1 Electrical Technical Services Group Power Systems Analysis and Special Consulting Services Electrical Engineering
2
3 reliable POWER Today s complex industrial electrical power systems require special analysis to establish performance acceptability. KBR has been a recognized leader in the field of power system analysis for over twenty-five years, contributing to actually developing many of the standards and practices currently in use by the industry. In addition, the Electrical Engineering organization at KBR is unique among E&C firms, differentiated by a staff of power system engineering experts, the Electrical Technical Services Group (ETSG). The ETSG can provide the full range of analytical engineering services essential for the effective planning, design, and reliable operation of even the most complex electrical power system. Engineering services that can be provided as either a stand-alone effort or in support of a multi-discipline project include: Power Distribution System Studies Plant Power System / Equipment Surveys System / Equipment Grounding Evaluations Tie Line (Watt & Var) Control / Load Shedding Systems On-site Power Systems Seminars The Power Distribution System Studies mentioned are used to predict the performance of a power distribution system. These studies determine the behavior of and the operating duties imposed on the electrical equipment and components applied within the system during normal and abnormal events. Such studies include: Fault Analysis / Breaker Application (Short-Circuit) Studies Load Flow & Motor Starting Voltage Drop Studies Load Analysis Studies Protective Device Coordination Studies Motor Starting Torque / Acceleration Time Studies Arc Flash Hazard Assessment / Personal Protective Equipment (PPE) Studies Grounding, Bonding, and Ground Mat Design Studies Transient Stability Studies Cable Ampacity Studies Lightning and Surge Protection Studies Harmonic Analysis Reliability / Availability Studies State-of-the-art computer-based technology is employed in performing all these analytical investigations. Several types of power system studies are illustrated and a brief description of the studies available appears on the following pages.
4 Protective Device Coordination Time-Current Curve Time-current plots of protective device characteristics and equipment ratings provide graphical evidence that equipment is properly protected and protective devices are selective with one another. These curves are created using commercially available software. Device Setting Summary sheets provide a complete listing of the recommended settings and calibrating data for plotted protective devices along with the settings or ratings for all other protective devices in the system. These sheets greatly simplify and streamline the work performed by the field technicians setting the devices. Additionally, relay configuration files generated by ETSG are downloaded directly into microprocessor-based relays. This approach virtually eliminates relay setting errors and further reduces commissioning time. Short-Circuit Calculations The total short-circuit current and contribution from each circuit element complete with corresponding X/R ratios are calculated at each bus in the system. These values can be compared with the rating of the switching / interrupting devices to confirm that proper devices have been selected. Line-to-ground faults as well as three-phase faults can be evaluated.
5 Ground Mat Potentials For a given ground grid design and soil condition, the mesh and perimeter touch voltages at the earth s surface are calculated and compared with tolerable (safe) touch potentials. The locations of dangerous voltage levels, where present, are precisely identified so that appropriate corrective measures can be incorporated into the ground grid design. Transient Stability Studies The dynamic response of prime movers / generators and induction / synchronous motors can be modeled and system performance studied for user-defined upset conditions such as faults, line or machine outages, step-load changes or motor starting. These studies will guide system design, protective device settings, or load shedding requirements to ensure that the power system will regain operating equilibrium following the upset. Results can be graphically represented by a plot of machine / system parameters with time.
6 Electrical Power System y Studies Fault Analysis / Breaker Application Study Calculates per ANSI or IEC standards momentary and interrupting fault duties at every system bus. Compares circuit breaker, fuses and non-fusible equipment ratings with imposed duties to verify that device start-up circuit capabilities are adequate. Protective Device Coordination Study Plots the time-current curve at specified values for each protective device applied on the power system and identifies device calibration points. Arc Flash Hazard Assessment Using information determined from the protective device coordination study and short-circuit study, this analysis calculates arc flash energy exposure levels for defined operations or switching conditions at each plant bus location. These exposure levels are then used to identify Personal Protective Equipment (PPE) and working distances as prescribed by NFPA 70E and IEEE Load Flow Study Calculates the system steady-state bus voltages, kilowatt and kilovar branch loads for motor and static loads. Accepts capacitors, off-nominal transformer taps and generator loading levels, and allows investigation of various operating modes. Reports provided on buses with abnormal voltages, branch loading / losses and total system loading / demand conditions. Motor Starting Voltage Drop Study Calculates the system voltage levels before and just after the impact of a motor being started, referred to as a snapshot voltage drop calculation. Motor Starting Torque / Acceleration Time Study Using motor / load inertia and torque values, calculates the motor voltage and output torque during the accelerating period, and determines the overall starting time. Ground Mat Potential Study Determines step and touch potentials to evaluate shock hazards in substations or other ground mat environments. Performs a detailed mesh-by-mesh analysis of the mat to precisely identify hazard locations and optimal design remedies. Transient Stability Study Using the dynamic characteristics of prime movers and synchronous machinery, calculates the response of these machines to various system disturbances and plots the machine variables with respect to time in order to reveal any unstable operating conditions requiring load shedding or other corrective measures. Cable Ampacity Study Using the Neher-McGrath calculation method, calculates the ampacity or operating temperature of multiple cable circuits direct buried or in underground duct banks. Harmonic Analysis With harmonic producing loads on a system having power factor correction capacitors: (a) calculates the system bus voltages, kilowatt and kilovar branch loads at various multiples of fundamental frequency; (b) calculates the total voltage and current values at each bus so that unacceptable voltage distortion and the frequency where harmonic amplification exists are easily identified; and (c) can be used to evaluate the effectiveness of harmonic filters and tuning reactors. Reliability / Availability Studies Using standard failure rates and outage duration times for electrical components: (a) calculates the statistical availability (expected percentage of up-time) of a power system; and (b) can be used for comparison of alternative system designs from an overall availability standpoint and to evaluate the worth of redundant circuit designs within a specific system. Note: All Electrical Power System Studies conform to procedures and practices described in the latest version of IEEE Standard 399 Recommended Practice for Industrial and Commercial Power Systems Analysis, (The Brown Book) as well as all other related standards on the subject. KBR uses commercially available software programs to perform the calculation for all these studies. For further information, contact the KBR Electrical Chief Technology Engineer.
7 Representativep Listing g of Power System y Studies Esso Exploration & Production Chad, Inc. Chad Development & Export System Facility Project Power system: Four in-plant 42 MW, 13.8 kv gas turbine generators (GTG); 33 kv Gas Insulated Switchgear (GIS) main substation; 66 kv and 33 kv transmission lines to remote substations; and several 33 kv, 6.6 kv, and 400 V substations. Short-circuit, load flow, motor starting, transient stability, protective device coordination, insulation coordination, harmonic load flow, and ground mat potential studies. Shell Philippines Malampaya Project, Offshore Philippines Power system: Three 8 MVA, 4.16 kv GTGs; two 1.3 MW, 480 V emergency generators; 4.16 kv and 480 V distribution systems. Short-circuit, load flow, motor starting, transient stability, and protective device coordination studies. ExxonMobil Kizomba FPSO FEED Project, Offshore Angola Power system: Three 35 MVA, 13.8 kv GTGs; one 5 MVA, 4.16 kv essential generator; and 1.5 MW emergency generator; and 15 kv subsea cable distribution system to remote platforms. Electrical system optimization studies for distribution voltage selection, load flow, short-circuit, and motor starting analysis. Exxon Singapore Olefins Project, Jurong Island, Singapore Power system: kv and kv substations, two 135 MVA base-rated utility-tie transformers, two 104 MVA GTGs, two 100 MVA base-rated generator transformers, two 75 MVA distribution transformers. Short-circuit, load flow, motor starting, motor re-acceleration, and protective device coordination studies. Farmland Mississippi Chemical Ammonia Project, Point Lisas, Trinidad Power system: 13.8 kv substation with 16 MW STG and utility tie. Short-circuit, load flow, motor starting, transient stability, and protective device coordination studies. Maraven Refinery Expansion Project, Cardon, Venezuela Power system: New kv substation with two 140 MVA transformers and current limiting reactors that tie an Independent Power Producer (IPP) and this expansion project into the existing facility, which contains three GTGs and four STGs. Short-circuit, load flow, motor starting, transient stability, load shedding, motor re-acceleration, and protective device coordination studies.
8 Electrical Engineering 601 Jefferson Avenue Houston, Texas Tel: Attn: Electrical Chief Technology Engineer Worldwide Headquarters 4100 Clinton Drive Houston, Texas Tel: K /03 Printed in the U.S.A Kellogg Brown & Root a Halliburton company Printed by KBR Communications
Typical Data Requirements Data Required for Power System Evaluation
Summary 66 Carey Road Queensbury, NY 12804 Ph: (518) 792-4776 Fax: (518) 792-5767 www.nepsi.com sales@nepsi.com Harmonic Filter & Power Capacitor Bank Application Studies This document describes NEPSI
More informationEngineering innovation
Eaton's Electrical Engineering Services & Systems Solutions Focus Seamless Solutions for Reliable, Efficient and Safe Power Systems Engineering innovation Progressive solutions for today s power systems
More informationPower System Analysis
PDHonline Course E194 (15 PDH) Power System Analysis Instructor: Timothy L. O'Hearn, PE 2012 PDH Online PDH Center 5272 Meadow Estates Drive Fairfax, VA 22030-6658 Phone & Fax: 703-988-0088 www.pdhonline.org
More informationPower Quality for Information Technology System
Power Quality for Information Technology System ITS OBVIOUS THE TOLERANCE IS DIFFRENT But What isn t Tobvious? HOW MANY OF YOU HAVE : A COMPUTER AT HOME? = Computers are not screens and Keyboards COMPUTERS
More informationPart 1 System Modeling & Studies for Existing Systems
Part 1 System Modeling & Studies for Existing Systems Operation Technology, Inc. Copyright 2009 Result of rapid release of energy due to an arcing fault between two conductors. Bus voltages > 208V Temperatures
More informationElectrical Distribution Services for Mining and Metals Industries
Electrical Distribution Services for Mining and Metals Industries Solutions to help maximize plant reliability and ensure personnel safety Make the most of your energy SM Electrical Systems are Serious
More informationHow the National Grid System Operates. Chris Gorman Lead Account Executive Syracuse
How the National Grid System Operates Chris Gorman Lead Account Executive Syracuse 2 Parts of the Electric System Parts of the Electric System 1. Generating Station: Produces Electricity. 2. Transmission
More informationSPECIFICATION COG-2007
Cleco Power LLC SPECIFICATION COG-2007 FOR PARALLEL OPPERATION OF CUSTOMER-OWNED GENERATION ON CLECO S ELECTRICAL SYSTEM Revised: March 7, 2014 CONTENTS ITEM NO. TITLE PAGE NO. 1.0 Scope 3 2.0 Policy On
More informationHyperlinks are Inactive
Prepared by: NIB/EOB PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES 05503 Department: Electric T&D Section: T&D Engineering and Technical Support Approved by: G.O. Duru (GOD)
More informationCahier technique no. 196
Collection Technique... Cahier technique no. 196 Integration of local power generation in industrial sites and commercial buildings T. Hazel "Cahiers Techniques" is a collection of documents intended for
More informationNuclear Power Plant Electrical Power Supply System Requirements
1 Nuclear Power Plant Electrical Power Supply System Requirements Željko Jurković, Krško NPP, zeljko.jurkovic@nek.si Abstract Various regulations and standards require from electrical power system of the
More informationELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F
ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F TABLE OF CONTENTS Appendix F - Electrical Engineering Design Criteria F.1 Introduction...F-1 F.2 Codes and Standards...F-1 F.3 Switchyard and Transformers...F-1
More informationLIMITING SHORT-CIRCUIT CURRENTS IN MEDIUM-VOLTAGE APPLICATIONS
LIMITING SHORT-CIRCUIT CURRENTS IN MEDIUM-VOLTAGE APPLICATIONS Terence Hazel Senior Member IEEE Schneider Electric 38050 Grenoble France Abstract The power requirements for large industrial sites is increasing.
More informationPower System review W I L L I A M V. T O R R E A P R I L 1 0, 2 0 1 3
Power System review W I L L I A M V. T O R R E A P R I L 1 0, 2 0 1 3 Basics of Power systems Network topology Transmission and Distribution Load and Resource Balance Economic Dispatch Steady State System
More informationGeneral Validation Test Program for Wind Power Plants Connected to the Hydro-Québec Transmission System
General Validation Test Program for Wind Power Plants Connected to the Hydro-Québec Transmission System Direction Planification des actifs et expertise de transport February 2011 TABLE OF CONTENTS 1. CONDUCTING
More informationABB PSPS Erich Steinmann; Generator control-2013
ABB PSPS Erich Steinmann; Generator control-2013 GENERATOR CONTROL THE MODULAR SOLUTION FOR GENERATORS To make sure that power is efficiently converted into electric energy, it is necessary to supervise
More informationDesign of electrical power system for a 1000MW nuclear power generating station
Design of electrical power system for a 1000MW nuclear power generating station K Raja, K Yesunadam Dept. of Electrical & Electronics Engineering, Lingaya s Institute of Management & Technology, Vijayawada,
More informationThe Importance of the X/R Ratio in Low-Voltage Short Circuit Studies
The Importance of the X/R Ratio in Low-Voltage Short Circuit Studies DATE: November 17, 1999 REVISION: AUTHOR: John Merrell Introduction In some short circuit studies, the X/R ratio is ignored when comparing
More informationETAP 11 The Future of Power Systems Engineering & Operation - Today
ETAP 11 The Future of Power Systems Engineering & Operation - Today Innovation Automation Collaboration Multi-Dimension Database Lock & unlock element properties 10 States to track equipment conditions
More informationCIRCUIT BREAKER INTERRUPTING CAPACITY AND SHORT-TIME CURRENT RATINGS
CIRCUIT BREAKER INTERRUPTING CAPACITY AND SHORT-TIME CURRENT RATINGS David D. Roybal, P.E. Senior Member, IEEE Eaton Electrical 3697 Mount Diablo Boulevard Lafayette, CA 94549 Abstract Low-voltage circuit
More informationECE 586b Course Project Report. Auto-Reclosing
ECE 586b Course Project Report Auto-Reclosing Srichand Injeti May 5, 2008 Department Of Electrical and computer Engineering University Of Western Ontario, London Ontario Table of contents 1. Introduction...1
More informationVariable Frequency Drives - a Comparison of VSI versus LCI Systems
Variable Frequency Drives - a Comparison of VSI versus LCI Systems Introduction TMEIC is a leader in the innovative design and manufacture of large ac variable f requency drive systems. TMEIC has been
More informationwww.klmtechgroup.com TABLE OF CONTENT
Page : 1 of 13 Project Engineering Standard www.klmtechgroup.com KLM Technology #03-12 Block Aronia, Jalan Sri Perkasa 2 Taman Tampoi Utama 81200 Johor Bahru Malaysia ELECTIRAL GROUNDING TABLE OF CONTENT
More informationControl Strategies of the Doubly Fed Induction Machine for Wind Energy Generation Applications
Control Strategies of the Doubly Fed Induction Machine for Wind Energy Generation Applications AUTHORS Dr. Gonzalo Abad, The University of Mondragon, SPAIN. Dr. Miguel Ángel Rodríguez, Ingeteam Transmission
More informationPMCS. Integrated Energy Management Solution. Unlock the Full Potential of Power Networks Through Integration. Complete Solution. Informed Decisions
PMCS Integrated Energy Management Solution Unlock the Full Potential of Power Networks Through Integration Power Management Control System (PMCS) is a highly customizable, fully integrated end-to-end Energy
More informationPacifiCorp Original Sheet No. 476 FERC Electric Tariff, Substitute 6 th Rev Volume No. 11 APPENDIX 2 TO SGIP
PacifiCorp Original Sheet No. 476 APPENDIX 2 TO SGIP SMALL GENERATOR INTERCONNECTION REQUEST (Application Form) Transmission Provider: Designated Contact Person: Address: Telephone Number: An Interconnection
More informationElectrical Engineering
Electrical Engineering Trust our people. R eady is a professional engineering firm with highlyqualified electrical and controls personnel focused on providing solutions to meet your specific needs. Ready
More informationReplacement Breakers & Retrofit Products
14 SWITCHGEAR Replacement Breakers & Retrofit Products Medium Voltage Replacement Circuit Breakers Ratings from 5 38 kv, 250 1500 MVA, 1200-3000 Amperes Replacement circuit breakers provide a cost-effective
More informationFACTS. Solutions to optimise network performance GRID
Solutions to optimise network performance GRID Solutions to optimise your network Our worldwide presence: Better solutions for your network all around the world Tampere Philadelphia Stafford Konstanz Beijing
More informationProduct brochure Multi Functional Switchgear PASS M00 72.5 kv Flexible and compact switchgear solutions for windfarms
Product brochure Multi Functional Switchgear PASS M00 72.5 kv Flexible and compact switchgear solutions for windfarms The future of Wind Farms As offshore wind farms move towards deploying higher capacity
More informationElectric Power Systems An Overview. Y. Baghzouz Professor of Electrical Engineering University of Nevada, Las Vegas
Electric Power Systems An Overview Y. Baghzouz Professor of Electrical Engineering University of Nevada, Las Vegas Overview Power Generation Conventional power generation Power generation from renewables
More informationCONSULTATION PAPER FOR PROPOSED MODIFICATIONS TO THE TRANSMISSION CODE
CONSULTATION PAPER FOR PROPOSED MODIFICATIONS TO THE TRANSMISSION CODE Closing date for submission of representations: 30 th Sep 2014, 5 pm 18 AUG 2014 ENERGY MARKET AUTHORITY 991G Alexandra Road #01-29
More informationWide Area Monitoring Current Continental Europe TSOs Applications Overview
Wide Area Monitoring Current Continental Europe TSOs Applications Overview Version 5 System Protection & Dynamics Working Group 20th September 2015 1. Content 1. Content... 2 2. Introduction... 3 3. Main
More informationPredictive Maintenance
PART ONE of a predictive maintenance series Predictive Maintenance Overview Predictive maintenance programs come in all shapes and sizes, depending on a facility s size, equipment, regulations, and productivity
More informationMEDIUM AND HIGH VOLTAGE CAPACITORS, CAPACITOR BANKS AND SYSTEMS
MEDIUM AND HIGH VOLTAGE CAPACITORS, CAPACITOR BANKS AND SYSTEMS Meher Capacitors offers reliable and innovative products and solutions in the fields of Reactive Power Compensation, Power Quality and Energy
More informationShort Circuit Current Calculations
Introduction Several sections of the National Electrical Code relate to proper overcurrent protection. Safe and reliable application of overcurrent protective devices based on these sections mandate that
More informationThe following table shows approximate percentage wise the
SHORT-CIRCUIT CALCULATION INTRODUCTION Designing an electrical system is easy and simple, if only the normal operation of the network is taken into consideration. However, abnormal conditions which are
More informationEaton s Electrical Services & Systems. Technical Training Safety Training
Eaton s Electrical Services & Systems Technical Training Safety Training 2 EATON CORPORATION Eaton s Electrical Services & Systems Technical Training Safety Training Eaton conducts technical training and
More informationC.I.8.2 Offsite Power System. C.I.8.2.1 Description
C.I.8 Electric Power The electric power system is the source of power for station auxiliaries during normal operation, and for the reactor protection system and ESF during abnormal and accident conditions.
More informationThis document should be reviewed at least every two years.
1.0 Change Control Version Date Modification Author(s) Reviews and Approvals by Issue 1 06 August 2007 Initial Document Philip J. Tatro David Wright Issue 2 29 February Removed Confidential from Philip
More informationEARTHING SYSTEM CALCULATION
BAZIAN STEAL FACTORY S/S 132/11kV, 1x30/40MVA EARTHING SYSTEM CALCULATION Kurdistan Region Sulaimani May 2011 Bazian Steal Factory S/S 132/11kV, 1x30/40 MVA Contents: 1. Introduction... 3 2. List of references
More informationANCILLARY EQUIPMENT AND ELECTRICAL EQUIPMENT Power Supply Systems and Electrical Equipment for Desalination Plants - Y.M. Hamud and A.H.
POWER SUPPLY SYSTEMS AND ELECTRICAL EQUIPMENT FOR DESALINATION PLANTS Y.M. Hamud and A.H. Anwar Abu Dhabi Water and Electricity Authority, Abu Dhabi, UAE Keywords : Electrical System, Network for Desalination,
More informationEverything you need for protection scheme testing
Power System Simulator for Testing Protection Relays and Schemes Everything you need for protection scheme testing The is the only instrument with the high power, flexibility and software to perform full
More informationFusible Disconnect Switch
Circuit Breakers Circuit breakers are used in panelboards and switchboards to provide circuit protection and provide a means of energizing and de-energizing a circuit. Siemens Sentron molded case circuit
More informationMinimizing Impact of Electric Utility Outages with Backup Generation
Minimizing Impact of Electric Utility Outages with Backup Generation Introduction of the Speaker Michael Dempsey, PE Senior Electrical Engineer Carter & Burgess, Inc. Energy & Power Solutions Facility
More informationLAB1 INTRODUCTION TO PSS/E EE 461 Power Systems Colorado State University
LAB1 INTRODUCTION TO PSS/E EE 461 Power Systems Colorado State University PURPOSE: The purpose of this lab is to introduce PSS/E. This lab will introduce the following aspects of PSS/E: Introduction to
More informationUnified requirements for systems with voltages above 1 kv up to 15 kv
(1991) (Rev.1 May 2001) (Rev.2 July 2003) (Rev.3 Feb 2015) Unified requirements for systems with voltages above 1 kv up to 15 kv 1. General 1.1 Field of application The following requirements apply to
More informationIntroduction. Harmonics and IEEE 519 Page 1 of 19
Introduction In an ideal power system, the voltage supplied to customer equipment, and the resulting load current are perfect sine waves. In practice, however, conditions are never ideal, so these waveforms
More informationEarthing Guidance Notes
Central Networks Earthing Manual Section E2 Earthing Guidance Notes Version: 2 Date of Issue: September 2007 Author: Nigel Johnson Job Title: Earthing Specialist Approver: John Simpson Job Title: Head
More informationINTRODUCTION TO SYSTEM PROTECTION. Hands-On Relay School 2012
INTRODUCTION TO SYSTEM PROTECTION Hands-On Relay School 2012 CONGRATULATIONS On choosing the field of system protection. It is an exciting, challenging profession. System protection has changed considerably
More informationDC TRANSMISSION BASED ON VOLTAGE SOURCE CONVERTERS
DC TRANSMISSION BASED ON VOLTAGE SOURCE CONVERTERS by Gunnar Asplund, Kjell Eriksson, Hongbo Jiang, Johan Lindberg, Rolf Pålsson, Kjell Svensson ABB Power Systems AB Sweden SUMMARY Voltage Source Converters
More informationRule 5.500 Fast Track Analysis for National Life Insurance Co.
Rule 5.500 Fast Track Analysis for National Life Insurance Co. For a 500 kw Solar array to be located at 155 Northfield Street in Montpelier, Vermont Green Mountain Power Pam Allen Date: 5/31/13 SECTION
More informationSpending too much to maintain aging switchgear? Circuit breaker solutions from Square D Services.
Spending too much to maintain aging switchgear? Circuit breaker solutions from Square D Services. Spending too much time and money on equipment maintenance? Square D Services: Your source for circuit breaker
More informationINTRODUCTION TO SYNCHRONIZING AUTOMATIC SYNCHRONIZING CONSIDERATIONS AND APPLICATIONS
INTRODUCTION TO SYNCHRONIZING AUTOMATIC SYNCHRONIZING CONSIDERATIONS AND APPLICATIONS INTRODUCTION It is the intention of this presentation to provide an explanation of the automatic synchronizing process,
More informationA program for co-funded ASHRAE research relating to response to extreme events and anticipated harsh power system environments.
Proposed Research TC 1.9 Electrical Systems Adapting HVAC Systems to Operate Under Duress DRAFT Lawrence Markel, Research Subcommittee Chair ASHRAE Technical Committee 1.9 Electrical Systems 1 August 2002
More information2a. IEM Indoor Metal Clad Medium Voltage Switchgear 15KV 16346-1. 2a. Section 16346 INDOOR METAL CLAD MEDIUM VOLTAGE SWTICHGEAR (Std.
2a. IEM Indoor Metal Clad Medium Voltage Switchgear 15KV 16346-1 2a. Section 16346 INDOOR METAL CLAD MEDIUM VOLTAGE SWTICHGEAR (Std. Relays) Part 1 General 1.1 CONDITIONS AND REQUIREMENTS: A. Refer to
More informationWhat s up with Arc Flash?
What s up with Arc Flash? Presented by Mark Haskins, CSP Practical Safety Solutions, LLC CONN OSHA Breakfast Roundtable February 18, 2014 2014 Practical Safety Solutions, LLC What is Arc Flash? Definition
More informationShunt Capacitor Bank Fundamentals and Protection
2003 Conference for Protective Relay Engineers - Texas A&M University April 8-10, 2003, College Station (TX) Shunt Capacitor Bank Fundamentals and Protection Gustavo Brunello, M.Eng, P.Eng Dr. Bogdan Kasztenny
More informationThe design and performance of Static Var Compensators for particle accelerators
CERN-ACC-2015-0104 Karsten.Kahle@cern.ch The design and performance of Static Var Compensators for particle accelerators Karsten Kahle, Francisco R. Blánquez, Charles-Mathieu Genton CERN, Geneva, Switzerland,
More informationRISK MITIGATION for ELECTRICAL WORK. Feb 2013 San Diego CA
RISK MITIGATION for ELECTRICAL WORK Feb 2013 San Diego CA Agenda I. RISK Define the Risks Arc Flash Review II. MITIGATION 3 Easy Steps New Designs Vs. Existing Systems III. DUKE UNIVERSITY EXAMPLE I. Risk
More informationGENERATOR DIFFERENTIAL PROTECTION RELAY STABILITY VIS-A -VIS SELECTION OF CTS MR. H. C. MEHTA & MR. JAY MEHTA Power Linker Group Co.
GENERATOR DIFFERENTIAL PROTECTION RELAY STABILITY VIS-A -VIS SELECTION OF CTS MR. H. C. MEHTA & MR. JAY MEHTA Power Linker Group Co., Mumbai ABSTRACT : For generator differential protection, one set of
More informationAMSC s Superconductor Cable Technologies for Electric Utilities
International Workshop 2014 AMSC s Superconductor Cable Technologies for Electric Utilities Michael Ross, P.E. Managing Director of Superconductor Power Systems AMSC Corporate Facts Headquartered in MA,
More informationGrounding of Electrical Systems NEW CODE: Grounding and Bonding
Grounding of Electrical Systems NEW CODE: Grounding and Bonding Presented By Scott Peele PE Grounding of Electrical Systems Outline Defining the Terms Why should I Ground? Types of Grounding Systems Separately
More information100% Stator Ground Fault Detection Implementation at Hibbard Renewable Energy Center. 598 N. Buth Rd 3215 Arrowhead Rd
100% Stator Ground Fault Detection Implementation at Hibbard Renewable Energy Center Introduction Roger Hedding Steven Schoenherr, P.E. ABB Inc. Minnesota Power 598 N. Buth Rd 3215 Arrowhead Rd Dousman,
More informationEssPro Energy Storage Grid Substation The power to control energy
EssPro Energy Storage Grid Substation The power to control energy EssPro Grid gives you the power to control energy helping to keep smart grids in balance Maximizing the value and performance of energy
More informationENGINEERING REPORT. XYZ Corporation 100 Anyplace Drive Chicago, Illinois 60613
ENGINEERING REPORT XYZ Corporation 100 Anyplace Drive Chicago, Illinois 60613 PERFORMED BY: MIDWEST ELECTRICAL CONSULTANTS, INC 18055 UPLAND DRIVE TINLEY PARK, ILLINOIS 60487 (708) 444-0001 fax: 444-0003
More informationElectrical Predictive and Preventative Maintenance
Electrical Predictive and Preventative Maintenance Electrical and mechanical equipment is subject to failure at the worst possible time for no apparent reason. - Mose Ramieh III There are two types
More informationWhat Are the Qualifications to Conduct Arc Flash Studies? Where Do You Begin?
What Are the Qualifications to Conduct Arc Flash Studies? Where Do You Begin? Comparing apples-to-apples bids Plant Services Special Report A shock hazard analysis should be included as part of an arc
More informationPSS E. High-Performance Transmission Planning Application for the Power Industry. Answers for energy.
PSS E High-Performance Transmission Planning Application for the Power Industry Answers for energy. PSS E architecture power flow, short circuit and dynamic simulation Siemens Power Technologies International
More informationAn Overview of Wind Plant Design Standards and Common Nomenclature and Available Resources to the Power Engineer
An Overview of Wind Plant Design Standards and Common Nomenclature and Available Resources to the Power Engineer IEEE PES Wind Plant Collector System Design Working Group Session: Wind Plant Collector
More informationWhite Paper SolarEdge Three Phase Inverter System Design and the National Electrical Code. June 2015 Revision 1.5
White Paper SolarEdge Three Phase Inverter System Design and the National Electrical Code June 2015 Revision 1.5 Shalhevet Bar-Asher; SolarEdge Technologies, Inc. Bill Brooks, PE; Brooks Engineering LLC
More informationA USERS GUIDE TO ARC RESISTANT LOW VOLTAGE SWITCHGEAR & MOTOR CONTROL ANALYTICAL COMPARISON VS ARC FLASH TEST RESULTS
A USERS GUIDE TO ARC RESISTANT LOW VOLTAGE SWITCHGEAR & MOTOR CONTROL ANALYTICAL COMPARISON VS ARC FLASH TEST RESULTS By: Gabriel Arce, ABB, San Luis Potosi, Mexico Casey McCollum, ABB, Houston, TX John
More informationATTACHMENT F. Electric Utility Contact Information Utility Name. For Office Use Only
ATTACHMENT F CATEGORY 2 GENERATOR INTERCONNECTION APPLICATION FOR ALL PROJECTS WITH AGGREGATE GENERATOR OUTPUT OF MORE THAN 20 KW BUT LESS THAN OR EQUAL TO 150 KW Also Serves as Application for Category
More informationCity Of Ottawa High Voltage Substation Inspection, Maintenance Rev 00 2015 July 17 and Testing, ROPEC Page 1
2015 July 17 and Testing, ROPEC Page 1 PART 1 GENERAL 1.1. Scope.1 Equipment replacement and testing for a 44 kv 4.16kV/600V substation: a. Replacement of Insulators as indicated on the drawings in Appendix
More informationUnderstanding Arc Flash
Understanding Arc Flash Presented by Eddie F. Jones, PE 1 2 3 4 5 Five to 10 arc flash explosions occur in electric equipment every day in the United States. This number does not include cases in which
More informationFIXED CHARGE: This is a cost that goes towards making the service available, including
ELECTRICITY BILL COMPONENTS FIXED CHARGE: This is a cost that goes towards making the service available, including installation and maintenance of poles, power lines and equipment, and 24-hour customer
More informationApplication of Four-Pole Circuit Breakers within Data Centers
Application of Four-Pole Circuit Breakers within Data Centers December 2013/AT324 by Frank Waterer, Fellow Engineer, Schneider Electric Engineering Services Make the most of your energy SM Revision #1
More informationARC FLASH CALCULATIONS & LABELING REQUIREMENTS
ARC FLASH CALCULATIONS & LABELING REQUIREMENTS Presented by: Edmund Elizalde EYP Mission Critical Facilities, Inc. Slides by: Lonnie Lindell SKM Systems Analysis, Inc. 1 Agenda NEC 110.16 NFPA 70E IEEE
More informationMINISTERIE VAN ECONOMISCHE ZAKEN GENERAL COST COMPARISON BETWEEN UNDERGROUND CABLES AND O.H. LINE SYSTEMS FOR H.V. TRANSMISSION
MINISTERIE VAN ECONOMISCHE ZAKEN GENERAL COST COMPARISON BETWEEN UNDERGROUND CABLES AND O.H. LINE SYSTEMS FOR H.V. TRANSMISSION REPORT ON NETWORK RELIABILITY ASPECTS OF THE CHOICE LINE VERSUS CABLE FOR
More informationSubstation Grounding Study Specification
Substation Grounding Study Specification Introduction A grounding study is required for name of station, a / / kv substation located in name of location and connected to the following circuits: number
More informationELECTRICAL SAFETY RISK ASSESSMENT
ELECTRICAL SAFETY RISK ASSESSMENT The intent of this procedure is to perform a risk assessment, which includes a review of the electrical hazards, the associated foreseeable tasks, and the protective measures
More informationFACT SHEET. BSES, Delhi - Distribution Network. Power Systems Consultancy from ABB
BSES, Delhi - Distribution Network improve power quality System design for optimal techno-economic distribution network based on current and future load forecast Analysis of existing sub-transmission and
More informationExcitation. www.andritz.com/neptun
Excitation www.andritz.com/neptun 02 NEPTUN Excitation Excitation 3 x 150 MW, Kopswerke II, Austria Dynamics with brain power The excitation system of a synchronous generator makes it possible to supply
More informationPower Quality Standards for Electric Service
Power Quality Standards for Electric Service Effective June 1, 2008 A transition period will exist from June 1 through December 31, 2008 in which installations may be approved and connected as long as
More informationSIZING THE PRIMARY POWER SYSTEM FOR RESISTANCE WELDERS
SIZING THE PRIMARY POWER SYSTEM FOR RESISTANCE S By Jack Farrow, May, 2004 WELDING TECHNOLOGY CORPORATION ABSTRACT Information on how to select the correct size of substation transformer and 480V bus to
More informationT 3000. Substation Maintenance and Commissioning Test Equipment
T 3000 Substation Maintenance and Commissioning Test Equipment Multi function system for testing substation equipment such as: current, voltage and power transformers, all type of protection relays, energy
More informationGuide to the electrical parameter classifications of IEC 60950 and IEC 62368 safety standards
Guide to the electrical parameter classifications of IEC 60950 and IEC 62368 safety standards Abstract This Guide is an informative listing of selected terms and definitions found in IEC Glossary entry
More informationTransfer Equipment Controls
Control Types Manual Transfer Switches Nonautomatic Transfer Switches Automatic Transfer Switches The type of control system for the transfer switch will vary depending on the type of switching equipment
More informationElectrical Power System Fundamentals for Non-Electrical Engineers
Electrical Power System Fundamentals for Non-Electrical Engineers by Steve Mackay EIT Micro-Course Series Every two weeks we present a 35 to 45 minute interactive course Practical, useful with Q & A throughout
More informationBill is the author of 15 papers and lectures on transmission lines and other power system topics.
Transmission Lines Electricity s Highway This talk starts with an explanation of Surge Impedance Loading and demonstrates how it is used for transmission line work. The St. Clair Curve widely used in transmission
More informationThe Application and Benefits of Multi-phase Auto-reclosing
he Application and Benefits of Multi-phase Auto-reclosing etsuya Miyoshi*, Atsushi Kasai* Abstract - In this paper we explain the disadvantages in using single- and three-phase auto-reclosing on double
More informationEmergency Power System Services Industrial UPS, Batteries, Chargers, Inverters and Static Switches
Emergency Power System Services Industrial UPS, Batteries, Chargers, Inverters and Static Switches Downtime Is Not An Option The industrial uninterruptible power supply (UPS) is the foundation of your
More informationETAP Validation Cases and Comparison Results
ETAP Validation Cases and Comparison Results ETAP is Verified and Validated (V&V) against field results, real system measurements, published cases, other programs, and hand calculations in order to ensure
More informationPower management system Reliable and energy efficient
Power management system Reliable and energy efficient Power management systems 2 Power management system With ABB and the worldwide implementations of the power management system, you can rely on engineering
More informationTechnical Electrical Field Service Support. Knowledge + Experience = Power. Field Service
Technical Electrical Field Service Support Knowledge + Experience = Power Field Service WRE Field Service Wismer & Rawlings Electric Ltd. Substation Testing and Commissioning Mission Statement To be recognized
More informationOnline Transformer Insulation Monitoring System BushingGard Product Focus. Maximizing Transformer Uptime and Reliability
Online Transformer Insulation Monitoring System BushingGard Product Focus Maximizing Transformer Uptime and Reliability Critical Energy Transfer... Large power transformers are found around the world at
More informationWhen power interruptions happen.
When power interruptions happen. We know it s never a good time to have your power go out, so we work all year pruning trees and investing in our system to cut down on problems before they start. Outage
More informationTitle 20 PUBLIC SERVICE COMMISSION. Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES. Chapter 02 Engineering
Title 20 PUBLIC SERVICE COMMISSION Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES Chapter 02 Engineering Authority: Public Utility Companies Article, 2-121, 5-101 and 5-303, Annotated Code of Maryland.
More informationRequest for Payment Instructions Wholesale Distribution Access Tariff (WDAT) Attachment I - GIP
Grid Interconnection & Contract Development Request for Payment Instructions Wholesale Distribution Access Tariff (WDAT) Attachment I - GIP Submittal Instructions Prior to submitting your application and
More information