1 May 2009 I-85 CORRIDOR LIGHT RAIL TRANSIT FEASIBILITY STUDY Executive Summary Prepared for: Gwinnett Village Community Improvement District 1412 Oakbrook Drive, Suite 181 Norcross, Georgia Gwinnett Place Community Improvement District 3700 Crestwood Parkway, Suite 680 Duluth, Georgia Prepared by: HDR Engineering, Inc Peachtree Street, Suite 2210 Atlanta, Georgia
2 I-85 CORRIDOR LIGHT RAIL TRANSIT FEASIBILITY STUDY Executive Summary Prepared for: Gwinnett Village Community Improvement District 1412 Oakbrook Drive, Suite 181 Norcross, Georgia Gwinnett Place Community Improvement District 3700 Crestwood Parkway, Suite 680 Duluth, Georgia Prepared by: HDR Engineering, Inc Peachtree Street, Suite 2210 Atlanta, Georgia May 2009
3 Table of Contents 1 Introduction Alternatives Refinement Technology Assessment Conceptual Engineering Track Alignment Station Locations Maintenance Facility Technical Analysis Travel Demand Forecasting Operating Plans Operating and Maintenance Cost Estimates Capital Cost Estimates Limited Environmental Assessment Evaluation and Recommendations Funding Opportunities About This Report...13 Table of Tables Table 1: Comparison of Transit Technology Options... 2 Table 2: Alignment Alternatives... 3 Table 3: Estimated Daily Boardings per Station... 7 Table 4: Summary of Operating Requirements... 8 Table 5: Capital Cost Estimates... 8 Table 6: Evaluation Matrix... 10
4 1 INTRODUCTION The was commenced in September, 2008 to evaluate the technical and financial viability of a light rail line in Gwinnett County. The project co-sponsors, Gwinnett Village Community Improvement District and Gwinnett Place Community Improvement District, initiated the project to explore the potential benefit of serving the I-85 corridor with light rail transit (LRT). Figure 1 displays the extent of the corridor examined for the I-85 Corridor LRT Feasibility Study. Figure 1: I-85 LRT Study Corridor As part of this study, conceptual LRT alignments and station locations were identified and analyzed. Capital and operating costs were estimated for each alternative along with a basic ridership forecast and environmental screening. The preferred alignment, which was developed alongside the project sponsors and in conjunction with a number of stakeholders, was evaluated to determine its relative strengths compared to other recently implemented LRT systems. Finally, a number of funding opportunities at both the federal and local levels were identified. The results of this analysis are summarized herein and presented in greater detail in Executive Summary 1
5 the following sections of the final report. 2 ALTERNATIVES REFINEMENT 2.1 Technology Assessment A technology assessment was conducted to evaluate the various transit technology options for the I-85 corridor. Heavy rail transit (HRT), light rail transit (LRT), and modern streetcar were evaluated as part of this analysis. Table 1 displays a comparison of each mode by operating variable. Heavy rail is the most capital-intensive transit mode, while modern streetcar is typically the least expensive mode to build. However, HRT provides the highest capacity and operating speeds. Light rail transit, which can be classified into two categories high cost, exclusive right-of-way and moderate cost, shared right-of-way provides a balance between HRT and streetcar, as it offers operating speeds and capacity that can compete with heavy rail at a fraction of the capital cost. Table 1: Comparison of Transit Technology Options Light Rail Light Rail Heavy Rail Exclusive Right of Streetcar Shared Right of Way Way Cost/Mile $ million $ million $25-60 million $15-30 million Seated Capacity/Train Service Range Up to 30 Miles Up to 20 Miles Up to 15 Miles 2 to 10 Miles Maximum Speed MPH MPH MPH MPH Average Speed MPH MPH MPH 8-15 MPH Station Spacing > 1 Mile 1/2 to 1 Mile 1/2 to 1 Mile ¼ to ½ Mile Executive Summary 2
6 3 CONCEPTUAL ENGINEERING The conceptual engineering phase of the I-85 Corridor LRT Feasibility Study involved identifying preliminary track alignments, station locations, and maintenance facility sites. Substantial data analysis and field assessments along with evaluation of existing land use and transportation plans provided the information necessary to develop conceptual LRT routes and station locations. 3.1 Track Alignment Six preliminary track alignment options were identified and screened based on the following factors: Right-of-way availability Land use compatibility Future land use plans, both at the CID and County levels Topographic constraints Potential impacts to street traffic operations Availability of adjacent land for maintenance facility Additionally, coordination meetings were held with other stakeholder agencies including MARTA and the Gwinnett County Department of Transportation in order to further vet and refine the alignment alternatives. Based on input from these agencies and CID staff, a preferred alternative was developed for further analysis. Table 2 provides a brief description of each alternative, while Figure 2 graphically displays each alignment alternative. Table 2: Alignment Alternatives Alternative Route One-Way Travel Miles Time (Mins) Description Preferred Industrial Corridor / Satellite Blvd. / Satellite Blvd. Alternative Industrial Corridor / Venture Dr. / Utility Corridor Alternative Jimmy Carter Blvd. / Satellite Blvd. / Satellite Blvd. Alternative Industrial Corridor / Venture Dr. / Satellite Blvd. Alternative Jimmy Carter Blvd. / Venture Dr. / Utility Corridor Alternative Jimmy Carter Blvd. / Venture Dr. / Satellite Blvd. Executive Summary 3
7 Figure 2: Alignment Alternatives 3.2 Executive Summary 4
8 3.3 Station Locations A total of nine station locations were identified for the Preferred Alternative, as displayed in Figure 3, below. These preliminary station locations were determined based on the following criteria: Topography Current land use Adjacent land uses Redevelopment potential Sufficient size to accommodate the station and ancillary facilities Roadway access Pedestrian access Environmental fatal flaws The stations are classified into two categories: major and neighborhood. Major stations will serve larger office and retail markets and tend to have more amenities and intermodal transfer facilities, while neighborhood stations will be smaller and tend to serve smaller, more pedestrian-oriented market areas. Major stations identified include Norcross, Gwinnett Village, Indian Trail, Pleasant Hill, Gwinnett Place, and Gwinnett Arena. Neighborhood stations identified include Mitchell Road, Liddell Road, and Duluth Highway. Figure 3: Station Locations for Preferred Alternative Executive Summary 5
9 3.4 Maintenance Facility Fourteen preliminary sites, as displayed in Figure 4, were screened for suitability as a possible maintenance facility site for the LRT corridor. In consideration of the costs associated with nonrevenue train movements, the bulk of the sites identified were near either terminus of the alignment. Because most of the land within the corridor is built-out, it is likely that any potential maintenance facility site would have to be redeveloped. Thus, sites were identified and screened based on adjacent land use compatibility and parcel size. It was determined that six sites within the industrial area on the western end of the alignment should be advanced for further analysis and consideration. Figure 4: Maintenance Facility Site Options Executive Summary 6
10 4 TECHNICAL ANALYSIS The Technical Analysis phase of the I-85 Corridor LRT Feasibility Study involved further examination of the alignment options identified in the Conceptual Engineering phase. Highlevel ridership estimates were developed based on existing Transit Planning Board (TPB) travel demand forecasts. LRT operating plans were created and used to develop operating and maintenance cost estimates. Capital costs were estimated based on the preliminary engineering drawings. Finally, a limited environmental analysis was conducted to identify any major environmental fatal flaws. 4.1 Travel Demand Forecasting Estimated daily boardings for the LRT line from Norcross to Gwinnett Arena were developed based on the TPB Concept3 travel demand forecasts which included a line from Cumberland to Gwinnett Arena. This forecast was adapted to include only that ridership that would occur on the Gwinnett County portion of the TPB alignment. Ridership by station, as displayed in Table 3, was estimated based on low, medium, and high land use scenarios. It should be noted that the stations coded for the Concept3 model differ slightly from those stations identified in this study. Thus, these ridership estimations are for proxy use only, and will be further refined in Phase II of the I-85 Corridor LRT Feasibility Study. Table 3: Estimated Daily Boardings per Station Station Total Daily Boardings (2030 Model Year) LRT Low LRT Med. LRT High MARTA HRT Norcross 6,799 9,432 11,839 2,200 Gwinnett Village/Jimmy Carter Blvd ,117 6,000 Indian Trail 1,951 3,030 4,325 3,400 Gwinnett Place 2,966 4,200 5,339 9,300 Old Norcross 692 1,007 1,064 n/a Boggs 1,171 1,453 1,733 n/a Gwinnett Arena 2,024 2,576 3,388 n/a Total: 16,236 22,563 28,805 20, Operating Plans Operating plans for each alternative were developed based on ridership estimations and data provided in the conceptual engineering phase of the project. Operating requirements for each alternative are displayed in Table 4, below. Because the alternatives had only marginal differences in route miles and running time, the operating requirements are similar for each alignment with respect to car-miles, car-hours, train-hours, and peak trains. Executive Summary 7
11 Table 4: Summary of Operating Requirements Route Peak -----Annual Revenue----- Lay Cycle ---Trains--- ALT Miles LRVs Car-Miles Car-Hours Train-Hours Over Time Peak Base Eve. Preferred Alternative ,382, ,760 46, Alternative ,366, ,760 46, Alternative ,339, ,760 46, Alternative ,309, ,760 46, Alternative ,320, ,760 46, Alternative ,263, ,760 46, Operating and Maintenance Cost Estimates Operating and maintenance (O&M) costs were estimated based on the projected operating requirements for each alternative. A fully-allocated cost model was developed using data from nine peer LRT systems. The unit costs for each operating variable derived from these peer systems were applied to corresponding planned units of service for each alternative to estimate total annual O&M costs. Annual O&M costs (estimated in 2009 dollars) range from approximately $25.1 million to $25.6 million. 4.4 Capital Cost Estimates Capital costs were estimated using the Federal Transit Administration s (FTA) Standard Cost Categories (SCC). Standard Cost Categories include all capital components of the LRT construction process. Unit costs for each SCC were developed and applied to the units required for construction of each LRT alternative. The total capital costs and capital cost per mile for each alternative are listed in Table 5, below. Table 5: Capital Cost Estimates Alignment Option Total Cost Length (miles) Cost per Mile Preferred Alternative $1,017 million $73 million Alternative 1 $918 million $67 million Alternative 2 $1,058 million $78 million Alternative 3 $926 million $69 million Alternative 4 $959 million $71 million Alternative 5 $967 million $73 million Executive Summary 8
12 4.5 Limited Environmental Assessment A preliminary screening of the LRT corridor was performed in order to identify any areas of environmental concern. While this exercise does not fulfill or replace any local, state or federal requirements for environmental permitting, it provides a baseline indication as to the potential environmental hazards within the corridor. There were 37 documented sites found within 150 of the preferred alignment, and 279 within the corridor as a whole. Remediation may be required depending on the severity of environmental risk posed at these sites. Executive Summary 9
13 5 EVALUATION AND RECOMMENDATIONS The preferred alternative was evaluated against five peer LRT systems that have been recently constructed or are currently being built. The proposed Gwinnett LRT system compares favorably with regard to capital and operating cost variables. However, the system s ridership received lower ratings compared to the peer system average. Further ridership analysis to be performed during Phase II of this project will allow for greater certainty as to how the Gwinnett system s projected ridership will compete with the peer systems. It is important that the Gwinnett LRT system is rated favorably with regard to these variables as each contributes to the funding formulas dictated by the FTA for New Starts funding. System Phase Projected Ridership (Design Year) Table 6: Evaluation Matrix Daily New Ridership Ridership/Rou te-mile Cost/New Rider Capital Cost (YOE) Capital Cost/Mile Annual O&M Cost (YOE) Annual O&M/Route Mile Gwinnett Norcross to Arena - N/A - N/A Charlotte South Corridor o Houston Downtown to Astrodome o - + o Minneapolis Hiawatha Corridor o Phoenix East Valley + + o + - o - + Seattle Central Link + o Positive rating with regard to criterion o Neutral rating with regard to criterion - Negative rating with regard to criterion Executive Summary 10
14 6 FUNDING OPPORTUNITIES A number of funding opportunities exist to finance a LRT project in Gwinnett County. In addition to federal New Starts grant funding, which typically fund up to half of a project s total capital costs, the following federal and local funding options exist: Development Impact Fees/Benefit Assessment Districts Tax Increment Financing (TIFs) Federal Discretionary Funds Federal Railroad Administration Intercity Passenger Rail Investment Grants Public-Private Partnerships (PPP) Bonding Grant Anticipation Notes TIFIA Loans State Infrastructure Banks Private Donations Dedicated Sales Tax Hotel/Motel Tax Car Rental Tax Vehicle Registration Fee Property Tax for Transit Joint Development on Existing and Planned Facilities Tolls Congestion Pricing Safety Inspection Fee New Resident Impact Fee Distance-based Road User Fee On-going operating and maintenance expenses should also be planned for prior to implementation of a LRT system. While some of the aforementioned funding opportunities for capital expenses may also be applied to operating expenses, funding options for operating and maintenance typically include: Fare revenues Advertising revenues Interest Taxes Federal funding (5307, JARC, CMAQ [in non-attainment areas], STP) Parking revenues Joint development funds. Executive Summary 11
15 7 FINAL REPORT The I-85 Corridor Light Rail Feasibility Study Final Report is divided into four sections. Section 1, Refine Alternatives Final Report, includes the technology assessment report and documentation of the conceptual engineering process. Section 2, Technical Analysis Final Report, documents the technical studies performed for the project including ridership estimation, operating plan development, operating and maintenance cost estimation, capital cost estimation, and a limited environmental assessment. Section 3, Evaluation and Recommendations and Funding Opportunities, detail the evaluation methodology and results and funding opportunities for the proposed LRT project. Finally, Section 4 Station Renderings, includes a number of conceptual renderings for the Gwinnett Village, Mitchell Road, and Gwinnett Place Stations. In the months following preparation of the final report, Phase II of the I-85 Corridor LRT Feasibility Study will be conducted. Phase II will encompass detailed ridership forecasting using a travel demand model specifically coded for the proposed LRT corridor as well as a comprehensive travel market analysis. A third section will provide a detailed framework for advancing the project into the FTA New Starts project development process. Executive Summary 13
Addendum to the Arterial Transitway Corridors Study
January 2013 1 Addendum to the Arterial Transitway Corridors Study The Arterial Transitway Corridors Study (ATCS) evaluated and prioritized arterial bus rapid transit (BRT) improvements to nine corridors
More informationSouthwest Light Rail Transit Minneapolis-St. Paul, Minnesota New Starts Project Development (Rating Assigned November 2014)
Southwest Light Rail Transit Minneapolis-St. Paul, Minnesota New Starts Project Development (Rating Assigned November 2014) Summary Description Proposed Project: Light Rail Transit 15.7 Miles, 17 Stations
More information5.0 FINANCIAL ANALYSIS AND COMPARISON OF ALTERNATIVES
5.0 FINANCIAL ANALYSIS AND COMPARISON OF ALTERNATIVES 5.1 FINANCIAL ANALYSIS The cost of a transportation investment falls into two categories: capital costs, and operating and maintenance (O&M) costs.
More informationTriangle Transit Financial Plan. Durham Orange Light Rail Transit Project
Durham Orange Light Rail Transit Project September 2012 TABLE OF CONTENTS LIST OF TABLES... ii LIST OF FIGURES... iii 1. Introduction... 1 1 1.1. DESCRIPTION OF PROJECT SPONSOR... 1 1 1.1.1. Durham Transit
More informationMid-Coast Corridor Transit Project San Diego, California New Starts Engineering (Rating Assigned November 2015)
Mid-Coast Corridor Transit Project San Diego, California New Starts Engineering (Rating Assigned November 2015) Summary Description Proposed Project: Light Rail Transit 10.9 Miles, 9 Stations Total Capital
More informationEvergreen Line Rapid Transit Project Business Case Executive Summary. February 2008. Reviewed by
Evergreen Line Rapid Transit Project Business Case Executive Summary February 2008 Reviewed by Recommendation and Executive Summary The business case for the Evergreen Line Rapid Transit Project (the Project)
More informationMid-Coast Corridor Transit Project San Diego, California New Starts Project Development (Rating Assigned November 2014)
Mid-Coast Corridor Transit Project San Diego, California New Starts Project Development (Rating Assigned November 2014) Summary Description Proposed Project: Light Rail Transit 10.9 Miles, 9 Stations Total
More informationMAKING TRACKS. A Primer for Implementing Transit Fixed Guideway Projects
MAKING TRACKS A Primer for Implementing Transit Fixed Guideway Projects Introduction Demand for new fixed guideway projects is strong nationwide. Each year hundreds of new fixed guideway projects across
More informationVRE SYSTEM PLAN SUMMARY
VRE System Plan Summary January 2014 VRE SYSTEM PLAN SUMMARY VRE A Cost-Effective Contributor to Regional Mobility During the last decade, VRE has demonstrated its ability to accommodate a rapid and substantial
More informationEagle Commuter Rail Denver, Colorado Final Design (Based upon information received by FTA in November 2010)
Eagle Commuter Rail Denver, Colorado Final Design (Based upon information received by FTA in November 2010) Summary Description Proposed Project: Electrified Commuter Rail 30.2 Miles, 13 Stations Total
More informationThe financial plan was prepared in conjunction with the Technical Working Group. Refer to Table 3-1: Funding and Implementation Plan.
3 Financial Plan The purpose of the financial plan is to identify funding options that would be likely sources of money to advance recommendations made by this study. The Capitol Region Transportation
More informationLegislative Fiscal Bureau One East Main, Suite 301 Madison, WI 53703 (608) 266-3847 Fax: (608) 267-6873
Legislative Fiscal Bureau One East Main, Suite 301 Madison, WI 53703 (608) 266-3847 Fax: (608) 267-6873 February 16, 2010 TO: FROM: Members Joint Committee on Finance Bob Lang, Director SUBJECT: Governor's
More informationGTA Cordon Count Program
Transportation Trends 2001-2011 Executive Summary Project No. TR12 0722 September 2013 1.0 Introduction The Cordon Count program was established to collect traffic data as a tool for measuring travel trends
More informationWhen is BRT the Best Option? 1:30 2:40 p.m.
TRB/APTA 2004 Bus Rapid Transit Conference When is BRT the Best Option? 1:30 2:40 p.m. Paul Larrousse Director, National Transit Institute (NTI) (Moderator) TRB/APTA 2004 Bus Rapid Transit Conference Session
More informationIntegrating GO RER and SmartTrack. Leslie Woo, Chief Planning Officer February 10, 2016
Integrating GO RER and SmartTrack Leslie Woo, Chief Planning Officer February 10, 2016 Purpose and Scope To present update on development of options for integrating SmartTrack and GO RER based on the following
More informationIntroduction to Station Area Planning The Charlotte Story
Introduction to Station Area Planning The Charlotte Story Boston 2009 Steve Hamwey - Sasaki Associates, Inc. Troy Russ - Glatting Jackson, Inc. October 31 st, 2009 Station Area Planning October 15th History
More informationS-11: Tacoma Link Extension to Tacoma Community College
Project Number S-11 Subarea Pierce Primary Mode Light Rail Facility Type Corridor Length 3.65 miles Version ST Board Workshop Date Last Modified 11-25-2015 PROJECT AREA AND REPRESENTATIVE ALIGNMENT SHORT
More information2035 FINANCIAL RESOURCES FORECAST
2035 FINANCIAL RESOURCES FORECAST AKRON METROPOLITAN AREA TRANSPORTATION STUDY 806 CITICENTER BUILDING 146 SOUTH HIGH STREET AKRON, OHIO 44308 December 2012 This report was prepared by the Akron Metropolitan
More information10 Aviation Element. 10.1 Introduction. 10.1.1 Purpose of Chapter
10 Aviation Element 10.1 Introduction 10.1.1 Purpose of Chapter This chapter provides the aviation element of the RFATS 2035 Long Range Transportation Plan. It describes the existing conditions and trends
More informationFinancial Analysis and Funding
California High- Speed Rail Authority Revised 2012 Business Plan Chapter 7 Financial Analysis and Funding Introduction This chapter presents the financial analysis and funding strategy for the California
More informationQuestions and Answers about the Orange Bus/Rail Investment Plan
Why are transit improvements needed? Questions and Answers about the Orange Bus/Rail Investment Plan The Triangle Region is now home to 1.5 million people. The U.S. Census and the 2035 Joint Long Range
More informationand the statewide and metropolitan transportation planning and programming process in California:
Financial constraint... and the statewide and metropolitan transportation planning and programming process in California: A GUIDE TO FEDERAL AND STATE FINANCIAL PLANNING REQUIREMENTS Prepared by: Federal
More informationDoing More with the Same: How the Trinity Railway Express Increased Service without Increasing Costs
Doing More with the Same: How the Trinity Railway Express Increased Service without Increasing Costs W. T. "Bill" Farquhar Trinity Railway Express Irving, TX Abstract The Trinity Railway Express (TRE)
More informationGrowth of Addis Ababa
Growth of Addis Ababa Founded in 1887, and has expanded rapidly Now among the ten largest cities in Sub Saharan Africa Annual growth rate is 3.8% By 2020 population growth would reach to eight million.
More informationTRANSPORTATION SERVICE STANDARDS ELEMENT GOALS, OBJECTIVES & POLICIES
TRANSPORTATION SERVICE STANDARDS ELEMENT GOALS, OBJECTIVES & POLICIES Background One of the most critical public services provided by a community is the community s transportation system. An effective
More informationUnderstanding Value Capture as a Transportation Finance Strategy in Massachusetts. March 15, 2013
Understanding Value Capture as a Transportation Finance Strategy in Massachusetts March 15, 2013 Background The Massachusetts Legislature will soon explore options to increase transportation revenue. One
More informationLight Rail Transit in Phoenix
4. Presentation and Discussion: Phoenix Light Rail Implementation Wulf Grote Planning and Development Director, Phoenix Valley Metro Light Rail Transit in Phoenix Broadway Citizen s Task Force February
More informationSeattle Streetcar Center City Connector Seattle, Washington Small Starts Project Development (Rating Assigned November 2015)
Seattle Streetcar Center City Connector Seattle, Washington Small Starts Project Development (Rating Assigned November 2015) Summary Description Proposed Project: Streetcar 1.3 Miles, 4 Stations otal Capital
More informationUtilizing Value Capture for Transportation Funding
Utilizing Value Capture for Transportation Funding Transport Chicago 2011 Conference Go To 2040 Capital Transportation Projects Go To 2040 Fiscally Constrained Projects 5 Extension/new projects 10 Transportation
More informationChapter 5 Financial Plan
The Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users (SAFETEA_LU) requires that the MTP incorporate a financial plan for the planning period. The MTP is required to
More informationFinancial Plan Status Report
Financial Plan Status Report Broward MPO Board March 13, 2014 Financial Sub-Committee Membership SFRTA (lead agency) Broward MPO FDOT Miami-Dade MPO Palm Beach MPO South Florida Regional Planning Council
More informationMOTION NO. M2015-63 WSDOT Task Order for Final Design Services PROPOSED ACTION
MOTION NO. M2015-63 WSDOT Task Order for Final Design Services MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Capital Committee 07/09/15 Final Action Ahmad Fazel, DECM Executive Director Ron Lewis, East
More informationEvaluation Criteria and Mode Progression for RouteAhead Rapid Transit Projects
Evaluation Criteria and Mode Progression for RouteAhead Rapid Transit Projects C2012-0684 ATTACHMENT 2 The RouteAhead draft 30-year rapid transit plan was developed in coordination with the Investing in
More informationA Review of Transit Technology Specifications
. Transit Technologies Worksheet A Review of Transit Technology Specifications 1 2 3 4 5 6 1. Heavy Rail Transit 2. Commuter Rail Transit 3. Light Rail Transit 4. Modern Streetcar 5. Heritage Trolley 6.
More informationDowntown Tampa Transportation Vision
Downtown Tampa Transportation Vision Executive Summary August 1, 2006 Hillsborough County Metropolitan Planning Organization County Center, 18 th Floor Tampa, Florida 33602 813-272-5940 www.hillsboroughmpo.org
More informationFilling the Gap: Funding Transit Infill Stations in the United States
Filling the Gap: Funding Transit Infill Stations in the United States Amanda Wall Vandegrift Parsons Brinckerhoff Nathan M. Macek, AICP Parsons Brinckerhoff INTRODUCTION Many fixed guideway transit systems
More informationCoordinated Transit Planning in Toronto SmartTrack Eglinton West LRT Eglinton East LRT Scarborough Subway Extension Relief Line Waterfront Transit
Coordinated Transit Planning in Toronto SmartTrack Eglinton West LRT Eglinton East LRT Scarborough Subway Extension Relief Line Waterfront Transit Public Information Session May 31, 2016 Transportation
More informationEffect on structures. Uniform settlement - no concerns. Angular distortion - causes damage due to tensile strain
Effect on structures Uniform settlement - no concerns Angular distortion - causes damage due to tensile strain 1/500 - safe limit for no cracking of buildings 1/150 - potential structural damage 36 37
More informationDallas-Fort Worth Area Major Transportation Projects
Dallas-Fort Worth Area Major Transportation Projects Presented by: Jeffrey C. Neal Program Manager Transportation North Central Texas Council of Governments (NCTCOG) August 14, 2014 Texas Society of Professional
More informationMidtown Corridor Alternatives Analysis Scope of Work. April 18, 2012
Midtown Corridor Alternatives Analysis Scope of Work April 18, 2012 Table of Contents PART 1: STUDY AREA MAPS... 1 Attachment A: Existing and Planned Transit Service... 2 Attachment B: Corridor Boardings
More informationREINVENTING TRANSIT FROM A SOCIAL SERVICE TO A CRITICAL PUBLIC UTILITY
REINVENTING TRANSIT FROM A SOCIAL SERVICE TO A CRITICAL PUBLIC UTILITY THE PRE 1950 PAST. Extensive networks for streetcars, trams and buses. Operated by the private sector through a system of franchises
More informationWilmington to Newark Commuter Rail Improvement Project
Wilmington to Newark Commuter Rail Improvement Project The Delaware Transit Corporation (DTC), a subsidiary of the Delaware Department of Transportation (DelDOT), is undertaking a rail capacity expansion
More informationSCOPE OF WORK for High Speed Rail and Intercity Passenger Rail Program Federal Grant Application Development
Draft 06162009 SCOPE OF WORK for High Speed Rail and Intercity Passenger Rail Program Federal Grant Application Development The Minnesota Department of Transportation (Mn/DOT) requires the services of
More informationGUIDANCE FOR TRANSIT FINANCIAL PLANS
U.S. Department of Transportation Federal Transit Administration GUIDANCE FOR TRANSIT FINANCIAL PLANS JUNE 2000 Prepared By: Federal Transit Administration Office of Planning Office of Program Management
More informationBolder Policies Brighter Future. Chrissy Mancini Nichols Metropolitan Planning Council
Bolder Policies Brighter Future Chrissy Mancini Nichols Metropolitan Planning Council Metropolitan Planning Council Since 1934, the Metropolitan Planning Council (MPC) has been dedicated to shaping a more
More informationEnvironmental Impact Statement for the Washington Union Station Expansion Project
This document is scheduled to be published in the Federal Register on 11/04/2015 and available online at http://federalregister.gov/a/2015-28079, and on FDsys.gov 4910-06-P DEPARTMENT OF TRANSPORTATION
More informationProposed New Starts/Small Starts Policy Guidance
Proposed New Starts/Small Starts Policy Guidance Table of Contents I. INTRODUCTION... 1 II. PROJECT JUSTIFICATION CRITERIA... 4 MOBILITY IMPROVEMENTS... 4 OPERATING EFFICIENCIES... 5 Measure:... 5 Calculation:...
More informationLincoln Downtown Master Plan Update
Lincoln Downtown Master Plan Update Table of Contents Executive Summary........................................... 1 Complete Streets Framework.................................... 3 Promenade Creating
More informationInfrastructure and Growth Leadership Advisory Group Ideas and Approaches Survey
Infrastructure and Growth Leadership Advisory Group Ideas and Approaches Survey In its second meeting, the Infrastructure and Growth Leadership Advisory Group expanded and refined the list of approaches/ideas
More informationTechnical Report Documentation Page. 2. Government Accession No. 3. Recipient's Catalog No. 1. Report No. FHWA/TX-13/0-6737-1
1. Report No. FHWA/TX-13/0-6737-1 4. Title and Subtitle EXECUTIVE REPORT: TOLL ROADS, TOLL RATES, AND DRIVER BEHAVIOR 2. Government Accession No. 3. Recipient's Catalog No. Technical Report Documentation
More informationProposed Program of High Capacity Transit Improvements City of Atlanta DRAFT
I 20 West Heavy Rail Northside Drive Bus Rapid Contingent Multi Jurisdicitional Projects Atlanta Light Rail Clifton Light Rail * I 20 East Bus Rapid * Atlanta BeltLine Central Loop Irwin AUC Line Downtown
More informationChapter 9: Transportation
Chapter 9: Transportation What is this chapter about? The goals and policies in this chapter convey the City s intent to: Create a coordinated, efficient, and more affordable multimodal transportation
More informationImpact Analysis: The Atlanta Braves new Stadium Project. March 2014. A Cushman & Wakefield Research Publication
Impact : The new Stadium Project A Cushman & Wakefield Research Publication March 2014 1 Executive Summary The new baseball stadium project will dramatically transform the Cumberland/Galleria area of Northwest
More informationto provide a framework within which the City Council and Mayor can evaluate and compare proposed uses of tax increment financing TIF; and
Note: Minneapolis Tax Increment Financing Policy Proposed Amendment July 8, 2011; Revised October 12, 2011 Additions proposed in the July 8 version are indicated by underlining; deletions are indicated
More informationAppendix C Related Studies
Appendix C Related Studies Intermodal Transit Village Concept Plan Appendix C Related Studies This appendix summarizes studies that are current at the time of this Plan. Intermodal Transit Village Concept
More informationINDOT 2000-2025 Long Range Plan
Chapter 9 INDOT 2000-2025 Long Range Plan Highway Needs Analysis Overview The statewide transportation planning process provides for the identification of highway needs through a comprehensive process
More informationPART II SCHEDULE. Scope of Services. Special Terms and Conditions. Virginia Railway Express
PART II SCHEDULE SECTION TITLE D E Scope of Services Special Terms and Conditions 11 SECTION D SCOPE OF SERVICES D.1 OVERVIEW A. The selected firm is referred to herein as either the Consultant or the
More informationPrimer on Transportation Funding and Governance in Canada s Large Metropolitan Areas
Transportation Association of Canada Primer on Transportation Funding and Governance in Canada s Large Metropolitan Areas The transportation funding and governance frameworks of Canada s metropolitan regions
More informationPerformance Goals and Objectives:
Online Briefing Winter 2011 2012 Purpose: The purpose of the Project is to examine and recommend ways of introducing higher passenger train speeds on the Empire Corridor and ways to improve reliability,
More informationTOTAL NUMBER OF DEATHS DUE TO LEVEL CROSSING ACCIDENTS
LEVEL CROSSING ACCIDENT FATALITIES The purpose of this publication is to provide an overview of level crossing fatalities in Australia. The information provided is based on unpublished data obtained from
More informationAppendix J Santa Monica Travel Demand Forecasting Model Trip Generation Rates
Appendix J Santa Monica Travel Demand Forecasting Model Trip Generation Rates SANTA MONICA TRAVEL DEMAND FORECASTING MODEL TRIP GENERATION RATES SUBMITTED BY: 201 Santa Monica Blvd., Suite 500 Santa Monica,
More informationChapter 13: Implementation Plan
Chapter 13: 13.1. INTRODUCTION The purpose of the implementation chapter of the Comprehensive Plan is to set forth the actions that the City will take to ensure that the plans, programs and policies set
More informationSR-18 Corridor Improvements in Wood County
Public Meeting Information Package SR- Corridor Improvements in Wood County Thursday, May 19, 2011 10:00 a.m. to 1:00 p.m. Meeting Location: Hancock-Wood Electric Cooperative Building 1399 Business Park
More informationExecutive Summary. Does a Streetcar Make Sense in Anaheim
Does a Streetcar Make Sense in Anaheim Streetcar in Portland s Pearl District Anaheim s proposed streetcar compares well with national best practice in Portland, Seattle and Tampa where new streetcars
More informationWhy NEC FUTURE? 457 MILES LONG 2,200 DAILY TRAINS 750,000 DAILY PASSENGERS. Study Partners. Key Needs
457 MILES LONG 2,200 DAILY TRAINS 750,000 DAILY PASSENGERS THE NEC IS THE BUSIEST RAIL CORRIDOR IN THE NATION, AND IS VITAL TO THE ECONOMY AND CITIES OF THE NORTHEAST. Why NEC FUTURE? The Northeast United
More information12MAP-21, a funding and authorization bill to govern U.S. federal surface MONITORING IMPLEMENTATION AND PERFORMANCE
MONITORING IMPLEMENTATION AND PERFORMANCE 12MAP-21, a funding and authorization bill to govern U.S. federal surface transportation spending, creates a data-driven, performance-based multimodal program
More informationRegional Rail Briefing. March 24, 2010
Regional Rail Briefing March 24, 2010 Agenda o o o o o o o Welcome Special Greetings Overview of High Speed Rail for Florida Station Representatives Responses -Orlando International Airport (OIA) -Orange
More informationMount Royal College Transit Service Plan
Mount Royal College Transit Service Plan Background In 2007 November response to Council Report C2007-78 West LRT Alignment, Budget and Project Delivery, Council directed the Administration to report back
More informationSouth Waterfront Area Dave Unsworth
South Waterfront Area Dave Unsworth TriMet Capital Projects September 14, 2011 Presentation outline Background Partnering Agreements Project descriptions OHSU Portland Aerial Tram New Campus Portland Streetcar
More informationThe Lancaster Medical District Master Plan. The Lancaster Campus District 1
The Lancaster Medical District Master Plan The Lancaster Campus District 1 Table of Contents 1 INTRODUCTION 3 2 THE PLANNING PROCESS 4 Assumptions 6 3 PLANNING CONTEXT AND ECONOMIC OUTLOOK 7 Site Analysis
More informationMercer County Multi-Modal Transportation Plan Year 2025 Travel Demand Model
Mercer County Multi-Modal Transportation Plan Year 2025 Travel Demand Model Prepared For West Virginia Department of Transportation Transportation Planning Division Building 5, Room 824 1900 Kanawha Blvd.
More informationSOUTHWEST-TO-NORTHEAST TRANSPORTATION CORRIDOR STUDY
DOCUMENT REVIEW 3.20.2015 TABLE OF CONTENTS INTRODUCTION... 1 SOUTHWEST-TO-NORTHEAST TRANSPORTATION CORRIDOR STUDY... 2 FORT WORTH PARK-AND-RIDE DEVELOPMENT STUDY... 4 JOHNSON COUNTY PASSENGER RAIL STUDY...
More informationChapter 3: Third Street Light Rail
Chapter 3: Third Street Light Rail The Third Street Light Rail Project is the most significant capital investment in generations for Muni. The 6.9-mile two-phase project, now under construction, will bring
More informationHuntley Partners, Inc.
Huntley Partners, Inc. Development Feasibility, & Implementation The Potential Impact of Tax Increment on Public-Private Slide 1 Huntley: TADs Development Feasibility & Smyrna Savannah Metropolitan Gwinnett
More informationRPA 14/ATURA Surface Transportation Program (STP) APPLICATION FOR FUNDS
RPA 14/ATURA Surface Transportation Program (STP) APPLICATION FOR FUNDS Please provide the following information when applying to RPA 14/ATURA for Surface Transportation Program (STP) funding for projects
More informationTransportation Alternatives
1 Transportation Alternatives Transportation alternatives involve a variety of components: Location Alternatives - when and where service is provided - general location as well as level of service on the
More information2009-3. The Preservation of Local Truck Routes: A Primary Connection between Commerce and the Regional Freight Network
2009-3 The Preservation of Local Truck Routes: A Primary Connection between Commerce and the Regional Freight Network July 2009 This Goods Movement Challenges and Opportunities Report was prepared jointly
More informationR-06: Innovation and Technology Fund
Project Number R-06 Subarea Systemwide Primary Mode Facility Type Length Version ST Board Workshop Date Last Modified 11-25-2015 PROJECT AREA AND REPRESENTATIVE ALIGNMENT SHORT PROJECT DESCRIPTION This
More informationCITY OF ROANOKE AND TOWN OF VINTON, VIRGINIA. RSTP Funds Joint Application FOR
CITY OF ROANOKE AND TOWN OF VINTON, VIRGINIA RSTP Funds Joint Application FOR Tinker Creek Pedestrian Bridge: Tinker Creek and Glade Creek Greenways Connection Date: September 15, 2014 RSTP Project Profile
More informationImplementation Strategy
Implementation Strategy 6 The following implementation strategy defines strategic points of intervention for complete streets programming, including visioning, goal-setting, local agency plans, coordination
More informationAlternatives to the Circ Project Prioritization Methodology Prepared for Circ Task Force July 28, 2011
Alternatives to the Circ Project Prioritization Methodology Prepared for Circ Task Force July 28, 2011 CCRPC staff has developed a draft methodology described below and detailed in the attached pages for
More informationTCRP Report 153: Guidelines for Providing Access to Public Transportation Stations. Part 2: Station Typology and Mode of Access Planning Tool
TCRP Report 153: Guidelines for Providing Access to Public Transportation Stations Part 2: Station Typology and Mode of Access Planning Tool Jamie Parks, AICP Kittelson & Associates, Inc. Acknowledgements
More informationBASSETT CREEK VALLEY MASTER PLAN OPEN HOUSE
BASSETT CREEK VALLEY MASTER PLAN OPEN HOUSE February 23, 2006 PROJECT INTRODUCTION Project Area 230 acres $50 million estimated market value (approximately) 50 acres parkland 100 residences (estimated)
More informationWHOLISTIC ENGINEERING: APPLIED TO PRT & DUAL MODE TRANSPORTATION
WHOLISTIC ENGINEERING: APPLIED TO PRT & DUAL MODE TRANSPORTATION Mark S. Buehrer, P.E., 2020 ENGINEERING, Bellingham, Washington, USA a DMS where passenger service is provided only by common-carrier vehicles
More informationExecutive Summary. Transportation Needs CHAPTER. Existing Conditions
CHAPTER 1 Executive Summary The City of Forest Grove Transportation System Plan (TSP) was updated to keep it consistent with recent growth trends in the city and other transportation planning efforts in
More informationSouth Florida East Coast Corridor (SFECC) Projects. February 7, 2012
Project Update to City of Ft. Lauderdale Central lbroward deast West ttransit it& South Florida East Coast Corridor (SFECC) Projects February 7, 2012 Transit Studies Building a network of premium transit.
More informationTRANSPORTATION MODELLING IN CALGARY
TRANSPORTATION MODELLING IN CALGARY Why Do We Use Transportation Models? There are three approaches that can be used for proceeding to develop a transportation system for Calgary s future. One approach
More informationTransit Technology Alternatives
Transit Technology Alternatives Fixed Guideway Systems (see http://www.apta.com/research/info/define/index.cfm) Heavy rail - HR Heavy Rail is a system that is totally separated from its surroundings and
More informationAPPENDIX G OPERATIONS AND MAINTENANCE COST ESTIMATION MODEL
DRAFT APPENDIX G OPERATIONS AND MAINTENANCE COST ESTIMATION MODEL Operations and Maintenance Cost Methodology and Results The Colorado Department of Transportation is conducting an Advanced Guideway System
More informationPlanning for the future. building a great city, great neighbourhoods
Planning for the future building a great city, great neighbourhoods Table of contents 1 Looking ahead 2.4 million Calgarians 2 Goals 3 Building a sustainable, connected city of great neighbourhoods 4 Finding
More informationTransit in the United States 3. Operating Costs and Performance Measures 13. Quality of Transit Service 19. ADA Compliance Bus 28
1999 National Transit Summaries and Trends Introduction 1 Introduces the transit modes discussed throughout the NTST. Transit in the United States 3 National statistics and trends in ridership, miles of
More informationFinancial Plan & Implementation. Matrix
Financial Plan & Implementation Matrix Revenue Projections and Financial Assumptions 1.0 Context. Background. The development of the financial plan is consistent with requirements regarding the development
More informationSTATE OF DELAWARE DEPARTMENT OF TRANSPORTATION CAPITAL TRANSPORTATION PROGRAM TRANSIT FACILITIES 3-306
SUPPORT SYSTEM TRANSIT FACILITIES 3-306 NEWARK TRANSIT HUB PROJECT SCOPE/DESCRIPTION: Funding was authorized to begin a study to select a site for the Newark Transit Hub. Future improvements may include
More informationTransitways and the RouteAhead for Calgary Transit
Transitways and the RouteAhead for Calgary Transit Chris Jordan, P.Eng., M.Sc., Manager, Strategic Planning, Calgary Transit, Transportation, City of Calgary Jen Malzer, P.Eng., M.Sc., Senior Transit Planner,
More informationSection ALTERNATIVES. 3. Alternatives
Section 3 ALTERNATIVES 3. Alternatives 3.0 Alternatives The Springfield Rail Improvements Project Build Alternatives would utilize different routes. The No Build Alternative includes the continuation of
More informationAEROTROPOLIS ATLANTA HARTSFIELD-JACKSON ATLANTA INTERNATIONAL AIRPORT 175,000+ 100+ SQUARE MILES 1 REGIONAL COMMISSION 4 INTERSTATE SYSTEMS
$32.5B OF DIRECT ECONOMIC IMPACT AEROTROPOLIS ATLANTA BY THE NUMBERS 5 MARTA STATIONS 1 REGIONAL COMMISSION 4 INTERSTATE SYSTEMS 36 AIRLINES 100+ SQUARE MILES 4,700 ACRES (H-JAIA) 1.3M SQUARE FEET OF AIR
More informationStouffville Corridor Rail Service Expansion
Stouffville Corridor Rail Service Expansion Stouffville Corridor Rail Service Expansion Class Environmental Assessment Study WELCOME PUBLIC INFORMATION CENTRE #2 Tuesday January 28, 2014 Agincourt Recreation
More informationNew York Avenue-Florida Avenue- Galludet University Metro Station: A Case Study
New York Avenue-Florida Avenue- Galludet University Metro Station: A Case Study The New York Avenue-Florida Avenue-Galludet University Metro station in Washington DC is a result of planners and neighborhood
More informationPROJECT PREPARATORY TECHNICAL ASSISTANCE
A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The Government of Azerbaijan, the Ministry of Transport and Baku Metro Company requested ADB to help improving its urban transport system and
More informationRailyard Alternatives and I-280 Boulevard Feasibility Study. Planning Commission February 6, 2014
Railyard Alternatives and I-280 Boulevard Feasibility Study Planning Commission February 6, 2014 Problem Statement Major pieces of new infrastructure are planned including: Downtown Rail Extension (DTX)
More information