Material Requirements Planning. Managing Inventories of Items With Dependent Demand

Size: px
Start display at page:

Download "Material Requirements Planning. Managing Inventories of Items With Dependent Demand"

Transcription

1 Material Requirements Planning Managing Inventories of Items With Dependent Demand 1

2 Demand Types Dependent Demand: Demand for items that are component parts to be used in the production of finished goods Independent Demand: Demand generated outside the system. Usually, demand for end-items or items sold individually, e.g. spare parts 2

3 Demand & MRP Dependent demand should be handled differently than independent demand Production should be planned taking into consideration the link between independent demand and sub-assembly requirements Material Requirements Planning (MRP) is the universally accepted tool for managing inventories of items with dependent demand 3

4 MRP Functionality Material Requirements Planning: Calculate the quantity of raw materials and sub-assemblies to produce the necessary end-item quantities (as expressed with independent demand) Coordination of Purchase and Production P Orders (or Jobs): Determine and coordinate the start times of all jobs so that end-items are completed before due dates 4

5 Time in MRP In MRP systems, time is divided in fixed intervals or it is considered a continuous variable Item requirements within a specific time interval are usually supposed to apply from the beginning of the interval 5

6 MRP Schematic Master Production Schedule Inventory Status Delivery data Product Structure, i.e., Bill of Material Material Requirements Plan Purchasing Requirements Production Requirements 6

7 MRP Inputs Master Production Schedule (MPS) Gross Requirements (authorized) Production Forecasts Item Master File (BOM) Lot Sizing Rule Period order quantity (POQ) or (FOP) Lot for lot (L4L) Fixed order quantity (FOQ) 7

8 MRP Inputs Planning Lead Time (Constant) Inventory Status (on-hand Inventory) Scheduled Receipts Identifier (Purchase Order of Job number) Due date and release date Unit of measure and quantity 8

9 Item Master Data Item master data contains: Item code Item description Bill of Materials Lot-size Planned lead times 9

10 Bill of Materials The relation between an end-item and its sub-assemblies is described in the Bill of Materials (BOM). For example for end items A and B, the BOM is: BOM example for end items A & B 10

11 Bill of Materials Usually, an end-item is composed of many components and sometimes it is even linked to several different BOMs Production uses BOMs to calculate the load and material requirements at each production stage in order to produce an end-item 11

12 Bill of Materials For each BOM component, a Low Level Code (LLC) is defined; this code indicates the lowest level a specific component is found End-items have LLCs equal to zero A group of items used only for the assembly of enditems has LLC equal to 1 A group used for the production of items with LLC equal to 1, has LLC equal to 2 and so forth Most commercial MRP packages integrate a BOM processor which automatically attributes the LLC to all items based on BOM data 12

13 Master Production Schedule (MPS) MPS contains information about: Gross requirements Due dates Purchase and production orders and scheduled receipts On-hand inventory 13

14 MPS Example 14

15 MPS Vs. Forecasts Unit Time frame Horizon Updating Forecasting Product Families Month - Quarter Years Month - Quarter MPS Product and sub-assemblies Day, Week, Month Weeks to months Week Function General Management Planning/Production

16 On-hand Inventory Inventory records contain information about: Storage location Current available quantities Raw material inventory status Crib" inventory (pre-processed and stored inventory) Sub-assembly inventory status Allocation of reserved items to on-going processes 16

17 Scheduled Receipts A scheduled receipt refers to: For purchased items: the issuance of a purchase order and notification of the supplier For produced items: the production routing and the issuance of a production order As soon as the purchase/production order is issued, the scheduled order issuance is deleted and a scheduled receipt is generated 17

18 Lot-sizing The lot sizing rule determines the balance between two contradicting goals: The decrease of on-hand inventory (small lot size) The decrease of order intervals (large lot size) Lot size rules are used to balance the costs of high inventory levels and administration costs induced by too many orders 18

19 Planning Lead Time Planning lead time (PLT) is used to determine the start time of each operation Start time is calculated by subtracting the PLT from the due date If PLTs were accurate, MRP would result in Justin-Time production Usually, PLTs cannot be known a priori and most of the times they are purposely elongated 19

20 MRP Procedure For each BOM level (starting from level 0), MRP performs: Netting: Calculation of net requirements Gross requirements are subtracted from on-hand inventory and scheduled receipts Gross requirements for items with LLC=0 derive from MPS while for items with LLC>0 derive from previously executed MRP calculations Lot sizing Lot sizing: The material requirements are divided in lots according to the lot-sizing rule used 20

21 MRP Procedure Time phasing: Start times for each job is calculated by subtracting lead times from due dates BOM explosion: Based on start times, the lot size and BOM, gross requirements are calculated for the lower LLC Iteration: All steps are repeated until all BOM levels are processed 21

22 MRP Netting Netting performs mainly two functions: Adjust Scheduled Receipts Calculate net requirements MRP assumes that all Scheduled Receipts (SR) will be delivered before any other is placed MRP assumes that gross requirements will be first met by current inventory, then by adjusting SRs and finally by placing new production/purchase orders 22

23 MRP Netting Gross requirements that cannot be met by current inventory and/or adjusted SRs are net requirements If t* is the first time bucket where SRs and current inventory cannot meet gross requirements, net requirements are calculated as follows: Equal to zero for t<t*, Equal to negative inventory (I t ) for period t* Equal to gross requirements (D t ) after period t* N t = 0 I Dt t Net requirements are used in the next level of MRP calculations (lot sizing) for for for t t t < = > t t t * * * 23

24 Netting Example Gross requirement of units in week 1 can be met by current inventory and so the SR of 10 units can be delayed In week 2, gross requirement (20) cannot be met by inventory (5) - The SR of week1 is transferred to week1 The first negative inventory is observed in week 6 - Its value represents the net requirements for this period For weeks 6-8, the net requirements are equal to the gross requirements PART A Gross requirements Scheduled receipts Adjusted SRs Projected on-hand Net requirements

25 Lot-sizing After net requirements, the production lots must be determined MRP assumes that requirements are deterministic and non-constant Most common lot-sizing policies: Lot-for-lot, production lot for a period equals net requirements for this period Fixed order period (FOP) or period order quantity - This policy aims at the reduction of the number of orders by combining net requirements of adjacent periods Fixed order quantity (FOQ) - This policy aims at the reduction of the number of orders by ordering a fixed amount of items, independent of the net requirements 25

26 Lot-sizing Example Suppose the lot-sizing policy for Item A is fixed order period (for P=2 periods) Net requirements of period 6 and 7 are combined PART A Gross requirements Scheduled receipts Adjusted SRs Projected on-hand Net requirements Planned order receipts

27 Time phasing Almost all MRP packages assume that time to perform some processes is strictly predetermined although some systems allow planned lead time increase with job size MRP treats lead times as properties of the items and sometimes of the jobs/operations but not of the shop floor For item A, assume that the lead time to assemble it is two periods PART A Gross requirements Scheduled receipts Adjusted SRs Projected on-hand Net requirements Planned order receipts Planned order releases

28 BOM explosion Based on planned order releases for Item A, gross requirements for items 100 and 200 can be calculated As a result, for item 100, 90 units for period 4 and 60 units for period 6 are required. For item 200, 45 units for period 4 and 30 for period 6 are required. These requirements must be added to any other requirements already generated by other higher level items (such as A) The next step is to iterate this procedure for items at the lower BOM levels PART A Planned order releases

29 BOM explosion MPS for item B is presented as well as current inventory for items B, 100, 300 and 500. T Demand PART NUMBER CURRENT ON-HAND SRS Due Quantity LOT-SIZING RULE LEAD TIME B 40 0 FOP, 2 weeks 2 weeks Lot-for-lot 2 weeks Lot-for-lot 1 week Lot-for-lot 4 weeks 29

30 BOM explosion MRP results for item B PART B Gross requirements Scheduled receipts Adjusted SRs Projected on-hand Net requirements 20 Planned order receipts Planned order releases

31 BOM explosion For each unit of B, one unit of 500 is required. Thus, scheduled order releases for item B are equivalent to gross requirements for item 500. There is no SR PART 500 Gross requirements Scheduled receipts Adjusted SRs Projected on-hand 40 Net requirements Planned order receipts Planned order releases As lead time for item 500 is 4 weeks, there is not enough time to prepare 25 units before week As a result, a planned order release is generated by MRP 35 with the warning 30 that it might be late *

32 BOM explosion At the lower level (LLC=2) and for item 100, there are two sources of requirements: 2 units for each A and 1 unit for each 500 There is no SR PART Required from A Required from Gross requirements Projected on-hand Net requirements Planned order receipts Planned order releases

33 BOM explosion The only item with LLC=3 is item 300. Its requirements are generated by items B and 100. There is a scheduled receipt of 100 units on week2. No adjusting is needed since this SR may cover the requirements for this period. PART Required from B Required from Gross requirements Scheduled receipts 100 Adjusted SRs 100 Projected on-hand Net requirements 65 Planned order receipts 65 Planned order releases 65 33

34 BOM explosion Summary Transaction Part Number Old Due Date or Release Date New Due Date Quantity Notice Change notice A Defer Change notice Α Expedite Planned order release A OK Planned order release A OK Planned order release B OK Planned order release B OK Planned order release B 6 8 OK Planned order release OK Planned order release OK Planned order release OK Planned order release OK Planned order release Late Planned order release OK

35 MRP Outputs Planned Order Release Part Number Number of Units Due date Change Notices Expediting (move earlier) Deferring (making due date later) 35

36 MRP Outputs Exception Reports, i.e., discrepancies between what is expected and what will transpire: Job count differences Inventory discrepancies Imminently tardy jobs 36

37 MRP Problems Capacity Infeasibility Assumption = production line with fixed lead time Lead time does not depend upon WIP Result = infinite capacity Problem when production levels near capacity 37

38 MRP Problems Long Planned Lead Times Pressure to increase planned lead times Penalties for late jobs assumed greater than excess inventories WIP with accumulate & lead times will further increase Irresponsive approach by production managers 38

39 MRP Problems Constant Lead Times Pessimistic values (inflation) to secure due-dates System Nervousness Small change in MPS leads to large change in Planned Releases Strange effects, e.g.: Decrease in demand may result in a feasible MRP Plan to become infeasible!!! 39

40 MRP Problems Nervousness example Two parts, A & B Part A: Lead Time of two weeks Fixed Order Period (five weeks) Part B (1 required for each Part A): Lead Time of four weeks Fixed Order Period (five weeks) 40

41 MRP Problems Nervousness example (continued) Table 1: MRP Calculations for Item A Before Change in Demand Week Item A Gross Requirements Scheduled Receipts Projected On-hand Inventory Net Requirements Planned Order Receipts 14 Planned Order Releases Table 2: MRP Calculations for Item B Before Change in Demand Week Item B Gross Requirements Scheduled Receipts 14 Projected On-hand Inventory Net Requirements 48 Planned Order Receipts 48 Planned Order Releases 48 Table 3: MRP Calculations for Item A After Change in Demand Week Item A Gross Requirements Scheduled Receipts Projected On-hand Inventory Net Requirements Planned Order Receipts 63 Planned Order Releases 63 Table 4: MRP Calculations for Item B After Change in Demand Week Item B Gross Requirements 63 Scheduled Receipts 14 Projected On-hand Inventory Net Requirements 47 Planned Order Receipts 47 Planned Order Releases 47* *Indicates a late start 41

42 MRP Problems Nervousness can be reduced by: Different lot-sizing rules for different BOM levels FOQ for end items FOQ or L4L for intermediate BOM levels FOP for the lowest levels 42

43 MRP Problems Nervousness can be reduced by: Proper use of lot-sizing rules E.g., in L4L magnitude of change no larger than MPS Freezing the early part of the MPS (Frozen Zones) Time Fences (gradual freezing) Firm Planned Orders (not allowed to change early PO) 43

44 MRP Problems Revisit the example nervousness eliminated! Table 1: MRP Calculations for Item A Before Change in Demand Table 5: MRP Calculations for Item A After Change for Firm Planned Orders Week Item A Gross Requirements Scheduled Receipts Projected On-hand Inventory Net Requirements Planned Order Receipts 14 Planned Order Releases Table 2: MRP Calculations for Item B Before Change in Demand Week Item B Gross Requirements Scheduled Receipts 14 Projected On-hand Inventory Net Requirements 48 Planned Order Receipts 48 Planned Order Releases 48 Week Item A Gross Requirements Scheduled Receipts 14 Projected On-hand Inventory Net Requirements 49 Planned Order Receipts [14] 49 Planned Order Releases [14] 49 Table 6: MRP Calculations for Item B After Change for Firm Planned Orders Week Item B Gross Requirements Scheduled Receipts 14 Projected On-hand Inventory Net Requirements 47 Planned Order Receipts 47 Planned Order Releases 47 44

45 MRP ΙΙ Infeasible plans, long planned lead times, system nervousness jeopardize the successful execution of MRP In order to confront these problems, additional functionalities have been added to the main MRP procedure These functionalities were implemented in a wider information system known as Manufacturing Resource Planning or MRP II 45

46 MRP II Manufacturing Resource Planning Additional Functions: Demand Management Forecasting Rough-cut Capacity Planning Capacity Requirements Planning Dispatching Input and Output Control 46

47 MRP II Long-term forecast Resource Planning Aggregate production planning Long Range Planning Rough-cut Capacity Planning (RCCP) Master Production Scheduling (MPS) Firm Orders Short-term forecast Bill-of-materials (BOM) On-hand inventory Scheduled receipts Material Requirements Planning (MRP) Job pool Demand Management Capacity Requirements Planning (CRP) Intermediate Range Planning Job Release Routing data Job Dispatching I/O control Short-term Control 47

48 MRP ΙΙ hierarchy Long term planning Long term planning includes: resource planning aggregate planning forecasting The planning horizon length for long term planning is usually from six months to five years The re-planning interval usually varies from once a month to once every six months Detail level is low. Usually, long term planning deals with families of products 48

49 MRP ΙΙ hierarchy Forecasting The forecasting functionality aims at future demand prediction Long term forecasts are very important since they determine availability, general production planning and staff requirements Short-term forecasting transforms a long term forecast for a family of products to short-term forecast for individual products Both functions belong to the demand management module at the medium term planning level 49

50 MRP ΙΙ hierarchy Resource planning Resource planning is the procedure during which capacity requirements are calculated during medium term planning Decisions like infrastructure expansion or the purchase of new facilities belong to resource planning Future resource availability can be forecasted through resource planning This data is then entered to the aggregate planning level 50

51 MRP ΙΙ hierarchy Aggregate planning Aggregate planning is used to determine: Production levels Staffing level (human resources) Inventory levels Overtime Anything concerning medium term production planning Detail level is usually one month and aggregate planning deals with families of products Optimization methods like linear programming are frequently used to aid aggregate planning 51

52 Medium term planning Main functions of production planning Includes: demand management rough-cut capacity planning master production scheduling material requirements planning capacity requirements planning 52

53 Medium term planning Demand management Demand management is about translating aggregate long term forecasts in detailed forecasts by also taking into account individual customer orders Based on this function, a set of real customer orders and a forecast of anticipated orders are created As time goes by, anticipated orders must be replaced by actual customer orders 53

54 Medium term planning Available to promise (ATP) Demand management is finalized with a technique known as Available to Promise-ATP This function allows the planner to know which MPS orders are already linked to customer orders and which are available for the fulfillment of new customer needs If the ATP function is coupled with a feasible MPS (in terms of resource availability) the realistic due date assignment is simplified If more than anticipated orders are placed so as lead times become very large, then additional capacity (e.g. overtime) might be required If incoming orders are less than anticipated, sales might want to offer discounts or some other motivations to stimulate demand In each case, the forecast and most likely, the aggregate plan must be revised 54

55 Medium term planning Production planning Master production schedule uses forecasts along with confirmed production orders from the demand management module and by using the total resource availability limits, develops a plan at the highest level of planning detail Consequently, master production schedule contains the quantities of orders for each time bucket for each component with independent demand, for each planning date 55

56 Medium term planning Production planning For most enterprises, order quantities are given in the end-item level. However, for some cases it is more practical to group end-items to product families. Such an example is automotive industries where the exact type and specification of a vehicle are determined in the last stage, during its final assembly. In these cases, a final assembly plan determines when end-items are produced while MPS is used to determine the models to be produced. A basic input for this type of planning is item s super-bill which is a description for the various options of each model. 56

57 Medium term planning Rough-cut capacity planning Rough-cut capacity planning (RCCP) is used to provide a fast estimation of whether critical production resources are adequate for a given MPS Generally, RCCP uses a bill of resources for each MPS item Bill of resources is a database of the critical resource requirements for producing one unit of an end-item Apart from the end-item itself, resource requirements include all requirements for lower level items in order to produce one end-product 57

58 RCCP Example For example, let item A be produced by using A1 and A2. Product A requires 1h in resource 21 while A1 and A2 require 0.5h and 1h respectively As a result, the bill of resources of item A would indicate that item A requires 2.5h at resource 21 in order to be produced Also let item B that requires 2h at resource 21 in order to be produced (with no lower level items) PROCESS CENTRE PART A PART B WEEK Part A Part B

59 RCCP Run WEEK Part A (hour) Part B (hour) Total (hour) O 35 Available Over(+)/under(-) After running RCCP, it is obvious that in some periods, resource availability is inadequate while in others it is more than enough It depends on the production manager to act accordingly aiming at the reduction of this fluctuation; the choices are: Adjust MPS by changing due dates Adjust resource availability by adding resources or by using overtime or some sort of outsourcing for various stages of the production process 59

60 Medium term planning RCCP RCCP does not perform offsetting. As a result, periods used must be long enough so as end-items can be produced (from raw materials to end product) in one single period. Moreover, RCCP supposes that requirements can be performed without taking into account actual shop floor status. Hence, what can be really produced is frequently overestimated. RCCP does not perform netting. While this is acceptable for end items, it creates many problems when there are many common items among end products and work-inprogress level is high. 60

61 Medium term planning CRP Capacity Requirements Planning (CRP) is a more detailed (in comparison to RCCP) check of whether resources are adequate for a given production schedule. Necessary CRP inputs include: All planned order releases Current work-in-progress Routing information Lead times and capacity for all resources CRP does not optimize resource allocation but performs a process also known as infinite forward loading: It forecasts finish times of each job for all resources by using predetermined constant lead times. It then calculates the forecasted load of each resource for all periods All loads are then compared to actual resource availability Overloads are not confronted. The system just informs the production manager for the potential overload. 61

62 CRP Example Suppose a resource with a lead time of three days and capacity of 400 units per day. At the beginning of the current day, 400 units were just released, 500 units had been released for one day and 300 units had been released for two days. The planned order releases for the next five days are: DAY Planned order releases

63 CRP Example By using the three day lead time, we can calculate when items will leave this specific resource If more than 400 units are calculated to leave the resource, then the resource will be considered overloaded for this specific period. In the resource utilization graph: During the first day, total load is 300 (300 units already entered into the resource) During the second day, the load is 500 indicating an overload. This load comes from orders already entered into the system 63

64 CRP Drawbacks CRP assumes that processing time is irrelevant to the resource load even if the latter one is above capacity. As a result, calculating load after an overloaded period might not be accurate. Typically, CRP does not forecast accurately the load in periods close to the current date. Another CRP drawback is that it just indicates overloads without proposing a solution to this problem A major inconsistency of CRP is that, just like MRP, supposes infinite resource availability. This assumption stems from the constant lead time assumption which is not linked to resource load. 64

65 Medium term planning Material Requirements Planning Material requirements planning (MRP) functionality is exactly the same with the typical MRP. As already mentioned, MRP creates a job pool which is consists of planned order releases. Finally, these requirements are released to the shop floor through a process called job release. 65

66 Short term planning Plans that were processed during the long and medium term planning functions, are then executed by short term control functions. These function are: Job release job dispatching input/output production control 66

67 Short term planning Job Release The job release function converts the planned order release to schedule receipts One of job release s most important functions is allocation When some products are composed of common materials, there might be a conflict in case of inadequate material supply Job release might rationally organize such conflicts 67

68 Short term planning Job Release For example, suppose there are two planned order releases (POR) that both require item A and there is not enough inventory of item A for both of them Moreover, the first POR requires item B of which there is enough inventory while the other POR requires item C the inventory of which is inadequate The Job release function will proceed with the release of the first POR since there is enough inventory for all of its stages A shortage notification would be created for the second POR which would remain in the job pool until sufficient inventory existed for all production stages 68

69 Short term planning As soon as a production or purchase order is released, the prompt completion must be monitored. Moreover, the final quantity and quality must comply with initial specifications. Purchase orders can be tracked. Production orders are controlled through two functions: shop floor control (SFC) with two sub-functions: job dispatching input/output control production activity control (PAC) 69

70 Short term planning Job Dispatching Job Dispatching deals with the rules that determine the operation sequence in a resource. These rules should: Respect due dates Keep resource utilization high Reduce production times 70

71 Job Dispatching Rules One of the simplest rules is also known as the shortest process time (SPT) rule. Based on SPT, operations are ordered in such a way that orders with shortest processing are executed first. SPT use decreases mean production times and increases resource utilization - Mean due date is also very good SPT does not perform very well when there are operations with long processing times An alternative to SPT is SPTx where the next operation to be performed is the one with the shortest processing time unless an operation has been queued for more than x time units. 71

72 Job Dispatching Rules If all jobs have almost the same size and routings are consistent, a good dispatching rule is the earliest due date (EDD) rule. According to this rule, the operation which is closer to its due date is performed first. EDD performs well under the assumptions mentioned above but generally it does not perform better than SPT. The least slack rule: The slack of an operation is defined as its due date minus the remaining processing time (including setups). The highest priority operation is the one with the least slack. 72

73 Job Dispatching Rules The Least slack per remaining operation rule: This rule is similar to the least slack rule but the slack is divided with the number of jobs that are not scheduled yet. The smaller this ratio is, the higher the priority of the job. The Critical ratio (Cr) rule: According to this rule, operations are scheduled based on the ratio (due date current date)/processing time remaining. If: Cr >1, the job will most likely finish early. If Cr <1, the job might finish late If Cr <0, the job is already late 73

74 Short term planning Input/Output Control Input/Output production control was introduced at first as a method to keep lead times under control. I/O control functions in the following way: WIP level is checked at all resources If WIP is above a predefined level, the amount of released orders is too high and must be reduced If WIP is below a predefined level, the amount of released orders is too low and must be increased If WIP is in between the low and high level thresholds, the amount of released orders is acceptable Reductions and increases of released orders must be performed by altering the MPS 74

75 Short term planning Input/Output Control I/O control is an efficient way to control job release in respect to capacity. However, after WIP levels have increased, the system is most likely out of control. This is why pull systems often perform better than push systems like MRP, MRP II and ERP. While push systems control releases (through MPS) by measuring WIP levels, pull systems measure WIP and production activity on a more frequent basis. As a result, pull systems do not allow WIP levels to become exceedingly high and indicate potential problems 75 fairly quick

Material Requirements Planning. Lecturer: Stanley B. Gershwin

Material Requirements Planning. Lecturer: Stanley B. Gershwin Material Requirements Planning Lecturer: Stanley B. Gershwin MRP Overview Primary source: Factory Physics by Hopp and Spearman. Basic idea: Once the final due date for a product is known, and the time

More information

1 Material Requirements Planning (MRP)

1 Material Requirements Planning (MRP) IEOR 4000: Production Management page 1 Professor Guillermo Gallego 1 Material Requirements Planning (MRP) Material Requirements Planning (MRP) is a computer-based production planning and inventory control

More information

Material Requirements Planning (MRP)

Material Requirements Planning (MRP) Material Requirements Planning (MRP) Unlike many other approaches and techniques, material requirements planning works which is its best recommendation. Joseph Orlicky, 1974 1 History Begun around 1960

More information

Production Planning Solution Techniques Part 1 MRP, MRP-II

Production Planning Solution Techniques Part 1 MRP, MRP-II Production Planning Solution Techniques Part 1 MRP, MRP-II Mads Kehlet Jepsen Production Planning Solution Techniques Part 1 MRP, MRP-II p.1/31 Overview Production Planning Solution Techniques Part 1 MRP,

More information

MASTER PRODUCTION SCHEDULE

MASTER PRODUCTION SCHEDULE 6 MASTER PRODUCTION SCHEDULE MGT2405, University of Toronto, Denny Hong-Mo Yeh So far, in discussing material requirement planning (MRP), we have assumed that master production schedule (MPS) is ready

More information

CHAPTER 6 AGGREGATE PLANNING AND INVENTORY MANAGEMENT 명지대학교 산업시스템공학부

CHAPTER 6 AGGREGATE PLANNING AND INVENTORY MANAGEMENT 명지대학교 산업시스템공학부 CHAPTER 6 AGGREGATE PLANNING AND INVENTORY MANAGEMENT 명지대학교 산업시스템공학부 Learning Objectives You should be able to: Describe the hierarchical operations planning process in terms of materials planning & capacity

More information

MATERIAL REQUIREMENTS PLANNING

MATERIAL REQUIREMENTS PLANNING MATERIAL REQUIREMENTS PLANNING A basic tool for performing the detailed material planning function in the manufacture of component parts and their assembly into finished items. MRP s Managerial objective

More information

Chapter 7. Production, Capacity and Material Planning

Chapter 7. Production, Capacity and Material Planning Chapter 7 Production, Capacity and Material Planning Production, Capacity and Material Planning Production plan quantities of final product, subassemblies, parts needed at distinct points in time To generate

More information

ISE 421 QUANTATIVE PRODUCTION PLANNING

ISE 421 QUANTATIVE PRODUCTION PLANNING ISE 421 QUANTATIVE PRODUCTION PLANNING LECTURE III MRP, MRPII, ERP, APS Dr. Arslan ÖRNEK 2013 2014 Fall Term PRODUCTION PLANNING & SCHEDULING (PP&S) PP&S is one of the most critical activities in a manufacturing

More information

OR topics in MRP-II. Mads Jepsens. OR topics in MRP-II p.1/25

OR topics in MRP-II. Mads Jepsens. OR topics in MRP-II p.1/25 OR topics in MRP-II Mads Jepsens OR topics in MRP-II p.1/25 Overview Why bother? OR topics in MRP-II p.2/25 Why bother? Push and Pull systems Overview OR topics in MRP-II p.2/25 Overview Why bother? Push

More information

Planning Optimization in AX2012

Planning Optimization in AX2012 Planning Optimization in AX2012 Streamline your manufacturing operations with Master Planning and Forecasting Kevin Cosman 11 June 2013 About the Presenter Kevin Cosman, Senior Solutions consultant with

More information

BSCM Sample TEST. CPIM(Certified In Production & Inventory Management) - 1 -

BSCM Sample TEST. CPIM(Certified In Production & Inventory Management) - 1 - BSCM Sample TEST. 1. Which of the following demand fulfillment approaches typically provides the longest delivery time? A) Engineer-to-order. B) Make-to-order. C) Assemble-to-order. D) Make-to-stock. 2.

More information

Material Requirements Planning (MRP)

Material Requirements Planning (MRP) The Priority Enterprise Management System Material Requirements Planning (MRP) Contents MRP - Introduction...2 Calculating Demand for Top-Level Parts...2 Calculating Demand for Sub-assemblies and Raw Materials...3

More information

Universidad del Turabo MANA 705 DL Workshop Eight W8_8_3 Aggregate Planning, Material Requirement Planning, and Capacity Planning

Universidad del Turabo MANA 705 DL Workshop Eight W8_8_3 Aggregate Planning, Material Requirement Planning, and Capacity Planning Aggregate, Material Requirement, and Capacity Topic: Aggregate, Material Requirement, and Capacity Slide 1 Welcome to Workshop Eight presentation: Aggregate planning, material requirement planning, and

More information

Dependent vs Independent Demand. The Evolution of MRP II. MRP II:Manufacturing Resource Planning Systems. The Modules In MRP II System

Dependent vs Independent Demand. The Evolution of MRP II. MRP II:Manufacturing Resource Planning Systems. The Modules In MRP II System MRP II:Manufacturing Resource Planning Systems IE 505: Production Planning Control Lecture Notes* Rakesh Nagi University at Buffalo * Adapted in part from Lecture Notes of Dr. George Harhalakis, University

More information

BILL OF RESOURCES AND PRIORITY-CAPACITY BALANCING

BILL OF RESOURCES AND PRIORITY-CAPACITY BALANCING Bill of Resources and PriorityCapacity Balancing 5 BILL OF RESOURCES AND PRIORITYCAPACITY BALANCING MGT2405, University of Toronto, Denny HongMo Yeh Load and capacity are terms that are often used interchangeably.

More information

PARADIGMS THAT DRIVE COSTS IN MANUFACTURING. The whole purpose of a business enterprise is pretty simple to make a profit by selling

PARADIGMS THAT DRIVE COSTS IN MANUFACTURING. The whole purpose of a business enterprise is pretty simple to make a profit by selling PARADIGMS THAT DRIVE COSTS IN MANUFACTURING The whole purpose of a business enterprise is pretty simple to make a profit by selling products or services to persons who desire those particular goods or

More information

Material Requirements Planning MRP

Material Requirements Planning MRP Material Requirements Planning MRP ENM308 Planning and Control I Spring 2013 Haluk Yapıcıoğlu, PhD Hierarchy of Decisions Forecast of Demand Aggregate Planning Master Schedule Inventory Control Operations

More information

Manufacturing. Manufacturing challenges of today and how. Navision Axapta solves them- In the current explosive economy, many

Manufacturing. Manufacturing challenges of today and how. Navision Axapta solves them- In the current explosive economy, many Manufacturing challenges of today and how Navision Axapta solves them- the solution for change; controlled by you. Manufacturing In the current explosive economy, many manufacturers are struggling to keep

More information

1 2 3 4 5 Demand 150 170 180 160 160

1 2 3 4 5 Demand 150 170 180 160 160 MGT 3110: Exam 2 Study Guide 1. What is aggregate planning? What is its purpose? 2. What are demand options for aggregate planning? Give examples and discuss the effects of each. 3. Why is there a need

More information

TU-E2020 ADVANCED OPERATIONS MANAGEMENT. Demand management Sales & Operations Planning Master Production Scheduling

TU-E2020 ADVANCED OPERATIONS MANAGEMENT. Demand management Sales & Operations Planning Master Production Scheduling TU-E2020 ADVANCED OPERATIONS MANAGEMENT Demand management Sales & Operations Planning Master Production Scheduling 1982 1983 1984 1985 1986 1987 1988 1989 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999

More information

How to Configure and Use MRP

How to Configure and Use MRP SAP Business One How-To Guide PUBLIC How to Configure and Use MRP Applicable Release: SAP Business One 8.8 All Countries English October 2009 Table of Contents Purpose... 3 The MRP Process in SAP Business

More information

An investigation into production scheduling systems

An investigation into production scheduling systems Computer Science Kjell Olofsson An investigation into production scheduling systems D-dissertation (10 p) 2004:06 This report is submitted in partial fulfillment of the requirements for the Master s degree

More information

INDEPENDENT STUDY PAILIN UDOMSANTI

INDEPENDENT STUDY PAILIN UDOMSANTI 1 INDEPENDENT STUDY ERP Comparison : Production Planning and Control Module PAILIN UDOMSANTI An Independent Study submitted in Partial Fulfillment of the requirements For the Degree of Master of Engineering

More information

Short-term Planning. How to start the right operation at the right shop at the right time? Just in Time (JIT) How to avoid waste?

Short-term Planning. How to start the right operation at the right shop at the right time? Just in Time (JIT) How to avoid waste? Short-term Planning Material Requirements Planning (MRP) How to get the right material in the right quantity at the right time? Manufacturing Resource Planning (MRP2) How to start the right operation at

More information

Chapter 7 Production Planning

Chapter 7 Production Planning Production Planning and Control Chapter 7 Production Planning Professor JIANG Zhibin Dr GRANG Na Department of Industrial Engineering & Management Shanghai Jiao Tong University Contents Introduction Master

More information

Master Scheduling and Rough-cut Capacity Planning

Master Scheduling and Rough-cut Capacity Planning Master Scheduling and Rough-cut Capacity Planning SUPPLEMENT D Before studying this supplement you should know or, if necessary, review 1. Capacity management concepts, Chapter 9, pp. 316 322. 2. Work

More information

Operations Management

Operations Management 13-1 MRP and ERP Operations Management William J. Stevenson 8 th edition 13-2 MRP and ERP CHAPTER 13 MRP and ERP McGraw-Hill/Irwin Operations Management, Eighth Edition, by William J. Stevenson Copyright

More information

2.4 Capacity Planning

2.4 Capacity Planning 2.4 Capacity Planning Learning Objectives Explain functions & importance of capacity planning State four techniques for capacity planning Explain capacity planning factor and bill of capacity techniques

More information

Basics of Supply Chain Management (BSCM) Curriculum

Basics of Supply Chain Management (BSCM) Curriculum Basics of Supply Chain Management (BSCM) Curriculum Version 4.0 Session 1 to Supply Chain Management to Manufacturing Role of Manufacturing Global Citizenship Manufacturing Business Model Business Environment

More information

Functional Area Systems Production / Operation Systems

Functional Area Systems Production / Operation Systems ACS-1803 Introduction to Information Systems Instructor: Kerry Augustine Functional Area Systems Production / Operation Systems Lecture Outline 5, Part 2 ACS-1803 Introduction to Information Systems Examples:

More information

26/10/2015. Functional Area Systems Production / Operation Systems. Examples: Functional Area Info Systems. Functional Area Information Systems

26/10/2015. Functional Area Systems Production / Operation Systems. Examples: Functional Area Info Systems. Functional Area Information Systems ACS-1803 Introduction to Information Systems Instructor: Kerry Augustine Functional Area Systems Production / Operation Systems Lecture Outline 5, Part 2 ACS-1803 Introduction to Information Systems Examples:

More information

QAD Enterprise Applications Standard & Enterprise Edition. Training Guide MRP/CRP

QAD Enterprise Applications Standard & Enterprise Edition. Training Guide MRP/CRP QAD Enterprise Applications Standard & Enterprise Edition Training Guide MRP/CRP 70-3220A QAD 2011.1 Standard & Enterprise Edition Lab: Enterprise Edition 2011.1 r01 - Training Workspace: 10USA > 10USACO

More information

ERP(Enterprise Resource Planning) & MRP

ERP(Enterprise Resource Planning) & MRP ERP(Enterprise Resource Planning) & MRP Mr.Vijayakumar S 1 Session Objectives At the end of this session the delegate would have understood ERP ERP example SAP MRP and structure MRP1 & MRPII difference

More information

Manufacturing Applications in Microsoft Dynamics GP 10.0

Manufacturing Applications in Microsoft Dynamics GP 10.0 Manufacturing Applications in Microsoft Dynamics GP 10.0 8817: Manufacturing Applications in Microsoft Dynamics GP 10.0 (4 Days) About this Course This four-day instructor-led course provides students

More information

Product Documentation SAP Business ByDesign 1302. Supply Chain Planning and Control

Product Documentation SAP Business ByDesign 1302. Supply Chain Planning and Control Product Documentation PUBLIC Supply Chain Planning and Control Table Of Contents 1 Supply Chain Planning and Control.... 6 2 Business Background... 8 2.1 Demand Planning... 8 2.2 Forecasting... 10 2.3

More information

INVENTORY MANAGEMENT

INVENTORY MANAGEMENT 7 INVENTORY MANAGEMENT MGT2405, University of Toronto, Denny Hong-Mo Yeh Inventory management is the branch of business management that covers the planning and control of the inventory. In the previous

More information

IT-375 using the 6 th Edition PRODUCTION AND INVENTORY CONTROL CHAPTER 1: INTRODUCTION TO MATERIALS MANAGEMENT

IT-375 using the 6 th Edition PRODUCTION AND INVENTORY CONTROL CHAPTER 1: INTRODUCTION TO MATERIALS MANAGEMENT IT-375 using the 6 th Edition PRODUCTION AND INVENTORY CONTROL CHAPTER 1: INTRODUCTION TO MATERIALS MANAGEMENT What is wealth? GDP = production = profits What is the source of wealth? The conversion process

More information

MED NITC MANUFACTURING REQUIREMENTS PLANNING (MNMRP) SOFTWARE PACKAGE

MED NITC MANUFACTURING REQUIREMENTS PLANNING (MNMRP) SOFTWARE PACKAGE MED NITC MANUFACTURING REQUIREMENTS PLANNING (MNMRP) SOFTWARE PACKAGE A tool for material planning and scheduling of components and subassemblies of assembled products A tool useful for MSME Dr. V. Madhusudanan

More information

Issues in Information Systems Volume 14, Issue 2, pp.353-358, 2013

Issues in Information Systems Volume 14, Issue 2, pp.353-358, 2013 A MODEL FOR SIMULTANEOUS DECISIONS ON MASTER PRODUCTION SCHEDULING, LOT SIZING, AND CAPACITY REQUIREMENTS PLANNING Harish C. Bahl, California State University-Chico, hbahl@csuchico.edu Neelam Bahl, California

More information

CISCM STUDY GUIDE. International Purchasing and Supply Chain Management Institute, 2006 1

CISCM STUDY GUIDE. International Purchasing and Supply Chain Management Institute, 2006 1 CISCM STUDY GUIDE International Purchasing and Supply Chain Management Institute, 2006 1 TABLE OF CONTENTS PART PAGE PART I Materials, Production, Inventory, Logistics, and Supply Chain Management 3 PART

More information

IM 322 Inventory Management

IM 322 Inventory Management IM 322 Inventory Management Chapter 9: Material Requirement Planning -1- Textbook: Donald Waters, Inventory Control and Management, 2 nd ed Chapter Outline Master Scheduling The use of MRP (Material Requirement

More information

Operations Management

Operations Management Operations Management Short-Term Scheduling Chapter 15 15-1 Outline GLOAL COMPANY PROFILE: DELTA AIRLINES THE STRATEGIC IMPORTANCE OF SHORT- TERM SCHEDULING SCHEDULING ISSUES Forward and ackward Scheduling

More information

Key Benefits: Minimize lead times and maximize on-time deliveries to customers. Respond quickly to changes in demand for materials and capacity

Key Benefits: Minimize lead times and maximize on-time deliveries to customers. Respond quickly to changes in demand for materials and capacity Microsoft Business Solutions Axapta Master Planning streamlines your manufacturing processes and supply chain to help you reduce costs and satisfy customer demands. Key Benefits: Minimize lead times and

More information

1.3 ERP System Evolution

1.3 ERP System Evolution 1.3 ERP System Evolution Learning Objectives State the purpose of enterprise resource planning (ERP) systems List the challenges facing the industry List the development stages of the manufacturing planning

More information

Automated Scheduling Methods. Advanced Planning and Scheduling Techniques

Automated Scheduling Methods. Advanced Planning and Scheduling Techniques Advanced Planning and Scheduling Techniques Table of Contents Introduction 3 The Basic Theories 3 Constrained and Unconstrained Planning 4 Forward, Backward, and other methods 5 Rules for Sequencing Tasks

More information

Chapter 11. MRP and JIT

Chapter 11. MRP and JIT Chapter 11 MRP and JIT (Material Resources Planning and Just In Time) 11.1. MRP Even if MRP can be applied among several production environments, it has been chosen here as a preferential tool for the

More information

MOS 3330 Test 2 Review Problems & Solutions

MOS 3330 Test 2 Review Problems & Solutions MOS 3330 Test 2 Review Problems & Solutions General Information Test date, time, location: See the course outline See also the course web site: dan.uwo.ca/courses/3330 Test time conflict (due to having

More information

12 MRP and ERP. Dr. Ron Lembke

12 MRP and ERP. Dr. Ron Lembke 12 MRP and ERP Dr. Ron Lembke Historical Perspective MRP II Manufacturing Resource Planning ERP- Enterprise Resource Planning mrp material requirements planning MRP Crusade (1975) Material Requirements

More information

for Sage 100 ERP Work Order Overview Document

for Sage 100 ERP Work Order Overview Document for Sage 100 ERP Work Order Document 2012 Sage Software, Inc. All rights reserved. Sage Software, Sage Software logos, and the Sage Software product and service names mentioned herein are registered trademarks

More information

SAP APO SNP (Supply Network Planning) Sample training content and overview

SAP APO SNP (Supply Network Planning) Sample training content and overview SAP APO SNP (Supply Network Planning) Sample training content and overview Course Objectives At the completion of this course, you will be able to: Understand the concepts of SNP and supply chain network

More information

Industry Environment and Concepts for Forecasting 1

Industry Environment and Concepts for Forecasting 1 Table of Contents Industry Environment and Concepts for Forecasting 1 Forecasting Methods Overview...2 Multilevel Forecasting...3 Demand Forecasting...4 Integrating Information...5 Simplifying the Forecast...6

More information

A New Approach for Finite Capacity Planning in MRP Environment

A New Approach for Finite Capacity Planning in MRP Environment A New Approach for Finite Capacity Planning in MRP Environment Hong-bum Na 1, Hyoung-Gon Lee 1, and Jinwoo Park 1 1 Dept. of Industrial Engeering / Automation & Systems Research Inst. Seoul National University

More information

TU-E2020. Capacity Planning and Management, and Production Activity Control

TU-E2020. Capacity Planning and Management, and Production Activity Control TU-E2020 Capacity Planning and Management, and Production Activity Control Copyright Jari Laine 11/23/2015 Copyright Jari Laine 11/23/2015 Different capacity planning options 1 4 7 10 13 16 19 22 25 28

More information

Master Production Scheduling

Master Production Scheduling Master Production Scheduling Revised May 7, 2002. mps.doc Author: Dean Ziegler, CPIM Table of Contents Instructions: Search Tips Using Systems2win Word documents Systems2win Copyright Terms How does Master

More information

Manufacturing Efficiency Guide

Manufacturing Efficiency Guide Note: To change the product logo for your ow n print manual or PDF, click "Tools > Manual Designer" and modify the print manual template. Contents 3 Table of Contents 1 Introduction 5 2 What Is Manufacturing

More information

INTRODUCTION. What is Enterprise Resource Planning?

INTRODUCTION. What is Enterprise Resource Planning? 1 INTRODUCTION MGT2405, University of Toronto, Denny Hong-Mo Yeh What is Enterprise Resource Planning? According to the definition given in the APICS Dictionary (American Production and Inventory Control

More information

Operations Management Study Guide

Operations Management Study Guide Operations Management Study Guide Inventory Management Amazon.com example Wanted to be a virtual retailer (no inventory, no warehouse, no overhead) Now, they are one of the largest retailers Obtain knowledge

More information

Production Planning & Control. Chapter 2. Aggregate Planning & Master Production Scheduling. Chapter2 1

Production Planning & Control. Chapter 2. Aggregate Planning & Master Production Scheduling. Chapter2 1 Production Planning & Control Chapter 2 Aggregate Planning & Master Production Scheduling Chapter2 1 Aggregate Planning & Master Production Scheduling W hy Aggregate Planning Is Necessary Fully load facilities

More information

APICS acknowledges the Basics of Supply Chain Management Committee for its contributions in the development of this resource.

APICS acknowledges the Basics of Supply Chain Management Committee for its contributions in the development of this resource. APICS acknowledges the Basics of Supply Chain Management Committee for its contributions in the development of this resource. Jim Caruso, CPIM, CSCP (chair) Carol Bulfer, CPIM James F. Cox, Ph.D., CFPIM,

More information

An Introduction to Capacity Planning

An Introduction to Capacity Planning An Introduction to Capacity Planning JDEdwards OneWorld 2000 What is Capacity Planning for? Capacity Planning, in its various guises, is used to ensure that sufficient capacity is available to accomplish

More information

Material Requirement Planning (MRP) Mohd Yusnurahman Bin Mohd Yuznah

Material Requirement Planning (MRP) Mohd Yusnurahman Bin Mohd Yuznah Material Requirement Planning (MRP) Nur'Ain Binti Yahaya Hazwan Bin Ismail Mohd Yusnurahman Bin Mohd Yuznah Nurhazwani Binti Jaya B050810172 B050810289 B050810294 B050810188 What is MRP? a system that

More information

Expert s Guide to Successful MRP Projects. September 2012

Expert s Guide to Successful MRP Projects. September 2012 September 2012 Ziff Davis Research All Rights Reserved 2012 White Paper Executive Summary For most manufacturers, the planning department performs business critical functions. It is responsible for balancing

More information

Microsoft Dynamics GP. Manufacturing Planning Functions

Microsoft Dynamics GP. Manufacturing Planning Functions Microsoft Dynamics GP Manufacturing Planning Functions Copyright Copyright 2007 Microsoft Corporation. All rights reserved. Complying with all applicable copyright laws is the responsibility of the user.

More information

Agenda. TPPE37 Manufacturing Control. A typical production process. The Planning Hierarchy. Primary material flow

Agenda. TPPE37 Manufacturing Control. A typical production process. The Planning Hierarchy. Primary material flow TPPE37 Manufacturing Control Agenda Lecture 2 Inventory Management 1. Inventory System Defined 2. Inventory Costs 3. Inventory classification 4. Economic order quantity model 5. Newsboy problem 6. Reorder

More information

Alessandro Anzalone, Ph.D. Hillsborough Community College, Brandon Campus

Alessandro Anzalone, Ph.D. Hillsborough Community College, Brandon Campus Alessandro Anzalone, Ph.D. Hillsborough Community College, Brandon Campus 1. Introduction 2. Background and Fundamental Concepts 3. Bills of Material 4. The MRP Explosion 5. Other MRP Issues 6. Potential

More information

Module 5 The R+ Available Stock Calculation

Module 5 The R+ Available Stock Calculation Welcome to Demand Driven Technologies, the home of Replenishment plus and module 5 of our education tutorials Understanding the R+ Available Stock Calculation This module is intended to provide a basic

More information

GESTION DE LA PRODUCTION ET DES OPERATIONS PICASSO EXERCICE INTEGRE

GESTION DE LA PRODUCTION ET DES OPERATIONS PICASSO EXERCICE INTEGRE ECAP 21 / PROD2100 GESTION DE LA PRODUCTION ET DES OPERATIONS PICASSO EXERCICE INTEGRE 2004-2005 Prof : Pierre Semal : semal@poms.ucl.ac.be Assistants : Eléonore de le Court : delecourt@poms.ucl.ac.be

More information

NETWORK BUSINESS SYSTEMS SOFTWARE SYSTEM DOCUMENTATION MANUFACTURING SYSTEM FEATURES

NETWORK BUSINESS SYSTEMS SOFTWARE SYSTEM DOCUMENTATION MANUFACTURING SYSTEM FEATURES NETWORK BUSINESS SYSTEMS SOFTWARE SYSTEM DOCUMENTATION MANUFACTURING SYSTEM FEATURES WORK ORDERS Standard Mfg. vs. Full Mfg./MRP Manufacturing Target date, open date, closed date You can make and buy the

More information

Rough Cut Capacity Planning-(RCCP)-(Case Study)

Rough Cut Capacity Planning-(RCCP)-(Case Study) Advances in Theoretical and Applied Mechanics, Vol. 7, 2014, no. 2, 53-66 HIKARI Ltd, www.m-hikari.com http://dx.doi.org/10.12988/atam.2014.4612 Rough Cut Capacity Planning-(RCCP)-(Case Study) Raqeyah

More information

A DECISION SUPPORT SYSTEM FOR CAPACITY MANAGEMENT. A Senior Project. presented to

A DECISION SUPPORT SYSTEM FOR CAPACITY MANAGEMENT. A Senior Project. presented to A DECISION SUPPORT SYSTEM FOR CAPACITY MANAGEMENT A Senior Project presented to the Faculty of the Industrial and Manufacturing Engineering Department California Polytechnic State University, San Luis

More information

Item Master and Bill of Material

Item Master and Bill of Material 4 Item Master and Bill of Material MGT2405, University of Toronto, Denny Hong Mo Yeh The enterprise resource planning (ERP) system plans and controls all resources in an enterprise. Material requirement

More information

Going Lean the ERP Way

Going Lean the ERP Way Going Lean the ERP Way Somnath Majumdar Abstract: Lean concepts and techniques are widely used all over the world today to eliminate waste in all processes. These are applicable for all organizations,

More information

ERP Course: Production and Materials Management Reading: Chapter 6 from Mary Sumner

ERP Course: Production and Materials Management Reading: Chapter 6 from Mary Sumner ERP Course: Production and Materials Management Reading: Chapter 6 from Mary Sumner Peter Dolog dolog [at] cs [dot] aau [dot] dk 5.2.03 Information Systems September 16, 2008 2 Sales Finished and packaged

More information

Manufacturing Planning and Control for Supp Chain Management

Manufacturing Planning and Control for Supp Chain Management Manufacturing Planning and Control for Supp Chain Management Sixth Edition F. Robert Jacobs Indiana University William L. Berry The Ohio State University (Emeritus) D. Clay Whybark University of North

More information

AGGREGATE & CAPACITY PLANNING

AGGREGATE & CAPACITY PLANNING 7 Ir. Haery Sihombing/IP Pensyarah Fakulti Kejuruteraan Pembuatan Universiti Teknologi Malaysia Melaka AGGREGATE & CAPACITY PLANNING Aggregate Planning Determine the resource capacity needed to meet demand

More information

Functional Area Systems Lecture 5

Functional Area Systems Lecture 5 ACS-1803 Introduction to Information Systems Instructor: David Tenjo Functional Area Systems Lecture 5 1 1. ACCOUNTING TRANSACTION SYSTEMS 2 1 Business Transaction Cycles 3 Business Transaction Cycles

More information

CHAPTER 6: SALES ORDERS

CHAPTER 6: SALES ORDERS Chapter 6: Sales Orders CHAPTER 6: SALES ORDERS Objectives Introduction The objectives are: Review the various forms and list pages for working with sales orders. Determine and apply different sales order

More information

DEVELOPMENT OF LOW COST MRP SOFTWARE FOR A MANUFACTURING,

DEVELOPMENT OF LOW COST MRP SOFTWARE FOR A MANUFACTURING, KOLEJ UNIVERSITI TEKNIKAL KEBANGSAAN MALAYSIA DEVELOPMENT OF LOW COST MRP SOFTWARE FOR A MANUFACTURING, PROCESS Thesis submitted in accordance with the partial requirements of the Kolej Universiti Teknikal

More information

Sage 200 Manufacturing Datasheet

Sage 200 Manufacturing Datasheet Sage 200 Manufacturing Datasheet Sage 200 Manufacturing is a powerful manufacturing solution that enables you to manage your entire supply chain in detail, end to end, giving you the information needed

More information

Management Information Systems

Management Information Systems Faculty of Foundry Engineering Virtotechnology Management Information Systems Classification, elements, and evolution Agenda Information Systems (IS) IS introduction Classification Integrated IS 2 Information

More information

Master Planning The Forgotten, But Vital, Manufacturing Supply Chain Planning Process

Master Planning The Forgotten, But Vital, Manufacturing Supply Chain Planning Process Master Planning The Forgotten, But Vital, Manufacturing Supply Chain Planning Process KEN TITMUSS, CFPIM INTRODUCTION Over the last twelve years the author has presented numerous APICS and SAPICS educational

More information

Visual Planning and Scheduling Systems. A White Paper. Gregory Quinn President Quinn & Associates Inc September 2006 Updated October 2006

Visual Planning and Scheduling Systems. A White Paper. Gregory Quinn President Quinn & Associates Inc September 2006 Updated October 2006 Visual Planning and Scheduling Systems A White Paper By Gregory Quinn President Quinn & Associates Inc September 2006 Updated October 2006 Visual Planning and Visual Scheduling Systems Introduction The

More information

Demand forecasting & Aggregate planning in a Supply chain. Session Speaker Prof.P.S.Satish

Demand forecasting & Aggregate planning in a Supply chain. Session Speaker Prof.P.S.Satish Demand forecasting & Aggregate planning in a Supply chain Session Speaker Prof.P.S.Satish 1 Introduction PEMP-EMM2506 Forecasting provides an estimate of future demand Factors that influence demand and

More information

Inventory: Independent Demand Systems

Inventory: Independent Demand Systems Inventory: Independent Demand Systems Inventory is used in most manufacturing, service, wholesale, and retail activities and because it can enhance profitability and competitiveness. It is widely discussed

More information

NEW MODELS FOR PRODUCTION SIMULATION AND VALIDATION USING ARENA SOFTWARE

NEW MODELS FOR PRODUCTION SIMULATION AND VALIDATION USING ARENA SOFTWARE NEW MODELS FOR PRODUCTION SIMULATION AND VALIDATION USING ARENA SOFTWARE Marinela INŢĂ 1 and Achim MUNTEAN 1 ABSTRACT: Currently, Lean Manufacturing is a recognized topic in many research fields, which

More information

Linear Programming Supplement E

Linear Programming Supplement E Linear Programming Supplement E Linear Programming Linear programming: A technique that is useful for allocating scarce resources among competing demands. Objective function: An expression in linear programming

More information

Realizing the Benefits of Finite Capacity Scheduling to Manage Batch Production Systems

Realizing the Benefits of Finite Capacity Scheduling to Manage Batch Production Systems Presented at the WBF North American Conference Baltimore, MD, USA 30 April - 4 May 2007 67 Alexander Drive PO Box 12277 Research Triangle Park, NC 27709 +1.919.314.3970 Fax: +1.919.314.3971 E-mail: info@wbf.org

More information

ORACLE MANUFACTURING MATERIAL PLANNING FOR PROCESS MANUFACTURING

ORACLE MANUFACTURING MATERIAL PLANNING FOR PROCESS MANUFACTURING ORACLE MANUFACTURING MATERIAL PLANNING FOR PROCESS MANUFACTURING KEY FEATURES MATERIAL PLANNING FOR PROCESS INCLUDES: Material and rough cut capacity planning Multi-level graphical pegging Advanced sourcing

More information

Short-Term Scheduling

Short-Term Scheduling Strategic Implications of By scheduling effectively, companies use assets more effectively and create greater capacity per dollar invested, which, in turn, lowers cost This added capacity and related flexibility

More information

Linear Programming Notes VII Sensitivity Analysis

Linear Programming Notes VII Sensitivity Analysis Linear Programming Notes VII Sensitivity Analysis 1 Introduction When you use a mathematical model to describe reality you must make approximations. The world is more complicated than the kinds of optimization

More information

Choosing Planning & Scheduling solutions for Metals

Choosing Planning & Scheduling solutions for Metals Choosing Planning & Scheduling solutions for Metals White Paper The planning and scheduling of metals production presents special problems because of the complexity of the manufacturing process and the

More information

Production Management

Production Management Production Management Chwen-Tzeng Su, PhD Professor, Department of Industrial Management National Yunlin University of Science & Technology Touliu, Yunlin, Taiwan 640, R.O.C. E-mail: suct@yuntech.edu.tw

More information

SPREADSHEET SIMULATOR FOR INVENTORY MANAGEMENT IN A SUPPLY CHAIN

SPREADSHEET SIMULATOR FOR INVENTORY MANAGEMENT IN A SUPPLY CHAIN SPREADSHEET SIMULATOR FOR INVENTORY MANAGEMENT IN A SUPPLY CHAIN ABSTRACT Sakir Esnaf Istanbul University, Faculty of Business Administration Department of Production Management Avcilar,Istanbul 34850

More information

Business Proposal: Recommendation for Implementation of the SAGE Enterprise Suite. Debbie Miksiewicz. Elaine Kithcart BSA 375. Mr.

Business Proposal: Recommendation for Implementation of the SAGE Enterprise Suite. Debbie Miksiewicz. Elaine Kithcart BSA 375. Mr. Business Proposal: Recommendation for Implementation of the SAGE Enterprise Suite Debbie Miksiewicz Elaine Kithcart BSA 375 Mr. Andrew Mahaney April 17, 2011 Business Proposal 2 Table of Contents Introduction

More information

Manufacturing Planning and Control for Supply Chain Management

Manufacturing Planning and Control for Supply Chain Management Manufacturing Planning and Control for Supply Chain Management APICS/CPIM Certification Edition F. Robert Jacobs Indiana University William L. Berry The Ohio State University (Emeritus) D.ClayWhybark University

More information

Manufacturing Flow Management

Manufacturing Flow Management Manufacturing Flow Management Distribution D Distribution Authorized to Department of Defense and U.S. DoD Contractors Only Aim High Fly - Fight - Win Supply Chain Management Processes Information Flow

More information

Logistics. Presenting Navision Axapta Logistics

Logistics. Presenting Navision Axapta Logistics Logistics Overview Contracts, trade agreements, special pricing and discounts Price and discount management, purchase and sales Inventory, purchase and sales forecasting Forecast evaluation Product development

More information

MGT 3110 - Exam 2 Formulas. Item $ Usage % of $ usage Cumulative % of $ Cumulative % of no. of items Class

MGT 3110 - Exam 2 Formulas. Item $ Usage % of $ usage Cumulative % of $ Cumulative % of no. of items Class Chapter 12 Inventory Management MGT 3110 - Exam 2 Formulas ABC Classification rule: Class A: ~15% of items, 70-80% annual $ usage Class B: ~30% of items, 15-25% annual $ usage Class C: ~55% of items, 5%

More information