EVALUATING THE LACK OF FLEXIBILITY AGAINST THE BENEFITS OF IN-PIT CRUSHING AND CONVEYING

Size: px
Start display at page:

Download "EVALUATING THE LACK OF FLEXIBILITY AGAINST THE BENEFITS OF IN-PIT CRUSHING AND CONVEYING"

Transcription

1 EVALUATING THE LACK OF FLEXIBILITY AGAINST THE BENEFITS OF IN-PIT CRUSHING AND CONVEYING Optimizing Mine Operations Conference Toronto 2013 Date Bob McCarthy Snowden

2 Outline Introduction IPCC basics Mine planning concepts for IPCC Guidelines for flexibility Conclusions

3 Introduction flexibility Flexibility is necessary? Just a matter of perspective Consider underground mining Fixed stope location and geometry Fixed development options Lack of flexibility bad? Consider underground mining technology Longwall coal mining Continuous miners and conveying Not too different from IPCC

4 Introduction paradigms Paradigm shift UG Miners are used to working under constraining conditions Open pit miners not so Requires a paradigm shift, but one with lateral familiarity How to survive the paradigm shift? Mine planning Change management

5 Introduction why bother? Potential rewards (study results) Cash cost reductions between US$0.18/t and US$0.82/t Net Present Cost improvements US$900m discount) Typical reduction in manning averages 6.5 persons per truck saved Typical reduction in ancillary equipment 25% Reduction in infrastructure costs (greenfields) Overall capital for long life mines is near neutral (when truck replacements are taken into account) Reduced carbon footprint

6 Introduction why bother? Truck savings

7 Outline Introduction IPCC basics Mine planning concepts for IPCC Guidelines for flexibility Conclusions

8 IPCC basics Integrated open-pit mining system A true alternative to pure truck-shovel operations Not a new technology Three general types of IPCC systems From MMD Group Fixed or Semi-fixed Semi-Mobile Fully Mobile

9 IPCC basics IPCC system components Crushers In-pit conveyors (fully mobile) Stationary conveyors Conveyor crossing Slewing spreader, radial stacker or tripper car spreader Ancillary equipment (crawlers, cranes, etc.)

10 IPCC basics fully mobile in-pit conveyors Bench transfer conveyor the conveyor that moves material from the mobile crusher to the bench conveyor It can come in many variations: belt wagons transfer bridges mobile conveyors per Sandvik Belt wagons and transfer bridges can convey to a bench conveyor above or below the current bench elevation per Metso

11 IPCC basics fully mobile in-pit conveyors Bench conveyor the conveyor that runs the length of a mining area (defined here as a panel), along which the mobile crusher traverses It can be fed from up to three benches (typical maximum) It is relocated by either track shifting (pipeline dozer) or selfpropelling Its length may change according to the width of the panel (but has minimum, driven by frequency of shifting) Bench conveyors on different benches Visonta lignite mine (Hungary) A.Oberrauner

12 IPCC basics fully mobile in-pit conveyors Portable conveyor a movable conveyor, used to extend the reach from or to a bench conveyor or dump conveyor of shorter length (up to 100 m), can be self-propelled may be used when erratic shaped benches are encountered or when dumps need extending can be used in series (piggy-back, grasshopper) per Terra Nova Technologies Ltd

13 Mining Direction Bench Trunk Conveyor IPCC basics fully mobile in-pit conveyors Bench trunk conveyor the conveyor to which the bench conveyor discharges is aligned in the overall mining direction (90 to the bench conveyor) needs to be extendable as mining advances Face Travel Bench Conveyor

14 IPCC basics stationary conveyors Stationary conveyor conveyors that are not regularly moved, but can be moved through dismantling and re-assembling modules Connection conveyor any non-specialised conveyor that transports material within the pit to a pit exit conveyor. Pit exit conveyor the last leg on the journey out of the pit, this typically ascends an incline, whether a pit haul ramp, a steeper dedicated conveyor ramp, or a tunnel incline; also used for ascending a waste dump Overland conveyor this conveyor connects the pit to the dumping area. This can be to a waste dump or an ore treatment facility per Sandvik

15 IPCC basics crossings Two common solutions to equipment / conveyor interactions Tunnel (culvert) Conveyor bridge

16 IPCC basics dumping / spreading systems Spreaders Radial stackers Tripper cars Track shiftable Self-propelled From Sandvik Mining and Construction

17 From FLSmidth IPCC basics dumping / spreading systems Discharge boom Transfer Bridge Tripper Car 50m >50m From Sandvik Mining and Construction

18 Outline Introduction IPCC basics Mine planning concepts for IPCC Guidelines for flexibility Conclusions

19 Mine planning Fully mobile panels and strips Semi-mobile crusher access Relocation of crushers Dump development

20 Mine planning fully mobile panels and strips Panels are serviced by a single bench conveyor on a single bench Multiple panels can operate in one pushback or terrace Panels are aligned in long dimension Panels are multiples of strips wide Bench conveyor can serve up to three benches in a panel

21 Mine planning fully mobile panels and strips When all benches in current strip are complete, bench conveyor track shifts When all strips in panel are complete, the system is relocated Relocation is either to another region of the pit of similar elevation or to a box cut to sink down

22 Mine planning fully mobile panels and strips Three bench operation (B3-C1-P1-N1) B Three benches per bench conveyor C One crusher per bench conveyor P One pass per strip N One bench conveyor per terrace

23 Mine planning semi-mobile crusher access Access options Permanent Temporary

24 Mine planning semi-mobile crusher access A permanent designed alcove into the high wall along the haul road access path Crusher Station Conveyor Access Ramp Slot Catch Berm Conveyor Bridge Down Ramp Direction Permanent Ramp System Up to Crusher Station & Waste Dumps Ramp Turning Area onto Crusher Tip Head Shovel

25 Mine planning semi-mobile crusher access A permanent location within an over-width haul road

26 Mine planning semi-mobile crusher access Taking advantage of a temporary wall for a permanent station location

27 Mine planning semi-mobile crusher access A temporary location along the haul road with access to the truck tip off the haul road Conveyor Bridge Ramp Conveyor Crusher Station Operating Shovel Operating Shovel

28 Mine planning semi-mobile crusher access A temporary location along the haul road with access to the truck tip via temporary ramps off the bench TurningArea.. No Access to Exit Pit Ramp Shovel Face CrusherStation TEMPORARYRamp Shovel Face

29 Mine planning semi-mobile crusher access For each additional bench, the length of a temporary ramp (and footprint on the working bench) increases. Each additional bench increases the average cycle time for the trucks and therefore the number of trucks needed. Balancing this is the desire to reduce the frequency of crusher shifts. Beyond four benches per crusher shift, the footprint of the temporary access ramp becomes significant relative to the available bench area. While a crusher could be relocated once every 6 months, no more than once per year is preferable; therefore, 4 benches per year is a good maximum bench advance rate.

30 Mine planning relocation of crushers Common misconception that relocation takes months and is a major engineering task Crusher relocation can be accomplished in 7 days or less From Sandvik Mining and Construction

31 Mine planning relocation of crushers From Sandvik Mining and Construction

32 Mine planning conveyor pit exits Primary challenge is the pit exit corridor Options include: Alongside haul roads Dedicated conveyor routes (can be greater than 20%) Tunnel Most common route is the haulage ramp Complex exits increase the number of transfer points

33 Mine planning haul road considerations Extra width required for conveyor allocation

34 Mine planning dedicated conveyor pit exit Truck Turning Circle Area Dedicated Conveyor Ramp at 15 degree angle Double Crusher Station Temp 10% Road Ramp for Truck Access to Dump Pocket Area Crusher Station Relocation Access Area

35 Mine planning dedicated conveyor pit exit Using what geology gave you

36 Mine planning flexibility? you bet Conveyor distribution point, Hambach lignite mine, Germany per RWE

37 Mine planning IPCC dump designs Generic simplified radial dump layout

38 Mine planning IPCC dump designs Can be very high dump heights

39 Mine planning IPCC dump designs Waste dumping starting bottom-up dump

40 Mine planning IPCC dump designs IPCC dumps differ from truck waste dumps per: The location of the dump does not need to be immediately adjacent to the pit. With spreaders, there is no dump lift height restriction due to the risk of crest failure as a spreader can stand far back from the dump edge. Geotechnical investigation is still required of foundation, but also resized waste material. Leachates?

41 Outline Introduction IPCC basics Mine planning concepts for IPCC Guidelines for flexibility Conclusions

42 Guidelines to IPCC mine planning Key considerations in planning for all IPCC systems Material characteristics determination (UCS, fines, abrasiveness) Loading equipment matching to IPCC Operating hours of overall system Mining above IPCC ramp conveyors is generally not allowed; blasting adjacent to IPCC equipment to be reduced or eliminated Maximize size of push backs for: vertical bench advance, elbow room, pit exit conveyor on haul road Pit exit conveyors use footwalls or temporary walls to advantage; establish lowest accessible depth SMIPCC vs FMIPCC Dump construction generally not an issue unless construction is bottom up in which case consider truck built starter platforms or if no trucks, a viable sequence. Electricity supply; is it there?

43 Guidelines to IPCC mine planning Key considerations in planning for Semi-Mobile IPCC Elaborateness of crusher stations; <240t trucks vs. ultra class Blast design; multiple bench and pre-split blasting for crusher stations Crusher relocation planning; temporary ramps vs permanent ramps Vertical advance rate is constrained; though 8 benches per year are technically possible, 4 or less are preferred to reduce crusher relocations Ensure truck dump traffic flow allows for achieving expected crusher feed rates

44 Guidelines to IPCC mine planning Key considerations in planning Fully Mobile IPCC Minimum strip/bench conveyor length; balance maximizing IPCC usage vs. conveyor shifting and relocation delays Maximize IPCC mineable material by appropriate panel/strip configurations Multiple bench configurations; maximize benches served by a single bench conveyor datum (three bench operation optimal) Plan out box cut sequence, schedule accordingly; consider extra bench conveyor to minimize delays Plan out dump construction, particularly if bottom up and no trucks available

45 Outline Introduction IPCC basics Mine planning concepts for IPCC Guidelines for flexibility Conclusions

46 Conclusions IPCC means a whole new terminology and way to approach mine planning Cost savings and other benefits are substantial, while loss of flexibility is real There is no replacement for good planning to create a mine plan that builds in flexibility that is lost operationally IPCC is a new paradigm and transitioning to it is a significant change Ensure change management aspects are addressed, if not a full change management approach

In-Pit Crushing and Conveying Phil Morriss

In-Pit Crushing and Conveying Phil Morriss In-Pit Crushing and Conveying Phil Morriss AGENDA 1. Introduction - what is In-Pit Crushing and Conveying (IPCC)? 2. What does a quarry need from IPCC? 3. Why and when should we consider using it? 4. How

More information

Types of Mining - Expert Table

Types of Mining - Expert Table See page 6 Minerals Downunder Teacher Guide (2002) - Activity 4a Types of Mining - Expert Table How to Jigsaw Information 1. Divide the class into Home Groups of five for the five different types of mining

More information

COAL MINING TECHNOLOGY. A Presentation by MANOJ KUMAR SINGH Manager(IE), NCL-HQ, Singrauli(MP)-486 889 E-mail : mks_ie@nclhq.nic.

COAL MINING TECHNOLOGY. A Presentation by MANOJ KUMAR SINGH Manager(IE), NCL-HQ, Singrauli(MP)-486 889 E-mail : mks_ie@nclhq.nic. COAL MINING TECHNOLOGY A Presentation by MANOJ KUMAR SINGH Manager(IE), NCL-HQ, Singrauli(MP)-486 889 E-mail : mks_ie@nclhq.nic.in, M-9993875526 MINING TECHNOLOGY OPENCAST MINING TECHNOLOGY Shovel-Dumper

More information

Walking and Working Surface Checklist:

Walking and Working Surface Checklist: Walking and Working Surfaces Purpose: This information is presented to improve the level of safety in our operations, and to inform you that we will comply with the OSHA Standard 29 CFR 1910.23. Responsibility:

More information

3D Modelling & Mine Planning Software. Comprehensive tools provide a competitive advantage from exploration to rehabilitation.

3D Modelling & Mine Planning Software. Comprehensive tools provide a competitive advantage from exploration to rehabilitation. 3D Modelling & Mine Planning Software Comprehensive tools provide a competitive advantage from exploration to rehabilitation. Maptek Vulcan, the world s premier 3D mining software solution, allows users

More information

BENEFITS OF USING MOBILE CRUSHING AND SCREENING PLANTS IN QUARRYING CRUSHED STONE. 1. Introduction. Mario Klanfar*, Darko Vrkljan*

BENEFITS OF USING MOBILE CRUSHING AND SCREENING PLANTS IN QUARRYING CRUSHED STONE. 1. Introduction. Mario Klanfar*, Darko Vrkljan* AGH Journal of Mining and Geoengineering vol. 36 No. 3 2012 Mario Klanfar*, Darko Vrkljan* BENEFITS OF USING MOBILE CRUSHING AND SCREENING PLANTS IN QUARRYING CRUSHED STONE 1. Introduction Mobile crushers

More information

Workplace Incident Fatalities Accepted by the Workers Compensation Board in 2014

Workplace Incident Fatalities Accepted by the Workers Compensation Board in 2014 Workplace Incident Fatalities Accepted by the Workers Compensation Board in 2014 Workplace Incident Fatalities Year to date, numbers as of December 31, 2014 Workplace Incident fatalities are cases where

More information

Florida Building Code 2004 SECTION 1009 STAIRWAYS AND HANDRAILS

Florida Building Code 2004 SECTION 1009 STAIRWAYS AND HANDRAILS Florida Building Code 2004 SECTION 1009 STAIRWAYS AND HANDRAILS 1009.1 Stairway width. The width of stairways shall be determined as specified in Section 1005.1, but such width shall not be less than 44

More information

Hydraulic Excavators

Hydraulic Excavators Chapter 8 Hydraulic Excavators Hydraulic excavators are designed to excavate below the ground surface on which the machine rests. These machines have good mobility and are excellent for general-purpose

More information

Deswik.Sched. Gantt Chart Scheduling

Deswik.Sched. Gantt Chart Scheduling Deswik.Sched Gantt Chart Scheduling SCHEDULING SOLUTIONS THAT SET US APART A dynamic, modern approach to scheduling From interactive Gantt charts to PERT network diagrams, Deswik.Sched is tailored for

More information

Simple Machines. What are simple machines?

Simple Machines. What are simple machines? Definitions to know: Simple Machines Work done when an applied force causes an object to move in the direction of the force Energy ability to cause change; can change the speed, direction, shape, or temperature

More information

Basements and Deep Building Construction Policy 2014

Basements and Deep Building Construction Policy 2014 Basements and Deep Building Construction Policy 2014 APPROVAL Council / CEO 27 October 2014 VERSION NO: Version 1.0 TRIM REF: 14/67838 REVIEW 30/10/2019 RESPONSIBLE EXECUTIVE General Manager City Assets

More information

Geotechnical Management. An Overview on typical system elements

Geotechnical Management. An Overview on typical system elements Geotechnical Management An Overview on typical system elements Purpose of presentation Overview of the elements of a robust geotechnical system for an Open Cut to allow you to ask questions at this seminar

More information

3 Tappan Zee Bridge Rehabilitation Options

3 Tappan Zee Bridge Rehabilitation Options 3 Tappan Zee Bridge Rehabilitation Options 3.1 Introduction This chapter describes possible options that rehabilitate and enhance the existing Tappan Zee Bridge. Four Rehabilitation Options have been developed:

More information

CONSTRUCTION TRAFFIC MANAGEMENT PLAN V11, 26/09/12

CONSTRUCTION TRAFFIC MANAGEMENT PLAN V11, 26/09/12 If the project you are constructing was subject to planning permission and a condition requiring a Construction Traffic Management Plan (CTMP) was applied to the planning consent, this condition will need

More information

Working in a quarry guidelines

Working in a quarry guidelines Working in a quarry guidelines July 2011 Introduction Not much material exists on quarries in SA. In the mining industry, quarries are often not focussed on or dealt with although a quarry in SA is a mine.

More information

A new short- and medium-term production scheduling tool MineSight Schedule Optimizer (MSSO)

A new short- and medium-term production scheduling tool MineSight Schedule Optimizer (MSSO) A new short- and medium-term production scheduling tool MineSight Schedule Optimizer (MSSO) Zhanyou Huang a, Wenlong Cai a, A. Frederick Banfield a a Mintec, Inc., Tucson, Arizona, USA The MineSight Schedule

More information

Stefan Sjöström, SEABB, PAPI UGM Automation ABB Underground mining Mobile Integration. ABB Group May 18, 2015 Slide 1 3BSE081096-212

Stefan Sjöström, SEABB, PAPI UGM Automation ABB Underground mining Mobile Integration. ABB Group May 18, 2015 Slide 1 3BSE081096-212 Stefan Sjöström, SEABB, PAPI UGM Automation ABB Underground mining Mobile Integration May 18, 2015 Slide 1 Integrated Mine automation and electrification Mine Operation Center Substations GIS Substations

More information

Lödige Goods Passenger Lifts

Lödige Goods Passenger Lifts Lödige Goods Passenger Lifts OLYMPUS-Series Goods Lifts TRAFFICO Car Lifts TECHNOLOGY IN MOTION Service Intralogistik Systems Machines Lifts Road Lödige Industries Technology in Motion The core competence

More information

Base Cabinet with Self-storing Folding Doors and Floor

Base Cabinet with Self-storing Folding Doors and Floor Usable Kitchens When designing a kitchen for use by persons with mobility impairments, especially those who use wheelchairs, careful layout of the kitchen is crucial to maintaining accessibility. People

More information

Software Stability Model for Dump Truck Scheduling

Software Stability Model for Dump Truck Scheduling Software Stability Model for Dump Truck Scheduling Dr. Mohamed Fayad Majid Nabavi Abstract The software stability model is applied to a classic dispatching problem, namely: Dump Truck Scheduling. Like

More information

Stacker and reclaimer systems for cement plants

Stacker and reclaimer systems for cement plants Stacker and reclaimer systems for cement plants 2 Heavy-duty performance Key benefits All stacker and reclaimer systems are: - Ideal for both prehomogenisation and buffer storage - Designed for heavy-duty

More information

Settlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains

Settlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains Settlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains Doug Jenkins 1, Chris Lawson 2 1 Interactive Design Services, 2 Reinforced

More information

choice for the application.

choice for the application. Accumulating Conveyors and Accumulating Machines Choosing the Right Accumulation Solution for your Application Planning for Accumulation Accumulation is required in high speed production lines to make

More information

Fabrication, Delivery and Installation

Fabrication, Delivery and Installation Evaporator D The Modules Fabrication, Delivery and Installation Marine Access Development In order to safely deliver the modules by sea to the Sellafield site, a temporary development has been constructed

More information

Rockhampton Office Brisbane Office Tarong Site. Barron Gorge Hydro PS Kareeya Hydro PS Mica Creek PS

Rockhampton Office Brisbane Office Tarong Site. Barron Gorge Hydro PS Kareeya Hydro PS Mica Creek PS Business Procedure Traffic Management Document Number OHS-PROC-130 This document applies to the following sites: All Sites Rockhampton Office Brisbane Office Tarong Site Barron Gorge Hydro PS Kareeya Hydro

More information

Training Simulators for the Mining Industry

Training Simulators for the Mining Industry Training Simulators for the Mining Industry PHOTO OVERVIEW Fifth Dimension Technologies www.5dt.com 1.0 Introduction 5DT (Fifth Dimension Technologies) is a high technology company specializing in Virtual

More information

May 24, 2011. These Questions and Answers (Q&A) consolidate, clarify, update and replace all prior Q&As regarding this subject

May 24, 2011. These Questions and Answers (Q&A) consolidate, clarify, update and replace all prior Q&As regarding this subject Questions and Answers n MSHA S Program Policy Letter (PPL) (P11-V-13) on Post- Accident Two-Way Communications and Electronic Tracking Requirements of the Mine Improvement and New Emergency Response Act

More information

GUIDELINES FOR MINE HAUL ROAD DESIGN

GUIDELINES FOR MINE HAUL ROAD DESIGN GUIDELINES FOR MINE HAUL ROAD DESIGN Dwayne D. Tannant & Bruce Regensburg School of Mining and Petroleum Engineering Department of Civil and Environmental Engineering University of Alberta 2001 SMART Surface

More information

Free Examples of plant layout drawing

Free Examples of plant layout drawing Free layout examples; a wide variety of industrial layouts, within different facility types. Principles of plant layout and design will apply widely. Free Examples of plant layout drawing Principles of

More information

Automated Mine Scheduling: What is it and will it help me?

Automated Mine Scheduling: What is it and will it help me? Automated Mine Scheduling: What is it and will it help me? Introduction This article discusses the philosophies, strategies, goals and pitfalls in automating a mine schedule. The intention is to give an

More information

Truck: A125 48.140. 3:22 PM ton. Maximize payload, maximize profit. LOADRITE X2650 Excavator Scales. transforming the way the world works

Truck: A125 48.140. 3:22 PM ton. Maximize payload, maximize profit. LOADRITE X2650 Excavator Scales. transforming the way the world works Truck: A125 48.14 Maximize payload, maximize profit LOADRITE X265 Excavator Scales transforming the way the world works Maximize payload, maximize profit Excavator vs. truck scales X265 excavator weighing

More information

Backfill for Bench Stoping Operations

Backfill for Bench Stoping Operations Backfill for Bench Stoping Operations E. Villaescusa Professor of Mining Geomechanics, Western Australian School of Mines K. Kuganathan Senior Backfill Research Engineer, Mount Isa Mines ABSTRACT This

More information

Mine Schedule Implementation Using a Multi-Agent Based System

Mine Schedule Implementation Using a Multi-Agent Based System Mine Schedule Implementation Using a Multi-Agent Based System Kapageridis, I.K., Technological Education Institute of Western Macedonia, Department of Geotechnology and Environment, Koila, Kozani 50100,

More information

FIBER OPENING AND BLENDING. AUTEFA Solutions leads the way

FIBER OPENING AND BLENDING. AUTEFA Solutions leads the way FIBER OPENING AND BLENDING AUTEFA Solutions leads the way AUTEFA SOLUTIONS Experience, Know-How and Competence in Nonwoven Technology AUTEFA Solutions leads the way AUTEFA Solutions represents companies

More information

Outotec HIGmills; A Fine Grinding Technology

Outotec HIGmills; A Fine Grinding Technology 23 rd International Mining Congress & Exhibition of Turkey 16-19 April 2013 ANTALYA Outotec HIGmills; A Fine Grinding Technology H. Lehto Outotec Finland Oy A. Paz Outotec Pty Ltd, Perth, Australia I.

More information

Table 4.9 Storm Drain Inlet Protetion Applicable for

Table 4.9 Storm Drain Inlet Protetion Applicable for BMP C220: Storm Drain Inlet Protection Purpose To prevent coarse sediment from entering drainage systems prior to permanent stabilization of the disturbed area. Conditions of Use Type of Inlet Protection

More information

There is no water, surface tension cracks, nor other environmental conditions present that reduce the stability of the excavation.

There is no water, surface tension cracks, nor other environmental conditions present that reduce the stability of the excavation. Part 1926 Subpart P Introduction The Occupational Safety and Health Administration (OSHA) issued its first Excavation and Trenching Standard in 1971 to protect workers from excavation hazards. Since then,

More information

EQUIPMENT SAFETY EARTHMOVING MATERIAL HANDLING NAVFAC MIDLANT

EQUIPMENT SAFETY EARTHMOVING MATERIAL HANDLING NAVFAC MIDLANT EQUIPMENT SAFETY EARTHMOVING MATERIAL HANDLING COMMON EARTHMOVING EQUIPMENT SKID LOADERS BACKHOE FRONT END LOADER GRADERS SCRAPERS BULL DOZERS Lots of stuff Here! COMMON MATERIAL HAULING TRUCKS ALL TYPES

More information

How To Use Leica Dozernav Plus

How To Use Leica Dozernav Plus Leica DozerNav Plus High precision GPS dozer guidance More than a guidance system Leica DozerNav Plus > helping you drive productivity with ease Leica DozerNav Plus the benefits at a glance Real-time feedback

More information

The entire document shall be read and understood before proceeding with a test. ISTA 3B 2013 - Page 1 of 35

The entire document shall be read and understood before proceeding with a test. ISTA 3B 2013 - Page 1 of 35 Packaged-Products for Less-Than-Truckload (LTL) Shipment ISTA 3 Series General Simulation Performance Test PROCEDURE VERSION DATE Last TECHNICAL Change: NOVEMBER 2012 Last EDITORIAL Change: JANUARY 2013

More information

How to Estimate the Cost of Support of Excavation for Foundation Installation. CPE Candidate No. 0113013. May 15, 2013

How to Estimate the Cost of Support of Excavation for Foundation Installation. CPE Candidate No. 0113013. May 15, 2013 How to Estimate the Cost of Support of Excavation for Foundation Installation CPE Candidate No. 0113013 May 15, 2013 1 How to Estimate the Cost of Support of Excavation for Foundation Installation Table

More information

Road Rehabilitation and Reconstruction Using AutoCAD Civil 3D

Road Rehabilitation and Reconstruction Using AutoCAD Civil 3D Road Rehabilitation and Reconstruction Using AutoCAD Civil 3D Contents Introduction... 3 Introduction to Corridor Targets... 3 Surface Targets... 4 Width and Offset Targets... 5 Elevation or Slope Targets...

More information

Presentation ThyssenKrupp Bulk Materials Handling Dr. Markus Oles

Presentation ThyssenKrupp Bulk Materials Handling Dr. Markus Oles Presentation ThyssenKrupp Bulk Materials Handling Dr. Markus Oles Developing the future. 1 Desarrollamos el futuro para usted Source: EMO, Netherlands Content Group overview TK as Partner Integrated solutions

More information

GPS BASED TRUCK DISPATCH SYSTEM (TDS) IN HIGHLY MECHANIZED BAUXITE MINES A CASE STUDY.

GPS BASED TRUCK DISPATCH SYSTEM (TDS) IN HIGHLY MECHANIZED BAUXITE MINES A CASE STUDY. GPS BASED TRUCK DISPATCH SYSTEM (TDS) IN HIGHLY MECHANIZED BAUXITE MINES A CASE STUDY. Dr Ashutosh Roul, PhD Senior Manager(Mines),NALCO. NALCO Asia s largest integrated Aluminium Complex, Encompassing

More information

USE OF SOLUTION STRATEGY IN OPEN CAST MINING TRUCK DISPATCHING SYSTEM

USE OF SOLUTION STRATEGY IN OPEN CAST MINING TRUCK DISPATCHING SYSTEM USE OF SOLUTION STRATEGY IN OPEN CAST MINING TRUCK DISPATCHING SYSTEM Kazem Oraee & Bahareh Asi Azad Univeristy Tehran South, Tehran, Iran Kavoshgaran consulting engineers, Tehran, Iran ABSTRACT: The technique

More information

ADA POST INSPECTION CHECKLIST. Job No. Route County Location

ADA POST INSPECTION CHECKLIST. Job No. Route County Location ADA POST INSPECTION CHECKLIST Job No. Route County Location SIDEWALKS All sidewalks constructed within the project limits are ADA compliant. Sidewalks are 5 or greater in width. Exception, existing sidewalks

More information

At the completion of this guide you should be comfortable with the following:

At the completion of this guide you should be comfortable with the following: This guide provides instructions and best practices for deployment of the Yealink W52P IP DECT phones and repeaters RT10, which is intended for qualified technicians (or administrator) who will deploy

More information

OPTIMIZATION OF LOAD HAUL DUMP MINING SYSTEM BY OEE AND MATCH FACTOR FOR SURFACE MINING

OPTIMIZATION OF LOAD HAUL DUMP MINING SYSTEM BY OEE AND MATCH FACTOR FOR SURFACE MINING OPTIMIZATION OF LOAD HAUL DUMP MINING SYSTEM BY OEE AND MATCH FACTOR FOR SURFACE MINING *Ram Prasad Choudhary Department of Mining Engineering, National Institute of Technology Karnataka, Surathkal-575025

More information

APPLICATION OF OPENRISK AT OPEN CAST COAL MINES

APPLICATION OF OPENRISK AT OPEN CAST COAL MINES APPLICATION OF OPENRISK AT OPEN CAST COAL MINES * ** B.J. Madden *** I. Canbulat * Anglo Technical Division ** G-Ro Geotechnical Services (Pty) Ltd *** Groundwork Consulting (Pty) Ltd ABSTRACT OpenRisk,

More information

BUCKET AND CUTTING TOOTH DEVELOPMENTS FOR THE BUCKET WHEEL EXCAVATORS OF MÁTRA POWER STATION LLC

BUCKET AND CUTTING TOOTH DEVELOPMENTS FOR THE BUCKET WHEEL EXCAVATORS OF MÁTRA POWER STATION LLC Geosciences and Engineering, Vol. 1, No. 1 (2012), pp. 177 186. BUCKET AND CUTTING TOOTH DEVELOPMENTS FOR THE BUCKET WHEEL EXCAVATORS OF MÁTRA POWER STATION LLC GÁBOR LADÁNYI ISTVÁN SÜMEGI Department of

More information

Pole Lathe and Shave Horse Design

Pole Lathe and Shave Horse Design Pole Lathe and Shave Horse Design These pictures and accompanying words are Copyright Michael Hughes February 2002. They are not to be re-produced, in part or whole, without permission from the author.

More information

Christa s Lost Lessons Simple Machines

Christa s Lost Lessons Simple Machines Christa s Lost Lessons Simple Machines Introduction: Among the six lost lessons, the simple machines demonstration was most rudimentary. Perhaps, it is because most earth-based simple machines are crafted

More information

Candelaria and Ojos del Salado Chile

Candelaria and Ojos del Salado Chile TSX : LUN OMX : LUMI 2016 Candelaria Key Facts Open Pit and Underground Mine Copper, gold, and silver 2016 estimate 124,000-128,000 tonnes copper Cash costs of $1.45 per lb copper after by-product credits

More information

Patrik Westerlund & Marcello Sanchez, SEABB, PAPI UGM Automation ABB Underground mining Mobile Integration

Patrik Westerlund & Marcello Sanchez, SEABB, PAPI UGM Automation ABB Underground mining Mobile Integration Patrik Westerlund & Marcello Sanchez, SEABB, PAPI UGM Automation ABB Underground mining Mobile Integration May 6, 2015 Slide 1 Integrated Mine automation and electrification Mine Operation Center Substations

More information

ENVIRONMENTAL CODE OF PRACTICE FOR CONCRETE BATCH PLANT & ROCK WASHING OPERATIONS

ENVIRONMENTAL CODE OF PRACTICE FOR CONCRETE BATCH PLANT & ROCK WASHING OPERATIONS ENVIRONMENTAL CODE OF PRACTICE FOR CONCRETE BATCH PLANT & ROCK WASHING OPERATIONS PREPARED BY: DEPARTMENT OF ENVIRONMENT AND LANDS INDUSTRIAL ENVIRONMENTAL ENGINEERING DIVISION APRIL 16, 1992 - TABLE OF

More information

Conveyor Belt Group. Flexowell -belts for safe and efficient steep inclined and vertical conveying

Conveyor Belt Group. Flexowell -belts for safe and efficient steep inclined and vertical conveying Conveyor Belt Group Flexowell -belts for safe and efficient steep inclined and vertical conveying FLEXOWELL Worldwide the number 1 for up- and downhill conveying In 1964, the first FLEXOWELL -conveyor

More information

Focus on learning key. 1 NIHL impacts. Exercise. Discuss. Introduction

Focus on learning key. 1 NIHL impacts. Exercise. Discuss. Introduction Focus on learning key Exercise Analyse the information in your work group Date: Shift: Discussion led by: Attendees names: Discuss Go through questions in your workgroup Introduction Being exposed to excessive

More information

The Manitoba Water Services Board SECTION 022180 Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11

The Manitoba Water Services Board SECTION 022180 Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11 Page 1 of 11 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work described herein shall consist of the excavation of trenches (or excavation of tunnels); the supply and placing of bedding and backfill materials;

More information

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0

More information

Corrugated Packaging 101

Corrugated Packaging 101 Corrugated Packaging 101 By Melissa Montague, Wexxar Packaging Inc. The purpose of this paper is to help businesses (large and small) develop an appreciation for the science of corrugated material and

More information

Partnerships Implementing Engineering Education Worcester Polytechnic Institute Worcester Public Schools

Partnerships Implementing Engineering Education Worcester Polytechnic Institute Worcester Public Schools Partnerships Implementing Engineering Education Worcester Polytechnic Institute Worcester Public Schools Supported by: National Science Foundation Simple Machines: 4.G.2 _ Inclined Planes and Pulleys Grade

More information

ASSET MANAGEMENT GUIDE FOR PROJECT DESIGN FORMAT

ASSET MANAGEMENT GUIDE FOR PROJECT DESIGN FORMAT ASSET MANAGEMENT GUIDE FOR PROJECT DESIGN FORMAT 1. BACKGROUND There has been an increasing awareness of design features, which produce poor whole-of-life costs. These poor whole-of-life costs manifest

More information

TABLE OF CONTENTS. INTRODUCTION... 5 Advance Concrete... 5 Where to find information?... 6 INSTALLATION... 7 STARTING ADVANCE CONCRETE...

TABLE OF CONTENTS. INTRODUCTION... 5 Advance Concrete... 5 Where to find information?... 6 INSTALLATION... 7 STARTING ADVANCE CONCRETE... Starting Guide TABLE OF CONTENTS INTRODUCTION... 5 Advance Concrete... 5 Where to find information?... 6 INSTALLATION... 7 STARTING ADVANCE CONCRETE... 7 ADVANCE CONCRETE USER INTERFACE... 7 Other important

More information

Manual Handling- The Whole Story!

Manual Handling- The Whole Story! Manual Handling- The Whole Story! For Responsible Managers and Assessors Course Notes Mark Mallen Group Health and Safety Manager July 2005 Course Content 1 What is Manual Handling? 2 What s the Problem?

More information

High Capacity Hot Air Dryer

High Capacity Hot Air Dryer High Capacity Hot Air Dryer MADE IN AUSTRIA autumn 2015 www.zimmer-austria.com page 1 Hot air dryer type: Compact HC The modular construction of the high efficiency and powerful hot air nozzle dryer is

More information

NEW BLUE LINE CONNECTIONS

NEW BLUE LINE CONNECTIONS Washington Metropolitan Area Transit Authority NEW BLUE LINE CONNECTIONS 3/31/2014 A Major Capital Project of Momentum s Metro 2025 Program In support of its new strategic plan, Metro has considered the

More information

Expertise in heavy loads. ThyssenKrupp freight elevators.

Expertise in heavy loads. ThyssenKrupp freight elevators. Expertise in heavy loads. ThyssenKrupp freight elevators. A Company of ThyssenKrupp Elevator ThyssenKrupp Aufzüge TK Moving heavy loads can be light work. Know-how and technology from a single source.

More information

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix.

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix. Storm Drainage 13-C-1 APPENDIX C INLETS 1.0 Introduction The application and types of storm drainage inlets are presented in detail in this Appendix. 2.0 Inlet Locations Inlets are required at locations

More information

Safety Applications for GPS Systems in the Mining Industry

Safety Applications for GPS Systems in the Mining Industry Safety Applications for GPS Systems in the Mining Industry Introduction The Global Positioning System (GPS) has been available for civilian use for more than 20 years now. It has found many navigation,

More information

KITCHENS. Tip PAGE 1 FITTING YOUR KITCHEN GUIDE. How to mark out a kitchen. Tools required for installing a kitchen STEP ONE STEP TWO STEP THREE

KITCHENS. Tip PAGE 1 FITTING YOUR KITCHEN GUIDE. How to mark out a kitchen. Tools required for installing a kitchen STEP ONE STEP TWO STEP THREE FITTING YOUR KITCHEN GUIDE How to mark out a kitchen PAGE 1 Before starting on the installation, measure 870mm from the lowest point of the floor and mark a datum line around the room to indicate where

More information

Wren Kitchens Installation Tips... 3. Carefully check your kitchen delivery... 4. Measuring out and marking up... 5. Fitting the base cabinets...

Wren Kitchens Installation Tips... 3. Carefully check your kitchen delivery... 4. Measuring out and marking up... 5. Fitting the base cabinets... tra 1 Index Wren Kitchens Installation Tips... 3 Carefully check your kitchen delivery... 4 Measuring out and marking up... 5 Fitting the base cabinets... 6 Fitting the corner cabinets... 7 The 972mm or

More information

Container design and types

Container design and types Container technology can transport mainly piece goods over great distances. The strong container protects good during the transport, the standardized dimensions let them store in well defined stacks and

More information

Operating Concept and System Design of a Transrapid Maglev Line and a High-Speed Railway in the pan-european Corridor IV

Operating Concept and System Design of a Transrapid Maglev Line and a High-Speed Railway in the pan-european Corridor IV Operating Concept and System Design of a Transrapid Maglev Line and a High-Speed Railway in the pan-european Corridor IV A. Stephan & E. Fritz IFB Institut für Bahntechnik GmbH, Niederlassung, Germany

More information

42U/45U 28" Wide Rack Installation & Service Guide

42U/45U 28 Wide Rack Installation & Service Guide 42U/45U 28" Wide Rack Installation & Service Guide 96-00171-005 Rev B Important Information Information in this document is subject to change without notice and does not represent a commitment on the part

More information

Mining with Paste Fill

Mining with Paste Fill Mining with Paste Fill Mehmet Yumlu, Principal Mining Engineer AMC Consultants Pty Ltd AusIMM Cobar Mining Seminar AMC Con nsultants Pty Ltd Outline Introduction ti What is Paste Fill? Why Using Paste

More information

TOOLS FOR SELF RELIANCE REFURBISHING SHEET No 2. Registered Charity No 280437. Saws for Woodworking

TOOLS FOR SELF RELIANCE REFURBISHING SHEET No 2. Registered Charity No 280437. Saws for Woodworking Registered Charity No 280437 Saws for Woodworking Issued December 2002 Registered Charity No 280437 page no 1 SAW TYPES Rip saw For cutting along the grain Crosscut saw [A smaller version is known as a

More information

PowerPoint: Graphics and SmartArt

PowerPoint: Graphics and SmartArt PowerPoint: Graphics and SmartArt Contents Inserting Objects... 2 Picture from File... 2 Clip Art... 2 Shapes... 3 SmartArt... 3 WordArt... 3 Formatting Objects... 4 Move a picture, shape, text box, or

More information

Gate Leg Drop Leaf Table Plans

Gate Leg Drop Leaf Table Plans Preparing the table top blanks: Cut and glue enough 3/4 stock to make three panels 40 long by 24 wide (they will be cut to final size at a later time). While the glue dries we will work on the legs. Preparing

More information

CONSTRUCTION SEQUENCE & PROGRAMME

CONSTRUCTION SEQUENCE & PROGRAMME CONSTRUCTION SEQUENCE & PROGRAMME 2 CONTENTS 1.0 Introduction 7 2.0 Key activities 8 2.1 Airport related activities 2.2 Construction of new roads and accesses 2.3 Earthworks zone a 2.4 Earthworks zone

More information

ADA Checklist for Polling Places

ADA Checklist for Polling Places U.S. Department of Justice Civil Rights Division Disability Rights Section Americans with Disabilities Act ADA Checklist for Polling Places February 2004 Reproduction Reproduction of this document is encouraged.

More information

W E C O N V E Y Q U A L I T Y DISCHARGE SYSTEMS

W E C O N V E Y Q U A L I T Y DISCHARGE SYSTEMS W E C O N V E Y Q U A L I T Y DISCARGE SYSTEMS W E C O N V E Y ROTARY DISCARGE MACINE TYPE RDM-R The LOUISE Rotating Rotary Discharge Machine (RDM-R) is a central unit to extract difficult bulk material

More information

Information Technology Career Path Overview

Information Technology Career Path Overview Information Technology Career Path Overview + Joy Global Has a Positive Corporate Culture Joy Global is a company of diverse people working among operating divisions located in communities around the world.

More information

Update on Heap Leach potential of the Murchison gold project

Update on Heap Leach potential of the Murchison gold project 3 July 2012 Australian-based Kentor Gold Limited (ASX: KGL) is entering the ranks of operating gold mining companies in 2012. The Company is progressing a pipeline of advanced projects in Australia and

More information

Asset Management Guide For Project Design Format

Asset Management Guide For Project Design Format NZ Transport Agency Page 1 of 6 Asset Management Guide For Project Design Format 1 Background There has been an increasing awareness of design features, which produce poor wholeof-life costs. These poor

More information

Functional overview. PRECISE l RELIABLE l REAL-TIME MONITORING - 1 - Document Number: MW2511. www.mineware.com

Functional overview. PRECISE l RELIABLE l REAL-TIME MONITORING - 1 - Document Number: MW2511. www.mineware.com Functional overview PRECISE l RELIABLE l REAL-TIME MONITORING Document Number: MW2511 www.mineware.com - 1 - Stay on track, on target + on plan Argus is the unrivalled system in global shovel monitoring.

More information

Sale of surplus Road Planings price structure

Sale of surplus Road Planings price structure Sale of surplus Road Planings price structure Target prices (2009) Delivery Direct from road planing works From stockpile Price 6 / tonne + VAT (within 10 miles radius) 8 / tonne + VAT (within 10 miles

More information

Using the Leadership Pipeline transition focused concept as the vehicle in integrating your leadership development approach provides:

Using the Leadership Pipeline transition focused concept as the vehicle in integrating your leadership development approach provides: Building your Leadership Pipeline Leadership transition focused development - White Paper The Leadership Pipeline framework Business case reflections: 1. Integrated leadership development 2. Leadership

More information

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED NEW COAL-FIRED POWER STATION IN THE LEPHALALE AREA, LIMPOPO PROVINCE

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED NEW COAL-FIRED POWER STATION IN THE LEPHALALE AREA, LIMPOPO PROVINCE ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED NEW COAL-FIRED POWER STATION IN THE LEPHALALE AREA, LIMPOPO PROVINCE FOCUS GROUP MEETING 10 MARCH 2006 09:30 KUMBA RESOURCES OFFICES, PRETORIA DRAFT

More information

GEAROLOGY 4-1 WORMS AND WORM GEARS WORMS AND WORM GEARS

GEAROLOGY 4-1 WORMS AND WORM GEARS WORMS AND WORM GEARS GEAROLOGY 4-1 4 4-2 GEAROLOGY COMMON APPLICATIONS: Worm and worm gear sets are used in many, everyday products including: electrical mixers, hubometers, right Now that you have an understanding of two

More information

CONVEYING TECHNOLOGY LOADING TECHNOLOGY PALLETIZING TECHNOLOGY PACKAGING TECHNOLOGY SORTATION AND DISTRIBUTION SYSTEMS

CONVEYING TECHNOLOGY LOADING TECHNOLOGY PALLETIZING TECHNOLOGY PACKAGING TECHNOLOGY SORTATION AND DISTRIBUTION SYSTEMS CONVEYING TECHNOLOGY LOADING TECHNOLOGY PALLETIZING TECHNOLOGY PACKAGING TECHNOLOGY SORTATION AND DISTRIBUTION SYSTEMS High capacity chain bucket elevators BEUMER CONVEYING TECHNOLOGY Bucket elevators

More information

1,300 people, $100M annually into the regional economy. Upgrading Mine-Wide Wireless Network with Zero Downtime. square miles,

1,300 people, $100M annually into the regional economy. Upgrading Mine-Wide Wireless Network with Zero Downtime. square miles, Upgrading Mine-Wide Wireless Network with Zero Downtime Rajant Connects Huge Mine with a Robust, Unified Network. To the layman, mining operations are a gritty, noisy and perilous undertaking involving

More information

Pallet Rack: How to Avoid Costly Errors in Planning & Installing

Pallet Rack: How to Avoid Costly Errors in Planning & Installing Special Report Pallet Rack: How to Avoid Costly Errors in Planning & Installing By Tom Jameson, President ShelfPlus, Inc. Expert tips & strategies for making sure your pallet rack project maximizes efficiency

More information

Optical Cable Pre-Construction Survey. Keywords Stationary Reel Method, empty innerducts, sub-ducts, microducts, Intermediate-feed manholes

Optical Cable Pre-Construction Survey. Keywords Stationary Reel Method, empty innerducts, sub-ducts, microducts, Intermediate-feed manholes Optical Cable Pre-Construction Survey Author John Peters Issued December 2012 Abstract Pre-construction site survey is one of the most important steps in the engineering and placement of a new optical

More information

301.7D. Mini Hydraulic Excavator

301.7D. Mini Hydraulic Excavator 301.7D Mini Hydraulic Excavator Engine Weights Gross Power (ISO 14396) 17.9 kw 24.3 hp Operating Weight with Canopy 1610 kg 3,550 lb Net Power 13.2 kw 17.7 hp Operating Weight with Cab 1720 kg 3,792 lb

More information

CHAPTER 8 CIVIL DESIGN

CHAPTER 8 CIVIL DESIGN CHAPTER 8 CIVIL DESIGN A. GENERAL This Chapter includes standards and design considerations for other civil engineering design in structural, drainage and utilities. Design considerations for electrical

More information

Traffic Management Issue 1.0 Revision: v2 October 2014

Traffic Management Issue 1.0 Revision: v2 October 2014 Disclaimer IMPORTANT: The information in this guide is of a general nature, and should not be relied upon as individual professional advice. If necessary, legal advice should be obtained from a legal practitioner

More information

IP Network Control: Turning an Art into a Science. Case Study: Global Crossing

IP Network Control: Turning an Art into a Science. Case Study: Global Crossing Case Study: Global Crossing IP Network Control: Turning an Art into a Science Company: Industry: Global Crossing Holdings Ltd. Telecommunications Challenge(s): Global Crossing want the visibility and control

More information

9. The kinetic energy of the moving object is (1) 5 J (3) 15 J (2) 10 J (4) 50 J

9. The kinetic energy of the moving object is (1) 5 J (3) 15 J (2) 10 J (4) 50 J 1. If the kinetic energy of an object is 16 joules when its speed is 4.0 meters per second, then the mass of the objects is (1) 0.5 kg (3) 8.0 kg (2) 2.0 kg (4) 19.6 kg Base your answers to questions 9

More information