1

2 CONTENTS Preface o Message from SCAL o Message from PUB 1. Importance of Effective Earth Control Measure (ECM) 2. Roles of Construction Industry 3. Implementation of an Effective ECM a. Erosion Control b. Sediment Control c. Maintenance & Review 4. Submission Requirements For ECM 5. Checklist of Erosion and Sediment Control 6. Bad & Good Practices at Construction Sites 7. Legislation and Code of Practice 8. Listing of ECM Products, Services and Technology Providers Annexes Annex 1 Roles of Construction Industry Annex 2 Sample Specifications and Itemised BQ for ECM Annex 3 Schematic Drawing for ECM at Construction Sites Annex 4 TSS Samples (50mg/l)

3 Preface Message from SCAL: The Singapore Contractors Association is pleased to collaborate with the key partners of the industry including PUB to promote good environmental practice to keep Singapore s water catchments clean. SCAL urges contractors to take earth control measures and prevent silty discharge from construction activities and hope that with this guidebook, contractors can help to minimize and prevent upstream pollution. We urge all to conserve and value our scarce water resource and work together to improve the quality of water to be enjoyed by everybody. Desmond Hill President Singapore Contractors Association Ltd

4 Message from PUB: This guidebook is the result of a joint effort between the Singapore Contractors Association Ltd (SCAL) and the PUB. We are very grateful to the Association for its active participation in this publication. My sincere thanks to the President and Council Members of SCAL, and members who have contributed towards the publication of this guidebook. We now have beautiful and clean waterways that we can be proud of. Everyone of us plays a part in keeping our waters clean. As contractors, your role is important. Through the simple and conscious act of controlling earth and silt washdowns, you can prevent your site from becoming a source of muddy waters that taint our waterways. This guidebook is the 3 rd edition and contains an updated silt and earth control measures that construction industry has to implement at every construction site to achieve the regulated discharge standard. We hope that you will find this guidebook useful. And together, we must do our part to ensure that our beautiful waterways and rivers remain clean and clear at all time. With best wishes, Tan Nguan Sen Director, Catchment & Waterways Department Public Utilities Board

5 1. Importance of Effective Earth Control Measures (ECM) Singapore is well respected for our clean and green environment as well as our resourcefulness in harnessing our scarce water resources. Over the years, we have spent much effort to clean up and beautify our rivers & waterways. This has resulted in the clean and aesthetic waterways, like Singapore River and Kallang Basin which Singaporeans enjoy today. Singapore River Sungei Sembawang Sungei Api Api

6 While our rivers and waterways are clean most of the time, we still see them turn brown during and after a rain. The silty brown water is spoiling our proud image of a green and clean Singapore. More importantly, the silty water is hampering our effort to make every drop counts as the silt will make it more difficult and costly to treat. Over the next 1 to 3 years, more of our waterways will be dammed up to increase Singapore's robustness in water resources. By 2008, a barrage will be built across Marina Channel which will impound water from 5 major urban river catchments. Together we can definitely do more and better to improve the quality of the storm runoffs discharging into our waterways. What causes the river to turn brown? Silt and sediment control is a key element in our water resources management strategy. Sediments introduced into our rivers cause environmental pollution and increase flood risk and turn our river water brown. Sediments can remain suspended for a very long time. The major source of sediments is from construction sites. Construction activities disturb existing ground cover and vegetation, and expose much bare surfaces. (For fuller detail, please refer to ECM website:

7 2. Roles of Construction Industry Note: The earth control measure (ECM) is meant for the control of silty discharge due to rain water. Other waste water (slurry water, bentonite etc) due to construction activities such as piling or tunneling work should be separately treated (A) Contractor The roles of Contractor during the whole duration of a typical project development process are summarized in the table below: 1. Engage QECP for detailed ECM (see schematic drawing in Annex 3) 2. Provide information on topography, soil, construction work and schedule, site facilities, etc to QECP 3. Submit ECM plan prepared and endorsed by both QECP and Contractor to PUB together with an application for Clearance Certificate to commence earthworks 4. Obtain Clearance Certificate to commence earthworks from PUB Before Commencement of works 5. Engage ECO or trained person in ECM 6. Implement QECP s endorsed ECM plan before commencement of works a. Erosion Control 1) Minimise exposure of bare surface by paving up, erosion control blankets or scheduling works in phases, etc b. Sediment Control 1) perimeter silt fence 2) perimeter cut off drains 3) silt trap 4) storage tanks / ponds 5) treatment system etc

8 1. Monitor and Maintain the ECM to ensure effectiveness 2. Engage QECP to : a) Set up site monitoring and management system for ECM b) review in tandem with progress of works and implement the revised ECM accordingly 3. Submit weekly reports of ECM at site to QECP During Construction 4. provide continuous monitoring and recording system at discharge point before public drain 5. cover up the active work surfaces with canvas sheet during rain or at the end of the workday 6. Make available to PUB Officers at all times of visits the followings: i. QECPs endorsed ECM plan (latest revision) ii. Records of inspections by QECP and ECO iii. Continuous record Before Completion 1. Provide / establish finishing surfaces (close turfing, concrete paving, road surfaces etc) 2. Obtain QECP s approval before ECM is removed (B) Developer and Professional Each sector of the construction industry plays a critical role in implementing an effective earth control measures (ECM) at construction sites. Please refer to Annex 1 for fuller details of the roles. The key roles are summarised below: (1) Developer / QP to include sample specifications and itemised BQ for ECM (see Annex 2) in tender document before commencement of works. (2) QECP to advise developer / QP and plan, design and monitor effective ECM. *QECP Qualified Erosion Control Professional

9 3. Implementation of an Effective ECM An effective earth control measure (ECM) must comprise 2 aspects: (a) Erosion Control to minimise bare earth surfaces (b) Sediment Control to contain, storage and treat silt sediments and shall comply with Clause 6.3 of the Code of Practice on Surface Water Drainage (See Chapter 7) (A) Erosion Control It is much easier and more cost effective to prevent erosion than to trap sediments after erosion has taken place. With proper planning, a site should not have more than 0.1 ha of bare surface at any one time. The following are some good ECM management practices to minimise erosion by ensuring minimum bare earth surfaces at all time: Scheduling of works: 1 to properly sequence and schedule the earthworks / demolition / construction works in stages and progressively to minimise bare surfaces. 2 to minimise site disturbance by keeping site clearance works to a minimum by retaining as much of the existing vegetation as possible. 3 to establish final surface (by close turfing, concrete paving, road surfaces etc) immediately. No bare surfaces: 1 to pave up the bare surfaces and all construction access by concrete or milled waste or other suitable materials. 2 to protect the bare slopes by close turfing, cementitious spray / grouting or erosion control blanket. 3 to protect the earth stockpiles by erosion control blanket. 4 to cover up the active work surfaces by canvas sheet during rain or before work stop at the end of workday. 5 to turf up the bare surfaces immediately in an earthwork / demolition work if there is no subsequent construction activities.

10 (B) Sediment Control After achieving minimum bare earth surfaces, sediment control facilities must be put in place to capture the sediments washed down from the construction sites. Some of these sediment control measures and facilities which must be in place before the works start shall include the following: Containment: 1 to provide concrete lined cut off drains (minimum C7 precast channel) along the perimeter of the construction sites. 2 to provide silt fence properly installed and embedded onto the ground along the perimeter cut off drains (between the construction site and the cut off drains). Storage: 1 to provide sedimentation basins of adequate size and sufficient numbers along the perimeter cut off drains and before the discharge points into public drain. 2 to provide storage tank, reservoir of adequate size and sufficient numbers to temporarily store / contain rainwater before treatment. Treatment: 1 to provide treatment units or coagulant units to treat silty water before discharge into public drain. (C) Maintenance and Review 1 to maintain all erosion and sedimentation control facilities to ensure effectiveness at all time. 2 to review ECM regularly as the work progresses.

11 4. Submission Requirements for ECM Note: The earth control measure (ECM) is meant for the control of silty discharge due to rain water. Other waste water (slurry water, bentonite etc) due to construction activities such as piling or tunneling work should be separately treated (A) During Planning Stage The owner / developer should take note of the standard clause for the ECM requirement before obtaining DC clearance / approval Earth Control Measures: Effective erosion and sediment control measures shall be provided by the developer / owner and the QP shall advise his developer / owner to provide such effective measures and facilities with inputs from Qualified Erosion Control Professional (including site management system and perimeter cut off drain, silt traps, storage ponds, treatment plants, etc) to ensure clean discharge that complies with the statutory requirement. The proposed erosion and sediment control measures shall be submitted by a Qualified Erosion Control Professional (QECP) to Public Utilities Board for approval before commencement of works. All affected watercourses shall be desilted and cleared until completion of work. For reference, the information can be found in the website (B) Before commencement of work The Contractor shall apply for a Clearance Certificate to commence works (which will require ECM) together with the proposed erosion and sediment control measures (prepared and endorsed by a QECP) to PUB. The earth control measures shall comply with the requirements stipulated in Clause 6.3 of the Code of Practice on Surface Water Drainage (Posted at PUB website address

12 (C) During Construction Stage The Contractor shall submit the ECM proposal duly endorsed by his QECP to PUB and carbon copied to the owner / developer as follows: 1 Before Work Commences to submit the ECM proposal indicating that: a minimum bare surfaces will be ensured according to the construction activities in each phase. b effective sediment control facilities (Including storage and treatment facilities) will be implemented c a system of ECM as indicated in (a) and (b) above will be in place before work commence d Clearance Certificate (See (B) above) to commence earthworks is obtained 2 During Work to revise and resubmit the ECM proposals according to each phase of the construction activities indicating that: a b c minimum bare surfaces will be ensured according to the construction activities in each phase. effective sediment control facilities (Including storage and treatment facilities) will be implemented a system of ECM as indicated in a and b above will be revised and put in place to control silty discharge for each phase 3 Upon Work Completion to confirm that all the site activities have been completed and the ECM can be removed. (D) Before Work Completion The contractor shall inform PUB that ECM will be removed based on QECP s recommendation / approval.

13 5. Checklist of Erosion and Sediment Control Note: The earth control measure (ECM) is meant for the control of silty discharge due to rain water. Other waste water (slurry water, bentonite etc) due to construction activities such as piling or tunneling work should be separately treated (A) Checklist of Erosion Control No bare surfaces To protect bare slopes and stockpiles with close turfing or erosion control blankets or lean concrete To establish final surface / turfing quickly To cover up active work surfaces by canvas sheet during rain or before work stop at the end of workday Scheduling of works To minimise bare earth surfaces to 0.1ha at any one time To sequence and schedule earthworks / demolition or construction works in stages and progressively with subsequent activities To pave up all construction access and bare surfaces with concrete, milled waste, etc To minimize site disturbance by keeping site clearance works to a minimum by retaining as much of the existing vegetation as possible. To establish final surface / turfing quickly

14 (B) Checklist of Sediment Control Containment To provide perimeter lined cut off drains To provide perimeter silt fences along perimeter cut off drains To provide turbidity curtain for work alongside rivers & waterways To protect earth slopes/surfaces with closed turfing, milled waste, concrete, erosion control blankets, polythene sheets or other suitable materials Storage To provide adequate size and number of sedimentation sumps or storage tanks before treatment of silty water To provide adequate size and number of sedimentation sumps or storage tanks before discharge and along the perimeter cit off drain Treatment To provide treatment unit / coagulant unit to treat silty water before discharge Maintenance To maintain sediment control facilities at least once a week and after every storm event (C) Regular Review To review ECM plan with QECP as work progresses To remove ECM only at the end of work and as advised by QECP

15 6. Bad & Good Practices at Construction Sites NO Silty Discharge

16 6. Bad & Good Practices at construction sites NO BARE SURFACE Without turfing With turfing Without ECB With ECB Without Lean Concrete With Lean concrete List of technology providers in chapter 8

17 6. Bad & Good Practices at construction sites Silt Fence & Perimeter Drain Silt fence not properly embedded resulting in gaps below the fence & Silt fence installed on the wrong side. It should be installed to trap the silt from the worksite Silt fence firmly embedded in ground and installed in between cut off drain and worksite List of technology providers in chapter 8

18 6. Bad & Good Practices at construction sites Silt Trap Inadequate silt trap resulted in silty water discharges onto adjacent public place Silt trap properly designed with the usage of polymer block & geotextiles. (note: sand or granite chip as filter is not accepted) List of technology providers in chapter 8

19 6. Bad & Good Practices at construction sites Silty Water Treatment System List of technology providers in chapter 8

20 6. Bad & Good Practices at construction sites Turbidity Curtain List of technology providers in chapter 8

21 7. Legislation and Code of Practices The following legislation and requirements pertaining to the control of erosion and sediment are highlighted: THE SEWERAGE AND DRAINAGE ACT, CAP. 294 Works affecting storm water drainage system Section 26(1) No person shall carry out or cause to be carried out any works which will affect any storm water drainage system, drain or drainage reserve, directly or indirectly, without obtaining in respect of those works, a clearance certificate or approval of the Board. Section 26(2) Where any work has been carried out in contravention of subsection 26(1), the Board may by Notice in writing require the person who carried out the works, the owner or occupier of any premises in respect of which the works were carried out to carry out such works as the Board thinks necessary within such time as may be specified in the Notice. Default in compliance with notice Section 41(1) Where a person on whom a Notice under section 26 is served fails to comply with the notice within the time specified in the Notice, he shall be guilty of an offence and shall be liable on conviction to a fine not exceeding $20,000.

22 SEWERAGE AND DRAINAGE (SURFACE WATER DRAINAGE) REGULATIONS REVISED EDITION 2001 Prohibition of discharge of silt, etc. into storm water drainage system Regulation 4(1) No person shall discharge or cause or permit the discharge into the storm water drainage system of Total Suspended Solids in concentrations greater than 50 milligrams per litre of the discharge. Regulation 4(2) Every person carrying out earthworks or construction works shall comply with the Code of Practice and in particular with the following requirements: a) earth control measures shall be provided and maintained in accordance with the Code of Practice b) runoff within, upstream of and adjacent to the work site shall be effectively drained away without causing flooding within or in the vicinity of the work site. c) all earth slopes shall be set outside a drainage reserve; d) all earth slopes adjacent to any drain shall be closed turfed; and e) adequate measures shall be taken to prevent any earth, sand, topsoil, concrete, debris or any other material to fall or washed into the storm water drainage system from the stockpile thereof. SEWERAGE AND DRAINAGE (SURFACE WATER DRAINAGE) REGULATIONS REVISED EDITION 2003 Penalty Regulation 6 Any person who contravenes or fails to comply with any provision of these Regulations shall be guilty of an offence and shall be liable on conviction to a fine not exceeding $5,000 and, in the case of a continuing offence, to a further fine of $500 for every day or part thereof during which the offence continues after conviction.

23 CODE OF PRACTICE ON SURFACE WATER DRAINAGE (Fifth Edition Mar 2000) Addendum No. 3 Aug 2006 This addendum shall be read in conjunction with the Code of Practice on Surface Water Drainage (Fifth Edition Mar 2000) and shall form part of the Code of Practice. S/No. Part /Page Amendments /corrections No 1 2 Define Qualified Erosion Control Professional 2 18 Delete Clauses to and Substitute with Clauses to (1) Define Qualified Erosion Control Professional Terminology "Qualified Erosion Control Professional" (QECP) means a Professional Engineer who is registered under the Professional Engineers Act Chapter 253, has in force a practising certificate issued under that Act, and has satisfactorily completed a specialized professional course in erosion and sediment control. (2) Delete Clauses to and Substitute with Clauses to Earth Control Measures Water Quality Parameters to be Complied with The discharge from any construction / earthwork sites into storm water drainage system shall not contain Total Suspended Solids (TSS) in concentrations greater than, or turbidity exceeding, the prescribed limits under Regulation 4(1) of the Sewerage and Drainage (Surface Water Drainage) Regulations Minimal or No Discharge A construction / earthwork site should practice recycling of water. The recycled water could be used for non potable purposes in order to minimise discharge into the stormwater drainage systems ECM Specifications in Tenders Developers / owners and Qualified Persons should include the earth control measures (ECM) specifications and schematic or conceptual ECM plans in the tender documents and allow for the cost of ECM in the tenders Permit to start Earthworks The site operator / contractor shall obtain a written permission (or a clearance certificate) from Public Utilities Board before the commencement of any earthwork.

24 6.3.5 Submission of ECM proposal before commencement of works Before commencement of works, the site operator / owner shall engage a Qualified Erosion Control Professional (QECP) to plan and design a system of earth control measures (ECM) to meet the requirements cited in Clause The site operator / owner shall submit the detailed ECM proposal, endorsed by his QECP, to the Public Utilities Board for record, prior to the commencement of works. The ECM proposals (with calculations) shall include a plan (a typical plan is as shown in Drawing No.9) Design Criteria of ECM The ECM shall be designed to cope with a minimum design rainfall intensity of a return period of 1 in 2 years storm ECM to be installed before commencement of work The ECM shall be installed by the site operator / contractor according to the endorsed plans and the completed ECM at site shall be approved by the QECP before commencement of construction and earthworks General Guidelines for Effective ECM An effective ECM requires 2 components which shall include, but is not limited to, the following minimum measures in order to meet the legal requirements cited under Regulation 4(1) of the Sewerage and Drainage (Surface Water Drainage) Regulations: (A) Erosion Control Measures The erosion control measures shall minimise the extent and duration of any exposed / bare / erodible surfaces by: a. Proper Work Sequencing Adopting proper construction staging and work sequencing will help to ensure that no large bare / erodible surfaces are exposed for a long duration of time. b. Covering up of all bare / erodible surfaces All bare surfaces (including earth stockpiles) shall be by concrete lining, concrete paving, milled waste, erosion control blankets, close turfing or other suitable materials. Accesses within the site and at exit / entrance as well as the surfaces where site facilities (such as office, fabrication and storage yards) shall be paved. For those work areas, they shall be covered by canvas sheets, tarpaulin sheeting or other suitable materials during rains or before work stops every day. c. Progressive and timely revegetation and stabilisation This is to ensure that all bare surfaces are restored immediately upon completion of work at every stage. If a construction site has very little bare / erodible surfaces, the operator / contractor will have less difficulty in containing and treating the silty discharges as described in Clause (B) below. For those areas within a

25 construction site which have been paved / covered and will not cause silty discharge, it is possible to drain these areas directly into the storm water drainage system without treatment. (B) Sediment Control Measures The sediment control measures shall trap, contain and treat the silty discharges from within a construction / earthworks site (including rain, runoff, water from washbay, underground water at basement, etc) by providing: a. Perimeter Cut off Drain Perimeter cut off drains shall be concrete lined and adequate to capture all runoff from the site to prevent overflow onto adjacent properties. b. Perimeter Silt Fence Silt fences shall be erected along the perimeter cut off drain (between the construction site and perimeter cut off drain). The silt fence is to be embedded firmly into the ground and made from an approved geotextile filter fabric or equivalents to capture the sediment from stormwater runoff. The sediment built up behind the silt fence must be regularly removed. c. Intermediate Silt Trap Intermediate silt traps of suitable size shall be installed at regular intervals along the perimeter lined cut off drain. Within the intermediate silt traps, suitable geotextile filter fabric or equivalents shall be installed across the full depth and width and / or coagulation assistance materials shall be placed. Silt traps relying primarily on hardcore, granite chips or sands for filtration, are not acceptable. d. Sedimentation Basin or Storage Pond / Tank Before silty discharge leaves the site, the silt and sediments shall be separated from the water. This can be achieved by either: i. in a sedimentation basin / pond (which will take days for settlement to take place and a large basin volume), or ii. through a treatment system cum storage tank. The basin / tank shall have a storage capacity to cope with the volume of water from a rain based on a minimum design return period of 1 in 2 years storm. e. Treatment System If the design of a sedimentation basin cannot meet the TSS requirement, then other suitably sized treatment system shall be installed to treat all silty discharge from construction and earthwork sites. The treated effluent could be recycled for non potable use. f. Turbidity Curtains For works in or adjacent to water bodies, such as canals, rivers, sea or in a reclamation work, turbidity curtain(s) shall be installed along all the exposed slopes / riverbanks. The silty discharge

26 trapped within the turbidity curtain shall be allowed to be settled or treated, and the settled silt removed g. Wheel wash the waters used to wash the wheels of the trucks / vehicles shall not be discharged into stormwater drainage system at any time. The silty water within the wheel wash basin shall be connected to the sedimentation basin / treatment system. The silt collected at the bottom of the wheel wash shall be removed Review of ECM during Contract duration The site operator/ contractor shall ensure that the ECM designed and installed shall be continuously reviewed by the QECP for every stage of the construction and earthworks. The ECM shall remain effective throughout the whole duration of works. The site operator / contractor shall add or amend the ECM at site according to the design of the QECP Maintenance of ECM during Contract duration The site operator / contractors shall operate and maintain the ECM regularly to ensure the ECM remains effective throughout the whole duration of works. This may involve replacing of silt fences and erosion control blankets or re paving of concrete surfaces or replacing of membrane module or polymers blocks Monitoring of Discharge during Contract duration The site operator / contractor shall monitor the TSS and turbidity of the discharge before the discharge enters the storm water drainage system. The site operator / contractor shall submit regular reports (including photographic and monitoring records) of the site ECM as well as those for discharge quality to the Public Utilities Board over the whole duration of the project Removal upon Completion The ECM shall not be removed before the completion of work. The site operator/ owner shall inform Public Utilities Board prior to removal of the ECM on completion of the project.

27 8. Listing of ECM products, services and technologies providers (For updated list of suppliers, please visit ECM website Erosion Control Blankets Abacus Corp, Belton Industries Inc, FNW, Kingfibre & Soilguard CHT Natural Solutions, yufong@starhub.net.sg Fibromat; Fibrotag, walltag@singnet.com.sg Mirafi Geosynthetics North American Green : Indirect Screening for Silt / Debris Control CDS Technologies : Rocla : Stormceptor : Polymer CCM Singapore Pte Ltd, Tel : Trident Chemicals Enterprise, Tel : Silt Fence AbacusCorp, abetrad@singnet.com.sg Geotag Silt Fence, walltag@singnet.com.sg Mirafi Geosynthetics Products : Permathere : Southeast Environment Services, Inc : Tencate, m.sim@tencate.com Silt Water Treatment System Flexi Systems, flexi_system@yahoo.com.sg Glowtech, Tel: KBI Contracts & Marketing Pte Ltd, yufong@starhub.net.sg Sam McCoy Engineering P/L: Singaport Cleanseas P/L, victorp@ultra flo.com.sg SiltTreat, chengkf@pacific.net.sg WETSEP, sales@scottvickers.com.sg Turbidity Curtain Elastec American Marine Inc : Geotag Silt / Turbidity Curtain, walltag@singnet.com.sg Mentanza Pty Ltd : Permathene :

28 Annexes Annex 1 Roles of Construction Industry Annex 2 Sample Specifications and Itemised BQ for ECM Annex 3 Schematic Drawing for ECM at Construction Sites Annex 4 TSS Samples (50mg/l)

29 Annex 1 Roles of construction industry Project ROLES Development Process Owner / Developer / Qualified Person QECP (Engaged by Owner / Developer) (I) Planning & Design 1. Qualified Person could consult PUB on the need to engage QECP for proposals that involve minimium earth disturbance in the early stage (i.e. during DC Clearance) Qualified Person to advise the owner / developer accordingly. 2. Developer to engage QECP for preliminary ECM & specifications 3. Developer to endorse BP for compliance with ECM as specified in Code of Practice on Surface Water Drainage (Latest Edition) 1. Conduct site assessment, plan, design and submit preliminary ECM to PUB for record 2. Advise Owner / Developer / Qualified Person to : a. include ECM specifications (incl the preliminary ECM plan for project and allow for costs) (see Annex 2 for sample specification and itemised BQ) b. refer to ECM (II) Tender 1. Developer / Qualified Person to evaluate preliminary ECM plan in tender submission 2. Qualified Person to submit successful Contractor s particulars to PUB 1. Stipulate ECM requirements according to site conditions of the project and allow tenderers to price for them in the tender document 2. Provide advice / evaluation on submitted preliminary ECM plan and method statements received from tenderers

30 Contractor QECP (Engaged by Contractor) (May or may not be the same QECP of Developer / Owner above) (III) Before Commencement of works 1. Engage QECP for detailed ECM 2. Provide information on topography, soil, construction work and schedule, site facilities, etc to QECP 3. Submit ECM plan prepared and endorsed by both QECP and Contractor to PUB together with an application for Clearance Certificate to commence earthworks 4. Obtain Clearance Certificate to commence earthworks from PUB 5. Engage ECO or trained person in ECM 6. Implement QECP s endorsed ECM plan before commencement of works a. Erosion Control 1 Minimise exposure of bare surface by paving up, erosion control blankets or scheduling works in phases, etc b. Sediment Control 1 perimeter silt fence 2 perimeter cut off drains 3 silt trap 4 storage tanks / ponds 5 treatment system etc 1. Prepare a detailed ECM plan (basing on information provided on topography, soil, construction work and schedule, site facilities, etc) for all phases of the project for submission to PUB. QECP may be required to make presentation to PUB. 2. Advise Contractor to submit ECM plan to PUB and obtain Permit or Clearance Certificate to commence earthwork before commencement of works 3. Advise Contractor on setting up of a monitoring and control system at site, including: a. appointment of and brief Environmental Control Officer or trained person in ECM on the ECM plan and checklist b. monitoring the installation of ECM to QECP s specifications and ensuring its effectiveness c. scheduling of maintenance of ECM and inspections

31 (IV) During Construction 1. Monitor, Maintain the ECM to ensure effectiveness 2. Engage QECP to a) Set up site monitoring and management system for ECM b) review in tandem with progress of works and implement the revised ECM accordingly 3. Submit weekly reports of ECM at site to QECP 4. provide continuous monitoring and recording system at discharge point before public drain 5. cover up the active work surfaces with canvas sheet during rain or at the end of the workday 6. Make available to PUB Officers at all times of visits the followings: i. Endorsed ECM plan ii. Records of inspections by QECP and ECO iii. Continuous record 1. Advise contractor on the effectiveness of the site monitoring and management systems. 2. Review ECM in tandem with progress of works 3. Oversee the keeping of ECM inspections records. 4. Requiring Contractor s ECO or trained person in ECM to submit weekly reports for checking and compilation. 5. Inform PUB of any non compliances of ECM plan (V) Before Completion 1. Provide / establish finishing surfaces (close turfing, concrete paving, road surfaces etc) 2. Obtain QECP s approval before ECM is removed 1. Ensure ECM is removed only after completion of all works CIJC PUB Task Force s Visit to Model ECM Site (22 Apr 2006)

32 Annex 2 SAMPLE SPECIFICATIONS FOR EARTH CONTROL MEASURES (Revision 3 Sep 06) 1. The Contractor shall be responsible for preventing silt from being washed into public drains by implementing effective Earth Control Measures (ECM) for the construction site to meet the requirements under the latest Sewerage and Drainage Act Cap 294. (Information on ECM requirements can be found in the Code of Practice on Surface Water Drainage and the website The contractor shall note that the ECM are for the containment and treatment of silty discharges due to the impact of rainwater. ECM are not meant for the treatment of wastewater due to construction activities (such as slurry from tunnelling, pipe jacking and bore piling works) which shall be treated to comply with the requirements under Environmental Pollution Control Act (Chapter 94A). 2 In his tender submission, the Contractor shall submit his schematic ECM plans of the construction site for the whole duration of the contract period taking into account the different phases of construction activities. He shall also provide the name of the Qualified Erosion Control Professional (QECP) who will be endorsing the ECM plan after the tender is awarded. These schematic ECM plans shall make the Contractor aware of the ECM requirements and the cost to implement an effective ECM. Notwithstanding the submission of these schematic ECM plans, the Contractor shall deem to have separately priced for the ECM in the contract sum. 3 Before construction works commence on site, the Contractor shall engage a QECP to plan and design the ECM, and he shall install the ECM according to the QECP's design. The ECM plan and design shall be submitted 1 week after the award of the contract. During the course of the construction works, the Contractor together with his QECP shall review the ECM proposal regularly to meet the changing needs of the construction activities. The Contractor shall improve the ECM as advised by his QECP. The planning and design of the ECM shall meet the minimum requirements stipulated and in accordance to the Code of Practice on Surface Water Drainage. 4 The Contractor shall maintain the ECM for the whole duration of the contract to ensure that it is effective at all times. Proper records detailing the maintenance works, supported by dated photographs, shall be kept by the Contractor for verification. 5 The Contractor shall not remove the ECM until all works are completed and upon the advice of his QECP.

33 6 The Contractor shall submit the ECM proposal duly endorsed by his QECP to PUB for records. The proposed ECM shall consist of the following four parts: I. Project Particulars The following information shall be provided under the Project Particulars: (a) Project description (b) Name and address of site occupier; (c) Site area and contract period; (d) Location map and site plan. II. Erosion Control Plan (described in 7) III. Sediment Control Plan (described in 8) IV. Site ECM Management System (descried in 9) 7 During construction, the Contractor shall minimize the formation of bare surfaces under the ECM's Erosion Control Plan. The Plan shall depict graphically the activities, including sequence of work, type and duration for each phase of construction activities to include the following measures to: (a) sequence and schedule of the earthworks I demolition works in stages and progressively with the subsequent construction activities and building works. (b) minimise site disturbance by keeping site clearance works to a minimum by retaining as much of the existing vegetation as possible. (c) pave up the bare surfaces and all construction access by concrete or milled waste or other suitable materials. (d) protect the bare slopes with close turfing, concrete grouting, or erosion control blanket. (e) protect the earth stockpiles with erosion control blanket. (f) restore ground cover over disturbed areas, which are or have become bare, as soon as possible. (g) cover up the active work surfaces with canvas sheet during rain or at the end of the workday. 8 The Contractor shall put in place the ECM's Sediment Control Plan, which aims to capture the sediments washed down from the construction sites. Some of these sediment control measures and facilities, which must be in place before the works start, shall include but not limited to the following: (a) concrete lined cut off drains (minimum C7 precast channel) along the perimeter of the construction sites. (b) silt fence properly installed and embedded onto the ground along the perimeter cut off drains (between the construction site and the cut off drain).

34 (c) sedimentation basins or any other sediment filtering or settling system of adequate size and sufficient numbers along the perimeter cut off drain and before the discharge points into public drain. (d) a storage basin / tank may be required to temporarily store the large amount of rainwater falling on to the whole site before treatment. (e) a treatment system to treat silty discharge shall be provided before the discharge points into public drain. (f) turbidity curtains shall be installed along all the exposed slopes / riverbanks for works in or adjacent to water bodies, such as canals, rivers, sea or in a reclamation work. The silty discharge trapped within the turbidity curtain shall be allowed to be settled / treated and removed. 9 The contractor, shall at the advice of his QECP, put in place a site monitoring and reporting system including but not limited to the following: (a) Daily ECM inspection report by the QECP appointed site personnel (b) Regular site inspection by the QECP (c) Continuous monitoring and recording system shall be installed at the discharge point (after ECM) before public drain 10 The QECP shall submit full basis of design back up with design calculations to show clearly how the perimeter cut off drains, silt fence, sedimentation basins, storage basin / tank and treatment system are designed and sized as well as how such design will effectively filter off silt and allow only clean water to discharge into public drains. The QECP shall also submit the design specifications on the treatment system which can effectively treat the silty discharge from the construction site. The intensity of a one in two year storm should be adopted for the proposed design. SAMPLE ITEMISED BQ FOR EARTH CONTROL MEASURES: S/No Description Qty Unit Rate Amount ($) A B C Allow for engaging a Qualified Erosion Control Professional to design, review and submit Earth Control Measures Proposals to the full satisfaction of the SO. All as specified, throughout the whole duration of works. Allow for the implementation and maintenance of the Erosion Control Plan; all as specified. Allow for the implementation and maintenance of Sediment Control Plan (including the provision of the storage and treatment facilities); all as specified. Item Item Item D Allow for site reporting and monitoring system throughout the whole duration of contract. TOTAL TO SUMMARY OF TENDER Item

35 Annex 3 Schematic Drawing for ECM at Construction Sites

36 Annex 4 50 mg/l 250 mg/l 500 mg/l 5000 mg/l Water sample with various Total Suspended Solids (TSS) Readings.

37 1 st edition nd edition December rd edition September 2006

City of Shelbyville Site Inspection Checklist

City of Shelbyville Site Inspection Checklist City of Shelbyville Site Inspection Checklist General Information Project Name: KYR10 Permit Number: Date: Project Location: Contractor: Conractor Representative: Inspector's Name: Title: Signature : Weather

More information

Outlet stabilization structure

Outlet stabilization structure Overview of Sedimentation and Erosion Control Practices Practice no. 6.41 Outlet stabilization structure Erosion at the outlet of channels, culverts, and other structures is common, and can cause structural

More information

CONSTRUCTION STORMWATER POLLUTION PREVENTION PLAN TEMPLATE

CONSTRUCTION STORMWATER POLLUTION PREVENTION PLAN TEMPLATE CONSTRUCTION STORMWATER POLLUTION PREVENTION PLAN TEMPLATE The following template may be used as a general guide for development of a Stormwater Pollution Prevention Plan (SWPPP) for construction activities.

More information

SITE-SPECIFIC BEST MANAGEMENT PRACTICES (SSBMP) PLAN/STORM WATER POLLUTION PREVENTION PLAN (SWPPP) REVIEW CHECKLIST

SITE-SPECIFIC BEST MANAGEMENT PRACTICES (SSBMP) PLAN/STORM WATER POLLUTION PREVENTION PLAN (SWPPP) REVIEW CHECKLIST This checklist may be used by applicants for encroachment permits, and contractors in development of Site Specific Best Management Practice (SSBMP) Plans or Storm Water Pollution Prevention Plans (SWPPP)

More information

Construction Site Draina e

Construction Site Draina e ProPECC PN 1/94 ENVIRONMENTAL PROTECTION DEPARTMENT PRACTICE NOTE FOR PROFESSIONAL PERSONS Construction Site Draina e Introduction The purpose of this practice note is to provide some basic environmental

More information

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department Land Disturbance, Erosion Control and Stormwater Management Checklist Walworth County Land Conservation Department The following checklist is designed to assist the applicant in complying with the Walworth

More information

Minimizes sediment and debris from entering storm drains that lead to waterways and watercourses.

Minimizes sediment and debris from entering storm drains that lead to waterways and watercourses. 4.5-p DRAIN INLET PROTECTION Alternative Names: DI protection, Drop Inlet Protection DESCRIPTION Storm drain inlet (DI) protection slows and ponds stormwater, and filters sediment and debris before it

More information

Storm Drain Inlet Protection

Storm Drain Inlet Protection Objectives EC Erosion Control SE Sediment Control TR Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Objective

More information

COLORADO DEPARTMENT OF TRANSPORTATION STORMWATER FIELD INSPECTION REPORT - ACTIVE CONSTRUCTION

COLORADO DEPARTMENT OF TRANSPORTATION STORMWATER FIELD INSPECTION REPORT - ACTIVE CONSTRUCTION COLORADO DEPARTMENT OF TRANSPORTATION STORMWATER FIELD INSPECTION REPORT - ACTIVE CONSTRUCTION (1) Project Name: (2) Project Contractor: (3) Erosion Control Supervisor/SWMP Administrator: (4) CDOT Project

More information

Construction Site Inspection Checklist for OHC000004 By making use of some simple Best Management Practices (BMPs) a construction site operator can

Construction Site Inspection Checklist for OHC000004 By making use of some simple Best Management Practices (BMPs) a construction site operator can Construction Site Inspection Checklist for OHC000004 By making use of some simple Best Management Practices (BMPs) a construction site operator can do his or her share to protect Ohio's water resources

More information

CODE OF PRACTICE SURFACE WATER DRAINAGE. Sixth Edition Dec 2011

CODE OF PRACTICE SURFACE WATER DRAINAGE. Sixth Edition Dec 2011 CODE OF PRACTICE ON SURFACE WATER DRAINAGE Sixth Edition Dec 2011 CODE OF PRACTICE ON SURFACE WATER DRAINAGE Public Utilities Board would like to thank the following Professional Institutions for their

More information

Storm Drain Inlet Protection

Storm Drain Inlet Protection Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Category

More information

SE-10 STORM DRAIN INLET PROTECTION. Objectives

SE-10 STORM DRAIN INLET PROTECTION. Objectives STORM DRAIN INLET PROTECTION SE-10 Objectives Erosion Control - EC Sediment Control - SE Tracking Control - TC Wind Erosion Control - WE Non-Storm Water Management - NS Waste and Materials Management -

More information

SITE-SPECIFIC BEST MANAGEMENT PRACTICES (BMP) PLAN REVIEW CHECKLIST

SITE-SPECIFIC BEST MANAGEMENT PRACTICES (BMP) PLAN REVIEW CHECKLIST This checklist may be used by applicants for encroachment permits, and contractors in development of Site- Specific BMP Plans for projects. plan reviewers will use this checklist to review the Site-Specific

More information

CITY OF ST. CA THARINE S. cn- Olc.4 BY-LAW NO. WHEREAS the Council of the Corporation of the City of St. Catharines, is

CITY OF ST. CA THARINE S. cn- Olc.4 BY-LAW NO. WHEREAS the Council of the Corporation of the City of St. Catharines, is ~: ~,,' " CITY OF ST. CA THARINE S BY-LAW NO. cn- Olc.4 A By-law to regulate sanitary and storm drainage. WHEREAS the Council of the Corporation of the City of St. Catharines, is authorized by the provisions

More information

STORMWATER POLLUTION PREVENTION PLAN TEMPLATE. 1.0 SITE DESCRIPTION 1.1 Project Name and Location Date

STORMWATER POLLUTION PREVENTION PLAN TEMPLATE. 1.0 SITE DESCRIPTION 1.1 Project Name and Location Date STORMWATER POLLUTION PREVENTION PLAN TEMPLATE Disclaimer: This template was developed for guidance purposes only in an effort to assist Construction Storm Water permit applicants in meeting state and local

More information

Certificate of Competency (CoC) In Earth Control Measures (ECM) for Construction Site Personnel (37th Run) 19 April 2012

Certificate of Competency (CoC) In Earth Control Measures (ECM) for Construction Site Personnel (37th Run) 19 April 2012 Certificate of Competency (CoC) In Earth Control Measures (ECM) for Construction Site Personnel (37th Run) 19 April 2012 INTRODUCTION Before commencement of construction and earthworks, the site occupier/owner

More information

SECTION 104 PREVENTION, CONTROL, AND ABATEMENT OF EROSION AND WATER POLLUTION

SECTION 104 PREVENTION, CONTROL, AND ABATEMENT OF EROSION AND WATER POLLUTION SECTION 104 PREVENTION, CONTROL, AND ABATEMENT OF EROSION AND WATER POLLUTION 104-1 Description. Provide erosion control measures on the project and in areas outside the right-of-way where work is accomplished

More information

Activity Yes No N/A Notes

Activity Yes No N/A Notes CE 2020 (Rev. 12/11) Page 1 of 5 PROJECT NAME AND SITE ADDRESS: CONTRACT NUMBER: ORACLE NUMBER: WDID NUMBER: CONTRACTOR NAME AND ADDRESS: PROJECT SITE RISK LEVEL: Risk Level 1 Risk Level 2 Risk Level 3

More information

Definition of Tower from the Bradley County Zoning Resolution

Definition of Tower from the Bradley County Zoning Resolution Definition of Tower from the Bradley County Zoning Resolution 43. TOWER. Any outdoor structure designed and constructed to support one (1) or more transmitting or receiving devices for telephone, radio

More information

ENVIRONMENTAL CODE OF PRACTICE FOR CONCRETE BATCH PLANT & ROCK WASHING OPERATIONS

ENVIRONMENTAL CODE OF PRACTICE FOR CONCRETE BATCH PLANT & ROCK WASHING OPERATIONS ENVIRONMENTAL CODE OF PRACTICE FOR CONCRETE BATCH PLANT & ROCK WASHING OPERATIONS PREPARED BY: DEPARTMENT OF ENVIRONMENT AND LANDS INDUSTRIAL ENVIRONMENTAL ENGINEERING DIVISION APRIL 16, 1992 - TABLE OF

More information

Temporary Batch Plants

Temporary Batch Plants Categories EC SE TC WE NS WM Erosion Control Sediment Control Tracking Control Wind Erosion Control Non-Stormwater Management Control Waste Management and Materials Pollution Control Legend: Primary Category

More information

Vehicle Tracking Control (VTC)

Vehicle Tracking Control (VTC) Vehicle Tracking Control (VTC) SM-4 Description Vehicle tracking controls provide stabilized construction site access where vehicles exit the site onto paved public roads. An effective vehicle tracking

More information

Compost-Based Stormwater Best Management Practices Using Compost to Improve Stormwater Management and Erosion Control On Roadsides

Compost-Based Stormwater Best Management Practices Using Compost to Improve Stormwater Management and Erosion Control On Roadsides Compost-Based Stormwater Best Management Practices Using Compost to Improve Stormwater Management and Erosion Control On Roadsides Chris Newman US EPA Region 5 Chicago, IL Compost-Based BMPs Compost-based

More information

Management of Catchment Water Quality Inspection and Rehabilitation of Private Sewers

Management of Catchment Water Quality Inspection and Rehabilitation of Private Sewers Management of Catchment Water Quality Inspection and Rehabilitation of Private Sewers 1 Outline Our Water Resources Managing Catchment Water quailty Plugging Used Water Leaks from Sewers Private Sewer

More information

SUSTAINABLE URBAN DRAINAGE SYSTEMS

SUSTAINABLE URBAN DRAINAGE SYSTEMS overflow can lead into a permeable conveyance system to increase further the benefit and reduce the need for pipe systems. Pollutant removal rates have been shown to be high, with some pollutants being

More information

Florida Department of Environmental Protection

Florida Department of Environmental Protection Florida Department of Environmental Protection Background Mobile vehicle and equipment washing involves washing at a location where vehicles are based (such as a trucking company, warehouse, bus station,

More information

SECTION 5. Sediment Control Measures

SECTION 5. Sediment Control Measures SECTION 5 Sediment Control Measures 60. STORM DRAIN INLET PROTECTION When Runoff from earth change activities will discharge to a catch basin or storm drain inlet. A newly constructed catch basin or storm

More information

THE CORPORATION OF THE CITY OF GUELPH. THEREFORE the council of the Corporation of the City of Guelph enacts as follows:

THE CORPORATION OF THE CITY OF GUELPH. THEREFORE the council of the Corporation of the City of Guelph enacts as follows: THE CORPORATION OF THE CITY OF GUELPH By-law (1993)-14515 A by-law respecting storm water disposal from private property in the City of Guelph, to amend By-law (1987)-12602 and to adopt Municipal Code

More information

City of Beaumont, Texas Grading Permit Information

City of Beaumont, Texas Grading Permit Information General Information City of Beaumont, Texas Grading Permit Information The permit application shall be signed by the property owner (or lessee) or his authorized representative and by the contractor (if

More information

Concrete Waste Management

Concrete Waste Management Categories EC SE TC WE NS WM Erosion Control Sediment Control Tracking Control Wind Erosion Control Non-Stormwater Management Control Waste Management and Materials Pollution Control Legend: Primary Category

More information

Construction Site Inspection. Inspecting to Keep You in Compliance

Construction Site Inspection. Inspecting to Keep You in Compliance Construction Site Inspection Inspecting to Keep You in Compliance Inspection/Monitoring/Reporting Know if your plan is working Document corrective actions Ketchikan A Contractor that destroys their site

More information

Sewerage Management System for Reduction of River Pollution

Sewerage Management System for Reduction of River Pollution Sewerage Management System for Reduction of River Pollution Peter Hartwig Germany Content page: 1 Introduction 1 2 Total emissions 3 3 Discharge from the wastewater treatment plants 4 4 Discharge from

More information

3.4 DRAINAGE PLAN. 3.4.1 Characteristics of Existing Drainages. 3.4.2 Master Drainage System. Section 3: Development Plan BUTTERFIELD SPECIFIC PLAN

3.4 DRAINAGE PLAN. 3.4.1 Characteristics of Existing Drainages. 3.4.2 Master Drainage System. Section 3: Development Plan BUTTERFIELD SPECIFIC PLAN 3.4 DRAINAGE PLAN This section describes the existing onsite drainage characteristics and improvements proposed within this Specific Plan. Following this description, drainage plan development standards

More information

Storm Water Management Requirements for Construction Projects Less than One Acre

Storm Water Management Requirements for Construction Projects Less than One Acre Storm Water Management Requirements for Construction Projects Less than One Acre Purpose: UC Irvine s Phase II Small MS4 Storm Water Permit requires construction projects less than one acre in size to

More information

THE NATURAL RESOURCES AND ENVIRONMENT ORDINANCE (CAP. 84 - LAWS OF SARAWAK, 1958 Ed.)

THE NATURAL RESOURCES AND ENVIRONMENT ORDINANCE (CAP. 84 - LAWS OF SARAWAK, 1958 Ed.) THE NATURAL RESOURCES AND ENVIRONMENT ORDINANCE (CAP. 84 - LAWS OF SARAWAK, 1958 Ed.) THE NATURAL RESOURCES AND ENVIRONMENT (PRESCRIBED ACTIVITIES) ORDER, 1994 (Made under section 11A(1)) (Incorporating

More information

DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS

DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS Phase I MS4 permits require continuous updating of the stormwater system inventory owned and operated by the MS4. They also include inspection

More information

Storm Drain Inlet Protection for Construction Sites (1060)

Storm Drain Inlet Protection for Construction Sites (1060) Storm Drain Inlet Protection for Construction Sites (1060) Wisconsin Department of Natural Resources Conservation Practice Standard I. Definition A temporary device installed in or around a storm drain

More information

Architectural Processing and Inspections for Home Mortgage Insurance

Architectural Processing and Inspections for Home Mortgage Insurance Page 1 of 5 [Text Only] Architectural Processing and Inspections for Home Mortgage Insurance Directive Number: 4145.1 SITE GRADING AND DRAINAGE GUIDELINES Construction complaints and structural defect

More information

SECTION A: LOCAL STORM WATER POLLUTION PREVENTION PLAN

SECTION A: LOCAL STORM WATER POLLUTION PREVENTION PLAN INSTRUCTIONS FOR PREPARING THE LOCAL STORM WATER POLLUTION PREVENTION PLAN City of Hawthorne For sites between 1 and 5 acres As of March 10, 2003, EPA Phase II rules will supercede this document. The Local

More information

Scheduling Maintenance for Infiltration Basins and Trenches

Scheduling Maintenance for Infiltration Basins and Trenches Visual Inspection for Infiltration Practices Visual inspection is a rapid assessment procedure for qualitatively evaluating the functionality of a stormwater best management practice (BMP). Visual inspections

More information

Tree Pits Operation & Maintenance Guide

Tree Pits Operation & Maintenance Guide Tree Pits Operation & Maintenance Guide What are tree pits? Tree pits collect stormwater runoff from small carpark areas or roads. Runoff filters through the tree roots and surrounding soil mix, trapping

More information

London Borough of Waltham Forest LOCAL FLOOD RISK MANAGEMENT STRATEGY. Summary Document

London Borough of Waltham Forest LOCAL FLOOD RISK MANAGEMENT STRATEGY. Summary Document LOCAL FLOOD RISK MANAGEMENT STRATEGY Summary Document October 2013 Local Flood Risk Management Strategy Summary 1 Introduction 2 Partner responsibilities 3 What do we know about flooding in the borough?

More information

Environmental Construction Operations Plan (ECO Plan) Framework

Environmental Construction Operations Plan (ECO Plan) Framework ALBERTA INFRASTRUCTURE AND TRANSPORTATION Environmental Construction Operations Plan (ECO Plan) Framework COPYRIGHT, MAY 2005 THE CROWN IN RIGHT OF THE PROVINCE OF ALBERTA, AS REPRESENTED BY THE MINISTER

More information

Mine Plan of Operations Reclamation Bond Checklist

Mine Plan of Operations Reclamation Bond Checklist Mine Plan of Operations Reclamation Bond Checklist NOTE: This checklist is provided to assist the operator in calculating the engineering and environmental costs required to properly stabilize, reclaim,

More information

Town of Elkton & Cecil Soil Conservation District Checklist for Joint Agency Review Stormwater Management / Erosion and Sediment Control

Town of Elkton & Cecil Soil Conservation District Checklist for Joint Agency Review Stormwater Management / Erosion and Sediment Control Town of Elkton & Cecil Soil Conservation District Checklist for Joint Agency Review Stormwater Management / Erosion and Sediment Control Project Name: Tax Map Parcel: Acreage: Plat: ADC Map & Grid Engineering

More information

Emergency Spillways (Sediment basins)

Emergency Spillways (Sediment basins) Emergency Spillways (Sediment basins) DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short-Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1]

More information

City of Paso Robles Community Development Department Construction Site Storm Water Quality Requirements

City of Paso Robles Community Development Department Construction Site Storm Water Quality Requirements City of Paso Robles Community Development Department Construction Site Storm Water Quality Requirements Overview of the City s Construction Storm Water Program The City of Paso Robles is committed to protecting

More information

STANDARD INSPECTION FORM GENERAL PERMIT FOR STORMWATER ASSOCIATED WITH CONSTRUCTION ACTIVITY

STANDARD INSPECTION FORM GENERAL PERMIT FOR STORMWATER ASSOCIATED WITH CONSTRUCTION ACTIVITY STANDARD INSPECTION FORM GENERAL PERMIT FOR STORMWATER ASSOCIATED WITH CONSTRUCTION ACTIVITY Project Name Permittee NOI # Start Time Inspector s Name(s) Green Card Certification # Inspector s Contact Information

More information

Permeable Pavement Construction Guide

Permeable Pavement Construction Guide Permeable Pavement Construction Guide Permeable pavement at Olympic Park, Waitakere Final Construction result What are permeable pavements? Permeable pavements are hard surface paving systems that reduce

More information

Planning, Health and Environment Division

Planning, Health and Environment Division 18 Planning, Health and Environment Division A Planning Guide to Sustainable Drainage Systems Introduction Working in co-operation with the Environment Agency, Severn Trent Water Ltd., the Highway Authority

More information

SAMPLE COPY. Stormwater Pollution Prevention Plan. A site map must be developed and must contain, at a minimum, the following information:

SAMPLE COPY. Stormwater Pollution Prevention Plan. A site map must be developed and must contain, at a minimum, the following information: Stormwater Pollution Prevention Plan "I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure

More information

Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1

Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1 6 Index inlet protection excavated drop inlet protection (Temporary) 6.50.1 HARDWARE CLOTH AND GRAVEL INLET PROTECTION Block and gravel inlet Protection (Temporary) sod drop inlet protection ROCK DOUGHNUT

More information

CHAPTER 2 CONSTRUCTION STORMWATER POLLUTION PREVENTION

CHAPTER 2 CONSTRUCTION STORMWATER POLLUTION PREVENTION CHAPTER 2 CONSTRUCTION STORMWATER POLLUTION PREVENTION CONTENTS 2.0 INTRODUCTION 2-1 2.1 MIMINUM REQUIREMENT #2 SWPP 2-1 ELEMENT 1: MARK CLEARING LIMITS 2-1 ELEMENT 2: ESTABLISH CONSTRUCTION ACCESS 2-2

More information

A. Describe the existing drainage patterns on-site as shown on Map I, including any potential flooding and erosion problems.

A. Describe the existing drainage patterns on-site as shown on Map I, including any potential flooding and erosion problems. 19. STORMWATER MANAGEMENT A. Describe the existing drainage patterns on-site as shown on Map I, including any potential flooding and erosion problems. The majority of the approximately ±500 acre Property

More information

1.7.0 Floodplain Modification Criteria

1.7.0 Floodplain Modification Criteria 1.7.0 Floodplain Modification Criteria 1.7.1 Introduction These guidelines set out standards for evaluating and processing proposed modifications of the 100- year floodplain with the following objectives:

More information

PRIVATE TREATMENT CONTROL BMP OPERATION AND MAINTENANCE VERIFICATION FORM BIORETENTION FACILITIES, VEGETATED SWALES & HIGHER RATE BIOFILTERS

PRIVATE TREATMENT CONTROL BMP OPERATION AND MAINTENANCE VERIFICATION FORM BIORETENTION FACILITIES, VEGETATED SWALES & HIGHER RATE BIOFILTERS BIORETENTION FACILITIES, VEGETATED SWALES & HIGHER RATE BIOFILTERS Check here for Address or phone number change the fiscal year (July 1 June 30), and date(s) maintenance was performed. Under Inspection,

More information

Massachusetts Department of Environmental Protection Bureau of Resource Protection - Wetlands Program Checklist for Stormwater Report

Massachusetts Department of Environmental Protection Bureau of Resource Protection - Wetlands Program Checklist for Stormwater Report Important: When filling out forms on the computer, use only the tab key to move your cursor - do not use the return key. A. Introduction A Stormwater Report must be submitted with the Notice of Intent

More information

Storm Drain Inlet Protection

Storm Drain Inlet Protection Source: Caltrans Construction Site Best Management Practices Manual, 2003. Description Applications Installation and Implementation Requirements Devices installed at storm drain inlets to detain and/or

More information

CITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES

CITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES CITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES INTRODUCTION What is a Construction Management Plan? The City of Vincent requires careful management of construction involving excavation and retention

More information

Interlocking Concrete Pavement Institute (ICPI) Model Stormwater Ordinance for Permeable Interlocking Concrete Pavements August 2010

Interlocking Concrete Pavement Institute (ICPI) Model Stormwater Ordinance for Permeable Interlocking Concrete Pavements August 2010 Interlocking Concrete Pavement Institute (ICPI) Model Stormwater Ordinance for Permeable Interlocking Concrete Pavements August 2010 Background What are permeable interlocking concrete pavements (PICP)?

More information

Applicable Rules - Air 30 TAC 116.110 Permits All facilities must be authorized by a permit, a standard permit, or a permit by rule. Small mixers unde

Applicable Rules - Air 30 TAC 116.110 Permits All facilities must be authorized by a permit, a standard permit, or a permit by rule. Small mixers unde Concrete Batch Plant Investigations 1 Applicable Rules - Air 30 TAC 116.110 Permits All facilities must be authorized by a permit, a standard permit, or a permit by rule. Small mixers under 5 ft 3 are

More information

Drainage By-law. WM-4 Consolidated April 18, 2011. This by-law is printed under and by authority of the Council of the City of London, Ontario, Canada

Drainage By-law. WM-4 Consolidated April 18, 2011. This by-law is printed under and by authority of the Council of the City of London, Ontario, Canada Drainage By-law WM-4 Consolidated April 18, 2011 This by-law is printed under and by authority of the Council of the City of London, Ontario, Canada Disclaimer: The following consolidation is an electronic

More information

Overview of Singapore s Drainage Management Approach July 2011

Overview of Singapore s Drainage Management Approach July 2011 Overview of Singapore s Drainage Management Approach July 2011 1 Background Singapore is a small Island surrounded by the sea and therefore drainage is affected by tidal conditions. Singapore also has

More information

DRAINAGE :: DRAINAGE CONCERN FREQUENTLY ASKED QUESTIONS

DRAINAGE :: DRAINAGE CONCERN FREQUENTLY ASKED QUESTIONS DRAINAGE :: DRAINAGE CONCERN FREQUENTLY ASKED QUESTIONS The City of DeSoto s Department of Development Services is the point of contact for storm drainage related issues. The following are some frequently

More information

APPLICATION PROCESS FOR LAND DISTURBING PERMIT

APPLICATION PROCESS FOR LAND DISTURBING PERMIT PREFACE: APPLICATION PROCESS FOR LAND DISTURBING PERMIT The property owner, developer and designated planners and engineers shall review the general development plans and detailed plans of the Local Issuing

More information

Environmental Site Inspection Checklist

Environmental Site Inspection Checklist Note : This form is designed for general use and may not be exhaustive. Modifications and additions may be necessary to suit individual projects and to address specific environmental issues and associated

More information

Vehicle Tracking Pad

Vehicle Tracking Pad Stormwater Quality Best Management Practices Construction Sites s When to use: Where construction vehicles leave active construction areas onto surfaces where runoff is not checked by sediment controls

More information

MARICOPA COUNTY ENVIRONMENTAL HEALTH CODE CHAPTER II SEWAGE AND WASTES SECTION 8

MARICOPA COUNTY ENVIRONMENTAL HEALTH CODE CHAPTER II SEWAGE AND WASTES SECTION 8 MARICOPA COUNTY ENVIRONMENTAL HEALTH CODE CHAPTER II SEWAGE AND WASTES SECTION 8 ONSITE WASTEWATER TREATMENT FACILITIES REGULATION 1. Definitions a. Aggregate means a clean graded hard rock, volcanic rock,

More information

Appendix I: BMP Inspection Form CASQA SWPPP Template 91 January2011 BMP INSPECTION REPORT Date and Time of Inspection: Date Report Written: Inspection Type: (Circle one) Weekly Complete Parts I,II,III

More information

Erosion and Sediment Control Guidelines for. Small Sites

Erosion and Sediment Control Guidelines for. Small Sites Erosion and Sediment Control Guidelines for Small Sites Erosion and Sediment Control Guideline for Small Sites Page Contents 1. Introduction 2. Environmental Law and Building Act & Sequence of works 3.

More information

CHAPTER 372-68 WAC WATER POLLUTION CONTROL AND ABATEMENT PLANS FOR SEWAGE DRAINAGE BASINS

CHAPTER 372-68 WAC WATER POLLUTION CONTROL AND ABATEMENT PLANS FOR SEWAGE DRAINAGE BASINS CHAPTER 372-68 WAC WATER POLLUTION CONTROL AND ABATEMENT PLANS FOR SEWAGE DRAINAGE BASINS Last Update: 6/8/88 WAC 372-68-010 Authority. 372-68-020 Purpose. 372-68-030 Definitions. 372-68-040 Planning guide.

More information

REFERENCE. All National Grid personnel who plan and perform work involving protected water resources are responsible for:

REFERENCE. All National Grid personnel who plan and perform work involving protected water resources are responsible for: EG-30NY ENVIRONMENTAL GUIDANCE PAGE 1 of 9 DATE 10/1/10 EP 3 Natural Resource Protection 1.0 SCOPE AND RESPONSIBILITIES National Grid s New York service territory encompasses thousands of wetlands, lakes,

More information

BUILDING SURVEYING 313021

BUILDING SURVEYING 313021 BUILDING SURVEYING 313021 Session topic SUDS - Sustainable Urban Drainage Systems Session objectives To examine various Sustainable Urban Drainage Systems (SUDS) for managing rainwater run-off and discuss

More information

Chapter 2 Stormwater Pollution Prevention Plan (SWPPP) for Park Operations

Chapter 2 Stormwater Pollution Prevention Plan (SWPPP) for Park Operations SWPPP for Park Operations 2 Chapter 2 Stormwater Pollution Prevention Plan (SWPPP) for Park Operations Bordered by Lake Washington & Lake Sammamish, the City of Bellevue has more than 60 miles of streams,

More information

General Insurance - Domestic Insurance - Home Contents Storm water damage policy exclusion flood damage

General Insurance - Domestic Insurance - Home Contents Storm water damage policy exclusion flood damage Determination Case number: 227307 General Insurance - Domestic Insurance - Home Contents Storm water damage policy exclusion flood damage 4 April 2011 Background 1. The Applicants insured their home contents

More information

Sydney Port Botany Terminal 3 Project Water Resource Management Plan

Sydney Port Botany Terminal 3 Project Water Resource Management Plan Civil Works Construction Contract Phase 1 1/8 Terms and Definitions The following terms, abbreviations and definitions are used in this plan: Terms Explanation SPBT3 Sydney Port Botany Terminal 3 CEMP

More information

3. Given the geographic extent of the area, amendments have been made to the following regional planning documents

3. Given the geographic extent of the area, amendments have been made to the following regional planning documents AMENDMENTS TO THE REGIONAL PLANS RELATING TO LAND REPAIR ON EARTHQUAKE DAMAGED RESIDENTIAL LAND UNDER s27 OF THE CANTERBURY EARTHQUAKE RECOVERY ACT 2011 1. This memorandum outlines the specific changes

More information

Best Practice Environmental Management. Environmental Guidelines for Major Construction Sites

Best Practice Environmental Management. Environmental Guidelines for Major Construction Sites Best Practice Environmental Management Environmental Guidelines for Major Construction Sites Environmental Guidelines for Major Construction Sites Environment Protection Authority 477 Collins Street, Melbourne

More information

DOÑA ANA COUNTY DESIGN STORM CRITERIA GUIDELINES FOR COMMERCIAL AND RESIDENTIAL SITES. Run-off Analysis Methods

DOÑA ANA COUNTY DESIGN STORM CRITERIA GUIDELINES FOR COMMERCIAL AND RESIDENTIAL SITES. Run-off Analysis Methods DOÑA ANA COUNTY DESIGN STORM CRITERIA GUIDELINES FOR COMMERCIAL AND RESIDENTIAL SITES Run-off Analysis Methods This document sets forth the minimum design, technical criteria and specifications for the

More information

Block and Gravel Inlet Protection (BIP)

Block and Gravel Inlet Protection (BIP) Block and Gravel Inlet Protection (BIP) Practice Description Block and gravel inlet protection is a sediment control barrier formed around a storm drain inlet by the use of standard concrete block and

More information

Drainage. Information for those with problem drains

Drainage. Information for those with problem drains Drainage Information for those with problem drains Contents 1 Purpose 2 Introduction 2 Explanations: what is a drain and what is a sewer 3 Explanation of the responsibilities for public and private sewers

More information

Beseck Switching Station Inspection

Beseck Switching Station Inspection Page 1 of 5 Docket No. 272 Development and Management Plan Inspection The Connecticut Light and Power Company Certificate of Environmental Compatibility and Public Need for the construction of a new 345-kV

More information

Storm Drain Inlet Protection for Construction Sites (1060)

Storm Drain Inlet Protection for Construction Sites (1060) Storm Drain Inlet Protection for Construction Sites (1060) Wisconsin Department of Natural Resources Conservation Practice Standard I. Definition A temporary device installed in or around a storm drain

More information

To prevent increased stormwater runoff entering Council s drainage system and causing overloading of the system that in turn might cause flooding.

To prevent increased stormwater runoff entering Council s drainage system and causing overloading of the system that in turn might cause flooding. Background & Issues To provide guidelines and requirements for Developers, the Community and the Shire s Planning and Sustainability officers for connection to the Shire s Stormwater Drainage Disposal

More information

Pollution Control NEW! NEW! Stormwater Attenuation Systems Sustainable Urban Drainage Solutions for Domestic & Commercial Applications. klargester.

Pollution Control NEW! NEW! Stormwater Attenuation Systems Sustainable Urban Drainage Solutions for Domestic & Commercial Applications. klargester. Pollution Control NEW! NEW! Stormwater Attenuation Systems Sustainable Urban Drainage Solutions for Domestic & Commercial Applications klargester.com Stormwater Attenuation Systems Sustainable Urban Drainage

More information

SECTION ELEVEN: ACTIVITIES REQUIRING A CERTIFIED EROSION AND SEDIMENT CONTROL PLAN 1

SECTION ELEVEN: ACTIVITIES REQUIRING A CERTIFIED EROSION AND SEDIMENT CONTROL PLAN 1 SECTION ELEVEN: ACTIVITIES REQUIRING A CERTIFIED EROSION AND SEDIMENT CONTROL PLAN 1 An application for approval of a soil erosion and sediment control plan in accordance with these regulations shall be

More information

Preventing Storm Water Pollution: What We Can Do

Preventing Storm Water Pollution: What We Can Do Preventing Storm Water Pollution: What We Can Do ~Employee Training Series~ Streets and Drainage Maintenance PREPARED IN COOPERATION WITH THE Texas Commission on Environmental Quality AND U.S. ENVIRONMENTAL

More information

Guidelines for. Permeable Pavement

Guidelines for. Permeable Pavement What is permeable pavement? Guidelines for Permeable Pavement When rainwater falls on conventional pavement, such as concrete, it accumulates and then flows across and off of this impervious surface as

More information

Outdoor Storage of Raw Materials SC-33

Outdoor Storage of Raw Materials SC-33 Objectives Cover Contain Educate Reduce/Minimize Description Raw materials, by-products, finished products, containers, and material storage areas exposed to rain and/or runoff can pollute stormwater.

More information

CHAPTER 17. Sewers and Sewage

CHAPTER 17. Sewers and Sewage Sec. 17-1. Industrial Wastes in Rivers and Streams; Treatment. Sec. 17-4. Discharging Water or Waste Onto Sidewalks. CHAPTER 17. SEWERS AND SEWAGE ARTICLE 1 GENERALLY Sec. 17-1. Industrial Wastes in Rivers

More information

Creating the environment for business

Creating the environment for business 1. Introduction 1.1 Introduction to Water Cycle Strategies (WCS) 1.1.1 Background The water cycle describes the pathways and processes through which water moves through the natural and built environment,

More information

Environmental Guidelines for Preparation of an Environmental Management Plan

Environmental Guidelines for Preparation of an Environmental Management Plan 2013 Environmental Guidelines for Preparation of an Environmental Management Plan Environmental Management Division Environmental Protection Agency 3/13/2013 ENVIRONMENTAL GUIDELINES FOR PREPARATION OF

More information

BMP-7. A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet.

BMP-7. A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet. BMP-7 BMP: STORM DRAIN INLET PROTECTION Definition A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet. To prevent sediment from entering storm drainage systems

More information

Sustainable Drainage Systems (SUDS) A guide for developers

Sustainable Drainage Systems (SUDS) A guide for developers Sustainable Drainage Systems (SUDS) A guide for developers We are the Environment Agency. It s our job to look after your environment and make it a better place for you, and for future generations. Your

More information

Quick Guide to Application for Clearance for Drainage Works for issuance of Certificate of Statutory Completion (CSC) Minor Project

Quick Guide to Application for Clearance for Drainage Works for issuance of Certificate of Statutory Completion (CSC) Minor Project Quick Guide to Application for Clearance for Drainage Works for issuance of Certificate of Statutory Completion (CSC) Minor Project DOCUMENTS TO BE SUBMITTED FOR CSC All "As-built" or "As-constructed"

More information

INFORMATION SHEET ORDER NO. R5-2011-XXXX TRIANGLE ROCK PRODUCTS, INC. FLORIN ROAD AGGREGATE PLANT SACRAMENTO COUNTY

INFORMATION SHEET ORDER NO. R5-2011-XXXX TRIANGLE ROCK PRODUCTS, INC. FLORIN ROAD AGGREGATE PLANT SACRAMENTO COUNTY ORDER NO. R5-2011-XXXX INFORMATION SHEET Background Triangle Rock, Inc. (Discharger) submitted a Report of Waste Discharge (RWD) on 23 August 2010. The Discharger is expanding the mining operations at

More information

CITY OF HIGHLAND PARK, ILLINOIS Stormwater Management Fact Sheet

CITY OF HIGHLAND PARK, ILLINOIS Stormwater Management Fact Sheet CITY OF HIGHLAND PARK, ILLINOIS Stormwater Management Fact Sheet WHAT IS STORMWATER MANAGEMENT? Stormwater management is the method for channeling rainfall through pipes and sewers away from property to

More information

BEST MANAGEMENT PRACTICES (BMPs)... What are They? GOOD HOUSEKEEPING PRACTICES Your Business Should Employ

BEST MANAGEMENT PRACTICES (BMPs)... What are They? GOOD HOUSEKEEPING PRACTICES Your Business Should Employ BEST MANAGEMENT PRACTICES (BMPs)... What are They? CLEAN STREETS MEAN CLEAN STREAMS Inexpensive to implement and easy to use, BMPs help you to do your share to protect the environment. The term Best Management

More information

SCHEDULE 2 TO THE DEVELOPMENT PLAN OVERLAY Shown on the planning scheme map as DPO2 WAVERLEY GOLF COURSE, LYSTERFIELD VALLEY

SCHEDULE 2 TO THE DEVELOPMENT PLAN OVERLAY Shown on the planning scheme map as DPO2 WAVERLEY GOLF COURSE, LYSTERFIELD VALLEY SCHEDULE 2 TO THE DEVELOPMENT PLAN OVERLAY Shown on the planning scheme map as DPO2 WAVERLEY GOLF COURSE, LYSTERFIELD VALLEY 1.0 Conditions and requirements for permits A permit to use and develop the

More information