1 Needham Heights Neighborhood Association Add-A-Lane Contract V along a Section of I-95 includes 6 Bridges Project File No June 9,
2 Agenda Project Update Overview Bid and Contract Award Schedule Preliminary Construction Schedule 2
3 Bid and Award Schedule July 1, 2014 Contractors Bid Due Late August/Early September Contractor NTP October 2014 Construction Start January 2019 Construction Completion 3
4 Preliminary Construction Schedule Notice-to-Proceed to Contractor: Aug/Sep 2014 Estimated Completion Dates of Construction Stages: Stage 1: October 2015 Stage 2: September 2017 Stage 3: May 2018 Stage 4: September 2018 Stage 5: December 2018 Partial Opening of Kendrick St. Interchange: July 2016 Substantial Completion: December
5 Existing Lane Configuration 5
6 Future Lane Configuration 4 Travel Lanes in each direction south of Highland Ave. 5 Travel Lanes in each direction between Highland Ave. and Rte. 9 New Kendrick Street Interchange Collector-Distributor Roadways between Kendrick St. and Highland Ave. Reconfigured Rte. 9 Interchange 6
7 Stage 1 Construction: Sept Oct
8 Stage 2 Construction: Oct Sept
9 Stage 3 Construction: Sept May
10 Stage 4 Construction: May 2018 Sept
11 Stage 5 Construction: Sept Dec
12 Questions 12
13 Project Components Project Components South of Kendrick Street New Kendrick Street Interchange Kendrick Street to Highland Avenue Highland Avenue to Route 9 Route 9 Interchange Noise Barrier North of Route 9 Mitigation Parcel at Great Plain Avenue 13
14 Project Limits Project Limits: North of MBTA RR Bridge Project Limits: North of Rte. 9 14
15 Project Limits Off-Site Mitigation Site at Great Plain Avenue 15
16 Project Limits Noise Barrier Along I-95 SB north of Route 9 16
17 Proposed Roadway Improvements Widen roadway into median to add 1 travel lane in each direction Restore breakdown lanes and provide widened shoulder at median New Kendrick St. interchange New collector/distributor roads, Kendrick St. Highland Ave. Auxiliary lanes in each direction between Highland Ave. & Rte. 9 Reconfigure Rte. 9 interchange 17
18 Bridges and Walls Bridges 3 Replacement Bridges 1 Widening 1 Removal RR Bridge 1 New Bridge Retaining Walls 16 Locations Total Length 9,986 LF Noise Barriers 7 Locations Total Length 10,424 LF 18
19 South Project Limit to Kendrick Street 19
20 South Project Limit to Kendrick Street 20
21 South Project Limit to Kendrick Street 21
22 New Kendrick Street Interchange 22
23 Existing Kendrick Street Bridge 23
24 Proposed Kendrick Street Bridge Looking East 2 Span Similar to Existing Constructed in 2 Stages 24
25 New Ramp K-1 over Ramp K-2 Bridge 25
26 New Ramp K-1 over Ramp K-2 Bridge 26
27 New C/D Roads Between Kendrick Street and Highland Avenue Collector/ Distributor Road Collector/ Distributor Road 27
28 Existing Highland Avenue Interchange 28
29 Proposed Highland Avenue Interchange 29
30 Proposed Highland Avenue Bridge 30
31 MBTA Railroad Bridge & Retaining Wall at 32 Fremont Street Remove Existing Bridge New Retaining Wall P 31
32 New Auxiliary Lanes Between Highland Avenue and Route 9 Sudbury Aqueduct 32
33 New Auxiliary Lanes Between Highland Avenue and Route 9 33
34 Central Avenue Bridges 34
35 Central Avenue Bridges - Modifications 35
36 Route 9 Interchange 36
37 Reconfiguration of the Route 9 Interchange 37
38 Reconfiguration of the Route 9 Interchange Relocate SB offramp on improved alignment Remove I-95 SB loop ramp Relocate NB off-ramp on improved alignment Remove I-95 NB loop ramp 38
39 Proposed Route 9 Bridge 39
40 Incentives/Disincentives Milestone #2 Substantial Completion $30,000/day $4,020,000 maximum Milestone #3 Completion of Br. No. N and Ramps K-3 and K-4 $11,000/day $407,000 maximum 40
DISTRICT 3 TRAFFIC MANAGEMENT PLAN CHECKLIST
State of California Business, Transportation and Housing Agency DISTRICT 3 TRAFFIC MANAGEMENT PLAN CHECKLIST District / EA: District 3/ EA 03-3E380 Date Prepared: 1/10/2013 Prepared By: Robert Himes Stage
More informationThe Need for Traffic Incident Management
The Need for Traffic Incident Management With traffic incidents responsible for approximately 50-60% of the congestion delays motorists encounter on the nation s roadways every day, increased roadway capacity
More informationWelcome! Purpose of Tonight s Meeting. Informational Open House to discuss two City projects: Goal is to LISTEN TO YOU
Purpose of Tonight s Meeting Informational Open House to discuss two City projects: Fairchild Street Subway Phase I Engineering: Immediate need to replace subway Bowman Avenue Feasibility Study Future
More informationMaryland Invests $845 Million in New Highway and Bridge Projects
Maryland Invests $845 Million in New Highway and Bridge Projects Completing Widening of MD 404 Talbot And Caroline Counties Top Regional Priority Queen Anne s, Talbot, and Caroline Counties Widening MD
More information3 Tappan Zee Bridge Rehabilitation Options
3 Tappan Zee Bridge Rehabilitation Options 3.1 Introduction This chapter describes possible options that rehabilitate and enhance the existing Tappan Zee Bridge. Four Rehabilitation Options have been developed:
More information3.1 Historical Considerations
3. Recommended Scope of Bridge improvements 3.1 Historical Considerations In the fall of 2000, an outside consultant, Fraser Design, suggested that the existing 4 th St. Bridge is potentially eligible
More informationNashville Area MPO Regional Freight Study fast action projects
Project #1 Beechcroft road (sr 247) at csx crossing Motor carrier survey location Maury County (Spring Hill, Tn) / City of Spring Hill Current at-grade railway crossing causes traffic delays as a result
More informationSCOTTSDALE TRANSPORTATION COMMISSION REPORT
SCOTTSDALE TRANSPORTATION COMMISSION REPORT To: Transportation Commission From: Paul Basha, Transportation Director Meeting Date: September 19, 2013 Subject: SR-101 Pima Freeway Improvements ITEM IN BRIEF
More informationI-66 Pavement Rehabilitation
I-66 Pavement Rehabilitation Fall Asphalt Conference Richmond, VA David Shiells, P.E. Virginia Department of Transportation David White Superior Paving Corporation October 2, 2012 Project Location 2 Goal
More informationSTATE HIGHWAY 360. PUBLIC HEARING Thursday, October 17, 2013 FROM: E. SUBLETT ROAD/ W. CAMP WISDOM ROAD TO: US 287
STATE HIGHWAY 360 PUBLIC HEARING Thursday, October 17, 2013 FROM: E. SUBLETT ROAD/ W. CAMP WISDOM ROAD TO: US 287 TIMBERVIEW HIGH SCHOOL, ARLINGTON, TEXAS Project Vicinity Proposed Project Length: Approximately
More informationTransportation Management Plan Template
DATE: TO: FROM: SUBJECT: Date Name Position Transportation Service Center Name Position Transportation Service Center Transportation Management Plan Job Number(s) Control Section(s) Route Details County
More informationLight Rail Transit in Phoenix
4. Presentation and Discussion: Phoenix Light Rail Implementation Wulf Grote Planning and Development Director, Phoenix Valley Metro Light Rail Transit in Phoenix Broadway Citizen s Task Force February
More informationSCHOOL OF ARCHITECTURE & COMMUNITY DESIGN COLLEGE OF THE ARTS UNIVERSITY OF SOUTH FLORIDA
SCHOOL OF ARCHITECTURE & COMMUNITY DESIGN COLLEGE OF THE ARTS UNIVERSITY OF SOUTH FLORIDA PROJECT OVERVIEW OVERVIEW The FCCD+R, in coordination with the FDOT District 7, are to facilitate numerous meetings
More informationAPPLICATION LAFAYETTE METROPOLITAN PLANNING ORGANIZATION (MPO) SURFACE TRANSPORTATION PROGRAM (STP) FUNDS TRANSPORTATION IMPROVEMENT PROGRAM (TIP)
APPLICATION LAFAYETTE METROPOLITAN PLANNING ORGANIZATION (MPO) SURFACE TRANSPORTATION PROGRAM (STP) FUNDS TRANSPORTATION IMPROVEMENT PROGRAM (TIP) To be considered for STP funding, a proposed project must
More informationNON-TRADITIONAL UTILITY COORDINATION on KYTC Projects. KYTC Partnering Conference September 9, 2014
NON-TRADITIONAL UTILITY COORDINATION on KYTC Projects KYTC Partnering Conference September 9, 2014 Non-Traditional Utility Agenda Traditional Approach Recognizing a Need for a New Tool in the Toolbox Non-Traditional
More informationTRANSPORTATION MANAGEMENT PLAN
TRANSPORTATION MANAGEMENT PLAN EMPIRE/BURBANK AND RAILROAD TRACKS PROJECT 07-LA-05 PM 29.4/31.6 State of California Department of Transportation District 7 Contract Number: EA 1218w1 Prepared by: Daisy
More information7.2 Warrants and Planning Considerations
Chapter 7 Interchanges 7.1 Introduction As discussed in Chapter 6, it is important that designers consider the needs and activities of the pedestrians, cyclists, and motorists to comprehensively plan for
More informationP. ALTERNATE TECHNICAL CONCEPTS FOR CONSTRUCTION, STAGING AND TRAFFIC CONTROL
P. ALTERNATE TECHNICAL CONCEPTS FOR CONSTRUCTION, STAGING AND TRAFFIC CONTROL 1.0 Description. 1.1 This specification allows bidders the opportunity to include in their overall bid proposal, pricing for
More informationPROJECT COST ESTIMATE ASSUMPTIONS AND EXCLUSIONS
C PROJECT ESTIMATE ASSUMPTIONS AND EXCLUSIONS In support of the alternatives development process, preliminary cost estimates were prepared for each of the three Candidate Build Alternatives. The cost estimates
More informationI-25/ARAPAHOE INTERCHANGE RECONSTRUCTION PROJECT
MANDATORY PRE-BID SIGN IN CDOT Carrie DeJiacomo, Program Engineer John Hall, Resident Engineer Telecia McCline, Project Manager Tammy Maurer, Assistant Project Manager David Evans/Hartwig Design Consultant
More informationRESOLUTIONS FOR APPROVAL OF AMENDMENTS TO THE 2015-2018 TRANSPORTATION IMPROVEMENT PROGRAM (TIP) AND 2040 REGIONAL TRANSPORTATION PLAN (RTP)
TPC Agenda Item 6A Mailout - 10/16/15 RESOLUTIONS FOR APPROVAL OF AMENDMENTS TO THE 2015-2018 TRANSPORTATION IMPROVEMENT PROGRAM (TIP) AND 2040 REGIONAL TRANSPORTATION PLAN (RTP) OCTOBER AMENDMENTS Amendment
More information8+ %!0"% 8+1!%"'$%,$"$
8+ 8+ %!0"% The next step in developing recommendations for improvements to Grand Avenue was to identify, develop and evaluate alternatives to address the issues and needs identified in the previous chapter.
More informationPRIORITIZATION PROCESSES
PROJECT SELECTION & PRIORITIZATION PROCESSES STIP Workshop Presented by: Bill Lawrence April 2011 Purpose and Review Overview of Project Selection Process Review Various Prioritization Processes Tk Take
More informationSTANDARD ELEMENTS OF A CONSTRUCTION MANAGEMENT PLAN
STANDARD ELEMENTS OF A CONSTRUCTION MANAGEMENT PLAN JULY 2015 Standard Elements of a Construction Management Plan (CMP) This guidance tool was developed through partnership between the Department of Planning
More informationBruce Highway (Cooroy to Curra) Section A (Cooroy southern interchange to Sankeys Road)
Bruce Highway (Cooroy to Curra) Section A (Cooroy southern interchange to Sankeys Road) Industry Briefing - 13 February 2013 Bruce Highway Upgrade (Cooroy to Curra) The Bruce Highway Upgrade (Cooroy to
More informationBrookdale Site. CB6 Update April 1, 2015
Brookdale Site CB6 Update April 1, 2015 Summary Timeline / Process How does DSNY operate now? Garage project and frequently asked questions Project facts Impact to emergency vehicle access Traffic congestion
More informationEXHIBIT A Accessible Truck Routes Map
EXHIBIT A Accessible Truck Routes Map ASHEVILLE, NORTH CAROLINA ROUTE: A ROUTE: B ROUTE: C ROUTE: D ROUTE: E EXHIBIT A EXHIBIT B Craven Street Improvements Map ASHEVILLE, NORTH CAROLINA EXHIBIT B EXHIBIT
More informationRESOLUTION NO. 1539 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF BONNEY LAKE, PIERCE COUNTY, WASHINGTON, APPROVING THE 192 ND CORRIDOR STUDY AND DIRECTING THE MAYOR TO PROCEED WITH PARTIAL DESIGN AND
More informationI-94 Rehabilitation Project
INTERSTATE 94 I-94 Rehabilitation Project FHWA-MI-EIS-01-01-F December 2004 Final Environmental Impact Statement and Section 4(f) Evaluation Executive Summary PREFACE The National Environmental Policy
More informationRoadway Cost Per Centerline Mile Revised June 2014
Rural Arterial From LRE MOT * Mobilization * Subtotal Total PE Design (15%) CEI (15%) Total Project ** New (2-Lane Roadway) with 5' Paved Shoulders $3,351,896 $335,190 $368,709 $4,055,794 $1,013,949 $5,069,743
More informationFHWA Minnesota Division Guidance for the Preparation of a FHWA INTERSTATE ACCESS REQUEST
FHWA Minnesota Division Guidance for the Preparation of a FHWA INTERSTATE ACCESS REQUEST August 2003 Background: The Federal Highway Administration (FHWA) has retained all approval rights to the control
More information5.14 Floodplains and Drainage/Hydrology
I-70 East Final EIS 5.14 Floodplains and Drainage/Hydrology 5.14 Floodplains and Drainage/Hydrology This section discusses floodplain and drainage/hydrology resources and explains why they are important
More informationThe Corporation of the TOWN OF MILTON
The Corporation of the TOWN OF MILTON Report to: From: Mayor G. A. Krantz & Members of Council M. Paul Cripps, P. Eng., Director, Engineering Services Date: November 11, 2013 Report No. ENG-039-13 Subject:
More informationFHWA Colorado Division Control of Access to the Interstate and its Right-of-Way February 2005
FHWA Colorado Division Control of Access to the Interstate and its Right-of-Way February 2005 Background: It is in the national interest to maintain the Interstate System to provide the highest level of
More informationComment #1: Provide an interchange at Route 7 and Farm Market Road/White Gate Road. This was studied in the late 1990 s.
Proposed Truck Climbing Lane Route 7 Westbound Between West Market Street and Route 9 UPC# 58599, Project # 6007-053-133, P101 Date of Meeting: August 24, 2010 Time: 6:00PM to 8:00PM Location: Rust Library
More informationMichael B. Hancock Mayor. October 31, 2014
Michael B. Hancock Mayor City and County of Denver OFFICE OF THE MAYOR CITY AND COUNTY BUILDING DENVER, CO 80202-5390 TELEPHONE: (720) 865-9090 FAX: (720) 865-8787 TTY/ TTD: (720) 865-9010 October 31,
More informationAppendix J Transportation Management Plan Report. Traffic Operational Analysis Report
Appendix J Transportation Management Plan Report Traffic Operational Analysis Report Transportation Management Plan Report VIRGINIA AVENUE TUNNEL RECONSTRUCTION PROJECT WASHINGTON, DC PRELIMINARY TRANSPORTATION
More informationAppendix A Alternative Contracting General Engineering Consultant RFP. Appendix A
Appendix A 1 1.0 Requirements and Minimum Qualifications This section outlines requirements and minimum qualifications for the GEC. It is anticipated that the GEC will be used to support and supplement
More informationMission Creek Flood Control & Restoration Project. City of Fremont, Alameda County
Mission Creek Flood Control & Restoration Project City of Fremont, Alameda County Agenda Background Why are proposed improvements necessary? Proposed project components Challenges Construction schedule/phasing
More informationREPORTS & PRESENTATIONS AGENDA ITEM #III-3 CORTEZ BRIDGE PROJECT DEVELOPMENT AND ENVIRONMENT (PD&E) STUDY
NOTES REPORTS & PRESENTATIONS AGENDA ITEM #III-3 CORTEZ BRIDGE PROJECT DEVELOPMENT AND ENVIRONMENT (PD&E) STUDY Presenter: Summary: Tony Sherrad, FDOT Project Manager The Cortez Bridge in Manatee County,
More informationIllinois Tollway and Chicago Department of Transportation Construction Networking Event. March 13, 2015
Illinois Tollway and Chicago Department of Transportation Construction Networking Event March 13, 2015 Today s Agenda Welcome Illinois Tollway projects Chicago Department of Transportation (CDOT) projects
More informationRevere Beach Transit-Oriented Development Parcels Revere, Massachusetts. Design and Development Guidelines. Part Two.
Revere Beach Transit-Oriented Development Parcels Revere, Massachusetts Design and Development Guidelines Request for Qualifications and Expressions of Interest with Preliminary Development Plans Part
More informationQUALITY ASSURANCE. and QUALITY CONTROL PROCESS GUIDE. for PROJECT MANAGERS
QUALITY ASSURANCE and QUALITY CONTROL PROCESS GUIDE for PROJECT MANAGERS MDOT Trunkline Projects January 2005 TABLE OF CONTENTS Discussion.. 2 Scope Verification Meeting..... 3 Overview 3 Procedure...
More informationDraft Transportation Management Plan for Via Verdi Repair Project
for Via Verdi Repair Project prepared for City of Richmond This report was prepared by: This report was reviewed by: Ryan McClain, P.E. Fehr & Peers TABLE OF CONTENTS 1.0 INTRODUCTION & PROJECT DESCRIPTION...
More informationINSTITUTIONAL MASTER PLAN NOTIFICATION FORM / PROJECT NOTIFICATION FORM BOSTON UNIVERSITY MEDICAL CENTER
INSTITUTIONAL MASTER PLAN NOTIFICATION FORM / PROJECT NOTIFICATION FORM BOSTON UNIVERSITY MEDICAL CENTER JUNE 7, 2013 SUBMITTED TO: BOSTON REDEVELOPMENT AUTHORITY ONE CITY HALL SQUARE BOSTON, MA 02201
More informationI-25 / Rio Bravo Interchange
I-25 / Rio Bravo Interchange TONIGHT S MEETING SCHEDULE OPEN HOUSE 6:00 PM TO 6:30 PM PRESENTATION BEGINS AT 6:30 PM Q & A FOLLOWING PRESENTATION CN A300280 / PNA300280 I-25 / Rio Bravo Interchange SECOND
More informationBackground and Goals for the Project
City of Asheville, NC REQUEST FOR PROPOSALS Wilma Dykeman Riverway Environmental Analysis, Project Development, and Preliminary Design Submittal Address: Dan Baechtold, AICP City of Asheville Engineering
More informationVDOT Project Advertisements from 4/1/13-6/30/14 (by advertisement)
VDOT Project s from 4/1/13-6/30/14 (by advertisement) Description UPC Project Manager Phone RTE 85 - BRIDGE SYSTEM PRESERVATION (Richmond District-wide) BOYD ST - RECONSTR BETWEEN 2ND & 3RD ST & IMPR DRAINAGE
More informationMEMORANDUM. 4201 E. Arkansas Ave., Room 262, Denver, CO 80222 P 303.757.9204 F 303.757.9656 www.coloradodot.info
4201 E. Arkansas Ave., Room 262 Denver, CO 80222 MEMORANDUM TO: TRANSPORTATION COMMISSION FROM: JOSH LAIPPLY, CHIEF ENGINEER SCOTT RICHRATH, CHIEF FINANCIAL OFFICER DATE: SEPTEMBER 17, 2014 SUBJECT: PROGRAM
More information5 ALTERNATIVE SOLUTIONS AND EVALUATION
Page 23 5 ALTERNATIVE SOLUTIONS AND EVALUATION The process used for the assessment and evaluation of the alternatives follows the procedures of the Municipal Class EA, as described below: Identify a reasonable
More informationI-15 Ontario PCC Rehabilitation Project
I-15 Ontario PCC Rehabilitation Project CPTP Conference April 24, 2009 Jonathan den Hartog / Caltrans E.B. Lee / UC Berkeley David Lim / Caltrans David Thomas / Parsons I-15 Ontario Rehabilitation Project:
More information2017 Budget and Grid Management Charge Initial Stakeholder Meeting
2017 Budget and Grid Management Charge Initial Stakeholder Meeting June 16, 2016 Page 1 Agenda Topic 2017 Budget Process & GMC Rate Outlook Managing Employee Compensation Presenter(s) Ryan Seghesio & April
More informationWilmington to Newark Commuter Rail Improvement Project
Wilmington to Newark Commuter Rail Improvement Project The Delaware Transit Corporation (DTC), a subsidiary of the Delaware Department of Transportation (DelDOT), is undertaking a rail capacity expansion
More information;If jlllr ------------------------~M~E~M~O~T0~0~E~S~IG~N~E~R~S~1~-~3~7_ ~A~P~R~IL~1~9~9~5
;If jlllr ------------------------~M~E~M~O~T0~0~E~S~IG~N~E~R~S~1~-~3~7_ ~A~P~R~IL~1~9~9~5 lizltl'an.s Duties of Project Engineer The Project Engineer bas the primary responsibility of producing a complete,
More informationUS-95 Northwest Corridor Initial Financial Plan
T G YO N N HI O N N WA S NW CORRIDOR ROA D US-95 Northwest Corridor Initial Financial Plan C AV E ENU L E TO KY A April 2009 TABLE OF CONTENTS INTRODUCTION----------------------------------------------------------------------------------
More informationAPPENDIX J TRAFFIC STUDY
APPENDIX J TRAFFIC STUDY May 7, 2014 Ms. Leianne Humble Denise Duffy and Associates, Inc. 947 Cass Street, Suite 5 Monterey, CA 93940 Re: Traffic Study for the Heritage Oaks Memorial Park in San Jose,
More information11 p.m. to. Tuesday, June. will remain open. 14. closed
June 3, 2011 CONTACT: Marcia McAllister T: 703 572 0506 C: 571 730 9117 marcia.mcallister@dullesmetro.com Important Lane Closures June 5 11 Include Northbound Beltway Lanes, Eastbound Dulles Airport Access
More informationSector Design Concepts
Section C Sector Design Concepts C7 Sector 7 Great North Road Underpass 6 6 6 C7. Existing situation Sector 7 refers to the cut and cover section of the project linking the northern end of the deep tunnels
More informationFHWA Initial Financial Plan May 12, 2009
South Access to the Golden Gate Bridge Doyle Drive Project FHWA Major Projects Financial Plan FHWA Initial Financial Plan May 12, 2009 Submitted in Partnership by: Federal Highway Administration San Francisco
More informationCapital Action Plan Status Thru Dec 2015
Freeway Projects: I-5, Pico to Vista Hermosa $113.0 Jun-09 Dec-11 Jun-11 Oct-13 Feb-14 Oct-14 Dec-14 Aug-18 Project C $91.9 Jun-09 Oct-11 Jun-11 Oct-13 May-14 Sep-14 Dec-14 Aug-18 I-5, Vista Hermosa to
More informationAuckland Motorways Network Performance Monitoring
Network Performance Monitoring Anita Lin & Hanford Cheung Page 0 Auckland Motorways Network Performance Monitoring Authors Anita Lin Auckland Motorways (Presenter) Traffic Optimisation Leader BE, ME GIPENZ
More informationWSDOT s Approach to Seismic Retrofit of Highway Structures
WSDOT s Approach to Seismic Retrofit of Highway Structures Role of the Lifeline Route in Reducing Network Risk Lynn Peterson Secretary of Transportation Patrick Morin, PE Capital Program Development &
More informationSCHNEIDER CREEK REMEDIATION CLASS ENVIRONMENTAL ASSESSMENT ADDENDUM
SCHNEIDER CREEK REMEDIATION CLASS ENVIRONMENTAL ASSESSMENT ADDENDUM PUBLIC MEETING FEBRUARY 8 TH, 2012 The City of Kitchener and Grand River Conservation Authority (GRCA) are undertaking an Environmental
More informationConstruction Planning & Scheduling
University of Delaware Department of Civil and Environmental Engineering CIEG 467-013 Construction Planning & Scheduling Bob Muir, PE Construction Planning & Scheduling Necessity for Good Scheduling Time
More informationSAFETEA-LU TECHNICAL CORRECTIONS BILL SUMMARY
SAFETEA-LU TECHNICAL CORRECTIONS BILL SUMMARY Draft 7/2/08 The SAFETEA-LU Technical Corrections Bill (HR 1195) was enacted on June 6, 2008 (P.L. 110-244). The Bill can be found at: http://frwebgate.access.gpo.gov/cgi-bin/getdoc.cgi?dbname=110_cong_bills&docid=f:h1195enr.txt.pdf
More information763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule
763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule Description: This work shall reflect a Contractor s anticipated work plan for constructing the project using a Critical Path Method Project
More informationDulles Corridor Metrorail Project
Dulles Corridor Metrorail Project MONTHLY COST AND SCHEDULE UPDATE FOR PHASE 2 AS OF JULY 31, 2015 SEPTEMBER 2015 Phase 2 Cost Summary July Expenditures $ 19.2 Million Total Expenditures $ 508.7 Million
More informationScope Management Guideline August, 2015
Scope Management Guideline August, 2015 Check the Capital Project Delivery website to ensure this is the current version. Table of Contents Scope Management Overview... 1 Charter... 4 Scope Statement...
More informationPlanning Level Cost Estimation Tool. User s Manual
Planning Level Cost Estimation Tool User s Manual Atlanta Regional Commission Submitted By: User s Manual Table of Contents 1. INTRODUCTION... 1 2. OBJECTIVE... 1 3. FRAMEWORK OF THE TOOL... 2 4. HOW TO
More informationIH-635 MANAGED LANES PROJECT, SEG. 3.2
IH-635 MANAGED LANES PROJECT, SEG. 3.2 Location: Dallas, Texas Owner: Texas Department of Transportation Client: Ferrovial Agroman Construction Cost: $1 Billion Construction Completion Date: December,
More informationSurface Transportation Program (STP) Projects
Toledo Metropolitan Area Council of Governments American Reinvestment and Recovery Act (Economic Stimulus Program) Application Packet for: Surface Transportation Program (STP) Projects APPLICATIONS DUE
More informationHow To Improve Lrs Maintenance
GIS-T Conference 2015 Crossroads in the Heartland LRS Maintenance and Asset Management Systems Phil Hardy LRS Product Manager Agenda Evolution of LRS Maintenance Lessons learned implementing Roads & Highways
More informationGREENSBORO - HIGH POINT ROAD (SR 1486 / 4121)
NORTH CAROLINA DEPARTMENT OF TRANSPORTATION GREENSBORO - HIGH POINT ROAD (SR 1486 / 4121) FROM PROPOSED US 311 BYPASS TO HILLTOP ROAD (SR 1424) TIP PROJECT U-2412 WBS Element 34802 Federal Project Number
More informationEffect on structures. Uniform settlement - no concerns. Angular distortion - causes damage due to tensile strain
Effect on structures Uniform settlement - no concerns Angular distortion - causes damage due to tensile strain 1/500 - safe limit for no cracking of buildings 1/150 - potential structural damage 36 37
More informationSECTION XI OPINION OF PROBABLE COST
SECTION XI OPINION OF PROBABLE COST OPINION OF PROPABLE COSTS HARBOR ISLAND THE PAVILION 1) Provide a sprinkler system for the entire building. 8000 SF X $15/SF $120,000 2) Remove and replace existing
More informationThe financial plan was prepared in conjunction with the Technical Working Group. Refer to Table 3-1: Funding and Implementation Plan.
3 Financial Plan The purpose of the financial plan is to identify funding options that would be likely sources of money to advance recommendations made by this study. The Capitol Region Transportation
More informationAppendix. Change Management Plan. Communication Plan. QA/QC Plan. Transition and Closure Plan C-1
Appendix C Change Management Plan Communication Plan QA/QC Plan Transition and Closure Plan C-1 CHANGE MANAGEMENT PLAN Whether the effects of changes are positive or negative, managing change is an important
More informationSECTION III-06 Surfacing Page 1 Revised 3/2/10. See the DESIGN GUIDELINES in Section I-06 for requirements for cross slope of the roadway.
Page 1 Revised 3/2/10 See the DESIGN GUIDELINES in Section I-06 for requirements for cross slope of the roadway. For New/Reconstruction projects: The cross slope of the driving lanes range from 1.5% to
More informationJuly 2010 Met Council contributes $1 million to small business loan fund More Downtown Downtown Minneapolis St. Paul
July 2010 Chair Peter Bell of the Metropolitan Council speaks about the Met Council s contribution of $1 million to a $1.5 million small business loan fund during a July 20 news conference with Mayor R.T.
More informationChapter Forty-seven. RURAL TWO-LANE/MULTILANE STATE HIGHWAYS (New Construction/Reconstruction) BUREAU OF DESIGN AND ENVIRONMENT MANUAL
Chapter Forty-seven RURAL TWO-LANE/MULTILANE STATE HIGHWAYS (New Construction/Reconstruction) BUREAU OF DESIGN AND ENVIRONMENT MANUAL Illinois RURAL TWO-LANE/MULTILANE STATE HIGHWAYS December 2009 2 Illinois
More informationProgram Management. APWA North Carolina Chapter. Design-Build: Will it Work for You? William Palmieri, P.E.
APWA North Carolina Chapter Design-Build: Will it Work for You? Program Management William Palmieri, P.E. HDR Engineering, Inc. 695 Atlantic Avenue Boston, MA. 02111 (512) 627-6300 (m) August 6, 2015 William
More informationCITY OF ROANOKE AND TOWN OF VINTON, VIRGINIA. RSTP Funds Joint Application FOR
CITY OF ROANOKE AND TOWN OF VINTON, VIRGINIA RSTP Funds Joint Application FOR Tinker Creek Pedestrian Bridge: Tinker Creek and Glade Creek Greenways Connection Date: September 15, 2014 RSTP Project Profile
More informationThe Rehabilitation Alternative Huey P. Long Bridge Case Study. Bruce E. Peterson, P.E. Project Manager Modjeski and Masters, Inc.
The Rehabilitation Alternative Huey P. Long Bridge Case Study Bruce E. Peterson, P.E. Project Manager Modjeski and Masters, Inc. March 22, 2010 Replacement vs. Rehabilitation Project Background Introduction
More informationDESIGN-BUILD PROCUREMENT AND ADMINISTRATION GUIDE
ARIZONA DEPARTMENT OF TRANSPORTATION INTERMODAL TRANSPORTATION DIVISION DESIGN-BUILD PROCUREMENT AND ADMINISTRATION GUIDE 3rd Edition December 2007 Published by: ADOT Construction Group 206 S. 17 th Ave.,
More informationMIAMI-DADE EXPRESSWAY AUTHORITY (MDX) OPERATIONS COMMITTEE MEETING TUESDAY, AUGUST 27, 2013 12:00 PM
MIAMI-DADE EXPRESSWAY AUTHORITY (MDX) Attendees: Present Committee Members: Louis V. Martinez, Esq., Chair Gus Pego, P.E., Vice Chair via phone Alfredo L. Gonzalez, Esq. Jose M. Hevia Luz Weinberg Present
More informationInformational Workshop Public Meeting Kanawha Falls Bridge Project
Informational Workshop Public Meeting Kanawha Falls Project WV Department of Transportation Division of Highways in Cooperation with the Federal Highway Administration State Project S310-13-0.02 00 Federal
More informationUnited States Department of Transportation Federal Transit Administration
World Trade Center Transportation Hub Permanent World Trade Center PATH Terminal and Pedestrian Connections ENVIRONMENTAL REVIEW PROCESS Scoping Meeting October 8, 2003 and October 9, 2003 United States
More informationINDOT 2000-2025 Long Range Plan
Chapter 9 INDOT 2000-2025 Long Range Plan Highway Needs Analysis Overview The statewide transportation planning process provides for the identification of highway needs through a comprehensive process
More information770 TH Tseung Kwan O Development, Phase II, Grade Separated Interchange T1/P1/P2
770 TH Tseung Kwan O Development, Phase II, Grade Separated Interchange T1/P1/P2 Introduction The T1/P1/P2 junction is situated, north of Tseung Kwan O (TKO) Town Centre, at the junction of TKO Tunnel
More informationI-676 (Vine Expressway) Bridge Reconstruction Project 22 nd - 18 th Streets Philadelphia, PA. PSPE Presentation, December 3, 2015
I-676 (Vine Expressway) Bridge Reconstruction Project 22 nd - 18 th Streets Philadelphia, PA PSPE Presentation, December 3, 2015 Location Map N PROJECT LOCATION 22 nd 18 th Streets PHILADELPHIA, PA General
More informationMaryland SafeZones. Work Zone Automated Speed Enforcement Program. Eric Tabacek Deputy Director, Office of Traffic and Safety
Maryland SafeZones Work Zone Automated Speed Enforcement Program Eric Tabacek Deputy Director, Office of Traffic and Safety Overview Program goals Rules and regulations Citation processing Pilot program
More informationComprehensive Mobility Project Development Process Capital Metro ¼-Cent Fund Analysis
Comprehensive Mobility Project Development Process Capital Metro ¼-Cent Fund Analysis Transportation & Mobility projects that meet the following criteria: enhances regional mobility; supports public transit;
More informationPUBLIC INFORMATION MEETING SUMMARY
PUBLIC INFORMATION MEETING SUMMARY South Mountain Freeway Study 59th Avenue Alignment Alternative Prepared for: Arizona Department of Transportation Prepared by: HDR Engineering, Inc. 3200 East Camelback
More informationCHAPTER 27 New Public Road Connections. Table of Contents
Chapter 27 New Public Road Connections Table of Contents CHAPTER 27 New Public Road Connections Table of Contents CHAPTER 27 New Public Road Connections... 27-3 ARTICLE 1 - General... 27-3 Responsibility...
More informationCapacity Deficiency Project Application Jackson MPO Surface Transportation Program
Capacity Deficiency Project Application Jackson MPO Surface Transportation Program The following information must be completed for all Capacity Deficiency proposed Jackson MPO STP projects. MPO staff will
More informationHow To Build A City Of Virginia Beach Arena
City of Virginia Beach Arena Infrastructure Preliminary Conceptual Cost Estimates Doug Smith, Deputy City Manager Carl Tewksbury, Kimley-Horn City Council Briefing July 8, 2014 July 8, 2014 Presentation
More informationSUPPLEMENTAL SPECIFICATIONS CROSS SLOPE VERIFICATION:
September 22, 2009 Updated November 16, 2009 SUPPLEMENTAL SPECIFICATIONS CROSS SLOPE VERIFICATION: 1. DESCRIPTION: The cross slopes of the roadway are to be constructed as detailed in the plans and within
More information**The Winter 2010 edition of The Road Ahead newsletter is available online.
RTC e-news Brief for January 29, 2010. This e-newsletter was created to keep you informed about key activities and issues pertaining to Your RTC. I encourage you to share this information with your board
More information100 Design Controls and Exceptions
Table of Contents 100 Introduction... 1 101 Functional Classification... 1 101.1 General... 1 101.2 Urban & Rural... 1 101.3 Classification Used In ODOT Design Criteria... 1 102 Traffic Data... 2 102.1
More information