Schneider Electric Services: life-cycle solutions for electrical distribution equipment. Scopes of Work for Electrical Maintenance

Size: px
Start display at page:

Download "Schneider Electric Services: life-cycle solutions for electrical distribution equipment. Scopes of Work for Electrical Maintenance"

Transcription

1 Scopes of Work for Electrical Maintenance Schneider Electric Services: life-cycle solutions for electrical distribution equipment Make the most of your energy SM

2 Scopes of Work for Electrical Maintenance: TABLE OF CONTENTS Bulletin No. 1910DB1303 TABLE OF CONTENTS SECTION 1 INTRODUCTION...4 SECTION 2 GENERAL REQUIREMENTS...5 SECTION 3 AC DRIVES...6 SECTION 4 AIR SWITCHES: LOW VOLTAGE...7 SECTION 5 AIR SWITCHES: MEDIUM VOLTAGE, METAL-ENCLOSED...9 SECTION 6 AIR SWITCHES: HIGH AND MEDIUM VOLTAGE, OPEN STYLE...11 SECTION 7 SWITCHES: HVL/cc...12 SECTION 8 METERING DEVICES...14 SECTION 9 BUSWAYS, METAL- ENCLOSED...15 SECTION 10 OUTDOOR / SUBSTATION BUS...16 SECTION 11 CABLES: LOW VOLTAGE...17 SECTION 12 CABLES: MEDIUM VOLTAGE...18 SECTION 13 CAPACITORS: POWER FACTOR CORRECTION...19 SECTION 14 CIRCUIT BREAKERS: LOW VOLTAGE INSULATED CASE/ MOLDED CASE...20 SECTION 15 CIRCUIT BREAKERS: LOW VOLTAGE POWER (ANSI/IEEE C37.13)...22 SECTION 16 CIRCUIT BREAKERS: MEDIUM VOLTAGE AIR MAGNETIC...24 SECTION 17 CIRCUIT BREAKERS: MEDIUM VOLTAGE SF SECTION 18 CIRCUIT BREAKERS: MEDIUM VOLTAGE VACUUM...28 SECTION 19 CIRCUIT BREAKERS: MEDIUM VOLTAGE OIL...30 SECTION 20 DIRECT CURRENT SYSTEMS: BATTERIES AND CHARGERS...32 SECTION 21 EMERGENCY SYSTEMS: AUTOMATIC TRANSFER SWITCHES...33 SECTION 22 GROUND-FAULT PROTECTION SYSTEMS...35 SECTION 23 GROUNDING RESISTORS...37 SECTION 24 GROUNDING SYSTEMS...38 SECTION 25 ISOLATED POWER SYSTEMS...39 SECTION 26 MOTOR CONTROL CENTERS: LOW AND MEDIUM VOLTAGE...41 SECTION 27 MOTOR STARTERS: LOW VOLTAGE...44 SECTION 28 MOTOR STARTERS: MEDIUM VOLTAGE...45 SECTION 29 PROTECTIVE RELAYS...47 SECTION 30 STEP VOLTAGE REGULATORS...48 SECTION 31 SURGE ARRESTERS: LOW VOLTAGE SURGE PROTECTION DEVICES...50 SECTION 32 SURGE ARRESTERS: MEDIUM AND HIGH VOLTAGE SURGE PROTECTION DEVICES...51 SECTION 33 SWITCHGEAR AND SWITCHBOARD ASSEMBLIES: LOW AND MEDIUM VOLTAGE...52 SECTION 34 SWITCHGEAR DVCAS SECTION 35 TRANSFORMERS: DRY TYPE: ALL VOLTAGES - LARGE (GREATER THAN 167 SINGLE-PHASE AND 500KVA THREE-PHASE)...56 SECTION 36 TRANSFORMERS: DRY TYPE - SMALL (167KVA SINGLE-PHASE, 500KVA THREE-PHASE, AND SMALLER)

3 Scopes of Work for Electrical Maintenance: TABLE OF CONTENTS TABLE OF CONTENTS SECTION 37 TRANSFORMERS, INSTRUMENT...58 SECTION 38 TRANSFORMERS: LIQUID-FILLED: ALL VOLTAGES...60 SECTION 39 INFRARED SCANNING...62 LIST OF TABLES TABLE: Insulation Resistance Test Value Electrical Apparatus and Systems...63 TABLE: Switchgear Withstand Test Voltages...64 TABLE: Recommended Dissipation Factor/Power Factor at 20 C Liquid-Filled Transformers, Regulators, and Reactors Acceptance Test Values...65 TABLE: Insulating Fluid Limits...66 TABLE: Transformer Insulation Resistance Acceptance Testing...69 TABLE: Medium-Voltage Cables Acceptance Test Values...70 TABLE: Inverse Time Trip Test at 300% of Rated Continuous Current of Circuit Breaker Molded-Case Circuit Breakers...73 TABLE: Instantaneous Trip Tolerances for Field Testing of Circuit Breakers...74 TABLE: Instrument Transformer Dielectric Tests Field Acceptance...75 TABLE: Maximum Allowable Vibration Amplitude...76 TABLE: RESERVED...77 TABLE: Bolt-Torque Values for Electrical Connections...78 TABLE: SF6 Gas Tests...80 TABLE: Insulation Resistance Conversion Factors (20 C)...81 TABLE: High-Potential Test Voltage Automatic Circuit Reclosers...83 TABLE: High-Potential Test Voltage for Acceptance Testing of Line Sectionalizers...84 TABLE: Dielectric Withstand Test Voltages Metal-Enclosed Bus...85 TABLE: Thermographic Survey Suggested Actions Based on Temperature Rise...86 TABLE: Dielectric Withstand Test Voltages Electrical Apparatus Other than Inductive Equipment...87 TABLE: Rated Control Voltages and their Ranges for Circuit Breakers...88 TABLE: Accuracy of IEC Class TP Current Transformers Error Limit...91 TABLE: Minimum Radii for Power Cable Single & Multiple Conductor Cables with Interlocked Armor, Smooth or Corrugated Aluminum Sheath or Lead Sheath...92 TABLE: Recommended Torque Values for Field Installed Wiring, Bus and Cable Connections...94 TABLE: Maximum Micro-Ohms Per Pole...96 TABLE: Maximum Micro-Ohms Per Pole...97 TABLE: Maximum Micro-Ohms Per Pole...97 TABLE: Type DS, DSII, DSL, and DSLII Circuit Breaker

4 Scopes of Work for Electrical Maintenance: SECTION 1 INTRODUCTION Bulletin No. 1910DB1303 SECTION 1 INTRODUCTION The Scopes of Work (SOWs) described in this bulletin are recommended practices that are ordinarily used in the field to determine the condition of an electrical power system. These practices can form the basis for a comprehensive Electrical Preventative Maintenance (EPM) program, however, they are not intended to be a mandatory practice or applicable and all inclusive for each type of equipment found in modern electrical power distribution systems. The practices in this document describe What to Do and not How To Do It. These practices should only be performed by persons that are qualified by experience and training in the proper and safe execution of EPM. In lieu of a customer specification or other written guidelines, this bulletin details the inspection and testing procedures that Schneider Electric Services technicians follow while performing maintenance testing of electrical equipment. Our qualified field service representatives provide comprehensive maintenance and testing services with a scope of work that includes: Equipment inspection Protective device testing Cleaning and lubrication Adjustments Electrical testing, including insulation, current path, system function and other services. Acknowledgement The standard deliverables to the customer are those services described in the each section of these procedures and titled Visual and Mechanical Inspection and Electrical Tests. Optional Tests will only be performed by Schneider Electric technicians when specified on customer s purchase order and subsequent field service work order. For testing of equipment not detailed in this document, Schneider Electric Services will refer to manufacturer s instructions, NFPA 70B, IEEE, ANSI and other relevant standards. For additional information, contact Schneider Electric Services at This document has been prepared based on manufacturer instruction bulletins as well as, NFPA, IEEE, NEMA and ANSI standards Tables are based on information from Schneider Electric USA, Inc. and the ANSI/NETA Standard for Maintenance Testing Specifications for Electrical Power Equipment and Systems 4

5 Scopes of Work for Electrical Maintenance: SECTION 2 GENERAL REQUIREMENTS SECTION 2 GENERAL REQUIREMENTS! DANGER HAZARD OF ELECTRIC SHOCK, EXPLOSION, OR ARC FLASH Apply appropriate personal protective equipment (PPE) and follow safe electrical work practices. See NFPA 70E or CSA Z462. This equipment must be installed and serviced by qualified electrical personnel. Turn off all power supplying this equipment before working on or inside equipment. Always use a properly rated voltage sensing device to confirm power is off. Replace all devices, doors and covers before turning on power to this equipment. Failure to follow these instructions will result in death or serious injury. Schneider Electric Services (SES) considers the safety of our employees, customers and all persons associated or affected by our work to be our highest priority. All work performed by Schneider Electric will adhere to Schneider Electric Safe Work practices, NFPA 70E, Customer Requirements and State and Federal standards. In all cases the most stringent procedures will be adhered to. At any point if the lead Schneider Electric representative determines work cannot proceed safely in accordance with these requirements work will be halted until a mutually agreeable resolution is reached. Owner / Customer shall supply current and accurate one-line and as built drawings for review prior to commencement of work. These will be given to Schneider Electric Personnel for use throughout the testing project. Owner / Customer shall supply OEM (Original Equipment Manufacture) Operations and Maintenance Manuals for all equipment to be tested. Copies of these should be given to Schneider Electric Personnel for use throughout the testing project. Schneider Electric Services Employees are NOT AUTHORIZED to work on energized equipment. However, there are occasions in which it may be necessary to take voltage measurements within an energized enclosure. These measurements will be taken using all applicable procedures for energized work. Schneider Electric Services does not typically perform shutdown and/or switching operations, because these operations may result in damage to property or persons downstream of the equipment as a result of conduct, errors, or omissions made by others. If a customer requests Schneider Electric Company to perform such services, a copy of the Schneider Electric Shutdown/Switching policy must be reviewed and signed by the customer. The onsite technician(s) must also contact their Manager for approval and proper procedures prior to performing any shutdown and/or switching. Schneider Electric maintains an equipment calibration program to assure that the equipment used to monitor and measure data associated with key characteristics will provide data that is both accurate and repeatable. The calibration cycle is defined by manufacturer and industry guidelines. Equipment included in the program is identified by a calibration sticker or tag affixed to each piece of test equipment. Equipment calibration records are available for review based on project specifications. Should hazardous materials such as asbestos, PCB contaminated oils or other similar substances be encountered work will be suspended until a mutually agreeable plan can be implemented to safely handle the material. 5

6 Scopes of Work for Electrical Maintenance: SECTION 3 AC DRIVES Bulletin No. 1910DB1303 SECTION 3 AC DRIVES A. Visual and Mechanical Inspection 1. Document equipment nameplate data on the test report. 2. Check for broken operators, switches, or pilot lights; dented or bent enclosure structures. 3. Check for excessive dirt, dust, or moisture. 4. Verify that a properly sized grounding conductor is connected to the drive grounding lug and terminates on a ground lug in the power distribution panel. 5. Tighten all power wiring connections to proper torque value. Check line and load side connections of all disconnect switches, breakers, contactors, and overloads. 6. Check and tighten all control wiring connections, mounting hardware, drive control terminals and terminal block connections. 7. Check door and disconnect switch alignment and opening/closing operation. 8. Test all mechanical interlocking devices. 9. Manually operate all contactors to verify freedom of movement. 10. Verify that customer supplied fusing agrees with the manufacturer s recommendations. 11. Verify mechanical operation of isolation contactor. Tighten power and control connections. 12. Verify that all control and option boards are securely fastened and plug-in terminals are connected. 13. Check that properly sized thermal overloads are used in ISO/Bypass unit. 14. Document as found/ as left settings. B. Electrical Tests 1. Verify proper operation of the AFC-Off-Bypass selector switch (if used). 2. Set the AFC-Off-Bypass selector switch (if used) to Bypass and the Hand Off-Auto to Hand. Check the direction of motor rotation. Rotation should be clockwise (ABC) unless indicated differently by the project documentation. Note the as-found and as-left rotation on the start-up documentation. 3. Verify proper operation based on the High Speed (HSP) setting (maximum motor speed setting). Record your results. 4. Verify proper operation based on Check the Low Speed (LSP) setting (minimum motor speed setting). Record your results. 5. Verify that Hand and Auto controls, Start, Stop, and speed input, operate the drive correctly. 6. Check that all indicating lamps illuminate only for their assigned functions. Check all Push to Test lamps. 6

7 Scopes of Work for Electrical Maintenance: SECTION 4 AIR SWITCHES: LOW VOLTAGE SECTION 4 AIR SWITCHES: LOW VOLTAGE A. Visual and Mechanical Inspection 1. Document equipment nameplate data on test report. 2. Inspect physical and mechanical condition and clean equipment. 3. Confirm correct application of manufacturer specified lubricants at recommended locations. 4. Verify appropriate anchorage and required area clearances. 5. Verify appropriate equipment grounding. 6. Verify correct blade alignment, blade penetration, travel stops, and mechanical operation. 7. Verify and record fuse sizes and types are in accordance with record drawings and, if available, coordination studies. 8. Using a calibrated torque wrench or low resistance ohmmeter, verify that the tightness of accessible bolted connections and/or cable connections are in accordance with the manufacturer s published data. If no manufacturer s data is available, use the values in Table and Check all interlocking systems for correct operation and sequencing, and key distribution, if applicable. 10. Verify correct phase barrier installation. 11. Inspect all indicating and control devices for correct operation. 12. Check the condition of arc contacts and arc chutes. B. Electrical Tests NOTE: When performing dielectric tests, you must disconnect (or isolate) all Instrument and Control Transformers, Surge Protection Devices and other sensitive electronic equipment that may cause erroneous results or be damaged by the applied test voltage. Verify no paths to ground exist with an ohmmeter or initially testing insulation resistance at a low voltage. Record the date of the last calibration for each piece of test equipment used. 1. Perform insulation-resistance tests on each pole, phase-to-phase and phase-to-ground with switch closed and across each open pole for one minute. Test voltage shall be in accordance with manufacturer s published data or Table Test all auxiliary devices (solenoid trip, blown main fuse detector, etc.) for proper operation. 7

8 Scopes of Work for Electrical Maintenance: SECTION 4 AIR SWITCHES: LOW VOLTAGE Bulletin No. 1910DB Perform a Contact Resistance Test across each pole (phase): a. With the main power source de-energized, close and open the switch several times using either manual or electrical means. b. Apply a minimum current of 10 amperes dc through the closed contacts. If the test current does not conform to the manufacturer s specification, consult the manufacturer. c. Measure and record the median (middle) value of three readings (toggling the switch between each reading) compare with the manufacturers published information and adjacent poles. d. If the measured resistances are below the manufacturers published data and balanced, the condition of the device contacts is considered suitable for service. If the measured resistances exceed the manufacturers recommendations or are imbalanced, open and close the device several more times and repeat the test. Contact the factory if acceptable values of resistance cannot be achieved. 4. Measure fuse resistance to verify continuity. Take note of any deviations in excess of 15%. Record your results. 5. When ground fault protection is installed on switch, confirm settings are in accordance with the owner supplied coordination study. Verify proper calibration and operation by current injection. 8

9 Scopes of Work for Electrical Maintenance: SECTION 5 AIR SWITCHES: MEDIUM VOLTAGE, METAL-ENCLOSED SECTION 5 AIR SWITCHES: MEDIUM VOLTAGE, METAL-ENCLOSED A. Visual and Mechanical Inspection 1. Document equipment nameplate data on test report. 2. Inspect physical and mechanical condition and clean equipment.. 3. Confirm correct application of manufacturer specified lubricants at recommended locations. 4. Verify appropriate anchorage and required area clearances. 5. Verify appropriate equipment grounding. 6. Verify correct blade alignment, blade penetration, travel stops, and mechanical operation. 7. Verify that fuse sizes and types are in accordance with drawings and, if available, coordination studies. 8. Inspect fuse holders for tightness and alignment. 9. Verify that expulsion-limiting devices are in place on all holders having expulsion-type elements. Verify that they are installed to vent in the proper direction. 10. Using a calibrated torque wrench or low resistance ohmmeter, verify that the tightness of accessible bolted connections and/or cable connections are in accordance with the manufacturer s published data. If no manufacturer s data is available, use the values in Tables and Check all interlocking systems for correct operation and sequencing, and key distribution, if applicable. 12. Verify correct phase-barrier installation. 13. Inspect all indicating and control devices for correct operation. 14. Clean and inspect any connected surge arrestors and verify that they have been properly connected. Verify that they have the appropriate voltage rating per the manufacturer s drawings and system voltage, where applicable. B. Electrical Tests NOTE: When performing dielectric tests, disconnect all Instrument and Control Transformers, Surge Protection Devices, and other sensitive electronic equipment that may cause erroneous results or cause damage to equipment that is not rated in accordance with Switchgear industry standards. Verify no paths to ground exist with an ohmmeter or initially testing insulation resistance at a low voltage Record the date of the last calibration for each piece of test equipment used. 1. Perform insulation-resistance tests on each pole, phase-to-phase and phase-to-ground with switch closed and across each open pole for one minute. Test voltage shall be in accordance with manufacturer s published data or Table Verify that heaters have been connected and are operating properly. 3. Measure fuse resistance to verify continuity, record your results. 9

10 Scopes of Work for Electrical Maintenance: SECTION 5 AIR SWITCHES: MEDIUM VOLTAGE, METAL-ENCLOSED Bulletin No. 1910DB Perform a Contact Resistance Test across each pole (phase) a. With the main power source de-energized, close and open the switch several times using either manual or electrical means. b. Apply a minimum current of 10 amperes dc through the closed contacts. c. Measure and record the median (middle) value of three readings (toggling the switch between each reading) compare with the manufacturers published information and adjacent poles. d. If the measured resistances are below the manufacturers published data and balanced, the condition of the device contacts is considered suitable for service. If the measured resistances exceed the manufacturers recommendations or are imbalanced, open and close the device several more times and repeat the test. Contact the factory if acceptable values of resistance cannot be achieved. 5. Perform a dielectric test (Hi-Pot) on each pole with switch closed. Test each pole-to-ground with all other poles grounded. Test voltage shall be in accordance with manufacturer s published data or Table

11 Scopes of Work for Electrical Maintenance: SECTION 6 AIR SWITCHES: HIGH AND MEDIUM VOLTAGE, OPEN STYLE SECTION 6 AIR SWITCHES: HIGH AND MEDIUM VOLTAGE, OPEN STYLE A. Visual and Mechanical Inspection 1. Document equipment nameplate data on test report. 2. Inspect physical and mechanical condition and clean equipment. 3. Confirm correct application of manufacturer specified lubricants at recommended locations. 4. Verify that grounding is in accordance with industry standards and project specifications. 5. Using a calibrated torque wrench or low resistance ohmmeter, verify that the tightness of accessible bolted connections and/or cable connections are in accordance with the manufacturer s published data. If no, manufacturer s data is available, use the values in Tables and Perform mechanical operator tests in accordance with manufacturer s instructions. 7. Verify correct operation and adjustment of motor operator limitswitches and mechanical interlocks. 8. Verify correct blade alignment, blade penetration, travel stops, arc interrupter operation, and mechanical operation (over toggle). 9. Inspect fuse holders for tightness and alignment. 10. Check the condition of arc contacts and arc chutes. Verify correct size and type fuses if fuses are presently installed. B. Electrical Tests NOTE: When performing dielectric tests, disconnect all Instrument and Control Transformers, Surge Protection Devices, and other sensitive electronic equipment that may cause erroneous results or cause damage to equipment that is not rated in accordance with Switchgear industry standards. Verify no paths to ground exist with an ohmmeter or initially testing insulation resistance at a low voltage Record the date of the last calibration for each piece of test equipment used. 1. Perform insulation-resistance tests on each pole, phase-to-phase and phase-to-ground with switch closed and across each open pole for one minute. Test voltage should be in accordance with manufacturer s published data or Table Perform a contact-resistance test across each switch blade and fuse holder, record results. Compare with the manufacturer s published information and adjacent poles. Investigate any values that deviate from the manufactures recommended values. 3. Verify Operator targets and Gas targets, where applicable, are in proper sequence. 4. Perform a dielectric test (Hi-Pot) on each pole with switch closed. Test each pole-to-ground with all other poles grounded. Test voltage shall be in accordance with manufacturer s published data or Table

12 Scopes of Work for Electrical Maintenance: SECTION 7 SWITCHES: HVL/cc Bulletin No. 1910DB1303 SECTION 7 SWITCHES: HVL/cc A. Visual and Mechanical Inspection 1. Document equipment nameplate data on test report. 2. Inspect physical and mechanical condition and clean equipment. 3. Verify appropriate anchorage and required area clearances 4. Verify that all power cables are properly terminated and supported. NOTE: When routing shielded cable through window-type current transformers or ground sensor current transformers, the shieldground connection wire is normally routed back through the current transformer and solidly grounded 5. Using a calibrated torque wrench or low resistance ohmmeter, verify that the tightness of accessible bolted connections and/or cable connections are in accordance with the manufacturer s published data. If no manufacturer s data is available, use the values in Tables and Hi-Pot Test Values Equipment Field Test Voltages Rating AC DC 4.76kV 14kV 20kV 15kV 27kV 38kV 17.5kV 28.5kV 40kV 27kV 45kV 63kV 38kV 60kV 85kV 6. Inspect all control wiring. 7. If FuseLogic fuse trip system is installed, verify proper operation. 8. Verify all fuses are properly installed and clips lubricated with Mobil Verify that fuse sizes and types are in accordance with drawings and, if available, coordination studies. 10. Check all interlocking systems for correct operation and sequencing, and key distribution, if applicable. 11. If any isolating switch is not in operation and is left without incoming cables, the corresponding grounding switch must be closed and blocked by means of a padlock to avoid possible unintentional operation. 12. Verify appropriate equipment grounding. 13. Verify that all insulating surfaces are clean and dry. 14. Verify that all barriers and covers are secured 15. When equipped, verify proper operation of the ground switch and related interlocks. 16. Perform a minimum of 5 open / close operations while verifying smooth operation of the mechanism and all indicators. 17. Inspect all interlocks, indicating and control devices for correct operation. 12

13 Scopes of Work for Electrical Maintenance: SECTION 7 SWITCHES: HVL/cc B. Electrical Tests NOTE: Prior to performing dielectric tests, disconnect all Instrument and Control Transformers, Surge Protection Devices, Control and Power cables units, and other sensitive electronic equipment that may cause erroneous results or be damaged by the applied test voltage. Capacitive dividers supplied with the equipment must be properly connected or grounded. Verify no paths to ground exist with an ohmmeter or initially testing insulation resistance at a low voltage. Record the date of the last calibration for each piece of test equipment used. 1. Perform insulation-resistance tests on each pole, phase-to-phase and phase-to-ground with switch closed and across each open pole for one minute. Test voltage shall be in accordance with the above table. 2. Perform Hi-Pot test a. Apply voltage to each phase individually for one minute with the other two phases and enclosure grounded. (see table for hi-pot test values gradually increase voltage). 13

14 Scopes of Work for Electrical Maintenance: SECTION 8 METERING DEVICES Bulletin No. 1910DB1303 SECTION 8 METERING DEVICES A. Visual and Mechanical Inspection 1. Document equipment nameplate data on test report. 2. Inspect physical and mechanical condition and clean equipment. 3. Confirm case is properly grounded. 4. Verify tightness of electrical connections. 5. For electro-mechanical devices, verify freedom of movement, correct travel, alignment, and tightness of mounting hardware. 6. For microprocessor based meters confirm and record settings for system configuration, CT and PT ratios, multipliers, communications and other specified parameters are in accordance with record drawings or customer supplied specifications. B. Electrical Tests Record the date of the last calibration for each piece of test equipment used. 1. Check calibration of meters according to the manufacturer s published data. 2. Electrically confirm that current transformer and voltage transformer secondary circuits are intact. 14

15 Scopes of Work for Electrical Maintenance: SECTION 9 BUSWAYS, METAL-ENCLOSED SECTION 9 BUSWAYS, METAL- ENCLOSED A. Visual and Mechanical Inspection 1. Document equipment nameplate data on test report. 2. Inspect the busway for physical damage and clean equipment. 3. Inspect for appropriate bracing, suspension, alignment, clearances and enclosure grounding and bonding. 4. Verify that the neutral is only grounded at one point in accordance with NEC, CSA or other applicable standards. 5. Verify installation and proper operation of heaters, when applicable, 6. For outdoor busway, confirm removal of weep-hole plugs, if applicable, and the correct installation of joint shield(s). Verify that proper gasketing is in place. B. Electrical Tests NOTE: Prior to testing, confirm that all tap-off or plug-in devices are in the off position. Isolate the entire busway run by disconnecting any ties to transformers, switchboards, meters or other devices. Record the date of the last calibration for each piece of test equipment used. 1. Measure insulation resistance of each busway with an insulation resistance tester rated at 1000 volts. Make measurements phase-toground, phase-to-neutral and phase-to-phase and for one minute. Compare your results with Table Perform a dielectric test (Hi-Pot) on each bus section, phase-toground with phases not under test grounded, in accordance with Table NOTE: This test is standard on medium voltage busway and optional on low voltage busway. NOTE: The megohm readings should not be less than the value calculated from the following formula. Megohms = 100 / length of run (in feet) or Megohms = 30.5 / length of run (in meters) C. Optional Tests 1. Using a calibrated torque wrench or low resistance ohmmeter, verify that the tightness of accessible bolted connections and/or cable connections are in accordance with the manufacturer s published data. If no manufacturer s data is available, use the values in Tables and

16 Scopes of Work for Electrical Maintenance: SECTION 10 OUTDOOR / SUBSTATION BUS Bulletin No. 1910DB1303 SECTION 10 OUTDOOR / SUBSTATION BUS A. Visual and Mechanical Inspection 1. Document equipment nameplate data on test report. 2. Inspect the bus for physical damage and clean equipment. 3. Inspect for appropriate bracing, suspension, alignment, and proper grounding. 4. Verify that all support insulators are clean and undamaged. B. Electrical Tests Record the date of the last calibration for each piece of test equipment used. 1. Perform an insulation resistance test to confirm the system is free of any ground faults. Compare your results with Table Perform a dielectric test (Hi-Pot) on each bus, phase-to-ground with phases not under test grounded, in accordance with manufacturer s published data. Apply test voltage for one minute. Use test voltage values as shown in Table C. Optional Tests 1. Using a calibrated torque wrench or low resistance ohmmeter, verify that the tightness of accessible bolted connections and/or cable connections are in accordance with the manufacturer s published data. If no, manufacturer s data is available, use the values in Tables and

17 Scopes of Work for Electrical Maintenance: SECTION 11 CABLES: LOW VOLTAGE SECTION 11 CABLES: LOW VOLTAGE A. Visual and Mechanical Inspection 1. Document cable sizing and insulation type. 2. Inspect the exposed sections of cables for physical damage and clean equipment. 3. Using a calibrated torque wrench, verify that the tightness of accessible bolted connections is in accordance with the manufacturer s published data. If no manufacturer s data is available, use the values in Tables and Inspect compression-applied connectors for correct cable match and indentation. B. Electrical Tests NOTE: When performing dielectric tests, disconnect all Instrument and Control Transformers, Surge Protection Devices, and other sensitive electronic equipment that may cause erroneous results or cause damage to equipment that is not rated in accordance with industry standards. 1. Verify that the opposite end of the cable run being tested is properly isolated from both adjacent equipment and personnel during testing. 2. Record the date of the last calibration date for each piece of test equipment used. 3. Perform an insulation resistance test on each conductor between one conductor and ground with the other conductors grounded. Each conductor shall be tested in the same manner. a. The test shall be performed at 1000 volts dc for one minute if the insulation rating of the cable under test is rated at 600V. For cables rated less than 600V, the Vdc test voltage should be a minimum of 1.41 times the Vac rating of the cable. b. Each 480V feeder cable shall be tested with the cable connected to the racked-in but open breaker or switch at the equipment. Connection at the other end of each of these cables shall be as follows: i. Cables to Motor Control Centers shall be connected to the bus with the switches or breakers in the starters open. ii. Cables to motors and other equipment shall be connected to the motors and equipment with feeder switches open. NOTE: All cables connected to motors and transformers are effectively connected through the windings. To obtain results for individual conductors, isolate the cables from the utilization equipment. 17

18 Scopes of Work for Electrical Maintenance: SECTION 12 CABLES: MEDIUM VOLTAGE Bulletin No. 1910DB1303 SECTION 12 CABLES: MEDIUM VOLTAGE A. Visual and Mechanical Inspection 1. Document cable sizing and insulation type. 2. Inspect the exposed sections of cables for physical damage and clean equipment. 3. Using a calibrated torque wrench, verify that the tightness of accessible bolted connections is in accordance with the manufacturer s published data. If no manufacturer s data is available, use the values in Tables and Inspect compression-applied connectors for correct cable match and indentation. 5. Inspect cable terminations for proper installation in accordance with the termination manufacturers instructions. B. Electrical Tests NOTE: When performing dielectric tests, disconnect all Instrument and Control Transformers, Surge Protection Devices, and other sensitive electronic equipment that may cause erroneous results or cause damage to equipment that is not rated in accordance industry standards. 1. Verify that the opposite end of the cable run to be tested is disconnected and isolated from personnel. 2. Record the date of the last calibration for each piece of test equipment used. 3. Perform a shield continuity test on each conductor 4. With cables isolated at both ends, perform an insulation resistance test on each conductor between the conductor and ground with the conductors not under test grounded. Each conductor shall be tested in the same manner. The test shall be performed at 1000 volts dc for one minute. NOTE: Cable testing technology is an evolving science. DC testing may not be suitable for some cable types (Such as XLPE), however, may be best suited for other types (such as EPR). The test method employed should be based on project requirements and discussions with the project engineer. C. Optional Tests 1. Perform a dielectric test on medium voltage shielded cable per Table Refer to the manufacturer s published data, and perform in accordance with IEEE 400, checking leakage current and decay voltage over the specified time period. 2. Very Low Frequency (VLF) 3. Perform power-factor or dissipation-factor tests on each cable. NOTE: For long cable runs it may be necessary to utilize a resonating inductor due to the large amount of capacitance in the cable. 18

19 Scopes of Work for Electrical Maintenance: SECTION 13 CAPACITORS: POWER FACTOR CORRECTION SECTION 13 CAPACITORS: POWER FAC- TOR CORRECTION A. Visual and Mechanical Inspection WARNING: Capacitors are energy storing devices. Care should be exercised and testing performed before physically touching the terminals of any capacitor. Although a voltage detection device might indicate that the capacitor is not electrically energized, the capacitor could be storing a lethal charge. Do NOT falsely assume that the internal discharge resistor is intact and functional. Always assume that a capacitor is charged unless the capacitor has been de-energized from its normal power source and the capacitor has been externally discharged. 1. Document equipment nameplate data on test report. 2. Inspect the physical and mechanical condition of the equipment and clean equipment. 3. Inspect the capacitors for the correct mounting and required clearances, per the manufacturer s recommended procedures. 4. Confirm all ventilation openings are clear and unobstructed. 5. Verify that capacitors are electrically connected in their specified configuration, per the manufacturer s recommended procedures. 6. Using a calibrated torque wrench or low resistance ohmmeter, verify that the tightness of accessible bolted connections and/or cable connections are in accordance with the manufacturer s published data. If no manufacturer s data is available, use the values in Tables and B. Electrical Tests Record the date of the last calibration date for each piece of test equipment used. 1. Perform insulation-resistance tests from terminal(s) to case for one minute on capacitors with more than one bushing. The test voltage and minimum resistance shall be in accordance with the manufacturer s instructions or Table Measure and record the input voltage for the capacitor / bank. Voltage should not exceed the capacitor nameplate rating by more then 10%. 3. Measure the capacitance of all terminal combinations. 4. Measure the resistance of the internal discharge resistors. 19

20 Scopes of Work for Electrical Maintenance: SECTION 14 CIRCUIT BREAKERS:LV INSULATED CASE/ MOLDED CASE Bulletin No. 1910DB1303 SECTION 14 CIRCUIT BREAKERS: LOW VOLTAGE INSULATED CASE / MOLDED CASE A. Visual and Mechanical Inspection 1. Document equipment nameplate data on test report. 2. Clean and inspect circuit breaker for damage, correct mounting, alignment and grounding. 3. Open and close the circuit breaker to insure smooth operation. 4. Confirm correct application of manufacturer specified lubricants at recommended locations. 5. Inspect case for cracks or other defects. 6. When applicable, inspect condition and alignment of arc chutes, moving and stationary contacts. 7. Using a calibrated torque wrench or low resistance ohmmeter, verify that the tightness of accessible bolted connections and/or cable connections are in accordance with the manufacturer s published data. If no, manufacturer s data is available, use the values in Tables and Perform all mechanical operator and contact alignment tests on both the breaker and its operating mechanism. 9. Verify electric open/close and operation of installed accessories, such as Blown Fuse Indicators. Auxiliary Contacts, Cell Switches, Shunt Trip Devices, and Undervoltage Release. 10. Exercise the push to trip button to verify trip and reset. 11. When applicable, activate the Blown Fuse Indicator (BFI) and confirm by attempting to close the breaker without reset. 12. Verify rating plugs, sensors and settings are accordance with the coordination study supplied by the owner, if available. 13. Verify that all maintenance devices are available for servicing and operating the breaker. B. Electrical Tests NOTE: When performing dielectric tests, remove rating plugs, disconnects, all Instrument and Control Transformers, Surge Protection Devices, and other sensitive electronic equipment that may cause erroneous results or cause damage to equipment that is not rated in accordance with molded case circuit breaker industry standards. Record the date of the last calibration for each piece of test equipment used. 1. Perform a contact-resistance test in accordance with the following procedure. a. Open and close circuit breaker manually several times to ensure the mechanism linkages are free and operate properly. Trip the circuit breaker with the push to trip button if so equipped. Close the breaker. b. Measure the resistance across each pole with a digital lowresistance ohmmeter. 20

21 Scopes of Work for Electrical Maintenance: SECTION 14 CIRCUIT BREAKERS:LV INSULATED CASE/ MOLDED CASE c. Compare the resistance values with manufacturers published data and between phases. d. For circuit breakers manufactured by Schneider Electric compare your results to the values in Table Perform an insulation-resistance test at 1000 volts dc from pole-topole and from each pole-to-ground with breaker closed and across open contacts of each phase. Insulation resistance should be greater than 100 Megohms. 3. Verify correct operation of any auxiliary features such as trip and pickup indicators, electrical close and trip operation, trip-free, and anti pump function. 4. Perform the following trip unit / relay tests by secondary injection: a. Minimum pickup current. b. Long-time delay. c. Short-time pickup and delay. d. Ground-fault pickup and delay. e. Instantaneous pickup. C. Optional Tests 1. Perform the trip unit / relay tests utilizing primary current injection. 2. Perform a dielectric withstand test. 21

22 Scopes of Work for Electrical Maintenance: SECTION 15 CIRCUIT BREAKERS: LOW VOLTAGE POWER (ANSI/IEEE C37.13) Bulletin No. 1910DB1303 SECTION 15 CIRCUIT BREAKERS: LOW VOLTAGE POWER (ANSI/IEEE C37.13) A. Visual and Mechanical Inspection 1. Document equipment nameplate data on test report. 2. Clean and inspect circuit breaker for shipping damage, correct mounting, alignment and grounding. 3. Open and close the circuit breaker to insure smooth operation. 4. Confirm correct application of manufacturer specified lubricants at recommended locations. 5. Inspect condition and alignment of arc chutes, moving and stationary contacts. 6. Using a calibrated torque wrench or low resistance ohmmeter, verify that the tightness of accessible bolted connections and/or cable connections are in accordance with the manufacturer s published data. If no, manufacturer s data is available, use the values in Tables and Perform all mechanical operator and contact alignment tests on both the breaker and its operating mechanism. 8. Verify electrical open/ close operation of installed accessories, such as Blown Fuse Indicators. Auxiliary Contacts, Cell Switches, Shunt Trip Devices, and Undervoltage Release. 9. When applicable, activate the Blown Fuse Indicator (BFI) and confirm by attempting to close the breaker without reset. 10. Verify rating plugs, sensors and settings are accordance with the coordination study supplied by the owner, if available. 11. Verify that all maintenance devices are available for servicing and operating the breaker. B. Electrical Tests NOTE: When performing dielectric tests, remove rating plugs and disconnect all Instrument and Control Transformers, Surge Protection Devices, and other sensitive electronic equipment that may cause erroneous results or cause damage to equipment that is not rated in accordance with circuit breaker industry standards. Record the date of the last calibration for each piece of test equipment used. 1. Perform a contact-resistance test in accordance with the following procedure. a. Open and close circuit breaker manually several times to ensure the mechanism linkages are free and operate properly. Trip the circuit breaker with the push to trip button if so equipped. Close the breaker. b. Measure the resistance across each pole with a digital lowresistance ohmmeter. c. Compare the Resistance values with manufacturers published data and between phases. d. For circuit breakers manufactured by Schneider Electric compare your results to the values in Table

23 Scopes of Work for Electrical Maintenance: SECTION 15 CIRCUIT BREAKERS: LOW VOLTAGE POWER (ANSI/IEEE C37.13) 2. Perform an insulation-resistance test at 1000 volts dc from pole-topole and from each pole-to-ground with breaker closed and across open contacts of each phase. Insulation resistance should be greater than 100 Megohms. 3. Verify correct operation of any auxiliary features such as trip and pickup indicators, electrical close and trip operation, trip-free, and anti pump function. 4. Perform the following trip unit / relay tests by secondary injection: a. Minimum pickup current. b. Long-time delay. c. Short-time pickup and delay. d. Ground-fault pickup and delay. e. Instantaneous pickup. C. Optional Tests 1. Perform the trip unit / relay tests utilizing primary current injection. 2. Perform a dielectric withstand test. 23

24 Scopes of Work for Electrical Maintenance: SECTION 16 CIRCUIT BREAKERS: MEDIUM VOLTAGE AIR MAGNETIC Bulletin No. 1910DB1303 SECTION 16 CIRCUIT BREAKERS: MEDIUM VOLTAGE AIR MAGNETIC A. Visual and Mechanical Inspection 1. Document equipment nameplate data on test report. 2. Clean the circuit breaker and inspect the physical and mechanical condition. 3. Confirm correct application of manufacturer specified lubricants at recommended locations. 4. Inspect anchorage and grounding. 5. Inspect and verify that adjustments of the mechanism are in accordance with the manufacturer s instructions. 6. Measure critical distances as recommended by manufacturer if indicated by contact resistance test results. 7. If required by the manufacturer, slow close/open breaker and check for binding. (This may not be possible in all cases where special or optionally supplied tooling is required) 8. Using a calibrated torque wrench or low resistance ohmmeter, verify that the tightness of accessible bolted connections and/or cable connections are in accordance with the manufacturer s published data. If no manufacturer s data is available, use the values in Table and Record as-found and as-left counter operations. B. Electrical Tests 1. Record the date of the last calibration for each piece of test equipment used. a. Perform a contact-resistance test in accordance with the following procedure. b. Open and close circuit breaker manually several times to ensure the mechanism linkages are free and operate properly. c. Measure the resistance across each pole with a digital lowresistance ohmmeter. d. Compare the Resistance values with manufacturers published data and between phases. 2. Perform insulation-resistance tests pole-to-pole, pole-to-ground, and across open poles in accordance with Table Verify trip, close, trip-free, and antipump functions. 4. Trip the circuit breaker by operating each protective device. 5. Perform a Hi-Pot (dielectric) test in accordance with the manufacturer s instructions. 24

25 Scopes of Work for Electrical Maintenance: SECTION 16 CIRCUIT BREAKERS: MEDIUM VOLTAGE AIR MAGNETIC C.Optional Tests 1. Perform an insulation-resistance test on all control wiring in accordance with Table Do not perform this test on wiring connected to solid- state relays. 2. Perform time-travel analysis using a travel distance analyzer. 3. Perform dissipation-factor/power-factor tests on breaker and bushings on each pole with the breaker open, and on each phase with the breaker closed. 4. Perform a minimum pick-up voltage test on trip and close coils. 25

26 Scopes of Work for Electrical Maintenance: SECTION 17 CIRCUIT BREAKERS: MEDIUM VOLTAGE SF6 Bulletin No. 1910DB1303 SECTION 17 CIRCUIT BREAKERS: MEDIUM VOLTAGE SF6 A. Visual and Mechanical Inspection 1. Document equipment nameplate data on test report. 2. Clean and inspect the physical and mechanical condition of the breaker. 3. Confirm that lubricants have been correctly applied at the manufacturer's recommended locations. 4. Inspect anchorage and grounding. 5. Inspect and verify that adjustments of the mechanism are in accordance with the manufacturer's instructions. 6. Check indicators for gas leaks in accordance with the manufacturer's instructions. 7. Verify correct operation of all air and SF6 gas pressure switches, alarms and cutouts. (NOTE: For sealed interrupters, the pressure cannot be varied to change the state of pressure switches.) 8. If required by the manufacturer, slow close/open breaker and check for binding. (This may not be possible in all cases where special or optionally supplied tooling is required) 9. Using a calibrated torque wrench or low resistance ohmmeter, verify that the tightness of accessible bolted connections and/or cable connections are in accordance with the manufacturer s published data. If no manufacturer's data is available, use the values in Table and Record as-found and as-left counter operations. B. Electrical Tests Record the date of the last calibration for each piece of test equipment used. 1. Perform a contact-resistance test in accordance with the following procedure. a. Open and close circuit breaker manually several times to ensure the mechanism linkages are free and operate properly. b. Measure the resistance across each pole with a digital lowresistance ohmmeter. c. Compare the Resistance values with manufacturers published data and between phases. 2. Perform insulation-resistance tests pole-to-pole, pole-to-ground, and across open poles in accordance with Table Perform a Hi-Pot (dielectric) test in accordance with the manufacturer s instructions. 4. Verify trip, close, trip-free, and antipump functions. 5. Trip the circuit breaker by operating each protective device. 26

27 Scopes of Work for Electrical Maintenance: SECTION 17 CIRCUIT BREAKERS: MEDIUM VOLTAGE SF6 C. Optional Tests 1. Perform an insulation-resistance test on all control wiring in accordance with Table Do not perform this test on wiring connected to solid-state relays. 2. Perform time-travel analysis using a travel distance analyzer. 3. Perform dissipation-factor/power-factor tests on breaker and bushings on each pole with the breaker open, and on each phase with the breaker closed. 4. Perform a minimum pick-up voltage test on trip and close coils. 27

28 Scopes of Work for Electrical Maintenance: SECTION 18 CIRCUIT BREAKERS: MEDIUM VOLTAGE VACUUM Bulletin No. 1910DB1303 SECTION 18 CIRCUIT BREAKERS: MEDIUM VOLTAGE VACUUM A. Visual and Mechanical Inspection 1. Document equipment nameplate data on test report. 2. Clean the circuit breaker and inspect physical and mechanical condition. 3. Confirm correct application of manufacturer specified lubricants at recommended locations. 4. Inspect anchorage, alignment, and grounding. 5. Inspect and verify that adjustments of the mechanism are in accordance with the manufacturer s instructions. 6. Measure critical distances, such as contact gap, as specified by the manufacturer s service bulletin. 7. Using a calibrated torque wrench or low resistance ohmmeter, verify that the tightness of accessible bolted connections and/or cable connections are in accordance with the manufacturer s published data. If no manufacturer's data is available, use the values in Tables and Record as-found and as-left operation counter readings. B. Electrical Tests NOTE: When performing dielectric tests, disconnect all Instrument and Control Transformers, Surge Protection Devices, and other sensitive electronic equipment that may cause erroneous results or cause damage to equipment. Surge Protection Devices must be completely disconnected from the electrical system (including neutral and ground). Record the date of the last calibration for each piece of test equipment used. 1. Perform a contact-resistance test in accordance with the following procedure. a. Open and close circuit breaker manually several times to ensure the mechanism linkages are free and operate properly. b. Measure the resistance across each pole with a digital lowresistance ohmmeter. c. Compare the Resistance values with manufacturers published data and between phases. 2. Verify the trip, close, trip-free, and antipump functions. 3. Trip the circuit breaker by operating each protective device. 4. Perform insulation-resistance tests pole-to-pole, pole-to-ground, and across open circuit breaker separable contacts in accordance with Table Perform a vacuum bottle integrity test in strict accordance with manufacturer's instructions. Note: Some manufacturers specify either AC or DC voltage for this test. Contact the manufacturer if repeated consistent breakdowns are encountered. 28

Schneider Electric Services: life-cycle solutions for electrical distribution equipment. Scopes of Work for Electrical Acceptance Testing

Schneider Electric Services: life-cycle solutions for electrical distribution equipment. Scopes of Work for Electrical Acceptance Testing Scopes of Work for Electrical Acceptance Testing Schneider Electric Services: life-cycle solutions for electrical distribution equipment Make the most of your energy SM Scopes of Work for Electrical Acceptance

More information

CAPACITOR BANK TESTING SWP

CAPACITOR BANK TESTING SWP 1. PURPOSE AND SCOPE The purpose of this Standard Work Practice (SWP) is to standardise and prescribe the method for testing Capacitor Banks including capacitors, tuning reactors and inrush limiting reactors.

More information

Submit shop drawings for equipment provided under this section Shop drawings shall indicate:

Submit shop drawings for equipment provided under this section Shop drawings shall indicate: Section 16435 - SWITCHBOARDS Introduction Part 1 - General Reference The work under this section is subject to requirements of the Contract Documents including the General Conditions, Supplementary Conditions,

More information

SECTION 263235 STANDBY GENERATOR TESTING AND COMMISSIONING

SECTION 263235 STANDBY GENERATOR TESTING AND COMMISSIONING SECTION 263235 STANDBY GENERATOR TESTING AND COMMISSIONING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Standby generators. 2. Automatic Transfer Switches (ATS). 3. System start-up services. 4.

More information

Circuit Breakers and Switchgear. Thomas Greer Director of Engineering TLG Services

Circuit Breakers and Switchgear. Thomas Greer Director of Engineering TLG Services Circuit Breakers and Switchgear Thomas Greer Director of Engineering TLG Services Presentation Outline Switchgear Definition Overcurrent Protection Devices Circuit Breaker Trip Curves and Coordination

More information

2a. IEM Indoor Metal Clad Medium Voltage Switchgear 15KV 16346-1. 2a. Section 16346 INDOOR METAL CLAD MEDIUM VOLTAGE SWTICHGEAR (Std.

2a. IEM Indoor Metal Clad Medium Voltage Switchgear 15KV 16346-1. 2a. Section 16346 INDOOR METAL CLAD MEDIUM VOLTAGE SWTICHGEAR (Std. 2a. IEM Indoor Metal Clad Medium Voltage Switchgear 15KV 16346-1 2a. Section 16346 INDOOR METAL CLAD MEDIUM VOLTAGE SWTICHGEAR (Std. Relays) Part 1 General 1.1 CONDITIONS AND REQUIREMENTS: A. Refer to

More information

ARCO Electric Products Installation and Maintenance Manual Low Voltage Automatic Power Factor Correction Capacitor Systems 2013

ARCO Electric Products Installation and Maintenance Manual Low Voltage Automatic Power Factor Correction Capacitor Systems 2013 ARCO Electric Products Installation and Maintenance Manual Low Voltage Automatic Power Factor Correction Capacitor Systems 2013 READ CAREFULLY These instructions are intended to cover good practices in

More information

AC Electric Motors best practice

AC Electric Motors best practice If you want to learn more about best practice machinery maintenance, or world class mechanical equipment maintenance and installation practices, follow the link to our Online Store and see the Training

More information

Electronic Trip Circuit Breaker Basics Circuit Breaker Application Guide Class 0600

Electronic Trip Circuit Breaker Basics Circuit Breaker Application Guide Class 0600 Electronic Trip Circuit Breaker Basics Circuit Breaker Application Guide Class 0600 Data Bulletin 0600DB1104 03/2012 Retain for future use. Electronic Trip Circuit Breaker Basics 0600DB1104 Table of Contents

More information

Primary and Secondary Electrical Distribution Systems

Primary and Secondary Electrical Distribution Systems Primary and Secondary Electrical Distribution Systems Critical Facilities Round Table 12th Quarterly Membership Meeting June 2, 2006 David D. Roybal. P.E. Eaton Electrical Cutler-Hammer Products Utility

More information

Secondary Unit Substations

Secondary Unit Substations 14 SWITCHGEAR Secondary Unit Substations Overview Siemens offers a wide variety of unit substation designs to meet customer requirements. A unit substation consists of one or more transformers mechanically

More information

Vacuum Circuit Breaker Type VAD-3

Vacuum Circuit Breaker Type VAD-3 Instruction Bulletin Bulletin 6055-11 Vacuum Circuit Breaker Type VAD-3 4.76 kv, 29 ka (250 MVA) 4.76 kv, 41 ka (350 MVA) 8.25 kv, 33 ka (500 MVA) 15.0 kv, 18 ka (500 MVA) 15.0 kv, 28 ka (750 MVA) 15,0

More information

Atlanta Chapter IEEE Industry Applications Society

Atlanta Chapter IEEE Industry Applications Society Atlanta Chapter IEEE Industry Applications Society Electrical Equipment Room Design Considerations presented at the Sheraton Buckhead Hotel Atlanta, Georgia November 20, 2006 Outline 1. Definitions 2.

More information

SUGGESTED SPECIFICATION for Series 185 Service Entrance Rated Automatic Transfer Switches

SUGGESTED SPECIFICATION for Series 185 Service Entrance Rated Automatic Transfer Switches SUGGESTED SPECIFICATION for Series 185 Service Entrance Rated Automatic Transfer Switches PART 1 GENERAL 1.01 Scope Optional Standby Power Generator Systems A. Furnish and install automatic transfer switches

More information

Unified requirements for systems with voltages above 1 kv up to 15 kv

Unified requirements for systems with voltages above 1 kv up to 15 kv (1991) (Rev.1 May 2001) (Rev.2 July 2003) (Rev.3 Feb 2015) Unified requirements for systems with voltages above 1 kv up to 15 kv 1. General 1.1 Field of application The following requirements apply to

More information

26 3213.13 Diesel Engine Driven Generators Page 1 of 6

26 3213.13 Diesel Engine Driven Generators Page 1 of 6 Last Update: December 8, 2014 A. Description of System Consultant s Handbook Page 1 of 6 1. Provide a diesel engine driven electric generating unit, factory assembled, tested and certified to operate at

More information

Hyperlinks are Inactive

Hyperlinks are Inactive Prepared by: NIB/EOB PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES 05503 Department: Electric T&D Section: T&D Engineering and Technical Support Approved by: G.O. Duru (GOD)

More information

City Of Ottawa High Voltage Substation Inspection, Maintenance Rev 00 2015 July 17 and Testing, ROPEC Page 1

City Of Ottawa High Voltage Substation Inspection, Maintenance Rev 00 2015 July 17 and Testing, ROPEC Page 1 2015 July 17 and Testing, ROPEC Page 1 PART 1 GENERAL 1.1. Scope.1 Equipment replacement and testing for a 44 kv 4.16kV/600V substation: a. Replacement of Insulators as indicated on the drawings in Appendix

More information

SWITCHGEAR Section 16. SECTION INCLUDES This Section includes service and distribution switchboards rated 600 V and less.

SWITCHGEAR Section 16. SECTION INCLUDES This Section includes service and distribution switchboards rated 600 V and less. PART 1 - GENERAL SECTION INCLUDES This Section includes service and distribution switchboards rated 600 V and less. RELATED SECTIONS Division 16 Section "Basic Electrical Materials and Methods" for general

More information

Single Phase Soft Starter

Single Phase Soft Starter Single Phase Soft Starter Installation & Operating Manual 6/02 Table of Contents Section 1 General Information................................................... 1 1 General Description................................................

More information

Evaluating Water-Damaged Electrical Equipment

Evaluating Water-Damaged Electrical Equipment Evaluating Water-Damaged Electrical Equipment 1 USE OF THIS PUBLICATION This publication provides information on how to evaluate electrical equipment that has been exposed to water through flooding, fire

More information

Dead Tank Outdoor Vacuum Circuit Breaker, Type VOX

Dead Tank Outdoor Vacuum Circuit Breaker, Type VOX Dead Tank Outdoor Vacuum Circuit Breaker, Type VOX Class 6065 Instruction Bulletin 6065-13 11/2011 Retain for future use. Hazard Categories and Special Symbols Read these instructions carefully and look

More information

Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components

Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components Course No: E02-010 Credit: 2 PDH Boris Shvartsberg, Ph.D., P.E., P.M.P. Continuing Education

More information

Instruction Bulletin. MCS025 Sync-Check Module Installation Sheet

Instruction Bulletin. MCS025 Sync-Check Module Installation Sheet Instruction Bulletin 63230-216-244B1 LaVergne, TN, USA MCS025 Sync-Check Module Installation Sheet Retain for future use. DANGER HAZARD OF ELECTRIC SHOCK, EXPLOSION, OR ARC FLASH Only qualified electrical

More information

Product Description Full Voltage Starting Electric Fire Pump Controllers FTA1000

Product Description Full Voltage Starting Electric Fire Pump Controllers FTA1000 Product Description Full Voltage Starting Electric Fire Pump Controllers FTA1000 Description Firetrol FTA1000 Full Voltage Fire Pump Controllers are intended for use with electric motor driven fi re pumps

More information

CONTROL PANEL INSTALLATION INSTRUCTIONS. Single Phase Simplex Page 2-7. 3-Phase Simplex Page 8-13

CONTROL PANEL INSTALLATION INSTRUCTIONS. Single Phase Simplex Page 2-7. 3-Phase Simplex Page 8-13 CONTROL PANEL INSTALLATION INSTRUCTIONS Single Phase Simplex Page 2-7 3-Phase Simplex Page 8-13 Single Phase Simplex SXL21=3, SXL24=3, SXH21=3, and SXH24=3 Manufactured by SJE-Rhombus Installation Instructions

More information

D. Infrared scanning reports with pictures printed in a final report with any deficiencies and actions taken to rectify.

D. Infrared scanning reports with pictures printed in a final report with any deficiencies and actions taken to rectify. SECTION 263354 STATIC UPS TESTING AND COMMISSIONING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes 1. System start-up services. 2. Battery charging. 3. Load bank testing. 4. Battery load testing. 5.

More information

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV 1. SCOPE This document details PowerSystems requirements for electrical testing of HV Equipment up to and including 33kV. 2. ISSUE RECORD This is a Reference document. The current version of Controlled

More information

Product Description Primary Resistance Starting Electric Fire Pump Controllers FTA1500

Product Description Primary Resistance Starting Electric Fire Pump Controllers FTA1500 Product Description Primary Resistance Starting Electric Fire Pump Controllers FTA1500 Description Firetrol FTA1500 Primary Resistance Fire Pump Controllers use resistors in the line to reduce line voltage

More information

SECTION 26 29 23 VARIABLE FREQUENCY DRIVES

SECTION 26 29 23 VARIABLE FREQUENCY DRIVES SECTION 26 29 23 VARIABLE FREQUENCY DRIVES PART 1 GENERAL 1.01 SCOPE A. Furnish and install individual freestanding variable frequency AC drives (VFD) as shown on the Drawings and specified herein. 1.02

More information

SERVICE-LIFE EVALUATIONS OF LOW-VOLTAGE POWER CIRCUIT BREAKERS AND MOLDED-CASE CIRCUIT BREAKERS

SERVICE-LIFE EVALUATIONS OF LOW-VOLTAGE POWER CIRCUIT BREAKERS AND MOLDED-CASE CIRCUIT BREAKERS SERVICE-LIFE EVALUATIONS OF LOW-VOLTAGE POWER CIRCUIT BREAKERS AND MOLDED-CASE CIRCUIT BREAKERS Michael J Sprague Member, IEEE Cutler-Hammer, Inc. 130 Commonwealth Drive Warrendale, PA 15086 USA Abstract

More information

Fusible Disconnect Switch

Fusible Disconnect Switch Circuit Breakers Circuit breakers are used in panelboards and switchboards to provide circuit protection and provide a means of energizing and de-energizing a circuit. Siemens Sentron molded case circuit

More information

Spending too much to maintain aging switchgear? Circuit breaker solutions from Square D Services.

Spending too much to maintain aging switchgear? Circuit breaker solutions from Square D Services. Spending too much to maintain aging switchgear? Circuit breaker solutions from Square D Services. Spending too much time and money on equipment maintenance? Square D Services: Your source for circuit breaker

More information

Section 9: Power Distribution Equipment Bill Brown, P.E., Square D Engineering Services

Section 9: Power Distribution Equipment Bill Brown, P.E., Square D Engineering Services Section 9: Power Distribution Equipment Bill Brown, P.E., Square D Engineering Services Introduction Power Distribution Equipment is a term generally used to describe any apparatus used for the generation,

More information

SECTION 26 09 13 - POWER MONITOR FOR ELECTRICAL, STEAM CONDENSATE, AND WATER PART I - GENERAL

SECTION 26 09 13 - POWER MONITOR FOR ELECTRICAL, STEAM CONDENSATE, AND WATER PART I - GENERAL SECTION 26 09 13 - POWER MONITOR FOR ELECTRICAL, STEAM CONDENSATE, AND WATER PART I - GENERAL 1.1 SUMMARY A. This section describes the requirements for the installation of Power Monitors and associated

More information

Evaluating Water-Damaged Electrical Equipment

Evaluating Water-Damaged Electrical Equipment Evaluating Water-Damaged Electrical Equipment 1 USE OF THIS PUBLICATION This publication provides information on how to evaluate electrical equipment that has been exposed to water through flooding, fire

More information

MEDIUM VOLTAGE METAL CLAD SWITCHGEAR

MEDIUM VOLTAGE METAL CLAD SWITCHGEAR MEDIUM VOLTAGE METAL CLAD SWITCHGEAR PART 1 - GENERAL 1.1 DESCRIPTION This section specifies the furnishing, installation, connection and testing of the medium voltage switchgear. 1.2 SWITCHGEAR FEATURES

More information

101 BASICS SERIES LEARNING MODULE 3: FUNDAMENTALS OF ELECTRICAL DISTRIBUTION. Cutler-Hammer

101 BASICS SERIES LEARNING MODULE 3: FUNDAMENTALS OF ELECTRICAL DISTRIBUTION. Cutler-Hammer 101 BASICS SERIES LEARNING MODULE 3: FUNDAMENTALS OF ELECTRICAL DISTRIBUTION Cutler-Hammer WELCOME Welcome to Module 3, Fundamentals of Electrical Distribution. If you have successfully completed Module

More information

CIRCUIT BREAKER INTERRUPTING CAPACITY AND SHORT-TIME CURRENT RATINGS

CIRCUIT BREAKER INTERRUPTING CAPACITY AND SHORT-TIME CURRENT RATINGS CIRCUIT BREAKER INTERRUPTING CAPACITY AND SHORT-TIME CURRENT RATINGS David D. Roybal, P.E. Senior Member, IEEE Eaton Electrical 3697 Mount Diablo Boulevard Lafayette, CA 94549 Abstract Low-voltage circuit

More information

S&C Type FVR Vacuum Substation Circuit Breaker

S&C Type FVR Vacuum Substation Circuit Breaker S&C Type FVR Vacuum Substation Circuit Breaker 15 kv to 38 kv, 110 kv BIL to 150 kv BIL, 1200 A to 4000 A, Class 6065 Instructions for Installation 6065-3001 S&C ELECTRIC COMPANY Specialists in Electric

More information

Evaluating Water-Damaged Electrical Equipment

Evaluating Water-Damaged Electrical Equipment Evaluating Water-Damaged Electrical www.nema.org Evaluating Water-Damaged Electrical 1 USE OF THIS PUBLICATION This publication provides information on how to evaluate electrical equipment that has been

More information

HVL 5 38 kv Load Interrupter Switchgear. The Standard for Performance, Protection and Dependability

HVL 5 38 kv Load Interrupter Switchgear. The Standard for Performance, Protection and Dependability HVL 5 38 kv Load Interrupter Switchgear The Standard for Performance, Protection and Dependability For a generation of engineers, Square D High Voltage Load (HVL ) Interrupter Switchgear by Schneider Electric

More information

Arc Flash Avoidance and its Application to Overhead Traveling Cranes

Arc Flash Avoidance and its Application to Overhead Traveling Cranes Arc Flash Avoidance and its Application to Overhead Traveling Cranes Whitepaper August 2012 Jason Wellnitz, Controls Product Manager Material Handling Numerous technical papers, bulletins, magazine articles

More information

WE-350 Series ¼ Turn Electric Actuator

WE-350 Series ¼ Turn Electric Actuator WE-350 Series ¼ Turn Electric Actuator Operation and Installation Manual Pg 1 (Rev. 020113) Table of Contents 1.0 General 1.1 Pre-Installation Inspection 1.2 Storage 1.3 Features & General Information

More information

ELECTRICAL SAFETY RISK ASSESSMENT

ELECTRICAL SAFETY RISK ASSESSMENT ELECTRICAL SAFETY RISK ASSESSMENT The intent of this procedure is to perform a risk assessment, which includes a review of the electrical hazards, the associated foreseeable tasks, and the protective measures

More information

Installation, Operation and Maintenance Instructions Viper -S Solid Dielectric Reclosers Three Phase, Vacuum Recloser.

Installation, Operation and Maintenance Instructions Viper -S Solid Dielectric Reclosers Three Phase, Vacuum Recloser. Installation, Operation and Maintenance Instructions Viper -S Solid Dielectric Reclosers Three Phase, Vacuum Recloser GWI 531-1 Rev. 6 May, 2008 Supersedes Rev. 5 dated October,2005 Table of Contents Section

More information

Dead Tank Circuit Breaker 72PM40-C Proven reliability through common platforms

Dead Tank Circuit Breaker 72PM40-C Proven reliability through common platforms Dead Tank Circuit Breaker 72PM40-C Proven reliability through common platforms ABB innovations for changing demands ABB (www.abb.com) is a leader in power and automation technologies that enables utility

More information

Maintenance Report MEDIUM VOLTAGE POWER STATION 500SC / 630SC / 800SC / 900SC / 1000 1SC / 1000 2SC / 1250SC / 1600SC / 1800SC / 2000SC

Maintenance Report MEDIUM VOLTAGE POWER STATION 500SC / 630SC / 800SC / 900SC / 1000 1SC / 1000 2SC / 1250SC / 1600SC / 1800SC / 2000SC Maintenance Report MEDIUM VOLTAGE POWER STATION 500SC / 630SC / 800SC / 900SC / 1000 1SC / 1000 2SC / 1250SC / 1600SC / 1800SC / 2000SC Project name: Customer: Address, location of the system: Serial number

More information

TP-C2 Motor Operator CLEAVELAND / PRICE INC. Bulletin DB-111B12

TP-C2 Motor Operator CLEAVELAND / PRICE INC. Bulletin DB-111B12 Bulletin DB-111B12 TP-C2 Motor Operator CLEAVELAND / PRICE INC. 14000 Rt. 993, Trafford, PA 15085 (724) 864-4177 FAX (724) 864-9040 Email: sales@cleavelandprice.com Cleaveland/Price Type TP-C2 Motor Operator

More information

Emergency Power System Services Industrial UPS, Batteries, Chargers, Inverters and Static Switches

Emergency Power System Services Industrial UPS, Batteries, Chargers, Inverters and Static Switches Emergency Power System Services Industrial UPS, Batteries, Chargers, Inverters and Static Switches Downtime Is Not An Option The industrial uninterruptible power supply (UPS) is the foundation of your

More information

..OR How To Protect your 3-Phase Equipment Investment with 3-Phase Monitors from Time Mark...

..OR How To Protect your 3-Phase Equipment Investment with 3-Phase Monitors from Time Mark... ..OR How To Protect your 3-Phase Equipment Investment with 3-Phase Monitors from Time Mark... TIME MARK CORPORATION 11440 EAST PINE STREET TULSA, OK 74116 USA tel 918 438-1220 fax 918 437-7584 www.time-mark.com

More information

ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F

ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F TABLE OF CONTENTS Appendix F - Electrical Engineering Design Criteria F.1 Introduction...F-1 F.2 Codes and Standards...F-1 F.3 Switchyard and Transformers...F-1

More information

GUIDELINES FOR WATER-DAMAGED ELECTRICAL EQUIPMENT

GUIDELINES FOR WATER-DAMAGED ELECTRICAL EQUIPMENT GUIDELINES FOR HANDLING WATER-DAMAGED ELECTRICAL EQUIPMENT NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION 1300 NORTH 17 TH STREET, SUITE 1752 ROSSLYN, VIRGINIA 22209 703 841-3200 703 841-5900 FAX WWW.NEMA.ORG

More information

Arc Flash Hazards. Electrical Hazards. Dan Neeser Field Application Engineer DanRNeeser@Eaton.com. Electrical Hazards 2/18/2015. Shock.

Arc Flash Hazards. Electrical Hazards. Dan Neeser Field Application Engineer DanRNeeser@Eaton.com. Electrical Hazards 2/18/2015. Shock. Arc Flash Hazards Dan Neeser Field Application Engineer DanRNeeser@Eaton.com Electrical Hazards Electrical Hazards Shock Arc Flash Arc Blast 2 1 Arcing Fault Basics 35,000 F Radiant Heat & UV Speed of

More information

Short Circuit Current Calculations

Short Circuit Current Calculations Introduction Several sections of the National Electrical Code relate to proper overcurrent protection. Safe and reliable application of overcurrent protective devices based on these sections mandate that

More information

SECTION 16999 ELECTRICAL ACCEPTANCE TESTS

SECTION 16999 ELECTRICAL ACCEPTANCE TESTS SECTION 16999 ELECTRICAL ACCEPTANCE TESTS PART 1 2. AND 3. COMBINED 1.1 SUMMARY A. Description of Systems 1. Furnish all labor, materials, test equipment, and technical supervision to perform and record

More information

Replacement Breakers & Retrofit Products

Replacement Breakers & Retrofit Products 14 SWITCHGEAR Replacement Breakers & Retrofit Products Medium Voltage Replacement Circuit Breakers Ratings from 5 38 kv, 250 1500 MVA, 1200-3000 Amperes Replacement circuit breakers provide a cost-effective

More information

HAZARDS, INCLUDING SHOCK, ARC FLASH AND FIRE

HAZARDS, INCLUDING SHOCK, ARC FLASH AND FIRE Appendix B-2 - Electrical Safety In Design Final Report TECHNOLOGIES THAT REDUCE LIKELIHOOD OF INJURY FROM ELECTRICAL HAZARDS, INCLUDING SHOCK, ARC FLASH AND FIRE The following are technologies that reduce

More information

Industrial Automation Commonly-Used Terms

Industrial Automation Commonly-Used Terms Engineering Smarter Systems Industrial Automation Commonly-Used Terms A Glossary of Industrial Automation and Control Terms LECINC.COM 1 A Accelerating Time: Across the Line Starter: Action Device: Actuator:

More information

UNIVERSITY OF WASHINGTON Facilities Services Design Guide. Electrical. Switchboards. Basis of Design. Design Evaluation

UNIVERSITY OF WASHINGTON Facilities Services Design Guide. Electrical. Switchboards. Basis of Design. Design Evaluation Basis of Design This section applies to the design relating to low voltage switchboards. Design Criteria UW Class N1 facilities main switchboards shall be rear accessible. The main, tie and feeder breakers

More information

National Craft Assessment and Certification Program S P E C I F I C A T I O N S

National Craft Assessment and Certification Program S P E C I F I C A T I O N S National Craft Assessment and Certification Program S P E C I F I C A T I O N S INDUSTRIAL ELECTRICIAN V4 ELEC26_O4 Released September 2013 Focus Statement An Industrial Electrician must be able to interpret

More information

A Practical Guide to Dielectric Testing

A Practical Guide to Dielectric Testing Chroma Systems Solutions, Inc. A Practical Guide to Dielectric Testing 19032 Series Electrical Safety Analyzer & 19050 Series Hipot Tester AC/DC/IR/SCAN Keywords: Dielectric tests, insulation resistance

More information

MTE SERIES RLW. World REACTORS USER MANUAL PART NO. INSTR 030 REL. 090930. 2009 MTE Corporation

MTE SERIES RLW. World REACTORS USER MANUAL PART NO. INSTR 030 REL. 090930. 2009 MTE Corporation MTE SERIES RLW World REACTORS USER MANUAL PART NO. INSTR 030 REL. 090930 2009 MTE Corporation IMPORTANT USER INFORMATION NOTICE MTE Series RLW reactors are components designed to improve the reliability

More information

Evaluating Fire- and Heat-Damaged Electrical Equipment

Evaluating Fire- and Heat-Damaged Electrical Equipment Evaluating Fire- and Heat-Damaged Electrical Equipment www.nema.org 1 USE OF THIS PUBLICATION This publication provides information on how to evaluate electrical equipment that has been exposed to heat

More information

01.4IB.51200B PowlVac-AR Arc Resistant Switchgear. 5kV & 15kV 1200A, 2000A, 3000A, & 4000A Forced Cooled. Powered by Safety

01.4IB.51200B PowlVac-AR Arc Resistant Switchgear. 5kV & 15kV 1200A, 2000A, 3000A, & 4000A Forced Cooled. Powered by Safety PowlVac-AR Arc Resistant Switchgear 1200A, 2000A, 3000A, & 4000A Forced Cooled Powered by Safety PowlVac-AR Arc Resistant Switchgear 01.4IB.51200B Contact Information Powell Electrical Systems, Inc. www.powellind.com

More information

METER REQUIREMENTS GENERAL REQUIREMENTS SECTION D

METER REQUIREMENTS GENERAL REQUIREMENTS SECTION D 12 - ELECTRIC SERVICE HANDBOOK SECTION D METER REQUIREMENTS This chapter gives you information on Central Lincoln s metering requirements. It's divided into three sections: General requirements This section

More information

(3) Explosion proof. Designed to prevent ignition of any explosive gases or dust and dirt which may surround the motor.

(3) Explosion proof. Designed to prevent ignition of any explosive gases or dust and dirt which may surround the motor. ELECTRIC MOTORS Enclosures for Motors Types of motor enclosures generally used in farm applications: (1) Open type; drip proof or splash-proof. A general purpose motor for use in dry locations which are

More information

PRODUCT GUIDE. SL Medium Voltage IEC Vacuum Contactors

PRODUCT GUIDE. SL Medium Voltage IEC Vacuum Contactors PRODUCT GUIDE SL Medium Voltage IEC Vacuum Contactors Table of Contents 1 Overview Introduction....................................................2 Features........................................................2

More information

Product Description Digital Solid State Starting Electric Fire Pump Controllers FTA1930

Product Description Digital Solid State Starting Electric Fire Pump Controllers FTA1930 Product Description Digital Solid State Starting Electric Fire Pump Controllers FTA1930 Description Firetrol FTA1930 Digital Solid State Starting Fire Pump Controllers feature soft start, soft stop and

More information

MEDIUM AND HIGH VOLTAGE CAPACITORS, CAPACITOR BANKS AND SYSTEMS

MEDIUM AND HIGH VOLTAGE CAPACITORS, CAPACITOR BANKS AND SYSTEMS MEDIUM AND HIGH VOLTAGE CAPACITORS, CAPACITOR BANKS AND SYSTEMS Meher Capacitors offers reliable and innovative products and solutions in the fields of Reactive Power Compensation, Power Quality and Energy

More information

Sentron Series Circuit Breakers

Sentron Series Circuit Breakers Sentron Series Circuit Breakers Siemens Sentron Series circuit breakers are available in nine frame sizes: ED, FD, JD, LD, LMD, MD, ND, PD, and RD. Sentron Series circuit breakers have a wide range of

More information

SUBJECT: How to wire a motor starter Number: AN-MC-004 Date Issued: 2/08/2005 Revision: Original

SUBJECT: How to wire a motor starter Number: AN-MC-004 Date Issued: 2/08/2005 Revision: Original SUBJECT: How to wire a motor starter Number: AN-MC-004 Date Issued: 2/08/2005 Revision: Original A motor starter is a combination of devices to allow an induction motor to start, run and stop according

More information

ELECTRIC HEATER COMPANY Operating and Maintenance Manual For Immersion Heating Elements

ELECTRIC HEATER COMPANY Operating and Maintenance Manual For Immersion Heating Elements ELECTRIC HEATER COMPANY Operating and Maintenance Manual For Immersion Heating Elements HUBBELL ELECTRIC HEATER COMPANY P.O. BOX 288 STRATFORD, CT 06615 PHONE: (203) 378-2659 FAX: (203) 378-3593 INTERNET:

More information

Installation Instructions for Alarm Module Kit A043F059

Installation Instructions for Alarm Module Kit A043F059 Instruction Sheet 07-2013 Installation Instructions for Alarm Module Kit A043F059 1 Introduction The information contained within is based on information available at the time of going to print. In line

More information

Part 1 System Modeling & Studies for Existing Systems

Part 1 System Modeling & Studies for Existing Systems Part 1 System Modeling & Studies for Existing Systems Operation Technology, Inc. Copyright 2009 Result of rapid release of energy due to an arcing fault between two conductors. Bus voltages > 208V Temperatures

More information

IRRIGATION PUMPING Table of Contents - Section 900

IRRIGATION PUMPING Table of Contents - Section 900 IRRIGATION PUMPING Table of Contents - Section 900 PARAGRAPH 900.1 GENERAL 1 900.2 METERING REQUIREMENTS 1 900.3 CUSTOMER S CONTROL EQUIPMENT 2 900.4 SERVICE CONDUCTOR REQUIREMENTS 2 900.5 RECOMMENDATIONS

More information

FFI. Advances in Medium and Low Voltage Power Distribution ESS Metron Expo and Technical Seminars. Presented By: Greg Pelster & Robert Schmid

FFI. Advances in Medium and Low Voltage Power Distribution ESS Metron Expo and Technical Seminars. Presented By: Greg Pelster & Robert Schmid Advances in Medium and Low Voltage Power Distribution ESS Metron Expo and Technical Seminars Presented By: Greg Pelster & Robert Schmid FFI Ferrie, Franzmann Industries LOW VOLTAGE SWITCHGEAR & LOW VOLTAGE

More information

ELECTRICAL SAFETY. The standard unit for measuring electrical current.

ELECTRICAL SAFETY. The standard unit for measuring electrical current. ELECTRICAL SAFETY Introduction The following sections provide general safety guidelines and procedures for electrical safety. This chapter covers the following topics: TOPIC PAGE General Electrical Safety

More information

Power/Vac Metal-Clad Switchgear and Vacuum Circuit Breakers Maintenance and Troubleshooting Suggestions

Power/Vac Metal-Clad Switchgear and Vacuum Circuit Breakers Maintenance and Troubleshooting Suggestions 1 GE Consumer & Industrial Electrical Distribution Applications / Specifications DET-456 Power/Vac Metal-Clad Switchgear and Vacuum Circuit Breakers Maintenance and Troubleshooting Suggestions 2 POWER/VAC

More information

GROUND DETECTION CIRCUITS FOR STATIONARY APPLICATIONS (IN PLAIN DOWN TO EARTH LANGUAGE)

GROUND DETECTION CIRCUITS FOR STATIONARY APPLICATIONS (IN PLAIN DOWN TO EARTH LANGUAGE) GROUND DETECTION CIRCUITS FOR STATIONARY APPLICATIONS (IN PLAIN DOWN TO EARTH LANGUAGE) Matthew Theriault Designer Hindle Power Inc. Easton, PA SCOPE AND PURPOSE OF THE PAPER Why do we bother to monitor

More information

Oil and Coolant Circulating Heating System. Model - OCSM

Oil and Coolant Circulating Heating System. Model - OCSM Oil and Coolant Circulating Heating System Model - OCSM Installation & Operation Manual 216280-000 REV 2 Identifying Your System The HOTSTART heating system is designed to heat fluids for use in marine

More information

INSTALLATION AND MAINTENANCE INSTRUCTIONS FOR THREE PHASE INDUCTION MOTORS

INSTALLATION AND MAINTENANCE INSTRUCTIONS FOR THREE PHASE INDUCTION MOTORS INSTALLATION AND MAINTENANCE INSTRUCTIONS FOR THREE PHASE INDUCTION MOTORS Frames 143T - 449TZ 5100 North IH 35 Round Rock, Texas 78681 Phone: 800-451-8798 512-255-4141 Fax: 512-244-5512 RECEIVING 1. Check

More information

E&I MAINTENANCE ENTRY TEST ENABLING OBJECTIVES. DESCRIBE hazards and precautions taken to avoid injury in the workplace.

E&I MAINTENANCE ENTRY TEST ENABLING OBJECTIVES. DESCRIBE hazards and precautions taken to avoid injury in the workplace. SAFETY Industrial DESCRIBE hazards and precautions taken to avoid injury in the workplace. Example #1: All of the following are common PPE used to perform maintenance activities EXCEPT: a. Safety Glasses

More information

Choosing the Best Solution for Reducing Arc Energy

Choosing the Best Solution for Reducing Arc Energy CONVENTION SESSION HANDOUT Choosing the Best Solution for Reducing Arc Energy Terry L. Schiazza, Business Development Manager Square D / Schneider Electric SESSION #11 Independent Electrical Contractors

More information

Digital Energy ITI. Instrument Transformer Basic Technical Information and Application

Digital Energy ITI. Instrument Transformer Basic Technical Information and Application g Digital Energy ITI Instrument Transformer Basic Technical Information and Application Table of Contents DEFINITIONS AND FUNCTIONS CONSTRUCTION FEATURES MAGNETIC CIRCUITS RATING AND RATIO CURRENT TRANSFORMER

More information

Bussmann. All-In-One Module. Bussmann Power Module Switch. How to configure Part Numbers: Step 1: Select Switch Amperage 1

Bussmann. All-In-One Module. Bussmann Power Module Switch. How to configure Part Numbers: Step 1: Select Switch Amperage 1 How to configure Part Numbers: Step : Select Switch Amperage Power Module Switch Rating (Amps) Power Module Switch Catalog No. 30 3 60 6 00 200 2 400 4 Step 2: Select Options Needed 5 Bussmann Power Module

More information

Arc Flash Mitigation. Remote Racking and Switching for Arc Flash danger mitigation in distribution class switchgear.

Arc Flash Mitigation. Remote Racking and Switching for Arc Flash danger mitigation in distribution class switchgear. Arc Flash Mitigation Remote Racking and Switching for Arc Flash danger mitigation in distribution class switchgear. Distance is Safety We will discuss through examples of actual occurrences and possible

More information

Bypass transfer switch mechanisms

Bypass transfer switch mechanisms Power topic #6013 Technical information from Cummins Power Generation transfer switch mechanisms > White paper By Gary Olson, Director, Power Systems Development This paper describes the configuration

More information

Circuit Breakers. NRC Series. NRC Series. 900 www.idec.com

Circuit Breakers. NRC Series. NRC Series. 900 www.idec.com Switches & Pilot Lights Display Lights NRC series circuit breakers offer circuit protection which is far superior to using fuses in applications containing relay circuits, motor circuits, heater circuits,

More information

WINDING RESISTANCE TESTING

WINDING RESISTANCE TESTING WINDING RESISTANCE TESTING WINDING RESISTANCE TEST SET, MODEL WRT-100 ADWEL INTERNATIONAL LTD. 60 Ironside Crescent, Unit 9 Scarborough, Ontario, Canada M1X 1G4 Telephone: (416) 321-1988 Fax: (416) 321-1991

More information

STANDARDS AND RATINGS FOR THE APPLICATION OF MOLDED CASE, INSULATED CASE, AND POWER CIRCUIT BREAKERS

STANDARDS AND RATINGS FOR THE APPLICATION OF MOLDED CASE, INSULATED CASE, AND POWER CIRCUIT BREAKERS STANDARDS AND RATINGS FOR THE APPLICATION OF MOLDED CASE, INSULATED CASE, AND POWER CIRCUIT BREAKERS David D. Roybal, P.E. Senior Member, IEEE Cutler-Hammer, Inc. 3697 Mount Diablo Boulevard Lafayette,

More information

Standard for an Electrical Preventive Maintenance (EPM) Program

Standard for an Electrical Preventive Maintenance (EPM) Program Recommended Maintenance Practices for Electrical Distribution System Equipment Hartford Steam Boiler One State Street P.O. Box 5024 Hartford, CT 06102-5024 Tel: (800) 472-1866 www.hsb.com April 2013 Introduction

More information

INSTRUCTIONS FOR MAGNUM DS TRIP UNIT TESTING USING TEST KIT SYLES 140D481G02R, 140D481G02RR, 140D481G03 AND 140D481G04

INSTRUCTIONS FOR MAGNUM DS TRIP UNIT TESTING USING TEST KIT SYLES 140D481G02R, 140D481G02RR, 140D481G03 AND 140D481G04 I.L. 32-693 A INSTRUCTIONS FOR MAGNUM DS TRIP UNIT TESTING USING TEST KIT SYLES 140D481G02R, 140D481G02RR, 140D481G03 AND 140D481G04 DANGER DO NOT ATTEMPT TO INSTALL OR PERFORM MAINTE- NANCE ON EQUIPMENT

More information

Sample - No Commercial Use

Sample - No Commercial Use COMPLETE REVISION October 2010 Electrical PIP ELSSG01 Design and Fabrication of Low-Voltage Metal-Enclosed AC Power Circuit Breaker Switchgear PURPOSE AND USE OF PROCESS INDUSTRY PRACTICES In an effort

More information

What are the basic electrical safety issues and remedies in solar photovoltaic installations?

What are the basic electrical safety issues and remedies in solar photovoltaic installations? What are the basic electrical safety issues and remedies in solar photovoltaic installations? Presented by: Behzad Eghtesady City of Los Angeles Department of Building and Safety Topics Covered Photovoltaic

More information

This section applies to the design and installation of transformers.

This section applies to the design and installation of transformers. ELECTRICAL: TRANSFORMERS BASIS OF DESIGN This section applies to the design and installation of transformers. Design Criteria 13.8-kV equipment shall be 15-kV class. Coordinate with short-circuit studies

More information

Determining the Cause of AFCI Tripping Branch/Feeder and Combination Arc Fault Circuit Interrupters Class 760

Determining the Cause of AFCI Tripping Branch/Feeder and Combination Arc Fault Circuit Interrupters Class 760 Data Bulletin Determining the Cause of AFCI Tripping Branch/Feeder and Combination Arc Fault Circuit Interrupters Class 760 Retain for future use. 0760DB0204 Replaces 0760DB0204 R09/07 Precautions DANGER

More information

Insulation resistance testing

Insulation resistance testing resistance testing Application Note Introduction resistance testers can be used to determine the integrity of windings or cables in motors, transformers, switchgear, and electrical installations. The test

More information

Medium Voltage Motor Control Assemblies

Medium Voltage Motor Control Assemblies Medium Voltage Motor Control Assemblies Arc Resistant AMPGARD.1 Product............................................. 2 Application........................................... 2 Features, Benefits and Functions...................................

More information

Test Before Touch Easier Said Than Done. Ken Crawford, DuPont Kent Haggerty, Dupont

Test Before Touch Easier Said Than Done. Ken Crawford, DuPont Kent Haggerty, Dupont Test Before Touch Easier Said Than Done Ken Crawford, DuPont Kent Haggerty, Dupont Overview Test Before Touch (TBT) Principles Key Learnings by One Company One Method for Performing a TBT Induced Voltages

More information