Bridge option for forest roads: A composite timber beam and concrete deck bridge

Size: px
Start display at page:

Download "Bridge option for forest roads: A composite timber beam and concrete deck bridge"

Transcription

1 Bridge option for forest roads: A composite timber beam and concrete deck bridge A.G. Lee* Forestry Tasmania Abstract Bridge options for forest roads are traditionally limited to either timber bridges or bridges in permanent materials. The options have widely different design lives and costs. A composite timber bridge with a reinforced concrete deck designed and constructed by Forestry Tasmania provides a viable third option. Introduction In the last five years, Forestry Tasmania (FT) has developed and constructed various composite timber bridges with a reinforced concrete deck. To provide composite action, shear connectors have been used to connect the timber stringers to the concrete deck which is cast on site. Both single- and twin-span structures of single- and two-lane configuration have been constructed up to a span of 13 m. The objective was to develop a bridge design that had the characteristics of a permanent bridge structure without the cost premium. The benchmark to date has been the standard all-timber bridge. A summary of the characteristics of each bridge type is shown in Table 1. Cost comparisons Based on the indicative construction costs in Table 1, it is also necessary to factor in future maintenance and demolition costs as well as the initial construction cost and replacement costs for each bridge option. To illustrate, a discounted present-value cost analysis Table 1. Bridge comparisons. Forestry Tasmania Timber bridge composite bridge Permanent bridge Design life 20 years 40 years estimated 80 years plus Construction cost $400/m 2 $600/m 2 $800/m 2 plus Construction One week Three weeks plus Depends on materials; for period deck cure time example, one day road prior to usage interruption for pre-cast deck planks and abutments Skill level for Moderate High High installation Maintenance High, depending on Low Low depending on bridge requirements usage replace deck materials planks and deck runners * allan.lee@forestrytas.com.au Tasforests Vol

2 Table 2. Typical bridge replacement costs. (FT = Forestry Tasmania) Life cycle Assumptions Cost ($) usage (yrs) Timber bridge complete replacement 400/m 2 20 Timber bridge replacement runners 100/m 5 Timber bridge replacement deck 100/m 2 10 Timber bridge superstructure replacement stringers 165/m 2 20 Timber bridge abutment replacement 3000 each 40 Timber bridge demolition 1000 each FT design composite concrete deck on timber bridge 600/m 2 40 FT design bridge demolition 2000 each Permanent bridge structure 800/m 2 80 Table 3. Discounted present-value (PV) cost of replacement for a typical timber bridge option single lane, 10 m overall length structure and 4.5 m overall width (deck area = 45 m 2 ) for an 80-year life benefit. PV ($) Discount Rate Year Actual ($) Complete timber replacement Replace runners 5-yearly Replace runners and deck 10-yearly Bridge demolition and complete timber superstructure replacement 20-yearly abutment replacement 40-yearly Total cost ($) Table 4. Discounted present-value (PV) cost for a typical Forestry Tasmania composite bridge option and permanent material bridge option single lane, 10 m overall length structure and 4.5 m overall width (deck area = 45 m 2 ) for an 80-year life benefit. PV ($) Discount Rate Year Actual ($) Forestry Tasmania composite concrete deck on timber bridge Complete replacement Bridge demolition Complete replacement Total cost ($) Permanent material bridge Complete replacement Total cost ($) Tasforests Vol

3 is performed using typical costs and a common bridge situation (Table 2). Table 3 provides total and discounted costs over time for a typical timber bridge. The total costs allow for four 20-year replacement cycles for the timber bridge to provide a total of 80 years life benefit. Table 4 provides total and discounted costs over time for a typical FT composite bridge option assuming two 40-year replacement cycles to again provide a total of 80 years life benefit. A valid cost comparison of each bridge option requires that costing to achieve the same benefit be performed. The permanent material bridge option in Table 4 assumes a design life of 80 years. The FT composite concrete deck on timber bridge option gives the lowest total presentvalue cost for discount rates up to 7%. This suggests that it is the most economic option based on a whole-of-life cost analysis. Actual costs using both contracted prices received from the tender box and day-labour construction have confirmed a characteristic construction cost of around $600/m 2. Design concept The basic premise of the FT composite concrete deck on timber bridge design is that the design life of the timber stringers is doubled from 20 years in a timber bridge to 40 years by placing a concrete deck over the stringers and keeping the stringers dry. This reduces the rate of rot and decay in the stringer, which is the most common cause of stringer failure. The design features are: 1. Placement of concrete deck over the stringers to shed the water (Photo 1a, 1b; Figure 1). Photo 1a. Completed composite concrete and timber bridge. Tasforests Vol

4 Figure 1. Concrete deck on timber stringers. Photo 1b. Deck stringers only. Tasforests Vol

5 2. Placement of concrete abutment curtain wall with impact angle to prevent water infiltration into the ends of the stringers, which is the greatest area of rot in the stringer (Photo 2; Figure 2). 3. Polystyrene foam placed beneath the curtain wall to prevent cracking of the abutment wall after settlement of the abutment (Photo 2; Figure 2). 4. Overhanging kerb with drip edge and aluminium flashing draped over the outermost stringers to protect these from moisture (Photo 1a; Figure 1). Figure 2. Concrete abutment curtain wall. Photo 2. Completed abutment curtain wall. Tasforests Vol

6 5. Overhanging deck scuppers to keep deck run-off away from the outermost stringers (Photo 1a). 6. Timber greasing of end grains and installation of anti-fungal boron 'polesaver' rods for all timber components. 7. Stringers to be 'let in' to abutments either by cutting out of the abutment log or tapering of the stringer ends to prevent slabbing of the bottom of the stringer. 8. Provision of shear connectors between the tops of the stringers and concrete deck to provide composite action (Photo 3; Figure 3). This has resulted in an increased span capacity of two to three metres for a given stringer configuration (mid-span stringer diameter and number of stringers). 9. Shear connector detail to allow for stringer shrinkage and avoid punching of the shear connectors into the concrete deck (Figure 3). 10. Deck hold-down bolts to allow for stringer shrinkage (Photo 3; Figure 4). These design features are expected to increase the service life of the stringers from 20 to 40 years. There is enough evidence from existing structures in the field to support this expectation. The bridge crossing the Little Rapid River approximately 17.5 km from the start of the South Tayatea Road in the Circular Head District was built in This two-span structure has a concrete deck cast over four timber stringers on each span. Field inspections indicate that the stringers are dry and show very little deterioration for 23-yearold stringers. Timber bridges nearby of a similar age and working environment show a marked deterioration and are nearing the end of their useful life. The timber abutments of the bridge are still subject to ground moisture and therefore become the weak link in the structure although 40 years is a common design life for a crib abutment. Standard timber detailing to extend the life of the abutment is now the focus. Photo 3. Deck with shear connectors and hold-down bolts. Tasforests Vol

7 Shear connectors are added to provide composite action between the timber stringers and the concrete deck which is cast on site. Effectively, this results in the requirement for a smaller timber stringer for a given span. This is particularly important where the availability of long, large diameter stringers is restricted. Table 5 highlights the effect of composite and non-composite beam action using the design concept. Table 5. Span tables comparing composite and non-composite action. Mid-span Required span using Required span using beam diameter composite action non-composite action 400 mm up to 7.5 m up to 6.5 m 500 mm m m 600 mm m m 700 mm m m Figure 3. Shear connector detail. Figure 4. Deck hold-down detail. Tasforests Vol

8 Maintenance requirements Specific maintenance requirements for the composite concrete timber bridge are: Periodic tightening of the deck hold-down bolts as the timber stringers shrink. Cleaning of bridge scuppers and replacement of aluminium flashing if required. Replacement of anti-fungal boron rods in the abutments. The normal maintenance requirements of a timber bridge still apply. These may include: Periodic inspection of the bridge opening to remove flood obstructions and allow circulation of air to reduce shade and damp. Maintenance of the road approaches to minimise mud and run-off onto the bridge deck and adverse impact loading. Conclusion Experiences to date have indicated that the composite timber bridge with reinforced concrete deck is a viable bridge alternative in terms of mid-range cost and life compared with timber bridges and bridges in permanent materials. Design principles that minimise the rate of timber decay in the timber stringers by encasing the ends of the stringers in concrete and shedding water away from the stringers is expected to at least double the life of the stringers to an estimated design life of 40 years. Acknowledgements Ron Neve and Steve Smedley of Engineering Branch provided background information and drafting support. Structural analysis of the FT composite concrete deck on timber bridge was carried out by Peter Wood of Wood Brownley & Associates Civil Engineers under the technical direction of Ron Neve. Tasforests Tasforests Vol

Design of Bridges. Introduction. 3 rd to 4 th July 2012. Lecture for SPIN Training at the University of Dar es Salaam

Design of Bridges. Introduction. 3 rd to 4 th July 2012. Lecture for SPIN Training at the University of Dar es Salaam Design of Bridges Introduction 3 rd to 4 th July 2012 1 FUNCTION OF A BRIDGE To connect two communities which are separated by streams, river, valley, or gorge, etc. 2 EVOLUTION OF BRIDGES 1. Log Bridge

More information

How to Identify, Evaluate & Repair Shrinkage Cracks in Poured Concrete

How to Identify, Evaluate & Repair Shrinkage Cracks in Poured Concrete How to Identify, Evaluate & Repair Shrinkage Cracks in Poured Concrete What is concrete shrinkage cracking, how and where does it occur? Are concrete floor cracks a structural problem? How to recognize

More information

BRIDGES ARE relatively expensive but often are

BRIDGES ARE relatively expensive but often are Chapter 10 Bridges Chapter 10 Bridges Bridg Bridges -- usually the best, but most expensive drainage crossing structure. Protect bridges against scour. BRIDGES ARE relatively expensive but often are the

More information

Index 20010 Series Prestressed Florida-I Beams (Rev. 07/12)

Index 20010 Series Prestressed Florida-I Beams (Rev. 07/12) Index 20010 Series Prestressed Florida-I Beams (Rev. 07/12) Design Criteria AASHTO LRFD Bridge Design Specifications, 6th Edition; Structures Detailing Manual (SDM); Structures Design Guidelines (SDG)

More information

Bridge Type Selection

Bridge Type Selection Bridge Type Selection The major consideration for bridge type selection for bridges on the State Aid system is initial cost. Future maintenance costs, construction time, and location are considered when

More information

MILMAN & ASSOCIATES STRUCTURAL CONSULTING ENGINEERS/ PROJECT MANAGERS

MILMAN & ASSOCIATES STRUCTURAL CONSULTING ENGINEERS/ PROJECT MANAGERS MILMAN & ASSOCIATES STRUCTURAL CONSULTING ENGINEERS/ PROJECT MANAGERS May 29, 2013 Revision B Structural Guideline for Design and Installation Holes in Composite Floor Slab Terminal 3, Departure Level

More information

Timber Decks. Technical Note. March 2007

Timber Decks. Technical Note. March 2007 Timber Decks Technical Note. March 2007 This Technical Note contains general information for residential timber decks and floor frame structures for veranda s, patios etc which are exposed to the weather.

More information

DESIGN OF SLABS. 3) Based on support or boundary condition: Simply supported, Cantilever slab,

DESIGN OF SLABS. 3) Based on support or boundary condition: Simply supported, Cantilever slab, DESIGN OF SLABS Dr. G. P. Chandradhara Professor of Civil Engineering S. J. College of Engineering Mysore 1. GENERAL A slab is a flat two dimensional planar structural element having thickness small compared

More information

Post and Beam Construction

Post and Beam Construction Post and Beam Construction A Presentation By the Canadian Wood Council Canadian Conseil Wood canadien Council du bois Early settlers introduced the concept of post and beam construction in North America

More information

Safe & Sound Bridge Terminology

Safe & Sound Bridge Terminology Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries

More information

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION PART 8000 - PRECAST CONCRETE TABLE OF CONTENTS Item Number Page 8100 PRECAST CONCRETE CONSTRUCTION - GENERAL 8-3 8101 General

More information

~iffiui ~ Bridge Condition Survey. Inspection Date: 21 May 2003 District: San Angelo County: Tom Green Highway:

~iffiui ~ Bridge Condition Survey. Inspection Date: 21 May 2003 District: San Angelo County: Tom Green Highway: Texas Depadment of Transpo,tation Bridge Condition Survey Inspection Date: 21 May 2003 District: San Angelo County: Tom Green Highway: Irving Street Facility Name: Lone Wolf Bridge Structure Number: B00315-031

More information

STRUCTURES ENGINEERING DESIGN MANUAL

STRUCTURES ENGINEERING DESIGN MANUAL STRUCTURES ENGINEERING DESIGN MANUAL Denmark River Bridge No. 86A STRUCTURES ENGINEERING Document No: 3912/03 STRUCTURES ENGINEERING DESIGN MANUAL This manual is owned and controlled by the Senior Engineer

More information

CURRENT PRACTICE SHEET

CURRENT PRACTICE SHEET CURRENT PRACTICE SHEET INTRODUCTION An expansion joint can be defined as a device to support the surfacing, or to provide a running surface, across the expansion gap, ie the area between adjacent spans

More information

FEBRUARY 2014 LRFD BRIDGE DESIGN 4-1

FEBRUARY 2014 LRFD BRIDGE DESIGN 4-1 FEBRUARY 2014 LRFD BRIDGE DESIGN 4-1 4. STRUCTURAL ANALYSIS AND EVALUATION The analysis of bridges and structures is a mixture of science and engineering judgment. In most cases, use simple models with

More information

Chapter 2 Basis of design and materials

Chapter 2 Basis of design and materials Chapter 2 Basis of design and materials 2.1 Structural action It is necessary to start a design by deciding on the type and layout of structure to be used. Tentative sizes must be allocated to each structural

More information

Figure A. Maximum load testing of new precast concrete floor plank system

Figure A. Maximum load testing of new precast concrete floor plank system Load Testing of Precast Concrete Plank By Peter Gorgas, E.I.T. Figure A. Maximum load testing of new precast concrete floor plank system Overview Testing was performed in July 2012 at Northeast Precast

More information

Photo 2. View showing flour mill, machine shed, veranda and saw mill + storage shed.

Photo 2. View showing flour mill, machine shed, veranda and saw mill + storage shed. May 7,2015 KSANDER & ASSOCIATES CONSULTING PROFESSIONAL ENGINEERS 130 HUINTER STREET, UNIT 103, PETERBOROUGH, ONTARIO K9H2K8 TELEPHONE (705) 743-9221 FAX 743-0904 Ontario Region Conservation Authority

More information

G VYCOR DECK PROTECTOR. For longer lasting decks, install Grace Vycor Deck Protector. It s an easy add-on to your deck projects.

G VYCOR DECK PROTECTOR. For longer lasting decks, install Grace Vycor Deck Protector. It s an easy add-on to your deck projects. For longer lasting decks, install Grace Vycor Deck Protector. It s an easy add-on to your deck projects. G VYCOR DECK PROTECTOR Self-Adhered Flashing NEW FROM THE MAKERS OF G Ice & Water Shield I Moisture

More information

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL 7.0 7.1 GENERAL For the purpose of this manual, culverts are defined as structures that are completely surrounded by soil and located below the surface of the roadway parallel to the general direction

More information

US 51 Ohio River Bridge Engineering and Environmental Study

US 51 Ohio River Bridge Engineering and Environmental Study US 51 Ohio River Bridge Engineering and Environmental Study ITEM NOS. 1-100.00 & 1-1140.00 Prepared by: Michael Baker Jr., Inc. 9750 Ormsby Station Rd Louisville, KY 40223 August 16, 2013 Table of Contents

More information

201 WATER STREET FORWARDERS MUSEUM AND VISITORS INFORMATION CENTRE

201 WATER STREET FORWARDERS MUSEUM AND VISITORS INFORMATION CENTRE STRUCTURAL INSPECTION REPORT DRAFT 201 WATER STREET FORWARDERS MUSEUM AND VISITORS INFORMATION CENTRE TOWN OF PRESCOTT Date: November 2013 GENIVAR No.: 131-20617-00 2611 Queensview Drive, Suite 300, Ottawa,

More information

Detailing of Reinforcment in Concrete Structures

Detailing of Reinforcment in Concrete Structures Chapter 8 Detailing of Reinforcment in Concrete Structures 8.1 Scope Provisions of Sec. 8.1 and 8.2 of Chapter 8 shall apply for detailing of reinforcement in reinforced concrete members, in general. For

More information

National Council of Examiners for Engineering and Surveying. Principles and Practice of Engineering Structural Examination

National Council of Examiners for Engineering and Surveying. Principles and Practice of Engineering Structural Examination Structural Effective Beginning with the April 2011 The structural engineering exam is a breadth and exam examination offered in two components on successive days. The 8-hour Vertical Forces (Gravity/Other)

More information

Optimum proportions for the design of suspension bridge

Optimum proportions for the design of suspension bridge Journal of Civil Engineering (IEB), 34 (1) (26) 1-14 Optimum proportions for the design of suspension bridge Tanvir Manzur and Alamgir Habib Department of Civil Engineering Bangladesh University of Engineering

More information

Elevated Roads for Sri Lanka

Elevated Roads for Sri Lanka Elevated Roads for Sri Lanka M.T.R. Jayasinghe (Senior Professor, Structural Engineering, University of Moratuwa) Senior Professor M.T.R. Jayasinghe is a Professor of Structural Engineering, University

More information

Wood Projects Outdoors. Post Hole Specifications. Deck Span Tables. www.jon Eakes.com

Wood Projects Outdoors. Post Hole Specifications. Deck Span Tables. www.jon Eakes.com Wood Projects Outdoors Post Hole Specifications & Deck Span Tables www.jon Eakes.com Building Fences The depth of the fence posts into the ground must be at least one foot below the frost level for your

More information

OVERVIEW OF TMH19: DRAFT STANDARD FOR THE VISUAL ASSESSMENT OF ROAD STRUCTURES

OVERVIEW OF TMH19: DRAFT STANDARD FOR THE VISUAL ASSESSMENT OF ROAD STRUCTURES ROAD PAVEMENTS FORUM TWENTY-FIFTH MEETING 7 May 2013 OVERVIEW OF TMH19: DRAFT STANDARD FOR THE VISUAL ASSESSMENT OF ROAD STRUCTURES Michael Roux (CSIR Built Environment) Acknowledgements SANRAL Team Members:

More information

Fifteen years experience of design, production and assembling of prestressed Bridge decks in Timber

Fifteen years experience of design, production and assembling of prestressed Bridge decks in Timber Fifteen years experience of design, production and assembling of pre-stressed Bridge decks in Timber P. Jacobsson 1 Fifteen years experience of design, production and assembling of prestressed Bridge decks

More information

REHABILITATION PACKAGE 1-a

REHABILITATION PACKAGE 1-a 1-a WINONA BRIDGE (BRIDGE 5900) REHABILITATION PACKAGE 1-a Rehab option 1-a is a rehabilitation package whereby all spans of the existing structure would be rehabilitated to the degree feasible and strengthened

More information

Baton Rouge Foundation Repair

Baton Rouge Foundation Repair Baton Rouge Foundation Repair 13822 Florida Blvd Bldg 3 Baton Rouge, LA 70819 Baton Rouge Foundation Repair offers services to correct the settlement of both Slab foundations and Pier & Beam foundations

More information

Bridge Structural Rehabilitation Using FRP Laminates

Bridge Structural Rehabilitation Using FRP Laminates Bridge Structural Rehabilitation Using FRP Laminates South Santiam River Quartzville Road, Linn County Linn County Road Department 2011 Cooperative Partnerships Making Linn County a Better Place to Live

More information

Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing

Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing 1 Most basements show some signs of leaking and cracking. Through the years, problems with water, poor soils, grading, drainage and possible settling affect the integrity of a basement. Being able to recognize

More information

Remote Monitoring of Soil Pressures on Bridge Footings

Remote Monitoring of Soil Pressures on Bridge Footings More Info at Open Access Database www.ndt.net/?id=18252 Remote Monitoring of Soil Pressures on Bridge Footings Michael DAVIDSON 1, Zhihui ZHU 2, Issam HARIK 3, Charlie SUN 4, Kevin SANDEFUR 5 1 Bridge

More information

APPENDIX H DESIGN CRITERIA FOR NCHRP 12-79 PROJECT NEW BRIDGE DESIGNS

APPENDIX H DESIGN CRITERIA FOR NCHRP 12-79 PROJECT NEW BRIDGE DESIGNS APPENDIX H DESIGN CRITERIA FOR NCHRP 12-79 PROJECT NEW BRIDGE DESIGNS This appendix summarizes the criteria applied for the design of new hypothetical bridges considered in NCHRP 12-79 s Task 7 parametric

More information

Report on Sanctuary/Chancel Crawl Space Inspection. St. John in The Wilderness, 2896 Old Lakeshore Road Bright s Grove. Project No.

Report on Sanctuary/Chancel Crawl Space Inspection. St. John in The Wilderness, 2896 Old Lakeshore Road Bright s Grove. Project No. Report on Sanctuary/Chancel Crawl Space Inspection St. John in The Wilderness, 2896 Old Lakeshore Road Bright s Grove Project No. E112056 1. Background St. John in the Wilderness (SJITW) is considering

More information

BUILD A CARPORT. 2 - Planning the carport. 3 - Designing the carport

BUILD A CARPORT. 2 - Planning the carport. 3 - Designing the carport BUILD A CARPORT You only need basic DIY and woodworking skills to build a carport. The most important part of the job is setting the supporting posts truly vertical - a job for which another pair of hands

More information

1 DESIGN FACTORS THE RUBEROID BLUE BOOK 1

1 DESIGN FACTORS THE RUBEROID BLUE BOOK 1 1 DESIGN FACTORS 1.1 FALLS AND DRAINAGE 1.2 THERMAL DESIGN 1.3 VAPOUR CONTROL DESIGN GUIDE 1.4 TRAPPED MOISTURE 1.5 MOVEMENT AND MEMBRANES 1.6 WIND 1.7 WIND ATTACHMENT DESIGN GUIDE 1.8 FIRE 1.9 ROOF RENEWAL

More information

Formwork for Concrete

Formwork for Concrete UNIVERSITY OF WASHINGTON DEPARTMENT OF CONSTRUCTION MANAGEMENT CM 420 TEMPORARY STRUCTURES Winter Quarter 2007 Professor Kamran M. Nemati Formwork for Concrete Horizontal Formwork Design and Formwork Design

More information

Field Damage Inspection and Static Load Test Analysis of Jiamusi Highway Prestressed Concrete Bridge in China

Field Damage Inspection and Static Load Test Analysis of Jiamusi Highway Prestressed Concrete Bridge in China Advanced Materials Research Vols. 163-167 (2011) pp 1147-1156 Online available since 2010/Dec/06 at www.scientific.net (2011) Trans Tech Publications, Switzerland doi:10.4028/www.scientific.net/amr.163-167.1147

More information

2006-2008 MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS

2006-2008 MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS 2006-2008 MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS GENERAL 10/16/2008 The listed average unit prices are based on the

More information

STRUCTURAL ASSESSMENT. Full Metal Jacket Building 0 Prince Street, Alexandria, VA

STRUCTURAL ASSESSMENT. Full Metal Jacket Building 0 Prince Street, Alexandria, VA STRUCTURAL ASSESSMENT FOR Full Metal Jacket Building 0 Prince Street, Prepared by: ALPHA CORPORATION (Alpha) 1850 S. Loudoun Street, Suite 200 Winchester, VA 22601 540-723-0704 September 22, 2010 J. Michael

More information

NCMA TEK CONCRETE MASONRY FOUNDATION WALL DETAILS. TEK 5-3A Details (2003)

NCMA TEK CONCRETE MASONRY FOUNDATION WALL DETAILS. TEK 5-3A Details (2003) NCMA TEK National Concrete Masonry Association an information series from the national authority on concrete masonry technology CONCRETE MASONRY FOUNDATION WALL DETAILS TEK 5-3A Details (2003) Keywords:

More information

EAST LYME HIGH SCHOOL

EAST LYME HIGH SCHOOL Overview: 1971 N 1966 GYM 1966 CLASSROOM WING 1966 AUD. 1971 GYM 1998 1998 POOL EAST LYME HIGH SCHOOL Original 1966 Building: The original East Lyme High School was constructed in 1966 and was composed

More information

The following sketches show the plans of the two cases of one-way slabs. The spanning direction in each case is shown by the double headed arrow.

The following sketches show the plans of the two cases of one-way slabs. The spanning direction in each case is shown by the double headed arrow. 9.2 One-way Slabs This section covers the following topics. Introduction Analysis and Design 9.2.1 Introduction Slabs are an important structural component where prestressing is applied. With increase

More information

609 West Rock Road, Radford,VA 24141 540-633-5000 / (fax) 540-731-3712 RECOMMENDED ATTACHMENTS & CONNECTION DETAILS

609 West Rock Road, Radford,VA 24141 540-633-5000 / (fax) 540-731-3712 RECOMMENDED ATTACHMENTS & CONNECTION DETAILS 609 West Rock Road, Radford,VA 24141 540-633-5000 / (fax) 540-731-3712 RECOMMENDED ATTACHMENTS & CONNECTION DETAILS INDEX OF DRAWINGS SECTION A: A-1 = METAL TRACK TO PANEL ATTACHMENT A-2 = WOOD PLATE TO

More information

Evaluation and Field Load Testing of Timber Railroad Bridge

Evaluation and Field Load Testing of Timber Railroad Bridge Transportation Research Record 1696 Paper No. 5B0112 323 Evaluation and Field Load Testing of Timber Railroad Bridge Terry J. Wipf, Michael A. Ritter, and Douglas L. Wood Several spans of a 60-year-old

More information

Evaluation of Appropriate Maintenance, Repair and Rehabilitation Methods for Iowa Bridges

Evaluation of Appropriate Maintenance, Repair and Rehabilitation Methods for Iowa Bridges T. J. Wipf, F. S. Fanous, F. W. Klaiber, A. S. Eapen Evaluation of Appropriate Maintenance, Repair and Rehabilitation Methods for Iowa Bridges April 2003 Sponsored by the Iowa Department of Transportation

More information

Introduction. Eurocodes. Specification. Cost

Introduction. Eurocodes. Specification. Cost Introduction Eurocodes Specification Cost Structural Eurocodes BS EN 1990 (EC0): BS EN 1991 (EC1): Basis of structural design Actions on Structures BS EN 1992 (EC2): BS EN 1993 (EC3): BS EN 1994 (EC4):

More information

LOAD TESTING OF SOME NEW BRIDGES IN LATVIA

LOAD TESTING OF SOME NEW BRIDGES IN LATVIA LOAD TESTING OF SOME NEW BRIDGES IN LATVIA Edmunds Akimovs, Civ.Eng., Bridge Engineer, Consulting Company Inzenierbuve, Address: Azenes st. 20, Riga, LV1048, Latvia. E-mail: eakimovs@inzenierbuve.lv Ainars

More information

9.3 Two-way Slabs (Part I)

9.3 Two-way Slabs (Part I) 9.3 Two-way Slabs (Part I) This section covers the following topics. Introduction Analysis and Design Features in Modeling and Analysis Distribution of Moments to Strips 9.3.1 Introduction The slabs are

More information

Reinforced Concrete Slab Design Using the Empirical Method

Reinforced Concrete Slab Design Using the Empirical Method Reinforced Concrete Slab Design Using the Empirical Method BridgeSight Solutions for the AASHTO LRFD Bridge Design Specifications BridgeSight Software TM Creators of effective and reliable solutions for

More information

Snake River Bridge Load Test Addressing Bridge Management Issues WBES 2015 Reno, NV

Snake River Bridge Load Test Addressing Bridge Management Issues WBES 2015 Reno, NV Snake River Bridge Load Test Addressing Bridge Management Issues WBES 2015 Reno, NV Brice Carpenter, P.E. Bridge Diagnostics, Inc. 1995 57 th Court North, Suite 100 Boulder, CO 80301 (303) 494-3230 bricec@bridgetest.com

More information

STRUCTURAL ASSESSMENT REPORT BOLINAS MARINE STATION - BOLINAS, CALIFORNIA

STRUCTURAL ASSESSMENT REPORT BOLINAS MARINE STATION - BOLINAS, CALIFORNIA STRUCTURAL ASSESSMENT REPORT BOLINAS MARINE STATION - BOLINAS, CALIFORNIA College of Marin c/o Swinerton Management & Consulting P.O. Box 144003 835 College Avenue, Building MS-3 Kentfield, California

More information

Document type: Practice Note Title: External and internal membranes Document number: AC2234 Version: 5. 1. Purpose

Document type: Practice Note Title: External and internal membranes Document number: AC2234 Version: 5. 1. Purpose Document type: Practice Note Title: External and internal membranes Document number: AC2234 Version: 5 1. Purpose The purpose of this practice note is to address the incidence of deck and roof membrane

More information

Chapter 3 Pre-Installation, Foundations and Piers

Chapter 3 Pre-Installation, Foundations and Piers Chapter 3 Pre-Installation, Foundations and Piers 3-1 Pre-Installation Establishes the minimum requirements for the siting, design, materials, access, and installation of manufactured dwellings, accessory

More information

FLOOR MAINTENANCE GUIDE EXPECTATIONS AVOIDING PROBLEMS

FLOOR MAINTENANCE GUIDE EXPECTATIONS AVOIDING PROBLEMS No. 8 Brands Hatch Close Kyalami Business Park Kyalami Tel: 011 466 0701 Fax: 011 466 2919 Email: nici@forestflooring.co.za FLOOR MAINTENANCE GUIDE EXPECTATIONS AVOIDING PROBLEMS Please keep this folder

More information

STANDARD OPEN PATIO COVER

STANDARD OPEN PATIO COVER STANDARD OPEN PATIO COVER BUILDING & SAFETY DIVISION 201 E. LA HABRA BLVD. LA HABRA, CA 90631 62-90-9710 Call Before You Dig 1-800-227-2600 PLEASE NOTE: This information Bulletin is made available to assist

More information

INFORMATION SHEET ON TERMITES & TERMITE MANAGEMENT PROCEDURES

INFORMATION SHEET ON TERMITES & TERMITE MANAGEMENT PROCEDURES INFORMATION SHEET ON TERMITES & TERMITE MANAGEMENT PROCEDURES IMPORTANT INFORMATION: The Australian Standard AS 3660.2 Protection of buildings from subterranean termites provides details for minimising

More information

Ross River Suspension Bridge Ross River, Yukon. Life Cycle Cost Analysis

Ross River Suspension Bridge Ross River, Yukon. Life Cycle Cost Analysis DNA project managers planners architects engineers David Nairne + Associates Ltd Suite 250 171 W Esplanade North Vancouver British Columbia Canada V7M 3J9 T 604 984 3503 F 604 984 0627 E dna@ davidnairne.com

More information

Page & Turnbull imagining change in historic environments through design, research, and technology

Page & Turnbull imagining change in historic environments through design, research, and technology DCI+SDE STRUCTURAL EVALUATIONS OFFICE BUILDING, TOOL SHED & WATER TANK, AND BLACKSMITH & MACHINE SHOP BUILDINGS SAN FRANCISCO, CALIFORNIA [14290] PRIMARY PROJECT CONTACT: H. Ruth Todd, FAIA, AICP, LEED

More information

Residential Decks. Planning and Development Services Department

Residential Decks. Planning and Development Services Department Building Safety Division 8500 Santa Fe Drive Overland Park, KS 66212 (913) 895-6225 Fax (913) 895-5016 Email: permitservices@opkansas.org Planning and Development Services Department Residential Decks

More information

Roof Inspection Report 3840 Greenway Circle, Lawrence Kansas, 66046 Sauer-Danfoss Building

Roof Inspection Report 3840 Greenway Circle, Lawrence Kansas, 66046 Sauer-Danfoss Building Roof Inspection Report 3840 Greenway Circle, Lawrence Kansas, 66046 Sauer-Danfoss Building Prepared For: Ms Marilyn Bittenbender Colliers International 805 New Hampshire St Lawrence Kansas, 66046 Prepared

More information

Asphalt Shingle Application Requirements

Asphalt Shingle Application Requirements Alberta Allied Roofing Association Asphalt Shingle Application Requirements Section 1 Roof Decks 1.1 General Asphalt Shingles are not permitted to be installed directly over rigid insulation. When Asphalt

More information

THE STRUCTURAL ENGINEER

THE STRUCTURAL ENGINEER THE : 100 YEARS OF AN AUSTIN-CHANGING ICON By Nestor R. Rubiano, PhD, P.E., Structural Consultants, Inc., Austin, TX King Iron Bridge and Manufacturing Company of Cleveland, Ohio, and had a roadway width

More information

Preliminary steel concrete composite bridge design charts for Eurocodes

Preliminary steel concrete composite bridge design charts for Eurocodes Preliminary steel concrete composite bridge 90 Rachel Jones Senior Engineer Highways & Transportation Atkins David A Smith Regional Head of Bridge Engineering Highways & Transportation Atkins Abstract

More information

After reading this lesson you will be able to: 12.3 IMPORTANCE OF ROOF 12.4 TYPES OF ROOF IN A HOUSE

After reading this lesson you will be able to: 12.3 IMPORTANCE OF ROOF 12.4 TYPES OF ROOF IN A HOUSE 86 :: Certificate in Construction Supervision (CIVIL) 12 ROOF 12.1 INTRODUCTION The structure provided to cover the house surface (floor) is known as roof. For different situation and requirement, it is

More information

Structural Failures Cost Lives and Time

Structural Failures Cost Lives and Time Structural Failures Cost Lives and Time Recent failures of storage bins, silos and other structures highlight the need to increase awareness of hazards associated with these structures. Since 2010, one

More information

PENNDOT e-notification

PENNDOT e-notification PENNDOT e-notification Bureau of Project Delivery Bridge Design and Technology Division BRADD No. 036 October 18, 2013 Release of BRADD Version 3.2.0.0 The next release of PennDOT's Bridge Automated Design

More information

PRESTRESSED CONCRETE. Introduction REINFORCED CONCRETE CHAPTER SPRING 2004. Reinforced Concrete Design. Fifth Edition. By Dr. Ibrahim.

PRESTRESSED CONCRETE. Introduction REINFORCED CONCRETE CHAPTER SPRING 2004. Reinforced Concrete Design. Fifth Edition. By Dr. Ibrahim. CHAPTER REINFORCED CONCRETE Reinforced Concrete Design A Fundamental Approach - Fifth Edition Fifth Edition PRESTRESSED CONCRETE A. J. Clark School of Engineering Department of Civil and Environmental

More information

FINAL FAILURE INVESTIGATION WESTCHESTER NORTH LAGOON BRIDGE. Anchorage, Alaska

FINAL FAILURE INVESTIGATION WESTCHESTER NORTH LAGOON BRIDGE. Anchorage, Alaska FINAL FAILURE INVESTIGATION WESTCHESTER NORTH LAGOON BRIDGE Anchorage, Alaska August 2014 Prepared for: Municipality of Anchorage Project Management and Engineering P.O. Box 196650 Anchorage, Alaska 99519-6650

More information

STRUCTURAL ASSESSMENT

STRUCTURAL ASSESSMENT STRUCTURAL ASSESSMENT Project: 1432-1434 East Commerce St. Job. No: 122200 Location: San Antonio, TX Date: Dec. 10, 2012 Weather: Sunny, Windy,60 deg Performed by: Jeff Haughton and Frank Lamas, Alpha

More information

Structural Performance of Highway Bridges under Given Foundation Settlements

Structural Performance of Highway Bridges under Given Foundation Settlements ASEE 2014 Zone I Conference, April 3-5, 2014, University of Bridgeport, Bridgeport, CT, USA. Structural Performance of Highway Bridges under Given Foundation Settlements Zhan Su*; Qian Wang, PhD, PE, Assistant

More information

SPECIAL NOTE FOR ASPHALT WATERPROOFING MIX FOR BRIDGE-DECK OVERLAYS AND ADJACENT APPROACHES

SPECIAL NOTE FOR ASPHALT WATERPROOFING MIX FOR BRIDGE-DECK OVERLAYS AND ADJACENT APPROACHES SPECIAL NOTE FOR ASPHALT WATERPROOFING MIX FOR BRIDGE-DECK OVERLAYS AND ADJACENT APPROACHES 1. DESCRIPTION. Asphalt Waterproofing Mix (AWM) is a highly elastomeric, polymermodified, impermeable asphalt

More information

WI LEY Blackwell. Multi-storey Precast Concrete Framed Structures. Colin K. Jolly MSc, PhD, CEng, MICE, FIStructE

WI LEY Blackwell. Multi-storey Precast Concrete Framed Structures. Colin K. Jolly MSc, PhD, CEng, MICE, FIStructE Multi-storey Precast Concrete Framed Structures Kim S. Elliott BTech, PhD, CEng, MICE Colin K. Jolly MSc, PhD, CEng, MICE, FIStructE WI LEY Blackwell Contents Preface Notation Precast Concepts, History

More information

Figure 5-11. Test set-up

Figure 5-11. Test set-up 5.5. Load Procedure A uniform load configuration was used for the load tests. An air bag, placed on the top surface of the slab, was used for this purpose, and the load was applied by gradually increasing

More information

Chapter. Restoration of Damaged Structures

Chapter. Restoration of Damaged Structures 5 Chapter Restoration of Damaged Structures Bringing back a damaged structure to its pre-earthquake state and original strength is called restoration. This is the first step of building rehabilitation.

More information

IH-635 MANAGED LANES PROJECT, SEG. 3.2

IH-635 MANAGED LANES PROJECT, SEG. 3.2 IH-635 MANAGED LANES PROJECT, SEG. 3.2 Location: Dallas, Texas Owner: Texas Department of Transportation Client: Ferrovial Agroman Construction Cost: $1 Billion Construction Completion Date: December,

More information

5 ALTERNATIVE SOLUTIONS AND EVALUATION

5 ALTERNATIVE SOLUTIONS AND EVALUATION Page 23 5 ALTERNATIVE SOLUTIONS AND EVALUATION The process used for the assessment and evaluation of the alternatives follows the procedures of the Municipal Class EA, as described below: Identify a reasonable

More information

BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM

BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM Swaminathan Srinivasan, P.E., M.ASCE H.C. Nutting/Terracon David Tomley, P.E., M.ASCE KZF Design Delivering Success for

More information

Chapter 5 Bridge Deck Slabs. Bridge Engineering 1

Chapter 5 Bridge Deck Slabs. Bridge Engineering 1 Chapter 5 Bridge Deck Slabs Bridge Engineering 1 Basic types of bridge decks In-situ reinforced concrete deck- (most common type) Pre-cast concrete deck (minimize the use of local labor) Open steel grid

More information

RAILROAD DAMAGE FROM THE OCTOBER 16, 1999 HECTOR MINE EARTHQUAKE

RAILROAD DAMAGE FROM THE OCTOBER 16, 1999 HECTOR MINE EARTHQUAKE RAILROAD DAMAGE FROM THE OCTOBER 16, 1999 HECTOR MINE EARTHQUAKE By: William G. Byers, P.E. Burlington Northern and Santa Fe Railway 4515 Kansas Avenue Kansas City, Kansas 66106 Phone (913) 551-4070 Fax

More information

Technical Assignment 2 TABLE OF CONTENTS

Technical Assignment 2 TABLE OF CONTENTS 2 TABLE OF CONTENTS Executive Summary...3 Introduction..5 Gravity Loads......6 Design Codes......7 Materials..8 Existing Structural System.. 10 Existing Floor System 15 Alternate Floor Framing Systems...17

More information

Design of Steel Structures Prof. S.R.Satish Kumar and Prof. A.R.Santha Kumar. Fig. 7.21 some of the trusses that are used in steel bridges

Design of Steel Structures Prof. S.R.Satish Kumar and Prof. A.R.Santha Kumar. Fig. 7.21 some of the trusses that are used in steel bridges 7.7 Truss bridges Fig. 7.21 some of the trusses that are used in steel bridges Truss Girders, lattice girders or open web girders are efficient and economical structural systems, since the members experience

More information

Failing Coastal Wood Infrastructure on the Great Lakes

Failing Coastal Wood Infrastructure on the Great Lakes University of Wisconsin Sea Grant Institute Contact Gene Clark grclark@aqua.wisc.edu 715-392-3246 Failing Coastal Wood Infrastructure on the Great Lakes Gene Clark/UW Sea Grant Institute Introduction Many

More information

Since it was established in 1989, with a small manufacturing base in Qwa Qwa and a hire yard in Botswana, Uni-Span

Since it was established in 1989, with a small manufacturing base in Qwa Qwa and a hire yard in Botswana, Uni-Span formwork formwork Since it was established in 1989, with a small manufacturing base in Qwa Qwa and a hire yard in Botswana, Uni-Span has grown to become one of the major players in the scaffolding and

More information

Murrays Bay Wharf Investigation and Repairs - Options Assessment

Murrays Bay Wharf Investigation and Repairs - Options Assessment Report Murrays Bay Wharf Investigation and Repairs - Options Assessment Prepared for Auckland Council (Client) By Beca Ltd (Beca) 20 September 2013 Beca 2013 (unless Beca has expressly agreed otherwise

More information

PREVENTING GROUNDWATER POLLUTION: SECONDARY CONTAINMENT

PREVENTING GROUNDWATER POLLUTION: SECONDARY CONTAINMENT PREVENTING GROUNDWATER POLLUTION: SECONDARY CONTAINMENT PREVENTING GROUNDWATER POLLUTION IS EVERYONE S JOB! Even if our drinking water comes from rivers, lakes, or reservoirs, we need to be mindful of

More information

How to Install Hardwood Flooring Over a Sub Floor

How to Install Hardwood Flooring Over a Sub Floor How to Install Hardwood Flooring Over a Sub Floor Installation Preparation Instructions Read the entire instructions before starting your project. 1) INSPECT EACH PLANK (see fig. a) Wood is a natural product

More information

Analysis of the Interstate 10 Twin Bridge s Collapse During Hurricane Katrina

Analysis of the Interstate 10 Twin Bridge s Collapse During Hurricane Katrina Analysis of the Interstate 0 Twin Bridge s Collapse During Hurricane Katrina By Genda Chen, Emitt C. Witt III, David Hoffman, Ronaldo Luna, and Adam Sevi The Interstate 0 Twin Span Bridge over Lake Pontchartrain

More information

Note: All dimensions are nominal. All weights are for shipping purposes only. Availability is subject to change.

Note: All dimensions are nominal. All weights are for shipping purposes only. Availability is subject to change. CHANNEL DrAiNS Durable Designed for maximum durability and drainage, NDS Channel Drains are a proven alternative to traditional concrete drains. UV inhibitors in the grates, channel and component parts

More information

The better way to build TM. Installation Manual. FOUNDATION SIPs & FROST WALLS SIPs

The better way to build TM. Installation Manual. FOUNDATION SIPs & FROST WALLS SIPs The better way to build TM Installation Manual FOUNDATION SIPs & FROST WALLS SIPs February 2016 PWF FOUNDATION & FROST WALL SIPs Installation Manual Table of Contents Topics General Requirements...................................

More information

Wisconsin Building Products Evaluation

Wisconsin Building Products Evaluation Safety & Buildings Division 201 West Washington Avenue P.O. Box 2658 Madison, WI 53701-2658 Evaluation # 200813-O Wisconsin Building Products Evaluation Material Best Management Standards for Foundation

More information

How To Build A Luxury Apartment Complex In London

How To Build A Luxury Apartment Complex In London Post Tensioning Awards 2009 Project Summary Type of structure Location Architects Structural Engineer Residential with leisure suites including Swimming pool, Cinema, Virtual Golf, Wine Cellars, and Parking

More information

INTRODUCTION TO BEAMS

INTRODUCTION TO BEAMS CHAPTER Structural Steel Design LRFD Method INTRODUCTION TO BEAMS Third Edition A. J. Clark School of Engineering Department of Civil and Environmental Engineering Part II Structural Steel Design and Analysis

More information

March 19, 2014. Ms. Jean McDonald CAP Management 910 16th Street, Suite 1010 Denver, Colorado 80202

March 19, 2014. Ms. Jean McDonald CAP Management 910 16th Street, Suite 1010 Denver, Colorado 80202 Ms. Jean McDonald CAP Management 910 16th Street, Suite 1010 Denver, Colorado 80202 Re: Prospector s Point Walkway/Façade Repairs Martin/Martin, Inc Project No.: 13.0358.S.02 Ms. McDonald: Per your request

More information

SECTION 05 42 16 COLD-FORMED METAL DECK FRAMING Elevations Steel Deck Framing by Trex

SECTION 05 42 16 COLD-FORMED METAL DECK FRAMING Elevations Steel Deck Framing by Trex (Specifier Note: The purpose of this guide specification is to assist the specifier in correctly specifying cold-formed metal deck framing products and execution. The specifier needs to edit the guide

More information

Evaluation of Bridge Performance and Rating through Nondestructive

Evaluation of Bridge Performance and Rating through Nondestructive Evaluation of Bridge Performance and Rating through Nondestructive Load Testing Final Report Prepared by: Andrew Jeffrey, Sergio F. Breña, and Scott A.Civjan University of Massachusetts Amherst Department

More information

Requirements for Building Application Submission

Requirements for Building Application Submission THE DEVELOPMENT CONTROL AND PLANNING BOARD P O Box 597 Phone: 869 465-2277 Bladen Commercial Development Fax: 869 465-5842 Basseterre, St. Kitts Email: phyplskb@caribsurf.com To: Architects, Designers

More information

REPAIR AND RETROFIT OF BRIDGES DAMAGED BY THE 2010 CHILE MAULE EARTHQUAKE

REPAIR AND RETROFIT OF BRIDGES DAMAGED BY THE 2010 CHILE MAULE EARTHQUAKE Proceedings of the International Symposium on Engineering Lessons Learned from the 2011 Great East Japan Earthquake, March 1-4, 2012, Tokyo, Japan REPAIR AND RETROFIT OF BRIDGES DAMAGED BY THE 2010 CHILE

More information