Mitigation of Transformer Inrush Current Associated with DER Facilities connected on the Distribution Grid

Size: px
Start display at page:

Download "Mitigation of Transformer Inrush Current Associated with DER Facilities connected on the Distribution Grid"

Transcription

1 Mitigation of Transformer Inrush Current Associated with DER Facilities connected on the Distribution Grid Marc Lacroix Eng, M. Eng, Senior Member IEEE Pierre Taillefer Eng, Member IEEE VIZIMAX Inc. Montréal, Canada André Mercier Eng IREQ Hydro-Québec Montréal, Canada Abstract Integration of Distributed Energy Resources (DER) to the distribution system brings technical challenges due to the inrush current resulting from the energization of power transformer. Besides impacting power quality, transients may cause undesired protection tripping. This paper compares different techniques used to mitigate these transients. It also presents results from research carried out on Hydro-Québec Research Institute s distribution test line (IREQ). Outcomes of additional tests using Gang Operated (GO) circuit breakers (CB) and Controlled Switching Device (CSD) are also presented. This approach solves the problem of the re-energization of a windmill on a live windfarm, in order to minimize transients and sympathetic interactions between the transformers in the DER facility. Since the CS solution virtually does not require any installation footprint, it has the advantage of being easily adapted to the existing switchgear designs integrated at the base of the wind towers. Index Terms--Distributed Energy Resources, Controlled switching, pre-insertion resistors, inrush current, Independent Pole Operated circuit breaker, Gang Operated circuit breaker. I. INTRODUCTION Integration of Distributed Energy Resources (DER) to the distribution grid involves major technical challenges for the DSO and utilities, due to the inrush current resulting from the energization of plant power transformer from the grid. Besides impacting power quality, transients may cause undesired protection tripping. Hydro-Québec has defined a list of requirements to guide the connection of DER to the distribution network [1]. Among these requirements, we may find design criteria and test procedures for harmonics content, load unbalance, transients and rapid voltage change of the installation of an industrial customer or energy producer. In these specifications, one of the requirements is that the installations must not cause rapid voltage variation higher than 4.75% on the distribution network. Consequently, energization of DER transformers from the grid is very critical since excessive inrush current is a main cause of disturbances. On a weak grid, it is practically impossible to meet these design criteria without using appropriate inrush current mitigation. In this respect, Hydro-Québec has started in 2000 the deployment of CS for power transformers in hydro-electric power plants and critical high voltage substations, including those involved in network restoration after a blackout. The interconnection of small DER facilities (such as wind farms) to the distribution network involves the same technical issues as in the transmission system. Since inrush current can reach up to 12 times the rated current, mitigation techniques should put in place to avoid feeder s breaker tripping. For example, after a feeder circuit breaker tripping, the wind farm is disconnected and should not reconnect immediately after the restoration of the power on the distribution line. According to the standards, the producer should wait for at least 5 minutes after the presence of a "normal" voltage. The DER facility unloaded power transformer must then be reenergized with a mitigation technique to limit inrush current and transient overvoltage on the distribution network. In anticipation of the addition of 151 MW of power on their 25kV distribution network in the next few years, Hydro- Québec has mandated its Research Institute (IREQ) to study different transformer energization techniques in order to mitigate the inrush current. Among possible solutions, three different methods were evaluated at the IREQ distribution test network facilities and the testing results are presented here. The complete results of the study are presented in the referenced document [2]. II. COMPARISON OF INRUSH CURRENT MITIGATION TECHNIQUES The first transformers energization tests conducted by IREQ were done to characterize the distribution of inrush currents while energizing the transformer directly from the networks without using any mitigation technique. Later, these results were used as a reference to compare the three different tested inrush current mitigation techniques approaches: 1. Pre insertion resistor technique: as shown in figure 1, a 20 Ohms resistor is temporarily connected in series with the load in order to limit the initial inrush current.

2 This resistor is then shorted by the main CB to enable the full load current in the transformer. For power transformers applications, the CSD controls the closing moment of the CB according to the residual flux remaining in its core and resulting from previous deenergization. Using an IPO CB, this technique almost eliminates the inrush current and the associated voltage disturbances on the network. The residual flux in the transformer core is calculated by computing the mathematical integral of the voltage measured during the transformer deenergization on either the primary or secondary side of the transformer. III. Figure 1. Current inrush mitigation with pre insertion resistor 2. Energization transformers: The second approach also uses a series impedance current limiting technique, but this time two low cost 25kVA distribution transformers mounted back-to-back are used as smoothing inductors (figure 2). The equivalent impedance of these transformers was 330 Ohm. COMPARING THE MITIGATION TECHNIQUES The first transformers energization tests were done to characterize the distribution of inrush currents while energizing the transformer directly from the networks without using any mitigation technique (figure 4). In total, 51 energization tests were made with a 750-kVA distribution transformer, and 71 more tests were made with the addition of a 1MVA transformers connected in parallel for a total capacity of 1.75MVA. The purpose of adding a transformer in parallel was to verify if the inrush current would be proportional to the total capacity of the DER facility. Figure 4. Test bench for the transformer energization tests Figure 2. Current inrush mitigation using energization transformers 3. Controlled Switching Device integration (CSD): Since a few decades, this technique has been successfully used for switching of reactive devices, power transformers and transmission lines on HV power systems. Figure 3. Current inrush mitigation with CSD Comparing the average and maximum inrush current to the transformer capacity, it could be conservatively concluded from the tests that the maximum inrush current of an installation is proportional to the installed transformer capacity. During the subsequent tests, 25 to 40 energization tests were done on the 750kVA power transformer using the 3 inrush mitigation techniques previously described: 1. Gang operated CB equipped with pre-insertion resistor. 2. Gang operated CB with back-to-back energization transformers (equivalent to smoothing inductors). 3. Independent Pole Operated CB equipped with a Controlled Switching Device. Figure 5 summarizes the average value of the maximum inrush current expressed in Per Unit (PU) for the various mitigation techniques. During the tests, it has been observed that the best inrush current mitigation technique is using an independent pole operated CB equipped with a CSD that takes into account the residual flux. For the series impedance techniques (pre-insertion resistors and energization

3 transformer), the conclusion was that the higher the series impedance is, the better the inrush current mitigation is. windmills. An alternate solution was developed to overcome these problems. Figure 5. Comparison of the average of maximum inrush current (in pu) Figure 6 illustrates the cumulative probability distribution function of the inrush current for the various tests that were performed. It can be seen that only the CSD technique allows an almost complete elimination of the inrush current at all time. Using the other techniques, the inrush current was relatively high 50% of the time. Figure 6. Cumulative probability distribution function of the inrush current (comparison) The study conducted by IREQ did not take into account the situation where a windmill from a wind farm is returned to service after a period of maintenance (figure 7). Although the capacity of a single windmill transformer does not seem to be enough to cause a problem due to the limited capacity of short circuit, the rapid voltage variation at the utility interconnection point may exceed the limits established in the requirement document. The presence of sympathetic interactions between the transformers during the energization may result in further aggravation of the problem [5]. However, these phenomena can be controlled by the temporary de-energization of the wind farm in low wind speed conditions when returning the equipment in service. This technique may involve the residual flux equalization of each wind tower transformer before reenergizing the entire farm, which may result in a rather complex operation when there are a large number of Figure 7. Re-energization of a single transformer after maintenance IV. USING CSDS WITH GANG OPERATED CB The best solution for wind farms would be to mitigate the inrush current to an acceptable level at each windmill, solving both the re-energization of a single tower and the interconnection of a windmill at the grid voltage. However, due to the limited availability and higher cost of IPO CBs at medium voltage, an option would be to use a GO CB equipped with a CSD at each windmill of the facility. Since the CSD is compact, this solution has the advantage of being easily adapted to the existing switchgear designs integrated at the base of the windmill. Since there is an optimum GO CB closing moment that produces the minimum obtainable inrush current for each residual flux pattern in the transformer core [3][6], this CS technique requires the measurement of the residual flux in each phase of the windmill power transformer. It can be calculated by computing the integral of the transformer voltage during its de-energization [3] [4], either using an existing potential transformers or capacitive/resistive voltage divider sensor. Although that controlled opening of the CB can set a known residual flux pattern of +ϕ, 0, - ϕ that eliminates the transformer inrush current using a GO CB [1][3], it is almost impossible to control at all time the opening of the CB or the grid voltage loss on the distribution grid. Consequently, when a wind tower is de-energized, the residual flux pattern in the transformer core will always vary according to the transformer de-energization conditions. The transformer re-energization technique must therefore mitigate the inrush current at all time, no matter what is the residual flux pattern. In order to test this integrated CSD concept, additional testing was carried out on a 1 MVA power transformer (Dyn5) operated at 20kV using a GO vacuum CB, a configuration that is typically used at the base of small wind turbines. During these tests, the transformer was de-energized by controlling the CB opening with 30 degrees steps in order to produce different residual flux patterns in the transformer core. The CB was then closed back at the optimum electrical target corresponding to that flux pattern calculated by the CSD (figure 8).

4 During the tests conducted with the CSD, it was observed that for any transformer residual flux pattern, the maximum inrush current was 2.2 PU with an average of 1.5 PU. It could also be observed that the maximum inrush current in the 3 phases is in the same magnitude range regardless of the residual flux pattern. Figure 8. Inrush current as a function of the CB opening angle To establish a comparison, uncontrolled energization tests were also conducted using the same transformer by closing the CB at random time. During the tests, the maximum and minimum recorded inrushes current were 5.8 and 4.6 PU respectively, compared to 2.2 and 1.1 PU using the CSD mitigation technique (Figure 9). Figure 10. Inrush current as a function of the CB opening angle The main objective of the additional tests was not only to establish a comparison of the inrush current with/without using a CSD, but also to measure the effect of the closing angle deviation from the theoretical optimum target point. This target deviation is mainly caused by the mechanical repeatability of the CB, and the variation of the pre-arcing time when switching the 3 phases simultaneously with the CB. During these tests, the CB was repeatedly opened at an angle of 30 degrees to produce a known residual flux pattern in the transformer core, and both random and controlled closing of the CB were done to measure the resulting power transformer inrush current (figure 11). From these tests, it can be observed that a CB timing deviation of ±20 (1ms at 60Hz) would not produce a significant change in the resulting maximum inrush current. As an additional conclusion, the CSD technique offers stable inrush current mitigation and the mechanical repeatability of the CB to a certain extent would not produce excessive inrush current. Figure 9. Inrush current as a function of the CB opening angle As an initial conclusion from these tests, the use of a CSD with a GO CB offers a comparable inrush current reduction as provided by the energization transformer technique (Figure 2). Since it virtually does not require any installation footprint, this solution has the advantage of being easily adapted to the existing windmill switchgear designs. In order to verify the initial results, additional tests were carried out on a 21 MVA/66kV dry type power transformer (Yyn0) using a CSD controlling a GO SF 6 circuit breaker. During the tests, the maximum measured inrush current with random energization of the power transformer was 4.2 PU, compared with 1.3 PU with the CS technique. Figure 10. Inrush current as a function of the CB target angle deviation

5 V. CONCLUSION The tests conducted at IREQ research institute led to the conclusion that the use of series impedance mitigation techniques is simple but more expensive due to extra equipment and related installation, while reducing inrush current by a relatively small factor. However, the CS technique accounting for the transformer residual flux offers the best possible inrush current reduction, allowing DER facilities to meet stringent rapid voltage changes design criteria imposed by the grid code. Combined with an IPO CB, the CSD solution will almost eliminate the power transformer energization inrush current, making it the ideal switching solution at the HV grid interconnection point. When involving the interconnection of a wind farm on the MV distribution grid, the optimum solution is to mitigate the inrush current to an acceptable level at each of each windmill. This approach solves the re-energization of a single tower on a live farm, both minimizing the inrush current impacts on the grid and the sympathetic interactions between the transformers in the DER facility. However, due to the limited availability and higher cost of IPO CBs at medium voltage, this solution cannot be economically implemented in existing designs of wind tower switchgears. In this paper, an inrush current mitigation technique solution based on the use of a simultaneous pole operated VCB equipped with a CSD has been successfully tested on a 1MVA@20kV Dyn5 power transformer. During these tests, the maximum inrush current has been reduced by 2.6 times compared to random energization of the power transformer. It was also observed that the maximum inrush current in the 3 phases is in the same magnitude range regardless of the residual flux pattern. Additional testing has also been conducted with an SF6 GO CB equipped with a CSD on a 21 MVA@66kV Yyn0 dry type power transformer. These tests have not only shown similar inrush current mitigation (1.3 PU compared to 4.2 PU with random energization), but also demonstrated that the CS technique offer stable inrush current mitigation despite the CB closing time variation due to its mechanical repeatability. These testing results show an inrush mitigation that is in the same range as those obtained using a gang operated CB with back-to-back energization transformers initially tested at IREQ and presented here. Since it is compact, the CS solution can be easily adapted to the existing switchgear designs integrated at the base of the windmill. REFERENCES [1] Hydro-Québec, Vice-présidence réseau, "Exigences techniques relatives à la protection et à l émission de perturbations des installations de clients raccordées au réseau de distribution d'hydro-québec", March 2004 [2] Abbey, C. and Taillefer, P., "Mitigation of Transformer Inrush Current Associated with DER Facilities" PAC World Conference, Raleigh, USA, 2014 [3] Brunke, JH and Frohlich KJ, "Elimination of inrush currents by controlled switching. I. Theoretical considerations," IEEE Transactions on Power Delivery, vol.16, no.2, pp , April [4] A. Mercier, E. Portales, Y. Filion, and A. Salibi, Transformer Controlled Switching taking into account the core residual flux, a real case study, CIGRÉ Conference 2002, # [5] Rioual, M., & Sow, M. (2008). Study of the Sympathetic Interactions When Energizing Transformers for Wind-Farms: Description of the Phenomena Involved and Determination of the Stresses during their Energization. In 7th International Workshop on Large-Scale Integration of Wind Power into Power Systems and Transmission Networks for Offshore Wind Farms. Madrid, Spain. [6] Nishiwaki, S., Koshizuka, T., Saito, M. and Sato, Y. Residual Magnetic Fluxes in the Iron Core of Neutral Ungrounded Transformer That Are Required to Be Known for Controlled Switching, The International Conference on Electrical Engineering (2008)

EMTP STUDIES PERFORMED TO INSERT LONG AC CABLES IN THE FRENCH GRID

EMTP STUDIES PERFORMED TO INSERT LONG AC CABLES IN THE FRENCH GRID Tension (kv) Impedance (Ohms) EMTP STUDIES PERFORMED TO INSERT LONG AC CABLES IN THE FRENCH GRID frequency (Hz) Simon DESCHANVRES Yannick VERNAY RTE, CNER, Substations Department t (ms) EMTP-RV Users Group

More information

Product brochure Multi Functional Switchgear PASS M00 72.5 kv Flexible and compact switchgear solutions for windfarms

Product brochure Multi Functional Switchgear PASS M00 72.5 kv Flexible and compact switchgear solutions for windfarms Product brochure Multi Functional Switchgear PASS M00 72.5 kv Flexible and compact switchgear solutions for windfarms The future of Wind Farms As offshore wind farms move towards deploying higher capacity

More information

Typical Data Requirements Data Required for Power System Evaluation

Typical Data Requirements Data Required for Power System Evaluation Summary 66 Carey Road Queensbury, NY 12804 Ph: (518) 792-4776 Fax: (518) 792-5767 www.nepsi.com sales@nepsi.com Harmonic Filter & Power Capacitor Bank Application Studies This document describes NEPSI

More information

International Review of Grid Connection Requirements related with Voltage Dips for Wind Farms

International Review of Grid Connection Requirements related with Voltage Dips for Wind Farms International Review of Grid Connection Requirements related with Voltage Dips for Wind Farms J. A. Fuentes, M. Cañas, A. Molina, E. Gómez, F. Jiménez Abstract In this work, the Spanish grid code is compared

More information

Measurement, Modeling and Simulation of Capacitor Bank Switching Transients

Measurement, Modeling and Simulation of Capacitor Bank Switching Transients Measurement, Modeling and Simulation of Capacitor Bank Switching Transients Mirza Softić*, Amir Tokić**, Ivo Uglešić*** *Kreka - Dubrave e, Dubrave, Bosnia and Herzegovina (e-mail: softic_mirza@yahoo.com).

More information

THE PER-UNIT SYSTEM. (2) The per-unit values for various components lie within a narrow range regardless of the equipment rating.

THE PER-UNIT SYSTEM. (2) The per-unit values for various components lie within a narrow range regardless of the equipment rating. THE PER-UNIT SYSTEM An interconnected power system typically consists of many different voltage levels given a system containing several transformers and/or rotating machines. The per-unit system simplifies

More information

Generator Stator Protection, under/over voltage, under /over frequency and unbalanced loading. Ramandeep Kaur Aujla S.NO 250447392

Generator Stator Protection, under/over voltage, under /over frequency and unbalanced loading. Ramandeep Kaur Aujla S.NO 250447392 1 Generator Stator Protection, under/over voltage, under /over frequency and unbalanced loading By Ramandeep Kaur Aujla S.NO 250447392 ES 586b: Theory and applications of protective relays Department of

More information

MEDIUM AND HIGH VOLTAGE CAPACITORS, CAPACITOR BANKS AND SYSTEMS

MEDIUM AND HIGH VOLTAGE CAPACITORS, CAPACITOR BANKS AND SYSTEMS MEDIUM AND HIGH VOLTAGE CAPACITORS, CAPACITOR BANKS AND SYSTEMS Meher Capacitors offers reliable and innovative products and solutions in the fields of Reactive Power Compensation, Power Quality and Energy

More information

General Validation Test Program for Wind Power Plants Connected to the Hydro-Québec Transmission System

General Validation Test Program for Wind Power Plants Connected to the Hydro-Québec Transmission System General Validation Test Program for Wind Power Plants Connected to the Hydro-Québec Transmission System Direction Planification des actifs et expertise de transport February 2011 TABLE OF CONTENTS 1. CONDUCTING

More information

SURVEY OF HARMONIC DISTORTION IN LV AND MV NETWORKS: RESULTS AND CORRECTIVE STRATEGIES

SURVEY OF HARMONIC DISTORTION IN LV AND MV NETWORKS: RESULTS AND CORRECTIVE STRATEGIES SURVEY OF HARMONIC DISTORTION IN LV AND MV NETWORKS: RESULTS AND CORRECTIVE STRATEGIES E Bompard*, E Carpaneto*, R Napoli*, P Ribaldone**, C Vercellino** * Dipartimento di Ingegneria Elettrica Industriale,

More information

Context: significant penetration of DG = increased risks for system security

Context: significant penetration of DG = increased risks for system security Distributed Generation: towards an effective contribution to power system security IEEE Tampa GM 2007: Panel on Impact of Dispersed Generation on Power System structure & security Bruno Meyer Outline Context:

More information

SYNCHRONOUS MACHINES

SYNCHRONOUS MACHINES SYNCHRONOUS MACHINES The geometry of a synchronous machine is quite similar to that of the induction machine. The stator core and windings of a three-phase synchronous machine are practically identical

More information

Line Reactors and AC Drives

Line Reactors and AC Drives Line Reactors and AC Drives Rockwell Automation Mequon Wisconsin Quite often, line and load reactors are installed on AC drives without a solid understanding of why or what the positive and negative consequences

More information

System Grounding and Ground-Fault Protection Methods for UPS-Supplied Power Systems

System Grounding and Ground-Fault Protection Methods for UPS-Supplied Power Systems System Grounding and Ground-Fault Protection Methods for -Supplied Power Systems Bill Brown, P.E., Square D Critical Power Competency Center 1. INTRODUCTION The use of solid grounding for -supplied power

More information

ESB Networks Response. ERGEG Consultation. Voltage Quality Regulation in Europe

ESB Networks Response. ERGEG Consultation. Voltage Quality Regulation in Europe NETWORKS ESB Networks Response to ERGEG Consultation on Voltage Quality Regulation in Europe Date: 22 February 2007 Distribution System Operator ESB Networks Page 1 of 12 Contents 1.0 INTRODUCTION...3

More information

30 ms High Speed Transfer System (HSTS) Product Description

30 ms High Speed Transfer System (HSTS) Product Description 30 ms High Speed Transfer System (HSTS) Product Description 2 30 ms High Speed Transfer System (HSTS) Product Description Content Page 1 General 5 1.1 Description of the 30 ms high speed transfer system

More information

SPECIFICATION COG-2007

SPECIFICATION COG-2007 Cleco Power LLC SPECIFICATION COG-2007 FOR PARALLEL OPPERATION OF CUSTOMER-OWNED GENERATION ON CLECO S ELECTRICAL SYSTEM Revised: March 7, 2014 CONTENTS ITEM NO. TITLE PAGE NO. 1.0 Scope 3 2.0 Policy On

More information

What Matters for Successful Integration of Distributed Generation

What Matters for Successful Integration of Distributed Generation What Matters for Successful Integration of Distributed Generation Thomas Ackermann Energynautics GmbH, Germany t.ackermann@energynautics.com Expert User of DIgSILENT PowerFactory for Power Systems Studies

More information

CAPACITOR BANK TESTING SWP

CAPACITOR BANK TESTING SWP 1. PURPOSE AND SCOPE The purpose of this Standard Work Practice (SWP) is to standardise and prescribe the method for testing Capacitor Banks including capacitors, tuning reactors and inrush limiting reactors.

More information

Application of Four-Pole Circuit Breakers within Data Centers

Application of Four-Pole Circuit Breakers within Data Centers Application of Four-Pole Circuit Breakers within Data Centers December 2013/AT324 by Frank Waterer, Fellow Engineer, Schneider Electric Engineering Services Make the most of your energy SM Revision #1

More information

Chapter 1. Network Structures

Chapter 1. Network Structures Chapter 1 Network Structures Definition Standard IEC 60038 defines voltage ratings as follows: Low voltage (): for a phase-to-phase voltage of between 100 V and 1,000 V, the standard ratings are: 400 V

More information

100% Stator Ground Fault Detection Implementation at Hibbard Renewable Energy Center. 598 N. Buth Rd 3215 Arrowhead Rd

100% Stator Ground Fault Detection Implementation at Hibbard Renewable Energy Center. 598 N. Buth Rd 3215 Arrowhead Rd 100% Stator Ground Fault Detection Implementation at Hibbard Renewable Energy Center Introduction Roger Hedding Steven Schoenherr, P.E. ABB Inc. Minnesota Power 598 N. Buth Rd 3215 Arrowhead Rd Dousman,

More information

How To Choose A Transformer

How To Choose A Transformer Consider open loop MV network as an example source 1 source 2 NC NC NC or NO main MV switchboard A B Detail design of substation NC NC NC NO NC NC switchboard 1 switchboard 2 switchboard 3 MV MV MV LV

More information

VOLTAGE CONTROL IN DISTRIBUTION SYSTEMS AS A LIMITATION OF THE HOSTING CAPACITY FOR DISTRIBUTED ENERGY RESOURCES

VOLTAGE CONTROL IN DISTRIBUTION SYSTEMS AS A LIMITATION OF THE HOSTING CAPACITY FOR DISTRIBUTED ENERGY RESOURCES VOLTAGE CONTROL IN DISTRIBUTION SYSTEMS AS A LIMITATION OF THE HOSTING CAPACITY FOR DISTRIBUTED ENERGY RESOURCES C. Schwaegerl*, M.H.J. Bollen, K. Karoui #, A. Yagmur + *Siemens AG, # Tractebel STRI AB

More information

For a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V - 690 V - 1000 V (at 50 Hz)

For a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V - 690 V - 1000 V (at 50 Hz) 24 1. NETWORK CONFIGURATIONS definition Standard IEC 38 defines voltage ratings as follows: - Low voltage () For a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V - 690

More information

Earth Fault Detection Basics in Theory

Earth Fault Detection Basics in Theory Earth Fault Detection Basics in Theory Author: Dipl.-Ing. Ingo Kühnen Woodward Power Solutions Krefelder Weg 47 47906 Kempen, Germany Kempen, 16.04.2010 Earth_Fault_Detection_20100416.doc page 1 1. Star

More information

7. Reactive energy compensation

7. Reactive energy compensation 593 7. Reactive energy compensation 594 7. REACTIVE ENERGY COMPENSATION Reactive energy compensation is an important element for reducing the electricity bill and improving the quality of the electrical

More information

Integration of Distributed Generation in the Power System. IEEE Press Series on Power Engineering

Integration of Distributed Generation in the Power System. IEEE Press Series on Power Engineering Brochure More information from http://www.researchandmarkets.com/reports/2171489/ Integration of Distributed Generation in the Power System. IEEE Press Series on Power Engineering Description: A forward

More information

TECHNICAL INTERCONNECTION REQUIREMENTS FOR DISTRIBUTED GENERATION. Micro Generation & Small Generation, 3-phase, less than 30 kw

TECHNICAL INTERCONNECTION REQUIREMENTS FOR DISTRIBUTED GENERATION. Micro Generation & Small Generation, 3-phase, less than 30 kw TECHNICAL INTERCONNECTION REQUIREMENTS FOR DISTRIBUTED GENERATION Micro Generation & Small Generation, 3-phase, less than 30 kw i COPYRIGHT 2010 HYDRO ONE NETWORKS INC. ALL RIGHTS RESERVED ii LIMITATION

More information

Size template. Grid Connection Masterclass Energex John Lansley Senior Network Solutions Engineer

Size template. Grid Connection Masterclass Energex John Lansley Senior Network Solutions Engineer Size template Grid Connection Masterclass Energex John Lansley Senior Network Solutions Engineer The average system size has doubled since 2010 Key Network Issues Reverse power on up to 12 off 11 kv feeders

More information

INFLUENCE ANALYSIS OF SMALL REPOWERED WIND POWER PLANTS ON THE RELIABILITY OF THE LOCAL GRID

INFLUENCE ANALYSIS OF SMALL REPOWERED WIND POWER PLANTS ON THE RELIABILITY OF THE LOCAL GRID M.SC. ENG. GRZEGORZ BARZYK DR ENG. MIROSŁAW DOPIERA Electrotechnical Engineering Institute, TU Szczecin INFLUENCE ANALYSIS OF SMALL REPOWERED WIND POWER PLANTS ON THE RELIABILITY OF THE LOCAL GRID Key

More information

CO-ORDINATION OF PARALLEL AC-DC SYSTEMS FOR OPTIMUM PERFORMANCE

CO-ORDINATION OF PARALLEL AC-DC SYSTEMS FOR OPTIMUM PERFORMANCE CO-ORDINATION OF PARALLEL AC-DC SYSTEMS FOR OPTIMUM PERFORMANCE Ana Diez Castro & Rickard Ellström Ying Jiang Häfner Christer Liljegren Vattenfall Utveckling AB ABB Power Systems Gotlands Energiverk AB

More information

DIMENSIONING OF CURRENT TRANSFORMERS FOR PROTECTON APPLICATION

DIMENSIONING OF CURRENT TRANSFORMERS FOR PROTECTON APPLICATION ÿþ üûúùø öõöôùóùõò CT Dimensioning DIMENSIONING OF CURRENT TRANSFORMERS FOR PROTECTON APPLICATION Application note GER3973 1 CT Dimensioning ÿþ üûúùø öõöôùóùõò GER-3973 Application note ÿþ üûúùø öõöôùóùõò

More information

Power Voltage Transformers for Air Insulated Substations. THE PROVEN POWER.

Power Voltage Transformers for Air Insulated Substations. THE PROVEN POWER. Power Voltage Transformers for Air Insulated Substations THE PROVEN POWER. Introduction Trench Power Voltage Transformers (Power VTs) combine the attributes of an inductive voltage transformer with the

More information

Simple Methods for Calculating Short Circuit Current Without a Computer By Dennis McKeown, PE GE Senior System Application Engineer

Simple Methods for Calculating Short Circuit Current Without a Computer By Dennis McKeown, PE GE Senior System Application Engineer Simple Methods for Calculating Short Circuit Current Without a Computer By Dennis McKeown, PE GE Senior System Application Engineer A Short Circuit analysis is used to determine the magnitude of short

More information

Advanced Protection of Distribution Networks with Distributed Generators

Advanced Protection of Distribution Networks with Distributed Generators Date:- 8 10 March 2011 Venue: University of Manchester EES-UETP Course title Advanced Protection of Distribution Networks with Distributed Generators Peter Crossley Director of the Joule Centre School

More information

Paralleling Power Sources Which Share a Common Neutral

Paralleling Power Sources Which Share a Common Neutral Paralleling Power Sources Which Share a Common Neutral By: Tony Hoevenaars, P.E., President & CEO, Mirus International, Inc. Mike McGraw, President, NSOEM, Inc. When paralleling power sources that share

More information

F.C. Chan General Manager, CLP Engineering Ltd., Hong Kong SAR, China

F.C. Chan General Manager, CLP Engineering Ltd., Hong Kong SAR, China ELECTRIC POWER DISTRIBUTION SYSTEMS F.C. Chan General Manager, CLP Engineering Ltd., Hong Kong SAR, China Keywords: Distribution system planning, Load characteristics, Subtransmission Lines, Distribution

More information

Isolated-Parallel UPS Configuration

Isolated-Parallel UPS Configuration Isolated-Parallel UPS Configuration 1 Inhalt 1 Introduction... 4 2 IP systems configuration... 6 3 Projects... 17 4 Conclusions... 17 2 Abstract The isolated-parallel UPS configuration has become well

More information

Step Voltage Regulators

Step Voltage Regulators Step Voltage Regulators Don Wareham Field Application Engineer Today s Agenda Introduction Voltage Regulator theory Voltage Regulator application considerations Installation and proper bypassing Wrap-up/questions

More information

ECE 586b Course Project Report. Auto-Reclosing

ECE 586b Course Project Report. Auto-Reclosing ECE 586b Course Project Report Auto-Reclosing Srichand Injeti May 5, 2008 Department Of Electrical and computer Engineering University Of Western Ontario, London Ontario Table of contents 1. Introduction...1

More information

MAINTAINING SYSTEM BLACKSTART IN COMPETITIVE BULK-POWER MARKETS

MAINTAINING SYSTEM BLACKSTART IN COMPETITIVE BULK-POWER MARKETS MAINTAINING SYSTEM BLACKSTART IN COMPETITIVE BULK-POWER MARKETS BRENDAN KIRBY and ERIC HIRST Consulting in Electric-Industry Restructuring Oak Ridge, Tennessee Restructuring the electric-power industry

More information

Rule 5.500 Fast Track Analysis for National Life Insurance Co.

Rule 5.500 Fast Track Analysis for National Life Insurance Co. Rule 5.500 Fast Track Analysis for National Life Insurance Co. For a 500 kw Solar array to be located at 155 Northfield Street in Montpelier, Vermont Green Mountain Power Pam Allen Date: 5/31/13 SECTION

More information

Requirements for Offshore Grid Connections. in the. Grid of TenneT TSO GmbH

Requirements for Offshore Grid Connections. in the. Grid of TenneT TSO GmbH Requirements for Offshore Grid Connections in the Grid of TenneT TSO GmbH Bernecker Straße 70, 95448 Bayreuth Updated: 21 December 2012 1/10 Requirements for Offshore Grid Connections in the Grid of TenneT

More information

Power Quality Standards for Electric Service

Power Quality Standards for Electric Service Power Quality Standards for Electric Service Effective June 1, 2008 A transition period will exist from June 1 through December 31, 2008 in which installations may be approved and connected as long as

More information

Network Consulting for Power Grid Optimization

Network Consulting for Power Grid Optimization Network Consulting for Power Grid Optimization Project experience in India Network Consulting Competences Page 1 Our worldwide representation Manchester The Hague Denver Schenectady San Diego Houston Mexico

More information

Assessment of the Technical Issues relating to Significant Amounts of EHV Underground Cable in the All-island Electricity Transmission System

Assessment of the Technical Issues relating to Significant Amounts of EHV Underground Cable in the All-island Electricity Transmission System Assessment of the Technical Issues relating to Significant Amounts of EHV Underground Cable in the All-island Electricity Transmission System Summary Report November 2009 Technical Report on using EHV

More information

Planned Islanding on Rural Feeders - Utility Perspective

Planned Islanding on Rural Feeders - Utility Perspective INVITED PAPER FOR PRESENTATION AT THE IEEE PES 2008 GENERAL MEETING (PANEL ON MICROGRIDS), (JULY 20-24, PITTSBURGH, PENNSYLVANIA) Planned Islanding on Rural Feeders - Utility Perspective Farid Katiraei,

More information

AMSC s Superconductor Cable Technologies for Electric Utilities

AMSC s Superconductor Cable Technologies for Electric Utilities International Workshop 2014 AMSC s Superconductor Cable Technologies for Electric Utilities Michael Ross, P.E. Managing Director of Superconductor Power Systems AMSC Corporate Facts Headquartered in MA,

More information

DC TRANSMISSION BASED ON VOLTAGE SOURCE CONVERTERS

DC TRANSMISSION BASED ON VOLTAGE SOURCE CONVERTERS DC TRANSMISSION BASED ON VOLTAGE SOURCE CONVERTERS by Gunnar Asplund, Kjell Eriksson, Hongbo Jiang, Johan Lindberg, Rolf Pålsson, Kjell Svensson ABB Power Systems AB Sweden SUMMARY Voltage Source Converters

More information

Power transformers. Special transformers Railway

Power transformers. Special transformers Railway Power transformers Special transformers Railway A leader in railway systems Our compact and low-weight transformers fully comply with the customer s specifications. The products are developed together

More information

Power products and systems. Intelligent solutions for power distribution Zone concept

Power products and systems. Intelligent solutions for power distribution Zone concept Power products and systems Intelligent solutions for power distribution Zone concept Securing continuous power supply ABB is one of the world's leading power and automation technology companies whose products,

More information

Digital Energy ITI. Instrument Transformer Basic Technical Information and Application

Digital Energy ITI. Instrument Transformer Basic Technical Information and Application g Digital Energy ITI Instrument Transformer Basic Technical Information and Application Table of Contents DEFINITIONS AND FUNCTIONS CONSTRUCTION FEATURES MAGNETIC CIRCUITS RATING AND RATIO CURRENT TRANSFORMER

More information

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment March 20, 2009 Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment Table of Contents:

More information

Comparison of GIS and AIS systems for urban supply networks

Comparison of GIS and AIS systems for urban supply networks Comparison of GIS and AIS systems for urban supply networks Studies carried out by ABB show that for urban supply networks the combination of HV gas-insulated switchgear (GIS) and HV cable has important

More information

Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components

Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components Course No: E02-010 Credit: 2 PDH Boris Shvartsberg, Ph.D., P.E., P.M.P. Continuing Education

More information

2012 San Francisco Colloquium

2012 San Francisco Colloquium 2012 San Francisco Colloquium http : //www.cigre.org HVDC and Power Electronic Systems for Overhead Line and Insulated Cable Applications B4-8 Trans Bay Cable A Breakthrough of VSC Multilevel Converters

More information

WHITE PAPER GROUND FAULT. Lowering the Limits for Ground Fault Detection

WHITE PAPER GROUND FAULT. Lowering the Limits for Ground Fault Detection WHITE PAPER GROUND FAULT Lowering the Limits for Ground Fault Detection Current flowing to ground has only two paths it can flow to ground through a ground fault, or it can flow to ground through distributed

More information

Best Practices, Benefits and Economics of Load Testing IEEE PES Fort Worth, TX Chapter July 16, 2013

Best Practices, Benefits and Economics of Load Testing IEEE PES Fort Worth, TX Chapter July 16, 2013 Best Practices, Benefits and Economics of Load Testing IEEE PES Fort Worth, TX Chapter July 16, 2013 Mark Siira ComRent International 1 8/1/2013 Agenda Introduction Overview of Load Bank Testing Benefits

More information

Chapter 11. Inductors ISU EE. C.Y. Lee

Chapter 11. Inductors ISU EE. C.Y. Lee Chapter 11 Inductors Objectives Describe the basic structure and characteristics of an inductor Discuss various types of inductors Analyze series inductors Analyze parallel inductors Analyze inductive

More information

ANCILLARY EQUIPMENT AND ELECTRICAL EQUIPMENT Power Supply Systems and Electrical Equipment for Desalination Plants - Y.M. Hamud and A.H.

ANCILLARY EQUIPMENT AND ELECTRICAL EQUIPMENT Power Supply Systems and Electrical Equipment for Desalination Plants - Y.M. Hamud and A.H. POWER SUPPLY SYSTEMS AND ELECTRICAL EQUIPMENT FOR DESALINATION PLANTS Y.M. Hamud and A.H. Anwar Abu Dhabi Water and Electricity Authority, Abu Dhabi, UAE Keywords : Electrical System, Network for Desalination,

More information

ADMS(Advanced Distribution Management System ) in Smart Grid

ADMS(Advanced Distribution Management System ) in Smart Grid ADMS(Advanced Distribution Management System ) in Smart Grid 柯 佾 寬 博 士 Yi-Kuan Ke, Ph.D. 2014/03/28 Smart Grid Solution Smart Grid Solution Overview Smart Grid Solutions Smart Network Operation - Distribution

More information

Offshore wind farm electrical engineering (when considering the operation of array cabling at voltages of 66kV)

Offshore wind farm electrical engineering (when considering the operation of array cabling at voltages of 66kV) Offshore wind farm electrical engineering (when considering the operation of array cabling at voltages of 66kV) 29 th January 2015 Lyndon Greedy / Hans Cleijne 1 SAFER, SMARTER, GREENER DNV GL Renewables

More information

Arc Flash Mitigation. Remote Racking and Switching for Arc Flash danger mitigation in distribution class switchgear.

Arc Flash Mitigation. Remote Racking and Switching for Arc Flash danger mitigation in distribution class switchgear. Arc Flash Mitigation Remote Racking and Switching for Arc Flash danger mitigation in distribution class switchgear. Distance is Safety We will discuss through examples of actual occurrences and possible

More information

PROTECTION TECHNIQUE FOR TRANSIENT OVERVOLTAGE DUE TO CAPACITOR BANK SWITCHING IN DISTRIBUTION SYSTEMS USING HIGH PASS FILTER

PROTECTION TECHNIQUE FOR TRANSIENT OVERVOLTAGE DUE TO CAPACITOR BANK SWITCHING IN DISTRIBUTION SYSTEMS USING HIGH PASS FILTER VO. 1, NO., DEEMBER 15 SSN 1819-668 6-15 Asian Research Publishing Network (ARPN). All rights reserved. PROTETON TEHNQUE FOR TRANSENT OVERVOTAGE DUE TO APATOR BANK SWTHNG N DSTRBUTON SYSTEMS USNG HGH PASS

More information

SCADA Controlled Multi-Step Automatic Controlled Capacitor Banks & Filter Banks

SCADA Controlled Multi-Step Automatic Controlled Capacitor Banks & Filter Banks SCADA Controlled Multi-Step Automatic Controlled Capacitor Banks & Filter Banks Introduction SCADA (Supervisory Controlled and Data Acquisition) controlled multi-step metalenclosed automatic capacitor

More information

TWENTIES WORKSHOP, EWEA 2012 Unveiling the future energy system: full scale demonstrations to reach 2020 targets. 17th April 2012

TWENTIES WORKSHOP, EWEA 2012 Unveiling the future energy system: full scale demonstrations to reach 2020 targets. 17th April 2012 TWENTIES WORKSHOP, EWEA 2012 Unveiling the future energy system: full scale demonstrations to reach 2020 targets 17th April 2012 Session 2 Technological challenges to cope with in TWENTIES field tests

More information

A3-301 CURRENT INTERRUPTION WITH HIGH VOLTAGE AIR-BREAK DISCONNECTORS. J.H. SAWADA BC HYDRO (Canada) J.G. KRONE HAPAM B.V.

A3-301 CURRENT INTERRUPTION WITH HIGH VOLTAGE AIR-BREAK DISCONNECTORS. J.H. SAWADA BC HYDRO (Canada) J.G. KRONE HAPAM B.V. 21, rue d'artois, F-75008 Paris http://www.cigre.org A3-301 Session 2004 CIGRÉ CURRENT INTERRUPTION WITH HIGH VOLTAGE AIR-BREAK DISCONNECTORS D.F. PEELO* DF PEELO & ASSOCIATES R.P.P. SMEETS KEMA HIGH-POWER

More information

LIMITING SHORT-CIRCUIT CURRENTS IN MEDIUM-VOLTAGE APPLICATIONS

LIMITING SHORT-CIRCUIT CURRENTS IN MEDIUM-VOLTAGE APPLICATIONS LIMITING SHORT-CIRCUIT CURRENTS IN MEDIUM-VOLTAGE APPLICATIONS Terence Hazel Senior Member IEEE Schneider Electric 38050 Grenoble France Abstract The power requirements for large industrial sites is increasing.

More information

VOLTAGE REGULATOR AND PARALLEL OPERATION

VOLTAGE REGULATOR AND PARALLEL OPERATION VOLTAGE REGULATOR AND PARALLEL OPERATION Generator sets are operated in parallel to improve fuel economy and reliability of the power supply. Economy is improved with multiple paralleled generators by

More information

MV, HV AND EHV SWITCHGEAR TESTING & COMMISSIONING

MV, HV AND EHV SWITCHGEAR TESTING & COMMISSIONING Training Title MV, HV AND EHV SWITCHGEAR TESTING & COMMISSIONING Training Duration 5 days Training Date MV, HV and EHV Switchgear Testing & Commissioning 5 20 24 Apr $3,750 Dubai, UAE In any of the 5 star

More information

Siemens Integrated Substation Condition Monitoring System. Circuit Breaker Monitoring

Siemens Integrated Substation Condition Monitoring System. Circuit Breaker Monitoring Siemens Integrated Substation Condition Monitoring System Circuit Breaker Monitoring System Description Introduction The Circuit Breaker Monitor [CBM] is only one example of the way that the Substation

More information

PG&E Transmission Interconnection Handbook. Section L3: SUBSTATION DESIGN FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES

PG&E Transmission Interconnection Handbook. Section L3: SUBSTATION DESIGN FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES Section L3: SUBSTATION DESIGN FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES PURPOSE This section provides substation design information for Load Entities interconnected at transmission voltage

More information

COMPARISON OF THE FACTS EQUIPMENT OPERATION IN TRANSMISSION AND DISTRIBUTION SYSTEMS

COMPARISON OF THE FACTS EQUIPMENT OPERATION IN TRANSMISSION AND DISTRIBUTION SYSTEMS COMPARISON OF THE FACTS EQUIPMENT OPERATION IN TRANSMISSION AND DISTRIBUTION SYSTEMS Afshin LASHKAR ARA Azad University of Dezfoul - Iran A_lashkarara@hotmail.com Seyed Ali NABAVI NIAKI University of Mazandaran

More information

Impact of Distributed Generation on Voltage Profile in Deregulated Distribution System

Impact of Distributed Generation on Voltage Profile in Deregulated Distribution System Impact of Distributed Generation on Voltage Profile in Deregulated Distribution System W. EL-KHATTAM M. M. A. SALAMA Electrical & Computer Engineering, Waterloo University, Ontario, Canada Abstract: Due

More information

Transfer Equipment Controls

Transfer Equipment Controls Control Types Manual Transfer Switches Nonautomatic Transfer Switches Automatic Transfer Switches The type of control system for the transfer switch will vary depending on the type of switching equipment

More information

Current and voltage measuring relays

Current and voltage measuring relays Current and voltage measuring relays RXIK 1, RXEEB 1 and Page 1 Issued June 1999 Changed since July 1998 Data subject to change without notice RXIK 1 RXEEB 1 (SE980082) (SE980081) (SE970869) Features Application

More information

Modular Systems wind portfolio overview Power Collection and Grid Connection products

Modular Systems wind portfolio overview Power Collection and Grid Connection products Modular Systems wind portfolio overview Power Collection and Grid Connection products Slide 1 Modular Systems wind portfolio Wind power - definition A wind turbine is a device that converts kinetic energy

More information

Superconducting and Solid-State Electronic Fault Current Limiter Technologies The shift from demonstration projects to Business-as-Usual solutions

Superconducting and Solid-State Electronic Fault Current Limiter Technologies The shift from demonstration projects to Business-as-Usual solutions Superconducting and Solid-State Electronic Fault Current Limiter Technologies The shift from demonstration projects to Business-as-Usual solutions Dr. Detlev Kirsten & Herbert Piereder Solid State SSFCL

More information

FRCC Standards Handbook. FRCC Automatic Underfrequency Load Shedding Program. Revision Date: July 2003

FRCC Standards Handbook. FRCC Automatic Underfrequency Load Shedding Program. Revision Date: July 2003 F R C C FRCC Standards Handbook FRCC Automatic Underfrequency Load Shedding Program Revision Date: July 2003 FRCC Underfrequency Load Shedding Program Modification and Approval Process Requests to modify

More information

Product Data Bulletin

Product Data Bulletin Product Data Bulletin Power System Harmonics Causes and Effects of Variable Frequency Drives Relative to the IEEE 519-1992 Standard Raleigh, NC, U.S.A. INTRODUCTION This document describes power system

More information

GROUND DETECTION CIRCUITS FOR STATIONARY APPLICATIONS (IN PLAIN DOWN TO EARTH LANGUAGE)

GROUND DETECTION CIRCUITS FOR STATIONARY APPLICATIONS (IN PLAIN DOWN TO EARTH LANGUAGE) GROUND DETECTION CIRCUITS FOR STATIONARY APPLICATIONS (IN PLAIN DOWN TO EARTH LANGUAGE) Matthew Theriault Designer Hindle Power Inc. Easton, PA SCOPE AND PURPOSE OF THE PAPER Why do we bother to monitor

More information

Cost Benefit Methodology for Optimal Design of Offshore Transmission Systems

Cost Benefit Methodology for Optimal Design of Offshore Transmission Systems Centre for Sustainable Electricity and Distributed Generation Cost Benefit Methodology for Optimal Design of Offshore Transmission Systems Predrag Djapic and Goran Strbac July 2008 FUNDED BY BERR URN 08/1144

More information

Transformerless UPS systems and the 9900 By: John Steele, EIT Engineering Manager

Transformerless UPS systems and the 9900 By: John Steele, EIT Engineering Manager Transformerless UPS systems and the 9900 By: John Steele, EIT Engineering Manager Introduction There is a growing trend in the UPS industry to create a highly efficient, more lightweight and smaller UPS

More information

Power Quality Paper #3

Power Quality Paper #3 The Effect of Voltage Dips On Induction Motors by: M D McCulloch 1. INTRODUCTION Voltage depressions caused by faults on the system affect the performance of induction motors, in terms of the production

More information

Agenda do Mini-Curso. Sérgio Yoshio Fujii. Ethan Boardman. sergio.fujii@areva-td.com. ethan.boardman@areva-td.com

Agenda do Mini-Curso. Sérgio Yoshio Fujii. Ethan Boardman. sergio.fujii@areva-td.com. ethan.boardman@areva-td.com Agenda do Mini-Curso Sérgio Yoshio Fujii sergio.fujii@areva-td.com Ethan Boardman ethan.boardman@areva-td.com Agenda do Mini-Curso Sistemas de Distribuição (DMS) Characteristics of Distribution Network

More information

Line to Ground Voltage Monitoring on Ungrounded and Impedance Grounded Power Systems

Line to Ground Voltage Monitoring on Ungrounded and Impedance Grounded Power Systems Line to Ground Voltage Monitoring on Ungrounded and Impedance Grounded Power Systems by Reza Tajali, P.E. Square D Company, Power Systems Engineering Group 295 Tech Park Drive LaVergne, Tennessee 37086

More information

Variable Frequency Drives - a Comparison of VSI versus LCI Systems

Variable Frequency Drives - a Comparison of VSI versus LCI Systems Variable Frequency Drives - a Comparison of VSI versus LCI Systems Introduction TMEIC is a leader in the innovative design and manufacture of large ac variable f requency drive systems. TMEIC has been

More information

Sensitivity Analysis of Waveform Distortion Assessment for Wind Plants

Sensitivity Analysis of Waveform Distortion Assessment for Wind Plants Sensitivity Analysis of Waveform Distortion Assessment for Wind Plants Mariana B. Pereira 1, Einar V. Larsen 2, Sebastian A. Achilles 3 Energy Consulting General Electric 1 Av. Magalhães de Castro 4800,

More information

Voltage regulation in distribution systems - Tap changer and Wind Power

Voltage regulation in distribution systems - Tap changer and Wind Power CODEN:LUTEDX/(TEIE-5270)/1-59/(2010) Industrial Electrical Engineering and Automation Voltage regulation in distribution systems - Tap changer and Wind Power David Sáez Romero D of Industrial Electrical

More information

Type SA-1 Generator Differential Relay

Type SA-1 Generator Differential Relay ABB Automation Inc. Substation Automation and Protection Division Coral Springs, FL 33065 Instruction Leaflet 41-348.11C Effective: November 1999 Supersedes I.L. 41-348.11B, Dated August 1986 ( ) Denotes

More information

Calculation of Voltage Sag Indices for Distribution Networks

Calculation of Voltage Sag Indices for Distribution Networks Calculation of Voltage Sag Indices for Distribution Networks Juan A. Martinez-Velasco, Member, IEEE, Jacinto Martin-Arnedo, Nonmember Abstract This paper is presenting the main results of a work aimed

More information

The design and performance of Static Var Compensators for particle accelerators

The design and performance of Static Var Compensators for particle accelerators CERN-ACC-2015-0104 Karsten.Kahle@cern.ch The design and performance of Static Var Compensators for particle accelerators Karsten Kahle, Francisco R. Blánquez, Charles-Mathieu Genton CERN, Geneva, Switzerland,

More information

Single and Three Phase Transformer Testing Using Static Motor Circuit Analysis Techniques

Single and Three Phase Transformer Testing Using Static Motor Circuit Analysis Techniques Single and Three Phase Transformer Testing Using Static Motor Circuit Analysis Techniques Howard W. Penrose, Ph.D On behalf of ALL-TEST Pro, LLC Old Saybrook, CT Introduction Field and shop testing of

More information

ASK THE EXPERTS. Resistance Grounding Q&A. with industry experts

ASK THE EXPERTS. Resistance Grounding Q&A. with industry experts ASK THE EXPERTS Resistance Grounding Q&A with industry experts system grounding system grounding system grounding system grounding system grounding System Grounding Definition and Different Types What

More information

Design of Four Input Buck-Boost DC-DC Converter for Renewable Energy Application

Design of Four Input Buck-Boost DC-DC Converter for Renewable Energy Application Design of Four Input Buck-Boost DC-DC Converter for Renewable Energy Application A.Thiyagarajan Assistant Professor, Department of Electrical and Electronics Engineering Karpagam Institute of Technology

More information

Phase Balancing of Distribution Systems Using a Heuristic Search Approach

Phase Balancing of Distribution Systems Using a Heuristic Search Approach Phase Balancing of Distribution Systems Using a Heuristic Search Approach Lin, Chia-Hung*, Kang, Meei-Song**, Chuang, Hui-Jen**, and Ho, Chin-Ying** *National Kaohsiung University of Applied Sciences **Kao

More information

Study to Determine the Limit of Integrating Intermittent Renewable (wind and solar) Resources onto Pakistan's National Grid

Study to Determine the Limit of Integrating Intermittent Renewable (wind and solar) Resources onto Pakistan's National Grid Pakistan Study to Determine the Limit of Integrating Intermittent Renewable (wind and solar) Resources onto Pakistan's National Grid Final Report: Executive Summary - November 2015 for USAID Energy Policy

More information

N.J.A.C. 14:8-4 NET METERING FOR CLASS I RENEWABLE ENERGY SYSTEMS

N.J.A.C. 14:8-4 NET METERING FOR CLASS I RENEWABLE ENERGY SYSTEMS N.J.A.C. 14:8-4 NET METERING FOR CLASS I RENEWABLE ENERGY SYSTEMS 14:8-4.1 Scope This subchapter sets forth net metering requirements that apply to electric power suppliers, basic generation service providers

More information

Relion. Power system protection and automation reference Fast substation busbar protection with IEC 61850 and GOOSE

Relion. Power system protection and automation reference Fast substation busbar protection with IEC 61850 and GOOSE Relion Power system protection and automation reference Fast substation busbar protection with IEC 61850 and GOOSE Fast substation busbar protection with IEC 61850 and GOOSE Falu Elnät AB applies new power

More information