Geotechnical Design: Deep Water Pontoon Mooring Anchors
|
|
- Earl West
- 7 years ago
- Views:
Transcription
1 1077 Geotechnical Design: Deep Water Pontoon Mooring Anchors Ben Upsall 1, Garry Horvitz 1, Bob Riley 2, Tripp Howard 2, Kimball Olsen 3, and James R. Struthers 4 1 Hart Crowser, Inc., 1700 Westlake Avenue N., Suite 200, Seattle, WA, 98109, USA, (206) , ben.upsall@hartcrowser.com, garry.horvitz@hartcrowser.com. 2 KPFF Consulting Engineers, 101 Stewart Street, Suite 400, Seattle, WA, 98101, USA, (206) , briley@kpffspd.com, thoward@kpffspd.com. 3 Kiewit Engineering Co., East Fremont Drive, Centennial, CO, 80112, USA, kimball.olsen@kiewit.com. 4 Washington State Department of Transportation, 1655 South 2 nd Avenue, Tumwater, WA, 98512, USA, struthj@wsdot.wa.gov. ABSTRACT Anchoring floating structures in deep water can be challenging because of varying water depths, soil types, uses, and environmental loads. Three different anchor types, drilled shaft, gravity, and fluke anchors were used to meet these challenges for the new SR520 Evergreen Point Floating Bridge and Landings project in Seattle, Washington. The anchors were designed to resist the horizontal and vertical components of the maximum resultant anchor cable load of 570 tons under static and seismic conditions. The anchors are being proven through exhaustive full-scale field load tests. Verification tests are being loaded to a maximum of 570 tons, performance tests to 425 tons, and proof tests on all remaining production anchors to 300 tons. All anchors tested to date, including all performance and verification tests for all three anchor types, have met all (creep and total displacement) testing requirements. INTRODUCTION This paper presents a case history of the geotechnical challenges of designing and testing large-scale submarine anchors that will permanently moor the floating concrete pontoons for the SR520 Evergreen Point Floating Bridge and Landings Replacement Project in Seattle, Washington. The new floating bridge will replace an existing floating bridge and improve a major traffic corridor between Seattle and Bellevue, connecting the north-south I-405 and I- 5 highways. The new bridge will consist of 23 primary concrete pontoons and as many as 84 supplemental stability pontoons at maximum future capacity. At approximately 1.5 miles long, it will be the longest floating bridge in the world upon completion.
2 1078 Much like a floating dock, the floating bridge will be subjected to wind, wave, current, potential vessel impact, and seismic seiche forces. In order to maintain the floating bridge alignment, the loads on the pontoons must be resisted by anchors set into the sediments at the bottom of Lake Washington. Each pontoon will be held in place by at least two 3-1/8 inch structural strand cables attached to anchors installed in water ranging from 30 to 210 feet deep. The design of the anchorage system for the new bridge was complicated by: Variable subsurface conditions ranging from very dense glacially overridden soils to thick deposits of very soft diatomaceous sediments with unique engineering properties; Limited strength testing of the soft diatomaceous sediments from which to develop passive resistance values for anchor design. Very demanding lateral load requirements consisting of a 570-ton load applied to each anchor s low-angle cable connection; and Testing requirements that were difficult both to measure with the specified accuracy and to verify in deep water. SITE AND SUBSURFACE CONDITIONS Site. The site is located on Lake Washington spanning from just north of the Madison Park neighborhood of Seattle on the western side to Medina on the eastern side (Figure 1). An existing bridge currently spans this stretch of Lake Washington about two hundred feet to the south of the proposed bridge alignment. The existing bridge consists of two lanes in each direction and is a major east-west lifeline connecting north-south highways (I-5 and I-405) on either end. Figure 1. Vicinity Map Lake Washington is a long north-south glacially formed lake feature, carved out by the advance and retreat of several different glaciations. It is almost 18 miles long, as much as 4 miles wide, and up to about 214 feet deep. The lake bottom profile (Figure 2) along the proposed bridge alignment resembles the cross-section of a bath tub with a deep flat bottom and steep walls on the east and west sides.
3 1079 Soil. The subsurface conditions at the site were based on over 50 geotechnical explorations and hundreds of associated laboratory tests. In general, the steep sidewalls of the profile consist of very dense glacially overconsolidated sediments and the deep flat lake bottom consists of very soft diatomaceous silt (with unique engineering properties) and unconsolidated lacustrine sediments. Figure 2. Generalized Lake Bottom Profile ANCHOR TYPES, SELECTION, AND INSTALLATION Three different anchor designs were proposed to provide permanent moorage for the floating concrete pontoons: drilled shaft, gravity, and fluke. Bathymetric, geologic, and functional constraints provided the framework for selecting the type of anchor to be used at each location along the bridge alignment. Drilled Shaft Anchors. A total of five ten-foot-diameter drilled shaft anchors, ranging from 72 to 86 feet long, were used at the eastern- and western-most reaches of the project. These drilled shaft anchors are located in relatively shallow water (25 to 40 feet deep) in locations where the very dense glacially overconsolidated sediments were present near the mudline. The drilled shaft design, where only about 6 feet of shaft was exposed above the mudline, was well suited to these locations because sufficient clearance for deep-draft vessels was a project requirement. The drilled shaft anchors were installed through a steel casing embedded approximately 10 feet into the mudline. The excavations were performed under a synthetic slurry head to maintain an open hole and to minimize sloughing of the sidewall soils beneath the bottom of the casing. Gravity Anchors. A total of eight gravity anchors, 40 feet by 40 feet in plan and 23 feet tall, loosely resembling a reinforced concrete box without a lid (Figure 3), were designed for the steep side slopes of the lake bottom profile where the very dense glacially overconsolidated sediments were present near the mudline. The deeper water provided sufficient clearance for deep-draft vessels above the anchors which are exposed as much as 25 feet above the mudline.
4 1080 Figure 3. Basic Geometry of Gravity Anchor The gravity anchor design calls for first dredging a horizontal pad into the side slope of the lake bottom profile followed by placing a 2-foot thick shoulder ballast pad over the subgrade soils. The anchors would then be flooded and placed on the prepared gravel pad and finally filled with approximately 1,700 tons of ballast rock. Fluke Anchors. A total of 45 fluke anchors, which resemble a vertical plate anchor made of reinforced concrete (Figure 4), are used in the deep soft diatomaceous sediments on the lake bottom. The fluke anchors are 35 feet wide and 26 feet tall and were installed vertically into the soft lake bottom sediments. Figure 4. Basic Geometry of Fluke Anchor The fluke anchors were each lowered into place with a crane and installed into the soft lake bottom sediments using gravity along with the aid of an external water jetting frame. The area in front (towards the pontoon) of each anchor was then ballasted in a specific geometry with 1,250 tons of ballast rock to improve lateral resistance.
5 1081 ANCHOR DESIGN Due to the complex loading conditions, environmental constraints, soil-structure interaction, and testing complications, the design of each anchor type was completed in close cooperation between the project s geotechnical engineers, structural engineers, and contractors. The result is three vastly different anchor designs specifically tailored to meet the requirements for anchor function in difficult site conditions and the desire for minimizing the complexity of construction and testing. Drilled Shaft Anchors. The geotechnical design of the laterally loaded drilled shaft anchors had to consider both the lateral and vertical components of the resultant cable load (570 tons) in addition to seismic slope stability. The vertical component was easily resisted by the weight of the reinforced concrete shaft itself. The lateral component was evaluated using a p-y based lateral pile analysis method. Static and seismic slope stability was evaluated using limit equilibrium slope stability methods. Analyses for three different soil conditions were performed: static, pseudostatic, and liquefied. Based on the results of the stability analyses: The slopes into which all five drilled shafts will be installed appear to be stable during static soil conditions; The slopes into which three of the drilled shafts will be installed were found to have insufficient factors of safety against sliding during the pseudostatic (design level seismic) event; and The slopes into which two of the drilled shafts will be installed were found to have insufficient factors of safety against sliding with liquefied conditions. The drilled shafts that had insufficient factors of safety against sliding during the design level seismic event were further evaluated using probabilistic seismic slope displacement estimate methods (Bray and Travasaru, 2007) and were predicted to move on the order of 1 to 5 feet during the seismic event. These seismic slope displacements were used in conjunction with the limit equilibrium slope stability analyses to develop additional lateral loading profiles on the affected drilled shafts. One of the three affected shafts was capable of resisting the additional lateral loads due to seismic slope displacements without damaging the shaft largely because the failure surface was relatively shallow (about 10 feet below mudline). The other two drilled shafts were predicted to be intersected by a deep failure surface about 60 feet below the mudline. The loads created by the predicted slope movements were found to be too large to be reasonably resisted and these two drilled shafts would likely be irreparably damaged following a design level seismic event. The owner confirmed, due to redundancy in the system, that the loss of these two drilled shaft anchors during the seismic event would not likely jeopardize the overall performance of the bridge and decided to accept the risk of anchor failure and the long-term operations and maintenance responsibility if the drilled shafts needed to be replaced.
6 1082 Gravity Anchors. The geotechnical design of the laterally loaded gravity anchors had to consider both the lateral and vertical components of the resultant cable load (570 tons) in addition to seismic slope stability. The vertical component was easily resisted by the weight of the concrete anchor filled with 1,700 tons of ballast rock. The lateral component was evaluated by modeling the anchor as a frictional sliding block. The primary challenges to the lateral capacity evaluation were determining the frictional characteristics of the in-situ soil beneath the anchor. A level pad was excavated on the steep side slope of the lake using a clam-shell bucket. The clamshell was assumed to produce a hummocky surface, which resulted in some uncertainty when estimating how much soil would directly contact the anchor base. These challenges were circumvented by adding a minimum two-foot-thick gravel leveling pad between the clam-shell excavated surface and the bottom of the anchor. This provided an easily verified interface friction value as well as a level pad providing more uniform anchor contact. The pad also reduced the concerns that the anchors could exhibit long-term creep behavior under constant loading conditions. One additional component to the lateral capacity design was the inclusion of teeth or corrugations on the base of the concrete box (Figure 5) running perpendicular to the anchor cable direction. These corrugations allowed for the use of the internal friction angle of the gravel itself rather than just the interface friction angle between gravel and concrete by forcing the failure surface down into the gravel pad. Figure 5. Gravity Anchor Corrugation Static and seismic slope stability was evaluated using limit equilibrium slope stability methods. Analyses for three different soil conditions were performed: static, pseudostatic, and liquefied. Based on the results of the stability analyses: The slopes onto which the eight gravity anchors will be set appear to be stable during static soil conditions; The slopes onto which seven of the gravity anchors will be set were found to have insufficient factors of safety against sliding during the pseudostatic (design level seismic) event; and
7 1083 The slopes onto which all eight gravity anchors will be set appear to be stable during liquefied soil conditions. The gravity anchors that had insufficient factors of safety against sliding during pseudostatic soil conditions were further evaluated using probabilistic seismic slope displacement estimate methods (Bray and Travasaru, 2007). Two separate cases were evaluated for each affected anchor: 1) the critical anchor case which was defined as the critical failure surface that extends beneath the anchor leveling pad, and 2) the critical impact case which was defined as the critical failure surface located upslope of the gravity anchor that could potentially impact the side of the anchor during seismic slope displacement. Seismic slope displacements for the affected gravity anchors were predicted to be on the order of 2 to 4 feet and 0 to 4 feet for the critical anchor and critical impact cases, respectively. Movements of less than 4 feet for the critical anchor case fell within the project requirement that the anchors not move more than 10 feet from their original location as a result of the design level seismic event. Movements of less than 4 feet for the critical impact case were mitigated by excavating additional material upslope of the anchors and providing a minimum 5-foot buffer between the upslope gravity anchor walls and the toe of the soil slope above the anchor. Fluke Anchors. The geotechnical design of the laterally loaded fluke anchors had to consider both the lateral and vertical components of the resultant cable load (570 tons); however, due to the relatively flat lake bottom profile, seismic slope stability was not a concern. The vertical capacity design component was easily resisted by the skin friction along the perimeter of the fluke anchor and the weight of the anchor itself. The more complex lateral capacity design was performed using lateral earth pressure theory and a deformation based modeling program (FLAC). Two main stress cases were evaluated representing total and effective stress soil conditions. The total stress condition represented short duration (anchor test and seismic) loading while the effective stress condition represented the long duration (service) loading. The first challenge to the lateral capacity evaluation was determining the engineering characteristics of the in-situ diatomaceous silt present at the bottom of the lake. The diatomaceous soil was extremely difficult to sample and test. The significant concentrations of diatoms made the estimation of several common engineering properties difficult. Of these properties, those of which can be obtained or correlated from highly disturbed samples (such as water content and atterberg limits) were rendered irrelevant for typical soil types in the region due to the nature of the silt. The useful data included buoyant unit weight (average of about 12.5 pounds per cubic foot), diatom content percentage (ranging from about 0 to 60 percent), four sets of CU triaxial test results, and four load-displacement curves (Figure 6) from tests completed on fluke anchors installed to moor the existing bridge. The average strength parameters deduced from the CU triaxial tests for the total stress case included an internal friction angle of about 9 degrees and a cohesion value of
8 1084 approximately 170 pounds per square foot (psf). The average strength parameters deduced from the CU triaxial tests for the effective stress case included an effective internal friction angle of approximately 33 degrees and an effective cohesion value of approximately 50 psf. Load Displacement Curves Displacement in Feet EN ES KN KS FLAC Horizontal Load in Kips Figure 6. Historic Fluke Anchor and FLAC Model Load-Displacement Curves The FLAC model was used to independently back-calculate the same engineering properties of the lake-bottom soils using the load-displacement curves from the existing bridge. The model geometry matched the existing fluke anchor sizes and the model was calibrated to the curves by adjusting friction angle, cohesion, and stiffness of the diatomaceous soil unit. Figure 6 presents the four original load-displacement curves and the resulting load-displacement curve from the calibrated FLAC model. The resulting soil parameters from the FLAC model for the total stress case were an internal friction angle of about 9 degrees and a cohesion value of approximately 160 psf. The resulting soil parameters for the effective stress case were an effective internal friction angle of about 29 degrees and a cohesion value of 0 psf. These values correlate well with the average strength parameters obtained from the limited CU triaxial tests that were available. Once the engineering properties for the soil model had been back-calculated, the proposed fluke anchor geometry and ballast rock quantity were optimized for the maximum design cable load of 570 tons. The estimation of the ballast rock quantity was difficult to determine as it was unknown how much of the ballast rock, which would likely be placed via tremie tube from a barge, would sink into the soft diatomaceous silt. Therefore, three cases of ballast rock geometry were evaluated so as to bracket the potential range of solutions.
9 1085 Case 1 assumed that the ballast rock pile remains intact on top of the mudline, Case 2 assumed that the ballast rock mixes with or displaces the soil to a depth equivalent to the height of the ballast rock pile in Case 1, and Case 3 assumed that the ballast rock mixes with and disperses through the soil to a depth equivalent to twice the height of the ballast rock pile in Case 1. The three potential ballast rock geometry cases were each evaluated for the two different stress condition cases using the FLAC model. The optimized design included 1,250 tons of ballast rock placed in a stepped configuration in front of the anchor (Figure 4). This ballast rock configuration satisfied the loading requirements for all 6 different geometry and stress condition case combinations. ANCHOR TESTING Because of the difficulty in determining the engineering properties of the soils and the fact that the design anchor load requirements are almost four times higher than those of the existing bridge anchors (570 tons versus about 125 tons), verification testing was required in the contract. An anchor testing barge was designed and outfitted specifically for this project. Every production anchor will be proof tested in addition to a comprehensive suite of performance and verification test requirements. During each test, the anchors will be subjected to load hold periods ranging from 1 to 24 hours in duration to confirm that the soils are not susceptible to long-term creep failure. The creep rates must be decreasing over successive log cycles of time and must not exceed threshold values in order for the anchor to be accepted by the owner. The anchors must also have less than 10 feet of total displacement during the test. A data acquisition and processing system was designed for this project to monitor the testing barge position (continuous determination of latitude, longitude, elevation, pitch, roll, yaw, and tilt of the barge). The system also collected the tensile load in the test cables, the take-up of the test cables as the loads were applied, and the wind speed. This information was all time-stamped as it was collected and the processing programs calculated movements of the barge that was presented in real-time. The system also used the cable load, barge position, and cable take-up measurements in conjunction with theoretical cable catenary calculations to evaluate the amount of anchor deformation that had occurred during the test. The shaft anchors displayed negligible creep movement during the load holds and exhibited less than half of an inch of total displacement. This behavior generally met the expectations for laterally loaded drilled shafts in very dense soils. The gravity anchors displayed negligible creep movement during the load holds and exhibited total displacements on the order of less than about 12 inches. Creep movement was not anticipated due to the granular nature of the gravel leveling pad. The total displacements can likely be explained as the setting of the concrete teeth or corrugations on the bottom of the anchors into the gravel leveling pad.
10 1086 The fluke anchors exhibited negligible creep movement during the load holds and exhibited total displacements of less than about 4 feet. Some creep behavior had been anticipated because of the slowly draining nature of the diatomaceous silt. Anchor displacement during the test was anticipated by the designers as movement was considered necessary to fully engage the strength of the uncompacted pile of ballast rock in front of the fluke anchor. CONCLUSIONS The geotechnical design and testing of these deep water mooring anchors was complicated by: Highly variable subsurface conditions and bathymetric profile; Limited information on the engineering properties of the lake-bottom soils; Very demanding lateral load requirements; and Stringent acceptance criteria for deformation and creep on anchors set and tested in deep water conditions. These complications were addressed and overcome by the following: Three different anchor designs were used to meet the bathymetric, geologic, and functional constraints of the project; Anchor scale and design ingenuity were used to meet the demanding lateral load requirements; and A time stamped data tracking and monitoring system was used to provide real-time anchor testing results with an appropriate level of resolution. All anchors tested to date, including all performance and verification tests for all three anchor types, have met all (creep and total displacement) testing requirements. REFERENCES Bray, J.D., and Travasarou, T. (2007). Simplified procedure for estimating earthquake induced deviatoric slope displacements. Journal of Geotechnical and Geoenvironmental Engineering, ASCE, 133(4), Idriss, I.M., and Boulanger, R.W. (2008). Soil Liquefaction during Earthquakes. EERI, Oakland, California. Itasca, (2011). Fast Lagrangian Analysis of Continua (FLAC) 2-D. Version
BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM
BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM Swaminathan Srinivasan, P.E., M.ASCE H.C. Nutting/Terracon David Tomley, P.E., M.ASCE KZF Design Delivering Success for
More informationSafe & Sound Bridge Terminology
Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries
More information4.11 Geologic and Soil Resources
4.11 Geologic and Soil Resources Geology and soils are evaluated as part of an environmental document because conditions in the project area can influence the type and size of a project s structure, the
More informationHigh Strain Dynamic Load Testing of Drilled Shafts
Supplemental Technical Specification for High Strain Dynamic Load Testing of Drilled Shafts SCDOT Designation: SC-M-712 (9/15) September 3, 2015 1.0 GENERAL This work shall consist of performing high-strain
More informationPDCA Driven-Pile Terms and Definitions
PDCA Driven-Pile Terms and Definitions This document is available for free download at piledrivers.org. Preferred terms are descriptively defined. Potentially synonymous (but not preferred) terms are identified
More informationOhio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin PLAN SUBGRADES
Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering Geotechnical Bulletin GB 1 PLAN SUBGRADES Geotechnical Bulletin GB1 was jointly developed by the Offices
More informationComprehensive Design Example 2: Foundations for Bulk Storage Facility
Comprehensive Design Example 2: Foundations for Bulk Storage Facility Problem The project consists of building several dry product storage silos near an existing rail siding in an open field presently
More informationc. Borehole Shear Test (BST): BST is performed according to the instructions published by Handy Geotechnical Instruments, Inc.
Design Manual Chapter 6 - Geotechnical 6B - Subsurface Exploration Program 6B-2 Testing A. General Information Several testing methods can be used to measure soil engineering properties. The advantages,
More informationSAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS
Page 1 of 9 SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS 1. GENERAL REQUIREMENTS 1. Description of Work: This work consists of furnishing all materials, equipment and
More informationFOUNDATION DESIGN. Instructional Materials Complementing FEMA 451, Design Examples
FOUNDATION DESIGN Proportioning elements for: Transfer of seismic forces Strength and stiffness Shallow and deep foundations Elastic and plastic analysis Foundation Design 14-1 Load Path and Transfer to
More informationReport on. Wind Resistance of Signs supported by. Glass Fiber Reinforced Concrete (GFRC) Pillars
Report on Wind Resistance of Signs supported by Glass Fiber Reinforced Concrete (GFRC) Pillars Prepared for US Sign and Fabrication Corporation January, 2006 SUMMARY This study found the attachment of
More informationThe Verdura Wall check with your local building department
The Verdura Wall The Verdura Wall by Soil Retention Products, Inc of Carlsbad, California can be constructed as a gravity retaining structure or a geosynthetic reinforced segmental retaining wall, depending
More informationSHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS
SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS Vince Luongo Petrifond Foundation Co., Ltd. PROJECT DESCRIPTION The York Durham Sanitary System (YDSS) Interceptor in the Town of Richmond Hill located
More informationGLOSSARY OF TERMINOLOGY
GLOSSARY OF TERMINOLOGY AUTHORIZED PILE LENGTHS - (a.k.a. Authorized Pile Lengths letter) Official letter stating Engineer's recommended length of concrete piles to be cast for construction of foundation.
More informationLEGACY REPORT ER-5110. www.icc-es.org. ICC Evaluation Service, Inc. Reissued November 1, 2003. Legacy report on the 1997 Uniform Building Code
LEGACY REPORT Reissued November 1, 2003 ICC Evaluation Service, Inc. www.icc-es.org Business/Regional Office # 5360 Workman Mill Road, Whittier, California 90601 # (562) 699-0543 Regional Office # 900
More informationEXAMPLE 1 DESIGN OF CANTILEVERED WALL, GRANULAR SOIL
EXAMPLE DESIGN OF CANTILEVERED WALL, GRANULAR SOIL A sheet pile wall is required to support a 2 excavation. The soil is uniform as shown in the figure. To take into account the friction between the wall
More informationUp-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations
Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations Nathan A. Ingraffea, P.E., S.E. Associate, KPFF Consulting Engineers, Portland, Oregon, USA Abstract The use of steel sheet
More informationSUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS
July 14, 2015 1.0 GENERAL BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS This work shall consist of furnishing all materials, equipment, labor, and incidentals necessary for conducting bi-directional
More information6 RETROFITTING POST & PIER HOUSES
Retrofitting Post & Pier Houses 71 6 RETROFITTING POST & PIER HOUSES by James E. Russell, P.E. 72 Retrofitting Post & Pier Houses Retrofitting Post & Pier Houses 73 RETROFITTING POST AND PIER HOUSES This
More informationPILE FOUNDATIONS FM 5-134
C H A P T E R 6 PILE FOUNDATIONS Section I. GROUP BEHAVIOR 6-1. Group action. Piles are most effective when combined in groups or clusters. Combining piles in a group complicates analysis since the characteristics
More informationSPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 11/5/13)
Page 1 of 7 STONE STRONG SYSTEMS SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised ) PART 1: GENERAL 1.01 Description A. Work includes furnishing and installing precast modular blocks
More informationMETHOD OF STATEMENT FOR STATIC LOADING TEST
Compression Test, METHOD OF STATEMENT FOR STATIC LOADING TEST Tension Test and Lateral Test According to the American Standards ASTM D1143 07, ASTM D3689 07, ASTM D3966 07 and Euro Codes EC7 Table of Contents
More informationNational Council of Examiners for Engineering and Surveying. Principles and Practice of Engineering Structural Examination
Structural Effective Beginning with the April 2011 The structural engineering exam is a breadth and exam examination offered in two components on successive days. The 8-hour Vertical Forces (Gravity/Other)
More informationWorked Example 2 (Version 1) Design of concrete cantilever retaining walls to resist earthquake loading for residential sites
Worked Example 2 (Version 1) Design of concrete cantilever retaining walls to resist earthquake loading for residential sites Worked example to accompany MBIE Guidance on the seismic design of retaining
More informationChapter 4 SUBSURFACE INVESTIGATION GUIDELINES
Chapter 4 SUBSURFACE INVESTIGATION GUIDELINES Final SCDOT GEOTECHNICAL DESIGN MANUAL August 2008 Table of Contents Section Page 4.1 Introduction...4-1 4.2 Subsurface Investigation...4-2 4.2.1 Preliminary
More informationBUTE Department of Construction Management and Technology
BUTE Department of Construction Management and Technology 02.10.2012 Definition 1: Foundation: The structure, that transmits the load of the building to the soil Definition 2: Load bearing soil (strata):
More informationWashington 98102-3699, mike.bailey@hartcrowser.com
LESSONS LEARNED FROM A STONE COLUMN TEST PROGRAM IN GLACIAL DEPOSITS Barry S. Chen 1, P.E., Member, Geo-Institute and Michael J. Bailey 2, P.E., Member, Geo-Institute ABSTRACT A stone column test program
More informationINTRODUCTION TO SOIL MODULI. Jean-Louis BRIAUD 1
INTRODUCTION TO SOIL MODULI By Jean-Louis BRIAUD 1 The modulus of a soil is one of the most difficult soil parameters to estimate because it depends on so many factors. Therefore when one says for example:
More informationALLOWABLE LOADS ON A SINGLE PILE
C H A P T E R 5 ALLOWABLE LOADS ON A SINGLE PILE Section I. BASICS 5-1. Considerations. For safe, economical pile foundations in military construction, it is necessary to determine the allowable load capacity
More informationTremie Concrete CM 420 CM 420 CM 420 CM 420. Temporary Structures. Tremie Concrete
Tremie Concrete Underwater concrete plays an important role in the construction of offshore structures. It may be used to tie together various elements in composite action (i.e., to tie piling to the footing).
More informationANNEX D1 BASIC CONSIDERATIONS FOR REVIEWING STUDIES IN THE DETAILED RISK ASSESSMENT FOR SAFETY
ANNEX D1 BASIC CONSIDERATIONS FOR REVIEWING STUDIES IN THE DETAILED RISK ASSESSMENT FOR SAFETY ANNEX D1: BASIC CONSIDERATIONS FOR REVIEWING STUDIES IN DRA FOR SAFETY D1-1 ANNEX D1 BASIC CONSIDERATIONS
More information6.0 Results of Risk Analyses
6. Results of Risk Analyses A risk analysis of the optimized embankment designs for the Salton Sea restoration project was conducted jointly by Kleinfelder and representatives from Reclamation. A risk
More informationDesigned and Engineered to Perform
History EARTH CONTACT PRODUCTS, L.L.C., is a family owned company, based in Olathe, Kansas. This company was built upon Don May s U.S. Patented fourth-generation Steel Piering System that has led to the
More informationOutline MICROPILES SUBJECT TO LATERAL LOADING. Dr. Jesús Gómez, P.E.
MICROPILES SUBJECT TO LATERAL LOADING Dr. Jesús Gómez, P.E. Micropile Design and Construction Seminar Las Vegas, NV April 3-4, 2008 Outline When are micropiles subject to lateral load? How do we analyze
More informationSoil Screw Design Manual Edition 2
Soil Screw Design Manual Edition 2 Page TOC-1 Hubbell Power Systems, Inc. All Rights Reserved Copyright 2015 CONTENTS CONTENTS TABLE of CONTENTS INTRODUCTION and APPLICATIONS Section 1 PURPOSE AND SCOPE...
More informationBRIDGES ARE relatively expensive but often are
Chapter 10 Bridges Chapter 10 Bridges Bridg Bridges -- usually the best, but most expensive drainage crossing structure. Protect bridges against scour. BRIDGES ARE relatively expensive but often are the
More informationCONCRETE SEGMENTAL RETAINING WALL SYSTEM
CONCRETE SEGMENTAL RETAINING WALL SYSTEM PART 1: GENERAL SPECIFICATIONS 1.01 Work Included A. Work shall consist of furnishing and constructing a Rockwood Classic 8 with PCS unit segmental retaining wall
More informationDynamic Load Testing of Helical Piles
Dynamic Load Testing of Helical Piles ANNUAL KANSAS CITY SPECIALTY SEMINAR 2014 JANUARY 10, 2014 Jorge Beim JWB Consulting LLC Pile Dynamics, Inc. Main Topics Brief description of the Dynamic Load Test
More informationMicropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation
Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Jeff R. Hill, P.E. Hayward Baker Inc. 111 W. Port Plaza Drive Suite 600 St. Louis, MO 63146 314-542-3040 JRHill@HaywardBaker.com
More informationCEEN 162 - Geotechnical Engineering Laboratory Session 7 - Direct Shear and Unconfined Compression Tests
PURPOSE: The parameters of the shear strength relationship provide a means of evaluating the load carrying capacity of soils, stability of slopes, and pile capacity. The direct shear test is one of the
More informationWisconsin Building Products Evaluation
Safety & Buildings Division 201 West Washington Avenue P.O. Box 2658 Madison, WI 53701-2658 Evaluation # 200813-O Wisconsin Building Products Evaluation Material Best Management Standards for Foundation
More informationDesign, Testing and Automated Monitoring of ACIP Piles in Residual Soils
Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils Stephen W. Lacz 1, M. ASCE, P.E. and Richard C. Wells 2, F. ASCE, P.E. 1 Senior Professional, Trigon Kleinfelder, Inc., 313 Gallimore
More informationCOSMOS 2012: Earthquakes in Action COSMOS 2012
COSMOS 2012 What is SFSI and why is it important? Soil issues in Earthquakes Structures where SFSI important Retaining structures (lateral earth pressure) Foundations (spread and pile footings, bearing
More informationRIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas http://www.mass.gov/dep/water/laws/policies.
RIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas http://www.mass.gov/dep/water/laws/policies.htm#storm Definition: A permanent, erosion-resistant ground cover
More informationCONCRETE SEGMENTAL RETAINING WALL SYSTEM
CONCRETE SEGMENTAL RETAINING WALL SYSTEM PART 1: GENERAL SPECIFICATIONS 1.01 Work Included A. Work shall consist of furnishing and constructing a Rockwood Vintage TM unit segmental retaining wall (SRW)
More informationHow to Design and Build a Fence/G traverse Bridge or Graffiti Project
Outline Project Location Project Description Project History Site Constraints Geotechnical Investigation & Soil Profile Foundation Design Process Photos Project Location Project Limits: The Grand River
More informationProperty Inspection. 83A Ascot Avenue North New Brighton Christchurch STRUCTURAL REPORT
Property Inspection 83A Ascot Avenue North New Brighton Christchurch STRUCTURAL REPORT March 2013 This document has been prepared for the benefit of Clint Marston. No liability is accepted by this company
More informationIndex. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1
6 Index inlet protection excavated drop inlet protection (Temporary) 6.50.1 HARDWARE CLOTH AND GRAVEL INLET PROTECTION Block and gravel inlet Protection (Temporary) sod drop inlet protection ROCK DOUGHNUT
More informationState of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary
More informationvulcanhammer.net This document downloaded from
This document downloaded from vulcanhammer.net since 1997, your source for engineering information for the deep foundation and marine construction industries, and the historical site for Vulcan Iron Works
More informationSTRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.
STRUCTURES 1. General. Critical structures may impact the integrity of a flood control project in several manners such as the excavation for construction of the structure, the type of foundation, backfill
More informationA CASE STUDY ON THE USE OF FLEXIBLE EARTH RETAINING STRUCTURE IN UNSTABLE SLOPES
A CASE STUDY ON THE USE OF FLEXIBLE EARTH RETAINING STRUCTURE IN UNSTABLE SLOPES H. Turan DURGUNOGLU Ahmet SAHIN Onder AKCAKAL Zetas Zemin Teknolojisi A.S., TOKI-Housing Development Zetas Zemin Teknolojisi
More informationSPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT
SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT 1.0 SOIL IMPROVEMENT 1.1 General Soil Investigation Information are provided in Part B1 annex as a guide to the Contractor for his consideration
More informationproduct manual HS-4210 HS-4210_MAN_09.08 Digital Static Cone Penetrometer
HS-4210_MAN_09.08 product manual HS-4210 Digital Static Cone Penetrometer Introduction This Manual covers the measurement of bearing capacity using the Humboldt Digital Static Cone Penetrometer (DSCP).
More informationCH. 2 LOADS ON BUILDINGS
CH. 2 LOADS ON BUILDINGS GRAVITY LOADS Dead loads Vertical loads due to weight of building and any permanent equipment Dead loads of structural elements cannot be readily determined b/c weight depends
More informationEngineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. The Leading Edge.
TM TM Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. SM The Leading Edge. 10 One Major Causes of foundation settlement or more conditions may
More informationChapter 3 Pre-Installation, Foundations and Piers
Chapter 3 Pre-Installation, Foundations and Piers 3-1 Pre-Installation Establishes the minimum requirements for the siting, design, materials, access, and installation of manufactured dwellings, accessory
More informationSystem. Stability. Security. Integrity. 150 Helical Anchor
Model 150 HELICAL ANCHOR System PN #MBHAT Stability. Security. Integrity. 150 Helical Anchor System About Foundation Supportworks is a network of the most experienced and knowledgeable foundation repair
More informationIH-635 MANAGED LANES PROJECT, SEG. 3.2
IH-635 MANAGED LANES PROJECT, SEG. 3.2 Location: Dallas, Texas Owner: Texas Department of Transportation Client: Ferrovial Agroman Construction Cost: $1 Billion Construction Completion Date: December,
More informationOPERE DI PROTEZIONE CONTRO LA CADUTA MASSI: ASPETTI PROGETTUALI. Reti in aderenza. Daniele PEILA. Daniele PEILA
OPERE DI PROTEZIONE CONTRO LA CADUTA MASSI: ASPETTI PROGETTUALI Reti in aderenza 0 Simple mesh drapery system 1 Simple mesh drapery system 2 Fixed drapery sistem 3 Fixed drapery sistem 4 Fixed drapery
More informationINDIRECT METHODS SOUNDING OR PENETRATION TESTS. Dr. K. M. Kouzer, Associate Professor in Civil Engineering, GEC Kozhikode
INDIRECT METHODS SOUNDING OR PENETRATION TESTS STANDARD PENETRATION TEST (SPT) Reference can be made to IS 2131 1981 for details on SPT. It is a field edtest to estimate e the penetration e resistance
More informationENCE 4610 Foundation Analysis and Design
This image cannot currently be displayed. ENCE 4610 Foundation Analysis and Design Shallow Foundations Total and Differential Settlement Schmertmann s Method This image cannot currently be displayed. Strength
More informationATLAS RESISTANCE Pier Foundation Systems
ATLAS RESISTANCE Pier Foundation Systems Foundation Repair Systems for Civil Construction Applications: Residential, Commercial, Industrial Atlas Resistance Piers have been used to restore and/or stabilize
More informationStep 11 Static Load Testing
Step 11 Static Load Testing Test loading is the most definitive method of determining load capacity of a pile. Testing a pile to failure provides valuable information to the design engineer and is recommended
More informationEarth Pressure and Retaining Wall Basics for Non-Geotechnical Engineers
PDHonline Course C155 (2 PDH) Earth Pressure and Retaining Wall Basics for Non-Geotechnical Engineers Instructor: Richard P. Weber, P.E. 2012 PDH Online PDH Center 5272 Meadow Estates Drive Fairfax, VA
More informationSECTION 1 GENERAL REQUIREMENTS
Page 1 of 6 SECTION 1 GENERAL REQUIREMENTS 1. SCOPE OF WORK: The work to be performed under the provisions of these documents and the contract based thereon includes furnishing all labor, equipment, materials,
More information5/1/2013. Topics. The challenge is to better maintain native characteristics of soils during and after construction
PIN Foundations Topics Applications Design and Construction Flow Control Credits www.pinfoundations.com Copyright 2008, Pin Foundations, Inc. Curtis Hinman WSU Extension Faculty, Watershed Ecologist chinman@wsu.edu
More informationLoad and Resistance Factor Geotechnical Design Code Development in Canada. by Gordon A. Fenton Dalhousie University, Halifax, Canada
Load and Resistance Factor Geotechnical Design Code Development in Canada by Gordon A. Fenton Dalhousie University, Halifax, Canada 1 Overview 1. Past: Where we ve been allowable stress design partial
More informationGeotechnical Design Monopile Foundations for Offshore Wind Turbines
Geotechnical Design Monopile Foundations for Offshore Wind Turbines R.J.N.J. Luiken, Structural specialist Van Oord Dredging and Marine Contractors Copyright Van Oord 2012 1 Content Content - Company profile
More informationKentucky Lake Bridge Pile Load Testing Overview Ohio Transportation Engineering Conference Columbus, Ohio 10/28/2015
Kentucky Lake Bridge Pile Load Testing Overview Ohio Transportation Engineering Conference Columbus, Ohio 10/28/2015 Presented by: Jeff Dunlap, P.E. Terracon Consultants 1 Project Site Kentucky Official
More informationCONTRACT SPECIFICATIONS - SEISMIC ISOLATION BEARINGS
CONTRACT SPECIFICATIONS - SEISMIC ISOLATION BEARINGS 1.0 DESIGN 1.1 Scope of Work 1.1.1 This work shall consist of furnishing Isolation Bearings and installing Isolation Bearing Assemblies at the locations
More information4.3.5 - Breakaway Walls
4.3.5 - Breakaway Walls Elevation of a structure on a properly designed foundation reduces the potential for water damage from flooding. When the space below the lowest elevated floor is maintained free
More informationSUPPLEMENTAL SPECIFICATIONS CROSS SLOPE VERIFICATION:
September 22, 2009 Updated November 16, 2009 SUPPLEMENTAL SPECIFICATIONS CROSS SLOPE VERIFICATION: 1. DESCRIPTION: The cross slopes of the roadway are to be constructed as detailed in the plans and within
More informationHow To Model A Shallow Foundation
Finite Element Analysis of Elastic Settlement of Spreadfootings Founded in Soil Jae H. Chung, Ph.D. Bid Bridge Software Institute t University of Florida, Gainesville, FL, USA Content 1. Background 2.
More informationREINFORCED CONCRETE. Reinforced Concrete Design. A Fundamental Approach - Fifth Edition. Walls are generally used to provide lateral support for:
HANDOUT REINFORCED CONCRETE Reinforced Concrete Design A Fundamental Approach - Fifth Edition RETAINING WALLS Fifth Edition A. J. Clark School of Engineering Department of Civil and Environmental Engineering
More informationStrength Determination of "Tooth-Paste" Like Sand and Gravel Washing Fines Using DMT
Strength Determination of "Tooth-Paste" Like Sand and Gravel Washing Fines Using DMT David L. Knott, P.E. and James M. Sheahan, P.E. HDR Engineering, Inc. 3 Gateway Center Pittsburgh, PA 15222-1074 Phone:
More informationAPPENDIX G VOLUME DETERMINATION DRAFT FEASIBILITY STUDY
PORTLAND HARBOR RI/FS APPENDIX G VOLUME DETERMINATION DRAFT FEASIBILITY STUDY DRAFT Prepared for The Prepared by Anchor QEA, LLC TABLE OF CONTENTS TABLE OF CONTENTS... I LIST OF FIGURES... II LIST OF TABLES...
More informationChapter 3 DESIGN AND CONSTRUCTION FEATURES IMPORTANT TO SEISMIC PERFORMANCE
Chapter 3 DESIGN AND CONSTRUCTION FEATURES IMPORTANT TO SEISMIC PERFORMANCE To satisfy the performance goals of the NEHRP Recommended Seismic Provisions, a number of characteristics are important to the
More informationLymon C. Reese & Associates LCR&A Consulting Services Tests of Piles Under Axial Load
Lymon C. Reese & Associates LCR&A Consulting Services Tests of Piles Under Axial Load Nature of Services The company has a long history of performance of tests of piles and pile groups under a variety
More informationFigure A-1. Figure A-2. continued on next page... HPM-1. Grout Reservoir. Neat Cement Grout (Very Flowable) Extension Displacement Plate
Addendum HELICAL PULLDOWN Micropile (HPM) Introduction The HPM is a system for constructing a grout column around the shaft of a standard Helical Screw Foundation (see Figure A1). To begin the process,
More informationPage & Turnbull imagining change in historic environments through design, research, and technology
DCI+SDE STRUCTURAL EVALUATIONS OFFICE BUILDING, TOOL SHED & WATER TANK, AND BLACKSMITH & MACHINE SHOP BUILDINGS SAN FRANCISCO, CALIFORNIA [14290] PRIMARY PROJECT CONTACT: H. Ruth Todd, FAIA, AICP, LEED
More informationCaltrans Geotechnical Manual
Cone Penetration Test The cone penetration test (CPT) is an in-situ sounding that pushes an electronic penetrometer into soil and records multiple measurements continuously with depth. Compared with rotary
More informationTHE OBJECTIVES OF ROUTINE ROAD CUTS AND FILLS
Chapter 11 Slope Stabiliza bilization and Stability of Cuts and Fills THE OBJECTIVES OF ROUTINE ROAD CUTS AND FILLS are 1) to create space for the road template and driving surface; 2) to balance material
More informationThe demand for new roadway
Designing strong walls on weak soils Civil engineers have options to remedy foundation soil problems and meet project cost and schedule requirements. By Fadi Faraj, P.E.; Michael H. Garrison, P.E.; and
More informationStability. Security. Integrity.
Stability. Security. Integrity. PN #MBHPT Foundation Supportworks provides quality helical pile systems for both new construction and retrofit applications. 288 Helical Pile System About Foundation Supportworks
More informationNumerical Modelling for Shallow Tunnels in Weak Rock By Evert Hoek Unpublished Notes
Numerical Modelling for Shallow Tunnels in Weak Rock By Evert Hoek Unpublished Notes Introduction When designing a shallow tunnel in a poor quality rock mass, the designer has to face a number of problems
More informationAnalysis of the Interstate 10 Twin Bridge s Collapse During Hurricane Katrina
Analysis of the Interstate 0 Twin Bridge s Collapse During Hurricane Katrina By Genda Chen, Emitt C. Witt III, David Hoffman, Ronaldo Luna, and Adam Sevi The Interstate 0 Twin Span Bridge over Lake Pontchartrain
More informationUse and Application of Piezocone Penetration Testing in Presumpscot Formation
Use and Application of Piezocone Penetration Testing in Presumpscot Formation Craig W. Coolidge, P.E. Summit Geoengineering Services, Rockland, Maine ABSTRACT: This paper examines the advantages and limitations
More informationEurocode 7 - Geotechnical design - Part 2 Ground investigation and testing
Brussels, 18-20 February 2008 Dissemination of information workshop 1 Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing Dr.-Ing. Bernd Schuppener, Federal Waterways Engineering
More informationITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT
ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT Description: This work shall consist of furnishing all materials, equipment and labor necessary for conducting an Osterberg Cell (O-Cell) Load
More informationTable 4.9 Storm Drain Inlet Protetion Applicable for
BMP C220: Storm Drain Inlet Protection Purpose To prevent coarse sediment from entering drainage systems prior to permanent stabilization of the disturbed area. Conditions of Use Type of Inlet Protection
More informationSoil Mechanics. Outline. Shear Strength of Soils. Shear Failure Soil Strength. Laboratory Shear Strength Test. Stress Path Pore Pressure Parameters
Soil Mechanics Shear Strength of Soils Chih-Ping Lin National Chiao Tung Univ. cplin@mail.nctu.edu.tw 1 Outline Shear Failure Soil Strength Mohr-Coulomb Failure Criterion Laboratory Shear Strength Test
More informationApplication Study of FLAC in Analysis of Slope Stability
Application Study of FLAC in Analysis of Slope Stability HAO Fengshan, WANG Lei College of Civil and Traffic, Liaoning Technical University, Fuxin, Liaoning Abstract: FLAC is a numerical analysis software
More informationPART TWO GEOSYNTHETIC SOIL REINFORCEMENT. Martin Street Improvements, Fredonia, Wisconsin; Keystone Compac Hewnstone
GEOSYNTHETIC SOIL REINFORCEMENT Martin Street Improvements, Fredonia, Wisconsin; Keystone Compac Hewnstone DESIGN MANUAL & KEYWALL OPERATING GUIDE GEOSYNTHETIC SOIL REINFORCEMENT Keystone retaining walls
More informationDrained and Undrained Conditions. Undrained and Drained Shear Strength
Drained and Undrained Conditions Undrained and Drained Shear Strength Lecture No. October, 00 Drained condition occurs when there is no change in pore water pressure due to external loading. In a drained
More informationMOCK-UP TEST REPORT. Rendered to: TUBELITE, INC. PROJECT: 200 Series Curtain Wall Mock-Up
MOCK-UP TEST REPORT Rendered to: TUBELITE, INC. PROJECT: 200 Series Curtain Wall Mock-Up Report No: 85616.01-120-32 Test Completion Date: 01/15/09 Report Date: 02/11/09 Record Retention End Date: 01/15/13
More informationComparison of Seismic Retrofitting Methods for Existing Foundations in Seismological Active Regions
Comparison of Seismic Retrofitting Methods for Existing Foundations in Seismological Active Regions Peyman Amini Motlagh, Ali Pak Abstract Seismic retrofitting of important structures is essential in seismological
More informationGeotechnical Investigation using Standard Penetration Test (SPT) in Rangamati, Bandarban and Khagrachari Towns
1. Introduction 1.1 Scope of Work The Asian Disaster Preparedness Centre (ADPC) is implementing the project Seismic Hazard and Vulnerability Mapping for Rangamati, Bandarban and Khagrachari Municipality.
More informationResidential Deck Safety, Construction, and Repair
Juneau Permit Center, 4 th Floor Marine View Center, (907)586-0770 This handout is designed to help you build your deck to comply with the 2006 International Residential Building code as modified by the
More informationGeotechnical Measurements and Explorations Prof. Nihar Ranjan Patra Department of Civil Engineering Indian Institute of Technology, Kanpur
Geotechnical Measurements and Explorations Prof. Nihar Ranjan Patra Department of Civil Engineering Indian Institute of Technology, Kanpur Lecture No. # 13 (Refer Slide Time: 00:18) So last class, it was
More information