1 Resource Adequacy: Theory and Markets Presented to: Joint SPARC and Markets Committee David B. Patton, Ph.D. President, Potomac Economics April 23, 2014
2 Introduction Potomac Economics is the Independent Market Monitor ( IMM ) for MISO, monitoring the conduct/actions of both participants and MISO to identify: Flaws in market rules that create inefficiencies or gaming opportunities; Efficiency improvements; Market power abuses and manipulation; In addition to this primary scope, we also: Review and evaluate new market rules and design changes; and Support MISO s implementation of its market power mitigation measures. This presentation will focus to two essential market design issues: Resource Adequacy; Interchange with adjacent markets; and External interface pricing.
3 Resource Adequacy Threshold Question: Is the purpose of the MISO markets to provide price signals to facilitate efficient investment, retirement, and maintenance decisions that will satisfy MISO s resource adequacy needs? I believe the answer should be yes because efficient market signals: Will not impede the States planning processes or ability to oversee or facilitate investment by their regulated utilities; Provide valuable economic signals that can assist States and their regulated utilities make the most cost-effective choices; Facilitate efficient capacity imports and low-cost merchant investment; Prevent inefficient exports out of the MISO region; Facilitate a vibrant forward (bilateral contract market); Allow wholesale market revenues to cover a much larger share of utilities capital costs (rather than retail ratepayers); and Ultimately generate substantial savings for the region s consumers due to the effects described above. -3-
4 Market-Based Investment/Retirement Market-based investment in wholesale electricity markets is ultimately facilitated by the markets economic signals, including: Energy and ancillary service net revenues during non-shortages; Energy and ancillary service net revenues during shortages; and Capacity market net revenues; Long-run equilibrium is achieved when the combination of these expected revenues cover entry costs of the marginal resource. Energy-only markets include the first two revenue streams and will generally not satisfy RTOs planning reserve needs. In other words, there is missing money. Capacity markets exist primarily to provide the missing money. -4-
5 Why is There Missing Money in Electricity Markets? Planning reserve requirements exceed levels that an energy-only market would provide, assuming the energy market prices shortages efficiently. Why? The 1 day in 10 year reliability standard implies a value of lost load of $100,000 to $200,000 per MWh Therefore, additional revenues are needed to prompt the higher level of investment needed to satisfy these targets. The higher planning margins result in more supply, which reduces the frequency of shortages (and associated shortage revenues). Real-time prices may not always fully reflect the value of energy because of the effects of the ISO s reliability actions: Committing peaking resources or other generating resources; Curtailing load; and Curtailing exports; -5-
6 Essential Attribute: Capacity Demand Curve Demand for Capacity. Based on the reliability value provided by the capacity. Vertical demand curve indicates that the last MW needed to meet the capacity requirement has extreme value and the first MW of surplus has no value. In reality, each MW of surplus capacity increases reliability, although these reliability increases diminish as the surplus grows. Supply of Capacity. The competitive offer for capacity (i.e., the marginal cost of selling capacity) is generally close to zero because the costs of satisfying the capacity obligations are usually very low. These characteristics cause: Clearing prices to almost always be close to zero. Poor investment signals produced only from shortages that are unpredictable and unstable. -6- P P* Q* Quantity Cleared = Minimum Requirement Capacity Requirement (Vertical Demand Curve) Competitive Supply Stack Q
7 Essential Attribute: Capacity Demand Curve A sloped demand curve reflects that additional capacity above the minimum does have reliability value (which decreases as the excess increases). The price (P*) would be determined by the marginal value of additional capacity as represented by the sloped demand curve, rather than by a supply offer. A sloped demand curve: Provides more efficient prices that reflect the prevailing surplus. Improves price stability, which should facilitate investment by reducing price risk. Reduces incentives to withhold capacity by raising the opportunity costs of withholding (foregone revenues) and decreasing its price effects. -7- P Clearing Price P* Minimum Capacity Requirement Capacity Requirement (Sloped Demand Curve) Q* Quantity Cleared Q
8 Locational Requirements and Zones Transmission constraints cause RTOs planning needs to vary locationally to satisfy: Resource adequacy needs; and Transmission security needs. In order to efficiently facilitate investment (and retirement) decisions, these local needs must by accurately reflected in the capacity market. Prices should dynamically adjust based on the supply and demand that exists in local areas. -8-
9 Questionable Attribute: Forward Procurement Capacity markets vary regarding when capacity must by procured: NYISO (and MISO): Shortly before the operating year or month. New England and PJM: Roughly 3 years in advance. Primary role for the capacity markets, regardless of the procurement timeframe, is to establish a transparent, efficient price for capacity. Such prices facilitate efficient forward contracting and long-term decisions (investment, retirement, and maintenance). Many in the industry confuse RTOs mandatory forward procurement with longer-term forward contracting. They are not substitutes; Bilateral forward contracting remains key under any market design for locking in revenues and facilitating financing of new resources. Mandatory forward procurement has significant potential drawbacks and it premature to determine whether this is desirable attribute. -9-
Preliminary Results of Analysis of the Broader Regional Markets Initiatives
Preliminary Results of Analysis of the Broader Regional Markets Initiatives Presented to: NYISO Management Committee David B. Patton, Ph.D. Potomac Economics April 21, 2010 1 Introduction This presentation
More informationClosing the Gap Between Wholesale and Retail
Closing the Gap Between Wholesale and Retail Transactive Energy Workshop March 28-29 Robert B. Burke GWAC MEMBER & PRINCIPAL ANALYST ISO NEW ENGLAND INC. Disclaimer This presentation represents the thoughts
More informationINDEPENDENT SYSTEM OPERATORS (VI + Access Rules vs. ISO vs. ITSO)
INDEPENDENT SYSTEM OPERATORS (VI + Access Rules vs. ISO vs. ITSO) Paul L. Joskow September 28, 2007 ALTERNATIVE SYSTEM OPERATOR MODELS System operator (SO) is vertically integrated utility (G+T) Functional
More informationPJM Overview and Wholesale Power Markets. John Gdowik PJM Member Relations
PJM Overview and Wholesale Power Markets John Gdowik PJM Member Relations PJM s Role Ensures the reliability of the high-voltage electric power system Coordinates and directs the operation of the region
More information2010 STATE OF THE MARKET REPORT
2010 STATE OF THE MARKET REPORT FOR THE ERCOT WHOLESALE ELECTRICITY MARKETS POTOMAC ECONOMICS, LTD. Independent Market Monitor for the ERCOT Wholesale Market August 2011 TABLE OF CONTENTS Executive Summary...
More informationELECTRIC UTILITY INTEGRATED RESOURCE PLAN (IRP)
ELECTRIC UTILITY INTEGRATED RESOURCE PLAN (IRP) Demand-Side Resources PRESENTED TO THAI ENERGY REGULATORY COMMISSION, OERC, AND UTILITIES DELEGATION Boston, Massachusetts PRESENTED BY ROMKAEW BROEHM MARIKO
More informationPJM LMP Market Overview
PJM LMP Market Overview Andrew Ott Senior Vice President, Markets June 10, 2010 PJM as Part of the Eastern Interconnection 6,038 substations KEY STATISTICS PJM member companies 600+ millions of people
More informationUNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) Coordination Between Natural Gas ) Docket No. AD12-12-000 And Electricity Markets ) ) COMMENTS OF DOMINION RESOURCES SERVICES,
More informationPerformance Metrics. For Independent System Operators And Regional Transmission Organizations
Performance Metrics For Independent System Operators And Regional Transmission Organizations A Report to Congress In Response to Recommendations of the United States Government Accountability Office April
More informationA Capacity Market that Makes Sense
Electricity Journal, 18, 43-54, August/September 2005. A Capacity Market that Makes Sense Peter Cramton and Steven Stoft 1 15 June 2005 Abstract We argue that a capacity market is needed in most restructured
More informationABOUT ELECTRICITY MARKETS. Power Markets and Trade in South Asia: Opportunities for Nepal
ABOUT ELECTRICITY MARKETS Power Markets and Trade in South Asia: Opportunities for Nepal February 14-15, 2011 Models can be classified based on different structural characteristics. Model 1 Model 2 Model
More informationAn Overview of the Midwest ISO Market Design. Michael Robinson 31 March 2009
An Overview of the Midwest ISO Market Design Michael Robinson 31 March 2009 The Role of RTOs Monitor flow of power over the grid Schedule transmission service Perform transmission security analysis for
More informationMULTIPLE CHOICE. Choose the one alternative that best completes the statement or answers the question.
MBA 640 Survey of Microeconomics Fall 2006, Quiz 6 Name MULTIPLE CHOICE. Choose the one alternative that best completes the statement or answers the question. 1) A monopoly is best defined as a firm that
More informationIs It Possible to Charge Market-Based Pricing for Ancillary Services in a Non-ISO Market?
Is It Possible to Charge Market-Based Pricing for Ancillary Services in a Non-ISO Market? Regulation and Operating Reserves 33 rd Eastern Conference Center for Research in Regulated Industry Romkaew P.
More informationUpdate on Northeast Seams Issues. January 9, 2008 NYISO Management Committee Meeting
Update on Northeast Seams Issues January 9, 2008 NYISO Management Committee Meeting Status of Seams Projects Current Deliverables Project 1. Intra-Hour Transaction Scheduling NYISO and ISO-NE have documented
More informationNYISO Demand Response Programs: Enrollment
NYISO Demand Response Programs: Enrollment Donna Pratt Demand Response Market Product Specialist New York Independent System Operator DR-Expo Chicago, Illinois October 16-17, 2007 New York Independent
More informationFERC Workshop on Price Formation: Scarcity and Shortage Pricing, Offer Mitigation, and Offer Caps in RTO and ISO Markets (Docket. No.
FERC Workshop on Price Formation: Scarcity and Shortage Pricing, Offer Mitigation, and Offer Caps in RTO and ISO Markets (Docket. No. AD14-14-000) October 28, 2014 Market Presentation Design Title & Analysis
More information2013 STATE OF THE MARKET REPORT ERCOT WHOLESALE ELECTRICITY MARKETS POTOMAC ECONOMICS, LTD. Independent Market Monitor for the ERCOT Wholesale Market
2013 STATE OF THE MARKET REPORT FOR THE ERCOT WHOLESALE ELECTRICITY MARKETS POTOMAC ECONOMICS, LTD. Independent Market Monitor for the ERCOT Wholesale Market September 2014 TABLE OF CONTENTS Executive
More informationIn the Supreme Court of the United States
NOS. 14-614, 14-623 In the Supreme Court of the United States W. KEVIN HUGHES, et al., Petitioners, v. TALEN ENERGY MARKETING, LLC (F/K/A PPL ENERGYPLUS, LLC), et al., Respondents. CPV MARYLAND, LLC, v.
More informationTHE FERC STANDARD MARKET DESIGN GIGANOPR: RESEARCH NEEDS
THE FERC STANDARD MARKET DESIGN GIGANOPR: RESEARCH NEEDS Presentation by George Gross University of Illinois at Urbana-Champaign Modernizing the National Electric Power Grid NSF Workshop November 18-19,
More informationTHE ECONOMY AT FULL EMPLOYMENT. Objectives. Production and Jobs. Objectives. Real GDP and Employment. Real GDP and Employment CHAPTER
THE ECONOMY AT 29 FULL EMPLOYMENT CHAPTER Objectives After studying this chapter, you will able to Describe the relationship between the quantity of labour employed and real GDP Explain what determines
More informationQuantifying the Amount and Economic Impacts of Missing Energy Efficiency in PJM s Load Forecast
Quantifying the Amount and Economic Impacts of Missing Energy Efficiency in PJM s Load Forecast PREPARED FOR The Sustainable FERC Project PREPARED BY Ahmad Faruqui, Ph.D. Sanem Sergici, Ph.D. Kathleen
More informationNew York's Capacity Market "Demand Curve" Dr. Thomas Paynter CPUC-CEOB-CAISO Installed Capacity Conference San Francisco, CA October 4-5, 2004
New York's Capacity Market "Demand Curve" Dr. Thomas Paynter CPUC-CEOB-CAISO Installed Capacity Conference San Francisco, CA October 4-5, 2004 The New York Independent System Operator (NYISO), like other
More informationUNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) ) ) )
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Independent Market Monitor for PJM v. PJM Interconnection, L.L.C. ) ) ) ) ) ) Docket No. EL14- -000 COMPLAINT AND MOTION TO CONSOLIDATE
More informationNYISO Tariffs: MST Section 5 Control Area Services: Rights and Obligations. NYISO Tariffs. New York Independent System Operator, Inc.
NYISO Tariffs New York Independent System Operator, Inc. NYISO Tariffs Document Generated On: 10/14/2011 Page 1 5.10 NYCA Minimum Installed Capacity Requirement The NYCA Minimum Installed Capacity Requirement
More informationOperator Initiated Commitments in RTO and ISO Markets
Price Formation in Organized Wholesale Electricity Markets Docket No. AD14-14-000 Staff Analysis of Operator Initiated Commitments in RTO and ISO Markets December 2014 For further information, please contact:
More informationUsing Demand Response Programs to Benefit the. PtikJ Patrick J. Oshie, Ohi Commissioner Washington Utilities & Transportation Commission
Using Demand Response Programs to Benefit the Customer and the Utility PtikJ Patrick J. Oshie, Ohi Commissioner i Washington Utilities & Transportation Commission i 1 What is Demand Response? Changes in
More informationPre Test Chapter 3. 8.. DVD players and DVDs are: A. complementary goods. B. substitute goods. C. independent goods. D. inferior goods.
1. Graphically, the market demand curve is: A. steeper than any individual demand curve that is part of it. B. greater than the sum of the individual demand curves. C. the horizontal sum of individual
More informationThe Power Market: E-Commerce for All Electricity Products By Edward G. Cazalet, Ph.D., and Ralph D. Samuelson, Ph.D.
The Power Market: E-Commerce for All Electricity Products By Edward G. Cazalet, Ph.D., and Ralph D. Samuelson, Ph.D. Why not use the Web to buy and sell transmission rights at prices derived from bids
More informationPJM Overview of Markets. Georgian Delegation PUCO Office April 11, 2013
PJM Overview of Markets Georgian Delegation PUCO Office April 11, 2013 1 Agenda Introduction Energy Markets Locational Marginal Pricing - LMP Two Settlement - Day Ahead / Real time Ancillary Services Capacity
More informationEnergy in the Wholesale Market December 5, 2012 1:30 p.m. to 3:30 p.m. Irving, Texas Robert Burke, Principal Analyst ISO New England
Business Models for Transactive Energy in the Wholesale Market December 5, 2012 1:30 p.m. to 3:30 p.m. Irving, Texas Robert Burke, Principal Analyst ISO New England About ISO New England (ISO) Not-for-profit
More informationSingle Electricity Market (SEM) and interaction with EMIR. Central Bank of Ireland
Single Electricity Market (SEM) and interaction with EMIR Central Bank of Ireland 11 th July 2014 About EAI Overview of SEM and its Participants The market is a gross mandatory pool and consists of generators
More informationThe Locational Based Marginal Prices ( LBMPs or prices ) for Suppliers and Loads in
17.1 LBMP Calculation Method The Locational Based Marginal Prices ( LBMPs or prices ) for Suppliers and Loads in the Real-Time Market will be based on the system marginal costs produced by either the Real-
More informationMMU Comments on Analysis Group Findings Regarding the FCM Lock-In Provision
MMU Comments on Analysis Group Findings Regarding the FCM Lock-In Provision Pallas LeeVanSchaick NYISO Market Monitoring Unit Potomac Economics Installed Capacity Working Group February 25, 2015 Introduction
More informationMarketing Concept. The Marketing Concept
Marketing Concept Ted Mitchell is a philosophy of business competition. We need to know what it is, what it assumes, and what it implies. What is it? holds that the key to achieving organizational goals
More informationPresentation for The National Commission for Energy State Regulation of Ukraine
Presentation for The National Commission for Energy State Regulation of Ukraine Todd Keech Laura Walter PJM Interconnection June 17, 2014 What is PJM? 1 What is PJM? ISO RTO Map Part of Eastern Interconnection
More informationUNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Southwest Power Pool, Inc. ) ) Docket No. ER12-1179-000 MOTION FOR LEAVE TO INTERVENE AND PROTEST OF THE ELECTRIC POWER SUPPLY ASSOCIATION
More informationEvaluating Energy Offer Cap Policy Market Roadmap ID: 42 Issues List: MR042. Market Subcommittee (MSC) May 3, 2016
Evaluating Energy Offer Cap Policy Market Roadmap ID: 42 Issues List: MR042 Market Subcommittee (MSC) May 3, 2016 Purpose Purpose and Key Takeaways Review proposed FERC Energy Offer Cap rules, and potential
More informationUtilities Policy. Using forward markets to improve electricity market design q. Lawrence M. Ausubel, Peter Cramton * abstract
Utilities Policy 18 (2010) 195e200 Contents lists available at ScienceDirect Utilities Policy journal homepage: www.elsevier.com/locate/jup Using forward markets to improve electricity market design q
More informationDemand Response in Capacity and Electricity Markets: What Role Can and Should It Play?
Demand Response in Capacity and Electricity Markets: What Role Can and Should It Play? Professor Joel B. Eisen Austin Owen Research Fellow University of Richmond School of Law Austin Electricity Conference
More informationConvergence Bidding Tutorial & Panel Discussion
Convergence Bidding Tutorial & Panel Discussion CAISO June 13, 2006 Joe Bowring PJM Market Monitor www.pjm.com Convergence Basics Day-Ahead Market basics Day-Ahead and Real-Time Market interactions Increment
More informationPRICE FORMATION IN ISOs AND RTOs PRINCIPLES AND IMPROVEMENTS
Economic Consulting PRICE FORMATION IN ISOs AND RTOs PRINCIPLES AND IMPROVEMENTS SUSAN L. POPE 1 October 2014 Executive Summary Assessment of concerns about price formation and prompt action to address
More informationImpact of Coal Plant Retirements on the Capacity and Energy Market in PJM
Impact of Coal Plant Retirements on the Capacity and Energy Market in PJM by Neil Copeland Debashis Bose Black & Veatch INTRODUCTION It has recently been observed that U.S. electricity providers are announcing
More informationMULTIPLE CHOICE. Choose the one alternative that best completes the statement or answers the question.
Chapter 11 Monopoly practice Davidson spring2007 MULTIPLE CHOICE. Choose the one alternative that best completes the statement or answers the question. 1) A monopoly industry is characterized by 1) A)
More informationVirtual Transactions in the PJM Energy Markets
PJM Interconnection October 12, 2015 This page is intentionally left blank. PJM 2015 www.pjm.com i P age Table of Contents Executive Summary... 1 Background... 3 Synopsis of the Virtual Transactions...
More informationCAPACITY MECHANISMS IN EU POWER MARKETS
CAPACITY MECHANISMS IN EU POWER MARKETS Can we progress to bilateral energy options? Simon Bradbury Ultimately, European renewable targets mean that prices and dispatch patterns will be dictated by wind
More informationUNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Price Formation in Energy and ) Docket No. AD14-14-000 Ancillary Services Markets Operated ) By Regional Transmission Organizations
More informationMULTIPLE CHOICE. Choose the one alternative that best completes the statement or answers the question.
MULTIPLE CHOICE. Choose the one alternative that best completes the statement or answers the question. 1) Firms that survive in the long run are usually those that A) remain small. B) strive for the largest
More information2016/2017 RPM Base Residual Auction Results
Executive Summary The 2016/2017 Reliability Pricing Model (RPM) Base Residual Auction (BRA) cleared 169,159.7 MW of unforced capacity in the RTO. Accounting for load and resource commitments under the
More information1. Supply and demand are the most important concepts in economics.
Page 1 1. Supply and demand are the most important concepts in economics. 2. Markets and Competition a. Market is a group of buyers and sellers of a particular good or service. P. 66. b. These individuals
More informationCALIFORNIA ISO. Pre-dispatch and Scheduling of RMR Energy in the Day Ahead Market
CALIFORNIA ISO Pre-dispatch and Scheduling of RMR Energy in the Day Ahead Market Prepared by the Department of Market Analysis California Independent System Operator September 1999 Table of Contents Executive
More informationDemand, Supply and Elasticity
Demand, Supply and Elasticity CHAPTER 2 OUTLINE 2.1 Demand and Supply Definitions, Determinants and Disturbances 2.2 The Market Mechanism 2.3 Changes in Market Equilibrium 2.4 Elasticities of Supply and
More informationAggregate Demand and Aggregate Supply Ing. Mansoor Maitah Ph.D. et Ph.D.
Aggregate Demand and Aggregate Supply Ing. Mansoor Maitah Ph.D. et Ph.D. Aggregate Demand and Aggregate Supply Economic fluctuations, also called business cycles, are movements of GDP away from potential
More informationD) surplus; negative. 9. The law of one price is enforced by: A) governments. B) producers. C) consumers. D) arbitrageurs.
1. An open economy is one in which: A) the level of output is fixed. B) government spending exceeds revenues. C) the national interest rate equals the world interest rate. D) there is trade in goods and
More informationA Comparison of PJM s RPM with Alternative Energy and Capacity Market Designs
A Comparison of PJM s RPM with Alternative Energy and Capacity Market Designs September 2009 Johannes Pfeifenberger Kathleen Spees Adam Schumacher Prepared for PJM Interconnection, L.L.C. TABLE OF CONTENTS
More informationGenerator Optional. Timeline including the next steps. A practical example. Potential benefits of OFA? Key implications. How might OFA work?
Generator Optional Firm Access Rights Australian Energy Market Commission announces terms of reference for detailed design work On the 6 March 2014, the Australian Energy Market Commission (AEMC) released
More informationPerspective on Trends in U.S. Electricity Markets and Nuclear Power Plant Shutdowns. September 2013
Perspective on Trends in U.S. Electricity Markets and Nuclear Power Plant Shutdowns September 2013 Nuclear Plant Shutdowns: The Situation Five reactors shut down Four in 2013 One at the end of 2014 Crystal
More informationMULTIPLE CHOICE. Choose the one alternative that best completes the statement or answers the question.
MBA 640, Survey of Microeconomics, Quiz #4 Fall 2006 Name MULTIPLE CHOICE. Choose the one alternative that best completes the statement or answers the question. 1) In the short run, A) there are no variable
More informationThe Materials Contained Are Property of GP Renewables & Trading, LLC and are considered proprietary. This is not for distribution.
The Materials Contained Are Property of GP Renewables & Trading, LLC and are considered proprietary. This is not for distribution. 1 Wholesale Power 101 Maximizing Asset Value & Minimizing Risk 2 Facts
More informationGeneration and Transmission Interconnection Process
PJM Manual 14A Generation and Transmission Interconnection Process Revision: 18 Effective Date: January 28, 2016 Prepared by Planning Division Generation Interconnection Department PJM 2016 Table of Contents
More informationsink asset load power pool ISO pool participant bids operating constraints ancillary service declarations
G1 DEFINITIONS In the ISO rules: acceptable operational reason means with respect to a source asset, any one or more of the following: i) a circumstance related to the operation of the generating asset
More informationA Guide to Inform Institutions about Participation in PJM s Demand Response Programs
A Guide to Inform Institutions about Participation in PJM s Demand Response Programs John Soden & Robin Aldina Dr. Dalia Patiño-Echeverri, Advisor May 2013 Masters Project submitted in partial fulfillment
More informationMemo INTRODUCTION UNDER-SCHEDULING
California Independent System Operator Memo To: ISO Board of Governors From: Greg Cook, Senior Policy Analyst/Market Surveillance Committee Liaison CC: ISO Officers Date: September 28, 2000 Re: Management
More informationPrice Responsive Demand for Operating Reserves in Co-Optimized Electricity Markets with Wind Power
Price Responsive Demand for Operating Reserves in Co-Optimized Electricity Markets with Wind Power Zhi Zhou, Audun Botterud Decision and Information Sciences Division Argonne National Laboratory zzhou@anl.gov,
More informationElectricity Market Design: The Good, the Bad, and the Ugly
Published in the Proceedings of the Hawaii International Conference on System Sciences, January, 2003. Electricity Market Design: The Good, the Bad, and the Ugly Peter Cramton University of Maryland cramton@umd.edu
More informationPractice Questions Week 8 Day 1
Practice Questions Week 8 Day 1 Multiple Choice Identify the choice that best completes the statement or answers the question. 1. The characteristics of a market that influence the behavior of market participants
More informationMULTIPLE CHOICE. Choose the one alternative that best completes the statement or answers the question.
Suvey of Macroeconomics, MBA 641 Fall 2006, Final Exam Name MULTIPLE CHOICE. Choose the one alternative that best completes the statement or answers the question. 1) Modern macroeconomics emerged from
More informationProblem Set #5-Key. Economics 305-Intermediate Microeconomic Theory
Problem Set #5-Key Sonoma State University Economics 305-Intermediate Microeconomic Theory Dr Cuellar (1) Suppose that you are paying your for your own education and that your college tuition is $200 per
More informationApril 29, 2010. The ISO sent its proposed tariff amendment to the Commission via overnight delivery on December 23, 2009.
California Independent System Operator Corporation April 29, 2010 VIA OVERNIGHT DELIVERY The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC
More information2014 STATE OF THE MARKET REPORT FOR THE NEW YORK ISO MARKETS
2014 STATE OF THE MARKET REPORT FOR THE NEW YORK ISO MARKETS By: David B. Patton, Ph.D. Pallas LeeVanSchaick, Ph.D. Jie Chen, Ph.D. Market Monitoring Unit for the New York ISO May 2015 2014 State of the
More informationprocess is usually performed with an additional SCUC and has been the natural fit for the use of wind power forecasts. Currently, however, since this
Impact of Variable Renewable Energy on US Electricity Markets By J.C. Smith, Stephen Beuning, Henry Durrwachter, Erik Ela, David Hawkins, Brendan Kirby, Warren Lasher, Jonathan Lowell, Kevin Porter, Ken
More informationWHITE PAPER THE NIAGARA FRAMEWORK A PLATFORM FOR DEMAND RESPONSE
WHITE PAPER WP THE NIAGARA FRAMEWORK A PLATFORM FOR DEMAND RESPONSE The Niagara Framework A Platform for Demand Response Executive Summary A PLATFORM FOR DEMAND REPONSE The Federal Energy Regulatory Commission
More informationMonopolistic Competition
In this chapter, look for the answers to these questions: How is similar to perfect? How is it similar to monopoly? How do ally competitive firms choose price and? Do they earn economic profit? In what
More informationMarket Solutions to Loop Flow
Market Solutions to Loop Flow Robert Pike Director, Market Design New York Independent System Operator Business Issues Committee September 9, 2009 1 Agenda Background Recommendation Next Steps Solution
More informationChapter 04 Firm Production, Cost, and Revenue
Chapter 04 Firm Production, Cost, and Revenue Multiple Choice Questions 1. A key assumption about the way firms behave is that they a. Minimize costs B. Maximize profit c. Maximize market share d. Maximize
More informationEnergy Ventures Analysis 1901 N. Moore St. Arlington, VA 22209 (703) 276 8900
T H E I M P A C T O F E A R L Y C O A L R E T I R E M E N T S O N K E Y P O W E R M A R K E T S ISO = 46.6% Prepared for: National Mining Association Washington, DC Northwest = 41.3% MISO = 36.8% NYISO
More informationChapter 22 The Cost of Production Extra Multiple Choice Questions for Review
Chapter 22 The Cost of Production Extra Multiple Choice Questions for Review 1. Implicit costs are: A) equal to total fixed costs. B) comprised entirely of variable costs. C) "payments" for self-employed
More informationPJM Interconnection LLC Regional Transmission Organization (RTO)
PJM Interconnection LLC Regional Transmission Organization (RTO) ComEd Generator Interconnection Meeting October 2015 William Patzin PJM Infrastructure Coordination October 2015 PJM 2013 Nine Major North
More informationA new electricity market for Northern Ireland and Ireland from 2016 - Integrated Single Electricity Market (I-SEM)
A new electricity market for Northern Ireland and Ireland from 2016 - Integrated Single Electricity Market (I-SEM) Non-technical summary High level design Draft Decision Paper SEM -14-047 June 2014 1 INTRODUCTION
More informationEURELECTRIC presentation. EURELECTRIC contribution to a reference model for European capacity markets. DG COMP workshop 30 June 2015
EURELECTRIC presentation EURELECTRIC contribution to a reference model for European capacity markets DG COMP workshop 30 June 2015 EURELECTRIC believes that energy, flexibility and capacity are all needed
More informationHow To Understand The Benefits Of The French Power Market Plan
Why Did the US (Mostly) Go With LMP? Benefits of Flow Based Allocation Benjamin F. Hobbs EPRG, University of Cambridge, UK DoGEE, Johns Hopkins University, USA Market Surveillance Committee, California
More informationErrata to BPA POWER PRODUCTS CATALOG September 1999. Factoring Product Availability section remove second sentence. See attached replacement page.
Errata to BPA POWER PRODUCTS CATALOG September 1999 Page 16: Page 17: Page 24: Page 25: Factoring Product Availability section remove second sentence. See attached replacement page. Detailed Description:
More informationConcepts and Experiences with Capacity Mechanisms
Concepts and Experiences with Capacity Mechanisms Manuel Baritaud, International Energy Agency Conference Capacity Mechanisms: Experiences in Various European Countries Bundesministerium fur Wirtschaft
More informationHigh Penetration of Distributed Solar PV Generation
High Penetration of Distributed Solar PV Generation Lessons Learned from Hawaii September 30, 2014 Discussion Overview Solar PV penetrations trends in Hawaii Lessons learned from Hawaii s high penetration
More informationEuropean Commission Public Consultation on GENERATION ADEQUACY, CAPACITY MECHANISMS AND THE INTERNAL MARKET IN ELECTRICITY
February 2013 European Commission Public Consultation on GENERATION ADEQUACY, CAPACITY MECHANISMS AND THE INTERNAL MARKET IN ELECTRICITY Reply from NASDAQ OMX The NASDAQ OMX Group, Inc. delivers trading,
More informationComparison of Market Designs
Public Utility Commission of Texas Comparison of Market Designs Market Oversight Division Report Project 26376, Rulemaking Proceeding on Wholesale Market Design Issues in the Electric Reliability Council
More informationWhat is hourly pricing and what does it mean for you? Customer Meetings May 2006
What is hourly pricing and what does it mean for you? Customer Meetings May 2006 Catherine McDonough Project Manager 1 (315) 428-5641 Background In 1998, National Grid (NG) extended hourly pricing to our
More informationICAP/UCAP Overview. Aaron Westcott Awestcott@nyiso.com 518 356 7657. If possible, Please mute your phones Please do not use the hold button.
ICAP/UCAP Overview Aaron Westcott Awestcott@nyiso.com 518 356 7657 If possible, Please mute your phones Please do not use the hold button. Agenda What is ICAP/UCAP? How are ICAP and UCAP calculated? How
More informationCourse notes for EE394V Restructured Electricity Markets: Locational Marginal Pricing
Course notes for EE394V Restructured Electricity Markets: Locational Marginal Pricing Ross Baldick Copyright c 2015 Ross Baldick www.ece.utexas.edu/ baldick/classes/394v/ee394v.html Title Page 1 of 29
More informationDemand Response Programs: Lessons from the Northeast
Demand Response Programs: Lessons from the Northeast Charles Goldman E. O. Lawrence Berkeley National Laboratory CAGoldman@lbl.gov Mid Atlantic Demand Response Initiative Meeting Baltimore MD December
More informationCHAPTER 7: AGGREGATE DEMAND AND AGGREGATE SUPPLY
CHAPTER 7: AGGREGATE DEMAND AND AGGREGATE SUPPLY Learning goals of this chapter: What forces bring persistent and rapid expansion of real GDP? What causes inflation? Why do we have business cycles? How
More informationReal-Time Pricing and Demand Side Participation in Restructured Electricity Markets
Real-Time Pricing and Demand Side Participation in Restructured Electricity Markets Robert H. Patrick Frank A. Wolak Graduate School of Management Department of Economics Rutgers University Stanford University
More informationCameron ECON 100: FIRST MIDTERM (A) Winter 01
Cameron ECON 100: FIRST MIDTERM (A) Winter 01 Answer all questions in the space provided on the exam. Total of 40 points (and worth 22.5% of final grade). Read each question carefully, so that you answer
More informationSecurity of electricity supply
Security of electricity supply Definitions, roles & responsibilities and experiences within the EU Thomas Barth Chairman of Energy Policy & Generation Committee EURELECTRIC Outline Security of Supply a
More informationFREQUENTLY ASKED QUESTIONS
1. WHY 3DOM NOW? As leaders in the retail energy business, we are committed to being a category creator and innovator in the energy industry. We are always researching and tracking trends to develop product
More information152 FERC 61,218 DEPARTMENT OF ENERGY FEDERAL ENERGY REGULATORY COMMISSION. 18 CFR Part 35. [Docket No. RM15-24-000]
152 FERC 61,218 DEPARTMENT OF ENERGY FEDERAL ENERGY REGULATORY COMMISSION 18 CFR Part 35 [Docket No. RM15-24-000] Settlement Intervals and Shortage Pricing in Markets Operated by Regional Transmission
More informationScarcity Pricing. Draft Compliance Filing Language. CAISO Fourth Replacement Tariff. November 10, 2009
CAISO Fourth Replacement Tariff November 10, 2009 * * * 27.1.2 Ancillary Service Prices. 27.1.2.1 Ancillary Service Marginal Prices. As provided in Section 8.3, Ancillary Services are procured and awarded
More informationWorkshop B. 11:15 a.m. to 12:30 p.m.
Workshop B Advanced Energy Management Tools: Benefitting from the Competitive Electricity Marketplace Beyond the Fixed Rate & Key Issues to Understand when Comparing Electricity Quotes 11:15 a.m. to 12:30
More informationArticle 7: Supporting innovative electricity storage with federal and state policy
Scope: This article describes how policies and regulations affect the deployment of innovative technology by electric utilities in states with regulated and deregulated electricity markets. For the full
More informationThe Circular Flow of Income and Expenditure
The Circular Flow of Income and Expenditure Imports HOUSEHOLDS Savings Taxation Govt Exp OTHER ECONOMIES GOVERNMENT FINANCIAL INSTITUTIONS Factor Incomes Taxation Govt Exp Consumer Exp Exports FIRMS Capital
More information