Figures Figure 1. Schematic Diagram of the Challenge 3 Figure 2. Process Block Diagram of the FGD Blowdown Treatment System 5

Size: px
Start display at page:

Download "Figures Figure 1. Schematic Diagram of the Challenge 3 Figure 2. Process Block Diagram of the FGD Blowdown Treatment System 5"

Transcription

1 IWC Case Study: Cost-minimization Approach to the Design, Procurement, Installation and Commissioning of a FGD Wastewater Treatment System at a Power Station Antonio O. Lau, Ph.D., Infilco Degremont, Inc. Richard A. Ubaldi, Infilco Degremont, Inc. Michael G. McDonough, Dominion Resources Services, Inc. Edward V. Bowes, formerly with Dominion Wayne G. Spitzner, formerly with Dominion Keywords: Flue Gas Desulfurization, Wastewater, Heavy Metals, Open Book Table of Contents Abstract 2 Background 2 Introduction to the Challenge 2 The Technical Challenge and its Solution 3 The Open Book Concept for Project Implementation 6 The Goal 6 Scope and Responsibility 7 Payment Basis 9 Major Commercial Terms 9 Benefits of a DRS-IDI Open Book Alliance 10 Project Execution 12 Summary 12 References 12 Acknowledgements 12 Figures Figure 1. Schematic Diagram of the Challenge 3 Figure 2. Process Block Diagram of the FGD Blowdown Treatment System 5 Tables Table 1. Removal of Total Suspended Solids (TSS) and Heavy Metals from the FGD Blowdown Stream 4 Table 2. Benefits of a DRS-IDI Open Book Alliance 10 1

2 Abstract An innovative approach was utilized to design, procure, install and commission a FGD wastewater treatment system at a power generating station in Virginia. Dominion Resources Services, Inc. (DRS) and Infilco Degremont, Inc. (IDI) partnered to develop and optionally install a cost-effective flue-gas desulfurization (FGD) wastewater treatment system using a phased, Open Book approach. One of the critical steps in this approach is to define the wastewater treatment process interactively between the Owner, DRS, and the scrubber and wastewater treatment Equipment Suppliers. This step proved to be successful in minimizing the overall project cost because it recognized the inter-dependent design aspects of two important systems previously evaluated independently, while eliminating those expenditures associated with uncertainties (i.e., contingencies) normally built into a process design in typical competitive bids. This highly successful project was commissioned in 2009, costs were kept below the target value, and the facility met all the performance guarantees. A detailed discussion on the implementation of this Open Book concept is provided in this paper. Background Air emissions from coal-fired power plants require the installation of various types of air pollution control system technologies. One such technology is the use of wet scrubbers for the removal of sulfur dioxide (SO 2 ) from stack emissions. The wet scrubbing of flue gases with lime or limestone slurries is a proven and commercially established process to decrease SO 2 emissions. However, inherent with this system is the blowdown of a slurry stream that contains elevated concentrations of suspended and dissolved solids, chlorides, sulfates, heavy metals (chromium, mercury, selenium, etc.), and nitrates. FGD systems available in the marketplace have different combinations of characteristics (such as coal type, scrubber type, additive use, operational strategies, etc.) that result in extremely varied wastewater characteristics. This paper describes the unique implementation of a physical/chemical treatment process for the removal of total suspended solids (TSS) and heavy metals from a FGD blowdown stream. Introduction to the Challenge The DRS project engineering team developed the conceptual process values and system design, and then commissioned detailed engineering of the FGD system and Balance of Project designs to an Architectural/Engineering consulting engineering firm. They also decided that economically the gypsum produced by the FGD system would not be landfilled, but rather sent to a wall board manufacturer who provided stringent gypsum quality criteria. The final component of the FGD system required a downstream wastewater treatment (WWT) system to handle the variable characteristics of the blowdown stream. Thus, an iterative design approach had to be undertaken to generate the most cost-effective wastewater treatment system that was 2

3 flexible enough to handle the expected blowdown variations while equally matched to the most cost-effective scrubber system. This integrated System is extremely important because a malfunctioning WWT System would compromise the gypsum quality, requiring it to be sent to a landfill, or worse, cause the issuance of violation notices because of effluent excursions. Figure 1. Schematic Diagram of the Challenge Gas Scrubber Gypsum Blowdown WWT System Because the cost of the initial scrubber system is so much higher than the downstream WWT System, scrubber decisions often come first, and the WWT System must be designed to match the scrubber blowdown values required to maintain gypsum quality. A typical project execution method would then commission a consulting engineering firm to broadly layout the WWT System parameters and have separate supplies bid an independent detailed design. However, DRS, who has a competent engineering staff of their own, decided to explore the advantages of an Open Book agreement directly with a WWT supplier who had expertise in treating complex FGD wastewaters and could assist in optimizing the integration of the various processes directly with DRS. Under this approach, the commissioned engineering firm was used as the overall project advisor. DRS also had options of their own relating to the siting of the WWT system within the plant boundaries which affected the design, layout and ultimate cost. These options also benefitted from the Open Book collaboration. The Technical Challenge and its Solution IDI has extensive experience in designing WWT systems for FGD wastewaters. The influent design parameters were the following: Flow Rate: 300 gpm (150 gpm per scrubber) Total Suspended Solids (TSS): 20,000 mg/l Total Dissolved Solids (TDS): 20,000 60,000 mg/l Chlorides: 30,000 mg/l 3

4 The requirements of the WWT system were as follows: Meet or exceed 20 heavy metal effluent requirements. Provide 99% operational reliability. Comply with the limited space availability. WWT system to be completely indoors. Design a future biological treatment system to meet expected requirements for selenium and nutrient control. The WWT system proposed by IDI met all these requirements and is shown below in Table 1 and Figure 2. Table 1. Removal of Total Suspended Solids (TSS) and Heavy Metals from the FGD Blowdown Stream Parameter Removal Efficiency (%) TSS 99.9 Ag 90 Al 99.5 As 96.7 Cd 95 Cu 95 Cr 70 Fe 99.7 Hg 90 Ni 75 Pb 90 Zn 98 4

5 Figure 2. Process Block Diagram of the FGD Blowdown Treatment System FGD Wastewater 300 GPM (Max) ph = 6.0 Equalization Tank Lime Desaturation Tank ph = Sludge Recycle Organo-Sulfide Coagulant Metals Precipitation Tanks Flocculant Sludge Waste Clarifiers/Thickeners (DensaDeg ) HCI Effluent Tank Sludge Dewatering System Ash Storage Area 5

6 The overall treatment process consisted of the following components: 1. Wastewater Equalization Tank. 2. Desaturation Tank for ph elevation and gypsum desaturation using lime, (Ca(OH) 2 ), to raise the ph to the required level for optimum treatment. 3. External Sludge Recirculation from the DensaDeg Clarifiers/Thickeners to the Desaturation Tank to aid in gypsum desaturation. 4. Heavy Metal Precipitation Tanks (2 tanks) using an organo-sulfide solution. 5. Dosing of a Coagulant, such as ferric chloride. 6. Dosing of a Flocculant aid (e.g., polymer) to the Reactor Tank of the DensaDeg units. 7. Flocculation, Sedimentation, Thickening and Final Clarification in the DensaDeg Clarifiers/Thickeners (2 units). 8. ph adjustment at the outlet of the DensaDeg units to a ph range of Excess sludge removal from the DensaDeg units. 10. Effluent Tank. 11. Sludge dewatering system (Sludge Holding Tank and 2 recessed chamber filter presses). The Open Book Concept for Project Implementation The Goal The goal of the Open Book approach was to establish an exclusive contractual relationship to align the resources of DRS and IDI to work together toward a common goal of achieving a superior, value-added FGD blowdown WWT System design. This approach would also utilize the expertise from all three parties (DRS, IDI and the Engineer) to develop an optimally designed, environmentally compliant WWT System in accordance with all current federal, state and local codes, laws and regulations. The goals of the parties further included defining in greater specificity the following items: Wastewater influent and effluent characteristics, physical-chemical and biological treatment considerations, operating parameters and transients and both current and projected regulatory thresholds. 6

7 Required WWT System components and redundancy. Required chemical and polymer selection and consumption. Footprint location on a crowded power plant site. WWT System capital cost. Development of the construction bid package based on final engineering drawings. Expedited implementation schedule. Construction oversight and/or management. Start-up, testing and commissioning. Operator training and system turnover. Operating considerations and refinements. Cost of initial investment (including start-up spare parts and consumables). Sludge production, dewatering capabilities and disposal. Individual equipment warranties and overall system performance parameters. Scope and Responsibility The itemized WWT System scope and responsibility of the parties were outlined in five phases. Phase I Joint Development This first phase consisted on the following activities by the IDI Team at no cost to DRS. Participated and provided technical support to include, but not be limited to, participation in the design and scheduling coordination meetings, meetings with plant operators, and touring appropriate facilities as required. Provided preliminary layout, flow and P&ID drawings, boundary interfaces and related documentation and data for the WWT System, including better definition of the influent and effluent parameters and their possible variations. 7

8 Progressively developed a scope of supply and services and corresponding WWT System target pricing, cost and consumption of chemicals and polymers and with options and/or alternatives. Assisted in providing technical support and commercial discussions as necessary to better discuss and promote the technology of the WWT System. Provided technical support to DRS in its permit applications and any public hearings that were required. The DRS Team provided its parallel support and any third party costs required to achieve the above goals. At the conclusion of Phase I, a not-to-exceed target price was developed and DRS made their decision to proceed with a full contract covering the balance of the Phases. Had DRS decided not to go further than Phase I, IDI would have been paid a not-to-exceed documented cost previously agreed upon by both organizations. Phase II Detailed Engineering and Design Continuing from the support items in Phase I, IDI provided the following: Coordinated the development of the Project s Critical Path Milestones (CPM) with DRS as it related to the System supply. Completed all process engineering and design and submitted to DRS for review and approval of all drawings and documentation. Refined bidder s list and solicited competitive bids for all equipment and any required third party services. Completed all bid evaluations, shared evaluation results and recommendations with DRS. Processed the awards to selected equipment bidders. Completed all WWT System descriptions. Phase III Equipment Procurement, Fabrication and Delivery Provided equipment costs with an explicit mark-up. Jointly prepared a construction bid package for DRS use. Phase IV Start-up, Testing and Equipment Commissioning Provided support for the start-up, testing and commissioning of the WWT system based on agreed upon service rates for IDI personnel conducting field work. 8

9 Phase V - Warranty Period Provided a 2 year warranty for all supplied equipment. Payment Basis As noted above, the DRS-IDI Open Book alliance used an incentivized payment schedule wherein both parties benefited from the long-term working relationship. The following general provisions were used: Payments to IDI were linked to the five phases of the Project. IDI offered to pay its own internal and approved third-party costs during Phase I. Payment for the balance of the phases was linked to defined, mutually agreed set of milestones with the expectation that they included as a minimum, coverage for detailed engineering, release for fabrication, equipment delivery and final commissioning. IDI s detailed internal and third-party engineering, procurement and project coordination costs, including overhead and margin, were a lump-sum, not-to-exceed cost guarantee plus a determined and explicit percentage management and profit fee. Agreed overage and/or approved change notices were billed at an agreed upon rate. IDI s proprietary equipment and third-party equipment were furnished as a lump sum not-to-exceed cost guarantee plus a management fee. IDI provided site field service cost for in-state start-up, testing, commissioning and any follow-up non-warranty service at an agreed-upon rate. An incentive program was also implemented to provide both parties with opportunities to reduce costs and prevent overruns. Major Commercial Terms The following major commercial terms were included in the Open Book agreement: IDI guaranteed meeting mutually agreed critical path milestone events, including delivery of all major equipment, or be subject to proportionately derived liquidated damages, the sum of which would not exceed an agreed upon percentage of the WWT System cost. IDI guaranteed that it would meet mutually agreed-upon WWT System performance parameters or it would repair and/or replace such WWT System components as necessary at its expense until such performance was achieved. The sum of any incurred liability to include liquidated damages or make whole performance obligations was limited to a value of the WWT System cost. 9

10 IDI provided warranty for each equipment component of the WWT System in accordance with its standard warranty provisions for 2 years from Provisional Acceptance or 30 months from receipt of equipment on site, whichever came first. Neither party was liable to the other for any special, incidental or consequential damages in connection to work performed as part of the Project. Other commercial terms and conditions such as scheduling and coordination, confidentiality and exclusivity, insurance, taxes, force majeure, design changes, documentation and audit rights, indemnification, dispute resolution and termination were incorporated into the definitive agreement by mutual agreement and in accordance with accepted industry standards for such clauses. Benefits of a DRS-IDI Open Book Alliance The Open Book approach to project implementation provided the following benefits to the DRS- IDI alliance: Table 2. Benefits of a DRS-IDI Open Book Alliance BENEFIT Open Book, Not-to-Exceed Price IMPACT 1. Given the iterative nature of FGD effluent treatment, this approach provided DRS with an important understanding of cost components. 2. Not-to-exceed price provided a platform for DRS to accurately budget expenses. Interactive Design Approach 1. Allowed for discussions with DRS, Owner s Engineer, and scrubber supplier to refine the total system design from a cost and performance standpoint. 2. Reduced design changes. 3. Expedited schedule. Committed Resources IDI planned and reserved its prime resources and those of its prime sub-contractors for the benefit of DRS s project. 10

11 BENEFIT On-going R&D Validation of Design Alternatives IMPACT 1. Verified design assumptions and calculations prior to detailed engineering and fabrication. 2. Avoided unnecessary changes. 3. Expedited schedule. Operator O&M Interface 1. Optimized layout 2. Optimized design for load and transients. 3. Optimized labor and possible shift utilization. 4. Standardized equipment manufacturer selection. 5. Allowed for better implementation of specific needs to ease maintenance. Regulatory Interface 1. IDI assisted DRS in regulatory discussion of control technology. 2. IDI helped present arguments against over-control. 3. IDI helped formulate strategies for favorable public opinion. Expedited Schedule Minimized Construction Cost Team meetings on the above subjects resulted in faster communication of needs and resolution of issues in an open dialogue format. Engineering design was 100% complete before executing the Construction Contract, thus providing an exact design to eliminate contingencies normally applied by the Construction Contractor. 11

12 Project Execution Throughout the project, weekly meetings, monthly reports and progress milestone invoices were provided to DRS, which included a summary of the hours spent and all the procurement costs. Summary A FGD wastewater treatment system was successfully implemented for Dominion Resources Services (DRS) using the Open Book alliance approach. The overall project costs and schedule were minimized because it recognized the inter-dependent design aspects of three important systems (scrubber, wastewater treatment system and gypsum quality) previously evaluated independently, while eliminating those expenditures associated with uncertainties (i.e., contingencies) normally built into a process design in typical competitive bidding situations. The key features of the Open Book project implementation approach were the following: Owner s Engineer was involved in the design and selection of the scrubber and provided additional advisory services for the design and procurement of the WWT System. The EPC contracting strategy was avoided which resulted in cost savings and an expedited project schedule. Direct interaction between DRS and IDI staff resulted in an optimized WWT System at the lowest possible cost. This highly successful project was commissioned in 2009 and the WWT System met all the performance guarantees. The costs were kept below the target value. References 1. Pudvay, Michael L., Operating Experience on the Treatment of FGD Scrubber Blowdown from Existing Generating Stations, IWC-05-69, San Antonio, TX (2005). 2. Mierzejewski, M.K., Wastewater Management at FGD Installations, Proceedings, 88 th Air and Waste Management Association Conference, San Antonio, TX (1995). Acknowledgements We would like to acknowledge the following individuals for their assistance in preparing this paper: Mr. Dwyane Terrier of Dominion, and Hunter Cox, IDI s Project Manager. 12

Environmental Technology March/April 1998

Environmental Technology March/April 1998 Treating Metal Finishing Wastewater Sultan I. Amer, Ph.D. AQUACHEM INC. Environmental Technology March/April 1998 Wastewater from metal finishing industries contains high concentrations of contaminants

More information

Removing Thallium from Industrial FGD Scrubber Water with Sorbster Adsorbent Media

Removing Thallium from Industrial FGD Scrubber Water with Sorbster Adsorbent Media Case History MAR Systems Inc. Removing Thallium from Industrial FGD Scrubber Water with Sorbster Adsorbent Media Trace thallium levels in process and wastewater streams pose a human toxicity threat. Tidwell

More information

Iron and Steel Manufacturing

Iron and Steel Manufacturing Pollution Prevention and Abatement Handbook WORLD BANK GROUP Effective July 1998 Iron and Steel Manufacturing Industry Description and Practices Steel is manufactured by the chemical reduction of iron

More information

Pursuant to Department of Environmental Protection Rules Chapter 555, effective March 9, 2009

Pursuant to Department of Environmental Protection Rules Chapter 555, effective March 9, 2009 APPLICATION FOR ADDITION OF TRANSPORTED WASTES IN WASTEWATER TREATMENT FACILITIES Pursuant to Department of Environmental Protection Rules Chapter 555, effective March 9, 2009 This application is to be

More information

Assessing the Changes Required by the Industrial Boiler MACT Regulations

Assessing the Changes Required by the Industrial Boiler MACT Regulations Technical Paper MS-17 Assessing the Changes Required by the Industrial Boiler MACT Regulations Authors: A.L. LeClair L.M. McDermitt Babcock & Wilcox Power Generation Group, Inc. Barberton, Ohio, U.S.A

More information

Materials Management:

Materials Management: Materials Management: Damodara U. Kini, P.E. OFTEN OVERLOOKED AS A COST SOLUTION, SUCCESSFULLY MANAGING MATERIALS CAN LEAD TO GREATER SAVINGS. Damodara U. Kini is procurement manager at Raytheon, Engineers

More information

Removing Heavy Metals from Wastewater

Removing Heavy Metals from Wastewater Removing Heavy Metals from Wastewater Engineering Research Center Report David M. Ayres Allen P. Davis Paul M. Gietka August 1994 1 2 Removing Heavy Metals From Wastewater Introduction This manual provides

More information

Heavy Metal Separation from Flue Gas Scrub Water with TMT15

Heavy Metal Separation from Flue Gas Scrub Water with TMT15 Heavy Metal Separation from Flue Gas Scrub Water with TMT15 McIlvaine Company Hot Topic Hour on FGD Wastewater Treatment Rüdiger Peldszus June 16, 2011 An attractive company One of the global leaders in

More information

Multi-pollutant control solutions for coal based power plants

Multi-pollutant control solutions for coal based power plants Multi-pollutant control solutions for coal based power plants By Luca Mancuso and Hans Janssen Content SOx control Wet Scrubbers Open towers Dual Flow Tray Technology Semi-Dry SDA CFB Scrubbers Dust control

More information

Bill Maxwell, U.S. Environmental Protection Agency, OAQPS (C439-01)

Bill Maxwell, U.S. Environmental Protection Agency, OAQPS (C439-01) TO: Bill Maxwell, U.S. Environmental Protection Agency, OAQPS (C439-01) FROM: Jeffrey Cole, RTI International DATE: December 2003 SUBJECT: Methodology for Estimating Cost and Emissions Impact for Coal-

More information

Coagulation and Flocculation

Coagulation and Flocculation Coagulation and Flocculation Groundwater and surface water contain both dissolved and suspended particles. Coagulation and flocculation are used to separate the suspended solids portion from the water.

More information

Experience and Qualifications of PROCESS PLANTS CORPORATION

Experience and Qualifications of PROCESS PLANTS CORPORATION Experience and Qualifications of PROCESS PLANTS CORPORATION Table of Contents Section 1. Project Services pg 3-20 Engineering Services Project management Design engineering Design management Construction

More information

IMPACT OF CHEMICALS ADDITION IN WATER/WASTEWATER TREATMENT ON TDS CONCENTRATION AND SLUDGE GENERATION Jurek Patoczka, PhD, PE Hatch Mott MacDonald 27 Bleeker Str., Millburn, NJ 07041 (973) 912 2541 jurek.patoczka@hatchmott.com

More information

Appendix 2-1. Sewage Treatment Process Options

Appendix 2-1. Sewage Treatment Process Options Appendix 2-1 Sewage Treatment Process Options Table of Contents Appendix 2-1 Sewage Treatment Process Options 1 Introduction...1 2 Chemically Enhanced Primary Treatment (CEPT) Processes...2 2.1 CEPT with

More information

Phosphorus Removal. Wastewater Treatment

Phosphorus Removal. Wastewater Treatment Phosphorus Removal In Wastewater Treatment by Derek Shires (512) 940-2393 Derek.Shires@ett-inc.com Why do we care? Eutrophication of surface water - Especially reservoirs Maximum agronomic uptake - Limiting

More information

REQUEST FOR PROPOSAL TO PROVIDE CONSTRUCTION MANAGEMENT AND GENERAL CONTRACTOR SERVICES SPRINGVILLE CITY NEW AQUATICS AND ACTIVITIES CENTER

REQUEST FOR PROPOSAL TO PROVIDE CONSTRUCTION MANAGEMENT AND GENERAL CONTRACTOR SERVICES SPRINGVILLE CITY NEW AQUATICS AND ACTIVITIES CENTER RFP #2016-02 REQUEST FOR PROPOSAL TO PROVIDE CONSTRUCTION MANAGEMENT AND GENERAL CONTRACTOR SERVICES FOR SPRINGVILLE CITY NEW AQUATICS AND ACTIVITIES CENTER RELEASE DATE: January 29, 2016 DUE DATE: February

More information

Wastewater Nutrient Removal

Wastewater Nutrient Removal Wastewater Nutrient Removal An overview of phosphorus and nitrogen removal strategies Presented by: William E. Brown, P.E. Peter C. Atherton, P.E. Why are nutrients an issue in the environment? Stimulates

More information

A Low Cost Chemical Remediation Technology for Heavy Metals in Shipyard Stormwater. SBIR Topic N06 133

A Low Cost Chemical Remediation Technology for Heavy Metals in Shipyard Stormwater. SBIR Topic N06 133 A Low Cost Chemical Remediation Technology for Heavy Metals in Shipyard Stormwater SBIR Topic N06 133 1 Normal Ave, CSAM RI 121A Montclair, NJ 07043 973 655 7385 SIROM TECHNOLOGY SIROM has developed a

More information

ACTIFLO Process For Wet Weather and Wastewater Treatment

ACTIFLO Process For Wet Weather and Wastewater Treatment ACTIFLO Process For Wet Weather and Wastewater Treatment ACTIFLO Microsand Ballasted Clarification Process ACTIFLO is a high rate, compact process developed by Veolia Solutions & Technologies. The process

More information

School Construction Projects

School Construction Projects The process of educating young people seems to be continually developing. New insights regarding how students most effectively receive retain and gain understanding of information and principles affect

More information

Reactor Clarifier Solids Contact Clarifiers

Reactor Clarifier Solids Contact Clarifiers Reactor Clarifier Solids Contact Clarifiers Solids Contact and Flocculating Clarifiers for Water & Wastewater Treatment Key features & benefits Large diameter turbine producing high internal recycling

More information

If you have questions regarding the submittal information, please contact Mr. Jeffrey Davis at (713)795-6207.

If you have questions regarding the submittal information, please contact Mr. Jeffrey Davis at (713)795-6207. ./'""~ NR~ CERTIFIED MAIL May 18,2009 Mr. Richard Kinch US Environmental Protection Agency (5306P) 1200 Pennsylvania Avenue, NW Washington, DC 20460 SUBJECT: Request for Information Under Section 104(e)

More information

REQUEST FOR PROPOSAL: GIS MANAGEMENT AND DESIGN SUPPORT: FOR UTILITY SERVICES OCTOBER 21, 2011 CITY OF ALEXANDRIA DIVISIONS OF FINANCE AND UTILITIES

REQUEST FOR PROPOSAL: GIS MANAGEMENT AND DESIGN SUPPORT: FOR UTILITY SERVICES OCTOBER 21, 2011 CITY OF ALEXANDRIA DIVISIONS OF FINANCE AND UTILITIES REQUEST FOR PROPOSAL: GIS MANAGEMENT AND DESIGN SUPPORT: FOR UTILITY SERVICES OCTOBER 21, 2011 CITY OF ALEXANDRIA DIVISIONS OF FINANCE AND UTILITIES Table of Contents 1 Introduction...2 1.1 Overview...

More information

CHAPTER 8 UPGRADING EXISTING TREATMENT FACILITIES

CHAPTER 8 UPGRADING EXISTING TREATMENT FACILITIES CHAPTER 8 UPGRADING EXISTING TREATMENT FACILITIES 8-1. General. Upgrading of wastewater treatment plants may be required to handle increased hydraulic and organic loadings to meet existing effluent quality

More information

[Project Name] NZTA Contract No. [Contract Number] Schedule of Prices

[Project Name] NZTA Contract No. [Contract Number] Schedule of Prices [Project Name] NZTA Contract No. [Contract Number] Schedule of Prices Schedule of Prices SP1

More information

SYNERGISTIC APPLICATION OF ADVANCED PRIMARY AND SECONDARY WASTEWATER TREATMENT SYSTEMS

SYNERGISTIC APPLICATION OF ADVANCED PRIMARY AND SECONDARY WASTEWATER TREATMENT SYSTEMS SYNERGISTIC APPLICATION OF ADVANCED PRIMARY AND SECONDARY WASTEWATER TREATMENT SYSTEMS Published in Water and Waste Digest membrane issue, November 2008 Miroslav Colic; Chief Scientist, Clean Water Technology

More information

Technical Feasibility of a Wet Weather Flow Treatment Facility

Technical Feasibility of a Wet Weather Flow Treatment Facility Wastewater Master Plan DWSD Project No. CS-1314 Technical Feasibility of a Wet Weather Flow Treatment Facility Technical Memorandum Original Date: August 9, 2001 Revision Date: September 2003 Author: Tetra

More information

PROJECT PROCUREMENT MANAGEMENT

PROJECT PROCUREMENT MANAGEMENT 12 PROJECT PROCUREMENT MANAGEMENT Project Procurement Management includes the processes required to acquire goods and services from outside the performing organization. For simplicity, goods and services,

More information

Facility Classification Standards

Facility Classification Standards Facility Classification Standards Approval Date: April 3, 2009 Effective Date: April 3, 2009 Approved By: Nancy Vanstone, Deputy Minister Version Control: Replaces Facility Classification Standards dated

More information

INCINERATION IN JAPAN

INCINERATION IN JAPAN INCINERATION IN JAPAN DR. CHIAKI IZUMIKAWA Regulations in the environmental field are becoming severe and severe. At the same time, NIMBY syndrome is becoming stronger day by day. The cost of incineration

More information

WISCONSIN WASTEWATER OPERATORS ASSOCIATION

WISCONSIN WASTEWATER OPERATORS ASSOCIATION Integrity. People. Knowledge. WISCONSIN WASTEWATER OPERATORS ASSOCIATION ANNUAL CONFERENCE GREEN BAY Resources. MEETING LOW LEVEL PHOSPHORUS LIMITS BY CHEMICAL ADDITION WHAT IS PHOSPHORUS Atomic # 15 Electron

More information

September 2014 Report No. 15-001

September 2014 Report No. 15-001 John Keel, CPA State Auditor An Audit Report on Selected Contracts at the Texas Facilities Commission Report No. 15-001 An Audit Report on Selected Contracts at the Texas Facilities Commission Overall

More information

City of Dallas Specifications for Sewer Camera Maintenance & Repair Services with Parts BM1308

City of Dallas Specifications for Sewer Camera Maintenance & Repair Services with Parts BM1308 City of Dallas Specifications for Sewer Camera Maintenance & Repair Services with Parts BM1308 PURPOSE: The purpose for this specification is to establish a 36 month service contract for maintenance and

More information

Owner s project control review. 2014 Baker Tilly Virchow Krause, LLP

Owner s project control review. 2014 Baker Tilly Virchow Krause, LLP Owner s project control review 2014 Baker Tilly Virchow Krause, LLP About Baker Tilly > Established in 1931 > One of the top 20 largest accounting and advisory firms in the United States according to Accounting

More information

THE LAW OF BIOMASS Setting Up Shop: Design, Engineering, and Construction of Biomass Projects

THE LAW OF BIOMASS Setting Up Shop: Design, Engineering, and Construction of Biomass Projects THE LAW OF BIOMASS Setting Up Shop: Design, Engineering, and Construction of Biomass Projects Karl F. Oles Stoel Rives LLP 600 University Street, Suite 3600 Seattle, WA 98101-4109 206-386-7535 kfoles@stoel.com

More information

TABLE OF CONTENTS Number Subject Date Financial Policies Internal Controls Financial Reporting Revenue Management Treasury Expenditure Management

TABLE OF CONTENTS Number Subject Date Financial Policies Internal Controls Financial Reporting Revenue Management Treasury Expenditure Management TABLE OF CONTENTS Number Subject Date Financial Policies 501 Policy Framework 07/11/2012 Internal Controls 502 Internal Controls and Fraud Prevention 07/11/2012 503 Ethics 07/11/2012 Financial Reporting

More information

GUIDELINES FOR LEACHATE CONTROL

GUIDELINES FOR LEACHATE CONTROL GUIDELINES FOR LEACHATE CONTROL The term leachate refers to liquids that migrate from the waste carrying dissolved or suspended contaminants. Leachate results from precipitation entering the landfill and

More information

Considered: 05/24/2016

Considered: 05/24/2016 EXECUTIVE SUMMARY SANTA CLARA COUNTY CIVIC CENTER PROPOSED MASTER DEVELOPMENT AGREEMENT Revised May 2, 2016 County Team County, Office of Asset and Economic Development, Office of the County Executive

More information

Description of the Water Conserv II Facility

Description of the Water Conserv II Facility Description of the Water Conserv II Facility Introduction The Water Conserv II (WCII) Water Reclamation Facility provides service to a majority of the southwest section of Orlando. The WCII facility has

More information

Sustainable Water Management. for the Power Industry

Sustainable Water Management. for the Power Industry Sustainable Water Management for the Power Industry for the Power industry Creating water solutions Water and Wastewater Treatment Specialist Veolia Water Solutions & Technologies has over 300 power generation

More information

WASTEWATER TREATMENT OBJECTIVES

WASTEWATER TREATMENT OBJECTIVES WASTEWATER TREATMENT OBJECTIVES The student will do the following: 1. Define wastewater and list components of wastewater. 2. Describe the function of a wastewater treatment plant. 3. Create a wastewater

More information

TRANSPORT FOR LONDON (TfL) LOW EMISSIONS CERTIFICATE (LEC) GUIDANCE NOTES FOR THE COMPANY AUDIT PROCESS. LEC (Company Audit) Guidance Notes

TRANSPORT FOR LONDON (TfL) LOW EMISSIONS CERTIFICATE (LEC) GUIDANCE NOTES FOR THE COMPANY AUDIT PROCESS. LEC (Company Audit) Guidance Notes TRANSPORT FOR LONDON (TfL) LOW EMISSIONS CERTIFICATE (LEC) GUIDANCE NOTES FOR THE COMPANY AUDIT PROCESS LEC (Company Audit) Guidance Notes Glossary of Terms Transport for London (TfL) London Low Emission

More information

This example of a completed sampling plan worksheet has been included to illustrate the information

This example of a completed sampling plan worksheet has been included to illustrate the information APPENDIX B EXAMPLE OF A COMPLETED SAMPLING PLAN WORKSHEET This example of a completed sampling plan worksheet has been included to illustrate the information necessary to document a sampling program for

More information

https://www.ofgem.gov.uk/publications-and-updates/ofto-build-providing-additional-flexibility-through-extendedframework

https://www.ofgem.gov.uk/publications-and-updates/ofto-build-providing-additional-flexibility-through-extendedframework All interested parties Direct Dial: 020 7901 1849 Email: transmissioncompetition@ofgem.gov.uk Date: 17 November 2015 Dear Colleague EPC Contract Principles for OFTO Build Tenders This letter provides guidance

More information

MAJOR EQUIPMENT PURCHASE CONTRACT

MAJOR EQUIPMENT PURCHASE CONTRACT MAJOR EQUIPMENT PURCHASE CONTRACT CONSUMERS ENERGY COMPANY ONE ENERGY PLAZA JACKSON, MI 49201 ( Buyer ) ( Seller ) Date:, 20 Subject to the provisions of this Major Equipment Purchase Contract ( Contract

More information

Sealed bids will be received by the City of Dearborn, at the Office of the Purchasing

Sealed bids will be received by the City of Dearborn, at the Office of the Purchasing CITY OF DEARBORN ADVERTISEMENT FOR NATURAL GAS PROVIDER TO THE CITY OF DEARBORN, MICHIGAN Sealed bids will be received by the City of Dearborn, at the Office of the Purchasing Agent, 2951 Greenfield, Dearborn,

More information

WASTE WATER TREATMENT SYSTEM (OPERATING MANUALS )

WASTE WATER TREATMENT SYSTEM (OPERATING MANUALS ) Page 1 of 76 1.0 PURPOSE The purpose of the Wastewater Treatment System is to remove contaminates from plant wastewater so that it may be sent to the Final Plant Effluent Tank and eventually discharged

More information

REQUEST FOR PROPOSALS (RFP) - Construction Management Services. Germantown School District Office

REQUEST FOR PROPOSALS (RFP) - Construction Management Services. Germantown School District Office REQUEST FOR PROPOSALS (RFP) - Construction Management Services From: Germantown School District Project: Germantown School District Addition & Renovations to Rockfield Elementary School N132 W18473 Rockfield

More information

Flue Gas Desulfurization

Flue Gas Desulfurization Over 100 Years of Process and Mechanical Reliability Flue Gas Desulfurization Cleaner Answers to Your FGD System PEOPLE, PROCESS, PRODUCTS, PERFORMANCE GUARANTEED Agitation & Oxidation Limestone Slurry,

More information

Schedule of Prices. Project Name Contract No. Contract Number

Schedule of Prices. Project Name Contract No. Contract Number Schedule of Prices Project Name Contract No. Contract Number C3-LS-BP-Issue 2 SP Page 1 Printed 1 March 2011 >: 1. When preparing the schedule

More information

EPA 821-R-09-008. Steam Electric Power Generating Point Source Category: Final Detailed Study Report

EPA 821-R-09-008. Steam Electric Power Generating Point Source Category: Final Detailed Study Report EPA 821-R-09-008 Steam Electric Power Generating Point Source Category: Final Detailed Study Report October 2009 This page intentionally left blank. Contents CONTENTS ii Page EXECUTIVE SUMMARY... xii 1.

More information

Construction Management Standards of Practice

Construction Management Standards of Practice Construction Management Standards of Practice 2010 Edition Advancing Professional Construction/ Program Management Worldwide. 7926 Jones Branch Drive, Suite 800 McLean, VA 22102-3303 USA 703.356.2622 703.356.6388

More information

POTW PHOSPHORUS REMOVAL PROCESSES

POTW PHOSPHORUS REMOVAL PROCESSES POTW PHOSPHORUS REMOVAL PROCESSES Ohio Lake Erie Phosphorus Task Force - December 20, 2007 ROBERT M. BONNETT, PE Northeast Ohio Regional Sewer District OUTLINE SOURCES AND FORMS IN WASTEWATER TYPICAL POTW

More information

ORDINANCE NO.------- THE PEOPLE OF THE CITY OF LOS ANGELES DO ORDAIN AS FOLLOWS:

ORDINANCE NO.------- THE PEOPLE OF THE CITY OF LOS ANGELES DO ORDAIN AS FOLLOWS: ORDINANCE NO.------- An ordinance authorizing the award of one design-build contract for the decommissioning, disablement, demolition and removal of Scattergood Generating Station Unit 3 pursuant to a

More information

Jeffery J. Williams Emerson Process Management Power & Water Solutions 200 Beta Drive Pittsburgh, PA. 15238

Jeffery J. Williams Emerson Process Management Power & Water Solutions 200 Beta Drive Pittsburgh, PA. 15238 Author: Jeffery J. Williams Power & Water Solutions 200 Beta Drive Pittsburgh, PA. 15238 Keywords: Abstract: Efficiency, Enterprise Automation, Expert Systems, Modeling, Neural Networks, Optimization,

More information

REMOVAL OF PHOSPHATE FROM WASTEWATER USING LOW-COST ADSORBENTS

REMOVAL OF PHOSPHATE FROM WASTEWATER USING LOW-COST ADSORBENTS International Journal of Engineering Inventions ISSN: 2278-7461, www.ijeijournal.com Volume 1, Issue 7 (October2012) PP: 44-50 REMOVAL OF PHOSPHATE FROM WASTEWATER USING LOW-COST ADSORBENTS Dr. C.R.Ramakrishnaiah

More information

Auditing Capital Projects and Project Controls. March 2013

Auditing Capital Projects and Project Controls. March 2013 Auditing Capital Projects and Project Controls March 2013 Internal Audit Perspective Oversight Insight Foresight Is the process operating as planned? Are controls, resources, and performance measures adequate

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS The Board of Supervisors of Tazewell County, Virginia is soliciting proposals, pursuant to Section 56-575.4 of the Code of Virginia, from private entities to design and build an onsite

More information

Metal Ion + EDTA Metal EDTA Complex

Metal Ion + EDTA Metal EDTA Complex Simplified Removal of Chelated Metals Sultan I. Amer, AQUACHEM INC. Metal Finishing, April 2004, Vol. 102 No. 4 Chelating agents are used in large quantities in industrial applications involving dissolved

More information

Development of Advanced Wastewater Treatment and Reclamation System

Development of Advanced Wastewater Treatment and Reclamation System 14 Development of Advanced Wastewater Treatment and Reclamation System TAKESHI TERAZAKI *1 HOZUMI OTOZAI *2 KOSUKE SHIGIISHI *2 HIDEO SUZUKI *3 HIROSHI NAKASHOJI *4 HIROYUKI KAWAMOTO *5 Recycling and the

More information

CWD BALDWIN PLANT NEW RESIDUALS HANDLING SYSTEM

CWD BALDWIN PLANT NEW RESIDUALS HANDLING SYSTEM CWD BALDWIN PLANT NEW RESIDUALS HANDLING SYSTEM OTCO Water Workshop March, 2011 Frank Woyma Plant Manager Nick Pizzi Vice-President EE&T ENVIRONMENTAL ENGINEERING & TECHNOLOGY, INC. Objectives Review the

More information

IDENTIFYING YOUR WASTE

IDENTIFYING YOUR WASTE United States Environmental Protection Agency EPA530-F-97-029 September 1997 http://www.epa.gov Solid Waste and Emergency Response IDENTIFYING YOUR WASTE THE STARTING POINT This brochure explains the methodology

More information

Document Commentary. AIA Document C191 2009, Standard Form Multi-Party Agreement for Integrated Project Delivery

Document Commentary. AIA Document C191 2009, Standard Form Multi-Party Agreement for Integrated Project Delivery Document AIA Document C191 2009, Standard Form Multi-Party Agreement for Integrated Project Delivery INTRODUCTION Current practice in the construction industry promotes inefficiency when the key project

More information

Experts Review of Aerobic Treatment Unit Operation and Maintenance. Bruce Lesikar Texas AgriLife Extension Service

Experts Review of Aerobic Treatment Unit Operation and Maintenance. Bruce Lesikar Texas AgriLife Extension Service Experts Review of Aerobic Treatment Unit Operation and Maintenance Bruce Lesikar Texas AgriLife Extension Service Overview Overview of Aerobic Treatment Units Installing for accessibility to system components

More information

Contract No: Disclaimer:

Contract No: Disclaimer: Contract No: This document was prepared in conjunction with work accomplished under Contract No. DE-AC09-09SR22505 with the U.S. Department of Energy (DOE) National Nuclear Security Administration (NA).

More information

Document Comparison. AIA Documents A134 2009 and A131CMc 2003

Document Comparison. AIA Documents A134 2009 and A131CMc 2003 Document Comparison AIA Documents A134 2009 and A131CMc 2003 AIA Document A134 2009 is in the right-hand column. Corresponding sections of AIA Document A131 CMc 2003 are in the left-hand column. Sections

More information

Total Water & Wastewater Management for Shale Gas Production. Treatment and Operation Solutions

Total Water & Wastewater Management for Shale Gas Production. Treatment and Operation Solutions Total Water & Wastewater Management for Shale Gas Production Treatment and Operation Solutions Impact of Water and Wastewater from Shale Gas Fracturing Operations As the number of shale gas fracturing

More information

Technical Support Services Accelerated Learning Through the Visual Presentation of Technical Information

Technical Support Services Accelerated Learning Through the Visual Presentation of Technical Information TSS Module 11 Waste Neutralization pdf documents Text in pdf documents may appear fuzzy or blocky due to file compression. To change the appearence in Acrobat TM Reader TM 3.X, go to the menu item: File

More information

I BAU HAMBURG Dry Product Handling

I BAU HAMBURG Dry Product Handling IBAU HAMBURG Your efficient partner for modern and effective bulk material handling I BAU HAMBURG PLANT DESIGN - ENGINEERING - EPC-CONTRACTING CEMENT - THERMAL POWER - MINERALS Central Cone Silos Single

More information

THE MC CLARIFLOW UPFLOW SOLIDS CONTACT CLARIFIER

THE MC CLARIFLOW UPFLOW SOLIDS CONTACT CLARIFIER The Ultimate UPFLOW SOLIDS CONTACT CLARIFIER by Arthur C. Schlicht November 1999 Walker Process Equipment Division of McNish Corporation 840 North Russell Avenue Aurora, IL 60506-2853 PHONE: (630) 892-7921

More information

Roadmap Performance Target Best technology Capability

Roadmap Performance Target Best technology Capability Sulfur Dioxide Control Technologies In Electric Power Plants CCTR Basic Facts File #5 Brian H. Bowen, Marty W. Irwin The Energy Center at Discovery Park Purdue University CCTR, Potter Center, 500 Central

More information

RAILROAD COMMISSION OF TEXAS APPENDIX C LIST OF E&P WASTES: EXEMPT AND NONEXEMPT

RAILROAD COMMISSION OF TEXAS APPENDIX C LIST OF E&P WASTES: EXEMPT AND NONEXEMPT RAILROAD COMMISSION OF TEXAS APPENDIX C LIST OF E&P WASTES: EXEMPT AND NONEXEMPT WASTE MINIMIZATION IN THE OIL FIELD - APPENDIX C NOTES RAILROAD COMMISSION OF TEXAS LIST OF E&P WASTES: EXEMPT AND NON EXEMPT

More information

Within the context of this policy, the following definitions apply:

Within the context of this policy, the following definitions apply: BOARD OF EDUCATION POLICY 4050 PROCUREMENT OF GOODS AND/OR SERVICES Effective: July 1, 2011 I. Policy Statement The Board of Education of Howard County expects that the funds provided to them for all goods

More information

ICAO Procurement Process Briefing

ICAO Procurement Process Briefing ICAO Procurement Process Briefing The following is a briefing in an effort to provide the reader with an insight into the ICAO Technical Co-operation Bureau s Procurement Process and role in relation to

More information

PRINCIPLES OF FLUE GAS WATER RECOVERY SYSTEM

PRINCIPLES OF FLUE GAS WATER RECOVERY SYSTEM PRINCIPLES OF FLUE GAS WATER RECOVERY SYSTEM John H. Copen - SIEMENS Power Generation, Inc. Terrence B. Sullivan - SIEMENS Power Generation, Inc. Bruce C. Folkedahl - Energy & Environmental Research Center

More information

PRE-QUALIFICATION ANNOUNCEMENT

PRE-QUALIFICATION ANNOUNCEMENT Warsaw March 9, 2011 PRE-QUALIFICATION ANNOUNCEMENT The contracting authority 00-526 Warsaw, ul. Krucza 24/26, Poland Website: www.elektrowniapolnoc.pl Contact person: Mr. Marek Obuchowicz E-mail: info@elektrowniapolnoc.pl

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 903 CONSTRUCTION QC/QA PROGRAM

San Antonio Water System Standard Specifications for Construction ITEM NO. 903 CONSTRUCTION QC/QA PROGRAM ITEM NO. 903 CONSTRUCTION QC/QA PROGRAM 903.1 DESCRIPTION: This item shall govern the preparation and implementation of the Contractor s Construction Quality Control/Quality Assurance (QC/QA) Program for

More information

SPANISH POWER PLANTS DEI Compliance

SPANISH POWER PLANTS DEI Compliance Work Order Synthesis ENGINEERING AND Sheet 1 of 11 PROJECT SPANISH POWER PLANTS DEI Compliance Security Index Internal Use / P TITLE CLIENT ENEL GLOBAL GENERATION JOB no. Document no. CLIENT SUBMITTAL

More information

Outlook on Integrated Gasification Combined Cycle (IGCC) Technology

Outlook on Integrated Gasification Combined Cycle (IGCC) Technology The IGCC Process: From Coal To Clean Electric Power Outlook on Integrated Gasification Combined Cycle (IGCC) Technology Testimony of Edward Lowe Gas Turbine-Combined Cycle Product Line Manager General

More information

Cost Estimating Procedure. Table of Contents

Cost Estimating Procedure. Table of Contents Cost Estimating Procedure Table of Contents 1.0 PURPOSE... 1 2.0 SCOPE... 1 3.0 REFERENCES... 1 4.0 DESCRIPTION... 1 5.0 PROCEDURE DETAILS... 2 5.1 Developing a Detailed Cost Estimate... 2 5.2 Basis of

More information

AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER-AT-RISK

AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER-AT-RISK AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER-AT-RISK MD ANDERSON AGREEMENT No. This Agreement is made as of, 20xx (the Effective Date ), by and between The Owner: M D Anderson Cancer Center c/o Sourcing

More information

INDUSTRIAL BOILER MACT FACTSHEET

INDUSTRIAL BOILER MACT FACTSHEET INDUSTRIAL BOILER MACT FACTSHEET The National Emission Standards for Hazardous Air Pollutants (NESHAP) for Industrial/Commercial/Institutional Boilers and Process Heaters (40 CFR Part 63, Subpart DDDDD),

More information

REQUEST FOR PROPOSAL. for CONSTRUCTION MANAGEMENT SERVICES. for the ENCINA WASTEWATER AUTHORITY FY 2015 MAJOR PLANT REHABILITATION PROJECT

REQUEST FOR PROPOSAL. for CONSTRUCTION MANAGEMENT SERVICES. for the ENCINA WASTEWATER AUTHORITY FY 2015 MAJOR PLANT REHABILITATION PROJECT REQUEST FOR PROPOSAL for CONSTRUCTION MANAGEMENT SERVICES for the ENCINA WASTEWATER AUTHORITY FY 2015 MAJOR PLANT REHABILITATION PROJECT Ref: Admin.15 12265c September 23, 2015 Proposals Due November 2,

More information

DEMO Version. Owner and Contractor OCNMP103

DEMO Version. Owner and Contractor OCNMP103 Page 1 of 12 AGREEMENT made as of the in the year of (In words, indicate day, month and year) day of BETWEEN the Owner: (Name, address and other information) DEMO Version and the Contractor: (Name, address

More information

Phoenix Process Engineering, Inc. Project Experience Helping Clients Achieve MACT Compliance

Phoenix Process Engineering, Inc. Project Experience Helping Clients Achieve MACT Compliance Phoenix Process Engineering, Inc. Project Experience Helping Clients Achieve MACT Compliance The Boiler MACT, 40 CFR 63, Subpart DDDDD, was vacated in 2007 by the U.S Court of Appeals and the 2004 rule

More information

ETV Joint Verification Statement

ETV Joint Verification Statement THE ENVIRONMENTAL TECHNOLOGY VERIFICATION PROGRAM U.S. Environmental Protection Agency ETV Joint Verification Statement TECHNOLOGY TYPE: Continuous Emission Monitor APPLICATION: TECHNOLOGY NAME: COMPANY:

More information

Edmonton Waste Management Centre Contract Review November 2, 2015

Edmonton Waste Management Centre Contract Review November 2, 2015 Edmonton Waste Management Centre Contract Review November 2, 2015 The Office of the City Auditor conducted this project in accordance with the International Standards for the Professional Practice of Internal

More information

Special thanks to Ohio DOT. Utility Relocation Costs

Special thanks to Ohio DOT. Utility Relocation Costs Special thanks to Ohio DOT Utility Relocation Costs Order of Events DOT requests Utility to relocate due to Highway project Utility engages PEF to provide preliminary Design and Construction Estimate Using

More information

The Consultant is a person or an entity engaged by the Client or the Architect to provide services supplementary to those provided by the Architect.

The Consultant is a person or an entity engaged by the Client or the Architect to provide services supplementary to those provided by the Architect. Definitions Additional Services Additional Services are those professional services which are not contemplated at the time of execution of the contract and therefore cannot be identified then as being

More information

PROCUREMENT PRACTICES AT PUBLIC HOUSING AGENCIES

PROCUREMENT PRACTICES AT PUBLIC HOUSING AGENCIES PROCUREMENT PRACTICES AT PUBLIC HOUSING AGENCIES Table of Contents Procurement Regulations and Agency 3 Procurement Policies and Procedures 3 Roles and Responsibilities 4 Board of Commissioners 4 Sample

More information

Phosphorus Removal in Wastewater Treatment

Phosphorus Removal in Wastewater Treatment RESEARCH & DEVELOPMENT REPORT NO. Phosphorus Removal in Wastewater Treatment (Final Report) Research and Development Section Electrical & Mechanical Projects Division Nov 2013 Final Report endorsed by

More information

The Commonwealth of Massachusetts AUDITOR OF THE COMMONWEALTH

The Commonwealth of Massachusetts AUDITOR OF THE COMMONWEALTH The Commonwealth of Massachusetts AUDITOR OF THE COMMONWEALTH ONE ASHBURTON PLACE, ROOM 1819 BOSTON, MASSACHUSETTS 02108 A. JOSEPH DeNUCCI AUDITOR TEL. (617) 727-6200 NO. 2008-1461-3A INDEPENDENT STATE

More information

GUIDELINE. Professional Engineers Providing Project Management Services. Published by Association of Professional Engineers of Ontario

GUIDELINE. Professional Engineers Providing Project Management Services. Published by Association of Professional Engineers of Ontario GUIDELINE Professional Engineers Providing Project Management Services 1991 Published by Association of Professional Engineers of Ontario CONTENTS FOREWORD...3 1.0 GENERAL INFORMATION AND DEFINITIONS...3

More information

A NOVEL ION-EXCHANGE/ELECTROCHEMICAL TECHNOLOGY FOR THE TREATMENT OF AMMONIA IN WASTEWATER

A NOVEL ION-EXCHANGE/ELECTROCHEMICAL TECHNOLOGY FOR THE TREATMENT OF AMMONIA IN WASTEWATER A NOVEL ION-EXCHANGE/ELECTROCHEMICAL TECHNOLOGY FOR THE TREATMENT OF AMMONIA IN WASTEWATER ABSTRACT Leonard P. Seed, M.Sc., P.Eng., Enpar Technologies Inc. * Daren D. Yetman, A.Sc.T., Enpar Technologies

More information

William E. Dunn Water Reclamation Facility. Facility Overview & Information

William E. Dunn Water Reclamation Facility. Facility Overview & Information William E. Dunn Water Reclamation Facility Facility Overview & Information General Area Served: Plant History Facility Highlights Northern Pinellas County St. Joseph Sound to East Lake Road (E/W) Tampa

More information

PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION

PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION PMP SAMPLE QUESTIONS http://www.tutorialspoint.com/pmp-exams/pmp_sample_questions.htm Copyright tutorialspoint.com BASED ON PMBOK 5TH EDITION Here are 200 more objective type sample questions and their

More information

OPTIMIZING PHOSPHORUS REMOVAL BY CHEMICAL ADDITION AT ORADEA WASTEWATER TREATMENT PLANT

OPTIMIZING PHOSPHORUS REMOVAL BY CHEMICAL ADDITION AT ORADEA WASTEWATER TREATMENT PLANT JAES_1(14)_1_2011 GLIGOR E., pp.67-72 SECTION Civil Engineering and Installations OPTIMIZING PHOSPHORUS REMOVAL BY CHEMICAL ADDITION AT ORADEA WASTEWATER TREATMENT PLANT GLIGOR Emil 1, IONESCU Gheorghe-Constantin

More information

Chemistry at Work. How Chemistry is used in the Water Service

Chemistry at Work. How Chemistry is used in the Water Service Chemistry at Work How Chemistry is used in the Water Service WATER TREATMENT Everyday, more than 100 water treatment works in Northern Ireland put approximately 680 million litres of water into the supply

More information

BLUEPRINT PROJECT INSURANCE: OWNER S PROFESSIONAL LIABILITY EXPOSURES AND SOLUTIONS CONSTRUCTION PRACTICE

BLUEPRINT PROJECT INSURANCE: OWNER S PROFESSIONAL LIABILITY EXPOSURES AND SOLUTIONS CONSTRUCTION PRACTICE CONSTRUCTION PRACTICE BLUEPRINT October 2014 www.willis.com PROJECT INSURANCE: OWNER S PROFESSIONAL LIABILITY EXPOSURES AND SOLUTIONS Owners of construction projects face many risk management challenges

More information