Small Scale Generation Grid Connection Information Pack. 1 st October 2015

Size: px
Start display at page:

Download "Small Scale Generation Grid Connection Information Pack. 1 st October 2015"

Transcription

1 Small Scale Generation Grid Connection Information Pack 1 st October 2015

2 Factors to consider for a Renewable Energy Project The success of a renewable energy project involves bringing many individual factors together as shown in the jigsaw puzzle above. The connection of your renewable energy scheme to the Northern Ireland Electricity Networks grid is only one factor to consider in your overall project. This information pack will take you through the key factors that need to be considered and the steps required when obtaining a grid connection. 22/02/20165 Small Scale Generation Grid Connection Information Pack 2

3 Connecting Small Scale Generation to the Electricity Network As renewable energy technologies including wind turbines, anaerobic digesters, hydro and PV become more mature and common; there is an increasing demand on Northern Ireland Electricity Networks (NIE Networks) to provide connections to the Northern Ireland network. Significant levels of small scale generation have already been committed on the distribution network, leading to network saturation and high costs for further connections in some areas. Prospective applicants may wish to refer to the NIE Networks website for further useful information on congested areas and general information on connection issues. For information on the quantities of connected generation visit: Where a developer wishes to connect and operate a generator in parallel with the NIE Networks network, the developer must apply to NIE Networks for connection. Once a connection application is successfully processed the developer will then enter into a connection agreement with NIE Networks. The following information sheets outline the process, application fees and, approximate timescales for obtaining a connection offer to connect a generating unit to the NIE Networks distribution system. Customers or their installers are required to register their project online via the NIE Networks web site, at to obtain a full application pack. Alternatively, NIE Networks can be contacted by post at the address below: Summary of the Contents in this information pack: 1. General Safety Information 2. Feasibility Study and Fees Central Processing and Registration Northern Ireland Electricity Networks 57 Dargan Road Belfast BT3 9JU Small Scale Generation Connection Process 4. Application Information and Fees 5. Connection Application Design 6. Pre-Construction and Construction Works 7. Timescales for Grid Connection 8. Renewable Obligation Certificates (ROCs) 9. Complaints Annex 1- Relevant Legislation 22/02/20165 Small Scale Generation Grid Connection Information Pack 3

4 1. General Safety Information NIE Networks would draw your attention to the considerable danger associated with working in the vicinity of electrical equipment, whether underground or overhead. The greatest care must be exercised not to come into contact or to bring materials, equipment, appliances or tools too close to electrical equipment, otherwise workers and indeed other persons not directly concerned may be subject to very grave risk, which may lead to a serious or even fatal accident. Site safety must be in accordance with HSE Guidance Note GS6 (Avoidance of Danger from Overhead Electric Lines) and HSE Booklet HS(G)47 (Avoiding Danger from Underground Services). Further information can be found on the NIE Networks safety website at or at Clearance to NIE Networks Distribution Network (Diagram 1) Diagram 1 22/02/20165 Small Scale Generation Grid Connection Information Pack 4

5 Clearance to NIE Networks Transmission Network (Diagram 2) Diagram 2 22/02/20165 Small Scale Generation Grid Connection Information Pack 5

6 2. Feasibility Study and Fees To facilitate customers wishing to connect and export energy generated to the electricity network, NIE Networks offers to carry out a feasibility study for projects that are at an initial investment appraisal stage. This study is optional and provides information to help a customer develop their own business plan. To complete a feasibility study for a particular project NIE Networks will require you to complete NIE Networks Generator Enquiry Form and forward it to NIE Networks with the appropriate non-refundable fee see below. A copy of the generator's electrical data sheet may also be attached if this is available. Generation Maximum installed Capacity Feasibility Study Fee 150kW or less 566 More than 150kW 1,132 All fees listed are exclusive of VAT which should be added at the current tax point rate of 20%. Cheques should be made payable to Northern Ireland Electricity Networks Ltd. NOTE: The cost to apply for a feasibility study is linked to the Statement of Charges that is currently approved and may be subject to change in line with future approved Statement of Charges. Only on receipt of both the fee and adequate technical information will NIE Networks progress a feasibility study. It may take NIE Networks up to three months to provide a feasibility study following receipt of all required information and appropriate payment. The feasibility study will consider the most appropriate connection arrangement at your specific location, at that point in time, and details of the work required to provide connection for the requested capacity and technology. The feasibility study will provide potential developers with: an indication that a connection is achievable an indicative cost for providing a suitable network connection and an outline of the work involved in constructing the connection including information on: connection voltage level connection point to the NIE Networks electricity network details of the connection arrangement This will help applicants to decide if they wish to proceed with their project as planned. Applicants should be aware that a feasibility study does not reserve network capacity for a particular project, and NIE Networks cannot guarantee that a connection will be available when an applicant makes a formal application for connection. The study is effectively a snapshot at a point in time. 3. Small Scale Generation Connection Process Diagram 3 provides an overview of the process for applying to NIE Networks for a small scale generation connection and outlines the basic steps to be worked through. The diagram highlights where connection offers may be impacted by capacity issues and extensions on the timeframe to make a connection offer may be sought by NIE Networks. It also explains the process which NIE Networks works through once an offer has been accepted by an applicant. More detail on this in Section (6) - Pre-Construction & Construction works. 22/02/20165 Small Scale Generation Grid Connection Information Pack 6

7 Small Scale Generation Process (Diagram 3) 22/02/20165 Small Scale Generation Grid Connection Information Pack 7

8 4. Application Information and Fees A grid connection application (leading to an offer) is available to all customers. There is no requirement to have a feasibility study carried out before making a connection application. When a connection application is received by NIE Networks, it is registered and given a unique job reference number. The applicant will be informed of this number in writing and should quote this number when inquiring about their application. This study is a full technical appraisal and requires the applicant to submit a formal application (referred to as the NIE Networks Generator Questionnaire) including the full technical specification of the generator being connected and the appropriate non-refundable fee. Relevant Connection Application Fees (CAF) can be found in the Statement of Charges at the following link: NOTE: The cost to apply for a grid connection application is linked to the Statement of Charges that is currently approved and may be subject to change to future approved Statement of Charges. Customer Category Connection Application Fee NIE Networks fee s: A B C Customer requiring a generation capacity of less than or equal to 20kW: e.g. 10kW application fee = Category A = 566 (+VAT) 566 Customer requiring a generation capacity of more than 20kW and less than or equal to 150kW: 1,697 e.g. 150kW application fee = Category B = 1,697 (+VAT) Customer requiring a generation capacity of more than 150kW and less than or equal to 2MW: 5,659 e.g. 250kW application fee = Category C = 5,659 (+VAT) All the fees listed above are exclusive of VAT which should be added at the current tax point rate of 20%. Application fees may be paid by cheque and BACS. Cheques should be made payable to Northern Ireland Electricity Networks Ltd. 22/02/20165 Small Scale Generation Grid Connection Information Pack 8

9 The application will be checked to ensure it contains: Completed Generator Questionnaire and all documentation referred to within the questionnaire Technical specifications of generators typically including: Flicker co-efficient Starting currents and type of starter for each generator installed Impedance data for each generator installed and connecting network to the point of connection Harmonic studies Single line diagram 1: 25000, 1:2500 and 1:500 scale site location plans Site layout plan, including proposed substation location Easting and Northing co-ordinates of each generator Easting and Northing co-ordinates of customer substation Generator Capacity along with Maximum Export Capacity (MEC) 1 Required The relevant Connection Application Fee If Maximum Import Capacity (MIC) 2 >200kVA then load details required If the application does not have all the required information, NIE Networks will write to the applicant and request this information. In relation to timeline to make the offer, the job will be put on hold until all this information is received. Planning permission is no longer a pre-requisite for an application, however if you do have planning permission for your development (or do not require planning permission), please send evidence of this and any relevant details. Following the receipt of all information and payment, the connection study may take up to three months to complete. Should you proceed with the proposal; the appropriate Network Connection & Capacity Study fee will be deducted from the final connection charge, provided the project is completed within three years from the initial date of application. The connection offer will outline the connection voltage, connection costs, terms and conditions for connection and details of the work required to provide the connection for the requested capacity and technology. 1 Maximum Export Capacity is the value you are requesting to be recorded against Your connection in NIE Networks system as the maximum capacity that can be generated/exported by your connection 2 Maximum Import Capacity means the value recorded against Your connection in NIE Networks system as the maximum capacity that can be used/imported by your connection 22/02/20165 Small Scale Generation Grid Connection Information Pack 9

10 5. Connection Application Design At the preliminary design stage, consideration will be given to whether there is capacity to connect the generator to the NIE Networks Distribution system. If there is not capacity to connect your generator at present, NIE Networks will write to you and offer the option of either cancelling your application and receiving a refund, or remaining in the process until an offer can be made at some future date. If you chose to remain in the process until an offer can be made then NIE Networks will seek an extension from the Utility Regulator on the time to make a connection offer. For more information on capacity issues in your area refer to the NIE Networks Heat Map: Heat-Map If there is capacity to connect your generator, a detailed design will be carried out to determine how the generator would be connected, including: Studies to determine technical feasibility Plant requirements including Switchgear Protection requirements Overhead Line route (and options) Underground cable route Environmental considerations/constraints Civil works Scada and Communications requirements Site visits will carried out to the determine site specific requirements The offer will then be issued to the applicant within 90 days. It will include Details of the connection design with diagrams The cost of the connection and connection offer validity period. Details of how to accept the offer and the necessary deposit required Estimated timeframe for completion- see Section (7) This offer is valid for 90 days from the date of issue and the applicant must forward their acceptance of terms and deposit to NIE Networks within this 90 day period. Once the offer has been accepted and the deposit paid, NIE Networks will proceed with the activities required to connect the generator to the Distribution System. More detail on this in Section (6) - Pre- Construction & Construction works. If the offer is not accepted within the stipulated 90 day period, then the application will become void and the applicant will need to re-apply if they wish to continue to pursue a connection. NOTE: The costs of your grid connection will be linked to the Statement of Charges that is approved at that point in time when the offer is made, and may be subject to change to future approved Statement of Charges if a final balance or re-quote is required. 22/02/20165 Small Scale Generation Grid Connection Information Pack 10

11 6. Pre-Construction & Construction Works The cost basis of the connection depends on the extent of the construction work required to connect the scheme along with any appropriate reinforcement necessary to maintain the electricity network within statutory voltage and reactive power limits. If your generator is located at the extremity of the 11,000 volt network, the cost is likely to be greater than a location closer to a primary substation. The level of generation already connected, or committed to connect, will also impact on any network rebuild required to maintain the distribution network within statutory limits. This makes it difficult to provide indicative costs that can be used as a guide by prospective applicants. For more information on likely connection costs in your area refer to the NIE Networks Heat Map: Heat-Map Please refer to the Statement of Charges for Connection to the Northern Ireland Distribution System for indications of costs for connection: Oct.aspx When you accept the Terms of Connection of Generation and make any necessary payment, NIE Networks will: Complete a full survey of the route Seek to obtain wayleaves from landowners Seek to obtain DOE Planning Permission for overhead line work. Obtain DETI Article 40 consent for the overhead line if required. Procure major items of plant Agree suitable earthing design for the site. Complete necessary legalities including substation lease, cable easements and right of way if required Final construction and energisation works Generation however cannot begin until both the owner of the generator and NIE Networks have signed the Generator Agreement (which will be supplied by NIE Networks). The Agreement must be signed by you, witnessed and returned to NIE Networks. Your installer is required to complete G59 3 testing and submit the test results and Schedule 1A form (supplied by NIE Networks along with your connection offer) to NIE Networks for approval. If approved, NIE Networks will sign the Generator Agreement and schedule 1A form and return a copy to you for your records. 3 NIE Networks Engineering Recommendation G59/1/NI 22/02/20165 Small Scale Generation Grid Connection Information Pack 11

12 7. Timescales for Grid Connection Typical Timescale where Planning Permission for linework is not required Acceptance to Construction Application to Procurement of Plant & Equipment Quotation Survey Legalities & Construction 3 months 2 3 months 4 6 months Average time for connection is approx. 6 months but could take up to 9 months, depending on earthing requirements, legalities and ordering of equipment. These timescales are subject to NIE Networks being able to: - Procure major items of plant in 5 months DOE Planning Permission & Wayleaves not being required Achieve a suitable earthing design for the site. Typical Timescale where Planning Permission for linework is required Application Acceptance to Construction to Quotation Survey & Wayleaves Procurement of Plant & Equipment Planning Permission Legalities & Construction 3 months 2 6 months 4 6 months 4 6 months Average time for connection is approx 12 months, but could take up to 18 months depending on earthing requirements, legalities and ordering of equipment. These timescales are subject to NIE Networks being able to: - Obtain wayleaves from Landowners Obtain DOE Planning Permission for overhead line work. Procure major items of plant in 5 months Achieve a suitable earthing design for the site. 22/02/20165 Small Scale Generation Grid Connection Information Pack 12

13 and will be impacted by the extent of line build and consenting requirements. 8. Renewable Obligation Certificates The Renewables Obligation (RO) is the main support mechanism for renewable electricity projects in the UK. It places an obligation on all UK suppliers of electricity to source an increasing proportion of their electricity from renewable sources. A Renewable Obligation Certificate (ROC) is a green certificate issued by OFGEM to an accredited renewable energy generator for eligible renewable electricity generated within the United Kingdom and supplied to customers within the United Kingdom by a licensed electricity supplier. In Northern Ireland OFGEM manage the ROC administration process on behalf of the Nl Utility Regulator. For further information you can contact: Utility Regulator, Queens House, 14 Queen Street, Belfast, Bt1 6ED - Tel No: or log on to their website DETI, Department of Enterprise Trade and Investment, Netherleigh, Massey Avenue, Belfast BT4 2JP - Tel No: or log on to their website 9. Complaints At NIE Networks, customer service is very important to us. However, if you are unhappy with any aspect of our customer service you can submit a complaint: Online: visit Our customer helpline, , is open from 8am-5pm, Monday- Friday. In writing to: Customer Relations Manager Northern Ireland Electricity Networks Limited Carn Industrial Estate Portadown, BT63 5QJ Consumer Council If your complaint is not resolved to your satisfaction or if at any time you are unhappy with our response, the Consumer Council, an independent body, may be able to help: Online : visit By phone In writing to: The Consumer Council Floor 3, Seatem House, Alfred street Belfast, BT2 8EN 22/02/20165 Small Scale Generation Grid Connection Information Pack 13

14 Relevant legislation regarding connections includes: ANNEX 1- LEGISLATION The Electricity (Northern Ireland) Order 1992 o Article 19- Duty to connect on request o Article 20- Procedure for requiring a connection o Article 21- Exceptions from duty to connect NIE Networks Distribution Licence. o Condition 30- Requirement to Offer terms for Connection to and Use of Distribution System 22/02/20165 Small Scale Generation Grid Connection Information Pack 14

15 Applications should be sent in hard copy to: Central Processing & Registration Northern Ireland Electricity Networks Limited 57 Dargan Road BELFAST BT3 9JU Telephone: nienetworks.co.uk 22/02/20165 Small Scale Generation Grid Connection Information Pack 15

What do you need to do?

What do you need to do? COMMERCIAL CONNECTION your Business. What do you need to do? Complete an application Please complete your application and attach your plans listed in the checklist below (you can tear off and retain the

More information

npower Microgeneration Scheme Feed In Tariffs A Guide to the Clean Energy Cashback Scheme RF8148 npm7523 Solar brochure.indd 1

npower Microgeneration Scheme Feed In Tariffs A Guide to the Clean Energy Cashback Scheme RF8148 npm7523 Solar brochure.indd 1 npower Microgeneration Scheme Feed In Tariffs A Guide to the Clean Energy Cashback Scheme RF8148 npm7523 Solar brochure.indd 1 28/03/2011 15:52 What s inside Make money from the energy you generate An

More information

Re: Connection to the Electricity Distribution System at: [GV_SINGLE_LINE_ADDR_PREM]

Re: Connection to the Electricity Distribution System at: [GV_SINGLE_LINE_ADDR_PREM] [GV_AUTH_OFFICER] [GV_NAME_LINE] [GV_ADDRESS_LINE1] [GV_ADDRESS_LINE2] [GV_ADDRESS_LINE3] [GV_ADDRESS_LINE4] [GV_ADDRESS_LINE5] Date: [GV_ISSUE_DATE ] Job No: [GV_NOTIFNUMZ2] MPRN: [GV_MPRN] Re: Connection

More information

NORTHERN IRELAND ELECTRICITY Ltd STATEMENT OF CHARGES FOR USE OF. THE NORTHERN IRELAND ELECTRICITY Ltd ELECTRICITY DISTRIBUTION SYSTEM

NORTHERN IRELAND ELECTRICITY Ltd STATEMENT OF CHARGES FOR USE OF. THE NORTHERN IRELAND ELECTRICITY Ltd ELECTRICITY DISTRIBUTION SYSTEM NORTHERN IRELAND ELECTRICITY Ltd STATEMENT OF CHARGES FOR USE OF THE NORTHERN IRELAND ELECTRICITY Ltd ELECTRICITY DISTRIBUTION SYSTEM BY AUTHORISED PERSONS Effective from 1 October 2011 to 30 September

More information

Supporting business our structure

Supporting business our structure Supporting AgriFood Agenda First Trust Bank structure Supporting agri business AgriFood Funds Renewable energy projects (estimated costs & returns) Funding renewable energy projects Recent renewable energy

More information

NEW CABLE? - Understanding the cost to connect renewable generation in Orkney

NEW CABLE? - Understanding the cost to connect renewable generation in Orkney New Holland, Holm 500kW Partner of Choice in Mid-Size Wind NEW CABLE? - Understanding the cost to connect renewable generation in Orkney Hammer, Westray 500kW Colin Risbridger Windflow UK Development Manager

More information

e-factsheet Feed-in Tariffs what we have to offer

e-factsheet Feed-in Tariffs what we have to offer e-factsheet Feed-in Tariffs what we have to offer 2 of 12 Feed-in Tariffs (FITs) make renewable generation more financially rewarding for smaller installations and help reduce the UK s carbon emissions.

More information

STATEMENT OF CHARGING METHODOLOGY FOR USE OF ELECTRICITY NORTH WEST LIMITED S ELECTRICITY DISTRIBUTION NETWORK

STATEMENT OF CHARGING METHODOLOGY FOR USE OF ELECTRICITY NORTH WEST LIMITED S ELECTRICITY DISTRIBUTION NETWORK STATEMENT OF CHARGING METHODOLOGY FOR USE OF ELECTRICITY NORTH WEST LIMITED S ELECTRICITY DISTRIBUTION NETWORK This statement is effective from 1 April 2010 This statement is approved by the Gas and Electricity

More information

A GUIDE TO. Connecting Renewable and CHP Electricity Generators to the Electricity Network

A GUIDE TO. Connecting Renewable and CHP Electricity Generators to the Electricity Network A GUIDE TO Connecting Renewable and CHP Electricity Generators to the Electricity Network A Guide to Connecting Renewable and CHP Electricity Generators to the Electricity Network October 2008 Guide prepared

More information

Leasing scheme information

Leasing scheme information Leasing scheme information Introduction Thank you for your interest in Genesis Housing Association leasing scheme. This information booklet sets out the stages, the requirements and the factors you will

More information

Networks. ESB Networks Ltd Basis of Charges for Connection to the Distribution System. Commercial and Customer Asset Management ESB Networks Ltd.

Networks. ESB Networks Ltd Basis of Charges for Connection to the Distribution System. Commercial and Customer Asset Management ESB Networks Ltd. Networks ESB Networks Ltd Basis of Charges for Connection to the Distribution System Revision Date: 14/01/20010 Revision No.: 1 Document No: DOC-10129-AXQ Issued by: ESB Networks Ltd Approved by : CER

More information

Viking Link Interconnector

Viking Link Interconnector Viking Link Interconnector Public information event for Bicker Parish Why we re here today We re here today to introduce the Viking Link project, to explain what we want to build and to answer any questions

More information

Your Professional Indemnity Solution.

Your Professional Indemnity Solution. Pinsure Your Professional Indemnity Solution. 18 Henfield Business Park, Shoreham Road, Henfield, West Sussex, BN5 9SL Tel. 01273 494914 ~ Fax. 01273 494964 Email: pinsure@pinsure.co.uk Web: www.pinsure.co.uk

More information

Generating a Return. July 2008 BHA SEMINAR

Generating a Return. July 2008 BHA SEMINAR Generating a Return July 2008 BHA SEMINAR Why invest in renewable generation? Reduces CO 2 emissions and climate change Reduces cost of electricity at the site as not paying for transmission of electricity

More information

SHE Transmission. 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015

SHE Transmission. 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015 SHE Transmission 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015 Summary This paper presents SHE Transmission s views and approach on the impact of transmission losses on the transmission

More information

Application Procedures For Electricity Connection To Consumers Electrical Installations In The New Electricity Market

Application Procedures For Electricity Connection To Consumers Electrical Installations In The New Electricity Market Application Procedures For Electricity Connection To Consumers Electrical Installations In The New Electricity Market October 2002 Forms & presentation material will be published in the EMA website www.ema.gov.sg

More information

Your Options. A simple guide to available debt options

Your Options. A simple guide to available debt options Your Options A simple guide to available debt options Contents Welcome 3 Our Customer Service Charter 3 Protected Trust Deeds 4 Debt Arrangement Scheme 6 Sequestration 8 Debt Management Plan 10 Minimal

More information

Preliminary Information Memorandum. Thanet Offshore Transmission Assets. July 2009

Preliminary Information Memorandum. Thanet Offshore Transmission Assets. July 2009 Preliminary Information Memorandum Thanet Offshore Transmission Assets July 2009 SUMMARY In April 2009 Ofgem distributed a teaser document, UK Offshore Transmission Investment Opportunity, to investors

More information

UKLPG APPROVED AUTOGAS INSTALLER CONSUMER CODE

UKLPG APPROVED AUTOGAS INSTALLER CONSUMER CODE UKLPG APPROVED AUTOGAS INSTALLER CONSUMER CODE e-mail autogas@uklpg.org Website www.drivelpg.co.uk Office 2.2, Christchurch Business Centre, Grange Road, Christchurch, Dorset, BH23 4JD. CONTENTS SECTION

More information

Terms of Business FBD Insurance plc

Terms of Business FBD Insurance plc Terms of Business FBD Insurance plc Why have terms of business? This document protects you. It is required by the Central Bank of Ireland. It is important that you read it in full. If there is anything

More information

Your Van Policy Summary

Your Van Policy Summary Your Van Policy Summary Your Summary of Cover Dear customer This booklet is your policy summary, so please keep the booklet safe for when you need it. There are also some useful tips on what to do in an

More information

Engineering Recommendation G81 - Part 1: Design and Planning

Engineering Recommendation G81 - Part 1: Design and Planning PRODUCED BY THE ENGINEERING DIRECTORATE OF THE ENERGY NETWORKS ASSOCIATION Engineering Recommendation G81 - Part 1: Design and Planning Issue 2 Ammendment 1 January 2008 Framework for design and planning,

More information

0800 121 6022 www.consumercouncil.org.uk

0800 121 6022 www.consumercouncil.org.uk a series of guides for energy users from the Consumer Council Switching domestic natural gas supplier 0800 121 6022 www.consumercouncil.org.uk March 2013 Switching domestic natural gas supplier Contents

More information

Getting Connected. A guide to how to apply for a New Connection to the Network

Getting Connected. A guide to how to apply for a New Connection to the Network Getting Connected A guide to how to apply for a New Connection to the Network About Us SP Energy Networks is part of the ScottishPower Group of companies. We provide power on behalf of supply companies

More information

Utility Warehouse. Feed-In Tariff scheme. Application form

Utility Warehouse. Feed-In Tariff scheme. Application form Utility Warehouse Feed-In Tariff scheme Application form Applying for a Utility Warehouse Feed-In Tariff Thank you for your interest in the Utility Warehouse Feed-In Tariff scheme The Feed-in Tariff (FIT)

More information

Please find enclosed with our compliments, a memory stick with the following information on for your reference 1 :

Please find enclosed with our compliments, a memory stick with the following information on for your reference 1 : E Classic Boiler Servicing Plan It is coming to that time of year when your E-Classic is going to be under high demand. It is therefore essential that it has been maintained and serviced according to manufacturer

More information

G8 - Contracts for Difference Metering

G8 - Contracts for Difference Metering PUBLIC G8 - Contracts for Difference Metering EMRS Guidance EMR Settlement Limited Version 1.0 12 October 2015 CONTENTS Change Amendment Record...4 1. Introduction...5 2. Purpose...5 3. What is the Electrical

More information

Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position X1-114.

Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position X1-114. Generation Interconnection System Impact Study Report For PJM Generation Interconnection Request Queue Position X1-114 Sandyston January 2012 Preface The intent of the System Impact Study is to determine

More information

Becoming Gas Safe Registered

Becoming Gas Safe Registered Becoming Gas Safe Registered all businesses and engineers that undertake gas work must be registered with Gas Safe Register. BECOMING REGISTERED WITH GAS SAFE REGISTER IS EASY AND FAST. The gas registration

More information

JAGUAR INSURANCE ASSET PROTECTION

JAGUAR INSURANCE ASSET PROTECTION JAGUAR INSURANCE ASSET PROTECTION 1 INTRODUCTION Did you know that if your vehicle is written off as a total loss through an accident, fire, theft or adverse weather conditions, most motor insurance companies

More information

Apex Risk Advisors Limited trading as Apex Insurance Brokers 7 South Mall, Cork. Fax: 021 2399204 www.apexinsurance.ie

Apex Risk Advisors Limited trading as Apex Insurance Brokers 7 South Mall, Cork. Fax: 021 2399204 www.apexinsurance.ie Apex Risk Advisors Limited trading as Apex Insurance Brokers Tel: 021 2398864 7 South Mall, Cork. Fax: 021 2399204 www.apexinsurance.ie General Terms of Business These terms of business set out the basis

More information

FP Marine Risks Limited

FP Marine Risks Limited FP Marine Risks Limited Terms of Business CONTENTS Introduction and Scope... 3 Management and Service Standards... 3 Placing Services... 4 Duty of Disclosure... 6 Solvency of Underwriters... 6 Confidentiality

More information

How To Pay For A Tutor In Ireland

How To Pay For A Tutor In Ireland CLAIM FORM FOR HOME TUITION PAYMENTS TO BE PAID DIRECTLY BY AGREEMENT TO COMPANIES DURING THE 2015.16 SCHOOL YEAR Name of Company: Parents are advised that, as an exceptional measure and for an agreed

More information

SQS SUPPLIER FREQUENTLY ASKED QUESTIONS

SQS SUPPLIER FREQUENTLY ASKED QUESTIONS SQS SUPPLIER FREQUENTLY ASKED QUESTIONS Page 1 of 17 CONTENTS 1. BACKGROUND... 5 What is SQS?... 5 Who is Achilles?... 5 What is the role of Achilles?... 6 2. REGISTRATION... 6 Which suppliers are required

More information

Terms of Reference Annex: Energy Sector

Terms of Reference Annex: Energy Sector Terms of Reference Annex: Energy Sector 1. Interpretation 1.1 The definitions, below, apply to both this Annex and the Terms of Reference in relation to complaints brought to Ombudsman Services: Energy

More information

KnocKdown Rebuild PRoceSS Guide

KnocKdown Rebuild PRoceSS Guide Knockdown Rebuild PROCESS GUIDE With Boutique you can have it all location, space, quality, convenience and lifestyle 02 03 04 05 If you're knocking down your existing home and rebuilding, Boutique has

More information

Consultation on proposals for the levels of banded support for solar PV under the Renewables Obligation for the period 1 April 2013 to 31 March 2017

Consultation on proposals for the levels of banded support for solar PV under the Renewables Obligation for the period 1 April 2013 to 31 March 2017 Consultation on proposals for the levels of banded support for solar PV under the Renewables Obligation for the period 1 April 2013 to 31 March 2017 7 September 2012 Department of Energy and Climate Change

More information

Good Energy Feed-in Tariff sign up form

Good Energy Feed-in Tariff sign up form For internal use only For use 15/01/16 onwards Gen D Good Energy Feed-in Tariff sign up form We know Britain can build a renewable energy future, and small-scale generation is vital to achieving this.

More information

How To Apply For Land Division In Australia

How To Apply For Land Division In Australia Development Act 1993 GUIDE FOR APPLICANTS Land Division Guide GUIDE FOR APPLICANTS Land Division Guide Planning SA Primary Industries and Resources SA 136 North Terrace Adelaide GPO Box 1815 South Australia

More information

FIXED CHARGE: This is a cost that goes towards making the service available, including

FIXED CHARGE: This is a cost that goes towards making the service available, including ELECTRICITY BILL COMPONENTS FIXED CHARGE: This is a cost that goes towards making the service available, including installation and maintenance of poles, power lines and equipment, and 24-hour customer

More information

Supplier Registration System

Supplier Registration System Supplier Registration System www.sse.com/potentialsuppliers A guide for Suppliers www.sse.com/potentialsuppliers 03 ONE WAY OF WORKING We are keen to introduce one way of working in procurement, making

More information

Feed-in Tariff Application Form

Feed-in Tariff Application Form Feed-in Tariff Application Form How to complete this form This is an application form for ScottishPowers Feed-in Tariff (FIT) Scheme. ScottishPower is a mandatory FIT licensee and is required to register

More information

ELECTRICITY NORTH WEST LTD GENERAL CONDITIONS OF CONTRACT (BUSINESS)

ELECTRICITY NORTH WEST LTD GENERAL CONDITIONS OF CONTRACT (BUSINESS) ELECTRICITY NORTH WEST LTD GENERAL CONDITIONS OF CONTRACT (BUSINESS) 1. Definitions In these Conditions: "Acceptance Form" means the acceptance form provided by Us to You with the Contract Documentation;

More information

Specialist Miscellaneous Professions (Legal Liability) Professional Liability Insurance Summary

Specialist Miscellaneous Professions (Legal Liability) Professional Liability Insurance Summary Specialist Miscellaneous Professions (Legal Liability) Professional Liability Insurance Summary Specialist Miscellaneous Professions Underwritten by a member of the QBE Insurance Group (QBE) This insurance

More information

Redundancy Payments Services. A Statement of Charter Standards

Redundancy Payments Services. A Statement of Charter Standards Redundancy Payments Services A Statement of Charter Standards How can we help you? Losing your job through redundancy can come as quite a shock. One of the first things you will want to know is what payments

More information

CUSTOMER CONNECTION GUIDE

CUSTOMER CONNECTION GUIDE CUSTOMER CONNECTION GUIDE A GUIDE TO CONNECTING ELECTRICITY SUPPLY TO YOUR PROPERTY IN UNITED ENERGY S AREA Document No: UE4309 Issue: 4 Issue Date: 1 April, 2014 1 CUSTOMER CONNECTION GUIDE A GUIDE TO

More information

Guild Accreditation Information Pack

Guild Accreditation Information Pack Guild Accreditation Information Pack Guild Accreditation Of Short Training Courses Accreditation of training courses is vital for any school as it means your students will be able to obtain insurance with

More information

LONG ISLAND UNIVERSITY RECORDS RETENTION POLICY

LONG ISLAND UNIVERSITY RECORDS RETENTION POLICY LONG ISLAND UNIVERSITY RECORDS RETENTION POLICY Statement of Policy Long Island University requires the retention of University records for specific periods of time, regardless of format, taking into account

More information

Cost to Northern Ireland of Workplace Injuries and Ill-health

Cost to Northern Ireland of Workplace Injuries and Ill-health Cost to Northern Ireland of Workplace Injuries and Ill-health Economic Research March 2013 Prepared by DETI Analytical Services for the Health and Safety Executive Northern Ireland (HSENI) Introduction

More information

GUIDANCE FOR APPLICANTS AND LANDOWNERS AND/OR OCCUPIERS

GUIDANCE FOR APPLICANTS AND LANDOWNERS AND/OR OCCUPIERS GUIDANCE FOR APPLICANTS AND LANDOWNERS AND/OR OCCUPIERS Application to the Secretary of State for Energy and Climate Change for the grant of a Necessary (Compulsory) Electricity Wayleave in England and

More information

Engineering Recommendation G81 Issue: October 2004

Engineering Recommendation G81 Issue: October 2004 Engineering Recommendation G81 Issue: Part 4 - Framework for design and planning of industrial and commercial underground connected loads up to and including 11kV 2004 Energy Networks Association All rights

More information

Key information pack. Fixed Rate Cash ISA

Key information pack. Fixed Rate Cash ISA Fixed Rate Cash ISA Key information pack Post Office Money Fixed Rate Cash ISA is provided by OneFamily. Savings in Post Office Money cash ISAs are deposited with Bank of Ireland UK. PostOfficeMoney.co.uk

More information

Gas turbine power plants

Gas turbine power plants Gas turbine power plants A global challenge Apart from other sources of energy such as water, coal and uranium, the use of natural gas and fuel oil is an important factor in assuring a reliable supply

More information

Contract for Difference for non-uk Renewable Electricity Projects

Contract for Difference for non-uk Renewable Electricity Projects Contract for Difference for non-uk Renewable Electricity Projects August 2014 Crown copyright 2014 URN 14D/291 You may re-use this information (not including logos) free of charge in any format or medium,

More information

Terms of Reference Annex: Energy Sector

Terms of Reference Annex: Energy Sector Terms of Reference Annex: Energy Sector 1. Interpretation 1.1 The definitions, below, apply to both this Annex and the Terms of Reference in relation to complaints brought to Ombudsman Services: Energy

More information

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment March 20, 2009 Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment Table of Contents:

More information

Blue Bubble Lettings Limited Landlord Terms of Business Tenant Find Service

Blue Bubble Lettings Limited Landlord Terms of Business Tenant Find Service Blue Bubble Lettings Limited Landlord Terms of Business Tenant Find Service This agreement is made between the Landlord of the property and Blue Bubble Lettings Limited, acting as the Landlord s Agent.

More information

-1- PSEG-LI Update of LIPA SGIP Full Docw-NYISO reqmts above 10 MW 10-27-14

-1- PSEG-LI Update of LIPA SGIP Full Docw-NYISO reqmts above 10 MW 10-27-14 PSEG-Long Island Smart Grid Small Generator Interconnection Procedures for New Distributed Resources 20 MW or Less Connected in Parallel with LIPA s Radial Distribution Systems -1- PSEG-LI Update of LIPA

More information

NIRIG response to EMR: Consultation on Proposals for Implementation

NIRIG response to EMR: Consultation on Proposals for Implementation 90% NIRIG response to EMR: Consultation on Proposals for Implementation 23 rd December 2013 The Northern Ireland Renewables Industry Group (NIRIG) is a joint collaboration between the Irish Wind Energy

More information

Key Features. Pension Annuity. This brochure outlines the key features of the Just Retirement Pension Annuity. Contents

Key Features. Pension Annuity. This brochure outlines the key features of the Just Retirement Pension Annuity. Contents Pension Annuity Key Features This brochure outlines the key features of the Just Retirement Pension Annuity. The Financial Conduct Authority is a financial services regulator. It requires us, Just Retirement,

More information

Tradesman Essential Per Capita Liability Insurance Summary of Cover

Tradesman Essential Per Capita Liability Insurance Summary of Cover Tradesman Essential Per Capita Liability Insurance www.towergate.co.uk This leaflet provides a summary of the significant features, benefits and limitations of the cover provided by your Tradesman Essentials

More information

Obtaining Pre-Application Planning Advice

Obtaining Pre-Application Planning Advice Obtaining Pre-Application Planning Advice Summary of Services Available and Charges 2014/15 Contents Page 2 Page 5 Page 7 Page 8 Page 9 Section A Pre-Application Planning Advice that requires a Fee and

More information

card account Terms and Conditions Handled with care Your account credit card

card account Terms and Conditions Handled with care Your account credit card card account Your account Handled with care credit card Contents These tell you about the services that are available with your Post Office card account. Please read this booklet carefully as a Post Office

More information

KEY FEATURES OF THE OPENWORK PENSION ACCOUNT (SIPP)

KEY FEATURES OF THE OPENWORK PENSION ACCOUNT (SIPP) KEY FEATURES OF THE OPENWORK PENSION ACCOUNT (SIPP) 2 INTRODUCTION The Financial Conduct Authority is a financial services regulator. It requires us, Investment Funds Direct Limited (IFDL), to give you

More information

Tidal Energy. Wind Energy. Transmission & Distribution Network. Offshore Substation. Onshore Substation. Tidal Stream Energy.

Tidal Energy. Wind Energy. Transmission & Distribution Network. Offshore Substation. Onshore Substation. Tidal Stream Energy. Offshore Renewables Tidal Energy Transmission & Distribution Network Offshore Substation Wind Energy Onshore Substation Tidal Stream Energy Consumer Atkins in Offshore Renewables The offshore wind journey

More information

Private Motor Vehicle Excess Protect

Private Motor Vehicle Excess Protect Private Motor Vehicle Excess Protect Insurance Policy Flux Direct 2 The Causeway, Bishops Stortford, Herts, CM23 2EJ In the event of a claim please call: 0844 888 7361 Customer Service: 0800 089 0154 Or

More information

Key Features of the Guaranteed Income Bond

Key Features of the Guaranteed Income Bond Key Features Savings & Investments Key Features of the Guaranteed Income Bond All documentation and communication about your bond will be in English. Phoenix Life Assurance Limited is able to provide literature

More information

Welcome Pack. Fixed Rate Business Bond

Welcome Pack. Fixed Rate Business Bond Welcome Pack Fixed Rate Business Bond Creating better futures Cambridge & Counties Bank is a unique partnership between two established and respected institutions Trinity Hall, Cambridge and Cambridgeshire

More information

guide to legal services

guide to legal services guide to legal services Contents Introduction 1 Legal Advice (Personal Matters) 2 What is Legal Advice? 2 How is Legal Advice obtained? 2 What Information does NIPSA HQ need? 3 Issue and Completion of

More information

Feed-in Tariff Application Form

Feed-in Tariff Application Form Feed-in Tariff Application Form How to complete this form This is an application form for ScottishPowers Feed-in Tariff (FIT) Scheme. ScottishPower is a mandatory FIT licensee and is required to register

More information

Methodology for Solar Power Projects

Methodology for Solar Power Projects Annexure E Methodology for Solar Power Projects This methodology is applicable to the solar power projects included in the composite policy for new and renewable (non-conventional energy sources) power

More information

Asda Van Insurance. Terms of Business. money

Asda Van Insurance. Terms of Business. money Asda Van Insurance Terms of Business money Contents page number TERMS OF BUSINESS... 3 About The Service we Provide... 3 Our Status and the Services Provided... 3 The Capacity in Which We re Acting...

More information

The Types of Standard 2 Guidance on the Standards 2 Changes to Legislation 2

The Types of Standard 2 Guidance on the Standards 2 Changes to Legislation 2 CONTENTS INTRODUCTION 2 The Types of Standard 2 Guidance on the Standards 2 Changes to Legislation 2 SCOTTISH CORE STANDARDS FOR ACCREDITED LANDLORDS 3 1 Communication with the Tenant 3 2 Equality Issues,

More information

PROCEDURE FOR ISSUANCE OF RENEWABLE ENERGY CERTIFICATE TO THE ELIGIBLE ENTITY BY CENTRAL AGENCY

PROCEDURE FOR ISSUANCE OF RENEWABLE ENERGY CERTIFICATE TO THE ELIGIBLE ENTITY BY CENTRAL AGENCY PROCEDURE FOR ISSUANCE OF RENEWABLE ENERGY CERTIFICATE TO THE ELIGIBLE ENTITY BY CENTRAL AGENCY 1. OBJECTIVE 1.1. This procedure shall provide guidance to the entities to implement Renewable Energy Certificate

More information

OFFICE OF GAS AND ELECTRICITY MARKETS TRANSITIONAL TENDER REGIME FOR OFFSHORE TRANSMISSION ASSETS DRAFT DATA ROOM POPULATION GUIDELINES

OFFICE OF GAS AND ELECTRICITY MARKETS TRANSITIONAL TENDER REGIME FOR OFFSHORE TRANSMISSION ASSETS DRAFT DATA ROOM POPULATION GUIDELINES OFFICE OF GAS AND ELECTRICITY MARKETS TRANSITIONAL TENDER REGIME FOR OFFSHORE TRANSMISSION ASSETS DRAFT DATA ROOM POPULATION GUIDELINES Office of Gas and Electricity Markets 9 Millbank London SW1P 3GE

More information

Solar PV For Surrey Schools - Information Pack

Solar PV For Surrey Schools - Information Pack Solar PV For Surrey Schools - Information Pack Solar PV for Surrey Schools: Summary of options and key considerations School interested in solar PV OPTION 1 Own investment: School is responsible for the

More information

Welcome Pack. Fixed Rate Business Bond

Welcome Pack. Fixed Rate Business Bond Welcome Pack Fixed Rate Business Bond Creating better futures Cambridge & Counties Bank is a unique partnership between two established and respected institutions Trinity Hall, Cambridge and Cambridgeshire

More information

Your Van Insurance Motor Legal Protection Policy Booklet

Your Van Insurance Motor Legal Protection Policy Booklet Your Van Insurance Motor Legal Protection Policy Booklet Contents Motor Legal Protection Insurance...3 Motor Legal Expenses...3 Helpline Services...3 Motor Legal Expenses Policy Summary...4 Cancellation

More information

Architects and Engineers Professional Liability Insurance Summary

Architects and Engineers Professional Liability Insurance Summary Architects and Engineers Professional Liability Insurance Summary Underwritten by a member of the QBE Insurance Group (QBE) This insurance is an annual contract unless stated otherwise in the quotation

More information

Contract for the supply of electricity to business premises

Contract for the supply of electricity to business premises Conditions of supplying electricity These conditions apply if you are a business customer (which includes a Micro Business customer) and are using our electricity services to supply your Premises. (For

More information

TERMS OF BUSINESS. Registered as an Insurance Intermediary under the European Communities (Insurance Mediation) Regulations, 2005 (as amended).

TERMS OF BUSINESS. Registered as an Insurance Intermediary under the European Communities (Insurance Mediation) Regulations, 2005 (as amended). TERMS OF BUSINESS INTRODUCTION The purpose of this document is to set out the basis on which Campion Insurances Limited trading as Campion Insurance, Bestquote.ie and ISME Insurance Services will provide

More information

Fleet Excess Protect

Fleet Excess Protect Fleet Excess Protect Policy Wording Thank you for choosing Fleet Excess Protect Insurance. The information in this policy wording contains important information and we have made it as easy as possible

More information

International Payments Terms & Conditions

International Payments Terms & Conditions International Payments Terms & Conditions International Payments Terms & Conditions Introduction Outward International Payments are payments that allow you to send money abroad in foreign currency or sterling

More information

DOCUMENTED PROCEDURE MANUAL

DOCUMENTED PROCEDURE MANUAL NAPIT REGISTERED INSTALLERS DOCUMENTED PROCEDURE MANUAL CONTENTS 1. INTRODUCTION 2. DEFINITIONS 3. RESPONSIBILITY FOR QUALITY 4. DOCUMENT AND DATA CONTROL 5. CUSTOMER ENQUIRIES AND QUOTATIONS 6. CONTRACTS

More information

ELECTRICITY SUPPLY/ TRADE LICENSE KORLEA INVEST A.S

ELECTRICITY SUPPLY/ TRADE LICENSE KORLEA INVEST A.S Hamdi Mramori Street, No 1 Prishtina 10000 Kosovo Tel: +381 (0) 38 247 615 ext. 103 Fax: +381 (0) 38 247 620 e-mail: info@ero-ks.org www.ero-ks.org ELECTRICITY SUPPLY/ TRADE LICENSE GRANTED TO: KORLEA

More information

pensions investments life insurance Administrator Guide

pensions investments life insurance Administrator Guide pensions investments life insurance Personal Retirement Savings Accounts (PRSA) Administrator Guide About us Established in Ireland in 1939, Irish Life is now part of the Great-West Lifeco group of companies,

More information

Feed-in Tariff Application Form

Feed-in Tariff Application Form Feed-in Tariff Application Form am applying for a British Gas Feed-in Tariff and have A new installation An extension on an existing installation How to make a successful application Please make sure you

More information

Consumer Code. for Home Builders

Consumer Code. for Home Builders Consumer Code for Home Builders This document contains the Consumer Code requirements together with non-mandatory good practice guidance for Home Builders Second Edition January 2010 Contents Meaning of

More information

Feed in Tariffs for Microgeneration. Jos Mister Energy Saving Trust

Feed in Tariffs for Microgeneration. Jos Mister Energy Saving Trust Feed in Tariffs for Microgeneration Jos Mister Energy Saving Trust Funding and Finance Feed in Tariffs Clean Energy Cashback April 2010 Renewable Heat Incentive April 2011 Business support Enhanced Capital

More information

Distributed Generation Standards under the ENC Licence

Distributed Generation Standards under the ENC Licence Distributed Generation Standards under the ENC Licence Effective from: February 2012 BK-CSR-IG-0127 GTC Distributed Generation Standards under ENC Licence Rev 01 Page 1 of 7 Introduction The following

More information

Guide for Applicants

Guide for Applicants Guide for Applicants Analyst Networks Fixed Term (2 years) Key Dates for Applicants Closing Date: Noon on Friday 29 July 2016 Interview Dates: w/c 8 August 2016 in Queens House, Belfast Utility Regulator

More information

1.3 What is the cash accounting scheme?

1.3 What is the cash accounting scheme? Foreword This notice cancels and replaces Notice 731 (August 2008). Details of any changes to the previous version can be found in paragraph 1.2 of this notice. The legal basis for the cash accounting

More information

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited TABLE OF CONTENTS 1.0 Purpose and Scope...2 1.1 Methodology Purpose...2

More information

SSE s criteria used for GHG emissions reporting

SSE s criteria used for GHG emissions reporting SSE s criteria used for reporting 1 Introduction This document details the annual greenhouse gas emissions reporting approach used by SSE Plc to report the tonnes of carbon dioxide equivalent (CO2e) during

More information

ES281 COMPANY-SPECIFIC APPENDICES TO ENA ENGINEERING RECOMMENDATION G81 PART 1

ES281 COMPANY-SPECIFIC APPENDICES TO ENA ENGINEERING RECOMMENDATION G81 PART 1 ES281 COMPANY-SPECIFIC APPENDICES TO ENA ENGINEERING RECOMMENDATION G81 PART 1 Design and Planning Specification for New Low Voltage Installations for Housing Developments 1. SCOPE This appendix to ENA

More information

Guide to Current Account Switching

Guide to Current Account Switching Guide to Current Account Switching Thinking of switching? All you have to do is follow these 3 easy steps to move to your new Allied Irish Bank (GB) current account. Get in touch! Call into a branch, or

More information

COMPUTER QUOTE TERMS OF BUSINESS AND INFORMATION REGARDING OUR SERVICES

COMPUTER QUOTE TERMS OF BUSINESS AND INFORMATION REGARDING OUR SERVICES COMPUTER QUOTE TERMS OF BUSINESS AND INFORMATION REGARDING OUR SERVICES Birch House Parklands Business Park Forest Road Denmead Hampshire PO7 6XP (Computer Quote is the trading name of Stride Limited)

More information

Online Fixed Energy A Guaranteed Deal

Online Fixed Energy A Guaranteed Deal Online Fixed Energy A Guaranteed Deal Online Fixed Price Energy August 2014 Offer Prices effective from 20th March 2013 Limited Offer subject to availability and may be withdrawn from sale at any time.

More information

Asda Van Insurance. money. Terms of Business

Asda Van Insurance. money. Terms of Business Asda Van Insurance money Terms of Business Contents page number TERMS OF BUSINESS... 3 About The Service we Provide... 3 Our Status and the Services Provided... 3 The Capacity in Which We re Acting...

More information

Choice Home Loans Penrith & Blue Mountains

Choice Home Loans Penrith & Blue Mountains Credit Guide This document provides you with information relating to our activities and those of our credit representatives. It contains information about various fees and charges that may be payable by

More information