Effective Pre-Commissioning planning and initiation of PC. A Checklist for Pre-Commissioning of Offshore Facilities

Size: px
Start display at page:

Download "Effective Pre-Commissioning planning and initiation of PC. A Checklist for Pre-Commissioning of Offshore Facilities"

Transcription

1 A Checklist for Pre-Commissioning of Offshore Facilities Effective Pre-Commissioning planning and initiation of PC activities provide a necessary bridge between earlier project execution phases, including Mechanical Completion, and the final commissioning and startup of the facility. PC can be an essential mark between the transition from a discipline-based approach to one that verifies the functionality of systems, regardless of their location on the facility. The planning required for an efficient Pre-Commissioning (PC) of an offshore facility is typically started during the early stages of detail design and commences immediately after Mechanical Completion (MC) has been achieved, which itself follows the engineering design and construction phases. Prior to initiating the PC actual work stage, the supervisor of the MC phase creates a formal document transferring the complete dossier of all activity of the system for handover to the Pre-Commissioning team, along with a register or punchlist that indicates any remaining MC work that still needs to be completed or closed out. Pre-Commissioning is Systems Driven Whereas Mechanical Completion includes the non-functional testing of equipment to confirm the integrity of its fabrication and installation to the intended design, Pre-Commissioning verifies the mechanical completion, the functionality of the system as well as calibration of the instrumentation to the facilities controls and control systems. While MC is completed by area or discipline, the Pre-Commissioning phase will be turned over to specialists who can address confirmation by system, ensuring that it is complete and ready for final Commissioning and startup. This phase can best commence efficiently after all of the components are in place so that systems, rather than individual pieces, can be verified. The PC contractor also engages the design engineering firm, vendors, manufacturers and operating personnel for support and their expertise. During the Pre-Commissioning effort, there can be many activities completed during the onshore phase and then moved offshore for completion of the system check-out. Where

2 Pre-commissioning addresses readiness by system rather than by individual pieces of equipment.

3 practical, piping should be power flushed and dried; communication systems tested to the fullest extent possible; instrument and electrical loops will be verified; instruments will undergo initial and final calibration; pumps can be operated where possible; motors verified for proper rotation and can be run and tested (burned in); and rotating equipment can receive initial (cold) alignments. The Pre-Commissioning phase is vital to schedule adherence of the project and a necessity in helping to minimize cost overruns. Ideally, PC activities should be planned as part of the construction and earlier project execution strategy so there can be a smooth transition from structural, mechanical, electrical, instrumentation and controls fabrication to systems checks where scheduled work is maximized. This time in the project is when potential flaws of construction, uncompleted tasks and system inadequacies can come to light and be addressed early enough to minimize schedule delays. Without a thorough Pre-Commissioning effort, potentially time-consuming and expensive modifications can go undone onshore, only to be addressed in a much more difficult offshore environment. Organization and Planning Are Key The selection of a Pre-Commissioning team is one of the most important milestones that will need to be addressed. The team will be responsible for planning and supplying the critical support and leadership during this project phase. The leadership as well as team members should, therefore, be experienced with the planning, tasks, schedule and project drivers regarding startup, as well as its complexities. After the project has determined the Scope of Work, the overall project schedule and startup drivers, an organization chart needs to be established, defining the overall hierarchy of how the PC team fits within the overall project management team. Additionally, a roles and responsibilities matrix required for the upcoming activities should be established. There will need to be separate designators in organizational charts created indicating location for the onshore and offshore PC work due to potential differences in contractual arrangements, transportation, personnel housing, parts availability and numerous other issues. Only after the scope of The pre-commissioning team is vital to maintaining project schedule

4 work and organizational plan is in place can the initial schedule be prepared, establishing the critical milestones for handing off systems to the commissioning and operations teams. These milestones are often how the PC team and their progress will be measured. The responsibility matrix is important to complement the organization definitions. The level of the matrices vary from broad to detailed, but its main use is to identify not only the scope of work and supply, but also the responsibility and Simultaneous Operations (SIMOPs) which may occur. For the purpose of this discussion, getting to the matrix level of PC and MC interface, along with the other SIMOPs is wise early enough to best identify any potential holes during the different phases of work. As discussed previously, identifying the location of the PC work plays an important role in the responsibility of certain activities and interfaces. For example, due to contractual limitations as well as schedule drivers, the onshore MC work will take priority and the facility where the work is being performed would be the driver. Whereas offshore the MC work may still be the priority, however the driver would be the Operator. The matrix, therefore, can identify not only the task but the responsibility of the work, whereas the details of the work are identified within the PC procedures and tracking database. In the initial planning of the PC stage, a critical path should be evaluated to establish the procedures that will be optimal to success. Although the best laid plans always have their obstacles, a plan must be established as a starting point. A detailed list of required activities would be created by the PC team and coupled with the data developed earlier in the project by engineering and managed through an electronic project information management system. The PC contractor is responsible for maintaining the data base, tracking progress critical for adhering to schedule and determining the status of the various activities. Reference data provided by engineering and the other delivery teams will need to be organized by the PC contractor according to the identified systems and should reside in a location accessible to all who will be utilizing it. Data includes, but is not limited to, PFDs, P&IDs, mechanical, electrical motor and ISA data sheets, instrument and electrical loop drawings, wiring plans and elevations for skids and modules, as well as the manufacturer s final data manuals for purchased equipment. A potential shortcoming is in not obtaining the interface data from outside of the topsides delivery team, e.g. subsea, export pipeline, communications, hull fabricators equipment. The key will be to provide a conscious effort to close these gaps early within the project so as not to impact the planned startup date. Successful PC work relies on detailed planning and defined responsibilities The PC work normally is broken down into discreet, manageable systems. The systems are separated according to the logical process flow, rather than by a package vendor. For example, a heat media system might include a fired unit, heat recovery unit, storage unit and pumps, along with interconnect piping, instrumentation, controls and electrical, all of which have likely been supplied by different vendors and reside on separate skids. This systems breakdown is the logical process to verify construction, confirm the integrity of the design, and prepare the system for handover to operations as the phase goes forward. The organization also allows for the commissioning of sub-systems within a system, without having to initiate work on the entire system. This avoids having to work around a finish to start on a system scenario, thus pushing the overall startup schedule past the desired outcome. The PC of utility systems is typically the first to be addressed and completed. This allows life support for the offshore personnel in addition to minimizing the need for additional components to PC the process systems later.

5 It is essential that good record keeping and a detailed preventative maintenance plan be initiated and carried out through handover to operations during the PC phase. A job or activity card system is an output of the existing database system, resulting as an archive to the work performed as an as built record. Task sheets record the subsystems and systems which have been completely pre- commissioned and ready for handover to be integrated into the facilities operating systems. In the overall PC work plan and prior to initiating the PC work, a meeting schedule should be established so that overall planning and progress can be regularly discussed and understood by all parties. Each of the participants should have a schedule that can be owned by them, reviewed intermittently by the team and adjusted accordingly, so that progress coincides among all team members. The critical path should be reviewed at a minimum weekly and recovery plans generated or updated as necessary. Deck space and personnel management are a critical part of offshore PC activities POB Management An important consideration in Pre-Commissioning is planning for the required number of personnel needed to undertake the offshore PC activities, the transportation requirements for the crews and their supplies, and the allocated personnel on board (POB) space to accommodate them. While working during the onshore phase space is somewhat unlimited with the exception of interfaces with Construction, offshore work presents a whole different set of challenges. Offshore, the PC team will have to work closely with all of the different work scopes onboard to understand each other s schedules and manpower requirements. These would include topsides Hookup and Commissioning (HUC), subsea flowline installation and testing contractors, and the export pipeline installation and testing contractors, as well as 3rd party vendors, communications personnel and Operations. During the offshore phase, depending upon timing and the hull type, a habitability inspection will be conducted by the U.S. Coast Guard or similar regulatory body. The work plan shall include in the overall schedule identifying work onshore, work offshore, work to achieve quarters habitation, Temporary Certificate of Inspection (TCOI), Final Certificate of Inspection (COI), and Handover to Operations. A variety of systems must be carefully planned for and put in place in order for approval of these various milestones. For TCOI these may include sufficient living quarters; temporary power generation; fire fighting, fire detection and suppression equipment; emergency evacuation equipment; potable water and sewage treatment provisions; and communications equipment. Planning for and precisely scheduling manpower is critical. If sufficient facilities are not available on the platform, floatels or other means for housing personnel might be required at a significant extra cost. The critical nature of the work being performed offshore compared with the other activities along with the schedule must be evaluated in depth to determine the cost/schedule benefit and work plan for utilizing a flotel. This also means weather limitations and transfer of personnel risks must be evaluated. Similarly, working space and delivery areas must be closely planned to accommodate the simultaneous operations (SIMOPS) being conducted during the pre-commissioning and subsequent commissioning operations. Conclusion In order for the PC segment to be successful, a good and detailed Pre-Commissioning/Commissioning plan should be developed, as early in the project as possible and good interface between all groups must be established. An experienced team, equipped with the necessary tools, data base, organizational structure, defined responsibilities and procedures, can assure that the Pre-Commissioning segment is efficient and can keep costs and schedule in-line with expectations. For more information concerning Mustang s capabilities in Mechanical Completion and Pre-Commissioning/Commissioning, contact Richard Shirley or Dan Vela at richard.shirley@ mustangeng.com or dan.vela@mustangeng.com.

TRANSNET PIPELINES. TPL 25 Tarlton Commissioning Plan

TRANSNET PIPELINES. TPL 25 Tarlton Commissioning Plan TPL 25 Tarlton Commissioning Plan Issue Date: 03/07/2015 Revision No.: A Project No.: 11992 Date: 03/07/2015 Document Title: TPL25 Tarlton Commissioning Plan Author: Edward Standen Revision Number: A Checked

More information

& Start-up Directory

& Start-up Directory & Start-up Directory INTEGRATED SERVICE SOLUTIONS Index C H A P T E R 1 INTRODUCTION 4 C H A P T E R 2 COMMISSIONING & START UP SERVICE 5 2.1 Standard Implementation Path 6 2.2 The Home Office Phase 7

More information

PROJECT AND CONSTRUCTION MANAGEMENT SERVICES FOR KUWAIT PORT AUTHORITY FOR PROJECTS AT SHUAIBA PORT

PROJECT AND CONSTRUCTION MANAGEMENT SERVICES FOR KUWAIT PORT AUTHORITY FOR PROJECTS AT SHUAIBA PORT PROJECT AND CONSTRUCTION MANAGEMENT SERVICES FOR KUWAIT PORT AUTHORITY FOR PROJECTS AT SHUAIBA PORT - INTRODUCTION 1.1. General. Kuwait Ports Authority (KPA) through the Ministry Of Finance (MOF) wishes

More information

Statement of Work. 3.0 Details of Service Pre Start-up. - 1 - Cooling Start-up Service. Installation Service. Table of Contents. 1.0 Executive Summary

Statement of Work. 3.0 Details of Service Pre Start-up. - 1 - Cooling Start-up Service. Installation Service. Table of Contents. 1.0 Executive Summary Installation Service Statement of Work - 1 - Cooling Start-up Service Cooling Start-up Service Service 1.0 Executive Summary Table of Contents 1.0 Executive Summary 2.0 Features & Benefits 3.0 Details

More information

Mechanical Installation

Mechanical Installation Page -1-1. INTRODUCTION AND PURPOSE 1.1. This specification covers the installation, testing and precommissioning of mechanical equipment. Work is to be performed in conjunction with the manufacturer s

More information

Backup Fuel Oil System Decommissioning & Restoration Plan

Backup Fuel Oil System Decommissioning & Restoration Plan Backup Fuel Oil System Page 1 of 19 Overview of Physical Fuel Oil System and Decommissioning Steps The fuel oil system at Milford Power consists of a number of subsystems. These include the following:

More information

TEST MANAGEMENT SOLUTION Buyer s Guide WHITEPAPER. Real-Time Test Management

TEST MANAGEMENT SOLUTION Buyer s Guide WHITEPAPER. Real-Time Test Management TEST MANAGEMENT SOLUTION Buyer s Guide WHITEPAPER Real-Time Test Management How to Select the Best Test Management Vendor? The implementation of a Test Management system to automate business processes

More information

Expert Reference Series of White Papers. Intersecting Project Management and Business Analysis

Expert Reference Series of White Papers. Intersecting Project Management and Business Analysis Expert Reference Series of White Papers Intersecting Project Management and Business Analysis 1-800-COURSES www.globalknowledge.com Intersecting Project Management and Business Analysis Daniel Stober,

More information

Building Commissioning 17900-1

Building Commissioning 17900-1 SECTION 17900 BUILDING COMMISSIONING PART 1 - GENERAL 1.01 WORK DESCRIPTION: A. General: 1. The Commissioning process is a joint team effort to ensure that all mechanical equipment, controls, and systems

More information

Project organisation and establishing a programme management office

Project organisation and establishing a programme management office PROJECT ADVISORY Project organisation and establishing a programme office Leadership Series 1 kpmg.com/nz About the Leadership Series KPMG s Leadership Series is targeted towards owners of major capital

More information

Operational Excellence Management System

Operational Excellence Management System Operational Excellence Management System Operational Excellence Management System FTO Services is committed to conducting business in a manner that is compatible with the environmental and economic needs

More information

A. The Commissioning Authority (CxA) has been contracted or will be contracted directly with the Owner for this project.

A. The Commissioning Authority (CxA) has been contracted or will be contracted directly with the Owner for this project. DIVISION 23 HEATING, VENTILATING, AND AIR CONDITIONING (HVAC) SECTION 23 08 02 PART 1 GENERAL 1.01 AUTHORITY (CxA) A. The Commissioning Authority (CxA) has been contracted or will be contracted directly

More information

How To Manage A Project

How To Manage A Project Project Management - Maintenance Management p. 105 to 112 Project Management - Maintenance Management PGP / OCP-E PGP / OCP Project Management Major Grassroots Projects 5 Days Level: Foundation To provide

More information

Total Subsea Services

Total Subsea Services Total Subsea Services Customer Support FMC Customer Support provides service and strategic life of field planning and solutions designed to deliver immediate and long-term satisfaction to operators worldwide.

More information

LONG INTERNATIONAL. Andrew Avalon, P.E., PSP and Curtis W. Foster

LONG INTERNATIONAL. Andrew Avalon, P.E., PSP and Curtis W. Foster Andrew Avalon, P.E., PSP and Curtis W. Foster LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com

More information

OPITO APPROVED STANDARD. Offshore Muster Coordinator. (Competence Assessment Standard - Industry Guidance)

OPITO APPROVED STANDARD. Offshore Muster Coordinator. (Competence Assessment Standard - Industry Guidance) OPITO APPROVED STANDARD (Competence Assessment Standard - Industry Guidance) OPITO is an Industry owned not for profit organisation that exists solely to service the needs of the Oil and Gas Industry.

More information

Practical Experience Requirements Initial Professional Development for Professional Accountants

Practical Experience Requirements Initial Professional Development for Professional Accountants International Accounting Education Standards Board AGENDA ITEM 2-3 Revised Draft of IEPS(Clean Version) Proposed International Education Practice Statement Practical Experience Requirements Initial Professional

More information

Proven Best Practices for a Successful Credit Portfolio Conversion

Proven Best Practices for a Successful Credit Portfolio Conversion Proven Best Practices for a Successful Credit Portfolio Conversion 2011 First Data Corporation. All trademarks, service marks and trade names referenced in this material are the property of their respective

More information

The Job of the Project Manager. Robert Youker World Bank (retired) 5825 Rockmere Drive Bethesda, Md. USA 20816 bobyouker@worldnet.att.

The Job of the Project Manager. Robert Youker World Bank (retired) 5825 Rockmere Drive Bethesda, Md. USA 20816 bobyouker@worldnet.att. The Job of the Project Manager Robert Youker World Bank (retired) 5825 Rockmere Drive Bethesda, Md. USA 20816 bobyouker@worldnet.att.net For any organization and for any project manager it is vitally important

More information

BNA FEDERAL CREDIT UNION DISASTER RECOVERY PLAN

BNA FEDERAL CREDIT UNION DISASTER RECOVERY PLAN BNA FEDERAL CREDIT UNION DISASTER RECOVERY PLAN INTRODUCTION The need for a contingency plan for business interruptions is vital to the operations of the BNA Federal Credit Union. Without such a plan,

More information

05-15-98 ELECTRICAL ENGINEERING ASSOCIATE, 7525

05-15-98 ELECTRICAL ENGINEERING ASSOCIATE, 7525 CITY OF LOS ANGELES CIVIL SERVICE COMMISSION CLASS SPECIFICATION POSTED JUNE 1999 05-15-98 ELECTRICAL ENGINEERING ASSOCIATE, 7525 Summary of Duties: Performs professional electrical engineering work in

More information

CHAPTER 5 - SAFETY ASSESSMENTS, LOG OF DEFICIENCIES AND CORRECTIVE ACTION PLANS

CHAPTER 5 - SAFETY ASSESSMENTS, LOG OF DEFICIENCIES AND CORRECTIVE ACTION PLANS CHAPTER 5 - SAFETY ASSESSMENTS, LOG OF DEFICIENCIES AND CORRECTIVE ACTION PLANS A. INTRODUCTION... 1 B. CHAPTER-SPECIFIC ROLES AND RESPONSIBILITIES... 1 C. SAFETY PROGRAM ASSESSMENT PROCESS... 3 D. FACILITY-MAINTAINED

More information

SC21 Manufacturing Excellence. Process Overview

SC21 Manufacturing Excellence. Process Overview SC21 Manufacturing Excellence Process Overview Prepared by:- The SC21 Performance, Development and Quality (PDQ) Special Interest Group (SIG) Acknowledgement The scoring methodology used in the Management

More information

Roles and Responsibilities of Plant Commissioning, Hydrocarbon Introduction and Acceptance Test Run

Roles and Responsibilities of Plant Commissioning, Hydrocarbon Introduction and Acceptance Test Run Page 1 of 8 Introduction Roles and Responsibilities of Plant Commissioning, Hydrocarbon Introduction and Acceptance Test Run There are many parts of a grass root chemical plant construction. They include

More information

Guidelines for a PROJECT EXECUTION PLAN

Guidelines for a PROJECT EXECUTION PLAN Guidelines for a PROJECT EXECUTION PLAN 1. OBJECTIVES The objectives of this guideline are: To provide a standard template for Project Execution Plans (PEP); To identify the critical items which need to

More information

PLANNING FOR YOUR PROJECT

PLANNING FOR YOUR PROJECT PLANNING FOR YOUR PROJECT This tool kit has been designed to provide an introduction to planning. It will help you to think about the reasons behind why you should plan, what to plan and the variations

More information

PROGRAM CRITERIA FOR ELECTRICAL ENGINEERING TECHNOLOGY

PROGRAM CRITERIA FOR ELECTRICAL ENGINEERING TECHNOLOGY PROGRAM CRITERIA FOR ELECTRICAL ENGINEERING TECHNOLOGY Scope These program criteria apply to programs having titles involving Electrical Engineering Technology including: electrical engineering, electrical

More information

POLICY ON OCCUPATIONAL HEALTH AND SAFETY RISK MANAGEMENT

POLICY ON OCCUPATIONAL HEALTH AND SAFETY RISK MANAGEMENT THE NORTHCOTT SOCIETY POLICY ON OCCUPATIONAL HEALTH AND SAFETY RISK MANAGEMENT VOLUME: 2 Policy on Management and Organisational Issues SECTION: B Occupational Health & Safety & Workers Compensation SUB-SECTION:

More information

Optimizing Mega Project Execution with Integrated Interface Management and Project Scheduling

Optimizing Mega Project Execution with Integrated Interface Management and Project Scheduling Optimizing Mega Project Execution with Integrated Interface Management and Project Scheduling By: Sandra MacGillivray VP, Product & Marketing 519-772-3181 Introduction In today s mega projects, implementing

More information

The PNC Financial Services Group, Inc. Business Continuity Program

The PNC Financial Services Group, Inc. Business Continuity Program The PNC Financial Services Group, Inc. Business Continuity Program 1 Content Overview A. Introduction Page 3 B. Governance Model Page 4 C. Program Components Page 4 Business Impact Analysis (BIA) Page

More information

AGILE - QUICK GUIDE AGILE - PRIMER

AGILE - QUICK GUIDE AGILE - PRIMER AGILE - QUICK GUIDE http://www.tutorialspoint.com/agile/agile_quick_guide.htm Copyright tutorialspoint.com AGILE - PRIMER Agile is a software development methodology to build a software incrementally using

More information

Off-the-Shelf Software: A Broader Picture By Bryan Chojnowski, Reglera Director of Quality

Off-the-Shelf Software: A Broader Picture By Bryan Chojnowski, Reglera Director of Quality Off-the-Shelf Software: A Broader Picture By Bryan Chojnowski, Reglera Director of Quality In the past decade, there has been a sea change in the business software domain. Many companies are no longer

More information

Project Management. On-Site Training and Facilitation Services. www.performanceweb.org. For more information, visit

Project Management. On-Site Training and Facilitation Services. www.performanceweb.org. For more information, visit Project Management On-Site Training and Facilitation Services For more information, visit www.performanceweb.org Benefits of On-Site Training The Performance Institute s proven consulting methodology is

More information

Quality Assurance - Karthik

Quality Assurance - Karthik Prevention is better than cure Quality Assurance - Karthik This maxim perfectly explains the difference between quality assurance and quality control. Quality Assurance is a set of processes that needs

More information

ITS specification Handover and commissioning process (ITS-10-01)

ITS specification Handover and commissioning process (ITS-10-01) ITS specification Handover and commissioning process (ITS-10-01) NZ Transport Agency Effective from September 2011 Copyright information This publication is copyright NZ Transport Agency (NZTA). Material

More information

Guide to: Successful Customer Onboarding

Guide to: Successful Customer Onboarding Guide to: Successful Customer Onboarding Getting Started The first 90 days will decide the fate of most implementations. While the complexity of your product could shift the timeline, if a customer feels

More information

Application development = documentation processing

Application development = documentation processing Application development = documentation processing Software is documented information about activities, that can be transformed into executable computer instructions performing the activities as documented.

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 903 CONSTRUCTION QC/QA PROGRAM

San Antonio Water System Standard Specifications for Construction ITEM NO. 903 CONSTRUCTION QC/QA PROGRAM ITEM NO. 903 CONSTRUCTION QC/QA PROGRAM 903.1 DESCRIPTION: This item shall govern the preparation and implementation of the Contractor s Construction Quality Control/Quality Assurance (QC/QA) Program for

More information

Managing Successful Software Development Projects Mike Thibado 12/28/05

Managing Successful Software Development Projects Mike Thibado 12/28/05 Managing Successful Software Development Projects Mike Thibado 12/28/05 Copyright 2006, Ambient Consulting Table of Contents EXECUTIVE OVERVIEW...3 STATEMENT OF WORK DOCUMENT...4 REQUIREMENTS CHANGE PROCEDURE...5

More information

Guidelines for FEASIBILITY STUDY

Guidelines for FEASIBILITY STUDY Guidelines for FEASIBILITY STUDY INTRODUCTION This document describes the best practices to be followed during the preparation of a Feasibility Study for the Facilities Development of an upstream asset.

More information

3 SYSTEM DEVELOPMENT METHODOLOGIES

3 SYSTEM DEVELOPMENT METHODOLOGIES 3 SYSTEM DEVELOPMENT METHODOLOGIES 3.1 INTRODUCTION Different types of system development methodologies are used in designing information system. Depending upon the actual requirement of the system, different

More information

COMMISSIONING OF FIRE ALARM SYSTEMS

COMMISSIONING OF FIRE ALARM SYSTEMS COMMISSIONING OF FIRE ALARM SYSTEMS OWNER FURNISHED The owner directly contracts an independent third party commissioning agent for this project. This Commissioning Plan has been included for reference

More information

Facility Maintenance Management Competency 4.9

Facility Maintenance Management Competency 4.9 Competency 4.9 Facility maintenance management personnel shall demonstrate the ability to perform project management duties as required to provide facility maintenance management technical support to a

More information

Agile Project Execution

Agile Project Execution ebook Agile Project Execution The future of Industrial Process Automation projects v1.4 EMK(VDS)-TR-EB-01 APEX ebook Table of Contents Intro Agile Project Execution Page 2. Chapter 1 Conventional Project

More information

IMPLEMENTATION NOTE. Validating Risk Rating Systems at IRB Institutions

IMPLEMENTATION NOTE. Validating Risk Rating Systems at IRB Institutions IMPLEMENTATION NOTE Subject: Category: Capital No: A-1 Date: January 2006 I. Introduction The term rating system comprises all of the methods, processes, controls, data collection and IT systems that support

More information

Implementing ERP in Small and Mid-Size Companies

Implementing ERP in Small and Mid-Size Companies Implementing ERP in Small and Mid-Size Companies This is an excerpt from the April 1, 2001 issue of CIO Magazine ERP Implementation in 10 Easy Steps. 1. Ask the board of directors for an arbitrary but

More information

Compliance Focused Preapproval Preparation Program. By Mike Ronningen, RAC

Compliance Focused Preapproval Preparation Program. By Mike Ronningen, RAC Compliance Focused Preapproval Preparation Program By Mike Ronningen, RAC 14 July 2011 Submitting a Premarket Approval Application (PMA) for a Class III medical device to the US Food and Drug Administration

More information

msd medical stores department Operations and Sales Planning (O&SP) Process Document

msd medical stores department Operations and Sales Planning (O&SP) Process Document msd medical stores department Operations and Sales Planning (O&SP) Process Document August 31, 2011 Table of Contents 1. Background... 3 1.1. Objectives... 3 1.2. Guiding Principles... 3 1.3. Leading Practice...

More information

GE Oil & Gas. Industrial modules. Turnkey power-generation and compression solutions to increase efficiency, reliability & power in restrictive areas

GE Oil & Gas. Industrial modules. Turnkey power-generation and compression solutions to increase efficiency, reliability & power in restrictive areas GE Oil & Gas Industrial modules Turnkey power-generation and compression solutions to increase efficiency, reliability & power in restrictive areas Industrial modules Modern oil and gas operations must

More information

1.040 Project Management

1.040 Project Management MIT OpenCourseWare http://ocw.mit.edu 1.040 Project Management Spring 2009 For information about citing these materials or our Terms of Use, visit: http://ocw.mit.edu/terms. Fred Moavenzadeh Spring 2009

More information

www.ntos.no Hydraulic Solutions keep your operations running specialist services

www.ntos.no Hydraulic Solutions keep your operations running specialist services www.ntos.no Hydraulic Solutions keep your operations running specialist services rental products MAINTAINS A HIGH LEVEL OF PERFORMANCE NTOS designs and installs hydraulic solutions for the international

More information

Nothing in this job description restricts management's right to assign or reassign duties and responsibilities to this job at any time.

Nothing in this job description restricts management's right to assign or reassign duties and responsibilities to this job at any time. T47400A, page 1 Nothing in this job description restricts management's right to assign or reassign duties and responsibilities to this job at any time. DUTIES Serves as the planner/scheduler for the Utilities

More information

PRINCE2:2009 Glossary of Terms (English)

PRINCE2:2009 Glossary of Terms (English) accept (risk response) acceptance acceptance criteria activity agile methods approval approver assumption assurance A risk response to a threat where a conscious and deliberate decision is taken to retain

More information

PROJECT MANAGEMENT PLAN CHECKLIST

PROJECT MANAGEMENT PLAN CHECKLIST PROJECT MANAGEMENT PLAN CHECKLIST The project management plan is a comprehensive document that defines each area of your project. The final document will contain all the required plans you need to manage,

More information

Section Five Learning Module D:

Section Five Learning Module D: Section Five Learning Module D: the Project 5.1 Module D: Objectives At the conclusion of this module you will be able to: implement a project plan; keep control of a project plan; effectively review a

More information

Guide to Successful Program Management

Guide to Successful Program Management RG Perspective Guide to Successful Program Management 12 Ways to Make Your Program Deliver on Time, on Target, and on Budget 11 Canal Center Plaza Alexandria, VA 22314 HQ 703-548-7006 Fax 703-684-5189

More information

Spec. Standard: 11/27/06 01310-1 Revision: 11/27/06

Spec. Standard: 11/27/06 01310-1 Revision: 11/27/06 SECTION 01310 CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. Construction Progress Schedule: The CONTRACTOR shall submit a detailed work progress schedule showing all work in a graphic format suitable

More information

Module 13: Emergency Preparedness and Response

Module 13: Emergency Preparedness and Response Module 13: Emergency Preparedness and Response Guidance...13-2 Tools...13-4 Tool 13-1: Emergency Preparedness and Response Worksheet...13-4 Tool 13-2: Emergency Preparedness and Response Requirements Matrix...13-5

More information

01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING)

01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING) 01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING) PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

A S S E T I N T E G R I T Y I N T E L L I G E N C E

A S S E T I N T E G R I T Y I N T E L L I G E N C E ASSET INTEGRITY INTELLIGENCE Fe atured Article BEST PRACTICES OF MAINTENANCE PLANNING & SCHEDULING MATT MIDAS, GenesisSolutions, An ABS Group Company VOLUME 21, ISSUE 2 MARCH APRIL 2015 BEST PRACTICES

More information

INSPECTION AND CONSTRUCTION MANAGEMENT CAPABILITIES

INSPECTION AND CONSTRUCTION MANAGEMENT CAPABILITIES INSPECTION AND CONSTRUCTION MANAGEMENT CAPABILITIES 9601 JONES ROAD, SUITE 242 HOUSTON, TEXAS 77065 (832) 678-2210 FAX (832) 678-2310 Table of Contents SECTION 1 - CORPORATE OVERVIEW... 3 SECTION 2 - RESPONSIBILITIES

More information

NORSOK STANDARD COMMON REQUIREMENTS MECHANICAL COMPLETION AND COMMISSIONING

NORSOK STANDARD COMMON REQUIREMENTS MECHANICAL COMPLETION AND COMMISSIONING NORSOK STANDARD COMMON REQUIREMENTS MECHANICAL COMPLETION AND COMMISSIONING Rev. 1, May 1996 Rev. 1, May 1996 CONTENTS 1 FOREWORD 2 2 SCOPE 2 3 NORMATIVE REFERENCES 2 4 DEFINITIONS AND ABBREVIATIONS 2

More information

For sustaining an emergency response, a. A Process for Determining Sustainability During Emergencies:

For sustaining an emergency response, a. A Process for Determining Sustainability During Emergencies: A Process for Determining Sustainability During Emergencies: For sustaining an emergency response, a healthcare organization needs a process to determine the length of time it can remain in existence by

More information

SERVICES. Designing, deploying and supporting world class communications solutions.

SERVICES. Designing, deploying and supporting world class communications solutions. Designing, deploying and supporting world class communications solutions. DESIGN Expertise, technologies, tools and ideas Business environments, regulation, expansion and obsolescence are drivers that

More information

// Benchmarking Project Schedules

// Benchmarking Project Schedules // Benchmarking Project Schedules Dr. Dan Patterson, PMP CEO & President, Acumen March 2011 www.projectacumen.com Table of Contents Introduction... 4 Benchmarking Overview... 4 Uses of Schedule Benchmarking...

More information

Offshore Work Packages

Offshore Work Packages Rampion Offshore Wind Farm Offshore Work Packages Meet The Buyer Naren Mistry, Engineering Manager 26 th Feb 2014 Rampion Offshore Project Scope Design, manufacture, transportation and Installation: Up

More information

Designing the Information System

Designing the Information System Pension System Management Designing the Information System Oleksiy Sluchynsky MENA Regional Workshop in Pension Administration May 2005 osluchynskyy@worldbank.org Company LOGO 1 Topics of Presentation

More information

Making the right choice: Evaluating outsourced revenue cycle services vendors

Making the right choice: Evaluating outsourced revenue cycle services vendors Making the right choice: Evaluating outsourced revenue cycle services vendors Page 1 Managing resources at today s hospitals and health systems is an ongoing challenge, considering the numerous clinical

More information

Experience and Qualifications of PROCESS PLANTS CORPORATION

Experience and Qualifications of PROCESS PLANTS CORPORATION Experience and Qualifications of PROCESS PLANTS CORPORATION Table of Contents Section 1. Project Services pg 3-20 Engineering Services Project management Design engineering Design management Construction

More information

LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT CONSTRUCTION PLANS QUALITY CONTROL / QUALITY ASSURANCE MANUAL

LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT CONSTRUCTION PLANS QUALITY CONTROL / QUALITY ASSURANCE MANUAL LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT CONSTRUCTION PLANS QUALITY CONTROL / QUALITY ASSURANCE MANUAL August 2008 TABLE OF CONTENTS Section 1 - Introduction... 3 1.1 Defining Plan Quality...

More information

Delivery Management Guidelines Delivery Process 2 - Project Management

Delivery Management Guidelines Delivery Process 2 - Project Management Delivery Management Guidelines Delivery Process 2 - Project Management Version control Version 9-1 Date 2010-10-18 Status Approved The IDMS Prov Infr Strat DP1: Portfolio Management DP1-1 Infrastructure

More information

www.ronrosenhead.co.uk Joining Instructions for 3 day project management event

www.ronrosenhead.co.uk Joining Instructions for 3 day project management event Joining Instructions for 3 day project management event To: All Participants We are looking forward to working with you to develop your project management skills and to discuss their application to current

More information

Using the Proxy NPV Model for Value-Based Strategic Decisions

Using the Proxy NPV Model for Value-Based Strategic Decisions Using the Proxy NPV Model for Value-Based Strategic Decisions January 2011 Westney Consulting Group, Inc. www.westney.com The Importance of Value-Based Development Decisions The Influence Curve has long

More information

OBLIGATION MANAGEMENT

OBLIGATION MANAGEMENT OBLIGATION MANAGEMENT TRACK & TRACE: CONTRACTUAL OBLIGATIONS Better Visibility. Better Outcomes RAMESH SOMASUNDARAM DIRECTOR, IT VENDOR MANAGEMENT SERVICES MARCH 2012 E N E R G I C A Governance Matter

More information

pm4dev, 2016 management for development series Project Scope Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

pm4dev, 2016 management for development series Project Scope Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS pm4dev, 2016 management for development series Project Scope Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development

More information

Integrating Quality Assurance into the GIS Project Life Cycle

Integrating Quality Assurance into the GIS Project Life Cycle Integrating Quality Assurance into the GIS Project Life Cycle Abstract GIS databases are an ever-evolving entity. From their humble beginnings as paper maps, through the digital conversion process, to

More information

Automatic Fire Fighting Monitors

Automatic Fire Fighting Monitors Automatic Fire Fighting Monitors Fire Protection Solutions Automatic Fire Fighting Monitors Foreword Automatic monitors are devices used to deliver large amounts of water or water/foam solution to remote

More information

Priori ty ... ... ...

Priori ty ... ... ... .Maintenance Scheduling Maintenance scheduling is the process by which jobs are matched with resources (crafts) and sequenced to be executed at certain points in time. The maintenance schedule can be prepared

More information

Document Commentary. AIA Document C191 2009, Standard Form Multi-Party Agreement for Integrated Project Delivery

Document Commentary. AIA Document C191 2009, Standard Form Multi-Party Agreement for Integrated Project Delivery Document AIA Document C191 2009, Standard Form Multi-Party Agreement for Integrated Project Delivery INTRODUCTION Current practice in the construction industry promotes inefficiency when the key project

More information

Attachment 16.1 SA Power Networks: Customer Data Quality Plan 2015-2020 September 2014

Attachment 16.1 SA Power Networks: Customer Data Quality Plan 2015-2020 September 2014 Attachment 16.1 SA Power Networks: Customer Data Quality Plan 2015-2020 September 2014 Customer Data Quality Plan 2015-2020 V1.1 Executive Summary The commencement of Full Retail Contestability in 2004

More information

8 Briefing. Responsible investor

8 Briefing. Responsible investor Issue Responsible investor 8 Briefing 20th September 2013 In 2010, we accepted all 26 recommendations made by the Bly Report our internal investigation into the Deepwater Horizon incident. BP has committed

More information

CAN/ULC S1001-11 Integrated Systems Testing of Fire Protection and Life Safety Systems and Fire Protection Commissioning

CAN/ULC S1001-11 Integrated Systems Testing of Fire Protection and Life Safety Systems and Fire Protection Commissioning CAN/ULC S1001-11 Integrated Systems Testing of Fire Protection and Life Safety Systems and Fire Protection Commissioning Presentation To: Canadian Fire Alarm Association (CFAA) Alberta Technical Seminar

More information

OTC 12979. Managing the Cost & Schedule Risk of Offshore Development Projects Richard E. Westney Westney Project Services, Inc.

OTC 12979. Managing the Cost & Schedule Risk of Offshore Development Projects Richard E. Westney Westney Project Services, Inc. OTC 12979 Managing the Cost & Schedule Risk of Offshore Development Projects Richard E. Westney Westney Project Services, Inc. Copyright 2001, Offshore Technology Conference This paper was prepared for

More information

Languages: : French (Mother tongue), English (Fluent), Portuguese (Basic Level)

Languages: : French (Mother tongue), English (Fluent), Portuguese (Basic Level) curriculum vitae Name: : Jeremy de BARBARIN Position: : Engineering Manager Date/Place of Birth: : 14 th of June 1973 in Marseille (France) Nationality: : French Languages: : French (Mother tongue), English

More information

ACG Commissioning Guideline

ACG Commissioning Guideline ACG Commissioning Guideline Appendix A Sample Commissioning Specification NOTES TO APPENDIX A This appendix contains a sample Request for Proposal (RFP) for Commissioning Services as would be issued by

More information

ENVIRONMENTAL POLICY & MANAGEMENT SYSTEM GUIDE

ENVIRONMENTAL POLICY & MANAGEMENT SYSTEM GUIDE ENVIRONMENTAL POLICY & MANAGEMENT SYSTEM GUIDE 1 Statement of Intent Corps Security aims to create and maintain through staff awareness, the highest level of environmental responsibility. We regard the

More information

Engineering Support Services

Engineering Support Services GE Power & Water Water & Process Technologies Support Services for the Automation and Control of Water and Process Applications It Starts with Listening for Customer Value Automation and process control

More information

Project Management Issues in the Finance Transformation Arena

Project Management Issues in the Finance Transformation Arena Project Management Issues in the Finance Transformation Arena Projects, and the ability to deliver them on time and on budget, not only represent an ongoing challenge for any organization, but also require

More information

8.0 ENVIRONMENTAL PROTECTION MONITORING AND FOLLOW-UP

8.0 ENVIRONMENTAL PROTECTION MONITORING AND FOLLOW-UP 8.0 ENVIRONMENTAL PROTECTION MONITORING AND FOLLOW-UP 8.1 INTRODUCTION Mitigation measures, monitoring and other follow-up actions identified in Chapter 7 (Environmental Effects Assessment and Mitigation)

More information

DATA QUALITY STRATEGY

DATA QUALITY STRATEGY DATA QUALITY STRATEGY June 2008 G:\Performance Management\data quality\data Quality Strategy08.doc 1 CONTENTS CONTENTS 2 1. INTRODUCTION 3 2. BACKGROUND INFORMATION 3 3. THE PRINCIPLES OF DATA QUALITY

More information

BFB-IS-10: Systems Development Standards

BFB-IS-10: Systems Development Standards Responsible Officer: VP - Chief Information Officer Responsible Office: IT - Information Technology Services Issuance Date: 5/18/2001 Effective Date: 5/18/2001 Scope: [Scope] Contact: Stephen Lau Email:

More information

Features. Emerson Solutions for Abnormal Situations

Features. Emerson Solutions for Abnormal Situations Features Comprehensive solutions for prevention, awareness, response, and analysis of abnormal situations Early detection of potential process and equipment problems Predictive intelligence network to

More information

Welcome to the Data Analytic Toolkit PowerPoint presentation an introduction to project management. In this presentation, we will take a brief look

Welcome to the Data Analytic Toolkit PowerPoint presentation an introduction to project management. In this presentation, we will take a brief look Welcome to the Data Analytic Toolkit PowerPoint presentation an introduction to project management. In this presentation, we will take a brief look at project management to understand the process and some

More information

Asset Management Conformity Assessment Fitness for Service QHSE. Oil & Gas Services and Tools. For the benefit of business and people

Asset Management Conformity Assessment Fitness for Service QHSE. Oil & Gas Services and Tools. For the benefit of business and people Asset Management Conformity Assessment Fitness for Service QHSE Oil & Gas Services and Tools For the benefit of business and people Services along the whole life of Facilities Bureau Veritas services can

More information

Organizational Design Toolkit

Organizational Design Toolkit Organizational Design Toolkit We provide below highlights of the approach to developing/confirming the preferred service delivery model and organizational structure for an organization. The key steps are:

More information

LOOP Technology Limited. vision. inmotion IMPROVE YOUR PRODUCT QUALITY GAIN A DISTINCT COMPETITIVE ADVANTAGE. www.looptechnology.

LOOP Technology Limited. vision. inmotion IMPROVE YOUR PRODUCT QUALITY GAIN A DISTINCT COMPETITIVE ADVANTAGE. www.looptechnology. LOOP Technology Limited vision inmotion IMPROVE YOUR PRODUCT QUALITY GAIN A DISTINCT COMPETITIVE ADVANTAGE www.looptechnology.com Motion Control is an established part of the production process in a diverse

More information

Test Specification. Introduction

Test Specification. Introduction Test Specification Introduction Goals and Objectives GameForge is a graphical tool used to aid in the design and creation of video games. A user with little or no experience with Microsoft DirectX and/or

More information

Commissioning Plan Preparation Guide. Version 2.0 (Replaces Project Test Plans Preparation Guide, Version 1.0, September 2012)

Commissioning Plan Preparation Guide. Version 2.0 (Replaces Project Test Plans Preparation Guide, Version 1.0, September 2012) Commissioning Plan Preparation Guide Version 2.0 (Replaces Project Test Plans Preparation Guide, Version 1.0, September 2012) September 2013 Commissioning Plan Preparation Guide Contents 1.0 Introduction...

More information

VENDOR MANAGEMENT. General Overview

VENDOR MANAGEMENT. General Overview VENDOR MANAGEMENT General Overview With many organizations outsourcing services to other third-party entities, the issue of vendor management has become a noted topic in today s business world. Vendor

More information

2015-2017 STRATEGIC PLAN SMALL BUSINESS DEVELOPMENT CENTER NETWORK ILLINOIS DEPARTMENT OF COMMERCE AND ECONOMIC OPPORTUNITY

2015-2017 STRATEGIC PLAN SMALL BUSINESS DEVELOPMENT CENTER NETWORK ILLINOIS DEPARTMENT OF COMMERCE AND ECONOMIC OPPORTUNITY 2015-2017 STRATEGIC PLAN SMALL BUSINESS DEVELOPMENT CENTER NETWORK ILLINOIS DEPARTMENT OF COMMERCE AND ECONOMIC OPPORTUNITY 1 INTRODUCTION Lead Economic Development Agency - The Department of Commerce

More information