Sewer Inspection and Maintenance Chamber and Shaft

Size: px
Start display at page:

Download "Sewer Inspection and Maintenance Chamber and Shaft"

Transcription

1 Sewer Inspection and Maintenance Chamber and Shaft ightweight components for ease of installation ong service life Resistant to chemical attack (H 2 S) common in gravity sewers Adjustable pipe connections for onsite adjustments Non-access cover arrangement, for security and safety Flexible corrugated riser accommodates ground movement and dynamic traffic loads Pressure tested to 50kPa Suitable at depths up to 5 metres Prebenched bases provide a perfect hydraulic channel EZIpit

2 Product Overview The Iplex EZIpit is a real breakthrough in sewer construction technology, allowing a leak-free plastic sewer system. The environmental, technical and economical demands of water authorities for a watertight, corrosion proof, stable and durable sewer system are now a reality, with the Iplex EZIpit. The Iplex EZIpit provides considerable benefits over conventional concrete systems, especially where site access is difficult or environmental issues are a concern. The EZIpit can be handled without heavy lifting equipment and installed at the same time as the sewer pipes. As a result substantial cost savings in construction can be achieved and risks associated with open excavation minimised. The EZIpit provides easy access from the surface for inspection, water jet cleaning and maintenance in gravity sewer and drainage systems. The advanced design allows safe access for typical CCTV inspection and rodding equipment but prevents man entry. The EZIpit base and riser components effectively seal to provide resistance to infiltration and as a consequence, eliminate inflows during periods of prolonged wet weather. This results in cost savings for sewage treatment plant operators and minimises the potential for environmentally hazardous discharges. The base and riser are made of injection moulded polypropylene, which provides high resistance to chemical attack, exceptional toughness and ensures a long service life. The moulded benching provides the perfect hydraulic channel to avoid chokes in sewers. The System The EZIpit is a polypropylene inspection and maintenance chamber which consists of a base, a corrugated riser and cover arrangements suitable for vehicular (Class D) and non-vehicular (Class B) loading. The EZIpit is suitable for use with DWV PVC Sewer pipe manufactured to AS/NZS 1260 PVC-U pipes and fittings for drain, waste and vent applications. The EZIpit is available in two sizes providing flexibility in design and construction. The EZIpit 600, Chamber is available for greater accessibility with remote cleaning and inspection equipment and the high-tech EZIpit 425 Shaft for more compact design and flexibility in your sewer network. EZIpit Riser is manufactured as a single wall corrugated polypropylene pipe. ight grey in colour for DN600 and orange for DN425. The prebenched EZIpit base is available with 6 different flow profiles allowing change in direction and side connections. The standard flow profiles are: 30, 60, 90, straight through (180 ), tee, and double tee profile. The EZIpit base also incorporates revolutionary features such as adjustable pipe connections, which simplifies installation. The adjustable pipe connections allow a free angular deflection of up to 7.5 from the centre line in all directions. This flexibility makes it possible to adjust the angle and/or grade in the trench.

3 Product information EZIpit Chamber (DN600) and Shaft (DN425) Assembly (Class B non-trafficable conditions) Assemblies EZIpit Chamber (DN600) Assembly (Class D trafficable conditions) EZIpit Shaft (DN425) Assembly (Class D trafficable conditions) Access Cover Vegetation Ring Access Cover Frame Access Cover Concrete Encasing Frame Concrete Support ring DN425 Rubber Ring Shroud id id* Cap* Cap DN600 Rubber Ring DN425 Riser Rubber Ring* DN425 Rubber Ring Riser* DN425 dark orange DN600 grey DN600 Riser DN425 Base DN600 Rubber Ring Rubber Ring* DN600 Base Base* * Can be either DN600 or DN425 NOTE: Illustrations of assemblies are not to scale. If critical contact Iplex Pipelines.

4 Product information Standards The EZIpit cover arrangement has been purposely designed to meet Australian conditions and complies with AS3996 Access covers and grates. Support for EZIpit Cover arrangement to be authorised by the ocal Water Authority. The EZIpit inspection and maintenance chamber complies with EN and WSA137 Industry Standard for Maintenance Shafts and Chambers for Sewerage. Installation The EZIpit is suitable for installation depths up to 5 meters. Refer to AS/NZS Buried flexible pipelines Part 1: Structural Design and AS/NZS Buried flexible pipelines Part 2: Installation for embedment and compaction requirements. Refer to Iplex EZIpit Inspection and Maintenance Chamber Product Guide for assembly guidelines. Typical Installation in Non-Trafficable Conditions Class B Footways, Parks and Basements (DN600 & DN425) 300mm (min.) Redgum, Concrete or Recycled Plastic Bearers (as per Sewerage Code of Australia WSA 02) EZIpit Frame Trench Width EZIpit Sewer AS 3996 Class B Vegetation Ring EZIpi t Cover 300mm (min.) Vegetation Ring EZIpit Class B Cover & Frame (AS 3996) Redgum, Concrete or Recycled Plastic Bearers DN800 PE Shroud Depth to Invert (Max. 5m) EZIpit Cap & id Arrangement Compacted embedment material around shaft and across trench. Installation as per AS/NZS & AS/NZS EZIpit Riser (Height adjustable on site) Base PVC Sewer Pipe* (AS/NZS 1260) DN150, DN225, DN300 & DN375 Pipe embedment Foundation Native Soil Note: * Pipe sizes limited in some base flow profiles.

5 Product information Typical Installation in Trafficable Conditions Class D (DN600) EZIpit Class D Cover & Frame (AS 3996) Asphalt, Bitumen or Concrete Road Surface EZIpit Precast Concrete ring EZIpit Cap & id Arrangement Compacted embedment material around shaft and across trench. Installation as per AS/NZS & AS/NZS Depth to Invert (Max. 5m) EZIpit Riser (Height adjustable on site) Base PVC Sewer Pipe* (AS/NZS 1260) DN150, DN225, DN300 & DN375 Pipe embedment Foundation Native Soil Note: * Pipe sizes limited in some base flow profiles. Typical Installation in Trafficable Conditions Class D (DN425) EZIpit Class D Cover & Frame (AS 3996) Asphalt, Bitumen or Concrete Road Surface Concrete Encasing Rubber Ring Compacted embedment material around shaft and across trench. Installation as per AS/NZS & AS/NZS Depth to Invert (Max. 5m) EZIpit Riser (Height adjustable on site) Base PVC Sewer Pipe* (AS/NZS 1260) DN150, DN225 & DN300 Pipe embedment Foundation Native Soil Note: * Pipe sizes limited in some base flow profiles.

6 Product RANGE EZIpit Base EZIpit Base: Straight through (180 ) Channel Base Sizes Dimensions (mm) (mm) TGB DN425 X DN TGB DN425 X DN TGB DN425 X DN TGB DN425 X DN TGB DN600 X DN TGB DN600 X DN TGB DN600 X DN TGB600375* DN600 X DN Note: * DN375 connection does not allow for any angular deflection. EZIpit Base: Bend (90 ) Channel Base Sizes Dimensions (mm) (mm) TGB DN425 X DN TGB DN600 X DN TGB DN600 X DN TGB DN600 X DN EZIpit Base: Bend (60 ) Channel Base Sizes Dimensions (mm) (mm) TGB DN425 X DN TGB DN600 X DN TGB DN600 X DN TGB DN600 X DN Note: All bases come with RRJ adjustable connections suitable for DWV pipe manufactured to AS/NZS1260. Empty unbenched EZIpit 600 base also available upon request (TGB600). All dimensions are approximate only and images are not to scale. If critical contact Iplex Pipelines.

7 Product RANGE EZIpit Base EZIpit Base: Bend (30 ) Channel Base Sizes Dimensions (mm) (mm) TGB DN425 X DN TGB DN600 X DN TGB DN600 X DN TGB DN600 X DN EZIpit Base: Bend Tee Channel Base Sizes Dimensions (mm) (mm) TGB425T150 DN425 X DN TGB600T150 DN600 X DN TGB600T225 DN600 X DN TGB600T300 DN600 X DN EZIpit Base: Bend Double Tee Channel Base Sizes Dimensions (mm) (mm) TGB425X100 DN425 X DN TGB425X150 DN425 X DN TGB600X150 DN600 X DN TGB600X225 DN600 X DN TGB600X300 DN600 X DN Note: All bases come with RRJ adjustable connections suitable for DWV pipe manufactured to AS/NZS1260. Empty unbenched EZIpit 600 base also available upon request (TGB600). All dimensions are approximate only and images are not to scale. If critical contact Iplex Pipelines.

8 Product RANGE EZIpit Riser Dimensions DN (mm) TGPP425B DN TGPP425C TGPP425F TGPP600A TGPP600AV TGPP600B TGPP600C TGPP600DV TGPP600F Note: DN425 Riser dark orange in colour. DN600 Riser grey in colour. EZIpit Riser Rubber Ring Dimensions DN TGSEA GERSEW DN425 DN600 EZIpit Cap and id Dimensions DN GME300S42C 425 GME300S6C 600 EZIpit Shroud (For class B non trafficable conditions only) POH04800T Size DN 800 x 300mm Note: Can be used for both the EZIpit DN425 and DN600. Note: All dimensions are approximate only and images are not to scale. If critical contact Iplex Pipelines.

9 Product RANGE EZIpit Concrete Support Ring (For class D trafficable conditions only) GMTG300CR Note: Can only be used for the EZIpit DN600. EZIpit Cover Arrangements GME300S36D2CR GME300S6D2 GME300S6B2 DN425 Class D Access Cover DN600 Class D Frame & Access Cover DN600 Class B Frame & Access Cover DN600 Class D DN600 Class B DN425 Class D EZIpit Union Coupling TGU425 GR58600 DN425 Union DN600 Union EZIpit 425 In-situ Connector TGCON42510 TGCON42515 DN100 In-situ Connector DN150 In-situ Connector Note: All dimensions are approximate only and images are not to scale. If critical contact Iplex Pipelines.

10 Product RANGE EZIpit Drill Saw for Shaft TGDSAW10 TGDSAW15 DN100 Drill Saw DN150 Drill Saw Gatic Sealing Compound GM37501 GM37504 GM kg Sealing Compound 4kg Sealing Compound 20kg Sealing Compound Iplex Pipe ubricant J J J kg Pipe ubricant 1kg Pipe ubricant 4kg Pipe ubricant Disclaimer: The information contained in this document should serve as a guide only and is subject to change without notice. Iplex Pipelines Australia Pty td does not invite any person to act or rely upon such information and liability for such information is excluded. In particular, as new technology is developed rapidly, product specifications, designs and components may change and Iplex Pipelines Australia Pty td reserves the right at its discretion to make changes as it see fit. The information contained in this document does not form part of the terms and conditions of sale or constitute the description of any goods to be supplied by Iplex Pipelines Australia Pty td or its distributors. Before purchasing goods, customers should source current product information from their distributor or seek expert advice on their particular intended use and application for the product. No part of this document may be reproduced, stored in a retrieval system or transmitted in any form, electronic, mechanical recording or otherwise without the prior written consent of Iplex Pipelines Australia Pty td. The designs, graphics, logos, tradenames, trademarks and other intellectual property contained in this document are either owned by Iplex Pipelines Australia Pty td or used with the permission of the owner or licensee, and must not be used without prior written consent. Copyright 2013 Iplex Pipelines Australia Pty td. All rights reserved. IPX/45 APR2013 Contact Details For all enquiries and orders contact Iplex Pipelines National Contact Centre: Civil: Fax: sales@iplexpipelines.com.au

Pipes and Fittings for Gravity Sewer Mains. SewerMAX

Pipes and Fittings for Gravity Sewer Mains. SewerMAX SewerMAX High resistance to tree root intrusion and groundwater infiltration lightweight for ease of installation low embodied energy for environmental benefits long service life Excellent chemical resistance

More information

Reticulation sewers in basements Technical guidelines

Reticulation sewers in basements Technical guidelines Reticulation sewers in basements Technical guidelines Overview What These guidelines explain our technical requirements for laying sewers in building basements. The scope of the guide is restricted to

More information

TG 105 ALLOWABLE PIPE SIZE, CLASS AND MATERIALS FOR WATER MAINS TECHNICAL GUIDELINE. Manager Asset Management SOUTH AUSTRALIAN WATER CORPORATION

TG 105 ALLOWABLE PIPE SIZE, CLASS AND MATERIALS FOR WATER MAINS TECHNICAL GUIDELINE. Manager Asset Management SOUTH AUSTRALIAN WATER CORPORATION TG 105 SOUTH AUSTRALIAN WATER CORPORATION TECHNICAL GUIDELINE ALLOWABLE PIPE SIZE, CLASS AND MATERIALS FOR WATER MAINS Issued by: Manager Asset Management Issue Date: SA WATER 2007 This document is copyright

More information

Greater Dublin Strategic Drainage Study Regional Drainage Policies - Volume 2 New Development

Greater Dublin Strategic Drainage Study Regional Drainage Policies - Volume 2 New Development 7 SPECIFICATIONS There is currently no Irish specification for construction of drainage works, or water supply works. There are several publications that give guidance on drainage works, such as the Building

More information

DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL

DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL 1.01 DESCRIPTION A. Furnish and install all storm drains, including manholes, inlets, service lines and other appurtenant

More information

Guide to working on Public Sewers

Guide to working on Public Sewers Guide to working on Public Sewers affected by Building Works Introduction Severn Trent Water Ltd requires the work to be done in order to protect the public sewer and minimise the risk of us having to

More information

Appendix A: Acceptable pipe and fitting materials

Appendix A: Acceptable pipe and fitting materials Watercare Services Limited Water and Code of Practice Content from the NZS 4404:2010 Land development and subdivision infrastructure has been reproduced for use in the Infrastructure Design s Manual for

More information

SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION

SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION 1. SCOPE Pipe subsoil drains shall be constructed in accordance with this specification and in conformity with the lines, grades and cross-sections shown

More information

Native InDesign 2890 SaniTite Brochure 1/8" 100 300 CMYK April 17, 07

Native InDesign 2890 SaniTite Brochure 1/8 100 300 CMYK April 17, 07 Sanitary Sewer Pipe Tough pipe for a tough environment SaniTite Sanitary Sewer Pipe delivers the features that engineers, contractors and municipalities demand durability, performance, handling, toughness

More information

Integrated Manhole Ladder System

Integrated Manhole Ladder System Application: This innovative product has been designed to provide safe access and egress to precast concrete manholes and inspection chambers. It can also be used within any other underground concrete

More information

Royal Seal Gasketed Sewer Pipe

Royal Seal Gasketed Sewer Pipe Royal Seal Gasketed Sewer Pipe Royal Seal Gasketed Sewer Pipe Royal Seal gasketed sewer pipe with our specially designed Double Seal Locked-In (DSLI ) gasket is an extremely durable pipe with a leak proof

More information

Access chambers and maintenance shafts. Issue 1

Access chambers and maintenance shafts. Issue 1 Access chambers and maintenance shafts Issue 1 Contents Access chambers (worker-entry) 1 Applications 2 Benefits 2 Design information 3 Components 3 Precast base 3 Shaft 3 Taper top (option one) 3 Squat

More information

SECTION 08000 STORM DRAINAGE TABLE OF CONTENTS

SECTION 08000 STORM DRAINAGE TABLE OF CONTENTS SECTION 08000 STORM DRAINAGE 08010 DESIGN A. Location B. Sizing TABLE OF CONTENTS 08020 MATERIALS A. Pipe Materials B. Structure Materials C. Installation D. Inlets and Outlets 08030 INSPECTIONS AND TESTING

More information

PART 5 : WASTEWATER DRAINAGE

PART 5 : WASTEWATER DRAINAGE Authorised by : City Waters Unit Manager Page 1 of 15 PART 5 : WASTEWATER DRAINAGE 5.1 INTRODUCTION This Manual sets out the basic design principles for drainage of wastewater. While some construction

More information

SERVICE LINE EXTENSION AND SERVICE LINE CONNECTION CONDENSED SANITARY SEWER SYSTEM INSTALLATION SPECIFICATIONS

SERVICE LINE EXTENSION AND SERVICE LINE CONNECTION CONDENSED SANITARY SEWER SYSTEM INSTALLATION SPECIFICATIONS 1001 SOUTH LEECHBURG HILL LEECHBURG, PA 15656 Phone: 724-845-9355 Fax: 724-845-1186 SERVICE LINE EXTENSION AND SERVICE LINE CONNECTION CONDENSED SANITARY SEWER SYSTEM INSTALLATION SPECIFICATIONS 1. General

More information

Corrosion protection linings. Issue 1

Corrosion protection linings. Issue 1 Corrosion protection linings Issue 1 Introduction While Humes sewerage pipes and products are designed to serve over 100 years in accordance with AS/NZS 4058, we offer corrosion protection linings to increase

More information

Pipeline Replacement using Relining

Pipeline Replacement using Relining Pipeline Replacement using Relining Mark Heathcote, March 2006 Relining of old pipeline systems is becoming an increasingly attractive option to asset owners and operators as an effective alternative to

More information

AGENDA. Pipe Materials / Trends The Reason for Change Design / Standards Pipe Selection Installation Examples Conclusion

AGENDA. Pipe Materials / Trends The Reason for Change Design / Standards Pipe Selection Installation Examples Conclusion AGENDA Pipe Materials / Trends The Reason for Change Design / Standards Pipe Selection Installation Examples Conclusion Water & Sewerage Pipe Materials Flexible Pipes Replacing Rigid Pipes Old Days Vitrified

More information

www.defra.gov.uk Annex B

www.defra.gov.uk Annex B www.defra.gov.uk Annex B National Build Standards Design and Construction of new gravity foul sewers and lateral drains Water Industry Act 1991 Section 106B Flood and Water Management Act 2010 Section

More information

Proposed Construction of Basement Flood Risk Assessment. 35 Edwardes Square London W8 6HH

Proposed Construction of Basement Flood Risk Assessment. 35 Edwardes Square London W8 6HH Proposed Construction of Basement Flood Risk Assessment 35 Edwardes Square London W8 6HH 1 Introduction This FRA has been carried out in accordance with the National Planning Policy Statement (NPPF), the

More information

Stormwater/Wetland Pond Construction Inspection Checklist

Stormwater/Wetland Pond Construction Inspection Checklist : Construction Inspection ChecklistsTools Stormwater/Wetland Pond Construction Inspection Checklist Project: Location: Site Status: Date: Time: Inspector: SATISFACTORY/ UNSATISFACTORY COMMENTS Pre-Construction/Materials

More information

FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation

FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation 644-10-569 Page 1 of 9 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING

More information

The Most Advanced Name in Drainage Systems. Sanitary Sewer Pipe

The Most Advanced Name in Drainage Systems. Sanitary Sewer Pipe The Most Advanced Name in Drainage Systems Sanitary Sewer Pipe SaniTite Sanitary Sewer Pipe delivers the features that engineers, contractors and municipalities demand durability, performance, handling,

More information

SECTION 6A STORM DRAIN DESIGN Mar. 2002 S E C T I O N 6A STORM DRAIN - DESIGN

SECTION 6A STORM DRAIN DESIGN Mar. 2002 S E C T I O N 6A STORM DRAIN - DESIGN S E C T I O N 6A STORM DRAIN - DESIGN 6A.l Scope 6A.2 Storm Water Quantity 6A.3 Storm Drain Hydraulics 6A.4 Depths 6A.5 Locations 6A.6 Curved Storm Drains 6A.7 Manholes 6A.8 Catch basins 6A.9 Storm Drain

More information

Introduction. Contents. General. Materials and workmanship. Diagrams. Other regulations. References

Introduction. Contents. General. Materials and workmanship. Diagrams. Other regulations. References Introduction General This Technical Booklet has been prepared by the Department of the Environment for Northern Ireland and provides for certain methods and standards of building which, if followed, will

More information

Building over or close to a public sewer

Building over or close to a public sewer Building over or close to a public sewer thameswater.co.uk/developerservices thameswater.co.uk/developerservices 1 Questions and answers Did you know Thames Water is legally responsible for more than 100,000

More information

FY08 SEWER POINT REPAIRS BID TABULATION

FY08 SEWER POINT REPAIRS BID TABULATION 6-07-831 Page 1 of 12 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING "

More information

Uniclass L7315 + L2123 EPIC J3413. CI/SfB (52.5) Heavy duty channel drainage system ACO S Range

Uniclass L7315 + L2123 EPIC J3413. CI/SfB (52.5) Heavy duty channel drainage system ACO S Range Uniclass L7315 + L2123 EPIC J3413 CI/SfB (52.5) Heavy duty channel drainage system ACO S Range ACO S Range CHANNEL DRAINS Load Class BS EN 1433:2002 Optimum solution The ACO S Range is an interconnecting

More information

PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE

PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE REGION OF PEEL PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE Sanitary Sewer Design Criteria REVISED July 2009 PUBLIC WORKS SANITARY SEWER DESIGN CRITERIA TABLE OF CONTENTS

More information

50AI01oe 02/15. Labko GRP cesspools. Instructions for installation, operation and maintenance

50AI01oe 02/15. Labko GRP cesspools. Instructions for installation, operation and maintenance 02/15 Labko GRP cesspools Instructions for installation, operation and maintenance Reliable solutions Wastewater treatment systems Contents 1 LABKO CESSPOOLS... 3 1.1 GENERAL... 3 1.2 IMPORTANT TO KNOW

More information

HYLINER AKS HDPE LINING

HYLINER AKS HDPE LINING HYLINER AKS HDPE LINING FOR CONCRETE PIPE Manufactured from HDPE Available in white and black Sheets up to 3 m width D1.12 HyLiner AKS HDPE Lining for Concrete Pipe October 2013 0800 WE PIPE (93 7473)

More information

Drainage and Grease Management for the Commercial Kitchen

Drainage and Grease Management for the Commercial Kitchen Drainage and Grease Management for the Commercial Kitchen ACO. The future of drainage. The ACO system chain provides drainage solutions to meet the needs of tomorrow s food service facilities. Hostile

More information

Fabricated Drainage Products

Fabricated Drainage Products Fabricated Drainage Products Complete Drainage System Inline Drains are used At the beginning of a drain line Add a new water inlet to an existing drain line using a riser pipe and tee HARCO Surface Drainage

More information

DIVISION 4300 STORM DRAINAGE

DIVISION 4300 STORM DRAINAGE DIVISION 4300 STORM DRAINAGE SECTION 4305 STORM SEWER PART 1 - GENERAL 1.01 SCOPE This section covers the construction of storm sewers for the collection and transport of stormwater runoff. 1.02 REFERENCES

More information

Industry Guidelines. Design Guidance for Polypropylene Structured Wall Pipes ISSUE 1.0

Industry Guidelines. Design Guidance for Polypropylene Structured Wall Pipes ISSUE 1.0 Industry Guidelines Design Guidance for Polypropylene Structured Wall Pipes ISSUE 1.0 Ref: POP015 18 July 2012 Disclaimer In formulating this guideline PIPA has relied upon the advice of its members and,

More information

The Manitoba Water Services Board SECTION 027030 Standard Construction Specifications September 2013 Page 1 of 21

The Manitoba Water Services Board SECTION 027030 Standard Construction Specifications September 2013 Page 1 of 21 September 2013 Page 1 of 21 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work described herein shall consist of the construction of sewers including: the supply and installation of pipe, saddles, tees,

More information

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions. SECTION LS 2530 SANITARY SEWERS PART 1 GENERAL 1.1 SUBMITTALS A. General: Submit the following in accordance with The General Conditions. 1. Product data for drainage piping specialties. 2. Shop drawings

More information

PMS Reflex Blue C Mining PMS 8401C

PMS Reflex Blue C Mining PMS 8401C PMS Reflex Blue C ing PMS 8401C About Poly Pipe Pty Ltd Located in the Hunter Valley, NSW, Australia, Poly Pipe Pty Ltd (Poly Pipe) has an ultra modern extrusion, high tech manufacturing facility. It supplies

More information

SEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST

SEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST SEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST For permanent structures per Delaware SCS Pond Code 378 and Delaware Sediment and Stormwater Regulations KEY PROJECT INFORMATION Item meets standard

More information

Town House 11265 Center Highway North Huntingdon, PA 15642

Town House 11265 Center Highway North Huntingdon, PA 15642 APPENDIX C SPECIFICATIONS FOR THE CONSTRUCTION OF BUILDING LATERAL SANITARY SEWERS DECEMBER 2004, INCLUDING AMENDMENTS ADOPTED ON FEBRUARY 6, 2008 AND APRIL 2, 2008; EFFECTIVE ON MAY 1, 2008 Town House

More information

1. Description. 2. List of Accessories included A B C F G H

1. Description. 2. List of Accessories included A B C F G H 1. Description This unit is a pump that will clear the waste from a domestic shower and washbasin. The unit will start automatically. Please pay particular attention to the following: Possible danger to

More information

Mandatory Part 1.4 BUILD OVER OR NEAR SEWERS, STORMWATER DRAINS AND WATER MAINS

Mandatory Part 1.4 BUILD OVER OR NEAR SEWERS, STORMWATER DRAINS AND WATER MAINS Mandatory Part 1.4 BUILD OVER OR NEAR SEWERS, STORMWATER DRAINS AND WATER MAINS Table of Contents Purpose... 2 Commencement... 2 Application... 2 Referral Agency... 2 Compliance with the QDC... 2 Associated

More information

ISSUE 08/08. KEEP INFORMED Look for other Good Idea Leaflets that could help you with your current project.

ISSUE 08/08. KEEP INFORMED Look for other Good Idea Leaflets that could help you with your current project. 7648_GIL_074_07_08.qxd:GIL 074 01 06 27/8/08 16:47 Page 1 ISSUE 08/08 74 UNDERGROUND DRAINAGE Wickes stock a wide range of drainage products, whether it s to replace old drainage systems in the event of

More information

(52) In6 Publication CCM2 May 2000 ADVANCED DRAINAGE SYSTEM CATCHPITS, CHAMBERS & MANHOLES RIDGIDRAIN ENGINEERING EXCELLENCE

(52) In6 Publication CCM2 May 2000 ADVANCED DRAINAGE SYSTEM CATCHPITS, CHAMBERS & MANHOLES RIDGIDRAIN ENGINEERING EXCELLENCE (52) In6 Publication CCM2 May 2000 ENGINEERING EXCELLENCE RIDGIDRAIN ADVANCED DRAINAGE SYSTEM CATCHPITS, CHAMBERS & MANHOLES AN INTRODUCTION TO POLYPIPE CIVILS LTD AN UNRIVALLED RANGE OF CATCHPITS MANHOLES

More information

SECTION 02630 STORM DRAINAGE SYSTEM

SECTION 02630 STORM DRAINAGE SYSTEM SECTION 02630 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes specifications for storm drainage systems including modifications and connections to existing storm drainage systems. 1.02 REFERENCE

More information

Note: All dimensions are nominal. All weights are for shipping purposes only. Availability is subject to change.

Note: All dimensions are nominal. All weights are for shipping purposes only. Availability is subject to change. CHANNEL DrAiNS Durable Designed for maximum durability and drainage, NDS Channel Drains are a proven alternative to traditional concrete drains. UV inhibitors in the grates, channel and component parts

More information

Standard Specification for the Laying of Sewer Lines and Appurtenances in the Hurunui District

Standard Specification for the Laying of Sewer Lines and Appurtenances in the Hurunui District Standard Specification for the Laying of Sewer Lines and Appurtenances in the Hurunui District 1. SCOPE OF WORK This Specification applies to the laying of sewer pipes and all associated appurtenances

More information

SECTION 02530 STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.

SECTION 02530 STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250. 02530-1 of 5 SECTION 02530 STORM DRAINAGE STRUCTURES 02530.01 GENERAL A. Description Storm drainage structure construction shall include, but not necessarily be limited to, furnishing and installing or

More information

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary

More information

DRAINAGE SYSTEMS FOR BEVERAGE INDUSTRIES

DRAINAGE SYSTEMS FOR BEVERAGE INDUSTRIES DRAINAGE SYSTEMS FOR BEVERAGE INDUSTRIES K E E P I N G U P T H E F L O W S T A I N L E S S S T E E L D R A I N A G E S Y S T E M S BREWERIES & DAIRIES BLÜCHER provides drainage solutions for removing

More information

Policy 11: Land Development Guidelines

Policy 11: Land Development Guidelines Policy 11: Land Development Guidelines Section 5 5.0 Sewerage Reticulation Design Requirements Table of Contents 5.0 Sewerage Reticulation Design Requirements...1 5.1 Introduction...2 5.2 Design Requirements

More information

EVALUATION OF EXHUMED PVC SEWER PIPES.

EVALUATION OF EXHUMED PVC SEWER PIPES. EVALUATION OF EXHUMED PVC SEWER PIPES. J. Tennakoon 1 and A. J. Whittle 2 1 Ipswich Water. 2 Iplex Pipelines Australia Pty Limited ABSTRACT Ipswich Water has commenced reviewing the useful lives of different

More information

Couplings. Drain Couplings Standard Couplings Large Diameter Couplings Adaptor Couplings Flexible Saddles Bushes

Couplings. Drain Couplings Standard Couplings Large Diameter Couplings Adaptor Couplings Flexible Saddles Bushes Drain Couplings Standard Couplings Large Diameter Couplings Adaptor Couplings Flexible Saddles Bushes Flex-Seal couplings meet a range of UK and international legislation requirements and quality standards

More information

SECTION 221413 FACILITY STORM DRAINAGE PIPING

SECTION 221413 FACILITY STORM DRAINAGE PIPING SECTION 221413 FACILITY STORM DRAINAGE PIPING PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01

More information

CW 2130 - GRAVITY SEWERS TABLE OF CONTENTS

CW 2130 - GRAVITY SEWERS TABLE OF CONTENTS August 2010 CW 2130 - GRAVITY SEWERS TABLE OF CONTENTS 1. DESCRIPTION... 1 1.1 General... 1 1.2 Definitions... 1 1.3 Referenced Standard Construction Specifications... 1 1.4 Referenced Standard Details...

More information

Compliance Document for New Zealand Building Code Clause G13 Foul Water Second Edition

Compliance Document for New Zealand Building Code Clause G13 Foul Water Second Edition Compliance Document for New Zealand Building Code Clause G13 Foul Water Second Edition Prepared by the Department of Building and Housing This Compliance Document is prepared by the Department of Building

More information

Beacon Hill Sewer District Standard Specifications

Beacon Hill Sewer District Standard Specifications Beacon Hill Sewer District Standard Specifications Residential Gravity Side Sewer Including Design Criteria and Standard Construction Drawings Residential Gravity Side Sewer Design Criteria 1. Provisions

More information

SECTION G SEWERS (STORM, SANITARY AND FDC)

SECTION G SEWERS (STORM, SANITARY AND FDC) G-1 GENERAL SECTION G SEWERS (STORM, SANITARY AND FDC) The Consulting Engineer is to monitor all specified pipe and granular materials, pipe slopes and run lengths and ensure the outlined criteria below

More information

ITS specification Jointing chambers and pull pits (ITS-02-02)

ITS specification Jointing chambers and pull pits (ITS-02-02) ITS specification Jointing chambers and pull pits (ITS-02-02) NZ Transport Agency Effective from September 2011 Copyright information This publication is copyright NZ Transport Agency (NZTA). Material

More information

LS 2540 SEWER LATERALS AND INSPECTION TEES

LS 2540 SEWER LATERALS AND INSPECTION TEES LS 2540 SEWER LATERALS AND INSPECTION TEES A. Summary B. Submittals C. Site Information D. Sewer Pipe and Fittings E. Lateral Locations F. Lateral Installation G. Inspection Tee Installation H. Removal

More information

EFFECTIVE FEBRUARY 2014. note: drainage permit required to call for a dampproof inspection

EFFECTIVE FEBRUARY 2014. note: drainage permit required to call for a dampproof inspection EFFECTIVE FEBRUARY 2014 note: drainage permit required to call for a dampproof inspection 1. ROOF DRAINS/DECK DRAINS (INTERIOR ) All roof and deck drains within the perimeter of the building shall be APPROVED

More information

CITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT

CITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT Page 1 CITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT CIVIC CENTRE 2141 MAJOR MACKENZIE DRIVE MAPLE ONTARIO L6A 1T1 905-832-2281 Page 2 SECTION 1 - GENERAL OBJECTIVES To provide

More information

PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE

PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE REGION OF PEEL PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE Storm Sewer Design Criteria REVISED July 2009 PUBLIC WORKS STORM SEWER DESIGN CRITERIA TABLE OF CONTENTS 1.0

More information

SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.

SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250. 02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily

More information

MAP KEYS GLOSSARY FOR THE DRAINAGE AND WATER REPORT

MAP KEYS GLOSSARY FOR THE DRAINAGE AND WATER REPORT Record MAP KEYS GLOSSARY FOR THE DRAINAGE AND WATER REPORT Abandoned Gravity Private Combined Gravity Private Foul Gravity Private Surface Water Gravity Public Combined Gravity Public Foul Gravity Public

More information

SPR PE Steel Reinforced Liner

SPR PE Steel Reinforced Liner ENGINEERED SOLUTIONS SPR PE Steel Reinforced Liner Reline Done Right Contech is your single source for rehabilitation of sanitary & storm sewers, culverts and bridges. Contech Engineered Solutions has

More information

SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT

SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT The following are minimum requirements for installation of conventional trench sewage disposal systems in St. Mary s County,

More information

SECTION 02400 - STORM DRAIN SYSTEM

SECTION 02400 - STORM DRAIN SYSTEM SECTION 02400 - STORM DRAIN SYSTEM CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement And

More information

SECTION 02720 SANITARY SEWER AND STORM DRAIN SYSTEMS

SECTION 02720 SANITARY SEWER AND STORM DRAIN SYSTEMS SECTION 02720 SANITARY SEWER AND STORM DRAIN SYSTEMS PART 1 GENERAL 1.01 SECTION INCLUDES A. The requirements for pipe material and installation in sewer and drainage collection systems. All materials

More information

U-LINER AC NEW AND UNIQUE ADHESIVE PE-LINER FOR DOMESTIC CONNECTIONS. www.rehau.com. Construction Automotive Industry

U-LINER AC NEW AND UNIQUE ADHESIVE PE-LINER FOR DOMESTIC CONNECTIONS. www.rehau.com. Construction Automotive Industry U-LINER AC NEW AND UNIQUE ADHESIVE PE-LINER FOR DOMESTIC CONNECTIONS www.rehau.com Construction Automotive Industry NEW ADHESIVE U-LINER AC Modern trenchless renovation and refurbishment processes have

More information

sales@fabfit.com.au TRADE PRODUCT GUIDE MAKE THE RITE CONNECTION WWW.FABFIT.COM.AU www.fabfit.com.au Page a

sales@fabfit.com.au TRADE PRODUCT GUIDE MAKE THE RITE CONNECTION WWW.FABFIT.COM.AU www.fabfit.com.au Page a Page a TRADE PRODUCT GUIDE MAKE THE RITE CONNECTION WWW.FABFIT.COM.AU Manufacturers and distributors of plumbing fittings. Fabfit Certification The following trade products guide details the range of plumbing

More information

ACO Water Management: Civils + Infrastructure

ACO Water Management: Civils + Infrastructure ACO Water Management: Civils + Infrastructure Technical data Introduction to The unit provides an aesthetically pleasing solution when linking proprietary conveyance drainage systems to vegetated infiltration

More information

GRP Manholes and Chambers. for Gravity and Pressure Applications

GRP Manholes and Chambers. for Gravity and Pressure Applications GRP Manholes and Chambers for Gravity and Pressure Applications Table of contents 1 GRP Manholes and Chambers...3 1.1 General Information... 3 1.2 Purpose... 3 1.3 Quality Standards... 3 1.4 Features &

More information

Top 10+ Mistakes of DWV plumbing design

Top 10+ Mistakes of DWV plumbing design Top 10+ Mistakes of DWV plumbing design Listed below are the some of the most frequently missed items, noticed by our inspectors, at plumbing rough-in when non-plumbers attempt plumbing design. Most of

More information

SECTION 724 PIPE CULVERTS

SECTION 724 PIPE CULVERTS SECTION 724 PIPE CULVERTS 724.1 Description. This work shall consist of providing pipe or pipe arch of the diameter or shape designated, laid upon a firm bed and backfilled as specified. Where appropriate

More information

Type of Sewer Systems. Solomon Seyoum

Type of Sewer Systems. Solomon Seyoum Type of Sewer Systems Solomon Seyoum 0 Learning objectives Upon completion of this lecture, the participants will be able to differentiate between types of sewer systems and discuss different aspects of

More information

STANDARD PLUMBING AND DRAINAGE REGULATION 2003

STANDARD PLUMBING AND DRAINAGE REGULATION 2003 Queensland Subordinate Legislation 2003 No. 265 Plumbing and Drainage Act 2002 STANDARD PLUMBING AND DRAINAGE REGULATION 2003 TABLE OF PROVISIONS Section Page PART 1 PRELIMINARY Division 1 Introduction

More information

NAYLOR. Metro Duct. The Complete Duct and Access System M E T R O D R A I N. The MANUFACTURING EXCELLENCE Awards Winner - Best SME

NAYLOR. Metro Duct. The Complete Duct and Access System M E T R O D R A I N. The MANUFACTURING EXCELLENCE Awards Winner - Best SME NAYLOR M E T R O D R A I N Metro Duct The Complete Duct and Access System e m a i l : s a l e s @ n a y l o r. c o. u k w e b : w w w. n a y l o r. c o. u k Winners Growing Business The MANUFACTURING EXCELLENCE

More information

PREDICTING THE RESIDUAL LIFE OF PVC SEWER PIPES.

PREDICTING THE RESIDUAL LIFE OF PVC SEWER PIPES. PREDICTING THE RESIDUAL LIFE OF PVC SEWER PIPES. A. J. Whittle Iplex Pipelines Australia Pty Limited. J. Tennakoon Ipswich Water, Queensland, Australia. ABSTRACT Ipswich Water commenced reviewing the service

More information

Ridgistorm-XL - the latest innovative

Ridgistorm-XL - the latest innovative Ridgistorm-XL - the latest innovative solution to SUDS and stormwater management Combined with the technical expertise, knowledge and support of Polypipe, Ridgistorm-XL is designed as a bespoke application

More information

PP MASTERTM S T I F F N E S S S N 1 2 R I N G THE NEW POLYPROPYLENE SEWER PIPE SYSTEM

PP MASTERTM S T I F F N E S S S N 1 2 R I N G THE NEW POLYPROPYLENE SEWER PIPE SYSTEM PP MASTERTM R I N G S T I F F N E S S S N 1 2 THE NEW POLYPROPYLENE SEWER PIPE SYSTEM The future today. PP MASTERTM The new standard in sewer construction. A powerful piece of the future: PP MASTER, a

More information

ENGINEERING STANDARDS MANUAL SECTION 5 WASTEWATER DRAINAGE

ENGINEERING STANDARDS MANUAL SECTION 5 WASTEWATER DRAINAGE CODE OF PRACTICE FOR CITY INFRASTRUCTURE & LAND DEVELOPMENT ENGINEERING STANDARDS MANUAL SECTION 5 WASTEWATER DRAINAGE Issue 4.6 Sept 2008 Section 5 Page 1 SECTION 5.0 WASTEWATER DRAINAGE Note: The adoption

More information

3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees.

3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees. The following shall serve as the minimum requirements for contractors performing work in relation to the Authority s potable water and sanitary sewer system(s), appurtenances and service connections. General:

More information

SECTION 9.02 BUILDING SUBSURFACE DRAINS (PERIMETER, ETC.)

SECTION 9.02 BUILDING SUBSURFACE DRAINS (PERIMETER, ETC.) CHAPTER 9 SEWER / STORM DRAIN / IRRIGATION LINES SECTION 9.01 GENERAL This section covers the requirements for piping materials and installation of Lehi City sewer, storm drainage and irrigation collection

More information

SECTION 02700 SEWERAGE AND DRAINAGE PART 1 - GENERAL 1.01 RELATED DOCUMENTS

SECTION 02700 SEWERAGE AND DRAINAGE PART 1 - GENERAL 1.01 RELATED DOCUMENTS SECTION 02700 SEWERAGE AND DRAINAGE PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including the General and Supplementary Conditions and Division 1 Specification

More information

This unit is a pump that will clear the waste from a domestic shower and washbasin, bath, washing machine, glass washer and a sink.

This unit is a pump that will clear the waste from a domestic shower and washbasin, bath, washing machine, glass washer and a sink. 1. Description This unit is a pump that will clear the waste from a domestic shower and washbasin, bath, washing machine, glass washer and a sink. The unit will start automatically. Please pay particular

More information

ACO Water Management: Civils + Infrastructure

ACO Water Management: Civils + Infrastructure ACO Water Management: Civils + Infrastructure Uniclass L3 + L735 CI/SfB (5.5) EPIC J343 ACO MultiDrain MD ACO MultiDrain MD channel drainage system Technical Data ACO MultiDrain MD Introduction to the

More information

CONTENTS. Yale University Design Standards. Underground Electrical Duct Bank. A. Summary. B. System Design and Performance Requirements

CONTENTS. Yale University Design Standards. Underground Electrical Duct Bank. A. Summary. B. System Design and Performance Requirements 16600 Underground Electrical Duct Bank This document provides design standards only, and is not intended for use, in whole or in part, as a specification. Do not copy this information verbatim in specifications

More information

Concrete Pipes. Concrete Pipes

Concrete Pipes. Concrete Pipes Various Types of Manufactured and Supplied by the Wolfman Company 1. Data Concrete pipes of all types are manufactured at Wolfman according to IS-27 (May 2010). IS 27 is the Israeli Standard that adopted

More information

Section 02702 SEWER PIPE INSTALLATION AND TESTING

Section 02702 SEWER PIPE INSTALLATION AND TESTING PART 1 - GENERAL Section 02702 SEWER PIPE INSTALLATION AND TESTING 1-1. SCOPE. This section covers the installation and testing of all sewer pipe furnished under the following specification sections: Concrete

More information

CHAPTER 6 - SANITARY SEWER

CHAPTER 6 - SANITARY SEWER CHAPTER 6 - SANITARY SEWER 6.1 GENERAL This section covers the requirements for PVC plastic sewer pipe materials and installation in sanitary sewer construction. 6.2 PIPE PVC gravity sewer pipe and fittings

More information

EXCAVATION AND PILING NEAR SEWERS, STORMWATER DRAINS AND WATER MAINS

EXCAVATION AND PILING NEAR SEWERS, STORMWATER DRAINS AND WATER MAINS NMP 1.4 EXCAVATION AND PILING NEAR SEWERS, STORMWATER DRAINS AND WATER MAINS Index Purpose... 2 Application... 2 Referral Agency... 2 Associated Requirements... 2 Referenced Standards...2 Definitions...

More information

SANITARY SEWER SPECIFICATIONS

SANITARY SEWER SPECIFICATIONS SANITARY SEWER SPECIFICATIONS OCTOBER 2003 HARVEST-MONROVIA WATER, SEWER, AND FIRE PROTECTION AUTHORITY SECTION 1.00 1.10 Purpose The purpose of this document is to assemble the sewer specifications, policies,

More information

CIVIL ENGINEERING. Sewage Pipe System. POLO-ECO plus PREMIUM 12. POLO-ECO plus PREMIUM 10

CIVIL ENGINEERING. Sewage Pipe System. POLO-ECO plus PREMIUM 12. POLO-ECO plus PREMIUM 10 CIVIL ENGINEERING Sewage Pipe System POLO-ECO plus PREMIUM 12. POLO-ECO plus PREMIUM 10 POLO-ECO plus PREMIUM The trend-setting advancement of 3-layer technology POLO-ECO plus PREMIUM with an extra measure

More information

SIENA STONE GRAVITY RETAINING WALL INSTALLATION SPECIFICATIONS. Prepared by Risi Stone Systems Used by permission.

SIENA STONE GRAVITY RETAINING WALL INSTALLATION SPECIFICATIONS. Prepared by Risi Stone Systems Used by permission. SIENA STONE GRAVITY RETAINING WALL INSTALLATION SPECIFICATIONS Prepared by Risi Stone Systems Used by permission. 1-800-UNILOCK www.unilock.com FOREWORD This outline specification has been prepared for

More information

Prepare a drainage system layout and specification notes for a low- rise building.

Prepare a drainage system layout and specification notes for a low- rise building. STUDENT MATERIALS Prepare a drainage system layout and specification notes for a low- Outcome 1 - rise building. In this outcome you will study the technology of below and above ground drainage systems.

More information

Saferand easierinstallation

Saferand easierinstallation EN 85-07 Saferand easierinstallation IföSigninstallationsystem andifösignbuilt-incistern www.ifosanitar.com/sign Aneffectivesolution withmanyadvantages. Ifö Sign installation system makes life a little

More information

Louisiana Administrative Code Title 51 Part XIII. Sewage Disposal

Louisiana Administrative Code Title 51 Part XIII. Sewage Disposal Louisiana Administrative Code Title 51 Part XIII. Sewage Disposal Regulations Regarding Septic Tank Installations with Field Beds/Absorption Trenches For Individual Residential Installations Chapter 3.

More information

REPAIRS TO DAMAGED SEWERS

REPAIRS TO DAMAGED SEWERS REPAIRS TO DAMAGED SEWERS A digout is the replacement of sewer or storm water pipes that are either broken or blocked due to tree roots, ground movement or ageing of pipes. When the use of high-pressure

More information