Go-Live Cutover Planning and Conversion Strategy for Discrete Manufacturing Organization (Oracle Applications ERP)

Size: px
Start display at page:

Download "Go-Live Cutover Planning and Conversion Strategy for Discrete Manufacturing Organization (Oracle Applications ERP)"

Transcription

1 Go-Live Cutover Planning and Conversion Strategy for Discrete Manufacturing Organization (Oracle Applications ERP) Introduction: Effective Cutover Planning is very essential for successful Go-Live. Lack of effective planning and execution during this period may lead to severe reconciliation problems and transaction backlogs. Such problems often results in roll-back to legacy system or huge cost pile-up to clear the transaction backlog or reconcile the inaccurate conversion during Cutover period. Such issues can be prevented if good thought is given to plan the Cutover transition phase in a way that is least intrusive and in sync with physical situation of the organization. I've tried to explain some of the important considerations for effective Cutover planning in a discrete manufacturing organization and laid out a step-by-step approach towards the same. Though I've considered Oracle Application as the ERP platform but most of the steps are common to any standard off-the-shelf ERP system. The analysis here is restricted to Inventory and Discrete Manufacturing functions which are often the most complex functions to plan during Cutover due to large volume of data involved. Cutover Planning: Let us refer the following timeline for this case study (indicative dates used for illustration). Go-Live transition has been divided into 4 phases as follows: Production Down-time starts 29th Dec, Friday) End of Post Go-Live Syncup 7 th Jan, Monday A B C D Cutover preparation starts 15 th Dec Go-Live (1st Jan, Monday)

2 Phase A: "Cutover Preparation" This phase starts post UAT sign-off and goes until actual start date of Cutpver. There are several activities which need to be planned and executed before the actual Cutover period starts. Following is a list of steps that need to be executed within this phase. 1. Physical Counting and Stock Adjustments: To ensure accurate inventory migration to a new system at Go-Live it is essential to have accurate inventory figures in the legacy system first. Since Cutover period is usually very short to minimize the production down time, physical counting and stock adjustments in legacy system should be done in Cutover preparation phase. This should be done for all the stores including WIP stores/sub-inventories (if any) Though exact timing for this activity will vary from one organization to another but it should ideally be done as close to actual Cutover as possible to avoid any mismatch in inventory balances during the actual Cutover period. This activity will ensure that legacy system has correct inventory values (and likewise the inventory account balances) and the values recorded during Cutover can be relied upon for loading open balances to new system at Go-Live. This will prevent the users from a tedious activity of physical counting during Cutover period as legacy system has already been brought into sync. with physical stock very recently. 2. Cutover Production Planning: Production should be planned in a way that there is minimum number of open WIP jobs at the cut-over date. Lesser the no. of open jobs at cutover date, lesser would be the open WIP transactions and hence reconciliation would be lot easier and less time consuming. There are usually two production scenarios involved: i) Short Lead Time Assemblies: If the production lead times are short (as compared to the duration of Cutover preparation phase), it is recommended to complete the production of as much assemblies as possible before

3 Cutover. The objective must be to reach near zero WIP (ideally zero) i.e. to inventorize the assemblies and convert them as open stock instead of open jobs. ii) Long Lead Time Assemblies: If the production lead times are long (as compared to the duration of Cutover preparation phase) it might not always be possible to complete all open WIP jobs by cutover date. Under this scenario it is recommended that a judicious Job Cutover stage be decided for such jobs and communicated to shop-floor accordingly. It is very important to stick to this Job cutover schedule as open WIP data will be compiled based on this information and any deviations should be duly recorded in pre-specified template (conversion template for open WIP transactions). It usually becomes very difficult to assess the exact status of open jobs in a short Cutover period and that is the reason it should be a pre-planned activity with all deviations duly recorded. This process helps in quick compilation of the most complex WIP open data for conversion during Cutover phase. Further, It should be ensured that all associated sub-assembly jobs be completed and closed as far as possible before the cutover date. 3. Master data preparation: Master data should be collected and consolidated in pre-decided and well-tested (during SIT/UATs) data formats in this Cutover preparation phase. All master data elements created until this date should be collected and verified for correctness after due sanity checks. Master Data elements pertinent to Manufacturing area are: Item Master along-with Item Categories Departments, Resources and Resource-Department association Bills of Material Routing User defined costs (if any)

4 Since the volume of data involved in a typical Manufacturing organization is huge, getting this master data ready and validated beforehand goes a long-way in achieving smooth conversion. Any potential data issues are identified and resolved way earlier then actual Cutover period thus preventing critical situation in short Cutover period. 4. Configuration and Setups: All system configurations and setups (to be initiated post UAT sign-off) should be completed on Production instance in Cutover preparation stage itself to make the system ready for master data conversions. If possible responsibility matrix and user assignments should also be completed at this stage itself. The objective is to complete as much setup as possible leaving only the last minute setups for Cutover period. 5. Master Data Conversions: All master data collected in step Step # 2 should be migrated to Production instance in this phase to make this instance ready for open transactions data load during the next Cutover phase. Further there should be a process in place to identify the incremental master data records post this conversion and before go-live. It can be a SQL script for each of the master data elements where creation date is greater post this conversion date or there has to be a manual process for this brief duration i.e. whenever a new master data element is created post this date it must be recorded in a separate template as well which can be loaded again prior to Cutover phase start date. 6. Smoke Test: It is recommended to carry out a smoke test to identify any potential issues with Production Setups and overall configuration. Production instance should be cloned post execution of step Step # 5 & 6 to a testing environment where one complete manufacturing cycle can be executed to validate the core setups and master data definitions. It will help in early identification of issues (if any) which if not resolved timely may become show stoppers during Go-Live.

5 Phase B: "Cutover Period" Phase B represents the actual cutover period. No production activity should take place in this Cutover period until absolutely essential since it may lead to reconciliation problems which might be difficult to overcome during short span of Cutover. As per our illustration, it starts on 29 th December, Friday i.e. no production activity will take place between Friday morning and Monday morning. Following is a list of activities to be taken care of during this phase: 7. Incremental Master Data Load: Since bulk of Manufacturing master data is loaded in Cutover preparation phase itself, very few master data records (which have been added since the last load and duly captured as mentioned in Step # 5), would need to be migrated to Production instance during Cutover. Once incremental master data load is completed, it should be reconciled with total records in legacy system as per the pre-tested scripts to ensure that no record has been left out. 8. Incremental Production Setups: There might be few incremental production setups which might need to be done in addition to Step # 4 to make the Production instance ready for transactions e.g. Opening inventory periods. 9. Open Transaction Data Load: Once all remaining master data has been loaded and Production Setups are completed, immediate next step is open transactions loading. Following Open Data elements would need to be loaded for Discrete Manufacturing: Open Inventory Stock (including all inventory stores as well as WIP/shop-floor stores) Since physical stock was already reconciled in cutover preparation phase (Step # 1), no physical counting or adjustments are requiring during this short Cutover period. Please note that open inventory stock conversion should be carried along-with the cost: Average Unit Item Cost (Average Costing) or Standard Unit Item Costs (Standard Costing)

6 Open WIP conversion This conversion will be required in long lead time production scenario as mentioned in Step # 2: Following data elements would need to be converted in case open WIP jobs exist in Cutover: o Open Discrete Jobs: Standard / Non-Standard Discrete Jobs which are still under process during Cutover. o Open Move Transactions: Operation completion transactions which have already been booked against these open jobs. There are usually two options for converting move Transactions. (i) Automated - Convert move transactions through Oracle WIP Move Transactions interface (ii) Manual In this approach users need to perform the move transactions against open jobs manually once Open WIP jobs are converted. It depends upon the availability of time and manpower to choose one of the above approaches. o Open WIP Material Transactions: WIP Material (components) issue transactions (time charged) which have already been booked against these open jobs. There are usually three scenarios for converting WIP Material transactions. (i) Move Transaction linked: If charge type for material is either "Operation Pull" or "Assembly Pull", material will be charged automatically as move transactions are converted in above step or charged during job completion respectively. (ii) Through Interface - Convert WIP material transactions (for components with charge type as "Push") through Oracle WIP Transactions Interface (iii) Manual In this approach users need to perform the WIP material transactions (for components with charge type as "Manual") against open jobs manually to incur the material cost into job valuation. It depends upon the availability of time and manpower to choose one of the above approaches

7 Note: WIP Material conversion is very critical activity as it directly impacts the inventory - WIP valuation. All WIP components which are to be transacted after Job creation must first be converted as inventory stock in WIP stores (or respective sub-inventories which are mapped as supply subinventories in Oracle BOM) i.e. all material stock which has been consumed until Cutover for open jobs must be recorded in pre-specified formats and this stock should be converted as open inventory stock in respective stores as discussed above. o Open Resource Transactions: Resource issue transactions (time charged) which have already been booked against these open jobs. There are usually three scenarios for converting resource transactions. (i) Move Transaction linked: If charge type for resources is used as "WIP Move", resources will be charged automatically as move transactions are converted in above step. (ii) Through Interface - Convert resource transactions (for resources with charge type as "Manual") through Oracle Resource Transactions Interface (iii) Manual In this approach users need to perform the resource transactions (for resources with charge type as "Manual") against open jobs manually once Open WIP jobs are converted to incur the resource cost into job valuation. It depends upon the availability of time and manpower to choose one of the above approaches 10. Pre-Production Smoke Test: It is recommended to clone the Production instance once again (once all above steps are completed successfully) to testing environment to carry out pre-production cycle testing once before Go- Live. 11. Reconciliation: One last step which is most essential before Go-Live is Open Data Reconciliation. All open transaction data balances must exactly match with the balances from legacy system in terms of quantity as well as value. Following are some of the key reconciliation activities:

8 Open inventory stock balances: On-hand Quantity with inventory data compiled from legacy system, Inventory value with the Trial Balance (Material Valuation Account) in legacy system Open WIP balances: No. of Jobs, Material and resource quantities issued to jobs with open data compiled from legacy system; WIP valuation with WIP account balance in Trial Balance from Legacy system Note: Since this article focuses on Cutover Planning and Conversion strategy, I've not covered Reconciliation in detail. I might write a separate post to cover the detailed reconciliation steps involved. There will also be one short article on Account selection and its financial implications for Open Data Migration in Oracle (For Inventory and Manufacturing open data). 12. Go-Live: Once pre-production smoke test and Data reconciliation steps are completed successfully, new system can be pronounced Live and released to business for normal usage.

9 Phase C & D: "Post Go-Live Sync-up and Stabilization Phases" 13. Sync-up Activity: Although it is strongly recommended to shut down all operations during Cutover period but still there might be few transactions which have been carried out in the Cutover period due to their absolutely essential nature. Such transactions, if any, should have been recorded manually outside the system since legacy system is frozen as soon as Cutover phase is pronounced active. Users must enter these transactions manually in the system as soon as the new system goes live. This step is required only in exceptional scenarios and may not be required if everything goes as planned. 14. Demand Aggregation and Production Plan Runs: MDS is defined post go-live to capture all open demand. MDS Run fetches all open Sales Orders and Projects against which shipping is yet to be done and consolidates it into the chosen MDS plan. Master Production Schedule (MPS) and MRP (Material Requirement Planning) plans are then launched to get the supply plan to meet the open demand as recorded by MDS. All open orders are automatically netted as supply thus preventing any duplication. Note: "Net WIP Jobs" should be checked in Plan options. Subsequent plan runs can be scheduled as required by the business. 15. Data References for Business Users: Since business users are usually acquainted to legacy data definitions it often becomes difficult for them to correctly identify data elements in the initial phase after Go-Live due to probable changes in data structures or nomenclatures. This affects their operational efficiency and may lead to lags in transaction recording in new system. Thus, it is recommended to share ready data references to business users for normal functioning of business processes.

10 Hope you will find this analysis interesting; your suggestions and feedback are most welcome! Regards, Manu Singhal The Oracle Manufacturing Blog

Cutover Considerations & ERP Migration Best Practices. General Ledger & Inventory

Cutover Considerations & ERP Migration Best Practices. General Ledger & Inventory Cutover Considerations & ERP Migration Best Practices 2525 South Lamar Blvd. Suite 10 Austin, TX 78704 512.299.9170 www.cetecerp.com General Ledger & Inventory 1. Cease transactional activity in legacy

More information

The Most Powerful Tool In Your Belt

The Most Powerful Tool In Your Belt The Most Powerful Tool In Your Belt M a i n t e n a n c e C o n n e c t i o n 1 4 7 7 D r e w A v e, S u i t e 1 0 3 D a v i s, C A 9 5 6 1 6 P h o n e : ( 8 8 8 ) 567-3434 F a x : ( 7 7 5 ) 2 5 5-6 3

More information

Smarter Balanced Assessment Consortium. Recommendation

Smarter Balanced Assessment Consortium. Recommendation Smarter Balanced Assessment Consortium Recommendation Smarter Balanced Quality Assurance Approach Recommendation for the Smarter Balanced Assessment Consortium 20 July 2012 Summary When this document was

More information

Quality Assurance - Karthik

Quality Assurance - Karthik Prevention is better than cure Quality Assurance - Karthik This maxim perfectly explains the difference between quality assurance and quality control. Quality Assurance is a set of processes that needs

More information

Utilizing KolibriMFG Software System to Schedule and Control Shop Floor

Utilizing KolibriMFG Software System to Schedule and Control Shop Floor Utilizing KolibriMFG Software System to Schedule and Control Shop Floor Lajos Kiss Patternium AC., www.patternium.hu, lk812@vnet.hu Abstract: Manufacturing software modules are essential part of any large

More information

Automating New Market Entry Rollout

Automating New Market Entry Rollout Automating New Market Entry Rollout W H E R E T E C H N O L O G Y W O R K S F O R B U S I N E S S The material contained in this document is proprietary to Triniti (Triniti). This material may not be disclosed,

More information

Going Lean the ERP Way

Going Lean the ERP Way Going Lean the ERP Way Somnath Majumdar Abstract: Lean concepts and techniques are widely used all over the world today to eliminate waste in all processes. These are applicable for all organizations,

More information

How To Implement An Enterprise Resource Planning Program

How To Implement An Enterprise Resource Planning Program ERP Implementation Program Key phases of ERP implementation: Analysis of the company existing or designing new business process descriptions Inventory of the company s existing formal workflows or designing

More information

Data Migration Strategy in ERP Introduction:

Data Migration Strategy in ERP Introduction: Introduction: Along with optimum design of chart of account structure, effective and efficient migration of data is one of the cornerstones for the success of an ERP implementation. Since a number of questions

More information

Material Requirements Planning (MRP)

Material Requirements Planning (MRP) The Priority Enterprise Management System Material Requirements Planning (MRP) Contents MRP - Introduction...2 Calculating Demand for Top-Level Parts...2 Calculating Demand for Sub-assemblies and Raw Materials...3

More information

Milestone Deliverables

Milestone Deliverables Milestone Deliverables The Hands-On Approach To Implementing ERP Projects By Peter Gross Pemeco Inc. 416 Wood Avenue Montréal, Québec H3Y 3J2 Canada Pemeco Inc. Serving Business Since 1978 Table of Contents

More information

Inventory Costing Repair and Restoration

Inventory Costing Repair and Restoration White Paper Dynamics NAV / Navision Inventory Costing Repair and Restoration Now you can use NAV for Inventory Costing as it was meant to be used Download this White Paper on the web at http://www.dynamicswest.com/navisioncostrepair.html

More information

A Culture Change for Inventory Management

A Culture Change for Inventory Management A Culture Change for Inventory Management A Large city hospital moves from implements surgical procedures using Oracle Work-in-Process, with a big leg up from the More4Apps Bill of Materials Wizard. Many

More information

SAP GENERAL LEDGER MIGRATION

SAP GENERAL LEDGER MIGRATION SAP GENERAL LEDGER MIGRATION Support for migration from classic general ledger to new general ledger The new general ledger in SAP ERP Financial Accounting offers quite a lot of functionality, such as

More information

The Stacks Approach. Why It s Time to Start Thinking About Enterprise Technology in Stacks

The Stacks Approach. Why It s Time to Start Thinking About Enterprise Technology in Stacks The Stacks Approach Why It s Time to Start Thinking About Enterprise Technology in Stacks CONTENTS Executive Summary Layer 1: Enterprise Competency Domains Layer 2: Platforms Layer 3: Enterprise Technology

More information

MANAGE. Inventory Costing. Microsoft Dynamics NAV 5.0. Technical White Paper

MANAGE. Inventory Costing. Microsoft Dynamics NAV 5.0. Technical White Paper MANAGE Microsoft Dynamics NAV 5.0 Inventory Costing Technical White Paper This paper is intended for people who are involved in the implementation of costing functionality at a customer site and for those

More information

WHITE PAPER. Ready, Set, Go Upgrade to ERP Cloud Release 10

WHITE PAPER. Ready, Set, Go Upgrade to ERP Cloud Release 10 WHITE PAPER Ready, Set, Go Upgrade to ERP Cloud Release 10 INTRODUCTION It s time to upgrade our ERP. For many, those words often trigger thoughts of projects past where countless hours are spent bringing

More information

ERP Course: Production and Materials Management Reading: Chapter 6 from Mary Sumner

ERP Course: Production and Materials Management Reading: Chapter 6 from Mary Sumner ERP Course: Production and Materials Management Reading: Chapter 6 from Mary Sumner Peter Dolog dolog [at] cs [dot] aau [dot] dk 5.2.03 Information Systems September 16, 2008 2 Sales Finished and packaged

More information

Migrating to Google Apps for Work An Inside Look at How Enterprises Go Google

Migrating to Google Apps for Work An Inside Look at How Enterprises Go Google Migrating to Google Apps for Work An Inside Look at How Enterprises Go Google CONTENTS Introduction Prep Steps Execution Post Go-Live/Closeout Executive Summary At Accenture, we are often asked two questions

More information

Aegis Standard Report Template Examples

Aegis Standard Report Template Examples Aegis Standard Report Template Examples Contents Introduction... 3 Quality and Test Reports... 4 NPI Reports... 13 Production & WIP Tracking Reports... 18 System Administration Reports... 23 Material and

More information

MASTER PRODUCTION SCHEDULE

MASTER PRODUCTION SCHEDULE 6 MASTER PRODUCTION SCHEDULE MGT2405, University of Toronto, Denny Hong-Mo Yeh So far, in discussing material requirement planning (MRP), we have assumed that master production schedule (MPS) is ready

More information

Managing Agile Projects in TestTrack GUIDE

Managing Agile Projects in TestTrack GUIDE Managing Agile Projects in TestTrack GUIDE Table of Contents Introduction...1 Automatic Traceability...2 Setting Up TestTrack for Agile...6 Plan Your Folder Structure... 10 Building Your Product Backlog...

More information

Master Production Scheduling

Master Production Scheduling Master Production Scheduling Revised May 7, 2002. mps.doc Author: Dean Ziegler, CPIM Table of Contents Instructions: Search Tips Using Systems2win Word documents Systems2win Copyright Terms How does Master

More information

Oracle Project Management: r12 Inventory Management Bill of Material Engineering Accel r12.x

Oracle Project Management: r12 Inventory Management Bill of Material Engineering Accel r12.x coursemonster.com/uk Oracle Project Management: r12 Inventory Management Bill of Material Engineering Accel r12.x View training dates» Overview This course will be applicable for customers who have implemented

More information

efacto efacto is a multipurpose ERP Software for

efacto efacto is a multipurpose ERP Software for efacto efacto is a multipurpose ERP Software for Manufacturing Distribution Manufacturing and Distribution innovated after brainstorming efforts by skilled techno logician and continually updated based

More information

Automation, End User Engagement, and Business Process Improvement

Automation, End User Engagement, and Business Process Improvement Automation, End User Engagement, and Business Process Improvement The Recipe for R12 Implementation Success Table of Contents Overview 1 Conversion of Vast Amounts of Data 1 Automating Using MORE4APPS

More information

Data Collection for Manufacturing

Data Collection for Manufacturing for Manufacturing G.S.D. Associates offers data collection expertise in the key applications that help our customers operate more efficiently and at lower cost: Work-In-Process (WIP) Tracking, Inventory

More information

Consolidating Multiple Product Development Systems at TreeHouse Foods into SAP Product Lifecycle Management

Consolidating Multiple Product Development Systems at TreeHouse Foods into SAP Product Lifecycle Management Consolidating Multiple Product Development Systems at TreeHouse Foods into SAP Product Lifecycle Management Kathy Kugelman, TreeHouse Foods Robin Patrawala, Linx-AS SESSION CODE: PL1288 AGENDA About TreeHouse

More information

In this topic, you will learn about SAP s recommended methodology and tools for managing implementation projects.

In this topic, you will learn about SAP s recommended methodology and tools for managing implementation projects. In this topic, you will learn about SAP s recommended methodology and tools for managing implementation projects. 1 On completion of this topic, you will be able to: Describe the Accelerated Implementation

More information

Go-Live / Migration Considerations. General Ledger & Inventory. 2525 South Lamar Blvd. Suite 10 Austin, TX 78704 512.299.9170 www.tech-x.

Go-Live / Migration Considerations. General Ledger & Inventory. 2525 South Lamar Blvd. Suite 10 Austin, TX 78704 512.299.9170 www.tech-x. Go-Live / Migration Considerations 2525 South Lamar Blvd. Suite 10 Austin, TX 78704 512.299.9170 www.tech-x.com General Ledger & Inventory 1. Cease transactional activity in legacy system. 2. Export trial

More information

Graphical Scheduler. Get on time All the time. For Production

Graphical Scheduler. Get on time All the time. For Production Graphical Scheduler Get on time All the time For Production Summary JobPack Graphical Scheduler provides REAL DELIVERY DATES, Instantly and in real time. At a glance late jobs are known, bottlenecks identified,

More information

Seradex White Paper A newsletter for manufacturing organizations April, 2004

Seradex White Paper A newsletter for manufacturing organizations April, 2004 Seradex White Paper A newsletter for manufacturing organizations April, 2004 Using Project Management Software for Production Scheduling Frequently, we encounter organizations considering the use of project

More information

Top reasons why ekanban should be a key element of your lean manufacturing plan

Top reasons why ekanban should be a key element of your lean manufacturing plan Infor ERP Top reasons why ekanban should be a key element of your lean manufacturing plan Table of contents Executive summary... 3 Reactive manufacturing model... 4 Move over manual Kanban... 6 Electronic

More information

Improve your Close Cycle Using Financial Close Manager

Improve your Close Cycle Using Financial Close Manager Improve your Close Cycle Using Financial Close Manager 2.28.2014 Presenters Seth Landau EVP of Consulting Services MindStream Analytics slandau@mindstreamanalytics.com www.mindstreamanalytics.com AGENDA

More information

5 Steps To Successful ERP Implementation

5 Steps To Successful ERP Implementation By Sean W. O Donnell, President, Datacor, Inc. Introduction Tougher competition in the marketplace is generating the need to better optimize resources, improve profitability and keep customers satisfied.

More information

MATERIAL REQUIREMENTS PLANNING

MATERIAL REQUIREMENTS PLANNING MATERIAL REQUIREMENTS PLANNING A basic tool for performing the detailed material planning function in the manufacture of component parts and their assembly into finished items. MRP s Managerial objective

More information

Earned Value Management for Enterprise Resource Planning Implementations

Earned Value Management for Enterprise Resource Planning Implementations Earned Value Management for Enterprise Resource Planning Implementations Venu Kotamraju Abstract ERP implementations are a special breed of projects. They are often characterized by aggressive timelines,

More information

CHAPTER 6 AGGREGATE PLANNING AND INVENTORY MANAGEMENT 명지대학교 산업시스템공학부

CHAPTER 6 AGGREGATE PLANNING AND INVENTORY MANAGEMENT 명지대학교 산업시스템공학부 CHAPTER 6 AGGREGATE PLANNING AND INVENTORY MANAGEMENT 명지대학교 산업시스템공학부 Learning Objectives You should be able to: Describe the hierarchical operations planning process in terms of materials planning & capacity

More information

Automated Inventory System

Automated Inventory System Automated Inventory System User Manual Developed by USDA Food and Nutrition Service June 2009 (Incomplete) Table of Contents Welcome Menu Client Services Report System Inventory System Operations Tailgate

More information

Job Manager for Tool and Die Shops

Job Manager for Tool and Die Shops Job Manager for Tool and Die Shops What makes Tool and Die Shops unique? First, most orders are for a unique Tool or Die. No two Jobs are alike. The Job is a one of a kind job, not a mass production type

More information

DEVELOPMENT OF LOW COST MRP SOFTWARE FOR A MANUFACTURING,

DEVELOPMENT OF LOW COST MRP SOFTWARE FOR A MANUFACTURING, KOLEJ UNIVERSITI TEKNIKAL KEBANGSAAN MALAYSIA DEVELOPMENT OF LOW COST MRP SOFTWARE FOR A MANUFACTURING, PROCESS Thesis submitted in accordance with the partial requirements of the Kolej Universiti Teknikal

More information

TEN TIPS FOR A SUCCESSFUL INFOR IMPLEMENTATION

TEN TIPS FOR A SUCCESSFUL INFOR IMPLEMENTATION TEN TIPS FOR A SUCCESSFUL INFOR IMPLEMENTATION Copyright 2015 Panorama Consulting Solutions. All Rights Reserved. 720.515.1377 Panorama- Consulting.com Successfully implementing an Infor ERP system involves

More information

Agile QA Process. Anand Bagmar Anand.Bagmar@thoughtworks.com abagmar@gmail.com http://www.essenceoftesting.blogspot.com. Version 1.

Agile QA Process. Anand Bagmar Anand.Bagmar@thoughtworks.com abagmar@gmail.com http://www.essenceoftesting.blogspot.com. Version 1. Agile QA Process Anand Bagmar Anand.Bagmar@thoughtworks.com abagmar@gmail.com http://www.essenceoftesting.blogspot.com Version 1.1 Agile QA Process 1 / 12 1. Objective QA is NOT the gatekeeper of the quality

More information

SAP APO SNP (Supply Network Planning) Sample training content and overview

SAP APO SNP (Supply Network Planning) Sample training content and overview SAP APO SNP (Supply Network Planning) Sample training content and overview Course Objectives At the completion of this course, you will be able to: Understand the concepts of SNP and supply chain network

More information

4.4 Commissioning, Handover and Warranty

4.4 Commissioning, Handover and Warranty 4.4 Commissioning, Handover and Warranty 4.4.1 Building Commissioning and Manuals The Building Commissioning formalizes the review and integration of all project expectations during the planning and design,

More information

This case study walks you through the challenges involved in each step of the MDM initiative as shown in Fig.1 below: Oracle PLM.

This case study walks you through the challenges involved in each step of the MDM initiative as shown in Fig.1 below: Oracle PLM. Critical Success Factors for an MDM Initiative A Case Study of Cypress Semiconductor Mahender Bist Rapidflow Apps Inc. Jay Kilby Cypress Semiconductor Abstract Master Data Management (MDM) is becoming

More information

esims Web Overview. Synthes Information Management Suite.

esims Web Overview. Synthes Information Management Suite. esims Web Overview. Synthes Information Management Suite. esims Table of Contents esims Web Overview What Is it? 2 Options 2 Before You Get Started 3 Technical Requirements 4 Project Implementation Timeline

More information

Microsoft Dynamics GP

Microsoft Dynamics GP Microsoft Dynamics GP How to determine, maintain, and report accurate costing in Inventory in Microsoft Dynamics GP 9.0 and 10.0 Article This article has been provided to address questions about the calculation

More information

Business System Software

Business System Software Business System Software BUSINESS SYSTEM SOFTWARE For Custom Product Manufacturing Engineering Fabrication & Jobbing Food & Chemical Process Industries Distribution & Wholesale Sales, Service & Repair

More information

Configuration and Asset Management

Configuration and Asset Management IT Product Life Cycle Management 43 Chapter 4 Configuration and Asset Management Configuration management is the process of monitoring and reviewing approved product configurations periodically while the

More information

Cloud Services Guide. (Managed Services Guide) JDA Cloud Services. Version 3.3. Date: 29th October 2012

Cloud Services Guide. (Managed Services Guide) JDA Cloud Services. Version 3.3. Date: 29th October 2012 Cloud Services Guide (Managed Services Guide) JDA Cloud Services Version 3.3 Date: 29th October 2012 Legal notice Copyright 2012, JDA Software Group, Inc. All rights reserved. JDA is a Registered Trademark

More information

IMPLEMENTATION OF ERP IN A SMALL ORGANIZATION FOR SEAMLESS TECHNOLOGY

IMPLEMENTATION OF ERP IN A SMALL ORGANIZATION FOR SEAMLESS TECHNOLOGY IMPLEMENTATION OF ERP IN A SMALL ORGANIZATION FOR SEAMLESS TECHNOLOGY Mr. Ashok Kumar, HOD/Associate Professor, Deptt. Of Computer Science & Engineering, GRD Institute of management & technology, Dehradun,

More information

Microsoft Dynamics NAV

Microsoft Dynamics NAV Microsoft Dynamics NAV Maximizing value through business insight Business Intelligence White Paper November 2011 The information contained in this document represents the current view of Microsoft Corporation

More information

CLOUD TRENDS & MIGRATION TO THE CLOUD. Udi Keidar VP Cloud Services, ClickSoftware

CLOUD TRENDS & MIGRATION TO THE CLOUD. Udi Keidar VP Cloud Services, ClickSoftware CLOUD TRENDS & MIGRATION TO THE CLOUD Udi Keidar VP Cloud Services, ClickSoftware Market Trends What happens in the market SaaS Adoption Is Growing Across The Enterprise Forrester: Key Takeaways - General

More information

Overcoming Testing Challenges in SAP Upgrade Projects

Overcoming Testing Challenges in SAP Upgrade Projects Overcoming Testing Challenges in SAP Upgrade Projects Applies to: SAP Upgrade Projects. For more information, visit the Enterprise Resource Planning homepage. Summary Testing in SAP Upgrade forms the crucial

More information

ORACLE CONFIGURE TO ORDER SOLUTION

ORACLE CONFIGURE TO ORDER SOLUTION ORACLE CONFIGURE TO ORDER SOLUTION KEY FEATURES ORACLE CONFIGURE TO ORDER SOLUTION PROVIDES SUITE LEVEL SUPPORT FOR YOUR CONFIGURED BUISNESS. KEY FEATURES INCLUDE: Create and maintain assemble to order

More information

Guidelines for Effective Data Migration

Guidelines for Effective Data Migration Guidelines for Effective Data Migration Applies to: SAP R/3. All releases. For more information, visit the ABAP homepage. Summary Data Migration is an important step in any SAP implementation projects.

More information

Realizing the Benefits of Finite Capacity Scheduling to Manage Batch Production Systems

Realizing the Benefits of Finite Capacity Scheduling to Manage Batch Production Systems Presented at the WBF North American Conference Baltimore, MD, USA 30 April - 4 May 2007 67 Alexander Drive PO Box 12277 Research Triangle Park, NC 27709 +1.919.314.3970 Fax: +1.919.314.3971 E-mail: info@wbf.org

More information

9 Steps to Successful SharePoint Migration to Office365. By Sebastian Atar

9 Steps to Successful SharePoint Migration to Office365. By Sebastian Atar 9 Steps to Successful SharePoint Migration to Office365 By Sebastian Atar 9 Steps to Successful SharePoint Migration to Office365 By Sebastian Atar Goal The goal of this white paper is to prepare you to

More information

WHITEPAPER. Count your inventory in the right way for right results. Abstract

WHITEPAPER. Count your inventory in the right way for right results. Abstract WHITEPAPER Count your inventory in the right way for right results - Shantanu Anant Bedekar Abstract ERPs provide many features for cycle count setup and execution. Organizations err by not utilizing any

More information

Retail Business Management Software Implementation

Retail Business Management Software Implementation Retail Business Management Software Implementation 1. Introduction In the changing business environment, successful IT implementation plays a crucial role in the success and growth of a retail business.

More information

Oracle Asset Tracking

Oracle Asset Tracking Oracle Asset Tracking User's Guide Release 12.2 Part No. E48803-04 September 2015 Oracle Asset Tracking User's Guide, Release 12.2 Part No. E48803-04 Copyright 2008, 2015, Oracle and/or its affiliates.

More information

Top 10 Reasons to Virtualize VMware Zimbra Collaboration Server with VMware vsphere. white PAPER

Top 10 Reasons to Virtualize VMware Zimbra Collaboration Server with VMware vsphere. white PAPER Top 10 Reasons to Virtualize VMware Zimbra Collaboration Server with VMware vsphere white PAPER Email outages disrupt a company s ability to conduct business. Issues as diverse as scheduled downtime, human

More information

ebook for creative agencies using project management software to increase productivity in your agency

ebook for creative agencies using project management software to increase productivity in your agency ebook for creative agencies using project management software to ebook for creative agencies About the Authors Summary Introduction..... 3 7 Creative Roles.... 6 New Business.... 11 Creative Team......

More information

Case Study: How Hollister Simultaneously Minimized Inventory Costs and Stabilized Service Levels Using Two Little Known, but Effective, Tools

Case Study: How Hollister Simultaneously Minimized Inventory Costs and Stabilized Service Levels Using Two Little Known, but Effective, Tools Case Study: How Hollister Simultaneously Minimized Inventory Costs and Stabilized Service Levels Using Two Little Known, but Effective, Tools Steve Grace Hollister Incorporated 2011 Wellesley Information

More information

2. Which transaction in the order-to-cash business process creates a financial accounting document?

2. Which transaction in the order-to-cash business process creates a financial accounting document? SAP EDUCATION SAMPLE QUESTIONS: C_TERP10_65 Disclaimer: These sample questions are for self-evaluation purposes only and do not appear on the actual certification exams. Answering the sample questions

More information

SAP ERP Upgrade Checklist Project Preparation

SAP ERP Upgrade Checklist Project Preparation A SAP ERP Upgrade Checklist Project Preparation Upgrade Project Phase Project Preparation Definition From the project perspective the project preparation phase includes: Learning about the new functionality

More information

Enterprise Data Management. Data Factory as a Service (DFaS)

Enterprise Data Management. Data Factory as a Service (DFaS) Enterprise Data Management Data Factory as a Service (DFaS) Data Factory as a Service (DFaS) What is DFaS? DFaS offers a proven approach to deliver comprehensive services for end-to-end data conversion

More information

FaciliWorks. Desktop CMMS Software. Making Maintenance Manageable

FaciliWorks. Desktop CMMS Software. Making Maintenance Manageable FaciliWorks Desktop CMMS Software Making Maintenance Manageable Why Your Facility Needs CMMS Software Improve productivity Control operations and maintenance costs Maximize asset uptime Prevent mistakes

More information

Line of Business Solutions Complement Large Scale Postmodern ERP Deployment Strategies by Cultura Technologies

Line of Business Solutions Complement Large Scale Postmodern ERP Deployment Strategies by Cultura Technologies Line of Business Solutions Complement Large Scale Postmodern ERP Deployment Strategies by Cultura Technologies Executive Summary Highly specialized Line of Business (LOB) solutions, such as AGRIS and CINCH,

More information

Wave 2 User Acceptance Testing (UAT) Scenario Workshop Cash Management (CM)

Wave 2 User Acceptance Testing (UAT) Scenario Workshop Cash Management (CM) Wave 2 User Acceptance Testing (UAT) Scenario Workshop Cash Management (CM) Agenda Purpose and Expected Outcome Wave 1 UAT Scenarios Functionality Introduction Review Related UAT Scenarios Collect Additional

More information

Job Manager for Metal Fabrication

Job Manager for Metal Fabrication Job Manager for Metal Fabrication What makes Metal Fabrication unique? First, most metal shops are building to unique specifications. The Jobs are service type jobs, not production type jobs. Mass Production

More information

A GUIDE TO IMPLEMENTING SAP BUSINESS ONE

A GUIDE TO IMPLEMENTING SAP BUSINESS ONE A GUIDE TO IMPLEMENTING SAP BUSINESS ONE THE ULTIMATE GUIDE If you are considering SAP Business One as your business management solution or have already selected SAP Business One and you are about to embark

More information

Oracle Network Logistics

Oracle Network Logistics Oracle Network Logistics Concepts and Procedures Release 11i November, 2000 Part No. A86681_01 Oracle Network Logistics Concepts and Procedures, Release 11i Part No. A86681_01 Copyright 1996, 2000, Oracle

More information

Anytime Banking Troubleshooting

Anytime Banking Troubleshooting Anytime Banking Troubleshooting Welcome to the Troubleshooting area. Here you can get information and suggestions for problems you may be experiencing. Click on a problem below for information and suggestions

More information

AVLOR SERVER CLOUD RECOVERY

AVLOR SERVER CLOUD RECOVERY AVLOR SERVER CLOUD RECOVERY WHITE PAPER 1 Table of Contents Abstract... 2 1. Introduction... 3 2. Server Cloud Recovery... 3 3. Amazon AWS Cloud... 4 a. What it is... 4 b. Why Use AWS?... 5 4. Difficulties

More information

for Sage 100 ERP Work Order Overview Document

for Sage 100 ERP Work Order Overview Document for Sage 100 ERP Work Order Document 2012 Sage Software, Inc. All rights reserved. Sage Software, Sage Software logos, and the Sage Software product and service names mentioned herein are registered trademarks

More information

MD348 Umoja Asset, Inventory and Equipment Master Data Maintenance. Umoja Asset, Inventory and Equipment Master Data Maintenance Version 5 1

MD348 Umoja Asset, Inventory and Equipment Master Data Maintenance. Umoja Asset, Inventory and Equipment Master Data Maintenance Version 5 1 MD348 Umoja Asset, Inventory and Equipment Master Data Maintenance Umoja Asset, Inventory and Equipment Master Data Maintenance Version 5 Copyright Last Modified: United Nations 17-August-13 1 Agenda Course

More information

SMART Solutions for Active Directory Migrations

SMART Solutions for Active Directory Migrations SMART Solutions for Active Directory Migrations Challenges of Active Directory Migrations Types of Active Directory Migrations Intra- Forest Migration between Domains in the Same Forest Separate a Forest

More information

White Paper On Pilot Method Of ERP Implementation

White Paper On Pilot Method Of ERP Implementation White Paper On Pilot Method Of ERP Implementation Rod Clarke Rod Clarke provides guidance, advice and support to businesses in successfully applying IS/IT in support of their business goals. He brings

More information

ICS Technology. PADS Viewer Manual. ICS Technology Inc PO Box 4063 Middletown, NJ 077748 732-671-5400 www.icstec.com

ICS Technology. PADS Viewer Manual. ICS Technology Inc PO Box 4063 Middletown, NJ 077748 732-671-5400 www.icstec.com ICS Technology PADS Viewer Manual ICS Technology Inc PO Box 4063 Middletown, NJ 077748 732-671-5400 www.icstec.com Welcome to PADS Viewer Page 1 of 1 Welcome to PADS Viewer Welcome to PADS (Public Area

More information

Brochure. SAP Business One for Manufacturing. Software for Manufacturing Organisations

Brochure. SAP Business One for Manufacturing. Software for Manufacturing Organisations Brochure SAP Business One for Manufacturing Software for Manufacturing Organisations SAP Business One for Manufacturing SAP Business One for Manufacturing offers an unparalleled combination of functionality

More information

44-76 mix 2. Exam Code:MB5-705. Exam Name: Managing Microsoft Dynamics Implementations Exam

44-76 mix 2. Exam Code:MB5-705. Exam Name: Managing Microsoft Dynamics Implementations Exam 44-76 mix 2 Number: MB5-705 Passing Score: 800 Time Limit: 120 min File Version: 22.5 http://www.gratisexam.com/ Exam Code:MB5-705 Exam Name: Managing Microsoft Dynamics Implementations Exam Exam A QUESTION

More information

OpenERP at a Glance. Open Source: OpenERP is committed to Open Source. The software is published under the AGPL licence

OpenERP at a Glance. Open Source: OpenERP is committed to Open Source. The software is published under the AGPL licence OpenERP at a Glance OpenERP is a comprehensive suite of business applications including Sales, CRM, Chatter, Project management, Warehouse management, Manufacturing, Accounting and Human Resources. Complete

More information

Inventory Management Overview Document. for Sage 100 ERP

Inventory Management Overview Document. for Sage 100 ERP Document for Sage 100 ERP 2012 Sage Software, Inc. All rights reserved. Sage Software, Sage Software logos, and the Sage Software product and service names mentioned herein are registered trademarks or

More information

PIVOTAL CONNECTOR FOR MARKETO. Copyright 2015 Tokara Solutions. All Rights Reserved.

PIVOTAL CONNECTOR FOR MARKETO. Copyright 2015 Tokara Solutions. All Rights Reserved. PIVOTAL CONNECTOR FOR MARKETO CRM & Marketing Integration: Why It s Needed In addition to generating brand buzz and creating campaign collateral, your marketing teams are working hard at contact management

More information

Best Practices in Release and Deployment Management

Best Practices in Release and Deployment Management WHITEPAPER Best Practices in Release and Deployment Management Mark Levy Through 2016, a lack of effective release management will contribute up to 80% of production incidents in large organizations with

More information

Synchronization via API. Business Overview

Synchronization via API. Business Overview Synchronization via API Business Overview Introduction Content Intent and Scope Objectives Definitions Stock Sync Order Sync Returns Product Creation Requirements? FAQs Introduction Intent and Scope Intent

More information

The Power of Inventory Control: Serialized Inventory Tracking

The Power of Inventory Control: Serialized Inventory Tracking The Power of Inventory Control: Serialized Inventory Tracking At a Glance: Legacy ERP solutions often do not reflect the physical reality of the material handling process. These legacy systems force the

More information

ebook THE SURVIVAL GUIDE FOR MIGRATING TO A CLOUD- BASED CRM

ebook THE SURVIVAL GUIDE FOR MIGRATING TO A CLOUD- BASED CRM ebook THE SURVIVAL GUIDE FOR MIGRATING TO A CLOUD- BASED CRM Table of Contents 03 04 06 08 09 10 12 INTRODUCTION PROJECT KICK-OFF & EFFECTIVE COMMUNICATION TRAIN, TRAIN, AND TRAIN AGAIN SELL THE PRODUCT

More information

Preparing For the Demo

Preparing For the Demo HMS Demo Script Copyright Copyright 2002-2003 Horizons International, Inc. All rights reserved. Information in this document is subject to change without notice. The software described in this document

More information

Material Requirements Planning (MRP)

Material Requirements Planning (MRP) Material Requirements Planning (MRP) Unlike many other approaches and techniques, material requirements planning works which is its best recommendation. Joseph Orlicky, 1974 1 History Begun around 1960

More information

Introduction to Buying a Small Business Cloud ERP Solution from VersAccounts

Introduction to Buying a Small Business Cloud ERP Solution from VersAccounts Introduction to Buying a Small Business Cloud ERP Solution from VersAccounts Global Dec 1, 2014 Thank you for your interest in VersAccounts! Data Sheet Contact Us: North America: +1 855 445 2281 Europe:

More information

COST/FUNDING SOURCE: $549,050/FY2014 and FY2015 Uniform Rate

COST/FUNDING SOURCE: $549,050/FY2014 and FY2015 Uniform Rate AGENDA ITEM C3 DATE: April 7, 2014 TO: FROM: SUBJECT: Matt Jordan, General Manager Charles H. Carden, Chief Operating Officer Computerized Maintenance Management System Implementation Services Award Contract

More information

The End of Reconciliation - Feed Manager

The End of Reconciliation - Feed Manager The End of Reconciliation - Feed Manager Client: Large Merchant Trading Organization Exchange Trades per Day: 4,000 Reconciliations eliminated: 4 The Business Problem Our client is a large merchant trading

More information

Oracle SCM. Course duration: 45 Hrs Class duration: 1-1.5hrs

Oracle SCM. Course duration: 45 Hrs Class duration: 1-1.5hrs Course duration: 45 Hrs Class duration: 1-1.5hrs Course are: Inventory Purchasing Order Management Brief Introduction to WIP and BOM Manufacturing Modules Overview on R12 SCM Modules Oracle SCM New Features

More information

Jet Data Manager 2012 User Guide

Jet Data Manager 2012 User Guide Jet Data Manager 2012 User Guide Welcome This documentation provides descriptions of the concepts and features of the Jet Data Manager and how to use with them. With the Jet Data Manager you can transform

More information

Four Strategies for Smarter Inventory Control

Four Strategies for Smarter Inventory Control Whitepaper April 2016 Four Strategies for Smarter Inventory Control Section 01 Synopsis This paper is provided for companies that carry inventory (manufacturers, distributors, retailers and service providers)

More information

Worksoft Case Study www.worksoft.com 1

Worksoft Case Study www.worksoft.com 1 U.S. Federal Government Agency Executive Summary A U.S. Federal Government Agency recently adopted Worksoft Certify to increase efficiency, reduce costs, shorten project timelines, capture institutional

More information

Key Insight 5 Marketing Goals and Objectives You Should Set. By WalkMe

Key Insight 5 Marketing Goals and Objectives You Should Set. By WalkMe 1 Key Insight 5 Marketing Goals and Objectives You Should Set By WalkMe 2 Setting appropriate marketing goals and objectives can increase your chances of success in business. You are able to align the

More information