INFORmATION DISCLOSURE FOR ELECTRICITY NETWORKS ASSET MANAGEMENT PLAN ELECTRICITY NETWORKS FY2011 FY2021 1

Size: px
Start display at page:

Download "INFORmATION DISCLOSURE FOR ELECTRICITY NETWORKS ASSET MANAGEMENT PLAN ELECTRICITY NETWORKS FY2011 FY2021 1"

Transcription

1 INFORmATION DISCLOSURE FOR ELECTRICITY NETWORKS ASSET MANAGEMENT PLAN ELECTRICITY NETWORKS FY2011 FY2021 1

2 contents EXECUTIVE SUMMARY... 2 POWERCO AND THE NEW ZEALAND ELECTRICITY INDUSTRY... 4 OUR ELECTRICITY NETWORK... 6 ASSETS COVERED... 7 THE ASSET MANAGEMENT PLAN AND PROCESS... 8 PURPOSE OF THIS SUMMARY AMP... 9 HOW TO PROVIDE FEEDBACK... 9 PROCESS OVERVIEW... 9 ASSET MANAGEMENT STRATEGY OVERVIEW WHO WANTS WHAT FROM THE ASSETS? STATE OF THE ASSETS PERFORMANCE AGAINST TARGET OVERVIEW RISK MANAGEMENT ASSET LIFE CYCLE PLAN NETWORK DEVELOPMENT PLAN NETWORK PERFORMANCE ENHANCEMENT CAPITAL EXPENDITURE OPERATIONAL EXPENDITURE FINANCIAL ASSET MANAGEMENT IMPROVEMENT INFORMATION SYSTEMS SERVICE PROVISION STRATEGY PROJECT MAPS KEY DEFINITIONS SUMMARY ASSET MANAGEMENT PLAN ELECTRICITY NETWORKS FY2012 FY2021

3 SUMMARY ASSET MANAGEMENT PLAN ELECTRICITY NETWORKS FY2012 FY2021 1

4 EXECUTIVE SUMMARY Welcome to the 2012 edition of our Summary Asset Management Plan (AMP). This Summary AMP outlines the key points, that we consider relevant to interested parties, from Powerco s full AMP. It is intended to provide a starting point for discussions with key stakeholders and generate increased feedback on the vital service Powerco provides. The full AMP is an important part of Powerco s planning and investment framework. It describes for our customers, shareholders, employees and partners how we will manage our electricity distribution network to deliver the standards of reliability of electricity supply that our customers demand and the commercial performance that our shareholders expect. The AMP is a technical document that sets the context for the annual investment we believe is necessary to maintain the performance of existing network assets and to provide future capacity and security through investment in new assets. The programmes of work identified in the AMP are based on our current understanding of customer and stakeholder requirements, and our knowledge of the existing and projected condition and performance of the assets on our networks. The 2012 AMP covers a planning period from 1 April 2012 to 31 March However, our main focus is on ensuring that our work programmes for the next three to five years are clearly defined and form part of a longer-term asset strategy. Each year, a comprehensive update of the plan is completed to reflect changes on the network, new technologies that are available and work we have undertaken during the year to develop a better understanding of the overall health of our assets. The updated AMP also reflects independent feedback we have received on our Asset Management methodologies from the Commerce Commission and its expert advisors. Our ultimate aim is to optimise the life-cycle costs of our assets whilst meeting agreed service targets and future demand requirements at an acceptable level of network risk what we term achieving a steady state level of efficient asset investment. However, as a regulated supplier of electricity services, we have to work within the realities of a regulatory price cap, and so achieving everything that is identified in the plan is not always possible and, in some cases, we are required to apply a risk-based prioritisation approach to our investments. We consider this to be an acceptable approach as long as this doesn t erode our operating headroom and ability to manage the on-going risk of adverse network performance and/or result in grossly inefficient cost outcomes. Powerco has a constructive relationship with its economic Regulator, the Commerce Commission, and where we believe long-term investment requirements may be compromised by the current regulatory allowances we will discuss this with them. We believe our AMP is an important starting point for engaging positively with the Commission and its advisers to ensure long-term investment levels remain appropriate. Whilst being primarily a document developed for Powerco s own planning purposes, publication of the AMP also satisfies the regulatory requirement to disclose details of our Asset Management methodologies, in accordance with the Electricity Disclosure Handbook 2004 (as amended 2008). Asset Strategy and Context for the 2012 AMP Powerco understands that good Asset Management underpins the ability of our networks to deliver both supply quality and security, and value for consumers. We refer to Asset Management in this context as the co-ordinated policies and practices through which we acquire, analyse and review information on our assets, assess future network requirements and deliver cost-effective and safe investment in our network. An important element of our Asset Management practice is a focus on continuous improvement and, to this end, we have recently assessed our practices against the criteria in the International Infrastructure Management Manual and using the Asset Management Maturity Assessment Tool prepared by Parsons Brinckerhoff NZ for the Commerce Commission. The results, whilst identifying some areas for improvement, mainly in relation to data capture and information systems, were on the whole positive. From a strategic perspective, we are seeking to extend our planning horizon out to 20-plus years to make more explicit the company s strategy for delivering outputs and meeting demand over the long term. 2 SUMMARY ASSET MANAGEMENT PLAN ELECTRICITY NETWORKS FY2012 FY2021

5 Our focus to date, on effective Asset Management has enabled the company to deliver strong outcomes for our customers over recent years. We have established the company as a low-cost operator in comparison with our peers in New Zealand, whilst maintaining a stable operating performance overall, which also benchmarks favourably. Ultimately, this has flowed through to lower prices for customers. Central to our strategy of containing costs has been the introduction of processes to optimise expenditure on our networks, within the regulatory allowances and to the level where returns to the company s shareholders are considered acceptable. However, whilst our headline network performance and the reliability of supply experienced by our customers (when taken in aggregate), has been broadly stable over recent years, our analysis indicates a slow but observable deterioration in asset condition and an increase in the average age of assets on certain parts of our network. Perhaps, not surprisingly we are starting to observe a correlation between declining reliability performance and the health and age of our assets at these localised network hot spots. Left unchecked, we anticipate this declining performance trend will continue, resulting in an unacceptable level of supply interruption to our customers. As we set out in the full AMP, there are a number of short-term initiatives and investment decisions that we can apply to target interventions at the worstperforming parts of our network, but increased levels of investment will almost certainly be required in the longer term to redress this adverse performance trend. However, as our customers, through increased prices, will ultimately fund investments, we believe it is important that the case for increased expenditure is well articulated, fully justified, and completed with appropriate consultation with our customers and the Regulator. We will be progressing this work over the next 18 months. The full AMP provides more details on the issues discussed here. It also describes in detail our plans for addressing each issue. We look forward to discussing our plans with you. SUMMARY ASSET MANAGEMENT PLAN ELECTRICITY NETWORKS FY2012 FY2021 3

6 POWERCO AND THE New Zealand ELECTRICITY INDUSTRY To provide relevant feedback on Powerco s AMP, it is vital that any interested parties understand the structure of New Zealand s electricity industry and Powerco s role in it. This country s electricity industry has undergone considerable structural change over the past 14 years as the Government has worked to promote competition, reliability and fair prices for consumers. As part of the distribution sector, Powerco sits midway along the supply chain. It contracts with Transpower for transmission services and with generators embedded in our networks. At present, we do not sell electricity we own and operate the infrastructure that delivers it from the National Grid to individual homes and businesses. Our main customers are energy retailers with whom we have wholesale use of system agreements. We invoice retailers for the cost of our services, which comprise delivery (including transmission) charges, and maintaining and upgrading the distribution network. Retailers bundle up the cost of our services, along with their own services and those of generators, into customers monthly electricity bills. Retailers, which compete for customers, set the overall price for the end-consumer. The different sectors of the industry are described next. 4 SUMMARY ASSET MANAGEMENT PLAN ELECTRICITY NETWORKS FY2012 FY2021

7 Figure 1: Sectors of the New Zealand Electricity Industry 1. Generation 2. Transmission 3. Distribution 4. Retailing 5. Consumers Generators, as the name suggests, are the companies that generate electricity in power stations. Generators are also entitled to sell electricity to consumers and energy retailers. Numerous generation sites around the country supply electricity to the National Grid. Transpower owns and operates the National Grid, which comprises pylons, high-voltage cables and switchgear for transmitting bulk electricity from generation sites to distributors. Transpower transmits electricity from generating stations to 178 Grid Exit Points (GXPs) around New Zealand. These GXPs are the points of supply for distribution networks like Powerco s. At the GXPs, electricity is transformed to lower voltages then distributed to end-users via overhead lines and underground cables by local distribution (lines) companies. There are currently 29 distribution companies, which operate within set boundaries and range from publicly listed companies to community-owned trusts. The 1998 Electricity Reform Act required full ownership separation of distribution businesses from energy (retail and generation) businesses, preventing Powerco and other lines companies from participating in the retail or generation sectors. The Electricity Industry Bill 2009 allows distribution companies to once again participate in the retail and generation sectors, subject to strict controls. Retail companies sell delivered electricity to end-consumers. Retailers bundle up the costs from the other sectors of the industry, along with their own costs to run a retail business, and provide electricity consumers with a monthly bill. They set the final price consumers pay for electricity. These companies are also allowed to participate in the generation sector. Residential and business consumers buy delivered energy from retail companies. Large industrial and commercial consumers also purchase electricity from retail companies but may also have the option of contracting directly with distribution companies for electricity distribution services. SUMMARY ASSET MANAGEMENT PLAN ELECTRICITY NETWORKS FY2012 FY2021 5

8 OUR ELECTRICITY NETWORK Powerco is New Zealand s second largest electricity distributor in terms of customer connections and largest in terms of geographical area covered and the length of our network. We own and operate a large network of electricity distribution assets that, over the last year, delivered 4652 GWh of electricity through approximately 30,000km of lines and cables to more than 319,000 consumer connections. Powerco s networks supply electricity to a diverse range of communities and consumer types, from major provincial centres with highly interconnected CBD networks, through to remote rural communities; from large industrial plants to small back-country shearing quarters. Powerco s networks cover Thames-Coromandel, Hauraki, Tauranga and Western Bay of Plenty, Matamata Piako and South Waikato (collectively known as our Eastern Region) and Taranaki, Whanganui, Rangitikei, Manawatu, Tararua and Wairarapa (collectively known as our Southern and Western Regions). OPERATIONS Electricity Networks Electricity distribution networks in the Tauranga, Thames, Coromandel, Eastern and Southern Waikato, Rangitikei, Taranaki, Whanganui, Manawatu and Wairarapa regions. Figure 2: Powerco Electricity Network Operations Map 6 SUMMARY ASSET MANAGEMENT PLAN ELECTRICITY NETWORKS FY2012 FY2021

9 ASSETS COVERED The full AMP, to which this summary refers, provides detailed information on Powerco s fixed electricity network assets. The following graphs and table provide a summary of the assets covered. 2,500 Replacement Cost by Asset Category Electricity Network Replacement Cost by Asset Type $million Replacement Cost ($m) 2,000 1,500 1, Overhead Underground Transformers Switchgear Substations 200 Asset Category Assets Valued at ODV Replacement Cost Assets Valued at Current Replacement Cost Overhead Line Underground Cable Distribution Transformers Distribution Switchgear Zone Substations SCADA/Comms/Ripple Spares (Emergency & Critical) Figure 5: Replacement Cost by Asset Category Table 1: Key Network Statistics Figure 3: Electricity Network Asset Replacement Cost by Asset Type Southern & Key Network Statistics as at 31 March 2012 Eastern Western Total Length of Overhead Circuit (km) 7,679 14,644 22,323 Electricity Network Replacement Cost by Function 1, Length of Underground Circuit (km) 4,407 3,192 7,600 Subtransmission Circuit Length (km) 592 1,011 1,603 Distribution Circuit Length (km) 5,828 10,780 16,609 Low-Voltage Circuit Length (km) 5,667 6,044 11,711 $million Number of Zone Substations and Switching Stations Zone Substation Transformer Capacity (MVA) Distribution Transformer Capacity (MVA) 1,418 1,548 2,967 0 Subtransmission Zone Substation & GXP Protection & Control Distribution Distribution Substation Low Voltage Spares (Emergency & Critical) Figure 4: Electricity Network Asset Replacement Cost by Functional Category (2004 ODV) SUMMARY ASSET MANAGEMENT PLAN ELECTRICITY NETWORKS FY2012 FY2021 7

10 THE ASSET MANAGEMENT PLAN AND PROCESS With Powerco s electricity network assets ranging in age from new to more than 50 years old, effective long-term planning is a fundamental requirement of our business. Our AMP is an integral part of that planning because it not only explains Powerco s management and maintenance policies, but also sets out our plans for focused investment in security, capacity and reliability of an ageing network that is facing constantly rising levels of demand. This means Powerco has increasing investment requirements as assets progressively reach the end of their useful lives. The full AMP contains specific details on Powerco s short- and long-range planning for network development, renewal and maintenance. In other words, the AMP is a high-level document providing management, stakeholders and any interested parties with a broad overview of Powerco s asset management policies, asset details, service levels, capital and maintenance works planning, expenditure forecasts, risk management and performance evaluation. Incorporating information from a range of other internal documents, the AMP sets out the performance criteria for the assets, and summarises the actions needed to achieve those performance criteria. Developing the AMP is a key step in ensuring that the needs of all stakeholders are properly considered and incorporated into Powerco s long-term Asset Management strategies. It also ensures that plans provide, subject to any regulatory constraints, the optimum balance between levels of service and the efficient costs to provide the required service. Figure 6 illustrates the structure of the full AMP and what each section is trying to address. Who wants what from the assets? What is the state of the assets? Section 2 Define Stakeholders Define AM Drivers Section 3 Describe Assets What performance are we targeting from the assets? How are we doing vs. the target? What are the gaps? Section 4 Set Performance Targets Section 5 Performance Evaluation Section 6 Analyse Network Risks How are we managing the network and solving any performance gaps? Section 7 Set Asset Life Cycle Strategy Analyse Renewal Needs Section 9 Reliability, Safety, Environment Enhancement Needs Protection & Control, Smart Network Development Figure 6: Structure of Asset Management Plan Section 8 Security Criteria Prepare Load Forecasts System Growth Needs What does this mean for the works programmes and required expenditure? Section 7, 8 and 9 Develop Work Programmes Linked with AM Driver Section 10 Set Expenditure Forecasts How can we improve? Section 11 Develop AM Improvement Initiatives 8 SUMMARY ASSET MANAGEMENT PLAN ELECTRICITY NETWORKS FY2012 FY2021

11 PURPOSE OF THIS SUMMARY AMP Electricity distribution networks and the Asset Management processes that drive them are very complex. Therefore, a huge amount of information is required to compile a thorough AMP. This complexity and level of detail can act as a barrier to providing feedback for some parties, due to a feeling of information overload. Powerco recognises this and that is why we have produced this Summary AMP, which is intended to identify the key issues relevant to the majority of interested parties. Anyone interested in Powerco s AMP or operations in general is encouraged to read this summary to learn more about our business and what we are trying to achieve on behalf of all our stakeholders. If further information is required, Powerco s full AMP is available at: Please note, this Summary AMP is intended to be consistent with the full AMP published in April Therefore, commentary, figures and dates contained within this Summary AMP reflect those from the published date for the full AMP. HOW TO PROVIDE FEEDBACK Powerco provides a vital service to your community. Therefore, it is vital that you have your say on the service we provide. We welcome feedback on this Summary AMP, our full AMP, or any aspect of our business or the electricity industry. Feedback can be provided in the following ways: By yourview@powerco.co.nz By telephone: 0800 POWERCO ( ) By post: Consultation Manager C/- Powerco Ltd Level 2, 84 Liardet St Private Bag 2061 New Plymouth 4342 PROCESS OVERVIEW The Asset Management process requires that electricity is provided at the most efficient cost. This is a process of many parts, including: Strategy Long-term strategic direction for the management of the assets and the business operations. This is the key interface for customer consultation and corporate strategy. Planning This process involves planning for the renewal, development, maintenance and operation of the assets. Service provision This involves the delivery of construction, maintenance and operating services on the network assets. Network operations This involves the management of the real-time operation of the network, recording network outages and approving planned outages and access to the network by service providers. Information This involves the maintenance of, and reporting from, the asset information databases. There is, of course, extensive and constant interaction between these processes, and with corporate, customer and regulatory management teams. SUMMARY ASSET MANAGEMENT PLAN ELECTRICITY NETWORKS FY2012 FY2021 9

12 ASSET MANAGEMENT STRATEGY OVERVIEW At its highest level, the Asset Management process seeks to find and optimise the most efficient trade-off between cost, service and risk. By minimising the costs, the asset manager may compromise on asset performance and asset risk; by minimising the asset risk, service performance may be compromised and costs increased. These three areas are intrinsically linked and the asset manager seeks to achieve the appropriate balance between them. This is represented in the following diagram. Powerco s AMP identifies and provides details on the following key electricity Asset Management-related strategies: 1. Renewal and modernisation: Modernisation of the network involves the replacement and updating of our aged assets to reduce the risk of asset failure, which can result in interruptions to supply. Powerco s required renewal expenditure is forecast to trend upwards as the wave of assets installed between the 1950s and early 1980s approaches end-of-life. Figure 8 shows the increase in forecast renewal expenditure. Asset Renewal Capital & Operational Expenditure If too much focus is put on one of these areas, the other two areas will be compromised COST NETWORK ASSETS LEVEL OF RISK Nominal Expenditure ($000) PERFORMANCE LEVELS A 2007 A 2008 A 2009 A 2010 A 2011 A 2012 B Asset Replacement and Renewal 2013 F 2014 F 2015 F 2016 F 2017 F Refurbishment and Renewal Maintenance 2018 F 2019 F 2020 F 2021 F 2022 F Year (ending June) Figure 8: Actual and Forecast Asset Renewal Capital and Maintenance Expenditure Figure 7: Cost, Performance and Risk Balance 10 SUMMARY ASSET MANAGEMENT PLAN ELECTRICITY NETWORKS FY2012 FY2021

13 2. Increasing the redundancy (duplication) of the core network: Redundancy means that if one critical component fails or needs to be taken out of service, there is another component ready to continue supply. This includes increasing zone substation capacity and installing more network automation. Powerco has identified the potential for 17 zone substations to be built and 20 additional transformer banks to be installed at existing substations over the next 10 years. 3. Standardising systems and processes: This is a key strength of Powerco s employees and a significant focus for management. Powerco has developed a common maintenance management system and an integrated, easily accessible suite of information systems. There has also been continuing development of design, construction and maintenance standards, which lead to lower risk profiles in the network and less reliance on field staff. Further investment in the standardisation of systems and processes will allow us to extend asset lives. 4. Management of public safety: Electrical equipment is capable of causing serious harm or death so safety is of utmost importance to Powerco. Safety performance enhancement is to a large extent workforce-related, and is about fostering safety-focused leadership and culture within both Powerco and its contractors. Most of the safety initiatives described in the full AMP are, therefore, people-focused rather than network equipment-focused. Nevertheless, some network projects are centred on eliminating safety hazards. Safety enhancement programmes are driven from a variety of perspectives and sources. They are generally approached with risk-based techniques. Powerco has an established Health and Safety Plan and its purpose is to document the proposed pathway we will take to execute and improve all areas of our Health and Safety performance. The main areas of focus are: Committed safety leadership; Business-wide safety culture; and Continuous improvement of safety systems. 5. Distribution automation and more interconnections at feeder level: Smart network plans, which are a recent addition to Powerco s AMP, aim to be self-healing and capable of shifting the load from peak times. They are something to which regulators in many countries are now paying greater attention because they are perceived to offer customers improvements in performance and cost. Smart networks, which offer flatter, more manageable patterns of demand, fit well with Powerco s business plan objectives of improving reliability through automated solutions, and managing increasing investment profiles through non-asset solutions. 6. Continuous improvement and optimisation of our inspection and maintenance standards: Powerco s Network Standards set the requirements for the design and construction of equipment. Our standards also set out our requirements for maintenance inspections and servicing, and guidelines for the overhaul of equipment. The standards reflect the range of different contractor drivers in place across Powerco s network as well as a need to prevent corner-cutting, while not disallowing new ways of doing things. The standards and policies follow a continuous improvement process whereby the standards are challenged as they are used. Input to the standards preparation and update process can arise during semiregular standards road shows, through the field work audit process or if anyone has a new idea that should be tried out. SUMMARY ASSET MANAGEMENT PLAN ELECTRICITY NETWORKS FY2012 FY

14 WHO WANTS WHAT FROM THE ASSETS? The following figure illustrates the relationship between Powerco s main stakeholders, their drivers and the Asset Management process. The diagram now includes a recognition of the business planning process as the stakeholder drivers are equally (and in some cases more appropriately) applicable to the business planning process. Customers/ Consumers Service/Price Safety Load Growth Government & Regulator Economic Efficiency (Long-Term Interest of Consumers) Environmental Safety & Compliance Owners & Lenders Long-Term Value (Productivity & Utilisation) Risk Management Employees & Contractors Safety Workflow Certainty Market Costs Various media communication channels, such as newspaper and radio advertising and Powerco s website. In addition to the above, Powerco has a Consultation Manager dedicated to planning and co-ordinating consultation activities and maintaining relationships with key stakeholders. Feedback obtained through consultation is incorporated into Powerco s Asset Management planning to help ensure Powerco s plans are aligned with consumer and stakeholder expectations. We ensure this happens by involving a wide range of Powerco people in customer consultation, including engineers, key decision-makers and business leaders. This way, consumer feedback goes directly to the people who are able to act on it. Business Planning Process Asset Management Process Development, Renewal, Maintenance, Operation Asset Performance Asset Age/Condition Assets Figure 9: Asset Management Process Stakeholders and Drivers Powerco uses a range of best-practice methods to undertake consultation and to identify stakeholder interests, including, but not limited to: Key Account Managers assigned to liaise directly with large or industrial consumers. Consumer surveys conducted at events like the Mystery Creek and Central Districts Agricultural Field Days. Surveys are designed to help Powerco understand if consumer expectations about the quality of their electricity supply are being met. Attendance of Powerco staff at these events also provides consumers with an opportunity to discuss any concerns they may have directly with Powerco. Workshops and focus group-type meetings with regulators, consumers and consumer representative groups. Powerco Chief Engineer Michael Whaley responds to a question at a consultation with members of the Taranaki Chamber of Commerce. Also on hand from Powerco to listen to consumer feedback were (from left to right) Planning Manager Peter Armstrong, Regulatory Manager Charlotte Littlewood and Network Operations Manager Phil Marsh. 12 SUMMARY ASSET MANAGEMENT PLAN ELECTRICITY NETWORKS FY2012 FY2021

15 Figure 10 below illustrates the influences of the various drivers affecting the total amount spent on the network over time. Network Spend Long-term Shareholder value Productivity Regulated Revenue Utilisation Asset Age, Condition & Configuration Renewal Service Development Load Growth Safety O&M Environmental Indirect Costs Market Costs For Work Risk Mgmt Asset Management Process Time Figure 10: Illustration of the Influence of Asset Management Drivers Powerco Performance Engineer Ken Pattie discusses Powerco s BasePower solution for remote rural consumers at the Whanganui River settlement of Matahiwi. The diagram reflects the current situation, which can be summarised as upwards pressure on network spend through: The required level of service. Load growth. Safety, environmental and other regulatory compliance obligations. The market costs for field work activities. The current attributes of the network, i.e. asset age, condition and configuration. The drivers that place downwards pressure on network expenditure are: Powerco s commercial driver to achieve long-term sustainable value for its shareholders, which (in this context) is reflected in utilisation and productivity drivers. The regulated revenue, namely the allowable revenue and form of control. SUMMARY ASSET MANAGEMENT PLAN ELECTRICITY NETWORKS FY2012 FY

16 At a strategy level, constraints, Asset Management drivers and the needs and interests of various stakeholders are evaluated and considered as part of the corporate planning process. These are all applied during the network planning process. It must be recognised that, with such a wide range of stakeholders, their drivers and needs will also vary widely. For example, Powerco s consultation to date indicates that most consumers wish to see reliability and quality standards improve or remain at present levels but do not wish to pay more for electricity overall. However, maintaining or improving standards requires a greater level of investment due to an ageing network and load growth. By restricting Powerco s revenue through priceconstraining regulation, Regulators seek to put downwards pressure on electricity prices. The regulation is limited in its effectiveness in constraining overall retail prices because the majority of a retail electricity bill is made up of components that are outside Powerco s control. However, it does have a large impact on how much Powerco is able to invest back into the network at the same time, Powerco must continue to maintain reliability and quality standards while still making a fair return to investors. As such, Powerco seeks to operate an efficient business and to ensure regulatory consistency, predictability, transparency and accountability to help lower perceived investment risk, thus allowing for investment at appropriate levels required to achieve the optimal balance of all stakeholder expectations. It is at the strategy level where the best overall balance between these drivers and needs is sought. At a tactical and operational level in the network planning process, the investment policy and Asset Management strategy is shaped by Powerco s multi-stakeholder assessment process. This process is a key part of the way in which network development and renewal programmes are formed. Powerco faces a constant balancing act to ensure the needs of consumers and stakeholders are met at the optimal levels of price and quality. Feedback from electricity retailers and consumers is essential in ensuring we achieve the best possible balance for the widest possible range of stakeholders. To help achieve the optimal balance, projects are assessed using a multi-stakeholder optimisation process (known as Coin Optimiser), whereby the projects are reviewed against a set of four strategic objectives. The primary objectives of the optimisation process are: To provide a consistent approach to the development of capital works programmes that balances (potentially conflicting) stakeholder requirements; To eliminate (or mitigate) any high risks to public safety, network performance, customer outcomes, public relations, or employee engagement; and To maximise the strategic value of the portfolio of projects that make up the capital works programme. Further details on the optimisation process are set out in Section 2.5 of the full AMP. 14 SUMMARY ASSET MANAGEMENT PLAN ELECTRICITY NETWORKS FY2012 FY2021

17 STATE OF THE ASSETS The age profile by replacement costs of the entire infrastructure asset base (on current replacement costs) is presented as a nine-year moving average and is shown in the diagram below. Replacement Cost ($m) Total Asset Replacement Cost vs Age Year of Original Commision (Years) Substations Switchgear Transformers Underground Overhead Figure 11: Total Asset Age Profile. Condition monitoring shows that the assets are generally in the condition expected of their age ODL PERFORMANCE AGAINST TARGET OVERVIEW Table 2: Current Electricity Asset Performance Electricity Measure Measure (2011) Target for 2013 Commentary Network reliability (SAIDI) Network reliability (SAIFI) Customer density Average consumption Direct operating costs min/ customer (actual) min/ customer (excluding major storm events) 2.62 interruptions/ customer (actual & excluding major storm events) <210 min/ customer (excluding major storm events) <2.8 interruptions/ customer (excluding major storm events) We believe that the static SAIDI numbers are masking an underlying deterioration in performance at certain locations and within specific asset groups. Left unchecked and in the absence of increased investment, we expect further deterioration in performance in these hot spot areas over time See above 10.7 ICPs/km N/A Urban/rural mix, below weighted industry average 14.6 MWh/ICP N/A Low (presenting growth opportunity). Benchmarking weakness $1146/km $1310/km Efficient spend but we are becoming increasingly concerned with the adequacy of the operating expenditure Capex spend $2666/km Benchmark on information disclosures Asset investment Efficient level of spend, around the median for the industry. $4128/ICP $4500/ICP Efficient, especially when compared to similar density distribution companies Load factor 66% 65% High load factor, good spread of customer load Zone substation capacity utilisation Security 51% 40% Higher than target utilisation. Indicates investment needed in zone substation capacity Substation and feeder security N/A Generally appropriate. Standards are commensurate with load. Increasing need for investment in subtransmission lines Asset condition years average age Asset condition reports N/A Asset condition well monitored. Appropriate asset condition commensurate with age, but increasing investment profile SUMMARY ASSET MANAGEMENT PLAN ELECTRICITY NETWORKS FY2012 FY

18 Performance looks at the consumer-related service requirements, and the confirmation of these requirements through the consumer consultation process. It then looks at the ways in which economic efficiency is assured in the Asset Management process, contractor performance, safety performance, environmental matters and statutory compliance. The targets also take into account the type of assets used across our network, and make comparisons with other New Zealand lines companies with the same customer density and ratio of overhead to underground construction. They also consider past planning practice, economic factors, recognised international best practice and safety. Powerco achieves a balance between owner requirements and legislative, regulatory and consumer expectations in setting these performance criteria. The levels of service adopted by Powerco for its Asset Management Plan are based on the internationally recognised measurements, SAIDI, SAIFI and CAIDI (which are acronyms for formulae covering the duration and frequency of power outages, and their customer bases) and accepted New Zealand lines companies best practice. Powerco conducts an extensive Customer Communications Programme to verify that performance targets match consumer and stakeholder expectations. Consumer consultation is a requirement of the Commerce Act (Electricity Distribution Thresholds Notice 2004). The primary intention of this requirement is to ensure distribution businesses effectively consult with, and take into account, the views of their customers and stakeholders. Regardless of regulatory requirements, Powerco views consumer consultation as common sense essentially, our job is made easier if the communities in which we operate understand who we are and how our business operates. In addition to Powerco-initiated consultation, a database is kept of all complaints and suggestions registered by its customers through Powerco s call centre. These complaints are mapped by type for later reference in planning activities. Economic efficiency is an important driver for maintenance, renewal and development work. A large proportion of repair work, refurbishment and asset replacement work is undertaken only after economic analysis to determine the most cost-effective solution. This frequently involves the choice between replacement and continued maintenance. Safety is a critical driver of the Asset Management process. Electrical plant and equipment are capable of causing serious harm. Measures must be taken to ensure, as far as practicable, the safety of employees and the public. To this end, the network must be maintained in a way that meets statutory requirements, follows good engineering practice, and is considered safe in accordance with recognised industry standards. Safety is determined by a combination of: Asset design; Maintaining the assets in a safe condition; Safe operating and work practices; and Statute: The Electricity Regulations, Electrical Codes of Practice and the Australian/New Zealand Standard Wiring Rules. There is also the Safety Manual Electricity Industry (SM-EI), which contains the framework for Powerco s safety-related network operation. Powerco has now implemented its network operating procedures to comply with the requirements of SM-EI. Additionally, there are the Building Act, the Health and Safety in Employment Act, the Hazardous Substances and New Organisms Act 1996, and various guides set out by the Electricity Engineers Association. Powerco has adopted the practice of working as a reasonable and prudent operator to guide safe Asset Management practices. Its health and safety policy and procedures are set out in documents in the Powerco Business Management System. Contractors can receive instructions from the Contracts Works Manual and the Network Operations Manual, both of which are new initiatives that operate with online search applications. The company carries out a policy of auditing its contractors for health and safety compliance, along with their quality of workmanship. Health and safety audit breaches are divided into major and minor. We have a focus on continual improvement on health and safety and have a target number of zero major breaches. 16 SUMMARY ASSET MANAGEMENT PLAN ELECTRICITY NETWORKS FY2012 FY2021

19 RISK MANAGEMENT A large part of the Asset Management process involves managing risks associated with the assets on behalf of our stakeholders. For example, public safety risks may arise due to inadequately secured equipment, risks of unexpected supply outages may arise due to inadequately trimmed trees, or there could be inadvertent breaches of legislation. Powerco s Board and management are committed to maintaining a business environment that demonstrates good corporate governance practices. Risk management is therefore an integral part of Powerco s business to support effective decision-making and provide assurance. The aim of the risk management programme is to identify and understand the likelihood, consequence, control effectiveness, and action plans required to make risk levels acceptable. The risk management programme is supported by Powerco s corporate insurance programme, which includes low-probability and high-impact events. Our approach to risk management is aligned to the new AS/NZS ISO 31000:2009 standard for risk management. More in-depth details on Powerco s risk management programme are provided in Section 6 of our full AMP. This section on risk management has now been moved to the middle of the AMP from being at the end. This reflects our view that the management of risks is central to the Asset Management process, rather than being simply an output. ASSET LIFE CYCLE PLAN As Powerco s network continues to age, more investment in renewal and maintenance is required to maintain current reliability levels. Powerco is spending less on asset renewal than what asset age profiles indicate should be spent; however, this must be viewed in the context of regulated allowable revenue. The required increase in replacement costs is demonstrated in the following figure. Replacement Cost ($m) All Assets Replacement Profile ODV Replacement Cost (June 2011 quantities in $2004 terms) Year of Replacement (FY) Current Replacement Cost (including capital efficiency factor) 9 year rolling average, Current Replacement Cost (including capital efficiency factor) 50 Year Average Current Replacement Cost (including capital efficiency factor) Renewal Budget (Real $2011) Figure 12: Total Network Asset Replacement Profile A number of renewal projects are described in the maps that follow in this Summary AMP. The maps show the major projects Powerco wishes to undertake prior to application of the multi-stakeholder assessment process described earlier. SUMMARY ASSET MANAGEMENT PLAN ELECTRICITY NETWORKS FY2012 FY

20 Maintenance Work Types Powerco s maintenance work comprises the following elements: Maintenance management and maintenance planning; Routine inspections and condition assessments; Routine servicing; Non-routine servicing (overhauls); Fault first response, callouts; Asset relocations (where an asset is simply moved and not replaced); Evaluation of inspection and condition-monitoring results to determine any maintenance or renewal requirements (this may be performed in the field at the time of inspection/condition-monitoring or later by engineering staff); Evaluating faults to predict maintenance or renewal requirements; Performing corrective maintenance or renewal as a result of the above; and Service disconnections. Asset Renewal Strategic Themes Powerco s scheduled asset renewal strategy encompasses three main themes, each of which is appropriate for the different asset types. A run-to-failure strategy is applied to assets where the consequences of failure are not major and where the costs of on-going condition-monitoring may outweigh the costs of failure. This strategy is applied to equipment such as small pole-mounted distribution transformers, underground distribution feeder cable spurs, LV cables, expulsive fuses and surge arresters. A risk- and condition-based replacement strategy is applied where there is a significant implication due to failure, such as major health and safety risks, significant reliability of supply consequences or a major expense in repair. This strategy is applied where on-going condition inspections are needed to comply with regulations or where the costs of condition-monitoring are small compared with the costs associated with failure. It is applied to equipment such as poles, cross-arms, important distribution feeder cables and zone substation transformers. An age- and obsolescence-based replacement strategy is applied to assets with a high level of technical complexity or a high level of interconnectedness with other network assets (that is, the operation of a system as a whole is dependent on the integrity of several assets). It includes the need to replace equipment because of the availability of spares, or for standardisation or changes in technology. This strategy is applied to equipment such as zone substation switchgear, SCADA equipment and protection relays. Reactive renewal strategies are based around the need to renew assets that have failed and need to be replaced in a short time or to renew assets with a high imminent risk of failure. Asset Renewal Forecasting Process The most accurate means of forecasting renewal needs for the network is through knowledge of the condition of the assets. A condition-based renewal programme is the most accurate for a period of around one to five years. Beyond this, renewal forecasts are best made using age profiles. Renewal forecasting involves determining the quantity of assets needing renewal (renewal tasks) and the unit costs per renewal task. The forecast renewal expenditure equals the product of these two factors. The asset condition information is presently being compiled in the Maintenance Management system, and so the full extent of condition-based renewal needs is still in progress. Estimates of condition-based renewal forecasts, calculated on the information available, have been entered into Powerco s Improvement Register and an extract of the renewal expenditure needs from this is given in Section 10 of the full AMP. Life-Extension Practices Various life-extension techniques have been tried by Powerco, but apart from transformer refurbishment, these really apply to only specialised assets, and many of the techniques have had only limited degrees of success. Redeployment, Upgrade and Disposal of Existing Assets Powerco is presently developing its policy on reusing second-hand materials, such as poles and conductors, and rotables, such as transformers. Powerco is also updating its disposal policies in line with its Environmental Strategy. It is not envisaged that any major network assets will need disposal that would have environmental consequences during the period covered by the full AMP. 18 SUMMARY ASSET MANAGEMENT PLAN ELECTRICITY NETWORKS FY2012 FY2021

21 NETWORK DEVELOPMENT PLAN The network security criteria describe the factors considered when preparing the long- and medium-term development plans. Load forecasts are presented and these, along with the security criteria, culminate in the capital works programme for development. Powerco has a range of development plans for different categories of equipment and customer bases. Network security of supply is a measure of the resilience of the network to operational changes, such as planned outages (e.g. those required for maintenance), and unforeseen events (e.g. forced outages, such as those caused by equipment failure or storms, as well as unexpected customer loads). The ability of the network to accommodate unforeseen events is a factor that can influence reliability of supply, somewhat akin to a network balance sheet. Powerco s security of supply criteria have been set taking into account the Electricity Engineers Association s Security of Supply Guidelines and the report, entitled Interaction between Transmission and Distribution System Planning from the CIGRE/CIRED Working Group, as well as the findings of the customer communications process. Load forecasting for the purposes of the Asset Management process is based on growth in peak-time demands. Peak requirements need to be understood to determine the required capacity of a lines infrastructure that will support local load growth. The most significant influences on demand growth continue to result from changes in population and household composition, and the growth or relocation of industry. Internal migration patterns thus have a strong influence on the observed demand growth. Government initiatives to promote energy efficiency and the preference for renewable sources of energy have been considered in preparing the forecast growth. Known industry changes such as oil and gas exploration and development; primary sector changes; and infrastructure, such as ports account for step changes seen in forecasts. The establishment of major new industries can have a considerable impact within a short time on the level of demand experienced in any given locality. The possibility of new spot loads is monitored through Key Account Managers, Resource Management Act notifications and consumer consultation. SUMMARY ASSET MANAGEMENT PLAN ELECTRICITY NETWORKS FY2012 FY

22 NETWORK PERFORMANCE ENHANCEMENT Powerco s network enhancement plans encompass: Reliability improvements, which take into account feeder reliability performance, historical trends and plans for automation; Protection and control developments, including SCADA, load control and metering; Environmental performance and improvement; Safety performance enhancement; and Smart network implementation. The network enhancement processes are driven by several of the big picture strategic themes of renewal and modernisation, automation, safety management and smartening the network. The major network enhancement projects Powerco wishes to undertake are described in the maps that follow in this Summary AMP. All network enhancement projects will also go through the multi-stakeholder assessment process. CAPITAL EXPENDITURE Capital expenditure (capex) is the budget used to create new assets or to increase the service performance or potential of an existing asset. The forecast total capital expenditure to FY2022 is shown in the graph below. Nominal Expenditure ($m) Total Network Capex 2006 A 2007 A 2008 A 2009 A 2010 A 2011 A 2012 B 2013 F 2014 F 2015 F Financial Year 2016 F 2017 F 2018 F 2019 F 2020 F 2021 F 2022 F Figure 13: Total Network Capital Expenditure Capital budgets, under the categories of System Growth, Reliability, Safety, Environment and Asset Renewal, are monitored at the end of every month and budget re-forecasts are made quarterly. A portion is set aside for reactive or unforeseen work, such as equipment failure or storms. Under- or over-spend in this category is accommodated by juggling other projects in the capital programme. Allowance is also made for opportunities to purchase land for future zone substation sites or easements for lines. In our experience, gradual land- or easement-banking, as the opportunities arise to a well-thought-out development plan, is a more efficient way of developing the network than an urgent short-term focus. 20 SUMMARY ASSET MANAGEMENT PLAN ELECTRICITY NETWORKS FY2012 FY2021

SUMMARY ASsET MANAGEMENT PLAN

SUMMARY ASsET MANAGEMENT PLAN SUMMARY ASsET MANAGEMENT PLAN INFORmATION DISCLOSURE FOR ELECTRICITY NETWORKS JUNE 2010 2019 ASSET MANAGEMENT PLAN ELECTRICITY NETWORKS FY2010 FY2019 1 contents CHIEF EXECUTIVE S STATEMENT... 2 POWERCO

More information

COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited

COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited PB ASSOCIATES COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN Prepared for PB Associates Quality System: Document Identifier : 153162 Top Energy Final Report Revision : 2 Report Status : Final Date

More information

Disclaimer: The information in this document has been prepared in good faith and represents Powerco s intentions and opinions at the date of issue.

Disclaimer: The information in this document has been prepared in good faith and represents Powerco s intentions and opinions at the date of issue. ASSET MANAGEMENT PLAN 2013 Disclaimer: The information in this document has been prepared in good faith and represents Powerco s intentions and opinions at the date of issue. Powerco however, operates

More information

Powerco Limited Pricing Guide 2015 ANNUAL REPORT 2015

Powerco Limited Pricing Guide 2015 ANNUAL REPORT 2015 ANNUAL REPORT 2015 PRICING GUIDE 2015 1 CONTENTS Introduction Page 03 Who we are Page 04 The Electricity Industry Page 05 Our Pricing Policy Page 08 How Powerco Performs Page 10 Pricing Methodology Page

More information

DISCLOSURE OF ELECTRICITY PRICING METHODOLOGY PURSUANT TO REQUIREMENT 22 OF THE ELECTRICITY INFORMATION DISCLOSURE REQUIREMENTS 2004

DISCLOSURE OF ELECTRICITY PRICING METHODOLOGY PURSUANT TO REQUIREMENT 22 OF THE ELECTRICITY INFORMATION DISCLOSURE REQUIREMENTS 2004 DISCLOSURE OF ELECTRICITY PRICING METHODOLOGY PURSUANT TO REQUIREMENT 22 OF THE ELECTRICITY INFORMATION DISCLOSURE REQUIREMENTS 2004 Effective 1 April 2010 TABLE OF CONTENTS 1 INTRODUCTION... 1 2 DESCRIPTION

More information

2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology

2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology 2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology Version Number 1 26 June 2015 Tasmanian Networks Pty Ltd (ACN 167 357 299) Table of contents 1 Introduction... 1 2 Meeting our

More information

NETWORK MANAGEMENT STRATEGY

NETWORK MANAGEMENT STRATEGY ABN 85 082 464 622 NETWORK MANAGEMENT STRATEGY DOCUMENT NUMBER: NW-#30065608-V6 DATE: 12 MAY 2011 NW-#30065608-v6-Network_Management_Strategy.DOC Page 1 of 20 This page is intentionally blank. NW-#30065608-v6-Network_Management_Strategy.DOC

More information

Lifecycle Strategy DISPOSAL AND DIVESTMENT

Lifecycle Strategy DISPOSAL AND DIVESTMENT Lifecycle Strategy DISPOSAL AND DIVESTMENT Document 07/10/2013 Page 1 of 19 C O P Y R I G H T 2013 T R A N S P O W E R N E W Z E A L A N D L I M I T E D. A L L R I G H T S R E S E R V E D This document

More information

ELECTRICITY DISTRIBUTION BUSINESS ASSET MANAGEMENT PLANS AND CONSUMER ENGAGEMENT : BEST PRACTICE RECOMMENDATIONS

ELECTRICITY DISTRIBUTION BUSINESS ASSET MANAGEMENT PLANS AND CONSUMER ENGAGEMENT : BEST PRACTICE RECOMMENDATIONS IN CONJUNCTION WITH SAUNDERS UNSWORTH LTD PARSONS BRINCKERHOFF ASSOCIATES ELECTRICITY DISTRIBUTION BUSINESS ASSET MANAGEMENT PLANS AND CONSUMER ENGAGEMENT : BEST PRACTICE RECOMMENDATIONS Prepared for APRIL

More information

Asset Management Policy March 2014

Asset Management Policy March 2014 Asset Management Policy March 2014 In February 2011, we published our current Asset Management Policy. This is the first update incorporating further developments in our thinking on capacity planning and

More information

TEC Capital Asset Management Standard January 2011

TEC Capital Asset Management Standard January 2011 TEC Capital Asset Management Standard January 2011 TEC Capital Asset Management Standard Tertiary Education Commission January 2011 0 Table of contents Introduction 2 Capital Asset Management 3 Defining

More information

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited TABLE OF CONTENTS 1.0 Purpose and Scope...2 1.1 Methodology Purpose...2

More information

RCP2 Portfolio Overview Document

RCP2 Portfolio Overview Document RCP2 Portfolio Overview Document Portfolio: Expenditure Class: Base Capex Expenditure Category: Grid Replacement & Refurbishment As at date: 15 November 2013 Expenditure Forecast Real 2012/13 NZ$ (m) 2015-2016

More information

Business Area Distribution

Business Area Distribution Business Area Distribution David Ringmar Director Network Strategy and Development Vattenfall Capital Markets Day, Solna, 27 May 2015 Facts and figures Business Area Distribution Vattenfall s total lenght

More information

Asset Management Strategy

Asset Management Strategy Asset Management Strategy ElectraNet Corporate Headquarters 52-55 East Terrace, Adelaide, South Australia 5000 PO Box, 7096, Hutt Street Post Office, Adelaide, South Australia 5000 Tel: (08) 8404 7966

More information

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission PLC, Scottish Hydro Electric Transmission Limited

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission PLC, Scottish Hydro Electric Transmission Limited NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission PLC, Scottish Hydro Electric Transmission Limited TABLE OF CONTENTS 1.0 Purpose and Scope...2 1.1 Methodology Purpose...2 2.0

More information

Corporate Risk Management Policy

Corporate Risk Management Policy Corporate Risk Management Policy Managing the Risk and Realising the Opportunity www.reading.gov.uk Risk Management is Good Management Page 1 of 19 Contents 1. Our Risk Management Vision 3 2. Introduction

More information

Gas Distribution Asset Management Plan 2013 2023

Gas Distribution Asset Management Plan 2013 2023 Gas Distribution Asset Management Plan 2013 2023 Table of Contents (Note that each section is individually numbered) SECTION 1 Executive Summary SECTION 2 2 BACKGROUND AND OBJECTIVES 4 2.1 Context for

More information

4 Adoption of Asset Management Policy and Strategy

4 Adoption of Asset Management Policy and Strategy 4 Adoption of Asset Management Policy and Strategy Abstract The report recommends the adoption of an updated Asset Management Policy 2014 and an Asset Management Strategy 2014-2019. Both documents are

More information

16 West Coast Regional Plan

16 West Coast Regional Plan 16 West Coast Regional Plan 16.1 Regional overview 16.2 West Coast transmission system 16.3 West Coast demand 16.4 West Coast generation 16.5 West Coast significant maintenance work 16.6 Future West Coast

More information

WATE R O&M S E RV I CE S An asset management perspective

WATE R O&M S E RV I CE S An asset management perspective WATE R O&M S E RV I CE S An asset management perspective Smart asset management solutions create long term value With more than 150 years of water industry experience and responsibility for operations

More information

Cost Allocation Method

Cost Allocation Method Cost Allocation Method Ergon Energy Corporation Limited Document Summary Version: 4.0 Status: AER Approved Version History and Date of Issue Version Date Issued Summary of Changes 1.0 March 2009 Initial

More information

AFFILIATE RELATIONSHIPS CODE FOR ELECTRICITY DISTRIBUTORS AND TRANSMITTERS

AFFILIATE RELATIONSHIPS CODE FOR ELECTRICITY DISTRIBUTORS AND TRANSMITTERS AFFILIATE RELATIONSHIPS CODE FOR ELECTRICITY DISTRIBUTORS AND TRANSMITTERS ONTARIO ENERGY BOARD Revised May 16, 2008 (Originally issued on April 1, 1999) 1. GENERAL AND ADMINISTRATIVE PROVISIONS 1.1 Purpose

More information

Jemena Electricity Networks (Vic) Ltd

Jemena Electricity Networks (Vic) Ltd Jemena Electricity Networks (Vic) Ltd 2016-20 Electricity Distribution Price Review Regulatory Proposal Attachment 7-2 Asset management framework and governance Public 30 April 2015 Jemena Electricity

More information

Asset Management Plan

Asset Management Plan 2013 Asset Management Plan www.topenergy.co.nz INTRODUCTION Introduction It gives me great pleasure to present Top Energy s 2013-2023 Network Asset Management Plan (AMP). The 2013 plan follows on from

More information

Network Risk Assessment Guideline

Network Risk Assessment Guideline Network Risk Assessment Guideline Network Risk Assessment Guideline Table of Contents Revision history... ii 1. Purpose and Scope... 1 2. Definitions, Abbreviations and Acronyms... 1 3. References... 2

More information

CUSTOMER-FACING PERFORMANCE MEASURES

CUSTOMER-FACING PERFORMANCE MEASURES CUSTOMER-FACING PERFORMANCE MEASURES CUSTOMER FEEDBACK AND RESPONSE Transpower New Zealand Limited March 2013 Customer-facing performance measures Transpower New Zealand Limited 2007. All rights reserved.

More information

Changing data needs from a life cycle perspective in the context of ISO 55000

Changing data needs from a life cycle perspective in the context of ISO 55000 Changing data needs from a life cycle perspective in the context of ISO 55000 Mr. Ed de Vroedt and Mr. Peter Hoving Affiliation: UMS Group Europe; edevroedt@umsgroup.com, +316 1026 6162 ABSTRACT This paper

More information

Asset Management Plan. A 10-year management plan for Orion s electricity network from 1 April 2014 to 31 March 2024

Asset Management Plan. A 10-year management plan for Orion s electricity network from 1 April 2014 to 31 March 2024 Asset Management Plan A 10-year management plan for Orion s electricity network from 1 April 2014 to 31 March 2024 Front cover: A team from Connetics installs 11,000 volt and 400 volt cables into a supply

More information

SP Energy Networks 2015 2023 Business Plan

SP Energy Networks 2015 2023 Business Plan Environmental Discretionary Reward Scheme 1 SP Energy Networks 2015 2023 Business Plan Executive summary SP Distribution Ltd SP Manweb plc July 2013 RIIO ED1 Business Plan 2015 to 2023 2 A Message from

More information

Asset Management Plan. A 10-year management plan for Orion s electricity network from 1 April 2015 31 March 2025

Asset Management Plan. A 10-year management plan for Orion s electricity network from 1 April 2015 31 March 2025 Asset Management Plan A 10-year management plan for Orion s electricity network from 1 April 2015 31 March 2025 Front cover: A team from Independent Line Services removing conductors prior to dismantling

More information

Asset Management Plan 2012

Asset Management Plan 2012 Asset Management Plan 2012 Period Covered: 1 April 2012 to 31 March 2022 Approved by: Network Waitaki Directors 27 February 2012 Table of Contents 1.0 Summary 5 1.1 Purpose of the Plan 5 1.2 Date Completed

More information

EDB Information Disclosure Requirements Information Templates for Schedules 11a 13

EDB Information Disclosure Requirements Information Templates for Schedules 11a 13 EDB Information Disclosure Requirements Information Templates for Schedules 11a 13 Disclosure Date 31 March 2015 Start Date (first day) 1 April 2015 Templates for Schedules 11a 13 (Asset Management Plan)

More information

ASSET MANAGEMENT STRATEGY Approved

ASSET MANAGEMENT STRATEGY Approved Approved Document TP.TG 01.01 30/10/2014 Approved Transpower New Zealand Limited 2014. All rights reserved. Page 1 of 25 C O P Y R I G H T 2014 T R A N S P O W E R N E W Z E A L A N D L I M I T E D. A

More information

Agenda do Mini-Curso. Sérgio Yoshio Fujii. Ethan Boardman. sergio.fujii@areva-td.com. ethan.boardman@areva-td.com

Agenda do Mini-Curso. Sérgio Yoshio Fujii. Ethan Boardman. sergio.fujii@areva-td.com. ethan.boardman@areva-td.com Agenda do Mini-Curso Sérgio Yoshio Fujii sergio.fujii@areva-td.com Ethan Boardman ethan.boardman@areva-td.com Agenda do Mini-Curso Sistemas de Distribuição (DMS) Characteristics of Distribution Network

More information

PUBLIC UTILITIES COMMISSIO~t~ Docket No. DE 15-

PUBLIC UTILITIES COMMISSIO~t~ Docket No. DE 15- Th~NALZZ~ Exhibit STATE OF NEW HAMPSHIRE t~~eeee BEFORE THE FROM FILE PUBLIC UTILITIES COMMISSIO~t~ Liberty Utilities (Granite State Electric) Corp. dibla Liberty Utilities Calendar Year 2014 Reliability

More information

to Asset Management Policy and Guidance Draft Version 1.4 9 July 2015

to Asset Management Policy and Guidance Draft Version 1.4 9 July 2015 D to Asset Management Policy and Guidance Draft Version 1.4 9 July 2015 This page has been left blank intentionally Page 2 of 24 Page 3 of 24 This page has been left blank intentionally Page 4 of 24 Strategic

More information

Attachment 20.27 SA Power Networks: Network Program Deliverability Strategy

Attachment 20.27 SA Power Networks: Network Program Deliverability Strategy Attachment 20.27 SA Power Networks: Network Program Deliverability Strategy Network Program Deliverability Strategy 2015-20 Regulatory Control Period SA Power Networks www.sapowernetworks.com.au Internal

More information

6 June 2014. Cathyrn Blair Stakeholder Engagement 2015 to 2020 Directions and Priorities SA Power Networks GPO Box 77 ADELAIDE SA 5001.

6 June 2014. Cathyrn Blair Stakeholder Engagement 2015 to 2020 Directions and Priorities SA Power Networks GPO Box 77 ADELAIDE SA 5001. ABN 14 725 309 328 136 Greenhill Road Unley SA 5061 Telephone 08 8300 0103 Fax 08 8300 0204 Email customerservice@business-sa.com www.business-sa.com 6 June 2014 Cathyrn Blair Stakeholder Engagement 2015

More information

Commission de l énergie de l Ontario. Filing Requirements for Electricity Transmission and Distribution Applications. Chapter 5.

Commission de l énergie de l Ontario. Filing Requirements for Electricity Transmission and Distribution Applications. Chapter 5. Ontario Energy Board Commission de l énergie de l Ontario Ontario Energy Board Filing Requirements for Electricity Transmission and Distribution Applications Chapter 5 Consolidated Distribution System

More information

NETWORK OUTPUT MEASURES CONSULTATION

NETWORK OUTPUT MEASURES CONSULTATION NETWORK OUTPUT MEASURES CONSULTATION Great Britain s electricity transmission network transmits high-voltage electricity from where it is produced to where it is needed throughout the country. It broadly

More information

Low Voltage Asset Management (LVAM) The key to reliable and safe electricity

Low Voltage Asset Management (LVAM) The key to reliable and safe electricity Low Voltage Asset Management (LVAM) The key to reliable and safe electricity Archie Jaykaran Distribution Division Eskom SA Contents Change drivers Scope, Approach, Project status LV Planning and Design

More information

Asset Management Plan 2012 2022

Asset Management Plan 2012 2022 Asset Management Plan 2012 2022 April 2012 safe, reliable, hassle free service safe, reliable, hassle free service Table of Contents Section 1: Summary Section 2: Background and Objectives Section 3: Assets

More information

Western Power transmission and distribution annual asset management report. prepared by Asset Management Division

Western Power transmission and distribution annual asset management report. prepared by Asset Management Division 2006 Western Power transmission and distribution annual asset management report prepared by Asset Management Division Disclaimer The Asset Management Division of Western Power has published this document

More information

2006 Report. of the. Optimised Deprival Valuation of Transpower s System Fixed Assets. as at 30 June 2006

2006 Report. of the. Optimised Deprival Valuation of Transpower s System Fixed Assets. as at 30 June 2006 T R A N S P O W E R N E W Z E A L A N D L I M I T E D 2006 Report of the Optimised Deprival Valuation of Transpower s System Fixed Assets as at 30 June 2006 Prepared by Transpower New Zealand Limited Reviewed

More information

7 Directorate Performance Managers. 7 Performance Reporting and Data Quality Officer. 8 Responsible Officers

7 Directorate Performance Managers. 7 Performance Reporting and Data Quality Officer. 8 Responsible Officers Contents Page 1 Introduction 2 2 Objectives of the Strategy 2 3 Data Quality Standards 3 4 The National Indicator Set 3 5 Structure of this Strategy 3 5.1 Awareness 4 5.2 Definitions 4 5.3 Recording 4

More information

The Asset Management Landscape

The Asset Management Landscape The Asset Management Landscape ISBN 978-0-9871799-1-3 Issued November 2011 www.gfmam.org The Asset Management Landscape www.gfmam.org ISBN 978-0-9871799-1-3 Published November 2011 This version replaces

More information

Updated SCER Demand Side Participation Program December 2013

Updated SCER Demand Side Participation Program December 2013 Updated SCER Demand Side Participation Program December 2013 The Standing Council on Energy and Resources (SCER) has adopted this framework to guide its demand side participation (DSP) work. The framework

More information

Executive summary 2. 1 Introduction 4

Executive summary 2. 1 Introduction 4 Flexible Networks for a Low Carbon Future Future Network Monitoring Strategy September 2015 Contents Executive summary 2 Glossary 3 1 Introduction 4 2 Fundamental principles of monitoring 5 2.1 LCT monitoring

More information

SMART ASSET MANAGEMENT MAXIMISE VALUE AND RELIABILITY

SMART ASSET MANAGEMENT MAXIMISE VALUE AND RELIABILITY SMART ASSET MANAGEMENT MAXIMISE VALUE AND RELIABILITY Electrical equipment is a critical component of your asset portfolio. Beyond its financial value, it plays an even greater role in your business performance.

More information

Before the Department of Energy Washington, D.C. 20585 ) ) ) ) ) ) NBP RFI: Data Access, Third Party Use, and Privacy

Before the Department of Energy Washington, D.C. 20585 ) ) ) ) ) ) NBP RFI: Data Access, Third Party Use, and Privacy Before the Department of Energy Washington, D.C. 20585 In the Matter of Implementing the National Broadband Plan by Empowering Consumers and the Smart Grid: Data Access, Third Party Use, and Privacy )

More information

Asset Management System. ERA Assessment Report

Asset Management System. ERA Assessment Report Report for: Asset Management System ERA Assessment Report LR ref: 1660006 Western Power Corporation Assessment dates: 26 th May 6 th June 2008 Assessment location: Perth Western Australia Assessment criteria:

More information

ENTERPRISE RISK MANAGEMENT FRAMEWORK

ENTERPRISE RISK MANAGEMENT FRAMEWORK ROCKHAMPTON REGIONAL COUNCIL ENTERPRISE RISK MANAGEMENT FRAMEWORK 2013 Adopted 25 June 2013 Reviewed: October 2015 TABLE OF CONTENTS 1. Introduction... 3 1.1 Council s Mission... 3 1.2 Council s Values...

More information

Capital Works Management Framework

Capital Works Management Framework POLICY DOCUMENT Capital Works Management Framework Policy for managing risks in the planning and delivery of Queensland Government building projects Department of Public Works The concept of the asset

More information

Company Policy MANAGEMENT OF OVERHEAD PRIVATE AND SHARED MAINS. Page 1 of 11

Company Policy MANAGEMENT OF OVERHEAD PRIVATE AND SHARED MAINS. Page 1 of 11 MANAGEMENT OF OVERHEAD PRIVATE AND SHARED MAINS Page 1 of 11 MANAGEMENT OF OVERHEAD PRIVATE AND SHARED MAINS 2015 Contents 1.0 POLICY STATEMENT... 3 2.0 PURPOSE... 4 3.0 REFERENCES... 4 4.0 DEFINITIONS...

More information

An Introduction to Risk Management. For Event Holders in Western Australia. May 2014

An Introduction to Risk Management. For Event Holders in Western Australia. May 2014 An Introduction to Risk Management For Event Holders in Western Australia May 2014 Tourism Western Australia Level 9, 2 Mill Street PERTH WA 6000 GPO Box X2261 PERTH WA 6847 Tel: +61 8 9262 1700 Fax: +61

More information

Central bank corporate governance, financial management, and transparency

Central bank corporate governance, financial management, and transparency Central bank corporate governance, financial management, and transparency By Richard Perry, 1 Financial Services Group This article discusses the Reserve Bank of New Zealand s corporate governance, financial

More information

FIXED CHARGE: This is a cost that goes towards making the service available, including

FIXED CHARGE: This is a cost that goes towards making the service available, including ELECTRICITY BILL COMPONENTS FIXED CHARGE: This is a cost that goes towards making the service available, including installation and maintenance of poles, power lines and equipment, and 24-hour customer

More information

BPM 2015: Business Process Management Trends & Observations

BPM 2015: Business Process Management Trends & Observations BPM 2015: Business Process Management Trends & Observations 1 I BPM 2015: Business Process Management Trends & Observations BPM 2015: Business Process Management Trends & Observations Executive Summary

More information

Attachment 16.1 SA Power Networks: Customer Data Quality Plan 2015-2020 September 2014

Attachment 16.1 SA Power Networks: Customer Data Quality Plan 2015-2020 September 2014 Attachment 16.1 SA Power Networks: Customer Data Quality Plan 2015-2020 September 2014 Customer Data Quality Plan 2015-2020 V1.1 Executive Summary The commencement of Full Retail Contestability in 2004

More information

Last revised: September 1, 2014 TRANSMISSION FUNCTION TITLES AND JOB DESCRIPTIONS

Last revised: September 1, 2014 TRANSMISSION FUNCTION TITLES AND JOB DESCRIPTIONS Last revised: September 1, 2014 TRANSMISSION FUNCTION TITLES AND JOB DESCRIPTIONS EVP, Chief Operations Officer, has primary responsibility for the overall planning, operations and control of the transmission

More information

SHE Transmission. 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015

SHE Transmission. 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015 SHE Transmission 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015 Summary This paper presents SHE Transmission s views and approach on the impact of transmission losses on the transmission

More information

Asset Management Plan

Asset Management Plan 2014 Asset Management Plan www.topenergy.co.nz INTRODUCTION Introduction It gives me great pleasure to present Top Energy s 2014-2024 Network Asset Management Plan (AMP). The 2014 AMP follows on from the

More information

Network Asset Management Plan

Network Asset Management Plan Network Asset Management Plan CEOM 8018 2014-2019 Page 1 of 87 TROLLED COPY IF PRINTED UNCON PREPARED BY: CAPITAL WORKS P ROGRAM M ANAGER DOCUMENT NUMBER: AUTHORISED BY: PAUL BRAZIER POSITION TITLE: Manager

More information

HIGH PEAK BOROUGH COUNCIL. Report to the Corporate Select Committee. 19th January 2016

HIGH PEAK BOROUGH COUNCIL. Report to the Corporate Select Committee. 19th January 2016 AGENDA ITEM 5 HIGH PEAK BOROUGH COUNCIL Report to the Corporate Select Committee 19th January 2016 TITLE: EXECUTIVE COUNCILLOR: CONTACT OFFICER: WARDS INVOLVED: Housing Revenue Account (HRA) Business Plan

More information

June 2015. Position Paper Contribution to the debate on electricity market design and capacity markets

June 2015. Position Paper Contribution to the debate on electricity market design and capacity markets June 2015 Position Paper Contribution to the debate on electricity market design and capacity markets Eurogas is the association representing the European gas wholesale, retail and distribution sectors.

More information

Asset Management Plan

Asset Management Plan Asset Management Plan 2010-2019 West Coast s Locally Owned Electricity Distributor Asset Management Plan A 10 Year Management Plan for Westpower s Electricity Network From 1 April 2009 to 31 March 2019

More information

Customer Installation Safety Plan. March 2015

Customer Installation Safety Plan. March 2015 Customer Installation Safety Plan March 2015 Document History Issue No. Date Approved By Summary of Changes 1 June 2014 Chief Engineer Updated and revised in line with requirement for biennial review under

More information

THE STATE OF THE New ECONOMY

THE STATE OF THE New ECONOMY THE STATE OF THE New Zealand DIGITAL ECONOMY October 2012 CONTENTs EXECUTIVE SUMMARY 2 EXPANDING THE DIGITAL ECONOMY 3 THE PROMISE OF THE DIGITAL ECONOMY 5 CLOUD COMPUTING: THE BENEFIT OF NEW TECHNOLOGIES

More information

Smart meters: Removing regulatory barriers and maintaining consumer safety for a market-led roll out of smart meters in New South Wales

Smart meters: Removing regulatory barriers and maintaining consumer safety for a market-led roll out of smart meters in New South Wales Smart meters: Removing regulatory barriers and maintaining consumer safety for a market-led roll out of smart meters in New South Wales The NSW Government is committed to a voluntary, market-led roll out

More information

A RESPONSIBLE, COLLABORATIVE AND AGILE ORGANISATION

A RESPONSIBLE, COLLABORATIVE AND AGILE ORGANISATION 44 NZ Transport Agency Statement of intent 215 19 A RESPONSIBLE, COLLABORATIVE AND AGILE ORGANISATION In order to deliver our desired targets and results effectively and efficiently, we continue to invest

More information

A Guide For Preparing The Financial Information Component Of An Asset Management Plan. Licensing, Monitoring and Customer Protection Division

A Guide For Preparing The Financial Information Component Of An Asset Management Plan. Licensing, Monitoring and Customer Protection Division A Guide For Preparing The Financial Information Component Of An Asset Management Plan Licensing, Monitoring and Customer Protection Division July 2006 Contents 1 Important Notice 2 2 Scope and purpose

More information

2014 Price Review Business Plan Supporting Appendices Network Management. Published 2 December 2013

2014 Price Review Business Plan Supporting Appendices Network Management. Published 2 December 2013 2014 Price Review Business Plan Supporting Appendices Network Management Published 2 December 2013 2 Executive Summary This appendix summarises our approach to Network Management. The appendix focuses

More information

Investors in People Assessment Report. Presented by Alli Gibbons Investors in People Specialist On behalf of Inspiring Business Performance Limited

Investors in People Assessment Report. Presented by Alli Gibbons Investors in People Specialist On behalf of Inspiring Business Performance Limited Investors in People Assessment Report for Bradstow School Presented by Alli Gibbons Investors in People Specialist On behalf of Inspiring Business Performance Limited 30 August 2013 Project Reference Number

More information

Distributed Generation: Frequently Asked Questions

Distributed Generation: Frequently Asked Questions Distributed Generation: Frequently Asked Questions 1) What is distributed generation (DG)? Generating technologies located close to where the electricity is being used that are connected to the electric

More information

Review of Asset Management Practices in the Ontario Electricity Distribution Sector March 10th, 2009

Review of Asset Management Practices in the Ontario Electricity Distribution Sector March 10th, 2009 Review of Asset Management Practices in the Ontario Electricity Distribution Sector March 10th, 2009 Disclaimer The views expressed in this report are those of KPMG LLP and do not necessarily represent

More information

Network Pricing Trends

Network Pricing Trends Network Pricing Trends Queensland Perspective 20 January 2015 Foreword This report has been prepared for Infrastructure Partnerships Australia (IPA). Its purpose is to help build community understanding

More information

UNDERGROUND TELECOMMUNICATIONS CABLES ACROSS PRIVATE LAND

UNDERGROUND TELECOMMUNICATIONS CABLES ACROSS PRIVATE LAND FACT SHEET TELEPHONE 0800 327 646 I WEBSITE WWW.FEDFARM.ORG.NZ UNDERGROUND TELECOMMUNICATIONS CABLES ACROSS PRIVATE LAND BACKGROUND The Rural Broadband Initiative envisages substantially improved broadband

More information

ENTERPRISE RISK MANAGEMENT POLICY

ENTERPRISE RISK MANAGEMENT POLICY ENTERPRISE RISK MANAGEMENT POLICY TITLE OF POLICY POLICY OWNER POLICY CHAMPION DOCUMENT HISTORY: Policy Title Status Enterprise Risk Management Policy (current, revised, no change, redundant) Approving

More information

Washington DC Power Sector Overview

Washington DC Power Sector Overview Washington DC Power Sector Overview Kenneth (Ken) Glick Public Service Commission Of the District of Columbia December 8, 2014 DC Power Market Area - Summary Single electric utility that has divested itself

More information

Attachment 20.73 SA Power Networks: Capital and operating historical expenditure October 2014

Attachment 20.73 SA Power Networks: Capital and operating historical expenditure October 2014 Attachment 20.73 SA Power Networks: Capital and operating historical expenditure October 2014 Contents 1. Purpose... 3 2. Capital expenditure... 3 2.1 Capital expenditure summary 2005-2020... 3 2.2 Explanation

More information

Tasmanian Transmission Revenue Proposal

Tasmanian Transmission Revenue Proposal Tasmanian Transmission Revenue Proposal An overview for Tasmanian electricity consumers Regulatory control period 1 July 2014 30 June 2019 Tasmanian Networks Pty Ltd About TasNetworks We are Tasmania s

More information

Risk Management Plan 2012-2015

Risk Management Plan 2012-2015 Risk Management Plan 2012-2015 This controlled document shall not be copied in part or whole without the express permission of the author or the author s representative. Revision Date Previous Revision

More information

ESB Networks Response. ERGEG Consultation. Voltage Quality Regulation in Europe

ESB Networks Response. ERGEG Consultation. Voltage Quality Regulation in Europe NETWORKS ESB Networks Response to ERGEG Consultation on Voltage Quality Regulation in Europe Date: 22 February 2007 Distribution System Operator ESB Networks Page 1 of 12 Contents 1.0 INTRODUCTION...3

More information

Slough Borough Council. Highway Asset Management Strategy

Slough Borough Council. Highway Asset Management Strategy Slough Borough Council Highway Asset Management Strategy OUR AMBITION USING RESOURCES WISELY By 2019 the Council s income and the value of its assets will be maximised 1 Key Priorities 1.1 We understand

More information

Naperville Smart Grid Initiative

Naperville Smart Grid Initiative Naperville Smart Grid Initiative Business Case Fundamentals Updated on 9/7/2010 Summary The NGSI program delivers an excellent ROI by increasing network reliability, operational efficiencies, reducing

More information

Treasure Valley Electric Plan - Community Advisory Committee

Treasure Valley Electric Plan - Community Advisory Committee Treasure Valley Electric Plan - Community Advisory Committee What is a transmission line and why are they necessary? A transmission line is used to conduct electricity between two points. Without high

More information

- Internal distribution only. Corporate Real Estate and Facilities Cost Reduction

- Internal distribution only. Corporate Real Estate and Facilities Cost Reduction - Internal distribution only Corporate Real Estate and Facilities Cost Reduction Summary By moving from typical to best practice, organisations can improve value for money and reduce their real estate

More information

ELECTRICITY PRICING METHODOLOGY 2013

ELECTRICITY PRICING METHODOLOGY 2013 ELECTRICITY PRICING METHODOLOGY 2013 EFFECTIVE 1 APRIL 2013 DISCLOSED IN ACCORDANCE WITH SECTION 2.4.1 OF THE ELECTRICITY DISTRIBUTION INFORMATION DISCLOSURE DETERMINATION 2012 CONTENTS PAGE 1. Definitions...

More information

Finance Effectiveness Efficiency

Finance Effectiveness Efficiency Business Unit Finance Effectiveness Efficiency An overview Agenda Page 1 Efficiency - An overview 1 2 Our services 7 3 Case study 14 Section 1 Efficiency - An overview 1 Section 1 Efficiency - An overview

More information

OPERATIONAL CASE STUDY PRACTICE EXAM ANSWERS

OPERATIONAL CASE STUDY PRACTICE EXAM ANSWERS OPERATIONAL CASE STUDY PRACTICE EXAM ANSWERS The Practice Exam can be viewed at http://www.pearsonvue.com/cima/practiceexams/ These answers have been provided by CIMA for information purposes only. The

More information

Safety Management Systems (SMS) guidance for organisations

Safety Management Systems (SMS) guidance for organisations Safety and Airspace Regulation Group Safety Management Systems (SMS) guidance for organisations CAP 795 Published by the Civil Aviation Authority, 2014 Civil Aviation Authority, CAA House, 45-59 Kingsway,

More information

Risk management systems of responsible entities

Risk management systems of responsible entities Attachment to CP 263: Draft regulatory guide REGULATORY GUIDE 000 Risk management systems of responsible entities July 2016 About this guide This guide is for Australian financial services (AFS) licensees

More information

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV 1. SCOPE This document details PowerSystems requirements for electrical testing of HV Equipment up to and including 33kV. 2. ISSUE RECORD This is a Reference document. The current version of Controlled

More information

Infor Enterprise Asset Management (EAM)

Infor Enterprise Asset Management (EAM) PROGRESSIVE Infor Enterprise Asset Management (EAM) Joined up thinking dedicated to the oil & gas industry www.progressive-tsl.com Infor Enterprise Asset Management (EAM) Infor Enterprise Asset Management

More information

EXECUTIVE SUMMARY. Asset Management Relationships and Dependencies. Introduction

EXECUTIVE SUMMARY. Asset Management Relationships and Dependencies. Introduction EXECUTIVE SUMMARY Introduction The Asset Management Plan demonstrates sound stewardship of the Region s existing assets to support services at desired levels and to ensure the support of the Region s infrastructure

More information

ESKOM DISTRIBUTION NETWORK PLANNING, A QUANTUM LEAP TO MEET INCREASED LOAD GROWTH AND IMPROVED NETWORK RELIABILITY

ESKOM DISTRIBUTION NETWORK PLANNING, A QUANTUM LEAP TO MEET INCREASED LOAD GROWTH AND IMPROVED NETWORK RELIABILITY ESKOM DISTRIBUTION NETWORK PLANNING, A QUANTUM LEAP TO MEET INCREASED LOAD GROWTH AND IMPROVED NETWORK RELIABILITY Author & Presenter: CG Carter-Brown PhD Eskom, Chief Engineer IARC Co-author: R Stephen

More information

TRANSPORT FOR LONDON CORPORATE PANEL

TRANSPORT FOR LONDON CORPORATE PANEL AGENDA ITEM 4 TRANSPORT FOR LONDON CORPORATE PANEL SUBJECT: EMPLOYEE ENGAGEMENT DATE: 17 NOVEMBER 2009 1 PURPOSE AND DECISION REQUIRED 1.1 The purpose of this report is to advise the Panel on TfL s approach

More information

REVIEW OF ELECTRICITY (CONSUMER SAFETY) ACT 2004 ISSUES PAPER

REVIEW OF ELECTRICITY (CONSUMER SAFETY) ACT 2004 ISSUES PAPER REVIEW OF ELECTRICITY (CONSUMER SAFETY) ACT 2004 ISSUES PAPER April 2010 HOW TO MAKE A SUBMISSION Written submissions are invited to this Issues Paper. Please send submissions by email to: policy@services.nsw.gov.au

More information

Water Environment Association of Texas. General Concepts of Asset Management

Water Environment Association of Texas. General Concepts of Asset Management Water Environment Association of Texas General Concepts of Asset Management Wayne Francisco June 5, 2013 How to best use the money we receive to preserve our infrastructure Yes, it is something you re

More information