Portway Extensions Concept Development Study APPENDIX F PRELIMINARY CONSTRUCTION COST ESTIMATES

Size: px
Start display at page:

Download "Portway Extensions Concept Development Study APPENDIX F PRELIMINARY CONSTRUCTION COST ESTIMATES"

Transcription

1 Portway Extensions Concept Development Study Final Report APPENDIX F PRELIMINARY CONSTRUCTION COST ESTIMATES

2 Portway Extensions Concept Development Study Final Report In advance of an economic impact analysis to be conducted as part of the next stage of the Portway Extensions program, preliminary construction cost estimates were prepared for the roadway infrastructure improvement concepts presented in Section X of this report. The cost estimates follow the NJDOT preliminary estimation procedures. Following is a summary table of the infrastructure improvement costs (exclusive of any required right-of-way acquisition or extensive environmental remediation that may be required). Also presented are the computation sheets detailing the construction items, estimated quantities and unit costs for each recommended alternative concept.

3 Table F-1 Portway Extensions Concept Development Study Recommended Infrastructure Improvements Preliminary Construction Cost Estimates Figure Cost Number Alternative Concept Description Estimate X.3 Northern Extensions $ 65,, X.4 NJ Turnpike Interchange 15-W Area $ 19,, X.5 Hackensack River Bridge 161,, X.6 NJ Turnpike Interchange 14-A Scheme 1 65,, X.7 NJ Turnpike Interchange 14-A Scheme 2 11,, X.8 NJ Turnpike Interchange 14 5,, X.9 Interim Newark Bay Bridge Improvement 186,, X.1 Bayonne Bridge 4,, X.11 Routes 1&9 Northbound at Delancy Street 8,, X.12 NJ Turnpike Interchange 13-A - Kapkowski Road Area 48,, X.13 NJ Turnpike Interchange 13 4,, X.14 NJ Turnpike Interchange 12 Area 7,, X.15 NJ Turnpike Interchange 1 Area 11,, Total (w/14-a Scheme 1) $ 79,, Total (w/14-a Scheme 2) $ 754,, Summary Page 1

4 Classification Number 1 - NEW CONSTRUCTION - English Route PORTWAY EXTENSIONS Section/Contract # NORTHERN EXTENSIONS PM UPC No. EARTHWORK (must be calculated) Unit Quantity x Unit Price Amount Stripping (4-6" Depth) Acre 26 4,5 15,3 Roadway Exc. Unclassified, See (J) C.Y. 15 Removal of Conc. Base & Conc. Surface Courses, See (K) S.Y. Channel Excavation C.Y Ditch Excavation C.Y. 1 Borrow Excavation Zone 3, See (J) C.Y. 14, ,259,376 EARTHWORK TOTAL = $1,364,676 Suggested procedure for calculating earthwork: A) Determine Typical section (number of lanes, median widths, side slopes, etc.). B) Get latest topography map available. C) Plot proposed alignment on topo map. D) Develop profile using topo controls such as existing roads, streams, rivers and design manual. E) Calculate Areas for the typical section in 1 foot increments of cut or fill. F) At 1 to 6 foot intervals (depending on frequency of X-section changes) calculate the earthwork. G) Calculate any other significant earthwork (ramps, cross-roads, etc.). H) Make appropriate earthwork corrections for the pavement box and striping. Use 21 inch depth for rigid pavement, 26 inch depth for all flexible pavement and 4 inch depth for stripping. I) Deduct any roadway excavation from borrow required to calculate Borrow Excavation Zone 3. J) See Construction Cost Estimate Work Sheet (Section 3.1). This worksheet must be utilized for the most recent price information. K) 11.2 to 12.5, based on the quantity, location and type of project. PAVEMENT 12 FOOT WIDE LANE (from subgrade up) Pav't. Type Description of Pavement Cost/Linear A 1 inch R.C. Pavement 156 B 2 inch HMA Surf. Crs. & 8 inch HMA Base 61 C 3 inch HMA Surf. Crs. & 4 inch HMA Base 46 D 2 inch HMA Surf. Crs. & 2 inch HMA Base 22 E Bridge Approach & Transition Slabs 156 Computation Table for Pavement. Cost Type Cost from table above x Length x Pavement *W.F. = Amount B 61 56, ,19,543 E ,416 PAVEMENT TOTAL = $7,71,959 *Width Factors = Ratio of 12 foot wide lane to actual pavement width. Example = actual pavement width = 25 foot = 25/12 = 2.8 W.F. Northern Extensions Page 2

5 CONTEXT SENSITIVE DESIGN Attach additional sheet detailing items and costs of context sensitive design work = CULVERTS ///////////////////////////////////////////////// ///////////////////////////////////////////////////////// COVER < W > Type 1 W< 2 Feet < W > Type 2 W> 2 feet Type Layout (3) Skew (1) Cover (2) Cost Per Sq. Area w x L exceeds -6 to 1' Sq. Feet degrees 1' to 2' Type 1 Short Culverts Difficult -6 to 1' 23.5 Conditions under 1 Square Feet degrees 1' to 2' 235. Area w x L exceeds -6 to 1' Sq. Feet degrees 1' to 2' Type 2 Short Culverts Difficult -6 to 1' 23.5 Conditions under 1 Square Feet degrees 1' to 2' 235. For skews over 6 degrees it will be necessary to make a special analysis and establish a square meter price comparable to above. Description Area Computation x Cost per Sq. = Amount Culvert Total = BRIDGES For the Bridge Sketch see the Construction Cost Estimation Preparation Manual 1 to 3 spans and 2 side spans (Max. Span 1 feet) H = Clear Height 14 To 23 feet (4) L = 1 to 4 feet & all viaducts over 4 feet (5) Class Layout Skew (1) Foundation (2) Cost per Sq. Width at Least to 4 No Piles I 45 feet Degrees Piles at Stub Abut Piles at Piers & Stub to 6 No Piles 145. Degrees Piles at Stub Abut Piles at Piers & Stub Northern Extensions Page 3

6 For the Bridge Sketch see the Construction Cost Estimation Preparation Manual 1 to 3 spans and 2 side spans (Max. Span 1 feet) (3) H = Clear Height 14 feet (4) L = under 4 feet Class Layout Skew (1) Foundation (2) Cost per Sq. L exceeds W to 4 No Piles II Area L x W Degrees On Piles exceeds 45 4 to 6 No Piles Sq. Feet Degrees On Piles W exceeds L to 4 No Piles III Area L x W Degrees On Piles exceeds 45 4 to 6 No Piles Sq. Feet Degrees On Piles 31. Width 3 - to 4 No Piles IV 45 feet Degrees On Piles Area W x L under 4 to 6 No Piles Sq. Degrees On Piles For the Bridge Sketch see the Construction Cost Estimation Preparation Manual 1 to 2 spans (Max. Span 125 feet) H = Clear Height 14 feet (4) L = 1 to 25 feet Layout Skew (1) Foundation (2) Cost/ Sq. Width at Least to 4 No Piles feet Degrees Piles at Semi-Stub Abut. Piles at Piers & Semi-Stub Abut to 6 No Piles Minimum Length Degrees Piles at Semi-Stub Abut feet Piles at Piers & Semi-Stub Abut $ Length Width Cost per SF Bridge Total 1. For skews over 6 degrees it will be necessary to make a special analysis and establish a square foot price comparable to above. 2. For very bad foundation conditions requiring unusual lengths or spacing of piles, it will be necessary to establish a square foot price. 3. For longer spans, adjust the cost per square foot to reflect increased cost of structural members. 4. For span bridges, it is expected the length of the side span will be in- creased in proportion to any increase in height. Because of the resultant increase in deck area, the square foot price will remain approximately the same in the range of heights shown. For extremely high structures (particularly for viaducts), square foot prices will have to be increased. 5. For structures over 4 foot long (viaducts), reduce the cost per square foot if repetitive span length and forming can be used. Reduce by $.5 for lengths from 4 to 6 feet and by $1. for lengths over 6 feet. (Do not forget adjustments (3) and (4) above on viaducts). Northern Extensions Page 4

7 6. For statically indeterminate structures, square foot prices will have to be established. Structure Description Calculated Sq. of Bridge Deck x Cost Per Square = Amount 7, ,84, 17, ,937,5 17, ,937,5 17, ,937,5 Sub Total $27,652,5 Clearing Site Bridge *-3% of Sub Total % BRIDGE TOTAL $27,652,5 *Pick appropriate percent based on the size, type and materials of existing structure DRAINAGE (includes inlets and cross drains) Rural project length (miles) x cost per mile = Amount Urban project length (miles) x cost per mile = Amount The above are the total costs of basins, manholes, longitudinal and transverse pipes, underdrains, headwalls, protecting curbs, aprons, etc. for a divided highway with a depressed median. The costs are assumed to apply to 4, 6 or 8 lane sections since there will be no appreciable difference in the number of basins or the sizes or lengths of pipes. Frontage Road & Ramp Drainage length of ramp or frontage rd. in feet 56,672 x cost per foot 55 3,116,96 = Amount DRAINAGE TOTAL = $3,116,96 INCIDENTAL ITEMS Item Cost / L.F. x Quantity = Amount Beam Guide Rail ,336 1,312,128 Fence 6 High " X 16" Conc. Vertical Curb ,344 1,558,48 15" X 41" Conc. Barrier Curb " X 41" Conc. Barrier Curb " X Variable Conc. Barrier Curb 46 Sign Bridge 38, Cantilever Sign Structure 6,5 INCIDENTAL ITEMS TOTAL = $2,87,68 Northern Extensions Page 5

8 LANDSCAPE Quantity x Unit Prices = Amount Topsoil and Seeding (Mainline) Length of Project in miles 112,815 Planting (Mainline) Length of Project in miles 64,5 Topsoil, Seeding, Planting (Finger Ramp Number of Finger Ramps 12,5 Topsoil, Seeding, Planting (Loop Ramp) Number of Loop Ramps 2, Topsoil, Seeding (Access Road) Length of Access Road in Feet 56, ,79 LANDSCAPE TOTAL = $447,79 NOISE ABATEMENT Unit Quantity x Cost = Amount Noise Wall L.F. 35 NOISE ABATEMENT TOTAL = GENERAL ITEMS Item Project Length (miles) x Cost/Mile = Amount Field Office ,26 473,582 Materials Field Laboratory ,97 39,979 Erosion Control during Constructio , ,813 GENERAL ITEMS TOTAL = $1,472,374 SUMMARY Route PORTWAY EXTENSIONS Section/Contract # NORTHERN EXTENSIONS PM UPC No. Totals from other Work Type pages Earthwork 1,364,676 Pavement 7,71,959 Context Sensitive Design Culverts Bridges 27,652,5 Drainage 3,116,96 Incidental Items 2,87,68 Landscape 447,79 Noise Abatement General Items 1,472,374 PROJECT SUBTOTAL $44,635,786 Northern Extensions Page 6

9 Other Items Proj. Subtotal Range Choice Amount Lighting, Traffic Stripes, Signs 3% of Proj. and Delineators Subtotal 1,339,74 Maintenance of Traffic 1.5% of Proj. Subtotal 669,537 Training 1% of Proj. Subtotal 446,358 Mobilization 4,463,579 9% of Proj. Project Cost < 5. (Mil.) Subtotal Project Cost 5. & above 1% of Proj. Subtotal Progress Schedule Project Cost(Mil.) $ 58, Less than to 5. 6, 5. to 1. 8, 1. to 2. 15, 2. to 3. 3, 3. to 4. 4, 4. & above 58, 58 Clearing Site Project Cost (Mil.) $ 49, Less than 1. 15, 1. to 2. 3, 2. to 5. 45, 5. to , 1. to 2. 22, 2. to 3. 24, 3. to 4. 25, 4. & above 49, 49 Construction Layout Project Cost(Mil.) $ 89, Less than 1. 7, 1. to 2. 2, 2. to 5. 42, 5. to 1. 87, 1. to 2. 16, 2. to 3. 22, 3. to 4. 49, 4. & above 89, 89 PROJECT TOTAL $52,992,332 Northern Extensions Page 7

10 CONTINGENCIES & ESCALATION Y Y = Number of Years until midpoint of construction duration plus number of years until construction start. If midpoint is less than 2 years from the date of this estimate, no escalation is required.. Maximum value = 1% $53,787,217 Project Total Contingencies (1+C) 1 + [.1 (Y+1) (Y- Construction 2)] Estimate for PD 2. Project Cost(Mil.) Contingencies (C) Percent Average Construction Duration in Years -1 3% % % 3. Over 5 1.5% 4.15 CONSTRUCTION ENGINEERING (CE) % of Construction Project Cost (Mil.) Cost Less than % 1. to % 5. to % 1. & above 9.5% CONSTRUCTION ENGINEERING AMOUNT $5,19, CONSTRUCTION CHANGE ORDER CONTINGENCIES Total Federal Participating Items in Millions of $ Construction Change Order Contingency Amount $ to.1 $6,.1 to.5 25,.5 to 5. 25, + 4% of amount in excess of $5, 5. to 1. 25, + 3% of amount in excess of $5,, 1. to , + 2% of amount in excess of $1,, 15. and above 455, + 1.5% of amount in excess of $15,, - $5, max For State Funded Projects, Contingencies for Change orders = CHANGE ORDER CONTINGENCY AMOUNT = $5, UTILITIES RELOCATIONS BY COMPANIES/OWNERS $53,787,217.9 $4,84,85 x % or + Estimate = Construction Cost for Initial Estimate Use % or utilities detailed estimate Utility Relocation Cost for Initial Estimate If there are no utility relocations on the project indicate No Utilities in the box above. RIGHT OF WAY COST If there is no ROW cost on the project indicate No ROW the box SUMMARY Construction Estimate for Initial 53,787,217 Construction Engineering (CE) 5,19,786 Contingencies 5, Utilities Relocations 4,84,85 Total Construction Cost $64,237,853 Right of Way Cost Northern Extensions Page 8

11 Classification Number 1 - NEW CONSTRUCTION - English Route PORTWAY EXTENSIONS Section/Contract # NJ TURNPIKE INTERCHANGE 15W PM UPC No. EARTHWORK (must be calculated) Unit Quantity x Unit Price Amount Stripping (4-6" Depth) Acre ,5 72,9 Roadway Exc. Unclassified, See (J) C.Y. 113, ,72,8 Removal of Conc. Base & Conc. Surface Courses, See (K) S.Y. Channel Excavation C.Y Ditch Excavation C.Y. 1 Borrow Excavation Zone 3, See (J) C.Y. 57, ,336 EARTHWORK TOTAL = $2,467,56 Suggested procedure for calculating earthwork: A) Determine Typical section (number of lanes, median widths, side slopes, etc.). B) Get latest topography map available. C) Plot proposed alignment on topo map. D) Develop profile using topo controls such as existing roads, streams, rivers and design manual. E) Calculate Areas for the typical section in 1 foot increments of cut or fill. F) At 1 to 6 foot intervals (depending on frequency of X-section changes) calculate the earthwork. G) Calculate any other significant earthwork (ramps, cross-roads, etc.). H) Make appropriate earthwork corrections for the pavement box and striping. Use 21 inch depth for rigid pavement, 26 inch depth for all flexible pavement and 4 inch depth for stripping. I) Deduct any roadway excavation from borrow required to calculate Borrow Excavation Zone 3. J) See Construction Cost Estimate Work Sheet (Section 3.1). This worksheet must be utilized for the most recent price information. K) 11.2 to 12.5, based on the quantity, location and type of project. PAVEMENT 12 FOOT WIDE LANE (from subgrade up) Pav't. Type Description of Pavement Cost/Linear A 1 inch R.C. Pavement 156 B 2 inch HMA Surf. Crs. & 8 inch HMA Base 61 C 3 inch HMA Surf. Crs. & 4 inch HMA Base 46 D 2 inch HMA Surf. Crs. & 2 inch HMA Base 22 E Bridge Approach & Transition Slabs 156 Computation Table for Pavement. Cost Type Cost from table above x Length x Pavement *W.F. = Amount B 61 31, ,787,16 B 61 6, ,949 E ,2 PAVEMENT TOTAL = $9,16,165 *Width Factors = Ratio of 12 foot wide lane to actual pavement width. Example = actual pavement width = 25 foot = 25/12 = 2.8 W.F. 15W Page 9

12 CONTEXT SENSITIVE DESIGN Attach additional sheet detailing items and costs of context sensitive design work = CULVERTS ///////////////////////////////////////////////// ///////////////////////////////////////////////////////// COVER < W > Type 1 W< 2 Feet < W > Type 2 W> 2 feet Type Layout (3) Skew (1) Cover (2) Cost Per Sq. Area w x L exceeds -6 to 1' Sq. Feet degrees 1' to 2' Type 1 Short Culverts Difficult -6 to 1' 23.5 Conditions under 1 Square Feet degrees 1' to 2' 235. Area w x L exceeds -6 to 1' Sq. Feet degrees 1' to 2' Type 2 Short Culverts Difficult -6 to 1' 23.5 Conditions under 1 Square Feet degrees 1' to 2' 235. For skews over 6 degrees it will be necessary to make a special analysis and establish a square meter price comparable to above. Description Area Computation x Cost per Sq. = Amount Culvert Total = BRIDGES For the Bridge Sketch see the Construction Cost Estimation Preparation Manual 1 to 3 spans and 2 side spans (Max. Span 1 feet) H = Clear Height 14 To 23 feet (4) L = 1 to 4 feet & all viaducts over 4 feet (5) Class Layout Skew (1) Foundation (2) Cost per Sq. Width at Least to 4 No Piles I 45 feet Degrees Piles at Stub Abut Piles at Piers & Stub to 6 No Piles 145. Degrees Piles at Stub Abut Piles at Piers & Stub W Page 1

13 For the Bridge Sketch see the Construction Cost Estimation Preparation Manual 1 to 3 spans and 2 side spans (Max. Span 1 feet) (3) H = Clear Height 14 feet (4) L = under 4 feet Class Layout Skew (1) Foundation (2) Cost per Sq. L exceeds W to 4 No Piles II Area L x W Degrees On Piles exceeds 45 4 to 6 No Piles Sq. Feet Degrees On Piles W exceeds L to 4 No Piles III Area L x W Degrees On Piles exceeds 45 4 to 6 No Piles Sq. Feet Degrees On Piles 31. Width 3 - to 4 No Piles IV 45 feet Degrees On Piles Area W x L under 4 to 6 No Piles Sq. Degrees On Piles For the Bridge Sketch see the Construction Cost Estimation Preparation Manual 1 to 2 spans (Max. Span 125 feet) H = Clear Height 14 feet (4) L = 1 to 25 feet Layout Skew (1) Foundation (2) Cost/ Sq. Width at Least to 4 No Piles feet Degrees Piles at Semi-Stub Abut. Piles at Piers & Semi-Stub Abut to 6 No Piles Minimum Length Degrees Piles at Semi-Stub Abut feet Piles at Piers & Semi-Stub Abut $ Length Width Cost per SF Bridge Total 1. For skews over 6 degrees it will be necessary to make a special analysis and establish a square foot price comparable to above. 2. For very bad foundation conditions requiring unusual lengths or spacing of piles, it will be necessary to establish a square foot price. 3. For longer spans, adjust the cost per square foot to reflect increased cost of structural members. 4. For span bridges, it is expected the length of the side span will be in- creased in proportion to any increase in height. Because of the resultant increase in deck area, the square foot price will remain approximately the same in the range of heights shown. For extremely high structures (particularly for viaducts), square foot prices will have to be increased. 5. For structures over 4 foot long (viaducts), reduce the cost per square foot if repetitive span length and forming can be used. Reduce by $.5 for lengths from 4 to 6 feet and by $1. for lengths over 6 feet. (Do not forget adjustments (3) and (4) above on viaducts). 15W Page 11

14 6. For statically indeterminate structures, square foot prices will have to be established. Structure Description Calculated Sq. of Bridge Deck x Cost Per Square = Amount 17, ,937,5 17, ,937,5 17, ,937,5 2, ,22,5 Sub Total $57,15, Clearing Site Bridge *-3% of Sub Total % BRIDGE TOTAL $57,15, *Pick appropriate percent based on the size, type and materials of existing structure DRAINAGE (includes inlets and cross drains) Rural project length (miles) x cost per mile = Amount Urban ,265,68 project length (miles) x cost per mile = Amount The above are the total costs of basins, manholes, longitudinal and transverse pipes, underdrains, headwalls, protecting curbs, aprons, etc. for a divided highway with a depressed median. The costs are assumed to apply to 4, 6 or 8 lane sections since there will be no appreciable difference in the number of basins or the sizes or lengths of pipes. Frontage Road & Ramp Drainage length of ramp or frontage rd. in feet 6,888 x cost per foot ,84 = Amount DRAINAGE TOTAL = $3,644,52 INCIDENTAL ITEMS Item Cost / L.F. x Quantity = Amount Beam Guide Rail ,82 649,934 Fence 6 High " X 16" Conc. Vertical Curb ,64 1,67,55 15" X 41" Conc. Barrier Curb " X 41" Conc. Barrier Curb " X Variable Conc. Barrier Curb 46 Sign Bridge 38, Cantilever Sign Structure 6,5 INCIDENTAL ITEMS TOTAL = $1,716,989 15W Page 12

15 LANDSCAPE Quantity x Unit Prices = Amount Topsoil and Seeding (Mainline) Length of Project in miles 6 112, ,89 Planting (Mainline) Length of Project in miles 6 64,5 387, Topsoil, Seeding, Planting (Finger Ramp Number of Finger Ramps 4 12,5 5, Topsoil, Seeding, Planting (Loop Ramp) Number of Loop Ramps 1 2, 2, Topsoil, Seeding (Access Road) Length of Access Road in Feet 7.9 LANDSCAPE TOTAL = $1,133,89 NOISE ABATEMENT Unit Quantity x Cost = Amount Noise Wall L.F. 35 NOISE ABATEMENT TOTAL = GENERAL ITEMS Item Project Length (miles) x Cost/Mile = Amount Field Office ,26 323,98 Materials Field Laboratory ,97 211,481 Erosion Control during Constructio , ,938 GENERAL ITEMS TOTAL = $1,4,517 SUMMARY Route PORTWAY EXTENSIONS Section/Contract # NJ TURNPIKE INTERCHANGE 15W PM UPC No. Totals from other Work Type pages Earthwork 2,467,56 Pavement 9,16,165 Context Sensitive Design Culverts Bridges 57,15, Drainage 3,644,52 Incidental Items 1,716,989 Landscape 1,133,89 Noise Abatement General Items 1,4,517 PROJECT SUBTOTAL $76,142,586 15W Page 13

16 Other Items Proj. Subtotal Range Choice Amount Lighting, Traffic Stripes, Signs 3% of Proj. and Delineators Subtotal 2,284,278 Maintenance of Traffic 1.5% of Proj. Subtotal 1,142,139 Training 1% of Proj. Subtotal 761,426 Mobilization 7,614,259 9% of Proj. Project Cost < 5. (Mil.) Subtotal Project Cost 5. & above 1% of Proj. Subtotal Progress Schedule Project Cost(Mil.) $ 58, Less than to 5. 6, 5. to 1. 8, 1. to 2. 15, 2. to 3. 3, 3. to 4. 4, 4. & above 58, 58 Clearing Site Project Cost (Mil.) $ 49, Less than 1. 15, 1. to 2. 3, 2. to 5. 45, 5. to , 1. to 2. 22, 2. to 3. 24, 3. to 4. 25, 4. & above 49, 49 Construction Layout Project Cost(Mil.) $ 89, Less than 1. 7, 1. to 2. 2, 2. to 5. 42, 5. to 1. 87, 1. to 2. 16, 2. to 3. 22, 3. to 4. 49, 4. & above 89, 89 PROJECT TOTAL $89,382,687 15W Page 14

17 CONTINGENCIES & ESCALATION Y Y = Number of Years until midpoint of construction duration plus number of years until construction start. If midpoint is less than 2 years from the date of this estimate, no escalation is required.. Maximum value = 1% $9,723,428 Project Total Contingencies (1+C) 1 + [.1 (Y+1) (Y- Construction 2)] Estimate for PD 2. Project Cost(Mil.) Contingencies (C) Percent Average Construction Duration in Years -1 3% % % 3. Over 5 1.5% 4.15 CONSTRUCTION ENGINEERING (CE) % of Construction Project Cost (Mil.) Cost Less than % 1. to % 5. to % 1. & above 9.5% CONSTRUCTION ENGINEERING AMOUNT $8,618, CONSTRUCTION CHANGE ORDER CONTINGENCIES Total Federal Participating Items in Millions of $ Construction Change Order Contingency Amount $ to.1 $6,.1 to.5 25,.5 to 5. 25, + 4% of amount in excess of $5, 5. to 1. 25, + 3% of amount in excess of $5,, 1. to , + 2% of amount in excess of $1,, 15. and above 455, + 1.5% of amount in excess of $15,, - $5, max For State Funded Projects, Contingencies for Change orders = CHANGE ORDER CONTINGENCY AMOUNT = $5, UTILITIES RELOCATIONS BY COMPANIES/OWNERS $9,723,428.9 $8,165,18 x % or + Estimate = Construction Cost for Initial Estimate Use % or utilities detailed estimate Utility Relocation Cost for Initial Estimate If there are no utility relocations on the project indicate No Utilities in the box above. RIGHT OF WAY COST If there is no ROW cost on the project indicate No ROW the box SUMMARY Construction Estimate for Initial 9,723,428 Construction Engineering (CE) 8,618,726 Contingencies 5, Utilities Relocations 8,165,18 Total Construction Cost $18,7,262 Right of Way Cost 15W Page 15

18 Classification Number 1 - NEW CONSTRUCTION - English Route PORTWAY EXTENSIONS Section/Contract # HACKENSACK RIVER BRIDGE PM UPC No. EARTHWORK (must be calculated) Unit Quantity x Unit Price Amount Stripping (4-6" Depth) Acre 4,5 Roadway Exc. Unclassified, See (J) C.Y. Removal of Conc. Base & Conc. Surface Courses, See (K) S.Y. Channel Excavation C.Y Ditch Excavation C.Y. 1 Borrow Excavation Zone 3, See (J) C.Y. EARTHWORK TOTAL = Suggested procedure for calculating earthwork: A) Determine Typical section (number of lanes, median widths, side slopes, etc.). B) Get latest topography map available. C) Plot proposed alignment on topo map. D) Develop profile using topo controls such as existing roads, streams, rivers and design manual. E) Calculate Areas for the typical section in 1 foot increments of cut or fill. F) At 1 to 6 foot intervals (depending on frequency of X-section changes) calculate the earthwork. G) Calculate any other significant earthwork (ramps, cross-roads, etc.). H) Make appropriate earthwork corrections for the pavement box and striping. Use 21 inch depth for rigid pavement, 26 inch depth for all flexible pavement and 4 inch depth for stripping. I) Deduct any roadway excavation from borrow required to calculate Borrow Excavation Zone 3. J) See Construction Cost Estimate Work Sheet (Section 3.1). This worksheet must be utilized for the most recent price information. K) 11.2 to 12.5, based on the quantity, location and type of project. PAVEMENT 12 FOOT WIDE LANE (from subgrade up) Pav't. Type Description of Pavement Cost/Linear A 1 inch R.C. Pavement 156 B 2 inch HMA Surf. Crs. & 8 inch HMA Base 61 C 3 inch HMA Surf. Crs. & 4 inch HMA Base 46 D 2 inch HMA Surf. Crs. & 2 inch HMA Base 22 E Bridge Approach & Transition Slabs 156 Computation Table for Pavement. Cost Type Cost from table above x Length x Pavement *W.F. = Amount E ,2 PAVEMENT TOTAL = $187,2 *Width Factors = Ratio of 12 foot wide lane to actual pavement width. Example = actual pavement width = 25 foot = 25/12 = 2.8 W.F. Hackensack River Page 16

19 CONTEXT SENSITIVE DESIGN Attach additional sheet detailing items and costs of context sensitive design work = CULVERTS ///////////////////////////////////////////////// ///////////////////////////////////////////////////////// COVER < W > Type 1 W< 2 Feet < W > Type 2 W> 2 feet Type Layout (3) Skew (1) Cover (2) Cost Per Sq. Area w x L exceeds -6 to 1' Sq. Feet degrees 1' to 2' Type 1 Short Culverts Difficult -6 to 1' 23.5 Conditions under 1 Square Feet degrees 1' to 2' 235. Area w x L exceeds -6 to 1' Sq. Feet degrees 1' to 2' Type 2 Short Culverts Difficult -6 to 1' 23.5 Conditions under 1 Square Feet degrees 1' to 2' 235. For skews over 6 degrees it will be necessary to make a special analysis and establish a square meter price comparable to above. Description Area Computation x Cost per Sq. = Amount Culvert Total = BRIDGES For the Bridge Sketch see the Construction Cost Estimation Preparation Manual 1 to 3 spans and 2 side spans (Max. Span 1 feet) H = Clear Height 14 To 23 feet (4) L = 1 to 4 feet & all viaducts over 4 feet (5) Class Layout Skew (1) Foundation (2) Cost per Sq. Width at Least to 4 No Piles I 45 feet Degrees Piles at Stub Abut Piles at Piers & Stub to 6 No Piles 145. Degrees Piles at Stub Abut Piles at Piers & Stub Hackensack River Page 17

20 For the Bridge Sketch see the Construction Cost Estimation Preparation Manual 1 to 3 spans and 2 side spans (Max. Span 1 feet) (3) H = Clear Height 14 feet (4) L = under 4 feet Class Layout Skew (1) Foundation (2) Cost per Sq. L exceeds W to 4 No Piles II Area L x W Degrees On Piles exceeds 45 4 to 6 No Piles Sq. Feet Degrees On Piles W exceeds L to 4 No Piles III Area L x W Degrees On Piles exceeds 45 4 to 6 No Piles Sq. Feet Degrees On Piles 31. Width 3 - to 4 No Piles IV 45 feet Degrees On Piles Area W x L under 4 to 6 No Piles Sq. Degrees On Piles For the Bridge Sketch see the Construction Cost Estimation Preparation Manual 1 to 2 spans (Max. Span 125 feet) H = Clear Height 14 feet (4) L = 1 to 25 feet Layout Skew (1) Foundation (2) Cost/ Sq. Width at Least to 4 No Piles feet Degrees Piles at Semi-Stub Abut. Piles at Piers & Semi-Stub Abut to 6 No Piles Minimum Length Degrees Piles at Semi-Stub Abut feet Piles at Piers & Semi-Stub Abut , $113,68,8 Length Width Cost per SF Bridge Total 1. For skews over 6 degrees it will be necessary to make a special analysis and establish a square foot price comparable to above. 2. For very bad foundation conditions requiring unusual lengths or spacing of piles, it will be necessary to establish a square foot price. 3. For longer spans, adjust the cost per square foot to reflect increased cost of structural members. 4. For span bridges, it is expected the length of the side span will be in- creased in proportion to any increase in height. Because of the resultant increase in deck area, the square foot price will remain approximately the same in the range of heights shown. For extremely high structures (particularly for viaducts), square foot prices will have to be increased. 5. For structures over 4 foot long (viaducts), reduce the cost per square foot if repetitive span length and forming can be used. Reduce by $.5 for lengths from 4 to 6 feet and by $1. for lengths over 6 feet. (Do not forget adjustments (3) and (4) above on viaducts). Hackensack River Page 18

21 6. For statically indeterminate structures, square foot prices will have to be established. Structure Description Calculated Sq. of Bridge Deck x Cost Per Square = Amount Sub Total Clearing Site Bridge *-3% of Sub Total % BRIDGE TOTAL *Pick appropriate percent based on the size, type and materials of existing structure DRAINAGE (includes inlets and cross drains) Rural project length (miles) x cost per mile = Amount Urban project length (miles) x cost per mile = Amount The above are the total costs of basins, manholes, longitudinal and transverse pipes, underdrains, headwalls, protecting curbs, aprons, etc. for a divided highway with a depressed median. The costs are assumed to apply to 4, 6 or 8 lane sections since there will be no appreciable difference in the number of basins or the sizes or lengths of pipes. Frontage Road & Ramp Drainage length of ramp or frontage rd. in feet x cost per foot 55 = Amount DRAINAGE TOTAL = INCIDENTAL ITEMS Item Cost / L.F. x Quantity = Amount Beam Guide Rail Fence 6 High " X 16" Conc. Vertical Curb " X 41" Conc. Barrier Curb " X 41" Conc. Barrier Curb " X Variable Conc. Barrier Curb 46 Sign Bridge 38, Cantilever Sign Structure 6,5 INCIDENTAL ITEMS TOTAL = Hackensack River Page 19

22 LANDSCAPE Quantity x Unit Prices = Amount Topsoil and Seeding (Mainline) Length of Project in miles 112,815 Planting (Mainline) Length of Project in miles 64,5 Topsoil, Seeding, Planting (Finger Ramp Number of Finger Ramps 12,5 Topsoil, Seeding, Planting (Loop Ramp) Number of Loop Ramps 2, Topsoil, Seeding (Access Road) Length of Access Road in Feet 7.9 LANDSCAPE TOTAL = NOISE ABATEMENT Unit Quantity x Cost = Amount Noise Wall L.F. 35 NOISE ABATEMENT TOTAL = GENERAL ITEMS Item Project Length (miles) x Cost/Mile = Amount Field Office 1 44, Materials Field Laboratory 1 28, Erosion Control during Constructio 1 64, GENERAL ITEMS TOTAL = $137,65 SUMMARY Route PORTWAY EXTENSIONS Section/Contract # HACKENSACK RIVER BRIDGE PM UPC No. Totals from other Work Type pages Earthwork Pavement 187,2 Context Sensitive Design Culverts Bridges 113,68,8 Drainage Incidental Items Landscape Noise Abatement General Items 137,65 PROJECT SUBTOTAL $114,5,65 Hackensack River Page 2

23 Other Items Proj. Subtotal Range Choice Amount Lighting, Traffic Stripes, Signs 3% of Proj. and Delineators Subtotal 3,42,168 Maintenance of Traffic 1.5% of Proj. Subtotal 1,71,84 Training 1% of Proj. Subtotal 1,14,56 Mobilization 11,4,561 9% of Proj. Project Cost < 5. (Mil.) Subtotal Project Cost 5. & above 1% of Proj. Subtotal Progress Schedule Project Cost(Mil.) $ 58, Less than to 5. 6, 5. to 1. 8, 1. to 2. 15, 2. to 3. 3, 3. to 4. 4, 4. & above 58, 58 Clearing Site Project Cost (Mil.) $ 49, Less than 1. 15, 1. to 2. 3, 2. to 5. 45, 5. to , 1. to 2. 22, 2. to 3. 24, 3. to 4. 25, 4. & above 49, 49 Construction Layout Project Cost(Mil.) $ 89, Less than 1. 7, 1. to 2. 2, 2. to 5. 42, 5. to 1. 87, 1. to 2. 16, 2. to 3. 22, 3. to 4. 49, 4. & above 89, 89 PROJECT TOTAL $133,114,474 Hackensack River Page 21

24 CONTINGENCIES & ESCALATION Y Y = Number of Years until midpoint of construction duration plus number of years until construction start. If midpoint is less than 2 years from the date of this estimate, no escalation is required.. Maximum value = 1% $135,111,191 Project Total Contingencies (1+C) 1 + [.1 (Y+1) (Y- Construction 2)] Estimate for PD 2. Project Cost(Mil.) Contingencies (C) Percent Average Construction Duration in Years -1 3% % % 3. Over 5 1.5% 4.15 CONSTRUCTION ENGINEERING (CE) % of Construction Project Cost (Mil.) Cost Less than % 1. to % 5. to % 1. & above 9.5% CONSTRUCTION ENGINEERING AMOUNT $12,835, CONSTRUCTION CHANGE ORDER CONTINGENCIES Total Federal Participating Items in Millions of $ Construction Change Order Contingency Amount $ to.1 $6,.1 to.5 25,.5 to 5. 25, + 4% of amount in excess of $5, 5. to 1. 25, + 3% of amount in excess of $5,, 1. to , + 2% of amount in excess of $1,, 15. and above 455, + 1.5% of amount in excess of $15,, - $5, max For State Funded Projects, Contingencies for Change orders = CHANGE ORDER CONTINGENCY AMOUNT = $5, UTILITIES RELOCATIONS BY COMPANIES/OWNERS $135,111,191.9 $12,16,7 x % or + Estimate = Construction Cost for Initial Estimate Use % or utilities detailed estimate Utility Relocation Cost for Initial Estimate If there are no utility relocations on the project indicate No Utilities in the box above. RIGHT OF WAY COST If there is no ROW cost on the project indicate No ROW the box SUMMARY Construction Estimate for Initial 135,111,191 Construction Engineering (CE) 12,835,563 Contingencies 5, Utilities Relocations 12,16,7 Total Construction Cost $16,66,761 Right of Way Cost Hackensack River Page 22

25 Classification Number 1 - NEW CONSTRUCTION - English Route PORTWAY EXTENSIONS Section/Contract # NJTP INT 14A - SCHEME 1 PM UPC No. EARTHWORK (must be calculated) Unit Quantity x Unit Price Amount Stripping (4-6" Depth) Acre ,5 92,745 Roadway Exc. Unclassified, See (J) C.Y. 11, ,66,8 Removal of Conc. Base & Conc. Surface Courses, See (K) S.Y. Channel Excavation C.Y Ditch Excavation C.Y. 1 Borrow Excavation Zone 3, See (J) C.Y. 9, ,81,56 EARTHWORK TOTAL = $2,834,385 Suggested procedure for calculating earthwork: A) Determine Typical section (number of lanes, median widths, side slopes, etc.). B) Get latest topography map available. C) Plot proposed alignment on topo map. D) Develop profile using topo controls such as existing roads, streams, rivers and design manual. E) Calculate Areas for the typical section in 1 foot increments of cut or fill. F) At 1 to 6 foot intervals (depending on frequency of X-section changes) calculate the earthwork. G) Calculate any other significant earthwork (ramps, cross-roads, etc.). H) Make appropriate earthwork corrections for the pavement box and striping. Use 21 inch depth for rigid pavement, 26 inch depth for all flexible pavement and 4 inch depth for stripping. I) Deduct any roadway excavation from borrow required to calculate Borrow Excavation Zone 3. J) See Construction Cost Estimate Work Sheet (Section 3.1). This worksheet must be utilized for the most recent price information. K) 11.2 to 12.5, based on the quantity, location and type of project. PAVEMENT 12 FOOT WIDE LANE (from subgrade up) Pav't. Type Description of Pavement Cost/Linear A 1 inch R.C. Pavement 156 B 2 inch HMA Surf. Crs. & 8 inch HMA Base 61 C 3 inch HMA Surf. Crs. & 4 inch HMA Base 46 D 2 inch HMA Surf. Crs. & 2 inch HMA Base 22 E Bridge Approach & Transition Slabs 156 Computation Table for Pavement. Cost Type Cost from table above x Length x Pavement *W.F. = Amount B ,125, B ,5 B 6 7, ,752,5 B 6 11, ,486, 21 Page 1 1/9/23

26 PAVEMENT TOTAL = $4,596, *Width Factors = Ratio of 12 foot wide lane to actual pavement width. Example = actual pavement width = 25 foot = 25/12 = 2.8 W.F. CONTEXT SENSITIVE DESIGN Attach additional sheet detailing items and costs of context sensitive design work = CULVERTS ///////////////////////////////////////////////// /////////////////////////////////////////////////////////// COVER < W > Type 1 W< 2 Feet < W > Type 2 W> 2 feet Type Layout (3) Skew (1) Cover (2) Cost Per Sq. Area w x L exceeds -6 to 1' Sq. Feet degrees 1' to 2' Type 1 Short Culverts Difficult -6 to 1' 23.5 Conditions under 1 Square Feet degrees 1' to 2' 235. Area w x L exceeds -6 to 1' Sq. Feet degrees 1' to 2' Type 2 Short Culverts Difficult -6 to 1' 23.5 Conditions under 1 Square Feet degrees 1' to 2' 235. For skews over 6 degrees it will be necessary to make a special analysis and establish a square meter price comparable to above. Description Area Computation x Cost per Sq. = Amount Culvert Total = BRIDGES For the Bridge Sketch see the Construction Cost Estimation Preparation Manual 1 to 3 spans and 2 side spans (Max. Span 1 feet) H = Clear Height 14 To 23 feet (4) L = 1 to 4 feet & all viaducts over 4 feet (5) Class Layout Skew (1) Foundation (2) Cost per Sq. Width at Least to 4 No Piles I 45 feet Degrees Piles at Stub Abut Piles at Piers & Stub Page 2 1/9/23

27 For the Bridge Sketch see the Construction Cost Estimation Preparation Manual 1 to 3 spans and 2 side spans (Max. Span 1 feet) (3) H = Clear Height 14 feet (4) L = under 4 feet 4 to 6 No Piles 145. Degrees Piles at Stub Abut Piles at Piers & Stub Class Layout Skew (1) Foundation (2) Cost per Sq. L exceeds W to 4 No Piles II Area L x W Degrees On Piles exceeds 45 4 to 6 No Piles Sq. Feet Degrees On Piles W exceeds L to 4 No Piles III Area L x W Degrees On Piles exceeds 45 4 to 6 No Piles Sq. Feet Degrees On Piles 31. Width 3 - to 4 No Piles IV 45 feet Degrees On Piles Area W x L under 4 to 6 No Piles Sq. Degrees On Piles For the Bridge Sketch see the Construction Cost Estimation Preparation Manual 1 to 2 spans (Max. Span 125 feet) H = Clear Height 14 feet (4) L = 1 to 25 feet Layout Skew (1) Foundation (2) Cost/ Sq. Width at Least to 4 No Piles feet Degrees Piles at Semi-Stub Abut. Piles at Piers & Semi-Stub Abut to 6 No Piles Minimum Length Degrees Piles at Semi-Stub Abut feet Piles at Piers & Semi-Stub Abut $ Length Width Cost per SF Bridge Total 1. For skews over 6 degrees it will be necessary to make a special analysis and establish a square foot price comparable to above. 2. For very bad foundation conditions requiring unusual lengths or spacing of piles, it will be necessary to establish a square foot price. 3. For longer spans, adjust the cost per square foot to reflect increased cost of structural members. 4. For span bridges, it is expected the length of the side span will be in- creased in proportion to any increase in height. Because of the resultant increase in deck area, the square foot price will remain approximately the same in the range of heights shown. For extremely high structures (particularly for viaducts), square foot prices will have to be increased. 5. For structures over 4 foot long (viaducts), reduce the cost per square foot if repetitive span length and forming can be used. Reduce by $.5 for lengths from 4 to 6 feet and by $1. for lengths over 6 feet. (Do not forget adjustments (3) and (4) above on viaducts). 21 Page 3 1/9/23

28 6. For statically indeterminate structures, square foot prices will have to be established. Structure Description Calculated Sq. of Bridge Deck x Cost Per Square = Amount 26, 225 5,85, Sub Total $5,85, Clearing Site Bridge *-3% of Sub Total % BRIDGE TOTAL $5,85, *Pick appropriate percent based on the size, type and materials of existing structure DRAINAGE (includes inlets and cross drains) Rural project length (miles) x cost per mile = Amount Urban ,848 project length (miles) x cost per mile = Amount The above are the total costs of basins, manholes, longitudinal and transverse pipes, underdrains, headwalls, protecting curbs, aprons, etc. for a divided highway with a depressed median. The costs are assumed to apply to 4, 6 or 8 lane sections since there will be no appreciable difference in the number of basins or the sizes or lengths of pipes. Frontage Road & Ramp Drainage length of ramp or frontage rd. in feet 12,338 x cost per foot ,59 = Amount DRAINAGE TOTAL = $1,549,438 INCIDENTAL ITEMS Item Cost / L.F. x Quantity = Amount Beam Guide Rail ,875 Fence 6 High " X 16" Conc. Vertical Curb ,97 315,838 15" X 41" Conc. Barrier Curb " X 41" Conc. Barrier Curb ,33 24" X Variable Conc. Barrier Curb Page 4 1/9/23

29 Sign Bridge 38, Cantilever Sign Structure 6, INCIDENTAL ITEMS TOTAL = $2,42,245 LANDSCAPE Quantity x Unit Prices = Amount Topsoil and Seeding (Mainline) Length of Project in miles ,815 18,54 Planting (Mainline) Length of Project in miles ,5 13,2 Topsoil, Seeding, Planting (Finger Ramp Number of Finger Ramps 3 12,5 37,5 Topsoil, Seeding, Planting (Loop Ramp) Number of Loop Ramps 2 2, 4, Topsoil, Seeding (Access Road) Length of Access Road in Feet 7.9 LANDSCAPE TOTAL = $361,24 NOISE ABATEMENT Unit Quantity x Cost = Amount Noise Wall L.F. 35 NOISE ABATEMENT TOTAL = GENERAL ITEMS Item Project Length (miles) x Cost/Mile = Amount Field Office ,26 172,614 Materials Field Laboratory ,97 112,983 Erosion Control during Construction , ,63 GENERAL ITEMS TOTAL = $536,66 SUMMARY Route PORTWAY EXTENSIONS Section/Contract # NJTP INT 14A - SCHEME 1 PM UPC No. Totals from other Work Type pages Earthwork 2,834,385 Pavement 4,596, Context Sensitive Design Culverts Bridges 5,85, Drainage 1,549,438 Incidental Items 2,42,245 Landscape 361,24 21 Page 5 1/9/23

30 Walls 125* * ,353,4 General Items 536,66 Traffic Signals 4* , Toll 15*9 13,5, PROJECT SUBTOTAL $44,613,332 Other Items Proj. Subtotal Range Choice Amount Lighting, Traffic Stripes, Signs and 3% of Proj. Delineators Subtotal 1,338,4 Maintenance of Traffic 1.5% of Proj. Subtotal 669,2 Training 1% of Proj. Subtotal 446,133 Mobilization 4,461,333 9% of Proj. Project Cost < 5. (Mil.) Subtotal Project Cost 5. & above 1% of Proj. Subtotal Progress Schedule Project Cost(Mil.) $ 58, Less than to 5. 6, 5. to 1. 8, 1. to 2. 15, 2. to 3. 3, 3. to 4. 4, 4. & above 58, 58 Clearing Site Project Cost (Mil.) $ 49, Less than 1. 15, 1. to 2. 3, 2. to 5. 45, 5. to , 1. to 2. 22, 2. to 3. 24, 3. to 4. 25, 4. & above 49, 49 Construction Layout Project Cost(Mil.) $ 89, Less than 1. 7, 1. to 2. 2, 2. to 5. 42, 5. to 1. 87, 1. to 2. 16, 2. to 3. 22, 3. to 4. 49, 4. & above 89, 89 PROJECT TOTAL $52,966,398 CONTINGENCIES & ESCALATION Y = Number of Years until midpoint of construction duration plus number of years until construction start. If midpoint is less than 2 years from the. date of this estimate, no escalation is required. Maximum value = 1% $53,76,894 Project Total Contingencies (1+C) Y 1 + [.1 (Y+1) (Y- 2)] Construction Estimate for PD Page 6 1/9/23

31 Project Cost(Mil.) Contingencies (C) Percent Average Construction Duration in Years -1 3% % % 3. Over 5 1.5% 4.15 CONSTRUCTION ENGINEERING (CE) % of Construction Project Cost (Mil.) Cost Less than % 1. to % 5. to % 1. & above 9.5% CONSTRUCTION ENGINEERING AMOUNT $5,17, CONSTRUCTION CHANGE ORDER CONTINGENCIES Total Federal Participating Items in Millions of $ Construction Change Order Contingency Amount $ to.1 $6,.1 to.5 25,.5 to 5. 25, + 4% of amount in excess of $5, 5. to 1. 25, + 3% of amount in excess of $5,, 1. to , + 2% of amount in excess of $1,, 15. and above 455, + 1.5% of amount in excess of $15,, - $5, max For State Funded Projects, Contingencies for Change orders = CHANGE ORDER CONTINGENCY AMOUNT = $5, UTILITIES RELOCATIONS BY COMPANIES/OWNERS $53,76,894.9 $4,838,48 x % or + Estimate = Construction Cost for Initial Estimate Use % or utilities detailed estimate Utility Relocation Cost for Initial Estimate If there are no utility relocations on the project indicate No Utilities in the box above. RIGHT OF WAY COST If there is no ROW cost on the project indicate No ROW the box SUMMARY Construction Estimate for Initial 53,76,894 Construction Engineering (CE) 5,17,285 Contingencies 5, Utilities Relocations 4,838,48 Total Construction Cost $64,26,659 Right of Way Cost 21 Page 7 1/9/23

32 Classification Number 1 - NEW CONSTRUCTION - English Route PORTWAY EXTENSIONS Section/Contract # NJTP INT 14A - SCHEME 2 PM UPC No. EARTHWORK (must be calculated) Unit Quantity x Unit Price Amount Stripping (4-6" Depth) Acre ,5 13,5 Roadway Exc. Unclassified, See (J) C.Y. 155, ,333,685 Removal of Conc. Base & Conc. Surface Courses, See (K) S.Y. Channel Excavation C.Y Ditch Excavation C.Y. 1 Borrow Excavation Zone 3, See (J) C.Y. 113, ,367,988 EARTHWORK TOTAL = $3,831,678 Suggested procedure for calculating earthwork: A) Determine Typical section (number of lanes, median widths, side slopes, etc.). B) Get latest topography map available. C) Plot proposed alignment on topo map. D) Develop profile using topo controls such as existing roads, streams, rivers and design manual. E) Calculate Areas for the typical section in 1 foot increments of cut or fill. F) At 1 to 6 foot intervals (depending on frequency of X-section changes) calculate the earthwork. G) Calculate any other significant earthwork (ramps, cross-roads, etc.). H) Make appropriate earthwork corrections for the pavement box and striping. Use 21 inch depth for rigid pavement, 26 inch depth for all flexible pavement and 4 inch depth for stripping. I) Deduct any roadway excavation from borrow required to calculate Borrow Excavation Zone 3. J) See Construction Cost Estimate Work Sheet (Section 3.1). This worksheet must be utilized for the most recent price information. K) 11.2 to 12.5, based on the quantity, location and type of project. PAVEMENT 12 FOOT WIDE LANE (from subgrade up) Pav't. Type Description of Pavement Cost/Linear A 1 inch R.C. Pavement 156 B 2 inch HMA Surf. Crs. & 8 inch HMA Base 61 C 3 inch HMA Surf. Crs. & 4 inch HMA Base 46 D 2 inch HMA Surf. Crs. & 2 inch HMA Base 22 E Bridge Approach & Transition Slabs 156 Computation Table for Pavement. Cost Type Cost from table above x Length x Pavement *W.F. = Amount B ,175, B ,5 B ,3, B ,8 B ,219, 21 Page 1 1/9/23

33 $6,489,3 *Width Factors = Ratio of 12 foot wide lane to actual pavement width. Example = actual pavement width = 25 foot = 25/12 = 2.8 W.F. CONTEXT SENSITIVE DESIGN Attach additional sheet detailing items and costs of context sensitive design work = CULVERTS ///////////////////////////////////////////////// /////////////////////////////////////////////////////////// COVER < W > Type 1 W< 2 Feet < W > Type 2 W> 2 feet Type Layout (3) Skew (1) Cover (2) Cost Per Sq. Area w x L exceeds -6 to 1' Sq. Feet degrees 1' to 2' Type 1 Short Culverts Difficult -6 to 1' 23.5 Conditions under 1 Square Feet degrees 1' to 2' 235. Area w x L exceeds -6 to 1' Sq. Feet degrees 1' to 2' Type 2 Short Culverts Difficult -6 to 1' 23.5 Conditions under 1 Square Feet degrees 1' to 2' 235. For skews over 6 degrees it will be necessary to make a special analysis and establish a square meter price comparable to above. Description Area Computation x Cost per Sq. = Amount Culvert Total = BRIDGES For the Bridge Sketch see the Construction Cost Estimation Preparation Manual 1 to 3 spans and 2 side spans (Max. Span 1 feet) H = Clear Height 14 To 23 feet (4) L = 1 to 4 feet & all viaducts over 4 feet (5) Class Layout Skew (1) Foundation (2) Cost per Sq. Width at Least to 4 No Piles I 45 feet Degrees Piles at Stub Abut Piles at Piers & Stub Page 2 1/9/23

34 For the Bridge Sketch see the Construction Cost Estimation Preparation Manual 1 to 3 spans and 2 side spans (Max. Span 1 feet) (3) H = Clear Height 14 feet (4) L = under 4 feet 4 to 6 No Piles 145. Degrees Piles at Stub Abut Piles at Piers & Stub Class Layout Skew (1) Foundation (2) Cost per Sq. L exceeds W to 4 No Piles II Area L x W Degrees On Piles exceeds 45 4 to 6 No Piles Sq. Feet Degrees On Piles W exceeds L to 4 No Piles III Area L x W Degrees On Piles exceeds 45 4 to 6 No Piles Sq. Feet Degrees On Piles 31. Width 3 - to 4 No Piles IV 45 feet Degrees On Piles Area W x L under 4 to 6 No Piles Sq. Degrees On Piles For the Bridge Sketch see the Construction Cost Estimation Preparation Manual 1 to 2 spans (Max. Span 125 feet) H = Clear Height 14 feet (4) L = 1 to 25 feet Layout Skew (1) Foundation (2) Cost/ Sq. Width at Least to 4 No Piles feet Degrees Piles at Semi-Stub Abut. Piles at Piers & Semi-Stub Abut to 6 No Piles Minimum Length Degrees Piles at Semi-Stub Abut feet Piles at Piers & Semi-Stub Abut $ Length Width Cost per SF Bridge Total 1. For skews over 6 degrees it will be necessary to make a special analysis and establish a square foot price comparable to above. 2. For very bad foundation conditions requiring unusual lengths or spacing of piles, it will be necessary to establish a square foot price. 3. For longer spans, adjust the cost per square foot to reflect increased cost of structural members. 4. For span bridges, it is expected the length of the side span will be in- creased in proportion to any increase in height. Because of the resultant increase in deck area, the square foot price will remain approximately the same in the range of heights shown. For extremely high structures (particularly for viaducts), square foot prices will have to be increased. 5. For structures over 4 foot long (viaducts), reduce the cost per square foot if repetitive span length and forming can be used. Reduce by $.5 for lengths from 4 to 6 feet and by $1. for lengths over 6 feet. (Do not forget adjustments (3) and (4) above on viaducts). 21 Page 3 1/9/23

PROJECT COST ESTIMATE ASSUMPTIONS AND EXCLUSIONS

PROJECT COST ESTIMATE ASSUMPTIONS AND EXCLUSIONS C PROJECT ESTIMATE ASSUMPTIONS AND EXCLUSIONS In support of the alternatives development process, preliminary cost estimates were prepared for each of the three Candidate Build Alternatives. The cost estimates

More information

NOTICE TO CONTRACTORS. CALL ORDER 700 FEDERAL PROJECT NO. STPD-6-2(122) LOCATION: US-34/US-6,CULBERTSON-McCOOK COUNTIES: HITCHCOCK RED WILLOW

NOTICE TO CONTRACTORS. CALL ORDER 700 FEDERAL PROJECT NO. STPD-6-2(122) LOCATION: US-34/US-6,CULBERTSON-McCOOK COUNTIES: HITCHCOCK RED WILLOW NOTICE TO CONTRACTORS CALL ORDER 700 FEDERAL PROJECT NO. STPD-6-2(122) LOCATION: US-34/US-6,CULBERTSON-McCOOK COUNTIES: HITCHCOCK RED WILLOW The Nebraska Department of Roads will receive sealed bids in

More information

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix.

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix. Storm Drainage 13-C-1 APPENDIX C INLETS 1.0 Introduction The application and types of storm drainage inlets are presented in detail in this Appendix. 2.0 Inlet Locations Inlets are required at locations

More information

Legacy Trail Extension Feasibility Study. Preliminary Cost Estimate

Legacy Trail Extension Feasibility Study. Preliminary Cost Estimate Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5

More information

Planning Level Cost Estimation Tool. User s Manual

Planning Level Cost Estimation Tool. User s Manual Planning Level Cost Estimation Tool User s Manual Atlanta Regional Commission Submitted By: User s Manual Table of Contents 1. INTRODUCTION... 1 2. OBJECTIVE... 1 3. FRAMEWORK OF THE TOOL... 2 4. HOW TO

More information

Majors Program Cost Estimating Software. User Manual. Created by the Construction and Materials Support Center at the University of Wisconsin-Madison

Majors Program Cost Estimating Software. User Manual. Created by the Construction and Materials Support Center at the University of Wisconsin-Madison Majors Program Cost Estimating Software User Manual Created by the Construction and Materials Support Center at the University of Wisconsin-Madison August, 2011 Contents Introduction... 3 Intentions of

More information

Exhibit A Scope of Work

Exhibit A Scope of Work Exhibit A Scope of Work The agreement for S.P. 3116-142 (T.H. 169-Cross Range Expressway) includes final design plans for a 1.55 mile length of a 2 lane to 4 lane expansion project located 0.66 miles SW

More information

Roadway Cost Per Centerline Mile Revised June 2014

Roadway Cost Per Centerline Mile Revised June 2014 Rural Arterial From LRE MOT * Mobilization * Subtotal Total PE Design (15%) CEI (15%) Total Project ** New (2-Lane Roadway) with 5' Paved Shoulders $3,351,896 $335,190 $368,709 $4,055,794 $1,013,949 $5,069,743

More information

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition. Design Guide Basis of Design This section applies to the design and installation of earthwork and backfill. Design Criteria No stockpiling of excavation materials is allowed unless the Geotechnical Engineer

More information

STORM WATER PROJECT COST ESTIMATES & LOCATION MAPS. Appendix F

STORM WATER PROJECT COST ESTIMATES & LOCATION MAPS. Appendix F STORM WATER PROJECT COST ESTIMATES & LOCATION MAPS Appendix F RIVERDALE CITY CAPITAL FACILITIES PLAN STORM DRAINAGE Engineer's Cost Estimate January 2009 Project Name: 4400 South Street - Piping and Collection

More information

HIGHWAY DEPARTMENT ACCESS AND RIGHT OF WAY WIDTH GUIDELINES

HIGHWAY DEPARTMENT ACCESS AND RIGHT OF WAY WIDTH GUIDELINES Approved 6/26/01 HIGHWAY DEPARTMENT ACCESS AND RIGHT OF WAY WIDTH GUIDELINES All new, modified and/or changed use access(es) onto county roads shall be subject to the access and corridor protection guidelines

More information

DESCRIPTION OF WORK:

DESCRIPTION OF WORK: DEPARTMENT OF PUBLIC WORKS COUNTY OF HENRICO P.O. BOX 27032 RICHMOND, VIRGINIA 23273 PERMIT NO. One (1) copy of application and four (4) copies of plans are hereby made to the Director of Public Works

More information

CHAPTER 17: STORM SEWER STANDARDS. 17.00 Introduction. 17.01 Administration. 17.02 Standards 17.1

CHAPTER 17: STORM SEWER STANDARDS. 17.00 Introduction. 17.01 Administration. 17.02 Standards 17.1 CHAPTER 17: STORM SEWER STANDARDS 17.00 Introduction 17.01 Administration 17.02 Standards 17.1 17.00 INTRODUCTION The purpose of this chapter is to provide guidance for the design and construction of storm

More information

UNIT PRICE LIST January 2009

UNIT PRICE LIST January 2009 UNIT PRICE LIST January 2009 1 INTRODUCTION The purpose of the Unit Price List is to provide a resource for the preparation of cost estimates for subdivisions and permit projects and should be used only

More information

The unit costs are based on the trend line of the 3 low bids for the average quantity.

The unit costs are based on the trend line of the 3 low bids for the average quantity. Page 1 of 8 COST ESTIMATE GENERAL INSTRUCTIONS The unit costs are based on the trend line of the 3 low bids for the average quantity. Apply the Unit Costs to ordinary structures. Unit Costs should generally

More information

Los Angeles County Department Of Public Works. Land Development Division. Bond Calculation Sheets

Los Angeles County Department Of Public Works. Land Development Division. Bond Calculation Sheets Los Angeles County Department Of Public Works Land Development Division Bond Calculation Sheets Effective July 1, 2015 COUNTY OF LOS ANGELES DEPARTMENT OF PUBLIC WORKS LAND DEVELOPMENT DIVISION ROADS COST

More information

Safe & Sound Bridge Terminology

Safe & Sound Bridge Terminology Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries

More information

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department Land Disturbance, Erosion Control and Stormwater Management Checklist Walworth County Land Conservation Department The following checklist is designed to assist the applicant in complying with the Walworth

More information

SECTION 5 DRAFTING STANDARDS

SECTION 5 DRAFTING STANDARDS SECTION 5 DRAFTING STANDARDS 1 SECTION FIVE TABLE OF CONTENTS Description Page TABLE OF CONTENTS... 5-2 GENERAL... 5-3 DRAFTING STANDARDS... 5-5 DRAFTING MINIMUM REQUIREMENTS HANDOUT... 5-8 2 GENERAL 1.

More information

SECTION 08000 STORM DRAINAGE TABLE OF CONTENTS

SECTION 08000 STORM DRAINAGE TABLE OF CONTENTS SECTION 08000 STORM DRAINAGE 08010 DESIGN A. Location B. Sizing TABLE OF CONTENTS 08020 MATERIALS A. Pipe Materials B. Structure Materials C. Installation D. Inlets and Outlets 08030 INSPECTIONS AND TESTING

More information

SECTION 02530 STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.

SECTION 02530 STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250. 02530-1 of 5 SECTION 02530 STORM DRAINAGE STRUCTURES 02530.01 GENERAL A. Description Storm drainage structure construction shall include, but not necessarily be limited to, furnishing and installing or

More information

SECTION III-06 Surfacing Page 1 Revised 3/2/10. See the DESIGN GUIDELINES in Section I-06 for requirements for cross slope of the roadway.

SECTION III-06 Surfacing Page 1 Revised 3/2/10. See the DESIGN GUIDELINES in Section I-06 for requirements for cross slope of the roadway. Page 1 Revised 3/2/10 See the DESIGN GUIDELINES in Section I-06 for requirements for cross slope of the roadway. For New/Reconstruction projects: The cross slope of the driving lanes range from 1.5% to

More information

Storm Drainage Systems 11.9-1

Storm Drainage Systems 11.9-1 Storm Drainage Systems 11.9-1 11.9 Gutter Flow Calculations 11.9.1 Introduction Gutter flow calculations are necessary in order to relate the quantity of flow (Q) in the curbed channel to the spread of

More information

Unit Price Averages Reports

Unit Price Averages Reports Unit Price Averages Reports 12/7/2015 UNIT PRICE AVERAGES REPORT Disclaimer The information provided in the following Unit Price Averages Report is only for the use of Alberta Infrastructure & Transportation

More information

IH-635 MANAGED LANES PROJECT, SEG. 3.2

IH-635 MANAGED LANES PROJECT, SEG. 3.2 IH-635 MANAGED LANES PROJECT, SEG. 3.2 Location: Dallas, Texas Owner: Texas Department of Transportation Client: Ferrovial Agroman Construction Cost: $1 Billion Construction Completion Date: December,

More information

FDOT DBE CERTIFICATION NAICS CODE GUIDE WITH CAP SIZES

FDOT DBE CERTIFICATION NAICS CODE GUIDE WITH CAP SIZES NAICS CODE Highway, Street, and Bridge Construction SIZE CAP ($ MIL) 237310 Asphalt Roadway (includes 300, 320, 327, 330, 334, 336, 337, 338) Application of prime and tack coats, leveling surfaces and

More information

Grinding equipment that causes raveling, aggregate fractures or disturbance to the joints shall not be permitted.

Grinding equipment that causes raveling, aggregate fractures or disturbance to the joints shall not be permitted. Guide Specification: Diamond Grinding for City Streets Publication Date: May 24, 2010 SCOPE City streets are defined as roadways with a closed drainage system along with numerous structures such as manholes,

More information

Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin PLAN SUBGRADES

Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin PLAN SUBGRADES Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering Geotechnical Bulletin GB 1 PLAN SUBGRADES Geotechnical Bulletin GB1 was jointly developed by the Offices

More information

Chapter 4 SUBSURFACE INVESTIGATION GUIDELINES

Chapter 4 SUBSURFACE INVESTIGATION GUIDELINES Chapter 4 SUBSURFACE INVESTIGATION GUIDELINES Final SCDOT GEOTECHNICAL DESIGN MANUAL August 2008 Table of Contents Section Page 4.1 Introduction...4-1 4.2 Subsurface Investigation...4-2 4.2.1 Preliminary

More information

Work Breakdown Structure Element Dictionary. Final Design

Work Breakdown Structure Element Dictionary. Final Design Initiation FD 4.1 Initiation encompasses deliverables associated with the development, implementation and control of the project s schedule, budget and scope. The lead office develops these project parameters

More information

2006-2008 MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS

2006-2008 MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS 2006-2008 MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS GENERAL 10/16/2008 The listed average unit prices are based on the

More information

APPENDIX D INLET CAPACITY AND SPACING. The capacity and spacing design of storm drainage inlets are presented in detail in this Appendix.

APPENDIX D INLET CAPACITY AND SPACING. The capacity and spacing design of storm drainage inlets are presented in detail in this Appendix. Storm Drainage 3-D- PPENDIX D INET CPCITY ND SPCING.0 Introduction The capacity and spacing design of storm drainage inlets are presented in detail in this ppendix. 2.0 Design Recurrence Interval and Spread

More information

How To Build A Road In A Townhouse

How To Build A Road In A Townhouse FDOT DBE CERTIFICATION SPECIALTY/ SHEET WITH CAP SIZES Highway, Street, and Bridge Construction SIZE CAP ($ MIL) 237310 Asphalt Roadway $ 22.41 Application of prime and tack coats, leveling surfaces and

More information

CHAPTER 7 ROAD STORM DRAINAGE SYSTEMS

CHAPTER 7 ROAD STORM DRAINAGE SYSTEMS CHAPTER 7 ROAD STORM DRAINAGE SYSTEMS Note: All questions and comments should be directed to the Hydraulics Unit Supervisor, Environmental Services Section. Revised November 2015 Road Storm Drainage Systems

More information

SUPPLEMENTAL SPECIFICATIONS CROSS SLOPE VERIFICATION:

SUPPLEMENTAL SPECIFICATIONS CROSS SLOPE VERIFICATION: September 22, 2009 Updated November 16, 2009 SUPPLEMENTAL SPECIFICATIONS CROSS SLOPE VERIFICATION: 1. DESCRIPTION: The cross slopes of the roadway are to be constructed as detailed in the plans and within

More information

BUSINESS DEVELOPMENT INITIATIVE SMALL BUSINESS PROGRAM GUIDANCE FOR RESERVING CONTRACTS

BUSINESS DEVELOPMENT INITIATIVE SMALL BUSINESS PROGRAM GUIDANCE FOR RESERVING CONTRACTS Construction/Maintenance Contracts and Design/Build Low Bid Contracts 1. Districts are responsible for reviewing their work program and identifying contracts that are good candidates for the Business Development

More information

CHAPTER 2 HYDRAULICS OF SEWERS

CHAPTER 2 HYDRAULICS OF SEWERS CHAPTER 2 HYDRAULICS OF SEWERS SANITARY SEWERS The hydraulic design procedure for sewers requires: 1. Determination of Sewer System Type 2. Determination of Design Flow 3. Selection of Pipe Size 4. Determination

More information

Chapter 22. Lump Sum Project Guidelines

Chapter 22. Lump Sum Project Guidelines Chapter 22 Lump Sum Project Guidelines 22.1 General...22-1 22.2 Project Selection...22-3 22.3 Plans Preparation...22-5 22.4 Preliminary Estimate...22-7 22.5 Specifications...22-9 22.6 Contracts Administration...22-11

More information

ROAD SURVEYING Section I. RECONNAISSANCE SURVEY PREPARATION AND SCOPE

ROAD SURVEYING Section I. RECONNAISSANCE SURVEY PREPARATION AND SCOPE CHAPTER 2 ROAD SURVEYING Section I. RECONNAISSANCE SURVEY PREPARATION AND SCOPE The reconnaissance survey is an extensive study of an entire area that might be used for a road or airfield. Its purpose

More information

FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation

FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation 644-10-569 Page 1 of 9 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING

More information

WESTFIELD-WASHINGTON ADVISORY PLAN COMMISSION December 7, 2015 1512-SPP-24 & 1512-ODP-24

WESTFIELD-WASHINGTON ADVISORY PLAN COMMISSION December 7, 2015 1512-SPP-24 & 1512-ODP-24 Petition Number: Subject Site Address: Petitioner: Request: East side of Oak Road, north of 151 st Street Langston Development Co. Primary Plat and Overall Development Plan amendment review for Mapleridge

More information

Preliminary Design Report Clay County, Florida Carpet n Drapes Culvert Repair and Rehabilitation July 21, 2006

Preliminary Design Report Clay County, Florida Carpet n Drapes Culvert Repair and Rehabilitation July 21, 2006 Clay County, Florida Carpet n Drapes Culvert Repair and Rehabilitation July 21, 2006 1.0 Background and Repair and Rehabilitation Recommendation Clay County has contracted Camp Dresser & McKee Inc. (CDM)

More information

Town of Elkton & Cecil Soil Conservation District Checklist for Joint Agency Review Stormwater Management / Erosion and Sediment Control

Town of Elkton & Cecil Soil Conservation District Checklist for Joint Agency Review Stormwater Management / Erosion and Sediment Control Town of Elkton & Cecil Soil Conservation District Checklist for Joint Agency Review Stormwater Management / Erosion and Sediment Control Project Name: Tax Map Parcel: Acreage: Plat: ADC Map & Grid Engineering

More information

Riverside County Transportation Department Summary of Bids

Riverside County Transportation Department Summary of Bids Bids Open: 2 pm Date: Wednesday, March 4, 2015 BASE BID SCHEDULE 1 - Rudell Road Reconstruction Project NO. CODE CONTRACT PROJECT No. B3-0470 and C4-0069 COUNTY'S ESTIMATE 1 All American Asphalt Corona,

More information

Description Quantity Cost Total Cost

Description Quantity Cost Total Cost APPENDIX: ITEMIZED CONSTRUCTION COST ESTIMATE Description Quantity Cost Total Cost 1 CASCADE FALLS 1a Existing Cascade Falls Upgrades Structural Repairs - Steps, Railing, Walls, Pool Lump Sum $500,000

More information

Demo Existing Curb Demo Existing Asphalt Roadway Demo Asphalt Saw Cutting Protection Fence - 4 Snow Fence with T posts

Demo Existing Curb Demo Existing Asphalt Roadway Demo Asphalt Saw Cutting Protection Fence - 4 Snow Fence with T posts SECTION 00300 BID FORM S For additions and deletions to the Contract, the following unit prices shall be applicable for the specific items listed. Unit Prices shall be complete, in place including required

More information

VILLAGE OF LOMBARD CONTRACT DOCUMENT NUMBER ST-09-06 BID PROPOSAL

VILLAGE OF LOMBARD CONTRACT DOCUMENT NUMBER ST-09-06 BID PROPOSAL VILLAGE OF LOMBARD CONTRACT DOCUMENT NUMBER ST-09-06 BID PROPOSAL I/We hereby agree to furnish to the Village of Lombard all necessary materials, equipment, and labor, to complete the North Industrial

More information

FLORIDA DEPARTMENT OF TRANSPORTATION GUIDELINE FOR

FLORIDA DEPARTMENT OF TRANSPORTATION GUIDELINE FOR FLORIDA DEPARTMENT OF TRANSPORTATION GUIDELINE FOR ESTABLISHING CONSTRUCTION CONTRACT DURATION July 2010 DISCLAIMER: The following documentation as a whole was derived from Federal Highway Administration

More information

Chapter 4 ASSET INVENTORY AND CONDITION CHAPTER 4 ASSET INVENTORY AND CONDITION PAGE 33

Chapter 4 ASSET INVENTORY AND CONDITION CHAPTER 4 ASSET INVENTORY AND CONDITION PAGE 33 Chapter 4 ASSET INVENTORY AND CONDITION CHAPTER 4 ASSET INVENTORY AND CONDITION PAGE 33 This page intentionally left blank. PAGE 34 MINNESOTA GO MNDOT TRANSPORTATION ASSET MANAGEMENT PLAN ASSET INVENTORY

More information

8.1.3 General Design Guidelines. The following guidelines shall be used when designing inlets along a street section:

8.1.3 General Design Guidelines. The following guidelines shall be used when designing inlets along a street section: . Introduction Presented in this chapter are the criteria and methodology for design and evaluation of storm sewer inlets located in Town of Castle Rock. The review of all planning submittals will be based

More information

FY08 SEWER POINT REPAIRS BID TABULATION

FY08 SEWER POINT REPAIRS BID TABULATION 6-07-831 Page 1 of 12 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING "

More information

SITE PLAN REVIEW RESOLUTION BERGEN COUNTY, NEW JERSEY

SITE PLAN REVIEW RESOLUTION BERGEN COUNTY, NEW JERSEY SP SITE PLAN REVIEW RESOLUTION BERGEN COUNTY, NEW JERSEY Document available on line at www.co.bergen.nj.us/planning TABLE OF CONTENTS I. DEFINITIONS FOR SITE PLAN RESOLUTION II. PROCEDURES: A. General

More information

ENGINEERING DESIGN GUIDELINES. for SUBDIVISIONS OR COMMERCIAL DEVELOPMENTS

ENGINEERING DESIGN GUIDELINES. for SUBDIVISIONS OR COMMERCIAL DEVELOPMENTS ENGINEERING DESIGN GUIDELINES for SUBDIVISIONS OR COMMERCIAL DEVELOPMENTS City of Birmingham Department of Planning, Engineering and Permits Engineering Division Office of the City Engineer 2008 TABLE

More information

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary

More information

2011 HYDRAULICS MANUAL

2011 HYDRAULICS MANUAL STATE OF LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT P.O. Box 94245 Baton Rouge, Louisiana 70804-9245 http://www.dotd.la.gov/ HYDRAULICS MANUAL Hydraulics (225) 379-1306 PREFACE The following

More information

SOLD. Lot 1. 1 Mile: Population: 10,200 Median HH Income: $33,100. 3 Mile: Population: 80,200 Median HH Income: $34,900

SOLD. Lot 1. 1 Mile: Population: 10,200 Median HH Income: $33,100. 3 Mile: Population: 80,200 Median HH Income: $34,900 Walmart Outparcels For Sale College Station, TX Store # 1150 1815 Brothers Blvd FM 2818 W SOLD Texas Ave S/ Hwy 6 Longmire Dr Brothers Blvd Lot 1 For more information about this site, contact: Lot 1: ±2.41

More information

CHAPTER 8 CIVIL DESIGN

CHAPTER 8 CIVIL DESIGN CHAPTER 8 CIVIL DESIGN A. GENERAL This Chapter includes standards and design considerations for other civil engineering design in structural, drainage and utilities. Design considerations for electrical

More information

Construction Survey Procedures

Construction Survey Procedures Chapter 15 Construction Survey Procedures 15-01 General In performing construction surveying, preparation is a major part of the operation. Study the contract plans, special provisions, Standard Plans,

More information

Chapter Forty-seven. RURAL TWO-LANE/MULTILANE STATE HIGHWAYS (New Construction/Reconstruction) BUREAU OF DESIGN AND ENVIRONMENT MANUAL

Chapter Forty-seven. RURAL TWO-LANE/MULTILANE STATE HIGHWAYS (New Construction/Reconstruction) BUREAU OF DESIGN AND ENVIRONMENT MANUAL Chapter Forty-seven RURAL TWO-LANE/MULTILANE STATE HIGHWAYS (New Construction/Reconstruction) BUREAU OF DESIGN AND ENVIRONMENT MANUAL Illinois RURAL TWO-LANE/MULTILANE STATE HIGHWAYS December 2009 2 Illinois

More information

Paving Capitalization Work Categories and Treatments

Paving Capitalization Work Categories and Treatments Statement of ODOT Infrastructure Capitalization Policy Government Accounting Standards Board (GASB) 34 requires public agencies to capitalize infrastructure assets on their financial statements for periods

More information

Local Road Assessment and Improvement Drainage Manual

Local Road Assessment and Improvement Drainage Manual Local Road Assessment and Improvement Drainage Manual Donald Walker, T.I.C. Director, author Lynn Entine, Entine & Associates, editor Susan Kummer, Artifax, design Transportation Information Center University

More information

CHAPTER 4 STORM DRAINAGE SYSTEMS

CHAPTER 4 STORM DRAINAGE SYSTEMS CHAPTER 4 STORM DRAINAGE SYSTEMS 4.1 Overview... 4-1 4.1.1 Introduction... 4-1 4.1.2 Inlet Definition... 4-1 4.1.3 Criteria... 4-1 4.2 Pavement Drainage... 4-2 4.2.1 Introduction... 4-2 4.2.2 Storm Drain

More information

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0

More information

PLANNED UNIT DEVELOPMENT & SIDEWALK WAIVER REQUEST STAFF REPORT Date: November 7, 2013

PLANNED UNIT DEVELOPMENT & SIDEWALK WAIVER REQUEST STAFF REPORT Date: November 7, 2013 PLANNED UNIT DEVELOPMENT & SIDEWALK WAIVER REQUEST STAFF REPORT Date: November 7, 2013 NAME LOCATION Audubon Properties, LLC. 4700 & 4960 Dauphin Island Parkway West side of Dauphin Island Parkway, 580

More information

Rehabilitation of the Red Bank Road Bridge over Hoover Reservoir. Presented By: Doug Stachler, P.E.

Rehabilitation of the Red Bank Road Bridge over Hoover Reservoir. Presented By: Doug Stachler, P.E. Rehabilitation of the Red Bank Road Bridge over Hoover Reservoir Presented By: Doug Stachler, P.E. Project Organization Owner Delaware County Engineers Office Design Consultant CH2M HILL Contractor Double

More information

Stormwater/Wetland Pond Construction Inspection Checklist

Stormwater/Wetland Pond Construction Inspection Checklist : Construction Inspection ChecklistsTools Stormwater/Wetland Pond Construction Inspection Checklist Project: Location: Site Status: Date: Time: Inspector: SATISFACTORY/ UNSATISFACTORY COMMENTS Pre-Construction/Materials

More information

FDOT Specifications List

FDOT Specifications List FDOT Specifications List TABLE OF CONTENTS DIVISION II CONSTRUCTION DETAILS CLEARING CONSTRUCTION SITE 110 Clearing and Grubbing... 152 EARTHWORK AND RELATED OPERATIONS 120 Excavation and Embankment...

More information

CONSTRUCTION COST ESTIMATES

CONSTRUCTION COST ESTIMATES Chapter 8 CONSTRUCTION COST ESTIMATES SCDOT BRIDGE DESIGN MANUAL April 2006 Table of Contents Section Page 8.1 PROGRAMMING ESTIMATES...8-1 8.1.1 Bridge Replacement Projects...8-1 8.1.2 Other Projects...8-1

More information

MONETARY GUARANTY PROCEDURE PACKAGE FREDERICK COUNTY, VIRGINIA

MONETARY GUARANTY PROCEDURE PACKAGE FREDERICK COUNTY, VIRGINIA MONETARY GUARANTY PROCEDURE PACKAGE FREDERICK COUNTY, VIRGINIA Department of Planning and Development 107 North Kent Street, Suite 202 Winchester, Virginia 22601 Phone: (540) 665-5651 Fax: (540) 665-6395

More information

PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE

PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE REGION OF PEEL PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE Storm Sewer Design Criteria REVISED July 2009 PUBLIC WORKS STORM SEWER DESIGN CRITERIA TABLE OF CONTENTS 1.0

More information

Colorado Off-System Bridge Program Description and Guidelines for Selecting Bridges for Rehabilitation or Replacement Funding

Colorado Off-System Bridge Program Description and Guidelines for Selecting Bridges for Rehabilitation or Replacement Funding C Colorado Off-System Bridge Program Description and Guidelines for Selecting Bridges for Rehabilitation or Replacement Funding These guidelines are intended to provide assistance in selecting OFF-SYSTEM

More information

P. ALTERNATE TECHNICAL CONCEPTS FOR CONSTRUCTION, STAGING AND TRAFFIC CONTROL

P. ALTERNATE TECHNICAL CONCEPTS FOR CONSTRUCTION, STAGING AND TRAFFIC CONTROL P. ALTERNATE TECHNICAL CONCEPTS FOR CONSTRUCTION, STAGING AND TRAFFIC CONTROL 1.0 Description. 1.1 This specification allows bidders the opportunity to include in their overall bid proposal, pricing for

More information

3.1 Historical Considerations

3.1 Historical Considerations 3. Recommended Scope of Bridge improvements 3.1 Historical Considerations In the fall of 2000, an outside consultant, Fraser Design, suggested that the existing 4 th St. Bridge is potentially eligible

More information

2015 ODOT Bridge Design Conference May 12, 2014. DeJong Rd Bridge High- Seismic Zone Case Study: Bridge Rehab vs. Replacement.

2015 ODOT Bridge Design Conference May 12, 2014. DeJong Rd Bridge High- Seismic Zone Case Study: Bridge Rehab vs. Replacement. 2015 ODOT Bridge Design Conference May 12, 2014 DeJong Rd Bridge High- Seismic Zone Case Study: Bridge Rehab vs. Replacement Mary Ann Triska 2015 HDR, all rights reserved. Presentation Outline Project

More information

Date. Resubmit this form during the year if there are changes in your company ownership or financial standing.

Date. Resubmit this form during the year if there are changes in your company ownership or financial standing. COLORADO DEPARTMENT OF TRANSPORTATION CONTRACTOR PREQUALIFICATION STATEMENT (EXPERIENCE, EQUIPMENT AND FINANCIAL) Return to: Contracts & Market Analysis Prequalification Unit 4201 E. Arkansas,4th Floor

More information

SECTION 7- STORM SEWER

SECTION 7- STORM SEWER SECTION 7- STORM SEWER 7.1. STORM SEWERS.... 7-1 7.2. SUMP DRAINS... 7-3 7.3. CATCH BASINS... 7-3 7.4. MANHOLES... 7-4 7.5. STORM SEWER CALCULATIONS... 7-4 7.6. CULVERTS AND BRIDGES... 7-5 7.7. OPEN CHANNELS...

More information

City Streets as State Highways Maintenance Guidelines Briefing Summary March 21, 2013

City Streets as State Highways Maintenance Guidelines Briefing Summary March 21, 2013 Streets as Highways Maintenance Guidelines Briefing Summary March 21, 2013 Background Within the of Washington there are over 500 centerline miles of Streets that also function as Highways. Cities that

More information

Informational Workshop Public Meeting Kanawha Falls Bridge Project

Informational Workshop Public Meeting Kanawha Falls Bridge Project Informational Workshop Public Meeting Kanawha Falls Project WV Department of Transportation Division of Highways in Cooperation with the Federal Highway Administration State Project S310-13-0.02 00 Federal

More information

BMP-7. A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet.

BMP-7. A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet. BMP-7 BMP: STORM DRAIN INLET PROTECTION Definition A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet. To prevent sediment from entering storm drainage systems

More information

I-66 Pavement Rehabilitation

I-66 Pavement Rehabilitation I-66 Pavement Rehabilitation Fall Asphalt Conference Richmond, VA David Shiells, P.E. Virginia Department of Transportation David White Superior Paving Corporation October 2, 2012 Project Location 2 Goal

More information

TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth

TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth TABLE OF CONTENTS NO. MP-1 MP-2 MP-3 MP-4 MP-4.01 MP-4.02 MP-4.03 MP-5 MP-5.01 MP-5.02 MP-5.03 MP-5.04 MP-5.05 MP-5.06 MP-5.07 MP-5.08 MP-5.11 MP-5.12 MP-5.13 MP-5.14 MP-5.15 MP-5.16 MP-5.18 MP-5.19 MP-5.20

More information

BUSINESS DEVELOPMENT INITIATIVE SMALL BUSINESS PROGRAM GUIDANCE FOR RESERVING CONTRACTS

BUSINESS DEVELOPMENT INITIATIVE SMALL BUSINESS PROGRAM GUIDANCE FOR RESERVING CONTRACTS Construction/Maintenance Contracts and Design/Build Low Bid Contracts 1. Districts are responsible for reviewing their work program and identifying contracts that are good candidates for the Business Development

More information

FIBER-OPTIC CABLE PLAN CHECK

FIBER-OPTIC CABLE PLAN CHECK Engineering Division 201 North Broadway, Escondido, CA 92025 (760) 839-4651, FAX (760) 839-4597 FIBER-OPTIC CABLE PLAN CHECK To: Date: Project: Project No. Address: Check No. Attn: Via: The attached plans

More information

Drainage DR-701. Materials Field Sampling. Purpose of the Guidance Manual. General DR 701-1

Drainage DR-701. Materials Field Sampling. Purpose of the Guidance Manual. General DR 701-1 DR-701 Chapter Materials Field Sampling Drainage Subject INLETS INTRODUCTION & STORM SEWERS General Purpose of the Guidance Manual DR 701-1 STORM SEWER DEFINITION KYTC defines a storm sewer as two or more

More information

5.14 Floodplains and Drainage/Hydrology

5.14 Floodplains and Drainage/Hydrology I-70 East Final EIS 5.14 Floodplains and Drainage/Hydrology 5.14 Floodplains and Drainage/Hydrology This section discusses floodplain and drainage/hydrology resources and explains why they are important

More information

CHAPTER 1181 Improvements

CHAPTER 1181 Improvements 139 CHAPTER 1181 Improvements 1181.01 Performance bond; 1181.07 Street name signs. construction plans; 1181.08 Street lighting. improvements. 1181.09 Improvements bond. 1181.02 Monuments. 1181.10 Maintenance

More information

SUBDIVISION ROAD CONSTRUCTION AND INSPECTION PROCEDURES

SUBDIVISION ROAD CONSTRUCTION AND INSPECTION PROCEDURES BOARD OF COUNTY COMMISSIONERS ST. MARY S COUNTY LEONARDTOWN, MARYLAND SUBDIVISION ROAD CONSTRUCTION AND INSPECTION PROCEDURES APRIL, 1991 AMENDED: JUNE, 2002 DEPARTMENT OF PUBLIC WORKS & TRANSPORTATION

More information

URBAN DRAINAGE CRITERIA

URBAN DRAINAGE CRITERIA URBAN DRAINAGE CRITERIA I. Introduction This division contains guidelines for drainage system design and establishes a policy for recognized and established engineering design of storm drain facilities

More information

Ohio Department of Transportation Prebid Questions

Ohio Department of Transportation Prebid Questions Project No. 093005 Sale Date - 12/9/2009 Question Submitted: 11/10/2009 Are all underdrains to be replaced in both resurface and full depth areas? Where are the underdrains to be placed? In areas where

More information

Minimizes sediment and debris from entering storm drains that lead to waterways and watercourses.

Minimizes sediment and debris from entering storm drains that lead to waterways and watercourses. 4.5-p DRAIN INLET PROTECTION Alternative Names: DI protection, Drop Inlet Protection DESCRIPTION Storm drain inlet (DI) protection slows and ponds stormwater, and filters sediment and debris before it

More information

SECTION 31 20 00 EARTH MOVING

SECTION 31 20 00 EARTH MOVING SECTION 31 20 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for excavating, filling, and grading for earthwork at Parking Structure, new exit stair and as required to

More information

Underground Injection Control Storm Water Information

Underground Injection Control Storm Water Information Underground Injection Control Storm Water Information Best Management Practices DEQ has reviewed the EPA definition of a subsurface fluid distribution system and the infiltration design best management

More information

Surface Transportation Program (STP)

Surface Transportation Program (STP) Project Name: Project Sponsor: FEDERAL FUNDS PROJECT APPLICATION TRANSPORTATION IMPROVEMENT PROGRAM 2008-2013 SALT LAKE and OGDEN/ LAYTON URBAN AREAS Surface Transportation Program (STP) Urban Surface

More information

STORMWATER MANAGEMENT CHECKLIST

STORMWATER MANAGEMENT CHECKLIST STORMWATER MANAGEMENT CHECKLIST *This checklist must be completed and part of the Land Disturbing Permit submittal for review if the acreage disturbed is one (1) acre or more: I. SUPPORTING DATA Narrative

More information

Outlet stabilization structure

Outlet stabilization structure Overview of Sedimentation and Erosion Control Practices Practice no. 6.41 Outlet stabilization structure Erosion at the outlet of channels, culverts, and other structures is common, and can cause structural

More information

The Basics of Chapter 105 Waterways and Wetlands Permitting in PA

The Basics of Chapter 105 Waterways and Wetlands Permitting in PA The Basics of Chapter 105 Waterways and Wetlands Permitting in PA April 17, 2013 Goal To develop a basic understanding of PA Department of Environmental Protection (DEP) and US Army Corps of Engineers

More information

Table 4.9 Storm Drain Inlet Protetion Applicable for

Table 4.9 Storm Drain Inlet Protetion Applicable for BMP C220: Storm Drain Inlet Protection Purpose To prevent coarse sediment from entering drainage systems prior to permanent stabilization of the disturbed area. Conditions of Use Type of Inlet Protection

More information

LIMITED SCOPE CONCEPT DEVELOPMENT REPORT

LIMITED SCOPE CONCEPT DEVELOPMENT REPORT LIMITED SCOPE CONCEPT DEVELOPMENT REPORT Route 33 Resurfacing Project Eastbound: Milepost 24.2 to Milepost 28.9 Westbound: Milepost 24.3 to Milepost 28.9 Manalapan & Freehold Townships, Monmouth County

More information

SECTION III DRAINAGE

SECTION III DRAINAGE SECTION III DRAINAGE TOC-III.1 of 5 TABLE OF CONTENTS DRAINAGE FACILITIES No. Title D-1 Standard Underdrains D-2 Longitudinal Underdrain for Flexible Paving D-3 Spring Control Method & Detail D-4 Trench

More information

Chagrin River Watershed Partners, Inc. Cost Analysis of Low Impact Development Best Management Practices

Chagrin River Watershed Partners, Inc. Cost Analysis of Low Impact Development Best Management Practices Chagrin River Watershed Partners, Inc. Cost Analysis of Low Impact Development Best Management Practices Amy H. Brennan (440) 975-3870 www.crwp.org abrennan@crwp.org Chagrin River Watershed Partners Formed

More information