Expo Light Rail Line. Expo Line Community Meeting Quarterly Phase 2 Construction Update Santa Monica September 2014

Size: px
Start display at page:

Download "Expo Light Rail Line. Expo Line Community Meeting Quarterly Phase 2 Construction Update Santa Monica September 2014"

Transcription

1 Expo Line Community Meeting Quarterly Phase 2 Construction Update Santa Monica September 2014

2 Meeting Agenda Phase 2 Construction Update Meeting Santa Monica Meeting Purpose and Format Construction Update Maintenance Facility Update Expo Bikeway Update Next Steps Open House Session

3 Meeting Purpose and Format Meeting Purpose and Format The purpose of tonight s meeting is to: Provide an update on construction activity in the City of Santa Monica Share information on the Maintenance Facility and Expo Bikeway Receive input and feedback from the community The format will include a short presentation followed by an interactive Open House session to facilitate dialogue and community input. Please be sure to visit all the stations and: Collect information Ask questions Share your ideas

4 Expo Line Project Description Phase 2 Expo Line from Culver City to Santa Monica: 6.6 mile corridor 7 new Stations 64,000 Daily Riders by 2030 Estimated Travel Time (Downtown LA to Santa Monica): 46 minutes Estimated Cost: $1.5 billion Final design in now complete Project is 70% complete Major construction started in 2012

5 26 th Street/Bergamot Station Street view from looking east

6 17 th Street/SMC Station Street view looking east

7 Downtown Santa Monica Station Street view from Colorado Avenue looking east

8 Construction Progress Expo Phase 2 Construction Progress at a Glance 2014 Construction Highlights: Station construction is more than 63% complete All 7 bridges have been completed Track installation to be completed this Fall Roadway widening work and final paving continues

9 Construction Update Expo Right-of-Way (ROW) Construction Progress Rail Installation at 19 th Street Maintenance Facility Building Progress Downtown Santa Monica Station Concrete Pour TPSS Installation at Olympic and Cloverfield

10 Ongoing Construction Activities thru December 2014 Centinela Ave to 4th Street Continue with track installation Traffic signal, street light installation and train control installation Final street improvements Sidewalk installation between Stewart and Cloverfield 6th Street is the remaining track track crossing tentatively scheduled for Oct 27-Nov 5 Irrigation and permanent fence installation Installation of OCS Poles and Catenary Wires Construction Progress Olympic Bridge Rail Installation Progress

11 Construction Progress Station Progress thru December th Street/ Bergamot 17 th Street/ SMC Downtown Santa Monica Foundation work nearing completion On-going electrical and systems installation Canopy and archway installation Platform paver installation has been completed Track installation was completed in June 26 th Street /Bergamot Station Paver Installation

12 Construction Progress Station Progress thru December th Street/ Bergamot 17 th Street/ SMC Downtown Santa Monica On-going electrical and systems installation Canopy and archway installation Paver installation has been completed Foundation work is complete Track installation was completed in July 17 th Street /SMC Station Tactile Warning Paver Installation

13 Construction Progress Station Progress thru December th Street/ Bergamot 17th Street/ SMC Downtown Santa Monica Foundation work on-going Utility work on-going Electrical Systems Installation Platform paver installation to start in November Track installation to be completed in October Downtown Santa Monica Station Concrete Pour

14 Bikeway and Maintenance Facility Expo Bikeway Design/Construction Soil removal and grading Irrigation, drainage systems, and curb and gutter Electrical and lighting conduits Maintenance Facility On-going installation of building pre-cast panels Typical Bike Path Design Installation of Main building interior utilities and walls On-site rail installation to start in mid-october Foundation construction for secondary and third buildings continues Maintenance Facility Building Foundation Progress

15 Construction Timeline Construction Progress and Timeline Construction Timeline 2011 Pre-Construction Activities 2012 Bridge Construction, Utility Relocation and Guideway Excavation, and Soundwalls Bridge and Station Construction, Utility Relocation, Soundwalls, Track Installation and Street/Roadway Improvements Continue Street/Roadway Improvements, Track Installation, Utility Relocation Station Finishes, Electrical System, Train Control, and Landscaping Installation Continue Street/Roadway Improvements and Landscaping Installation, Systems Testing and Pre-Revenue Operations

16 Next Steps Next Steps Provide regular updates to stakeholder groups throughout construction Next Quarterly Project Construction Update Meeting: 2015 Santa Monica Community Update Meeting

17 Format for Open House Session The room is divided into informational tables where you can: View final renderings of the Phase 2 stations Open House Session Meet with project staff that can address your questions/concerns on issues such as station design, noise impacts, traffic and circulation, and safety Provide your feedback Table #1 Table #2 Table #3 General Project Information and Expo Bikeway Construction Design

18 Contacts How to Reach Us Project Website: Sign-up on our homepage to be added to the project database and receive notices via . Project Hotline: EXPO (3976) Community Relations Contacts: Torri Hill SRJV Community Relations Manager or Heather Rozman SRJV Community Relations Coordinator or Social Media:

Expo Light Rail Line. Expo Board Presentation Monthly Project Status Update May 7, 2015

Expo Light Rail Line. Expo Board Presentation Monthly Project Status Update May 7, 2015 Expo Board Presentation Monthly Project Status Update May 7, 2015 Expo Phase 1 Phase 1 Project Status Closeout Status Completing Closeout of Remaining Elements of Work Final As-Builts nearing completion

More information

Project Status Update Open House West End Corridor

Project Status Update Open House West End Corridor Project Status Update Open House West End Corridor The Exposition Construction Authority cordially invites you to a Project Status Update Open House for the Exposition Light Rail Line At this meeting we

More information

Roadway Cost Per Centerline Mile Revised June 2014

Roadway Cost Per Centerline Mile Revised June 2014 Rural Arterial From LRE MOT * Mobilization * Subtotal Total PE Design (15%) CEI (15%) Total Project ** New (2-Lane Roadway) with 5' Paved Shoulders $3,351,896 $335,190 $368,709 $4,055,794 $1,013,949 $5,069,743

More information

Welcome! Purpose of Tonight s Meeting. Informational Open House to discuss two City projects: Goal is to LISTEN TO YOU

Welcome! Purpose of Tonight s Meeting. Informational Open House to discuss two City projects: Goal is to LISTEN TO YOU Purpose of Tonight s Meeting Informational Open House to discuss two City projects: Fairchild Street Subway Phase I Engineering: Immediate need to replace subway Bowman Avenue Feasibility Study Future

More information

Evanston Main Street Station TOD Plan and Study. Appendix A.1: Station Area Existing Conditions

Evanston Main Street Station TOD Plan and Study. Appendix A.1: Station Area Existing Conditions Evanston Main Street Station TOD Plan and Study Appendix A.1: Station Area Existing Conditions EvanstonMainStreetStation TODPlanandStudy A 1 AppendixA.1: ExistingConditions Table of Contents Station Locations

More information

PLANNED UNIT DEVELOPMENT & SIDEWALK WAIVER REQUEST STAFF REPORT Date: November 7, 2013

PLANNED UNIT DEVELOPMENT & SIDEWALK WAIVER REQUEST STAFF REPORT Date: November 7, 2013 PLANNED UNIT DEVELOPMENT & SIDEWALK WAIVER REQUEST STAFF REPORT Date: November 7, 2013 NAME LOCATION Audubon Properties, LLC. 4700 & 4960 Dauphin Island Parkway West side of Dauphin Island Parkway, 580

More information

AGENDA ITEM SUMMARY FORT COLLINS CITY COUNCIL 11

AGENDA ITEM SUMMARY FORT COLLINS CITY COUNCIL 11 DATE: September 4, 2012 STAFF: Patrick Rowe, Terry Tyrell Helen Matson AGENDA ITEM SUMMARY FORT COLLINS CITY COUNCIL 11 SUBJECT Second Reading of Ordinance No. 080, 2012, Authorizing the Acquisition by

More information

Northwest Light Rail Extension Pre-Construction/Final Design. Public Meeting November 27 & 29, 2012

Northwest Light Rail Extension Pre-Construction/Final Design. Public Meeting November 27 & 29, 2012 Northwest Light Rail Extension Pre-Construction/Final Design Public Meeting November 27 & 29, 2012 6:00 6:30 p.m. Open House 6:30 7:00 p.m. Presentation 7:00 8:00 p.m. Open House 2 Project Overview Carla

More information

Gardnerville Water Company Regular Board Meeting Minutes Tuesday, April 8, 2014 5:00 p.m. Board Room 1579 Virginia Ranch Rd Gardnerville, NV 89410

Gardnerville Water Company Regular Board Meeting Minutes Tuesday, April 8, 2014 5:00 p.m. Board Room 1579 Virginia Ranch Rd Gardnerville, NV 89410 Gardnerville Water Company Regular Board Meeting Minutes Tuesday, April 8, 2014 5:00 p.m. Board Room 1579 Virginia Ranch Rd Gardnerville, NV 89410 Board Members Present: Barbara Henningsen, Chairman Mark

More information

PROJECT COST ESTIMATE ASSUMPTIONS AND EXCLUSIONS

PROJECT COST ESTIMATE ASSUMPTIONS AND EXCLUSIONS C PROJECT ESTIMATE ASSUMPTIONS AND EXCLUSIONS In support of the alternatives development process, preliminary cost estimates were prepared for each of the three Candidate Build Alternatives. The cost estimates

More information

OPTIMUS WORK CLASSIFICATION LIST ENTER ALL THAT APPLY

OPTIMUS WORK CLASSIFICATION LIST ENTER ALL THAT APPLY Cost Code # Description Cost Code # Description 01 00 00.001 General Requirements 02 00 00.001 Existing Conditions 01 31 19.13.001 Preconstruction Meetings 02 21 00.001 Surveys 01 32 33.001 Photographic

More information

CITY OF BRAMPTON STREET CORRIDOR MASTER PLAN

CITY OF BRAMPTON STREET CORRIDOR MASTER PLAN 1.0 INTRODUCTION... 1 1.1 Purpose of Document... 1 1.2 Master Plan Goal...1 1.3 Design Objectives... 2 1.4 Design Approach... 2 2.0 PROJECT SCOPE...2 2.1 City Context 2 2.2 Regional Context 2 3.0 DESIGN

More information

APPENDIX F RIGHTS-OF-WAY PRESERVATION GUIDELINES

APPENDIX F RIGHTS-OF-WAY PRESERVATION GUIDELINES Los Angeles County Metropolitan Transportation Authority (Metro) 2009 Transportation Improvement Program Call for Projects APPENDIX F RIGHTS-OF-WAY PRESERVATION GUIDELINES Los Angeles County Metropolitan

More information

NAHB 1-00-0000 PRODUCT DEFINITION

NAHB 1-00-0000 PRODUCT DEFINITION NAHB Standard Homebuilder Cost Codes Cost Code Description 1-00-0000 PRODUCT DEFINITION 1-01-0000 PREAQUISITION COSTS 1-01-0110 Feasibility Study 1-01-0120 Environmental Impact Study 1-01-0130 Option Fees

More information

DESCRIPTION OF WORK:

DESCRIPTION OF WORK: DEPARTMENT OF PUBLIC WORKS COUNTY OF HENRICO P.O. BOX 27032 RICHMOND, VIRGINIA 23273 PERMIT NO. One (1) copy of application and four (4) copies of plans are hereby made to the Director of Public Works

More information

CHAPTER 8 CIVIL DESIGN

CHAPTER 8 CIVIL DESIGN CHAPTER 8 CIVIL DESIGN A. GENERAL This Chapter includes standards and design considerations for other civil engineering design in structural, drainage and utilities. Design considerations for electrical

More information

Light Rail Transit in Phoenix

Light Rail Transit in Phoenix 4. Presentation and Discussion: Phoenix Light Rail Implementation Wulf Grote Planning and Development Director, Phoenix Valley Metro Light Rail Transit in Phoenix Broadway Citizen s Task Force February

More information

Florida Avenue Multimodal Transportation Study. June 19, 2013

Florida Avenue Multimodal Transportation Study. June 19, 2013 Florida Avenue Multimodal Transportation Study June 19, 2013 Today s Agenda Team & project introduction Project Timeline What you said Tools we use Mapped data and what clues it can provide Highlights

More information

Cost Reduction Opportunities

Cost Reduction Opportunities Cost Reduction Opportunities 9 December 2015 Presentation to MassDOT Board of Directors & MBTA Fiscal and Management Control Board Arup 2 A global, integrated, multidisciplinary firm of professionals 13,000

More information

Moving Ruston Forward. City of Ruston Infrastructure Maintenance and Improvements

Moving Ruston Forward. City of Ruston Infrastructure Maintenance and Improvements Moving Ruston Forward City of Ruston Infrastructure Maintenance and Improvements MLK Extension Project will be done in conjunction with proposed water and sewer improvements Connect Martin Luther King

More information

Legacy Trail Extension Feasibility Study. Preliminary Cost Estimate

Legacy Trail Extension Feasibility Study. Preliminary Cost Estimate Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5

More information

Alternatives Presentation Meeting Middlebury WCRS(23)

Alternatives Presentation Meeting Middlebury WCRS(23) Alternatives Presentation Meeting Middlebury WCRS(23) Main Street (VT 30/TH 2 Bridge 102) and Merchants Row (TH 8 Bridge 2) over Vermont Railway June 4, 2013 Twilight Hall Auditorium, Middlebury College

More information

Description Quantity Cost Total Cost

Description Quantity Cost Total Cost APPENDIX: ITEMIZED CONSTRUCTION COST ESTIMATE Description Quantity Cost Total Cost 1 CASCADE FALLS 1a Existing Cascade Falls Upgrades Structural Repairs - Steps, Railing, Walls, Pool Lump Sum $500,000

More information

Stouffville Corridor Rail Service Expansion

Stouffville Corridor Rail Service Expansion Stouffville Corridor Rail Service Expansion Stouffville Corridor Rail Service Expansion Class Environmental Assessment Study WELCOME PUBLIC INFORMATION CENTRE #2 Tuesday January 28, 2014 Agincourt Recreation

More information

Pavement Management Program

Pavement Management Program Pavement Management Program 2014 Street Maintenance Program Executive Summary 01/21/2014 Presented by Mark Thiel Assistant Director of Public Works Program Overview Start of current program 2005 825.1

More information

Appendix J Santa Monica Travel Demand Forecasting Model Trip Generation Rates

Appendix J Santa Monica Travel Demand Forecasting Model Trip Generation Rates Appendix J Santa Monica Travel Demand Forecasting Model Trip Generation Rates SANTA MONICA TRAVEL DEMAND FORECASTING MODEL TRIP GENERATION RATES SUBMITTED BY: 201 Santa Monica Blvd., Suite 500 Santa Monica,

More information

IDOT Chicago - St. Louis High-Speed Rail Program Management

IDOT Chicago - St. Louis High-Speed Rail Program Management 1 www.idothsr.org www.connectthemidwest.com IDOT Chicago - St. Louis High-Speed Rail Program Management Lessons Learned: Sealing the Corridor For 110 MPH Operations Thomas W. Hunter Parsons Brinckerhoff

More information

Facility Summary. Facility Condition Summary. Seattle School District David T. Denny International Infrastructure. Facility Components

Facility Summary. Facility Condition Summary. Seattle School District David T. Denny International Infrastructure. Facility Components Infrastructure Facility Condition Summary Weighted Avg Condition Score Facility Components Systems Surveyor/ Date Done Comments G Sitework.9 Site Improvements Parking Pedestrian Paving Site Development

More information

MTA UNIVERSAL STATION PEDESTRIAN BRIDGE Los Angeles, CA. Project Manual and Specification 100% PE SUBMITTAL TABLE OF CONTENTS

MTA UNIVERSAL STATION PEDESTRIAN BRIDGE Los Angeles, CA. Project Manual and Specification 100% PE SUBMITTAL TABLE OF CONTENTS Los Angeles, CA Project Manual and Specification DIVISION 1 GENERAL CONDITIONS 01 01 10 STATEMENT OF WORK 01 11 00 SUMMARY OF THE WORK 01 14 05 METRO (OWNER) - DIRECTED STOPPAGES 01 20 00 PRICE AND PAYMENT

More information

SECTION 02221 SELECTIVE DEMOLITION

SECTION 02221 SELECTIVE DEMOLITION SECTION 02221 PART 1 -GENERAL 1.01 DESCRIPTION This section includes all material, labor, machinery and supervision required to demolish and remove the following items where applicable and as noted on

More information

Effect on structures. Uniform settlement - no concerns. Angular distortion - causes damage due to tensile strain

Effect on structures. Uniform settlement - no concerns. Angular distortion - causes damage due to tensile strain Effect on structures Uniform settlement - no concerns Angular distortion - causes damage due to tensile strain 1/500 - safe limit for no cracking of buildings 1/150 - potential structural damage 36 37

More information

ADA POST INSPECTION CHECKLIST. Job No. Route County Location

ADA POST INSPECTION CHECKLIST. Job No. Route County Location ADA POST INSPECTION CHECKLIST Job No. Route County Location SIDEWALKS All sidewalks constructed within the project limits are ADA compliant. Sidewalks are 5 or greater in width. Exception, existing sidewalks

More information

Lincoln Downtown Master Plan Update

Lincoln Downtown Master Plan Update Lincoln Downtown Master Plan Update Table of Contents Executive Summary........................................... 1 Complete Streets Framework.................................... 3 Promenade Creating

More information

CITY OF ROANOKE AND TOWN OF VINTON, VIRGINIA. RSTP Funds Joint Application FOR

CITY OF ROANOKE AND TOWN OF VINTON, VIRGINIA. RSTP Funds Joint Application FOR CITY OF ROANOKE AND TOWN OF VINTON, VIRGINIA RSTP Funds Joint Application FOR Tinker Creek Pedestrian Bridge: Tinker Creek and Glade Creek Greenways Connection Date: September 15, 2014 RSTP Project Profile

More information

UNIT PRICE LIST January 2009

UNIT PRICE LIST January 2009 UNIT PRICE LIST January 2009 1 INTRODUCTION The purpose of the Unit Price List is to provide a resource for the preparation of cost estimates for subdivisions and permit projects and should be used only

More information

General Obligation Bond Projects FYE 2013-2018

General Obligation Bond Projects FYE 2013-2018 General Obligation Bond Projects FYE 2013-2018 2009 City of Norman Community Survey Final Report 2011 CTP Survey Results Storm Drainage and Street Widening Projects Combined Storm Water/Transportation

More information

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project MONTHLY COST AND SCHEDULE UPDATE FOR PHASE 2 AS OF JULY 31, 2015 SEPTEMBER 2015 Phase 2 Cost Summary July Expenditures $ 19.2 Million Total Expenditures $ 508.7 Million

More information

Robert D. Trimborn Airport Director Santa Monica Airport

Robert D. Trimborn Airport Director Santa Monica Airport Robert D. Trimborn Airport Director Santa Monica Airport Association of California Airports Conference - September 18, 2009 Noise Air Emissions Ground Support Equipment Alternative Fuels and Green

More information

Walkable Communities Florida Department of Transportation State Safety Office Pedestrian and Bicycle Program April 1995 www.dot.state.fl.us/safety Twelve Steps for an Effective Program Page 1 Twelve Steps

More information

FY 2011 OHIO SMALL CITIES COMMUNITY DEVELOPMENT BLOCK GRANT COMPREHENSIVE DOWNTOWN REVITALIZATION PROGRAM

FY 2011 OHIO SMALL CITIES COMMUNITY DEVELOPMENT BLOCK GRANT COMPREHENSIVE DOWNTOWN REVITALIZATION PROGRAM CITYOFOBERLIN OHIO CITY OF OBERLIN, OHIO FY 2011 OHIO SMALL CITIES COMMUNITY DEVELOPMENT BLOCK GRANT COMPREHENSIVE DOWNTOWN REVITALIZATION PROGRAM Background In October, 2011, the City of Oberlin Planning

More information

Date. Resubmit this form during the year if there are changes in your company ownership or financial standing.

Date. Resubmit this form during the year if there are changes in your company ownership or financial standing. COLORADO DEPARTMENT OF TRANSPORTATION CONTRACTOR PREQUALIFICATION STATEMENT (EXPERIENCE, EQUIPMENT AND FINANCIAL) Return to: Contracts & Market Analysis Prequalification Unit 4201 E. Arkansas,4th Floor

More information

CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT

CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT Volkert Field Office 80 M Street SE, Suite 725 Washington, DC 20003 RIVERSMART WASHINGTON - CONSTRUCTION RIVERSMART MACFARLAND, RIVERSMART LAFAYETTE AND GREEN ALLEYS CHEVY CHASE D.C. Contract No.: DCKA-2013-C-0160

More information

Chapter 22. Lump Sum Project Guidelines

Chapter 22. Lump Sum Project Guidelines Chapter 22 Lump Sum Project Guidelines 22.1 General...22-1 22.2 Project Selection...22-3 22.3 Plans Preparation...22-5 22.4 Preliminary Estimate...22-7 22.5 Specifications...22-9 22.6 Contracts Administration...22-11

More information

CITY OF NEW ORLEANS. Repaving the Gateway to the French Quarter: Implementing the Downtown Infrastructure Improvement Project

CITY OF NEW ORLEANS. Repaving the Gateway to the French Quarter: Implementing the Downtown Infrastructure Improvement Project CITY OF NEW ORLEANS Repaving the Gateway to the French Quarter: Implementing the Downtown Infrastructure Improvement Project 8/7/2014 Agenda Background Project Scope Lessons Learned Discussion 2 Superdome

More information

Introduction to Station Area Planning The Charlotte Story

Introduction to Station Area Planning The Charlotte Story Introduction to Station Area Planning The Charlotte Story Boston 2009 Steve Hamwey - Sasaki Associates, Inc. Troy Russ - Glatting Jackson, Inc. October 31 st, 2009 Station Area Planning October 15th History

More information

July 2010 Met Council contributes $1 million to small business loan fund More Downtown Downtown Minneapolis St. Paul

July 2010 Met Council contributes $1 million to small business loan fund More Downtown Downtown Minneapolis St. Paul July 2010 Chair Peter Bell of the Metropolitan Council speaks about the Met Council s contribution of $1 million to a $1.5 million small business loan fund during a July 20 news conference with Mayor R.T.

More information

C-2 Construction, Inc. - NAICS Codes

C-2 Construction, Inc. - NAICS Codes C-2 Construction, Inc. - NAICS Codes 212313 - Crushed and Broken Granite Mining and Quarrying This U.S. industry comprises: (1) establishments primarily engaged in developing the mine site, and/or mining

More information

Moving Ahead for Progress in the 21 st Century (MAP-21)

Moving Ahead for Progress in the 21 st Century (MAP-21) Streets and Freeways Subcommittee Meeting Moving Ahead for Progress in the 21 st Century (MAP-21) September 20, 2012 Metro s America Fast Forward Proposal Included in MAP-21 Act Enhances Transportation

More information

TD AMERITRADE Park Omaha

TD AMERITRADE Park Omaha TD AMERITRADE Park Omaha November 19, 2009 Report No. 6 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment

More information

CRENSHAW/LAX TRANSIT CORRIDOR PROJECT

CRENSHAW/LAX TRANSIT CORRIDOR PROJECT CRENSHAW/LAX TRANSIT CORRIDOR PROJECT A New Beginning for the Crenshaw Corridor Through Use of Innovative Procurement Strategies Robert Ball, P.E. and Kimberly Ong, P.E. Los Angeles Metropolitan Transportation

More information

APPLICATION LAFAYETTE METROPOLITAN PLANNING ORGANIZATION (MPO) SURFACE TRANSPORTATION PROGRAM (STP) FUNDS TRANSPORTATION IMPROVEMENT PROGRAM (TIP)

APPLICATION LAFAYETTE METROPOLITAN PLANNING ORGANIZATION (MPO) SURFACE TRANSPORTATION PROGRAM (STP) FUNDS TRANSPORTATION IMPROVEMENT PROGRAM (TIP) APPLICATION LAFAYETTE METROPOLITAN PLANNING ORGANIZATION (MPO) SURFACE TRANSPORTATION PROGRAM (STP) FUNDS TRANSPORTATION IMPROVEMENT PROGRAM (TIP) To be considered for STP funding, a proposed project must

More information

IH-635 MANAGED LANES PROJECT, SEG. 3.2

IH-635 MANAGED LANES PROJECT, SEG. 3.2 IH-635 MANAGED LANES PROJECT, SEG. 3.2 Location: Dallas, Texas Owner: Texas Department of Transportation Client: Ferrovial Agroman Construction Cost: $1 Billion Construction Completion Date: December,

More information

Mayors Welcome Strong Surrey Votes Yes Coalition Support. Yes Vote Would Vastly Improve Transit and Transportation in Fast Growing City

Mayors Welcome Strong Surrey Votes Yes Coalition Support. Yes Vote Would Vastly Improve Transit and Transportation in Fast Growing City Mayors Welcome Strong Surrey Votes Yes Coalition Support Yes Vote Would Vastly Improve Transit and Transportation in Fast Growing City February 11, 2015 Vancouver, BC The Mayors Council on Regional Transportation

More information

City of Valdosta Land Development Regulations. Table of Contents

City of Valdosta Land Development Regulations. Table of Contents TITLE 1 ADMINISTRATION Chapter 102 General Provisions 102-1 Title 102-2 Purpose 102-3 Authority 102-4 Jurisdiction 102-5 Application of Ordinance 102-6 Relationship to Existing Ordinances 102-7 Powers

More information

SEMINOLE PRATT WHITNEY ROAD & NORTHLAKE BLVD. FREQUENTLY ASKED QUESTIONS

SEMINOLE PRATT WHITNEY ROAD & NORTHLAKE BLVD. FREQUENTLY ASKED QUESTIONS UPDATED: 01/31/14 SEMINOLE PRATT WHITNEY ROAD & NORTHLAKE BLVD. FREQUENTLY ASKED QUESTIONS Q. 1. What are the County s plans for Seminole Pratt Whitney Road between SR 80 (Southern Blvd) and the Bee Line

More information

Street Audit Tool: Web 2.0 Tools

Street Audit Tool: Web 2.0 Tools Name: Email: Instructions: Auditor Information (1) Use all three tools for your assessment (2) If the tool can not determine the criteria, check (3) Indicate the tools used (4) Rate the effectiveness of

More information

Public Hearing. City Council Study Session. February 11, 2013

Public Hearing. City Council Study Session. February 11, 2013 Public Hearing City Council Study Session February 11, 2013 1 Staff Report Summarize the Overlay Conduct Public Hearing Council Discussion Schedule and Next Steps 2 2012-13 2007-2008 2013-2014 2013-2014

More information

Surface Transportation Program (STP)

Surface Transportation Program (STP) Project Name: Project Sponsor: FEDERAL FUNDS PROJECT APPLICATION TRANSPORTATION IMPROVEMENT PROGRAM 2008-2013 SALT LAKE and OGDEN/ LAYTON URBAN AREAS Surface Transportation Program (STP) Urban Surface

More information

Monitoring Highway Assets with Remote Technology

Monitoring Highway Assets with Remote Technology Monitoring Highway Assets with Remote Technology For the Michigan Department of Transportation July 2013 DYE MANAGEMENT GROUP, INC. Project Scope Summary of Technologies Aerial Imagery with LiDAR Mobile

More information

New Road 11.0m Asphalt 23m ROW

New Road 11.0m Asphalt 23m ROW New Road 11.0m Asphalt 23m ROW Granular A - 150 mm sq. m. $5.35 $69.53 Granular B - 300 mm sq. m. $7.35 $95.54 Concrete Curb and Gutter m. $44.67 $89.34 HL3 Asphalt - 40 mm sq. m. $7.66 $84.23 HL 4 or

More information

11 p.m. to. Tuesday, June. will remain open. 14. closed

11 p.m. to. Tuesday, June. will remain open. 14. closed June 3, 2011 CONTACT: Marcia McAllister T: 703 572 0506 C: 571 730 9117 marcia.mcallister@dullesmetro.com Important Lane Closures June 5 11 Include Northbound Beltway Lanes, Eastbound Dulles Airport Access

More information

EXHIBIT A Accessible Truck Routes Map

EXHIBIT A Accessible Truck Routes Map EXHIBIT A Accessible Truck Routes Map ASHEVILLE, NORTH CAROLINA ROUTE: A ROUTE: B ROUTE: C ROUTE: D ROUTE: E EXHIBIT A EXHIBIT B Craven Street Improvements Map ASHEVILLE, NORTH CAROLINA EXHIBIT B EXHIBIT

More information

South Greeley Highway Corridor: Main Street of South Cheyenne

South Greeley Highway Corridor: Main Street of South Cheyenne South Greeley Highway Corridor: Main Street of South Cheyenne South Cheyenne Community Development Association Adopted by the Laramie County Board of Commissioners, June 18, 2013 The South Cheyenne Community

More information

HIGHWAY DEPARTMENT ACCESS AND RIGHT OF WAY WIDTH GUIDELINES

HIGHWAY DEPARTMENT ACCESS AND RIGHT OF WAY WIDTH GUIDELINES Approved 6/26/01 HIGHWAY DEPARTMENT ACCESS AND RIGHT OF WAY WIDTH GUIDELINES All new, modified and/or changed use access(es) onto county roads shall be subject to the access and corridor protection guidelines

More information

Access Management South Dakota Department of Transportation

Access Management South Dakota Department of Transportation Public Meeting/ Open House October 21, 2014 Minnehaha County Environmental Assessment and Section 4(f) De Minimis Analysis Northern Segment of Hwy 100 I-90 to South of Madison Street Minnehaha County The

More information

Bond Release Process for New Subdivision Developments in Fairfax County

Bond Release Process for New Subdivision Developments in Fairfax County Bond Release Process for New Subdivision Developments in Fairfax County An Overview for Homeowners Associations A Fairfax County, Va., publication April 2009 For more information or to request this document

More information

Development Services Department City of San Antonio. Permits & Licenses. Development Services Manager. Deputy Historic Preservation Officer

Development Services Department City of San Antonio. Permits & Licenses. Development Services Manager. Deputy Historic Preservation Officer Development Services Department City of San Antonio Development Process 101 Permits & Licenses Michael Dice Development Services Manager Kathy Rodriguez Deputy Historic Preservation Officer 1 Permit &

More information

APPENDIX F:TRIPLE BOTTOM LINE ANALYSIS

APPENDIX F:TRIPLE BOTTOM LINE ANALYSIS APPENDIX F:TRIPLE BOTTOM LINE ANALYSIS Triple Bottom Line Analysis Map (TBLAM) Project or Decision: College Ave Corridor for FC Moves long range transportation plan for College Ave., for redevelopment

More information

Assessing Paved Trails for Compliance with Standards and Best Practices

Assessing Paved Trails for Compliance with Standards and Best Practices Assessing Paved Trails for Compliance with Standards and Best Practices Session Presenters: Kristin Maravilla, Planner/Designer Masters in Landscape Architecture (UC Berkeley) Masters in City and Regional

More information

MONTHLY MONITORING REPORT. World Trade Center Port Authority Trans-Hudson Terminal PORT AUTHORITY OF NEW YORK AND NEW JERSEY New York, New York

MONTHLY MONITORING REPORT. World Trade Center Port Authority Trans-Hudson Terminal PORT AUTHORITY OF NEW YORK AND NEW JERSEY New York, New York MONTHLY MONITORING REPORT World Trade Center Port Authority Trans-Hudson Terminal PORT AUTHORITY OF NEW YORK AND NEW JERSEY New York, New York January 2014 PMOC Contract Number: DTFT60-09-D-00008 Task

More information

Los Angeles Metro Rapid

Los Angeles Metro Rapid Los Angeles Metro Rapid Why BRT In Los Angeles Public dissatisfied with slow bus service Average bus speeds had declined by 10% since late- 1980s LADOT found that 50% of the time a bus is in service it

More information

Queens Midtown Tunnel Repair, Restoration, Rehabilitation Projects. Manhattan Community Board 6 Transportation Committee - June 2, 2014

Queens Midtown Tunnel Repair, Restoration, Rehabilitation Projects. Manhattan Community Board 6 Transportation Committee - June 2, 2014 Queens Midtown Tunnel Repair, Restoration, Rehabilitation Projects Manhattan Community Board 6 Transportation Committee - June 2, 2014 Opened to traffic in 1940 Two parallel tubes (North & South), each

More information

Exhibit A Scope of Work

Exhibit A Scope of Work Exhibit A Scope of Work The agreement for S.P. 3116-142 (T.H. 169-Cross Range Expressway) includes final design plans for a 1.55 mile length of a 2 lane to 4 lane expansion project located 0.66 miles SW

More information

APPENDIX K Capital Costs Methodology Report

APPENDIX K Capital Costs Methodology Report APPENDIX K Capital Costs Methodology Report September 2013 Capital Cost Estimating Report Table of Contents 1.0 Information... 5 1.1 Introduction... 5 1.2 Purpose and Goal... 5 2.0 Description of Project...

More information

CD i -STREETS- Detail #

CD i -STREETS- Detail # -STREETS- Detail # 3000 Vertical Curb, Gutter and Sidewalk 3010 Low-Profile Curb, Gutter and Sidewalk 3020 Rolled Curb, Gutter and Sidewalk 3030 Separated Sidewalk, Curb & Gutter 3040 Sidewalk Staged Construction

More information

Developer s/consultants Field Services Guidelines

Developer s/consultants Field Services Guidelines Developer s/consultants Field Services Guidelines 2007 Engineering and Works Department DEVELOPER S/CONSULTANT S FIELD SERVICES GUIDELINES Fourth Electronic Edition February 2007 STATEMENT OF COMPLETION

More information

Transit, Rail, Program, Project & Construction Management Experience

Transit, Rail, Program, Project & Construction Management Experience Point of Contact Peter M. Cipolla Vice President, Rail & Transit Mobile: 925.219.5235 Email: peter.cipolla@hatchmott.com Project Management Oversight Services Introduction & Background Hatch Mott MacDonald

More information

Wilmington to Newark Commuter Rail Improvement Project

Wilmington to Newark Commuter Rail Improvement Project Wilmington to Newark Commuter Rail Improvement Project The Delaware Transit Corporation (DTC), a subsidiary of the Delaware Department of Transportation (DelDOT), is undertaking a rail capacity expansion

More information

Seattle Public Schools Building Excellence IV Projects Under Construction

Seattle Public Schools Building Excellence IV Projects Under Construction Seattle Public Schools Building Excellence IV Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee

More information

SOLD. Lot 1. 1 Mile: Population: 10,200 Median HH Income: $33,100. 3 Mile: Population: 80,200 Median HH Income: $34,900

SOLD. Lot 1. 1 Mile: Population: 10,200 Median HH Income: $33,100. 3 Mile: Population: 80,200 Median HH Income: $34,900 Walmart Outparcels For Sale College Station, TX Store # 1150 1815 Brothers Blvd FM 2818 W SOLD Texas Ave S/ Hwy 6 Longmire Dr Brothers Blvd Lot 1 For more information about this site, contact: Lot 1: ±2.41

More information

The work has continued on final Phase 4 and is nearing completion.

The work has continued on final Phase 4 and is nearing completion. Updates-January 22, 2013 29369-Rehab Plaza Deck/Drainage Budget: $18,000,000, constr. Start 8/2009 The work has continued on final Phase 4 and is nearing completion. The main plaza area of phase 4 is now

More information

FIRE RESTORATION-REBUILD PROCESS SANTA BARABARA GETTING STARTED:

FIRE RESTORATION-REBUILD PROCESS SANTA BARABARA GETTING STARTED: FIRE RESTORATION-REBUILD PROCESS SANTA BARABARA INSURANCE GETTING STARTED: 1. Contact Insurance Company meeting with insurance adjuster to get funds for the rebuilding process started. 2. Set up a construction

More information

Jewish Home Lifecare, Manhattan Replacement Nursing Facility Project. DEIS Public Hearing May 7 and May 8, 2014

Jewish Home Lifecare, Manhattan Replacement Nursing Facility Project. DEIS Public Hearing May 7 and May 8, 2014 Jewish Home Lifecare, Manhattan Replacement Nursing Facility Project DEIS Public Hearing May 7 and May 8, 2014 Project Program Illustrative Site Plan and Stack Diagram SEQR Assessment SEQR DEIS follows

More information

Figure 4-21. L3: Level 2 SR 99 Elevated Light Rail Alternative Detail - 1 of 4

Figure 4-21. L3: Level 2 SR 99 Elevated Light Rail Alternative Detail - 1 of 4 4-34 SEE FIGURE 4-22 N 14TH ST ROOSEVELT WAY N 130th Street N 130TH ST NE NORTHGATE WAY N 0 1/4 Miles Elevated Light Rail At-Grade Light Rail Elevated Light Rail Station At-Grade Light Rail Station Figure

More information

PART II SCHEDULE. Scope of Services. Special Terms and Conditions. Virginia Railway Express

PART II SCHEDULE. Scope of Services. Special Terms and Conditions. Virginia Railway Express PART II SCHEDULE SECTION TITLE D E Scope of Services Special Terms and Conditions 11 SECTION D SCOPE OF SERVICES D.1 OVERVIEW A. The selected firm is referred to herein as either the Consultant or the

More information

Update on Previous Related Transportation Enhancement Grants

Update on Previous Related Transportation Enhancement Grants ROUND 16 ROUND 16 Update on Previous Related Transportation Enhancement Grants Pima County and City of Tucson staff are implementing the Pima County-Tucson Safe Routes to Schools Pilot Program. This program

More information

Guiding Principles. McCauley Area Focused Urban Design Plan. 1 Connect: Chinatown and Little Italy with downtown and surrounding areas

Guiding Principles. McCauley Area Focused Urban Design Plan. 1 Connect: Chinatown and Little Italy with downtown and surrounding areas McCauley Area Guiding Principles 1 Connect: Chinatown and Little Italy with downtown and surrounding areas 2 Strengthen: Cultural character in Chinatown and Little Italy 3 Develop: Strong East West pedestrian

More information

I-66 Pavement Rehabilitation

I-66 Pavement Rehabilitation I-66 Pavement Rehabilitation Fall Asphalt Conference Richmond, VA David Shiells, P.E. Virginia Department of Transportation David White Superior Paving Corporation October 2, 2012 Project Location 2 Goal

More information

Maintenance Management and Asset Management

Maintenance Management and Asset Management Defining and Understanding the Difference Between Maintenance Management and Asset Management Dr. Simon Lewis AgileAssets, Inc. 12th AASHTO-TRB Maintenance Management Conference Annapolis Maryland, July

More information

How To Manage Transportation Asset Management

How To Manage Transportation Asset Management 1 TRANSPORTATION ASSET MANAGEMENT THE NEW BUSINESS MODEL FOR TRANSPORTATION AGENCIES Presented at the AASHTO Subcommittee on Transportation Finance Policy Business Meeting Irvine, California June 26, 2012

More information

in Marina Del Rey Prepared by: County of Los Angeles Department of Public Works

in Marina Del Rey Prepared by: County of Los Angeles Department of Public Works Planned Public Works Projects in Marina Del Rey Prepared by: County of Los Angeles Department of Public Works Planned Projects in Marina Del Rey Waterline Projects Phase II Phase III Roadway Projects Admiralty

More information

COPPER BEECH TOWNHOME DEVELOPMENT

COPPER BEECH TOWNHOME DEVELOPMENT COPPER BEECH TOWNHOME DEVELOPMENT This 28 acre, 30 Townhome development is slated to open doors in time for the 2007 2008 college school year. To accommodate this project s tight time line, Dennis Corporation

More information

Engineering Standard

Engineering Standard Public Transport Services Engineering Standard Stations - Bicycle Facilities PART 129013 AR-PW-PM-SPE-00129013 (D073) Document Control Document Status Document Amendment Record Revision Change Description

More information

Revere Beach Transit-Oriented Development Parcels Revere, Massachusetts. Design and Development Guidelines. Part Two.

Revere Beach Transit-Oriented Development Parcels Revere, Massachusetts. Design and Development Guidelines. Part Two. Revere Beach Transit-Oriented Development Parcels Revere, Massachusetts Design and Development Guidelines Request for Qualifications and Expressions of Interest with Preliminary Development Plans Part

More information

Draft Non Transportation Performance Measures Including Related Qualitative Assessment of Example Sections

Draft Non Transportation Performance Measures Including Related Qualitative Assessment of Example Sections Draft Non Transportation Performance Measures Including Related Qualitative Assessment of Example Sections Phil Erickson Community Design + Architecture Mike Johnson HDR Engineering CTF Charrette Approach

More information

MAIN STREET IMPROVEMENTS Water, Sewer, Stormwater and Streetscape Improvements

MAIN STREET IMPROVEMENTS Water, Sewer, Stormwater and Streetscape Improvements MAIN STREET IMPROVEMENTS Water, Sewer, Stormwater and Streetscape Improvements Presentation July 23, 2014 A. Morton Thomas and Associates, Inc. 800 King Farm Boulevard, 4 th Floor Rockville, Maryland 20850

More information

Pavement Management Program

Pavement Management Program Pavement Management Program 2013 Street Maintenance Program Executive Summary 1/15/2013 Presented by Mark Thiel Assistant Director Public Works Program Overview Start of current program 2005 812.5 Lane

More information

to imagine a transportation vision

to imagine a transportation vision to imagine a transportation vision Before 2007 many wondered Was collaboration and coalition building even possible in Los Angeles County? Creating the Measure R coalition sent a new message This is how

More information

Hyperlinks are Inactive

Hyperlinks are Inactive Prepared by: NIB/EOB PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES 05503 Department: Electric T&D Section: T&D Engineering and Technical Support Approved by: G.O. Duru (GOD)

More information

Smart Cycling IN SANTA MONICA SANTA MONICA POLICE DEPARTMENT BE SMART. BE VISIBLE. BE ATTENTIVE. HAVE FUN!

Smart Cycling IN SANTA MONICA SANTA MONICA POLICE DEPARTMENT BE SMART. BE VISIBLE. BE ATTENTIVE. HAVE FUN! Smart Cycling IN SANTA MONICA BE SMART. BE VISIBLE. BE ATTENTIVE. HAVE FUN! Safety Tips and Rules of the Road for Cyclists SANTA MONICA POLICE DEPARTMENT Rules of the Road Drivers, bicyclists, and pedestrians

More information