1 Audit of Coal and Petroleum Exploration Licences in NSW PHASE 2 REPORT April 2012

2 CONTENTS 1. EXECUTIVE SUMMARY TASK PHASE BACKGROUND METHODOLOGY SUMMARY OF RESULTS DETAILED ANALYSIS CONSULTATION LEGAL RECOMMENDATIONS APPENDIX.. 37 a) Summary of Typical Conditions s and s b) List of s and s Audited in Phase 2 c) Summary of significant risk non-compliances identified by auditors d) Project Plan and Timetable e) Audit of Exploration Licences in NSW August 2011 Guideline f) Key Results of Audit g) Breakdown of Results into Resources & Energy Units h) Mining Act 1992, Part 11, Division 6 i) Petroleum (Onshore) Regulation 2007, Clause 27A

3 1. EXECUTIVE SUMMARY This report provides the results of Phase 2 of the Audit of Coal and Petroleum (coal seam gas) Exploration Licences in NSW. The audit forms part of the staged implementation of the Government s Strategic Regional Land Use Policy. Phase 1 involved a desktop audit of all Exploration Licences (s) for coal and Petroleum Exploration Licences (s) to identify areas or specific licences warranting more detailed audits against all conditions. For a summary of typical and conditions please refer to Appendix A. Out of a total 187 coal s and 49 s, 20 coal s and 22 s were identified and then targeted for the Phase 2 audit (see Appendix B). Phase 2 involved a detailed independent audit to identify licence holder compliance with all conditions of s and s. The aim was to measure compliance with conditions and from that recommend changes to process or conditions where considered appropriate. The audits were undertaken against all licence conditions pertaining to each licence respectively, with the exception of 7223 which was not audited against environmental conditions as it was subject to a full compliance audit against these conditions earlier this year. Conditions were divided into groupings for analysis by the Department of Trade and Investment, Regional Infrastructure and Services Division of Resources & Energy (Resources & Energy). They included Titles, Coal Advice, Petroleum Geoscience, Environment and Safety. Consultation with the Office of the Environment & Heritage (OEH) and the Department of Planning & Infrastructure (DP&I) was undertaken during the audit program and review process. The audits were undertaken at the licence holder s expense by independent auditors, approved by Resources & Energy. Requests to conduct audits were sent on 30 August Report on Audit of Coal and Petroleum Exploration Licences in NSW Phase 2 3

4 2011. All 42 audits were completed and submitted to Resources & Energy by 31 October A Government official attended approximately 55% of the audits to observe and verify evidence of compliance. This included officers from Resources & Energy, as well as officers from OEH and DP&I. The results indicate an overall high level of compliance with licence conditions. In total 87% of the conditions audited were either fully compliant, with no observations, or not applicable (as they had not been triggered yet). Observations, which referred to conditions that were technically compliant but where improvements to performance could be made, were reported against 8% of conditions. Of the total 1355 individual conditions audited, 5% were found to be non-compliant. There were 11 level NC1 (significant risk) non-compliances and 55 level NC2 (low risk) non-compliances. For a summary of the significant risk non-compliances, identified by auditors, please refer to Appendix C. Of the 11 NC1 level non-compliances identified, on review by Resources and Energy four were considered by to be low risk or NC2 level non-compliances, (for example the conditions for storage of drill core). Resources & Energy officers have acted upon, or are continuing to act upon, the significant risk non-compliances identified. Corrective actions are also to be followed up with licence holders for those NC1s that had no previous enforcement action. Some reasons for non-compliance were: Not meeting reporting requirements for geological and environmental conditions; Environmental actions not completed satisfactorily; Approvals not sought from Resources & Energy; and Lack of documentation or updating of documentation required. A total of nine recommendations have resulted from this audit. Four pertain to changes to conditions and five pertain to changes to process. Report on Audit of Coal and Petroleum Exploration Licences in NSW Phase 2 4

5 2. TASK PHASE TWO Phase two required undertaking a detailed audit of licence holder compliance with all conditions of Exploration Licences (s) for coal and Petroleum Exploration Licences (s). Responses to the audit were then compiled, analysed and this report provides detailed results identifying areas of non-compliance and recommends changes to process or conditions where considered necessary. 3. BACKGROUND On 12 May 2011, Cabinet approved a state-wide audit of coal and coal seam gas exploration licences to review their current status and ensure holders are adhering to conditions of their licences. In order to complete the audit within a timeframe of six months and reduce the level of resources required, it was undertaken in two phases. Phase 1 Phase 1 involved a desktop analysis of all existing licences to identify areas of noncompliance including a review of: Grant date, number of renewals, last renewal date, pending title dealings, current expenditure commitment and security held; Status of geological reporting; and Surface Disturbance Notifications, list of approved activities, number of site inspections carried out, incident reports received, enforcement actions, rehabilitation reporting status, pending dealings, Rehabilitation and Relinquishment Reports (only if security release is requested) and individual approval requirements regarding reporting. Following compilation of data and analysis, a report was prepared to outline the areas of non-compliance and identify areas or specific licences warranting more detailed audits against all conditions. Report on Audit of Coal and Petroleum Exploration Licences in NSW Phase 2 5

6 Phase 2 Phase 2 involved a detailed assessment of the licences identified through the desktop audit process (Phase 1). Licence holders were required to provide additional information, including evidence of compliance, to enable an effective audit of compliance against all of the licence conditions. Audits were carried out by independent auditors engaged at the licence holder s expense, including targeted field compliance inspections. Following compilation and analysis of the results, this report has been prepared to provide a summary of the results and recommendations for changes to process and conditions where considered necessary. The audit process has been the responsibility of the Department of Trade and Investment, Regional Infrastructure and Services Division of Resources & Energy (Resources & Energy). It has been undertaken in consultation with the Office of Environment & Heritage (OEH) and the Department of Planning & Infrastructure (DP&I). Resources & Energy is also responsible for reporting the status of the audit process to the Strategic Land Use Working Group (SLUWG). Resources & Energy is responsible for enforcing compliance with and requirements. Report on Audit of Coal and Petroleum Exploration Licences in NSW Phase 2 6

7 4. METHODOLOGY A project plan for the audit was developed, setting out responsibilities, actions to be taken and a timetable for the audit to be completed by 30 November A copy of the Project Plan is attached as Appendix D. The audit covers the responsibility of a number of separate units within Resources & Energy. The responsibilities of these units are: Titles Administers the grant and renewal of exploration and mining titles, including special conditions, under the Mining Act 1992 and the Petroleum (Onshore) Act Coal Advice Assesses exploration reports. Checks that reports follow the guideline (Exploration Reporting: A Guide for Reporting on Exploration and Prospecting in NSW) and contain the relevant technical information and geological data. Prepares the report for archiving in DIGS. Compiles a list of titles which are not complying with exploration reporting Condition 44/Section E and follows up non-compliance. Provides recommendations to the Titles section with respect to the granting and renewal of titles based on proposed and completed exploration work programs and reporting compliance. Provides advice on title conditions to licence holders, such as Condition 20 Core and Samples. Engages with other Government Departments that require notifications, as per conditions, from licence holders. Petroleum Geoscience Titles Management - Reviews applications, renewals, variations and suspensions of s by providing technical comments as to their merit, sufficiency and compliance. - Receives, evaluates and accepts all reports by matching them with title conditions, compliance and archiving. Report on Audit of Coal and Petroleum Exploration Licences in NSW Phase 2 7

8 - Monitors and gives advice on exploration work program commitment. - Receives technical presentations on work programs, visits field operations and monitors exploration activities of licence holders. - Facilitates the performance of work programs and submission of reports by giving advice and administering guidelines and policy. - Evaluates end of title or surrender/cancellation of permit reports and recommends release of security. Database Management - Receives, catalogues, analyses and accepts all reports, field data, processed data and interpretation reports for archiving and database management. - Provides data to clients. Environment (Environment Sustainability Unit) Assesses environmental impacts of exploration activities in accordance with Part 5 of the Environmental Planning and Assessment Act Regulates environmental sustainability performance of exploration activity. Provides recommendations to the Titles section with respect to the granting and renewal of titles based on environmental performance of the explorer. Mine Safety Operations Regulates Occupational Health & Safety (OHS) of exploration activity. Audit Process A letter requesting an audit be undertaken against all of the licence conditions was sent to 42 licence holders on 30 August A number of requirements were included stating that the: Audit (including preparation of the audit report) be carried out by an independent auditor directly engaged by the licence holder, at the holder s expense. Auditor be accredited to undertake site audits and be approved by the Executive Director Mineral Resources. Prior to the audit commencing, approval of the Report on Audit of Coal and Petroleum Exploration Licences in NSW Phase 2 8

9 auditor was sought in writing and had to include details establishing independence and the absence of conflict of interest. Where possible, the auditor was accompanied by an officer of the NSW Government to verify the audit process. Licence holder was to notify Resources & Energy of the date of commencement of the audit, giving seven days prior notice and include a timetable for the audit. Audit report was to be returned to Resources & Energy no later than 14 October Audit was undertaken in accordance with the template and guideline provided titled Audit of Exploration Licences in NSW August 2011 (refer to Appendix E). Audit report comprise details of the audit carried out including purpose, scope, audit team details, pre-audit planning, audit timetable, opening meeting between auditor and licensee, audit procedure, audit outcome, discussion, closing meeting between auditor and licensee, conclusions, recommendations and corrective action reports. A number of licence holders requested an extension of time to complete the audit and these were granted. All audits were completed as requested by 31 October To assist licence holders and their auditors review the current status of the exploration licences and to facilitate responses for the audit, a guideline document was prepared by Resources & Energy. The purpose of the guideline was to provide a basis to understand the intent of the audit process, with suggested questions and methodologies to assist in obtaining the evidence required to verify compliance or otherwise. The auditor conducting the audit was advised that they may amend, or add to, the questions as necessary to verify compliance with all of the exploration licence conditions. To ensure that all conditions of the licence were audited, the auditor was to obtain, and use, the conditions of authority specified in the exploration licence current at the time of audit. The audit provides an examination of compliance with conditions at the time of the audit. The audit included a review of relevant documents referred to in the exploration Report on Audit of Coal and Petroleum Exploration Licences in NSW Phase 2 9

10 licence and conditions, interviews with licensee personnel and/or inspection of the operational areas of the site to confirm the results of the audit interviews. Each of the licence holders submitted details of their proposed auditor to Resources & Energy for approval prior to commencement. A review panel consisting of three Resources & Energy staff was established to review the auditor proposals and to make recommendations as to their suitability to the Executive Director Mineral Resources (EDMR). This panel was established to provide some rigour to the "acceptability" test, and included representatives from Environmental Sustainability Unit, Coal Advice Unit and Minerals & Land Use Assessment Unit. The licence holder was requested to provide information about the auditor including: Qualifications Affiliations Experience A statement regarding conflict of interest. As part of the review process several of the licence holders were requested to provide additional information prior to the approval of auditors, to enable the panel to adequately evaluate the appropriateness of the auditor. All of the detailed audits, conducted as Phase 2, took place between 30 August and 31 October A number of the audits were also attended by officers from either Resources & Energy, OEH or DP&I to validate and review the audit process. Government officers attended 55% of the audits undertaken. The audits were generally conducted over a number of days and included both documentation review and field inspections. The officers ensured that the auditors understood the scope of the audit, as well as checked that enough information was being sourced to complete the audit and the auditors had the full co-operation of the licence holders. Feedback from these officers, indicated that the auditors were thorough and sought the relevant information. Report on Audit of Coal and Petroleum Exploration Licences in NSW Phase 2 10

11 Analysis A consultant experienced in the undertaking and analysis of audits, Umwelt (Australia) Pty Ltd (Umwelt), was engaged to undertake the initial assessment of the audit reports. The methodology used by Umwelt to review the audit reports submitted is summarised below: The review team reviewed each audit report and used the audit analysis spreadsheets to record each auditor s assessment scores for each licence condition. Each reviewer then undertook a brief adequacy assessment of the audit findings by reviewing the list of audit evidence provided by the auditor and any comments made by the auditor. Collation and analysis of the audit findings were undertaken for both coal and petroleum exploration licences. Audit review findings have been documented in the analysis spreadsheets with graphical summaries of key issues. Key results of the audit outlining levels of compliance and observations are included in Appendix F. The results of the initial review, as well as the final audit reports, were then further reviewed by each of the specialist units within Resources & Energy to determine the degree of compliance with licence conditions and the number of non-compliances and observations. The non-compliances and observations were then reviewed in further detail by the units to examine the reasons for any non-compliance and to identify if they were significant or otherwise. Recommendations on improvements to process or changes to licence conditions were also made (refer to Chapter 9 Recommendations). Report on Audit of Coal and Petroleum Exploration Licences in NSW Phase 2 11

12 The test of compliance and/or breaches of conditions The following table outlines the definitions used in the Compliance Audit Checklist that was circulated to auditors as part of the audit guideline document and subsequently used in their reports. Table 1: Compliance Definitions C Compliance Adequate and appropriate implementation against current Departmental approval or conditions, or compliance with commitments made. O Observation A finding which is not likely to significantly affect the operation, which does not strictly relate to the scope of the audit of compliance and which could lead to performance improvement. NC Non-Compliance An inadequacy in the design and/or implementation against current Departmental approvals, licence conditions or management commitments. There are two subcategories of non-compliance: Category 1 (NC1) - a total absence of planning or implementation of a required operations element which presents an immediate risk or an isolated lapse in control in the implementation of an operations element which will lead to a significant risk, or Category 2 (NC2) - an isolated lapse or absence of control in the implementation of an operations element which may not be of significant risk. NA Not Applicable Used where a condition may not have been triggered or was not applicable for that particular licence. Report on Audit of Coal and Petroleum Exploration Licences in NSW Phase 2 12

13 5. SUMMARY OF RESULTS Level of compliance The audit results indicate an overall high level of compliance with licence conditions. In total 87% of the conditions audited were either fully compliant with no observations or not applicable (as they had not been triggered yet). Observations, which referred to conditions that were technically compliant but where improvements to performance could be made, were reported against 8% of conditions. Of the total 1355 individual audit conditions audited, 5% were found to be noncompliant. There were 11 level NC1 (significant risk) non-compliances and 55 level NC2 (low risk) non-compliances. Compliance Results Coal Exploration Licences The level of compliance recorded by the auditors was very high with only four of the 20 coal s audited having a reported NC1 (significant risk) non-compliance. Out of these four s, there were a total of 8 NC1 non-compliances reported. There were 30 NC2 (low risk) non-compliances reported across 12 s. Seven of the s audited reported no non-compliances. All audits, however, had some level of observation recorded. It is noted that there are a number of instances where multiple non-compliances recorded against a licence relate to a single incident. A number of these incidents had already been investigated by Resources & Energy and enforcement action taken. A number of licence conditions were noted as not assessed. This may have been because no activity, such as drilling, was occurring at the time of the audit was not assessed against environmental conditions as a full environmental audit was completed by Resources & Energy earlier this year. The only NC1 non-compliances reported in the category of Environment was in relation to 6288, which had four reported. Three of these reported non-compliances all related to the same incident, where an exploration activity was carried out without appropriate secondary approvals from Resources & Energy. Enforcement action had already been undertaken in relation to this incident. The fourth NC1 related to the use of non-native pasture grass in the revegetation of a drill site in a woodland area. Report on Audit of Coal and Petroleum Exploration Licences in NSW Phase 2 13

14 Most non-compliances (NC1 and NC2) reported under the Coal Advice category related to reporting requirements or the incorrect storage of drill core samples. Following further inquiry, Resources & Energy have concluded that storage is adequate. These noncompliances are all matters that should be readily observable by the Resources & Energy through its administration of exploration licences. A number of observations by auditors noted discrepancies between the reporting requirements under the terms of the licence and the obligations required by the Mining Regulation There were two reports of NC1 level non-compliance and four NC2 level noncompliances regarding safety related conditions. The NC1 recorded against 6433 related to risk assessment process and inadequate documentation. The NC1 recorded against 7223 related to non-conformance with safety management plan (SMP) requirements and poor maintenance of records. Following further inquiry, Resources & Energy have concluded that these two NC1 level non-compliances regarding safety related conditions were in fact lower level NC2 level non-compliances. There were no non-compliances reported for any s under the category of Titles. Out of the 42 licences, five were audited regarding their compliance with special conditions. Auditing of these conditions was variable due to the nature of the requirements under the conditions. The following charts show a breakdown of the audit results for each and the status against individual Resources & Energy categories of responsibility. Report on Audit of Coal and Petroleum Exploration Licences in NSW Phase 2 14

15 ComplianceStatusbyLicenceCoals NotAssessed NA C O NC2 NC Auth Auth 438 Auth 315 Auth 311 Auth 342 Auth SummaryofComplianceStatusbyDRECategoryCoals NotAssessed NA C O NC2 NC Environment CoalAdvice CoalSafety Titles SpecialConditions NC NC O C NA NotAssessed Report on Audit of Coal and Petroleum Exploration Licences in NSW Phase 2 15

16 Compliance Results Petroleum Exploration Licences The level of compliance recorded by the auditors was very high with only two of the 22 s audited having a reported NC1 (significant risk) non-compliance. Out of these two s, there were a total of three NC1 non-compliances reported. There were 25 NC2 (low risk) non-compliances recorded across 13 s and nine of the s audited were fully compliant. All audits, however, had some level of observation recorded. Two licences reported NC1 level non-compliances. The non-compliance reported for 445 related to the suspected dumping of drilling muds. Two NC1 level noncompliances were reported for 458. One related to the failure to properly rehabilitate a site, while the other non-compliance related to possible acid sulphate soil issues and the lack of appropriate surface water and groundwater monitoring. The NC2 level non-compliances reported under the Petroleum Geology category generally related to deficient, absent or late exploration reports. There is only one safety condition specifically prescribed in the, however licence holders are also required to comply with the Schedule of Onshore Petroleum Exploration and Production Safety Requirements as outlined in Clause 27 of the Petroleum (Onshore) Regulation A number of the requirements of the Schedule of Onshore Petroleum Exploration and Production Safety Requirements were audited as these were included as typical questions in the safety and environment categories in the audit guideline. No NC1 level compliances were reported for any s under the safety category. No NC1 level non-compliances were reported under the Titles category for s. The following charts show a breakdown of the audit results for each and the status against the Resources & Energy categories of responsibility. Report on Audit of Coal and Petroleum Exploration Licences in NSW Phase 2 16

17 ComplianceStatusbyLicencePetroleums NotAssessed NA C O NC2 NC SummaryofComplianceStatusbyDRECategoryPetroleums NotAssessed NA C O NC2 NC Environment Petroleum Geology PetroleumSafety NC NC O C NA NotAssessed Titles Please refer to Appendix G for a full summary of compliance by Resources & Energy category. Report on Audit of Coal and Petroleum Exploration Licences in NSW Phase 2 17

18 6. DETAILED ANALYSIS Each of the specialised units within Resources & Energy analysed the audit results, in particular the non-compliances and observations. Overall, the level of compliance across conditions for both coal and petroleum exploration licences was high, with 87% of the conditions having no non-compliances or observations recorded against them. The following comments were provided: Titles (Coal) Only one coal exploration licence (Authorisation 444) was reported as being non- compliant (NC2) against two conditions: In regard to these two non-compliances, the licence holder had provided the required information, however it was outside the timeframe given. The reason being that this particular title is jointly held and both parties have been operating independently. Observations were made against four coal exploration licences, three of which were against condition 32. The other was made against condition 21: Condition 32 is an overarching condition that indicates that for the purpose of condition 29 (the security held against the title), the licence holder shall be deemed to have failed to fulfil the obligations of the licence if they fail to comply with any condition, provision, condition of consent or approval, any provisions of the Mining Act 1992 or Mining Regulation 2010 or any direction or instruction given by the Resources & Energy. For the purpose of the audits, as per advice from Coal Advice, Mine Safety and Environment Sustainability Unit, no noncompliance or observation from the audit would result in the security being taken and used for the fulfilment of the licence holder s obligations. As such, it is considered that condition 32 would not come into effect for any of the observations made. Condition 21 relates to the notification of utility holders in relation to transmission lines, communication lines, pipelines and other public utilities where exploration Report on Audit of Coal and Petroleum Exploration Licences in NSW Phase 2 18

19 activities may impact on the infrastructure. The auditor indicated that no drilling had occurred during the current licence period, therefore there is no noncompliance with this condition, however previous notifications were considered to be inadequate. Titles (Petroleum) Only two petroleum exploration licences ( 2 & 443) were reported as being non- compliant (NC2) against one condition each: 2 was reported as non-compliant for condition 17 (the work program specified in the third Schedule is to be completed by the licence holder to the satisfaction of the Minister). Whilst the auditor gave a status as NA for Condition 17, the assessment of the work program against the requirements of Schedule 3, which was included in the auditor's compliance tables, indicated non-compliance in relation to a variation to the work program which was not notified and approved by the Resources & Energy. Work programs are often varied due to delays caused by approvals, weather, land access and equipment availability. These reasons are acceptable and licence holders do not have influence over these factors. The licence holder is in contact (via or phone) with the Manager Petroleum Geoscience when such circumstances occur, which is considered satisfactory. 443 was also reported as non-compliant for condition 17. The auditor assessed this condition with two items, NC2 and O. It was noted that Item 1 of the program of work was completed and a report submitted to Resources & Energy, however Item 2 had not been completed. The auditor commented that the current management team were understaffed which led to delays in report submission. The technical manager consults with Manager Petroleum Geoscience (via or phone) about the works undertaken and the planned work, which is considered sufficient. From the comments provided by Petroleum Geoscience in relation to these reported non-compliances, Resources & Energy does not consider that non-compliances have occurred. Report on Audit of Coal and Petroleum Exploration Licences in NSW Phase 2 19

20 Observations were made against 12 petroleum exploration licences, most of which were against conditions 16 (nomination of an exploration manager) and 17 (completion of a work program): For condition 16, many licence holders provided details to Resources & Energy of the technical advice that they have access to without actually nominating a technical manager and providing that persons details. This is considered to be acceptable to Resources & Energy. In regards to the observations for condition 17, some titles have variation dealings recorded in the Titles Administration System so variations to work programs have been applied for by the licence holders (specifically s 4, 267 and 427). Additionally, if the licence holders have not complied with the proposed program of work when the licence is due for renewal, they will have to justify why the program hasn t been met and substantiate why a licence should be renewed. In relation to the observation regarding condition 27(security) against 445, additional security for the drilling program approved in February 2011 has been provided. The observation made against 6 regarding plug and abandonment of one CSG core hole, in accordance with engineering specifications but without detailed assessment of implementation or Resources & Energy approval is noted. It was also noted that other nearby core holes were suitably assessed and approved by Resources & Energy. Coal Advice Eight coal exploration licences were noted as being non-compliant against either condition 38 (core samples), 42 (technical management) or 44 (geological reports). Two of these licences recorded NC1 non-compliances: The audit for 7223 reported inadequate storage of drill core. Resources & Energy does not consider the storage of core to be an NC1 non-compliance. While the auditor believed that plastic shrink wrapping of core was necessary, it is not typically done. Ease of access to stored core is also typically not an issue as reviewing logged and sampled core occurs infrequently. Drill core is Report on Audit of Coal and Petroleum Exploration Licences in NSW Phase 2 20

21 reasonably durable and there is low risk of core damage if it is temporarily exposed to weather before final storage. Malicious damage is a very low risk due to the remote location of the site. The audit for 5072 reported inadequate geological reporting. Inadequate geological reporting is not considered a NC1 non-compliance by Resources & Energy. The implementation of amendments to the Mining Act 1992 in November 2010 brought in new reporting formats and compliance requirements, with a 12 month transition period to ensure all companies became compliant with the new requirements. All reporting on 5072 is now up to date, adequate and in the correct format. The additional non-compliances were rated as NC2: There were a number of non-compliances reported against condition 38. The auditor noted that no drilling has occurred during the current licence period for 5297, however, previous management relating to the requirements of this condition were inadequate. For condition 42, Authorisation 311 and 315, as well as 5297, were noted as non-compliant as no formal advice to Resources & Energy of a change of technical manager was provided. It has been noted that advice was provided to the Coal Advice section via . For condition 44, a number of licences, 5297, 5892, 4968 and Authorisation 404 had non-compliances identified due to reports being late or not submitted at all. Coal Advice has noted that all of these reports have been provided and the non-compliance has been reported because they have been late or provided inadequate information. A possible reason is companies could not provide evidence they had submitted the reports so auditors noted a noncompliance. All current reporting is up to date for these licences. Of all the observations raised that are the responsibility of the Coal Advice section, conditions are being complied with and are not considered an issue, except for submission of annual reports from The audit report stated that two annual reports were sighted and that they were accepted by Resources & Energy. Resources & Report on Audit of Coal and Petroleum Exploration Licences in NSW Phase 2 21

22 Energy s evidence suggests that the report submitted was rejected and that a replacement has not yet been received. It has been noted that there are a number of conditions where the auditor has reported a not applicable response. This is considered to be appropriate as many conditions would not have been triggered in the activities of the licence. The Mining Act 1992 has provision for fines for non-compliance with reporting. A fine is a last resort and Resources & Energy now does a monthly check and notifies licence holders if they are late and requests reports be submitted promptly. There is a lack of awareness of what some of the licence conditions mean or an ignorance of conditions amongst employees of the licence holders, which will need to be addressed in an ongoing education process. Petroleum Geoscience Five petroleum exploration licences were noted as being non-compliant against condition 21 (reports and format for fixed agenda operations): 2, 4, 267, 285 and 285 had non-compliances reported due to reports being submitted outside the required timeframe or for reports lacking sufficient detail, as required by the licence condition. A reason for this may be inconsistency between the guidelines and condition, regarding the expected content of reports. All the observations raised in the audit reports that fall under Petroleum Geoscience s responsibility relate to conditions 21 and 22 (reports and format for fixed agenda operations). The following comments were made: Cuttings and core were not always submitted (not accepted) even though they were offered and made available to Resources & Energy. This raises a question of how long samples should be kept by licence holders and if they will be made available to Resources & Energy in the future. A review of storage capacity at Resources & Energy s Londonderry storage facility is also required. Some licence holders did not submit all of the required data. Report on Audit of Coal and Petroleum Exploration Licences in NSW Phase 2 22

23 Observations relating to the late submission of reports were also raised. In some cases interim reports were submitted. Petroleum Geoscience does not penalise companies for delayed submission, as long as the report was submitted in a reasonable timeframe. It is also not considered a faulty submission to provide a non-dated report. EROL (Exploration & Environmental Reports Online Lodgement) has a tool indicating when the report was submitted. Observations also indicate that receipt of submission is not always provided by Resources & Energy. It should be noted that EROL sends an auto response that the report was submitted (even if the report is not satisfactory). There is no receipt for submission of statistics and reminders are only issued if statistical returns are not submitted. Restrictions on file size submission via EROL were communicated to Resources & Energy. The reasons for delay and non-compliance in report submission are as follows: The Petroleum Act guideline is not attuned to the coal seam gas exploration and production conditions. The Act must be reviewed and amended. Submission of well completion reports six months after completion of operations is not realistic. One (1) year might be considered. There are too many reports to submit (such as annual, operational, end of work program, relinquishment, interim, statistics etc). The audit reports suggest a trend that Resources & Energy does not provide feedback regarding the submission of reports. Resources & Energy s approach has been to provide negative feedback, such as report rejection when important information is missing. If the report is accepted there is no feedback given to the company as there is no tool in EROL to automatically send a message that the report is satisfactory. This feedback is provided to the company upon request. Safety (Coal) Five coal exploration licences were noted as being non-compliant against either condition 26 (maintenance of open drillholes) or 36 (safety of operations). Two of these licences recorded NC1 non-compliances: Report on Audit of Coal and Petroleum Exploration Licences in NSW Phase 2 23

24 The audit of 7223 identified NC1 non-compliances relating to inadequacies with Safety Management Plans, specifically relating to: o Not all drill rig sites undertake or maintain risk management documentation in line with site Safety Management Plan (SMP) requirements. This relates to the "Take 5" hazard awareness tool, which was not being used as required in the SMP. Given that a SMP was in place for the site and there is no requirement to develop an SMP in the legislation referred to in the licence condition, Resources & Energy believe this non-compliance is more appropriately categorised as an NC2 (an isolated lapse or absence of control in the implementation of an operations element which may not be of significant risk). o Records not being maintained. This is related to administrative elements of the licence condition, and as such does not have an immediate risk and is more appropriately categorised as an NC2. The audit of 6433 identified that risk was not adequately documented or aligned with a recognised risk assessment process (International or Australian Standards). This is not considered an NC1 non-compliance in that there is no specific requirement to do the Risk Management Plan to the specifications that the auditor has indicated. This again is more appropriately categorised as an NC2. The additional non-compliances were rated as NC2: For condition 26, the audit report for Authorisation 404 noted that Resources & Energy was not notified that two holes were left open. The audit report for 6433 noted that a landowner had requested that a hole be left open, but no evidence was sighted to confirm this request. For condition 36, audit reports for 5410 identified non- compliances relating to inadequacies with Safety Management Plans identified that material safety data sheets (MSDS) were not available for all for materials held by the drilling contractors on site and some MSDS were more than five years old. Coal Safety believes these non-compliances are related to administrative elements and a failure of licence holder s safety management systems, rather than an immediate risk. Report on Audit of Coal and Petroleum Exploration Licences in NSW Phase 2 24

25 As such no serious problems are anticipated. Completion of corrective actions and a review of systems by licence holders are expected to rectify these issues. The observations raised in the audit reports that fall under Coal Safety s responsibility relate to condition 36 (safety of operations): 5883 audit report indicates the licence holder is relying on the implementation of the Quarry Safety Management Plan to address safety audit report indicated that while no drilling has occurred during the licence period, previous management relating to the requirements of this condition were noted as inadequate. This was not seen as an immediate risk. Safety (Petroleum) Two petroleum exploration licences were noted as being non-compliant against condition 18 (safety): The audit report for 445 noted that two non-compliances were raised relating to no evidence of strata leak off tests being undertaken and a lack of safety signs at well sites. 458 noted that two non-compliances were detected relating to site F-3 where the cellar cover plate handles were considered a hazard to people and animals and the hazard was not properly fenced off. The reasons for non-compliance can be attributed to a failure of risk management in the case of 458 where a risk control measure has itself introduced a hazard. The noncompliances appear to be isolated incidents and no serious problems are anticipated in undertaking corrective actions. A review of systems by licence holders is expected to rectify these issues. The observations recorded in the audit reports regarding safety relate to condition 18 (Safety): 445 noted an observation in relation to the lack of a site specific safety management plans (SMPs) for Keerrong 1 or Tunglebung 1, although specific SMPs had been prepared for other sites. Report on Audit of Coal and Petroleum Exploration Licences in NSW Phase 2 25

26 13 and 16 identified an opportunity to better integrate risk identification documentation and/or develop a 'roadmap' which describes how separate risk identification tools interact with each other. 238 noted that some job safety analysis (JSA) documents had become separated from the permit to work documents. 285 identified two observations in relation to a damaged para-webbing fence, with the licence holder unable to demonstrate follow-up and completion of corrective actions identified during a previous drill rig audit on one of its contractors. The audit report for 437 noted lack of awareness and understanding of emergency response procedures. It is anticipated that all these observations will be addressed with a review of the licence holder s safety management systems. Environment (Coal) Eleven coal exploration licences were noted as being non-compliant against at least one of the many environmental licence conditions: Four NC1 level non-compliances were reported in relation to Three of these reported non-compliances all related to the same incident, where an exploration activity was carried out without appropriate secondary approvals from Resources & Energy. Enforcement action by Resources & Energy has already been undertaken in relation to this incident and subsequent performance of the company has been reported as very good. The fourth NC1 related to the use of non-native pasture grass in the revegetation of a drill site in a woodland area. It is agreed that this is an NC1, or serious non-compliance, and Resources & Energy will resolve corrective action with the licence holder involving modification of their environmental management procedures for revegetation. All other non-compliances were classified as NC2 level and spread across a number of conditions relating to environment. Examples include not having Environmental Management Plans approved by Resources & Energy, minor rehabilitation issues, lack of detail in rehabilitation reports, minor diesel spill, rubbish on site, lack of formal landholder liaison programs and lack of risk Report on Audit of Coal and Petroleum Exploration Licences in NSW Phase 2 26

27 assessments for gas blowouts not being provided to Resources & Energy for approval. Where non-reporting has been identified, this may indicate new or inexperienced personnel whose main functions are that of geologist or engineer. For the smaller explorers the provision of experienced reporting staff may not be cost effective. The exploration sector appears to be dynamic in the level of vested corporate interests. This is reflected in changing joint venture partners and to some degree the management nexus between authorised licence holder and exploration program operator. This can result in inadequate systems of environmental management or poor communication of those systems at operator/contractor level. In particular, sector improvement in the areas of due diligence and internal auditing should apply to address these non-compliances. A number of observations have been reported against a range of the environmental conditions, again noting lack of formal submission of information to Resources & Energy or weaknesses in licence holders documentation systems and processes. All licence holders have been requested to confirm that corrective actions have been implemented or have a plan in place to implement them as soon as possible. Environment (Petroleum) Nine petroleum exploration licences were noted as being non-compliant against at least one of the many environmental licence conditions. Three NC1 level non-compliances were reported: The non-compliance reported for 445 related to the suspected dumping of drilling muds. Resources & Energy agree with the classification of the noncompliance to be of significant risk. Corrective action and improved procedures are to be sought from licence holder and confirmed by Resources & Energy. Two NC1 level non-compliances were reported for 458 and Resources & Energy agree with the classifications. One of these related to the failure to properly rehabilitate a site. Resources & Energy note the audit findings in relation to drill site rehabilitation and the status of these sites will be reviewed prior to Report on Audit of Coal and Petroleum Exploration Licences in NSW Phase 2 27

28 completion of the title and release of the security deposit. The other related to possible acid sulphate soil issues and the lack of appropriate surface water and groundwater monitoring. These matters have been addressed by the licence holder in subsequent activity applications to Resources & Energy. The additional non-compliances were rated as NC2: The NC2 level non-compliances were spread across a number of environment conditions including minor spills, poor documentation or landholder agreements, not gaining Resources & Energy approval for changes to work program, reports not being submitted to Resources & Energy and slow rehabilitation of sites. For s the non-compliances appear to demonstrate poor record keeping and lack of timeliness in project management, lack of progressive completion and rehabilitation of well sites. In most cases the non-compliances are not likely to have a significant impact on the environment. They would be addressed in corrective actions arising from the audit and in the final rehabilitation and relinquishment reporting process, which is prior to expiry of the exploration title and security deposit review. Where poor record keeping was noted, it is not suggested that the event did not occur, but rather that documentary evidence was not provided. A number of observations have been reported against a range of the environmental conditions again noting lack of formal submission of information to Resources & Energy, weaknesses in licence holder s documentation systems and processes and minor on site issues. All licence holders have been requested to confirm that corrective actions have been implemented or have a plan in place to implement them as soon as possible. Variations in audit reporting The following variations in audit reporting were raised when analysing the audit report information: The quality of the auditing undertaken varied considerably across the range of auditors. Some auditors undertook a comprehensive assessment against the Report on Audit of Coal and Petroleum Exploration Licences in NSW Phase 2 28

29 specific conditions of the licence, whilst others generally only addressed the Resources & Energy template questions. An initial review of the audits indicated that a large percentage of the auditors had simply followed the template document and had not considered whether the template contained all conditions present in the being audited. As a result, licence holders for 7 s and 5 s were asked to provide a revised audit report addressing all of the conditions of the title. Where a licence condition had several different components, some auditors assessed compliance against each specific component, whilst others only provided a compliance status for the condition as a whole. Where Category 2 or 3 activities had been undertaken within a licence area and additional approvals obtained from Resources & Energy, some auditors also undertook an assessment of compliance against the specific conditions of the approvals given. However, this was not common and was only undertaken by a select group of auditors. Report on Audit of Coal and Petroleum Exploration Licences in NSW Phase 2 29

30 7. CONSULTATION The Government decision stated that the Audit process will be undertaken in consultation with OEH and DP&I. On the 16 June 2011 copies of the project plan and the top level spreadsheets of data for coal and petroleum were forwarded to OEH and DP&I. The matter was placed on the agenda for the Coal Seam Gas Working Party (CSGWP) which includes representatives of OEH and DP&I plus others, for a status report. The status report on the audit was provided to the CSGWP at their meetings on 6 July, 2 August, 30 August, 29 September and 4 November 2011 respectively. A face to face meeting between Resources & Energy and OEH representatives was held on 1 August DP&I were unable to provide a representative for the meeting. A face to face meeting between Resources & Energy, OEH and DP&I was held on 15 August From this meeting, it emerged that OEH and DP&I were strongly of the opinion that more focus needed to be put on the environmental breaches, and as such it was agreed that all non-compliant s in the area of environment would go straight through to Phase 2 of the audit. It was agreed that the non-complying s for Petroleum Geoscience would be filtered to identify the licences that had multiple and/or significant non-compliances, as opposed to less significant non-compliances. Only the s with significant non-compliances would progress to Phase 2 of the audit. Following the meeting on 15 August it was also agreed that 2 (Camden) and 6505 (Caroona) would be included in Phase 2 of the audit due to the sensitivity and contentiousness of each of the licence areas respectively. A further meeting on 22 August concluded that officers from Resources & Energy, OEH, DP&I would attend some of the initial audits to see if the audit program is robust and to make any minor changes as required. It was agreed that Resources & Energy would establish the geographic areas and the licences to form part of the initial audits, and provide these to OEH and DP&I to then indicate who would contribute from their specific Departments. It was also agreed that DP&I would indicate if a number of s and s Report on Audit of Coal and Petroleum Exploration Licences in NSW Phase 2 30

GUIDE TO IMPLEMENTING A REGULATORY FOOD SAFETY AUDITOR SYSTEM

GUIDE TO IMPLEMENTING A REGULATORY FOOD SAFETY AUDITOR SYSTEM GUIDE TO IMPLEMENTING A REGULATORY FOOD SAFETY AUDITOR SYSTEM FEBRUARY 2016 2 Contents Introduction... 4 Scope and objectives... 5 Scope... 5 Objectives... 5 Responsibilities... 5 The role of the licensee

More information

Guide. Minister s Guide to Auditing for Building Surveyors. April 2014

Guide. Minister s Guide to Auditing for Building Surveyors. April 2014 Guide Minister s Guide to Auditing for Building Surveyors April 2014 Guide Minister s Guide to Auditing for Building Surveyors April 2014 Department of Planning, Transport and Infrastructure 136 North

More information

Pollution Incident Response Plan

Pollution Incident Response Plan Pollution Incident Response Plan Introduction Schmidt Quarries is committed to ensuring all aspects of our quarrying activities comply with the environmental legislative requirements in NSW. This Pollution

More information

Western Australian Auditor General s Report. Regulation of Training Organisations

Western Australian Auditor General s Report. Regulation of Training Organisations Western Australian Auditor General s Report Regulation of Training Organisations Report 11: June 2015 Office of the Auditor General Western Australia 7 th Floor Albert Facey House 469 Wellington Street,

More information

TRANSPORT FOR LONDON (TfL) LOW EMISSIONS CERTIFICATE (LEC) GUIDANCE NOTES FOR THE COMPANY AUDIT PROCESS. LEC (Company Audit) Guidance Notes

TRANSPORT FOR LONDON (TfL) LOW EMISSIONS CERTIFICATE (LEC) GUIDANCE NOTES FOR THE COMPANY AUDIT PROCESS. LEC (Company Audit) Guidance Notes TRANSPORT FOR LONDON (TfL) LOW EMISSIONS CERTIFICATE (LEC) GUIDANCE NOTES FOR THE COMPANY AUDIT PROCESS LEC (Company Audit) Guidance Notes Glossary of Terms Transport for London (TfL) London Low Emission

More information

GUIDELINE NO. 22 REGULATORY AUDITS OF ENERGY BUSINESSES

GUIDELINE NO. 22 REGULATORY AUDITS OF ENERGY BUSINESSES Level 37, 2 Lonsdale Street Melbourne 3000, Australia Telephone.+61 3 9302 1300 +61 1300 664 969 Facsimile +61 3 9302 1303 GUIDELINE NO. 22 REGULATORY AUDITS OF ENERGY BUSINESSES ENERGY INDUSTRIES JANUARY

More information

7 Directorate Performance Managers. 7 Performance Reporting and Data Quality Officer. 8 Responsible Officers

7 Directorate Performance Managers. 7 Performance Reporting and Data Quality Officer. 8 Responsible Officers Contents Page 1 Introduction 2 2 Objectives of the Strategy 2 3 Data Quality Standards 3 4 The National Indicator Set 3 5 Structure of this Strategy 3 5.1 Awareness 4 5.2 Definitions 4 5.3 Recording 4

More information

WORKPLACE HEALTH AND SAFETY AUDITING GUIDELINES

WORKPLACE HEALTH AND SAFETY AUDITING GUIDELINES WHS UNIT WORKPLACE HEALTH AND SAFETY AUDITING GUIDELINES Contents 1 Purpose... 1 2 Scope... 1 3 Definitions... 1 4 Responsibilities... 1 4.1 WHS Unit... 1 4.2 Auditor(s)... 1 4.3 Managers of Faculties

More information

AUDITOR GUIDELINES. Responsibilities Supporting Inputs. Receive AAA, Sign and return to IMS with audit report. Document Review required?

AUDITOR GUIDELINES. Responsibilities Supporting Inputs. Receive AAA, Sign and return to IMS with audit report. Document Review required? 1 Overview of Audit Process The flow chart below shows the overall process for auditors carrying out audits for IMS International. Stages within this process are detailed further in this document. Scheme

More information

Contractor Management Audit Checklist Metalliferous, Opal and Extractive Mines and Quarries

Contractor Management Audit Checklist Metalliferous, Opal and Extractive Mines and Quarries Contractor Management Audit Checklist Metalliferous, Opal and Extractive Mines and Quarries MEX-0 August 2009 Mine Safety Operations MEX-0 Page of 9 Background The legislative provisions for the Operators

More information

BLOOM AND WAKE (ELECTRICAL CONTRACTORS) LIMITED QUALITY ASSURANCE MANUAL

BLOOM AND WAKE (ELECTRICAL CONTRACTORS) LIMITED QUALITY ASSURANCE MANUAL 130 Wisbech Road Outwell Wisbech Cambridgeshire PE14 8PF Tel: (01945) 772578 Fax: (01945) 773135 Copyright 2003. This Manual and the information contained herein are the property Bloom & Wake (Electrical

More information

Code of Practice. for Inspecting and Certifying Buildings and Works. Building Control Regulations 2014

Code of Practice. for Inspecting and Certifying Buildings and Works. Building Control Regulations 2014 for Inspecting and Certifying Buildings and Works Building Control Regulations 2014 February, 2014 Table of Contents 1. Introduction 1 1.1 Status and Purpose of Code 1 1.2 Overview of Code 1 1.3 Application

More information

Water Resource (Great Artesian Basin) Plan 2006. Sale of general reserve unallocated water: Tender assessment report

Water Resource (Great Artesian Basin) Plan 2006. Sale of general reserve unallocated water: Tender assessment report Water Resource (Great Artesian Basin) Plan 2006 Sale of general reserve unallocated water: Tender assessment report This publication has been compiled by Water Services Support, Department of Natural Resources

More information

Drinking Water Quality Management Plan Review and Audit Guideline

Drinking Water Quality Management Plan Review and Audit Guideline Drinking Water Quality Management Plan Review and Audit Guideline This publication has been compiled by Queensland Water Supply Regulator, Department of Energy and Water Supply. State of Queensland, 2013.

More information

London STOCK EXCHANGE

London STOCK EXCHANGE London STOCK EXCHANGE 16 March 2006 For the attention of the Nominated Advisers/ Finance Directors/ Company Secretaries, all AIM Companies 10 Paternoster Square London EC4M 7LS Telephone 020 7797 1000

More information

Measuring your capabilities in Workplace Safety Management

Measuring your capabilities in Workplace Safety Management Working with business Measuring your capabilities in Workplace Safety Management ACC Workplace Safety Management Practices Audit Standards Contents Section 1 Audit standards for ACC s Workplace Safety

More information

Australian National Audit Office. Report on Results of a Performance Audit of Contract Management Arrangements within the ANAO

Australian National Audit Office. Report on Results of a Performance Audit of Contract Management Arrangements within the ANAO Australian National Audit Office Report on Results of a Performance Audit of Contract Management Arrangements within the ANAO Commonwealth of Australia 2002 ISBN 0 642 80678 0 10 December 2002 Dear Mr

More information

WESTERN AUSTRALIA HEAVY VEHICLE ACCREDITATION SCHEME (WAHVAS) BUSINESS RULES (DRAFT)

WESTERN AUSTRALIA HEAVY VEHICLE ACCREDITATION SCHEME (WAHVAS) BUSINESS RULES (DRAFT) WESTERN AUSTRALIA HEAVY VEHICLE ACCREDITATION SCHEME (WAHVAS) BUSINESS RULES (DRAFT) June 2015 DRAFT v1.3 Remove on final Contents 1. BUSINESS RULES OVERVIEW 3 1.1 Purpose 3 1.2 Legal Status of the Business

More information

Compliance Audit Handbook

Compliance Audit Handbook Compliance Audit Handbook This Compliance Audit Handbook has been produced by the Compliance and Assurance Section of the Department of Environment and Conservation NSW (DEC). For technical information

More information

REQUIREMENTS FOR CERTIFICATION BODIES TO DETERMINE COMPLIANCE OF APPLICANT ORGANIZATIONS TO THE MAGEN TZEDEK SERVICE MARK STANDARD

REQUIREMENTS FOR CERTIFICATION BODIES TO DETERMINE COMPLIANCE OF APPLICANT ORGANIZATIONS TO THE MAGEN TZEDEK SERVICE MARK STANDARD REQUIREMENTS FOR CERTIFICATION BODIES TO DETERMINE COMPLIANCE OF APPLICANT ORGANIZATIONS TO THE MAGEN TZEDEK SERVICE MARK STANDARD Foreword The Magen Tzedek Commission has established a standards and certification

More information

Appendix 1. This appendix is a proposed new module of the DFSA Rulebook. Therefore, the text is not underlined as it is all new text.

Appendix 1. This appendix is a proposed new module of the DFSA Rulebook. Therefore, the text is not underlined as it is all new text. Appendix 1 This appendix is a proposed new module of the DFSA Rulebook. Therefore, the text is not underlined as it is all new text. The DFSA Rulebook Auditor Module (AUD) PART 1 INTRODUCTION 1 APPLICATION

More information

Procedure: OHS CONTRACTOR MANAGEMENT

Procedure: OHS CONTRACTOR MANAGEMENT Procedure: OHS CONTRACTOR MANAGEMENT. Purpose This procedure outlines the occupational health and safety (OHS) requirements for the management of contractors engaged to perform tasks or services for Greater

More information

Planning Act 2008: Guidance on Changes to Development Consent Orders. December 2015 Department for Communities and Local Government

Planning Act 2008: Guidance on Changes to Development Consent Orders. December 2015 Department for Communities and Local Government Planning Act 2008: Guidance on Changes to Development Consent Orders December 2015 Department for Communities and Local Government Crown copyright, 2015 Copyright in the typographical arrangement rests

More information

Compliance Review Report Internal Audit and Risk Management Policy for the New South Wales Public Sector

Compliance Review Report Internal Audit and Risk Management Policy for the New South Wales Public Sector Compliance Review Report Internal Audit and Risk Management Policy for the New South Wales Public Sector Background The Treasury issued TPP 09-05 Internal Audit and Risk Management Policy for the New South

More information

Management of Environmental Risks and Emergencies. Compliance Audit Program

Management of Environmental Risks and Emergencies. Compliance Audit Program Management of Environmental Risks and Emergencies Compliance Audit Program 2012 State of NSW and Environment Protection Authority The State of NSW and the Environment Protection Authority (EPA) are pleased

More information

Chapter 3 Office of Human Resources Absenteeism Management

Chapter 3 Office of Human Resources Absenteeism Management Office of Human Resources Absenteeism Management Contents Section A - Background, Objective and Scope............................ 24 Section B - Criterion 1 - Communicating Expectations.......................

More information

Improving the ACT Building Regulatory System

Improving the ACT Building Regulatory System Improving the ACT Building Regulatory System Schedule of individual reform proposals Proposal Consultation responses Response Act/Regulation Design and Documentation 1.1 Minimum Design Documentation Guidelines

More information

Site visit inspection report on compliance with HTA minimum standards. London School of Hygiene & Tropical Medicine. HTA licensing number 12066

Site visit inspection report on compliance with HTA minimum standards. London School of Hygiene & Tropical Medicine. HTA licensing number 12066 Site visit inspection report on compliance with HTA minimum standards London School of Hygiene & Tropical Medicine HTA licensing number 12066 Licensed under the Human Tissue Act 2004 for the storage of

More information

Insurer audit manual

Insurer audit manual Insurer audit manual Disclaimer This publication may contain work health and safety and workers compensation information. It may include some of your obligations under the various legislations that WorkCover

More information

University of New England Compliance Management Framework and Procedures

University of New England Compliance Management Framework and Procedures University of New England Compliance Management Framework and Procedures Document data: Document type: Administering entity: Framework and Procedures Audit and Risk Directorate Records management system

More information

ASSET CREATION DEVELOPER PROCESS INSTRUCTIONS TO DESIGNERS - MAJOR WORKS -

ASSET CREATION DEVELOPER PROCESS INSTRUCTIONS TO DESIGNERS - MAJOR WORKS - ASSET CREATION DEVELOPER PROCESS INSTRUCTIONS TO DESIGNERS - MAJOR WORKS - INSTRUCTIONS TO DESIGNERS CONTENTS 1. INTRODUCTION 3 2. ROLE OF THE WATER SERVICING COORDINATOR 3 3. ROLE OF THE DESIGNER 3 4.

More information

LICENSING POLICY OF THE WORKCOVER AUTHORITY FOR SELF-INSURERS AND GROUP SELF INSURERS LICENSED UNDER SECTION 211 OF THE WORKERS COMPENSATION ACT, 1987

LICENSING POLICY OF THE WORKCOVER AUTHORITY FOR SELF-INSURERS AND GROUP SELF INSURERS LICENSED UNDER SECTION 211 OF THE WORKERS COMPENSATION ACT, 1987 LICENSING POLICY OF THE WORKCOVER AUTHORITY FOR SELF-INSURERS AND GROUP SELF INSURERS LICENSED UNDER SECTION 211 OF THE WORKERS COMPENSATION ACT, 1987 Self-insurance relieves an employer or corporate group

More information

Food Safety Enforcement Policy

Food Safety Enforcement Policy Food Safety Enforcement Policy Food Safety Enforcement Policy Introduction As a statutory Food Authority this document sets out what businesses or other persons being regulated can expect from us in relation

More information

Issue No. 02 BOBS May, 2008 Effective Date: 2008-06-01 UNCONTROLLED WHEN DOWNLOADED/PRINTED

Issue No. 02 BOBS May, 2008 Effective Date: 2008-06-01 UNCONTROLLED WHEN DOWNLOADED/PRINTED Page 1 of 7 Page 2 of 7 1. Purpose The purpose of this procedure is to ensure that enquiries on management system certification, the certification process and subsequent surveillance audits of companies

More information

Incident Reporting Requirements

Incident Reporting Requirements Incident Reporting Requirements Directive PNG014 February 2016 Revision 1.0 Governing Legislation: Acts: The Oil and Gas Conservation Act The Pipelines Act, 1998 Regulations: The Oil and Gas Conservation

More information

Final. Internal Audit Report. Creditors System

Final. Internal Audit Report. Creditors System Final Internal Audit Report Creditors System Document Details: Reference: 1.2 / 2014-15 Senior Manager, Internal Audit & Assurance: David Jenkins ext 6567 Date: 7 th January 2015 This report is not for

More information

FIRE SAFETY INFORMATION FACT SHEET

FIRE SAFETY INFORMATION FACT SHEET Disclaimers: This information was believed to be correct at the date of its publication. This information is for general information purposes only and should not be relied upon for legal advice. FIRE SAFETY

More information

Preparation of a Rail Safety Management System Guideline

Preparation of a Rail Safety Management System Guideline Preparation of a Rail Safety Management System Guideline Page 1 of 99 Version History Version No. Approved by Date approved Review date 1 By 20 January 2014 Guideline for Preparation of a Safety Management

More information

Response from the Department of Treasury, Western Australia, to the Productivity Commission s Draft Report Regulatory Impact Analysis: Benchmarking

Response from the Department of Treasury, Western Australia, to the Productivity Commission s Draft Report Regulatory Impact Analysis: Benchmarking Response from the Department of Treasury, Western Australia, to the Productivity Commission s Draft Report Regulatory Impact Analysis: Benchmarking Context Regulatory Impact Assessment (RIA) began in Western

More information

PRIVACY POLICY. comply with the Australian Privacy Principles ("APPs"); ensure that we manage your personal information openly and transparently;

PRIVACY POLICY. comply with the Australian Privacy Principles (APPs); ensure that we manage your personal information openly and transparently; PRIVACY POLICY Our Privacy Commitment Glo Light Pty Ltd A.C.N. 099 730 177 trading as "Lighting Partners Australia of 16 Palmer Parade, Cremorne, Victoria 3121, ( LPA ) is committed to managing your personal

More information

PRODUCT CERTIFICATION RULES GOVERNING THE SCHEME JANUARY 2006

PRODUCT CERTIFICATION RULES GOVERNING THE SCHEME JANUARY 2006 THE GAS SAFETY CERTIFICATION FOR GAS APPLIANCES AND COMPONENTS PRODUCT CERTIFICATION RULES GOVERNING THE SCHEME JANUARY 2006 MKP220.01 Issue Date: 2007-Oct-09 SAI Global Limited Copyright 2007 - ABN 67

More information

Office of the National Coordinator for Health IT Proposed Rule Public Comment Template

Office of the National Coordinator for Health IT Proposed Rule Public Comment Template Office of the National Coordinator for Health IT Proposed Rule Public Comment Template ONC Health IT Certification Program: Enhanced Oversight and Accountability Preface This document is meant to provide

More information

CHECKLIST ISO/IEC 17021:2011 Conformity Assessment Requirements for Bodies Providing Audit and Certification of Management Systems

CHECKLIST ISO/IEC 17021:2011 Conformity Assessment Requirements for Bodies Providing Audit and Certification of Management Systems Date(s) of Evaluation: CHECKLIST ISO/IEC 17021:2011 Conformity Assessment Requirements for Bodies Providing Audit and Certification of Management Systems Assessor(s) & Observer(s): Organization: Area/Field

More information

Health, Safety and Environment Management System

Health, Safety and Environment Management System Health, Safety and Environment Management System For Bridgeport Energy Ltd Level 7, 111 Pacific Highway North Sydney 2011 June, 2010 DOCUMENT CONTROL Title: Document Number: Health, Safety and Environmental

More information

Tender for. Provision of Risk Management Services for the Eyre Peninsula Local Government Association and Member Associations

Tender for. Provision of Risk Management Services for the Eyre Peninsula Local Government Association and Member Associations Tender for Provision of Risk Management Services for the Eyre Peninsula Local Government Association and Member Associations Select request for tenders Table of Contents Page No 1. Structure of this RFT...

More information

Hertsmere Borough Council. Data Quality Strategy. December 2009 1

Hertsmere Borough Council. Data Quality Strategy. December 2009 1 Hertsmere Borough Council Data Quality Strategy December 2009 1 INTRODUCTION Public services need reliable, accurate and timely information with which to manage services, inform users and account for performance.

More information

Certification Procedure of RSPO Supply Chain Audit

Certification Procedure of RSPO Supply Chain Audit : 1 of 19 Table of Contents 1. Purpose 2. Scope 3. Unit of Certification 3.1 Identity Preserved, Segregation, Mass Balance, 3.2. Book and Claim 4. Definitions 5. Responsibilities 5.1 Head of the Certification

More information

Australian Transport Council. National Standard for the Administration of Marine Safety SECTION 5

Australian Transport Council. National Standard for the Administration of Marine Safety SECTION 5 Australian Transport Council National Standard for the Administration of Marine Safety SECTION 5 APPROVAL AND AUDITING OF REGISTERED TRAINING ORGANISATIONS August 2008 First Published: August 2008 Endorsed

More information

Document Title: Trust Approval and Research Governance

Document Title: Trust Approval and Research Governance Document Title: Trust Approval and Research Governance Document Number: SOP034 Staff involved in development: Job titles only Document author/owner: Directorate: Department: For use by: RM&G Manager, R&D

More information

COMPLIANCE FRAMEWORK AND REPORTING GUIDELINES

COMPLIANCE FRAMEWORK AND REPORTING GUIDELINES COMPLIANCE FRAMEWORK AND REPORTING GUIDELINES DRAFT FOR CONSULTATION June 2015 38 Cavenagh Street DARWIN NT 0800 Postal Address GPO Box 915 DARWIN NT 0801 Email: utilities.commission@nt.gov.au Website:

More information

Australian Transport Council. National Standard for the Administration of Marine Safety SECTION 4 SURVEYS OF VESSELS

Australian Transport Council. National Standard for the Administration of Marine Safety SECTION 4 SURVEYS OF VESSELS Australian Transport Council National Standard for the Administration of Marine Safety SECTION 4 SURVEYS OF VESSELS Edition 1 Draft for comment issued 20 December 2005 Endorsed by the Australian Transport

More information

NOTE FOR MINING AND OIL & GAS COMPANIES - JU N E 2 0 0 9

NOTE FOR MINING AND OIL & GAS COMPANIES - JU N E 2 0 0 9 NOTE FOR MINING AND OIL & GAS COMPANIES - JU N E 2 0 0 9 A G U I D E T O A I M U K TA X B E N E F I T S 2 AIM Note for Mining, Oil and Gas Companies Contents Introduction 1 Companies to which this Note

More information

Essex County Council - Internal Audit Report 2007/08 -

Essex County Council - Internal Audit Report 2007/08 - Essex County Council - Internal Audit Report 2007/08 - Corporate Credit Cards FINAL REPORT 1. Executive Summary Department: Corporate Resources Audit Sponsor: Bob Coomber Interim Executive Director of

More information

RTO Delegations Guidelines

RTO Delegations Guidelines RTO Delegations Guidelines ISBN 0 7594 0389 9 Victorian Qualifications Authority 2004 Published by the Victorian Qualifications Authority This publication is copyright. Apart from any use permitted under

More information

Commonwealth Heritage

Commonwealth Heritage au s t r a l i a s Commonwealth Heritage MAKING A HERITAGE STR ATEGY What is a heritage strategy? Who needs to prepare a heritage strategy? When does a heritage strategy have to be prepared? When should

More information

NORTHERN TERRITORY ELECTRICITY RING-FENCING CODE

NORTHERN TERRITORY ELECTRICITY RING-FENCING CODE NORTHERN TERRITORY ELECTRICITY RING-FENCING CODE JULY 2001 Table of Provisions Clause Page 1. Authority...2 2. Application...2 3. Objectives...2 4. Ring-Fencing Minimum Obligations...2 5. Compliance with

More information

Presentation by BSI on the main changes to the IATF ISO/TS 16949 certification scheme

Presentation by BSI on the main changes to the IATF ISO/TS 16949 certification scheme Presentation by BSI on the main changes to the IATF ISO/TS 16949 certification scheme ISO/TS 16949 IATF Scheme rules 4 th edition areas that impact BSI Clients Copyright 2014 BSI. All rights reserved.

More information

Exploration rehabilitation and relinquishment report

Exploration rehabilitation and relinquishment report Form EDG13 Exploration rehabilitation and relinquishment report Mining Act 1992 and Petroleum (Onshore) Act 1991 April 2016 v2.1 More information For help with lodging this application, or for more information,

More information

Disability Employment Services Quality Framework Advice V 2.0

Disability Employment Services Quality Framework Advice V 2.0 Disability Employment Services Quality Framework Advice V 2.0 Disclaimer This document is not a stand-alone document and does not contain the entirety of Disability Employment Services Providers' obligations.

More information

Internal Audit Checklist

Internal Audit Checklist Internal Audit Checklist 4.2 Policy Verify required elements Verify management commitment Verify available to the public Verify implementation by tracing links back to policy statement Check review/revisions

More information

Assurance at Country Level: External Audit of Grant Recipients. Eastern Europe and Central Asia Regional Report. GF-OIG-13-037 20 August 2013

Assurance at Country Level: External Audit of Grant Recipients. Eastern Europe and Central Asia Regional Report. GF-OIG-13-037 20 August 2013 Assurance at Country Level: External Audit of Grant Recipients Eastern Europe and Central Asia Regional Report 20 August 2013 TABLE OF CONTENTS A. EXECUTIVE SUMMARY... 2 B. MESSAGE FROM THE EXECUTIVE DIRECTOR

More information

General Insurance Code of Practice. Overview of the Year 2009/2010

General Insurance Code of Practice. Overview of the Year 2009/2010 General Insurance Code of Practice Overview of the Year 2009/2010 1 of 74 General Insurance Code of Practice Overview of the Year 2009/2010 Contents 1. Overview of the Year 2009/2010 4 2. Snapshot of the

More information

WORK HEALTH AND SAFETY

WORK HEALTH AND SAFETY WORK HEALTH AND SAFETY SCOPE POLICY Work Health and Safety System Work Health and Safety Objectives Roles and Responsibilities Executive Responsibilities Manager Responsibilities Worker Responsibilities

More information

Guide to Assessment and Rating for Regulatory Authorities

Guide to Assessment and Rating for Regulatory Authorities Guide to Assessment and Rating for Regulatory Authorities January 2013 Copyright The details of the relevant licence conditions are available on the Creative Commons website (accessible using the links

More information

ACC AUDIT GUIDELINES - INJURY MANAGEMENT PRACTICES

ACC AUDIT GUIDELINES - INJURY MANAGEMENT PRACTICES ACC AUDIT GUIDELINES - INJURY MANAGEMENT PRACTICES Guidelines to understanding the audit standards for the Injury Management Section of the ACC Partnership Programme Please note: There is a separate guideline

More information

U & D COAL LIMITED A.C.N. 165 894 806 BOARD CHARTER

U & D COAL LIMITED A.C.N. 165 894 806 BOARD CHARTER U & D COAL LIMITED A.C.N. 165 894 806 BOARD CHARTER As at 31 March 2014 BOARD CHARTER Contents 1. Role of the Board... 4 2. Responsibilities of the Board... 4 2.1 Board responsibilities... 4 2.2 Executive

More information

Post-approval requirements for State significant mining developments October 2015. Web-based Reporting Guideline

Post-approval requirements for State significant mining developments October 2015. Web-based Reporting Guideline Post-approval requirements for State significant mining developments October 2015 Web-based Reporting Guideline Contents Preliminary... 1 Purpose and scope... 1 Reporting framework... 1 Definitions...

More information

AUDIT OF DET ASBESTOS MANAGEMENT IN QUEENSLAND SCHOOLS

AUDIT OF DET ASBESTOS MANAGEMENT IN QUEENSLAND SCHOOLS AUDIT OF DET ASBESTOS MANAGEMENT IN QUEENSLAND SCHOOLS Conducted By GASKIN CONSTRUCTION SERVICES PTY LTD TABLE OF CONTENTS SECTIONS Section 1 Section 2 Section 3 Section 4 Section 5 Section 6 Section 7

More information

Terms and Conditions of Offer and Contract (Works & Services) Conditions of Offer

Terms and Conditions of Offer and Contract (Works & Services) Conditions of Offer Conditions of Offer A1 The offer documents comprise the offer form, letter of invitation to offer (if any), these Conditions of Offer and Conditions of Contract (Works & Services), the Working with Queensland

More information

Guideline for Professional Services Contractor Performance Reporting

Guideline for Professional Services Contractor Performance Reporting ` Guideline for Professional Services Contractor Performance Procedure Applicable to: Transport Projects Quality Management System Status: Approved Division: Transport Projects Version: 10 Date of issue:

More information

GUIDELINES ISSUED UNDER PART 5A OF THE EDUCATION ACT 1990 FOR THE MANAGEMENT OF HEALTH AND SAFETY RISKS POSED TO SCHOOLS BY A STUDENT S VIOLENT

GUIDELINES ISSUED UNDER PART 5A OF THE EDUCATION ACT 1990 FOR THE MANAGEMENT OF HEALTH AND SAFETY RISKS POSED TO SCHOOLS BY A STUDENT S VIOLENT GUIDELINES ISSUED UNDER PART 5A OF THE EDUCATION ACT 1990 FOR THE MANAGEMENT OF HEALTH AND SAFETY RISKS POSED TO SCHOOLS BY A STUDENT S VIOLENT BEHAVIOUR CONTENTS PAGE PART A INTRODUCTION AND STATEMENT

More information

Contractor Connect Scheme Electrical Contractor and Worker Handbook

Contractor Connect Scheme Electrical Contractor and Worker Handbook Contractor Connect Scheme Electrical Contractor and Worker Handbook January 2016 Document release information Document number 13553681 Document title Revision status Contractor Connect Scheme handbook

More information

A Preliminary Study on the use of Forensic Accounting techniques to determine property agency trust accounting compliance

A Preliminary Study on the use of Forensic Accounting techniques to determine property agency trust accounting compliance A Preliminary Study on the use of Forensic Accounting techniques to determine property agency trust accounting compliance HERA ANTONIADES University of Technology, Sydney New South Wales, Australia 2009

More information

RDTL Procurement Best Practice Guide 7: Managing Contracts. RDTL MINISTRY OF FINANCE Procurement Service BEST PRACTICE GUIDE 7: MANAGING CONTRACTS

RDTL Procurement Best Practice Guide 7: Managing Contracts. RDTL MINISTRY OF FINANCE Procurement Service BEST PRACTICE GUIDE 7: MANAGING CONTRACTS RDTL MINISTRY OF FINANCE Procurement Service BEST PRACTICE GUIDE 7: MANAGING CONTRACTS 1 RDTL Procurement Guidelines The Procurement Legal Regime Decree Law sets out new procurement processes which must

More information

Accreditation Workbook for Mental Health Services. March 2014

Accreditation Workbook for Mental Health Services. March 2014 Accreditation Workbook for Mental Health Services March 2014 Accreditation Workbook for Mental Health Services, 2014 ISBN Print: 978-1-921983-66-5 ISBN Online: 978-1-921983-60-3 Commonwealth of Australia

More information

FNS40211 CERTIFICATE IV FINANCIAL SERVICES BOOKKEEPING

FNS40211 CERTIFICATE IV FINANCIAL SERVICES BOOKKEEPING FNS40211 CERTIFICATE IV FINANCIAL SERVICES BOOKKEEPING POWER UP YOUR CAREER WITH A QUALIFICATION THAT MAKES A DIFFERENCE It is a must have qualification for individuals who possess significant theoretical

More information

AUDIT STANDARDS EFFECTIVE FROM 1 APRIL 2002 ACC 440

AUDIT STANDARDS EFFECTIVE FROM 1 APRIL 2002 ACC 440 AUDIT STANDARDS EFFECTIVE FROM 1 APRIL 2002 ACC 440 What s new? These are the ACC Partnership Programme audit standards effective from 1 April 2002. They replace the audit standards released by ACC in

More information

WHS Contractor Management Procedure

WHS Contractor Management Procedure Wudinna District Council 1. Overview Wudinna District Council as part of its commitment under its Policy recognises its obligation to: Ensure, so far as is reasonably practicable, the health and safety

More information

Financial assurance under the Environmental Protection Act 1994

Financial assurance under the Environmental Protection Act 1994 This guideline describes the arrangements for financial assurance under the Environmental Protection Act 1994. It has been prescribed under the Environmental Protection Regulation 2008. The publication

More information

Securing safe, clean drinking water for all

Securing safe, clean drinking water for all Securing safe, clean drinking water for all Enforcement policy Introduction The Drinking Water Inspectorate (DWI) is the independent regulator of drinking water in England and Wales set up in 1990 by Parliament

More information

Strategic Industry Audit Report

Strategic Industry Audit Report Strategic Industry Audit Report www.tac.wa.gov.au 2012 Strategic Industry Audit of qualifications which lead to an electrician s licence in Western Australia The Training Accreditation Council conducted

More information

Information Management Advice 35: Implementing Information Security Part 1: A Step by Step Approach to your Agency Project

Information Management Advice 35: Implementing Information Security Part 1: A Step by Step Approach to your Agency Project Information Management Advice 35: Implementing Information Security Part 1: A Step by Step Approach to your Agency Project Introduction This Advice provides an overview of the steps agencies need to take

More information

Strategy and Procedures for Compliance and Enforcement

Strategy and Procedures for Compliance and Enforcement Strategy and Procedures for Compliance and Enforcement Dam Safety Program Ministry of Forests, Lands and Natural Resource Operations Last Update: November 2014 A Dam Safety Compliance & Enforcement Policy

More information

Operational Audit and. Asset Management System Review. Shire of Coolgardie

Operational Audit and. Asset Management System Review. Shire of Coolgardie Shire of Coolgardie Operational Audit and Asset Management System Shire of Review Dowerin 2011 (Water Services Operating Licence) Water Services Operating Licence (Sewerage and Non-Potable Water) DRAFT

More information

Board of Surveying and Spatial Information

Board of Surveying and Spatial Information Board of Surveying and Spatial Information Determinations 1. Surveyor s Assistant 2. Recognised Qualifications 3. General or Immediate Supervision 4. Board Examinations a) Part A Land Surveying Projects

More information

UNCONTROLLED COPY FOR REFERENCE ONLY

UNCONTROLLED COPY FOR REFERENCE ONLY CLOVER MACHINE AND MFG. 800 MATHEW ST. #101 SANTA CLARA, CA 95050 727-3380 727-7015 fax REVISION: DATE: PAGE 1 OF 45 QUALITY POLICY MANUAL DISTRIBUTION LIST: President Purchasing Manager Vice President

More information

Contractor Performance Report Scoring Guide

Contractor Performance Report Scoring Guide Report Main Roads Western Australia Table of Contents CONTRACTOR PERFORMANCE REPORT SCORING GUIDE... 3 1. APPLICATION... 3 2. REPORTING... 3 2.1 Objectives... 3 2.2 Frequency... 3 2.3 Responsibility...

More information

Review of an SMSF audit engagement questionnaire

Review of an SMSF audit engagement questionnaire Review of an SMSF audit engagement questionnaire Introduction Instructions for the Reviewer This questionnaire has been designed to help you assess whether the audit of Self Managed Superannuation Funds

More information

PROCEDURE. Part 3.1: Metering Service Provider (MSP) Registration, Revocation, and Deregistration PUBLIC. Market Manual 3: Metering. Issue 14.

PROCEDURE. Part 3.1: Metering Service Provider (MSP) Registration, Revocation, and Deregistration PUBLIC. Market Manual 3: Metering. Issue 14. PUBLIC MDP_PRO_0007 PROCEDURE Market Manual 3: Metering Part 3.1: Metering Service Provider (MSP) Registration, Revocation, and Deregistration Issue 14.0 This document provides an overview of the steps

More information

Information Commissioner's Office

Information Commissioner's Office Information Commissioner's Office IT Procurement Review Ian Falconer Partner T: 0161 953 6480 E: ian.falconer@uk.gt.com Last updated 18 June 2012 Will Simpson Senior Manager T: 0161 953 6486 E: will.g.simpson@uk.gt.com

More information

Department: Corporate Secretariat

Department: Corporate Secretariat RESPONSIBLE PERSON POLICY Department: Corporate Secretariat 1 Contents Overview 3 General Principles 4 Fitness 4 Propriety 4 Policies: 4 Entity needs and fitness analysis 4 Identifying responsible person

More information

Health and Safety Management Standards

Health and Safety Management Standards Health and Safety Management Standards Health and Safety Curtin University APR 2012 PAGE LEFT INTENTIONALLY BLANK Page 2 of 15 CONTENTS 1. Introduction... 4 1.1 Hierarchy of Health and Safety Documents...

More information

Accreditation Quality Assurance and Monitoring Policy

Accreditation Quality Assurance and Monitoring Policy T-300.1 Accreditation Quality Assurance and Monitoring Policy 27 February 2015 Version 2.1 T-300.1 Table of Contents Glossary of Terms... 3 List of Abbreviations... 4 1. Purpose... 5 2. Scope... 5 3. Overview...

More information

Contract and Vendor Management Guide

Contract and Vendor Management Guide Contents 1. Guidelines for managing contracts and vendors... 2 1.1. Purpose and scope... 2 1.2. Introduction... 2 2. Contract and Vendor Management 2.1. Levels of management/segmentation... 3 2.2. Supplier

More information

Managing Contractor Health and Safety Risks Guidelines for Local Government

Managing Contractor Health and Safety Risks Guidelines for Local Government Managing Contractor Health and Safety Risks Guidelines for Local Government Acknowledgements This manual has been prepared by Noel Arnold & Associates Pty Ltd, occupational health and safety consultants

More information

MARITIME OPERATOR SAFETY SYSTEM: MARITIME RULE PARTS 19 AND 44

MARITIME OPERATOR SAFETY SYSTEM: MARITIME RULE PARTS 19 AND 44 Office of the Minister of Transport Chair Cabinet Economic Growth and Infrastructure Committee MARITIME OPERATOR SAFETY SYSTEM: MARITIME RULE PARTS 19 AND 44 Proposal 1. The purpose of this paper is to

More information

Anglo American Procurement Solutions Site

Anglo American Procurement Solutions Site Anglo American Procurement Solutions Site Event Terms and Conditions Anglo American Procurement Solutions Site Event Terms and Conditions Event Terms and Conditions 3 1. Defined terms 3 2. Interpretation

More information

Adequate Records Management - Implementation Plan

Adequate Records Management - Implementation Plan GPO Box 2343 Adelaide SA 5001 Tel (+61 8) 8204 8773 Fax (+61 8) 8204 8777 DX:467 srsarecordsmanagement@sa.gov.au www.archives.sa.gov.au Adequate Records Management - Implementation Plan October 2012 Version

More information

ISO 9001:2000 AUDIT CHECKLIST

ISO 9001:2000 AUDIT CHECKLIST ISO 9001:2000 AUDIT CHECKLIST No. Question Proc. Ref. Comments 4 Quality Management System 4.1 General Requirements 1 Has the organization established, documented, implemented and maintained a quality

More information