HOUSES OF THE OIREACHTAS SERVICE

Size: px
Start display at page:

Download "HOUSES OF THE OIREACHTAS SERVICE"

Transcription

1 February 2013 HOUSES OF THE OIREACHTAS SERVICE Guidelines on Project Management

2 Page 1 of 18

3 Quick Reference Key Principles of Project Management 1. Definition A project delivers something new that is distinct from the routine work of the Service. Projects are clearly defined and time-bound and have specific staff and financial resources assigned. 2. General Requirements Projects must be founded in and consistent with the Service s strategies, plans and policies and they must comply with the Service s and with public service standard guidelines, rules and procedures. All relevant expertise that is necessary to conduct a project should be availed of and training should be provided to equip personnel with appropriate skills and knowledge. Project Management training will be provided by the Service on request. No activity in the nature of a project should be undertaken without due regard to the Project Management Guidelines set out in Office Notice 1 of Governance Framework: Project Roles, Phases and Requirements Every project should have persons at appropriate levels assigned to the following roles: Approver (at the appropriate level as set out in Office Notice 1/2011 or any subsequent notice setting out the Service s financial authority procedures e.g. at MAC, Assistant Secretary level, Commission Finance Committee, Commission). Sponsor (e.g. Assistant Secretary, Clerk of the Seanad, PO reporting to MAC or to MAC Sub Committee). Project Board (chaired, depending on scale and/or impact, by an Assistant Secretary, the Clerk of the Seanad or PO/AP other than the sponsor). Project Manager (designated manager or line manager reporting to project board guides the project through the process. Either accomplishes the task or ensures others accomplish the task.) Project Team (staff delivering the project under direction of project manager). Project Stakeholders (users and other interested and potential parties, including all of the above). External Reviewer (where considered necessary by the approver). Every project goes through the following main project phases within its life cycle. See Appendix 1: Project Governance Framework Diagram. INITIATION --> PLANNING --> IMPLEMENTATION --> CONTROLLING -->CONCLUSION These phases should be applied rigorously in the case of large projects. In the case of medium projects all five project management phases should be implemented but with a reduced level of documentation and formality. In the case of small projects a three phase process (combining some of the phases) can be used. Specific Requirements A project must: Be consultative by creating an environment in which staff and stakeholders can contribute. Be approved on the basis of a clear and comprehensive Phase 1 and Phase 2 Business Case. Be recorded on the Service s Projects Register. Identify the benefits to be achieved and how they will be measured. Be described and documented in a formal project plan. Be subject to risk assessment and critical path analysis that are kept under review and recorded to the Service s Risks Register Database. Have governance structures with project roles assigned and project phases defined. Have any change in scope, budget, timeline formally recognised, signed off and communicated. Have proper project records of decisions, meetings and events available for review. Be subject to financial control and monitoring and reporting of progress in delivery. Provide for timely and appropriate internal and external reviews during and after. Be formally signed off and reported on completion to confirm its purpose is achieved. Be subject to a formal post-project assessment of benefits and outcomes realisation. Page 2 of 18

4 Checklist: Service Guidelines on Project Management Activity or Deliverable Yes Partly No Comment Project Initiation Consult (Finance Officer, ICT, Procurement, staff at all levels and other stakeholders, as applicable) Business Case Phase:1 Approval in Principle (Purpose, Strategic Fit, Timescale/Priority, Benefits, Impacts, Interdependencies, Risks, Budget, Resources). Office Notice 1/2011refers Business Case Phase:2 Approval to Proceed (MAC, Assistant Secretary, Commission, other. Office Notice 01/2011 refers. Project Planning Project Plan (Scope, Roles, Structures, Systems, Procedures, Timescales, Tolerance Levels, Deliverables, Risk Assessment, Critical Path Analysis, Communications ) Project Implementation Governance Controls (Governance: Roles, structures, systems, and procedures observed and maintained. Issues Management. Project Team meetings and Project Board meetings held) Review of Progress & Continued Validity (Milestones and Deliverables) (Formal Internal Review Meetings) Project Control Control (Change Control, Project Records, Project Code, Expenditure Control, Interim Review& Monitoring ) Project Conclusion/Closure Closure (Delivered, piloted if applicable, Sign-Off Procedures, Post Project Assessment, Closure Report, Benefits Realisation Assessment, close risks) Compliance, where applicable Service Procurement Policy, Government & EU Public Procurement Procedures requirements met. Service and Public Expenditure Standards Rules and Procedures followed. Audit and risk management requirements met. ICT and consultancy guidelines followed. Training & Specialist Expertise, if applicable Training (Training needs of project personnel, identified and met) Specialist Expertise (Specialist Expertise needs identified, sourced and provided) Page 3 of 18

5 1. Introduction These guidelines are for staff of the Houses of the Oireachtas Service who are involved in the management of projects. The guidelines include general requirements (section 2 below) and a governance framework (section 3 below) for managing projects. These Guidelines supersede Office Notice 04/2008. A quick-reference summary of key project management principles is provided at the beginning of these guidelines and a project governance framework diagram is provided at Appendix 1. Training in project management will be organised on request to supplement these guidelines. 1.1 Purpose of the Guidelines: The purpose of the guidelines is to provide a common-sense toolkit to enable staff to deliver the proper and efficient use of the resources of the Commission and to ensure that projects in the Service are undertaken and managed in accordance with applicable public service rules and policies and with generally accepted best practice. 1.2 Definition of a Project: A project is an activity that requires the allocation of a budget and/or dedicated staff resources for a clearly defined and approved purpose and that brings beneficial change or added value. A project is therefore something that is distinct from the routine work of the Service and that is: new - i.e. it delivers a new product, system, process or other outcome that directly furthers stated business objectives of the Service in an obvious and defined way; defined clearly - i.e. it is clear what exactly is to be achieved, what are the critical stages along the way, what will measure whether it is working or not, what the finished product will look like and what exactly the benefits expected from that product will be; time bound - i.e. it has specified start and finish dates - if a project doesn t finish by the planned date, this must be accounted for; resourced with a specific budget and/or staff, the amount of which should be estimated at the start and kept under constant review - if a project exceeds its budget there must be a clear and accepted justification for this. 2. General Requirements The following are the high level requirements to be observed in undertaking projects within the Service. 2.1 Strategic and Policy Fit Projects should contribute directly to the delivery of the strategic commitments of the Commission as set out in its Strategic Plan and they should be consistent with the policies and corporate business plans of the Houses of the Oireachtas Service. 2.2 Public Service Standard Rules & Procedures Regard should be had to the applicable requirements of the law and of regulations, guidelines and indicators of best practice in the public service, including those in respect of expenditure, audit and risk, procurement, value for money, ICT projects and Business Continuity Plans. Page 4 of 18

6 Many of the requirements regarding are set out in the Blue Book on Public Financial Procedures, and in the Service s Financial Governance Handbook (Nov 2011) and in Office Notice 1/2011. Staff must ensure that they fulfil the requirements that are set out in Office Notice 1/2011 when seeking approval/sanction for new items of expenditure. Any queries in relation to the exercise of financial authority should be address to the Service s Finance and Management Information Unit The Department of Public Expenditure & Reform s The Public Spending Code, Expenditure Planning, Appraisal & Evaluation in the Irish Public Service (July 2012) brings together in one place details of the obligations that those responsible for spending public money are obliged to adhere to, as well as guidance material on how to comply with the obligations outlined. Link: Elements of the Public Spending Code apply to any project that: may incur expenditure in the near future (Initiation, Planning); is currently incurring expenditure (Management, Monitoring, Evaluation); has incurred expenditure in the recent past (Review, Evaluation). Managers of projects must comply, as appropriate, with the relevant requirements of the Code. 2.3 Procurement Where projects involve the procurement of goods or services, including incidental or indirect procurements, Service policy and applicable Government and EU public procurement procedures should be implemented rigorously. Many of these are set out in the Procurement Guidance for Staff booklet issued by the Procurement Unit in November 2010 and in the Service s Financial Governance Handbook that are available in the Discussion Database. If there is any doubt as to the procedures to apply in a given situation, the Procurement Officer should be consulted. A submission must be sent to the Oireachtas Service Contracts Committee (OCC) where: A. it is proposed for exceptional reasons not to have a competitive process (where the contract value is in excess of 25,000 exclusive of VAT), B. only one tender was received in response to an advertisement or invitation to tender, or C. it is proposed not to accept the lowest priced tender (where the contract value is in excess of 65,000 exclusive of VAT). The OCC will examine and quality assure the tendering procedure used, based on the documentation provided, and ensure that as far as possible, it was carried out in an open, objective and transparent manner. Additional requirements for IT and telecommunications expenditure on projects in the public sector are set out in Department of Public Expenditure & Reform Circulars 2/09 and 2/11. Guidance regarding the Management of Risk are set out in the Department of Public Expenditure and Review (D/PER) Risk Management Guidance for Government Departments and Offices (2004). Page 5 of 18

7 2.4 Specialist Expertise Different types of expertise will typically be required at different stages of a project (e.g. procurement expertise; including RFT design expertise; legal advice on contracts; financial advice on budgeting and calculating cost benefits or technical advice). The sources of expertise and practical experience available both formally and informally in the Service in the areas of law, procurement, ICT, finance and project management should be availed of, accordingly. Where a project requires specialist expertise that is not available from within the Service, it should be sought in the wider public service or procured from outside. DPER s Public Spending Code (2012) and Guidelines for Engagement of Consultants and other External Support by the Civil Service (2006) sets out best practice principles and guidance on the engagement and management of external consultants in the Civil Service. Evidence of the basis for selection of expert advisers should be contained on file and full attendance by external advisers at Project Board meetings should be required. The time spent by external advisors at meetings should be documented for expenditure monitoring and control purposes. In addition, terms of engagement should be completed to set out the role and responsibilities of external advisers. This should be agreed at the start of the project and address matters including the requirement to attend meetings. 2.5 Training Training that sets out in more detail the specific requirements in areas such as project plans, methodologies and checklists for project sponsors, managers and approvers to ensure that projects in the Service are properly managed will be made available, on request, to those involved in projects. Project management training needs should be identified by staff in their annual PMDS Learning & Development Plans. Any additional training requirements for staff involved in individual projects should also be incorporated as necessary in project plans and provided, accordingly, as part of each project. 3. Governance Framework The MAC is the strategic oversight, advisory and co-ordinating management board of the Houses of the Oireachtas Service. The reviewing and deciding on proposals for projects, new policies or investments for the Service in accordance with the provisions of Office Notices 1/2011 and 1/2013 is a function of the MAC as set out in the MAC Charter (revised June 2011). The relevant sub-committee of MAC shall consider business cases for project proposals as are referred to it by the Secretary General/MAC. The following governance measures and structures are necessary to ensure that projects are well structured and managed in accordance with best practice and can thus lead to successful outcomes for the Service and the Commission. 3.1 Project Roles Every project should have persons at appropriate levels assigned to the following roles, identified in the business case for approval of the project and incorporated in the project plan: Approver (at the appropriate level as set out in Office Notice 1/2011 or any subsequent notice setting out the Service s financial authority procedures e.g. at Management Advisory Committee, Assistant Secretary level). Sponsor (e.g. Assistant Secretary, Clerk of the Seanad, PO reporting to MAC or to MAC Sub Committee). Page 6 of 18

8 Project Board (chaired, depending on scale, by an Assistant Secretary, the Clerk of the Seanad or PO/AP other than the sponsor). Project Manager (designated manager or line manager reporting to project board guides the project through the process. Either accomplishes the task or ensures others accomplish the task.) Project Team (staff delivering the project under direction of project manager). Project Stakeholders (users and other interested and potential parties, including all of the above). External Reviewer (where considered necessary by the approver). Each of the project roles has a purpose and no project should unfold without the roles being formally designated. Training will made available on request to equip staff with the knowledge and skills necessary to fulfil their project roles. Where appropriate, training for project personnel should also be incorporated within individual projects. Reporting of large projects should be at an appropriate level and should not involve an undue level of administrative burden for the Project Board and Project Manager. In the case of projects that are large in either value or significance to the Service, it is recommended that the Project Board should include a member at Senior Management level in the Oireachtas Service (i.e. above PO level for Project Management Guidelines purposes). The following factors should be considered together when determining the overall requirement of Senior Management membership above PO level on a Project Board. The project cost (Appendix B, New Items of Expenditure, Cir 1/2011 refers). The level of Service resources, including staff required. Is the project a capital project valued at above 0.5m? Is the project an ICT/ ICT dependent project valued at above 250,000? Is there a high risk assessment score attached to the project. The stakeholders impacted by the project (e.g. cross-functional business areas, Members, Commission, external, potential). The complexity of the project. 3.2 Project Phases Every project goes through five main phases within its life cycle. Each phase, together with the tasks and activities that are typically associated with it, is described briefly further below and illustrated in Appendix 1. Project Governance Framework Diagram. INITIATION --> PLANNING --> IMPLEMENTATION --> CONTROLLING -->CONCLUSION Projects can be classified based on their size and complexity so that small and straightforward projects are implemented using simple and straightforward processes. Larger and more complex projects will use the fully defined process. In short, the project framework should be tailored to cater for the size and complexity of the project. Large Projects Projects that are strategically important, large cost, high risk or long duration will need formal and rigorous processes to ensure success. For these projects, all of the elements of the Guidelines on Project Management should be implemented in full, including all five project phases. Page 7 of 18

9 Medium Projects Other projects that may be large in size, but with less strategic importance or a lower risk profile, then all five phases should be implemented, but with a reduced level of documentation and formality. A Project Board should be considered. Small Projects Projects with low risk, low cost and shorter durations will require a less formal and less rigorous approach. For small projects, the recommendation is to combine some of the phases so that a three phase process is used (i.e. Initiate Plan, Implement Control, Conclude) with a reduced set of project records and outputs. The Project Sponsor and Project Manager may function as the Project Board. INITIATION APPRAISAL BEFORE EXPENDITURE IS INCURRED The Service s business case appraisal process is a two phased process, with Phase 1 aiming to establish whether, at face value, a sufficient case exists for considering a proposal in more depth. It leads to a recommendation on whether or not to proceed to the detailed appraisal stage, which can often be a costly exercise. Sanction/Approval requirements for new items of expenditure should be strictly adhered to. The Service Financial Governance Handbook, Office Notice 1/2011 and the D/PER Public Spending Code (2012) currently refer. Business Case: Phase 1 Request for Approval in Principle The Phase 1 Business Case submitted for approval should contain a full and clear definition of the resource commitments, including staff resources, for all projects. Staffing and other current costs arising must be consistent with the Service s policy on staffing and be consistent with the staffing levels approved in the Annual Resource Plan for the Service. The Business Case Proposal must outline cross-directorate relationships and inter-dependencies that may affect the project. The impact of the project on the work, processes and outcomes of other business areas must be discussed and any issues resolved with the relevant individuals and sections. The project management team should create an environment in which staff at all levels and other stakeholders who have experience, skills and knowledge of the project area can contribute appropriately to the project development. The ICT Unit must be consulted before putting forward a business case that involves any ICT dependency or that may impact on the Service s Business Continuity Plan, however incidental. The Business Continuity Plan for the relevant Sections should be amended to reflect any changes necessary as a result of the project s implementation. The Section Head(s) responsible should be notified of the amendments made. Where goods or services are to be purchased, the business case should also set out a procurement strategy for the project. Refer to: Procurement Guidance for Oireachtas Staff (Nov 2010); Public Procurement Guidelines ICT Procurement Frameworks ictprocurement.gov.ie for guidance. It is not envisaged that a Phase 1 approval would be valid for more than six months, unless there is a bona fide reason for the delay. Page 8 of 18

10 Business Case Phase 2: Request for Approval to Proceed with Project The detailed Phase 2 Business Case appraisal aims to provide a basis for decision on whether or not to give sanction to proceed with the project. It includes the clarification of the objectives, risks, impacts, exploration of options and quantification of costs and benefits. Cost Benefit Analysis: The costs of a project versus the expected benefits to be realised (and how they will be measured) should be set out in the business case. Where savings or increased outputs or efficiencies are expected to result, these should be quantified with reference to current costs/outputs etc. Sponsors and approvers should review with caution any project proposals where the benefits to be realised cannot be clearly identified. In particular, projects involving both significant innovation and a significant degree of risk should be subject to additional and rigorous monitoring and control throughout. Budget and Financial Authority: Projects should be undertaken in accordance with the applicable authorisation limits and rules in respect of official expenditure (currently Service s Finance Governance Handbook (Sept 2011), Office Notice 1/2011 and D/PER Public Spending Code (2012) currently refer). The budget should, for this purpose, include the full cost of all resources, including staff. The fact that a budget allocation may exist for a particular project in any given year does not mean that there is authority to commence the project without a business case and formal financial approval. All new approved projects should be reported to the OCSG by to declan.bale@oir.ie to be recorded to the Service s Register of Projects. Any potential impact of projects on the Service s Business Continuity Plan should be communicated immediately to the relevant person in charge of the Plan. PLANNING Project Plan: Every project, however small, should be governed by a project plan agreed by the Project Board or its equivalent and setting out the scope, roles, structures, systems, procedures, stages, timescales and deliverables of the project. The project plan should reflect the rationale as set out at the initiation stage (purpose, benefits, budget, resources), it should clearly convey what the project is for and identify its boundaries in terms of what it will and will not cover. The project plan should also include a communications plan and specify project tolerance levels, if any. A critical path analysis and a risk assessment should also be included. Communications Plan: The management of expectations amongst stakeholders and potential stakeholders is a key role of the Project Manager. Regular and open communication is essential where the project will impact on roles, responsibilities and/or work practices. The Project Plan should include a communications plan that includes a list of proposed communication activities associated with events and stakeholders, including the sponsor, project board, project team, ICT and external consultants as required. Forms of communication could include presentations to staff or members, ed newsletters, the development of a project website/shared documentation database etc. Budget, Scope and Time Tolerance Levels: Project tolerances, if granted, define the range within which the Project Manager can make decisions regarding the project plan s budget, scope and timelines without the Project Manager having to get approval from (or consult with) the Project Sponsor or Project Board. By defining tolerances, the Project Manager has the scope to make timely decisions regarding small deviations to the project plan and has clear criteria to make decisions on when it is necessary to submit changes to the Project Board for approval. Cost tolerance amounts should not be regarded by Project Managers as a blank cheque. Expenditure based on cost tolerance Page 9 of 18

11 amounts should comply with normal financial and procurement procedures including the sanction/approval requirements for new items of expenditure (Office Notice 1/2011 refers). Critical Path Analysis: This involves identifying time-critical tasks during implementation of the project, i.e. what must happen and by when for the project to remain on target. These are the tasks that, if delayed, will delay the entire project. It is, therefore, essential that this critical path, or schedule of project milestones and their expected achievement dates, be set out from the start in a formal (though simple) way in the project plan, approved by the Project Board or its equivalent and reviewed and updated regularly as the project unfolds. Without this, it will not be possible for those involved in a project to recognise whether or not it is achieving its milestone targets on time and is on track for completion. Risk Assessment: Risks are the things that can go wrong in projects. All projects involve some level of risk and failure to deal adequately with risks can have serious consequences, leading ultimately to project failure. The Houses of the Oireachtas Service s Risk Management Policy (Managing for Results) (Dec 2011) and the Department of Public Expenditure and Review (D/PER) Risk Management Guidance for Government Departments and Offices (2004) should be consulted when putting project risk management mechanism in place. Identified project risks should feed into the Service s business areas and organisation-wide risk management structures e.g. sections risk action plans, risk register database, risk materialisation reports. The overall feasibility of the project strategy should be tested in order to mitigate the risk of failure. In this regard, the importance of comprehensive pilot testing should not be overlooked. Obvious risks include cost overruns, purpose becoming unachievable or benefits unrealisable, delays and unforeseen (e.g. industrial relations or legal) difficulties. Other less obvious or projectspecific risks will need to be assessed in each case. Consideration of fraud risks should be part of any new project or service initiative. Identification of fraud risks and fraud prevention and detection measures and appropriate controls should be considered as a standard requirement. The key to dealing with risks is to anticipate them as far as possible and, when they arise, to address them in such a way as to minimise their effect on the progress and outcome of the project. To achieve this, risks need to be: identified and classified (what can go wrong Strategic, Environmental, Operational, Financial, Reputational, Procedural Core Business, Security, Legislative, other e.g. legal, risks); assessed (in terms of likelihood and significance); mitigate (accept, reduce, avoid, transfer); monitoring (constant monitoring and reassessed during lifetime of project) reporting: (report any perceived risks and failures of controls promptly including on risk register and risk materialisation reports. Any emerging new risk should never be ignored or denied - it should be declared by the Project Manager and dealt with up front even if this requires suspending the project while the problem is being investigated. Identified risks should be entered onto the Service s Risk Register Database. Page 10 of 18

12 Project Management Techniques: Training will be organised, on request, to staff involved in projects in the use of appropriate tools and methodologies, including IT software products, for planning and managing projects, for assessing risks and for carrying out critical path analysis. ICT Unit has a limited number of project management software licences that give access to project management tools, tables, templates and methodologies. These will be issued to project managers following confirmation of the requirement by a PO or Section Head with an indication of how long the licence will be required. IMPLEMENTATION Governance: Project managers and boards should ensure that the roles, structures, systems and procedures set out in the project plan are maintained during the project. Regular formal reviews should be provided and held to assess how the project is progressing against its original objectives, whether the purpose and/or project plan need to be revised and whether any remedial actions, including reconsideration of the viability of the project, are necessary. Issue Management: The Project Manager should define how issues will be managed and escalated during the project and ensure that the project team and board understand what the ground rules are. In general, the project team should know to advise the Project Manager of issues as soon as they arise do not wait for the next formal meeting. Issues must be resolved quickly and effectively. Project Managers should enter the issue into an issues log; determine who needs to be involved in its resolution; identify any potential costs; decide on action to be taken; track resolution of action points and communicate status to relevant personnel through methods established in the project s communication plan. CONTROLLING Change Control: Project Managers, Project Sponsors and Project Boards should maintain constant vigilance to ensure that, where there is any change, outside of specified tolerance levels, in the scope, cost or duration of a project, this is done by a formal change to the project plan that is signed off by the Project Board and the Project Approver before proceeding with the change. This is necessary to avoid drift in the scope, cost and duration of projects. Changes to the project scope, budget or duration should be managed by way of an exception report submitted by the Project Manager to the Project Board. Exception reports should inform the Project Board of the situation, and offer options and recommendations on the way to proceed. The exception report should include an assessment of the impact of the change on the approved business case, including costs. Exception reports must be resolved quickly and effectively and the decision to accept or reject the change resulting from the exception report should be communicated immediately to the appropriate personnel (e.g. Project Manager and Team, ICT/ Business Continuity Plan, external consultant, affected business areas, Finance Unit, MAC/subcommittee, Commission, as appropriate). To ensure that changes are monitored through to completion, a Change Log should be maintained by the Project Manager. This allows the Project Manager to identify any outstanding changes and to measure the actual impact of each change once implemented. It also ensures that a history of all changes is available later in the project. Page 11 of 18

13 If the change adopted affects any existing risk recorded or creates a new risk, this should be reflected on the Risk Register Database and if relevant, notified to the owner of the Business Continuity Plan. Project Records: An internal or external auditor or any senior manager accountable for a project will always be entitled to look for project records which should, therefore, be kept to a high standard in anticipation of such requests. A proper paper trail should, therefore, be kept for audit/accountability purposes as per Office Notice 1/2011. This means that immediately available and organised records should be maintained at all times covering the entire project history, including approval, planning, procurement, budget and expenditure control, minutes of project board meetings and all decisions made and significant events, including appropriate references to detailed information, occurring at Project Board, Project Manager and Project Team level. Project files should contain signed copies of Project Board minutes. Appropriate resources and training should be made available to ensure the maintenance of high standard project records. Control of Expenditure: Project Managers should forward the confirmation of the approval of the project business case expenditure (Office Notice 1/2011 currently refers) and details of the master budget, from which the project budget is being drawn, to the Finance Unit. The Finance Unit will record the approved budget in Integra, allocate a project code to the project and notify the Project Manager of the project code. It is the responsibility of the Project Manager to ensure the full and proper use of this coding by all involved. The Integra system will record a running total of the project budget spend and balance. The Project Manager should notify the Finance Unit of any cuts or additional costs approved by the Project Board. If the costs fall below or above budget tolerance levels, then the Project Manager should immediately inform the Project Board and Sponsor and other relevant stakeholders (e.g. Finance Unit, Assistant Secretary). Where budget tolerances are exceeded, the project should be referred to the appropriate management authority for further funding approval and review. The Project Manager should notify the Finance Unit when the final project payment is made. Interim Reviews and Monitoring of Progress: Project plans should include provision for effective and continuous reporting and monitoring within the project and, where appropriate, for independent external peer review. The Peer Review Process is a central initiative following a Government decision in The process is applied to major ICT projects in the public sector. Peer reviews provide assurance that a project can progress successfully to the next stage. Reviews are carried out at key decision points of a project. While it is unlikely that the Service will be engaged in many projects large enough to require such external review, peer review within the Service should be considered and implemented as a measure of best practice for large projects. Clear guidance in relation to peer review, templates and checklists are available on the Peer Review Process in the Public Sector website Regular reports should be submitted to the Project Board or its equivalent to ensure that project milestones are being met and expenditure is within budget. If adverse developments occur, such as cost overruns or delays, the progress reports should include recommendations to address the situation, including where warranted, the option of project termination. Page 12 of 18

14 CONCLUSION/ PROJECT CLOSURE Project Delivery: The Project Manager should ensure that all of the items in the Project Scope are successfully delivered at the end of the project. Pilot Project: Where appropriate, the project should undergo a period of testing of the new processes, systems or programme before they are put to productive use. The purpose of a pilot project is to test whether the system is working as it was designed while limiting business exposure. All projects that involve data processing (this may also apply to other areas) should be tested in a non-live environment (i.e. they should not interface with live systems). Pre-live testing should include personnel not involved in development Such tests should be carefully planned and results documented for review before going live to assure that the new system is robust. Sign-off Procedures: To ensure that projects are completed in a proper and formal manner, the end of each project must be formally signalled by a signing-off by the Sponsor to the effect that the completed project addresses the business need identified in the Business Case and that the project was delivered to the required specification, within budget and on time. The OCSG should be notified of the project closure to be record in the Projects Register. Post-Project Evaluation and Benefits Realisation: Within an appropriate period following completion of a project, a closure report should be prepared and submitted to the Sponsor setting out the extent to which the project has achieved its intended outcomes and whether the predicted benefits have been realised. Where realisation of these outcomes and benefits is expected to take a further period, a method and reporting system for assessing them in the future should be implemented. Risk Assessment: Risks that are no longer relevant should be terminated on the Risk Register. 4. Guidance and Reference Material Houses of the Oireachtas Service Policies and Guidelines, available in the Discussion Database under Project Management: Project Management Guidelines (updated Feb 2013) Project management Toolkit ( Feb 2013) Risk Management Policy Management of Results (Dec 2011) Financial Governance Handbook (Nov 2011) Office Notice 1/2011: Exercise of Financial Authority and the Placement of Orders for Goods and Services Procurement Guidance for Staff booklet (Nov 2010) ICT Unit: Project Managers access to project management software licences following confirmation of the requirement and indication of how long licence will be required. Public Service Policies and Guidelines and links Guidelines for Engagement of Consultants and other External Support by the Civil Service (2006). Page 13 of 18

15 Public Procurement Guidelines S.I. No.329 of 2006 European Communities (Award of Public Authorities' Contracts) Regulations. ICT Procurement Frameworks ictprocurement.gov.ie Peer Review in the Public Service. Risk Management Guidance for Government Departments and Offices (2004). Public Spending Code (July 2012). Public service ICT and egovernment Comptroller & Auditor General. Appendix 2: Summary of Conclusions of the Comptroller and Auditor General Report on PPARS. Appendix 3: Summary of Requirements for Management, Monitoring and Evaluation of egovernment Projects from the 2007 Report 1 of the Comptroller and Auditor General. Chapters from the 2010 Annual Report of the C&AG (Volume 2- Vote Management) Chapter 19 - Central Statistics Office - Data Management System Chapter 21 - Justice and Law Reform and Garda Síochána Fingerprint Systems Link: Other Article on Project Management by Ken Garrett ACCA. ACCA website. 1 Comptroller and Auditor General, Report on egovernment, Special Report 58, January 2008 Page 14 of 18

16 Appendix 1: Project Governance Framework Diagram Page 15 of 18

17 Appendix 2: Summary of Conclusions of the C&AG Report on PPARS 2 Vision and Goals: Business transformation projects demand a clear and consistent articulation of vision and goals; a full understanding of the cultural, organisational, process and technical changes required to support that vision; and a coherent but adaptable plan to effect those changes in practice at every level of the organisation. ICT alone cannot transform business processes. It is but one element in what must be a broadly-based approach to business change. The ICT solution selected should be appropriate to the needs being addressed and its requirements fully factored into the implementation plan. Cost Benefit Analysis: The cost benefit analysis must identify costs on as wide a basis as possible, be maintained and reassessed on an ongoing basis and set out targets and plans to achieve those benefits. User involvement: Users of a proposed system must be centrally involved at all stages of the project and additional resources must be provided to allow them to be so involved. Feasibility testing and piloting: The overall feasibility of the project strategy should be tested in order to mitigate the risk of failure. In this regard, the importance of comprehensive pilot testing should not be overlooked. Governance: Projects must not proceed without clearly defined lines of authority, responsibility and accountability and a means of ensuring they are observed in practice. Risk Management: A Risk Management process should form an integral part of projects at all stages and a process to mitigate and manage all risks identified should be put in place. Reviews: Gateway reviews (reviews at each major stage in a project cycle) need to be built into the approval process for major ICT projects and should be independent of the project team. Multiple Agency involvement: Where multiple agencies are involved, there must be clear buy-in based on an agreed project charter, resourcing agreements, governance protocols and budgets. Technical Management: Technical Management should rest with the party best equipped to handle it and there should be clear contractual terms to enforce this. Commissioning: Commissioning protocols should be in place. Expertise: Industry-best ICT and project management expertise should be developed within the public sector. Consultants: Contracts should be based either on defined specifications or managed in a way that focuses on milestones, deadlines and deliverables. High value contracts with consultants on large IT projects should incorporate provisions whereby each party shares the rewards and the risks. All agreements entered into should be subjected to regular, independent performance review. Such review should engage with all stakeholders in the project, including users. Funding: Effective accountability for results is more likely to be achieved through the use of a high level budget holder with regular financial reporting responsibilities. 2 Comptroller and Auditor General, Report on Value for Money Examination, Health Service Executive Development of Human Resource Management System for the Health Service (PPARS), December 2005 Page 16 of 18

18 Appendix 3: Summary of Requirements for Management, Monitoring and Evaluation of egovernment Projects from the 2007 Report 3 of the Comptroller and Auditor General For each major egovernment project, whether within an individual department/agency or across a number of departments/agencies, the following elements are required to support the achievement of effective process transformation. A current performance baseline against which results can be measured Target business benefits defined in measurable terms i.e. measurable change in service, efficiency, or effectiveness Formal assessment of the project risks An organisation appropriate to, and capable of, executing the process, drawn from the managers of the process itself, supported as required by expertise from other departments or from external sources An adequate budget for the full scope of the strategy Supporting methods, training, staffing and systems An appropriate change management programme An appropriate programme management control structure Management and governance structures that are effective and empowered Development methodologies which are appropriate to the project for instance, modular, incremental, agile development approaches may be more appropriate for complex innovative projects than the traditional, sequential software development model (the waterfall approach) Regular specific reporting on progress against measurable targets and budgets Regular review of business case targets Post-implementation review for all projects or programmes with benefits realised assessed against projected benefits and the costs incurred. 3 Comptroller and Auditor General, Report on egovernment, Special Report 58, January 2008 Page 17 of 18

Corporate Governance Standard for the Civil Service

Corporate Governance Standard for the Civil Service Corporate Governance Standard for the Civil Service 0 Contents Introduction... 1 Governance Principles, and Overview of Governance Framework.. 3 Chapters Chapter 1 - Department Overview... 7 Chapter 2

More information

PROJECT MANAGEMENT FRAMEWORK

PROJECT MANAGEMENT FRAMEWORK PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to

More information

The Gateway Review Process

The Gateway Review Process The Gateway Review Process The Gateway Review Process examines programs and projects at key decision points. It aims to provide timely advice to the Senior Responsible Owner (SRO) as the person responsible

More information

PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3)

PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3) PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3) 1st February 2006 Version 1.0 1 P3M3 Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce This is a Value

More information

Maturity Model. March 2006. Version 1.0. P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce

Maturity Model. March 2006. Version 1.0. P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce Maturity Model March 2006 Version 1.0 P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce This is a Value Added product which is outside the scope of the HMSO

More information

Project Management Framework

Project Management Framework Information Services Project Management Framework October 2003 Document ID No. Page 1 of 1 Contents 1. Introduction Page 3 2. Use of Framework Page 3 3. Project Register and Monitoring Page 4 4. Project

More information

Achieve. Performance objectives

Achieve. Performance objectives Achieve Performance objectives Performance objectives are benchmarks of effective performance that describe the types of work activities students and affiliates will be involved in as trainee accountants.

More information

Project Management Toolkit Version: 1.0 Last Updated: 23rd November- Formally agreed by the Transformation Programme Sub- Committee

Project Management Toolkit Version: 1.0 Last Updated: 23rd November- Formally agreed by the Transformation Programme Sub- Committee Management Toolkit Version: 1.0 Last Updated: 23rd November- Formally agreed by the Transformation Programme Sub- Committee Page 1 2 Contents 1. Introduction... 3 1.1 Definition of a... 3 1.2 Why have

More information

NSW Government ICT Benefits Realisation and Project Management Guidance

NSW Government ICT Benefits Realisation and Project Management Guidance NSW Government ICT Benefits Realisation and Project Management Guidance November 2014 CONTENTS 1. Introduction 1 2. Document purpose 1 3. Benefits realisation 1 4. Project management 4 5. Document control

More information

Welsh Government Response to the Report of the National Assembly for Wales Public Accounts Committee on Grant Management in Wales Final Report

Welsh Government Response to the Report of the National Assembly for Wales Public Accounts Committee on Grant Management in Wales Final Report Welsh Government Response to the Report of the National Assembly for Wales Public Accounts Committee on Grant Management in Wales Final Report The Welsh Government appreciates both the time and effort

More information

Financial and Commercial Services HIRE OF MANAGEMENT IT/IS CONSULTANTS

Financial and Commercial Services HIRE OF MANAGEMENT IT/IS CONSULTANTS Financial and Commercial Services HIRE OF MANAGEMENT IT/IS CONSULTANTS Table of Contents Contents INTRODUCTION... 2 1. DEFINING MANAGEMENT CONSULTANCY... 2 2. KEY SUCCESS FACTORS... 3 3. THE PROJECT APPROACH

More information

Principles and Procedures

Principles and Procedures DPE 022/05/2013 26 September 2014 Circular: 13/2014 Management of and Accountability for Grants from Exchequer Funds To: Accounting Officers, Finance Officers and Heads of Internal Audit. A Dhuine Uasail,

More information

Outsourcing. Definitions. Outsourcing Strategy. Potential Advantages of an Outsourced Service. Procurement Process

Outsourcing. Definitions. Outsourcing Strategy. Potential Advantages of an Outsourced Service. Procurement Process CIPS takes the view that the outsourcing of services to specialist providers can often lead to better quality of services and increased value for money. Purchasing and supply management professionals should

More information

Part B1: Business case developing the business case

Part B1: Business case developing the business case Overview Part A: Strategic assessment Part B1: Business case developing the business case Part B2: Business case procurement options Part B3: Business case funding and financing options Part C: Project

More information

Department of the Environment and Local Government. Project Management. Public Private Partnership Guidance Note 7. 14 April 2000

Department of the Environment and Local Government. Project Management. Public Private Partnership Guidance Note 7. 14 April 2000 Project Management Project Management Public Private Partnership Guidance Note 7 14 April 2000 Guidance Note 7 14 April 2000 Project Management Contents Section Page I INTRODUCTION...1 SCOPE AND PURPOSE

More information

John A Manzoni Chief Executive of the Civil Service. Email chief.executive@cabinetoffice.gov.uk

John A Manzoni Chief Executive of the Civil Service. Email chief.executive@cabinetoffice.gov.uk John A Manzoni Chief Executive of the Civil Service Email chief.executive@cabinetoffice.gov.uk 70 Whitehall London SW1A 2AS Telephone +44 (0) 20 7271 8822 Web www.cabinetoffice.gov.uk Paul Chinn Cabinet

More information

Governance, Risk and Best Value Committee

Governance, Risk and Best Value Committee Governance, Risk and Best Value Committee 2.00pm, Wednesday 23 September 2015 Internal Audit Report: Integrated Health & Social Care Item number Report number Executive/routine Wards Executive summary

More information

Resource Management. Determining and managing the people resources on projects can be complex as:

Resource Management. Determining and managing the people resources on projects can be complex as: Baseline Resource Management RESOURCE MANAGEMENT Purpose To provide a procedure and associated guidelines to facilitate the management of project people resources. Overview This Phase is used to establish

More information

Project Management Guidebook

Project Management Guidebook METHOD 12 3 empowering managers to succeed Project Management Guidebook ISBN 0-473-10445-8 A bout this e-book This e-book was created by Method123 (see www.method123.com) to help provide you with a simple

More information

Project Assessment Framework Establish service capability

Project Assessment Framework Establish service capability Project Assessment Framework Establish service capability July 2015 Component of the Project Assessment Framework (PAF) This document forms part of the Project Assessment Framework, as outlined below.

More information

Aberdeen City Council

Aberdeen City Council Aberdeen City Council Internal Audit Report Final Contract management arrangements within Social Care & Wellbeing 2013/2014 for Aberdeen City Council January 2014 Internal Audit KPI Targets Target Dates

More information

Introduction to the ITS Project Management Methodology

Introduction to the ITS Project Management Methodology Introduction to the ITS Project Management Methodology In September 1999 the Joint Legislative Committee on Performance Evaluation and Expenditure Review (PEER) produced a report entitled Major Computer

More information

PROJECT MANAGEMENT PLAN CHECKLIST

PROJECT MANAGEMENT PLAN CHECKLIST PROJECT MANAGEMENT PLAN CHECKLIST The project management plan is a comprehensive document that defines each area of your project. The final document will contain all the required plans you need to manage,

More information

CHECKLIST OF COMPLIANCE WITH THE CIPFA CODE OF PRACTICE FOR INTERNAL AUDIT

CHECKLIST OF COMPLIANCE WITH THE CIPFA CODE OF PRACTICE FOR INTERNAL AUDIT CHECKLIST OF COMPLIANCE WITH THE CIPFA CODE OF PRACTICE FOR INTERNAL AUDIT 1 Scope of Internal Audit 1.1 Terms of Reference 1.1.1 Do terms of reference: (a) establish the responsibilities and objectives

More information

GUIDELINES FOR THE ENGAGEMENT OF CONSULTANTS AND OTHER EXTERNAL SUPPORT BY THE CIVIL SERVICE

GUIDELINES FOR THE ENGAGEMENT OF CONSULTANTS AND OTHER EXTERNAL SUPPORT BY THE CIVIL SERVICE GUIDELINES FOR THE ENGAGEMENT OF CONSULTANTS AND OTHER EXTERNAL SUPPORT BY THE CIVIL SERVICE Department of Finance 2006 1 INTRODUCTION... - 4-1.1 CONSULTANTS, CONTRACTORS AND EXTERNAL SERVICE PROVIDERS...-

More information

Effective complaint handling

Effective complaint handling This guide sets out key information for state sector agencies about developing and operating an effective complaints process. It also provides information about the Ombudsman s role, as an independent,

More information

Housing Related Support Contract Management Framework 2009/10

Housing Related Support Contract Management Framework 2009/10 Housing Related Support Contract Management Framework 2009/10 0 If you would like this information in large print, audio tape or in any other format or language please contact the public information officer

More information

Draft Corporate Governance Standard for Central Government Departments

Draft Corporate Governance Standard for Central Government Departments 2015 Draft Corporate Governance Standard for Central Government Departments FOR PUBLIC CONSULTATION CONTENTS About this Standard... 1 Governance Principles... 3 Part 2 - Governance Framework... 7 Chapter

More information

Schools and Directorates Funded Projects for building, alteration and decorative works

Schools and Directorates Funded Projects for building, alteration and decorative works University of Sussex Schools and Directorates Funded Projects for building, alteration and decorative works Overview 1. All proposed building, alterations and decorative works to be funded from Schools

More information

THE SOUTH AFRICAN HERITAGE RESOURCES AGENCY MANAGEMENT OF PERFORMANCE INFORMATION POLICY AND PROCEDURES DOCUMENT

THE SOUTH AFRICAN HERITAGE RESOURCES AGENCY MANAGEMENT OF PERFORMANCE INFORMATION POLICY AND PROCEDURES DOCUMENT THE SOUTH AFRICAN HERITAGE RESOURCES AGENCY MANAGEMENT OF PERFORMANCE INFORMATION POLICY AND PROCEDURES DOCUMENT ACCOUNTABLE SIGNATURE AUTHORISED for implementation SIGNATURE On behalf of Chief Executive

More information

Prince 2 Health Check

Prince 2 Health Check Prince 2 Health Check Start-up Was there a Project Mandate? Was the Project Board designed/appointed before initiation was authorised? Was a Project Brief produced? Is the Project Brief to PRINCE standards?

More information

The Risk Management strategy sets out the framework that the Council has established.

The Risk Management strategy sets out the framework that the Council has established. Derbyshire County Council Management Policy Statement The Authority adopts a proactive approach to Management to achieve Best Value and continuous improvement and is committed to the effective management

More information

Contract Management Guideline

Contract Management Guideline www.spb.sa.gov.au Contract Management Guideline Version 3.2 Date Issued January 2014 Review Date January 2014 Principal Contact State Procurement Board Telephone 8226 5001 Contents Overview... 3 Contract

More information

Risk Management Policy and Process Guide

Risk Management Policy and Process Guide Risk Management Policy and Process Guide Status: pending Next review date: December 2015 Page 1 Information Reader Box Directorate Medical Nursing Patients & Information Commissioning Operations (including

More information

PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE:

PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: Project Name Project Management Plan Document Information Document Title Version Author Owner Project Management Plan Amendment History

More information

Part 1 Checklist. Feasibility 2. Investigation 9. Design 18. Construction 26

Part 1 Checklist. Feasibility 2. Investigation 9. Design 18. Construction 26 Part 1 Checklist Process Page 2 9 Design 18 26 Page 1 FEASIBILITY 1. Establishment 1.1 Establishment Recognise problem, need or opportunity. Formulate goal and objectives. Prepare project charter. Obtain

More information

ITS specification Handover and commissioning process (ITS-10-01)

ITS specification Handover and commissioning process (ITS-10-01) ITS specification Handover and commissioning process (ITS-10-01) NZ Transport Agency Effective from September 2011 Copyright information This publication is copyright NZ Transport Agency (NZTA). Material

More information

Rent to Buy 2015 to 2017

Rent to Buy 2015 to 2017 Rent to Buy 2015 to 2017 BIDDING PROSPECTUS September 2014 Rent to Buy Contents Page Number Ministerial Foreword 2 Chapter 1 Overview of the fund 3 Chapter 2 The funding model 4 Chapter 3 Bidding requirements

More information

PRINCE2:2009 Glossary of Terms (English)

PRINCE2:2009 Glossary of Terms (English) accept (risk response) acceptance acceptance criteria activity agile methods approval approver assumption assurance A risk response to a threat where a conscious and deliberate decision is taken to retain

More information

Guidelines on Appointments to State Boards Department of Public Expenditure and Reform, November 2014

Guidelines on Appointments to State Boards Department of Public Expenditure and Reform, November 2014 Guidelines on Appointments to State Boards Department of Public Expenditure and Reform, November 2014 Introduction and Context 1. Background 1.1 In 2011 the Government introduced new arrangements for appointments

More information

RISK MANAGEMENT POLICY

RISK MANAGEMENT POLICY RISK MANAGEMENT POLICY Approved by Governing Authority February 2016 1. BACKGROUND 1.1 The focus on governance in corporate and public bodies continues to increase. It resulted in an expansion from the

More information

Hertsmere Borough Council. Data Quality Strategy. December 2009 1

Hertsmere Borough Council. Data Quality Strategy. December 2009 1 Hertsmere Borough Council Data Quality Strategy December 2009 1 INTRODUCTION Public services need reliable, accurate and timely information with which to manage services, inform users and account for performance.

More information

Project Risk Analysis toolkit

Project Risk Analysis toolkit Risk Analysis toolkit MMU has a corporate Risk Management framework that describes the standard for risk management within the university. However projects are different from business as usual activities,

More information

Module 2: The Project Initiation Stage

Module 2: The Project Initiation Stage Overview Initiation stage is highly instrumental in the life cycle of a project as it defines the boundaries of the project gives clarity to all participants about the objectives, scope, cost timescale

More information

Gateway review guidebook. for project owners and review teams

Gateway review guidebook. for project owners and review teams Gateway review guidebook for project owners and review teams The State of Queensland (Queensland Treasury and Trade) 2013. First published by the Queensland Government, Department of Infrastructure and

More information

Internal Audit Report. Chief Executive s Unit. Review of Contract Management

Internal Audit Report. Chief Executive s Unit. Review of Contract Management Internal Audit Report Chief Executive s Unit Review of Contract Management February 2010 CONTENTS 1. BACKGROUND 1 Page 2. AUDIT SCOPE AND OBJECTIVES 1 3. AUDIT APPROACH 1 4. AMENDED PROCESS 2 5. SUMMARY

More information

7 Directorate Performance Managers. 7 Performance Reporting and Data Quality Officer. 8 Responsible Officers

7 Directorate Performance Managers. 7 Performance Reporting and Data Quality Officer. 8 Responsible Officers Contents Page 1 Introduction 2 2 Objectives of the Strategy 2 3 Data Quality Standards 3 4 The National Indicator Set 3 5 Structure of this Strategy 3 5.1 Awareness 4 5.2 Definitions 4 5.3 Recording 4

More information

Financial Management Framework >> Overview Diagram

Financial Management Framework >> Overview Diagram June 2012 The State of Queensland (Queensland Treasury) June 2012 Except where otherwise noted you are free to copy, communicate and adapt this work, as long as you attribute the authors. This document

More information

ACADEMIC POLICY FRAMEWORK

ACADEMIC POLICY FRAMEWORK ACADEMIC POLICY FRAMEWORK Principles, Procedures and Guidance for the Development & Review of Academic Policies [V.1] Page 2 of 11 TABLE OF CONTENTS 1. FRAMEWORK OVERVIEW... 3 2. PRINCIPLES... 4 3. PROCESS...

More information

University of New England Compliance Management Framework and Procedures

University of New England Compliance Management Framework and Procedures University of New England Compliance Management Framework and Procedures Document data: Document type: Administering entity: Framework and Procedures Audit and Risk Directorate Records management system

More information

Date: 7 February 2013

Date: 7 February 2013 Item No. Report title: Classification: Open Ward(s) or groups affected: From: Date: 7 February 2013 Meeting Name: Deputy Leader and Cabinet Member for Housing Management GW2: Leasehold and Ancillary Properties

More information

U & D COAL LIMITED A.C.N. 165 894 806 BOARD CHARTER

U & D COAL LIMITED A.C.N. 165 894 806 BOARD CHARTER U & D COAL LIMITED A.C.N. 165 894 806 BOARD CHARTER As at 31 March 2014 BOARD CHARTER Contents 1. Role of the Board... 4 2. Responsibilities of the Board... 4 2.1 Board responsibilities... 4 2.2 Executive

More information

Consultancy spending approval process: Initial guidance to NHS foundation trusts

Consultancy spending approval process: Initial guidance to NHS foundation trusts Annex One Consultancy spending approval process: Initial guidance to NHS foundation trusts Summary 1. Monitor, the NHS Trust Development Authority (TDA) and NHS England are jointly implementing an approval

More information

Relationship Manager (Banking) Assessment Plan

Relationship Manager (Banking) Assessment Plan Relationship Manager (Banking) Assessment Plan ST0184/AP03 1. Introduction and Overview The Relationship Manager (Banking) is an apprenticeship that takes 3-4 years to complete and is at a Level 6. It

More information

UoD IT Job Description

UoD IT Job Description UoD IT Job Description Role: Projects Portfolio Manager HERA Grade: 8 Responsible to: Director of IT Accountable for: Day to day leadership of team members and assigned workload Key Relationships: Management

More information

Internal Audit Quality Assessment Framework

Internal Audit Quality Assessment Framework Internal Audit Quality Assessment Framework May 2013 Internal Audit Quality Assessment Framework May 2013 Crown copyright 2013 You may re-use this information (excluding logos) free of charge in any format

More information

South West Lincolnshire NHS Clinical Commissioning Group Business Continuity Policy

South West Lincolnshire NHS Clinical Commissioning Group Business Continuity Policy South West Lincolnshire NHS Clinical Commissioning Group Business Continuity Policy Reference No: CG 01 Version: Version 1 Approval date 18 December 2013 Date ratified: 18 December 2013 Name of Author

More information

PROJECT MANAGEMENT GUIDELINES NATIONAL TRANSPORT AUTHORITY

PROJECT MANAGEMENT GUIDELINES NATIONAL TRANSPORT AUTHORITY PROJECT MANAGEMENT GUIDELINES FOR PROJECTS FUNDED BY THE NATIONAL TRANSPORT AUTHORITY (UP TO 20 MILLION IN VALUE) december 2011 Table of Contents Section A 1. Introduction 4 1.1 Purpose 4 1.2 Applicability

More information

Project Management Policy and Procedure

Project Management Policy and Procedure Project Management Policy and Procedure Author(s): Laura Graham Peter Griggs Approved SMT: October 2006 Issue Date: October 2006 Policy Review Date Ref: Contents: 1. Purpose and Scope 2. Aims and Objectives

More information

DERBYSHIRE COUNTY COUNCIL BUSINESS CONTINUITY POLICY

DERBYSHIRE COUNTY COUNCIL BUSINESS CONTINUITY POLICY DERBYSHIRE COUNTY COUNCIL BUSINESS CONTINUITY POLICY VERSION 1.0 ISSUED JULY 2015 CONTENTS Page CONTENTS VERSION CONTROL FOREWORD i ii iii POLICY 1 Scope 1 Aim and Objectives 1 Methods and Standards 1

More information

Information Commissioner's Office

Information Commissioner's Office Information Commissioner's Office IT Procurement Review Ian Falconer Partner T: 0161 953 6480 E: ian.falconer@uk.gt.com Last updated 18 June 2012 Will Simpson Senior Manager T: 0161 953 6486 E: will.g.simpson@uk.gt.com

More information

CONFIGURATION COMMITTEE. Terms of Reference

CONFIGURATION COMMITTEE. Terms of Reference SWBTB (8/13) 166 (g) CONFIGURATION COMMITTEE Terms of Reference 1. CONSTITUTION 1.1 The Board hereby resolves to establish a Committee of the Board to be known as the Configuration Committee (The Committee).

More information

Policy: D9 Data Quality Policy

Policy: D9 Data Quality Policy Policy: D9 Data Quality Policy Version: D9/02 Ratified by: Trust Management Team Date ratified: 16 th October 2013 Title of Author: Head of Knowledge Management Title of responsible Director Director of

More information

Major Project Governance Assessment Toolkit

Major Project Governance Assessment Toolkit Major Project Governance Assessment Toolkit Mark Ritchie, University of Edinburgh Pauline Woods-Wilson, Lancaster University Project and Change Management Group Project and Change Management Group Established

More information

Response from the Department of Treasury, Western Australia, to the Productivity Commission s Draft Report Regulatory Impact Analysis: Benchmarking

Response from the Department of Treasury, Western Australia, to the Productivity Commission s Draft Report Regulatory Impact Analysis: Benchmarking Response from the Department of Treasury, Western Australia, to the Productivity Commission s Draft Report Regulatory Impact Analysis: Benchmarking Context Regulatory Impact Assessment (RIA) began in Western

More information

Information Technology Project Oversight Framework

Information Technology Project Oversight Framework i This Page Intentionally Left Blank i Table of Contents SECTION 1: INTRODUCTION AND OVERVIEW...1 SECTION 2: PROJECT CLASSIFICATION FOR OVERSIGHT...7 SECTION 3: DEPARTMENT PROJECT MANAGEMENT REQUIREMENTS...11

More information

Business Plan 2016-2017

Business Plan 2016-2017 Business Plan 2016-2017 March 2016 Contents Introduction... 3 About us... 5 Role of Registrar... 5 Objectives for 2016-17... 5 Work programme for 2016/17... 6 Activity 1 Continue to operate an accessible,

More information

GOVERNMENT INTERNAL AUDIT COMPETENCY FRAMEWORK

GOVERNMENT INTERNAL AUDIT COMPETENCY FRAMEWORK GOVERNMENT INTERNAL AUDIT COMPETENCY FRAMEWORK March 2007 Government Internal Audit Profession This framework has been compiled by the Assurance, Control and Risk Team and the PSG Competency Framework

More information

Delivering Excellence in Insurance Claims Handling

Delivering Excellence in Insurance Claims Handling Delivering Excellence in Insurance Claims Handling Guide to Best Practice Delivering Excellence in Insurance Claims Handling Contents Page 1. Introduction 1 2. Executive Summary 2 3. Components of Best

More information

Making a positive difference for energy consumers. Competency Framework Band C

Making a positive difference for energy consumers. Competency Framework Band C Making a positive difference for energy consumers Competency Framework 2 Competency framework Indicators of behaviours Strategic Cluster Setting Direction 1. Seeing the Big Picture Seeing the big picture

More information

Page 5. The Adult Social Services and Health Committee. The Strategic Director of Adult Social Services, Housing and Health

Page 5. The Adult Social Services and Health Committee. The Strategic Director of Adult Social Services, Housing and Health Page 5 Agenda Item 5 Report to: The Adult Social Services and Health Committee Date: 20 th November 2012 Report of: The Strategic Director of Adult Social Services, Housing and Health Ward Location: All

More information

Procurement Transformation Division. Procurement guidance. Engaging and managing consultants. Includes definitions for consultants and contractors

Procurement Transformation Division. Procurement guidance. Engaging and managing consultants. Includes definitions for consultants and contractors Procurement guidance Engaging and managing consultants Includes definitions for consultants and contractors Procurement guidance: Engaging and managing consultants Page 2 of 17 Table of contents Table

More information

River Stour (Kent) Internal Drainage Board Risk Management Strategy and Policy

River Stour (Kent) Internal Drainage Board Risk Management Strategy and Policy River Stour (Kent) Internal Drainage Board Risk Management Strategy and Policy Page: 1 Contents 1. Purpose, Aims & Objectives 2. Accountabilities, Roles & Reporting Lines 3. Skills & Expertise 4. Embedding

More information

Data Communications Company (DCC) price control guidance: process and procedures

Data Communications Company (DCC) price control guidance: process and procedures Guidance document Contact: Tricia Quinn, Senior Economist Publication date: 27 July 2015 Team: Smarter Metering Email: tricia.quinn@ofgem.gov.uk Overview: The Data and Communications Company (DCC) is required

More information

Standard 1. Governance for Safety and Quality in Health Service Organisations. Safety and Quality Improvement Guide

Standard 1. Governance for Safety and Quality in Health Service Organisations. Safety and Quality Improvement Guide Standard 1 Governance for Safety and Quality in Health Service Organisations Safety and Quality Improvement Guide 1 1 1October 1 2012 ISBN: Print: 978-1-921983-27-6 Electronic: 978-1-921983-28-3 Suggested

More information

Unofficial Consolidation

Unofficial Consolidation CENTRAL BANK (SUPERVISION AND ENFORCEMENT) ACT 2013 (SECTION 48) (LENDING TO SMALL AND MEDIUM-SIZED ENTERPRISES) REGULATIONS 2015 (S.I. No. 585 of 2015) Unofficial Consolidation This document is an unofficial

More information

The Transport Business Cases

The Transport Business Cases Do not remove this if sending to pagerunnerr Page Title The Transport Business Cases January 2013 1 Contents Introduction... 3 1. The Transport Business Case... 4 Phase One preparing the Strategic Business

More information

pm4dev, 2016 management for development series Project Scope Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

pm4dev, 2016 management for development series Project Scope Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS pm4dev, 2016 management for development series Project Scope Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development

More information

SMBC ICT Functional Review Recommendations (Amended 1 st June 2016)

SMBC ICT Functional Review Recommendations (Amended 1 st June 2016) SMBC ICT Functional Review Recommendations (Amended 1 st June 2016) No. Recommendation ICT and Peer Review Comments Responsibility Deadline Current 1. Whilst the ICT Strategy is well defined and documented,

More information

AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP)

AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP) AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP) Copyright: Australian Institute of Project Management Document Information Document

More information

Step by Step Project Planning

Step by Step Project Planning Step by Step Project Planning Contents Introduction The Planning Process 1 Create a Project Plan...1 Create a Resource Plan...1 Create a Financial Plan...1 Create a Quality Plan...2 Create a Risk Plan...2

More information

Safety Management Systems (SMS) guidance for organisations

Safety Management Systems (SMS) guidance for organisations Safety and Airspace Regulation Group Safety Management Systems (SMS) guidance for organisations CAP 795 Published by the Civil Aviation Authority, 2014 Civil Aviation Authority, CAA House, 45-59 Kingsway,

More information

MONMOUTHSHIRE COUNTY COUNCIL DATA PROTECTION POLICY

MONMOUTHSHIRE COUNTY COUNCIL DATA PROTECTION POLICY MONMOUTHSHIRE COUNTY COUNCIL DATA PROTECTION POLICY Page 1 of 16 Contents Policy Information 3 Introduction 4 Responsibilities 7 Confidentiality 9 Data recording and storage 11 Subject Access 12 Transparency

More information

2010 MTEF: Budgeting for infrastructure and capital expenditure guidelines

2010 MTEF: Budgeting for infrastructure and capital expenditure guidelines 2010 MTEF: Budgeting for infrastructure and capital expenditure guidelines Introduction The guidelines below provide departments and entities with information to make budget submissions for capital projects

More information

Guidance Note: Corporate Governance - Board of Directors. March 2015. Ce document est aussi disponible en français.

Guidance Note: Corporate Governance - Board of Directors. March 2015. Ce document est aussi disponible en français. Guidance Note: Corporate Governance - Board of Directors March 2015 Ce document est aussi disponible en français. Applicability The Guidance Note: Corporate Governance - Board of Directors (the Guidance

More information

HEALTH SERVICE EXECUTIVE NATIONAL FINANCIAL REGULATION INTRODUCTION TO NATIONAL FINANCIAL REGULATIONS NFR - 00

HEALTH SERVICE EXECUTIVE NATIONAL FINANCIAL REGULATION INTRODUCTION TO NATIONAL FINANCIAL REGULATIONS NFR - 00 HEALTH SERVICE EXECUTIVE NATIONAL FINANCIAL REGULATION INTRODUCTION TO NATIONAL FINANCIAL REGULATIONS NFR - 00 Ver 3.0 9/10/2014 NFR 00 Introduction to Section 1: Introduction to 1.1-1.10 Introduction

More information

Independent Trustee (Corporate)

Independent Trustee (Corporate) Independent Trustee (Corporate) Your guide to applying for a market service licence In this guide 2 Introduction 5 Getting started 7 Fit and proper 9 Capability 11 Financial resources 12 Governance 13

More information

* draw up formal annual and multi-annual information technology plans;

* draw up formal annual and multi-annual information technology plans; Reference No: E168/427/85; Date: 14/07/86 Circular 13/1986:- Information Technology A Dhuine Uasail I am directed by the Minister for the Public Service to refer to Chapter 5 of the White Paper, "Serving

More information

Part E: Contract management

Part E: Contract management Overview Part A: Strategic assessment Part B1: Business case developing the business case Part B2: Business case procurement options Part B3: Business case funding and financing options Part C: Project

More information

Code of Corporate Governance

Code of Corporate Governance www.surreycc.gov.uk Making Surrey a better place Code of Corporate Governance October 2013 1 This page is intentionally blank 2 CONTENTS PAGE Commitment to good governance 4 Good governance principles

More information

GUIDE ON DEVELOPING SERVICE STANDARDS

GUIDE ON DEVELOPING SERVICE STANDARDS GUIDE ON DEVELOPING SERVICE STANDARDS Contents 1. Background... 3 2. Why the Guide/ Toolkit?... 4 3. Service Delivery Planning Value Chain Components... 4 4. Definition and types of Service Standards...

More information

Safety Regulation Group SAFETY MANAGEMENT SYSTEMS GUIDANCE TO ORGANISATIONS. April 2008 1

Safety Regulation Group SAFETY MANAGEMENT SYSTEMS GUIDANCE TO ORGANISATIONS. April 2008 1 Safety Regulation Group SAFETY MANAGEMENT SYSTEMS GUIDANCE TO ORGANISATIONS April 2008 1 Contents 1 Introduction 3 2 Management Systems 2.1 Management Systems Introduction 3 2.2 Quality Management System

More information

An Introduction to PRINCE2

An Introduction to PRINCE2 Project Management Methodologies An Introduction to PRINCE2 Why use a Project Methodology and What Does PRINCE2 Enable? PRINCE - PRojects IN Controlled Environments - is a project management method covering

More information

Worcester City Council Data Quality Policy

Worcester City Council Data Quality Policy Worcester City Council Data Quality Policy Content: 1. What is Data Quality? 2. Purpose of the Policy 3. Scope 4. Data quality in practice 5. Data quality checks and corrective action 6. Third party data

More information

Initiating Forms COPYRIGHTED MATERIAL 1.0 INITIATING PROCESS GROUP

Initiating Forms COPYRIGHTED MATERIAL 1.0 INITIATING PROCESS GROUP 1 Initiating Forms 1.0 INITIATING PROCESS GROUP The purpose of the initiating process group is to authorize a project, provide a high-level definition of the project, and identify stakeholders. There are

More information

Outsourcing. Knowledge Summary

Outsourcing. Knowledge Summary Knowledge Summary Outsourcing P&SM professionals should have the knowledge and skills required to manage the outsourcing process and to advise colleagues of the most appropriate solution to obtain best

More information

Securing Information in an Outsourcing Environment (Guidance for Critical Infrastructure Providers) Executive Overview Supplement.

Securing Information in an Outsourcing Environment (Guidance for Critical Infrastructure Providers) Executive Overview Supplement. Securing Information in an Outsourcing Environment (Guidance for Critical Infrastructure Providers) Executive Overview Supplement June 2011 DISCLAIMER: This document is intended as a general guide only.

More information

Managing ICT contracts in central government. An update

Managing ICT contracts in central government. An update Managing ICT contracts in central government An update Prepared by Audit Scotland June 2015 Auditor General for Scotland The Auditor General s role is to: appoint auditors to Scotland s central government

More information

Programme Governance and Management Plan Version 2

Programme Governance and Management Plan Version 2 PROCESS FOR CHANGE - Detailed Design Programme Governance and Management Plan Version 2 1 INTRODUCTION In October 2008, the Council approved the selection of seven opportunity themes to take forward from

More information

RDTL Procurement Best Practice Guide 7: Managing Contracts. RDTL MINISTRY OF FINANCE Procurement Service BEST PRACTICE GUIDE 7: MANAGING CONTRACTS

RDTL Procurement Best Practice Guide 7: Managing Contracts. RDTL MINISTRY OF FINANCE Procurement Service BEST PRACTICE GUIDE 7: MANAGING CONTRACTS RDTL MINISTRY OF FINANCE Procurement Service BEST PRACTICE GUIDE 7: MANAGING CONTRACTS 1 RDTL Procurement Guidelines The Procurement Legal Regime Decree Law sets out new procurement processes which must

More information