1 SPECIFICATIONS Rev: Section Helical Steel Piles 1. General 1.1. Description The work of this section consists of furnishing and installing steel helical piles manufactured by MacLean-Dixie LLC, Birmingham, AL Steel helical piles shall be designed and installed to resist the unfactored design loads as shown on Sheet S-. The geotechnical report for the site dated by is included in this project manual as specification section Related work specified elsewhere: All work as described herein shall be performed in accordance with all applicable safety codes in effect at the time of installation Quality Assurance Installation contractor s qualifications: installation shall be by a MacLean- Dixie Helical Foundation Systems authorized installation contractor. Proof of current certification by MacLean-Dixie Anchoring Systems shall be submitted to the Owner or their representative prior to starting installation upon request of the Owner or their representative All helical piles shall be installed in the presence of a designated representative of the Owner unless the Owner or their representative informs the installation contractor otherwise Welding: procedures shall meet the requirements of AWS Structural Welding Code, D1.1, latest edition. All welders shall be AWS certified Helical pile system shall be ICC-ES listed. The installation contractor shall furnish evidence to the Owner or their representative by means of the ICC-ES Evaluation Report number PFC-5551 if required. 1 of 9

2 1.3. Allowable Tolerances The following tolerances are suggested maximums. The final tolerances for a given project will be established prior to the commencement of the installation of the helical piles and will depend on the specific requirements of the project The centerline of the helical piles shall be within 2 inches of the location as shown on the plans Helical piles shall be within 2 degrees of design alignment The top elevation of the helical pile shall be within +1 inch to -1 inch of plan elevation. 2. Submittals 2.1 Construction Submittals The contractor shall submit working drawings for the helical piles to the Owner or their representative prior to the start of construction for review and approval if required The contractor shall submit detailed construction procedures proposed for use along with a list of the major installation equipment to the Owner or their representative if required The working drawings shall include the following items: a. Helical pile number and location b. Helical pile design load c. Type and size of shaft d. Helical configuration and diameter of helical plates e. Minimum effective installation torque f. Minimum overall length g. Angle of installation of the pile, if other than vertical h. Pile head elevation i. Helical pile attachment to the structure The contractor shall submit shop drawings for the helical pile components, including the corrosion protection and pile top termination device to the Owner or their representative for review and approval The contractor shall submit copies of calibration reports for each torque indicator or torque motor to be used on the project if requested by the Owner or their representative. The calibration tests shall be performed within forty five (45) days of the submitted date. The installation of the 2 of 9

3 helical piles shall not commence until the Owner or their representative has received the calibration reports. The calibration reports shall include, but are not limited to, the following information: a. Name of project and contractor b. Name of testing agency c. Identification (serial number) of device calibrated d. Description of calibrated testing equipment e. Date of calibration Work shall not commence until all submittals have been received and approved by the Owner or their representative. The contractor shall provide the Owner or their representative a reasonable amount of time to review, comment, and return the submittal documents after a complete set has been received. 2.2 Installation Records The contractor shall provide the Owner or their representative copies of all helical pile installation records with 24 hours after each installation is completed. These installation records shall include, but are not limited, to the following information: a. Name of project and contractor b. Name of contractor s supervisor during the installation of the piles c. Date and time of installation d. Name and model of installation equipment e. Type of torque indicator used f. Location of helical pile by assigned identification number g. Actual helical pile type and configuration including lead section (number and diameter of helical plates, number and type of extensions sections (manufacturer s SKU numbers) h. Helical piles installation time and any observations i. Total length of installed helical pile j. Cut-off elevation k. Installation angle of the helical pile l. Installation torque at one-foot intervals for at least the final 10 feet of installation m. Comments regarding any interruptions, obstructions, or other installation relevant information n. Rated load capacities. 3 of 9

4 3. Products and Materials 3.1 Solid Shaft Piles (Lead section and extensions) The 1½, 1¾ and 2 inch round cornered square (RCS) solid steel shafts shall be formed from hot-wrought carbon steel and shall confirm to ASTM A576 and the following descriptions: Grade 10V45M or equal, having a minimum yield strength of 70 KSI Grade 1530M, having a minimum yield strength of 90 KSI The round cornered square (RCS) solid steel shafts shall conform to the following torque rating (torsional strength): ,000 ft-lbs for 1½ inch RCS shafts ,000 ft-lbs for 1½ inch RCS high strength shafts ,000 ft-lbs for 1¾ inch RCS shafts ,000 ft-lbs for 2 inch RCS shafts Bolt holes cannot exceed +1/16 inch the nominal bolt diameter 3.2 Pipe Piles (Lead and extensions) The 2-7/8, 3-1/2 and 4-1/2 O.D. pipe piles shall conform to ASTM A500 Grade B The coupling material shall confirm to AISI 8620 or SC1045 per ASTM A The pipe helical pile shall conform to the following torque rating: ,500 ft-lbs for P28 series 2⅞ inch O.D. Schedule 40 Pipe Pile ,000 ft-lbs for P28 series 2⅞ inch O.D. Schedule 80 Pipe Pile ,400 ft-lbs for P35 series 3½ inch O.D. Schedule 40 Pipe Pile ,300 ft-lbs for P35 series 3½ inch O.D. Schedule 80 Pipe Pile ,000 ft-lbs for P45 series 4½ inch O.D. Schedule 40 Pipe Pile ,000 ft-lbs for P45 series 4½ inch O.D. Schedule 80 Pipe Pile ,000 ft-lbs for P8 series 8-5/8 inch O.D wall thickness 4 of 9

5 3.3 Helical Plates Helical plates shall be either ⅜ or ½ inch thick and shall conform to the following specification: ASTM 1011/1018 HSLA 55 or equal The leading edge (leading edge of helix welded to the shaft intersection) of all helices must be in the same plane. 3.4 Bolts/Nuts The sizes and types of bolts and nuts used to connect the helix pile extensions to lead sections or another extension shall conform to the following ASTM specifications: Coupling bolts with ⅝, ¾, or ⅞ inch diameter shall comply with ASTM A325 Grade 5, and shall have a Class C, hotdipped, zinc coating that complies with ASTM A153 Coupling bolts with 1 1/8 diameter on the 2 RCS or ¾ diameter on the 8 5/8, P8 pipe pile shall comply with SAE J429 Grade 8 or ASTM A354 grade BD, and shall have yellow dichromate zinc coating Coupling nuts shall conform to ASTM A563 and shall have a Class C, hot-dipped, zinc coating that complies with ASTM A Connection (Coupling Leads and Extensions) 3.5 Finish Couplings (engagement) for round corner steel (RCS) extensions will be formed as an integral part of the shaft extension material through a forging process except the 2 RCS. For the 2 RCS, the engagement will be a cast coupling Pipe pile couplings must be square engagement with connecting bolts not subjected to shear or bending during installation Couplings for pipe piles shall be cast steel AISI 8620 or SC1045 grade 40/ All other materials, if galvanizing is specified, shall have a Class B1, hot-dipped, galvanized coating, complying with ASTM A Material may also be furnished black (non-galvanized). 5 of 9

6 4.0 Execution 4.1 Site Conditions 4.2 Equipment The contractor shall review the work of all other trades and verify that all said work is completed to the point where helical pile installations may commence without restriction. The contractor shall verify that all helical piles can be installed in accordance with all relevant codes and regulations regarding such items as underground obstructions, utilities, right-of-way limitations, etc. The contactor shall notify the Owner or their representative of any noted discrepancy. The contractor shall not proceed with the installation of helical piles in the area(s) of said discrepancies until the discrepancies have been resolved. All costs associated with unresolved discrepancies shall be the responsibility of the Owner Installation equipment shall be a rotary type, hydraulic power driven torque motor with equal forward and reverse torque capabilities. This equipment shall be capable of continual adjustment of the torque drive unit s revolutions per minute (RPM s) during installation. Percussion drilling equipment will not be allowed. The torque motor shall have a torque capacity at least 15% greater than the torsional strength of steel shaft to be installed Equipment shall be capable of simultaneously applying adequate down pressure and torque. The equipment shall be capable of continuous position adjustment to maintain the proper helical pile alignment. 4.3 Installation Tooling Installing tooling shall consist of a Kelly Bar Adapter (KBA) and drive tools for the helical pile types to be used on the project. All tooling shall be used in accordance with the manufacturer s written installation instructions A torque indicator shall be used during the installation of all helical piles. The torque being applied by the installing units shall be monitored throughout the installation by the contractor. The torque-monitoring device shall either be a part of the installing unit or an independent device in-line with the installing unit. Calibration for either unit shall be available for review by the owner. Torque indicators shall: 6 of 9

7 a. Be capable of providing continuous measurement of the applied torque throughout the installation. b. Be capable of torque measurements in increments of at least 500 ft-lbs. c. Be calibrated prior to pre-production testing or start of work. Torque indicators, which are an integral part of the installation equipment, shall be calibrated on site. Torque indicators, which are mounted in line with the installation tooling, shall be calibrated either on site or at an appropriately equipped test facility. Torque indicators that measure torque as a function of hydraulic pressure shall be calibrated at normal operating temperatures. d. Be recalibrated, if in the opinion of the Owner, their representative, and/or the contractor, reasonable doubt exists as to the accuracy of the torque measurements. 4.4 Installation procedures The helical pile lead section shall be positioned at the location as shown on the working drawings. Battered helical piles can be positioned perpendicular to the ground to assist in initial advancement into the soil before the required batter angle is established. Engage and advance the helical pile lead and extension sections in a smooth, continuous manner with the rate of pile rotation in the range of 5 to 20 RPM s. Extension sections shall be used to obtain the required minimum overall length and installation torque as shown on the working drawings. The coupling bolt(s) and nut(s) used to connection sections shall be torqued to 40 ft-lbs Apply sufficient down pressure to uniformly advance the helical sections at a rate per revolution approximately equal to the pitch of the helices. The pitch of the helices is approximately 3 inches for standard RCS and pipe helical piles. The rate of rotation and magnitude of down pressure must be adjusted for different soil conditions and depths in order to maintain the penetration rate. 4.5 Termination Criteria The torque as measured during the installation shall not exceed the torque rating (torsional strength) of the steel helical lead and extension shaft sections The minimum installation torque and minimum overall length criteria as shown on the working drawings shall be satisfied prior to terminating the installation of the helical pile The top most helix shall be located not less than 5 times its diameter below the bottom of the foundation for deep foundation behavior 7 of 9

8 considerations. However, other site specific conditions, such as, frost, fill, soft compressible soils, expansive soils, etc. may warrant a greater minimum depth If the torsional strength rating of the helical pile and/or installing equipment has been reached prior to satisfying the minimum length required, the installation contractor shall have the following options: Terminate the installation at the length obtained with the approval by and acceptance of the Owner or their representative, or Remove the existing helical pile and install a new pile with fewer and/or smaller diameter helical plates. This new pile configuration shall be subject to review by and acceptance of the Owner or their representative. If the new pile is installed at the same location as the original pile, then the top most helix of the new helical pile shall be terminated at least three times the diameter of top most helix of the new pile beyond the termination depth of the original pile If the minimum installation torque as shown on the working drawings is not achieved at the minimum overall length and there is no maximum overall length constraint, the installation contractor shall have the following options: Install the helical pile deeper using additional extension sections, or Remove the existing helical pile and install a new pile with additional and/or larger diameter helical plates. This new pile configuration shall be subject to review by and acceptance of the Owner or their representative. If the new pile is installed at the same location as the original pile, then the top most helix of the new helical pile shall be terminated at least three times the diameter of top most helix of the new pile beyond the termination depth of the original pile, or Derate the load capacity of the helical pile and install additional helical pile(s). The derated capacity and additional helical pile location(s) shall be subject to the review by and acceptance of the Owner or their representative If the helical pile reaches refusal or is deflected by a subsurface obstruction, the installation shall be terminated and the helical pile removed. The obstruction shall be removed, if feasible, and the helical pile shall be reinstalled. If the obstruction cannot be removed, the helical 8 of 9

9 pile shall be installed at an adjacent location subject to review by and acceptance of the Owner or their representative If the torsional strength rating of the helical pile shaft and/or installation equipment has been reached prior to the proper positioning of the elevation of the top of the helical pile, the contractor may remove the last extension and replace it with a shorter length extension. If it is not feasible to remove the last extension, the contractor may cut said extension to the proper elevation. The contractor shall not reverse (back-out) the helical pile to facilitate extension removal The average torque for the last 3 feet of penetration shall be used as a basis of comparison with the minimum recommended installation torque as shown on the working drawings. The average torque is the average of the last 3 torque readings recorded at one-foot intervals. This average torque is intended solely as an indication of the helical pile s ultimate bearing capacity The contractor shall maintain a written installation record for each helical pile. This record shall include information as noted in Section 2.2 Installation Records. End of Specification 9 of 9

FOUNDATION & LOAD BEARING ELEMENTS 02450

FOUNDATION & LOAD BEARING ELEMENTS 02450 210 N. Allen St. Centralia, MO 65240 Phone: (573) 682-8414 Fax: (573) 682-8660 E-mail: hpscontact@hps.hubbell.com www.abchance.com This MANU-SPEC utilizes the Construction Specifications Institute (CSI)

More information

LEGACY REPORT ER-5110. www.icc-es.org. ICC Evaluation Service, Inc. Reissued November 1, 2003. Legacy report on the 1997 Uniform Building Code

LEGACY REPORT ER-5110. www.icc-es.org. ICC Evaluation Service, Inc. Reissued November 1, 2003. Legacy report on the 1997 Uniform Building Code LEGACY REPORT Reissued November 1, 2003 ICC Evaluation Service, Inc. www.icc-es.org Business/Regional Office # 5360 Workman Mill Road, Whittier, California 90601 # (562) 699-0543 Regional Office # 900

More information

PTS HELICAL PIERS INSTALLATION SPECIFICATIONS NOTICE

PTS HELICAL PIERS INSTALLATION SPECIFICATIONS NOTICE FORM A PTS HELICAL PIERS INSTALLATION SPECIFICATIONS NOTICE The following suggested specifications are written as a guide to assist the specifier in writing his own specifications. Specific circumstances

More information

SECTION 1 GENERAL REQUIREMENTS

SECTION 1 GENERAL REQUIREMENTS Page 1 of 6 SECTION 1 GENERAL REQUIREMENTS 1. SCOPE OF WORK: The work to be performed under the provisions of these documents and the contract based thereon includes furnishing all labor, equipment, materials,

More information

System. Stability. Security. Integrity. 150 Helical Anchor

System. Stability. Security. Integrity. 150 Helical Anchor Model 150 HELICAL ANCHOR System PN #MBHAT Stability. Security. Integrity. 150 Helical Anchor System About Foundation Supportworks is a network of the most experienced and knowledgeable foundation repair

More information

Stability. Security. Integrity.

Stability. Security. Integrity. Stability. Security. Integrity. PN #MBHPT Foundation Supportworks provides quality helical pile systems for both new construction and retrofit applications. 288 Helical Pile System About Foundation Supportworks

More information

GUIDE TO MODEL SPECIFICATION CHANCE Civil Construction

GUIDE TO MODEL SPECIFICATION CHANCE Civil Construction GUIDE TO MODEL SPECIFICATION CHANCE Civil Construction HELICAL PILES F STRUCTURAL SUPPT TYPES OF SPECIFICATIONS The three types of specifications that are used for Helical Pile projects are: Open Specifications:

More information

SECTION 02824 EXPANDED METAL MESH FENCE

SECTION 02824 EXPANDED METAL MESH FENCE SECTION 02824 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes specifications for expanded metal mesh fence on the right-of-way. 1.02 REFERENCE STANDARDS A. ASTM International (ASTM): 1.03 SUBMITTALS

More information

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS July 14, 2015 1.0 GENERAL BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS This work shall consist of furnishing all materials, equipment, labor, and incidentals necessary for conducting bi-directional

More information

DIVISION: 31 00 00 EARTHWORK SECTION: 31 63 00 BORED PILES REPORT HOLDER: HUBBELL POWER SYSTEMS, INC.

DIVISION: 31 00 00 EARTHWORK SECTION: 31 63 00 BORED PILES REPORT HOLDER: HUBBELL POWER SYSTEMS, INC. 0 ICC ES Report ICC ES (800) 4 6587 (56) 699 054 www.icc es.org 000 Most Widely Accepted and Trusted ESR 794 Reissued 05/05 This report is subject to renewal 05/06. DIVISION: 00 00 EARTHWORK SECTION: 6

More information

The Stabilizer TM. Benefits. www.griptite.com. Supplemental support system for sagging beams and floor joists within a crawl space

The Stabilizer TM. Benefits. www.griptite.com. Supplemental support system for sagging beams and floor joists within a crawl space The Stabilizer TM Supplemental support system for sagging beams and floor joists within a crawl space Pre-drilled holes in steel plate allow for connection to beam or floor joists. Benefits Levels and

More information

High Strain Dynamic Load Testing of Drilled Shafts

High Strain Dynamic Load Testing of Drilled Shafts Supplemental Technical Specification for High Strain Dynamic Load Testing of Drilled Shafts SCDOT Designation: SC-M-712 (9/15) September 3, 2015 1.0 GENERAL This work shall consist of performing high-strain

More information

High Capacity Helical Piles Limited Access Projects

High Capacity Helical Piles Limited Access Projects High Capacity Helical Piles Limited Access Projects Tel 403 228-1767 Canada, USA, Russia Brendan ODonoghue 519 830-6113 Presentation Summary 1. Helical piles Background on large diameter shafts and helices

More information

SECTION 32 31 13 CHAIN LINK FENCES AND GATES

SECTION 32 31 13 CHAIN LINK FENCES AND GATES SECTION 32 31 13 CHAIN LINK FENCES AND GATES PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Fence framework, fabric, and accessories. 2. Excavation for post bases. 3. Concrete foundation for posts

More information

MATERIAL SPECIFICATIONS

MATERIAL SPECIFICATIONS FENCING - 1 2-11-1 CHAIN LINK FENCE AND GATE(S) A. SCOPE MATERIAL SPECIFICATIONS This section covers the work necessary for the chain link fence gate(s), complete. General Like items of materials provided

More information

These specifications shall apply to all high strength bolts and anchor bolts.

These specifications shall apply to all high strength bolts and anchor bolts. BOLTS (New Section) 972 972.1 REQUIREMENTS These specifications shall apply to all high strength bolts and anchor bolts. 972.2 SPECIFIC REQUIREMENTS A. General: All bolts, nuts, and washers shall have

More information

1. Galvanized fence framework, fabric, and accessories. 2. Excavation for post bases, and concrete for post footings.

1. Galvanized fence framework, fabric, and accessories. 2. Excavation for post bases, and concrete for post footings. SECTION 32 31 13 CHAIN LINK FENCES PART 1 GENERAL 1.1 SUMMARY A. This Section includes: 1. Galvanized fence framework, fabric, and accessories. 2. Excavation for post bases, and concrete for post footings.

More information

Step 11 Static Load Testing

Step 11 Static Load Testing Step 11 Static Load Testing Test loading is the most definitive method of determining load capacity of a pile. Testing a pile to failure provides valuable information to the design engineer and is recommended

More information

New construction Repairing failed or old foundations Retrofit foundations Permanent battered piers Machinery/equipment foundations

New construction Repairing failed or old foundations Retrofit foundations Permanent battered piers Machinery/equipment foundations from New construction foundations don t have to be a headache. The CHANCE Helical Pier Foundation System gives you the performance of concrete without the drawbacks and liabilities of driven piles and

More information

Sports and High Mast Lighting Poles Phone: (866) 474-7200 Fax: (817) 924-7049

Sports and High Mast Lighting Poles Phone: (866) 474-7200 Fax: (817) 924-7049 Sports and High Mast Lighting Poles 4 High Mast Lighting Poles General American LitePole offers a raising and lowering system that allows for ease of maintaining the lighting system at ground level. Ideal

More information

Evaluation Report CCMC 13102-R Pieux Vissés Vistech / Postech Screw Piles

Evaluation Report CCMC 13102-R Pieux Vissés Vistech / Postech Screw Piles Evaluation Report CCMC 13102-R Pieux Vissés Vistech / Postech Screw Piles 1. Opinion 1of 6 MASTERFORMAT: 31 62 16.01 Evaluation issued: 2003-02-13 Re-evaluated: 2015-03-13 Re-evaluation due: 2018-02-13

More information

SECTION 08332 COILING COUNTER DOORS. Display hidden notes to specifier. (Don't know how? Click Here)

SECTION 08332 COILING COUNTER DOORS. Display hidden notes to specifier. (Don't know how? Click Here) SECTION 08332 COILING COUNTER DOORS Display hidden notes to specifier. (Don't know how? Click Here) PART 1 GENERAL 1.1 SECTION INCLUDES A. Coiling Metal Counter Doors. B. Coiling Counter Fire Doors. 1.2

More information

Hilti, Inc. 5400 South 122 nd East Avenue Tulsa, OK 74146. 1-800-879-8000 www.hilti.com

Hilti, Inc. 5400 South 122 nd East Avenue Tulsa, OK 74146. 1-800-879-8000 www.hilti.com Attached are page(s) from the 2014 Hilti North American Product Tech Guide. For complete details on this product, including data development, product specifications, general suitability, installation,

More information

ATLAS RESISTANCE Pier Foundation Systems

ATLAS RESISTANCE Pier Foundation Systems ATLAS RESISTANCE Pier Foundation Systems Foundation Repair Systems for Civil Construction Applications: Residential, Commercial, Industrial Atlas Resistance Piers have been used to restore and/or stabilize

More information

Comprehensive Design Example 2: Foundations for Bulk Storage Facility

Comprehensive Design Example 2: Foundations for Bulk Storage Facility Comprehensive Design Example 2: Foundations for Bulk Storage Facility Problem The project consists of building several dry product storage silos near an existing rail siding in an open field presently

More information

FORMAL TECHNICAL OPINION

FORMAL TECHNICAL OPINION Jon S. Corzine Governor Issued: March 1985 Revised: June 2001 Code Ref. Update: January 2011 State of New Jersey Department of Community Affairs Division of Codes and Standards PO Box 802 Trenton, New

More information

1. Division 2 Section "Earthwork" for filling and for grading work. 2. Division 3 Section "Cast-in-Place Concrete" for concrete

1. Division 2 Section Earthwork for filling and for grading work. 2. Division 3 Section Cast-in-Place Concrete for concrete SECTION 02821 - FENCES AND GATES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections,

More information

Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. The Leading Edge.

Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. The Leading Edge. TM TM Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. SM The Leading Edge. 10 One Major Causes of foundation settlement or more conditions may

More information

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS Page 1 of 9 SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS 1. GENERAL REQUIREMENTS 1. Description of Work: This work consists of furnishing all materials, equipment and

More information

SECTION 8 AMERICAN. Flanged Pipe

SECTION 8 AMERICAN. Flanged Pipe SECTION 8 AMERICAN Flanged Pipe The principal standards covering Flanged Pipe are ANSI/AWWA C115/A21.15 and ANSI/AWWA C110/A21.10. These and other standards are referenced throughout this Section either

More information

ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT

ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT Description: This work shall consist of furnishing all materials, equipment and labor necessary for conducting an Osterberg Cell (O-Cell) Load

More information

Preformed Metal Roofing and Siding

Preformed Metal Roofing and Siding Page -1-1. GENERAL 1.1. Description This specification along with the drawings covers the furnishing of all material, products, equipment, accessories, tools, services, transportation, labor and supervision

More information

METHOD OF STATEMENT FOR STATIC LOADING TEST

METHOD OF STATEMENT FOR STATIC LOADING TEST Compression Test, METHOD OF STATEMENT FOR STATIC LOADING TEST Tension Test and Lateral Test According to the American Standards ASTM D1143 07, ASTM D3689 07, ASTM D3966 07 and Euro Codes EC7 Table of Contents

More information

Mechanical Installation

Mechanical Installation Page -1-1. INTRODUCTION AND PURPOSE 1.1. This specification covers the installation, testing and precommissioning of mechanical equipment. Work is to be performed in conjunction with the manufacturer s

More information

DESCRIPTION. Stud Bolts for Pressure-Temperature Piping 2-1. General Purpose End-to-End Studs 2-2. Tap End Stud Bolts 2-3. Double End Stud Bolts 2-4

DESCRIPTION. Stud Bolts for Pressure-Temperature Piping 2-1. General Purpose End-to-End Studs 2-2. Tap End Stud Bolts 2-3. Double End Stud Bolts 2-4 DESCRIPTION PAGE B7 Studs and Nuts Stud Bolts for Pressure-Temperature Piping 2-1 General Purpose End-to-End Studs 2-2 Tap End Stud Bolts 2-3 Double End Stud Bolts 2-4 Sigma Fasteners, Inc. Section 2 STUD

More information

SECTION 26 05 49 VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS

SECTION 26 05 49 VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS SECTION 26 05 49 VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS PART 1 - GENERAL 1.1 SUMMARY A. This Section includes seismic restraints and other earthquake-damage-reduction measures for electrical

More information

Helical Piles. A Practical Guide to Design and Installation

Helical Piles. A Practical Guide to Design and Installation Brochure More information from http://www.researchandmarkets.com/reports/2216946/ Helical Piles. A Practical Guide to Design and Installation Description: An unbiased, comprehensive review of helical pile

More information

CITY OF LOS ANGELES CALIFORNIA

CITY OF LOS ANGELES CALIFORNIA BOARD OF BUILDING AND SAFETY COMMISSIONERS VAN AMBATIELOS PRESIDENT E. FELICIA BRANNON VICE PRESIDENT JOSELYN GEAGA-ROSENTHAL GEORGE HOVAGUIMIAN JAVIER NUNEZ CITY OF LOS ANGELES CALIFORNIA ERIC GARCETTI

More information

Foundation Installation

Foundation Installation Appendix B Foundation Installation Guidelines SOUTHWEST WINDPOWER, INC. - 1801 WEST ROUTE 66 - FLAGSTAFF, ARIZONA 86001 - PH: 928.779.9463 - FAX: 928.779.1485 www.skystreamenergy.com October 2006 Southwest

More information

SFI SPECIFICATION 61.1 EFFECTIVE: FEBRUARY 26, 2014

SFI SPECIFICATION 61.1 EFFECTIVE: FEBRUARY 26, 2014 SFI SPECIFICATION 61.1 EFFECTIVE: FEBRUARY 26, 2014 PRODUCT: Turbochargers 1.0 GENERAL INFORMATION 1.1 This SFI Specification establishes uniform test procedures and minimum standards for evaluating and

More information

SECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE

SECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE SECTION 15076 CEMENT-MORTAR LINED AND COATED (CML&C) STEEL PIPE PART 1 GENERAL 1.01 DESCRIPTION This section designates the requirements for steel pipe fabrication, test in shop, installation of steel

More information

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Jeff R. Hill, P.E. Hayward Baker Inc. 111 W. Port Plaza Drive Suite 600 St. Louis, MO 63146 314-542-3040 JRHill@HaywardBaker.com

More information

Section Fiberglass Reinforced Plastic Grating and Structural Fabrications

Section Fiberglass Reinforced Plastic Grating and Structural Fabrications Section 06600 Fiberglass Reinforced Plastic Grating and Structural Fabrications Part 1. General 1.01 Related documents: A. Contract drawings, including general drawings and addenda drawings. B. General

More information

INFORMATION BULLETIN NO.

INFORMATION BULLETIN NO. One- and Two-Family Standard Garage Slab and Foundation Wall Details for use with the 2012 International Residential Code (IRC) INFORMATION BULLETIN NO. 114-2012 October 1, 2012 City Planning & Development

More information

SECTION 15062 POLYVINYL CHLORIDE GRAVITY SEWER PIPE AND FITTINGS

SECTION 15062 POLYVINYL CHLORIDE GRAVITY SEWER PIPE AND FITTINGS SECTION 15062 POLYVINYL CHLORIDE (PVC) GRAVITY SEWER PIPE AND FITTINGS PART 1 GENERAL 1.01 DESCRIPTION This section designates the requirements for the manufacture and installation of polyvinyl chloride,

More information

How to Design Helical Piles per the 2009 International Building Code

How to Design Helical Piles per the 2009 International Building Code ABSTRACT How to Design Helical Piles per the 2009 International Building Code by Darin Willis, P.E. 1 Helical piles and anchors have been used in construction applications for more than 150 years. The

More information

LiftAlloy Chain Slings

LiftAlloy Chain Slings CHAIN SLING BASICS Slings Lift-All chain slings meet or exceed all OSHA, ASME B30.9 and NACM standards and regulations. chain slings, available in 80 for 7/32" and 7/8"- /4" and 00 for 9/32"-3/4", are

More information

Description of Bolt Torque Tables

Description of Bolt Torque Tables Description of Bolt Torque Tables (in) (in) (in) (sq.in.) Bolts (in) (ft.lbs.) (psi) (psi) (psig) (psi) (ft.lbs.) (psi) (ft.lbs.) 0.5 0.84 1.38 0.94 4 0.5 60 7560 32134

More information

STANDARD FOR NON-FIRE RATED ROLLING DOORS

STANDARD FOR NON-FIRE RATED ROLLING DOORS ANSI/DASMA 203-2004 AMERICAN NATIONAL STANDARD STANDARD FOR NON-FIRE RATED ROLLING DOORS Door & Access Systems Manufacturers Association, International Sponsor: 1300 Sumner Ave Cleveland, Ohio 44115-2851

More information

Suggested Specification for Hot-Dip Galvanizing Revised May 2002

Suggested Specification for Hot-Dip Galvanizing Revised May 2002 Suggested Specification for Hot-Dip Galvanizing Revised May 2002 This suggested specification is provided as a guide to producing a quality document calling for after-fabrication hot-dip galvanizing of

More information

Designed and Engineered to Perform

Designed and Engineered to Perform History EARTH CONTACT PRODUCTS, L.L.C., is a family owned company, based in Olathe, Kansas. This company was built upon Don May s U.S. Patented fourth-generation Steel Piering System that has led to the

More information

Section Fiberglass Reinforced Plastic Grating and Structural Fabrications

Section Fiberglass Reinforced Plastic Grating and Structural Fabrications Section 06600 Fiberglass Reinforced Plastic Grating and Structural Fabrications Part 1. General 1.01 Related documents: A. Contract drawings, including general drawings and addenda drawings. B. General

More information

GLOSSARY OF TERMINOLOGY

GLOSSARY OF TERMINOLOGY GLOSSARY OF TERMINOLOGY AUTHORIZED PILE LENGTHS - (a.k.a. Authorized Pile Lengths letter) Official letter stating Engineer's recommended length of concrete piles to be cast for construction of foundation.

More information

1. Division-5 Section Metal Fabrications for material and welding requirements related to wrought iron fencing.

1. Division-5 Section Metal Fabrications for material and welding requirements related to wrought iron fencing. SECTION 02835 SITE FENCES AND GATES PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division 1 Specification Sections,

More information

1.02 SYSTEM DESCRIPTION

1.02 SYSTEM DESCRIPTION 1 OF 7 MODULAR MEZZANINES GUIDE SPECIFICATIONS FOR PART 1 - GENERAL 1.01 RELATED WORK A. SECTION 03 30 00: Cast in Place Concrete (and Concrete Finishing) 1. The area where mezzanine is installed shall

More information

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL. STRUCTURES 1. General. Critical structures may impact the integrity of a flood control project in several manners such as the excavation for construction of the structure, the type of foundation, backfill

More information

SECTION 710 GUARDRAIL MATERIALS

SECTION 710 GUARDRAIL MATERIALS 710.08 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 SECTION 710 GUARDRAIL MATERIALS 710.01 General. Metal beam

More information

SECTION 260536 - CABLE TRAYS. A. Continuous, rigid, welded steel or stainless steel wire mesh cable management system.

SECTION 260536 - CABLE TRAYS. A. Continuous, rigid, welded steel or stainless steel wire mesh cable management system. SECTION 260536 - CABLE TRAYS PART 1 - GENERAL SECTION INCLUDES: A. Continuous, rigid, welded steel or stainless steel wire mesh cable management system. B. Cable tray systems are defined to include, but

More information

Transmission Foundations. helical piles and guy anchors for transmission structures. www.hubbellpowersystems.com

Transmission Foundations. helical piles and guy anchors for transmission structures. www.hubbellpowersystems.com Transmission Foundations helical piles and guy anchors for transmission structures www.hubbellpowersystems.com Grid locked on your transmission job? Instant Foundation helical piles go places concrete

More information

Technical Note PP 811-TN PE Flange Connections

Technical Note PP 811-TN PE Flange Connections Technical Note PP 811-TN PE Flange Connections Flange Connection Flanged joints are made using a DriscoPlex Flange Adapter that is fused to the pipe then joined to a mating flange adapter or a mating appurtenance

More information

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION PART 8000 - PRECAST CONCRETE TABLE OF CONTENTS Item Number Page 8100 PRECAST CONCRETE CONSTRUCTION - GENERAL 8-3 8101 General

More information

SECTION 32 31 00 EXPANDED METAL FENCING Meets Buy American Procurement

SECTION 32 31 00 EXPANDED METAL FENCING Meets Buy American Procurement PART 1 GENERAL SECTION 32 31 00 EXPANDED METAL FENCING Meets Buy American Procurement 1.1 SUMMARY A. Section Includes 1. Supply and install all materials and accoutrements required for the installation

More information

Specifications for Lightning Protection. ASAE Engineering Practice

Specifications for Lightning Protection. ASAE Engineering Practice Chapter 8: Lightning Specifications for Lightning Protection ASAE safety standards are not laws. They are recommended voluntary standards used by designers, engineers, manufacturers and users of the equipment,

More information

HIGH TENSION CABLE BARRIER

HIGH TENSION CABLE BARRIER Special Provision September 11, 2006 SECTION 02845 S HIGH TENSION CABLE BARRIER PART 1 GENERAL 1.1 SECTION INCLUDES A. Cable barrier materials and installation procedures. 1.2 RELATED SECTIONS A. Section

More information

Wastewater Capital Projects Management Standard Construction Specification

Wastewater Capital Projects Management Standard Construction Specification CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 10.1 Precast Concrete Pipe 10.1.1 General This section covers material requirements,

More information

Coupling Alignment Fundamentals

Coupling Alignment Fundamentals Page (1 of 14) CONTENTS I. Why Align Rotating Equipment? II. Defining Shaft Misalignment III. Alignment Methods Poor, Fair, Good and Best IV. Pre-Alignment Considerations V. Alignment Methods A. Rim and

More information

Structural Bolting. Notice the Grade 5 has a much smaller head configuration and a shorter shank then the A325 structural bolt. Rev.

Structural Bolting. Notice the Grade 5 has a much smaller head configuration and a shorter shank then the A325 structural bolt. Rev. Structural Bolting ASTM A325 and ASTM A490 are the two U.S. standard structural bolts. When looking at the mechanical requirements of bolts it appears that an ASTM A325 and SAE J429 Grade 5 are identical

More information

CONTRACT SPECIFICATIONS - SEISMIC ISOLATION BEARINGS

CONTRACT SPECIFICATIONS - SEISMIC ISOLATION BEARINGS CONTRACT SPECIFICATIONS - SEISMIC ISOLATION BEARINGS 1.0 DESIGN 1.1 Scope of Work 1.1.1 This work shall consist of furnishing Isolation Bearings and installing Isolation Bearing Assemblies at the locations

More information

The Manitoba Water Services Board SECTION 027110 Standard Construction Specifications September 2013 Page 1 of 12

The Manitoba Water Services Board SECTION 027110 Standard Construction Specifications September 2013 Page 1 of 12 September 2013 Page 1 of 12 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work shall consist of the supply and construction of a chain link fence, barb wire fences or mesh fences as shown on the Plans or

More information

A Solid Foundation Solution for Homeowners. from. Our products are made with 90% Recycled Material Down. Right. Solid. GREEN.

A Solid Foundation Solution for Homeowners. from. Our products are made with 90% Recycled Material Down. Right. Solid. GREEN. A Solid Foundation Solution for Homeowners from Our products are made with 90% Recycled Material Down. Right. Solid. GREEN. Stop the damaging effects of foundation settling... Sinking foundations, cracked

More information

SECTION 03400 PRECAST CONCRETE STRUCTURES

SECTION 03400 PRECAST CONCRETE STRUCTURES SECTION 03400 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes specifications for precast concrete structures, including fabrication and erection. 1.02 REFERENCE STANDARDS A. American Society for

More information

2013 Edition. Flanged fittings 30"-64" NSF. industrial Applications, water & Wastewater. Certified to ANSI/NSF 61

2013 Edition. Flanged fittings 30-64 NSF. industrial Applications, water & Wastewater. Certified to ANSI/NSF 61 30"-64" Ductile Iron industrial Applications, water & Wastewater 2 Table of Contents Flanged Fittings for Water 3 Flange Details 5 Flanged Fittings 6 90º and 45º Bend 6 22-1/2º and 11-1/4º Bends 7 Tees

More information

60.12. Depend-O-Lok FxE Expansion Coupling. System No. Submitted By Spec Sect Para Location Date Approved Date. DEPEND-O-LOK FxE EXPANSION COUPLING

60.12. Depend-O-Lok FxE Expansion Coupling. System No. Submitted By Spec Sect Para Location Date Approved Date. DEPEND-O-LOK FxE EXPANSION COUPLING 60.1 D-O-L FxE expansion couplings are a bolted, split-sleeve design that provides for expansion and contraction at the coupled joint. These couplings are furnished with restraint rings that, when affixed

More information

SECTION 02401 SHEETING, SHORING AND BRACING

SECTION 02401 SHEETING, SHORING AND BRACING SECTION 02401 SHEETING, SHORING AND BRACING This section should be edited to reflect soil conditions specific to the project site and the recommendations of a Geotechnical Engineer licensed in the State

More information

specifications A*COM SYSTEM bridging the gap. A*COM Commercial Ramp System PART 1 General

specifications A*COM SYSTEM bridging the gap.  A*COM Commercial Ramp System PART 1 General specifications A*COM Commercial Ramp System This section is based on products manufactured by A*COM and distributed by AlumiRamp, Inc., located at the following address: 855 Chicago Road, Quincy, MI 49082,

More information

SECTION ANCHOR BOLTS. A. Provide bolts and nuts that meet the standards given in Table 1.

SECTION ANCHOR BOLTS. A. Provide bolts and nuts that meet the standards given in Table 1. SECTION 16449 PART 1 DESCRIPTION A. Fabricate and install anchor bolts to be embedded in or attached to concrete. PART 2 MATERIALS 2.01 BOLTS AND NUTS A. Provide bolts and nuts that meet the standards

More information

Progressive, modern, innovative that s what Brunswick Steel is all about.

Progressive, modern, innovative that s what Brunswick Steel is all about. REFERENCE CATALOGUE Progressive, modern, innovative that s what Brunswick Steel is all about. Established in 1970 as a family owned business, Brunswick Steel initially began as a demolition and salvage

More information

GAS DISTRIBUTION PRODUCTS STEEL SERVICE TEES

GAS DISTRIBUTION PRODUCTS STEEL SERVICE TEES GAS DISTRIBUTION PRODUCTS STEEL SERVICE TEES CONTINENTAL INDUSTRIES ABOUT US THE ULTIMATE CONNECTION Our Company Continental Industries, headquartered in Tulsa, Oklahoma, was formed in 1958 and is today

More information

2014 Edition 3"-64" NSF. industrial Applications, water & Wastewater. Certified to ANSI/NSF 61

2014 Edition 3-64 NSF. industrial Applications, water & Wastewater. Certified to ANSI/NSF 61 3"-64" Ductile Iron industrial Applications, water & Wastewater 866.DI.IE 2 Table of Contents Flanged ipe for Water and Other Liquids 3 Ductile Iron Flanged ipe With Threaded Flanges-Flanged Details 5

More information

HOUSTON COMMUNITY COLLEGE HCC ALIEF CAMPUS MAIN BUILDING, FIRST, SECOND & FOURTH FLOORS RENOVATION ISSUE DATE: 10.17.12

HOUSTON COMMUNITY COLLEGE HCC ALIEF CAMPUS MAIN BUILDING, FIRST, SECOND & FOURTH FLOORS RENOVATION ISSUE DATE: 10.17.12 SECTION 27 05 26 - GROUNDING AND BONDING FOR COMMUNICATIONS SYSTEMS PART 1 - GENERAL 1.1 SUMMARY A. This Section includes grounding and bonding products, design requirements and installation for communications

More information

SECTION 15410 GROUND WATER STORAGE TANKS

SECTION 15410 GROUND WATER STORAGE TANKS SECTION 15410 GROUND WATER STORAGE TANKS PART 1 GENERAL.01 SCOPE A. Section Includes Requirements for designing, fabricating, and erecting a welded steel ground storage tank..02 SYSTEM DESCRIPTION A. Design

More information

Page B-1 Hubbell Power Systems, Inc. All Rights Reserved Copyright 2014 LOAD TESTS

Page B-1 Hubbell Power Systems, Inc. All Rights Reserved Copyright 2014 LOAD TESTS Page B-1 Hubbell Power Systems, Inc. All Rights Reserved Copyright 2014 Appendix B CONTENTS STATIC (TIEBACKS)... B-3 STATIC AXIAL (COMPRESSION/TENSION)... B-6 STATIC (LATERAL)... B-9 CAPACITY VERIFICATION

More information

SECTION 02832 CHAIN LINK FENCE AND GATES

SECTION 02832 CHAIN LINK FENCE AND GATES SECTION 02832 CHAIN LINK FENCE AND GATES PART 1 GENERAL 1.01 SECTION INCLUDES A. Fabrication, furnishing and installation of chain link fence, chain link gates, and extension brackets with barbed wire.

More information

PRODUCT DRAWINGS AND RATINGS Section 7

PRODUCT DRAWINGS AND RATINGS Section 7 PRODUCT DRAWINGS AND RATINGS Section 7 CONTENTS ATLAS RESISTANCE PIERS 7-1 PIER PIPE SHAFTS 7-1 REMEDIAL REPAIR BRACKETS for ATLAS RESISTANCE PIERS 7-2 ACCESSORIES for ATLAS RESISTANCE PIERS 7-6 CHANCE

More information

SECTION 31 20 00 EARTH MOVING

SECTION 31 20 00 EARTH MOVING SECTION 31 20 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for excavating, filling, and grading for earthwork at Parking Structure, new exit stair and as required to

More information

B.TECH. (AEROSPACE ENGINEERING) PROGRAMME (BTAE) Term-End Examination December, 2011 BAS-010 : MACHINE DESIGN

B.TECH. (AEROSPACE ENGINEERING) PROGRAMME (BTAE) Term-End Examination December, 2011 BAS-010 : MACHINE DESIGN No. of Printed Pages : 7 BAS-01.0 B.TECH. (AEROSPACE ENGINEERING) PROGRAMME (BTAE) CV CA CV C:) O Term-End Examination December, 2011 BAS-010 : MACHINE DESIGN Time : 3 hours Maximum Marks : 70 Note : (1)

More information

Reproduced with the permission of the American Welding Society (AWS), Miami, Florida - 09/15/2011. 7. Stud Welding

Reproduced with the permission of the American Welding Society (AWS), Miami, Florida - 09/15/2011. 7. Stud Welding 7. Stud Welding 7.1 Scope Section 7 contains general requirements for welding steel studs to steel (see 7.2.7 and 1.2.2 for approved steels). In addition, it stipulates specific requirements for the following:

More information

SECTION 27 05 36 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS

SECTION 27 05 36 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS SECTION 27 05 36 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS PART 1 GENERAL 1.01 DESCRIPTION A. The work covered by this section of the Specifications includes all labor necessary to perform and complete such

More information

NFPA 13 Standard for the Installation of Sprinkler Systems

NFPA 13 Standard for the Installation of Sprinkler Systems Tentative Interim Amendment NFPA 13 Standard for the Installation of Sprinkler Systems 2013 Edition Reference: Chapter 6 TIA 13-2 (SC 12-8-24/TIA Log #1054) Note: Text of the TIA issued and incorporated

More information

James M. Pleasants Company

James M. Pleasants Company James M. Pleasants Company SUBMITTAL DATA GAINESVILLE MECHANICAL DECEMBER 20, 2013 PROJECT: GSU: J-183 HUMANITIES LAW BLDG. QUOTE NO:12116 ENGINEER: STEVENS & WILKINSON GASKETED PLATE HEAT EXCHANGER Tag:

More information

STANDARD SPECIFICATIONS SECTION 05500 METAL FABRICATIONS

STANDARD SPECIFICATIONS SECTION 05500 METAL FABRICATIONS STANDARD SPECIFICATIONS SECTION 05500 METAL FABRICATIONS PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for providing metal fabricated items like castings, gratings, hatchways, ladders,

More information

Sign Posts and Supports

Sign Posts and Supports Sign Posts and Supports To address various signing needs and agency preferences, several types of supports are available. Small signs (less than 50 square feet) are commonly supported with either wood

More information

B. Trenching, Backfilling, and Compacting: STD SPEC 02223. A. Submit submittal packages in accordance with Standard Specification Section 01300

B. Trenching, Backfilling, and Compacting: STD SPEC 02223. A. Submit submittal packages in accordance with Standard Specification Section 01300 STANDARD SPECIFICATION SECTION 15065 PLASTIC (PVC) GRAVITY SEWER PIPE PART 1 - GENERAL 1.01 DESCRIPTION A. This section includes materials, installation, and testing of PVC gravity sewer pipe conforming

More information

ROOFING. Community Development Department Building Division 952-939-8394 eminnetonka.com

ROOFING. Community Development Department Building Division 952-939-8394 eminnetonka.com ROOFING Community Development Department Building Division 952-939-8394 eminnetonka.com This handout is intended only as a guide and is based in part on the 2007 Minnesota State Building Code and good

More information

ATTENTION ANYONE INSTALLING A MANUFACTURED HOME AFTER MAY 1, 2009

ATTENTION ANYONE INSTALLING A MANUFACTURED HOME AFTER MAY 1, 2009 Chester J. Culver Governor Patty Judge Lt. Governor Eugene T. Meyer Commissioner James Kenkel State Fire Marshal April 29, 2009 ATTENTION ANYONE INSTALLING A MANUFACTURED HOME AFTER MAY 1, 2009 The Iowa

More information

Helical Design Theory and Applications. By Darin Willis, P.E.

Helical Design Theory and Applications. By Darin Willis, P.E. Helical Design Theory and Applications By Darin Willis, P.E. Solution Systems Ram Jack utilizes two unique underpinning & anchoring systems Hydraulically driven piles (pressed) Helical piles (torqued)

More information

CHAIN-LINK FENCES BID SPECIFICATIONS DESCRIPTION

CHAIN-LINK FENCES BID SPECIFICATIONS DESCRIPTION CHAIN-LINK FENCES BID SPECIFICATIONS DESCRIPTION 1 This item shall consist of furnishing and erecting Chain-Link fence in accordance with these specifications and the details shown on the plans and in

More information

SECTION 02845 GUARDRAILS

SECTION 02845 GUARDRAILS SECTION 02845 GUARDRAILS PART 1 - GENERAL 1.01 SCOPE OF WORK A. Furnish all labor, materials, equipment and incidentals necessary and repair, replace or install all types of guardrails as specified herein

More information

DESIGN CLARIFICATION (DC)

DESIGN CLARIFICATION (DC) DESIGN CLARIFICATION (DC) Owner: Victor Valley Wastewater Reclamation Authority Date: 03/03/2015 Contractor: W M Lyles Carollo Project No.: 8299A.20 Project Name: Subregional WRPs DC No.: 001 DC Title:

More information

Prefabricated FRP Lift Station Sample Specifications Section 1 General

Prefabricated FRP Lift Station Sample Specifications Section 1 General Section 1 General 1. Description 1.1 Scope of Work: Contractor shall furnish all labor, materials, equipment and performance of all work necessary or incidental to furnish and install a simplex/duplex

More information