SUMMARY OF BILL OF QUANTITIES
|
|
- Philomena Cross
- 7 years ago
- Views:
Transcription
1 SUMMARY OF BILL OF QUANTITIES GN. FUVAHMULAKU JETTY Summary Bill No Description Amount 1 PRELIMINERIES GROUND WORK CONCRETE MASONRY, PLASTERING METAL AND TIMBER WORKS ROOFING CIELINGS PAINTING ELECRICAL INSTALLATIONS TENDERER'S ADJUSTMENTS 0.00 GRAND TOTAL carried to form of bid 0.00 Page 1
2 Gn. Fuvahmulaku Jetty Bill of Quantities Item Description Unit Qty Rate Total BILL No: 01 PRELIMINARIES 1.1 General Notes (1) Abbreviations m - metre No - numbers m 3 - cubic metre m 2 - square metre Lm - Linear metre t - tonnes incl - including mm - millimetre dia - diameter SS - Stainless steel GI - Galvonized iron 1.2 Site Management Costs (1) Allow for all on and off site management cost including costs of forman and asistants, temporaryservices,telephone,fax,hoardings and similar item Sign Board (1) Allow for sign boards item Clean-up (1) Allow for clean-up of completed works and site upon completion. item BILL No: 01 - PRELIMINERIES TOTAL OF BILL No: 01 - Carried over to summary 0.00 Page 2
3 Gn. Fuvahmulaku Jetty Bill of Quantities Item Description Unit Qty Rate Total BILL No: 02 GROUND WORKS 2.1 General (a) Rates shall include for: levelling, Grading, Trimming, Compacting to faces of excavation, keeping sides plumb, backfilling, consolidating and disposing surplus soil. 2.2 Site Clearing (1) Clearing site including trees less than 0.5m girth complete with situmps and roots. item Excavation (a) Excavation quantities are measured to the faces of concrete members. Rates shall include for all additional excavation required to place the formwork. Excavation for (1) Foundation beam TB1 & TB2 m Back Filling (a) Rates shall include for levelling, grading, trimming and compacting. (1) Backfilling to get level of 150mm below G.L item (2) Minimum 150mm thick hardcore on compacted ground item (3) 25mm thick sand bedding on hardcore item BILL No: 02 - GROUND WORKS TOTAL OF BILL No: 02 - Carried over to summary 0.00 Page 3
4 Gn. Fuvahmulaku Jetty Bill of Quantities Item Description Unit Qty Rate Total BILL No: 03 CONCRETE 3.1 General (a) Rates shall include for: placing in position; making good after removal of formwork and casting in all required items to conform to structural and excavated tolerences (b) Rates shall include making and transporting of formwork, oil, nails (c) Mix ratio for reinforced concrete shall be 1:2:3 and lean concrete shall be 1:2:6 by volume. (d) Rates shall include for: cleaning, fabrication, placing, the provision for all necessary temporary fixings and supports including tie wire and chair supports, laps and wastage (e) All reinforcing bars shall be high strength bars (1) Allow for concrete testing item Lean Concrete (a) Quantity is measured to the edges of concrete foundation memebers. Rates shall be inclusive of any additional concrete required to place the formwork. 50mm thick lean concrete to bottom of (1) Foundation beam TB1 & TB2 m Reinforced Concrete In-situ reinforced concrete to: Foundations (1) Foundation Pad F1 m (2) Foundation Beam TB1 & TB2 m Ground floor Columns (1) C1 Column, 250x250 m (2) C2 Column, 200x200 m Stair & Slab (1) Stair & Slab m Roof Level Attached Beams (1) Beam RB, 300x200 m WATER PROOFING (1) Apply slurry type water proofing to all surfaces of concrete below ground level in accordance with manufacturer's instructions. item BILL No: 03 - CONCRETE WORKS TOTAL OF BILL No: 03 - Carried over to summary 0.00 Page 4
5 Gn. Fuvahmulaku Jetty Bill of Quantities Item Description Unit Qty Rate Total BILL No: 04 MASONRY AND PLASTERING 4.1 GENERAL (a) Rates shall include for: cleaning out cavities, forming rebated reveals and pointing and cleaning down to reveals where necessary; fractional size blocks, all necessary machine cutting, cutting or forming chases or edges of floor slabs, cutting or leaving holes and openings as recesses for and building in pipes, conduits, sleeves and similar as required for all trades; leaving surfaces rough or raking out joints for plastering and flashings, bedding frames or plates, building in joists, bearers or similar, temporary supports to openings, templates, reinforcement in walls and for all necessary making good 4.2 Cement blockwork mm wide Cement Solid blocks, laid on and incl. mortar, tie rods, compression joint gap filler, nylon / plastic mesh as specified (1) Ground Floor m Plastering (a) Cement plastering on walls and concrete surfaces as specified incl. wire mesh at the joints of concrete surfaces and walls and water proofing additives / admixtures for all surfaces mm plaster on exterio of walls and concrete faces (1) Ground Floor m BILL No: 04 - MASONRY AND PLASTERING TOTAL OF BILL No: 04 - Carried over to summary 0.00 Page 5
6 Gn. Fuvahmulaku Jetty Bill of Quantities Item Description Unit Qty Rate Total BILL No: 05 METAL AND TIMBER WORKS 5.1 GENERAL (a) Rates shall include for: all fabrication work, welding, marking, drilling for bolts including those securing timbers, steel plates, bolts, nuts and any type of washer, riveted work, counter sinking and tapping for bolts or machine screws. (b) Rates shall include for all polishing and finishing as specified (c) Rates shall include for fabrication and erection and temporary supports and fixing into position 5.2 SS railing (1) 50mm dia SS pipe handrail (railing between columns) including all fixings and finishes complete as shown in the drawing Item Timber Roof structure Timber roof structure, including all fixings and complete as shown in the drawings to; (1) 50 x 150mm timber ridge members m (2) 50 x 100mm timber rafters m (3) 50 x 35mm timber battens m (4) 100 x 50mm timber wall plate m (5) Timber concealings Item 0.00 (6) Timber Decorative partitions Item 0.00 BILL No: 05 - MASONRY AND PLASTERING TOTAL OF BILL No: 05 - Carried over to summary 0.00 Page 6
7 Gn. Fuvahmulaku Jetty Bill of Quantities Item Description Unit Qty Rate Total BILL No: 06 ROOFING 6.1 General (a) Rates shall include for: fair edges,dressing over angel fillets, turning into grooves, all other labours, circular edges, nails, screws and other fixings and laps. 6.2 Roof Coverings Roofing Sheets (1) Lysaght (or equivalent) roofing sheets, inclusive of all fixtures, fixed in accordance with manufacturer's instructions m Capping and Flashing (1) 400 mm Girth Ridge Capping (HIP flashing) fixed in accordance with manufacturer's instructions (Rate shall include all fixtures) m Gutters & Downpipes Gutter (1) 150 x 150 mm Lysaught Gutter or equivalent, rates shall include for framing, supports, clips, brackets, stop-ends, down-pipe outlets, fixing and fastening m (2) 100mm dia. PVC Downpipes including all bends junctions, straps, brackets and clips m Insulations Rock Wool Insulation (1) Rock Wool Insulation with Aluminium foil on both sides, Rates shall include for wire mesh, nails, and all necessary fixtures m BILL No: 06 - ROOFING TOTAL OF BILL No: 06 - Carried over to summary 0.00 Page 7
8 Gn. Fuvahmulaku Jetty Bill of Quantities Item Description Unit Qty Rate Total BILL No: 7 CEILINGS 7.1 Plasterboard (External) Plasterboard ceiling panels on timber framework including trimming, nails, screws and other fixings. (1) Ground floor m BILL No: 07 - CEILINGS TOTAL OF BILL No: 07 - Carried over to summary 0.00 Page 8
9 Gn. Fuvahmulaku Jetty Bill of Quantities Item Description Unit Qty Rate Total BILL No: 8 PAINTING 8.1 General (a) Rates shall include for: the provision, erection and removal of scaffolding, preparation, rubbing down between coats and similar work, the protection and / or masking floors, fittings and similar works (b) All painting work shall be in accordance with the specifications 8.2 Columns Ceramic paint finish (1) Circuler columns no Ceilings Emulsion paint finish shall be "nippon" or equivalent on ceilings (1) Ground floor m BILL No: 08 - PAINTING TOTAL OF BILL No: 08 - Carried over to summary 0.00 Page 9
10 Gn. Fuvahmulaku Jetty Bill of Quantities Item Description Unit Qty Rate Total BILL No: 09 ELECTRICAL INSTALLATIONS 9.1 General (a) Rates shall include for: screws, nails, bolts, nuts, standard cable fixing or supporting clips, brackets, straps, rivets, plugs and all incidential accessories. (b) Rates for work in trench shall include for: excavation, maintaining faces of excavations, backfilling, compaction, appropriate cable covers, warning tape and disposal of surplus spoil. (c) Rates for work in trench shall include for electrical condiuts, fittings, equipment and similar all fixings to various building surfaces (d) Each Light / light fixtures and its switch is measured as one point; similarly each fan or each socket oulet is measured as one point; installation (f) All main distribution boards are 3 phase. 9.2 Electrical wiring Electrical wiring with copper conductor cable in conduits in walls and in casing on soffits of slab as specified to: (1) Wiring with 1.5mm2 cable to lighting points Lighting (1) Ceiling mount light (weatherproof) nos Light switches (a) All light switches shall be "Clipsal" or equivalent (1) One way switch no BILL No: 09 - ELECTRICAL INSTALLATIONS TOTAL OF BILL No: 09 - Carried over to summary 0.00 Page 10
11 Gn. Fuvahmulaku Jetty Bill of Quantities Item Description Unit Qty Rate Total BILL No: 10 TENDERER'S ADJUSTMENTS (a) Provide detail description of work items under each bill and insert extra page if required 10.1 Additions 1 Premilinaries - Bill no:1 2 Ground works - Bill no:2 3 Concrete - Bill no:3 4 Masonry and plastering - Bill no:4 5 Metal and Timber works - Bill no: 5 6 Roofing - Bill no:6 7 Ceiling - Bill no:7 8 Painting - Bill no:8 9 Electrical installations - Bill no:9 ADDITIONAL TOTAL 10.2 Omissions 1 Premilinaries - Bill no:1 2 Ground works - Bill no:2 3 Concrete - Bill no:3 4 Masonry and plastering - Bill no:4 5 Metal and Timber works - Bill no: 5 6 Roofing - Bill no:6 7 Ceiling - Bill no:7 8 Painting - Bill no:8 9 Electrical installations - Bill no:9 OMISSIONS TOTAL BILL No: 10 - TENDERER'S ADJUSTMENTS TOTAL OF BILL No: 10 - Carried over to summary 0.00 Page 11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
BILL OF QUANTITY FOR THE WORK OF "REPAIRING OF CIVIL & PLUMBING WORKS INSIDE AND OUTSIDE OF THE WORKSHOP"
BILL OF QUANTITY FOR THE WORK OF "REPAIRING OF CIVIL & PLUMBING WORKS INSIDE AND OUTSIDE OF THE WORKSHOP" Sl. 1 DISMANTLING WORK 1.1 Stripping off worn out plaster (outside and inside) and raking out joints
More informationInstallation Details. D1 General D2 Walls D3 Ceilings D4 Reference. D Installation Details
D Installation Details D1 General D2 Walls D3 Ceilings D4 Reference D Installation Details D Contents D1 General Installation and Fastening Sequence for Steel Studs D1.1 Fastener Selection D1.3 D2 Walls
More informationChapter. Restoration of Damaged Structures
5 Chapter Restoration of Damaged Structures Bringing back a damaged structure to its pre-earthquake state and original strength is called restoration. This is the first step of building rehabilitation.
More informationBOQ for Plumbing, Sanitary Works
BOQ for Plumbing, Sanitary Works Page 1 of 6 Sr.No Item Description Quantity Unit Rate Amount (Rs.) 1 SANITARY FIXTURES Providing & Fixing star white colour vitreous china wall mounted wc with 1a heavy
More informationPROJECT TITLE : 2-STOREY RESIDENCE LOCATION : ALONG DAANG HARI,MOLINO.BACOOR,CAVITE OWNER : CUEVASVILLE REALTY
PROJECT TITLE : 2-STOREY RESIDENCE LOCATION : ALONG DAANG HARI,MOLINO.BACOOR,CAVITE OWNER : CUEVASVILLE REALTY GENERAL SPECIFICATIONS These specifications are intended to cover the construction of the
More informationSTRUCTURAL CONCEPT FOR LIGHT GAUGE STEEL FRAME SYSTEM
Chapter 9 STRUCTURAL CONCEPT FOR LIGHT GAUGE STEEL FRAME SYSTEM 9.1 BACKGROUND Steel is widely used in the construction of multi-storey buildings. However, steel construction is seldom used and is traditionally
More informationFLAT ROOF CARPORT RECOMMENDED INSTRUCTION MANUAL
FLAT ROOF CARPORT RECOMMENDED INSTRUCTION MANUAL Table of Contents Introduction... 2 Components... 3 Step 1 Marking out the Perimeter of the Carport... 3 Step 2a Footing Set-Out for Concrete Block Pad
More informationNRG 75 CRF NRG GREENBOARD WALL SYSTEM
NRG GREENBOARD WALL SYSTEM NRG Energy Efficient Building Systems is pleased to announce a revolution in lightweight cladding systems. NRG Building Systems is the first and only company to achieve CodeMark
More informationCost Guide MARKET SUMMARY OVERVIEW REPAIRS AND MAINTENANCE ELECTRICAL ROOFING & ROOF DRAINAGE (UP TO TWO STOREYS; FIXED TO EXISTING ROOF FRAME)
Cost Guide < 1 > MARKET SUMMARY OVERVIEW Low interest rates and competitive construction pricing makes now a great time to renovate or build a new home. Interest rates are at historic lows and can be fixed
More informationFLAT ROOF BOX SPAN CARPORTS
AGS/NC/03 FLAT ROOF BOX SPAN CARPORTS Thank you for choosing this quality product. We strongly recommend that you read these instructions thoroughly. Please take your time and do not rush the erection
More informationGENERAL SPECIFICATION FOR CIVIL ENGINEERING WORKS SECTION 13 WORK FOR ELECTRICAL AND MECHANICAL INSTALLATIONS
GENERAL SPECIFICATION FOR CIVIL ENGINEERING WORKS SECTION 13 WORK FOR ELECTRICAL AND MECHANICAL INSTALLATIONS 13.1 13.2 2006 Edition SECTION 13 WORK FOR ELECTRICAL AND MECHANICAL INSTALLATIONS GENERAL
More informationnecessary for years of satisfactory service. SmartBlock insulating form concrete walls share the
Chapter 7 PLUMBING AND ELECTRICAL 7.1 Introduction to Plumbing and Electrical Consideration of support services such as plumbing and electrical systems from the preliminary schematics phase through final
More informationSchedule of Quantities
CIVIL WORK (A) 1 Providing and fixing corrugated galvanised iron sheets of 20 B.W.G. for roofing with wind ties including fastening with galvanised iron screw and bolts and lead and bitumen washers as
More informationINSTALLATION OF A BAY WINDOW
INSTALLATION OF A BAY WINDOW Installation of a Bay Window These instructions relate to the replacement of an existing bay window or replacement of a straight window with a new bay window, in an opening
More informationInstruction Manual 19/9/01. Flat Roof Carport
Flat Roof Carport Thank you for choosing this quality carport. We strongly recommend that you read these instructions thoroughly. The carport you are building may vary from a carport previously bought
More informationSECTION 02400 - STORM DRAIN SYSTEM
SECTION 02400 - STORM DRAIN SYSTEM CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement And
More informationCHAPTER 2 QUANTITY TAKE-OFF
CHAPTER 2 QUANTITY TAKEOFF The quantity takeoff is an important part of the cost estimate. It must be as accurate as possible and should be based on all available engineering and design data. Use of appropriate
More informationSTEP-BY-STEP. construction guide. Delivering better priced Conservatories, Sun Lounges and Garden Rooms via the Internet.
STEP-BY-STEP construction guide Delivering better priced Conservatories, Sun Lounges and Garden Rooms via the Internet. Welcome to our CONSERVATORY AND SUNROOM CONSTRUCTION GUIDE What is the specification
More informationElectrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016. Underground branch circuit feeding a detached garage:
Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016 * Garage construction requires permits (electrical, building) * Permits must be applied for at the time. * Dial
More informationAfter reading this lesson you will be able to: 12.3 IMPORTANCE OF ROOF 12.4 TYPES OF ROOF IN A HOUSE
86 :: Certificate in Construction Supervision (CIVIL) 12 ROOF 12.1 INTRODUCTION The structure provided to cover the house surface (floor) is known as roof. For different situation and requirement, it is
More informationTS 813 GROUNDING AND BONDING TTD 813.001 TRAFFIC SIGNAL INSTALLATION AND CONTROLLER CABINET GROUNDING SYSTEM TTD 813.005 CONTROLLER CABINET GROUNDING
TORONTO TRANSPORTATION January 2012 TS 813 GROUNDING AND BONDING TABLE OF CONTENTS 1. DRAWINGS TTD 813.001 TRAFFIC SIGNAL INSTALLATION AND CONTROLLER CABINET GROUNDING SYSTEM TTD 813.005 CONTROLLER CABINET
More informationLinea Weatherboard DIRECT FIX CONCRETE SLAB AND SOFFIT FIGURE 1
Top plate Stud Soffit lining 45mm min nog Fix scotia bead Building underlay/james Hardie rigid air barrier Soffit Detail Building underlay/james Hardie rigid air barrier Bottom plate 25mm wide cant strip.
More informationPLUMBING MAINTENANCE WORK FOR TOILETS IN HEAD OFFICE, SUPPLYCO ESTIMATE
Sl.No. PLUMBING MAINTENANCE WORK FOR TOILETS IN HEAD OFFICE, SUPPLYCO ESTIMATE Description of item Qty Unit Rate Amount 1 Demolishing tile work/cement concrete/( carefully taking out the closet and other
More information!!!!!! !!! Decra Plus DPSW010 DPSTW011 DPSW012 DPSW013 DPSW014 DPSW015 DPSW016 DPSW020 DPSW021 DPSW024 DPSW030 DPSW031 DPSW035 DPSW030 DPSW031 DPSW035
Decra Plus Drawing no DPSW010 DPSTW011 DPSW012 DPSW013 DPSW014 DPSW015 Description Shown In Decra Brochure Most Commonly Used Detail t~êã=oççñ=b~îéë=aéí~áä=b~îéë=lîéêü~åö=táíü=fåëìä~íéç=c~ëåá~=~åç=pçññáí
More informationSECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE
SECTION 15076 CEMENT-MORTAR LINED AND COATED (CML&C) STEEL PIPE PART 1 GENERAL 1.01 DESCRIPTION This section designates the requirements for steel pipe fabrication, test in shop, installation of steel
More informationCONSTRUCTION OF PERIMETER FENCE - COMMERCIAL AND T&D OFFICE COMPOUND, ONVERWAGT
BILL Nr1 - PRELIMINARIES 1.0 PRELIMINARY PARTICULARS CONSTRUCTION OF PERIMETER FENCE - COMMERCIAL 1.1 Funding The funding shall be provided by the Guyana Power & light Inc., of 40 Main street, North Cummingsburg,
More informationElectrical Wiring Technical Bulletin
Electrical Wiring Technical Bulletin Overview In general, SIP construction is easier and more cost effective when things are planned and thought out before the panels are manufactured. This process will
More informationSECTION 15140 - PIPE HANGERS AND SUPPORTS
Part I - GENERAL 1.01 SECTION INCLUDES A. The work covered under this section consists of the furnishing of all necessary labor, supervision, materials, equipment, and services to completely execute the
More informationWASHROOM UPGRADE SIR CHARLES TUPPER BUILDING 2250 RIVERSIDE DRIVE, OTTAWA, ON SIR CHARLES TUPPER BUILDING A0.0 COVER SHEET / DRAWING LIST
0 RIVERSIDE DRIVE, OTTAWA, ON A0.0 COVER SHEET / DRAWING LIST A0. LEGEND AND GENERAL NOTES A0. GENERAL NOTES A0. GENERAL NOTES A0. TYPICAL WASHROOM WALL/SINK SECTION A0. DETAIL - CONTROL JOINT A0. DETAIL
More informationCascade Remodeling Inc. PO Box 25687 Portland, OR 97298 Catalyzing Euphoria Phone (503) 297-2055, FAX (503) 297-0579 CCB # 67007
SPECIFICATIONS For Sample Customer SCOPE OF WORK: The contractor will provide labor and/or materials for the work as outlined in the estimate and the following specification. The contractor s estimate
More information7. Installation. installation 7.1.1. CAST-IN WINDOW SYSTEM 7.1. INSTALLATION OF WINDOW MAIN FRAME
7. Installation Window involves the fixing of window frame at an earlier construction stage and subsequent of the window sashes. This is a highly workmanship dependent process. Only trained and approved
More informationMarch 14, 2007. Installation of Bay, Bow and Garden Windows
March 14, 2007 Re: Installation of Bay, Bow and Garden Windows Attached are the Atrium Companies, Inc recommendation for the installation of bay, bow and garden windows. These instructions were developed
More informationSECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.
02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily
More informationICRC WORK SPECIFICATIONS IRAQ WATER AND HABITAT
ICRC WORK SPECIFICATIONS IRAQ WATER AND HABITAT GOVERNORATE : DISTRICT : LOCATION : DOHUK SUMEL SUMEL GO code : IRAK GEN ASSENG0 TITLE : Sharia / PHCC / Rehabilitation SO n : SO 03 WPA n : KIR16 0015 Job
More informationExtension. for. Pretend Customer 123 A Road HA7 9BP. at: 123 A Road HA7 9BP
for Pretend Customer at: Pretend Customer Site address: Monday, 23 November 2015 Dear Pretend Customer, Subject: Thank you for your valued enquiry and instructions to quote for the above project. We are
More informationEXAMPLE BILL OF MATERIALS
EXAMPLE BILL OF MATERIALS COMPONENTS 00.001 YELLOW ENVELOPE PACK 0 1 - LABELLED "ATTENTION BUILDER". [CONSISTS OF :- A3 & A4 PLANS, PLANS CONSTRUCTION MANUAL, BILL-OF-MATERIALS, VARIOUS DETAILS.] 00.002
More informationVOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10
VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10 SECTION B1: PREPARATION GUIDE B1.1 INTRODUCTION... B1-1
More informationPDmB, Inc. Definitions
Page 1 of 11 Definitions S Satisfactory Meets industry standards for proper material and installation NP Not Present Condition or item was not present at time of inspection NI Not Inspected Condition or
More informationSAMPLE SCHEDULE OF VALUES APPLICATION & CERTIFICATE FOR PAYMENT
SAMPLE SCHEDULE OF S 1.00 General Conditions 1.01 Project Management 1.02 General Superintendent 1.03 Superintendents 1.04 Safety Engineer 1.05 Scheduling 1.06 Field Engineering 1.07 Bonds 1.08 Trailer
More informationIF YOU NEED A POLE BARN OR DIY KIT CALL NOW AND LETS MAKE A DEAL
IF YOU NEED A POLE BARN OR DIY KIT CALL NOW AND LETS MAKE A DEAL Check out our Affordable Selection of DIY Pole Barn kit sizes and prices below. We offer a complete DIY pole barn kit plus independent experienced
More informationTARIFF CODE and updates standard
TARIFF CODE and updates standard No HS CODE AHTN CODE PRODUCT DESCRIPTION PRODUCT TYPE STANDARDS IDENTIFIED 7207 Semi finished products of iron or non alloy steel Containing by weight less than 0.25% of
More informationPark View Place. Compass. House. Royal Wharf Gardens Endeavour. House. Thameside. Sienna. House. House. Apartments Townhouses.
The Townhouses Park View Place A A Compass House A T T T Royal Wharf Gardens Endeavour House T A A Thameside House T Sienna House A A A A T Apartments Townhouses River Thames Compass House Compass House
More informationHolz Choices & Specifications
March 21, 2011 0. SALES AND DESIGN 1. UTILITIES AND PERMITS Holz Choices & Specifications 2. EXCAVATION AND LOT PREPARATION Job Beginning date of Monday May 2 nd, 2011 ALTERNATE: Garage walls as drawn
More informationMTA UNIVERSAL STATION PEDESTRIAN BRIDGE Los Angeles, CA. Project Manual and Specification 100% PE SUBMITTAL TABLE OF CONTENTS
Los Angeles, CA Project Manual and Specification DIVISION 1 GENERAL CONDITIONS 01 01 10 STATEMENT OF WORK 01 11 00 SUMMARY OF THE WORK 01 14 05 METRO (OWNER) - DIRECTED STOPPAGES 01 20 00 PRICE AND PAYMENT
More informationSECTION 02630 STORM DRAINAGE SYSTEM
SECTION 02630 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes specifications for storm drainage systems including modifications and connections to existing storm drainage systems. 1.02 REFERENCE
More informationELECTRICAL GUIDELINES FOR SINGLE-FAMILY HOME OWNERS:
ELECTRICAL GUIDELINES FOR SINGLE-FAMILY HOME OWNERS: Chapter 12 of the Burlington Code of ordinances allows owner occupants of single family homes to do their own wiring if they choose. If you choose to
More informationSuperform Products Ltd.
TYPICAL CORNER REINFORCING NOTE : SEE ENGINEERED REBAR SCHEDULES SUPPLIED BY THE MANUFACTURER STEEL REINFORCEMENT WALL CORNER 90 Copyright 2012 Sept. 2012 5.1.1 Rebar Spacing 6" 12" Max. Load LB./FT. 2000
More informationDiscussion on Products under the Scope of EN 1090-1 and proposed CEN/TR to clarify the scope
CEN/TC 135 N 686 European Committee for Standardization Comité Européen de Normalisation Europäisches Komitee für Normung CEN/TC 135 Execution of steel structures and aluminium structures N 686 Secretariat:
More informationFig. 2 WALL-TO-WALL PANEL CONNECTIONS CORNER WALL CONNECTION
SIPS SCREWS WITH MINIMUM 1" PENETRATION IN WOOD MEMBER IN SIP WALL PANEL CONNECTED TO @ 24" O.C. MAXIMUM OUTSIDE SKIN EACH SIDE OF FRAMING TYP. AS RECOMMENDED BY FOAM CORE AS EACH SIDE OF FRAMING TYP.
More informationBuilding Condition Assessment Report
Building Condition Assessment Report Asset C3c - Oak Terrace Cottage 121 Address Riverview Lands, 2601 Lougheed Highway, Coquitlam, BC. V5C 4J2 Construction Year Size (Gross Floor Area) 1920. 2,553 Sq.Ft.
More informationTECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE
TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION PART 8000 - PRECAST CONCRETE TABLE OF CONTENTS Item Number Page 8100 PRECAST CONCRETE CONSTRUCTION - GENERAL 8-3 8101 General
More informationAcumen Enterprises, Inc.
Hourly rates Discount w/o Rebate Electrician $78.00 10% $70.20 $70.73 HVAC Technician $78.00 10% $70.20 $70.73 Insulator $42.00 10% $37.80 $38.08 Sheet Metal Worker $74.00 10% $66.60 $67.10 Plumber/Pipefitter
More informationNote: All dimensions are nominal. All weights are for shipping purposes only. Availability is subject to change.
CHANNEL DrAiNS Durable Designed for maximum durability and drainage, NDS Channel Drains are a proven alternative to traditional concrete drains. UV inhibitors in the grates, channel and component parts
More informationMemtec Single Ply PVC Membrane Roofing and Waterproofing Technology. Modern Efficient Performance Cost Effective Flat Roofing Systems
Memtec Single Ply PVC Membrane Roofing and Waterproofing Technology Modern Efficient Performance Cost Effective Flat Roofing Systems Introduction A complete range of Memtec Roofing and Waterproofing Single
More informationPRESENTATION ON REPAIR AND REHABILITATION OF BUILDINGS DAMAGED IN EARTHQUAKE. By H P Gupta & D K Gupta
PRESENTATION ON REPAIR AND REHABILITATION OF BUILDINGS DAMAGED IN EARTHQUAKE By H P Gupta & D K Gupta DIFFERENT TYPES OF DAMAGES 1.Minor cracks 0.5 to 5 mm wide in load or non-load bearing walls 2.Major
More informationNATIONAL INSTITUTE OF BIOLOGICALS
Short Term Notice Inviting Quotations Quotations No. S.1-36/07/NIB/Engg. (Civil) Invitation to short term quotations for Repairing of damaged gypsum board false ceiling and painting with epoxy paint in
More informationMAST ARMS & POLES. Ornamental Pole Top & Bases
Ornamental Pole Top & Bases Pelco s decorative pole top and bases help make the traffic signal aesthetically pleasing to the eye. Available for various pole diameters and multiple finish options. Ornamental
More informationDIY GUIDE 10 EASY STEPS FOR TREATMENT OF RISING DAMP
DIY GUIDE 10 EASY STEPS FOR TREATMENT OF RISING DAMP CONTENTS WHAT IS RISING DAMP STEP 1 SURVEY STEP 2 METER READINGS STEP 3 CONCLUSION STEP 4 PREPARATION FOR TREATMENT STEP 5 TYPE OF TREATMENT STEP 6
More informationAll work must conform to the National Electric Code, latest edition, and all other applicable codes and regulations.
DIVISION 16 ELECTRICAL SECTION 16100 - ELECTRICAL PART 1 - GENERAL SCOPE All electrical work as shown on the drawings and as necessary to provide a complete electrical system. Include primary service,
More informationfirst look at GigaCrete s revolutionary new New Construction GigaHouse GigaHouse Utilizing GigaPanel
first look at GigaCrete s revolutionary new New Construction GigaHouse GigaHouse Utilizing GigaPanel What is GigaCrete GigaCrete is a family of products based on low carbon footprint Green ceramic binders
More informationIssue of the Guidelines on Prevention of Water Seepage in New Buildings
graphic: Buildings Department Your REF 來 函 檔 號 :. OUR REF 本 處 檔 號 :.BD GR/1-55/173 FAX 圖 文 傳 真 :..28400451 TEL 電 話 :..2626 1717 www.info.gov.hk/bd To : All Authorized Persons 7 March 2005 Registered Structural
More informationBrick Veneer Construction
Brick Veneer Construction Check list of suggested tools & support items Claw hammer Tape measure 3/4" [19 or 20] Wood chisel Wood or plastic shims Pry bar Utility knife Caulking and caulking gun Power
More informationConduit Fittings & Accessories Directional Drilling Conduit Utility Duct Telephone Duct Residential Boxes
CANTEX INC. 301 Commerce Ste 2700 Fort Worth, Texas 76102 817-215-7000 Fax: 817-215-7001 Conduit Fittings & Accessories Directional Drilling Conduit Utility Duct Telephone Duct Residential Boxes YOUR FULL
More informationTFL CUSTOM FIREPLACES WITH MASONRY BRICK LININGS. standard INSTALLATION SPECIFICATION INTO TIMBER FRAMING
6.CW.1A TFL CUSTOM FIREPLACES WITH MASONRY BRICK LININGS wood or gas standard INSTALLATION SPECIFICATION INTO TIMBER FRAMING The Fireplace Ltd is able to design and fabricate custom brick open masonry
More informationSPECIFICATIONS FOR VASWANI BRENTWOOD PROJECT. RCC Framed Structure confirming with zone II seismic detailing. Reinforced Cement Concrete
SPECIFICATIONS FOR VASWANI BRENTWOOD PROJECT 1. CONSTRUCTION: Foundation Super Structure Internal Walls External Walls Roof Retaining Walls RCC footing RCC Framed Structure confirming with zone II seismic
More informationBUILD A CARPORT. 2 - Planning the carport. 3 - Designing the carport
BUILD A CARPORT You only need basic DIY and woodworking skills to build a carport. The most important part of the job is setting the supporting posts truly vertical - a job for which another pair of hands
More informationGood Craftsmanship Guide. Carpentry and Joinery- Carcassing
Good Craftsmanship Guide Carpentry and Joinery- Carcassing Introduction This Good Craftsmanship Guide highlights key problems with the major elements of Carpentry and Joinery - Carcassing, and gives guidance
More information08003-1 WATER SERVICE 2
08003_Mar08_2011.pdf Page 1 of 7 INDEX Page 08003-1 WATER SERVICE 2 1.1 Pipe 2 1.1.1 Copper 2 1.1.2 Polyethylene 2 1.2 Valves and Fittings 2 1.2.1 Main Stops 3 1.2.2 Curb Stops 3 1.2.3 Curb Box 3 1.2.4
More informationProject : CONSTRUCTION OF BUILDING(including electrical and plumbing works) FOR NATIONAL CENTRE FOR SUSTAINABLE COASTAL MANAGEMENT,CHENNAI
Project : CONSTRUCTION OF BUILDING(including electrical and plumbing works) FOR NATIONAL CENTRE FOR SUSTAINABLE COASTAL MANAGEMENT,CHENNAI TENDER CLARIFICATIONS- no 3 dated 3rd Oct 13 issued in response
More information4. ANCHOR BOLTS AND STRAPS a. ½" anchor bolts shall be embedded 7" into concrete a maximum of 6' on center and 12" from corners and ends of plates.
GENERAL CODE REQUIREMENTS (BASEMENTS) 1. FOOTINGS a. Footings shall be below frost line depth (42"). b. For an 8" foundation wall, footings shall be no less than 8" deep and 16" wide. c. Steel reinforcement
More informationSECTION 02845 GUARDRAILS
SECTION 02845 GUARDRAILS PART 1 - GENERAL 1.01 SCOPE OF WORK A. Furnish all labor, materials, equipment and incidentals necessary and repair, replace or install all types of guardrails as specified herein
More informationBILL OF QUANTITIES Part No.: Part Description
Page 1 of 5 A. REMOVAL OF STRUCTURES 801 Demolition of Existing Structure lot 1 in words in words B. MASONRY WORKS 506(1)a Masonry Units (CHB) sq.m. 58.80 in words in words C. FABRICATED MATERIALS & HARDWARE
More informationTender schedule. Rate in
Name of work Maintanance work for hajj house at Karipur for the year 2012 Tender schedule Sl. No 1 1.00 Cubic Probable Quantity Description of work 2 8.00 Cubic 3 12.00 Cubic 4 7.00 Cubic Dismantling,
More informationSPECIFICATIONS FOR TENDER NO: PSNR/SCP/VKS/E 1635 ANNEXURE I TECHNICAL SPECIFICATIONS FOR LIGHTING HIGH MAST
TECHNICAL SPECIFICATIONS FOR LIGHTING HIGH MAST ANNEXURE I Sl.No. Description for BHEL Requirement Offered Deviation Scope of supply, erection and commissioning: 1 The scope of this specification covers
More informationCOMMONLY USED RESIDENTIAL BUILDING CODES
COMMONLY USED RESIDENTIAL BUILDING CODES INTERNATIONAL RESIDENTIAL CODE (2009) form revised 5/10 FOUNDATION 1. DESIGN OF FORMWORK. Section 1906.1 IBC 2009, Section R404.1.2.3.6 IRC 2009, ACI 318 Section
More informationDENVER MODEL 30 X 30 SPECIFICATIONS
DENVER MODEL 30 X 30 SPECIFICATIONS Dimensions: Roof Dimensions 30-0 x 30-0 (4) Columns (Center to Center) 25-6½ x 25-6½ Minimum Clearance 8-0 Roof Height @ Peak Dependent on Col. Ht. Hip Roof 4:12 pitch
More informationTYPICAL PATIO COVERS 111
City of Laguna Niguel Building Division 30111 Crown Valley Pkwy Laguna Niguel, CA 92677 (949) 362-4360 FAX 362-4369 www.cityoflagunaniguel.org TYPICAL PATIO COVERS 111 PLEASE NOTE: This information Bulletin
More informationCITY OF SELMA, TEXAS Inspection Checklist: Commercial
Rev Y71004 The Permits and Inspections Department welcomes you to the City of Selma. The following information is provided to you as guidance through the inspection process. The City of Selma provides
More informationAll work shall comply with applicable codes and ordinances. Work shall comply with the BOCA National Plumbing Code, latest edition.
DIVISION 15 MECHANICAL SECTION 15100 - PLUMBING PART 1 - GENERAL SCOPE Plumbing work includes all domestic water, gas, and sanitary sewer systems as shown on plans. Also all fixtures and equipment which
More informationLAYING BLOCK AND BRICK
LAYING BLOCK AND BRICK Products highlighted in this section: SAKRETE Type N Mortar Mix SAKRETE Type S Mortar Mix Brick And Block Laying Basics The first step in building a brick or block wall is to construct
More informationEFFECTIVE FEBRUARY 2014. note: drainage permit required to call for a dampproof inspection
EFFECTIVE FEBRUARY 2014 note: drainage permit required to call for a dampproof inspection 1. ROOF DRAINS/DECK DRAINS (INTERIOR ) All roof and deck drains within the perimeter of the building shall be APPROVED
More informationRemovable Aluminium posts
Post Solent Sail Shades Ltd 120 Billington Gardens Hedge End Southampton SO30 2RT Tel/Fax: 01489 788243 www.solentsailshades.co.uk Email: info@solentsailshades.co.uk Removable Aluminium posts Single Pole
More informationWorkSafe Guidance Document FALL PROTECTION IN RESIDENTIAL CONSTRUCTION
WorkSafe Guidance Document FALL PROTECTION IN RESIDENTIAL CONSTRUCTION WorkSafe Guidance Document Fall Protection in Residential Construction Table of Contents Executive Summary... 1 Introduction... 1
More informationNCMA TEK CONCRETE MASONRY FOUNDATION WALL DETAILS. TEK 5-3A Details (2003)
NCMA TEK National Concrete Masonry Association an information series from the national authority on concrete masonry technology CONCRETE MASONRY FOUNDATION WALL DETAILS TEK 5-3A Details (2003) Keywords:
More informationIf stepping is required, step at 180mm as seen in this picture.
Cast Foundations to standard building regulations requirements. Foundations must be cast completely level, 600mm wide by 230mm deep for single storey, double storey is not allowed by NHBRC. If stepping
More informationResidential Deck Safety, Construction, and Repair
Juneau Permit Center, 4 th Floor Marine View Center, (907)586-0770 This handout is designed to help you build your deck to comply with the 2006 International Residential Building code as modified by the
More informationHow To Build A Gambrel Roof And A Gable End Roof
Dutch Gable or Gambrel Roof and The Scotch Valley The folowing pages are an extract from Carp 12 text TAFE NSW Construction and Transport Division 71 HIP and VALLEY ROOFING GAMBREL / DUTCH GABLE The effect
More informationGPD Rubber Press Seals
GPD Rubber Press Seals Leading in in ideas SYSTEM-TECHNIK GPD Rubber Press Seals Design Available with a rubber thickness of 30 mm for sealing against non-pressing water and a rubber thickness of 60 mm
More informationAT&T Specifications Trenching Conduit Boxes and M anholes Aerial Entrance Masts Service Cabinets Bonding and Grounding
AT&T Specifications Trenching Conduit Boxes and M anholes Aerial Entrance Masts Service Cabinets Bonding and Grounding A Guide for California Developers of Com m ercial Property This guide consists of
More informationMark Cramer Inspection Services, Inc.
Mark Cramer Inspection Services, Inc. 492 Twentieth Avenue, Indian Rocks Beach, FL 34635-2970 (727) 595-4211 Fax (727) 596-7583 Certified Member #12085 American Society of Home Inspectors Construction
More informationK. D. FRAME ASSEMBLY FOR CLOSED STEEL STUD WALLS...Ins 10. FRAME INSTALLATION DETAILS FOR CLOSED STEEL STUD WALLS...Ins 11
K. D. FRAME ASSEMBLY FOR MASONRY WALLS...........................Ins 2 FRAME INSTALLATION DETAILS FOR MASONRY WALLS......................Ins 3 INSTALLING EXISTING MASONRY WALL ANCHORS IN FRAME..................Ins
More information2014 NEC Guide Lines for Home Owner Doing Electrical Work on their Property
2014 NEC Guide Lines for Home Owner Doing Electrical Work on their Property A brief summary of the most used code references for residential wiring State of Idaho Division of Building Safety Electrical
More informationQUOTATION FOR EXAMPLE BATHROOM RENOVATION
QUOTATION FOR EXAMPLE BATHROOM RENOVATION Prepared For: PEGASUS Client 99 Washington St Melrose, MA 02176 Quotation valid for 90 from: 12/21/10 PEGASUS Design-To-Build is pleased to have the opportunity
More informationInstallation Instructions
Installation Instructions 1. Position the unit onto bridging packers. These keep the unit away from any water sitting inside the frame. 2. Centralise the unit within the frame and pack the edges with appropriate
More informationL_All_Vocatinal_Ed_Construction. Sector: Construction. Sr. No Specialisation Page No 1 Construction and Building Technology 02.
L_All_Vocatinal_Ed_Construction Sector: Construction Sr. No Specialisation Page No 1 Construction and Building Technology 02 1 P a g e 2 P a g e VOCATIONAL EDUCATIONAL QUALIFICATION FRAMEWORK (Sector -
More informationDESCRIPTION UNIT QTY RATE TOTAL (KSHS) Supply and install the following: -
PROPOSED KISUMU HOUSING 3 BEDROOM-TYPE 1 ELECTRICAL INSTALLATION -SITE 01 DESCRIPTION UNIT QTY RATE TOTAL (KSHS) Supply and install the following: - 1.0 Final sub-circuit from Consumer Unit to lighting
More informationAdditions and Alterations
Additions and Alterations Addition and alteration construction is a miscellaneous grouping of home improvement and renovation projects that are generally geared toward the enhancement of an existing principal
More informationBOQ SPECIFICATIONS. The Blind system consist of a coated aluminium tube of 38 mm diameter with provision of fabric clamping.
BOQ SPECIFICATIONS VERTICAL BLINDS Vertical Blinds made of glass fibre fabrics in width 5 (or 4 ). Minimum overlapping of ¾ in fabric. Top aluminium anodized rail of 1.4 mm thickness. 2 inch wide channel
More informationHow To Repair A Boat Landing Deck With A Boat Bed
RESIDENTIAL INSULATED SHEATHING INSTALLATION GUIDE Residential Insulated Sheathing Installation Guide ROXUL COMFORTBOARD IS Table of Contents Slab-on-grade-to Above Grade Wall...1 Foundation Wall at Footing
More informationKAHU RESIDENTIAL ROOFING RRKA DETAIL LIST
KAHU DETAIL LIST 00 / 24 COVER SHEET 01 / 24 ROOF RIDGE 02 / 24 SAWTOOTH RIDGE 03 / 24 SAWTOOTH EAVE 04 / 24 ROOF VALLEY 05 / 24 ROOF - CHANGE PITCH 06 / 24 EAVE WITH METALLINE FASCIA 07 / 24 EAVE WITH
More information