Project Management. Project Management Fundamentals: Estimation and Project Control. Sergio Cavaliere. IBM Global Business Services

Size: px
Start display at page:

Download "Project Management. Project Management Fundamentals: Estimation and Project Control. Sergio Cavaliere. IBM Global Business Services"

Transcription

1 Project Management Sergio Cavaliere IBM Global Business Services

2 Agenda Estimating Basic Definitions Estimating Approaches an Techniques Project Estimating Project Control Overview Schedule and Cost Control Earned Value Management Exercises Estimation and Project Control

3 Estimating General Objective Verify common concepts Know best practices Select the Estimating Approach Make a Project Estimation

4 Estimating Definitions - 1 Estimating: evaluating the resources (labor, equipment, facilities) needed to complete project activities Plan: An organized set of decisions about how to carry out future activities and requires input from the estimate (including shedule and resource availability) Cost: the value of the estimate allocated as a budget available to deliver the plan (difference between cost and budget are called unresolved costs) Cost Estimating: evaluating the cost of the resources needed to complete project activities Cost Budgeting: allocating the costs estimated to individual project components to make them measurable and manageable Price: The amount quote to the client What is an estimate? An assessment of the likely quantitative result Usually applied to project cost factors and schedule Should include some indication of accuracy (e.g. +- percent) Usually used with a modifier (e.g. preliminary, conceptual, feasibility)

5 Estimating Definitions - 2 Software Creates project estimate Template Requires Estimating input and calibration Historical Data o defined algorithms Costs money Black box Overcomes black box tool Usually spread sheet Mechanism for undertaking estimation Many identified Tool variants e.g. Monte Carlo for variance e.g. Top-Down for estimating Use 2 or more Part of an estimate strategy

6 Estimating Definitions - 3 Items to consider Utilization factor: amount of time a FTE (Full Time Equivalent) can be used for the length of the project Hours available/year: (Exam (52 w X 5 d X 8 h) Duration parameters: Working Time: Activity duration based on number of hours a workday or a workweek Effort Hours: Hours required to complete a task Elapsed Time: Calendar Duration including weekends, holidays and breaks Productivity: rate at which work is produced Availability: resource present and ready to work Contiguous duration: work time that is not interrupted Interruptible duration: work time that may be interrupted Level of Effort: computed uniform rate of activity Some formulas Cost = Effort Hours Productivity X Unit Cost Effort / Productivity Resource duration = Availability

7 Estimating Types of Estimates Estimates per Phase: Pre-bid Offering Estimates per target Raw Development Technical What an estimate has to include? Labor Equipment Software Real estate Supplies

8 Estimating Quality of Estimate Correct Estimate prevents from causing troubled projects Types of Estimating Problems Absence of historical data Incorrect project / goal definition No accurate validation of the estimate Estimation is a process which requires governance Process Elements (lifecycle model, Data and metrics, Best Practices) Governance (Reviews, Action Plan, Roles)

9 Estimating Pricing Process Effort Estimating is a step of a process Factor Adjustments 5 Additional Factors 4 Price Project Consider Additional factors Additional Factors 3 Create Resource Plan Project Schedule Metric Size Measures Create Effort Estimate 1 Effort Estimate 2 Create Project Schedule Release Strategy

10 Estimating Estimation Life Cycle Model Start Client Request Decision to go on Indicative Estimate Request for detailed Proposal Proposed Estimate Deision made to close Decision not to continue Agreement made Closed Estimate Project End Committed Estimate

11 Estimating Committed Stage Committed Stage Estimation Process Project manager 3.1 Confirm work plans from Estimates 3.2 Gather actuals for the period 3.3 Integrate Change Orders Project Start 3.4 Estimation Checkpoint Review Plan Requires Changes? Type of Change? Estimating SME 3.5 Gather Actuals for Esrimation Factors Project Close 3.6 Review Estimation factors

12 Estimating Best Practices of Estimate 1. Quantify things 2. Use more than one approach 3. Use historical data and metrics 4. Same metrics for project measurements and estimate 5. Use recommended estimating tools 6. Analyze your input and output data 7. Estimates should be done by experts 8. Document the assumptions 9. Verify estimate with other people 10. The later you will make an estimate the more accurate it will be

13 Estimating Quantify things Quantify things needed to obtain a project size Estimation Parameters : Function points, Lines of Code, Use Cases Using in a Parametric Model Artifacts: modules, interfaces, screens, reports, implementation classes, data entities, etc. Driven by technique and project type. Many tools require the choice of a project pattern Using number and range of artifacts Using estimating factors

14 Estimating Use more than one approach Use more than one estimating approach Methods and Techniques might include: 1. One ore more top-down approach 2. A bottom up estimate (task by task or work product based) 3. Experts involvement (Delphi) The selected approach may involve the use of tools and/or spreadsheets: Validate when. All estimates agree Otherwise analyse assumptions By iterating, estimates from different methods start to converge The different approaches converge

15 Estimating Approaches Deadline Driven 1. Compute Estimate starting from the WBS 2. Add Resources and dependencies and generate the schedule 3. Add estimate for non included activities using historical data or expert support Analogy (use data of similar project types) 1. Identify projects similar to the one to be estimated 2. Note the effort, cost and schedule of the identified projects 3. Adjust effort, cost and schedule by assessing size, complexity and other factors Parametric (is most commonly supported by tools) 1. Confirm the size of the project using chosen parameters 2. Assess productivity related to the parameters and generate effort 3. Add any additional effort not included 4. Convert effort into schedule and determine cost

16 Estimating Approaches - 2 Artifacts and Work Distribution (uses the number and range of artifacts and info about how iyhe effort is distributed across the project phases) 1. Choose the artifacts and classify them by complexity 2. Count the artifacts 3. Calculate the build effort for each artifact according to its complexity, using hystorical data and expert support 4. Sum the build efforts 5. Asses the effort for non build activites, using the work distribution 6. Convert effort into schedule and determine cost Plan Driven (the most accurate) 1. Use historical data and expert knowledge to get ALL activities to be done 2. Determine the effort and allocate resources for each activity 3. Convert effort into schedule and determine cost 4. Add effort for resource leveling, non-productive hours, level of effort and so-on to get the total effort

17 Estimating Selecting the Estimation Approach (Indicative and Proposal Stage) No Yes No Yes, always No Yes if tool has rilevant Yes Yes Yes Use Only to give a go/no go decision on doability Not a primary method unless adequately calibrated Often a primary method in Indicative State, sometimes in Proposal If primary requires accurate historical data, otherwise can be used in validation approaches Yes No Yes No Should be the approach of choice when possible

18 Estimating Use historical data Use actual historical data and metrics Use harvested metrics from similar projects Make sure that the project has similar work pattern and size Analyse both successful and troubled similar projects Many tools have hystorical data db as basis for Estimate calculation

19 Estimating Example - a Parametric database Type Productivity Fpts FP/SM Project Name Pj no PM Type Project FP count (predicted) Project 1 1 John Smith ND C/S ,89 Project 2 2 John Smith ND web ,16 Project 3 3 John Smith ND C/S ,13 Project 4 4 John Smith Enh C/S ,52 Project 5 5 John Smith ND web ,74 Project 6 6 John Smith Enh web ,82 Project 7 7 John Smith ND C/S 92 12,84 Project 8 8 John Smith ND C/S ,49 Project 9 9 John Smith Enh web ,1 Project John Smith Enh C/S ,81 Project John Smith ND web ,2 Project John Smith ND C/S ,14 Project John Smith ND web ,35 Project John Smith ND web ,03 Project John Smith Enh C/S 96 36,24 Project John Smith Enh C/S ,47 Project John Smith Enh web ,32 Platform Average of all Web developments Variance (Standard deviation) Actual 23,59 5,11 Parametric Estimating From Parametric DB -> Web Portal Base Productivity = 21,09 (SD 5,15) My project size = 250 Expected Effort = 250/21,1 = 11,8 Staff Months Variance will be defined with Delphi or Monte Carlo techniques

20 Estimating Use same metrics Use same metrics for project measurements and estimate Match metrics to the estimating technique being used 1. Track at task level a plan with estimates at task level and use results as direct input for collection of metrics 2. A plan based on estimates of FP or Artifacts can be tracked against delivery of these artifacts The metrics match avoids: a. Allocation of gathered data downwards or to other variables b. Possible interpretive errors caused by such allocation It is always difficult to track at task level a project that was estimated al project level

21 Estimating Example - b Use the same metrics for estimating and tracking Test Scripts Completed Plan Actual Weeks

22 Estimating Use tools Use recommended estimating tools 1. Use one of several available tools (e.g. SLIM or those based on COCOMO II) 2. Avoid build an estimating worksheet to apply estimating techniques/approaches 3. Tools are usually based on harvested metrics and can provide excellent estimate validation 4. Choose the tool that fits your need: see what types of project it has been designed for 5. If possible choose tools where you can feed back actuals to remake and perfect estimating forecasts

23 Estimating Analyze data Analyze your input and output data Input Data: experience level of team, complexity of solution, work pattern, productivity, size, interfaces, client Inputs have all a degree of variance so as well the outputs 1. Verify provenance and accuracy of each input to better assess the confidence level (ball park estimate or based on reliable process as for ex. Function Point Analyis -) 2. Consider if the input data is appropriate to your project: Same Problem Domain Similar technical solution Similar project type (work pattern) Same project scope

24 Estimating Statistics must be verified for validity Top down vs Bottom-up approach: use of a large set of small numbers results in a global variance reduction -> Bottom-up approach is preferred When using Top-down approach we must be sure the numbers are based on a great variety of experience with similar projects/tasks to reduce the risk to be off how many projects? how many contributors?

25 Estimating Example - c Statistics must be verified for validity - Example

26 Estimating Variances Variance is always included in estimates Input data are affected by variance Output estimates are to be delivered with variance Nominal values and a range Specific techniques are used to compute variance: Delphi technique MonteCarlo technique

27 Estimating Variance Techniques There a number of commonly used techniques for assessing estimating variance: Wideband Delphi technique consensus in meeting PERT technique simple calculations Monte Carlo technique graphical output Using an estimating tool that generates variance Analyzing historical data records to determine variance (Gut feel NOT RELIABLE!)

28 Estimating Delphi Technique Subject Matter Experts are engaged Each SME gives 3 estimates: Low (1%) Nominal (50%) High (99%) Evaluations are shared and compared Final Estimates are generated

29 Estimating Delphi Technique: the process flow Delphi Flow Historical Data xxxx xxxx. xxxx.. Assumptions xxxx Interim xxxx. Estimate High xxxx.. Nom. Low.. Assumptions xxxx Interim xxxx. Estimate High xxxx.. Nom. Low.. Assumptions xxxx Estimate xxxx. High xxxx.. Nom. Low.. Initial Meeting Estimation Session Assess Results Present Results Agree Present Final Estimate No agreement

30 Estimating PERT Technique distribution assumed for optimistic, most likely and pessimistic guesses: Nominal = 1*Optimistic + 4*Most Likely + 1*Pessimistic Standard Deviation = (Optimistic pessimistic) / 6 PERT Estimate = ,3 (ab. 68% certainty -> 1 SD of Nominal)

31 Estimating Monte Carlo Technique Executes simulations on the basis of nominal values and theirs variances Supported by tools (adds-in in Excel, MS Project) Indicates Cumulative Frequencies by Nominal values Output in graph or table form

32 Estimating Understanding output data Overestimated Errror in Estimate to complete Requirements Design Code and Test Deployment Underestimated Higher Variance in early phases, reducing variance as the projects goes on to its completion

33 Estimating Other Best Practices Estimates carried out by experienced people Always assumptions must be documented Estimates need reviewing, updating and auditing, so an estimate report must be produced which specifies Method Used, Results, Assumptions Typical assumptions: Staff experience Productivity Size (artifacts and FP) Artifacts complexity Number of external interfaces Accuracy

34 Estimating Hidden Assumptions (typically obvious but to be considered) Data conversion / load / migration Training environment setup Printing location Historical Data Administrative tasks Auditing Analysing assumptions helps in identifying risks

35 Estimating Preparing a Project Estimate Roles Independent Estimating SME (evaluator) Project Manager (estimate total project size, effort, schedule& cost) Estimating Practitioner Estimating Independent Practitioner Independent Estimating SME (approver) Items to document Purpose of the Estimate Approaches used Project Content and scope Assumptions Baseline Values Active Participants Confidence Level Contingency

36 Estimating Preparing a Project Estimate - 2 Technical Estimate Size Estimate Effort Estimate Schedule Estimate Assumptions Resources allocated Project Estimate Additional roles, phases and activities A full schedule for all activities Overall effort Cost to complete Baseline Estimate Consolidate Estimate Components Document rationales and assumptions

37 Estimating Estimate Review (Indicative and Proposal Stage) Address main problems in determining the Estimate Insufficient historical information or validation Price not matching estimate Incorrect Project Definition No reassessment Verify Estimate Rules of thumb for quick validation Full check list for detailed assessment Risk Mitigation Plan in place which considers sources of variance This quote is from - "Steve McConnell", How to Defend an Unpopular Schedule, IEEE Software, Vol. 13, No. 3, May 1996

38 Project Control General Objective Verify common concepts Identify areas of Control Know Schedule and Cost Control parameters Know Earned Value Management

39 Project Control - Overview Scope Schedule Budget Customer Contract Risks Project Control Suppliers Change Management Quality Issue Management Problem Management

40 Project Control - Stages of Control Establish standards through plans and procedures Collect actual performance Information Compare actual and planned performance Take corrective action

41 Project Control - Compare Actual vs Planned Compare Actual vs Planned using Metrics Resource Utilization Number of Risk events passed or completed Number of changes over time Earned Value Defect Tasks start/finish (planned vs actual) Milestones Technical control point Deliverables

42 Estimating follow on Estimating in Delivery (Committed Stage) Estimating in delivery is strictly connected to controlling Scope and Size Schedule Cost Assumptions Risk Plan Performing Team Performing Differences between old and new Estimate generate new baselines Gaps are to be identified GAP Cost Budget Pert estimating approach used Low, Expected and High values. Standard deviation and Variance Variance = SD²

43 Estimating follow on Estimating in Delivery - 2 Reducing Variance means reducing Risks Overestimated Errror in Estimate to complete Requirements Design v v v v Code and Test Deployment but Underestimated NOTE: Estimate at Completion can increase even if Variance reduces Effort Estimate to Complete Date of Checkpoint Estimate to Complete Maximum Estimate to Complete Nominal Estimate to Complete Minimum Current Estimate at Completion Baseline Estimate Variance Mar Apr May Jun Jul ,00 69,44 38,03 51,36 44,44

44 Schedule and Cost Control - 1 Considering the Earned Value Allows objective assessment of variance Allows common understanding of the amount of work actually done Is incorporated in major project management SW packages Allows point-in-time analysis Allows forecast of future performance Can be determined at different levels (work element, summary, project)

45 Schedule and Cost Control - 2 Earned Value Definitions Budgeted Cost of Work Scheduled (BCWS): planned expenditure of each work package scheduled to be accomplished as of the status reporting date on the baseline schedule Actual Cost of Work Performed (ACWP): actual expenditure of each work package as of the status reporting date Budgeted Cost of Work Performed (BCWP): percentage complete of each work package as of the status reporting date multiplied by the baselined budget of that work package (EV) Budget at completion (BAC): the sum of all the baselined budgtes allocated to the project work packages

46 Schedule and Cost Control - 3 Earned Value Variance Analysis Cost Variance (CV): The difference between what was accomplished and what was spent to accomplish it CV = BCWP ACWP Negative CV denotes overexpenditure of budget for work done Positive CV denotes underexpenditure of budget for work done Schedule Variance (SV): The difference between what was accomplished and what was planned or scheduled to be accomplished SV = BCWP BCWS Negative CV denotes budget needed to catch up on work scheduled Positive CV denotes budget used for work accomplished earlier than planned

47 Schedule and Cost Control - 4 Earned Value Performance Index Analysis Cost Performance Index (CPI = BCWP/ACWP): Denotes past performance on the money spent as of the status reporting date Schedule Performance Index (SPI = BCWP/BCWS) Denotes past performance on the money spent as of the status reporting date Percentage complete vs. Percentage spent: Percentage complete (BCWP/BAC) Percentage spent (ACWP/BAC)

48 Schedule and Cost Control - 5 Forecasting Project Performance How much will it take to finish = estimate to complete (ETC): Alternatives ETC = Sum of new estimates of unfinished work (may be very accurate but also very time consuming) ETC = Sum of budgets of unfinished work ETC = BAC/CPI ACWP Show how much it will cost when done (EAC) EAC = ETC + ACWP

49 Schedule and Cost Control - 6 Forecasting Project Performance Efficiency level required to finish within budget = To-Complete- Performance-Index (TCPI) : TCPI = (BAC-BCWP) / (BAC ACWP) Denotes the performance required for the remaining work in order to get the project back on track (with no change) Is not and indicator of required overtime If the project is on schedule and on budget TCPI = 1 IF TCPI > 1, efficiency required might be unachievable Determine feasible TCPI and recalculate EAC

50 Earned value management implies reestimating discrete work units $ ETC EAC BAC VAC AC = actual costs SV = schedule variance CV = cost variance ETC = estimate to complete EAC = estimate at completion VAC = variance at completion BAC = budget at completion CV SV Budget (BCWS or PV) Actual (ACWP or AC) CV = EV AC SV = EV - PV Work performed (BCWP or EV) T=t Time

51 Plan for Earned Value Management: where we are Factor Adjustments 5 Additional Factors 4 Price Project Consider Additional factors Additional Factors 3 Create Resource Plan Project Schedule Metric Size Measures Create Effort Estimate 1 Effort Estimate 2 Create Project Schedule Release Strategy

52 Plan for Earned Value Management First find something that you can count and is a meaningful measure of product scope Define the units of work that are suitable for the project: this is represented by the WBS tailored for the solution Define organizational breakdown structure (OBS): teams, sub-contractors & control accounts, Define the Responsibility Assignment Matrix (RAM) Define the schedule or WHEN it is to be done! Spread total project effort amongst all Control Accounts Define the budget as the last step before project start, or by using an EVM acronym: Planned Value (PV) or Budgeted Cost for Work Scheduled (BCWS). Allocate the project budget to units of work (effort, costs, etc.) at the control account level.

53 Earned Value Management in delivery Factor Adjustments 5 Additional Factors 4 Price Project Consider Additional factors Additional Factors Project Schedule 3 Create Resource Plan Project Launch Tracking Progress and Reestimate Metric Size Measures Create Effort Estimate 1 Effort Estimate 2 Create Project Schedule Release Strategy Project Close

54 Tracking Progress with Earned Value - Build Indicators Planned value (PV) = of budgeted costs for each control account Actual cost (AC) = of timesheets + other costs Measure progress: 0/100 - work packages planned to start and complete 50/50-50% earned at start, 50% upon completion percent complete - Monthly estimate of % of work completed (subjective basis) units complete - Places a given value for each unit completed interim/weighted milestones - work packages subdivided into milestones each having a weight associated with it level of effort - value earned with the passage of time Calculate earned value (progress units x rates defined when estimating) Calculate cost variance CV = EV AC and schedule variance SV = EV PV Calculate estimate to complete (ETC): estimated cost (effort + expenses) needed to complete ETC implies adjustments to initial estimate based on actual productivity Calculate estimate at completion (EAC): EAC = AC + ETC

55 Schedule Control Adjusting the schedule to meet objectives: Change the relationships among tasks so that the critical path is shorter (fast-tracking) Do tasks in parallel not in sequence Change approach to work to create a different set of interrelated tasks with a shorter critical path (note: this may change the WBS) Change finish-start relationships to finish-finish ones Change a date constraint so that a task on the critical path can start or end sooner Crash the network to decrease the project total duration after alternatives and use of resources

56 Sample Problems - 1

57 Sample Problems - 2

58 Sample Problems - 3

59 Sample Problems - 4

60 Sample Problems Solutions - 1

61 Sample Problems Solutions - 2

62 Sample Problems Solutions - 3

Project Cost Management

Project Cost Management Project Cost Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points To Note Please

More information

Chapter 7. (PMBOK Guide)

Chapter 7. (PMBOK Guide) Chapter 7 Project Cost Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: marajabi@ut.ac.irac ir Homepage:

More information

Brainstorm. What is Cost and Project Cost Management?

Brainstorm. What is Cost and Project Cost Management? Brainstorm Suppose you need to create a network from scratch in your organization's headquarter. Your project is named HQ Network. Your major deliverables includes: LAN, WAN, server room, workstations,

More information

A Gentle Introduction to Earned Value Management Systems

A Gentle Introduction to Earned Value Management Systems A Gentle Introduction to Earned Value Management Systems Good metrics let us see if we are doing the right things and doing them well." Niwot Ridge Consulting 4347 Pebble Beach Niwot, Colorao www.niwotridge.com

More information

INSE 6230 Total Quality Project Management

INSE 6230 Total Quality Project Management Lecture 5 Project Cost Management Project cost management introduction Estimating costs and budgeting Earned Value Management (EVM) 2 IT projects have a poor track record for meeting budget goals Cost

More information

CPM -100: Principles of Project Management

CPM -100: Principles of Project Management CPM -100: Principles of Project Management Lesson B: Time and Cost Management Presented by Bruce R. Shaw, P.E., PMP starshaw@starpower.net Ph: 703-922-2772 Presented at the PMI-CPM 2002 Fall Conference

More information

Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance.

Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance. About the Tutorial Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance. This is a brief tutorial that acquaints

More information

Rules on using templates. MECH 896 Professional Development for MEng Students. Assignment #6A: Questions. Homework Discussion

Rules on using templates. MECH 896 Professional Development for MEng Students. Assignment #6A: Questions. Homework Discussion MECH 896 Professional Development for MEng Students Mohamed Hefny and Brian Surgenor (hefny@cs.queensu.ca and surgenor@me.queensu.ca) Rules on using templates 1) Must reference the template used 2) Use

More information

Profesor: Francisco Javier Sanz Pérez. by fjspsv, 2011. PMP Test C07_01

Profesor: Francisco Javier Sanz Pérez. by fjspsv, 2011. PMP Test C07_01 PMP Test C07_01 01. One common way to compute estimate at completion (EAC) is to take the budget at completion (BAC) and: A. Divide by SPI. B. Multiply by SPI. C. Multiply by CPI. D. Divide by CPI. 02.

More information

Module 5 Cost Management PMP Exam Questions

Module 5 Cost Management PMP Exam Questions Module 5 Cost Management PMP Exam Questions PMP, PMBOK and the Registered Education Provider logo are registered marks of the Project Management Institute, Inc Question 1 A company, which provides professional

More information

Earned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP

Earned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP Earned Value Exercise 1 Running head: Earned Value Exercise Earned Value Exercise SuCheng Wu MET AD 644: Project Risk, and Cost Management Paul B. Cook, PhD PMP Earned Value Exercise 2 Case 1: Background:

More information

700 Analysis and Reporting

700 Analysis and Reporting Jefferson Science Associates, LLC 700 Analysis and Reporting Project Control System Manual Revision 7-50 - 700 Analysis and Reporting This chapter of the JSA Project Control System Manual explains how

More information

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1 Earned Value Valerie Colber, MBA, PMP, SCPM Not for duplication nor distribution 1 Where did Earned Value Management come from? In 1967 the Department of Defense (DoD) established the Cost/Schedule Control

More information

PROJECTS SCHEDULING AND COST CONTROLS

PROJECTS SCHEDULING AND COST CONTROLS Professional Development Day September 27th, 2014 PROJECTS SCHEDULING AND COST CONTROLS Why do we need to Control Time and Cost? Plans are nothing; Planning is everything. Dwight D. Eisenhower Back to

More information

Using Earned Value Management for Improving Processes. By Cynthia K. West

Using Earned Value Management for Improving Processes. By Cynthia K. West Using Earned Value Management for Improving Processes By Cynthia K. West Summary: This article explains earned value management and explores how the metric can be used to improve project and business processes.

More information

AACE International Recommended Practice No. 86R 14

AACE International Recommended Practice No. 86R 14 AACE International Recommended Practice No. 86R 14 VARIANCE ANALYSIS AND REPORTING TCM Framework: 9.1 Project Cost Accounting 9.2 Progress and Performance Measurement 10.1 Project Performance Assessment

More information

IST 302 : Project Cost Management

IST 302 : Project Cost Management IST 302 : Project Cost Management Project Cost Management : Why do we care? 1 Cost and Cost Management Cost: Cost Management: Project Cost Management Processes Cost Estimating Developing an estimate of

More information

Selftestengine..PMI-SP.270 questions PMI-SP. PMI Scheduling Professional

Selftestengine..PMI-SP.270 questions PMI-SP. PMI Scheduling Professional Selftestengine..PMI-SP.270 questions Number: PMI-SP Passing Score: 800 Time Limit: 120 min File Version: 5.1 PMI-SP PMI Scheduling Professional This study guides are so comprehensible that anyone can understand

More information

Chapter 7: Project Cost Management. Munawar moenawar@gmail.com

Chapter 7: Project Cost Management. Munawar moenawar@gmail.com Chapter 7: Project Cost Management Munawar moenawar@gmail.com Learning Objectives Understand the importance of project cost management. Explain basic project cost management principles, concepts, and terms.

More information

Unit 5: Cost Management (PMBOK Guide, Chapter 7)

Unit 5: Cost Management (PMBOK Guide, Chapter 7) (PMBOK Guide, Chapter 7) The questions on this topic have historically been more difficult than average for some exam takers because of unfamiliarity with some of the math. You will be responsible for

More information

Chapter 6. (PMBOK Guide)

Chapter 6. (PMBOK Guide) Chapter 6 Project Time Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: marajabi@ut.ac.irac ir Homepage:

More information

Project Management Institute (PMBOK 2000) PMP Preparation Worksheet

Project Management Institute (PMBOK 2000) PMP Preparation Worksheet Project Integration Management Processes required to ensure that the various elements of the project are properly coordinated to meet / exceed stakeholder expectations. Project Plan Development Other ning

More information

PROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited

PROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT WHAT DOES THE TIME MANAGEMENT AREA ATTAIN? Manages the project schedule to ensure timely completion of

More information

Certification Exam Objectives: PK0-003

Certification Exam Objectives: PK0-003 Certification Exam Objectives: PK0-003 INTRODUCTION The CompTIA Project + examination is designed for business professionals involved with projects. This exam will certify that the successful candidate

More information

Earned Value Formulae

Earned Value Formulae Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from http://www.mosaicprojects.com.au/techniques.html#earnedvalue

More information

THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH

THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH By Nghi M. Nguyen, Ph.D., PE, PMP. * INTRODUCTION The management of engineering projects

More information

Project Cost Management

Project Cost Management Project Cost Management Guide to Mathematical Questions PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Present

More information

Introduction to earn value management in Civil Engineering

Introduction to earn value management in Civil Engineering 3 rd World Conference on Applied Sciences, Engineering & Technology 27-29 September 2014, Kathmandu, Nepal Introduction to earn value management in Civil Engineering S. K. KAMANE, S. A. MAHADIK, A. C.

More information

Project Management. ZEUS Student Seminar on 14 th November 2003 by Riko Wichmann. Riko Wichmann, MPY Zeus Student Seminar - PM, 14.11.

Project Management. ZEUS Student Seminar on 14 th November 2003 by Riko Wichmann. Riko Wichmann, MPY Zeus Student Seminar - PM, 14.11. Project Management ZEUS Student Seminar on 14 th November 2003 by Riko Wichmann Riko Wichmann, MPY Zeus Student Seminar - PM, 14.11.2003 1 Project Management - Training Program - Project Scope Management

More information

Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition.

Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition. Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition. Errata for Chapter 7 (Replacement pages provided) Deleted up to a given point in time from the description

More information

PMI Lexicon of Project Management Terms

PMI Lexicon of Project Management Terms Project Management Institute PMI Lexicon of Project Management Terms Version 3.0 Published by: Project Management Institute, Inc. 14 Campus Boulevard Newtown Square, Pennsylvania 19073-3299 USA Phone:

More information

Project Management Using Earned Value

Project Management Using Earned Value Project Management Using Earned Value Third Edition Gary C. Humphreys Earned Value Management Consulting Training 2002, 2011, 2014 Gary C. Humphreys Humphreys & Associates, Inc. All rights reserved. No

More information

Project Time Management

Project Time Management Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please

More information

An introduction to Earned Value Analysis

An introduction to Earned Value Analysis An introduction to Earned Value Analysis Prepared by: Suketu Nagrecha, MBA, PMP, CNA March 16, 2002 Earned Value Analysis - 2 Abstract Earned value analysis is a method of performance measurement. Many

More information

Project Execution - PM Elements

Project Execution - PM Elements Performance Initial Release 1. Introduction to Project Tracking and Reviewing Once a project has advanced to the phase of performance, the consistent and constant flow of information on the true status

More information

PROJECT SCHEDULING AND TRACKING

PROJECT SCHEDULING AND TRACKING PROJECT SCHEDULING AND TRACKING PROJECT SCHEDULING AND TRACKING Software project scheduling is an activity that distributes estimated effort across the planned project duration by allocating the effort

More information

Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects. Abstract. Introduction

Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects. Abstract. Introduction Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects Puian Masudifar, Deputy CEO, VIRA Consulting Engineers Fereydoun Fardad, Aryana Project Management

More information

Project Time Management

Project Time Management Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please

More information

專 案 管 理 實 務 嘉 義 縣 政 府 學 分 班 : 管 理 實 務 專 題 2006 中 正 大 學 企 管 系 助 理 教 授 周 瑞 生

專 案 管 理 實 務 嘉 義 縣 政 府 學 分 班 : 管 理 實 務 專 題 2006 中 正 大 學 企 管 系 助 理 教 授 周 瑞 生 專 案 管 理 實 務 嘉 義 縣 政 府 學 分 班 : 管 理 實 務 專 題 2006 中 正 大 學 企 管 系 助 理 教 授 周 瑞 生 講 師 介 紹 > 學 歷 台 灣 大 學 學 士 台 灣 大 學 碩 士 美 國 德 州 大 學 奧 斯 汀 校 區 工 程 專 案 管 理 博 士 中 華 民 國 土 木 工 程 大 地 工 程 水 土 保 持 工 程 專 門 技 術 人 員 高

More information

PMP Exam Preparation Answer Key

PMP Exam Preparation Answer Key Chapter 2 Answers 1) d) They are all of equal importance unless otherwise stated The Triple Constraint of Project Management is that Scope, Time, and Cost are all equal unless otherwise defined as such.

More information

plans based on actual cost, schedule and technical progress of work [1, 9].

plans based on actual cost, schedule and technical progress of work [1, 9]. An Analysis on Resource Planning, Estimation and Tracking of Project by Earned Value Management SHAIK MOHAMMAD MASOOD, DEVANAND.R, HARSHA H.N PG Student, Department of Civil Engineering, G.E.C, Hassan

More information

EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT

EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT Assoc. Prof. Anca Mehedintu Ph. D University of Craiova Faculty of Economics and Business Administration Craiova, Romania Prof. Cerasela Pirvu

More information

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu Management, Sixth Edition Note: See the text itself for full citations. More courses at cie-wc.edu Understand the importance of project cost management Explain basic project cost management principles,

More information

Topics. Project plan development. The theme. Planning documents. Sections in a typical project plan. Maciaszek, Liong - PSE Chapter 4

Topics. Project plan development. The theme. Planning documents. Sections in a typical project plan. Maciaszek, Liong - PSE Chapter 4 MACIASZEK, L.A. and LIONG, B.L. (2005): Practical Software Engineering. A Case Study Approach Addison Wesley, Harlow England, 864p. ISBN: 0 321 20465 4 Chapter 4 Software Project Planning and Tracking

More information

PMP Exam Tips on Cost Management, Fourth Edition. Parallels between Cost and Time estimating:

PMP Exam Tips on Cost Management, Fourth Edition. Parallels between Cost and Time estimating: , Fourth Edition Parallels between Cost and Time estimating: There are strong parallels between cost estimating and time estimating so you should have experienced some déjà vu when you first read it. In

More information

PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING

PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING 03-23-05 Christine Green, PMI PMBOK and Estimating EDS, Delivery

More information

How To Manage A Project

How To Manage A Project Project Management Institute Practice Standard for EARNED VALUE MANAGEMENT Global Project Management Institute Practice Standard for Earned Value Management Practice Standard for Earned Value Management

More information

Earned Value Management Tutorial Module 8: Reporting. Prepared by:

Earned Value Management Tutorial Module 8: Reporting. Prepared by: Earned Value Management Tutorial Module 8: Reporting Prepared by: Module 8: Government Required Reports Welcome to Module 8. The objective of this module is to introduce you to Government required reports.

More information

Earned Value and Agile Reporting

Earned Value and Agile Reporting Earned Value and Agile Reporting Anthony Cabri, Mike Griffiths Quadrus Development Inc. Abstract This paper reviews the concepts of Earned Value Management established in traditional project management,

More information

Project Control with ProTrack

Project Control with ProTrack Project Control with ProTrack 1.0 (last update: 11/11/08) 1 Project Control with ProTrack by Mario Vanhoucke Professor at Ghent University and Vlerick Leuven Gent Management School (Belgium) Partner OR-AS

More information

EVM.01. Earned Value Analysis Why it Doesn't Work

EVM.01. Earned Value Analysis Why it Doesn't Work EVM.01 Earned Value Analysis Why it Doesn't Work Mr. Joseph A Lukas, PE CCE F or many companies looking to improve project performance, earned value analysis (EVA) seems a logical technique to use on projects

More information

COINS EVA Earned Value Analysis

COINS EVA Earned Value Analysis COINS EVA Earned Value Analysis Nigel Cope July 2006 Earned Value Analysis The most widely used method for performance measurement of projects Combines scope, cost and schedule patterns Informs project

More information

Simple Earned Value (Using MS Project 2010)

Simple Earned Value (Using MS Project 2010) Simple Earned Value (Using MS Project 2010) This document outlines a Simple Earned Value technique, a technique which sticks to a simple 0/100% Milestone approach with some Level of effort tasks maintained

More information

Chapter 3: Project Cost Management

Chapter 3: Project Cost Management Chapter 3: Project Cost Management Learning Objectives o Understand the importance of project cost management. o Explain basic project cost management principles, concepts, and terms. o Discuss different

More information

The Two Most Useful Earned Value Metrics: the CPI and the TCPI

The Two Most Useful Earned Value Metrics: the CPI and the TCPI PM WORLD TODAY SECOND EDITIONS JUNE 2009 Editor s note: Second Editions are papers that have been previously published that have continued relevance and deserve additional visibility. The paper below was

More information

Appendix D Glossary Of Terms

Appendix D Glossary Of Terms Appendix D Glossary Of Terms The notational style used in this glossary is to begin the definition of each defined term with a new paragraph beginning with the term in UPPERCASE. Any word or phrase used

More information

Develop Project Charter. Develop Project Management Plan

Develop Project Charter. Develop Project Management Plan Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs

More information

Estimating Cost at Completion - Judgment & EV Information

Estimating Cost at Completion - Judgment & EV Information Page 1 of 10 Estimating Cost at Completion - Judgment & EV Information Cost estimating is often called a "black art" and, too often, estimates are structured to fit some predetermined idea of a number

More information

L10: Budgeting and Cost Control. Olivier de Weck

L10: Budgeting and Cost Control. Olivier de Weck ESD.36 System Project Management + L10: Budgeting and Cost Control Instructor(s) Olivier de Weck Lecture 10 Oct. 11, 2012 System Project Management ESD.36 Framework Project Preparation Enterprise has chosen

More information

Assignment 2: Microsoft Project Toolset. Eric Palmer & Mahindra Bheodari. Kennesaw State University. IS 8100 Spring 2015

Assignment 2: Microsoft Project Toolset. Eric Palmer & Mahindra Bheodari. Kennesaw State University. IS 8100 Spring 2015 Assignment 2: Microsoft Project Toolset 1 Assignment 2: Microsoft Project Toolset Eric Palmer & Mahindra Bheodari Kennesaw State University IS 8100 Spring 2015 Assignment 2: Microsoft Project Toolset 2

More information

Integration Mgmt / Initiating Process Group 4.1 Develop Project Charter

Integration Mgmt / Initiating Process Group 4.1 Develop Project Charter 1 Mgmt / Initiating Process Group 4.1 Develop Project Charter Project statement of work Business case Agreements Facilitation techniques Project charter 26/02/2013 18:23:36 1 2 Mgmt / Planning Process

More information

Software Project Scheduling. - Introduction - Project scheduling - Task network - Timeline chart - Earned value analysis

Software Project Scheduling. - Introduction - Project scheduling - Task network - Timeline chart - Earned value analysis Software Project Scheduling - Introduction - Project scheduling - Task network - Timeline chart - Earned value analysis Eight Reasons for Late Software Delivery An unrealistic deadline established by someone

More information

PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION

PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION PMP SAMPLE QUESTIONS http://www.tutorialspoint.com/pmp-exams/pmp_sample_questions_set2.htm Copyright tutorialspoint.com BASED ON PMBOK 5TH EDITION Here are 200 more objective type sample questions and

More information

Project Time Management

Project Time Management Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.

More information

FRA s Earned Value Management System Overview for Self Assessment Surveillance March 07-09, 2011

FRA s Earned Value Management System Overview for Self Assessment Surveillance March 07-09, 2011 FRA s Earned Value Management System Overview for Self Assessment Surveillance March 07-09, 2011 Dean Hoffer Head, Office of Project Management Oversight Outline EVMS History at the Lab FRA EVMS Documents

More information

Earned Value Management Guidelines

Earned Value Management Guidelines Effective Date: April 21, 2009 Status: Revision 1 Supersedes: NA Document Owner: Director, Environmental and Engineering Program Introduction This paper provides guidance and recommendations for the application

More information

Project Management: Tracking Progress and Earned Value with MS Project 2003

Project Management: Tracking Progress and Earned Value with MS Project 2003 Project Management: Tracking Progress and Earned Value with MS Project 2003 Project Planning Suppose you have been assigned a project to construct a website in a certain time frame and given a certain

More information

Agile and Earned Value. A white paper. October 2013. Author Stephen Jones, Sellafield Ltd

Agile and Earned Value. A white paper. October 2013. Author Stephen Jones, Sellafield Ltd Agile and Earned Value A white paper October 2013 Author Stephen Jones, Sellafield Ltd This document is a whitepaper produced by the APM Planning, Monitoring and Control SIG. It represents the thoughts

More information

Procurement Management S# What? Formula Additional Notes CPPC CPFF CPAF CPIF T&M FPEPA FPAF FPIF FFP

Procurement Management S# What? Formula Additional Notes CPPC CPFF CPAF CPIF T&M FPEPA FPAF FPIF FFP PMP Formulae & Tips Cheat Sheet P a g e Integration Management Develop Project Charter process Project Selection Methods (>> Benefit Measurement Methods >> Economic Models -7) Present Value (PV) FV The

More information

Quick Reference Guide Interactive PDF Project Management Processes for a Project

Quick Reference Guide Interactive PDF Project Management Processes for a Project Project Processes for a Project Click the Knowledge Area title (below and left in blue underline) to view the details of each Process Group. Project Process Groups and Knowledge Areas Mapping Project Process

More information

Project Management Glossary

Project Management Glossary Project Management Glossary THE VOCABULARY OF ACHIEVEMENT RON BLACK THE MENTOR GROUP WWW.RONBLACK.COM 800-381-8686 This glossary is an excerpt from Ron Black s book, The Complete Idiot s Guide to Project

More information

Project Management for Scientists

Project Management for Scientists Project Management for Scientists Cost & Schedule Estimates Christoph U. Keller, c.u.keller@uu.nl Sterrekundig Instituut Utrecht Utrecht University www.astro.uu.nl/~keller Outline Resource Assignments

More information

Lecture Slides for Managing and Leading Software Projects. Chapter 8: Measuring and Controlling Work Processes

Lecture Slides for Managing and Leading Software Projects. Chapter 8: Measuring and Controlling Work Processes Lecture Slides for Managing and Leading Software Projects Chapter 8: Measuring and Controlling Work Processes developed by Richard E. (Dick) Fairley, Ph.D. to accompany the tet Managing and Leading Software

More information

Earned Value Management System Description

Earned Value Management System Description LCLS Project Management Document # 1.1-015 Project Management Revision 3.0 Earned Value Management System Description Patricia Mast (LCLS Project Controls Manager) Signature Date Mark Reichanadter (LCLS

More information

Unit 4: Time Management (PMBOK Guide, Chapter 6)

Unit 4: Time Management (PMBOK Guide, Chapter 6) (PMBOK Guide, Chapter 6) The questions on this topic focus heavily on scheduling techniques, network diagrams, Gantt charts, the critical path, compressing the schedule, PERT, and float. You may or may

More information

IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques

IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques Kym Henderson Former Education Director, PMI Sydney Chapter March 2003 to March 2007 Kym.Henderson@froggy.com.au

More information

A DIFFERENT KIND OF PROJECT MANAGEMENT

A DIFFERENT KIND OF PROJECT MANAGEMENT SEER for Software SEER project estimation and management solutions improve success rates on complex software projects. Based on sophisticated modeling technology and extensive knowledge bases, SEER solutions

More information

PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >

PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name

More information

CVR/IT Consulting LLC

CVR/IT Consulting LLC 2011 CVR/IT Consulting LLC All Rights Reserved 1 www.cvr-it.com info@cvr-it.com Overview Easy Earned Value CVR/IT Consulting LLC 2011 CVR/IT Consulting LLC All Rights Reserved 2 Introduction Earned Value

More information

Summary of GAO Cost Estimate Development Best Practices and GAO Cost Estimate Audit Criteria

Summary of GAO Cost Estimate Development Best Practices and GAO Cost Estimate Audit Criteria Characteristic Best Practice Estimate Package Component / GAO Audit Criteria Comprehensive Step 2: Develop the estimating plan Documented in BOE or Separate Appendix to BOE. An analytic approach to cost

More information

Basic Concepts of Earned Value Management (EVM)

Basic Concepts of Earned Value Management (EVM) Basic Concepts of Earned Value Management (EVM) This article provides an introduction to the basic concepts of earned value management (EVM), from initial project planning through execution including data

More information

Tracking Software Development Progress with Earned Value and Use Case Point

Tracking Software Development Progress with Earned Value and Use Case Point ISBN 978-952-5726-06-0 Proceedings of the 2009 International Workshop on Information Security and Application (IWISA 2009) Qingdao, China, November 21-22, 2009 Tracking Software Development Progress with

More information

Chapter 5: Project Cost Management

Chapter 5: Project Cost Management Chapter 5: Project Cost Management 1 Learning Objectives Understand the importance of good project cost management Explain basic project cost management principles, concepts, and terms Describe how resource

More information

Project Scheduling & Tracking

Project Scheduling & Tracking Project Scheduling & Tracking Traditional Techniques: Work Breakdown Structure (WBS) Gantt Charts Precedence Diagrams Earned Value Planning It is the mark of an instructed mind to rest satisfied with the

More information

PROJECT COST MANAGEMENT

PROJECT COST MANAGEMENT PROJECT COST MANAGEMENT http://www.tutorialspoint.com/pmp-exams/project_cost_management.htm Copyright tutorialspoint.com Here is a list of sample questions which would help you to understand the pattern

More information

Assessing Schedule Performance with Earned Value

Assessing Schedule Performance with Earned Value FEATURED PAPER OCTOBER 2007 Time Is Up: Assessing Schedule Performance with Earned Value By Robert Van De Velde Time drives projects. Quick and accurate evaluation of schedule performance is crucial. Quantitative

More information

CLARITY PPM TIPS, TRICKS, and TERMINOLOGY

CLARITY PPM TIPS, TRICKS, and TERMINOLOGY CLARITY PPM TIPS, TRICKS, and TERMINOLOGY Clarity PPM Knowledge Sharing Series Helping the Clarity PPM Community Members Benefit from Best Practice TABLE OF CONTENTS 1 OVERVIEW... 3 2 OVERVIEW PAGE...

More information

Chapter 7: Project Cost Management. Information Technology Project Management, Fourth Edition

Chapter 7: Project Cost Management. Information Technology Project Management, Fourth Edition Chapter 7: Project Cost Management Information Technology Project Management, Fourth Edition Learning Objectives Understand the importance of project cost management. Explain basic project cost management

More information

Project Cost Management

Project Cost Management Project Skills Team FME www.free-management-ebooks.com ISBN 978-1-62620-982-9 Copyright Notice www.free-management-ebooks.com 2014. All Rights Reserved ISBN 978-1-62620-982-9 The material contained within

More information

Project Cost Management

Project Cost Management Project Cost Management Martin Pazderka martin.pazderka@inso.tuwien.ac.at INSO - Industrial Software Institut für Rechnergestützte Automation Fakultät für Informatik Technische Universität Wien Agenda

More information

Project Time Management

Project Time Management Project Academy Series Project Time Management 01/22/2015 01/23/2015 Welcome and Introductions Ramaswamy Adisesh: Data Processing Manager III California Project Management Office Department of Technology

More information

How to successfully manage your mega-project

How to successfully manage your mega-project BUILDING, CONSTRUCTION & REAL ESTATE How to successfully manage your mega-project Part II Stakeholder communication and project controls integration kpmg.com 2 Building, Construction & Real Estate How

More information

Predicting progress on your project

Predicting progress on your project www.nonsuch.co info@nonsuch.co Predicting progress on your project - using Lego bricks to understand Earned Value September 4 PM Conference 2015 Presented by Youssef Mourra Director, Principal Consultant

More information

Project Cost Management. Richard Boser

Project Cost Management. Richard Boser Project Cost Management Richard Boser Project Cost Management Introduction Course Objectives Upon completing today s activities you will be knowledgeable of tools and techniques to: Allocate overall costs

More information

Project Integration Management

Project Integration Management Integration Initiating ning Executing Monitoring & Controlling Closing 4.1 Develop Charter Statement Of Work Business Case 4.2 Develop 4.3 Direct and Manage Work 4.4 Monitor and Control Work 4.5 Perform

More information

Forecasting Project Schedule Completion by Using Earned Value Metrics

Forecasting Project Schedule Completion by Using Earned Value Metrics Forecasting Project Schedule Completion by Using Earned Value Metrics Ing. Stephan Vandevoorde Sr. Project Manager Fabricom Airport Systems svv@fabricom.be 1 Agenda Introduction Schedule performance indicators

More information

pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development

More information

Input, Output and Tools of all Processes

Input, Output and Tools of all Processes 1 CIS12-3 IT Project Management Input, Output and Tools of all Processes Marc Conrad D104 (Park Square Building) Marc.Conrad@luton.ac.uk 26/02/2013 18:22:06 Marc Conrad - University of Luton 1 2 Mgmt /

More information

The Plan s Journey From Scope to WBS to Schedule

The Plan s Journey From Scope to WBS to Schedule The Plan s Journey From Scope to WBS to Schedule Presented by: Rick Clare, CBAP, PMP, OCP, CSM PM Centers USA, LLC. 2013 Company Background Consulting and Training (Virtual, Public and Private Training)

More information