1 Procurement Strategy Homes for Haringey Achieving value for money should always be a priority for government, and it is never a finished process. Challenging economic circumstances impact directly on the public finances, and mean that the current drive for efficiency will be important to supporting continued improvement and investment in frontline services. This new operating environment comes after more than a decade of record levels of investment in public services. Some efficiency savings take time to deliver, requiring changes to contracts or major restructuring of services. That is why it is right to look ahead into the next spending review period as well as looking for short-term savings. (Source: Operational Efficiency Programme, Final Report 2009) 1. Introduction... Page 2 2. Background and Achievements Page 3 3. Strategy Review. Page 4 4. The Future Aspirations for the Next Five Years Page 6 5. Aspirations in Action. Page 7 Appendices to Strategy Appendix 1 Action Plan for Procurement: Years 1 and 2 Appendix 2 Larger Procurement Projects to be completed in Appendix 3 Current Situation Appendix 4 List of Procurement Team Authorities 2010 (to be completed) Appendix 5 Function of the Procurement Team (to be completed) Appendix 6 Key Performance Indicators Appendix 7 Tender Flowchart Appendix 8 Value for Money Reporting Homes for Haringey Limited: Procurement strategy 1

2 1. Introduction 1.1 Homes For Haringey Homes for Haringey Ltd was set up in 2006 by Haringey Council as an Arms Length Management Organisation (ALMO) with the aim to manage over 21,000 tenanted and leasehold homes. The procurement activity is integral part of the organisation s business and is delegated across the service departments Procurement occurs in cases where commercial transactions result in acquisition of goods, services and works from third parties. The concept of public procurement relates to the fact that Homes for Haringey Ltd is a public service organisation and its employees spend public money, consequently the organisation is required by law to comply with EU procurement directives and UK regulations in relation to the way it spends public funds. Public procurement is about Compliance, Risk and Cost Reduction Scope of this Strategy This strategy applies to staff with procurement responsibilities, budget holders, Executive Management Team and Senior Managers at Homes for Haringey, and anybody who by virtue of their professional position carry out procurement activity, or is a stakeholder to whom procurement is accountable, e.g. residents This strategy refers to any spend with third party providers funded by Homes for Haringey s management fee Relationship of Procurement Strategy to HfH Vision and Business Plan Homes for Haringey s vision is to be an outstanding provider of housing management services. To realise this vision the Executive Management Team have identified the role that Procurement must fulfil and the contribution and benefits this will bring to the organisation The effect of this role, and the impact of this strategy, will be to ensure leadership in all strategic and significant Procurement activities. This strategy will: facilitate the introduction of procedures to ensure that Procurement is regulatory compliant; will mitigate Risk and deliver consistent Value for Money. The supply chain will reflect Homes for Haringey s commitment not only to Sustainable Development but also for safe, healthy, working practices enjoyed by equal and diverse workforces This focus on Procurement will ensure that in-house personnel concerned with non strategic and transactional purchasing are advised and guided as to the most appropriate routes to market to ensure Value for Money is achieved. This may be by use of existing Haringey Council collaborative contracts, participation in other collaborative Framework Agreements negotiated by the Office of Government Commerce (OGC), or other recognised collaborative purchasing organisations or by benefiting from Homes for Haringey s devolved position to undertake specific procurements on their own behalf. Homes for Haringey Limited: Procurement strategy 2

3 1.3.4 The objective of this strategy is to shape the future activity of Homes for Haringey s Procurement to ensure achievement of the Vision. 1.4 Value for Money More than any other department Procurement must demonstrate that Value for Money has been achieved. In practical terms this necessity to concentrate on how the money is spent must be driven by a clear analysis of where the money is spent in relation to Homes for Haringey s Business Plan, market conditions, suppliers and spend categories. 2. Background and Achievements 2.1 Haringey Council Procurement Service Over the period the procurement activity was supported entirely by Haringey Council s Corporate Procurement Unit (CPU). CPU led the repairs and maintenance services procurement project on behalf of Homes for Haringey Client Department. CPU also directed a range of procurements within Homes for Haringey Design and Engineering Service. To date Homes for Haringey continues to procure most of the common goods and services using collaborative contracts originally set up by Haringey Council CPU. 2.2 Internalised Procurement Service In 2009 as a result of a Value for Money review a Procurement Manager post was created and filled to provide advice and support in an operational environment which has increasingly become more and more regulated. Over the period procurement has played a significant role in increasing value from external services. 2.3 Procurement Projects completed in Replacement of Fleet of Vehicles for the Repairs Service This was a further competition drawn from collaborative Framework Agreement. A contract was awarded at the level of approximately 7m over a period of four years. The market testing led to a saving of 900,000 compared to the previous contract which represents per cent saving. This procurement contributed to cost avoidance of 720,000 enabling the business unit to keep within budget Introduction of e-procurement card for fuel As a high volume, low value commodity, fuel was a suitable supply for e-procurement cards. This e-procurement card was introduced following an award from Procurement for Housing Single Supplier Framework Agreement. In addition to financial savings there have been significant process and environmental benefits Voids Subcontractors Repairs and Cleaning Services An EU tendering process was completed to support the Vacant Properties Repairs and cleaning services at 1.3 mln annual value and a multi-supplier Framework Agreement was awarded across three areas of activity. If contractors are used to the same level as previously the annual savings are up to 258,000. Homes for Haringey Limited: Procurement strategy 3

4 This project achieved a major supplier rationalisation by reducing significantly the number of suppliers used and exercised supplier leverage in that existing suppliers retained level of business at significantly reduced prices. It is considered that the use of an e- Auction necessitated further price reductions by the suppliers Stores Options: Procurement Analysis of Stores Operation Stores analysis identified areas of improvement of the in-house stores operation and materials sourcing. If the project is undertaken by the business, the savings generated on spend of 1.742m will be between 186k and 226k in year one, and 148k pa thereafter Spend data analysis and carbon audit Homes for Haringey were the first ALMO to undertake spend data analysis and have ongoing access to the Observatory database for up-to-date elaboration on spend. This facilitates the rapid interrogation and graphical presentation of all aspects of Homes for Haringey s spend data. The spend data analysis will also provide a carbon audit which will define the carbon foot print of the suppliers used by the organisation and the actions necessary to reduce the carbon impact of the business on the environment Introduction of e-procurement systems at Homes for Haringey Ltd and transforming tendering activity to e-tendering A range of e-procurement tools have been introduced in the business. These tools will generate both cashable and non-cashable efficiencies including environmental benefits contributing to Homes for Haringey s green agenda. E-notice, e-tender, erfx and e-auction tools have been introduced in the service and are currently utilised by relevant staff. 3. Strategy Review 3.1 This Procurement Strategy covers the period Reviews will be undertaken annually to reflect not only achievement of objectives but also changing market conditions, government policies and other factors, presently unforeseen, which will impact upon the strategy. 3.2 Major principles The following major principles are deemed inherent within and to the application of this strategy All aspects and actions consequent with the implementation of this Procurement Strategy, both internal and externally facing, will be undertaken in accordance with and strict adherence to Homes for Haringey s principles and policies in respect of: equality and diversity sustainability value for money continuous improvement through innovation and lean structures and systems stakeholder involvement (tenants and leaseholders) Homes for Haringey Limited: Procurement strategy 4

5 3.3 Current Situation In the last full financial year Homes for Haringey did business with 325 trade suppliers, spending approximately 17.9M, which equates to 68% of the management fee. Suppliers based within the London Borough of Haringey accounted for 8.48% of the spend. Please see details in Appendix There is significant duplication of resources in both purchasing processes and authorities. The impact of these duplications is to obscure inefficiencies and the failure to maximise purchasing power, supplier leverage or achieve full Value for Money The lack of a central contract database prevented a number of tenders being subjected to the full tender process; consequently Value for Money will not have been achieved The successes of the procurement projects undertaken within 2009 / 10 demonstrated the benefits which can be enjoyed by the move away from the existing, traditional tender process and the adoption of E-procurement and the creation of a partially centralised procurement function. In addition to the financial, cashable savings realised to date the new technology and procedures introduce a unified tendering process which not only sets out a consistent, methodical approach it will also produce non-cashable savings, in respect of process efficiencies, and environmental benefits resulting from the significant reduction in both paper and other stationery products. Homes for Haringey Limited: Procurement strategy 5

6 3.3.5 Strategic procurements to be undertaken within the next financial year are shown at Appendix The Future Aspirations for the Next Five Years 4.1 Procurement will be recognised as a leading contributor to the Homes for Haringey vision. 4.2 The prime objective to ensure regulatory compliance in all Procurement activity will be achieved. No challenges will be made as a consequence of the Remedies Directive which came into force on 20 December No Contract Awards will be deemed ineffective or set aside, no financial penalties, or delays incurred as a consequence of Homes for Haringey Procurements being challenged by unsuccessful bidders. 4.3 Homes for Haringey s objectives, reflecting Government Policy in respect of Value for Money and Sustainable Procurement will continue to deliver both financial and non financial benefits. 4.4 The strategic approach adopted to the reduction of costs, the increase in value and obtaining more for less will deliver significant financial benefits. All targets for cashable savings and cost avoidance will be achieved or surpassed. 4.5 The Procurement Team will have been self financing since formation. 4.6 Systems will be implemented for professional operation of a partly devolved, partly centralised procurement function. 4.7 Waste levels will be significantly reduced and the ongoing practice of the doctrine Reduce, Re-use, Recycle will continue to deliver environmental benefits and reduce Carbon Footprint further. 4.8 The 2010 Inspection will identify procurement within Homes for Haringey as having demonstrated Significant Prospects for Improvement. 4.9 The rationalised and reduced Supply Base will continue to supply goods and services of the required quality at competitive prices. All Contracts will be procured utilising E-procurement methodologies The Supply Base will reflect the demographics of the London Borough of Haringey and will comprise SME s, BME s, larger organisations, the voluntary sector and Partnerships. All suppliers will endorse and practice Homes for Haringey s policies and principles in respect of Equality and Diversity. Personnel will work in safe, healthy environments The Supply chain will sponsor and administer training schemes to assist the unemployed return to the workplace Suppliers will adopt and implement measurable continuous improvement programmes. Homes for Haringey Limited: Procurement strategy 6

7 4.13 Our supply partners will be accredited to specific oversight organisations such as Constructionline / CHAS (Contractors Health and Safety Assessment Scheme) to ensure ongoing compliance with Health & Safety and other applicable legislation. Homes for Haringey require suppliers not only to work in a safe manner but also to have employee safety in mind at all times. Our Suppliers will be encouraged to achieve OHSAS18001 certification Suppliers will be encouraged to achieve recognised external Quality Standards. e.g. ISO Our suppliers will be encouraged to implement appropriate environmental policies, ISO14001 or BS8555. The resulting benefits of these policies will be publicised to encourage other companies to adopt similar policies Homes for Haringey will work with the supply chain to implement the Sustainable Procurement Agenda making them aware of the needs and benefits the introduction of these policies will bring to all Homes for Haringey will undertake an extensive audit programme to address all aspects of a supplier s business in line with the Value for Money Strategy Existing Service Level Agreements, with both external organisations and London Borough of Haringey will be reviewed through Best Value and principles of efficiency, effectiveness and economy. 5. Aspirations in Action 5.1 People Forming and resourcing a procurement team with the necessary skills and attributes will be the first priority. Appendix 4 contains the relevant authorities and Appendix 5 functional responsibilities The strategy will be communicated to stakeholders by undertaking training events, briefing sessions and publications on website. Homes for Haringey Procurement Code of Practice will be developed as an operational tool for staff on procurement. Please see Appendix 7 for Homes for Haringey Tender Flowchart. 5.2 Processes Introduction of a consolidated contracts register and procurement calendar will enable procurement to have sight of, and address any issues to ensure compliance with procurement legislation Homes for Haringey will undertake a range of actions on the development of a procurement infrastructure and processes governing the relationships between procurement and users. This will reduce the number of authorised procurers and result in greater control and oversight of spend These actions will also include category management to comply with aggregation rules, the organisational wide roll out of e-procurement Homes for Haringey Limited: Procurement strategy 7

8 tools and systems for tender management, contract management; and Purchase-to-Pay systems The procurement transformation will include actions such as introducing p-cards where appropriate. Efficiency savings will also be achieved by reducing the number of purchase Invoices currently processed. The introduction of Fuel Cards has already shown the impact this technology can achieve. The wider introduction of Purchase Cards will not only further rationalise supplier base but also further generate non-cashable and environmental benefits. 5.3 Providers In accordance with the EU regulations our providers will be sourced by way of competitive tendering processes undertaken by Homes for Haringey, or other public sector bodies such as Office of Government Commerce, Haringey Council, Procurement for Housing, etc Homes for Haringey will investigate and wherever possible, involve the voluntary sector Homes for Haringey will investigate opportunities for entering into Partnering Contracts where it is considered they will deliver long-term benefits Rationalisation of the supplier base will provide greater opportunity for suppliers to develop strategically and subsequently to ensure maximum value is obtained from these strategic suppliers We will communicate with our suppliers to increase their understanding of our sustainable development, best value and equality objectives Suppliers who currently generate an excessive number of purchase invoices will be approached to provide consolidated monthly invoicing Regular reports on performance against key performance indicators will be provided (see Appendix 6) Value for Money Reports will be provided (see Appendix 8) The action plan, attached at Appendix 1, will be implemented. 5.4 Perceived Risks Non-compliance for challenges Failure to resource, both financial and human resources Lack of suitable working environments Stakeholder acceptance of strategy Expedience supersedes procedural and regulatory requirements Changes in government policy impacting on housing management services Homes for Haringey Limited: Procurement strategy 8

NUNEATON & BEDWORTH BOROUGH COUNCIL

NUNEATON & BEDWORTH BOROUGH COUNCIL NUNEATON & BEDWORTH BOROUGH COUNCIL PROCUREMENT STRATEGY 2012 2016 Both the Gershon Efficiency Review (2004) and the Roots Review (2009) highlighted the fundamental role Procurement plays in achieving

More information

PROCUREMENT STRATEGY

PROCUREMENT STRATEGY PROCUREMENT STRATEGY 2010 2014-1 - Contents SECTION Page 1. INTRODUCTION 3 2. THE STRATEGY RATIONALE 3 3. STRATEGIC OUTCOMES 5 4. SUPPORTING CORE BUSINESS DELIVERY 11 5. ENSURING EFFECTIVE PROCUREMENT

More information

Brent Council Corporate Procurement Strategy 2005

Brent Council Corporate Procurement Strategy 2005 Brent Council Corporate Procurement Strategy 2005 The Corporate Management Team endorsed a Corporate Procurement Strategy in September 2003. A number of interim reports to the Corporate Management Team

More information

Procurement Strategy The City Council s Procurement Strategy for the period

Procurement Strategy The City Council s Procurement Strategy for the period Procurement Strategy The City Council s Procurement Strategy for the period 2014-2016 1 Name Content Creator Darren Pearce, Strategic Manager Corporate Procurement, Stoke-on-Trent City Council darren.pearce@stoke.gov.uk

More information

Commissioning and Procurement Strategy

Commissioning and Procurement Strategy Cardiff Council Commissioning and Procurement Strategy 2011-2015 Delivering Quality and Value Proud to Deliver Contents Foreword Part 1 - Introduction 1.1 Purpose of the Strategy 1.2 Why Commissioning

More information

Corporate Procurement Strategy

Corporate Procurement Strategy Corporate Procurement Strategy 2012-2016 Created: October 2012 Version: 04 Page 1 of 13 Contents 1. Introduction... 3 1.1 Definition... 3 1.2 Purpose... 3 1.3 Aims and objectives... 3 2. Procurement at

More information

DRAFT. London Borough of Merton Procurement Strategy

DRAFT. London Borough of Merton Procurement Strategy DRAFT London Borough of Merton Procurement Strategy 2013-2016 3 Foreword Welcome to Merton s procurement strategy, which outlines our aims for the period 2013 2016 and shows how procurement will contribute

More information

Group Procurement Policy. Policy Owner: Executive Director Finance and Resources

Group Procurement Policy. Policy Owner: Executive Director Finance and Resources Group Procurement Policy Policy Owner: Executive Director Finance and Resources 0 Control Date Policy level Regulatory / Strategic Policy Reference FR/001/2012 Link to Strategy Procurement Strategy Version

More information

Gosport Borough Council. Procurement Strategy. Pursuit of Excellence

Gosport Borough Council. Procurement Strategy. Pursuit of Excellence Gosport Borough Council Procurement Strategy Delivering for Gosport Pursuit of Excellence Contents Page 1 Introduction to Gosport Borough Council s 2 Procurement Strategy 2 Strategic framework 3 3 Procurement

More information

Oadby and Wigston Borough Council PROCUREMENT STRATEGY

Oadby and Wigston Borough Council PROCUREMENT STRATEGY Oadby and Wigston Borough Council PROCUREMENT STRATEGY JUNE 2006 1 Contents Page(s) 1. Context...3 2. Oadby & Wigston s Vision for Procurement...3 3. Progress to Date...4 4. Procurement in the Organisation...4

More information

MOLE VALLEY DISTRICT COUNCIL CORPORATE PROCUREMENT POLICY & PRINCIPLES Secure the best goods and services available, appropriate to its needs

MOLE VALLEY DISTRICT COUNCIL CORPORATE PROCUREMENT POLICY & PRINCIPLES Secure the best goods and services available, appropriate to its needs MOLE VALLEY DISTRICT COUNCIL CORPORATE PROCUREMENT POLICY & PRINCIPLES 2016 Procurement Policy Statement Mole Valley District Council will Secure the best goods and services available, appropriate to its

More information

How to do Business with the London. Borough of Sutton

How to do Business with the London. Borough of Sutton How to do Business with the London Borough of Sutton February 2013 1 About this guide This guide has been developed to assist businesses wishing to sell their goods and services to the Borough. Contents

More information

PROCUREMENT STRATEGY

PROCUREMENT STRATEGY PROCUREMENT STRATEGY 2013-2017 Contents Introduction 3 Strategic Procurement in Context 4 Key Principles for Effective Procurement 6 Priorities for Improving Procurement 11 Procurement Action Plan 14 Forward

More information

Procurement Strategy. June Procurement Strategy

Procurement Strategy. June Procurement Strategy June 2015 Procurement Strategy Contents 1. VISION 2. PURPOSE 3. PROCUREMENT OBJECTIVES 4. PROCUREMENT AIMS 5. PROCUREMENT MEASURES 6. KEY PERFORMANCE INDICATORS 7. REVIEW Page 2 of 10 1 VISION Proactive

More information

Brentwood Borough Council

Brentwood Borough Council Brentwood Borough Council Strategy March 2014 Page 1 of 11 Index 1. Foreword... 3 2. Introduction... 4 2.1 The Purpose of... 4 2.2 The Current Situation... 4 2.3 Our Vision for... 5 2.4 Our Definition

More information

Procurement Strategy

Procurement Strategy Shetland Islands Council Corporate Services Capital Programme Service Procurement Strategy 2012-2015 Document: Procurement Strategy Approved: Author: Procurement Manager Stage: Final Date: February 2012

More information

PROCUREMENT STRATEGY

PROCUREMENT STRATEGY PROCUREMENT STRATEGY 2013 2016 Contents Foreword...1 Executive Summary...2 Background...2 1. Contributing to Council Strategy & Policy...3 2. Supporting Economic Development & Regeneration...4 3. Delivering

More information

SOUTH NORFOLK COUNCIL PROCUREMENT STRATEGY 2012 TO 2015

SOUTH NORFOLK COUNCIL PROCUREMENT STRATEGY 2012 TO 2015 SOUTH NORFOLK COUNCIL PROCUREMENT STRATEGY 2012 TO 2015 CONTENTS Introduction 1. What is Procurement? 2. The National Context 3. Objectives of the Procurement Strategy Procurement within South Norfolk

More information

PROCUREMENT STRATEGY

PROCUREMENT STRATEGY PROCUREMENT STRATEGY CONTENTS 1. Introduction What is procurement? Background Aims Procurement landscape Themes and principles How procurement is organised in Bexley 2. Our Strategy Strategy Approach 3.

More information

Corporate Procurement Strategy 2014-2017

Corporate Procurement Strategy 2014-2017 Strategy 2014-2017 Strategy 2014-2017 Introduction The Brighton & Hove community is distinctive for its strong international flavour and vibrant diversity of cultures. The make-up of the local population,

More information

BT EDUCATION & LOCAL GOVERNMENT. Strategic Sourcing. Transforming Procurement in Local Government

BT EDUCATION & LOCAL GOVERNMENT. Strategic Sourcing. Transforming Procurement in Local Government BT EDUCATION & LOCAL GOVERNMENT Strategic Sourcing Transforming Procurement in Local Government Transforming the way things get done Strategic Sourcing: Value through joined-up purchasing BT is working

More information

Ipswich Borough Council. Corporate Procurement and Commissioning Strategy

Ipswich Borough Council. Corporate Procurement and Commissioning Strategy Ipswich Borough Council Corporate Procurement and Commissioning Strategy The Corporate Procurement Strategy sets out the Vision and Strategic Aims, which direct and govern the Council s procurement activities.

More information

Procurement Indicators

Procurement Indicators Procurement Indicators Procurement value for money indicators guidance 1) Introduction This document sets out the indicators to be collected for the Procurement function. The guidance below starts by defining

More information

Appendix A Lancashire County Council Procurement Strategy October 2014

Appendix A Lancashire County Council Procurement Strategy October 2014 Appendix A Lancashire County Council Procurement Strategy October 2014 Foreword Lancashire County Council spends approximately 529m per year through procurement. The goods, services and works we procure

More information

Output Specification: Procurement. Output Specification: Procurement Service March 2013

Output Specification: Procurement. Output Specification: Procurement Service March 2013 Output Specification: Procurement Service March 2013 1 1 Contents 1 Contents... 2 2 Document Ownership... 2 3 Definitions... 3 4 Scope... 4 5 Data Room Documents... 7 6 Service Requirements... 9 7 Performance

More information

Procurement & Supply Chain Team. Purpose of the Role

Procurement & Supply Chain Team. Purpose of the Role Role: Responsible To: Responsible For: Location: Procurement & Supply Chain Manager Assistant Director of Finance Procurement & Supply Chain Team Liverpool Purpose of the Role Oversee the group s procurement

More information

University of Brighton Sustainable Procurement Strategy 2011-2015

University of Brighton Sustainable Procurement Strategy 2011-2015 University of Brighton Sustainable Procurement Strategy 2011-2015 Sustainable procurement in a challenging environment Introduction There is widespread recognition that climate change and the use of dwindling

More information

GMFRS Strategy. Procurement Finance and Technical Services. Greater Manchester Fire and Rescue Service. Policy Template (Draft)

GMFRS Strategy. Procurement Finance and Technical Services. Greater Manchester Fire and Rescue Service. Policy Template (Draft) GMFRS-45-38 Strategy Procurement 2015-2018 Finance and Technical Services Greater Manchester Fire and Rescue Service Policy Template (Draft) July 2012 Contents Contents... 2 Document Details... 3 Document

More information

Corporate Procurement Strategy

Corporate Procurement Strategy Worcestershire County Council Corporate Procurement Strategy 2013 1 7 Find out more online: www.worcestershire.gov.uk Foreword The Council adopted a new Corporate Plan in June 2011 with four key areas

More information

Delivering Customer Focused Outcomes and Value for Money through Commissioning and Procurement

Delivering Customer Focused Outcomes and Value for Money through Commissioning and Procurement Delivering Customer Focused Outcomes and Value for Money through Commissioning and Procurement Procurement Strategy 2012-2015 V1.0 Please consider the environment if you need to print this document and

More information

Procurement Strategy

Procurement Strategy Procurement Strategy 2014-15 www.gwynedd.gov.uk Table of content 1. Introduction 1.1 Procurement in Gwynedd 1.2 What we have achieved 2. Local Benefit from Procurement Spend 2.1 Category management 2.2

More information

Hertsmere Borough Council. Corporate Procurement Strategy

Hertsmere Borough Council. Corporate Procurement Strategy Hertsmere Borough Council Corporate Procurement Strategy 2007-2010 1. Introduction Hertsmere Borough Council ( the Council ) published its first Corporate Procurement Strategy in 2003. This was in response

More information

CABINET. 18 December 2013

CABINET. 18 December 2013 CABINET 18 December 2013 Title: Procurement of Various Supplies and Service Contracts Report of the Cabinet Member for Finance Open Report Wards Affected: None Report Author: Martin Storrs, Head of Procurement

More information

Delivering e-procurement Local e-gov National e-procurement Project Overarching Guide to e-procurement for LEAs

Delivering e-procurement Local e-gov National e-procurement Project Overarching Guide to e-procurement for LEAs 1. Introduction Background The National e-procurement Project (NePP) and Centre for Procurement Performance (CPP) are working to support and enable schools to meet their e- Government targets and to gain

More information

Page 97. Executive Head of Asset Planning, Management and Capital Delivery

Page 97. Executive Head of Asset Planning, Management and Capital Delivery Page 97 Agenda Item 7 Report to: Strategy and Resources Committee Date: 16 December 2013 Report of: Executive Head of Asset Planning, Management and Capital Delivery Ward Location: Not applicable Author

More information

Procurement Strategy. STAR Procurement is the shared procurement service for Stockport, Trafford and Rochdale Councils

Procurement Strategy. STAR Procurement is the shared procurement service for Stockport, Trafford and Rochdale Councils Procurement Strategy STAR Procurement is the shared procurement service for Stockport, Trafford and Rochdale Councils Foreword 1 This STAR Procurement Strategy sets out the strategic direction and priorities

More information

PROCUREMENT INVESTING IN CAMDEN

PROCUREMENT INVESTING IN CAMDEN PROCUREMENT INVESTING IN CAMDEN Procurement Strategy 2012-2015 London Borough of Camden Contents Front Page Page 1 Contents Page 2 Introduction Page 3 Camden Plan-Procurement contribution Page 4 01 Social

More information

How are companies currently changing their facilities management delivery model...?

How are companies currently changing their facilities management delivery model...? Interserve and Sheffield Hallam University market research 2012 Page 2 www.commercial.interserve.com How are companies currently changing their facilities management delivery model...? we have a strategy

More information

National e-procurement Project Delivering e-procurement

National e-procurement Project Delivering e-procurement National e-procurement Project Delivering e-procurement Desktop Guide to e-procurement Part 6: How to create a Business Case for e-procurement Supported by Office of the Deputy Prime Minister Delivering

More information

Merseyside Fire & Rescue Authority

Merseyside Fire & Rescue Authority Merseyside Fire & Rescue Authority PROCUREMENT STRATEGY 2015-2018 1 Version 1 June 2015 2 Document Version Control Issue No Date Issued by 1 9 th June 2015 Sharon Matthews CONTENTS 1. INTRODUCTION... 4

More information

JOINT PROCUREMENT STRATEGY

JOINT PROCUREMENT STRATEGY JOINT PROCUREMENT STRATEGY 2012-2016 Contents Foreword... 3 Introduction... 4 Strategic Procurement... 4 Key Principles for Effective Procurement... 7 Priorities for Improving Procurement...11 Procurement

More information

Luton Borough Council Corporate Procurement Strategy ( )

Luton Borough Council Corporate Procurement Strategy ( ) Luton Borough Council Corporate Procurement Strategy (2015 2019) Version: V1.7 Revised July 2015 Due for Revision March 2019 0 Contents Foreword... 2 Executive Summary... 3 Introduction... 4 Sustainable

More information

West Suffolk Procurement Strategy

West Suffolk Procurement Strategy West Suffolk Procurement Strategy 2014-2016 DOCUMENT SPONSOR Rachael Mann Head of Resources & Performance DOCUMENT AUTHOR Ziaul Quader Procurement Manager DOCUMENT APPROVED BY SEBC 24.06.2014 CABINET ON

More information

Vision Business Plan 2015 to 2020

Vision Business Plan 2015 to 2020 Vision 2020 Business Plan 2015 to 2020 Contents Para Page 1.0 Introduction 3 2.0 Our Mission 4 3.0 Our Aims 4 4.0 Our Values 5 5.0 Our Environment National Context Local Context Residents Staff 5-9 6.0

More information

Gloucester City Council PROCUREMENT STRATEGY

Gloucester City Council PROCUREMENT STRATEGY Gloucester City Council PROCUREMENT STRATEGY 2011-2016 Financial Services May 2011 Definitions Procurement The action of obtaining or procuring something; Financial assistance for the procurement of legal

More information

Shared service centres

Shared service centres Report by the Comptroller and Auditor General Cabinet Office Shared service centres HC 16 SESSION 2016-17 20 MAY 2016 4 Key facts Shared service centres Key facts 90m estimated savings made to date by

More information

Procurement Strategy 2007 to 2011

Procurement Strategy 2007 to 2011 Procurement Strategy 2007 to 2011 1 CONTENTS INTRODUCTION Aims of the Strategy What is Procurement? The Council s Strategic Objectives Council Spending Managing Risk PROCUREMENT STRATEGY SUMMARY PROVIDING

More information

Procurement and Contract Management Strategy 2013-2017

Procurement and Contract Management Strategy 2013-2017 Procurement and Contract Management Strategy 2013-2017 Title Owner Version 1 Distribution Procurement and Contract Management Strategy 2013 2017 Procurement and Performance Manager Corporate Issue date

More information

MPA/MPS PROCUREMENT STRATEGY 2009-12 TO BE THE UK LEADER IN PUBLIC SECTOR PROCUREMENT

MPA/MPS PROCUREMENT STRATEGY 2009-12 TO BE THE UK LEADER IN PUBLIC SECTOR PROCUREMENT MPA/MPS PROCUREMENT STRATEGY 2009-12 TO BE THE UK LEADER IN PUBLIC SECTOR PROCUREMENT CONTENTS Foreword ------------------------------------------------------------------------ 3 Executive Summary ---------------------------------------------------------

More information

Buckinghamshire & Milton Keynes Fire Authority

Buckinghamshire & Milton Keynes Fire Authority Procurement Strategy 2015-2020 ITEM 7 Buckinghamshire & Milton Keynes Fire Authority MEETING Executive Committee DATE OF MEETING 19 November 2014 OFFICER LEAD MEMBER SUBJECT OF THE REPORT EXECUTIVE SUMMARY

More information

QSS 0: Products and Services without Bespoke Contracts.

QSS 0: Products and Services without Bespoke Contracts. QSS 0: Products and Services without Bespoke Contracts. Amendment History Version Date Status v.1 Dec 2014 Updated For 2015 deployment Table of Contents 1. DEFINITIONS 3 2. INTRODUCTION 3 3. WORKING WITH

More information

Halton Borough Council. Procurement Strategy

Halton Borough Council. Procurement Strategy Halton Borough Council Procurement Strategy 2013-2016 1 Procurement Strategy Halton Borough Council 2013-2016 Foreword As a Council, we spend considerable sums of money on contracts; supplies and services;

More information

Purchasing and Managing Software Licences

Purchasing and Managing Software Licences Purchasing and Managing Software Licences REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 579 Session 2002-2003: 1 May 2003 LONDON: The Stationery Office 8.25 Ordered by the House of Commons to be printed

More information

Cork City Council CORPORATE PROCUREMENT PLAN

Cork City Council CORPORATE PROCUREMENT PLAN Cork City Council CORPORATE PROCUREMENT PLAN 2008 2010 Foreword Cork City Council is committed to delivering excellent quality services. The role a strategic approach to procurement has in achieving such

More information

Procurement Strategy

Procurement Strategy Procurement Strategy 2009 2013 Version 1.0 final Latest revision: 12 th May 2009 Contents Section Page Contacting Us 6 Foreword 7 1 Introduction 9 2 Application 10 3 What is Procurement? 10 4 Why Procurement

More information

Procurement Strategy 2013-2017 Delivering Social Value for our Community

Procurement Strategy 2013-2017 Delivering Social Value for our Community Procurement Strategy 2013-2017 Delivering Social Value for our Community Making Bath & North East Somerset an even better place to live, work and visit 1 Picture courtesy of Bath & News Media Group Our

More information

Our Commitment to a Sustainable Future A strategy for a sustainable future

Our Commitment to a Sustainable Future A strategy for a sustainable future Our Commitment to a Sustainable Future A strategy for a sustainable future The Newcastle Upon Tyne Hospitals NHS Foundation Trust 1 Climate change is one of the greatest threats to our health and well-being.

More information

Procurement and contract management strategy

Procurement and contract management strategy Procurement and contract management strategy Approved 2015 by Contents 1 Introduction...3 1.1 Purpose of procurement and contract management strategy 1.2 What is procurement? 1.3 What is contract management?

More information

Business Charter for Social Responsibility

Business Charter for Social Responsibility Business Charter for Social Responsibility This Charter describes the spirit, style and behaviours we will adopt and will expect our partners/suppliers to adopt as we jointly work together in an open,

More information

Appendix 1 - Procurement Strategy

Appendix 1 - Procurement Strategy Appendix 1 Appendix 1 - Procurement Strategy 2015 2020 1. Introduction This document sets out the strategic vision for procurement at Canterbury Christ Church University for the next five years. It has

More information

DORSET & WILTSHIRE FIRE AND RESCUE AUTHORITY Performance, Risk and Business Continuity Management Policy

DORSET & WILTSHIRE FIRE AND RESCUE AUTHORITY Performance, Risk and Business Continuity Management Policy Not Protectively Marked Item 6 Appendix B DORSET & WILTSHIRE FIRE AND RESCUE AUTHORITY Management Policy The Dorset & Wiltshire Fire and Rescue Authority () is the combined fire and rescue authority for

More information

PROCUREMENT STRATEGY April 2014 March 2017

PROCUREMENT STRATEGY April 2014 March 2017 PROCUREMENT STRATEGY April 2014 March 2017 Table of Contents 1. Contacts... 1 2. Introduction... 2 3. Structure... 4 4. Context... 6 5. Aims of the strategy... 7 7. Socially responsible procurement...

More information

Lancashire Combined Fire Authority PROCUREMENT STRATEGY

Lancashire Combined Fire Authority PROCUREMENT STRATEGY Lancashire Combined Fire Authority PROCUREMENT STRATEGY 2015-2018 Version 1 March 2015 Page 1 Document Version Control Issue No Date Issued by 1 4 th March 2015 Kim Larter CONTENTS 1. INTRODUCTION... 3

More information

Contents. Introduction Page 3. Section 1 Strategic Aim Page 4. Section 2 Professionally Resourced Page 5

Contents. Introduction Page 3. Section 1 Strategic Aim Page 4. Section 2 Professionally Resourced Page 5 Contents Introduction Page 3 Section 1 Strategic Aim Page 4 Section 2 Professionally Resourced Page 5 Section 3 Economic, Social and Environmental Impact Page 6 Section 4 Community Benefits Page 7 Section

More information

PROCUREMENT STRATEGY MAKING THE CHANGES MAXIMISING VALUE

PROCUREMENT STRATEGY MAKING THE CHANGES MAXIMISING VALUE PROCUREMENT STRATEGY 2011-2015 MAKING THE CHANGES MAXIMISING VALUE Page 1 of 29 CONTENTS INTRODUCTION 3 1 ABOUT THIS STRATEGY 1.1 SCOPE 4 1.2 IMPORTANCE TO THE COUNCIL 4 1.3 STRATEGY PURPOSE 5 1.4 STRATEGIC

More information

NCC Procurement Strategy

NCC Procurement Strategy PROCUREMENT STRATEGY 2016 2019 Foreword This procurement strategy sets out our vision and strategies demonstrating how we aim to use procurement to help Newport City Council deliver the Vision for Newport

More information

PROCUREMENT STRATEGY

PROCUREMENT STRATEGY Inverness College UHI Page 1 of 8 PROCUREMENT STRATEGY ST/CS/2011/001 Lead Officer (Post): Finance Officer Review date: April 2014 Department: Corporate Services Review Lead Officer (Post): Director of

More information

NATIONAL E-PROCUREMENT PROJECT GUIDANCE NOTES

NATIONAL E-PROCUREMENT PROJECT GUIDANCE NOTES NATIONAL E-PROCUREMENT PROJECT GUIDANCE NOTES PROCUREMENT SPEND ANALYSIS Title: Procurement Analysis Identification: Supports organisations in gathering and analysing procurement spend to highlight system

More information

Appendix A. Procurement Strategy 1

Appendix A. Procurement Strategy 1 Appendix A Procurement Strategy 2016 2019 Procurement Strategy 1 Title of Document: Procurement Strategy Document Date: 12 th December 2015 Author/s: Service Responsible for this document: Directorate:

More information

e-procurement A Guide For Suppliers

e-procurement A Guide For Suppliers e-procurement A Guide For Suppliers 1. Introduction Background The Government has given councils targets for the implementation of e-procurement and for benefits to be achieved from e-procurement. These

More information

REPORT 4 FOR DECISION. This report will be considered in public

REPORT 4 FOR DECISION. This report will be considered in public REPORT 4 Subject: Safety Readiness for the Summer 2013 Events Programme Agenda item: Public Item 7 Report No: 4 Meeting date: 28 May 2013 Report to: Board Report of: Mark Camley, Interim Executive Director

More information

This strategy has been developed by Corporate Procurement in line with The Council s high level priorities which are as follows:-

This strategy has been developed by Corporate Procurement in line with The Council s high level priorities which are as follows:- PROCUREMENT STRATEGY 1 Introduction Introduction to the Corporate Strategy for Procurement This document sets out the Council s Corporate. Its purpose is to provide Officers, Members, Contractors and the

More information

CITY OF LONDON PROCUREMENT STRATEGY MAY 2009

CITY OF LONDON PROCUREMENT STRATEGY MAY 2009 CITY OF LONDON PROCUREMENT STRATEGY MAY 2009 CONTEXT Definition Procurement is the process of acquiring goods, works and services, covering both acquisitions from third parties and from in house providers.

More information

Commissioning & Procurement Strategy Putting Blackpool First

Commissioning & Procurement Strategy Putting Blackpool First Commissioning & Procurement Strategy 2016-19 Putting Blackpool First Contents 1. Foreword... 1 2. Introduction... 2 3. Council Vision... 3 3.1. Local Context... 4 3.2. Regional Context... 4 3.3. National

More information

CABINET. 24 March 2015

CABINET. 24 March 2015 CABINET 24 March 2015 Title: Procurement of Electricity and Gas Supplies Report of the Cabinet Member for Finance Open Report with Exempt Appendix 4 Wards Affected: All Report Author: Andrew Sivess Group

More information

PROCUREMENT STRATEGY

PROCUREMENT STRATEGY PROCUREMENT STRATEGY Author: Responsible Lead Executive Director: Laura Ace & Terry Dunthorne Laura Ace Endorsing Body: Lanarkshire NHS Board meeting (25/9/13) Governance or Assurance Committee Audit Committee

More information

AUDIT & PERFORMANCE REVIEW COMMITTEE ON 26 TH SEPTEMBER 2007

AUDIT & PERFORMANCE REVIEW COMMITTEE ON 26 TH SEPTEMBER 2007 PAGE: 1 REPORT TO: SUBJECT: BY: AUDIT & PERFORMANCE REVIEW COMMITTEE ON 26 TH SEPTEMBER 2007 ASSET MANAGEMENT CHIEF FINANCIAL OFFICER 1. REASON FOR REPORT 1.1 To provide the Audit and Performance Review

More information

Procurement Strategy

Procurement Strategy Procurement Strategy Three Rivers Procurement Strategy Version 1.1 (August 2013) Contents Introduction... 3 Key Strategic Aims of the Procurement Strategy... 4 Visions and Objectives... 4 Strategic Parameters...

More information

Delivering e-procurement Local e-gov National e-procurement Project Overarching Guide to e-procurement for Schools

Delivering e-procurement Local e-gov National e-procurement Project Overarching Guide to e-procurement for Schools 1. Introduction Background The National e-procurement Project (NePP) and Centre for Procurement Performance (CPP) are working to support and enable schools to meet their e- Government targets and to gain

More information

DUBLIN CITY COUNCIL CORPORATE PROCUREMENT PLAN

DUBLIN CITY COUNCIL CORPORATE PROCUREMENT PLAN DUBLIN CITY COUNCIL CORPORATE PROCUREMENT PLAN 2015 2017 1 CORPORATE PROCUREMENT PLAN 2015-2017 CONTENTS 1. Introduction 3 2. Objectives 4-5 3. The Procurement Plan 6 4. Implementation 7-8 5. Procurement

More information

Bawden Contracting Services Ltd Job Profile. Contracts Manager. Purpose of the Job

Bawden Contracting Services Ltd Job Profile. Contracts Manager. Purpose of the Job Contracts Manager Purpose of the Job As Contracts Manager you will manage all aspects of the Grounds Maintenance contracting business safely and efficiently, maximising profitability through the completion

More information

Council Procurement Strategy ( ) DRAFT

Council Procurement Strategy ( ) DRAFT Council Procurement Strategy (2012-2015) DRAFT Foreword The launch of this three year strategy is a good opportunity to meet the challenging times ahead. More than ever before, public sector finance is

More information

Safety, Health, Environment and Quality Management. The Biffa Way

Safety, Health, Environment and Quality Management. The Biffa Way Safety, Health, Environment and Quality Management. The Biffa Way We will keep our people, our customers and the environment safe and take action if we see danger. Ian Wakelin Chief Executive 2 SHEQ Management

More information

PROCUREMENT & PAYMENT SERVICES STRATEGY & POLICY

PROCUREMENT & PAYMENT SERVICES STRATEGY & POLICY PROCUREMENT & PAYMENT SERVICES STRATEGY & POLICY 2015 2017 Contents Contents...1 Foreword Deputy Leader (Finance)...2 Procurement & Payment Services Strategy 2015-2017...3 1. Introduction...3 2. Ambition

More information

Procurement Guide. How to tender for the Council s. higher value services and. supply needs

Procurement Guide. How to tender for the Council s. higher value services and. supply needs Procurement Guide How to tender for the Council s higher value services and supply needs This guide has been developed to assist businesses wishing to do business with the London Borough of Bexley. 116

More information

7.11a: Quality in Project Management: PRINCE2 and ISO 9000

7.11a: Quality in Project Management: PRINCE2 and ISO 9000 7.11a: Quality in Project Management: PRINCE2 and ISO 9000 An overview of the PRINCE2 Method (PRINCE2 is a Trade Mark of the Office of Government Commerce) by Peter Whitelaw, Rational Management Pty Ltd,

More information

CONTENTS. Introduction. Background. Outcomes. 1. Making Savings 2. Supporting Local Economies 3. Leadership 4. Modernising Procurement.

CONTENTS. Introduction. Background. Outcomes. 1. Making Savings 2. Supporting Local Economies 3. Leadership 4. Modernising Procurement. CONTENTS Introduction Background Outcomes 1. Making Savings 2. Supporting Local Economies 3. Leadership 4. Modernising Procurement Conclusions Contacts Introduction Procurement is a key part of the government

More information

1. Executive Summary. 2. Definitions

1. Executive Summary. 2. Definitions 1. Executive Summary The aim of this strategy is to explain the different facets of e-procurement and clearly set out how Procurement Lincolnshire will approach e-procurement. This document links with

More information

Sustainable Supply Chain Policy

Sustainable Supply Chain Policy Sustainable Supply Chain Policy 1. Contents Page 2. Introduction & Purpose 1 3. Definitions 1 4. Benefits of a Sustainable approach to the Supply Chain 2 5. Operational Context 2 6. Elements & Principles

More information

Preparing an Environmental Policy

Preparing an Environmental Policy Preparing an Environmental Policy Compiled by Keith Snook May 2009 1/5 Background An environmental policy is an agreed documented statement of a business's stance towards the environment in which it operates.

More information

(2) That the contract runs from 1 April 2015 for an initial period of seven years. The value of the contract will be in the order of 10m per annum.

(2) That the contract runs from 1 April 2015 for an initial period of seven years. The value of the contract will be in the order of 10m per annum. Cabinet Member for Corporate Relations Redesign of Facilities Management Services April 2014 Report by Director Service Operations and Principal Manager Facilities Management Ref No: CR02(14/15) Key Decision:

More information

FIN01.1 Procurement Strategy

FIN01.1 Procurement Strategy FIN01.1 Procurement Strategy All College policies and procedures adhere to the guidelines and ethos of Equality and Diversity. When printed this document becomes UNCONTROLLED COPY Always refer to the Intranet

More information

University of Edinburgh Procurement Strategy 2012 16 updated May 2013

University of Edinburgh Procurement Strategy 2012 16 updated May 2013 University of Edinburgh Procurement Strategy 2012 16 updated May 2013 At the University of Edinburgh, we aim to meet our needs for goods, services and works in a way that achieves value for money on a

More information

How to tender for Council work a guide for contractors, suppliers and service providers

How to tender for Council work a guide for contractors, suppliers and service providers How to tender for Council work a guide for contractors, suppliers and service providers Contents 1 Introduction 4 2 Rules affecting works, supplies, and services 5 General rules 5 European Law 5 UK Law

More information

Procurement strategy

Procurement strategy Procurement strategy 2015-2018 Contents 1. Introduction... 3 1.1 Background... 3 1.2 Supplier Spend... 3 1.3 Local Impact... 3 2. Scope of the strategy... 3 3. Drivers and Challenges... 4 3.1 As part of

More information

Procurement Strategy

Procurement Strategy North West Ambulance Service NHS Trust Procurement Strategy 2015/16-2019/20 REFERENCE: FD.P.001 Document Control/ Changes Recommended By Written By Head of Procurement Approved by Approved Date Version

More information

Qualification Snapshot CIH Level 4 Certificate in Managing Responsive Repairs (QCF)

Qualification Snapshot CIH Level 4 Certificate in Managing Responsive Repairs (QCF) Qualification Snapshot CIH Certificate in Managing Responsive Repairs (QCF) The Chartered Institute of Housing (CIH) is an awarding organisation for national qualifications at levels 2, 3 and 4. CIH is

More information

PROCUREMENT STRATEGY:

PROCUREMENT STRATEGY: MIDLOTHIAN COUNCIL PROCUREMENT STRATEGY: 2015-2018 Page 1 Content 1. Foreword 3 2. Context 4 3. Review of Previous Activity 5 4. Objectives 6 5. Corporate Procurement Policy 8 5.1 Vision 8 5.2 Policy Principles

More information

SUFFOLK COUNTY COUNCIL PROCUREMENT RULES. Version 2 Jan 2016. Page 1 of 19

SUFFOLK COUNTY COUNCIL PROCUREMENT RULES. Version 2 Jan 2016. Page 1 of 19 SUFFOLK COUNTY COUNCIL PROCUREMENT RULES 2015 Version 2 Jan 2016. Page 1 of 19 TABLE OF CONTENTS 1. Introduction and Definitions... 3 2. Scope... 4 3. General Principles... 5 4. Responsibilities... 7 5.

More information

Cabinet Decision (Supplementary Report to the Contracts Forward Plan Q1 Report )

Cabinet Decision (Supplementary Report to the Contracts Forward Plan Q1 Report ) Cabinet Decision (Supplementary Report to the Contracts Forward Plan Q1 Report ) 5 th April 2016 Report of: Zena Cooke, Corporate Director of Resources Classification: [Unrestricted] Procurement Strategy

More information