a better position to challenge their competition. They can focus

More information

COINS EVA Earned Value Analysis

COINS EVA Earned Value Analysis COINS EVA Earned Value Analysis Nigel Cope July 2006 Earned Value Analysis The most widely used method for performance measurement of projects Combines scope, cost and schedule patterns Informs project

More information

Earned Value Formulae

Earned Value Formulae Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from http://www.mosaicprojects.com.au/techniques.html#earnedvalue

More information

Basics of Cost and Schedule Control

Basics of Cost and Schedule Control Basics of Cost and Schedule Control Topics Monitoring and Scheduling: Two Parts of a Feedback System. Definitions Schedule Updates from Monitoring Components of Effective Monitoring Cost Control As A Management

More information

// Benchmarking Project Schedules

// Benchmarking Project Schedules // Benchmarking Project Schedules Dr. Dan Patterson, PMP CEO & President, Acumen March 2011 www.projectacumen.com Table of Contents Introduction... 4 Benchmarking Overview... 4 Uses of Schedule Benchmarking...

More information

Analysis and Application of Earned Value Management in Software Development

Analysis and Application of Earned Value Management in Software Development Analysis and Application of Earned Value Management in Software Development Frank Tsui School of Computing and Software Engineering Southern Polytechnic State University, Marietta, Georgia, USA 30060 Abstract

More information

Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition.

Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition. Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition. Errata for Chapter 7 (Replacement pages provided) Deleted up to a given point in time from the description

More information

Brainstorm. What is Cost and Project Cost Management?

Brainstorm. What is Cost and Project Cost Management? Brainstorm Suppose you need to create a network from scratch in your organization's headquarter. Your project is named HQ Network. Your major deliverables includes: LAN, WAN, server room, workstations,

More information

CHAPTER 6 PROJECT CASH FLOW

CHAPTER 6 PROJECT CASH FLOW CHAPTER 6 PROJECT CASH FLOW In the previous chapters, techniques for project planning, scheduling, resources management, and timecost trade off have been introduced. This chapter will deal with project

More information

How To Manage A Project

How To Manage A Project Project Management Institute Practice Standard for EARNED VALUE MANAGEMENT Global Project Management Institute Practice Standard for Earned Value Management Practice Standard for Earned Value Management

More information

2010 MTEF: Budgeting for infrastructure and capital expenditure guidelines

2010 MTEF: Budgeting for infrastructure and capital expenditure guidelines 2010 MTEF: Budgeting for infrastructure and capital expenditure guidelines Introduction The guidelines below provide departments and entities with information to make budget submissions for capital projects

More information

700 Analysis and Reporting

700 Analysis and Reporting Jefferson Science Associates, LLC 700 Analysis and Reporting Project Control System Manual Revision 7-50 - 700 Analysis and Reporting This chapter of the JSA Project Control System Manual explains how

More information

Retained Fire Fighters Union. Introduction to PRINCE2 Project Management

Retained Fire Fighters Union. Introduction to PRINCE2 Project Management Retained Fire Fighters Union Introduction to PRINCE2 Project Management PRINCE2 PRINCE stands for: PRojects IN Controlled Environments and is a structured method which can be applied to any size or type

More information

An introduction to Earned Value Analysis

An introduction to Earned Value Analysis An introduction to Earned Value Analysis Prepared by: Suketu Nagrecha, MBA, PMP, CNA March 16, 2002 Earned Value Analysis - 2 Abstract Earned value analysis is a method of performance measurement. Many

More information

Budgetary Planning. Managerial Accounting Fifth Edition Weygandt Kimmel Kieso. Page 9-2

Budgetary Planning. Managerial Accounting Fifth Edition Weygandt Kimmel Kieso. Page 9-2 9-1 Budgetary Planning Managerial Accounting Fifth Edition Weygandt Kimmel Kieso 9-2 study objectives 1. Indicate the benefits of budgeting. 2. State the essentials of effective budgeting. 3. Identify

More information

Cash flow is the life line of a business. Many start-up

Cash flow is the life line of a business. Many start-up PM.02 ABC of Cash Flow Projections Mark T. Chen, PE CCE Cash flow is the life line of a business. Many start-up companies fail because of insufficient cash flow. From the perspectives of both owner and

More information

Project Time Management an essential element to project success

Project Time Management an essential element to project success Project Time Management an essential element to project success Abstract This paper discusses the reasons behind the necessity to apply sound Project Time Management principles and processes to projects

More information

Earned Value and Agile Reporting

Earned Value and Agile Reporting Earned Value and Agile Reporting Anthony Cabri, Mike Griffiths Quadrus Development Inc. Abstract This paper reviews the concepts of Earned Value Management established in traditional project management,

More information

Selftestengine..PMI-SP.270 questions PMI-SP. PMI Scheduling Professional

Selftestengine..PMI-SP.270 questions PMI-SP. PMI Scheduling Professional Selftestengine..PMI-SP.270 questions Number: PMI-SP Passing Score: 800 Time Limit: 120 min File Version: 5.1 PMI-SP PMI Scheduling Professional This study guides are so comprehensible that anyone can understand

More information

An Introduction to. Metrics. used during. Software Development

An Introduction to. Metrics. used during. Software Development An Introduction to Metrics used during Software Development Life Cycle www.softwaretestinggenius.com Page 1 of 10 Define the Metric Objectives You can t control what you can t measure. This is a quote

More information

Earned value method as a tool for project control

Earned value method as a tool for project control Budownictwo i Architektura 3 (2008) 15-32 Earned value method as a tool for project control Institute of Construction, Faculty of Civil and Sanitary Engineering, Lublin University of Technology, 20-618

More information

pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development

More information

Section Five Learning Module D:

Section Five Learning Module D: Section Five Learning Module D: the Project 5.1 Module D: Objectives At the conclusion of this module you will be able to: implement a project plan; keep control of a project plan; effectively review a

More information

Earned Value Management Guidelines

Earned Value Management Guidelines Effective Date: April 21, 2009 Status: Revision 1 Supersedes: NA Document Owner: Director, Environmental and Engineering Program Introduction This paper provides guidance and recommendations for the application

More information

Value Analysis, Functional Analysis, Value Engineering and Target Costing (P2) by Norwood Whittle

Value Analysis, Functional Analysis, Value Engineering and Target Costing (P2) by Norwood Whittle Value Analysis, Functional Analysis, Value Engineering and Target Costing (P2) by Norwood Whittle In a previous article I explained the relationship between Kaizen costing, target costing, total life-cycle

More information

SCT AND MCAS MIRAMAR FOTS SOUTHERN CALIFORNIA TRACON

SCT AND MCAS MIRAMAR FOTS SOUTHERN CALIFORNIA TRACON 1-5 CONSTRUCTION SCHEDULES 1-5.1 General, Network Analysis System (NAS).- 1-5.1.1 Applicable documents.- The Publication listed below forms a part of this specification and is applicable to the extent

More information

RELEVANT TO ACCA QUALIFICATION PAPER P3. Studying Paper P3? Performance objectives 7, 8 and 9 are relevant to this exam

RELEVANT TO ACCA QUALIFICATION PAPER P3. Studying Paper P3? Performance objectives 7, 8 and 9 are relevant to this exam RELEVANT TO ACCA QUALIFICATION PAPER P3 Studying Paper P3? Performance objectives 7, 8 and 9 are relevant to this exam Business forecasting and strategic planning Quantitative data has always been supplied

More information

Chapter 11. MRP and JIT

Chapter 11. MRP and JIT Chapter 11 MRP and JIT (Material Resources Planning and Just In Time) 11.1. MRP Even if MRP can be applied among several production environments, it has been chosen here as a preferential tool for the

More information

Value Analysis, Functional Analysis, Value Engineering and Target Costing (P2) by Norwood Whittle

Value Analysis, Functional Analysis, Value Engineering and Target Costing (P2) by Norwood Whittle Value Analysis, Functional Analysis, Value Engineering and Target Costing (P2) by Norwood Whittle In a previous article I explained the relationship between Kaizen costing, target costing, total life-cycle

More information

Project Management Glossary

Project Management Glossary Project Management Glossary THE VOCABULARY OF ACHIEVEMENT RON BLACK THE MENTOR GROUP WWW.RONBLACK.COM 800-381-8686 This glossary is an excerpt from Ron Black s book, The Complete Idiot s Guide to Project

More information

THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH

THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH By Nghi M. Nguyen, Ph.D., PE, PMP. * INTRODUCTION The management of engineering projects

More information

Project Time Management

Project Time Management Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please

More information

Project Management for Scientists

Project Management for Scientists Project Management for Scientists Cost & Schedule Estimates Christoph U. Keller, c.u.keller@uu.nl Sterrekundig Instituut Utrecht Utrecht University www.astro.uu.nl/~keller Outline Resource Assignments

More information

CHAPTER 9 PROJECT FINANCE AND CONTRACT PRICING

CHAPTER 9 PROJECT FINANCE AND CONTRACT PRICING CHAPTER 9 PROJECT FINANCE AND CONTRACT PRICING In the previous chapters, techniques for project planning, scheduling, resources management, and timecost trade off have been introduced. This chapter will

More information

10.1 Communications Planning 10.2 Information Distribution Figure 10 1 10.3 Performance Reporting 10.1 Communications Planning 10.

10.1 Communications Planning 10.2 Information Distribution Figure 10 1 10.3 Performance Reporting 10.1 Communications Planning 10. PROJECT 10 COMMUNICATIONS MANAGEMENT Project Communications Management includes the processes required to ensure timely and appropriate generation, collection, dissemination, storage, and ultimate disposition

More information

Appendix A of Project Management. Appendix Table of Contents REFERENCES...761

Appendix A of Project Management. Appendix Table of Contents REFERENCES...761 Appendix A Glossary Terms of Project Management Appendix Table of Contents REFERENCES...761 750 Appendix A. Glossary of Project Management Terms Appendix A Glossary Terms of Project Management A Activity

More information

Project Management: Tracking Progress and Earned Value with MS Project 2003

Project Management: Tracking Progress and Earned Value with MS Project 2003 Project Management: Tracking Progress and Earned Value with MS Project 2003 Project Planning Suppose you have been assigned a project to construct a website in a certain time frame and given a certain

More information

Elaboration of Scrum Burndown Charts.

Elaboration of Scrum Burndown Charts. . Combining Control and Burndown Charts and Related Elements Discussion Document By Mark Crowther, Empirical Pragmatic Tester Introduction When following the Scrum approach a tool frequently used is the

More information

EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS

EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS 14 EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS Dr. P.B.G. Dissanayake 1 1 Department of Civil Engineering, Faculty of Engineering, University of Peradeniya

More information

108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised 03-24-10)

108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised 03-24-10) CRITICAL PATH METHOD SCHEDULE (Revised 03-24-10) The Standard Specifications are revised as follows: SECTION 108, BEGIN LINE 177, INSERT AS FOLLOWS: 108.04.1 Critical Path Method Schedule (a) General Requirements

More information

EVM.01. Earned Value Analysis Why it Doesn't Work

EVM.01. Earned Value Analysis Why it Doesn't Work EVM.01 Earned Value Analysis Why it Doesn't Work Mr. Joseph A Lukas, PE CCE F or many companies looking to improve project performance, earned value analysis (EVA) seems a logical technique to use on projects

More information

A Short Introduction to Project Management

A Short Introduction to Project Management 2003 January April SFWR ENG 2B03 Slides 08 0 A Short Introduction to Project Management SFWR ENG 2B03 2003 Robert L. Baber 2003 January April SFWR ENG 2B03 Slides 08 1 Why Project Management? Why manage

More information

LEVEL ECONOMICS. ECON2/Unit 2 The National Economy Mark scheme. June 2014. Version 1.0/Final

LEVEL ECONOMICS. ECON2/Unit 2 The National Economy Mark scheme. June 2014. Version 1.0/Final LEVEL ECONOMICS ECON2/Unit 2 The National Economy Mark scheme June 2014 Version 1.0/Final Mark schemes are prepared by the Lead Assessment Writer and considered, together with the relevant questions, by

More information

Contract / Construction Management. November 2006

Contract / Construction Management. November 2006 Contract / Construction Management November 2006 Presentation Outline I. Introduction Project Management II. Contract/Construction Management Stage 1: Construction Period Stage 2: Defects Liability Period

More information

Producing a programme under the NEC form of contract

Producing a programme under the NEC form of contract Proceedings of the Institution of Civil Engineers Management, Procurement and Law 163 May 2010 Issue MP2 Pages 59 64 doi: 10.1680/mpal.2010.163.2.59 Paper 900033 Received 02/05/09 Accepted 19/08/09 Keywords:

More information

Chapter 7: Project Cost Management. Information Technology Project Management, Fourth Edition

Chapter 7: Project Cost Management. Information Technology Project Management, Fourth Edition Chapter 7: Project Cost Management Information Technology Project Management, Fourth Edition Learning Objectives Understand the importance of project cost management. Explain basic project cost management

More information

MTAT.03.244 Software Economics. Lecture 6: Software Cost Estimation (part II)

MTAT.03.244 Software Economics. Lecture 6: Software Cost Estimation (part II) MTAT.03.244 Software Economics Lecture 6: Software Cost Estimation (part II) Marlon Dumas marlon.dumas ät ut. ee Outline Review of Effort Estimation Homework Discussion on book chapter by Caper Jones Earned

More information

Paying off a debt. Ethan D. Bolker Maura B. Mast. December 4, 2007

Paying off a debt. Ethan D. Bolker Maura B. Mast. December 4, 2007 Paying off a debt Ethan D. Bolker Maura B. Mast December 4, 2007 Plan Lecture notes Can you afford a mortgage? There s a $250,000 condominium you want to buy. You ve managed to scrape together $50,000

More information

Sample Examination Questions

Sample Examination Questions Sample Examination Questions The following questions are examples of the type of questions that appear on the PMP Certification Examination. Disclaimer: These questions are intended for study purposes

More information

Chapter 2: Project Time Management

Chapter 2: Project Time Management Chapter 2: Project Time Management Learning Objectives o o o o Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules.

More information

Expert Reference Series of White Papers. Importance of Schedule and Cost Control

Expert Reference Series of White Papers. Importance of Schedule and Cost Control Expert Reference Series of White Papers Importance of Schedule and Cost Control 1-800-COURSES www.globalknowledge.com Importance of Schedule and Cost Control Bill Scott, PE, PMP, PgMP Outline I. Project

More information

Project Time Management

Project Time Management Project Skills Team FME www.free-management-ebooks.com ISBN 978-1-62620-981-3 Copyright Notice www.free-management-ebooks.com 2014. All Rights Reserved ISBN 978-1-62620-981-3 The material contained within

More information

Accounting System. Page 1 of 9

Accounting System. Page 1 of 9 Page 1 of 9 Accounting System In support of program management and Earned Value Management, the accounting system must be able to relate costs incurred to work accomplished. Not all accounting systems

More information

Since 1985, the Test Program Set (TPS) development

Since 1985, the Test Program Set (TPS) development Applying Management Reserve to Software Project Management Walter H. Lipke Oklahoma City Air Logistics Center, Directorate of Aircraft Maintenance, Software Division Today s standard of practice for managing

More information

COST THEORY. I What costs matter? A Opportunity Costs

COST THEORY. I What costs matter? A Opportunity Costs COST THEORY Cost theory is related to production theory, they are often used together. However, the question is how much to produce, as opposed to which inputs to use. That is, assume that we use production

More information

SoaDssPm: A new Service-Oriented Architecture of the decision support system for the Project Management.

SoaDssPm: A new Service-Oriented Architecture of the decision support system for the Project Management. SoaDssPm: A new Service-Oriented Architecture of the decision support system for the Project Management. Fatima Boumahdi, Rachid Chalal Abstract This paper presents an architecture for the Project Management,

More information

Project Execution - PM Elements

Project Execution - PM Elements Performance Initial Release 1. Introduction to Project Tracking and Reviewing Once a project has advanced to the phase of performance, the consistent and constant flow of information on the true status

More information

Introduction to earn value management in Civil Engineering

Introduction to earn value management in Civil Engineering 3 rd World Conference on Applied Sciences, Engineering & Technology 27-29 September 2014, Kathmandu, Nepal Introduction to earn value management in Civil Engineering S. K. KAMANE, S. A. MAHADIK, A. C.

More information

FRA s Earned Value Management System Overview for Self Assessment Surveillance March 07-09, 2011

FRA s Earned Value Management System Overview for Self Assessment Surveillance March 07-09, 2011 FRA s Earned Value Management System Overview for Self Assessment Surveillance March 07-09, 2011 Dean Hoffer Head, Office of Project Management Oversight Outline EVMS History at the Lab FRA EVMS Documents

More information

Practical Metrics for Managing and Improving Software Testing

Practical Metrics for Managing and Improving Software Testing Practical Metrics for Managing and Improving Software Testing Presented By: Shaun Bradshaw shaun.bradshaw@zenergytechnologies.com Slide 1 Part 1 Test Metrics Ten key metrics testers should track One bonus

More information

Unit 5: Cost Management (PMBOK Guide, Chapter 7)

Unit 5: Cost Management (PMBOK Guide, Chapter 7) (PMBOK Guide, Chapter 7) The questions on this topic have historically been more difficult than average for some exam takers because of unfamiliarity with some of the math. You will be responsible for

More information

Cost Estimating Procedure. Table of Contents

Cost Estimating Procedure. Table of Contents Cost Estimating Procedure Table of Contents 1.0 PURPOSE... 1 2.0 SCOPE... 1 3.0 REFERENCES... 1 4.0 DESCRIPTION... 1 5.0 PROCEDURE DETAILS... 2 5.1 Developing a Detailed Cost Estimate... 2 5.2 Basis of

More information

New Tools for Project Managers: Evolution of S-Curve and Earned Value Formalism

New Tools for Project Managers: Evolution of S-Curve and Earned Value Formalism New Tools for Project Managers: Evolution of S-Curve and Earned Value Formalism A Presentation at the Third Caribbean & Latin American Conference On Project Management, 21 23 May 2003 Denis F. Cioffi,

More information

This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts.

This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts. This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts. To begin, how does the Prime integrate the subcontractor

More information

Fundamentals Level Skills Module, Paper F5. 1 Hair Co. (a)

Fundamentals Level Skills Module, Paper F5. 1 Hair Co. (a) Answers Fundamentals Level Skills Module, Paper F5 Performance Management December 2012 Answers 1 Hair Co Weighted average contribution to sales ratio (WA C/S ratio) = total contribution/total sales revenue.

More information

PROJECT SCHEDULING AND TRACKING

PROJECT SCHEDULING AND TRACKING PROJECT SCHEDULING AND TRACKING PROJECT SCHEDULING AND TRACKING Software project scheduling is an activity that distributes estimated effort across the planned project duration by allocating the effort

More information

Study Questions for Chapter 9 (Answer Sheet)

Study Questions for Chapter 9 (Answer Sheet) DEREE COLLEGE DEPARTMENT OF ECONOMICS EC 1101 PRINCIPLES OF ECONOMICS II FALL SEMESTER 2002 M-W-F 13:00-13:50 Dr. Andreas Kontoleon Office hours: Contact: a.kontoleon@ucl.ac.uk Wednesdays 15:00-17:00 Study

More information

Profesor: Francisco Javier Sanz Pérez. by fjspsv, 2011. PMP Test C07_01

Profesor: Francisco Javier Sanz Pérez. by fjspsv, 2011. PMP Test C07_01 PMP Test C07_01 01. One common way to compute estimate at completion (EAC) is to take the budget at completion (BAC) and: A. Divide by SPI. B. Multiply by SPI. C. Multiply by CPI. D. Divide by CPI. 02.

More information

Applied Project Management ( APM )

Applied Project Management ( APM ) Applied Project Management Applied Project Management ( APM ) TRAINING PROGRAM Page 1 Of 7 APPLIED PROJECT MANAGEMENT PRO PROGRAM OVERVIEW This course provides in-depth Project Management Training and

More information

Tracking Software Development Progress with Earned Value and Use Case Point

Tracking Software Development Progress with Earned Value and Use Case Point ISBN 978-952-5726-06-0 Proceedings of the 2009 International Workshop on Information Security and Application (IWISA 2009) Qingdao, China, November 21-22, 2009 Tracking Software Development Progress with

More information

Module 3: The Project Planning Stage

Module 3: The Project Planning Stage Overview Once you've initiated the project and gathered all relevant information, you'll then begin planning your project. The planning stage depends on the size of your project, how much information you

More information

Objectives. Project Management Overview. Successful Project Fundamentals. Additional Training Resources

Objectives. Project Management Overview. Successful Project Fundamentals. Additional Training Resources Project Management for Small Business Moderator: Maria Mancha Frontline Systems, Inc. Objectives Project Management Overview Successful Project Fundamentals Additional Training Resources Project Management

More information

BEYOND EARNED VALUE: A Better Practice for Monitoring Project Performance 2012 Dr. Kenneth F. Smith, PMP ; Project Management Consultant

BEYOND EARNED VALUE: A Better Practice for Monitoring Project Performance 2012 Dr. Kenneth F. Smith, PMP ; Project Management Consultant BEYOND EARNED VALUE: A Better Practice for Monitoring Project Performance 2012 Dr. Kenneth F. Smith, PMP ; Project Management Consultant Introduction Earned Value (EV) has been around since the 1960 s

More information

INTEGRATION - THE KEY TO VALUE MANAGEMENT. Martin Robinson, Principal Consultant, WS Atkins Management Consultants

INTEGRATION - THE KEY TO VALUE MANAGEMENT. Martin Robinson, Principal Consultant, WS Atkins Management Consultants Introduction INTEGRATION - THE KEY TO VALUE MANAGEMENT Martin Robinson, Principal Consultant, WS Atkins Management Consultants The focus of the AGILE construction initiative is to identify ways that may

More information

GUIDE TO IMPLEMENTING A REGULATORY FOOD SAFETY AUDITOR SYSTEM

GUIDE TO IMPLEMENTING A REGULATORY FOOD SAFETY AUDITOR SYSTEM GUIDE TO IMPLEMENTING A REGULATORY FOOD SAFETY AUDITOR SYSTEM FEBRUARY 2016 2 Contents Introduction... 4 Scope and objectives... 5 Scope... 5 Objectives... 5 Responsibilities... 5 The role of the licensee

More information

Project Cost Control: The Way it Works By R. Max Wideman

Project Cost Control: The Way it Works By R. Max Wideman Project Cost Control: The Way it Works By R. Max Wideman 12/21/05 In a recent consulting assignment we realized that there was some lack of understanding of the whole system of project cost control, how

More information

EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT

EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT Assoc. Prof. Anca Mehedintu Ph. D University of Craiova Faculty of Economics and Business Administration Craiova, Romania Prof. Cerasela Pirvu

More information

Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration

Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration Prof. M. Rammohan Rao Former Dean Professor Emeritus Executive Director, Centre for Analytical

More information

IUCN Project Budgeting Guidelines

IUCN Project Budgeting Guidelines IUCN Project Budgeting Guidelines Version: 14 February 2014 Issued by: Chief Financial Officer Contents 1. Definition... 2 2. Purpose... 2 3. Budget principles :... 2 4. Budget types... 3 5. Budget structure...

More information

PM in construction industry

PM in construction industry PM in construction industry Construction 2. Lepel BME Department of Construction Technology and Management 19-03-2014 PM in general Project integration Project plan development Project plan execution Integrated

More information

A collection of Safran Project report samples for project professionals

A collection of Safran Project report samples for project professionals A collection of Safran Project report samples for project professionals Safran Software Solutions Global Offices: Houston, London, Oslo, Stavanger www.safran.com Contents Introduction... 2 About the Reports

More information

Simple Earned Value (Using MS Project 2010)

Simple Earned Value (Using MS Project 2010) Simple Earned Value (Using MS Project 2010) This document outlines a Simple Earned Value technique, a technique which sticks to a simple 0/100% Milestone approach with some Level of effort tasks maintained

More information

VIII. Project Management Glossary

VIII. Project Management Glossary https://www.wrike.com/project-management-guide/glossary/ VIII. Project Management Glossary Project management, like any other industry, has its share of unique terms. Don t be overwhelmed. Here is our

More information

Project Management Framework

Project Management Framework Information Services Project Management Framework October 2003 Document ID No. Page 1 of 1 Contents 1. Introduction Page 3 2. Use of Framework Page 3 3. Project Register and Monitoring Page 4 4. Project

More information

Schedule analytics tool

Schedule analytics tool Schedule analytics tool As capital project spend increases and aggressive deadlines are built into project schedules, the reliance on accurate, transparent and meaningful schedule practices is growing.

More information

What is Costrac? Approval of Budget against WBS. Feasibility Study Completed. Define & Map WBS. Approval of WBS. Estimate

What is Costrac? Approval of Budget against WBS. Feasibility Study Completed. Define & Map WBS. Approval of WBS. Estimate The outcome of any venture is most often affected by the ready availability of useful information on which timely decisions can be taken. For project success, the need is therefore to know where you re

More information

01 In any business, or, indeed, in life in general, hindsight is a beautiful thing. If only we could look into a

01 In any business, or, indeed, in life in general, hindsight is a beautiful thing. If only we could look into a 01 technical cost-volumeprofit relevant to acca qualification paper F5 In any business, or, indeed, in life in general, hindsight is a beautiful thing. If only we could look into a crystal ball and find

More information

Overview. Essential Questions. Precalculus, Quarter 4, Unit 4.5 Build Arithmetic and Geometric Sequences and Series

Overview. Essential Questions. Precalculus, Quarter 4, Unit 4.5 Build Arithmetic and Geometric Sequences and Series Sequences and Series Overview Number of instruction days: 4 6 (1 day = 53 minutes) Content to Be Learned Write arithmetic and geometric sequences both recursively and with an explicit formula, use them

More information

Chapter 1. Introduction

Chapter 1. Introduction Chapter 1 Introduction What is productivity, how is it measured and why is it important? These questions are a useful starting point from which we can define and explain the range of productivity measures

More information

1 Supplement: IAS 11 Construction contracts

1 Supplement: IAS 11 Construction contracts 1 Supplement: IAS 11 Construction contracts Introduction In this section we introduce construction contracts. We will look at the required treatments and disclosures under IAS 11. Make sure that you work

More information