Office of the County Auditor Evan A. Lukic, CPA County Auditor
|
|
- Charla Joseph
- 7 years ago
- Views:
Transcription
1 Review of Management Services Billings - Terminal 4 Expansion Project Phase 1B at Fort Lauderdale Hollywood International Airport (RLI No AV-01) September 13, 2010 Report No Office of the County Auditor Evan A. Lukic, CPA County Auditor
2 Table of Contents Executive Summary... 2 Purpose and Scope... 3 Methodology... 3 Background... 3 Findings and Recommendations... 9 Office of the County Auditor 1
3 Executive Summary This report summarizes our review of management services billed by Skanska USA Building Inc. (Skanska) under the Terminal 4 Expansion Project Phase 1B agreement (RLI No AV-01). This review was initiated at the request of Broward County Aviation Department (BCAD) personnel for assistance in reviewing amounts billed by Skanska. Our objective was to determine whether the amounts billed were consistent with the terms of the agreement. Our review disclosed: o o o Skanska overbilled the County $464,704. The overbilling was principally related to rates paid to two subcontractors in excess of rates allowable under the contract. Pay applications and supporting schedules did not sufficiently document work performed, certain subcontracted services did not appear to be project related, and other services were not clearly defined in the subcontract. As a result, we were unable to determine the extent to which certain billed services added value, were commensurate with the amounts billed, or were within the scope of the County s contract with Skanska. Skanska s subcontractor agreements did not include provisions mandated by their contract with the County. As a result, we were unable to obtain all documents necessary to thoroughly complete our review of one subcontractor s charges. We recommend the Board of County Commissioners direct the County Administrator to: 1. Deny payment of $464,704 (BCAD has withheld payments to Skanska pending the outcome of this review). 2. Take steps to ensure future pay applications include sufficient documentation to determine whether services are within the scope of the project, add value, and are commensurate with the amounts billed. 3. Strengthen contract compliance by requiring prime contractors to provide evidence that County contract requirements are included in each subcontract. Office of the County Auditor 2
4 Purpose and Scope This review was initiated in response to ongoing concerns of BCAD management. Our objective was to determine whether the amounts billed were consistent with the terms of the agreement. Our review covered the period from April 2006 to August Methodology To accomplish our objectives, we: Reviewed: o The Construction Contract between Skanska USA Building Inc. and Broward County dated December 13, 2005 (including all amendments), o Agreements between Skanska and its three subcontractors performing management services, o Selected pay applications, including underlying management services invoices from Skanska and its subcontractors, o Skanska and subcontractors payroll registers and other supporting documentation, o January 2009 and February 2009 recorded tapes of negotiation meetings between BCAD and Skanska, o BCAD s memorandum summarizing the review of Management Services, dated June 26, 2009, and o Skanska s Audited Financial Schedules 1 and Report of Independent Certified Public Accountant (CPA) dated June 19, Interviewed Skanska staff and two of their subcontractors, BCAD, and Keith and Associates, Inc. (Project Manager). Background Contract Summary On December 13, 2005, the Board of County Commissioners (Board) approved a contract with Skanska USA Building Inc. (Skanska) as the Construction Manager at Risk (CM@Risk) 2 for the Terminal 4 Expansion Project at the Fort Lauderdale-Hollywood International Airport, awarded under RLI No AV-01. The contract, for pre- 1 Financial schedules were prepared consistent with the Federal Acquisition Regulation (FAR) guidelines for Cost & Pricing data. 2 CM@Risk is a delivery method that entails a commitment by the Construction Manager to deliver the project within a Guaranteed Maximum Price. In addition to acting in the owner's interest, the construction manager must manage and control construction costs to not exceed the GMP. Office of the County Auditor 3
5 construction services and early work, was approved in the amount of $12.5 million. The parties entered into this contract before design documents were sufficiently completed to establish a Guaranteed Maximum Price (GMP) for the project. Therefore, it was anticipated that one or more addenda would be executed to establish a GMP and incorporate the documents fully describing the scope of work. On April 17, 2007 the Board approved an addendum to the contract establishing a GMP contract price of $34.9 million and 500 days for contract completion. On March 12, 2009 the Board approved the first amendment to the contract addendum increasing the GMP to $42.2 million and extending the project completion period to 806 days. The contract price elements approved in the original contract, addendum and amendment are summarized in Table 1 below: Table 1 Summary of Contract Price Elements Terminal 4 Expansion Project Contract Price Elements Original Construction Contract 12/13/2005 GMP Addendum 4/17/2007 First Amendment 3/12/2009 Estimated Direct Construction Cost $ $ 22,366,342 $ 28,283,440 Contractor s General Conditions 2,437,065 2,667,489 County s Early Construction Allowance 12,265,080 [Note 1] Management Services 3,007,469 4,816,040 Lump-sum Pre-Construction Services 148, , ,639 Reimbursable Pre-Construction Costs 100, , ,000 Contractor s Fixed Fee (4%) 1,299,835 1,531,937 County s Allowance Account 4,385,000 3,752,280 Document Completion Allowance 300, ,737 Construction Contingency 834, ,167 TOTAL $ 12,513,719 $ 34,878,676 $ 42,179,729 Source: Schedule Prepared by Office of the County Auditor using Contract Price Elements Note 1: The $12,265,080 in Early Construction Allowance was included in Estimated Direct Construction Cost as part of the Addendum approved by the Board on April 17, Contract Phases The original contract and addendum required Skanska to provide services for four phases of work: preconstruction services, construction, post construction, and warranty services. Office of the County Auditor 4
6 Preconstruction Services - This phase of the contract requires Skanska to: Review the contract documents, project requirements, existing on-site and off-site development, and surveys, Perform cost estimates and value engineering, Make recommendations to the County regarding constructability, staging, phasing, maintenance of airport operations, and maintenance of traffic during construction, and Prepare project schedules for all phases of the contract and bid packages for construction cost estimates to cover the scope of work of the project. Construction Services - This phase of the contract requires Skanska, as the CM@Risk, to provide management services, bid major subcontracts, hire subcontractors to perform the scope of services pursuant to the contract documents which include the technical specifications, drawings, general conditions, change orders, field orders, submittals and to be responsible for compliance with jobsite and worker safety requirements. Post-Construction Services - This phase of the contract requires Skanska to coordinate: Project close-out, including cooperating with preparation of the Certificates of Substantial and Final Completion, Completion of all punch list 3 items, warranty provisions, and Maintenance & Operational Manuals, Commencement of operations, and Transition to occupancy by the County and its tenants. Warranty Services - This phase of the contract requires Skanska to participate with County representatives in warranty inspections in the sixth and eleventh months after substantial completion. 4 Further, Skanska is responsible for coordinating and scheduling all warranty and service work. Management Services This review focused on reviewing the accuracy of management services invoices billed under the contract. In general, management services include staffing to provide project oversight for each of the phases listed above. For these services, allowable expenses include salaries for 21 staff positions such as a Project Executive, Engineers, and Estimators. For each hour of service provided, Skanska is permitted to bill the hourly rate 3 A "punch list" represents a summary of uncompleted or unsatisfactory work items. Examples of punch list items include damaged building components or problems with the final installation of building materials. 4 Article 1.28 of the contract defines Substantial Completion as the date certified in writing that indicates that the work is sufficiently complete in accordance with the contract documents and the project is available for use or occupancy by County for its intended purpose. A certificate of occupancy or temporary certificate of occupancy must be issued for substantial completion to be achieved. Office of the County Auditor 5
7 derived from salary plus defined burden rates for fringe benefits 5 consistent with the FAR guidelines. To determine the burden rate 6 for fringe benefits, the contract requires Skanska to provide the County with audited financial schedules of fringe benefits, and other allowable costs, within 90 days of the approval of the contract. While the majority of the management services were provided by Skanska s employees, some duties were performed by five staff positions 7 via contracts with three subcontractors. For each hour of service, the subcontractors billed Skanska at the rates in their contract with Skanska. The County contract provides for subcontractor rates based on the cost of work 8 plus overhead and profit. The contract limits the aggregate of the subcontractors' overhead and profit to fifteen percent (15%) of the subcontractors' cost of the work. The subcontractor s overhead and profit is in addition to the overhead and profit paid to Skanska in accordance with the agreement 9. During the term of the contract certain amounts billed by Skanska were contested by BCAD. Table 2 on page 7 depicts the chronology of events affecting payments for management services during the term of the contract. For example, in response to the failure to submit the certified schedules of fringe benefits, the County suspended payments for labor burden. In another instance, the County suspended payments for management services when there were concerns that billings were not commensurate with the progress of construction (earned value). 5 Article 33.2 of the contract states that fringe benefits include: sick leave, vacation, holiday, unemployment, excise and payroll taxes, contribution to social security, retirement benefits, etc. 6 The contract specified an initial fringe benefit factor/ burden rate of 50.68%. This percentage was later established as 50.04% with the audited financial schedules provided by Skanska dated June 19, The five staff positions filled by subcontractors include an Engineer, Assistant Superintendent, Senior Project Coordinator, Administrative Assistant, and a Project Executive 8 Cost of work represents hourly payroll rates plus fringe benefits. 9 The contract provided for $2,667,489 in General Conditions (Overhead) and Contractor Fees of $1,531,937 (Profit). Office of the County Auditor 6
8 Table 2 Chronology of Events Affecting Payments for Management Services April 2006 to February 2010 Number Dates of Description of Events Months April 2006 to June 2007 July 2007 to April Management services billed by Skanska and paid by the County based on hourly rates plus burden/fringe factor of 50.68%. In July 2007, the County suspended payment of the burden (fringe factor) because Skanska did not provide certified schedules of fringe benefits within 90 days as required by the contract. Management services billed by Skanska were paid by the County based on hourly rates without additional payment for burden. May 2008 to November Payments for management service were suspended because BCAD determined that billings were not commensurate with the percentage of construction completed. August 2008, BCAD requested the County Auditor to review Management Services costs billed in pay applications 28 and 29. The First Amendment to the contract approved by the Board on March 12, 2009, authorized the following: March 2009 A lump-sum amount of $1,533,228, for management service fee to cover the period March 2009 to February 2010 payable in 12 equal monthly installments of $127,769. $343,538 in retroactive payments for management services billed by subcontractors between May and November $214,757 for unpaid burden/fringe factor during the suspension period above. The amount was calculated using the certified fringe factor rate of 50.04%. The amendment required invoices, cancelled checks, payroll registers, time sheets, etc. to substantiate the costs billed. Retroactive lump-sum payment of $200,000 in management services for the period December 2008 to February 2009, payable as follows: o $100,000 upon approval of the first amendment and issuance of the Notice to Proceed, and o $100,000 no later than 30 days after achieving timely Substantial Completion. July 2009 BCAD identified overbilled amounts totaling $142,397 for services billed by two subcontractors. On July 10, 2009 BCAD requested County Auditor s assistance in reviewing amounts billed by Skanska and has withheld payment pending completion of this review. Source: Schedule prepared by Office of the County Auditor Office of the County Auditor 7
9 Management Services Billing Process Skanska and its subcontractors reported the following procedures for documenting hours and invoicing for services under this contract: Skanska s employees assigned to the County project enter the hours worked by project number in Skanska s electronic job cost system. The job cost system is a subset of the payroll system. At the end of the month, the accountant reviews the hours for accuracy, making adjustments where necessary for non chargeable hours such as: holiday, sick-time and vacation. The accountant then prepares a manual time sheet showing the hours for each employee, which is then signed by both the employee and supervisor. The accountant tallies the total hours for each employee and calculates the billable amount by multiplying the number of hours by the hourly rates provided by the Project Manager 10. The accountant prepares a schedule listing the employee names, total hours worked, hourly rates, and the fully burdened billable amount which includes the burden/fringe factor. Subcontractors employees prepare time sheets that document hours worked on the project. The time sheets are signed by the employee and supervisory personnel from both Skanska and the subcontractors. At the end of the month, the subcontractors tally the hours for each employee and prepare an invoice to Skanska at the hourly rates included in the agreements between Skanska and the subcontractors. Monthly Pay Applications Skanska is required by Article 6.1 of the contract to bill the County on a monthly basis. Skanska s accountant prepares the monthly pay application, including: The schedule showing management services provided by Skanska along with underlying time sheets, Invoices for management services from the three subcontractors with the supporting time sheets, Direct construction costs plus supporting documentation, Contractor s general conditions, The contractor s fee of four percent, and A deduction for retainage, as required by the contract. 10 The Project Manager named in the original contact was URS Corporation (URS was Project Manager through December 2008). The Project Manager was changed to Keith & Associates, Inc. in January 2009 (approved in the First Amendment). Office of the County Auditor 8
10 The pay applications are reviewed and approved by the Project Manager and BCAD personnel and are then forwarded to the Accounting Division for payment. The resulting vendor checks are mailed directly to Skanska. Current Project Status During the period December 2005 to February 2010, the County paid Skanska approximately $35.2 million which includes management services fees of approximately $4 million (11.4%). The project achieved Substantial Completion on January 23, 2010 and Final Completion on March 24, Table 3 below summarizes expenditures through February 28, Table 3 Payments to Skanska through February 28, 2010 Terminal 4 Expansion Project DESCRIPTION ALLOWABLE CONTRACT AMOUNT AMOUNT BILLED RETAINAGE AMOUNT PAID BALANCE Direct Construction Cost $ 29,335,595 $29,098,429 $ 1,964,816 $27,133,613 $ 237,166 Contractor s General Conditions 2,682,898 2,562,860 2,562, ,038 Management Services 4,819,464 4,009,598 4,009, ,866 Document Completion Allowance 599, ,550 County Early Construction Allowance 2,753,197 2,753,197 Contractors Fixed Fee 1,544,108 1,426, ,281 1,284, ,236 Lump-Sum Pre-Construction Services 148, ,639 14, ,775 0 Reimbursable Pre-Construction Costs 100,000 92,941 92,941 7,059 Construction Contingency 259, ,010 TOTAL $42,242, $37,339,339 $ 2,121,961 $35,217,378 $4,903,122 Source: Schedule prepared by Office of the County Auditor from information provided by BCAD Findings and Recommendations Finding 1. Skanska overbilled the County $464,704. A. Skanska s invoices included $410,684 of overbillings because rates charged by two subcontractors were in excess of the rates permitted by the County s contract. Articles and 16.1 of the contract state the rate charged by subcontractors represents the cost of work plus overhead and profit, and in no event shall the aggregate 11 The amount includes 13 change orders totaling $62,732 issued since the first amendment was approved on March 12, Office of the County Auditor 9
11 of the subcontractors' overhead and profit markups exceed fifteen percent (15%) of the subcontractors' cost of the work. We reviewed invoices totaling approximately $845,900 for work performed by two subcontractors during our review period from April 2006 to August We reviewed the subcontractors agreements and requested schedules 12 showing the fringe, overhead and profit information for the review period. One subcontractor provided the requested information for 2006, 2007, 2008, and The second subcontractor provided only a schedule for 2007; as a result, our review for this subcontractor was limited. For all invoices during the review period, we traced the hours billed to time sheets, validated pay rates to the payroll registers, and applied the fringe, overhead, and profit percentages 13 in accordance with the contract provisions in Article We also recalculated management services fees. Our review found the County was overbilled $410,684 because the subcontractors billing rates were not based on their actual cost, overhead and profit as required by Skanska s contract with the County. There was no apparent relationship between the rates billed to the County and rates actually paid to employees. B. Skanska s invoices did not reflect actual hours and pay rates resulting in net overbillings to the County of $44,299. We reviewed approximately $779,300 in invoices for management services for work performed directly by Skanska during 11 of the 25 months between April 2006 and April We reviewed the hours documented on time sheets; agreed hours billed to Skanska s electronic job cost system, validated pay rates to the payroll registers, applied the burden/fringe factor, and recalculated the management services fees for the sample invoices. Our review found that hours billed to the County by Skanska exceeded the hours charged to the project in Skanska job cost system and the billed rates varied from the rates in Skanska s payroll register. We utilized the hours 14 and actual payroll rates documented in the job cost and payroll systems and found the County was overbilled $44,299 C. The Skanska invoice for unpaid labor burden was overstated by $9,721. Exhibit 3 of First Amendment, approved by the Board on March 10, 2009, provided for payment of labor burden totaling $214,757 for the ten-month period from July 2007 to April This figure represented amounts billed by Skanska for the period when payment for 12 A FAR audit exemption request was approved by the County Auditor on May 5, 2008 for the two Subcontractors performing management services. 13 Due to the subcontractor s failure to provide information as requested we applied the 2007 fringe, overhead and profit percentages to invoices for 2006, 2008, and Vacation, holidays, and training hours erroneously coded to thet4 project in the Skanska s Job Cost and Payroll System were adjusted during the review. Office of the County Auditor 10
12 burden was suspended by the County because Skanska failed to submit certified schedules of fringe benefits as required by the contract. We reviewed invoices for three of the ten months of the suspension, recalculated the labor burden and found Skanska overbilled the County by $9,721. Table 4 below summarizes the amounts overbilled: Table 4 Summary of Amounts Overbilled Description Amount A. Subcontractors Excess Rates $ 410,684 B. Skanska Hours & Rates > Actual 44,299 C. Skanska Unsupported Labor Burden 9,721 Total Overbilled $ 464,704 Source: Schedule prepared by Office of the County Auditor BCAD has withheld payment to Skanska pending the results of this review. Recommendation 1. We recommend the Board of County Commissioners direct the County Administrator to deny payment of $464,704. Finding 2. We were unable to determine the extent to which certain billed services added value, were commensurate with the billed amounts, or were within the scope of the County s contract with Skanska. A. Invoices and supporting schedules did not document the work performed. Article 33.2 of the GMP Addendum approved by the Board on April 17, 2007, states management services shall be paid for as shown in Exhibit 3 and 3-1 for all personnel engaged directly on the project for time directly attributable to the project or the work and services described in a work authorization. We found management services invoices did not contain sufficient supporting documentation to verify the work performed. Skanska s and subcontractors Office of the County Auditor 11
13 invoices submitted to the County typically contained a schedule listing the staff members, the total number of hours worked, and their hourly rates along with time sheets. The invoices did not include descriptions of work performed. This information is essential to determine if the services were actually provided, added value, were commensurate with the billed amounts or were consistent with the agreed upon scope of services. B. Certain subcontracted services did not appear to be project related; other services were not clearly defined in the subcontract. i. The scope of services in one subcontractor agreement did not appear to be consistent with the management services required by the contract between Skanska and the County. We noted the subcontract provides for services including: Establishment of a library of available certified Disadvantaged Business Enterprise (DBE) contractors. Coordination of outreach initiative to recruit DBE contractors. Promotion of Skanska s DBE program within the business community. These services do not appear to add value to the project because the County has an existing library of DBEs which is available to Skanska and the outreach initiative and promotion of Skanska s DBE program do not appear to be project related. ii. While the scope of services in one other subcontract was vague providing services, limited to consulting to Skanska for the Ft Lauderdale Airport projects. This subcontractor was billed as the project executive. As noted above, the invoices did not include descriptions of work performed and as a result, we could not verify the nature of services actually provided. Recommendation 2. We recommend the Board of County Commissioners direct the County Administrator to take steps to ensure future pay applications include sufficient documentation to determine whether services are within the scope of the project, add value, and are commensurate with the amounts billed. Office of the County Auditor 12
14 Finding 3. Skanska s subcontractor agreements did not include provisions mandated by their contract with the County. Article 25.3 of the Skanska contract states the Contractor (Skanska) shall require subcontractors to keep and maintain comparable project records for the same time period and to permit the County to review, inspect, and audit such records. The contract specifically states that the Contractor shall include such requirements in all written subcontracts and purchase orders issued. We reviewed the agreements between Skanska and three subcontractors and found the agreements did not include the requirements to keep and maintain project records and permit the County to review such records. As noted above in finding one, we were not successful in obtaining all documents necessary to fully complete our review of one subcontractor s charges. Recommendation 3. We recommend the Board of County Commissioners direct the County Administrator to strengthen contract compliance by requiring prime contractors to provide evidence that County contract requirements are included in each subcontract. Office of the County Auditor 13
Review of Janitorial Services Contract at the Fort Lauderdale-Hollywood International Airport (RLI # 20070522-0-AV-2)
Review of Janitorial Services Contract at the Fort Lauderdale-Hollywood International Airport (RLI # 20070522-0-AV-2) March 23, 2011 Report No. 11-04 Evan A. Lukic, CPA County Auditor Table of Contents
More informationOffice of the County Auditor Evan A. Lukic, CPA County Auditor
Exhibit 1 B FLO R I DA Review of Hourly Labor Rates - Craven, Thompson and Associates, Inc. Consultant Services Contract for North County Neighborhood Improvement Project Northeast Quadrant February 6,
More informationREQUEST FOR PROPOSAL TO PROVIDE CONSTRUCTION MANAGEMENT AND GENERAL CONTRACTOR SERVICES SPRINGVILLE CITY NEW AQUATICS AND ACTIVITIES CENTER
RFP #2016-02 REQUEST FOR PROPOSAL TO PROVIDE CONSTRUCTION MANAGEMENT AND GENERAL CONTRACTOR SERVICES FOR SPRINGVILLE CITY NEW AQUATICS AND ACTIVITIES CENTER RELEASE DATE: January 29, 2016 DUE DATE: February
More informationOP-B-11-D2 ADMINISTRATION OF CONSTRUCTION MANAGER AGREEMENTS
OP-B-11-D2 ADMINISTRATION OF CONSTRUCTION MANAGER AGREEMENTS SPECIFIC AUTHORITY Sections 240.209(3)(p), 1001.74, 1013.46, F. S. OBJECTIVE To establish procedures for the administration of construction
More informationArchitect and Engineering Consultant Negotiations and Contracting Recommendations
Exhibit 1 Architect and Engineering Consultant Negotiations and Contracting Recommendations March 5, 2015 Report No. 15-8 Office of the County Auditor Evan A. Lukic, CPA County Auditor Table of Contents
More informationDEMO Version. Owner and Contractor OCNMP103
Page 1 of 12 AGREEMENT made as of the in the year of (In words, indicate day, month and year) day of BETWEEN the Owner: (Name, address and other information) DEMO Version and the Contractor: (Name, address
More informationReview of Miscellaneous Income Reporting to the Internal Revenue Service
Review of Miscellaneous Income Reporting to the Internal Revenue Service July 19, 2010 Report No. 10-12 Office of the County Auditor Evan A. Lukic, CPA County Auditor Table of Contents Topic Page Executive
More informationThe Commonwealth of Massachusetts AUDITOR OF THE COMMONWEALTH
The Commonwealth of Massachusetts AUDITOR OF THE COMMONWEALTH ONE ASHBURTON PLACE, ROOM 1819 BOSTON, MASSACHUSETTS 02108 A. JOSEPH DeNUCCI AUDITOR TEL. (617) 727-6200 NO. 2008-1461-3A INDEPENDENT STATE
More informationReport on Tasks Performed at the Request of the County Attorney s Office Regarding Broward County s Disadvantaged Business Enterprise (DBE) Program
Report on Tasks Performed at the Request of the County Attorney s Office Regarding Broward County s Disadvantaged Business Enterprise (DBE) Program July 10, 2008 Report No. 08-16 Office of the County Auditor
More informationContractor s Guide. April 2016
Contractor s Guide April 2016 The Minnesota Housing Finance Agency does not discriminate on the basis of race, color, creed, national origin, sex, religion, marital status, status with regard to public
More informationDocument A133 TM. BETWEEN the Owner: (Name, legal status and address) Case Western Reserve University 10900 Euclid Avenue Cleveland, Ohio 44106-7228
Document A133 TM 2009 Standard Form of Agreement Between Owner and Construction Manager as Constructor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price AGREEMENT
More informationTABLE OF CONTENTS OBJECTIVES, SCOPE, AND METHODOLOGY... 1 BACKGROUND... 2. Project Delivery Methodology... 2. Section I Funding Sources...
TABLE OF CONTENTS Page OBJECTIVES, SCOPE, AND METHODOLOGY... 1 BACKGROUND... 2 Project Delivery Methodology... 2 FINDINGS AND RECOMMENDATIONS Section I Funding Sources... 3 Section II Construction Costs...
More informationStandard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum
Document A101 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AGREEMENT made as of the in the year (In words, indicate day, month and year.)
More informationReasons for Change Orders
T E X A S D E PA R T M E N T O F T R A N S P O R TAT I O N A change order is defined in the 2004 Standard Specification Book as a written order to the Contractor detailing changes to the specified work,
More informationAGREEMENT. between BROWARD COUNTY. and. Turner Construction Company. for CONSTRUCTION MANAGEMENT SERVICES FOR VARIOUS AIRPORT PROJECTS (TBD)
AGREEMENT between BROWARD COUNTY and Turner Construction Company for CONSTRUCTION MANAGEMENT SERVICES FOR VARIOUS AIRPORT PROJECTS (TBD) IN BROWARD COUNTY, FLORIDA RLI # 20071014-0-AV-01A INDEX ARTICLE
More informationCHAPTER 15 EQUAL EMPLOYMENT OPPORTUNITY, ON-THE-JOB TRAINING AND PREVAILING WAGES
CHAPTER 15 EQUAL EMPLOYMENT OPPORTUNITY, ON-THE-JOB TRAINING AND PREVAILING WAGES 15.1 OVERVIEW To effectively assure Equal Employment Opportunity (EEO), the Federal Highway Administration (FHWA) requires
More informationAudit of Construction Contract Management Practices
SOUTH FLORIDA WATER MANAGEMENT DISTRICT Audit of Construction Contract Report # 05-10 Prepared by Office of Inspector General John W. Williams, Esq., Inspector General J. Timothy Beirnes, CPA, Director
More informationREQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES. Part I: Proposal Information
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES Part I: Proposal Information A. General Information The Berwick Area School District is soliciting proposals for construction management services
More informationOwner s project control review. 2014 Baker Tilly Virchow Krause, LLP
Owner s project control review 2014 Baker Tilly Virchow Krause, LLP About Baker Tilly > Established in 1931 > One of the top 20 largest accounting and advisory firms in the United States according to Accounting
More informationAGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER-AT-RISK
AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER-AT-RISK MD ANDERSON AGREEMENT No. This Agreement is made as of, 20xx (the Effective Date ), by and between The Owner: M D Anderson Cancer Center c/o Sourcing
More informationRFQ 00318348 NORTHSTAR AUDITING SERVICES ADDENDUM NO. 1 REF. LOCATION DESCRIPTION OF CHANGE. Revised Scope of Work. Work tasks have been revised.
RFQ 00318348 NORTHSTAR AUDITING SERVICES ADDENDUM NO. 1 DATE PUBLISHED: MAY 18, 2016 TO ALL PROSPECTIVE SUBMITTERS: THE FOLLOWING CHANGES ARE MADE: REF. LOCATION DESCRIPTION OF CHANGE Attachment A Attachment
More informationScottsdale Road Improvements, Phase 1
CITY AUDITOR'S OFFICE Scottsdale Road Improvements, Phase 1 October 30, 2015 AUDIT REPORT NO. 1509 CITY COUNCIL Mayor W.J. Jim Lane Suzanne Klapp Virginia Korte Kathy Littlefield Linda Milhaven Guy Phillips
More informationMINNESOTA STATE COLLEGES AND UNIVERSITIES
Projects with an estimated construction cost of $50,000 or less may be bid without advertising. Funding: The College/University must take appropriate action to confirm that funds are available in an active
More informationAGREEMENT BETWEEN THE BOARD OF REGENTS OF THE TEXAS A&M UNIVERSITY SYSTEM AND EVOLVE INFRASTRUCTURE SOLUTIONS, LLC, DESIGN-BUILD CONTRACTOR
DB-BIM Contract No. 5890 07/14 Project No. 02-3210 AGREEMENT BETWEEN THE BOARD OF REGENTS OF THE TEXAS A&M UNIVERSITY SYSTEM AND EVOLVE INFRASTRUCTURE SOLUTIONS, LLC, DESIGN-BUILD CONTRACTOR 1 DB-BIM Contract
More informationDEFINITIONS AND IDENTIFICATIONS
Bn\QWARD I~ el"s COUNTY - AGREEMENT BETWEEN BROWARD COUNTY AND RICONDO AND ASSOCIATES, INC. FOR CONSULTANT SERVICES FOR AIRPORT PLANNING CONSULTANT SERVICES RLI/RFP # R1277902Pl This is an Agreement ("Agreement")
More informationBy accepting this work engagement, consultant certifies that they are not currently working for any state or federal government agency.
Consultant Consultant SS No. (or Tax ID No.) Street Address City, State, Zip Employee Requiring Service Department Term of Agreement When to use this form: This standard agreement may be used for engaging
More informationTHIS AGREEMENT is made effective as of this day of in the year of.
STANDARD FORM OF CONSTRUCTION MANAGEMENT AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER (Where the basis of payment is Cost of the Work with a guaranteed maximum price) THIS AGREEMENT is made effective
More informationDEPARTMENTAL STANDARD OPERATING PROCEDURE Miami-Dade Aviation Department DSOP No. 03-03 Effective: February 4, 2004
DEPARTMENTAL STANDARD OPERATING PROCEDURE Miami-Dade Aviation Department DSOP No. 03-03 Effective: February 4, 2004 SUBJECT: REQUESTS FOR COPIES OF MIAMI-DADE AVIATION DEPARTMENT S SECURITY-RELATED RECORDS
More informationMASTER AGREEMENT FOR PROJECT MANAGEMENT AND CONSTRUCTION MANAGEMENT SERVICES
MASTER AGREEMENT FOR PROJECT MANAGEMENT AND CONSTRUCTION MANAGEMENT SERVICES THIS AGREEMENT is made and entered into this day of, 2007, by and between the University of Washington ( Owner ) and, ( Project
More informationINTERNAL CONTROL MATRIX FOR AUDIT OF BILLING SYSTEM CONTROLS Version No. 4.2 August 2006
INTERNAL CONTROL MATRIX FOR AUDIT OF BILLING SYSTEM CONTROLS Version No. 4.2 August 2006 1. MANAGEMENT REVIEWS The contractor should have policies and procedures for periodic monitoring of the billing
More informationVendor Performance Evaluation Requirements
Vendor Performance Evaluation Requirements The awarded vendor should note that the Contract Administrator will document the contractor s performance by completing a Vendor Performance Evaluation based
More informationSTANDARD AGREEMENT BETWEEN OWNER AND CONTRACTOR FOR LUMP SUM CONSTRUCTION
STANDARD AGREEMENT BETWEEN OWNER AND CONTRACTOR FOR LUMP SUM CONSTRUCTION THIS AGREEMENT made as of day of June In the year 2010 Between the Owner: (name, address, phone number) Boulder Housing Partners
More informationREQUEST FOR PROPOSALS (RFP) - Construction Management Services. Germantown School District Office
REQUEST FOR PROPOSALS (RFP) - Construction Management Services From: Germantown School District Project: Germantown School District Addition & Renovations to Rockfield Elementary School N132 W18473 Rockfield
More informationConstruction Management Standards of Practice
Construction Management Standards of Practice 2010 Edition Advancing Professional Construction/ Program Management Worldwide. 7926 Jones Branch Drive, Suite 800 McLean, VA 22102-3303 USA 703.356.2622 703.356.6388
More informationTransit Division Payroll Processing Review
Transit Division Payroll Processing Review June 8, 2009 Report No. 09-09 Office of the County Auditor Evan A. Lukic, CPA County Auditor Table of Contents Topic Page Executive Summary... 1 Purpose and Scope...
More informationMachinery and Equipment Loan Fund
PA TM PENNSYLVANIA come invent the future Machinery and Equipment Loan Fund Program Guidelines Commonwealth of Pennsylvania Tom Ridge, Governor www.state.pa.us Department of Community and Economic Development
More informationRequest for Proposal (RFP) 15003 Open-End Contract for Media Buying Service
Request for Proposal (RFP) 15003 Open-End Contract for Media Buying Service Section 1 Service Required The (Commission) is seeking proposals from advertising agencies or communication companies to work
More informationGuidelines for Congregations Internal Control Best Practices
Guidelines for Congregations Internal Control Best Practices A resource provided by the Office of the Treasurer of the Evangelical Lutheran Church in America In order to exercise good stewardship and care
More informationAGREEMENT between BROWARD COUNTY and Cummings-Balfour Beatty, A Joint Venture for CONSTRUCTION MANAGER AT RISK SERVICES TERMINAL 4 GATE REPLACEMENT - WESTERN EXPANSION at the Fort Lauderdale-Hollywood
More informationEnterprise Technology Services Division - Payroll Processing Review
Enterprise Technology Services Division - Payroll Processing Review August 12, 2009 Report No. 09-15 Evan A. Lukic, CPA County Auditor Table of Contents Topic Page Executive Summary... 1 Purpose and Scope...
More informationPerformance Audit Report. Department of Human Resources The Maryland Energy Assistance Program and the Electric Universal Service Program
Performance Audit Report Department of Human Resources The Maryland Energy Assistance Program and the Electric Universal Service Program Accounting Records Cannot Be Relied Upon to Provide Accurate Expenditure
More informationBoard of Supervisors February 10, 2000 Page 2. Summary of Findings
Board of Supervisors February 10, 2000 Page 2 Summary of Findings We have questioned a total of $37,320 in expenditures made by GHS. Of this amount, $24,863 represents disbursements that were undocumented
More informationEXHIBIT G ROLLING OWNER CONTROLLED INSURANCE PROGRAM (ROCIP)
EXHIBIT G ROLLING OWNER CONTROLLED INSURANCE PROGRAM (ROCIP) 1.0 Definitions Certificate of Insurance: Contract: Contractor: Contractor insurance cost City (Sponsor): Owner Controlled Insurance Program
More informationCONTRACT COMPLIANCE REVIEW CHECKLIST Nevada Department of Transportation, Contract Compliance Division
CONTRACT COMPLIANCE REVIEW CHECKLIST Nevada Department of Transportation, Contract Compliance Division Contractor: Complete this checklist. Attach all required documentation and send to the NDOT Contract
More informationGENERAL INFORMATION. REQUIRED SERVICES: are described in the enclosure consisting of 4 pages, dated 3/29/12 OR: are described as follows:
These documents consist of three parts (Part A - Request for Proposals; Part B - Proposal Form; Part C - Contract Award, Notice to Proceed & Invoice Summary), -- plus the current edition dated February
More informationDelDOT Professional Services Procurement Manual. Chapter Contents. Chapter Six Progress Payment and Reporting Procedures 6.1 PROGRESS PAYMENTS...
Chapter Contents Chapter Six Progress Payment and Reporting Procedures 6.1 PROGRESS PAYMENTS... 6-1 6.1.1 Payment and Reporting Submission Contents... 6-1 6.1.2 Payment and Reporting Schedule... 6-1 6.1.3
More informationThe BASICS of CONSTRUCTION ACCOUNTING Workshop GLOSSARY
The BASICS of CONSTRUCTION ACCOUNTING Workshop GLOSSARY From Financial Management & Accounting for the Construction Industry, CFMA. 2014 Matthew Bender and Company, Inc., a member of the LexisNexis Group.
More informationWelcome to the 2015 Construction Industry Occupational Wage Survey Workshop. August 17, 2015 Jason Payton Oregon Employment Department Auditorium
Welcome to the 2015 Construction Industry Occupational Wage Survey Workshop August 17, 2015 Jason Payton Oregon Employment Department Auditorium The Bureau of Labor and Industries contracts with the Oregon
More informationMANAGING THE PROJECT RECORD
MANAGING THE PROJECT RECORD Project Record Filing System 2 Agency Submittals 2 Site Acquisition 3 Planning 3 Pre-Qualification of Bidders 3 Bidding 4 Construction 4 Inspection 4 Legal 5 Contracts 5 Accounting
More informationOWNER CONTRACTOR AGREEMENT
BUSINESS AFFAIRS FACILITIES PLANNING AND CONSTRUCTION OWNER CONTRACTOR AGREEMENT This Agreement for Construction Services (the Agreement ) is made and entered into this day of January, 2008, by and between
More informationOperating Policy and Procedure. DATE: February 9, 2015
[Major revision posted 2/9/15 (replaces 9/19/12 edition)] Operating Policy and Procedure : Overtime DATE: February 9, 2015 PURPOSE: The purpose of this Operating Policy and Procedure (OP) is to establish
More informationI. DOING BUSINESS WITH MIAMI INTERNATIONAL AIRPORT
DOING BUSINESS WITH MIAMI INTERNATIONAL AIRPORT H: Presentations/Doing Business with MIA I. DOING BUSINESS WITH MIAMI INTERNATIONAL AIRPORT INTRODUCTION Miami International Airport (MIA) has a $6.2 billion
More informationGeneral Overview of Financial Management
1 General Overview of Financial Management U.S. Department of Housing and Urban Development Office of Community Planning and Development 2 Compliance Monitoring 3 Compliance Monitoring Types of Compliance
More informationState of Florida Department of Transportation
State of Florida Department of Transportation EXHIBIT A, TO PROVIDE STAFFING SERVICES AS DESCRIBED BY THE STATE OF FLORIDA OCCUPATIONAL GROUPS, PURCHASING AGENTS (13-1023) AND LOGISTICIANS (13-1081), FOR
More informationAudit Guide for Consulting Services Cost Rates. March 11, 2015
Audit Guide for Consulting Services Cost Rates March 11, 2015 Columbus Regional Airport Authority Audit Guide for Consulting Services Cost Rates TABLE OF CONTENTS: History... 3 Page Purpose and Objectives...
More informationOctober 28, 2014. Ann Marie T. Sullivan, M.D. Commissioner New York State Office of Mental Health 44 Holland Avenue Albany, NY 12229
October 28, 2014 Ann Marie T. Sullivan, M.D. Commissioner New York State Office of Mental Health 44 Holland Avenue Albany, NY 12229 Re: OMH Contract With Shorefront Mental Health Board - Compliance With
More informationPricing of Construction Contract Change Order Documentation
The contract language contained in this Exhibit will supplement and take precedence over all other change order pricing contract provisions in the Contract Documents provided by the Owner, Design-Builder
More informationRequest for Proposal For: CQ5 Java Developer. ABA Information Systems April 11, 2013. Table of Contents
Request for Proposal For: CQ5 Java Developer ABA Information Systems April 11, 2013 Table of Contents Bid Timetable [2] 1.0 General Information [3] 2.0 Proposal Requirements [6] 3.0 Criteria for Selection
More informationAGREEMENT FOR CONSTRUCTION MANAGEMENT SERVICES
BUSINESS AFFAIRS FACILITIES PLANNING AND CONSTRUCTION AGREEMENT FOR CONSTRUCTION MANAGEMENT SERVICES This Agreement for Construction Management Services (the Agreement ) is made and entered into this day
More informationREQUEST FOR PROPOSALS FOR Franchise Fees, Sales and Use Tax Audits
REQUEST FOR PROPOSALS FOR Franchise Fees, Sales and Use Tax Audits The City of Louisville, Colorado is accepting proposals for the purpose of performing sales and use tax, and franchise fee compliance
More informationSILVER CREEK ST. AUGUSTINE LLLP FINANCIAL STATEMENTS AND INDEPENDENT AUDITORS' REPORT. December 31, 2015 and 2014
FINANCIAL STATEMENTS AND INDEPENDENT AUDITORS' REPORT TABLE OF CONTENTS INDEPENDENT AUDITORS' REPORT 1 FINANCIAL STATEMENTS: BALANCE SHEET STATEMENT OF OPERATIONS STATEMENT OF PARTNERS' CAPITAL STATEMENT
More informationAV Parking System Review
Exhibit 1 AV Parking System Review May 6, 2011 Report No. 11-01 Office of the County Auditor Evan A. Lukic, CPA County Auditor Table of Contents Contents EXECUTIVE SUMMARY... 3 OBJECTIVES, SCOPE AND PROCEDURES...
More informationDISADVANTAGED BUSINESS ENTEPRISE PROGRAM CONTRACT COMPLIANCE MONITORING
DBE PROGRAM OVERVIEW DISADVANTAGED BUSINESS ENTEPRISE PROGRAM CONTRACT COMPLIANCE MONITORING It is the policy of the Columbus Regional Airport Authority (CRAA), in compliance with federal law (49 CFR 26),
More informationREQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT AT-RISK FOR LOGANVILLE ELEMENTARY SCHOOL (REPLACEMENT) FOR THE WALTON COUNTY SCHOOL DISTRICT
ADVERTISEMENT: REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT AT-RISK FOR LOGANVILLE ELEMENTARY SCHOOL (REPLACEMENT) FOR THE WALTON COUNTY SCHOOL DISTRICT The WALTON COUNTY SCHOOL DISTRICT will receive
More informationCONSTRUCTION PROJECT AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER
REAL ESTATE DEVELOPMENT AND MANAGEMENT CONSTRUCTION PROJECT AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER PROJECT NO: (Project Number) STATE FLAIR CODE: (Payment Code) PROJECT NAME AND LOCATION: (Project
More informationTime and Materials Invoice Requirements
Time and Materials Invoice Requirements Expense Report for Time and Materials type Contract Page 1 Contents Time and Materials Invoice Requirements... 1 Expense Report Invoice Data Submittal Requirements...
More informationCecilia Ross Director, Los Angeles Office of Public Housing, 9DPH. Joan S. Hobbs Regional Inspector General for Audit, 9DGA
Issue Date January 21, 2005 Audit Case Number 2005-LA-1805 TO: Cecilia Ross Director, Los Angeles Office of Public Housing, 9DPH FROM: SUBJECT: Joan S. Hobbs Regional Inspector General for Audit, 9DGA
More informationConstruction Bond Audit Report. Office of Auditor General
Construction Bond Audit Report (This page was left blank) TABLE OF CONTENTS Executive Summary 5 Background, Scope and Objectives, and Methodology....7 Audit Findings, Recommendations, and Management s
More informationCONSULTANT SERVICES MANUAL
WEST VIRGINIA DEPARTMENT OF TRANSPORTATION DIVISION OF HIGHWAYS CONSULTANT SERVICES MANUAL Prepared by the: Engineering Division Consultant Services Section April 2005 West Virginia Department of Transportation,
More informationJune 2008 Report No. 08-038. An Audit Report on The Department of Information Resources and the Consolidation of the State s Data Centers
John Keel, CPA State Auditor An Audit Report on The Department of Information Resources and the Consolidation of the State s Data Centers Report No. 08-038 An Audit Report on The Department of Information
More informationEXHIBIT G INSURANCE REQUIREMENTS
EXHIBIT G INSURANCE REQUIREMENTS (a) Insurance Coverages The CM/GC shall obtain, at its expense, and keep in effect during the term of the Contract, the insurance coverages listed below. The insurance
More informationCITY OF SPRINGFIELD, MISSOURI DIVISION OF PURCHASES INVITATION FOR BID #147-2016 ADDENDUM #1
CITY OF SPRINGFIELD, MISSOURI DIVISION OF PURCHASES INVITATION FOR BID #147-2016 ADDENDUM #1 Kara Daniel, Buyer Date Issued: March 31, 2016 City of Springfield Buyer s Email: kdaniel@springfieldmo.gov
More informationSAMPLE CONSTRUCTION COMPANY. FINANCIAL STATEMENT AND SUPPLENTARY INFORMANTION For the Year Ended December 31, 2011
FINANCIAL STATEMENT AND SUPPLENTARY INFORMANTION For the Year Ended December 31, 2011 The financial statement, prepared by an independent Certified Public Accountant, is essential for bonding purposes.
More informationPAYROLL, PAYABLES AND EXPENDITURES DIVISION EXPENDITURE CONTROL DEPARTMENT
PAYROLL, PAYABLES AND EXPENDITURES DIVISION Summary of Major Accomplishments The Expenditure Control Department consists of two functional areas, the Payroll Section and the Encumbrance and Disbursement
More informationof the Chancellor SUMMARY OF CHANGES
Subject: SABBATICAL LEAVE OF ABSENCE SUMMARY OF CHANGES This regulation replaces and supersedes C-650 dated 10/25/83. It sets forth the rules governing sabbatical leave of absence applicable to all pedagogical
More informationACCOUNTING & AUDIT GUIDELINES FOR CONTRACTS WITH CALTRANS
ACCOUNTING & AUDIT GUIDELINES FOR CONTRACTS WITH CALTRANS Mendocino County Page 1 of 5 INTRODUCTION The purpose of this brochure is to outline for you, a potential contractor with the California State
More informationNotes. Score. 1 Basic Services 1.1. A few instances; could have been more proactive
Jacobs Contract performance Tracking spreadsheet = Excellent 2 = Meets performance standards 1 = Improvement needed 0= Unsatisfactory Report for the time period: Annual report 210 Total average score 2.86
More informationUtility Coordination Procedures for Hillsborough County Construction Projects within County Rights-of-Way
Public Works Department Utility Coordination Procedures for Hillsborough County Construction Projects within County Rights-of-Way October 2015 HillsboroughCounty.org HILLSBOROUGH COUNTY Office of the County
More informationConstruction Management/ General Contractor Alternative Contracting Process
Clean Water State Revolving Fund Loan Program Construction Management/ General Contractor Alternative July 2011 Last Updated: 08/03/2011 By: Larry McAllister DEQ 11-WQ-027 Prepared by: Clean Water State
More informationLabor Compliance Program Guidebook For School Districts
Labor-Management-Consultants P.O. Box 24455 Oakland, CA 94623 Phone: (510) 835-7603 Fax: (510) 835-7613 www.davillier-sloan.com info@davillier-sloan.com Labor Compliance Program Guidebook For School Districts
More informationOBJECTIVE To establish procedures for administration of construction manager agreements, including negotiation, contracting and payments.
OP-B-11-D2 ADMINISTRATION OF CONSTRUCTION MANAGER AGREEMENTS SPECIFIC AUTHORITY Sections 240.209(3)(p), 1001.74, 1013.46, F. S. OBJECTIVE To establish procedures for administration of construction manager
More informationREQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES. PASSENGER SCREENING CHECKPOINT CONSOLIDATION PROJECT PROJECT No.
REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES PASSENGER SCREENING CHECKPOINT CONSOLIDATION PROJECT PROJECT No. FY15-805-67 Manchester-Boston Regional Airport is soliciting Proposals from qualified
More informationSIMPLIFIED BASIC CALCULATIONS FOR DEVELOPING FULLY LOADED HOURLY RATES
SIMPLIFIED BASIC CALCULATIONS FOR DEVELOPING FULLY LOADED HOURLY RATES FOR A SMALL CONTRACTOR OF CONSULTING SERVICES AT A GOVERNMENT FACILITY Step 1: Assemble Direct and Indirect Costs Direct Costs are
More informationAgreement between City of Snoqualmie, Washington and the Beckwith Consulting Group
Agreement between City of Snoqualmie, Washington and the Beckwith Consulting Group This agreement made this by and between the Beckwith Consulting Group, Planning, Design and Development Services, PO Box
More informationConstruction Manager @ Risk Request for Proposal ( RFP ) Insert Project Name University Project Number: xx-xxx-xx-xxxx
Construction Manager @ Risk Request for Proposal ( RFP ) Insert Project Name University Project Number: xx-xxx-xx-xxxx Insert RFP Issue Date Throughout this RFP Respondent or you means the prime firm responding
More informationFREDERICK COUNTY INTERAGENCY INTERNAL AUDIT AUTHORITY FREDERICK COUNTY PUBLIC SCHOOLS CONSTRUCTION MANAGEMENT PHASE II
FREDERICK COUNTY INTERAGENCY INTERNAL AUDIT AUTHORITY FREDERICK COUNTY PUBLIC SCHOOLS CONSTRUCTION MANAGEMENT PHASE II Report #12-03 September 21, 2011 Frederick County Internal Audit Division TABLE OF
More informationCDO WORKFORCE INVESTMENT BOARD. REPLACES CDO Workforce Investment Board Procurement Policy, dated 9/30/05
CDO WORKFORCE INVESTMENT BOARD POLICY #07-03: Local Procurement of Goods and Services DATE: November 14, 2007 APPLIES TO: Use of WIA Title I-B funds REPLACES CDO Workforce Investment Board Procurement
More informationHAWAII STANDARD GENERAL CONDITIONS FOR FORM OF AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR
HAWAII STANDARD GENERAL CONDITIONS FOR FORM OF AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR TABLE OF ARTICLES 1 AGREEMENT 2. SCOPE OF WORK 3. SUBCONTRACTOR S RESPONSIBILTIES 4. CONTRACTOR'S RESPONSIBILITIES
More informationConstruction Management At-Risk
Oconee County Schools P.O. Box 146, 34 School Street Watkinsville, GA 30677 706-769-5130 706-769-3513 REQUEST FOR PROPOSALS ISSUE DATE: March 10, 2016 RFP REF: Construction Management At-Risk Construction
More informationProcedures and Guidelines for External Grants and Sponsored Programs
Definitions: Procedures and Guidelines for External Grants and Sponsored Programs 1. Grant and Contract Financial Administration Office (Grants Office): The office within the Accounting Operations Area
More informationPost Award Accounting System Audit at Nonmajor Contractors
Activity Code 17740 B-1 Planning Considerations Post Award Accounting System Audit at Nonmajor Contractors To provide general guidance for the audit of the adequacy and suitability of nonmajor contractor
More informationINTERNAL CLAIMS AUDITOR
6650 INTERNAL CLAIMS AUDITOR The Internal Claims Auditor is an integral part of a properly designed system of internal controls. The position was created to carry out the important Board responsibility
More informationINSTRUCTIONS FOR PROVIDING PROFESSIONAL CONSULTING SERVICES
INSTRUCTIONS FOR PROVIDING PROFESSIONAL CONSULTING SERVICES Prepared by: Engineering Services and Internal Review May 2014 CONTENTS INTRODUCTION... 1 I. AUDIT EVALUATION... 2 II. PERFORMANCE AND POST-PERFORMANCE
More informationTABLE OF CONTENTS I. PURPOSE... 3 II. GOALS...3 III. DEFINITIONS... 3-4
CARROLL COUNTY MINORITY BUSINESS ENTERPRISE POLICY Department of the Comptroller Bureau of Purchasing 10/03/02 TABLE OF CONTENTS I. PURPOSE... 3 II. GOALS...3 III. DEFINITIONS... 3-4 IV METHODS OF PROCURMENENT
More informationAGREEMENT BETWEEN THE CITY OF CRESTWOOD, MO AND BIEG PLUMBING COMPANY FOR ON-CALL PLUMBING SERVICE FOR THE PERIOD
AGREEMENT BETWEEN THE CITY OF CRESTWOOD, MO AND BIEG PLUMBING COMPANY FOR ON-CALL PLUMBING SERVICE FOR THE PERIOD JANUARY 1, 2014 TO DECEMBER 31, 2015 AGREEMENT THIS AGREEMENT, is made and entered into
More informationChapter 10 - Contract Completion
Chapter 10 - Contract Completion Construction Manual 1-1000 General This Chapter contains guidelines that are followed on projects inspected and administered by the Department and its construction engineering
More informationWage & Hour. Frequently Asked Questions
Wage & Hour Frequently Asked Questions WHAT EXACTLY DOES WAGE & HOUR DO AND WHAT SERVICES DOES IT PROVIDE? Wage & Hour enforces many aspects of labor law including the collection of unpaid wages and benefits,
More informationCHAPTER 23. Contract Management and Administration
Date Issued: June 12, 2009 Date Last Revised: September 28, 2015 CHAPTER 23. Contract Management and Administration Table of Contents CHAPTER 23. Contract Management and Administration... 23-1 23.1 Policy...
More informationVacation policy Updated: January 2004
Vacation policy Updated: January 2004 This vacation policy applies to employees who are eligible for the core benefit program. The core program applies to the majority of benefits eligible full-time, part-time,
More informationREQUEST FOR PROPOSAL GRANT WRITING SERVICES
REQUEST FOR PROPOSAL GRANT WRITING SERVICES SCOPE OF SERVICES The Village of Maywood is seeking to retain a Consultant to assist the Village in researching and identifying potential grants and providing
More information