Aviation Authority Capital Improvement Program Project Status Report

Size: px
Start display at page:

Download "Aviation Authority Capital Improvement Program Project Status Report"

Transcription

1 Aviation Authority Capital Improvement Program Project Status Report June 2015 Prepared by Planning and Development and Development Program Services

2 Capital Improvement Project Status Report Overview The Capital Improvement Project Status Report is updated will be posted on the Authority s website on a monthly basis. The Capital Improvement Project Status Report is organized into following categories: I. Projects in Planning 1 II. Projects in Design.. 4 III. Projects Undergoing Construction / Implementation 10 IV. Projects Substantially Complete 18 V. Active Projects Spreadsheet and the Substantially Complete Spreadsheet 25 VI. Five-Year Capital Improvement Program Outlook 34 The Capital Improvement Project Status Report consists of specific information for each project, including the project title, estimated costs, designer, contractor, airport, project description, a project update, and significant dates according to the latest schedule. The Active Projects Spreadsheet mirrors the projects listed within sections I through IV of the Capital Improvement Project Status Report and contains specific project details related to contract or agreement amounts, approved change orders or amendments, DBE or W/MBE target and achievement amounts. Projects within the Substantially Complete section will be shown for one month only. The Substantially Complete spreadsheet will show all projects in the current fiscal year which achieved Substantial Completion. The spreadsheet provides additional information including the substantial completion date, an estimate of the final costs, and a comparison to the current budget. Projects which are being reported on for the current month are highlighted in yellow on the spreadsheet. The Five-Year Capital Improvement Program Outlook category consists of spreadsheets listing anticipated projects and estimated costs for the period The estimated project cost includes, initial in-house planning, advertising, design development, construction, construction management, construction contract administration, permitting and miscellaneous printing, copying and distribution costs and any other components associated with completion of the work. Schedules and budgets are updated during the course of the project. Any changes will be reflected in the next posting of the report. The runway designations for Airport and Peter O. Knight Airport changed effective January 13, Some project titles containing runway designations within their titles may not reflect these changes which are listed below: Peter O. Knight Airport runway 3/21 is now runway 4/22 and runway 17/35 is now runway 18/36. Airport runway 9/27 is now runway 10/28; runway 18R/36L is now runway 1L/19R and runway 18L/36R is now runway 1R/19L. Please call Dan Johnson at (813) or DGJohnson@Tampaairport.com if you have any questions regarding the Capital Improvement Program Status Report. i

3 Capital Improvement Project Status Report I. Projects in Planning June 2015 # Baggage Handling Systems Servers Upgrade/Enhancement FDOT F.M. # Substantial Completion: September 2016 Current : $1,303,900 NA Project Description: The scope of this project includes replacing all end of life computer equipment being used in the Baggage Handling System. Project Status: This project is currently on hold pending the TSA baggage consolidation project to move forward, as this project comes in at the end of the consolidation project. # Airfield Pavement Rehabilitation FDOT F.M. # Substantial Completion: May 2016 Current : $2,582,200 Kimley-Horn & Associate Project Description: The scope of this project is to design the rehabilitation of the existing Taxiway E north of Taxiway J and connector taxiways to Runway 1R-19L. Work will also include the renovation of Taxiways G, N-1 & S as well as the replacement of the connector taxiways to the FBO apron and rehabilitation of the apron itself. The reconstruction of Taxiway N at Runway 10 and the remarking of Taxiways are also included. Project Status: The agreement with the selected design firm, Kimley-Horn, is scheduled for the August Board meeting. # Perimeter Security Study and Enhancement Substantial Completion: June 2016 Current : $1,000,000 RS&H Project Description: The scope of this project is to study and enhance the perimeter security around the entire Air Operation Area (AOA). Project Status: fencing. The consultant has submitted a conditions assessment report on the perimeter security 1

4 # General Aviation Airports Master Plan Update 2014 FDOT F.M. # , F.M , F.M Substantial Completion: October 2015 Current : $955,500 Michael Baker Jr. Inc. Plant City, Peter O. Knight, & Tampa Executive Project Description: The scope of this project includes updating forecasts and re-evaluating demand and capacity recommended improvements that were implemented since the last master plan. In addition, the future phasing of development requirements for existing facilities will be identified and on-airport land use recommendations will be re-evaluated to determine the highest and best use of the airport properties. Once aviation related facility requirements have been identified, it is the goal of the Authority to maximize the appeal and dynamics of each airport and further identify resources necessary to capture defined markets to make each GA Airport self-sustaining. Project Status: The consultant finished the alternatives analysis and recommended a development alternative for each GA airport. Following staff approval, the consultant refined the recommended alternatives and continued to develop the Airport Layout Plans (ALPs) for all three airports. The consultant has begun to develop a financial plan for each recommended alternatives and continue to work on a business plan to supplement the information in each Master Plan. The recommended alternatives were presented to the public at three public meetings on May 19, May 28, and June 4, The project schedule has been updated for additional coordination and longer FAA review times. # Structural & Pavement Inspection & Rehabilitation FDOT F.M. # , F.M , F.M Substantial Completion: June 2015 Current : $1,567,300 RS&H Project Description: The scope of this project is to assure the structural integrity of the facilities and airfield pavement by first inspecting and then by providing the design and implementation for the repairs as required. Project Status: Final copies of the inspection reports have been received and reviewed. Based on the report a number of roadways and airfield pavements are going to be rehabilitated under this project. The consultant is working on the required work order for this design. 2

5 # HCAA Enterprise Resource Planning and Analytics Program Substantial Completion: February 2017 Current : $9,324,700 KPMG Project Description: The scope of this project is to perform an in-depth needs assessment and analysis on the challenges and desired capabilities around business function automation, cross functional integration, enterprise level reporting and dashboards, unified data modelling and elastic infrastructure capacity. The results of the assessment will be evaluated by the Authority and implemented in several releases. Project Status: The Human Capital Management project has completed the Phase 1 Systems Integration Testing (SIT) and is on schedule for Phase 1 Go-live in August The Business Intelligence project (VP binder and Passenger Analytics reporting) was delayed due to technical issues and is now scheduled with an estimated completion of August # Common/Shared Use Passenger Systems (C/SUPPS) Phase 2 Design Substantial Completion: May 2017 Current : $422,200 RS&H Project Description: The scope of this project provides the design for the continuation of C-SUPPS Phase 1 for the campus wide capability to provide C/SUPPS at an additional 10 gates at Airsides A, E, C, and F, along with 19 supporting ticket counters and Airline operational space. Project Status: RS&H is currently preparing a work order with an anticipated project design start date of September # Common Use Self Service Design Substantial Completion: May 2017 Current : $358,400 RS&H Project Description: The scope of this project provides the design for Common Use Self-Service (CUSS) at TPA s new ConRAC. CUSS allows for passengers to check-in, print a boarding pass, print baggage tags, checkin baggage, change a reservation without needing to go to the airline ticket counter, or interact with airline personnel. A single CUSS kiosk can be used by several different participating airlines and provides an easier and faster passage through the airport by the passenger. During the design phase of this project the actual system functions to be performed (i.e. boarding pass printing, bag tag printing, etc.) will be determined along with the actual number of kiosks, initial and ultimate. Only the initial number of kiosks will be provided, up to 20. Additionally, this project will provide the infrastructure, software, hardware, configuration, airline interfaces for the CUSS kiosks. Project Status: The project design start has been deferred to FY16 to allow the overall project design and construction schedule to more effectively align with the construction schedule and construction completion of the ConRAC facility. 3

6 II. Projects in Design # Consolidated Rental Car Facility Phase 1 Design Substantial Completion: October 2017 Current : $4,500,000 Design-Builder: Austin Commercial, L.P. Project Description: The scope of this project is to study the existing rental car facilities, customer service levels, existing and projected demand, and developing alternative design to serve future demand, including estimated cost to implement. The intent of this project is to provide 15% schematic design for the ConRAC. Project Status: The 15% Schematic Design was submitted on June 13, # Site Rehabilitation Substantial Completion: June 2019 Current : $1,210,100 CB&I Project Description: The project utilizes the Florida Department of Environmental Protection s riskbased corrective action provisions to address sites with soil and groundwater impacts. Project Status: The Authority is issuing work orders to the general environmental consultant for engineering work required to achieve site rehabilitation. In May 2015, a work order was issued to CB&I to complete the design of a soil source removal project for the former Hertz arsenic site. The 30% design is due in August # Airport Support Facilities - Fence Substantial Completion: TBD Current : $325,400 RS&H Project Description: Installation of roadway and fence around the Police firing range to provide flexibility in secure and non-secure side facility access. Project Status: This project has been deferred. 4

7 # Main Terminal Level Expansion & Concession Redevelopment Program Phase 1 Substantial Completion: February 2015 Current : $3,314,500 Atkins North America, Inc. Project Description: The scope of this project is to develop design criteria for expansion of the transfer level of the main terminal to accommodate an expanded concession program and to increase circulation space for higher passenger levels. The project also includes complete design for concession support facilities including a new receiving and distribution warehouse, storage and back of house in the main terminal and airsides. Project Status: All design work for is complete. Atkins is performing Construction Administration on the new Concessions Receiving and Distribution Warehouse project. # Main Terminal Shuttle Lobby Automation Substantial Completion: TBD Current : $1,569,200 Design-Builder: Skanska Project Description: The scope of this project is to evaluate the automation of the main terminal shuttle lobby entrances. Project Status: The design builder has provided a recommended solution for the project. The construction of this project is on hold pending further analysis. # Electronic Airport Layout Plan (e-alp) AIP # & FDOT F.M. # Substantial Completion: November 2015 Current : $2,000,000 AECOM Project Description: The scope of this project is to provide an electronic Airport Layout plan (ealp) for the FAA, prepare a traditional Airport Layout Plan (ALP), and conduct and prepare a Safety Risk Management Document (SRMD). Information collected under the Airports Geographic Information System (AGIS) will be used to populate the FAA s e-alp and the Airport s Interactive Airport Layout Plan (ialp) system. An additional element of the project is to update the Exhibit A property map, perform a boundary survey and provide title searches, as required, for a number of parcels purchased since Project Status: The mapping and attributing of planned data is currently in process for development of the ealp. Additional studies were needed for the east airfield taxiway development and 62.5:1 Zoning Surface. The traditional ALP, including the Exhibit A Property Map, was submitted to FAA on May 15,

8 # Commercial Real Estate Development Preliminary Planning & Design Substantial Completion: May 2016 Current : $2,600,000 Stantec Inc. Project Description: The scope of this project is to assist the Authority with investigating the possibility of a multi-phase, multi-year plan to subdivide and develop the airport s available/underutilized properties for future facilities in order to meet demand forecast for commercial real estate. Project Status: The scope of this project completed analysis, feasibility, and assessment of the commercial parcels, completed an evaluation regarding MRO development and prepared a conceptual plan for the commercial portions of the Gateway Area and has provided recommendations. # Checked Baggage System Upgrades & Optimization Construction Substantial Completion: September 2017 Current : $54,498,192 Design-Builder: Skanska Project Description: The scope of this project will provide for the final design and construction of the checked baggage system upgrades and optimization. The project includes all necessary facility modifications required for the reconstruction and optimization of the Checked Baggage Inspection System (CBIS) to include changes to baggage conveyors systems, programming, mechanical, plumbing, electrical, structural, telecommunications, and other infrastructure as necessary. The existing Explosive Detection System (EDS) units will be removed and replaced with new TSA provided EDS units within a reconfigured CBIS. The project will also encompass any necessary modifications to the Checked Baggage Resolution Areas and the On Screen Resolution Room. Project Status: The 30% design package was delivered on May 31, Due to budget constraints the TSA requested a revised 30% design. Development of the alternative design concepts are underway and will be complete in July. # Airside E Boarding Level and Boarding Bridge Carpet Replacement Substantial Completion: June 2016 Current : $1,446,600 RS&H Project Description: The scope of this project is to remove and replace the boarding level and boarding bridge carpet throughout Airside E due to end of its useful life. Project Status: The project is in bidding phase and the bids are due in October

9 # & # Replace Parking Revenue Control System Phase I & Phase II Substantial Completion: July 2016 Current : $13,885,400 Design-Builder: Manhattan Construction Project Description: The scope of the project will develop and deploy a new Parking, Access, Revenue Control System (PARCS) to consolidate all relevant parking and commercial vehicle operations into one fully functional management platform. Included in the project scope is a parking count by level system, license plate recognition, LED signage integration, SunPass Plus, and reconfiguration of the exit plaza for short and long term parking. Project Status: The design builder has completed 60% design and has bid the project for GMP development. The initial Part 2 contract was awarded at the May Board meeting to provide for the PARCS software and initial equipment, including installation of the test lanes at the Economy Garage. The 90% design is in progress based on the selected PARCS vendor. The design-builder is developing their proposal for the Supplement Part 2 contract, which is scheduled for award at the September Board meeting. # Long Term Parking Garage Levels 3, 4 & 5 Lighting Fixtures Replacement FDOT F.M # & Substantial December Completion: 2016 Current : $2,275,300 RS&H Tampa International Project Description: The scope of this project is to replace the outdated fixtures on level 3, 4, and 5 in the Long Term Parking Garage to provide more security and save maintenance costs. Project Status: The 100% design review meeting was held and due to other projects being done in the garage at this time the project has been placed on hold. # Short Term Parking Garage Level 7 Rehabilitation FDOT F.M. # & Substantial Completion: June 2016 Current : $2,998,000 RS&H Project Description: The scope of this project is to rehabilitate Level 7 and other areas in the Short Term Parking Garage (STPG) in order to extend the useful life. Project Status: The 90% design plans and cost estimate was submitted on June 28, 2015, and the 100% design is due in August

10 # Long Term Parking Garage Level 5 and Helix Rehabilitation Substantial Completion: December 2016 Current : $2,577,100 RS&H Project Description: The scope of this project is to rehabilitate Level 5 of the Long Term Parking Garage (LTPG) in order to extend the useful life. Project Status: The design kick off meeting was held on May 28, 2015 and the 30% design is due in July # Building #432 Roof Rehabilitation Substantial Completion: December 2015 Current : $263,900 RS&H Tampa International Project Description: The scope of this project is to replace a portion of the roof for Building #432 in order to extend the useful life. Project Status: The 100% design submittal is due in July. # Petroleum Storage Systems Refurbishment FDOT F.M. # Substantial Completion: February 2016 Current : $566,400 CB&I, Tampa Executive, Peter O. Knight & Plant City Project Description: The scope of this project is to refurbish various petroleum storage systems and pollution control devices in order to extend the useful life. Project Status: The 90% design submittal was received in June 2015 and the 100% design is due in July

11 # Asphalt Pavement Rehabilitations Tug Tunnel Drives & Hoover Blvd. Substantial Completion: April 2016 Current : $881,300 RS&H Project Description: The scope of this project is to rehabilitate and repair the existing asphalt pavements at various areas within the Tug Tunnel Drives and Hoover Blvd. in order to extend the useful life. Project Status: The construction contract for the project was awarded at the June 2015 Board meeting, and construction is expected to begin in July. # Refurbish Airside A Shuttle Superstructure Substantial Completion: December 2016 Current : $2,799,000 Design-Builder Skanska Project Description: The scope of this project is to refurbish and repaint the Airside A shuttle bridge superstructure in order to extend the useful life. Project Status: The Part II Supplement contract was awarded at the June 2015 Board meeting and construction is anticipated to begin in July # Seawall Rehabilitation Substantial Completion: April 2016 Current : $464,900 RS&H Peter O. Knight Project Description: The scope of this project is to rehabilitate sections of the existing seawall to prevent further erosion. Project Status: The final design was received on June 5, 2015 and the bidding will begin in July. # South Terminal Support Area (STSA) Roadway Improvements FDOT F.M. # Substantial Completion: October 2017 Current : $25,711,299 Design-Builder: Kimmins Contracting Corp Project Description: The scope of this project is to reconstruct all roadways in the STSA to support the new ConRAC, including relocating a section of the Bessie Coleman Service Road. Project Status: The 30% design continued through June and the 60% percent design plans are due in July

12 III. Projects Undergoing Construction / Implementation # ConRAC Substantial Completion: October 2017 Current : $323,543,613 Design- Builder: Austin Commercial, L.P. Project Description: The scope of this project is to construct a new consolidated rental car facility (ConRAC) on a 60 acre parcel of property located just south of the Economy Garage in the South Terminal Support Area. The ConRAC will be a three level, approximately 4,400 ready return space facility with a multi-level QTA. The plan also includes an adjacent surface lot to accommodate vehicle storage and rental car maintenance facilities. Project Status: The final Part II Supplemental contract was awarded at the May 2015 Board meeting. The construction of service centers 1, 2, and 3 associated site work and roadways are underway. Completion of services centers 1 and 2 is expected in September # Main Terminal Elevator Penthouses Roof Replacement and Equipment Modifications FDOT F.M. # Substantial Completion: December 2015 Current : $1,219,800 Design-Builder: Skanska Project Description: The scope of this project includes replacing the Main Terminal building elevator core penthouse roofs, including modifications to existing antennas and electrical equipment. Project Status: Construction began on the Earhart Core on June 18, # Airside F Boarding Level Carpet Replacement Substantial Completion: July 2014 Current : $835,800 RS&H Vantage Construction f/k/a Small Street Construction Project Description: The scope of this project is to remove and replace the Boarding Level carpet. Project Status: The final review and approval of the carpet occurred on June 22, Project closeout can proceed and the final pay application is schedule to be submitted on July 3,

13 # Main Terminal Stair Towers & Shuttle Guideway Bridge Rehabilitation & Taxiway B Bridge Reconstruction Substantial Completion: March 2015 & December 2016 Current : $3,883,400 Tagarelli Construction, Inc./ Skanska Project Description: The scope of this project includes the investigation, analysis and construction services for the reconstruction of the reinforced concrete span of the Taxiway B Bridge. The scope also includes the rehabilitation of the Main Terminal stair towers and shuttle guideway structures including painting the structural steel for the shuttle F guideway. Project Status: The reconstruction of the Taxiway B Bridge has been completed. Ongoing litigation is keeping this part of the project from being completed. Targarelli completed construction on the Main Terminal stair towers and shuttle guideways rehabilitation project in May Skanska is scheduled to begin painting the Airside F guideway structural steel in August # Airside E Airline and TSA Space Rehabilitation FDOT F.M. # Substantial Completion: August 2015 Current : $171,100 N/A In House Maintenance Projects Group Project Description: The scope of this project is to provide a clean, well-maintained work area for Airline and TSA tenants at Airside E. Project Status: During the month of June the in-house maintenance projects group rehabilitated the Delta space at Airside E ramp level. 11

14 # Airline, Patron, and STS Technology Modernization FDOT F.M. # Substantial Completion: September 2015 Current : $834,300 N/A In House Information Technology Services Project Description: The scope of this project is to replace all end of life computer equipment within the EVIDS display system throughout the facility, upgrade the EVIDS software server backend, and upgrade the Wi-Fi mesh network presence on each airside on the outside ground level. Project Status: The Wi-Fi mesh network has been completed and the team is currently preparing to roll out the 160 EVIDS replacement PC s. The EVIDS software and server backend has been upgraded. Two of the three initiatives have been completed and the third initiative is in line to be completed on time. # Authority Network Equipment Replacement Phase 2 Substantial Completion: February 2016 Current : $1,595,400 N/A In House Information Technology Services Tampa Int l, Tampa Executive & Peter O. Knight Project Description: The scope of this project is to replace and/or upgrade components in the Authority s network due to the end-of-life/end-of-service life issues or advancements in available technology that would enhance the service and support. Project Status: The project is at 50% completion and currently on schedule and within budget. # Paging System Replacement Phase 1 Airside E FDOT F.M. # Substantial Completion: July 2015 Current : $364,900 NA Alltel Project Description: The scope of this project is to upgrade the paging system at Airsides E to the currently supported version of the Innovative Electronic Designs (IED) system hardware and software. Project Status: Substantial Completion is scheduled for the end of July

15 # Short Term and Long Term Parking Garage Rehabilitation Substantial Completion: November 2015 Current : $1,706,600 RS&H Tagarelli Project Description: The scope of this project includes the structural rehabilitation of a number of areas within the garages, including the STPG Level 6, one half of LTPG Level 6 and other areas to extend useful its life. Project Status: The contractor has successfully completed and turned over the first two phases of the Short Term Parking Garage rehabilitation on May 21, 2015, June 20, 2015, respectively. Change Order 1 was executed on June 4, 2015 adding parking stall numbering for the 6 th level of the Short Term Parking Garage, as well as handrail and full height column paint. This Change Order increased the total contract sum by $15, and added 92 days to the schedule. # Replace Police Radio System Substantial Completion: February 2016 Current : $2,102,600 NA Communications International Project Description: The scope of this project is to replace the existing obsolete, standalone police radio system to a modern, digital system that provides interoperable communications with all other law enforcement agencies and fire departments in Hillsborough, Pinellas, and Pasco Counties. Project Status: The contractor has completed the installation of the Earhart penthouse roof equipment and is currently working on designing the new 700 MHz Bi-Directional Amplifier (BDA) system. # Carpet Replacement for Shuttles, Monorails and Elevator Lobbies Substantial Completion: July 2015 Current : $565,300 NA Gulf Coast Floors Project Description: The scope of this project is to replace the carpet in the Shuttles, Monorails and Elevator lobbies. Project Status: New carpet has been installed at all Short Term and Long Term Parking Garage elevator lobbies, Long Term Parking Garage elevator cabs and the monorail cars. 13

16 # ID Badge Training System Replacement Substantial Completion: April 2016 Current : $298,000 Safety and Security Instruction Project Description: The scope of this project is replace the existing Interactive Employee Training (IET) system with a new system utilizing web browser capability, and will be in compliance with PII requirements. This system will support closed captions, multiple languages, and provide the ability for Authority staff to update existing or add new training content. Project Status: The Authorized Signatory training course (AST) pilot is in progress. The SIDA training course will be delivered in July with a training pilot to follow. Movement Area Driver Training (MADT) will be delivered in late July. SMS training has been delayed due to the FAA comment period extension. # Airport Support Area Environmental Remediation Phase 6 Regulatory Completion: June 2019 Current : $3,750,000 AECOM (Parcel 4208, CDM Smith, Parcel 7406, CB&I 10 parcels) AECOM Technical Service, Inc. Project Description: The scope of this project includes soil and groundwater remediation for properties located in Drew Park Area. Project Status: The contractor continues to perform site rehabilitation of Parcel A large percentage of the contaminant mass has been removed and the focus has now shifted to spot treatment of persistent areas with an emphasis on upcoming regulatory closure. # Fuel Farm Maintenance Substantial Completion: February 2016 Current : $9,759,800 Tampa Fuel Consortium NA Project Description: The scope of this project includes upgrading the Fuel Farm areas that are required to maintain a level of service that is commensurate with industry standards. Project Status: Erosion control and dewatering has been installed. Installation of 12 drainage piping is complete. Layout of pump pad, motor control center building pad and conduit duct bank is in progress. 14

17 # Shared Use Passenger Processing Systems (SUPPS) Substantial Completion: August 2015 Current : $3,449,600 RS&H AirIT Project Description: The scope of this project includes a standard installation designed to provide a shared or common passenger processing platform (software and hardware), so any airline can operate at any location (ticket counter or gate) that has been designated as shared use. This project is the first of a multi-year effort that will provide for the airport wide SUPPS capability. This first phase will provide an initial roll out to 10 gates and 18 ticket counters at Airside A, E, and F, along with their supporting ticket counters and Airline operational space. Project Status: During the month of June the first groups of airline landside ticketing positions were switched over to the shared use passenger processing technology including Edelweiss, Cayman, Copa, and WestJet. The contractor continues working with airline s IT personnel to assist with set up of equipment, software, and training. # Main Terminal & Airport Concessions Redevelopment Program Substantial Completion: November 2017 Current : $131,303,410 Design-Builder: Skanska Project Description: The scope of this project is to expand the transfer level, relocate the main terminal shuttle lobbies, replace all escalators in the Main Terminal, refurbish interior finishes, replace signage in the Main Terminal and reconfigure all concessions spaces throughout the airport. Project Status: The Final Part 2 Supplemental contract was awarded at the June 2015 Board meeting. Work continues on the demolition and structural steel installation on east side expansion. # Concessions Receiving and Distribution Center Substantial Completion: January 2016 Current : $9,978,434 Atkins North America, Inc. J. Kokolakis Contracting, Inc. Project Description: The scope of this project includes the construction of a 20,000 sf consolidated concessions warehouse that will serve the Authority s new concessions program. Project Status: The first concrete pour took place on May 14, The stem walls have since been completed and the slab-on-grade has been infilled, compacted, and is currently being prepared for a July 1 st concrete pour. The contractor has been installing underground utilities and infrastructure for the site, as well as excavating and grading the East and Southeast Pond. 15

18 # Reconstruct Taxiway J Bridge Reconstruction FDOT F.M. # , , , & AIP # Substantial Completion: December 2016 Current : $34,076,400 Design-Builder: Cone & Graham, Inc. Project Description: The scope of this project includes reconstructing Taxiway J over the George Bean Parkway and Bessie Coleman Service Road to support the APM. The bridge will accommodate future widening of the parkway. Project Status: The contractor completed the installation of 17 out of 134 drilled shafts along with their corresponding foundations at Pier 3. Backfill and compaction around the footings was completed in order for the construction of pier wall/cap to commence. The first of seven pier wall sections is complete. Upon completion of the entire pier wall, backfill, and grading will resume for the construction of the outbound traffic lanes detour. # Airside F Boarding Bridges, PCA AHU and GPU Replacement Substantial Completion: February 2016 Current : $16,182,400 TY Lin Walbridge Project Description: The scope of this project includes replacing the Passenger Boarding Bridges, preconditioned air (PCA), air handling units (AHU) and ground power units (GPU) at all fourteen gates. Project Status: The Boarding Bridge installation at Gates 87, 88, 89, and 90 are complete and installation of Gate 86 is currently in progress. 16

19 # Automated People Mover (APM & DBOM) FDOT F.M. # Substantial Completion: October 2017 Current : $412,341,647 APM Infrastructure Design-Builder: Austin Commercial APM DBOM Design-Builder Mitsubishi Heavy Industries America, Inc. (MHIA) Airport APM Infrastructure: Project Description: The scope of this project is to construct the infrastructure associated with a 1.4 mile long Automated People Mover System (APM) from the Main Terminal to the new Consolidated Rental Car Facility. Three APM stations will also be constructed and located at the Main Terminal, Economy Garage, and the ConRAC. Project Status: The final Part 2 Supplemental contract was awarded at the May 2015 Board meeting. Preparatory work has begun related to the construction of the overhead APM guideway. Existing utilities are being relocated as necessary on areas that conflict with the overhead guideway support columns and stations. APM DBOM: Project Description: MHIA will provide a turnkey Automated People Mover System (APM) which will integrate with the APM infrastructure being built by Austin Commercial, L.P. under a separate contract. Project Status: The DBOM contract was awarded at the November 2014 Board meeting. Design related to the APM vehicles and associated necessary equipment to operate the system is underway at this time. MHIA is coordinating closely with Austin Commercial, L.P. to ensure no conflicts exist between the two related projects. 17

20 IV. Projects Substantially Complete # Airside C Passenger Boarding Bridges Refurbishment FDOT F.M. # Initial: Estimated Final: Substantial Completion: June 24, 2015 June 24, 2015 Board : $230,600 Revised : $218,400 $210,206 Design Amendments: $0 Construction Change Orders: $0 NA In House Maintenance Projects Group D/W/MBE: Design: 0% 0% Construction: 0% 0% Project Description: The scope of this project was to refurbish and repaint each Passenger Boarding Bridge (PBB) at Airside C which will extend the useful life. Periodic painting of each PBB is necessary in order to fully protect the bridges from the elements, to prevent rusting, and to restore them to a first class appearance. Project Performance: The project was completed under budget and on schedule. 18

21 # Main Terminal Paver Replacement FDOT F.M. # , Initial: Estimated Final: Substantial Completion: March 28, 2014 April 6, 2015 Board : $1,447,000 Revised : $1,562,700 $1,562,700 Design Amendments: $0 Construction Change Orders: $50,758 (3) RS&H Small Street Construction Company, Inc. d/b/a Vantage Construction Group Airport D/W/MBE: Design: 3.7% 3.7% Construction: 17.7% 43.5% Project Description: The scope of this project was to replace the existing curbside pedestrian walkway concrete pavers on the baggage claim level, ticket level, and pedestrian bridges at the Transfer level that were not replaced as part of the Curbside Modernization Project completed in April 2012 under Project # Project Performance: The scope was altered during the design phase to not replace the concrete pavers on the red side ticketing and baggage claim levels due to the proposed North Main Terminal expansion as approved in the Master Plan in April In addition, restoration of the blue side fountain plaza area was added to the project. The Board approved budget was exceeded by $115,700 due to adding the blue side fountain plaza restoration work and unforeseen conditions encountered during construction. Three change orders were issued due to unforeseen conditions in the mortar bed construction and bollard lighting. The schedule was exceeded due to adding the fountain plaza scope of work during the design phase and unforeseen conditions encountered during construction. The final W/MBE goal for Design was met and the construction goal was exceeded since the contractor is a WMBE who self-performed much of the work. 19

22 # Boarding Bridge Air Conditioning System FDOT F.M. # , Initial: Estimated Final: Substantial Completion: September 1, 2014 February 20, 2015 Board : $1,703,000 Revised : $2,144,200 $2,131,771 Design Amendments: $0 Construction Change Orders: $99, (2) RS&H BCH Mechanical D/W/MBE: Design: 0% 0% Construction: 10.3% 12.3% Project Description: The scope of this project was to install air conditioning systems on 34 passenger boarding bridges located at airsides A, C, and E to enhance passenger service. Project Performance: The Board approved budget was exceeded by $428,771 as a result of bids coming in higher than anticipated and added scope of work during construction. The project was initially bid to install air conditioning units in 34 boarding bridges. Bids were received and the lowest responsive bidder was significantly higher than the budget. As a result, the Authority canceled the bid and the project scope was revised to eliminate those bridges that were not under lease to the airlines. The project was rebid with the revised scope of 24 boarding bridges. A change order was executed at the end of the project to purchase equipment for the next 10 bridges to be installed by the Authority s maintenance department. The schedule was exceeded as a result of rebidding the project. 20

23 # Sustainability Management Plan AIP # Initial: Estimated Final: Substantial Completion: April 30, 2014 March 31, 2015 Board : $810,000 Revised : $893,900 $893,900 Design Amendments: $42,876 Construction Change Orders: $0 Ricondo and Associates NA D/W/MBE: Design: 13.0% 13.3% Construction: 0% 0% Project Description: The Federal Aviation Administration (FAA) selected the Authority to participate in their Sustainability Pilot Program and provided a large grant to assist in the preparation of the Aviation Authority s first Sustainability Management Plan (SMP). The SMP process included developing a baseline inventory, benchmarking, visioning, public outreach, and strategic planning. The deliverables also included a Sustainable Design Criteria Manual (SDCM) and numerous tools to expand and track the sustainability program at TPA and the three general aviation airports. Project Performance: The Board approved budget was exceeded by $83,900 as a result of increasing the scope of work and additional in house costs. After the study was complete, the Authority amended the consultant s contract to add fees in support of the Tampa Electric Company solar installation on the Economy Garage. Assistance was needed as the Authority was required to obtain FAA approval for the solar reflectivity. The schedule was exceeded as a result of delaying the consultant selection by one month and the added scope of work related to the FAA solar approval. 21

24 # Terminal Building Rehabilitation Initial: Estimated Final: Substantial Completion: July 4, 2015 May 27, 2015 Board : $674,300 Revised : $633,000 $607,200 Design Amendments: $0 Construction Change Orders: $0 RS&H R.L. Burns Tampa Executive Airport D/W/MBE: Design: 0% 0% Construction: 31.5% 31.5% Project Description: The scope of this project was to perform specific maintenance repairs and general aesthetic rehabilitation of the Tampa Executive Airport FBO terminal building, including painting, drywall repairs, new flooring, new lighting, millwork resurfacing, tile cleaning and window removal/resealing. Project Performance: The project was completed under budget and ahead of schedule. 22

25 8/26/2015 HCAA Project No. and Description Projects in Planning Architect/Engineer Contractor/Design- Builder Board Current PROJECTS (ACTIVE) - JUN 2015 Board Contract/ Agrmt Date Authorized Amount Sum of Change Orders / Amdmt by CEO by Board Total Authorized Baggage Handling Systems Servers Upgrade/Enhancement (TPA) Total Project Costs/ 1,303,900 1,303, % Airfield Pavement Rehabilitation - Design Only (TPA) Design RS&H (note 1) 12/01/14 15, ,716 15, % N/A N/A Other (In House/Misc) 3,913 3,913 3, % Total Project Costs/ 2,582,200 2,582,200 19, ,629 19, % Perimeter Security Study and Enhancement (TPA) Design RS&H (note 1) 11/04/14 45, ,687 43, % N/A N/A Other (In House/Misc) 1,723 1,723 1, % Total Project Costs/ 1,000,000 1,000,000 47, ,410 45, % General Aviation Airports Master Plan Update 2014 (PCA, POK, TEA) Design Michael Baker 01/27/14 892, , , % 11.6% 13.3% Other (In House/Misc) 17,203 17,203 17, % Total Project Costs/ 824, , , , , % Structural & Pavement Inspection & Rehabilitation (TPA) Design RS&H (note 1) 11/17/14 454, , , % N/A N/A Other (In House/Misc) 13,082 13,082 10, % Total Project Costs/ 1,567,300 1,567, , , , % HCAA Enterprise Resource Planning and Analytics Program (TPA) Design RS&H (note 1) 12/12/14 7, ,344 7, % N/A N/A Design (Other) 700, , , % Construction (Other) 7,659,218 7,659,218 5,658, % Other (In House/Misc) 27,387 27,387 23, % Total Project Costs/ 9,324,700 9,324,700 8,393, ,393,949 6,121, % & Common/Shared Use Passenger Systems (C/SUPPS) Phase 2 Design (TPA) Total Project Costs/ 780, , % Projects in Design Consolidated Rental Car Facility Phase I Design (TPA) Design (dbe %) Austin/Gresham Smith 03/11/14 2,629, ,629,983 1,882, % 17.7% 4.3% Design (addtl line to show wmbe %) Austin/Gresham Smith 03/11/ % 4.7% Design CB&I (note 2) 05/17/14 24, ,187 14, % N/A N/A Design Pasley Management 02/08/14 205, , , % N/A N/A Design Ricondo & Associates 457, , , % N/A N/A Design RS&H (note 1) 08/07/13 113, , , % N/A N/A Design (Other) 5, ,438 30, % Construction (Other) 13, ,449 13, % Other (In House/Misc) 150, , , % Total Project Costs/ 4,500,000 4,500,000 3,598, ,598,398 2,821, % Site Remediation (TPA) Design URS (note 5) 11/15/11 441, , , % 18.3% 14.7% Design CBI (note 2) 05/17/14 567, , , % 34.8% 12.6% Design (Other) 1,150 1, % Construction Other 2,868 2,868 2, % Other (In House/Misc) 75,182 75,182 75, % Total Project Costs/ 810,100 1,210,100 1,088, ,088, , % Amount Incurred Incurred DBE W/MBE Target DBE W/MBE Achieved to Date Footnotes on last page Page 1 of 9

26 8/26/2015 HCAA Project No. and Description Architect/Engineer Contractor/Design- Builder Board Current PROJECTS (ACTIVE) - JUN 2015 Board Contract/ Agrmt Date Authorized Amount Sum of Change Orders / Amdmt by CEO by Board Total Authorized Airport Support Facilities - Fence (TPA) Design RS&H (note 1) 09/04/12 2, ,508 2, % 15.5% 0.0% Other (In House/Misc) 10,999 10,999 10, % Total Project Costs/ 325, ,400 13, ,507 13, % Main Terminal Shuttle Lobby Automation (TPA) Design Ricondo & Associates 27, ,598 26, % N/A N/A Design Skanska/HOK 04/11/14 42, ,092 38, % 25.9% 9.9% Other (In House/Misc) 13,275 13,275 13, % Total Project Costs/ 2,300,000 1,569,200 82, ,965 78, % Electronic Airport Layout Plan (e ALP) (TPA) Design RS&H (note 1) 08/09/13 6, ,691 6, % N/A N/A Design Aecom Technical Svcs 09/05/13 1,894, ,894,227 1,448, % 10.8% 11.8% Other (In House/Misc) 39,970 39,970 39, % Total Project Costs/ 2,000,000 2,000,000 1,940, ,940,888 1,494, % Commercial Real Estate Development-Preliminary Planning & Design (TPA) Design Stantec 05/02/13 1,109, ,109, , % N/A N/A Other (In House/Misc) 1,531 1,531 1, % Total Project Costs/ 1,300,000 2,600,000 1,110, ,110, , % Checked Baggage System Upgrades and Optimization Construction (TPA) Design Michael Baker 14, ,505 14, % N/A N/A Design RS&H (note 1) 03/11/15 16, , % N/A N/A Design Skanska 12/05/14 4,219, ,219,043 1,630, % 15.0% 6.2% Other (In House/Misc) 38,346 38,346 38, % Total Project Costs/ 58,000,000 54,498,192 4,288, ,288,556 1,684, % Airside E Boarding Level and Boarding Bridge Carpet Replacement (TPA) Design RS&H (note 1) 01/10/14 117, ,292 72, % N/A N/A Other (In House/Misc) 24,130 24,130 24, % Total Project Costs/ 1,446,600 1,446, , ,422 96, % & Replace Parking Revenue Control System Phase I & Phase II (TPA) Design RS&H (note 1) 2, ,692 2, % N/A N/A Design (Other) 94, ,856 85, % N/A N/A Design-Builder Manhattan Construction/Walker 09/04/14 1,081, ,081, , % 16.1% 17.4% Other (In House/Misc) 56,110 56,110 56, % Total Project Costs/ 13,885,400 13,885,400 1,235, ,235, , % Long Term Parking Garage Levels 3, 4 & 5 Lighting Fixtures Replacement (TPA) Design RS&H (note 1) 12/12/14 124, ,131 52, % N/A N/A Other (In House/Misc) 8,779 8,779 8, % Total Project Costs/ 2,275,300 2,275, , ,910 61, % Short Term Parking Garage Level 7 Rehabilitation (TPA) Design RS&H (note 1) 12/31/14 185, ,189 29, % N/A 3.8% Other (In House/Misc) 11,972 11,972 11, % Total Project Costs/ 2,998,000 2,998, , ,161 41, % Long Term Parking Garage Level 5 and Helix Rehabilitation (TPA) Design RS&H (note 1) 12/31/14 159, , % N/A N/A Other (In House/Misc) 5,884 5,884 4, % Total Project Costs/ 2,577,100 2,577, , ,763 4, % Amount Incurred Incurred DBE W/MBE Target DBE W/MBE Achieved to Date Footnotes on last page Page 2 of 9

27 8/26/2015 HCAA Project No. and Description Architect/Engineer Contractor/Design- Builder Board Current PROJECTS (ACTIVE) - JUN 2015 Board Contract/ Agrmt Date Authorized Amount Sum of Change Orders / Amdmt by CEO by Board Total Authorized Building #432 Roof Rehabilitation (TPA) Design RS&H (note 1) 11/04/14 43, ,836 7, % N/A N/A Other (In House/Misc) 7,145 7,145 7, % Total Project Costs/ 263, ,900 50, ,981 15, % Petroleum Storage Systems Replacement/Refurbishment (TPA, TEA, POK, PCA) Design CB&I (note 2) 10/24/14 158, ,378 84, % N/A N/A Construction (Other) 12,600 12, % Other (In House/Misc) 4,205 4,205 4, % Total Project Costs/ 566, , , ,183 88, % Asphalt Pavement Rehabilitations - Tug Tunnel Drives & Hoover Blvd. (TPA) Design RS&H (note 1) 10/17/14 111, ,068 86, % 21.0% 21.0% Other (In House/Misc) 15,150 15,150 15, % Total Project Costs/ 775, , , , , % Refurbish Airside A Shuttle Superstructure (TPA) Design-Build - Design Skanska/HOK 87, ,323 20, % 25.9% 9.9% Design-Build - Construction Skanska/HOK 11/18/14 2,532, ,532,605 65, % 19.0% 3.5% Other (In House/Misc) 7,618 7,618 7, % Total Project Costs/ 2,308,000 2,799,000 2,627, ,627,546 92, % Seawall Rehabilitation (POK) Design RS&H (note 1) 12/05/14 76, ,240 32, % 13.1% 7.9% Other (In House/Misc) 13,811 13,811 13, % Total Project Costs/ 464, ,900 90, ,051 45, % South Terminal Support Area (STSA) Roadway Improvements (TPA) Design Austin/Gresham Smith 03/11/14 395, , , % 47.0% 51.6% Project Management Jacobs (note 7) 04/18/14 146, ,847 48, % N/A N/A Design Kimmins 09/04/14 2,241, ,241, , % 12.6% 7.0% Construction (Other) 380, ,794 31, % Other (In House/Misc) 96,503 96, , % Total Project Costs/ 21,409,200 25,711,299 3,260, ,260,629 1,564, % Projects Undergoing Construction/Implementation ConRAC (TPA) Design (dbe %) Austin/Gresham Smith 03/11/14 22,340,690-1,405, ,405,888 20,934,802 9,054, % 17.7% 9.7% Design (addtl line to show wmbe %) Austin/Gresham Smith 03/11/ % 10.9% Design RS&H (note 1) 08/07/13 60, ,245 45, % N/A N/A Design (Other) 128, ,653 18, % Project Management Jacobs (note 7) 04/18/14 2,644, ,644, , % 13.6% 2.0% Construction Austin/Gresham Smith 11/06/14 54,848, ,200, ,200, ,048,879 11,951, % 19.0% 3.8% Construction (Other) 1,124, ,124, , % Other (In House/Misc) 8,976, ,976,439 3,275, % Total Project Costs/ 318,700, ,543,612 90,122, ,794, ,917,763 25,798, % Main Terminal Elevator Penthouse Roof Replacement and Equipment (TPA) Design RS&H (note 1) 08/07/13 189, , , % N/A N/A Design-Build (Design) Skanska/HOK 04/11/14 132, ,419 56, % 25.9% 9.9% Design-Build (Construction) Skanska/HOK 11/06/14 928, ,408 18, % 19.0% 3.5% Construction (Other) 50, ,530 50, % Other (In House/Misc) 30,613 30,613 30, % Total Project Costs/ 696,000 1,219,800 1,331, ,331, , % Amount Incurred Incurred DBE W/MBE Target DBE W/MBE Achieved to Date Footnotes on last page Page 3 of 9

Aviation Authority Capital Improvement Program Project Status Report April 2016

Aviation Authority Capital Improvement Program Project Status Report April 2016 Aviation Authority Capital Improvement Program Project Status Report April 2016 Prepared by Planning and Development and Development Program Services Capital Improvement Project Status Report Overview

More information

Planned Procurement Opportunities Report. August 2014

Planned Procurement Opportunities Report. August 2014 HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report August 2014 Prepared by the Procurement Department Planned Procurement Opportunities Report - August 2014 Overview The Planned

More information

Planned Procurement Opportunities Report. March 2015

Planned Procurement Opportunities Report. March 2015 HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report March 2015 Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and posted

More information

Planned Procurement Opportunities Report. February 2015

Planned Procurement Opportunities Report. February 2015 HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report February 2015 Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and

More information

Planned Procurement Opportunities Report. April 2015

Planned Procurement Opportunities Report. April 2015 HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report April 2015 Prepared by the Procurement Department Planned Procurement Opportunities Report - April 2015 Overview The Planned

More information

Proposal For a Trivia Bid and Interview

Proposal For a Trivia Bid and Interview HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report May 2015 Prepared by the Procurement Department Planned Procurement Opportunities Report - May 2015 Overview The Planned

More information

Planned Procurement Opportunities Report. January 2015

Planned Procurement Opportunities Report. January 2015 HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report January 2015 Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and

More information

Planned Procurement Opportunities Report. June 2015

Planned Procurement Opportunities Report. June 2015 HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report June 2015 Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and posted

More information

Los Angeles World Airports

Los Angeles World Airports M E M O R A N D U M Los Angeles World Airports Date: Memo To: From: Subject: LAX Station Managers Raymond Jack, Airport Manager II LAX Operations Division Weekly Coordinated Construction Activity Runway

More information

The total estimated PFC revenue for the application is $266,900,000. The estimated charge effective date for this application is December 1, 2016.

The total estimated PFC revenue for the application is $266,900,000. The estimated charge effective date for this application is December 1, 2016. Public Notice of Application for Authority to Impose and Use Passenger Facility Charges (PFCs) at EWR, LGA, JFK and SWF and Amendment to Approved PFC Applications at EWR, LGA, and JFK The Port Authority

More information

Strategic Business Plan

Strategic Business Plan Williams Gateway Airport Authority Strategic Business Plan Fiscal Years 2011-2015 Adopted May 24, 2010 by the Phoenix-Mesa Gateway Airport Authority Board of Directors Page 2 TABLE OF CONTENTS Purpose...4

More information

KIEWIT CM/GC Enabling/Utilities

KIEWIT CM/GC Enabling/Utilities South Terminal Redevelopment Program KIEWIT CM/GC Enabling/Utilities Contract Value $50 million M/WBE Goal 20 percent Contact John Todd, LEED AP Project Manager 303.930.9046 john.todd@kiewit.com General

More information

AVIATION AUTHORITY REGULAR BOARD MEETING and PUBLIC HEARING. Thursday, October 2, 2014 9:00 A.M. Board Room Level 3 at Tampa International Airport

AVIATION AUTHORITY REGULAR BOARD MEETING and PUBLIC HEARING. Thursday, October 2, 2014 9:00 A.M. Board Room Level 3 at Tampa International Airport AVIATION AUTHORITY REGULAR BOARD MEETING and PUBLIC HEARING Thursday, 9:00 A.M. Board Room Level 3 at Tampa International Airport AGENDA Any person who desires to appeal any decisions made at this meeting

More information

Existing Facilities. Current and Forecast Demand

Existing Facilities. Current and Forecast Demand Existing Facilities JIA is served by a number of airside and landside facilities. There are two runways that serve the airport in an open V configuration. The Annual Service Volume (ASV) of the runway

More information

Business Information Technology. Airport Roundtable. ACI-NA Annual Conference and Exhibition BIT Workshop Atlanta, GA September 7, 2014

Business Information Technology. Airport Roundtable. ACI-NA Annual Conference and Exhibition BIT Workshop Atlanta, GA September 7, 2014 Business Information Technology Airport Roundtable ACI-NA Annual Conference and Exhibition BIT Workshop Atlanta, GA September 7, 2014 Asheville Regional Airport (AVL) Your Contact Information Name: Royce

More information

Building a Legacy of Sustainability in Tampa Bay. Airports Going Green Conference November 3, 2014

Building a Legacy of Sustainability in Tampa Bay. Airports Going Green Conference November 3, 2014 Building a Legacy of Sustainability in Tampa Bay Airports Going Green Conference November 3, 2014 Background Hillsborough County Aviation Authority Board Policy 770: Sustainability Management Board currently

More information

Planned Procurement Opportunities Report. June 2016

Planned Procurement Opportunities Report. June 2016 HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report June 2016 Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and posted

More information

MASTER PLAN DRAFT RECOMMENDED PLAN

MASTER PLAN DRAFT RECOMMENDED PLAN MASTER PLAN DRAFT RECOMMENDED PLAN City of Atlanta, Department of Aviation September 19, 2014 Draft Recommended Plan This document presents an overview of the findings and recommendations from the Master

More information

Hartsfield-Jackson Atlanta International Airport s

Hartsfield-Jackson Atlanta International Airport s Hartsfield-Jackson Atlanta International Airport s 2008-09 Closed Projects (Posted 1/6/2009) FC-3007000038C: MISCELLANEOUS BUILT-UP ROOF AND SINGLE PLY ROOF REPAIRS AT H-JAIA Furnish all labor, equipment,

More information

8 CELL PHONE LOT. 8.1 Background. 8.2 Previous Studies. 8.3 Facility Size/Configuration

8 CELL PHONE LOT. 8.1 Background. 8.2 Previous Studies. 8.3 Facility Size/Configuration 8 CELL PHONE LOT 8.1 Background Cell phone lots provide short term parking in which drivers (or meeters) wait for a cellular call from an arriving passenger prior to approaching the deplaning curbside

More information

HILLSBOROUGH COUNTY AVIATION AUTHORITY FINANCIAL STATEMENTS, OTHER FINANCIAL INFORMATION AND COMPLIANCE REPORTS

HILLSBOROUGH COUNTY AVIATION AUTHORITY FINANCIAL STATEMENTS, OTHER FINANCIAL INFORMATION AND COMPLIANCE REPORTS FINANCIAL STATEMENTS, OTHER FINANCIAL INFORMATION AND COMPLIANCE REPORTS YEARS ENDED SEPTEMBER 30, 2015 AND 2014 TABLE OF CONTENTS YEARS ENDED SEPTEMBER 30, 2015 AND 2014 INDEPENDENT AUDITORS REPORT 1

More information

Chapter 22. Lump Sum Project Guidelines

Chapter 22. Lump Sum Project Guidelines Chapter 22 Lump Sum Project Guidelines 22.1 General...22-1 22.2 Project Selection...22-3 22.3 Plans Preparation...22-5 22.4 Preliminary Estimate...22-7 22.5 Specifications...22-9 22.6 Contracts Administration...22-11

More information

UNIVERSITY OF MISSISSIPPI FIXED ASSET CAPITALIZATION POLICY

UNIVERSITY OF MISSISSIPPI FIXED ASSET CAPITALIZATION POLICY UNIVERSITY OF MISSISSIPPI FIXED ASSET CAPITALIZATION POLICY The term capitalized fixed assets includes land, improvements to land, easements, buildings, building improvements, vehicles, machinery, furniture,

More information

MISSOULA COUNTY AIRPORT AUTHORITY Regular Board Meeting April 26, 2016

MISSOULA COUNTY AIRPORT AUTHORITY Regular Board Meeting April 26, 2016 MISSOULA COUNTY AIRPORT AUTHORITY Regular Board Meeting April 26, 2016 THOSE PRESENT: STAFF: OTHERS: Chair Jeffrey Roth Commissioner Shane Stack Commissioner Larry Anderson Commissioner Paul Stafford Commissioner

More information

Nate Smith Executive Vice President DFW International Airport DALLAS/FORT WORTH INTERNATIONAL AIRPORT

Nate Smith Executive Vice President DFW International Airport DALLAS/FORT WORTH INTERNATIONAL AIRPORT Nate Smith Executive Vice President DFW International Airport DALLAS/FORT WORTH INTERNATIONAL AIRPORT DFW Airport: Connecting the World In four decades of existence, DFW has grown into a global super

More information

SECTION XI OPINION OF PROBABLE COST

SECTION XI OPINION OF PROBABLE COST SECTION XI OPINION OF PROBABLE COST OPINION OF PROPABLE COSTS HARBOR ISLAND THE PAVILION 1) Provide a sprinkler system for the entire building. 8000 SF X $15/SF $120,000 2) Remove and replace existing

More information

ADDENDUM NO. 1. Manchester Boston Regional Airport, City of Manchester, NH

ADDENDUM NO. 1. Manchester Boston Regional Airport, City of Manchester, NH Hoyle, Tanner Project No. 093145 ADDENDUM NO. 1 Manchester Boston Regional Airport, City of Manchester, NH Construct Relocated Roadway Airport Service Rd. Outside Runway Object Free Area (ROFA); Construct

More information

St. Petersburg-Clearwater International Airport. FY08 Budget Information Session May 3, 2007

St. Petersburg-Clearwater International Airport. FY08 Budget Information Session May 3, 2007 St. Petersburg-Clearwater International Airport FY08 Budget Information Session May 3, 2007 1 Department Direction/Highlights Departmental Direction As a regional gateway to Pinellas County, the St. Petersburg-Clearwater

More information

Operating Budget Data

Operating Budget Data J00A04 Debt Service Requirements Maryland Department of Transportation Operating Budget Data ($ in Thousands) FY 14 FY 15 FY 16 FY 15-16 % Change Actual Working Allowance Change Prior Year Special Fund

More information

IH-635 MANAGED LANES PROJECT, SEG. 3.2

IH-635 MANAGED LANES PROJECT, SEG. 3.2 IH-635 MANAGED LANES PROJECT, SEG. 3.2 Location: Dallas, Texas Owner: Texas Department of Transportation Client: Ferrovial Agroman Construction Cost: $1 Billion Construction Completion Date: December,

More information

NATIONAL INSTITUTE OF GOVERNMENT PURCHASING (NIGP) DESIGN AND CONSTRUCTION CODES

NATIONAL INSTITUTE OF GOVERNMENT PURCHASING (NIGP) DESIGN AND CONSTRUCTION CODES NATIONAL INSTITUTE OF GOVERNMENT PURCHASING (NIGP) DESIGN AND CONSTRUCTION CODES All searches and notifications on Bid4Michigan are based on National Institute of Government Purchasing (NIGP) codes. It

More information

MASTER PLAN PREPARATION

MASTER PLAN PREPARATION Located in the East Valley of the Phoenix Metropolitan Area, Phoenix-Mesa Gateway Airport is a former military airfield that has successfully made the transition to a full service commercial passenger

More information

Operations at Coulter Airfield

Operations at Coulter Airfield Operations at Coulter Airfield Outline Background Assets Budget Options Questions/Direction Vision (January 2010) 1. Maximize Economic Viability of Coulter Field as an Asset to the City Strategic Issue

More information

REBUILDING THE CTA FORREST CLAYPOOL, PRESIDENT CHRIS BUSHELL, SVP, INFRASTRUCTURE

REBUILDING THE CTA FORREST CLAYPOOL, PRESIDENT CHRIS BUSHELL, SVP, INFRASTRUCTURE REBUILDING THE CTA FORREST CLAYPOOL, PRESIDENT CHRIS BUSHELL, SVP, INFRASTRUCTURE Our Commitment: Increasing Investment Despite Lean Times Even while facing a $277M deficit, we are finding ways to rebuild

More information

PORT OF SEATTLE MEMORANDUM. COMMISSION AGENDA Item No. 6a ACTION ITEM Date of Meeting January 6, 2015

PORT OF SEATTLE MEMORANDUM. COMMISSION AGENDA Item No. 6a ACTION ITEM Date of Meeting January 6, 2015 PORT OF SEATTLE MEMORANDUM COMMISSION AGENDA Item No. 6a ACTION ITEM Date of Meeting January 6, 2015 DATE: TO: FROM: Michael Ehl, Director Airport Operations Wayne Grotheer, Director Aviation Project Management

More information

PART II SCHEDULE. Scope of Services. Special Terms and Conditions. Virginia Railway Express

PART II SCHEDULE. Scope of Services. Special Terms and Conditions. Virginia Railway Express PART II SCHEDULE SECTION TITLE D E Scope of Services Special Terms and Conditions 11 SECTION D SCOPE OF SERVICES D.1 OVERVIEW A. The selected firm is referred to herein as either the Consultant or the

More information

DEVELOPMENT STANDARDS FOR FACILITIES & IMPROVEMENTS. The Virginia Tech/Montgomery Regional Airport Authority November 19, 2002

DEVELOPMENT STANDARDS FOR FACILITIES & IMPROVEMENTS. The Virginia Tech/Montgomery Regional Airport Authority November 19, 2002 DEVELOPMENT STANDARDS FOR FACILITIES & IMPROVEMENTS The Virginia Tech/Montgomery Regional Airport Authority November 19, 2002 These Standards shall reflect all pre-existing agreements Adopted March 12,

More information

LONG-TERM INFRASTRUCTURE DEVELOPMENT PLAN

LONG-TERM INFRASTRUCTURE DEVELOPMENT PLAN Louis Armstrong New Orleans International Airport LONG-TERM INFRASTRUCTURE DEVELOPMENT PLAN April 2013 TABLE OF CONTENTS 03. INTRODUCTION 04. PURPOSE AND NEED 06. ALTERNATIVES ANALYSIS 10. KEY ELEMENTS

More information

Business Information Technology. Airport Roundtable. San Jose McEnery Convention Center San Jose, CA September 21, 2013

Business Information Technology. Airport Roundtable. San Jose McEnery Convention Center San Jose, CA September 21, 2013 Business Information Technology Airport Roundtable San Jose McEnery Convention Center San Jose, CA September 2, 203 Asheville Regional Airport ) Upgrading from Cisco Unified Communications Manager from

More information

Greater Orlando Aviation Authority

Greater Orlando Aviation Authority Orlando International Airport & Orlando Executive Airport Budgets Fiscal Year 2015-2016 Orlando, Florida Fiscal Year 2016 Budget-in-Brief ECONOMIC OUTLOOK According to Visit Orlando, Orlando set another

More information

PHOENIX-MESA GATEWAY AIRPORT AUTHORITY 5835 S. Sossaman Road Mesa, Arizona 85212 TELEPHONIC BOARD MEETING AGENDA. Monday, August 27, 2012 8:50 a.m.

PHOENIX-MESA GATEWAY AIRPORT AUTHORITY 5835 S. Sossaman Road Mesa, Arizona 85212 TELEPHONIC BOARD MEETING AGENDA. Monday, August 27, 2012 8:50 a.m. PHOENIX-MESA GATEWAY AIRPORT 5835 SOUTH SOSSAMAN ROAD MESA, ARIZONA 85212-6014 PHONE (480) 988 7600 FAX (480) 988 2315 PHOENIX-MESA GATEWAY AIRPORT AUTHORITY 5835 S. Sossaman Road Mesa, Arizona 85212 TELEPHONIC

More information

Massport, Delta & Terminal A. Presented by Betsy Taylor May 21, 2007

Massport, Delta & Terminal A. Presented by Betsy Taylor May 21, 2007 Massport, Delta & Terminal A Presented by Betsy Taylor May 21, 2007 Topics of the Day Overview of Logan Airport Logan s Physical Challenge Original Project The Revised Lease Financial Structure Logan is

More information

Substantial Improvement/Damage (FEMA 50% Rule) Frequently Asked Questions and Information

Substantial Improvement/Damage (FEMA 50% Rule) Frequently Asked Questions and Information SUBSTANTIAL IMPROVEMENT/DAMAGE WORKSHEET (FEMA 50% RULE) South County: Development Services North County: Development Services 4000 Tamiami Trail S. Room 122 1001 Sarasota Center Blvd Venice, Florida 34293-5076

More information

3.1 Historical Considerations

3.1 Historical Considerations 3. Recommended Scope of Bridge improvements 3.1 Historical Considerations In the fall of 2000, an outside consultant, Fraser Design, suggested that the existing 4 th St. Bridge is potentially eligible

More information

Exhibit 4 Page 1 of 14 BOARD OF COUNTY COMMISSIONERS, BROWARD COUNTY, FLORIDA

Exhibit 4 Page 1 of 14 BOARD OF COUNTY COMMISSIONERS, BROWARD COUNTY, FLORIDA Page 1 of 14 BOARD OF COUNTY COMMISSIONERS, BROWARD COUNTY, FLORIDA CHANGE ORDER NO: 6 BOARD REGULAR Project: 1133 - Design-Build Services for US 1/FEC RR Structures for Expansion of Runway 9R Contract:

More information

D Sample Notices to Property Owners, Sample Affidavits, and Other Material

D Sample Notices to Property Owners, Sample Affidavits, and Other Material D Sample Notices to Property Owners, Sample Affidavits, and Other Material These samples are offered to illustrate specific points in the Desk Reference. States and communities should examine them carefully

More information

APPENDICES G) DETAILED BACKBONE INFRASTRUCTURE CONSTRUCTION COST ESTIMATE SUMMARY

APPENDICES G) DETAILED BACKBONE INFRASTRUCTURE CONSTRUCTION COST ESTIMATE SUMMARY ALAMEDA POINT MASTER INFRASTRUCTURE PLAN March 31, 2014 APPENDICES G) DETAILED BACKBONE INFRASTRUCTURE CONSTRUCTION COST ESTIMATE SUMMARY Carlson, Barbee & Gibson, Inc. Backbone Infrastructure Engineer

More information

Master Plan Study Update OKI Regional Planning Forum February 24, 2012. Get here. Get there. Get home.

Master Plan Study Update OKI Regional Planning Forum February 24, 2012. Get here. Get there. Get home. Master Plan Study Update OKI Regional Planning Forum February 24, 2012 1 Agenda Master Plan Process Forecast Review Terminal Area Alternatives Discussion Next Steps 2 Forecast Discussion Baseline Forecast

More information

TD AMERITRADE Park Omaha

TD AMERITRADE Park Omaha TD AMERITRADE Park Omaha November 19, 2009 Report No. 6 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment

More information

Measurement Standards for Structures

Measurement Standards for Structures DALLAS/FT. WORTH INTERNATIONAL AIRPORT Measurement Standards for Structures November 2002 Updated: September 2003 Planning & Real Estate Department Table of Contents Standards for Measurements of Constructed

More information

REAL ESTATE DUE DILIGENCE CHECKLIST

REAL ESTATE DUE DILIGENCE CHECKLIST REAL ESTATE DUE DILIGENCE CHECKLIST October 2010 P.O. Box 2228 Baton Rouge, LA 70821 225.387.8605 www.charterschooltools.org info@charterschooltools.org Copyright 2010, Charter School Tools. All rights

More information

SAN FRANCISCO AIRPORT COMMISSION MINUTES

SAN FRANCISCO AIRPORT COMMISSION MINUTES SAN FRANCISCO AIRPORT COMMISSION MINUTES July 19, 2011 9:00 A.M. Room 400 - City Hall #1 Dr. Carlton B. Goodlett Place (400 Van Ness Avenue) City and County of San Francisco EDWIN M. LEE, MAYOR COMMISSIONERS

More information

HOWARD UNIVERSITY. I. Policy Statement. II. Rationale. III. Entities Affected by the Policy. IV. Definitions. Policy Number: 300-004

HOWARD UNIVERSITY. I. Policy Statement. II. Rationale. III. Entities Affected by the Policy. IV. Definitions. Policy Number: 300-004 HOWARD UNIVERSITY Policy Number: 300-004 Policy Title: ASSET CAPITALIZATION Responsible Officer: Chief Financial Officer Responsible Offices: Office of the Controller, Departments of Strategic Sourcing

More information

MEASURE G-2010 EXHIBIT B FULL TEXT BALLOT PROPOSITION OF THE SAN JOSE EVERGREEN COMMUNITY COLLEGE DISTRICT BOND MEASURE ELECTION NOVEMBER 2, 2010

MEASURE G-2010 EXHIBIT B FULL TEXT BALLOT PROPOSITION OF THE SAN JOSE EVERGREEN COMMUNITY COLLEGE DISTRICT BOND MEASURE ELECTION NOVEMBER 2, 2010 MEASURE G-2010 EXHIBIT B FULL TEXT BALLOT PROPOSITION OF THE SAN JOSE EVERGREEN COMMUNITY COLLEGE DISTRICT BOND MEASURE ELECTION NOVEMBER 2, 2010 To better prepare San Jose City College/ Evergreen Valley

More information

PLUMMER ELEMENTARY SCHOOL

PLUMMER ELEMENTARY SCHOOL INITIAL YEAR BUILT 1959 BUILDING AREA 69,400 SF CURRENT PROGRAM CAPACITY 481 ENROLLMENT 2008 228 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan PLUMMER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

Charlotte County Airport

Charlotte County Airport Charlotte County Airport Origin Originally acquired by Charlotte County in early 1940s County leased the property to the US Army during WWII Army improvements were deeded back to the County as Surplus

More information

FISCAL YEAR 2013 / WORK PLAN

FISCAL YEAR 2013 / WORK PLAN work plan City of Eugene Central Services Department Facility Management Division FISCAL YEAR 2013 / WORK PLAN City of Eugene Central Services Department Facility Management Division 210 Cheshire Avenue

More information

Information for Construction Contractors. Terry O Neill Taxpayer Service Specialist

Information for Construction Contractors. Terry O Neill Taxpayer Service Specialist Information for Construction Contractors Terry O Neill Taxpayer Service Specialist Today s Webinar Definitions and details 4 types of contractors Sales tax for each type of contractor Materials, Equipment,

More information

Info NEWS MEDIA GUIDE

Info NEWS MEDIA GUIDE Info Office of Public Affairs Miami-Dade Aviation Department P.O. Box 592075 Miami, Florida 33159 Phone: (305) 876-7017 Fax: (305) 869-1270 www.iflymia.com NEWS MEDIA GUIDE Table of Contents Introduction.............................

More information

Evanston Main Street Station TOD Plan and Study. Appendix A.1: Station Area Existing Conditions

Evanston Main Street Station TOD Plan and Study. Appendix A.1: Station Area Existing Conditions Evanston Main Street Station TOD Plan and Study Appendix A.1: Station Area Existing Conditions EvanstonMainStreetStation TODPlanandStudy A 1 AppendixA.1: ExistingConditions Table of Contents Station Locations

More information

Five Year Capital Plan

Five Year Capital Plan Five Year Capital Plan Fiscal Year 2010/11 Fiscal Year 2014/15 Business and Finance Division Five-Year Capital Plan Fiscal Year 2010-11 Fiscal Year 2014-15 3 Table of Contents 1. Executive Summary...1

More information

Basic Airport Security Awareness

Basic Airport Security Awareness Basic Airport Security Awareness Mineta San Jose International Airport Training Standards Program Division of Employee Services, Safety & Training Mineta San Jose International Airport Key Points: The

More information

NOTICE TO CONTRACTORS

NOTICE TO CONTRACTORS NOTICE TO CONTRACTORS Notice is hereby given that San Luis Obispo County Community College District, ( District ) is accepting sealed Informal Bidding Prequalification Applications and Formal Bidding Prequalification

More information

MICHIGAN AIRPORT DEVELOPMENT PROGRAM PACKAGE MDOT Office of Aeronautics. Airport Capital Improvement Plan 2014-2018

MICHIGAN AIRPORT DEVELOPMENT PROGRAM PACKAGE MDOT Office of Aeronautics. Airport Capital Improvement Plan 2014-2018 MICHIGAN AIRPORT DEVELOPMENT PROGRAM PACKAGE MDOT Office of Aeronautics Airport Capital Improvement Plan 20142018 Prepared for: West Michigan Regional Airport Holland, Michigan August 2013 Contact: Mr.

More information

GENERAL SERVICES AGENCY GOALS, OBJECTIVES AND ACCOMPLISHMENTS FISCAL YEAR 2007-2008

GENERAL SERVICES AGENCY GOALS, OBJECTIVES AND ACCOMPLISHMENTS FISCAL YEAR 2007-2008 GENERAL SERVICES AGENCY GOALS, OBJECTIVES AND ACCOMPLISHMENTS FISCAL YEAR 2007-2008 GSA Mission Statement The General Services Agency assists in providing the foundation upon which County Government is

More information

Regional Rail Briefing. March 24, 2010

Regional Rail Briefing. March 24, 2010 Regional Rail Briefing March 24, 2010 Agenda o o o o o o o Welcome Special Greetings Overview of High Speed Rail for Florida Station Representatives Responses -Orlando International Airport (OIA) -Orange

More information

SECTION 31 20 00 EARTH MOVING

SECTION 31 20 00 EARTH MOVING SECTION 31 20 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for excavating, filling, and grading for earthwork at Parking Structure, new exit stair and as required to

More information

REQUEST FOR PROPOSAL FOR PROFESSIONAL SERVICES (PS-0748-A) Appendix 1 Project Information. PS-0748-A Page 1 5/4/2016 Appendix 1

REQUEST FOR PROPOSAL FOR PROFESSIONAL SERVICES (PS-0748-A) Appendix 1 Project Information. PS-0748-A Page 1 5/4/2016 Appendix 1 REQUEST FOR PROPOSAL FOR PROFESSIONAL SERVICES (PS-0748-A) Project Information PS-0748-A Page 1 5/4/2016 Table of Contents Project Budget Worksheet Program Plan Project Location (Site Plan) Scope of Services

More information

OPTIMUS WORK CLASSIFICATION LIST ENTER ALL THAT APPLY

OPTIMUS WORK CLASSIFICATION LIST ENTER ALL THAT APPLY Cost Code # Description Cost Code # Description 01 00 00.001 General Requirements 02 00 00.001 Existing Conditions 01 31 19.13.001 Preconstruction Meetings 02 21 00.001 Surveys 01 32 33.001 Photographic

More information

Request for Qualifications for Program Management Support Services for The Greenville-Spartanburg International Airport Terminal Improvement Program

Request for Qualifications for Program Management Support Services for The Greenville-Spartanburg International Airport Terminal Improvement Program Request for Qualifications for Program Management Support Services for The Greenville-Spartanburg International Airport Terminal Improvement Program SECTION 1 - GENERAL INFORMATION The Greenville-Spartanburg

More information

The fees listed below are stand-alone fees. Additional Developemnt Review or Stormwater fees may apply. 1.0. Fee Activity

The fees listed below are stand-alone fees. Additional Developemnt Review or Stormwater fees may apply. 1.0. Fee Activity MINOR & MISCELLANEOUS PERMITS The fees listed below are stand-alone fees. Additional Developemnt Review or Stormwater fees may apply. 1.0 Fee Activity Fee Description Fee 50% REDUCED FEES FOR SINGLE FAMILY

More information

Construction Management Association of America San Diego Chapter

Construction Management Association of America San Diego Chapter Construction Management Association of America San Diego Chapter An Overview of 2015-2019 Capital Improvement Program Presented by: Iraj Ghaemi, P.E., Director Facilities Development November 13, 2014

More information

Advisory Circular Updates Airport Planning and Environmental Division (APP-400)

Advisory Circular Updates Airport Planning and Environmental Division (APP-400) Advisory Circular Updates Airport Planning and Environmental Division (APP-400) Danielle J. Rinsler, AICP Kent Duffy FAA Office of Airports December 11, 2013 Advisory Circular Update Context As of 2012,

More information

TO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: ACTION ITEM

TO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: ACTION ITEM GB6 Office of the President TO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: For Meeting of September 17, 2013 ACTION ITEM APPROVAL OF PRELIMINARY PLANS FUNDING, BLAKE HOUSE RENOVATIONS, REPAIR, AND

More information

RULES AND REGULATIONS CONTRACTOR WORK

RULES AND REGULATIONS CONTRACTOR WORK RULES AND REGULATIONS CONTRACTOR WORK CARILLON 227 West Trade Street Suite 330 Charlotte, NC 28202 The following Rules and Regulations shall govern the operation of contractor work in the Building. For

More information

Capital Improvement at Tampa International Airport Underway

Capital Improvement at Tampa International Airport Underway SUMMER 2015 A PUBLICATION BY LEA+ELLIOTT TRANSPORTATION CONSULTANTS Capital Improvement at Tampa International Airport Underway Rendering of the future APM station at Tampa International Airport s Main

More information

C-2 Construction, Inc. - NAICS Codes

C-2 Construction, Inc. - NAICS Codes C-2 Construction, Inc. - NAICS Codes 212313 - Crushed and Broken Granite Mining and Quarrying This U.S. industry comprises: (1) establishments primarily engaged in developing the mine site, and/or mining

More information

VEHICLE CROSSOVER INFORMATION PACK

VEHICLE CROSSOVER INFORMATION PACK VEHICLE CROSSOVER INFORMATION PACK CONTENTS Introduction Section A Section B Section C Section D Section E Criteria for approving a vehicle crossover application (Diagrams to demonstrate measurement criteria)

More information

The Authority is required to develop a Strategic Business Plan document after each approved Master Plan.

The Authority is required to develop a Strategic Business Plan document after each approved Master Plan. The Authority is required to develop a Strategic Business Plan document after each approved Master Plan. The Board approved the 2012 Master Plan at the April 2013 Board meeting. The 2013 Strategic Business

More information

Accounting and Administrative Manual Section 100: Accounting and Finance

Accounting and Administrative Manual Section 100: Accounting and Finance No.: A-25 Page: 1 of 8 General: This policy establishes guidelines for determining when certain expenditures should be capitalized as capital assets and specifies the university s depreciation policy.

More information

SCHEDULE A BY-LAW B-6 CLASSES OF PERMITS AND FEES

SCHEDULE A BY-LAW B-6 CLASSES OF PERMITS AND FEES 1. CALCULATION OF PERMIT FEES SCHEDULE A BY-LAW B-6 CLASSES OF PERMITS AND FEES Permit fees shall be calculated based on the formula given below, unless otherwise specified in this schedule: Permit Fee

More information

Greater Orlando Aviation Authority Buildings. Orlando International Airport Orlando, Florida, USA

Greater Orlando Aviation Authority Buildings. Orlando International Airport Orlando, Florida, USA Greater Orlando Aviation Authority Buildings Orlando International Airport Orlando, Florida, USA 800 flights per day on 40+ commercial airlines 13 th busiest airport in the U.S. / 29 th busiest in the

More information

Description Quantity Cost Total Cost

Description Quantity Cost Total Cost APPENDIX: ITEMIZED CONSTRUCTION COST ESTIMATE Description Quantity Cost Total Cost 1 CASCADE FALLS 1a Existing Cascade Falls Upgrades Structural Repairs - Steps, Railing, Walls, Pool Lump Sum $500,000

More information

COMMERCIAL AND GENERAL AVIATION

COMMERCIAL AND GENERAL AVIATION Existing Facilities Melbourne International Airport is served by three runways and a number of airside and landside facilities. The runways include Runway 05/23 (3,001 feet long by 75 feet wide), Runway

More information

City of Valdosta Land Development Regulations. Table of Contents

City of Valdosta Land Development Regulations. Table of Contents TITLE 1 ADMINISTRATION Chapter 102 General Provisions 102-1 Title 102-2 Purpose 102-3 Authority 102-4 Jurisdiction 102-5 Application of Ordinance 102-6 Relationship to Existing Ordinances 102-7 Powers

More information

Executive Management Program Status Report. January 31, 2016

Executive Management Program Status Report. January 31, 2016 Executive Management Program Status Report January 31, 2016 TABLE OF CONTENTS Element Overview Airside Element Utilities & Landside Element Terminal Element MSC Element Tenant Improvement Element Program

More information

TENDER FOR IT INTEGRATION AT THE BVI AIRPORTS AUTHORITY

TENDER FOR IT INTEGRATION AT THE BVI AIRPORTS AUTHORITY TENDER FOR IT INTEGRATION AT THE BVI AIRPORTS AUTHORITY Background BVI Airport Authority is presently owns and operates 3 airports in British Virgin Islands by providing passengers a safe and secure gateway

More information

Information Bulletin No. 4 What happens over the life of a building?

Information Bulletin No. 4 What happens over the life of a building? Information Bulletin No. 4 What happens over the life of a building? This series of Building Asset Management bulletins form part of a 3-year research project for corporations and managers. The bulletins

More information

Services outsourced in 2013 to a third-party firm (not including parts, equipment purchased). Type of Service

Services outsourced in 2013 to a third-party firm (not including parts, equipment purchased). Type of Service Outsourcing Services outsourced in 2013 to a third-party firm (not including parts, equipment purchased). Type of Service Abandoned Vehicle Auction Auctioneer Accounts Payable Services Actuarial Services

More information

City of Treasure Island FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage

City of Treasure Island FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage City of Treasure Island FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage Property Address: Company Name: Contractor Name: Contractor Address: City: State: Zip: License Number: Phone Number

More information

APPLICATION FOR NON-SUBSTANTIAL DAMAGE / IMPROVEMENT REVIEW

APPLICATION FOR NON-SUBSTANTIAL DAMAGE / IMPROVEMENT REVIEW APPLICATION FOR NON-SUBSTANTIAL DAMAGE / IMPROVEMENT REVIEW Parcel Number: Owner s Name: Co-Owner s Name: Owner s Mailing Address: Owner Phone Number: FIRM Panel: Lowest Floor Elevation (excluding garage):

More information

Liquid Effluent Treatment Plant (LETP) Land Clean-Up

Liquid Effluent Treatment Plant (LETP) Land Clean-Up Liquid Effluent Treatment Plant (LETP) Land Clean-Up Frequently Asked Questions What is proposed? Magnox Ltd is proposing to remove the redundant Liquid Effluent Treatment Plant (LETP) at Harwell and to

More information

Plan of Construction Operations (PCO)

Plan of Construction Operations (PCO) REQUEST FOR PROPOSAL APPENDIX G Plan of Construction Operations 13 006 A Taxi A Expansionn CLIENT: TradePort International Corporation, Operators of John C. Munro Hamilton International Airport (YHM) April

More information

Robert D. Trimborn Airport Director Santa Monica Airport

Robert D. Trimborn Airport Director Santa Monica Airport Robert D. Trimborn Airport Director Santa Monica Airport Association of California Airports Conference - September 18, 2009 Noise Air Emissions Ground Support Equipment Alternative Fuels and Green

More information

SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM

SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM Shepherd University Board of Governors June 9, 2005 Agenda Item No. 9 SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM In 1994 construction began on the Byrd Science and

More information

LOGAN TERMINAL B SUBSTATION UPGRADE

LOGAN TERMINAL B SUBSTATION UPGRADE AIRPORTS LOGAN TERMINAL E AND HEATING PLANT 5 KV AND 15 KV UPGRADES D 2015 Design replacement of two double-ended substations, HVAC upgrades for six substations, upgrades to 400 hertz gate power central

More information

Welcome. to the Tampa International Airport Sustainability Master Plan Visioning Session

Welcome. to the Tampa International Airport Sustainability Master Plan Visioning Session Welcome to the Tampa International Airport Master Plan Visioning Session To learn more about TPA s Master Plan Project, visit www.tampaairport.com/airport_business/sustainability.asp WHAT IS SustainabilitY?

More information

Request for Proposal East Tower Nursing Unit and Infrastructure Upgrade Grossmont Hospital

Request for Proposal East Tower Nursing Unit and Infrastructure Upgrade Grossmont Hospital Request for Proposal East Tower Nursing Unit and Infrastructure Upgrade Grossmont Hospital June 21, 2007 The Grossmont Healthcare District (GHD) will accept proposals for Architectural and Engineering

More information

AV Parking System Review

AV Parking System Review Exhibit 1 AV Parking System Review May 6, 2011 Report No. 11-01 Office of the County Auditor Evan A. Lukic, CPA County Auditor Table of Contents Contents EXECUTIVE SUMMARY... 3 OBJECTIVES, SCOPE AND PROCEDURES...

More information

DAYBREAK ATTACHED RESIDENCE DISCLOSURE STATEMENTS Acknowledgement of Receipt Form

DAYBREAK ATTACHED RESIDENCE DISCLOSURE STATEMENTS Acknowledgement of Receipt Form Builder Name: Lot Number: Page 1of 6 DAYBREAK ATTACHED RESIDENCE DISCLOSURE STATEMENTS Acknowledgement of Receipt Form These disclosure statements (the Attached Residence Disclosure Statements ) are provided

More information