Section 2.7 Contracts, Specifications, Quality Assurance and As-Built Documentation

Size: px
Start display at page:

Download "Section 2.7 Contracts, Specifications, Quality Assurance and As-Built Documentation"

Transcription

1 Section 2.7 Contracts, Specifications, Quality Assurance and As-Built Documentation Contents The Contents of this Section are as follows: page Introduction Construction Conditions of Contract and Specifications Engineering Drawing Presentation Survey Standards Quality Assurance and Inspection As-Built Documentation and Quality Assurance Record 5 November

2 2.7 Contracts, Specifications, Quality Assurance and As-Built Documentation Introduction The previous sections of Part 2 of this Code of Practice have discussed the engineering standards that Council believes will provide acceptable solutions, but not necessarily the only solutions, for the engineering works associated with subdivision or land use projects. Council will require in the Consent Conditions that these projects are properly documented and certified by an appropriate professional (refer Part 1 of the Code of Practice). This section of the Code of Practice will outline Council s requirements in relation to Construction Conditions of Contract and Specifications, Engineering Drawing Presentation, Quality Assurance and Inspection, As-Built Documentation and Quality Assurance Record Construction Conditions of Contract and Specifications If Council is to be a party to a Construction Contract, or if the works involved will eventually become the responsibility of Council, the General Conditions of Contract for construction will be NZS 3910 : 1987, Conditions of Contract for Building and Civil Engineering Construction. A number of Special Conditions of Contract will normally be required. The following list of Special Conditions is indicative only: Conditions of Tendering Type of Contract (e.g., Lump Sum or Measure and Value) Bonds Nomination of Engineer to the Contract Time Extensions Contract Period Liquidated Damages Insurance Health and Safety Traffic Management Quality Plans Programming of Work Other parts of a Construction Contract will include: The Schedule of Prices Basis of Payment Plant and Subcontractors Schedule Technical Specification November

3 The Technical Specification will detail the works to be completed under the Contract, the Standards to be applied and the means by which Standards will be measured. Reference will be made to Standard Specifications (NZS and TNZ) and/or Material Specifications if required. Council recommends that the advice of a suitably qualified professional be obtained when preparing and administering a Construction Contract. All construction documentation, and the Quality Control of works, will need to be certified by an appropriate professional, as discussed in Part 1 of this Code of Practice Engineering Drawing Presentation Drawings in support of land development and subdivision projects will be drawn on A1 Sheets (original size) at the following standard scales. The drawings will be of sufficient number and detail to adequately define the project. Road Plans 1:500, 1:250 Utility Service Plans 1:500, 1:250 Road Long Sections Service Long Sections Road Cross Sections 1:500 or 1:250 with a distortion of 5 to 10 to vertical scales 1:500 or 1:250 with a distortion of 5 to 10 to vertical scales 1:100 urban and rural Detail drawings shall utilise appropriate scales selected from any of the above or at 1:100, 1:50, 1:20 or 1:10. Draughting standards will comply with NZS/AS (1984) Technical drawing, Supplement No.3 (Jan 1984) Engineering Survey and Engineering Survey Design-Sewerage and Water Supply NZS/AS (1984) Technical drawing, Supplement No.4 (Jan 1984) Engineering Survey and Engineering Survey Design-Roads Survey Standards The following survey standards should be followed during the construction phase of a roading development. Survey Location of Control Points for Project These will be established by a Registered Surveyor from the national survey network for location, and for levels from the local level datum which will need to be confirmed on a project by project basis with the Hastings District Council. Once project control points are established these will be regarded as absolute in location and level accuracy for the purpose of control of location of features within the project. November

4 Setting Out Individual Lift or Location Pegs for Roading Works These will be set on a project by project basis. For roading works the final location will need to be within the tolerances set out below: Tolerances for setting out the work from the data supplied shall be: (a) Horizontal ± 10mm (b) Vertical ± 5mm Roading Construction Tolerances from lift pegs or other setting out points, which may include concrete kerb and channel or a fixed point of concrete kerbing, shall be as shown below. Reference shall also be made to the Transit New Zealand Specification TNZ B/2 : (a) Width Tolerances Unconstrained (i.e., no K & C) Constrained by K & C -20mm to + 100mm 0mm to + 20mm (b) Vertical Tolerances Kerb and Channel and footpaths - 5mm to + 5mm Pavement Layers Sub-base course Between Pavement Centreline and Pavement Edge Without Concrete With Concrete Channel Channel - 25mm + 5mm - 25mm + 5 mm Basecourse - 5 mm + 15 mm varies see note 1 Note 1 : Tolerance (i) at or close to the lip of channel - 5mm + 0mm (ii) at other locations on pavement - 5mm + 15mm Setting Out for Environmental Works These will be set on a project by project basis. For Environmental Works setting out for services will need to be within the following tolerances. Tolerances for setting out the work from the data supplied shall be: (a) Horizontal ± 50mm (b) Vertical ± 5mm November

5 2.7.5 Quality Assurance and Inspection The developer and his/her advisors are responsible for providing Council with Certifications of: standards of investigation, design and construction Quality Assurance. These must be provided for all engineering works associated with subdivision and land development, in accordance with Part 2 of this Code of Practice, and Section 4.0 of the District Plan. The Certification must be prepared by an appropriately qualified professional. If Council inspection of the facilities involved is required (in accordance with Sections 2.3, 2.4, 2.5 and 2.6 of this Code of Practice) the Construction documentation shall ensure that further to Clause of NZS 3910, the notification of readiness for inspection, recording, measuring and testing shall not be less than a minimum of 24 hours. Council will undertake any inspections and will advise the developer whether it is prepared to take responsibility for the development on behalf of the ratepayers of the Hastings District. Any areas where in the Councils view standards have not been met, will be notified to the developer for his action before compliance is recommended As-Built Documentation and Quality Assurance Record Council will require that the following documents are submitted by the developer with the required Certification by an appropriate professional (refer Part 1 of this Code of Practice) when applying for Subdivision Compliance or Code Compliance. As built drawings of all engineering works including earthworks, stormwater, sanitary sewer, water supply, and roading and traffic engineering (including subsoil drainage) to the standards required in Section For earthworks the As-builts will record the depth and location of fill, the position, type and size of any subsoil drains or structures including retaining walls, and the extent and location of cut batters. For stormwater and sanitary sewer the As-builts will detail the location of all property boundaries, pipe diameters and materials used, depths and date of completion, pumps, valves and control equipment (including manufacturers and date of manufacture), structures including manholes (giving levels of invert and lid), kerbs and sumps, and discharge points. The As-built plans for water supply will detail the location of all property boundaries, pipes, valves, hydrants and connections (including manufacturers and date of manufacture), pipe diameters and materials used, depths and date of completion. All specials made up shall be detailed on these plans. As-built plans of any rural water supply system and operating instructions shall be lodged with the Hastings District Council, who in this respect will act as librarian. November

6 For roading the As-Builts will detail the location of all property boundaries, the location and level of footpaths, kerbs, road centreline and structures including sumps. As-Builts will also provide the details of the pavement layers and the pavement sealing. Traffic engineering detail including the location of traffic islands, signs, streetlights and road marking must be provided. Each drawing will be clearly stamped as as built and signed by the person so certifying the same. Council will retain a copy of all as built drawings and Certification statements. If Computer Aided Drawing (CAD) has been used, A1 paper as built copies and computer file copy will be supplied in all cases. As-Builts will be based on co-ordinated data from permanent control points or measurement from co-ordinated property boundaries. The road centreline will be coordinated from permanent control points at no greater than 20m spacings. All locations will be dimensioned and shown on the plans. The tolerances shall be: (a) Horizontal ± 50mm (b) Vertical ± 5mm A summary of the Quality Assurance records obtained throughout the works will also be submitted when applying for Subdivision Compliance or Code Compliance. This will take the form of a report prepared by an appropriately qualified professional. The report will summarise the Quality Assurance Records and Standards achieved in all aspects of the project, in particular; - Earthworks (refer Section of the Code of Practice) - Stormwater (refer Section of the Code of Practice) - Sanitary Sewerage (refer Section of the Code of Practice) - Water Supply (refer to Sections and of the Code of Practice, in particular Testing, Cleaning and Disinfection, and Inspection During Construction) - Roading and Traffic Engineering (refer to Section of the Code of Practice, in particular , Inspection During Construction). In addition, if Council is not satisfied with the standard of information provided, any or all Quality Assurance records must be provided to Council with 24 hours upon receiving a written request to do so by Council. November

3. QUALITY ASSURANCE REQUIREMENTS

3. QUALITY ASSURANCE REQUIREMENTS 3. QUALITY ASSURANCE REQUIREMENTS 3.1 General This section covers the Kaipara District Council requirements for monitoring and testing of physical asset construction to ensure that the final asset delivered

More information

SECTION 5 DRAFTING STANDARDS

SECTION 5 DRAFTING STANDARDS SECTION 5 DRAFTING STANDARDS 1 SECTION FIVE TABLE OF CONTENTS Description Page TABLE OF CONTENTS... 5-2 GENERAL... 5-3 DRAFTING STANDARDS... 5-5 DRAFTING MINIMUM REQUIREMENTS HANDOUT... 5-8 2 GENERAL 1.

More information

MANUKAU CITY COUNCIL QUALITY ASSURANCE MANUAL FOR INSPECTION & RELEASE OF SUBDIVISIONS & LAND DEVELOPMENT PROJECTS

MANUKAU CITY COUNCIL QUALITY ASSURANCE MANUAL FOR INSPECTION & RELEASE OF SUBDIVISIONS & LAND DEVELOPMENT PROJECTS MANUKAU CITY COUNCIL QUALITY ASSURANCE MANUAL FOR INSPECTION & RELEASE OF SUBDIVISIONS & LAND DEVELOPMENT PROJECTS Reviewed and Revised October 2007 INTRODUCTION This document supersedes the 1992 edition

More information

TOPOGRAPHICAL SURVEY REPORT - PART OF L.R No. 7413/11 Done on February 2015 at International Union for Conservation of Nature (IUCN) Eastern African

TOPOGRAPHICAL SURVEY REPORT - PART OF L.R No. 7413/11 Done on February 2015 at International Union for Conservation of Nature (IUCN) Eastern African TOPOGRAPHICAL SURVEY REPORT - PART OF L.R No. 7413/11 Done on February 2015 at International Union for Conservation of Nature (IUCN) Eastern African Regional Office 01 CHAPTER ONE Checklist Page 2 of 8

More information

Greater Dublin Strategic Drainage Study Regional Drainage Policies - Volume 2 New Development

Greater Dublin Strategic Drainage Study Regional Drainage Policies - Volume 2 New Development 7 SPECIFICATIONS There is currently no Irish specification for construction of drainage works, or water supply works. There are several publications that give guidance on drainage works, such as the Building

More information

The checklist utilized by the Authority will be similar to that which is shown below. Project Name: Location: Consulting Engineering Firm:

The checklist utilized by the Authority will be similar to that which is shown below. Project Name: Location: Consulting Engineering Firm: Page 1 of 6 Section 1. PURPOSE This policy is an Engineering checklist of the Local Review Program for sanitary sewer improvement projects by the Bedford Regional Water Authority ( Authority ). Section

More information

ENGINEERING DESIGN GUIDELINES. for SUBDIVISIONS OR COMMERCIAL DEVELOPMENTS

ENGINEERING DESIGN GUIDELINES. for SUBDIVISIONS OR COMMERCIAL DEVELOPMENTS ENGINEERING DESIGN GUIDELINES for SUBDIVISIONS OR COMMERCIAL DEVELOPMENTS City of Birmingham Department of Planning, Engineering and Permits Engineering Division Office of the City Engineer 2008 TABLE

More information

Guide to Subdivision and Land Development

Guide to Subdivision and Land Development Guide to Subdivision and Land Development Fraser Thomas Ltd...... is a consulting company located in Manukau City which has provided Surveying, Engineering, Planning and Resource Management services in

More information

SPECIFICATION FOR CONSTRUCTION OF UNBOUND GRANULAR PAVEMENT LAYERS

SPECIFICATION FOR CONSTRUCTION OF UNBOUND GRANULAR PAVEMENT LAYERS TNZ B/02:2005 SPECIFICATION FOR CONSTRUCTION OF UNBOUND 1. SCOPE This specification shall apply to the construction of unbound granular pavement layers. The term pavement layer shall apply to any layer

More information

SECTION 01 78 29 AS-BUILT DOCUMENTATION

SECTION 01 78 29 AS-BUILT DOCUMENTATION SECTION 01 78 29 AS-BUILT DOCUMENTATION PART 1: GENERAL 1.01 AS-BUILTS Where identified as a product of the Work, provide as-built drawings adhering to the criteria provided here and in the special conditions.

More information

Urban Vehicle Crossing Application To be completed and fees paid for prior to approval

Urban Vehicle Crossing Application To be completed and fees paid for prior to approval Urban Vehicle Crossing Application To be completed and fees paid for prior to approval Applicant Details Name: Postal Address: Telephone Home: Work: Signed: Date: Proposed Contractor: Proposed Start Date:

More information

Specialised Data Specifications

Specialised Data Specifications Version 4.6.0 26 01 March 2015 SPECIALISED DATA SPECIFICATION have been created to document standards for specific types of spatial data that have requirements that may differ from, or be additional, to

More information

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0

More information

BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY

BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY MURRAY SHIRE COUNCIL BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY ADOPTED: 1 May 2012 1 BUILDING OVER OR NEAR WATER AND SEWER MAINS POLICY CONTENTS 1. Objective... 2 2. Requirements for Building Near

More information

Additional Services Agreement. Part 3: Schedule of our requirements

Additional Services Agreement. Part 3: Schedule of our requirements Additional Services Agreement Part 3: Schedule of our requirements Schedule of our requirements Part A Water Services 1 All water services All connections to our water mains, including those used for construction

More information

Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects

Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects March 2013 i Metropolitan Sewer District of Greater Cincinnati Wastewater Collection System Supplemental

More information

SUPPLEMENTAL SPECIFICATIONS CROSS SLOPE VERIFICATION:

SUPPLEMENTAL SPECIFICATIONS CROSS SLOPE VERIFICATION: September 22, 2009 Updated November 16, 2009 SUPPLEMENTAL SPECIFICATIONS CROSS SLOPE VERIFICATION: 1. DESCRIPTION: The cross slopes of the roadway are to be constructed as detailed in the plans and within

More information

Available in Base or Survey Standard or Survey Professional series with different modules add-ons to suit your technical requirement and budget.

Available in Base or Survey Standard or Survey Professional series with different modules add-ons to suit your technical requirement and budget. World First Leading the Surveying and Civil Engineering software application, civilcad 6 is the world first application of its kind to run in the Plug and Go concept. Delivered pre-installed on a customised

More information

24 Vesting of Assets and Asset Data

24 Vesting of Assets and Asset Data P age 892 24 Vesting of Assets and Asset Data 24.1 Asset Ownership Guidelines It is essential that AT's Asset Ownership Guidelines are read before reading the rest of this chapter. 24.2 Overview This Chapter

More information

Requirements for Building Application Submission

Requirements for Building Application Submission THE DEVELOPMENT CONTROL AND PLANNING BOARD P O Box 597 Phone: 869 465-2277 Bladen Commercial Development Fax: 869 465-5842 Basseterre, St. Kitts Email: phyplskb@caribsurf.com To: Architects, Designers

More information

CITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT

CITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT Page 1 CITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT CIVIC CENTRE 2141 MAJOR MACKENZIE DRIVE MAPLE ONTARIO L6A 1T1 905-832-2281 Page 2 SECTION 1 - GENERAL OBJECTIVES To provide

More information

ASSET MANAGEMENT GUIDE FOR PROJECT DESIGN FORMAT

ASSET MANAGEMENT GUIDE FOR PROJECT DESIGN FORMAT ASSET MANAGEMENT GUIDE FOR PROJECT DESIGN FORMAT 1. BACKGROUND There has been an increasing awareness of design features, which produce poor whole-of-life costs. These poor whole-of-life costs manifest

More information

Quick Guide to Application for Clearance for Drainage Works for issuance of Certificate of Statutory Completion (CSC) Minor Project

Quick Guide to Application for Clearance for Drainage Works for issuance of Certificate of Statutory Completion (CSC) Minor Project Quick Guide to Application for Clearance for Drainage Works for issuance of Certificate of Statutory Completion (CSC) Minor Project DOCUMENTS TO BE SUBMITTED FOR CSC All "As-built" or "As-constructed"

More information

Kansas City s Overflow Control Program

Kansas City s Overflow Control Program Kansas City s Overflow Control Program Kansas City Water Services Water Wastewater Stormwater 2 Water Services Department 1000 Positions 835 Employees 3 Utilities FY 13/14 Budget = $307 million Water Wastewater

More information

Standard terms and conditions

Standard terms and conditions Standard terms and conditions INTRODUCTION For the provision of a water service (Water Supply, Wastewater and Drainage) Under Section 73(2)(a) of the Water Services Act 2012, landowners may be entitled

More information

SANITARY SEWER BACKUP. Causes & Prevention

SANITARY SEWER BACKUP. Causes & Prevention SANITARY SEWER BACKUP Causes & Prevention A. PURPOSE The purpose of this publication is twofold: 1. It provides homeowners with basic information on the causes of sanitary sewer backups. 2. It provides

More information

UNIVERSITY OF WASHINGTON Facilities Services Design Guide. Civil. Topographical Survey. Design Evaluation. Construction Submittals

UNIVERSITY OF WASHINGTON Facilities Services Design Guide. Civil. Topographical Survey. Design Evaluation. Construction Submittals This section applies to design standards and procedures involved in the field location and plotting of all natural objects and surface improvements. This section also includes the requirements for submittal

More information

Asset Management Guide For Project Design Format

Asset Management Guide For Project Design Format NZ Transport Agency Page 1 of 6 Asset Management Guide For Project Design Format 1 Background There has been an increasing awareness of design features, which produce poor wholeof-life costs. These poor

More information

KAWERAU DISTRICT COUNCIL General Bylaw Part 9: On-site Wastewater Disposal Systems (2010)

KAWERAU DISTRICT COUNCIL General Bylaw Part 9: On-site Wastewater Disposal Systems (2010) KAWERAU DISTRICT COUNCIL General Bylaw Part 9: On-site Wastewater Disposal Systems (2010) Kawerau District Council General Bylaw Part 9: On-site Wastewater Disposal Systems (2010) Explanatory Statement

More information

CHAPTER 7: SUBDIVISION CONSTRUCTION, INSPECTION AND BONDING. 7.05 Subdivision Improvement Performance Bond Requirements

CHAPTER 7: SUBDIVISION CONSTRUCTION, INSPECTION AND BONDING. 7.05 Subdivision Improvement Performance Bond Requirements CHAPTER 7: SUBDIVISION CONSTRUCTION, INSPECTION AND BONDING 7.00 Construction 7.01 Inspection and Testing of Improvements 7.02 Approval of Improvements 7.03 City Engineer s Acceptance of All Improvements

More information

PART 5 : WASTEWATER DRAINAGE

PART 5 : WASTEWATER DRAINAGE Authorised by : City Waters Unit Manager Page 1 of 15 PART 5 : WASTEWATER DRAINAGE 5.1 INTRODUCTION This Manual sets out the basic design principles for drainage of wastewater. While some construction

More information

Council Policy. This Policy assists in the implementation of the Council Plan 2009-2013 Revised 2010, in particular Strategy 3.1.

Council Policy. This Policy assists in the implementation of the Council Plan 2009-2013 Revised 2010, in particular Strategy 3.1. Council Policy Council Policy Title: Council Policy Ref No: Council Policy Owner: Adopted by: Discharge of Pumped Subterranean Water Associated with Basements or Below-Ground Structures C/POL/INF/024 Director

More information

PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE

PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE REGION OF PEEL PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE Storm Sewer Design Criteria REVISED July 2009 PUBLIC WORKS STORM SEWER DESIGN CRITERIA TABLE OF CONTENTS 1.0

More information

CHAPTER 11 STORM DRAINAGE

CHAPTER 11 STORM DRAINAGE CHAPTER 11 STORM DRAINAGE SECTION 11 GENERAL 11.1 Scope. The provisions of this chapter shall govern the materials, design, construction and installation of storm drainage. 11.2 Where required. All roofs,

More information

DIVISION OF WATER QUALITY CONSTRUCTION GRANTS & LOANS SECTION FAST TRACK AUDIT CHECKLIST

DIVISION OF WATER QUALITY CONSTRUCTION GRANTS & LOANS SECTION FAST TRACK AUDIT CHECKLIST DIVISION OF WATER QUALITY CONSTRUCTION GRANTS & LOANS SECTION FAST TRACK AUDIT CHECKLIST CERTIFICATION 1. Did the engineer submit a certificate of completion utilizing the appropriate page of the issued

More information

Review of Civil Plant Management, Civil Construction Supervision, Civil Project Management, and Road Construction unit standards

Review of Civil Plant Management, Civil Construction Supervision, Civil Project Management, and Road Construction unit standards Page 1 of 8 Field Engineering and Technology Review of Civil Plant, Civil Construction, Civil Project, and Road Construction unit standards Existing classification Subfield Domain ID Civil Plant Operation

More information

SANITARY SEWER SPECIFICATIONS

SANITARY SEWER SPECIFICATIONS SANITARY SEWER SPECIFICATIONS OCTOBER 2003 HARVEST-MONROVIA WATER, SEWER, AND FIRE PROTECTION AUTHORITY SECTION 1.00 1.10 Purpose The purpose of this document is to assemble the sewer specifications, policies,

More information

SECTION 08000 STORM DRAINAGE TABLE OF CONTENTS

SECTION 08000 STORM DRAINAGE TABLE OF CONTENTS SECTION 08000 STORM DRAINAGE 08010 DESIGN A. Location B. Sizing TABLE OF CONTENTS 08020 MATERIALS A. Pipe Materials B. Structure Materials C. Installation D. Inlets and Outlets 08030 INSPECTIONS AND TESTING

More information

CITY OF ST. CA THARINE S. cn- Olc.4 BY-LAW NO. WHEREAS the Council of the Corporation of the City of St. Catharines, is

CITY OF ST. CA THARINE S. cn- Olc.4 BY-LAW NO. WHEREAS the Council of the Corporation of the City of St. Catharines, is ~: ~,,' " CITY OF ST. CA THARINE S BY-LAW NO. cn- Olc.4 A By-law to regulate sanitary and storm drainage. WHEREAS the Council of the Corporation of the City of St. Catharines, is authorized by the provisions

More information

SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION

SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION 1. SCOPE Pipe subsoil drains shall be constructed in accordance with this specification and in conformity with the lines, grades and cross-sections shown

More information

Exhibit A. Rules and Regulations for House Connections and Sewer Extensions

Exhibit A. Rules and Regulations for House Connections and Sewer Extensions The purpose of this application example is to provide assistance to small and medium sized rural communities in the drafting of documents necessary for the efficient operation of water, wastewater, and

More information

EXCAVATION AND PILING NEAR SEWERS, STORMWATER DRAINS AND WATER MAINS

EXCAVATION AND PILING NEAR SEWERS, STORMWATER DRAINS AND WATER MAINS NMP 1.4 EXCAVATION AND PILING NEAR SEWERS, STORMWATER DRAINS AND WATER MAINS Index Purpose... 2 Application... 2 Referral Agency... 2 Associated Requirements... 2 Referenced Standards...2 Definitions...

More information

PART 6 - STANDARD DESIGN AND CALCULATION FORMS 6.1 SANITARY SEWER DATA SHEET

PART 6 - STANDARD DESIGN AND CALCULATION FORMS 6.1 SANITARY SEWER DATA SHEET PART 6 - STANDARD DESIGN AND CALCULATION FORMS 6.1 SANITARY SEWER DATA SHEET Name of Municipality or Sewer District Name of Project Original Township and Lot Number Name of Engineer of Firm Preparing Plans

More information

City of Edmonton Page 1 of 5 Foundation Drain Discharge Collection System Guideline November, 2005

City of Edmonton Page 1 of 5 Foundation Drain Discharge Collection System Guideline November, 2005 City of Edmonton Page 1 of 5 This guideline will apply to all new developments involving singledetached, semi-detached or duplex houses in the City of Edmonton effective January 1, 2006. Preamble: This

More information

ORDINANCE NO. 2013 -

ORDINANCE NO. 2013 - ORDINANCE NO. 2013 - AN ORDINANCE OF BREVARD COUNTY, FLORIDA AMENDING CHAPTER 62, LAND DEVELOPMENT REGULATIONS SECTION 62-2891, LOT DRAINAGE, AND CHAPTER 22 BUILDINGS AND BUILDING REGULATIONS, SECTION

More information

Building over or close to a public sewer

Building over or close to a public sewer Building over or close to a public sewer thameswater.co.uk/developerservices thameswater.co.uk/developerservices 1 Questions and answers Did you know Thames Water is legally responsible for more than 100,000

More information

ROAD OPENING LICENCE APPLICATION FORM PLEASE READ ALL PARTS AND SECTIONS OF THIS FORM IN ADVANCE OF COMPLETING THE APPLICATION

ROAD OPENING LICENCE APPLICATION FORM PLEASE READ ALL PARTS AND SECTIONS OF THIS FORM IN ADVANCE OF COMPLETING THE APPLICATION ROAD OPENING LICENCE APPLICATION FORM PLEASE READ ALL PARTS AND SECTIONS OF THIS FORM IN ADVANCE OF COMPLETING THE APPLICATION N.B. WORK MUST NOT COMMENCE UNTIL LICENCE IS ISSUED June 2014 Roads Section

More information

Improving on-site domestic wastewater treatment systems - West Coast Lagoons Project

Improving on-site domestic wastewater treatment systems - West Coast Lagoons Project Improving on-site domestic wastewater treatment systems - West Coast Lagoons Project West Coast Lagoons Project- Improving Karekare, Piha, North Piha and Te Henga stream water quality Council is offering

More information

SPECIAL CONDITIONS OF CONTRACT

SPECIAL CONDITIONS OF CONTRACT AN SPECIAL CONDITIONS OF CONTRACT May 2013 TABLE OF CONTENTS S1. GENERAL... 2 S1.1 FORM OF CONTRACT... 2 S1.2 CONTINGENCY SUMS... 2 S1.3 STATUTORY REQUIREMENTS... 2 S1.4 GOODS AND SERVICES TAX... 2 S2.

More information

Town of Beaumont. Lot Grading Guidelines

Town of Beaumont. Lot Grading Guidelines Town of Beaumont Lot Grading Guidelines LOT GRADING APPROVAL PROCESS Lot Grading Guidelines... 3 Introduction... 3 Purpose... 3 Definitions... 3 Lot Grading... 3 Lot Grading Plan... 3 Lot Grading Certificate...

More information

CHAPTER 11 STORM DRAINAGE

CHAPTER 11 STORM DRAINAGE CHAPTER STORM DRAINAGE SECTION PC 0 GENERAL 0. Scope. The provisions of this chapter shall govern the materials, design, construction and installation of storm drainage. Storm water discharge shall be

More information

SECTION 33 41 13 PUBLIC STORM UTILITY DRAINAGE PIPING

SECTION 33 41 13 PUBLIC STORM UTILITY DRAINAGE PIPING SECTION 33 41 13 PUBLIC STORM PART 1 - GENERAL 1.01 SECTION INCLUDES A. Storm drainage piping, fittings, and accessories at proposed station areas and locations other than under and immediately adjacent

More information

PROCEDURE MANUAL FOR ENGINEERING CONSULTANTS

PROCEDURE MANUAL FOR ENGINEERING CONSULTANTS PROCEDURE MANUAL FOR ENGINEERING CONSULTANTS CITY OF GREATER SUDBURY ENGINEERING SERVICES DIVISION JUNE 2005 TABLE OF CONTENTS Chapter 1 - Reference Procedure Manuals and Specifications - CAD Drawing Requirements

More information

DESCRIPTION OF WORK:

DESCRIPTION OF WORK: DEPARTMENT OF PUBLIC WORKS COUNTY OF HENRICO P.O. BOX 27032 RICHMOND, VIRGINIA 23273 PERMIT NO. One (1) copy of application and four (4) copies of plans are hereby made to the Director of Public Works

More information

SECTION 33 31 00.11 GRAVITY SANITARY SEWERS

SECTION 33 31 00.11 GRAVITY SANITARY SEWERS SECTION 33 31 00.11 GRAVITY SANITARY SEWERS PART 1: GENERAL 1.01 SCOPE A. Gravity sanitary sewers and appurtenances. 1.02 SUBMITTALS A. Conform to requirements of Section 01 33 00 Submittals. B. Submit

More information

Before applying for a Road Opening Licence, please read and understand the following information.

Before applying for a Road Opening Licence, please read and understand the following information. Sept 2012 Before applying for a Road Opening Licence, please read and understand the following information. What is a Road Opening Licence? A Road Opening Licence (ROL) is a licence that allows the holder

More information

Close-Out Documents... 9

Close-Out Documents... 9 Water and Sanitary Sewer Service Connection Requirements Service Connection Requirements... 1 Application for Services... 2 Water Meter Application... 2 Wet Tap/Tie-in Connection Requirements... 3 Meter

More information

Township of Enniskillen. Asset Management Plan

Township of Enniskillen. Asset Management Plan Township of Enniskillen Asset Management Plan 2014 1 TABLE OF CONTENTS Page A. Introduction 3 B. State of Local Infrastructure 4 C. Desired Levels of Service 7 D. Asset Management Strategy 8 E. Financing

More information

5901 Milwaukee Street Planned Unit Development (GDP) (Second Addition to Grandview Commons)

5901 Milwaukee Street Planned Unit Development (GDP) (Second Addition to Grandview Commons) DATE: March 8, 2006 TO: FROM: SUBJECT: Plan Commission Larry D. Nelson, P.E., City Engineer 5901 Milwaukee Street Planned Unit Development (GDP) (Second Addition to Grandview Commons) The City Engineering

More information

SECTION 4Aggegate Subbase

SECTION 4Aggegate Subbase The contractor shall moist-cure the completed Lime Treated Subbase for a minimum of days before allowing any traffic on the compacted surface. The contractor shall be responsible for repairing any damages

More information

Standard Specification for the Laying of Sewer Lines and Appurtenances in the Hurunui District

Standard Specification for the Laying of Sewer Lines and Appurtenances in the Hurunui District Standard Specification for the Laying of Sewer Lines and Appurtenances in the Hurunui District 1. SCOPE OF WORK This Specification applies to the laying of sewer pipes and all associated appurtenances

More information

GUIDE TO SETTLEMENT OF CANTERBURY FLAT LAND CLAIMS

GUIDE TO SETTLEMENT OF CANTERBURY FLAT LAND CLAIMS GUIDE TO SETTLEMENT OF CANTERBURY FLAT LAND CLAIMS April 2013 i Introduction This guide focuses on repair methods for some of the types of land damage that occurred on flat residential land as a result

More information

Policy Guidance Notes and Requirements

Policy Guidance Notes and Requirements Policy Guidance Notes and Requirements Building over/close to Public Sewers Domestic Extensions and Garages 1.0 Introduction Householders and developers planning to build close to or over a public sewer

More information

Public Landscape Aids And Protection Of Assets

Public Landscape Aids And Protection Of Assets Territory and Municipal Services Reference Document 4 LANDSCAPE MANAGEMENT AND PROTECTION PLANS (LMPP) Requirements for the Protection of Public Landscape Assets Adjacent to Development Works Issue 2 Revision

More information

SECTION 33 05 16.13 PRECAST CONCRETE UTILITY STRUCTURES

SECTION 33 05 16.13 PRECAST CONCRETE UTILITY STRUCTURES SECTION 33 05 16.13 PRECAST CONCRETE PART 1 - GENERAL 1.01 SECTION INCLUDES A. This item shall consist of the construction of both sanitary and storm sewer precast concrete manholes in accordance with

More information

PENRITH CITY COUNCIL

PENRITH CITY COUNCIL PENRITH CITY COUNCIL DESIGN GUIDELINES FOR ENGINEERING WORKS FOR SUBDIVISIONS AND DEVELOPMENTS Adopted by Council 21 April, 1997 In force from 20 May 1997 as amended 20 November 2013 Penrith City Council

More information

Mandatory Part 1.4 BUILD OVER OR NEAR SEWERS, STORMWATER DRAINS AND WATER MAINS

Mandatory Part 1.4 BUILD OVER OR NEAR SEWERS, STORMWATER DRAINS AND WATER MAINS Mandatory Part 1.4 BUILD OVER OR NEAR SEWERS, STORMWATER DRAINS AND WATER MAINS Table of Contents Purpose... 2 Commencement... 2 Application... 2 Referral Agency... 2 Compliance with the QDC... 2 Associated

More information

Type of Sewer Systems. Solomon Seyoum

Type of Sewer Systems. Solomon Seyoum Type of Sewer Systems Solomon Seyoum 0 Learning objectives Upon completion of this lecture, the participants will be able to differentiate between types of sewer systems and discuss different aspects of

More information

SECTION EIGHT BONDING REQUIREMENTS

SECTION EIGHT BONDING REQUIREMENTS SECTION EIGHT BONDING REQUIREMENTS 8-00 BONDING REQUIREMENTS 8-01 No building permit for any construction in the subdivision shall be issued nor any lot within the subdivision conveyed until a bond has

More information

CHAPTER 1181 Improvements

CHAPTER 1181 Improvements 139 CHAPTER 1181 Improvements 1181.01 Performance bond; 1181.07 Street name signs. construction plans; 1181.08 Street lighting. improvements. 1181.09 Improvements bond. 1181.02 Monuments. 1181.10 Maintenance

More information

Integrated Manhole Ladder System

Integrated Manhole Ladder System Application: This innovative product has been designed to provide safe access and egress to precast concrete manholes and inspection chambers. It can also be used within any other underground concrete

More information

STANDARD PLUMBING AND DRAINAGE REGULATION 2003

STANDARD PLUMBING AND DRAINAGE REGULATION 2003 Queensland Subordinate Legislation 2003 No. 265 Plumbing and Drainage Act 2002 STANDARD PLUMBING AND DRAINAGE REGULATION 2003 TABLE OF PROVISIONS Section Page PART 1 PRELIMINARY Division 1 Introduction

More information

CCTV of Stormwater Systems. Cairns Regional Council. Commentary Guidelines #4037587

CCTV of Stormwater Systems. Cairns Regional Council. Commentary Guidelines #4037587 CCTV of Stormwater Systems Cairns Regional Council Commentary Guidelines Introduction Councils inherit assets through the donated asset process. In doing so, Councils immediately receive assets that are

More information

CHAPTER 17: STORM SEWER STANDARDS. 17.00 Introduction. 17.01 Administration. 17.02 Standards 17.1

CHAPTER 17: STORM SEWER STANDARDS. 17.00 Introduction. 17.01 Administration. 17.02 Standards 17.1 CHAPTER 17: STORM SEWER STANDARDS 17.00 Introduction 17.01 Administration 17.02 Standards 17.1 17.00 INTRODUCTION The purpose of this chapter is to provide guidance for the design and construction of storm

More information

To prevent increased stormwater runoff entering Council s drainage system and causing overloading of the system that in turn might cause flooding.

To prevent increased stormwater runoff entering Council s drainage system and causing overloading of the system that in turn might cause flooding. Background & Issues To provide guidelines and requirements for Developers, the Community and the Shire s Planning and Sustainability officers for connection to the Shire s Stormwater Drainage Disposal

More information

ADA POST INSPECTION CHECKLIST. Job No. Route County Location

ADA POST INSPECTION CHECKLIST. Job No. Route County Location ADA POST INSPECTION CHECKLIST Job No. Route County Location SIDEWALKS All sidewalks constructed within the project limits are ADA compliant. Sidewalks are 5 or greater in width. Exception, existing sidewalks

More information

Engineering Policy 146. Severe Weather Management Plans

Engineering Policy 146. Severe Weather Management Plans Engineering Policy 146 Severe Weather Management Plans January 2014 Contents Engineering Policy... 1 1 Policy statement... 1 2 Applicability... 1 3 Context... 1 4 Objectives and benefits... 1 5 Consultation...

More information

Guidance on applying for approval of installation of a commercial onsite wastewater system

Guidance on applying for approval of installation of a commercial onsite wastewater system Guidance on applying for approval of installation of a commercial onsite wastewater system This factsheet is designed to assist you to complete an Application to construct or install an apparatus for the

More information

Policy 11: Land Development Guidelines

Policy 11: Land Development Guidelines Policy 11: Land Development Guidelines Section 5 5.0 Sewerage Reticulation Design Requirements Table of Contents 5.0 Sewerage Reticulation Design Requirements...1 5.1 Introduction...2 5.2 Design Requirements

More information

City of Bakersfield Public Works Department Sewer System Management Plan December 2014

City of Bakersfield Public Works Department Sewer System Management Plan December 2014 City of Bakersfield Public Works Department Sewer System Management Plan December 2014 C:\Users\hmayberry\Desktop\SEWER SYSTEM MANAGEMENT PLAN 2014.doc 1 Sewer System Management Plan Index: Section 1 Goals

More information

SECTION 221413 FACILITY STORM DRAINAGE PIPING

SECTION 221413 FACILITY STORM DRAINAGE PIPING SECTION 221413 FACILITY STORM DRAINAGE PIPING PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01

More information

March 2006 DIVISION 3 - CW 2140-R3 TABLE OF CONTENTS

March 2006 DIVISION 3 - CW 2140-R3 TABLE OF CONTENTS March 2006 CW 2140 - SEWER AND MANHOLE CLEANING TABLE OF CONTENTS 1. DESCRIPTION... 1 1.1 General... 1 1.2 Definitions... 1 1.3 Referenced Standard Constructions... 1 3. CONSTRUCTION METHODS... 1 3.1 High

More information

Guidelines for Rights of Way

Guidelines for Rights of Way Guidelines for Rights of Way Guidelines for Statutory Rights of Way for Engineering and Public Works Infrastructure Rights of Way (Drainage, Sanitary, Water & Electrical Utilities) A Statutory Right of

More information

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department Land Disturbance, Erosion Control and Stormwater Management Checklist Walworth County Land Conservation Department The following checklist is designed to assist the applicant in complying with the Walworth

More information

The compliance of a roof to part of a new house at 28D Rata Street, Oxford, Waimakariri

The compliance of a roof to part of a new house at 28D Rata Street, Oxford, Waimakariri Determination 2009/103 The compliance of a roof to part of a new house at 28D Rata Street, Oxford, Waimakariri 1. The matters to be determined 1.1 This is a determination under Part 3 Subpart 1 of the

More information

Statement of Accounting Policies

Statement of Accounting Policies Statement of Accounting Policies Statement of Responsibility & Cautionary Note The Draft 2015/2025 Long Term Plan was authorised for issue by Council on 22 April 2015. The purpose of this Long Term Plan

More information

SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.

SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250. 02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily

More information

Permeable Pavement Construction Guide

Permeable Pavement Construction Guide Permeable Pavement Construction Guide Permeable pavement at Olympic Park, Waitakere Final Construction result What are permeable pavements? Permeable pavements are hard surface paving systems that reduce

More information

FLOODS FACT SHEET ADVICE FOR RESIDENTS Approvals for repairing, renovating or rebuilding flood-affected houses

FLOODS FACT SHEET ADVICE FOR RESIDENTS Approvals for repairing, renovating or rebuilding flood-affected houses 2 February 2011 Updated 16 March 2011 FLOODS FACT SHEET ADVICE FOR RESIDENTS Approvals for repairing, renovating or rebuilding flood-affected houses This fact sheet provides advice for residents about

More information

Office of Environment, Health and Safety (EH&S) - Sanitary Sewer Overflow Incident Form (rev. 12/2014)

Office of Environment, Health and Safety (EH&S) - Sanitary Sewer Overflow Incident Form (rev. 12/2014) STEP 1 Immediately call EH&S at (510) 642-3073 with the following details of the incident: Name of First Responder Phone Number of First Responder Location of Spill Is the spill potentially greater than

More information

GOUVEIA ENGINEERING. Pre-Bid Conference Meeting Minutes. City of Los Banos. Henry Miller Area Storm Drain and L Street Waterline

GOUVEIA ENGINEERING. Pre-Bid Conference Meeting Minutes. City of Los Banos. Henry Miller Area Storm Drain and L Street Waterline GOUVEIA ENGINEERING Pre-Bid Conference Meeting Minutes City of Los Banos Henry Miller Area Storm Drain and L Street Waterline Conference held at Intersection of West I Street and L Street, in Los Banos

More information

MAP KEYS GLOSSARY FOR THE DRAINAGE AND WATER REPORT

MAP KEYS GLOSSARY FOR THE DRAINAGE AND WATER REPORT Record MAP KEYS GLOSSARY FOR THE DRAINAGE AND WATER REPORT Abandoned Gravity Private Combined Gravity Private Foul Gravity Private Surface Water Gravity Public Combined Gravity Public Foul Gravity Public

More information

Drainage. Information for those with problem drains

Drainage. Information for those with problem drains Drainage Information for those with problem drains Contents 1 Purpose 2 Introduction 2 Explanations: what is a drain and what is a sewer 3 Explanation of the responsibilities for public and private sewers

More information

Tree Management Policy

Tree Management Policy Kingston District Council WE002 Tree Management Policy Keywords: Reference Number: WE002 Strategic Plan: Classification: Works & Engineering Policy First Issued/Approved: 2011 Review Frequency: Every 4

More information

Common Definitions and Glossary of Queensland Government Grants

Common Definitions and Glossary of Queensland Government Grants RPS V6-2013 Part 11 - Planning Scheme Policy 3 - Contributions and Security Bonding - Chapter 4 - Page 17 Chapter 4 - Security Bonding 3.4.1 Purpose (1) To outline the minimum requirements for security

More information

VEHICLE CROSSOVER INFORMATION PACK

VEHICLE CROSSOVER INFORMATION PACK VEHICLE CROSSOVER INFORMATION PACK CONTENTS Introduction Section A Section B Section C Section D Section E Criteria for approving a vehicle crossover application (Diagrams to demonstrate measurement criteria)

More information

SECTION 5: SANITARY SEWER SYSTEM DESIGN

SECTION 5: SANITARY SEWER SYSTEM DESIGN SECTION 5: SANITARY SEWER SYSTEM DESIGN 5.01 GENERAL Sanitary sewer improvements shall be designed to serve the ultimate level of City development as defined in the General Plan and the Wastewater Facilities

More information

Land development manual Section 73 Compliance Certificate application process

Land development manual Section 73 Compliance Certificate application process Land development manual Section 73 Compliance Certificate application process Published by Sydney Water PO Box 399 Parramatta NSW 2124 sydneywater.com.au Copyright 2013 Sydney Water Corporation Sydney

More information

THE CORPORATION OF DELTA ENGINEERING CONSULTANT PROJECT PROCEDURAL MANUAL

THE CORPORATION OF DELTA ENGINEERING CONSULTANT PROJECT PROCEDURAL MANUAL THE CORPORATION OF DELTA ENGINEERING CONSULTANT PROJECT PROCEDURAL MANUAL OCTOBER, 2013 TABLE OF CONTENTS 1. CHECKLIST PAGE NO. 2. CHECKLIST DETAILS A. Design Path 3 B. Property Acquisition 6 C. Outside

More information

How To Install An Overhead Sewer

How To Install An Overhead Sewer Village of Broadview Flood Control Assistance Program Village of Broadview 2350 S. 25 th Avenue, Broadview, IL 60155 INTRODUCTION The Village of Broadview is served by combined sewers which carry sewage

More information