1 Ashdown Richmond heights Lansdown Bath BA1 5QJ Te: E mail: ag@charlcombe.com Salix House 40 Westwells Neston Wilts SN13 9RQ Tel: E mail: jh@charlcombe.com Feb. 13 Rev. A CONSTRUCTION METHOD STATEMENT This Construction Method Statement is being prepared in order to discharge condition 7 on the planning consent ref: 11/05146/FUL. Final Risk Assessments and construction details are not available at this time but will be submitted as and when they become available if required. BRIEF PROJECT DESCRIPTION: This project involves the construction of five detached houses on a site to the east of Ensleigh House on the northern slopes of Bath. The houses will be built by Charlcombe Homes Ltd, which has already built several houses in the location. PROJECT DETAILS: 1. The registered office of Charlcombe Homes is: Ashdown Richmond Heights Lansdown Bath BA1 5QJ 2. Technical director of Charlcombe Homes, John Hartley, will have overall responsibility for the construction project. 3. Constraints on the planning consent concerning the resident bat will mean that construction will commence in March of 2013 after the bat has completed it s winter hibernation. 4. The project is to construct five, high quality, contempory detached houses together with the access roads, retaining walls and service installations. The site is set away from the Granville Road to the east and is set at a considerably lower level than the road. Access to the site will be via two access roads, one either side of Ensleigh House, which will be installed at the start of the project. 5. It is anticipated that the works will take around eighteen months to complete although it is hoped that this program can be reduced. 1
2 SIGNIFICANT CONSIDERATIONS ASSOCIATED WITH THE SITE: The bat: 1. A bat survey has been carried out and it has been established that there is a pipistrelle bat that is roosting in the roof space of Oakdene, the house that exists on the site at present. 2. Since this building will need to be demolished to make way for the development, it has been agreed that a purpose built bat barn will be erected to provide a replacement roosting space for the bat. 3. Additional bat boxes will also be installed on some of the houses to provide alternative accommodation for the bat. 4. This will be one of the first tasks of the project, after the roads have been installed to access the site. The protected trees: 1. There are protected trees on the site and also on the adjacent site. A Detailed Arboricultural Method Statement has been produced that details exactly what measures are required to avoid damage to the trees. 2. Both access roads will pass through, or close to, protected trees and so installing services to the site, down both these roads, this will almost certainly require some careful hand excavation. 3. There is a large protected conifer in the north eastern corner of the site and some tree protection fencing will be required around the tree. This will be erected at the very beginning of the project and not removed until completion. The ground conditions: 1. The site is set within a land slip plane above Bath and extensive ground investigation works have been carried out to assess the ground conditions. The Ground Investigation Report indicates that there is a slip plane around 3.0m down and this will require some extensive piling to ensure that the houses are founded on good ground. 2. The gardens will also require stabilising and it is expected that a row of piles will be required across lower side of the site, terminating below ground level, in order to stabilise the gardens to the houses. 3. These engineering works will be designed in detail with the assistance of the ground investigation company Core Geotechnical and the structural engineers, Pro Structures. 2
3 4. Both these organisations have experience of designing piling and ground works in these complex areas. Access: 1. There are two existing access points to the site and both these will be used as access to the site. Both these access roads will require upgrading to allow the passage of construction vehicles and access to the houses for the end purchasers. 2. These upgrading works will need to be carried out in strict adherence with the detailed Arboricultural Method Statement. 3. Both the access roads are single lane with limited turning heads at the site end. A risk assessment will be carried out to assess the risk this posses but it is suspected that a banks person will be required at all times for safe vehicular egress from the site. Services: 1. Introducing mains services to a site like this can be problematic in itself. Both access routes are through Root Protection Zones and so some hand digging will be required for the trenches for these services. 2. The bottom of the site is some 22m below the road so a significant sewage pumping unit will need to be installed to pump the sewage up to the drain in Granville Road. It is intended to run this rising main up the service trench so as to minimise disruption to the trees. PRE CONTRACT PAPERWORK: 1. Prior to commencement on site all the necessary planning conditions will be discharged in full. 2. This project will require full compliance with the current CDM legislation and an independent CDM Coordinator will be employed to manage the preparation and flow of health and safety information as required by the current CDM Regulations. 3. We will undertake a full, intrusive asbestos survey of Oakdene, the existing house, so that all the asbestos can be removed prior to demolishing the building. 4. The technical design of the new houses will be made with health & safety in mind so as to minimise the residual risks on site. Those risks that cannot be designed out will be assessed and the relevant risk assessments and task specific method statements produced. 5. The Construction Phase Health & Safety Plan will be prepared and this will be added to as the work advances. This document will be 3
4 produced and checked by the CDM Coordinator for compliance with the current regulations. 6. A building regulation application will be made to Bath and North East Somerset Council for the five houses. Charlcombe Homes has developed a good working relationship with BANES Building Control and we certainly intend to continue this relationship. 7. We employ the services of local health & safety advisors, The Building Safety Group, and they will monitor the works as they progress and their involvement will be vital. 8. Charlcombe Homes has an extremely good health and safety record and fully intends to maintain this record on this project. PROPOSED ORDER OF CONSTRUCTION 1. Before any site works commence the tree protection fencing will be erected and inspected and approved by BANES. 2. The next part of the project will involve the formation of the two access routes into the site. These are shown on the planning drawings and existing routes are being followed wherever possible. 3. Since there are protected trees on the site and on the adjacent site, the tree protection works will need to be carried out in conjunction with the access works. 4. Arboricultural works will be carried out in accordance with the Detailed Arboricultural Method Statement. 5. The existing house will then be demolished and crushed for re-use on the site. By crushing the building on site we are able to use the house as hardcore and so minimise road journeys and landfill. 6. The site will then be re-graded and the piling matts installed in readiness for the piling installation. 7. The sequence of work following this has yet to be programmed but a detailed program of works can be submitted when available if this is required. 4
5 SITE OPERATIONAL ARRANGEMENTS: Site deliveries: Materials and plant will only be delivered to the site between 8.00am and 5.30pm on Monday to Friday. No deliveries will take place on Saturdays or Sundays. All materials will be stored on site in designated storage positions ready to be used in the house construction. Contractors parking: The site is extremely tight in terms of access and the space on the site will be limited for materials storage, site welfare and management. Contractor s vehicles will need to be parked on Granville Road in permitted parking zones. Vehicle Management: Both the site access points are quite tight although they do accord with the appropriate visibility splays. If for any reason a vehicle is not able to leave the site in a forward direction, a banks person will be used to allow the safe egress from the site. 5
CONSTRUCTION TRAFFIC MANAGEMENT PLAN (CTMP)
CONSTRUCTION TRAFFIC MANAGEMENT PLAN (CTMP) [Colston Budd Hunt & Kafes Pty Ltd AS AMENDED BY City of Sydney] 23 March 2010 1. PREAMBLE 1.1 This document constitutes the Demolition and Traffic Management
More informationTree Condition Survey for Proposed Taplow Footbridge at Ray Mill Island and Taplow Riverside, Mill Lane Taplow, Buckinghamshire
Tree Condition Survey for Proposed Taplow Footbridge at Ray Mill Island and Taplow Riverside, Mill Lane Taplow, Buckinghamshire Tree Condition Survey for Proposed Taplow Footbridge at Ray Mill Island and
More informationCONSTRUCTION SEQUENCE & PROGRAMME
CONSTRUCTION SEQUENCE & PROGRAMME 2 CONTENTS 1.0 Introduction 7 2.0 Key activities 8 2.1 Airport related activities 2.2 Construction of new roads and accesses 2.3 Earthworks zone a 2.4 Earthworks zone
More informationPlease describe the proposal accurately and concisely. State the number of storeys proposed and the position of any extensions.
Householder Application for Planning Permission for Works or Extension to a Dwelling and for Relevant Demolition in a Conservation Area Town and Country Planning Act 1990 1. Applicant Name and Address
More informationConstruction Traffic Management Plan
Introduction This (CTMP) has been prepared in order to discharge Condition 20 of planning permission ref 07/02879/EFUL for the enabling site works associated with the wider Bath Western Riverside development.
More informationBUILDING OVER OR NEAR WATER & SEWER MAINS POLICY
MURRAY SHIRE COUNCIL BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY ADOPTED: 1 May 2012 1 BUILDING OVER OR NEAR WATER AND SEWER MAINS POLICY CONTENTS 1. Objective... 2 2. Requirements for Building Near
More informationIALN11006400 /05 01 19.06.13. FAO: The Planning Department The Royal Borough of Windsor and Maidenhead Town Hall, St. Ives Road Maidenhead SL6 1RF
IALN11006400 /05 01 19.06.13 FAO: The Planning Department The Royal Borough of Windsor and Maidenhead Town Hall, St. Ives Road Maidenhead SL6 1RF Dear Sir / Madam Re: 12/02994 BCA Sports Hall Condition
More informationConstruction Management Plan Template
Plan Template Planning Permit Number:... Date Planning Permit Issued:... Approval Stamp (Office Use only): Standard Plan Template Project details Company Operational Details.. Directors Name Company Name
More informationRev Issue Status Prepared / Date Approved/Date. - Draft 1 LOA / 15.09.14 JSE / 19.09.14
Nancy Hawksworth Barn Conversion: Moor Farm, London Road, Shardlow, Derbyshire Bat Survey Report September 2014 FPCR Environment and Design Ltd Registered Office: Lockington Hall, Lockington, Derby DE74
More informationGuidelines for Rights of Way
Guidelines for Rights of Way Guidelines for Statutory Rights of Way for Engineering and Public Works Infrastructure Rights of Way (Drainage, Sanitary, Water & Electrical Utilities) A Statutory Right of
More informationConstruction Management Plan (CMP) Application
About this form Principal Contractor (Applicant) Applicant Details (Person lodging application and main contact for CMP) DA and Site Details Development Consent for Works you are carrying out Construction
More informationLT McGuinness Site 10 Development, Wellington Waterfront. Construction Traffic Management Plan. 7 October 2014
LT McGuinness Site 10 Development, Wellington Waterfront Construction Traffic Management Plan 7 October 2014 TDG Ref: 12950 141007 ltm ctmp final report.docx LT McGuinness Site 10 Development, Wellington
More informationHouseholder Application for Planning Permission for Works or Extension to a Dwelling Town and Country Planning Act 1990
Householder Application for Planning Permission for Works or Extension to a Dwelling Town and Country Planning Act 1990 1. Applicant Name and Address Please enter the Applicant Details, including full
More informationSMS0045 Construction Health and Safety Policy and Procedures
SMS0045 Construction Health and Safety Policy and Procedures March 2015 Version 8 Please note that for projects utilising a CDM Co-ordinator under the transitional arrangements of CDM 2015 (between 6 April
More informationPART 4: SITE INFORMATION
TRANSNET PIPELINES TENDER NUMBER: PYP/W1/6/21/1646 DESCRIPTION OF THE WORKS: CONSTRUCTION OF THE FIRE PROTECTION SYSTEM UPGRADE FOR THE FUEL HANDLING AREAS OF THE TARLTON DEPOT AND IRP REFRACTIONATOR ONLY
More informationErection of replacement warehouse building and erection of two buildings in connection with builder s merchants
Plan: O 02/00708/FUL Thames Ward (A) Address: Development: Applicant: London Works, Ripple Road, Barking Erection of replacement warehouse building and erection of two buildings in connection with builder
More informationCITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES
CITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES INTRODUCTION What is a Construction Management Plan? The City of Vincent requires careful management of construction involving excavation and retention
More informationA Casebook of Fatal Accidents Related to Work-at-Height
A Casebook of Fatal Accidents Related to Work-at-Height Occupational Safety and Health Branch Labour Department Occupational Safety and Health Council This casebook is prepared by the Occupational Safety
More informationCroft House Lodge Tree Removal and Building Relocation Mitigation Report. November 2010
Croft House Lodge Tree Removal and Building Relocation Mitigation Report November 2010 1 A site meeting was held on 24/05/2010 at the site of the proposed Croft House Lodge Respite Centre, Carleton Road,
More informationBuilding over or close to a public sewer
Building over or close to a public sewer thameswater.co.uk/developerservices thameswater.co.uk/developerservices 1 Questions and answers Did you know Thames Water is legally responsible for more than 100,000
More informationCONSTRUCTION TRAFFIC MANAGEMENT PLAN Issue 2, V5, 11/11/13
Note: Please refer to the end of this document for guidance notes about completing this form Q1. What is the full postal address of the site? Your response Q2. Planning reference and revision number (if
More information19-27 Young Street Development Kensington
19-27 Young Street Development Kensington Construction Management Plan Resident Update Draft 2nd October 2013 υ Introduction An initial construction management meeting took place on Tuesday 10 th September
More information1 Welcome. The exhibition comprises a series of boards which provide some background information to show you our initial ideas for the site.
1 Welcome Thank you for taking the time to attend this public exhibition of our proposals for residential development on Land at Daws Farm, Back Road, Writtle (site shown opposite). The exhibition comprises
More informationLiquid Effluent Treatment Plant (LETP) Land Clean-Up
Liquid Effluent Treatment Plant (LETP) Land Clean-Up Frequently Asked Questions What is proposed? Magnox Ltd is proposing to remove the redundant Liquid Effluent Treatment Plant (LETP) at Harwell and to
More informationTHE TOWN AND COUNTRY PLANNING ACT 1990 Grant of Planning Permission
Civic Offices Havant Hampshire PO9 2AX Tel (023)9247 4174 Fax(023)9244 6588 DX50005 Havant www.havant.gov.uk To: ADP Architects Ltd Richmond Court 94 Botley Road Park Gate Southampton, Hants SO311BA For:
More informationCONSTRUCTION TRAFFIC MANAGEMENT PLAN V11, 26/09/12
If the project you are constructing was subject to planning permission and a condition requiring a Construction Traffic Management Plan (CTMP) was applied to the planning consent, this condition will need
More informationConstruction Traffic Management Plan
Construction Traffic Management Plan Proposed Additional Accommodation for SWDPLS Shinners Bridge Dartington Produced for and on behalf of Built Environments Team Devon County Council NPS South West Ltd
More informationExcavation & Trenching Procedure
Excavation & Trenching 1. Overview The will ensure, as far as is reasonably practicable, that the conduct of work relating to excavation and trenching will not be harmful to the health and safety of employees
More informationIt was my assignment to physically inspect the 8 trees on site near the proposed construction,
July 11, 2013 Tariton Properties 2555 Park Blvd Palo Alto, CA 94306 Re: Tree Survey To Whom It May Concern: Assignment It was my assignment to physically inspect the 8 trees on site near the proposed construction,
More informationKnock Down Rebuild. Building Process Building process - knock down rebuild 1
Knock Down Rebuild Building Process Building process - knock down rebuild 1 Building Process Your action Our action REMINDER Pre site Step 1 New Home Selection Congratulations. This marks the start of
More informationApproval Services Unit
Approval Services Construction Management Plan Pro-Forma Commercial Properties Please complete the enclosed form and return to:- By Mail: Approval Services Unit City of Perth Council House 27 St Georges
More informationDrainage. Information for those with problem drains
Drainage Information for those with problem drains Contents 1 Purpose 2 Introduction 2 Explanations: what is a drain and what is a sewer 3 Explanation of the responsibilities for public and private sewers
More informationDemolition & Construction Management Plan
Demolition & Construction Management Plan 72 76 Cadogan lane SW1 Demolition & Construction Management Plan Issue Date: March 2013 Contents: 1.0 Introduction 1.1 Objectives of the Plan 1.2 Project Overview
More informationStrategy Deployment Through Collaborative Planning. Linking the Strategy to Practical Activity
Strategy Deployment Through Collaborative Planning Linking the Strategy to Practical Activity Establish the Strategic Goal. After the Collaborative Planning activity Collaborative Planning iterative and
More informationTHIS PAGE INTENTIONALLY LEFT BLANK
THIS PAGE INTENTIONALLY LEFT BLANK Construction Traffic Management Plan 2 Contents 1. Introduction... 4 1.1 Conditions of Consent... 4 2. Goals of the CTMP... 6 2.1 Objectives... 6 2.2 Predicted Construction
More informationSan Antonio Water System Standard Specifications for Construction ITEM 866 SEWER MAIN TELEVISION INSPECTION
ITEM 866 SEWER MAIN TELEVISION INSPECTION 866.1 DESCRIPTION: The Contractor shall furnish all labor, materials, equipment, and incidentals to provide the televising and a NASSCO-(PACP) standard video,
More informationWORKING AT HEIGHT GUIDELINES. Version II
WORKING AT HEIGHT GUIDELINES Version II 21 st September 2011 WORKING AT HEIGHT GUIDELINES EXECUTIVE SUMMARY Working at height is where an individual is carrying out work in any place in the course of obtaining
More informationCAPITAL WORKS GUIDANCE DOCUMENT
COMMUNITY BUILDINGS TRANSFER PROGRAMME CAPITAL WORKS GUIDANCE DOCUMENT This document has been prepared to assist and advise management groups of community buildings who are involved in Durham County Council
More information1. It would create hazardous effects of storm water run-off. 3. It would increase hazardous driving conditions on the public road.
SECTION 6: REQUIREMENTS FOR A DRIVEWAY CONNECTION A. Required information. The application shall be accompanied by a sketch of the proposed driveway which at a minimum shall indicate: 1. Geometric information
More informationConstruction Management Statement. Residential development at Bywell House, St Mary s Hill, Ascot
Construction Management Statement Residential development at Bywell House, St Mary s Hill, Ascot Parking of Vehicles of Site Personnel, Operatives and Visitors Site staff, visitors to the development and
More informationConstruction Site Set Up Requirements
Process Code Number Revision COP A 035 B Document Title Construction Site Set Up Requirements B 1/11/10 SRC SAT DH Final A 1/10/10 SRC MI Draft comment Rev. Date Prepared Reviewed Approved Detail/Comment
More informationFederation of Piling Specialists
Federation of Piling Specialists COMPANY NAME CONTRACT NAME TENDER REF SCHEDULE OF ATTENDANCES AND FACILITIES TO BE PROVIDED BY THE CLIENT TO A STEEL SHEET PILING SPECIALIST For the purposes of this document
More informationTHE UNIVERSITY OF SHEFFIELD WORK AT HEIGHT POLICY
THE UNIVERSITY OF SHEFFIELD WORK AT HEIGHT POLICY CONTENTS Page No 1 INTRODUCTION 2 2 LEGISLATION 2 3 HIERARCHY OF CONTROL 2 4 WORK AT HEIGHT POLICY 3 5 ROLES AND RESPONSIBILITIES 3 6 RISK ASSESSMENTS
More informationWelcome Welcome to the public exhibition for development at Bowman Field. This exhibition provides an overview of the proposals for the site.
Welcome Welcome to the public exhibition for development at Bowman Field. This exhibition provides an overview of the proposals for the site. Background & Planning Context The Site The site is an area
More informationSEEKING COMPLETENESS WAIVERS AND PRELIMINARY & FINAL SITE PLAN APPROVAL
APPLICATION & REPORTS FOR PB2009-05 INTERNATIONAL DEVELOPMENT CORPORATION SEEKING COMPLETENESS WAIVERS AND PRELIMINARY & FINAL SITE PLAN APPROVAL MEMORANDUM TO: FROM: RE: Borough of Tinton Falls
More informationThe Granary, Back Street, Reepham, Norwich NR10 4SJ Tel. 01603 308 051 enquiries@internetsurveysltd.com www.internetsurveysltd.com
The Granary, Norwich NR10 4SJ Tel. 01603 308 051 enquiries@internetsurveysltd.com www.internetsurveysltd.com R E P O R T P R E P A R E D F O R Mrs J McCleave P R O P E R T Y A D D R E S S R I S K M A N
More information5. Specific Use Regulations
5. Specific Use Regulations 5.1 Application 5.1.1 The specific use regulations shall apply to all development unless otherwise exempted in this section. 5.1.2 Where these regulations may be in conflict
More informationSPECIFICATION NET LINE 1 - Wilkinson Street Diamond Crossing (WSDC) re-ballast
General Requirements: The existing fixed diamond crossing at the Armstrong Way / Wilkinson Street junction (NG7 7NW) has become contaminated with material from roadway run-off and requires re-ballasting
More informationK M D Hire Services, LONDON ROAD, NANTWICH, CW5 6LU
Application No: 11/2196N Location: Proposal: Applicant: Expiry Date: K M D Hire Services, LONDON ROAD, NANTWICH, CW5 6LU Extension and New Store Mr Dan Mellor 17-Aug-2011 SUMMARY RECOMMENDATION Approve
More informationA guide to appointing an architect
A guide to appointing an architect and to being a good client Hurditch Architecture, 24 Botallack, St Just, Penzance, Cornwall, TR19 7EP Page 1 of 7 RIBA Chartered Architects Architects act 1997 In the
More informationAppendix 8 Providing Pre-construction information and check list (Regulations 10)
Appendix 8 Providing Pre-construction information and check list (Regulations 10) Project specific health and safety information STFC will have procedures in place to ensure that there is timely release
More informationGuide Document for Development of WHS Management Plans
DISCLAIMER: THIS DOCUMENT IS PROVIDED AS GUIDANCE TO ASSIST CONTRACTORS IN MEETING THEIR OBLIGATIONS UNDER THE WHS LAW AND NTG CONTRACTS. NTG DOES NOT ACCEPT ANY RESPONSIBILITY FOR THE CONTENTS OF CONTRACTORS
More informationApplication No: 5/11/9004 District: South Lakeland
DEVELOPMENT CONTROL AND REGULATION COMMITTEE 20 July 2011 A Report by the Assistant Director - Planning & Sustainability Application No: 5/11/9004 District: South Lakeland Applicant: United Utilities Clearwater
More informationConstruction Management Statement. Introduction. Contents
Construction Management Statement Project Name Dee Point Primary School Introduction On all Morgan Sindall projects, the safety and welfare of all is of paramount importance. This document concentrates
More informationKAWERAU DISTRICT COUNCIL BUSINESS DISASTER RECOVERY PLAN 2011
KAWERAU DISTRICT COUNCIL BUSINESS DISASTER RECOVERY PLAN 2011 Kawerau District Council Private Bag 1004 Ranfurly Court KAWERAU 3169 Tel (07) 306 9009 Fax (07) 323 8072 Email kaweraudc@kaweraudc.govt.nz
More informationWeeping Tile Disconnection to Reduce the Impact of Basement Flooding London, Ontario
Weeping Tile Disconnection to Reduce the Impact of Basement Flooding London, Ontario September 19, 2013 Kyle Chambers, P.Eng. City of London Environmental and Engineering Services Department Today s presentation
More informationFigure 5.6a Construction worksites and corridor access Note: Indicative only, subject to detailed design.
A 0 NORTH 200 metres George Lane worksite North Strathfield Station worksite Strath eld Triangle A B Existing rail corridor Proposed underpass approach New/extended bridge Worksites Existing track Proposed
More informationUNDERGROUND TELECOMMUNICATIONS CABLES ACROSS PRIVATE LAND
FACT SHEET TELEPHONE 0800 327 646 I WEBSITE WWW.FEDFARM.ORG.NZ UNDERGROUND TELECOMMUNICATIONS CABLES ACROSS PRIVATE LAND BACKGROUND The Rural Broadband Initiative envisages substantially improved broadband
More informationPollution & Noise from Demolition & Construction Sites
CONTROL OF Pollution & Noise from Demolition & Construction Sites N oi se Co ns tru ct io n MAY 2008 THE LONDON BOROUGH 3 CONTENTS Part 1 Introduction Page 1. Background 4 2. Purpose of the code 5 3.
More informationBasements and Deep Building Construction Policy 2014
Basements and Deep Building Construction Policy 2014 APPROVAL Council / CEO 27 October 2014 VERSION NO: Version 1.0 TRIM REF: 14/67838 REVIEW 30/10/2019 RESPONSIBLE EXECUTIVE General Manager City Assets
More informationConstruction and Civil Work Management
STANDARD LME-12:001901 Uen Rev A Contents 1 Introduction... 3 2 Definitions... 3 3 Requirements... 4 3.1 General... 4 3.2 Responsibilities... 4 3.3 OHS Safety Plan... 5 3.4 Start of Construction Phase...
More informationPolicy for the Management of Asbestos in Buildings
in Buildings Health and Safety Services 1 A1. Introduction If asbestos fibres enter the lungs they can cause cancer or incurable disease. Consequently the University is committed to ensure that all reasonably
More information1.1 The application property is an extended two-storey semi-detached house fronting Bedale Road. The side garden adjoins a link road to Wydale Road.
COMMITTEE REPORT Date: 13 October 2011 Ward: Osbaldwick Team: Major and Parish: Osbaldwick Parish Commercial Team Council Reference: 11/02264/FUL Application at: 27 Bedale Avenue Osbaldwick York YO10 3NG
More informationSOIL-MAT ENGINEERS & CONSULTANTS LTD.
SOIL-MAT ENGINEERS & CONSULTANTS LTD. 130 LANCING DRIVE, HAMILTON, ONTARIO L8W 3A1 PHONE (905) 318-7440 FAX (905) 318-7455 E-MAIL: info@soil-mat.on.ca PROJECT NO.: SM 145464-E JANUARY 16, 2014 1371975
More information4 Alternatives and Design Evolution
4 Introduction 4.1 This Chapter describes the considerations and constraints influencing the siting, layout and massing of the Development. It also describes the main alternatives to the Development that
More informationFoul Drainage, systems and responsibility. Environmental Protection
Foul Drainage, systems and responsibility Environmental Protection The Building Act 1984 The Building Act 1984 can be used to deal with unsatisfactory provision for drainage and appliances which are harmful
More informationCompliance Noise Monitoring
Monitoring Byron Centre The Manse Road Myocum HEALTH SCIENCE ENVIROMENTAL EDUCATION ENVIRONMENTAL AUDITOR Monitoring Byron Centre The Manse Road Myocum Prepared for: Byron Shire Council Version 1.0 Date:
More informationSite Layout & Traffic Plan
Location Site address: Norbury Manor Business Enterprise College, Kensington Avenue, Thornton Heath, Croydon CR7 8BT. The new block will be constructed on the existing hard play area. The construction
More informationCITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT
Page 1 CITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT CIVIC CENTRE 2141 MAJOR MACKENZIE DRIVE MAPLE ONTARIO L6A 1T1 905-832-2281 Page 2 SECTION 1 - GENERAL OBJECTIVES To provide
More informationHousehold waste & recycling storage requirements
South Gloucestershire Council Guidance for Developers on Household waste & recycling storage requirements INTRODUCTION As part of the Council s aim to improve the quality of life for residents as well
More informationGOODS LIFT BOOKING, LOADING DOCK PROCEDURES & MANAGEMENT SERVICES PARKING
GOODS LIFT BOOKING, LOADING DOCK PROCEDURES & MANAGEMENT SERVICES PARKING 2014 PREPARED BY: Jones Lang LaSalle (NSW) Pty Ltd A.B.N. 37 002 851 925 Chifley Tower, 2 Chifley Square, Sydney NSW 2000 Tel:
More informationDELIVERY & SERVICING PLAN. REDWOOD PARTNERSHIP Consulting Engineers Transportation Planners
Redwood Partnership Transportation Limited Maritime House Basin Road North Portslade Brighton BN41 1WR T: 01273 414515 F: 01273 376824 E: consult@redwoodpartnership.co.uk www.redwoodpartnership.co.uk REDWOOD
More informationPublic Landscape Aids And Protection Of Assets
Territory and Municipal Services Reference Document 4 LANDSCAPE MANAGEMENT AND PROTECTION PLANS (LMPP) Requirements for the Protection of Public Landscape Assets Adjacent to Development Works Issue 2 Revision
More informationReport to Planning applications committee Item Date 6 March 2014 Head of planning services
Report to Planning applications committee Item Date 6 March 2014 Report of Head of planning services 4(7) Subject 13/02051/F Former Wellesley First School Wellesley Avenue North Norwich NR1 4NT Description:
More informationAREA: 2.37 acres NUMBER OF LOTS: 1 FT. NEW STREET: 0 LF. Single-family, Non-conforming machine shop
FILE NO.: Z-8958 NAME: Rock Structure Repair Short-form PID LOCATION: Located at 8024 Stanton Road DEVELOPER: Rock Structure Repair Attn. Rudy Gutierrez 3 Kipling Court Little Rock, AR 72209 ENGINEER:
More informationPolicy 7 Management of Asbestos
Policy 7 Management of Asbestos 1.0 Introduction Development & Infrastructure recognise both the need to protect their employees from the risks associated with encountering asbestos and the potential for
More informationFOUNDATION TECHNICAL CATEGORY 3 (TC3) AUGUST 2012
FOUNDATION TECHNICAL CATEGORY 3 (TC3) AUGUST 2012 Building and Housing has published technical guidance for foundation repairs and reconstruction for residential properties in green zone Foundation Technical
More informationCONSENT, PURSUANT TO SECTIONS 34A, 88, 104, 104C, and 108 OF THE RESOURCE MANAGEMENT ACT, IS GRANTED. THE FULL DECISION IS SET OUT BELOW
A U C K L A N D C O U N C I L Decision following the hearing of an application for resource consent SUBJECT: Application for resource consent under section 88 of the Resource Management Act 1991 by D C
More informationService Level Agreement/Specification
Service Level Agreement/Specification For Maintenance and Associated Risk Management Services at New College Campus and Associated properties May 2007 INDEX 1. SCOPE 2. MAINTENANCE SERVICE LEVELS a. Staffing
More informationNew Home Construction Packet
New Home Construction Packet Congratulations! You are building a new home in Meyerland. This packet of information was assembled to assist you with the process. It contains all the forms that you will
More informationINTERIM ADVICE NOTE 65/05 DESIGN OF VEHICLE RECOVERY OPERATIONS AT ROAD WORKS
INTERIM ADVICE NOTE 65/05 DESIGN OF VEHICLE RECOVERY OPERATIONS AT ROAD WORKS The Purpose of this document is to provide the Project Sponsor / Designer with comprehensive guidance on the range of issues
More informationUniversity Arms Hotel, Cambridge
Traffic Management Plan For University Arms Hotel, Cambridge Prepared By: James Batterbee Number: M1342 / Rev B Date: 29 th August 2014 CONTENTS: (1) INTRODUCTION (2) VEHICLE ACCESS & EGRESS AND PEDESTRIAN
More informationCITY OF ST. CA THARINE S. cn- Olc.4 BY-LAW NO. WHEREAS the Council of the Corporation of the City of St. Catharines, is
~: ~,,' " CITY OF ST. CA THARINE S BY-LAW NO. cn- Olc.4 A By-law to regulate sanitary and storm drainage. WHEREAS the Council of the Corporation of the City of St. Catharines, is authorized by the provisions
More informationLISTED BUILDING CONSENT APPLICATION HAMILTON HOUSE, 10 NORTH PARADE BUILDINGS. BATH. PROPOSED IRS SYSTEM, SATELLITE DISH & ANTENNA INSTALLATION.
LISTED BUILDING CONSENT APPLICATION HAMILTON HOUSE, 10 NORTH PARADE BUILDINGS. BATH. PROPOSED IRS SYSTEM, SATELLITE DISH & ANTENNA INSTALLATION. DECEMBER 2011 JOB NUMBER 00168 REVISION B MARCH 2012 Contents:
More informationCONSERVATION AREAS & LISTED BUILDING APPLICATIONS DETERMINED 28 th November 2015-18 th December 2015
CONSERVATION AREAS & LISTED BUILDING APPLICATIONS DETERMINED 28 th November 2015-18 th December 2015 REF: 15/04747/TPO ADDRESS: Foxwood Green Close EN1 2TB PROPOSAL: Work to 1 Ash tree covered by LBE ORDER
More informationRecommendations for future developments
C Recommendations for future developments C.1 Reducing flood risk through site layout and design C.1.1 C.1.2 Flood risk should be considered at an early stage in deciding the layout and design of a site
More informationSite Induction Presentation
ABC Contracting Site Induction Presentation This presentation provides a mock site induction and serves to help those people in the process of preparing and delivering site inductions It is essential that
More informationDemolition Works Measures for Public Safety
Re-issued under new categorization in August 2009 as Practice Note for Authorized Persons, Registered Structural Engineers and Registered Geotechnical Engineers APP-21 Buildings Department Practice Note
More informationTriton Knoll Offshore Wind Farm Limited Electrical System. Outline Traffic Management Plan
Triton Knoll Offshore Wind Farm Limited Electrical System Outline Traffic Management Plan October 2014 RWE Innogy UK Triton Knoll TMP Copyright 2014 RWE Innogy UK Ltd All pre-existing rights reserved.
More informationThe Tomato Plant Company Ltd. Method Statement and Risk Assessment Loads requiring lifting
The Tomato Plant Company Ltd Method Statement and Risk Assessment Loads requiring lifting Generic method statement & risk assessment for the removal of portable accommodation units and/or shipping containers
More informationApplication for electricity connections Business premises. Electricity. Send your completed application form with supporting documentation to:
Electricity Thank you for considering for your electricity connections. We have put together these notes to help you fill out your and to ensure we receive all the correct information for your application
More informationMelbourne Survey T 9869 0813 F 9869 0901
Melbourne Survey T 9869 081 F 9869 0901 COPERNICUS CIRCUIT SEE SHEET CENTRAL PARKWAY 5019 508 SEE SHEET 50 SEE SHEET 4 HARVARD STREET STANFORD STREET Melbourne Survey T 9869 081 F 9869 0901 No.1 5 57 No.
More informationWASTE STORAGE AND COLLECTION GUIDANCE FOR NEW DEVELOPMENTS
WASTE STORAGE AND COLLECTION GUIDANCE FOR NEW DEVELOPMENTS CONTENTS Page 1 Introduction 2 2 Planning Applications 3 3 Internal Segregation of Waste 3 4 Housing Developments 4 5 Apartment Developments 5-6
More informationELEMENT 4 - FUTURE LAND USE ELEMENT
ELEMENT 4 - FUTURE LAND USE ELEMENT Goal 1 To create a long-range development pattern which directs growth into developable areas and away from environmentally sensitive areas, in a manner that is compatible
More informationLAND USE CODE CHAPTER 18.68 GENERAL REGULATIONS
CHAPTER 18.68 GENERAL REGULATIONS SECTIONS: 18.68.010 Fences. 18.68.020 Vision Clearance Area. 18.68.030 Access. 18.68.040 Yard Requirements. 18.68.050 Special Setback Requirements. 18.68.070 Land Surveys.
More informationThe Bond Release Process for New Subdivision Developments: An Overview for Homeowners Associations DRAFT 6-4-08. Revised 9-25-08
The Bond Release Process for New Subdivision Developments: An Overview for Homeowners Associations DRAFT 6-4-08. Revised 9-25-08 Fairfax County requires developers to post a performance bond if they are
More informationShonks Barn, Mill Street, Hastingwood For Sale Barn for Conversion - OIEO 325,000
Shonks Barn, Mill Street, Hastingwood For Sale Barn for Conversion - OIEO 325,000 Summary Description: ESSEX BARNS are offering For Sale this GRADE II CURTILAGE LISTED DETACHED BARN FOR CONVERSION WITH
More informationALBERTA ENERGY AND UTILITIES BOARD Calgary Alberta
ALBERTA ENERGY AND UTILITIES BOARD Calgary Alberta HUNT OIL COMPANY OF CANADA INC. APPLICATION FOR A SWEET NATURAL GAS PIPELINE HARMATTAN-ELKTON, RICINUS, Examiner Report 2001-3 AND CAROLINE FIELDS Application
More information90 Brighton Road, Surbiton, Surrey
90 Brighton Road, Surbiton, Surrey Civil and Structural Engineering Basement Feasibility Report Mixed Use Scheme 108802-REP-002 March 2015 Contents 1. Executive Summary... 3 2. Site Description and Constraints...
More informationbuilding on success Trees and Basements Partial Review of the Core Strategy February 2014
building on success Trees and Basements Partial Review of the Core Strategy February 2014 Regulation 19, Town and Country Planning (Local Planning) (England) Regulations 2012. 2 Contents 1. Introduction...
More information