1 May 2009 I-85 CORRIDOR LIGHT RAIL TRANSIT FEASIBILITY STUDY Executive Summary Prepared for: Gwinnett Village Community Improvement District 1412 Oakbrook Drive, Suite 181 Norcross, Georgia Gwinnett Place Community Improvement District 3700 Crestwood Parkway, Suite 680 Duluth, Georgia Prepared by: HDR Engineering, Inc Peachtree Street, Suite 2210 Atlanta, Georgia

2 I-85 CORRIDOR LIGHT RAIL TRANSIT FEASIBILITY STUDY Executive Summary Prepared for: Gwinnett Village Community Improvement District 1412 Oakbrook Drive, Suite 181 Norcross, Georgia Gwinnett Place Community Improvement District 3700 Crestwood Parkway, Suite 680 Duluth, Georgia Prepared by: HDR Engineering, Inc Peachtree Street, Suite 2210 Atlanta, Georgia May 2009

3 Table of Contents 1 Introduction Alternatives Refinement Technology Assessment Conceptual Engineering Track Alignment Station Locations Maintenance Facility Technical Analysis Travel Demand Forecasting Operating Plans Operating and Maintenance Cost Estimates Capital Cost Estimates Limited Environmental Assessment Evaluation and Recommendations Funding Opportunities About This Report...13 Table of Tables Table 1: Comparison of Transit Technology Options... 2 Table 2: Alignment Alternatives... 3 Table 3: Estimated Daily Boardings per Station... 7 Table 4: Summary of Operating Requirements... 8 Table 5: Capital Cost Estimates... 8 Table 6: Evaluation Matrix... 10

4 1 INTRODUCTION The was commenced in September, 2008 to evaluate the technical and financial viability of a light rail line in Gwinnett County. The project co-sponsors, Gwinnett Village Community Improvement District and Gwinnett Place Community Improvement District, initiated the project to explore the potential benefit of serving the I-85 corridor with light rail transit (LRT). Figure 1 displays the extent of the corridor examined for the I-85 Corridor LRT Feasibility Study. Figure 1: I-85 LRT Study Corridor As part of this study, conceptual LRT alignments and station locations were identified and analyzed. Capital and operating costs were estimated for each alternative along with a basic ridership forecast and environmental screening. The preferred alignment, which was developed alongside the project sponsors and in conjunction with a number of stakeholders, was evaluated to determine its relative strengths compared to other recently implemented LRT systems. Finally, a number of funding opportunities at both the federal and local levels were identified. The results of this analysis are summarized herein and presented in greater detail in Executive Summary 1

5 the following sections of the final report. 2 ALTERNATIVES REFINEMENT 2.1 Technology Assessment A technology assessment was conducted to evaluate the various transit technology options for the I-85 corridor. Heavy rail transit (HRT), light rail transit (LRT), and modern streetcar were evaluated as part of this analysis. Table 1 displays a comparison of each mode by operating variable. Heavy rail is the most capital-intensive transit mode, while modern streetcar is typically the least expensive mode to build. However, HRT provides the highest capacity and operating speeds. Light rail transit, which can be classified into two categories high cost, exclusive right-of-way and moderate cost, shared right-of-way provides a balance between HRT and streetcar, as it offers operating speeds and capacity that can compete with heavy rail at a fraction of the capital cost. Table 1: Comparison of Transit Technology Options Light Rail Light Rail Heavy Rail Exclusive Right of Streetcar Shared Right of Way Way Cost/Mile $ million $ million $25-60 million $15-30 million Seated Capacity/Train Service Range Up to 30 Miles Up to 20 Miles Up to 15 Miles 2 to 10 Miles Maximum Speed MPH MPH MPH MPH Average Speed MPH MPH MPH 8-15 MPH Station Spacing > 1 Mile 1/2 to 1 Mile 1/2 to 1 Mile ¼ to ½ Mile Executive Summary 2

6 3 CONCEPTUAL ENGINEERING The conceptual engineering phase of the I-85 Corridor LRT Feasibility Study involved identifying preliminary track alignments, station locations, and maintenance facility sites. Substantial data analysis and field assessments along with evaluation of existing land use and transportation plans provided the information necessary to develop conceptual LRT routes and station locations. 3.1 Track Alignment Six preliminary track alignment options were identified and screened based on the following factors: Right-of-way availability Land use compatibility Future land use plans, both at the CID and County levels Topographic constraints Potential impacts to street traffic operations Availability of adjacent land for maintenance facility Additionally, coordination meetings were held with other stakeholder agencies including MARTA and the Gwinnett County Department of Transportation in order to further vet and refine the alignment alternatives. Based on input from these agencies and CID staff, a preferred alternative was developed for further analysis. Table 2 provides a brief description of each alternative, while Figure 2 graphically displays each alignment alternative. Table 2: Alignment Alternatives Alternative Route One-Way Travel Miles Time (Mins) Description Preferred Industrial Corridor / Satellite Blvd. / Satellite Blvd. Alternative Industrial Corridor / Venture Dr. / Utility Corridor Alternative Jimmy Carter Blvd. / Satellite Blvd. / Satellite Blvd. Alternative Industrial Corridor / Venture Dr. / Satellite Blvd. Alternative Jimmy Carter Blvd. / Venture Dr. / Utility Corridor Alternative Jimmy Carter Blvd. / Venture Dr. / Satellite Blvd. Executive Summary 3

7 Figure 2: Alignment Alternatives 3.2 Executive Summary 4

8 3.3 Station Locations A total of nine station locations were identified for the Preferred Alternative, as displayed in Figure 3, below. These preliminary station locations were determined based on the following criteria: Topography Current land use Adjacent land uses Redevelopment potential Sufficient size to accommodate the station and ancillary facilities Roadway access Pedestrian access Environmental fatal flaws The stations are classified into two categories: major and neighborhood. Major stations will serve larger office and retail markets and tend to have more amenities and intermodal transfer facilities, while neighborhood stations will be smaller and tend to serve smaller, more pedestrian-oriented market areas. Major stations identified include Norcross, Gwinnett Village, Indian Trail, Pleasant Hill, Gwinnett Place, and Gwinnett Arena. Neighborhood stations identified include Mitchell Road, Liddell Road, and Duluth Highway. Figure 3: Station Locations for Preferred Alternative Executive Summary 5

9 3.4 Maintenance Facility Fourteen preliminary sites, as displayed in Figure 4, were screened for suitability as a possible maintenance facility site for the LRT corridor. In consideration of the costs associated with nonrevenue train movements, the bulk of the sites identified were near either terminus of the alignment. Because most of the land within the corridor is built-out, it is likely that any potential maintenance facility site would have to be redeveloped. Thus, sites were identified and screened based on adjacent land use compatibility and parcel size. It was determined that six sites within the industrial area on the western end of the alignment should be advanced for further analysis and consideration. Figure 4: Maintenance Facility Site Options Executive Summary 6

10 4 TECHNICAL ANALYSIS The Technical Analysis phase of the I-85 Corridor LRT Feasibility Study involved further examination of the alignment options identified in the Conceptual Engineering phase. Highlevel ridership estimates were developed based on existing Transit Planning Board (TPB) travel demand forecasts. LRT operating plans were created and used to develop operating and maintenance cost estimates. Capital costs were estimated based on the preliminary engineering drawings. Finally, a limited environmental analysis was conducted to identify any major environmental fatal flaws. 4.1 Travel Demand Forecasting Estimated daily boardings for the LRT line from Norcross to Gwinnett Arena were developed based on the TPB Concept3 travel demand forecasts which included a line from Cumberland to Gwinnett Arena. This forecast was adapted to include only that ridership that would occur on the Gwinnett County portion of the TPB alignment. Ridership by station, as displayed in Table 3, was estimated based on low, medium, and high land use scenarios. It should be noted that the stations coded for the Concept3 model differ slightly from those stations identified in this study. Thus, these ridership estimations are for proxy use only, and will be further refined in Phase II of the I-85 Corridor LRT Feasibility Study. Table 3: Estimated Daily Boardings per Station Station Total Daily Boardings (2030 Model Year) LRT Low LRT Med. LRT High MARTA HRT Norcross 6,799 9,432 11,839 2,200 Gwinnett Village/Jimmy Carter Blvd ,117 6,000 Indian Trail 1,951 3,030 4,325 3,400 Gwinnett Place 2,966 4,200 5,339 9,300 Old Norcross 692 1,007 1,064 n/a Boggs 1,171 1,453 1,733 n/a Gwinnett Arena 2,024 2,576 3,388 n/a Total: 16,236 22,563 28,805 20, Operating Plans Operating plans for each alternative were developed based on ridership estimations and data provided in the conceptual engineering phase of the project. Operating requirements for each alternative are displayed in Table 4, below. Because the alternatives had only marginal differences in route miles and running time, the operating requirements are similar for each alignment with respect to car-miles, car-hours, train-hours, and peak trains. Executive Summary 7

11 Table 4: Summary of Operating Requirements Route Peak -----Annual Revenue----- Lay Cycle ---Trains--- ALT Miles LRVs Car-Miles Car-Hours Train-Hours Over Time Peak Base Eve. Preferred Alternative ,382, ,760 46, Alternative ,366, ,760 46, Alternative ,339, ,760 46, Alternative ,309, ,760 46, Alternative ,320, ,760 46, Alternative ,263, ,760 46, Operating and Maintenance Cost Estimates Operating and maintenance (O&M) costs were estimated based on the projected operating requirements for each alternative. A fully-allocated cost model was developed using data from nine peer LRT systems. The unit costs for each operating variable derived from these peer systems were applied to corresponding planned units of service for each alternative to estimate total annual O&M costs. Annual O&M costs (estimated in 2009 dollars) range from approximately $25.1 million to $25.6 million. 4.4 Capital Cost Estimates Capital costs were estimated using the Federal Transit Administration s (FTA) Standard Cost Categories (SCC). Standard Cost Categories include all capital components of the LRT construction process. Unit costs for each SCC were developed and applied to the units required for construction of each LRT alternative. The total capital costs and capital cost per mile for each alternative are listed in Table 5, below. Table 5: Capital Cost Estimates Alignment Option Total Cost Length (miles) Cost per Mile Preferred Alternative $1,017 million $73 million Alternative 1 $918 million $67 million Alternative 2 $1,058 million $78 million Alternative 3 $926 million $69 million Alternative 4 $959 million $71 million Alternative 5 $967 million $73 million Executive Summary 8

12 4.5 Limited Environmental Assessment A preliminary screening of the LRT corridor was performed in order to identify any areas of environmental concern. While this exercise does not fulfill or replace any local, state or federal requirements for environmental permitting, it provides a baseline indication as to the potential environmental hazards within the corridor. There were 37 documented sites found within 150 of the preferred alignment, and 279 within the corridor as a whole. Remediation may be required depending on the severity of environmental risk posed at these sites. Executive Summary 9

13 5 EVALUATION AND RECOMMENDATIONS The preferred alternative was evaluated against five peer LRT systems that have been recently constructed or are currently being built. The proposed Gwinnett LRT system compares favorably with regard to capital and operating cost variables. However, the system s ridership received lower ratings compared to the peer system average. Further ridership analysis to be performed during Phase II of this project will allow for greater certainty as to how the Gwinnett system s projected ridership will compete with the peer systems. It is important that the Gwinnett LRT system is rated favorably with regard to these variables as each contributes to the funding formulas dictated by the FTA for New Starts funding. System Phase Projected Ridership (Design Year) Table 6: Evaluation Matrix Daily New Ridership Ridership/Rou te-mile Cost/New Rider Capital Cost (YOE) Capital Cost/Mile Annual O&M Cost (YOE) Annual O&M/Route Mile Gwinnett Norcross to Arena - N/A - N/A Charlotte South Corridor o Houston Downtown to Astrodome o - + o Minneapolis Hiawatha Corridor o Phoenix East Valley + + o + - o - + Seattle Central Link + o Positive rating with regard to criterion o Neutral rating with regard to criterion - Negative rating with regard to criterion Executive Summary 10

14 6 FUNDING OPPORTUNITIES A number of funding opportunities exist to finance a LRT project in Gwinnett County. In addition to federal New Starts grant funding, which typically fund up to half of a project s total capital costs, the following federal and local funding options exist: Development Impact Fees/Benefit Assessment Districts Tax Increment Financing (TIFs) Federal Discretionary Funds Federal Railroad Administration Intercity Passenger Rail Investment Grants Public-Private Partnerships (PPP) Bonding Grant Anticipation Notes TIFIA Loans State Infrastructure Banks Private Donations Dedicated Sales Tax Hotel/Motel Tax Car Rental Tax Vehicle Registration Fee Property Tax for Transit Joint Development on Existing and Planned Facilities Tolls Congestion Pricing Safety Inspection Fee New Resident Impact Fee Distance-based Road User Fee On-going operating and maintenance expenses should also be planned for prior to implementation of a LRT system. While some of the aforementioned funding opportunities for capital expenses may also be applied to operating expenses, funding options for operating and maintenance typically include: Fare revenues Advertising revenues Interest Taxes Federal funding (5307, JARC, CMAQ [in non-attainment areas], STP) Parking revenues Joint development funds. Executive Summary 11

15 7 FINAL REPORT The I-85 Corridor Light Rail Feasibility Study Final Report is divided into four sections. Section 1, Refine Alternatives Final Report, includes the technology assessment report and documentation of the conceptual engineering process. Section 2, Technical Analysis Final Report, documents the technical studies performed for the project including ridership estimation, operating plan development, operating and maintenance cost estimation, capital cost estimation, and a limited environmental assessment. Section 3, Evaluation and Recommendations and Funding Opportunities, detail the evaluation methodology and results and funding opportunities for the proposed LRT project. Finally, Section 4 Station Renderings, includes a number of conceptual renderings for the Gwinnett Village, Mitchell Road, and Gwinnett Place Stations. In the months following preparation of the final report, Phase II of the I-85 Corridor LRT Feasibility Study will be conducted. Phase II will encompass detailed ridership forecasting using a travel demand model specifically coded for the proposed LRT corridor as well as a comprehensive travel market analysis. A third section will provide a detailed framework for advancing the project into the FTA New Starts project development process. Executive Summary 13

Addendum to the Arterial Transitway Corridors Study

Addendum to the Arterial Transitway Corridors Study January 2013 1 Addendum to the Arterial Transitway Corridors Study The Arterial Transitway Corridors Study (ATCS) evaluated and prioritized arterial bus rapid transit (BRT) improvements to nine corridors

More information

Southwest Light Rail Transit Minneapolis-St. Paul, Minnesota New Starts Project Development (Rating Assigned November 2014)

Southwest Light Rail Transit Minneapolis-St. Paul, Minnesota New Starts Project Development (Rating Assigned November 2014) Southwest Light Rail Transit Minneapolis-St. Paul, Minnesota New Starts Project Development (Rating Assigned November 2014) Summary Description Proposed Project: Light Rail Transit 15.7 Miles, 17 Stations

More information

5.0 FINANCIAL ANALYSIS AND COMPARISON OF ALTERNATIVES

5.0 FINANCIAL ANALYSIS AND COMPARISON OF ALTERNATIVES 5.0 FINANCIAL ANALYSIS AND COMPARISON OF ALTERNATIVES 5.1 FINANCIAL ANALYSIS The cost of a transportation investment falls into two categories: capital costs, and operating and maintenance (O&M) costs.

More information

Triangle Transit Financial Plan. Durham Orange Light Rail Transit Project

Triangle Transit Financial Plan. Durham Orange Light Rail Transit Project Durham Orange Light Rail Transit Project September 2012 TABLE OF CONTENTS LIST OF TABLES... ii LIST OF FIGURES... iii 1. Introduction... 1 1 1.1. DESCRIPTION OF PROJECT SPONSOR... 1 1 1.1.1. Durham Transit

More information

Mid-Coast Corridor Transit Project San Diego, California New Starts Engineering (Rating Assigned November 2015)

Mid-Coast Corridor Transit Project San Diego, California New Starts Engineering (Rating Assigned November 2015) Mid-Coast Corridor Transit Project San Diego, California New Starts Engineering (Rating Assigned November 2015) Summary Description Proposed Project: Light Rail Transit 10.9 Miles, 9 Stations Total Capital

More information

Evergreen Line Rapid Transit Project Business Case Executive Summary. February 2008. Reviewed by

Evergreen Line Rapid Transit Project Business Case Executive Summary. February 2008. Reviewed by Evergreen Line Rapid Transit Project Business Case Executive Summary February 2008 Reviewed by Recommendation and Executive Summary The business case for the Evergreen Line Rapid Transit Project (the Project)

More information

Mid-Coast Corridor Transit Project San Diego, California New Starts Project Development (Rating Assigned November 2014)

Mid-Coast Corridor Transit Project San Diego, California New Starts Project Development (Rating Assigned November 2014) Mid-Coast Corridor Transit Project San Diego, California New Starts Project Development (Rating Assigned November 2014) Summary Description Proposed Project: Light Rail Transit 10.9 Miles, 9 Stations Total

More information

MAKING TRACKS. A Primer for Implementing Transit Fixed Guideway Projects

MAKING TRACKS. A Primer for Implementing Transit Fixed Guideway Projects MAKING TRACKS A Primer for Implementing Transit Fixed Guideway Projects Introduction Demand for new fixed guideway projects is strong nationwide. Each year hundreds of new fixed guideway projects across

More information

VRE SYSTEM PLAN SUMMARY

VRE SYSTEM PLAN SUMMARY VRE System Plan Summary January 2014 VRE SYSTEM PLAN SUMMARY VRE A Cost-Effective Contributor to Regional Mobility During the last decade, VRE has demonstrated its ability to accommodate a rapid and substantial

More information

Eagle Commuter Rail Denver, Colorado Final Design (Based upon information received by FTA in November 2010)

Eagle Commuter Rail Denver, Colorado Final Design (Based upon information received by FTA in November 2010) Eagle Commuter Rail Denver, Colorado Final Design (Based upon information received by FTA in November 2010) Summary Description Proposed Project: Electrified Commuter Rail 30.2 Miles, 13 Stations Total

More information

The financial plan was prepared in conjunction with the Technical Working Group. Refer to Table 3-1: Funding and Implementation Plan.

The financial plan was prepared in conjunction with the Technical Working Group. Refer to Table 3-1: Funding and Implementation Plan. 3 Financial Plan The purpose of the financial plan is to identify funding options that would be likely sources of money to advance recommendations made by this study. The Capitol Region Transportation

More information

Legislative Fiscal Bureau One East Main, Suite 301 Madison, WI 53703 (608) 266-3847 Fax: (608) 267-6873

Legislative Fiscal Bureau One East Main, Suite 301 Madison, WI 53703 (608) 266-3847 Fax: (608) 267-6873 Legislative Fiscal Bureau One East Main, Suite 301 Madison, WI 53703 (608) 266-3847 Fax: (608) 267-6873 February 16, 2010 TO: FROM: Members Joint Committee on Finance Bob Lang, Director SUBJECT: Governor's

More information

GTA Cordon Count Program

GTA Cordon Count Program Transportation Trends 2001-2011 Executive Summary Project No. TR12 0722 September 2013 1.0 Introduction The Cordon Count program was established to collect traffic data as a tool for measuring travel trends

More information

When is BRT the Best Option? 1:30 2:40 p.m.

When is BRT the Best Option? 1:30 2:40 p.m. TRB/APTA 2004 Bus Rapid Transit Conference When is BRT the Best Option? 1:30 2:40 p.m. Paul Larrousse Director, National Transit Institute (NTI) (Moderator) TRB/APTA 2004 Bus Rapid Transit Conference Session

More information

Integrating GO RER and SmartTrack. Leslie Woo, Chief Planning Officer February 10, 2016

Integrating GO RER and SmartTrack. Leslie Woo, Chief Planning Officer February 10, 2016 Integrating GO RER and SmartTrack Leslie Woo, Chief Planning Officer February 10, 2016 Purpose and Scope To present update on development of options for integrating SmartTrack and GO RER based on the following

More information

Introduction to Station Area Planning The Charlotte Story

Introduction to Station Area Planning The Charlotte Story Introduction to Station Area Planning The Charlotte Story Boston 2009 Steve Hamwey - Sasaki Associates, Inc. Troy Russ - Glatting Jackson, Inc. October 31 st, 2009 Station Area Planning October 15th History

More information

S-11: Tacoma Link Extension to Tacoma Community College

S-11: Tacoma Link Extension to Tacoma Community College Project Number S-11 Subarea Pierce Primary Mode Light Rail Facility Type Corridor Length 3.65 miles Version ST Board Workshop Date Last Modified 11-25-2015 PROJECT AREA AND REPRESENTATIVE ALIGNMENT SHORT

More information

2035 FINANCIAL RESOURCES FORECAST

2035 FINANCIAL RESOURCES FORECAST 2035 FINANCIAL RESOURCES FORECAST AKRON METROPOLITAN AREA TRANSPORTATION STUDY 806 CITICENTER BUILDING 146 SOUTH HIGH STREET AKRON, OHIO 44308 December 2012 This report was prepared by the Akron Metropolitan

More information

10 Aviation Element. 10.1 Introduction. 10.1.1 Purpose of Chapter

10 Aviation Element. 10.1 Introduction. 10.1.1 Purpose of Chapter 10 Aviation Element 10.1 Introduction 10.1.1 Purpose of Chapter This chapter provides the aviation element of the RFATS 2035 Long Range Transportation Plan. It describes the existing conditions and trends

More information

Financial Analysis and Funding

Financial Analysis and Funding California High- Speed Rail Authority Revised 2012 Business Plan Chapter 7 Financial Analysis and Funding Introduction This chapter presents the financial analysis and funding strategy for the California

More information

Questions and Answers about the Orange Bus/Rail Investment Plan

Questions and Answers about the Orange Bus/Rail Investment Plan Why are transit improvements needed? Questions and Answers about the Orange Bus/Rail Investment Plan The Triangle Region is now home to 1.5 million people. The U.S. Census and the 2035 Joint Long Range

More information

and the statewide and metropolitan transportation planning and programming process in California:

and the statewide and metropolitan transportation planning and programming process in California: Financial constraint... and the statewide and metropolitan transportation planning and programming process in California: A GUIDE TO FEDERAL AND STATE FINANCIAL PLANNING REQUIREMENTS Prepared by: Federal

More information

Doing More with the Same: How the Trinity Railway Express Increased Service without Increasing Costs

Doing More with the Same: How the Trinity Railway Express Increased Service without Increasing Costs Doing More with the Same: How the Trinity Railway Express Increased Service without Increasing Costs W. T. "Bill" Farquhar Trinity Railway Express Irving, TX Abstract The Trinity Railway Express (TRE)

More information

Growth of Addis Ababa

Growth of Addis Ababa Growth of Addis Ababa Founded in 1887, and has expanded rapidly Now among the ten largest cities in Sub Saharan Africa Annual growth rate is 3.8% By 2020 population growth would reach to eight million.

More information

TRANSPORTATION SERVICE STANDARDS ELEMENT GOALS, OBJECTIVES & POLICIES

TRANSPORTATION SERVICE STANDARDS ELEMENT GOALS, OBJECTIVES & POLICIES TRANSPORTATION SERVICE STANDARDS ELEMENT GOALS, OBJECTIVES & POLICIES Background One of the most critical public services provided by a community is the community s transportation system. An effective

More information

Understanding Value Capture as a Transportation Finance Strategy in Massachusetts. March 15, 2013

Understanding Value Capture as a Transportation Finance Strategy in Massachusetts. March 15, 2013 Understanding Value Capture as a Transportation Finance Strategy in Massachusetts March 15, 2013 Background The Massachusetts Legislature will soon explore options to increase transportation revenue. One

More information

Light Rail Transit in Phoenix

Light Rail Transit in Phoenix 4. Presentation and Discussion: Phoenix Light Rail Implementation Wulf Grote Planning and Development Director, Phoenix Valley Metro Light Rail Transit in Phoenix Broadway Citizen s Task Force February

More information

Seattle Streetcar Center City Connector Seattle, Washington Small Starts Project Development (Rating Assigned November 2015)

Seattle Streetcar Center City Connector Seattle, Washington Small Starts Project Development (Rating Assigned November 2015) Seattle Streetcar Center City Connector Seattle, Washington Small Starts Project Development (Rating Assigned November 2015) Summary Description Proposed Project: Streetcar 1.3 Miles, 4 Stations otal Capital

More information

Utilizing Value Capture for Transportation Funding

Utilizing Value Capture for Transportation Funding Utilizing Value Capture for Transportation Funding Transport Chicago 2011 Conference Go To 2040 Capital Transportation Projects Go To 2040 Fiscally Constrained Projects 5 Extension/new projects 10 Transportation

More information

Chapter 5 Financial Plan

Chapter 5 Financial Plan The Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users (SAFETEA_LU) requires that the MTP incorporate a financial plan for the planning period. The MTP is required to

More information

Financial Plan Status Report

Financial Plan Status Report Financial Plan Status Report Broward MPO Board March 13, 2014 Financial Sub-Committee Membership SFRTA (lead agency) Broward MPO FDOT Miami-Dade MPO Palm Beach MPO South Florida Regional Planning Council

More information

MOTION NO. M2015-63 WSDOT Task Order for Final Design Services PROPOSED ACTION

MOTION NO. M2015-63 WSDOT Task Order for Final Design Services PROPOSED ACTION MOTION NO. M2015-63 WSDOT Task Order for Final Design Services MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Capital Committee 07/09/15 Final Action Ahmad Fazel, DECM Executive Director Ron Lewis, East

More information

Evaluation Criteria and Mode Progression for RouteAhead Rapid Transit Projects

Evaluation Criteria and Mode Progression for RouteAhead Rapid Transit Projects Evaluation Criteria and Mode Progression for RouteAhead Rapid Transit Projects C2012-0684 ATTACHMENT 2 The RouteAhead draft 30-year rapid transit plan was developed in coordination with the Investing in

More information

A Review of Transit Technology Specifications

A Review of Transit Technology Specifications . Transit Technologies Worksheet A Review of Transit Technology Specifications 1 2 3 4 5 6 1. Heavy Rail Transit 2. Commuter Rail Transit 3. Light Rail Transit 4. Modern Streetcar 5. Heritage Trolley 6.

More information

Downtown Tampa Transportation Vision

Downtown Tampa Transportation Vision Downtown Tampa Transportation Vision Executive Summary August 1, 2006 Hillsborough County Metropolitan Planning Organization County Center, 18 th Floor Tampa, Florida 33602 813-272-5940 www.hillsboroughmpo.org

More information

Filling the Gap: Funding Transit Infill Stations in the United States

Filling the Gap: Funding Transit Infill Stations in the United States Filling the Gap: Funding Transit Infill Stations in the United States Amanda Wall Vandegrift Parsons Brinckerhoff Nathan M. Macek, AICP Parsons Brinckerhoff INTRODUCTION Many fixed guideway transit systems

More information

Coordinated Transit Planning in Toronto SmartTrack Eglinton West LRT Eglinton East LRT Scarborough Subway Extension Relief Line Waterfront Transit

Coordinated Transit Planning in Toronto SmartTrack Eglinton West LRT Eglinton East LRT Scarborough Subway Extension Relief Line Waterfront Transit Coordinated Transit Planning in Toronto SmartTrack Eglinton West LRT Eglinton East LRT Scarborough Subway Extension Relief Line Waterfront Transit Public Information Session May 31, 2016 Transportation

More information

Effect on structures. Uniform settlement - no concerns. Angular distortion - causes damage due to tensile strain

Effect on structures. Uniform settlement - no concerns. Angular distortion - causes damage due to tensile strain Effect on structures Uniform settlement - no concerns Angular distortion - causes damage due to tensile strain 1/500 - safe limit for no cracking of buildings 1/150 - potential structural damage 36 37

More information

Dallas-Fort Worth Area Major Transportation Projects

Dallas-Fort Worth Area Major Transportation Projects Dallas-Fort Worth Area Major Transportation Projects Presented by: Jeffrey C. Neal Program Manager Transportation North Central Texas Council of Governments (NCTCOG) August 14, 2014 Texas Society of Professional

More information

Midtown Corridor Alternatives Analysis Scope of Work. April 18, 2012

Midtown Corridor Alternatives Analysis Scope of Work. April 18, 2012 Midtown Corridor Alternatives Analysis Scope of Work April 18, 2012 Table of Contents PART 1: STUDY AREA MAPS... 1 Attachment A: Existing and Planned Transit Service... 2 Attachment B: Corridor Boardings

More information

REINVENTING TRANSIT FROM A SOCIAL SERVICE TO A CRITICAL PUBLIC UTILITY

REINVENTING TRANSIT FROM A SOCIAL SERVICE TO A CRITICAL PUBLIC UTILITY REINVENTING TRANSIT FROM A SOCIAL SERVICE TO A CRITICAL PUBLIC UTILITY THE PRE 1950 PAST. Extensive networks for streetcars, trams and buses. Operated by the private sector through a system of franchises

More information

Wilmington to Newark Commuter Rail Improvement Project

Wilmington to Newark Commuter Rail Improvement Project Wilmington to Newark Commuter Rail Improvement Project The Delaware Transit Corporation (DTC), a subsidiary of the Delaware Department of Transportation (DelDOT), is undertaking a rail capacity expansion

More information

SCOPE OF WORK for High Speed Rail and Intercity Passenger Rail Program Federal Grant Application Development

SCOPE OF WORK for High Speed Rail and Intercity Passenger Rail Program Federal Grant Application Development Draft 06162009 SCOPE OF WORK for High Speed Rail and Intercity Passenger Rail Program Federal Grant Application Development The Minnesota Department of Transportation (Mn/DOT) requires the services of

More information

GUIDANCE FOR TRANSIT FINANCIAL PLANS

GUIDANCE FOR TRANSIT FINANCIAL PLANS U.S. Department of Transportation Federal Transit Administration GUIDANCE FOR TRANSIT FINANCIAL PLANS JUNE 2000 Prepared By: Federal Transit Administration Office of Planning Office of Program Management

More information

Bolder Policies Brighter Future. Chrissy Mancini Nichols Metropolitan Planning Council

Bolder Policies Brighter Future. Chrissy Mancini Nichols Metropolitan Planning Council Bolder Policies Brighter Future Chrissy Mancini Nichols Metropolitan Planning Council Metropolitan Planning Council Since 1934, the Metropolitan Planning Council (MPC) has been dedicated to shaping a more

More information

Environmental Impact Statement for the Washington Union Station Expansion Project

Environmental Impact Statement for the Washington Union Station Expansion Project This document is scheduled to be published in the Federal Register on 11/04/2015 and available online at http://federalregister.gov/a/2015-28079, and on FDsys.gov 4910-06-P DEPARTMENT OF TRANSPORTATION

More information

Proposed New Starts/Small Starts Policy Guidance

Proposed New Starts/Small Starts Policy Guidance Proposed New Starts/Small Starts Policy Guidance Table of Contents I. INTRODUCTION... 1 II. PROJECT JUSTIFICATION CRITERIA... 4 MOBILITY IMPROVEMENTS... 4 OPERATING EFFICIENCIES... 5 Measure:... 5 Calculation:...

More information

Lincoln Downtown Master Plan Update

Lincoln Downtown Master Plan Update Lincoln Downtown Master Plan Update Table of Contents Executive Summary........................................... 1 Complete Streets Framework.................................... 3 Promenade Creating

More information

Infrastructure and Growth Leadership Advisory Group Ideas and Approaches Survey

Infrastructure and Growth Leadership Advisory Group Ideas and Approaches Survey Infrastructure and Growth Leadership Advisory Group Ideas and Approaches Survey In its second meeting, the Infrastructure and Growth Leadership Advisory Group expanded and refined the list of approaches/ideas

More information

Technical Report Documentation Page. 2. Government Accession No. 3. Recipient's Catalog No. 1. Report No. FHWA/TX-13/0-6737-1

Technical Report Documentation Page. 2. Government Accession No. 3. Recipient's Catalog No. 1. Report No. FHWA/TX-13/0-6737-1 1. Report No. FHWA/TX-13/0-6737-1 4. Title and Subtitle EXECUTIVE REPORT: TOLL ROADS, TOLL RATES, AND DRIVER BEHAVIOR 2. Government Accession No. 3. Recipient's Catalog No. Technical Report Documentation

More information

Proposed Program of High Capacity Transit Improvements City of Atlanta DRAFT

Proposed Program of High Capacity Transit Improvements City of Atlanta DRAFT I 20 West Heavy Rail Northside Drive Bus Rapid Contingent Multi Jurisdicitional Projects Atlanta Light Rail Clifton Light Rail * I 20 East Bus Rapid * Atlanta BeltLine Central Loop Irwin AUC Line Downtown

More information

Chapter 9: Transportation

Chapter 9: Transportation Chapter 9: Transportation What is this chapter about? The goals and policies in this chapter convey the City s intent to: Create a coordinated, efficient, and more affordable multimodal transportation

More information

Impact Analysis: The Atlanta Braves new Stadium Project. March 2014. A Cushman & Wakefield Research Publication

Impact Analysis: The Atlanta Braves new Stadium Project. March 2014. A Cushman & Wakefield Research Publication Impact : The new Stadium Project A Cushman & Wakefield Research Publication March 2014 1 Executive Summary The new baseball stadium project will dramatically transform the Cumberland/Galleria area of Northwest

More information

to provide a framework within which the City Council and Mayor can evaluate and compare proposed uses of tax increment financing TIF; and

to provide a framework within which the City Council and Mayor can evaluate and compare proposed uses of tax increment financing TIF; and Note: Minneapolis Tax Increment Financing Policy Proposed Amendment July 8, 2011; Revised October 12, 2011 Additions proposed in the July 8 version are indicated by underlining; deletions are indicated

More information

Appendix C Related Studies

Appendix C Related Studies Appendix C Related Studies Intermodal Transit Village Concept Plan Appendix C Related Studies This appendix summarizes studies that are current at the time of this Plan. Intermodal Transit Village Concept

More information

INDOT 2000-2025 Long Range Plan

INDOT 2000-2025 Long Range Plan Chapter 9 INDOT 2000-2025 Long Range Plan Highway Needs Analysis Overview The statewide transportation planning process provides for the identification of highway needs through a comprehensive process

More information

PART II SCHEDULE. Scope of Services. Special Terms and Conditions. Virginia Railway Express

PART II SCHEDULE. Scope of Services. Special Terms and Conditions. Virginia Railway Express PART II SCHEDULE SECTION TITLE D E Scope of Services Special Terms and Conditions 11 SECTION D SCOPE OF SERVICES D.1 OVERVIEW A. The selected firm is referred to herein as either the Consultant or the

More information

Primer on Transportation Funding and Governance in Canada s Large Metropolitan Areas

Primer on Transportation Funding and Governance in Canada s Large Metropolitan Areas Transportation Association of Canada Primer on Transportation Funding and Governance in Canada s Large Metropolitan Areas The transportation funding and governance frameworks of Canada s metropolitan regions

More information

Performance Goals and Objectives:

Performance Goals and Objectives: Online Briefing Winter 2011 2012 Purpose: The purpose of the Project is to examine and recommend ways of introducing higher passenger train speeds on the Empire Corridor and ways to improve reliability,

More information

TOTAL NUMBER OF DEATHS DUE TO LEVEL CROSSING ACCIDENTS

TOTAL NUMBER OF DEATHS DUE TO LEVEL CROSSING ACCIDENTS LEVEL CROSSING ACCIDENT FATALITIES The purpose of this publication is to provide an overview of level crossing fatalities in Australia. The information provided is based on unpublished data obtained from

More information

Appendix J Santa Monica Travel Demand Forecasting Model Trip Generation Rates

Appendix J Santa Monica Travel Demand Forecasting Model Trip Generation Rates Appendix J Santa Monica Travel Demand Forecasting Model Trip Generation Rates SANTA MONICA TRAVEL DEMAND FORECASTING MODEL TRIP GENERATION RATES SUBMITTED BY: 201 Santa Monica Blvd., Suite 500 Santa Monica,

More information

Chapter 13: Implementation Plan

Chapter 13: Implementation Plan Chapter 13: 13.1. INTRODUCTION The purpose of the implementation chapter of the Comprehensive Plan is to set forth the actions that the City will take to ensure that the plans, programs and policies set

More information

SR-18 Corridor Improvements in Wood County

SR-18 Corridor Improvements in Wood County Public Meeting Information Package SR- Corridor Improvements in Wood County Thursday, May 19, 2011 10:00 a.m. to 1:00 p.m. Meeting Location: Hancock-Wood Electric Cooperative Building 1399 Business Park

More information

Executive Summary. Does a Streetcar Make Sense in Anaheim

Executive Summary. Does a Streetcar Make Sense in Anaheim Does a Streetcar Make Sense in Anaheim Streetcar in Portland s Pearl District Anaheim s proposed streetcar compares well with national best practice in Portland, Seattle and Tampa where new streetcars

More information

Why NEC FUTURE? 457 MILES LONG 2,200 DAILY TRAINS 750,000 DAILY PASSENGERS. Study Partners. Key Needs

Why NEC FUTURE? 457 MILES LONG 2,200 DAILY TRAINS 750,000 DAILY PASSENGERS. Study Partners. Key Needs 457 MILES LONG 2,200 DAILY TRAINS 750,000 DAILY PASSENGERS THE NEC IS THE BUSIEST RAIL CORRIDOR IN THE NATION, AND IS VITAL TO THE ECONOMY AND CITIES OF THE NORTHEAST. Why NEC FUTURE? The Northeast United

More information

12MAP-21, a funding and authorization bill to govern U.S. federal surface MONITORING IMPLEMENTATION AND PERFORMANCE

12MAP-21, a funding and authorization bill to govern U.S. federal surface MONITORING IMPLEMENTATION AND PERFORMANCE MONITORING IMPLEMENTATION AND PERFORMANCE 12MAP-21, a funding and authorization bill to govern U.S. federal surface transportation spending, creates a data-driven, performance-based multimodal program

More information

Regional Rail Briefing. March 24, 2010

Regional Rail Briefing. March 24, 2010 Regional Rail Briefing March 24, 2010 Agenda o o o o o o o Welcome Special Greetings Overview of High Speed Rail for Florida Station Representatives Responses -Orlando International Airport (OIA) -Orange

More information

Mount Royal College Transit Service Plan

Mount Royal College Transit Service Plan Mount Royal College Transit Service Plan Background In 2007 November response to Council Report C2007-78 West LRT Alignment, Budget and Project Delivery, Council directed the Administration to report back

More information

South Waterfront Area Dave Unsworth

South Waterfront Area Dave Unsworth South Waterfront Area Dave Unsworth TriMet Capital Projects September 14, 2011 Presentation outline Background Partnering Agreements Project descriptions OHSU Portland Aerial Tram New Campus Portland Streetcar

More information

The Lancaster Medical District Master Plan. The Lancaster Campus District 1

The Lancaster Medical District Master Plan. The Lancaster Campus District 1 The Lancaster Medical District Master Plan The Lancaster Campus District 1 Table of Contents 1 INTRODUCTION 3 2 THE PLANNING PROCESS 4 Assumptions 6 3 PLANNING CONTEXT AND ECONOMIC OUTLOOK 7 Site Analysis

More information

Mercer County Multi-Modal Transportation Plan Year 2025 Travel Demand Model

Mercer County Multi-Modal Transportation Plan Year 2025 Travel Demand Model Mercer County Multi-Modal Transportation Plan Year 2025 Travel Demand Model Prepared For West Virginia Department of Transportation Transportation Planning Division Building 5, Room 824 1900 Kanawha Blvd.

More information

SOUTHWEST-TO-NORTHEAST TRANSPORTATION CORRIDOR STUDY

SOUTHWEST-TO-NORTHEAST TRANSPORTATION CORRIDOR STUDY DOCUMENT REVIEW 3.20.2015 TABLE OF CONTENTS INTRODUCTION... 1 SOUTHWEST-TO-NORTHEAST TRANSPORTATION CORRIDOR STUDY... 2 FORT WORTH PARK-AND-RIDE DEVELOPMENT STUDY... 4 JOHNSON COUNTY PASSENGER RAIL STUDY...

More information

Chapter 3: Third Street Light Rail

Chapter 3: Third Street Light Rail Chapter 3: Third Street Light Rail The Third Street Light Rail Project is the most significant capital investment in generations for Muni. The 6.9-mile two-phase project, now under construction, will bring

More information

Huntley Partners, Inc.

Huntley Partners, Inc. Huntley Partners, Inc. Development Feasibility, & Implementation The Potential Impact of Tax Increment on Public-Private Slide 1 Huntley: TADs Development Feasibility & Smyrna Savannah Metropolitan Gwinnett

More information

RPA 14/ATURA Surface Transportation Program (STP) APPLICATION FOR FUNDS

RPA 14/ATURA Surface Transportation Program (STP) APPLICATION FOR FUNDS RPA 14/ATURA Surface Transportation Program (STP) APPLICATION FOR FUNDS Please provide the following information when applying to RPA 14/ATURA for Surface Transportation Program (STP) funding for projects

More information

Transportation Alternatives

Transportation Alternatives 1 Transportation Alternatives Transportation alternatives involve a variety of components: Location Alternatives - when and where service is provided - general location as well as level of service on the

More information

2009-3. The Preservation of Local Truck Routes: A Primary Connection between Commerce and the Regional Freight Network

2009-3. The Preservation of Local Truck Routes: A Primary Connection between Commerce and the Regional Freight Network 2009-3 The Preservation of Local Truck Routes: A Primary Connection between Commerce and the Regional Freight Network July 2009 This Goods Movement Challenges and Opportunities Report was prepared jointly

More information

R-06: Innovation and Technology Fund

R-06: Innovation and Technology Fund Project Number R-06 Subarea Systemwide Primary Mode Facility Type Length Version ST Board Workshop Date Last Modified 11-25-2015 PROJECT AREA AND REPRESENTATIVE ALIGNMENT SHORT PROJECT DESCRIPTION This

More information

CITY OF ROANOKE AND TOWN OF VINTON, VIRGINIA. RSTP Funds Joint Application FOR

CITY OF ROANOKE AND TOWN OF VINTON, VIRGINIA. RSTP Funds Joint Application FOR CITY OF ROANOKE AND TOWN OF VINTON, VIRGINIA RSTP Funds Joint Application FOR Tinker Creek Pedestrian Bridge: Tinker Creek and Glade Creek Greenways Connection Date: September 15, 2014 RSTP Project Profile

More information

Implementation Strategy

Implementation Strategy Implementation Strategy 6 The following implementation strategy defines strategic points of intervention for complete streets programming, including visioning, goal-setting, local agency plans, coordination

More information

Alternatives to the Circ Project Prioritization Methodology Prepared for Circ Task Force July 28, 2011

Alternatives to the Circ Project Prioritization Methodology Prepared for Circ Task Force July 28, 2011 Alternatives to the Circ Project Prioritization Methodology Prepared for Circ Task Force July 28, 2011 CCRPC staff has developed a draft methodology described below and detailed in the attached pages for

More information

TCRP Report 153: Guidelines for Providing Access to Public Transportation Stations. Part 2: Station Typology and Mode of Access Planning Tool

TCRP Report 153: Guidelines for Providing Access to Public Transportation Stations. Part 2: Station Typology and Mode of Access Planning Tool TCRP Report 153: Guidelines for Providing Access to Public Transportation Stations Part 2: Station Typology and Mode of Access Planning Tool Jamie Parks, AICP Kittelson & Associates, Inc. Acknowledgements

More information

BASSETT CREEK VALLEY MASTER PLAN OPEN HOUSE

BASSETT CREEK VALLEY MASTER PLAN OPEN HOUSE BASSETT CREEK VALLEY MASTER PLAN OPEN HOUSE February 23, 2006 PROJECT INTRODUCTION Project Area 230 acres $50 million estimated market value (approximately) 50 acres parkland 100 residences (estimated)

More information

WHOLISTIC ENGINEERING: APPLIED TO PRT & DUAL MODE TRANSPORTATION

WHOLISTIC ENGINEERING: APPLIED TO PRT & DUAL MODE TRANSPORTATION WHOLISTIC ENGINEERING: APPLIED TO PRT & DUAL MODE TRANSPORTATION Mark S. Buehrer, P.E., 2020 ENGINEERING, Bellingham, Washington, USA a DMS where passenger service is provided only by common-carrier vehicles

More information

Executive Summary. Transportation Needs CHAPTER. Existing Conditions

Executive Summary. Transportation Needs CHAPTER. Existing Conditions CHAPTER 1 Executive Summary The City of Forest Grove Transportation System Plan (TSP) was updated to keep it consistent with recent growth trends in the city and other transportation planning efforts in

More information

South Florida East Coast Corridor (SFECC) Projects. February 7, 2012

South Florida East Coast Corridor (SFECC) Projects. February 7, 2012 Project Update to City of Ft. Lauderdale Central lbroward deast West ttransit it& South Florida East Coast Corridor (SFECC) Projects February 7, 2012 Transit Studies Building a network of premium transit.

More information

TRANSPORTATION MODELLING IN CALGARY

TRANSPORTATION MODELLING IN CALGARY TRANSPORTATION MODELLING IN CALGARY Why Do We Use Transportation Models? There are three approaches that can be used for proceeding to develop a transportation system for Calgary s future. One approach

More information

Transit Technology Alternatives

Transit Technology Alternatives Transit Technology Alternatives Fixed Guideway Systems (see http://www.apta.com/research/info/define/index.cfm) Heavy rail - HR Heavy Rail is a system that is totally separated from its surroundings and

More information

APPENDIX G OPERATIONS AND MAINTENANCE COST ESTIMATION MODEL

APPENDIX G OPERATIONS AND MAINTENANCE COST ESTIMATION MODEL DRAFT APPENDIX G OPERATIONS AND MAINTENANCE COST ESTIMATION MODEL Operations and Maintenance Cost Methodology and Results The Colorado Department of Transportation is conducting an Advanced Guideway System

More information

Planning for the future. building a great city, great neighbourhoods

Planning for the future. building a great city, great neighbourhoods Planning for the future building a great city, great neighbourhoods Table of contents 1 Looking ahead 2.4 million Calgarians 2 Goals 3 Building a sustainable, connected city of great neighbourhoods 4 Finding

More information

Transit in the United States 3. Operating Costs and Performance Measures 13. Quality of Transit Service 19. ADA Compliance Bus 28

Transit in the United States 3. Operating Costs and Performance Measures 13. Quality of Transit Service 19. ADA Compliance Bus 28 1999 National Transit Summaries and Trends Introduction 1 Introduces the transit modes discussed throughout the NTST. Transit in the United States 3 National statistics and trends in ridership, miles of

More information

Financial Plan & Implementation. Matrix

Financial Plan & Implementation. Matrix Financial Plan & Implementation Matrix Revenue Projections and Financial Assumptions 1.0 Context. Background. The development of the financial plan is consistent with requirements regarding the development

More information

STATE OF DELAWARE DEPARTMENT OF TRANSPORTATION CAPITAL TRANSPORTATION PROGRAM TRANSIT FACILITIES 3-306

STATE OF DELAWARE DEPARTMENT OF TRANSPORTATION CAPITAL TRANSPORTATION PROGRAM TRANSIT FACILITIES 3-306 SUPPORT SYSTEM TRANSIT FACILITIES 3-306 NEWARK TRANSIT HUB PROJECT SCOPE/DESCRIPTION: Funding was authorized to begin a study to select a site for the Newark Transit Hub. Future improvements may include

More information

Transitways and the RouteAhead for Calgary Transit

Transitways and the RouteAhead for Calgary Transit Transitways and the RouteAhead for Calgary Transit Chris Jordan, P.Eng., M.Sc., Manager, Strategic Planning, Calgary Transit, Transportation, City of Calgary Jen Malzer, P.Eng., M.Sc., Senior Transit Planner,

More information

Section ALTERNATIVES. 3. Alternatives

Section ALTERNATIVES. 3. Alternatives Section 3 ALTERNATIVES 3. Alternatives 3.0 Alternatives The Springfield Rail Improvements Project Build Alternatives would utilize different routes. The No Build Alternative includes the continuation of

More information

AEROTROPOLIS ATLANTA HARTSFIELD-JACKSON ATLANTA INTERNATIONAL AIRPORT 175,000+ 100+ SQUARE MILES 1 REGIONAL COMMISSION 4 INTERSTATE SYSTEMS

AEROTROPOLIS ATLANTA HARTSFIELD-JACKSON ATLANTA INTERNATIONAL AIRPORT 175,000+ 100+ SQUARE MILES 1 REGIONAL COMMISSION 4 INTERSTATE SYSTEMS $32.5B OF DIRECT ECONOMIC IMPACT AEROTROPOLIS ATLANTA BY THE NUMBERS 5 MARTA STATIONS 1 REGIONAL COMMISSION 4 INTERSTATE SYSTEMS 36 AIRLINES 100+ SQUARE MILES 4,700 ACRES (H-JAIA) 1.3M SQUARE FEET OF AIR

More information

Stouffville Corridor Rail Service Expansion

Stouffville Corridor Rail Service Expansion Stouffville Corridor Rail Service Expansion Stouffville Corridor Rail Service Expansion Class Environmental Assessment Study WELCOME PUBLIC INFORMATION CENTRE #2 Tuesday January 28, 2014 Agincourt Recreation

More information

New York Avenue-Florida Avenue- Galludet University Metro Station: A Case Study

New York Avenue-Florida Avenue- Galludet University Metro Station: A Case Study New York Avenue-Florida Avenue- Galludet University Metro Station: A Case Study The New York Avenue-Florida Avenue-Galludet University Metro station in Washington DC is a result of planners and neighborhood

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The Government of Azerbaijan, the Ministry of Transport and Baku Metro Company requested ADB to help improving its urban transport system and

More information

Railyard Alternatives and I-280 Boulevard Feasibility Study. Planning Commission February 6, 2014

Railyard Alternatives and I-280 Boulevard Feasibility Study. Planning Commission February 6, 2014 Railyard Alternatives and I-280 Boulevard Feasibility Study Planning Commission February 6, 2014 Problem Statement Major pieces of new infrastructure are planned including: Downtown Rail Extension (DTX)

More information