Lightning Protection System Quality Installation and Maintenance. Lightning Protection System Quality Installation and Maintenance

Size: px
Start display at page:

Download "Lightning Protection System Quality Installation and Maintenance. Lightning Protection System Quality Installation and Maintenance"

Transcription

1 Lightning Protection System Quality Installation and Maintenance Lightning Protection System Quality Installation and Maintenance Michael J. Johnston NECA Executive Director Standards & Safety Mark S. Harger President/CEO Harger Lightning & Grounding This session is eligible for 1 Continuing Education Hour and 1 Contact Hour. To earn these hours you must: Have your badge scanned at the door Attend 90% of this presentation Fill out the online evaluation for this session Attendees Only 1

2 Why There is no ANSI accredited lightning protection standard that addresses best practices Less than 2% of all UL Master Label installations get re-inspected after the 5 year date Most lightning protection systems on structures are not being maintained Outline 1.0 Scope 2.0 Definitions 3.0 Design Procedures 4.0 Installation 5.0 Acquisition of Master Label Certificate 6.0 Inspection, Maintenance and Ground Testing Procedures 7.0 Project Management Procedures Attendees Only 2

3 1.0 - Scope To provide a Best Practices Lightning Protection System Installation Standard that ensures the completed installation complies with the requirements of NFPA 780, Standard for the Installation of Lightning Protection Systems. This standard will cover both new and existing structures Definitions Attendees Only 3

4 ANSI- Definitions A United States standards organization responsible for promoting and facilitating voluntary consensus standards and safeguarding their integrity. Down Conductor- Definitions A main conductor that carries lightning currents from the top of the structure to the grounding electrodes. Down Conductor Attendees Only 4

5 Exothermic- Definitions A process that produces a welded connection between a conductor and other objects. Ground Access Well- Definitions A protective enclosure which allows the ability to inspect and test individual grounding electrodes or the grounding electrode system. Attendees Only 5

6 NFPA 780- Definitions An ANSI recognized installation standard for lightning protection systems. Roof Conductor- Definitions A main conductor located at the roof level that interconnects strike termination devices to down conductors. Attendees Only 6

7 Definitions A connection device that assists in creating a water tight seal when penetrating a roof. Thru-Roof- Thru-Wall- Definitions A connection device that assists in creating a water tight seal when penetrating a wall. Attendees Only 7

8 3.0 - Design Procedures The lightning protection design shall be in accordance with the requirements of NFPA 780, standard for the insulation of lightning protection systems. Design Procedures The company providing the design should have a minimum of 5 years experience and be well versed with NFPA 780. Attendees Only 8

9 Design Procedures Example of a proper lightning protection shop drawing. Design Procedures Example of a proper lightning protection shop drawing details. Attendees Only 9

10 Design Procedures Generally, it is not advisable to rely on the lightning protection design information provided with the original plans as shown by this example. Design Procedures This is an example of a lightning protection drawing designed to meet the requirements of NFPA 780. Attendees Only 10

11 Design Procedures Lightning protection systems are designed specifically for the building or structures they are intended to protect. Design Procedures The design is not only impacted by the shape and size, but also by building systems and structural components. Attendees Only 11

12 4.0 - Installation The installation shall be in accordance with the requirements set forth in NFPA 780 and installed in a neat and workmanlike manner 4.1 Pre-Construction Site Assessment When: Once the submittal drawings have been approved and before construction begins Why: To review important aspects of the installation Who: Owner representative Supervisor Roofing contractor Electrical contractor Attendees Only 12

13 Pre-Construction Site Assessment Items to be discussed Location and placement of ground electrodes and down conductors Responsibility for sealing thru-roof penetrations Installation of adhesive mounting pads (if required) 4.2 Ground Electrode Installation and Common Bonding Ground electrodes shall be installed in accordance with NFPA 780. Common bonding between all building electrode systems shall be installed in accordance with NFPA 780 and NEC 70. Attendees Only 13

14 Ground Electrode Installation For testing and maintenance, access of each ground electrode should be available. Ground Electrode Installation Ground rods should be driven far enough away from the footing and drain tile and also past the roof s drip edge. Attendees Only 14

15 Ground Electrode Installation Ground rods shall be installed into undisturbed soil. If it is not practical to install ground rods outside of the building, the ground rods should be installed as close to the building s walls as practical without damaging the footing. Ground Electrode Installation The correct ground rod driver adapter should be used to avoid mushrooming or damaging the end of the ground rod. Attendees Only 15

16 Ground Electrode Installation If the damage to the ground rod is to severe, the top of the rod may need to be cut off so that the ground rod clamp or exothermic connection can be properly made. Ground Ring Electrode Installation If required, a ground ring electrode for the lightning protection system shall be installed at least 18 inches below earth unless prohibited by ground conditions. Attendees Only 16

17 Ground Ring Electrode Installation A ground ring electrode installed for the purposes of electrical grounding shall be installed to a depth of at least 30 inches. Ground Ring Electrode Installation Ground ring electrodes shall be continuous around the structure and connected to all down conductors. The ground ring electrode shall be installed below the frost line (if present) Attendees Only 17

18 Common Bonding Per NFPA 780, all grounding systems and underground metal piping that enters a building shall be bonded to the lightning protection system within 12 feet of grade level. Common Bonding Other grounding systems to be bonded include but are not limited to; Electrical service Communications Cable television Antenna systems Attendees Only 18

19 Common Bonding The use of an intersystem bonding termination device may help facilitate these connections. Common Bonding A master ground bar is another choice to help facilitate these connections. Attendees Only 19

20 Common Bonding Buildings exceeding 60 ft. in height, the bonding connections shall be made to a ground loop conductor. A ground ring conductor can serve as a ground loop conductor. 4.3 Down Conductors & Bonding When installing, ensure paths for down conductors are clear of obstructions, such as HVAC ducts, large pipes or structural columns or beams. Attendees Only 20

21 Down Conductors Lightning conductors must maintain a horizontal or downward path from air terminals to the grounding electrode. Down Conductors Down conductors shall be placed as widely as practicable around the perimeter of the building. Attendees Only 21

22 Down Conductors Sharp bends and splices in down conductors should be avoided. Bends and splices increase the impedance of the conductor. Down Conductors Down conductors shall be securely fastened to the structure at maximum 3 feet intervals. Attendees Only 22

23 10/5/15 Down Conductors The conductor clips and hardware must be the same material as the conductor or a material equally resistant to corrosion. Down Conductors When routing down conductors through exterior walls, a thru-wall device should be used to prevent moisture from entering the structure. Attendees Only 23

24 Down Conductors Exposed down conductors in areas subject to physical damage of theft shall be protected with guards or conduits at least 6 feet above grade. Down Conductors Down conductors that are installed in long vertical conduits or raceways should be supported to reduce the strain on the conductor. Class I conductors should be supported every 100 ft. Class II conductors should be supported every 80 ft. Attendees Only 24

25 Down Conductors Buildings with electrically continuous structural metal framework, the metal should be used as down conductors. Down Conductors When using the structural metal as a down conductor, the metal shall be cleaned down to base metal, removing all paint, rust, and mill scale to avoid high resistance connections. Attendees Only 25

26 Down Conductors When utilizing mechanical connections, antioxidant joint compound should be used to prevent corrosion. Down Conductors Routing down conductors in both new and existing construction may require reestablishing the integrity of fire-rated walls, floors, and ceilings. Attendees Only 26

27 Bonding Where down conductors are run on buildings with structural metal framework, each down conductor shall be bonded near the top and bottom. Bonding Steel reinforced concrete columns or CMU walls with reinforcing steel. The rebar shall be bonded at the top and bottom of the down conductors. Attendees Only 27

28 Bonding Grounded metal objects near down conductors may require bonding if located within the calculated side-flash or bonding distance. 4.4 Thru-Roof Installation Installation of thru-roof s should be reviewed with the roofing contractor, roofing manufacturer, architect and engineer prior to installation. Attendees Only 28

29 Thru-Roof Installation Thru-roof s are designed to accommodate various ranges of roof thickness. The thru-roof s assemblies should be modified at the site so they extend not more than 9 inches above the completed roof. Thru-Roof Installation Thru-roofs should not be installed in low areas of flat or gently sloping roofs. On pitched roofs, thru-roofs should not be located in valleys or near gutters. Attendees Only 29

30 4.5 Roof Top Installation Location & Mounting of Air Terminal Bases Generally air terminal bases are first to be mounted to the roof. Attendees Only 30

31 Location & Mounting of Air Terminal Bases The layout of air terminal bases typically start in the corner. The length of the roof edge or ridge is divided into equal spaces. Location & Mounting of Air Terminal Bases When mounting air terminals near corners and edges, the conductor must maintain at least a minimum 8 inch radius bend. Attendees Only 31

32 Location & Mounting of Air Terminal Bases When mounting air terminals on roof-top equipment, make sure that access panels are not obstructed. Location & Mounting of Air Terminal Bases Air terminal bases must be securely attached to the structure with corrosion resistant hardware. If adhesive is used, the roofing contractor and manufacturer must be consulted and they must make sure the adhesive is compatible with surface it is to be mounted to. Attendees Only 32

33 Routing of Roof Conductors Shop drawings will give the general routing of conductors on the roof. The number of splices and connectors may be minimized with some forethought. Conductors must be routed to avoid sharp bends of less than 90 degrees or radius bend less than 8 inches. Routing of Roof Conductors As with air terminal bases, conductors should be securely attached to the structure at maximum 3 feet intervals or less in areas where movement of the conductor is of a concern. Attendees Only 33

34 Routing of Roof Conductors Conductor that must run through the air for more than 3 feet must be supported. Avoid routing conductors perpendicular to the slope of pitched roofs where ice, snow or debris can collect. Routing of Roof Conductors Care should be taken when routing conductors to account for temperature change. Copper and aluminum conductors expand and contract. Attendees Only 34

35 Routing of Roof Conductors When routing roof conductors through walls, a thru-wall device should be used to prevent moisture from entering the structure. 4.6 Performance and Quality Control Issues Materials used in the installation of a lightning protection system must be listed or labeled by U.L. for use in lightning protection systems. Attendees Only 35

36 Materials Although a component may have the UL mark and be listed for the purpose of electrical work, it may not be listed to be used in a lightning protection installation. Materials Lightning protection materials must be compatible with the surfaces to which they are mounted. Attendees Only 36

37 Materials Confirm the compatibility of materials when making bonding connections to metal objects. Bimetallic connectors may be required. Materials Adhesives used must be compatible for two important reasons. The adhesive must be compatible with the surface it is being applied to ensure that it will not destroy the roof membrane or other surfaces. Compatibility is important to make sure that the adhesive functions properly and the components are held in place. Attendees Only 37

38 Exothermic Connections When making exothermic connections, all parts of the connection must be clean and free of moisture before making the connection. Conductor not properly cleaned Mold and conductor not properly dried 5.0 Acquisition of Master Label Certificate A Master Label Certificate indicates to the building owner that the installed lightning protection system meets the requirements of an installation standard. Attendees Only 38

39 Master Label Certificate A Master Label Certificate remains valid from the time of inspection until the expiration date unless modifications are made to the structure. A Master Label Certificate expires five years after the inspection date. Inspection Procedure The installer is responsible for coordinating access to all portions of the structure necessary to verify compliance with the specified standard. Some of these areas are; Main electrical power/distribution room Main communications room Service utilities such as sewer, fire suppression, etc. Rooftop Attics Basements Attendees Only 39

40 Submitting an Application Request for inspections shall be done through UL s web page. Submitting on line is a declaration that the installation complies with the applicable requirements. Post UL Inspection Documents Upon successful completion and inspection of the lightning protection system, the Master Label Certificate will be issued to the building owner and the installation contractor. It is the installation contractor s responsibility to ensure the Master Label Certificate is published on UL s public directory. Attendees Only 40

41 6.0 Inspection, Maintenance and Ground Testing Procedures Inspection and Maintenance Installations should be inspected upon completion and shall be required if the Master Label Certificate is specified. A maintenance manual should be provided to the building owner upon completion of the installation. 6.1 Inspection and Maintenance Periodic annual inspections are recommended, more frequent inspections may be required based on the following. Environmental conditions Classifications of the structure or area protected Mounting surface for lightning protection components. Lightning protection materials used. Attendees Only 41

42 Inspection and Maintenance The lightning protection system should also be inspected whenever any alterations or repairs have been made and if any lightning strikes have known to occur. In-depth inspections should be conducted every three to five years. 6.2 Visual Inspections Visual inspections are used to determine: Systems in good operating condition No loose connections No components have been compromised No down conductors have been detached, severed or stolen Attendees Only 42

43 Visual Inspections Visual inspections are also used to determine: Grounding electrodes are still attached All conductors, fasteners and other components are securely attached No alterations or additions have been made to the structure Surge protection devices are still operational. Lightning protection system is still in compliance with NFPA 780 Testing should be done to verify that concealed parts of the system are still electrically continuous as well as to determine if any additional equipotential bonding is needed. Attendees Only 43

44 Ground resistance testing of the individual grounding electrodes should be conducted to determine if there has been any increase in resistance since the original installation. 6.3 Inspection Guides An inspection guide should be prepared and made accessible to the party responsible for the lightning protection system. The following data should be covered. Overall condition of all lightning protection system components. Presence of any corrosion or material wear. Presence of any loose components. Resistance measurements of grounding electrodes. Presence of any new building components Changes made to the system or structure noted on the as-built drawings. Attendees Only 44

45 6.4 Maintenance Programs A maintenance program should contain a checklist of all items needing inspection including the following: Inspection of all conductors Reattach any loose conductors and replace if needed Inspect all fittings for tightness and corrosion. Test and record ground resistance of all grounding electrodes. Inspect all surge protection devices Record any new additions made to the structure Maintenance Programs Complete records should be kept of all maintenance procedures and inspections as they will assist in setting a baseline assessment of the lightning protection system and aid in establishing a preventive maintenance program. Attendees Only 45

46 6.5 Ground Testing There are two acceptable methods to test the resistance of a grounding electrode. Three point fall of potential Clamp-on test Ground Testing Fall of Potential Method The grounding electrode system (if multigrounded neutral system) and telecommunications ground must be disconnected. Individual grounding electrodes must be disconnected from the grounding electrode system and be tested individually to determine the resistance value. Attendees Only 46

47 Clamp-On Method Ground Testing The grounding electrode system must be connected to the electrical power system or a zero reference source. Proper placement of the unit is essential in order to obtain a correct reading. Grounding electrodes shall be tested individually to determine the resistance value. 7.0 Project Management Procedures Good project management procedures are essential to the successful design, installation and certification of a lightning protection system. Attendees Only 47

48 Project Management Project management begins with proper planning that includes: Defining the scope of the project Determining the best work flow Having procedures in place to deal with Communications Scope changes Quality issues Documentation Project Management Project design drawings need to be formalized into complete shop drawings that are coordinated and confirmed by all trade contractors as well as the architect and engineer. Approved shop drawings form the basis for the project documentation. Attendees Only 48

49 Project Management Determining the best work flow also requires proactive planning. Lightning protection systems interact with most other building systems. It is important to anticipate installation of other systems so that required connections can be made. Project Management Accurate documentation of the system installation is critically important to certification. Procedures must be in place to make certain all concealed portions are accurately documented on as-built drawings as well as with dated photos. Attendees Only 49

50 Don t forget Questions? 10:15-11:30 am Special Session: Life on the Rock 11:30 am - 4:00 pm NECA Show Hours Attendees Only 50

Specifications for Lightning Protection. ASAE Engineering Practice

Specifications for Lightning Protection. ASAE Engineering Practice Chapter 8: Lightning Specifications for Lightning Protection ASAE safety standards are not laws. They are recommended voluntary standards used by designers, engineers, manufacturers and users of the equipment,

More information

SECTION 22 LIGHTNING PROTECTION SYSTEM

SECTION 22 LIGHTNING PROTECTION SYSTEM SECTION 22 LIGHTNING PROTECTION SYSTEM 22.01 SCOPE: A. These Specifications shall form a part of the Contract Documents and shall govern construction work for all buildings to be built or modified for

More information

Lake County EOC. Vendor Quotes for Lightning Protection

Lake County EOC. Vendor Quotes for Lightning Protection Lake County EOC Vendor Quotes for Lightning Protection January 18, 2012 Electric Services Attn: Debbie Sutton Project: Subject: Lake County Emergency Communications & Operations Center Tavares, FL Lightning

More information

Air-Conditioning, Heating, and Refrigeration Institute. Sheet Metal and Air-Conditioning Contractors National Association

Air-Conditioning, Heating, and Refrigeration Institute. Sheet Metal and Air-Conditioning Contractors National Association Air-Conditioning, Heating, and Refrigeration Institute Sheet Metal and Air-Conditioning Contractors National Association GUIDELINE B-1997 ACKNOWLEDGEMENT These guidelines for Roof Mounted Outdoor Air-

More information

The National Armored Cable Manufacturers Association Presents. Installation Standard for Types AC and MC Cables

The National Armored Cable Manufacturers Association Presents. Installation Standard for Types AC and MC Cables The National Armored Cable Manufacturers Association Presents Installation Standard for Types AC and MC Cables An ANSI Standard Original document jointly produced by NECA and NACMA as Standard for Installing

More information

800 Communications Circuits

800 Communications Circuits ARTICLE 800 Communications Circuits INTRODUCTION TO ARTICLE 800 COMMUNICATIONS CIRCUITS This article has its roots in telephone technology. Consequently, it addresses telephone and related systems that

More information

HOUSTON COMMUNITY COLLEGE HCC ALIEF CAMPUS MAIN BUILDING, FIRST, SECOND & FOURTH FLOORS RENOVATION ISSUE DATE: 10.17.12

HOUSTON COMMUNITY COLLEGE HCC ALIEF CAMPUS MAIN BUILDING, FIRST, SECOND & FOURTH FLOORS RENOVATION ISSUE DATE: 10.17.12 SECTION 27 05 26 - GROUNDING AND BONDING FOR COMMUNICATIONS SYSTEMS PART 1 - GENERAL 1.1 SUMMARY A. This Section includes grounding and bonding products, design requirements and installation for communications

More information

Solar Panel Installations

Solar Panel Installations Solar Panel Installations Page 1 of 6 SINGLE-FAMILY RESIDENTIAL CHECKLIST City of Hayward Development Services Department Revised: 7-09-15 PERMIT REQUIREMENTS Permits are required for all solar panel installations.

More information

Chapter 3 Pre-Installation, Foundations and Piers

Chapter 3 Pre-Installation, Foundations and Piers Chapter 3 Pre-Installation, Foundations and Piers 3-1 Pre-Installation Establishes the minimum requirements for the siting, design, materials, access, and installation of manufactured dwellings, accessory

More information

INSTALLATION GUIDELINES for SOLAR PHOTOVOLTAIC SYSTEMS 1

INSTALLATION GUIDELINES for SOLAR PHOTOVOLTAIC SYSTEMS 1 City of Cotati Building Division 201 W. Sierra Ave. Cotati, CA 94931 707 665-3637 Fax 792-4604 INSTALLATION GUIDELINES for SOLAR PHOTOVOLTAIC SYSTEMS 1 Any PV system on a new structures should be included

More information

SECTION 27 05 36 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS

SECTION 27 05 36 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS SECTION 27 05 36 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS PART 1 GENERAL 1.01 DESCRIPTION A. The work covered by this section of the Specifications includes all labor necessary to perform and complete such

More information

COMMERCIAL COOKING HOODS, VENTILATION & FIRE SUPPRESSION SYSTEM GUIDELINES AND PROCEDURES

COMMERCIAL COOKING HOODS, VENTILATION & FIRE SUPPRESSION SYSTEM GUIDELINES AND PROCEDURES COMMERCIAL COOKING HOODS, VENTILATION & FIRE SUPPRESSION SYSTEM GUIDELINES AND PROCEDURES These guidelines are to be used for ALL commercial cooking hoods, ventilation systems and related fire suppression

More information

270526-TC Grounding and Bonding for Telecommunications Systems

270526-TC Grounding and Bonding for Telecommunications Systems 270526-TC Grounding and Bonding for Telecommunications Systems Part 1 - General Related Documents The following related sections of the OT standards shall also be applicable to this section. OT Engineer

More information

TITLE: MASONRY PARAPET WALLS AND FLAT ROOF REQUIREMENTS 11/1/09

TITLE: MASONRY PARAPET WALLS AND FLAT ROOF REQUIREMENTS 11/1/09 TITLE: MASONRY PARAPET WALLS AND FLAT ROOF REQUIREMENTS 11/1/09 PMT GUIDE # 10 Book of Order Section G-10.0102o: "The session is responsible for the mission and government of the particular church. It

More information

Mobile Home Pre-Inspection Checklist

Mobile Home Pre-Inspection Checklist Mobile Home Pre-Inspection Checklist TWO (2) STEP INSPECTION PROCESS STEP ONE: CALL FOR THE FIRST INSPECTION WHEN THESE ITEMS ARE COMPLETE. 1. Septic tank installed and plumbing complete. (SEE PLUMBING

More information

SWIMMING POOL, SPA, & HOT TUB GUIDELINES

SWIMMING POOL, SPA, & HOT TUB GUIDELINES SWIMMING POOL, SPA, & HOT TUB GUIDELINES Pool permit cost is based on the total value of the project. See Permit Fee Schedule Table 1A. A. Adopted construction codes and installation requirements 1. 2015

More information

www.klmtechgroup.com TABLE OF CONTENT

www.klmtechgroup.com TABLE OF CONTENT Page : 1 of 13 Project Engineering Standard www.klmtechgroup.com KLM Technology #03-12 Block Aronia, Jalan Sri Perkasa 2 Taman Tampoi Utama 81200 Johor Bahru Malaysia ELECTIRAL GROUNDING TABLE OF CONTENT

More information

4 Installation Requirements

4 Installation Requirements 4 Installation Requirements 9 4.1 Code Reference The authority having jurisdiction should be referenced to determine what law, ordinance or code shall apply in the use of flexible duct. Ducts conforming

More information

NORTH ORANGE COUNTY COMMUNITY COLLEGE DISTRICT SECTION 27 05 26 GROUNDING AND BONDING FOR COMMUNICATION SYSTEMS

NORTH ORANGE COUNTY COMMUNITY COLLEGE DISTRICT SECTION 27 05 26 GROUNDING AND BONDING FOR COMMUNICATION SYSTEMS SECTION GROUNDING AND BONDING FOR COMMUNICATION SYSTEMS RELATED SECTIONS: Section 27 00 00 General Requirements Section 27 02 00 Communication General Requirements Section 27 05 28 Pathways for Communications

More information

How To Plan Out An Array Of Solar Panels

How To Plan Out An Array Of Solar Panels CITY OF DOWNEY COMMUNITY DEVELOPMENT, BUILDING AND SAFETY 11111 Brookshire Avenue Downey, CA 90241 562.904.7142 (www.downeyca.org) B SECTION 01/01/2011 EFFECTIVE DATE PHOTOVOLTAIC 032 FORM NUMBER 2013

More information

TS 813 GROUNDING AND BONDING TTD 813.001 TRAFFIC SIGNAL INSTALLATION AND CONTROLLER CABINET GROUNDING SYSTEM TTD 813.005 CONTROLLER CABINET GROUNDING

TS 813 GROUNDING AND BONDING TTD 813.001 TRAFFIC SIGNAL INSTALLATION AND CONTROLLER CABINET GROUNDING SYSTEM TTD 813.005 CONTROLLER CABINET GROUNDING TORONTO TRANSPORTATION January 2012 TS 813 GROUNDING AND BONDING TABLE OF CONTENTS 1. DRAWINGS TTD 813.001 TRAFFIC SIGNAL INSTALLATION AND CONTROLLER CABINET GROUNDING SYSTEM TTD 813.005 CONTROLLER CABINET

More information

METER REQUIREMENTS GENERAL REQUIREMENTS SECTION D

METER REQUIREMENTS GENERAL REQUIREMENTS SECTION D 12 - ELECTRIC SERVICE HANDBOOK SECTION D METER REQUIREMENTS This chapter gives you information on Central Lincoln s metering requirements. It's divided into three sections: General requirements This section

More information

2014 NEC Guide Lines for Home Owner Doing Electrical Work on their Property

2014 NEC Guide Lines for Home Owner Doing Electrical Work on their Property 2014 NEC Guide Lines for Home Owner Doing Electrical Work on their Property A brief summary of the most used code references for residential wiring State of Idaho Division of Building Safety Electrical

More information

1997 Uniform Administrative Code Amendment for Earthen Material and Straw Bale Structures Tucson/Pima County, Arizona

1997 Uniform Administrative Code Amendment for Earthen Material and Straw Bale Structures Tucson/Pima County, Arizona for Earthen Material and Straw Bale Structures SECTION 70 - GENERAL "APPENDIX CHAPTER 7 - EARTHEN MATERIAL STRUCTURES 70. Purpose. The purpose of this chapter is to establish minimum standards of safety

More information

SECTION 611 ACCEPTANCE PROCEDURES FOR TRAFFIC CONTROL SIGNALS AND DEVICES

SECTION 611 ACCEPTANCE PROCEDURES FOR TRAFFIC CONTROL SIGNALS AND DEVICES SECTION 611 ACCEPTANCE PROCEDURES FOR TRAFFIC CONTROL SIGNALS AND DEVICES 611-1 Description. This Section sets forth Contract acceptance procedures for installations of traffic control signals and devices

More information

Please check with your local inspection authority for any additional requirements before installation.

Please check with your local inspection authority for any additional requirements before installation. Specifications for Residential Overhead Electric Service Installation This brochure addresses most typical residential overhead service installations. Variances for the following specifications must be

More information

LIFE SAFETY UPDATE. FULL SPRINKLERING OF ALL NURSING FACILITIES ADDITIONAL CLARIFICATIONS Prepared by Eric Rosenbaum, P.E. Hughes Associates, Inc.

LIFE SAFETY UPDATE. FULL SPRINKLERING OF ALL NURSING FACILITIES ADDITIONAL CLARIFICATIONS Prepared by Eric Rosenbaum, P.E. Hughes Associates, Inc. LIFE SAFETY UPDATE FULL SPRINKLERING OF ALL NURSING FACILITIES ADDITIONAL CLARIFICATIONS Prepared by Eric Rosenbaum, P.E. Hughes Associates, Inc. The purpose of this update is as follows: Remind all state

More information

Fixed Access Ladders. Table of Contents. 1. Legislative Requirements

Fixed Access Ladders. Table of Contents. 1. Legislative Requirements Fixed Access Ladders Engineering Data Sheet 2-04 Revised: January 1997 Table of Contents 1. Legislative Requirements 2. General 3. Rungs 4. Side Rails 5. Safety Cages 6. Attachment & Anchoring 7. Platforms

More information

GROWTH MANAGEMENT DEPARTMENT 201 SE 3 rd ST, (Second Floor), Ocala, FL 34471 (352) 629-8421; FAX: (352) 629-8264

GROWTH MANAGEMENT DEPARTMENT 201 SE 3 rd ST, (Second Floor), Ocala, FL 34471 (352) 629-8421; FAX: (352) 629-8264 BUILDING CODE GUIDELINES FOR ELECTRICAL INSPECTIONS Building Code compliance is the obligation of design professionals and/or contractors. Plan Review and Inspection Guidelines are intended to be used

More information

All work must conform to the National Electric Code, latest edition, and all other applicable codes and regulations.

All work must conform to the National Electric Code, latest edition, and all other applicable codes and regulations. DIVISION 16 ELECTRICAL SECTION 16100 - ELECTRICAL PART 1 - GENERAL SCOPE All electrical work as shown on the drawings and as necessary to provide a complete electrical system. Include primary service,

More information

ELECTRICAL GUIDELINES FOR SINGLE-FAMILY HOME OWNERS:

ELECTRICAL GUIDELINES FOR SINGLE-FAMILY HOME OWNERS: ELECTRICAL GUIDELINES FOR SINGLE-FAMILY HOME OWNERS: Chapter 12 of the Burlington Code of ordinances allows owner occupants of single family homes to do their own wiring if they choose. If you choose to

More information

Electrical Service Guidelines

Electrical Service Guidelines Electrical Service Guidelines Middle Tennessee Electric Membership Corporation Revised: May 23, 2013 MTEMC's Electrical Guidelines TABLE OF CONTENTS Right-of-Way Clearance Guide 3 MTEMC Requirements 4

More information

Pre-Drywall Inspection Report

Pre-Drywall Inspection Report SM MEDALLION INSPECTIONS helping people make informed decisions Pre-Drywall Inspection Report 5657 Garden Valley Place Milton, Georgia 30024 Prepared for Betsy and Paul Dougherty January12, 2015 Medallion

More information

Chapter 9. Bonding and Grounding

Chapter 9. Bonding and Grounding Chapter 9 Bonding and Grounding Objectives Describe why the cable should be bonded Describe bonding and grounding procedures Define Bonding and Grounding Explain Safety Benefits and intent of bonding and

More information

Consultants Handbook

Consultants Handbook Consultants Handbook CONSULTANTS HANDBOOK Welcome to our Wallis Designers Lightning Protection Handbook. This handbook offers a guide for any designers of the structural Lightning protection system to

More information

RACKING AND ATTACHMENT CRITERIA FOR EFFECTIVE MEMBRANE ROOF SYSTEM INTEGRATION Public Version 1: July 9, 2012

RACKING AND ATTACHMENT CRITERIA FOR EFFECTIVE MEMBRANE ROOF SYSTEM INTEGRATION Public Version 1: July 9, 2012 RACKING AND ATTACHMENT CRITERIA FOR EFFECTIVE MEMBRANE ROOF SYSTEM INTEGRATION Public Version 1: July 9, 2012 Commercial rooftops represent the most available, sustainable and secure real estate for new

More information

Vision Home Inspection

Vision Home Inspection Vision Home Inspection 324 Rams Run Shepherdsville KY 40165-7877 Inspector: James McFadden Property Inspection Report Client(s): Property address: Inspection date: View report summary This report is the

More information

FIRESTOPPING & SMOKE SEALS

FIRESTOPPING & SMOKE SEALS SPECIFICATION SECTION 07 84 00 FIRESTOPPING & SMOKE SEALS 1 GENERAL 1.1 SECTION INCLUDES 1.1.1 Comply with Division 1, General Requirements and Documents referred to therein. 1.1.2 It is the intent of

More information

Final inspections are completed by site visit only. Access to fenced yards shall be planned.

Final inspections are completed by site visit only. Access to fenced yards shall be planned. ROOFING RESIDENTIAL BUILDING INSPECTIONS DEPARTMENT www.ci.blaine.mn.us This handout is intended only as a guide and is based in part on the 2015 Minnesota State Building Code, Blaine City ordinances,

More information

Commercial Roof Management

Commercial Roof Management Disclaimer: This material is designed and intended for general informational purposes only, and is not intended, nor shall it be construed or relied upon, as specific legal advice. Roof damage is a leading

More information

Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016. Underground branch circuit feeding a detached garage:

Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016. Underground branch circuit feeding a detached garage: Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016 * Garage construction requires permits (electrical, building) * Permits must be applied for at the time. * Dial

More information

Excerpts from the Canadian National Building Code (NBC)

Excerpts from the Canadian National Building Code (NBC) Excerpts from the Canadian National Building Code (NBC) Reproduced here with Permission of the Copyright Owner, the National Research Council of Canada, Institute for Research in Construction. For more

More information

Asphalt Shingle Application Requirements

Asphalt Shingle Application Requirements Alberta Allied Roofing Association Asphalt Shingle Application Requirements Section 1 Roof Decks 1.1 General Asphalt Shingles are not permitted to be installed directly over rigid insulation. When Asphalt

More information

SECTION 15410 GROUND WATER STORAGE TANKS

SECTION 15410 GROUND WATER STORAGE TANKS SECTION 15410 GROUND WATER STORAGE TANKS PART 1 GENERAL.01 SCOPE A. Section Includes Requirements for designing, fabricating, and erecting a welded steel ground storage tank..02 SYSTEM DESCRIPTION A. Design

More information

CITY OF SELMA, TEXAS Inspection Checklist: Commercial

CITY OF SELMA, TEXAS Inspection Checklist: Commercial Rev Y71004 The Permits and Inspections Department welcomes you to the City of Selma. The following information is provided to you as guidance through the inspection process. The City of Selma provides

More information

2. Division 05 Structural Steel Framing for steel framework requirements

2. Division 05 Structural Steel Framing for steel framework requirements SECTION 131200 - CLIMBING WALLS PART 1 GENERAL 1.1 SUMMARY A. This section includes the following: 1. GFRC Rock Realistic Climbing Wall System B. Related Sections 1. Division 04 Unit Masonry 2. Division

More information

Residential Deck Safety, Construction, and Repair

Residential Deck Safety, Construction, and Repair Juneau Permit Center, 4 th Floor Marine View Center, (907)586-0770 This handout is designed to help you build your deck to comply with the 2006 International Residential Building code as modified by the

More information

RESIDENTIAL ELECTRICAL REQUIREMENTS (REVISED 3/28/2008) PERMIT REQUIREMENTS:

RESIDENTIAL ELECTRICAL REQUIREMENTS (REVISED 3/28/2008) PERMIT REQUIREMENTS: RESIDENTIAL ELECTRICAL REQUIREMENTS (REVISED 3/28/2008) PERMIT REQUIREMENTS: Signed completed Electrical Permit application form. Minnesota law requires all electrical work is to be performed by licensed,

More information

SECTION 28 05 00 COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY

SECTION 28 05 00 COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY SECTION 28 05 00 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specifications Sections, apply

More information

INSTALLATION OF A BAY WINDOW

INSTALLATION OF A BAY WINDOW INSTALLATION OF A BAY WINDOW Installation of a Bay Window These instructions relate to the replacement of an existing bay window or replacement of a straight window with a new bay window, in an opening

More information

FIREFINDER XLS ADDRESSABLE FIRE ALARM SYSTEM SECTION 13851

FIREFINDER XLS ADDRESSABLE FIRE ALARM SYSTEM SECTION 13851 FIREFINDER XLS ADDRESSABLE FIRE ALARM SYSTEM SECTION 13851 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and

More information

OPEN ITEMS LIST - CONSTRUCTION Project Name: East Central Middle School - Jackson County CLA#: 11003

OPEN ITEMS LIST - CONSTRUCTION Project Name: East Central Middle School - Jackson County CLA#: 11003 OPEN ITEMS LIST - CONSTRUCTION Project Name: East Central Middle School - Jackson County CLA#: 11003 No. Discipline Sent to Name Item Date Noted Date Resolved How item was resolved Electrical Contractor

More information

DESIGN AND INSTALLATION OF RESIDENTIAL FLEXIBLE DUCTWORK SYSTEMS

DESIGN AND INSTALLATION OF RESIDENTIAL FLEXIBLE DUCTWORK SYSTEMS DESIGN AND INSTALLATION OF RESIDENTIAL FLEXIBLE DUCTWORK SYSTEMS A. SCOPE 1. This information is intended to assist contractors, installers and code officials in the proper design and installation of flexible

More information

INTERNATIONAL STANDARD

INTERNATIONAL STANDARD INTERNATIONAL STANDARD IEC 62305-3 Edition 2.0 2010-12 colour inside Protection against lightning Part 3: Physical damage to structures and life hazard INTERNATIONAL ELECTROTECHNICAL COMMISSION PRICE CODE

More information

STREETLIGHT SYSTEM GROUNDING AND BONDING

STREETLIGHT SYSTEM GROUNDING AND BONDING Page: 1 of 8 STREETLIGHT SYSTEM GROUNDING AND BONDING 1. Scope This Construction Standard covers the grounding and bonding requirements for single phase streetlight systems served by the Looped Radial

More information

Requirements for Electrical Installations

Requirements for Electrical Installations ARTICLE 110 Requirements for Electrical Installations INTRODUCTION TO ARTICLE 110 REQUIREMENTS FOR ELECTRICAL INSTALLATIONS Article 110 sets the stage for how you ll implement the rest of the NEC. This

More information

Minimum Standards for Data/Voice Infrastructure in New Building Construction

Minimum Standards for Data/Voice Infrastructure in New Building Construction UNIVERSITY OF WATERLOO Minimum Standards for Data/Voice Infrastructure in New Building Construction 12/17/2012 Offices 1. Two Work Area Outlets (WAO) on opposite walls, each with 2 jacks 2. Each WAO shall

More information

Certification: Building Plans Examiner. Exam ID: B3

Certification: Building Plans Examiner. Exam ID: B3 Certification: Building Plans Examiner Exam ID: B3 Scope: A Building Plans Examiner will be responsible for reviewing submitted plans to determine if they meet the requirements of the various Building

More information

Packaged Terminal Air Conditioner Wall Sleeve Installation

Packaged Terminal Air Conditioner Wall Sleeve Installation Installation & Maintenance Data IM 1196 Group: PTAC Part Number: 910141799 Date: October 2013 Packaged Terminal Air Conditioner Installation x 42" PGAN with Top-Mounted Hydronic Heat Note: Installation

More information

Elevating Your House. Introduction CHAPTER 5

Elevating Your House. Introduction CHAPTER 5 CHAPTER 5 Elevating Your House Introduction One of the most common retrofitting methods is elevating a house to a required or desired Flood Protection Elevation (FPE). When a house is properly elevated,

More information

ELECTRICAL SERVICE REQUIREMENTS FOR MOBILE HOME DEVELOPMENTS

ELECTRICAL SERVICE REQUIREMENTS FOR MOBILE HOME DEVELOPMENTS Prepared by: ABB1 ELECTRICAL SERVICE REQUIREMENTS FOR MOBILE HOME DEVELOPMENTS 052521 Asset Type: Electric Metering Function: Construction Issued by: Quoc Hoang (QxH1) Date: 07-01-16 Rev. #06: This document

More information

Grounding & Bonding Why it is done And How to Install Properly

Grounding & Bonding Why it is done And How to Install Properly Grounding & Bonding Why it is done And How to Install Properly The technical information provided herein is to assist qualifi ed persons in planning and installing electric service to farms and residences.

More information

HEDDERMAN ENGINEERING, INC. www.heddermanengineering.com Office 281-355-9911, Fax 281-355-9903 office@heddermanengineering.com

HEDDERMAN ENGINEERING, INC. www.heddermanengineering.com Office 281-355-9911, Fax 281-355-9903 office@heddermanengineering.com HEDDERMAN ENGINEERING, INC. www.heddermanengineering.com Office 281-355-9911, Fax 281-355-9903 office@heddermanengineering.com, 2011 TO: Mr. REF: CONDITION OF PROPERTY SURVEY Dear Mr. : At your request,

More information

SECTION 11014 WINDOW WASHING SYSTEMS

SECTION 11014 WINDOW WASHING SYSTEMS SECTION 11014 WINDOW WASHING SYSTEMS PART 1 - GENERAL 1.1 SUMMARY A. Section includes, but is not limited to, design and furnishing portable davits, davit sleeves, dvit bases, four (4) removable outriggers,

More information

EAST LYME HIGH SCHOOL

EAST LYME HIGH SCHOOL Overview: 1971 N 1966 GYM 1966 CLASSROOM WING 1966 AUD. 1971 GYM 1998 1998 POOL EAST LYME HIGH SCHOOL Original 1966 Building: The original East Lyme High School was constructed in 1966 and was composed

More information

Roof Inspection. Summary Report

Roof Inspection. Summary Report Phone: (561) 866 9956 www.real-estate-inspections.com Roof Inspection Summary Report Subject Property File Number: 05-15-RF-002 Inspector: Craig Milliken, PE CPM Real Estate Inspections, Inc. Date of Inspection:

More information

RESIDENTIAL ROOFING & RE-ROOFING, ROOF VENTILATION AND ROOF SHEATHING REQUIREMENTS MICHIGAN RESIDENTIAL CODE 2000

RESIDENTIAL ROOFING & RE-ROOFING, ROOF VENTILATION AND ROOF SHEATHING REQUIREMENTS MICHIGAN RESIDENTIAL CODE 2000 RESIDENTIAL ROOFING & RE-ROOFING, ROOF VENTILATION AND ROOF SHEATHING REQUIREMENTS MICHIGAN RESIDENTIAL CODE 2000 SECTION R905 REQUIREMENTS FOR ROOF COVERINGS R905.1 Roof covering application. Roof coverings

More information

READ THIS MANUAL BEFORE PROCEEDING WITH THE INSTALLATION. FAILURE TO FOLLOW THE INSTALLATION INSTRUCTIONS MAY VOID YOUR WARRANTY!

READ THIS MANUAL BEFORE PROCEEDING WITH THE INSTALLATION. FAILURE TO FOLLOW THE INSTALLATION INSTRUCTIONS MAY VOID YOUR WARRANTY! READ THIS MANUAL BEFORE PROCEEDING WITH THE INSTALLATION. FAILURE TO FOLLOW THE INSTALLATION INSTRUCTIONS MAY VOID YOUR WARRANTY! The main power to any existing system must be disconnected prior to the

More information

METHOD STATEMENT FOR INSTALLATION OF CABLE TRAY/TRUNKING/LADDER

METHOD STATEMENT FOR INSTALLATION OF CABLE TRAY/TRUNKING/LADDER Page 1 of 6 FOR INSTALLATION OF CABLE TRAY/TRUNKING/LADDER 0 Issued for Review & Comments Rev. Date Description Eng. A.H Prepared by Checked by Approved by Page 2 of 6 REVISION CONTROL SHEET REV. NO. DATE

More information

The minimum reinforcement for the stem wall is the placement of:

The minimum reinforcement for the stem wall is the placement of: PolySteel creates an ideal insulated stem wall for concrete slabs that can make this part of your project easier and faster, in addition to making your finished project more energy-efficient. Figures 3.20

More information

ELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1

ELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1 KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1 PART 1 - GENERAL 1.01 RELATED DOCUMENTS: SECTION 16050 A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division-1

More information

City of San Diego Residential Photovoltaic Systems Inspection Guidelines

City of San Diego Residential Photovoltaic Systems Inspection Guidelines City of San Diego Residential Photovoltaic Systems Inspection Guidelines The purpose of inspections by DSD staff is to ensure compliance with the California Electrical Code (CEC), other applicable codes

More information

General Fire Code Requirements Within Commercial Tenant Spaces

General Fire Code Requirements Within Commercial Tenant Spaces FIRE DEPARTMENT in cooperation with Scope: General Fire Code Requirements Within Commercial Tenant Spaces This handout is designed to assist owners, architects, contractors and others in understanding

More information

RESIDENTIAL FOUNDATION GUIDELINE Johnson County, KS

RESIDENTIAL FOUNDATION GUIDELINE Johnson County, KS RESIDENTIAL FOUNDATION GUIDELINE Johnson County, KS Johnson County Building Officials Association January 2008 Residential Foundation Guideline Foundation designs for one-and two-family dwellings may use

More information

Exterior Elevated Elements Inspection Guidelines

Exterior Elevated Elements Inspection Guidelines Exterior Elevated Elements Inspection Guidelines Planning and Development 1. Guideline Purpose These guidelines are intended to assist practicing professionals in complying with Berkeley Municipal Code

More information

Wastewater Capital Projects Management Standard Construction Specification

Wastewater Capital Projects Management Standard Construction Specification CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 10.1 Precast Concrete Pipe 10.1.1 General This section covers material requirements,

More information

Lighthouse Engineering, L.L.C.

Lighthouse Engineering, L.L.C. Registered Engineering Firm (F: 9334) Phone: 214-577-1077 Fax: 214-224-0549 Website: www.lighthouseeng.com Email: Office@LighthouseEng.com Thursday, September 04, 2014 TO: Our Client RE: Initial Engineering

More information

Building Code Inspections and Fees

Building Code Inspections and Fees St. Mary s County Department of Land Use & Growth Management Customer Assistance Guide 22 Building Code Inspections and Fees May 10, 2014 This guide is intended to assist in the proper construction sequence

More information

REVEWED BY: Ross Rogien B.O/P.R. ADDITIONAL REVIEW(S) REQ.-FIRE DEPT Y/N

REVEWED BY: Ross Rogien B.O/P.R. ADDITIONAL REVIEW(S) REQ.-FIRE DEPT Y/N PLAN REVIEW FOR: PROJECT NAME: OWNER: ARCH/DESIGNER: ADDRESS: Ph/Fx: Plans Dated: E-mail: Sealed By: Estimated Project Cost - $ REVEWED BY: Ross Rogien B.O/P.R. ADDITIONAL REVIEW(S) REQ.-FIRE DEPT Y/N

More information

The Contractor shall furnish and install all shielded power cable suitable for use on this project.

The Contractor shall furnish and install all shielded power cable suitable for use on this project. Section 16122 PRIMARY POWER CABLES PART 1 GENERAL: WORK INCLUDED The Contractor shall furnish and install all shielded power cable suitable for use on this project. RELATED WORK Section 16020: Tests SUBMITTALS

More information

FIRE ALARM SYSTEM. A. Shop drawings shall be submitted as follows: 1. Manufacturer's published literature. for aspproval.

FIRE ALARM SYSTEM. A. Shop drawings shall be submitted as follows: 1. Manufacturer's published literature. for aspproval. Polk School District Specifications for the New Fire Alarm in the Existing Building Eastside Elementary School FIRE ALARM SYSTEM 1.01 SUBMITTALS A. Shop drawings shall be submitted as follows: 1. Manufacturer's

More information

UNIVERSITY OF WASHINGTON Facilities Services Design Guide. Architectural. Roofing. Basis of Design

UNIVERSITY OF WASHINGTON Facilities Services Design Guide. Architectural. Roofing. Basis of Design Basis of Design This section applies to roofing membranes, flashing and accessories. Design Criteria Adhere to the standards and details of the latest editions of the National Contractors Association (NRCA)

More information

CONTENTS. Yale University Design Standards. Underground Electrical Duct Bank. A. Summary. B. System Design and Performance Requirements

CONTENTS. Yale University Design Standards. Underground Electrical Duct Bank. A. Summary. B. System Design and Performance Requirements 16600 Underground Electrical Duct Bank This document provides design standards only, and is not intended for use, in whole or in part, as a specification. Do not copy this information verbatim in specifications

More information

Basement Moisture Problems

Basement Moisture Problems Foundations Foundation Purpose The purpose of a foundation is to distribute the weight of a structure securely into the ground. Engineering data regarding soil, rock and water conditions are used to design

More information

POST AND FRAME STRUCTURES (Pole Barns)

POST AND FRAME STRUCTURES (Pole Barns) POST AND FRAME STRUCTURES (Pole Barns) Post and frame structures. The following requirements serve as minimum standards for post and frame structures within all of the following structural limitations:

More information

ADDENDUM NO. 2 TO PROJECT NO. 43153

ADDENDUM NO. 2 TO PROJECT NO. 43153 ADDENDUM NO. 2 TO PROJECT NO. 43153 CONSTRUCTION WORK, MECHANICAL WORK, PLUMBING WORK, ELECTRICAL WORK PROVIDE VISITOR CENTER BUILDING AND SITE IMPROVEMENTS FIVE RIVERS ENVIRONMENTAL EDUCTION CENTER 56

More information

AT&T Specifications Trenching Conduit Boxes and M anholes Aerial Entrance Masts Service Cabinets Bonding and Grounding

AT&T Specifications Trenching Conduit Boxes and M anholes Aerial Entrance Masts Service Cabinets Bonding and Grounding AT&T Specifications Trenching Conduit Boxes and M anholes Aerial Entrance Masts Service Cabinets Bonding and Grounding A Guide for California Developers of Com m ercial Property This guide consists of

More information

City of Tucson and Pima County Arizona Building Code Appendix Chapter 72 Straw-Bale Structures

City of Tucson and Pima County Arizona Building Code Appendix Chapter 72 Straw-Bale Structures City of Tucson and Pima County Arizona Building Code Appendix Chapter 72 Straw-Bale Structures SECTION 7201 - PURPOSE The purpose of this appendix chapter is to establish minimum prescriptive standards

More information

A. The shade structure contractor shall be responsible for the design, engineering, fabrication, and supply of the work specified herein.

A. The shade structure contractor shall be responsible for the design, engineering, fabrication, and supply of the work specified herein. 13310 FABRIC SHADE STRUCTURES FOR PLAYGROUND AREAS ************************************************************************************************************************ SPECIFIER: CSI Master Format

More information

SECTION 807 PUMP STATION REHABILITATION

SECTION 807 PUMP STATION REHABILITATION SECTION 807 PUMP STATION REHABILITATION 807-1 DESCRIPTION: Rehabilitation of pump stations shall be defined as the cleaning, removal, repair and/or replacement of any and/or all components including but

More information

Summit Anchor Company, Inc.

Summit Anchor Company, Inc. Summit Anchor Company, Inc. Safety From The Top Down Roof and Wall Safety/Tie-Back Anchors Suspended Access Systems and Fall Protection Overview National Safety Standards OSHA regulations specifically

More information

STANDARD PROCEDURES FOR INSTALLATION OF METAL ROOF SYSTEMS

STANDARD PROCEDURES FOR INSTALLATION OF METAL ROOF SYSTEMS ROOFING APPLICATION STANDARD (RAS) No. 133 STANDARD PROCEDURES FOR INSTALLATION OF METAL ROOF SYSTEMS 1. Scope 1.1 This application standard has been developed to provide consistent information for the

More information

Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing

Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing 1 Most basements show some signs of leaking and cracking. Through the years, problems with water, poor soils, grading, drainage and possible settling affect the integrity of a basement. Being able to recognize

More information

DRAINAGE MATS For Vertical: Flow 15-P For Horizontal: Flow 18-H

DRAINAGE MATS For Vertical: Flow 15-P For Horizontal: Flow 18-H DRAINAGE MATS For Vertical: Flow 15-P For Horizontal: Flow 18-H Soil Drainage Mat with Built-In Protection Layer POLYGUARD DRAINAGE MATS are three-part prefabricated geocomposite drain consisting of a

More information

SECTION 260536 - CABLE TRAYS. A. Continuous, rigid, welded steel or stainless steel wire mesh cable management system.

SECTION 260536 - CABLE TRAYS. A. Continuous, rigid, welded steel or stainless steel wire mesh cable management system. SECTION 260536 - CABLE TRAYS PART 1 - GENERAL SECTION INCLUDES: A. Continuous, rigid, welded steel or stainless steel wire mesh cable management system. B. Cable tray systems are defined to include, but

More information

Trial Exams C. Standards and Regulations. Examination No: GH-08-C- 1 hour and 5 minutes plus 10 minutes reading time

Trial Exams C. Standards and Regulations. Examination No: GH-08-C- 1 hour and 5 minutes plus 10 minutes reading time Trial Exams C Standards and Regulations Examination No: GH-08-C- This test is intended to gauge your knowledge of essential information contained within AS/CA S009:2013. To qualify for an allpication to

More information

CITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT

CITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT Page 1 CITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT CIVIC CENTRE 2141 MAJOR MACKENZIE DRIVE MAPLE ONTARIO L6A 1T1 905-832-2281 Page 2 SECTION 1 - GENERAL OBJECTIVES To provide

More information

3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees.

3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees. The following shall serve as the minimum requirements for contractors performing work in relation to the Authority s potable water and sanitary sewer system(s), appurtenances and service connections. General:

More information

The Florida Building Code

The Florida Building Code Setting New Standards for Safety The Florida Building Code Florida Building Commission Florida Department of Community Affairs The Florida Building Code System The Florida Building Commission Florida Building

More information