1 Microsoft Quick Reference Tutorial Key Terms 2007 The Interface In a business sense, a project is an undertaking that will accomplish a specific task, such as the launch of a new product, an office party, or writing a report. Management The art of aligning resources and schedules to accomplish all of the tasks required for a project. Resource A person or thing that will be used to accomplish a task. For example, wood and carpenters would both be resources needed to build a house. Task Something that must be achieved for your project to be successful. For example, wood must be used to build a house. Constraint Constraints restrict the start and finish date of tasks. How long the task will take to complete. Units Labor needed to complete the task. If a resource is needed to complete the task, how much will be required. Title Bar (1) This tells you what program you re working in (Microsoft ) and what project (1). By default, Microsoft 2007 names unsaved projects 1, 2, and so on. Effort-driven Material driven These types of tasks will be completed by people. These types of tasks will be completed by resources. Menu Bar (2) Type a Question (3) Click any of these commands to see a list of possible options, then, click any of the options to perform that action. If you have a question, type it here! Keyboard Shortcuts Open a new project Ctrl + N Save a file Ctrl + S Open a file Ctrl + O Print a project Ctrl + P Close Alt + F4 Select All Ctrl + A Copy text Ctrl + C Cut text Ctrl + X Paste text Ctrl + V Undo last action Ctrl + Z Redo last action Ctrl + Z Find text Ctrl + F Replace text Ctrl + H New Task Insert Key Open Task Information Shift + F2 Document Controls (4) Toolbars (5, 6) Task Panes (7) Window (8) Status Bar (9) Scroll Bars (10, 11, 12) These buttons let you minimize ( ), maximize/restore ( ), or close () a certain project or the application. Toolbars have icons, which are small buttons with pictures that represent actions. When you click the button, that action will happen. For example, you could click the standard toolbar and your project would save. icon on the Task panes can display lots of different information, functional options, wizards, or links to other task panes or resources. You can navigate through task panes almost like pages in a browser. This is where you will enter your project s task information. In this image, you can see the task entry panel on the right and the Gantt chart (with dates listed at the top like a timeline) on the left. This bar can provide information on the current status of your application. Use these bars to view different parts of your window. You can use the arrows to move the view to the left or right, or drag the scroll bar to where you want it Velsoft Courseware Inc. All rights reserved. Velsoft Quick Reference Tutorial
2 Entering a New Task By default, will open to the task entry screen. Just type your task name and durations in the list. abbreviations: m Minute h Hour d Day w Week mo Month y Year Calendar Types There are three types of calendars in Microsoft : calendar Resource calendar This is the main calendar that controls when tasks are worked on and when resources work on tasks. Each resource can have its own calendar to reflect its hours of availability. Fields Captured for a Baseline Tasks Start Finish Cost Assignments Start Resources Finish Cost Cost Constraint Types Name Description Type As Soon As Possible (ASAP) As Late As Possible (ALAP) Start No Earlier Than (SNET) Finish No Earlier Than (FNET) Start No Later Than (SNLT) Finish No Later Than (FNLT) Must Start On (MSO) Must Finish On (MFO) All tasks start as soon as possible if you asked to schedule from the start date. All tasks start as late as possible if you asked to schedule from the end date. Specify the earliest possible date that this task can start. Specify the earliest possible date that this task can finish. Specify the latest possible date that this task can start. Specify the latest possible date that this task can finish. Specify the date that this task must start on. Specify the date that this task must finish on. Planning Your Inflexible Inflexible Task calendar Sometimes a task will need to have its own calendar to reflect its duration; for example, if a machine will run 24 hours a day. There are also three base calendars, which are like calendar templates. Standard ing time is set Monday through Friday, 8 am to 5 pm, with an hour (noon to 1 pm) set aside for lunch. Night Shift ing time is set Monday through Friday, 11 pm to 8 am, with an hour (3 am to 4 am) set aside for lunch. 24 hours ing time is every day and hour of the week; useful for resources (such as machines) that run constantly. Task Types Task Type Explanation If you change Fixed duration Fixed units (default task type) Fixed for these tasks will not change. This task s units will remain constant. This task s work will remain constant. recalculates Effort or material driven Units Either Units Units Either Units Effort driven Printing Your Units First, create a general outline of the project. You ll want to think about what the end result of the project will be. You ll also want to think about the general timeline, budget, and resources that you will have available. Next, create a task list. In this list you may want to specify how long each task is going to take, which tasks are going to be dependent on others, and which ones need to be broken down into sub-projects. Next, make a list of resources. Last but not least, think about your costs. You may even want to prepare a formal budget. File Print Ctrl + P Print icon ( ) on the standard toolbar Print Preview screen Page Setup dialogue Guide 2005 Velsoft Courseware Inc. All rights reserved. Velsoft Quick Reference tutorial.
3 Microsoft Quick Reference Tutorial 2007 Viewing the WBS Code 1. Switch to any table view. 2. Right-click a column header. 3. Click Insert Column. 4. Choose WBS for the field name. 5. Click OK. Using the Guide to Track Progress 1. Click the Track arrow. 2. Click Check the progress of the project. 3. Specify a status date. 4. Use filters and groups to gather data. Creating a Custom Filter 1. Click the menu. 2. Click Filtered For. Click More Filters. 3. Choose Task or Resource. 4. Click New. 5. Enter your criteria. 6. Click OK. Creating a Custom Toolbar 1. Right-click in a blank space beside the menu. 2. Click Customize. 3. Click the Toolbars tab. 4. Click New. 5. Enter a name for the toolbar. 6. Use the Commands tab of the Customize dialogue to add buttons to your toolbar. Status Indicators Blank Task is complete. Task is not complete, but all scheduled work has been completed by the status date. All scheduled work has not been completed by the status date. Task isn t scheduled to start until after the status date. Task Type Overview Task Type Explanation Must be Effort Driven? Fixed for these tasks will not change. No Fixed Units (Default Type) This task s units will remain constant. Fixed This task s work will remain constant. Yes No 2005 Velsoft Courseware Inc. All rights reserved. Velsoft Quick Reference Tutorial
4 Creating and Using Cost Resources New addition to Like a fixed cost, a cost resource has no relationship to the work required for a task or the amount of work resources applied to the task. Unlike a fixed cost, multiple cost resources can be assigned to a task. To create a cost resource: 1. Switch to Resource Sheet view. 2. Type the name for the resource. 3. Choose Cost for the resource type. To use a cost resource: 1. Switch to Gantt Chart view. 2. Select a task. 3. Click the Tools menu and click Assign Resources. 4. Choose your cost resource. 5. Enter a monetary value. Progress Line Types Interpreting Progress Lines Permanent Progress Line (circled in red) Recurring Progress Lines (circled in blue) Selected Progress Lined (circled in green) Choose to always display the current progress line, at the current date or the status date. Choose a date to have a progress line appear at every day, week, or month. Set specific dates to have progress lines appear. Right-facing peaks (in orange) Left-facing peaks (in blue) Straight line (in green) Tasks untouched by the progress line (in red) Task is ahead of schedule. Task is behind schedule. Task is on schedule. In the future, not affected by the progress line. Linking a to a Resource Pool Unlinking a from a Resource Pool 1. Open the project. 2. Open the resource pool. 3. Click the Tools menu. Choose Resource Sharing and click Share Resources. 4. Choose Use resources from... and select your file. 5. Set precedence options. Click OK. 1. Open the project. 2. Open the resource pool. 3. Click the Tools menu. Choose Resource Sharing and click Share Resources. 4. Choose Use own resources. 5. Click OK Velsoft Courseware Inc. All rights reserved. Velsoft Quick Reference Tutorial.
5 Microsoft Quick Reference Tutorial 2007 Using Multiple Views Click the Window menu and click Split. Now you can choose whatever view you want for each half of the window. Creating a Visual Report 1. Click the Reports menu. 2. Click Visual Reports. 3. Choose a category. 4. Click a report. 5. Click Edit Template. Using AutoFilter You will find this command on the Standard toolbar. It adds a drop-down menu to the top of each column. You can then click the menu and click an option. Then, only the rows that match this value will be shown. Task Link Types Finish to Start (FS) Finish to Finish (FF) Start to Start (SS) Start to Finish (SF) When the predecessor task finishes, the successor task will start. When the predecessor task finishes, the successor task will finish. When the predecessor task starts, the successor task will start. When the predecessor task starts, the successor task will finish. Scheduling Overtime 1. Switch to Gantt Chart view. 2. Click the Window menu. 3. Click Split. 4. Right-click the task form. 5. Click Resource. 6. Select the task. 7. Enter the overtime work. Using Lag Time and Lead Time Lag time and lead time allow you to delay or overlap linked tasks.. Note that although scheduling overtime will decrease the duration of the task, it will increase the cost as more work is required Velsoft Courseware Inc. All rights reserved. Velsoft Quick Reference Tutorial
6 Using Templates 1. Click the File menu and click New. 2. In the New task pane, click On Computer. 3. Choose your template. Using Change Highlighting This is a new feature in When you make a change to a task, other tasks that change as a result will be highlighted in blue. You can enable or disable this feature from the View menu. To enable the preview option, open the template and check Save template preview in File Properties. Contour Indicators Task Indicators Flat This is the default contour. is spread out evenly over the task duration. No indicator This task has a note attached to it. Back Loaded peaks at the end of the task duration. This task has a hyperlink attached to it. Front Loaded peaks at the beginning of the task duration. has estimated that this task will finish later than its deadline date. Double Peak peaks twice during the task. This task has an inflexible constraint. Early Peak peaks early in the task. This task has a flexible constraint. Late Peak peaks late in the task. This task has not been completed in the constraint time frame. Bell ramps up, goes to full-time, and then ramps down. Indicates a recurring task. Turtle ramps down slightly at the beginning and end of the task. Indicates a completed task. This task is an inserted project. The Equation s scheduling tools revolve around this equation: Task = Total / Resource Units If you modify a task s duration, will ask you if it is because the total work or the resource units have changed. Likewise, if you assign more or less resources, the task duration and total work will change accordingly. Remember that now features Change Highlighting, which makes it easy to see how a particular change affects other tasks. Using Task Drivers Task drivers are a new feature in To see what is driving a task, select a task, click the menu, and click Task Drivers. You will then see the Task Drivers task pane. This pane will list the factors that are affecting the start date of the selected task, including predecessor tasks and the task calendar Velsoft Courseware Inc. All rights reserved. Velsoft Quick Reference Tutorial.
7 Microsoft Quick Reference Tutorial 2007 Recording a Macro Useful Visual Basic Code Snippets 1. Plan out your macro. Know what you want to do and practice the commands so you will not make mistakes when you are recording. 2. Use the Tools Macro Record New Macro option or the Record button on the Visual Basic toolbar to display the Record Macro dialogue. 3. Set up your macro name, absolute or relative references, and other options in the dialogue. Click the OK button to start recording. 4. Perform the sequence of actions or commands that you want to record as a macro. 5. Stop the recording by using the menu options or the Stop button on the Visual Basic toolbar. Declare a variable Create an alert box Add an OK button to an alert box Basic If Then statement Comments Begin the macro code End the macro code Call another macro Dim variable name As variable type MsgBox Your text here vbokonly If condition evaluates to true Then statement your text here REM your text here Sub End sub Call MacroName Using the PERT Analysis Toolbar Shows the best possible outcome for your project. Shows the expected outcome for your project. Shows the worst possible outcome for your project. Recalculates the duration based on PERT fields. Enter PERT values for the current task. Enter PERT weights for the current task. Switch to PERT Entry Sheet view. About Macro Security PERT Scenario Types Low Medium Can run any macros. Prompted to run a macro. Medium-High Macros must be signed by trusted publisher or in a trusted location to run. High Only allowed to run macros that are stored in a trusted location. By default, the trusted location for 2007 is the Global template file (Global.mpt). Optimistic Expected Pessimistic This scenario will reveal the best possible outcome for your project. This scenario will reveal the most probable outcome of your project. This is a worst case scenario, which will reveal the worst possible outcome for your project Velsoft Courseware Inc. All rights reserved. Velsoft Quick Reference Tutorials
8 Earned Value Analysis Fields Abbreviation What it stands for What it shows Formula BCWS Budgeted Cost of Scheduled What should be spent on a task up to the status date. BCWP Budgeted Cost of Performed The cost of work completed on the task, according to the original budget. ACWP Budgeted Cost of Performed The sum of all costs for work performed on a task to date. N/A N/A N/A CV Cost Variance The difference between how much was budgeted for the task s work and how much the task actually cost. SV Schedule Variance The difference between how much was budgeted for the task s work and how much the task actually cost. ACWP - BCWP CV BCWP -BCWS SV CPI Cost Performance Index Ratio of budgeted cost to actual cost. BCWP ACWP EAC Estimate at Completion (also known as Forecast at Completion) s estimate of how much the task will cost when it is done. BAC Budgeted at Completion The budgeted amount that the task will cost when it is done. VAC Variance at completion Difference between actual and baseline costs at completion (BAC-EAC). SPI Schedule Performance Index Ratio of budgeted schedule to actual schedule. More than one means you re ahead of schedule; less than 1 means you re behind schedule. CV% Cost Variance Percent The difference between budgeted task cost and actual cost to date. SV% Schedule Variance Percent Percentage that you are ahead of, or behind, schedule. ACWP+(BAC-BCWP) CPI Derived from Baseline Cost field BAC - EAC VAC BCWP BCWS [(BCWP-ACWP)/BCWP] x 100 [SV/BCWM] x 100 TCPI To Complete Performance Index Ratio of work to be completed to money still budgeted. PPC Physical Percent Complete A value you can enter that will override % Complete. (BAC-BCWP) (BAC-ACWP) N/A Importing Outlook Tasks 1. Click the Tools menu. 2. Click Import Outlook Tasks. 3. Check tasks that you want to import. 4. Click OK. 5. with tasks as normal. Creating a Custom Form 1. Click the Forms button on the Custom Forms toolbar.. 2. In the Customize Forms dialogue, click New. 3. Name your form. Click OK. 4. Click the Edit menu and click Information. 5. Specify the size and position of your form. 6. Use the Item menu to add controls. 7. Save your form and exit the Custom Form Editor. 8. Use your form via the Customize Forms dialogue Velsoft Courseware Inc. All rights reserved. Velsoft Quick Reference Tutorials.
OVERVIEW. Microsoft Project terms and definitions
PROJECT 2003 DISCLAIMER: This reference guide is meant for experienced Microsoft Project users. It provides a list of quick tips and shortcuts for familiar features. This guide does NOT replace training
More informationINTRODUCTION TO MICROSOFT PROJECT 2007 CONTENTS
INTRODUCTION TO MICROSOFT PROJECT 2007 CONTENTS What is a Project... 2 The Steps involved in Setting up a Project... 3 Views... 4 How To Start a new project... 6 The Gantt Chart... 8 Outlining/Summary
More informationProject Creation and Gantt Chart Design Using Microsoft Project. R. Baker. The University of Tampa
Project Creation and Gantt Chart Design Using Microsoft Project R. Baker The University of Tampa What is Microsoft Project? Microsoft Project is a software package designed help managers manage a variety
More informationELECTRO-MECHANICAL PROJECT MANAGEMENT
CHAPTER-9 ELECTRO-MECHANICAL PROJECT MANAGEMENT Y K Sharma,SDE(BS-E), 9412739241(M) E-Mail ID: yogeshsharma@bsnl.co.in Page: 1 Electro-mechanical Project Management using MS Project Introduction: When
More informationIntroduction to Microsoft Project 2010
Introduction to Microsoft Project 2010 This document provides an introduction in using Microsoft Project 2010. Microsoft Project is a project management application that contains a set of tools to help
More informationPlanning and Scheduling Your Project Using Microsoft Project 2003
Planning and Scheduling Your Project Using Microsoft Project 2003 Sridhar Pandurangiah Director - Engineering sridhar@sastratechnologies.in Meeting Protocol Agenda Project File Project Calendar Creating
More informationMicrosoft Project 2007 Level 2: Working with Resources and Managing a Project
Microsoft Project 2007 Level 2: Working with Resources and Managing a Project By Robin Peers Robin Peers, 2008 ABOUT THIS CLASS In Microsoft Project 2007 Level 1: Creating Project Tasks, the focus was
More informationI N FO RM A T I O N T EC H N O L O G Y S ERV I C ES M I C ROSOFT PROJ EC T 2 0 1 0 T A S K M A N A GEM EN T LEARNING GUIDE
I N FO RM A T I O N T EC H N O L O G Y S ERV I C ES M I C ROSOFT PROJ EC T 2 0 1 0 T A S K M A N A GEM EN T LEARNING GUIDE Workshop Information Information Technology Services is happy to provide you with
More informationMicrosoft Project 2007 Level 1: Creating Project Tasks
Microsoft Project 2007 Level 1: Creating Project Tasks By Robin Peers Robin Peers, 2008 ABOUT THIS CLASS Regardless of job title, most of us have needed to act as a project manager, at one time or another.
More informationIT Training. Microsoft Project. Vicky Samways, IT Training Information System Services Version 2.1
IT Training Microsoft Project Vicky Samways, IT Training Information System Services Version 2.1 Scope Learning outcomes Find out when and how to use Microsoft Project. Learn how to create a project, break
More informationComputer Training Centre University College Cork
Computer Training Centre University College Cork Project 2013 Table of Contents What's new in Project 2013... 1 Manual scheduling... 1 Graphical Reports... 1 Trace task paths... 1 Easier view customization...
More informationBeginning Microsoft Project
Beginning Microsoft Project BEGINNING MICROSOFT PROJECT...1 WHAT IS PROJECT? WHAT IS IT USED FOR?...1 PROJECT WINDOWS... 1 Views and Tables...1 PHASE 1: PLANNING AND SETTING UP PROJECT...2 PLANNING AND
More informationMicrosoft Project 2010 Advanced
Microsoft Project 2010 Advanced Table Of Contents SECTION 1 - REFRESH OF THE BASICS... 3 GUIDE INFORMATION... 4 Introduction... 4 How To Use This Guide... 4 Objectives... 4 Instructions... 4 PROJECT INFORMATION
More informationLesson 6 - Managing Resources in a Project Plan
Lesson 6 - Managing Resources in a Project Plan Lesson Objectives In this lesson, you will manage resources in a project plan. You will: Create a resource calendar. Assign resources to tasks. Assign additional
More informationMicrosoft Project 2013
CALIFORNIA STATE UNIVERSITY, LOS ANGELES INFORMATION TECHNOLOGY SERVICES Microsoft Project 2013 Summer 2014, Version 1.0 Table of Contents Introduction...2 Overview of the User Interface...2 Creating a
More informationAdministration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by
Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by Paul E Harris Administration Evacuation Timings, meals and facilities Mobile phones
More informationMS Project Tutorial for Senior Design Using Microsoft Project to manage projects
MS Project Tutorial for Senior Design Using Microsoft Project to manage projects Overview: Project management is an important part of the senior design process. For the most part, teams manage projects
More informationMS Project 2000 Tutorial: Introduction
MS Project 2000 Tutorial: Introduction - Anjana Srikanth Stylus Systems is a Internet Technology company located in Bangalore India. One of our mottos is "a quality process creates a quality product."
More informationECDL. European Computer Driving Licence. Project Planning Project Management Software BCS ITQ Level 2. Syllabus Version 1.0
ECDL European Computer Driving Licence Project Planning Project Management Software BCS ITQ Level 2 Using Microsoft Project 2013 Syllabus Version 1.0 This training, which has been approved by BCS, The
More informationMicrosoft Project 2013 Guide to Task and Resource Planning
Starting a Project The Microsoft Project 2013 Start screen Double click Blank Project, select a Recent project, or click Open Other Projects to work on a saved project stored on disk or on SkyDrive. To
More informationMigrating to Excel 2010 from Excel 2003 - Excel - Microsoft Office 1 of 1
Migrating to Excel 2010 - Excel - Microsoft Office 1 of 1 In This Guide Microsoft Excel 2010 looks very different, so we created this guide to help you minimize the learning curve. Read on to learn key
More informationMicrosoft Migrating to Word 2010 from Word 2003
In This Guide Microsoft Word 2010 looks very different, so we created this guide to help you minimize the learning curve. Read on to learn key parts of the new interface, discover free Word 2010 training,
More informationCreate task relationships by linking tasks. Switch task scheduling from manual to automatic. Set nonworking days for the project plan.
2 In this chapter, you will learn how to: Start Microsoft Project Standard or Professional and save a new project plan. Enter task names. Estimate and record how long each task should last. Create a milestone
More informationApplied Project Management ( APM )
Applied Project Management Applied Project Management ( APM ) TRAINING PROGRAM Page 1 Of 7 APPLIED PROJECT MANAGEMENT PRO PROGRAM OVERVIEW This course provides in-depth Project Management Training and
More informationUSER CONVERSION P3, SURETRAK AND MICROSOFT PROJECT ASTA POWERPROJECT PAUL E HARRIS EASTWOOD HARRIS
P.O. Box 4032 EASTWOOD HARRIS PTY LTD Tel 61 (0)4 1118 7701 Doncaster Heights ACN 085 065 872 Fax 61 (0)3 9846 7700 Victoria 3109 Project Management Systems Email: harrispe@eh.com.au Australia Software
More informationUsing Microsoft Project 2000
Using MS Project Personal Computer Fundamentals 1 of 45 Using Microsoft Project 2000 General Conventions All text highlighted in bold refers to menu selections. Examples would be File and Analysis. ALL
More informationProject Management Dashboard Pro v5 Documentation
Project Management Dashboard Pro v5 Documentation Installation There is NO installation required. It s just a macro enabled excel file that opens if you have Excel 2007, 2010, 2013 and 2016 on your Windows
More informationProject 2010 Introduction
Microsoft Application Series Project 2010 Introduction Best STL Courses never cancelled: guaranteed Last minute rescheduling 24 months access to Microsoft trainers 12+ months schedule UK wide delivery
More informationProduced by Flinders University Centre for Educational ICT. PivotTables Excel 2010
Produced by Flinders University Centre for Educational ICT PivotTables Excel 2010 CONTENTS Layout... 1 The Ribbon Bar... 2 Minimising the Ribbon Bar... 2 The File Tab... 3 What the Commands and Buttons
More informationEXCEL 2007. Using Excel for Data Query & Management. Information Technology. MS Office Excel 2007 Users Guide. IT Training & Development
Information Technology MS Office Excel 2007 Users Guide EXCEL 2007 Using Excel for Data Query & Management IT Training & Development (818) 677-1700 Training@csun.edu http://www.csun.edu/training TABLE
More informationCreating and Viewing Task Dependencies between Multiple Projects using Microsoft Project
Creating and Viewing Task Dependencies between Multiple Projects using Microsoft Project Preliminary 1. You must have Microsoft Project 2003 or higher installed to complete these procedures. 2. If necessary,
More informationtechnical tips and tricks
technical tips and tricks Applying Earned Value Analysis Document author: Produced by: Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the smart
More informationABOUT THIS COURSE...3 ABOUT THIS MANUAL...4 EXCHANGING PROJECT PLAN DATA WITH OTHER APPLICATIONS...5
Table of Contents ABOUT THIS COURSE...3 ABOUT THIS MANUAL...4 EXCHANGING PROJECT PLAN DATA WITH OTHER APPLICATIONS...5 IMPORT A TASK LIST FROM AN EXCEL FILE INTO A NEW PROJECT PLAN... 6 Import a Task List
More informationMicrosoft Access 2010 handout
Microsoft Access 2010 handout Access 2010 is a relational database program you can use to create and manage large quantities of data. You can use Access to manage anything from a home inventory to a giant
More informationPlanning and Managing Projects with Microsoft Project Professional 2013
Slides Steps to Enter Duration: 1. In the Duration column of a task, enter a value, and press Enter on your keyboard Important Points: The default time unit is days, so when you enter 5, this becomes 5
More informationAbout the Tutorial. Audience. Prerequisites. Disclaimer & Copyright. MS Project 2013
About the Tutorial MS Project, the project management software program by Microsoft, is a very handy tool for project managers that helps them develop a schedule, assign resources to tasks, track the progress,
More informationPlanning and Managing Projects with Microsoft Project Professional 2013
Slides Slides Slides Steps to Enter Resource Types: 1. Click View and Resource Sheet 2. In the Type column of a resource, select Work, Material, or Cost, and press Enter on your keyboard Important
More informationProject Management: Tracking Progress and Earned Value with MS Project 2003
Project Management: Tracking Progress and Earned Value with MS Project 2003 Project Planning Suppose you have been assigned a project to construct a website in a certain time frame and given a certain
More informationTask Force on Technology / EXCEL
Task Force on Technology EXCEL Basic terminology Spreadsheet A spreadsheet is an electronic document that stores various types of data. There are vertical columns and horizontal rows. A cell is where the
More informationIn this session, we will explain some of the basics of word processing. 1. Start Microsoft Word 11. Edit the Document cut & move
WORD PROCESSING In this session, we will explain some of the basics of word processing. The following are the outlines: 1. Start Microsoft Word 11. Edit the Document cut & move 2. Describe the Word Screen
More informationIntroduction to Microsoft Access XP
Introduction to Microsoft Access XP Access is the database management system in Microsoft Office. A database is an organized collection of facts about a particular subject. An address book or a library
More informationOutlook Email. User Guide IS TRAINING CENTER. 833 Chestnut St, Suite 600. Philadelphia, PA 19107 215-503-7500
Outlook Email User Guide IS TRAINING CENTER 833 Chestnut St, Suite 600 Philadelphia, PA 19107 215-503-7500 This page intentionally left blank. TABLE OF CONTENTS Getting Started... 3 Opening Outlook...
More informationUsing Microsoft Office to Manage Projects
(or, Why You Don t Need MS Project) Using Microsoft Office to Manage Projects will explain how to use two applications in the Microsoft Office suite to document your project plan and assign and track tasks.
More informationMicrosoft Project From the WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org
Planning and Managing Software Projects 2010-11 Session 6 Microsoft Project From the WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Credits 2 These
More informationTopics. Project plan development. The theme. Planning documents. Sections in a typical project plan. Maciaszek, Liong - PSE Chapter 4
MACIASZEK, L.A. and LIONG, B.L. (2005): Practical Software Engineering. A Case Study Approach Addison Wesley, Harlow England, 864p. ISBN: 0 321 20465 4 Chapter 4 Software Project Planning and Tracking
More informationMS WORD 2007 (PC) Macros and Track Changes Please note the latest Macintosh version of MS Word does not have Macros.
MS WORD 2007 (PC) Macros and Track Changes Please note the latest Macintosh version of MS Word does not have Macros. Record a macro 1. On the Developer tab, in the Code group, click Record Macro. 2. In
More informationMicrosoft Excel Basics
COMMUNITY TECHNICAL SUPPORT Microsoft Excel Basics Introduction to Excel Click on the program icon in Launcher or the Microsoft Office Shortcut Bar. A worksheet is a grid, made up of columns, which are
More informationEXCEL FINANCIAL USES
EXCEL FINANCIAL USES Table of Contents Page LESSON 1: FINANCIAL DOCUMENTS...1 Worksheet Design...1 Selecting a Template...2 Adding Data to a Template...3 Modifying Templates...3 Saving a New Workbook as
More informationGOOGLE DOCS APPLICATION WORK WITH GOOGLE DOCUMENTS
GOOGLE DOCS APPLICATION WORK WITH GOOGLE DOCUMENTS Last Edited: 2012-07-09 1 Navigate the document interface... 4 Create and Name a new document... 5 Create a new Google document... 5 Name Google documents...
More informationNAVIGATION TIPS. Special Tabs
rp`=j~êëü~ää=påüççä=çñ=_ìëáåéëë Academic Information Services Excel 2007 Cheat Sheet Find Excel 2003 Commands in Excel 2007 Use this handout to find where Excel 2003 commands are located in Excel 2007.
More informationGantt View Quick Start Guide
Gantt View Quick Start Guide This document is intended to give you an overview of the MindGenius 4 Gantt view and its features. Topics covered in this document: Gantt Mode The Gantt View Switching Between
More informationProject 2010. Quick Reference. The Assignment Equation. EPM Architects www.epmarchitects.com
The Assignment Equation The following equation controls the relationship between the Work, Duration, and Assignment Units for a task assignment: Or Or Work: The number of hours of real work effort spent
More informationIntellect Platform - The Workflow Engine Basic HelpDesk Troubleticket System - A102
Intellect Platform - The Workflow Engine Basic HelpDesk Troubleticket System - A102 Interneer, Inc. Updated on 2/22/2012 Created by Erika Keresztyen Fahey 2 Workflow - A102 - Basic HelpDesk Ticketing System
More informationTasks can be added manually by typing them into the list Manually adding tasks put the project manager in control and is a good way to start
Project Management is the discipline of planning, organizing, and managing resources to complete a specific goal. Microsoft Project is software that helps you. Start your project Open Project 2010 and
More informationImplementing Mission Control in Microsoft Outlook 2010
Implementing Mission Control in Microsoft Outlook 2010 How to Setup the Calendar of Occasions, Not Doing Now List, Never Doing Now List, Agendas and the Vivid Display In Outlook 2010 Handout Version 3
More informationInternet Explorer 7. Getting Started The Internet Explorer Window. Tabs NEW! Working with the Tab Row. Microsoft QUICK Source
Microsoft QUICK Source Internet Explorer 7 Getting Started The Internet Explorer Window u v w x y { Using the Command Bar The Command Bar contains shortcut buttons for Internet Explorer tools. To expand
More informationHow To Use Ms Powerbook 2.5.2.2 On A Pc Or Mac Or Macbook 2 (Windows)
Overview 1 Content Overview Open a project file Create a new project plan Track progress View and print reports Share a project plan Conclusion 2 Overview With you can: create new/update project plan open
More informationProject Management: Intermediate Microsoft Project 2010
Project Management: Intermediate Microsoft Project 2010 This document includes instructions for managing resources, updating project plans, and designing visual reports. Managing Resources in a Project
More informationMicrosoft Office 2010: Introductory Q&As PowerPoint Chapter 1
Microsoft Office 2010: Introductory Q&As PowerPoint Chapter 1 Are the themes displayed in a specific order? (PPT 6) Yes. They are arranged in alphabetical order running from left to right. If you point
More informationOhio University Computer Services Center August, 2002 Crystal Reports Introduction Quick Reference Guide
Open Crystal Reports From the Windows Start menu choose Programs and then Crystal Reports. Creating a Blank Report Ohio University Computer Services Center August, 2002 Crystal Reports Introduction Quick
More informationRevealing the Secrets of Microsoft Project
2 Revealing the Secrets of Microsoft Project To know that one has a secret is to know half the secret itself. Henry Ward Beecher Topics Covered in This Chapter Recognizing the Underlying Rules of Project
More informationExcel Reports and Macros
Excel Reports and Macros Within Microsoft Excel it is possible to create a macro. This is a set of commands that Excel follows to automatically make certain changes to data in a spreadsheet. By adding
More informationtechnical tips and tricks
technical tips and tricks Document author: Produced by: Displaying a Critical Path Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the smart
More informationECDL. European Computer Driving Licence. Spreadsheet Software BCS ITQ Level 2. Syllabus Version 5.0
European Computer Driving Licence Spreadsheet Software BCS ITQ Level 2 Using Microsoft Excel 2010 Syllabus Version 5.0 This training, which has been approved by BCS, The Chartered Institute for IT, includes
More informationWORDPAD TUTORIAL WINDOWS 7
WORDPAD TUTORIAL WINDOWS 7 Quick Access bar Home Tab Triangles = More Commands Groups on the Home tab Right paragraph margin Left paragraph Margin & Indent Paragraphs Ruler Hover the mouse pointer over
More informationMicrosoft Migrating to Access 2010 from Access 2003
In This Guide Microsoft Access 2010 looks very different, so we created this guide to help you minimize the learning curve. Read on to learn key parts of the new interface, discover free Access 2010 training,
More informationMS Project Tips and Tricks
MS Project Tips and Tricks ELLEN LEHNERT, MVP, PMP, MCT, MCITP CONSULTANT/INSTRUCTOR LEHNERTCS, LLC WWW.LEHNERTCS.COM ELLEN@LEHNERTCS.COM Ellen Lehnert, MVP, PMP, MCT, MCITP Background in teaching, Business
More informationMicrosoft Access 2010 Part 1: Introduction to Access
CALIFORNIA STATE UNIVERSITY, LOS ANGELES INFORMATION TECHNOLOGY SERVICES Microsoft Access 2010 Part 1: Introduction to Access Fall 2014, Version 1.2 Table of Contents Introduction...3 Starting Access...3
More informationCreating a New Project
Creating a New Project Microsoft Project is a project management software program designed to assist project managers in developing plans, assigning resources to tasks, tracking progress, managing budgets,
More informationGetting Started with Excel 2008. Table of Contents
Table of Contents Elements of An Excel Document... 2 Resizing and Hiding Columns and Rows... 3 Using Panes to Create Spreadsheet Headers... 3 Using the AutoFill Command... 4 Using AutoFill for Sequences...
More informationProject Management within ManagePro
Project Management within ManagePro This document describes how to do the following common project management functions with ManagePro: set-up projects, define scope/requirements, assign resources, estimate
More informationMicrosoft Migrating to PowerPoint 2010 from PowerPoint 2003
In This Guide Microsoft PowerPoint 2010 looks very different, so we created this guide to help you minimize the learning curve. Read on to learn key parts of the new interface, discover free PowerPoint
More informationAdobe Conversion Settings in Word. Section 508: Why comply?
It s the right thing to do: Adobe Conversion Settings in Word Section 508: Why comply? 11,400,000 people have visual conditions not correctible by glasses. 6,400,000 new cases of eye disease occur each
More informationMicrosoft Outlook 2010
Microsoft Outlook 2010 Prepared by Computing Services at the Eastman School of Music July 2010 Contents Microsoft Office Interface... 4 File Ribbon Tab... 5 Microsoft Office Quick Access Toolbar... 6 Appearance
More informationPrimavera P6 102 Training Manual. Prepared by. Bill Pepoon, Managing Partner Construction Science, LLC
Primavera P6 102 Training Manual Prepared by Bill Pepoon, Managing Partner Construction Science, LLC 1 Day I Introduction Setting up a new Project Activities Activity Types Activity Durations Work Breakdown
More informationadded to the task, using Project, it will automatically calculate the schedule each time a new resource is added.
Chapter 3 Effort Driven Task Type By now, you will be getting sick of my repetition of the effort driven formula: Resource Units X Duration = Work I make no apologies, as it needs to be engraved in the
More informationCreating and Using Forms in SharePoint
Creating and Using Forms in SharePoint Getting started with custom lists... 1 Creating a custom list... 1 Creating a user-friendly list name... 1 Other options for creating custom lists... 2 Building a
More informationProject 2013: An introduction
Project 2013: An introduction TPAF Revision Information Version Date Author Changes made 1.0 February 2013 Jean Glendinning Created 2.0 November 2013 Jean Glendinning Amended elements 3.0 Feb 2014 Jean
More informationWorking with sections in Word
Working with sections in Word Have you have ever wanted to create a Microsoft Word document with some pages numbered in Roman numerals and the rest in Arabic, or include a landscape page to accommodate
More informationOutlook Tips & Tricks. Training For Current & New Employees
Outlook Tips & Tricks Training For Current & New Employees The workshop will help build the necessary skills needed to begin using Microsoft Outlook 2010. The participant will learn how to create e-mail
More informationExcel macros made easy
IT Training Excel macros made easy Jane Barrett, IT Training & Engagement Team Information System Services Version 1.1 Scope Learning outcomes Understand the concept of what a macro is and what it does.
More informationOutlook Web App McKinney ISD 5/27/2011
Outlook Web App McKinney ISD 5/27/2011 Outlook Web App Tutorial Outlook Web Access allows you to gain access to your messages, calendars, contacts, tasks and public folders from any computer with internet
More informationMICROSOFT OFFICE ACCESS 2007 - NEW FEATURES
MICROSOFT OFFICE 2007 MICROSOFT OFFICE ACCESS 2007 - NEW FEATURES Exploring Access Creating and Working with Tables Finding and Filtering Data Working with Queries and Recordsets Working with Forms Working
More informationMicrosoft Excel 2007. Introduction to Microsoft Excel 2007
Microsoft Excel 2007 Introduction to Microsoft Excel 2007 Excel is an electronic spreadsheet to organize your data into rows and columns. One can use it to perform basic to advanced level mathematical
More informationExcel Pivot Tables. Blue Pecan Computer Training Ltd - Onsite Training Provider www.bluepecantraining.com :: 0800 6124105 :: info@bluepecan.co.
Excel Pivot Tables 1 Table of Contents Pivot Tables... 3 Preparing Data for a Pivot Table... 3 Creating a Dynamic Range for a Pivot Table... 3 Creating a Pivot Table... 4 Removing a Field... 5 Change the
More informationProject Management Courses
"A well planned project will give results exactly as planned." Project Management Courses Professional Development Training has a specialised division of Project Management experts that will tailor the
More informationO UTLOOK 2003 HELP SHEET MAIL. Opening the program. Mail
O UTLOOK 2003 HELP SHEET MAIL Opening the program At Work Double-click the icon on your desktop. Or click the Start button. If this icon is displayed, click on it. If it is not displayed, click Start,
More informationMS Project 2007 Quick Guide
MS Project 2007 Quick Guide 1. Setup your project Add project information Determine project start date Check / Edit the standard/base calendar Check / Edit calendar calculation options Fine-tune your configuration
More informationMicrosoft Outlook 2007 Calendar Features
Microsoft Outlook 2007 Calendar Features Participant Guide HR Training and Development For technical assistance, please call 257-1300 Copyright 2007 Microsoft Outlook 2007 Calendar Objectives After completing
More informationUsing MS Project in Translation Projects Management
Using MS Project in Translation Projects Management When building a translation project plan, there must be taken into account: the tasks involved by the project, duration of each task, task dependencies,
More informationMicrosoft Office Access 2007 Basics
Access(ing) A Database Project PRESENTED BY THE TECHNOLOGY TRAINERS OF THE MONROE COUNTY LIBRARY SYSTEM EMAIL: TRAININGLAB@MONROE.LIB.MI.US MONROE COUNTY LIBRARY SYSTEM 734-241-5770 1 840 SOUTH ROESSLER
More informationMicrosoft Outlook 2003 Quick How-to Guide
Microsoft Outlook 2003 Quick How-to Guide Microsoft Outlook 2003 Quick How-to-Guide This document is designed to be a quick guide for the most common tasks in Outlook. It is separated into different sections
More informationQUICK START GUIDE RESOURCE MANAGERS. Last Updated: 04/27/2012
QUICK START GUIDE RESOURCE MANAGERS Last Updated: 04/27/2012 Table of Contents Introduction... 3 Getting started... 4 Logging into Eclipse... 4 Setting your user preferences... 5 Online help and the Eclipse
More informationMicrosoft Project 2007 Tutorial Boston University. Boston University, Dept of Administrative Sciences, Project Management Programs (2010)
Microsoft Project 2007 Tutorial Boston University Boston University, Dept of Administrative Sciences, Project Management Programs (2010) 1 2 Microsoft Project 2007 Tutorial Boston University Contents Table
More information1. Introduction. P2O is automatically loaded when you open Ms Project (2010 or 2013). The add-in can be found under the M5 Tools menu. 2.
1. Introduction Project 2 Outlook (P2O) will help Microsoft Project users to improve project communication by exporting MS Project tasks and information to MS Outlook Task or Appointments. Users don t
More informationAppendix A How to create a data-sharing lab
Appendix A How to create a data-sharing lab Creating a lab involves completing five major steps: creating lists, then graphs, then the page for lab instructions, then adding forms to the lab instructions,
More informationExcel 2007 Basic knowledge
Ribbon menu The Ribbon menu system with tabs for various Excel commands. This Ribbon system replaces the traditional menus used with Excel 2003. Above the Ribbon in the upper-left corner is the Microsoft
More informationMicrosoft Excel 2013 Tutorial
Microsoft Excel 2013 Tutorial TABLE OF CONTENTS 1. Getting Started Pg. 3 2. Creating A New Document Pg. 3 3. Saving Your Document Pg. 4 4. Toolbars Pg. 4 5. Formatting Pg. 6 Working With Cells Pg. 6 Changing
More informationMicrosoft PowerPoint 2010 Handout
Microsoft PowerPoint 2010 Handout PowerPoint is a presentation software program that is part of the Microsoft Office package. This program helps you to enhance your oral presentation and keep the audience
More informationHandout: Word 2010 Tips and Shortcuts
Word 2010: Tips and Shortcuts Table of Contents EXPORT A CUSTOMIZED QUICK ACCESS TOOLBAR... 2 IMPORT A CUSTOMIZED QUICK ACCESS TOOLBAR... 2 USE THE FORMAT PAINTER... 3 REPEAT THE LAST ACTION... 3 SHOW
More information