Exploring the Accuracy of Existing Effort Estimation Methods for Distributed Software Projects - Two Case Studies

Size: px
Start display at page:

Download "Exploring the Accuracy of Existing Effort Estimation Methods for Distributed Software Projects - Two Case Studies"

Transcription

1 Master Thesis Software Engineering Thesis no: MSE June 2009 Exploring the Accuracy of Existing Effort Estimation Methods for Distributed Software Projects - Two Case Studies Abid Ali Khan Zaka Ullah Muhammad School of Engineering Blekinge Institute of Technology Box 520 SE Ronneby Sweden

2 This thesis is submitted to the School of Computing at Blekinge Institute of Technology in partial fulfillment of the requirements for the degree of Master of Science in Software Engineering. The thesis is equivalent to 20 weeks of full time studies. Contact Information: Authors: Abid Ali Khan Address: Folkparksvägen 19:16, Ronneby, Sweden Zaka Ullah Muhammad Address: Folkparksvägen 22:02, Ronneby, Sweden University advisor: Dr. Darja Šmite Assistant Professor, BTH, School of Computing, SoftCenter, Ronneby School of Computing Blekinge Institute of Technology Box 520 SE Ronneby Sweden Internet : Phone : Fax : ii

3 ABSTRACT The term Globalization brought many challenges with itself in the field of software development. The challenge of accurate effort estimation in GSD is one among them. When talking about effort estimation, the discussion starts for effort estimation methods. There are a number of effort estimation methods available. Existing effort estimation methods used for co-located projects are might not enough capable to estimate effort for distributed projects. This is why; ratio of failure of GSD projects is high. It is important to calibrate existing methods or invent new with respect to GSD environment. This thesis is an attempt to explore the accuracy of effort estimation methods for distributed projects. For this purpose, the authors selected three estimation approaches: COCOMO II, SLIM and ISBSG. COCOMO II and SLIM are two well known effort estimation methods, whereas, ISBSG is used to check the trend of a project depending upon its (ISBSG s) repository. The selection of the methods and approaches was based on their popularity and advantages over other methods/approaches. Two finished projects from two different organizations were selected and analyzed as case studies. The results indicated that effort estimation with COCOMO II deviated % for project A and 9.71% for project B. Whereas, SLIM showed the deviation of 4.17% for project A and % for project B. Thus, the authors concluded that both methods underestimated the effort in the studied cases. Furthermore, factors that might cause deviation are discussed and several solutions are recommended. Particularly, the authors state that existing effort estimation methods can be used for GSD projects but they need calibration by considering GSD factors to achieve accurate results. This calibration will help in process improvement of effort estimation. Keywords: Effort Estimation, Global Software Development (GSD), COCOMO II, SLIM, ISBSG

4 ACKNOWLEDGEMENT First, we are grateful to our creator who blessed us with the abilities to contribute in human knowledge. We would like to express our heartily gratitude for our advisor Dr. Darja Šmite, who always guided and motivated us during this thesis work. Beside an advisor, she used her leadership abilities to encourage and motivate us when we needed it. Whenever we stuck on some issues regarding thesis, she always provided us positive response. She has provided assistance in numerous ways so that we can understand easily. This thesis would not have been possible without her kind support. We are thankful to her for helping us throughout our thesis. We also would like to thankful to Dr. Cidgem Gencel, Peter Vd Stad (QSM) and Christine Green (EDS) for their kind support and providing us valuable information regarding our work. Our sincere thanks also go to our friends and fellows for providing us moral support during our studies. Finally yet importantly, we would like to thank our families for their love, motivation and support that have guided us to achieve this milestone. We dedicate our work to our respective families. ii

5 Contents ABSTRACT...I ACKNOWLEDGEMENT... II 1 INTRODUCTION BACKGROUND PROBLEM DEFINITION AIMS AND OBJECTIVES RESEARCH QUESTIONS RESEARCH OUTCOMES RESEARCH METHODOLOGY Literature Review Empirical Case Studies Data Source Data Analysis VALIDITY THREATS PROJECT MANAGEMENT IN GSD GSD CHALLENGES PROJECT MANAGEMENT IN GSD EFFORT ESTIMATION OBJECTIVES OF EFFORT ESTIMATION EFFORT ESTIMATION METHODS COCOMO II Size estimation Cost Drivers Scale Factors COCOMO II Equation SLIM SLIM Tool CONTINUOUS IMPROVEMENT Reasons for Selecting COCOMO II and SLIM CASE STUDIES PROJECTS OVERVIEW Project A Description Project B Description EFFORT ESTIMATION WITH SELECTED APPROACHES Effort Estimation with COCOMO II Equation for COCOMO II Project A: COCOMO II Project B: COCOMO II Effort Estimation with SLIM Some Facts about SLIM Equations for SLIM Project A: SLIM Project B: SLIM ESTIMATION WITH ISBSG Project A: ISBSG Project B: ISBSG SUMMARY OF CALCULATIONS iii

6 5 ACCURACY OF EFFORT ESTIMATION COMPARISON OF ESTIMATED RESULTS VS ACTUAL EFFORT FACTORS THAT MIGHT CAUSE DEVIATION Project A Project B Comparison of Factors that Might Cause Deviation RELATED WORK RECOMMENDATIONS FOR IMPROVING EFFORT ESTIMATION SUGGESTIONS AND NEW FACTORS INVOLVEMENT FOR GSD Purpose and Process of Calibration DISCUSSION AND CONCLUSIONS RESULTS APPLICABILITY OF DIFFERENT METHODS IN INDUSTRY FUTURE WORK REFERENCES APPENDIX X APPENDIX Y iv

7 LIST OF TABLES Table 1: Cost Drivers COCOMO II Table 2: Analyses of different effort estimation methods [21, 23] Table 3: Selected Effort Estimation Methods [21, 23] Table 4: Actual Effort Project A Table 5: Actual Effort Project B Table 6: Scale Factors Project A Table 7: Cost Drivers (Effort Multiplier) Project A Table 8: Scale Factors Project B Table 9: Cost Drivers (Effort Multiplier) Project B Table 10: Variables and Values for Putnam s Equation Table 11: Analysis and Selection of ISBSG Table 12: SLOC/FP [49] Table 13: Total Functional Size of Studied Projects Table 14: Summer of Calculations with COCOMO II and SLIM Table 15: Summary of Calculations with ISBSG Table 16: Comparison of Estimated Results Vs Actual Effort Table 17: Estimation Results from ISBSG Both Projects Table 18: Factors that might cause deviation All factors Table 19: Factors that might cause deviation Not common in both projects v

8 LIST OF FIGURES Figure 1: Research Outline... 4 Figure 2: Project Management and GSD Factors [50]... 7 Figure 3: Effort Estimation Equation COCOMO II Figure 4: Putnam s Equation for SLIM (Productivity Parameter) [29] Figure 5: Putnam s Equation for SLIM (Effort Estimation) Figure 6: Phase Division Project A Figure 7: Phase Division Project B Figure 8: Putnam s Equation for SLIM with PP showing PI and B value [29] Figure 9: Effort Estimation with ISBSG Project A Figure 10: Effort Estimation with SLIM Project B Figure 11: Comparison of Actual Effort with Estimated from SLIM and COCOMO II Figure 12: Comparison of Actual Calendar Month with Estimated from ISBSG Figure 13: Effort Multipliers Outsourcing Factors for Offshore Outsourcing Software Development [2] Figure 14: Proposed equation for COCOMO II [2] vi

9 Abbreviations GSD Global Software Engineering ISBSG International Software Benchmarking Standards Group RE Requirement Engineering SRS Software Requirements Specification EDS Electronic Data System SLIM Software Life-cycle Model PI Productivity Index MBI Manpower Buildup Index LOC Line Of Code SLOC Source Line of Code PM Person Month EM Effort Multiplier SF Scale Factors QSM Quantitative Software Management COCOMO II Constructive Cost Model SPI Software Process Improvement IEEE Institute of Electrical and Electronic Engineers ACM Association for Computing Machinery HRM Human Resource Management UK United Kingdom PAK Pakistan USA United States of America ISO International Organization for Standardization MS Microsoft vii

10 1 INTRODUCTION 1.1 Background Globalization of the world is on a doorstep, economic growth and rapidly new inventions are forcing the software industry to boost up development speed in order to cope with these challenges. There is a need to globalize software development in order to save the time, cost and resources [1]. Global Software Development (GSD) is a strategy in which the software development is performed beyond the boundaries such as contextual, organizational, cultural, temporal, geographical and political. In GSD the software life cycle activities is distributing among teams across different boundaries [2]. The diverse distribution of the activities among different organizations all over the world causes a number of questions that need to be answered about realization and successful execution of GSD projects. However, there are insufficient tools, techniques and methods available for distributed projects [3]. Software industry is struggling to invent tools, techniques and methods for GSD projects [3]. This is one of the reasons why GSD is still using the same tools, techniques and methods even same practices for effort estimation, which are being used in co-located projects [4]. Effort estimation is a process that estimates necessary effort (cost, time, etc). It is highly important to make accurate/reliable estimates for the project [35, 36] at the beginning [5] to support project planning, and control the project within the budget and schedule [1]. To call a project successful, it has to be on time, in budget and fulfilling the customer s requirements effectively. On time delivery of the project is a burning issue in development organizations [1, 3, 33]. It becomes more difficult when talking about distributed organizations. The complex nature of distributed projects is one of the hurdles in effort estimation due to which organizations fail to estimate accurately. There is a need to overcome these problems. Researchers and software engineering communities are struggling to explore these complexities and their solutions [7, 8, 9]. Researchers have explored the process of software effort estimation extensively in the past couple of decades [4]. Research shows that wrong estimation of effort can lead a project to failure [10]. Wrong estimation of cost reduction tends to fail a project because organizations do not calculate all the risk and cost associated with Outsourcing Development. Statistics show that 60% of GSD projects fail [11]; latest research pointed out this figure as 40% [12]. Research also highlighted that 2 out of 5 international joint-venture project teams show poor performance [13]. That is why, the need of developing tools, techniques and methods, to overcome these failures is a big challenge. Methods like COCOMO II, SLIM, COBRA etc have been developed to facilitate the software development industry [6]. These models have been working and contributing in process improvement [14, 39, 40] and providing help for the planning team. Another research about the regression analysis by Magne Jorgensen [15] explains the accuracy and bias variation of an organizational estimate of software development effort through regression analysis. He collected information about variables that would affect the accuracy or bias of estimates of the performance of the task completed by organization. He concluded, it is possible that the type of formal analysis and regression-based model in some cases, support for human judgment [15, 37, 38]. Estimation of cost and duration is one of the inherent problems and main challenges of the software engineering business. It is difficult for a project manager to give estimate for distributed projects because there are some additional factors involved that should be taken into account when estimating effort. Beside these additional factors, processes of communication and coordination (considerably more effort consuming than in co-located projects) also contribute to the difficulty in estimation of distributed software projects [2]. 1

11 Co-located development practices are frequently being used in the GSD; it is good to use the same practices but the question is, whether the tools, techniques and methods used in co-located development are also efficient for GSD? There are no specific effort estimation methods available for the distributed projects [2]. Distributed projects are using the conventional effort estimation methods. Literature is missing to evaluate and address which effort estimation methods provide accurate results for distributed projects and which lead to faulty results [2]. Literature about the factors affecting accuracy of existing effort estimation methods for distributed projects is also lacking. This thesis is an attempt to explore the accuracy of existing effort estimation methods for GSD projects and investigate the factors affecting their accuracy. 1.2 Problem Definition As stated above, current effort estimation methods used for co-located software projects do not have enough capability to estimate effort and duration accurately for distributed software projects. It results into overly cost and schedule, and most of the projects fail. This is why, it is necessary to find some new methods or calibrate existing methods for distributed software projects. It is required to explore the accuracy of existing effort estimation methods and find the potential improvement alternatives. 1.3 Aims and Objectives The main aim of this thesis project is to explore the accuracy of existing effort estimation methods for distributed software projects. To meet this goal, following objectives are set: Investigation of well known effort estimation methods in software engineering; Collection of empirical data from distributed projects for further analysis; Application of different effort estimation methods; Comparison of results produced by different methods/approaches with the actual effort of investigated projects; Analysis of the results; Comparison of the results from COCOMO II and SLIM with related studies; Improvement suggestions. 1.4 Research Questions Corresponding to the aims and objectives the following are the research questions for this thesis project: Do existing effort estimation methods accurately estimate effort for distributed software projects? Do existing effort estimation methods provide optimistic or pessimistic calculation of the selected studied cases? Which method tends to provide more accurate estimates? In case of deviations, what are the factors that shall be considered when calculating effort for distributed software projects? What could be done for the improvement of effort estimation methods in distributed software projects? 2

12 1.5 Research Outcomes Meeting with above research questions, following outcomes were produced: Analysis of accuracy of effort estimation methods/approaches (COCOMO II, SLIM and ISBSG) for two distributed finished projects; Evaluated trends in deviation of COCOMO II, SLIM and ISBSG effort estimation with actual effort for selected studied cases; List of factors influencing effort estimation in studied cases; Recommendation for Software Process Improvement (SPI) activities in relation to effort estimation for distributed projects; Recommendation with respect to related studies; Hypotheses for future research. 1.6 Research Methodology The research conducted within this thesis was exploratory in nature and based on two case studies. Interviews conducted in order to obtain empirical data considering GSD projects in the studied organizations. A structured questionnaire (See appendix X) was designed and sent to the project manager to let him understand what would be asked during interview. Questionnaire was divided into several parts to collect personal data of the interviewee and, organizational and project information. Following are some main categories defined in questionnaire: Basic Information of Interviewee; General Information about organization and projects/products; Questions regarding finished project and team for that project; Domain related questions; Data related questions. These interviews conducted in a very friendly environment. The authors tried to extract all the related information from interviewee. Project manager helped the authors to fill questionnaire, which was documented later. Afterwards, authors used s and telephonic calls to collect missing data. This collected data was used as an input for analyses, calculations and comparisons later. Actual effort received from organizations, and results from effort estimation methods in this research were compared with each other. These comparisons showed some variation between them. These results were also compared with related scientific studies. From this point, a discussion on deviation of results was started. Factors caused these deviations were also discussed. At last, but not least, suggestions for the involvement of some factors related to distributed environment in existing effort estimation methods were given. This also led towards new hypotheses for future studies. To clear research outline, the authors divided above description in four phases. The following diagram shows the detailed view of research outline. 3

13 Figure 1: Research Outline In phase 1, authors gathered data regarding two finished GSD projects from different organizations. This data consisted of user manuals, SRS documents and size of project in SLOC. Interviews were the main approach for gathering data. The authors performed analyses on gathered data according to the selected effort estimation approaches in phase 2. The estimated results from phase 2 are then compared with actual effort and related studies in phase 3. Phase 4 consisted of analyses of different factors affecting these projects. The authors provided some recommendations according to estimated results and analyses of different affecting factors. At the end, the authors concluded and discussed about outcomes from this research, and provided some hypotheses for future work Literature Review The authors used literature review to have background and current knowledge of effort estimation methods, their pros and cons, and usage in the software industry. This background knowledge helped the authors during empirical case studies. Furthermore, literature review also helped in comparing case studies results with scientific literature. This identified suggestion for the improvement of effort estimation in GSD Empirical Case Studies Data of two finished GSD projects was used in this research project. COCOMO II, SLIM and ISBSG examined with the collected data from the GSD organizations. The authors used collected data as an input for the calculations and found different results. These results compared with different related studies. 4

14 Data Source Scientific literature and the industry were the main sources for this thesis. Online databases were used to gather the scientific research published through IEEE, ACM, and other libraries. Two structured interviews were conducted with project managers of investigated GSD projects. These project managers were highly experienced in the field of software development and of course had vast knowledge for studied cases. These interviews were documented immediately. Both literature review and interviews were used as input for further operations in this thesis Data Analysis The collected data was analyzed according to the objectives of this thesis. The authors analyzed different factors related to COCOMO II, SLIM and ISBSG. These analyses were then described into tabular forms. Investigation was completed on the basis of these analyzed data. Furthermore, these investigations were modeled the possible results and performed further actions such as comparisons, recommendations etc. During analysis, the authors considered all parameters, which helped for the accomplishment of this thesis report. 1.7 Validity Threats As it has mentioned above that the nature of this study was exploratory. The authors investigated two GSD finished projects in order to explore the accuracy of existing effort estimation methods. There were many confidential issues involved for and organization in order to provide the required data for this thesis. Therefore, it was quite difficult to find more case studies in this short period. The authors documented interviewed data before forgetting it. Results gained from these two case studies might not be too strong decision making. However, it showed a trend and authors pointed out some critical issues. It is still needed to validate these results over a number of projects. Furthermore, the case studies organizations were distributed in UK and PAK. It is therefore still required to validate this thesis results in the organizations with different structure and boundaries where the time zone difference is more than eight hours such as Africa, USA, etc. 5

15 2 PROJECT MANAGEMENT IN GSD 2.1 GSD Challenges The phenomenon of Global Software Development (GSD) is taking potential and the importance of GSD boost with the passage of time. GSD offers highly skilled personal with low cost. It is one of the reasons behind shifting software industry from co-located development to GSD. This shifting brought some new challenges in software development. The problems arising from the geographical, temporal and socio-cultural distance are the main challenges for GSD. Lack of formal communication generates misunderstandings in requirements or changes in the requirement specification. Real time contact between the distributed team is more difficult with temporal and geographical difference. Socio-cultural difference leads problems, such as, different opinions about the nature of the software development process. Language problem also discourages employees to online meeting. To avoid this fear he/she prefers to asynchronous communication e.g. etc. However, sometime one cannot express a problem through only words; he needs gesture, body language and pitch [16, 41, 42, 43]. Moreover, the distance and complexity of coordination is directly proportional. As distance increases, the complexity of coordination increases in software development process. This complexity also arise lack of familiarity with remotely located colleagues and increase in communication cost as well. Obviously, trust and teamwork cannot take birth in this situation. GSD environment erg to reduce these complexities also needed to enhance the ability to focus on coordination of resources [16, 17, 44]. There is a need to overcome these challenges and provide useful and common solutions to those challenges. 2.2 Project Management in GSD Because of time zone, geographic and communication differences, the project management is now a great challenge in GSD. Project management seems to be same entity for both co-located and GSD environment and, an experienced project manager can set the project on the success path. Some concealed risks sway project s success. Project managers are advancing and updating themselves according to the new paradigm of GSD. Both (literature and industry) are lacking to provide the standardized approaches, sights of GSD process management and problem solution [18, 45, 46, 47]. Some generic problems and hurdles need to solve and remove. According to [18] conclusion about global project management, it is recommended to overcome problems of communication manner. Employees also hesitate to adopt new means of interactive communications. Switching the personnel between their partners according to task distribution causing problems associated with wrong approach in project process distribution that affects the overall result of the project. There are also some problems of unclear-shared goals in the GSD environment. A project manager has to share this knowledge with the employees and the organizations. Effort estimation is one of important activity of project management. It is closely associated with risk management [50]. For GSD project, risk management requires more intension because there are some additional GSD factors involved. According to [50], GSD factors, e-g multisourcing, geographical distribution, temporal diversity, socio-cultural diversity, linguistic diversity, contextual diversity 6

16 and political & legislative diversity are the main roots for GSD threats that imperial the success of global project. These threats are directly affect the GSD project management activities. These threats reveal the weird nature of GSD project. They also generate a force that develops obstacles in a project. Figure 2 represents the relation of GSD factors, their threats and the effects of these threats on GSD project management. GSD Factors GSD Threats Multisourcing Lack of language skills Geographic Distribution Temporal Diversity Socio-cultural Diversity Terminology difference Lack of joint risk management Linguistic Diversity Contextual Diversity Political and Legislative Diversity Wrong effort estimation Lack of trust Temporal difference Complex project measurement Inconsistency in work practice Figure 2: Project Management and GSD Factors [50] Project managers require significant effort to forecast obvious and hidden risks associated with GSD factors, and perform necessary precautions to overcome challenges associated with these factors to succeed in GSD. All these GSD factors affect project management activities and thus should be taken into account by project managers when estimating project schedule. 7

17 3 EFFORT ESTIMATION 3.1 Objectives of Effort Estimation Effort estimation plays a key role in the field of software engineering. It helps in predicting the effort and duration required for completing a project [9]. Researches show, projects that often exceed, are without planning or using unrealistic approaches to plan their costs and schedules [9, 20, 35]. As the cost and duration of projects continuous to increase, the research attention is now attracting to gain better methods for accurate effort estimation. Accurate software project estimation is one of the most important activities in software development that can solve the problems of delays in projects [20, 35, 48]. It is much difficult to plan and control projects without an effective and strong estimate, in terms of effort and schedule indicating the calendar time required. Therefore, it is necessary to estimate effort for software development projects to set deadline and cost to meet quality. Projects history helps in estimation for new projects and it ensures positive results [20]. It also involves the expertise of estimators that lead towards good results. 3.2 Effort Estimation Methods In this section, two well-known effort estimation methods (COCOMO II and SLIM), used for analyzing data from finished projects in this thesis, are described. Furthermore, the authors also provided some reasons for selecting these methods COCOMO II COCOMO II is an extension to COCOMO 81, originally published in Software Engineering Economics by Dr. Barry Boehm [21] in The word COCOMO derived from COnstructive COst MOdel. This is widely used method for estimating cost and schedule for the projects at early stages. It helps to make software implication decisions. It estimates project cost, derived directly from Person Month (PM) effort. PM is number of hours a person spends on working for software development project in a calendar month. Its nominal value is defined as 152 hours for one person in a calendar month. 160 person-hours are also treated as one PM [20]. Excluding weekends and leaves, allowed in one calendar month, calculate these hours. COCOMO II estimates effort in PM. Keep remembering, PM and duration of project are different from each other. For example, if a project is estimated for 20 PM, it can have 5 months duration [20]. COCOMO II has a well-described structure for estimating necessary effort and duration of projects. It mainly uses size of project i.e. Source Lines Of Codes (SLOC) or Function Points (FP). Many organizations are now using FP as an input for estimating effort in COCOMO II [27]. COCOMO II deals with a large variety of factors, which influence the estimation of project. It has 17 cost drivers (for post architecture model) and 5 scale factors. Scale factors introduced in COCOMO II, were not available in COCOMO 81[20, 22]. There are three sub models for COCOMO II: Application Composition Model; Post Architecture Model; Early Design Model. 8

18 The projects that use Integrated Computer Aided Software Engineering tools are mostly estimated for effort and schedule by using Application Composition Model. Rapid application development uses these tools. Furthermore, these tools also support prototype activities occurring later in spiral model [22]. The Early Design and Post Architecture models are used to estimate effort and schedule for the projects like software infrastructure, embedded systems and large applications [20]. When there is incomplete project analysis, early design model is used for rough estimation. Whereas post-architecture model is used when analysis and top-level design of project is completed and know detailed information about project [20]. Post Architecture and Early Design models use the same approach to find the size of project and scale factors as well. Reusing code and other data from previous projects is also included in product sizing [20] Size estimation Size of software is direct input to calculate effort and schedule estimation in COCOMO II. It becomes very important for reliable estimation. Sizing is a difficult task because it includes new and reused code and modified code. In COCOMO II, aggregate size is used for new and reused code with updates. These adjustments take into account by considering amount of design, code and testing changes. There are two main types of size used in COCOMO II for effort and schedule estimation [20]: Source Lines Of Code (SLOC); Function Points (FP) Cost Drivers COCOMO II enhanced and added more cost drivers as compared with COCOMO 81. These cost drivers are divided into four categories for The Post-Architecture Model, the sub model of COCOMO II. Table 1 shows the cost drivers used in The Post-Architecture Model [20]. Product Factors Platform Factors Personnel Factors Project Factors Required Reusability Execution Time Analyst Capability Use of Software (RELY) Constraint (TIME) (ACAP) Tools (TOOL) Database Size (DATA) Main Storage Constraint (STOR) Programming Capability (PCAP) Multisite Development (SITE) Product Complexity (CPLX) Platform Volatility (PVOL) Application Experience (APEX) Scheduling Factor (SCED) Developed for Reusability (RUSE) Platform Experience (PLEX) Documentation match to life-cyclemodel (DOCU) Personal Continuity (PCON) 9

19 Language & Tools Experience (LTEX) Table 1: Cost Drivers COCOMO II Scale Factors These factors were not available in COCOMO 81 and included later in COCOMO II. These scale factors let the effort estimation team to make better approximation of influencing factors. These factors are related to organizational and team characteristics. Each scale factor has values from range of very low to extra high rating level. Each rating level has a weight/value. The weight of scaling factors for different organizations and projects could be different. Following are the scaling factors in COCOMO II [20]: Precedentedness (PREC); Development Flexibility (FLEX); Architecture/ Risk Resolution (RESL); Team Cohesion (TEAM); Process Maturity (PMAT) COCOMO II Equation The basic equation for COCOMO II is shown as figure 3 [20, 28]; Figure 3: Effort Estimation Equation COCOMO II Where A = 2.94 (for COCOMO II), size is Kilo Source Lines Of Code (KSLOC), EM i is Effort Multiplier, which can be calculated from cost drivers in COCOMO II E is used to calculate Scale Factors (SF) in COCOMO II. Formula for E is; E = B+ 0.01* SF j (j= 1 to 5) Where B = 0.91 for COCOMO II [20] Cost drivers are given in table 1 Equation for duration in COCOMO II is [20, 28] Duration = [C* (PM NS ) (D+0.2*(E-B)) ] Where C = 3.67, D = 0.28, B = 0.91 and PM NS is effort in PM excluding SCED cost driver PM NS = a * Size b * Π EM i (i= 1 to 16) 10

20 3.2.2 SLIM SLIM is another algorithmic method used to estimate effort and schedule of projects. SLIM stands for Software LIfe-cycle Model and is introduced by Putnam [23]. It was developed for measuring the general size of project based on its estimated SLOC. Later, it was modified for effort estimation using Rayleigh curve model [23]. Equation I (Figure 4) is use to find the productivity parameter (PP). PP is use to calculate the effort in man-years. Equation II (Figure 4) is used to calculate effort, using value of PP from equation I. Figure 4: Putnam s Equation for SLIM (Productivity Parameter) [29] Eq. I This implies that: Figure 5: Putnam s Equation for SLIM (Effort Estimation) Eq. II Where B is special skill factor PP is productivity parameter Duration is development schedule length in years Size is Source Lines Of Code SLIM Tool SLIM tool is the product of SLIM (for the proprietary of Putnam s model) which is metrics-based estimation tool, developed by Quantitative Software Management (QSM), using validated data of over 2600 projects. These projects were classified into nine different application categories. This tool helps the management to estimate the effort and time required to build medium and large software projects. The most important thing is that it can be customized for a specific organization [24]. There are two main management indicators, Productivity Index (PI) and Manpower Buildup Index (MBI). PI could be taken as process productivity. PI values were observed from 0.1 to 34, whereas its values were given 0.1 to 40.0 in SLIM tool by QSM to overcome future contingencies. A high PI value means that project s productivity is high and it is low complex. In case of PI having values below average implies 10% more development time and 30 % more cost. Second important indicator MBI is measure of staff buildup rate. Some factors, by which MBI is influenced, are schedule pressure, task concurrency and resource constraints. Its values are observed in the range of -3 to 10. A low MBI value implies [24]: 11

21 Longer time; Fewer people; Less effort; Fewer defects; Fewer LOC/month; Higher LOC/PM. The following are steps involved in effort estimation using SLIM tool [24]: First of all estimate product size; Select/analyze the PI and MBI values for this project; Get minimum time for solution; Determine alternative solution for time-effort-cost; Chose your desired solution; At the end, generate project plan from the chosen solution. 3.3 Continuous Improvement Consideration about calibration is very important when talking about estimation. Calibration is a technique that allows application of a general model to a specific set of data. Some of the case studies have shown that calibration is important for estimation because of the following reasons [22, 25]: Size of the project and its relation with effort, which are used in different methods for estimation, could be different for different environments (skills of coding, tools used, platform understandability etc). There could be high risk involved when using generic algorithms due to its contrast with organization structure and working Calibration is important because, in particular, organizational needs and availability of data varies Historical data about completed project plays integral role in effort estimation. However, it is important to calibrate the historical data accordingly before using it for estimation [34]. There are some factors that influence calibration such as; similar projects executed in past, features of finished project, and the complexity of the software to be developed [25, 26]. It is important for organizations to determine whether their estimates arrived at, for a project are realistic or not. This could be done by validating estimates against completed project data, which would describe the correctness/accuracy of estimates. It is also required to make sure to consider current development environment with respect to previously completed projects [26]. Calibration of co-located project experience would be helpful for GSD projects. Every organization might have their calibrated estimation models. Even in one organization there might be different models used for different kind of projects. Methodology may remains the same but some influencing factors might vary from project to project, thus calibration becomes very important [26, 31]. Organizations have many past-completed projects data. It would be beneficial to use that data to estimate effort and duration for new projects. In general, existing effort estimation methods required to calibrate by the addition/involvement of some new factors related to GSD environment etc. 12

22 There is also a need to introduce new tools and techniques for the calibration of existing effort estimation methods. Dynamic tools and techniques are one in this regard [31, 32] Reasons for Selecting COCOMO II and SLIM There are a number of methods used for effort estimation. In this thesis, two wellknown methods (COCOMO II and SLIM) were used. The authors investigated and analyzed different effort estimation methods. Table 2 shows the analyses of different effort estimation methods for software projects. The authors analyzed these methods by considering different reasons and objectives for selection. Methods Reasons Availability of literature Availability of tools Coverage of parameters Used for Early estimation COCOMO II Many Free tools available More than 17 cost drivers and 5 very important scale factors SLIM Sufficient, some are not free. Yes, but most of the tools are not free. 2 main parameters such as MBI and PP Expert Judgment Available but not sufficient Not specific Depends on expert Analogy Parkinson Price to Win Top Down Bottom- Up satisfactory Few Few Few Few Few - Not specific Depends on the nature of the project, which has to be compared with. - Varies accordingly Not specific Varies accordingly Yes Yes Yes Yes Yes Yes Yes Yes Algorithmic Yes Yes No No No No No No Widely Yes Yes Yes No No No No No Used Possible to calibrate - Yes - - Yes Yes Yes, different factors are available according to situations. Yes, According to QSM Table 2: Analyses of different effort estimation methods [21, 23] After analyses, the authors selected two effort estimation methods (COCOMO II and SLIM) to find their accuracy for selected cases. Both selected methods have many advantages over other methods. Table 3 shows specifically some common objectives of COCOMO II and SLIM. Not specific Varies accordingly 13

23 Methods COCOMO II SLIM Reasons Availability of literature Many Sufficient, some are not free Availability of tools Free tools available Yes, but most of the tools are not free Coverage of parameters More than 17 cost drivers 2 main parameters such as and 5 very important scale MBI and PP factors Used for early estimation Yes Yes Algorithmic Yes Yes Widely used Yes Yes Possible to calibrate Yes, different factors are Yes, According to QSM available according to situations Table 3: Selected Effort Estimation Methods [21, 23] 14

24 4 CASE STUDIES 4.1 Projects Overview After the literature review of both methods, the authors selected two different organizations for data collection. Exchanging s and online interviews ensured the data collection process. Parameters of both methods were considered during the interviews to elicit data according to these parameters. Some other necessary data, such as delay factors and suggestion for improvement from the project manager are also considered in this regard Project A Description Name: Workforce Evaluation Tool The Workforce Evaluation Tool offers an online balance scorecard, helping users to assess changes in workforce practice. It enables organizations to calculate performance in four key perspectives workforce, customer, service, and finance. The tool offers a visual representation of the performance in the aforementioned perspectives, and alerts best and the worst performance indicators. Data collection process was very difficult because of time constraint and unavailability of concerned person. Confidentiality was another issue in this regard. There was also a problem of lack of documentation. Although, the studied organization is ISO 9001:2008 and ISO certified, and also a Microsoft Gold Certified partner, it was observed that the organization is lacking to follow formal steps of software life cycle e.g. documentation and record keeping. An online interview was conducted to discuss the questionnaire and extract some more information related to the project. Interview session was of one and half hours long. A series of s exchanged later to remove the ambiguity from the gathered data. Interview information then documented and arranged in a readable and understandable form. This data was used as input to the both of the methods. Studied project was initially estimated through expert judgment, which estimated three calendar months to finish, but it delayed. Actual completion time of the project was four calendar months. According to the project manager, the development team consisted of 7 persons. The project manager also provided the duration spent on each activity, which helped the authors in finding the actual effort in person months, which was 14.4 person months. There were two locations involved in this project. The project activity distribution was organized as follows. Requirement engineering and deployment performed in the onshore (UK) office of the organization, whereas designing, coding, technical writing and testing performed in the offshore (PAK) office. There was no specific designation for project manager explicitly in this project, and requirement analyzer worked for project management activities. Figure 6 shows the pictorial representation of phases of the project. Table 4 provides detailed distribution of effort spent on each activity. 15

25 Figure 6: Phase Division Project A Phase Number of Person Hours Person Days Persons Requirements Engineering Design Coding Testing Technical Writing Total = person months Table 4: Actual Effort Project A 16

26 4.1.2 Project B Description Name: Computerized account system Computerized account system was an application for accounts system. It facilitated the organization in multi dimensional ways, such as record keeping, inventory, sales, reports etc. This project was built to convert the organizational manual account system into computerize. The client was using a manual record keeping procedure. The client decided to convert their manual record into computerized account system to get benefits from the modern technology. The duration of this project was estimated four calendar months by expert judgment, but it delayed one and half calendar months. Therefore, the total development period of this project was five and half calendar months. The authors used same strategy as for project A for the data collection process. This time, the authors were more prepared for data collection because of previous experience in project A. That is why, data collection time for project B was short as compare to project A. Online interview was arranged with project manager. The same questionnaire was used to gather data. According to the data provided by the organization, it was seventeen person months project. The team of this project consisted on six persons. During the interview, different issues and delay factors were discussed. Like project A, same agenda was strictly followed for data collection. Data was collected according to the requirements and methods parameters. The authors then organized data and discussed all the ambiguities with concerned person through s. This data was used for further process. Figure 7 shows the pictorial representation of phases of the project. Table 5 provides detailed time spent on each activity. Figure 7: Phase Division Project B Phase Number of Person Hours Person Days Persons Project Management Requirement Engineering Design + Technical Writing Coding + Deployment Testing Total = person months Table 5: Actual Effort Project B 17

27 4.2 Effort Estimation with Selected Approaches Effort Estimation with COCOMO II Equation for COCOMO II As already discussed above that COCOMO II model estimates the required effort (in Person-Months) based on size of software project. This size is calculated into thousands source lines of code (KSLOC) of software project. The size collected from organization is supposed to be effected SLOC, excluding blank spaces and comments. Studied organizations ensured that they calculated SLOC using specific tools. Following is the formula to estimate effort in PM for COCOMO II; Effort (PM) = A * Size E * Π EM i (i= 1 to 17)... (1), where A = 2.94 (for COCOMO II) EM i is effort multiplier; one can calculate it by multiplying all cost drivers values related to that project, with each other. E is the exponent derived from five scale factors. Its equation is as follows; E = B+ 0.01* SF j (j= 1 to 5). (2), where B = 0.91 (for COCOMO II) SF j is scale factor introduced in COCOMO II and mostly contain organizational and project team characteristics. It is calculated by adding all five-scale factor values. For both cases, values for scale factors and cost drivers were analyzed using interviews data, studying organizational characteristics, expert judgment etc. For these factors, organizations are contacted several times. Equation to find duration of project is as follows; Duration = [C* (PM NS ) (D+0.2*(E-B)) ]. (3), where C = 3.67, D = 0.28, B = 0.91 and PM NS is effort in PM excluding SCED cost driver. It means that one needs to calculate PM but he should not use SCED cost driver value for multiplication and in this way, result will be called PM NS. i-e PM NS = A * Size E * Π EM i (i= 1 to 16). (4) Project A: COCOMO II Table 6 and 7 show selected scale factors and cost drivers values for project A respectively. Some of the scales were gathered during interviews and remaining was selected by studying the organizational characteristics. 18

28 Scale Factors Value Precedentedness (PREC) Very high: 1.24 Development Flexibility (FLEX) High: 2.03 Architecture / Risk Resolution (RESL) High: 2.83 Team Cohesion (TEAM) Nominal: 3.29 Process Maturity (PMAT) High: 3.14 Table 6: Scale Factors Project A Effort Multiplier Value Product Factors Required Software Reliability (RELY) Nominal: 1.00 Data Size (DATA) N/A Develop for Reuse (RUSE) Nominal: 1.00 Documentation match to life-cycle needs (DOCU) Nominal: 1.00 Product Complexity (CPLX) Low : 0.87 Platform Cost Drivers Execution Time Constraint (TIME) N/A Main Storage Constraint (STOR) N/A Platform Volatility (PVOL) Low : 0.87 Personal Cost Drivers Analyst Capability (ACAP) High : 0.85 Programmer Capability (PCAP) High : 0.88 Applications Experience (APEX) Very High : 0.81 Platform Experience (PLEX) Very High : 0.85 Language and Tool Experience (LTEX) Very High : 0.85 Personnel Continuity (PCON) N/A Project Cost Drivers Use of Software Tools (TOOL) Very High : 0.78 Multisite Development (SITE) Very Low : 1.22 Required Development Schedule (SCED) Low : 1.14 Table 7: Cost Drivers (Effort Multiplier) Project A N/A means that values for this effort multiplier are not applicable in studied project. To solve equation 1 using gathered data for effort estimation, E was calculated first. This value of E was used in effort estimation equation for COCOMO II. E = *12.53 E= Final estimation of effort based on E and the given cost drivers values are as follows; Effort (PM) = 2.94* (10.537) * Effort (PM) = 12.1PM 19

29 Above result shows, effort required for this project is approximately equal to 12.1 Person-Months. 4; Duration of the project is calculated by providing related values to equation 3 and i.e. PM NS = 2.94 * ( ) * PM NS = PM Duration = [3.67* (10.61) ( *( )) ] Duration = 7.54 While executing the gathered data with COCOMO II, it is found that 12.1 PM effort was required to complete this project. Excluding SCED factor from effort, duration is calculated as 7.54 months. This shows that an effort of 12.1 Person Months was required to complete project A with duration of 7.54 months Project B: COCOMO II Table 8 and 9 show scale factors and cost drivers values for project B respectively. Same strategy (as in project A) was used to gather scales/values for cost drivers and scales factors and Scale Factors Value Precedentedness (PREC) Very High : 1.24 Development Flexibility (FLEX) Very High : 1.01 Architecture / Risk Resolution (RESL) Very High : 1.41 Team Cohesion (TEAM) High : 2.19 Process Maturity (PMAT) High: 3.14 Table 8: Scale Factors Project B Effort Multiplier Value Product Factors Required Software Reliability (RELY) Very Low: 0.82 Data Size (DATA) N/A Develop for Reuse (RUSE) Low: 0.95 Documentation match to life-cycle needs (DOCU) Low: 0.91 Product Complexity (CPLX) Low : 0.87 Platform Cost Drivers Execution Time Constraint (TIME) N/A Main Storage Constraint (STOR) N/A Platform Volatility (PVOL) Low : 0.87 Personal Cost Drivers Analyst Capability (ACAP) High : 0.85 Programmer Capability (PCAP) High : 0.88 Applications Experience (APEX) Very High : 0.81 Platform Experience (PLEX) Very High : 0.85 Language and Tool Experience (LTEX) Very High :

MTAT.03.244 Software Economics. Lecture 5: Software Cost Estimation

MTAT.03.244 Software Economics. Lecture 5: Software Cost Estimation MTAT.03.244 Software Economics Lecture 5: Software Cost Estimation Marlon Dumas marlon.dumas ät ut. ee Outline Estimating Software Size Estimating Effort Estimating Duration 2 For Discussion It is hopeless

More information

Extending Change Impact Analysis Approach for Change Effort Estimation in the Software Development Phase

Extending Change Impact Analysis Approach for Change Effort Estimation in the Software Development Phase Extending Change Impact Analysis Approach for Change Effort Estimation in the Software Development Phase NAZRI KAMA, MEHRAN HALIMI Advanced Informatics School Universiti Teknologi Malaysia 54100, Jalan

More information

CSSE 372 Software Project Management: Software Estimation With COCOMO-II

CSSE 372 Software Project Management: Software Estimation With COCOMO-II CSSE 372 Software Project Management: Software Estimation With COCOMO-II Shawn Bohner Office: Moench Room F212 Phone: (812) 877-8685 Email: bohner@rose-hulman.edu Estimation Experience and Beware of the

More information

Software Migration Project Cost Estimation using COCOMO II and Enterprise Architecture Modeling

Software Migration Project Cost Estimation using COCOMO II and Enterprise Architecture Modeling Software Migration Project Cost Estimation using COCOMO II and Enterprise Architecture Modeling Alexander Hjalmarsson 1, Matus Korman 1 and Robert Lagerström 1, 1 Royal Institute of Technology, Osquldas

More information

Software cost estimation. Predicting the resources required for a software development process

Software cost estimation. Predicting the resources required for a software development process Software cost estimation Predicting the resources required for a software development process Ian Sommerville 2000 Software Engineering, 6th edition. Chapter 23 Slide 1 Objectives To introduce the fundamentals

More information

Cost Estimation Driven Software Development Process

Cost Estimation Driven Software Development Process Cost Estimation Driven Software Development Process Orsolya Dobán, András Pataricza Budapest University of Technology and Economics Department of Measurement and Information Systems Pázmány P sétány 1/D

More information

Topics. Project plan development. The theme. Planning documents. Sections in a typical project plan. Maciaszek, Liong - PSE Chapter 4

Topics. Project plan development. The theme. Planning documents. Sections in a typical project plan. Maciaszek, Liong - PSE Chapter 4 MACIASZEK, L.A. and LIONG, B.L. (2005): Practical Software Engineering. A Case Study Approach Addison Wesley, Harlow England, 864p. ISBN: 0 321 20465 4 Chapter 4 Software Project Planning and Tracking

More information

Finally, Article 4, Creating the Project Plan describes how to use your insight into project cost and schedule to create a complete project plan.

Finally, Article 4, Creating the Project Plan describes how to use your insight into project cost and schedule to create a complete project plan. Project Cost Adjustments This article describes how to make adjustments to a cost estimate for environmental factors, schedule strategies and software reuse. Author: William Roetzheim Co-Founder, Cost

More information

Effect of Schedule Compression on Project Effort

Effect of Schedule Compression on Project Effort Effect of Schedule Compression on Project Effort Ye Yang, Zhihao Chen, Ricardo Valerdi, Barry Boehm Center for Software Engineering, University of Southern California (USC-CSE) Los Angeles, CA 90089-078,

More information

Fuzzy Expert-COCOMO Risk Assessment and Effort Contingency Model in Software Project Management

Fuzzy Expert-COCOMO Risk Assessment and Effort Contingency Model in Software Project Management Western University Scholarship@Western Electronic Thesis and Dissertation Repository April 2013 Fuzzy Expert-COCOMO Assessment and Effort Contingency Model in Software Project Management Ekananta Manalif

More information

Software cost estimation

Software cost estimation Software cost estimation Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 26 Slide 1 Objectives To introduce the fundamentals of software costing and pricing To describe three metrics for

More information

CISC 322 Software Architecture

CISC 322 Software Architecture CISC 322 Software Architecture Lecture 20: Software Cost Estimation 2 Emad Shihab Slides adapted from Ian Sommerville and Ahmed E. Hassan Estimation Techniques There is no simple way to make accurate estimates

More information

COCOMO-SCORM Interactive Courseware Project Cost Modeling

COCOMO-SCORM Interactive Courseware Project Cost Modeling COCOMO-SCORM Interactive Courseware Project Cost Modeling Roger Smith & Lacey Edwards SPARTA Inc. 13501 Ingenuity Drive, Suite 132 Orlando, FL 32826 Roger.Smith, Lacey.Edwards @Sparta.com Copyright 2006

More information

COCOMO II and Big Data

COCOMO II and Big Data COCOMO II and Big Data Rachchabhorn Wongsaroj*, Jo Ann Lane, Supannika Koolmanojwong, Barry Boehm *Bank of Thailand and Center for Systems and Software Engineering Computer Science Department, Viterbi

More information

Software Development Cost and Time Forecasting Using a High Performance Artificial Neural Network Model

Software Development Cost and Time Forecasting Using a High Performance Artificial Neural Network Model Software Development Cost and Time Forecasting Using a High Performance Artificial Neural Network Model Iman Attarzadeh and Siew Hock Ow Department of Software Engineering Faculty of Computer Science &

More information

Identifying Factors Affecting Software Development Cost

Identifying Factors Affecting Software Development Cost Identifying Factors Affecting Software Development Cost Robert Lagerström PhD Student at Industrial Information and Control Systems School of Electrical Engineering KTH Royal Institute of Technology Stockholm,

More information

Software Engineering. Dilbert on Project Planning. Overview CS / COE 1530. Reading: chapter 3 in textbook Requirements documents due 9/20

Software Engineering. Dilbert on Project Planning. Overview CS / COE 1530. Reading: chapter 3 in textbook Requirements documents due 9/20 Software Engineering CS / COE 1530 Lecture 4 Project Management Dilbert on Project Planning Overview Reading: chapter 3 in textbook Requirements documents due 9/20 1 Tracking project progress Do you understand

More information

Chapter 23 Software Cost Estimation

Chapter 23 Software Cost Estimation Chapter 23 Software Cost Estimation Ian Sommerville 2000 Software Engineering, 6th edition. Chapter 23 Slide 1 Software cost estimation Predicting the resources required for a software development process

More information

Project Plan. Online Book Store. Version 1.0. Vamsi Krishna Mummaneni. CIS 895 MSE Project KSU. Major Professor. Dr.Torben Amtoft

Project Plan. Online Book Store. Version 1.0. Vamsi Krishna Mummaneni. CIS 895 MSE Project KSU. Major Professor. Dr.Torben Amtoft Online Book Store Version 1.0 Vamsi Krishna Mummaneni CIS 895 MSE Project KSU Major Professor Dr.Torben Amtoft 1 Table of Contents 1. Task Breakdown 3 1.1. Inception Phase 3 1.2. Elaboration Phase 3 1.3.

More information

Project Plan 1.0 Airline Reservation System

Project Plan 1.0 Airline Reservation System 1.0 Airline Reservation System Submitted in partial fulfillment of the requirements of the degree of Master of Software Engineering Kaavya Kuppa CIS 895 MSE Project Department of Computing and Information

More information

Keywords Software Cost; Effort Estimation, Constructive Cost Model-II (COCOMO-II), Hybrid Model, Functional Link Artificial Neural Network (FLANN).

Keywords Software Cost; Effort Estimation, Constructive Cost Model-II (COCOMO-II), Hybrid Model, Functional Link Artificial Neural Network (FLANN). Develop Hybrid Cost Estimation For Software Applications. Sagar K. Badjate,Umesh K. Gaikwad Assistant Professor, Dept. of IT, KKWIEER, Nasik, India sagar.badjate@kkwagh.edu.in,ukgaikwad@kkwagh.edu.in A

More information

Software cost estimation

Software cost estimation Software cost estimation Sommerville Chapter 26 Objectives To introduce the fundamentals of software costing and pricing To describe three metrics for software productivity assessment To explain why different

More information

Safe and Simple Software Cost Analysis Barry Boehm, USC Everything should be as simple as possible, but no simpler.

Safe and Simple Software Cost Analysis Barry Boehm, USC Everything should be as simple as possible, but no simpler. Safe and Simple Software Cost Analysis Barry Boehm, USC Everything should be as simple as possible, but no simpler. -Albert Einstein Overview There are a number of simple software cost analysis methods,

More information

A Comparative Evaluation of Effort Estimation Methods in the Software Life Cycle

A Comparative Evaluation of Effort Estimation Methods in the Software Life Cycle DOI 10.2298/CSIS110316068P A Comparative Evaluation of Effort Estimation Methods in the Software Life Cycle Jovan Popović 1 and Dragan Bojić 1 1 Faculty of Electrical Engineering, University of Belgrade,

More information

Safety critical software and development productivity

Safety critical software and development productivity Preprint for conference proceedings for The Second World Congress on Software Quality, Yokohama, Sept 25.- 29, 2000. http://www.calpoly.edu/~pmcquaid/2wcsq Safety critical software and development productivity

More information

Software Project Planning - The Relationship between Project Planning and Project Success.

Software Project Planning - The Relationship between Project Planning and Project Success. Master Thesis Software Engineering Thesis no: MSE-2004-30 August 2004 Software Project Planning - The Relationship between Project Planning and Project Success. Andreas Ljungquist & Björn Rosander School

More information

An Introduction to. Metrics. used during. Software Development

An Introduction to. Metrics. used during. Software Development An Introduction to Metrics used during Software Development Life Cycle www.softwaretestinggenius.com Page 1 of 10 Define the Metric Objectives You can t control what you can t measure. This is a quote

More information

Project Planning and Project Estimation Techniques. Naveen Aggarwal

Project Planning and Project Estimation Techniques. Naveen Aggarwal Project Planning and Project Estimation Techniques Naveen Aggarwal Responsibilities of a software project manager The job responsibility of a project manager ranges from invisible activities like building

More information

Universiteit Leiden. ICT in Business. Leiden Institute of Advanced Computer Science (LIACS) Capability Maturity Model for Software Usage

Universiteit Leiden. ICT in Business. Leiden Institute of Advanced Computer Science (LIACS) Capability Maturity Model for Software Usage Universiteit Leiden ICT in Business Capability Maturity Model for Software Usage Name: Yunwei Huang Student-no: s1101005 Date: 16/06/2014 1st supervisor: Dr. Luuk Groenewegen 2nd supervisor: Dr. Nelleke

More information

Cost Estimation Strategies COST ESTIMATION GUIDELINES

Cost Estimation Strategies COST ESTIMATION GUIDELINES Cost Estimation Strategies Algorithmic models (Rayleigh curve Cost in week t = K a t exp(-a t 2 ) Expert judgment (9 step model presented later) Analogy (Use similar systems) Parkinson (Work expands to

More information

Software cost estimation

Software cost estimation CH26_612-640.qxd 4/2/04 3:28 PM Page 612 26 Software cost estimation Objectives The objective of this chapter is to introduce techniques for estimating the cost and effort required for software production.

More information

Incorporating Data Mining Techniques on Software Cost Estimation: Validation and Improvement

Incorporating Data Mining Techniques on Software Cost Estimation: Validation and Improvement Incorporating Data Mining Techniques on Software Cost Estimation: Validation and Improvement 1 Narendra Sharma, 2 Ratnesh Litoriya Department of Computer Science and Engineering Jaypee University of Engg

More information

University of Southern California COCOMO Reference Manual

University of Southern California COCOMO Reference Manual USC COCOMOII Reference Manual University of Southern California COCOMO Reference Manual 1 This manual is compatible with USC-COCOMOII.1999 version 0. Copyright Notice This document is copyrighted, and

More information

Software Requirements Metrics

Software Requirements Metrics Software Requirements Metrics Fairly primitive and predictive power limited. Function Points Count number of inputs and output, user interactions, external interfaces, files used. Assess each for complexity

More information

Deducing software process improvement areas from a COCOMO II-based productivity measurement

Deducing software process improvement areas from a COCOMO II-based productivity measurement Deducing software process improvement areas from a COCOMO II-based productivity measurement Lotte De Rore, Monique Snoeck, Geert Poels, Guido Dedene Abstract At the SMEF2006 conference, we presented our

More information

Scrum on Offshore Development Case Study

Scrum on Offshore Development Case Study Master Thesis Software Engineering Thesis no: MSE-2009-28 Nov. 2009 Communication Support to Scrum Methodology in Offshore Development Case Study Mermaid Technology, Denmark Kashif Ali Sulemani, Muhammad

More information

Module 11. Software Project Planning. Version 2 CSE IIT, Kharagpur

Module 11. Software Project Planning. Version 2 CSE IIT, Kharagpur Module 11 Software Project Planning Lesson 29 Staffing Level Estimation and Scheduling Specific Instructional Objectives At the end of this lesson the student would be able to: Identify why careful planning

More information

SOFTWARE COST DRIVERS AND COST ESTIMATION IN NIGERIA ASIEGBU B, C AND AHAIWE, J

SOFTWARE COST DRIVERS AND COST ESTIMATION IN NIGERIA ASIEGBU B, C AND AHAIWE, J SOFTWARE COST DRIVERS AND COST ESTIMATION IN NIGERIA Abstract ASIEGBU B, C AND AHAIWE, J This research work investigates the effect of cost drivers on software cost estimation. Several models exist that

More information

10 Keys to Successful Software Projects: An Executive Guide

10 Keys to Successful Software Projects: An Executive Guide 10 Keys to Successful Software Projects: An Executive Guide 2000-2006 Construx Software Builders, Inc. All Rights Reserved. www.construx.com Background State of the Art vs. State of the Practice The gap

More information

Best-Practice Software Engineering: Software Processes to Support Project Success. Dietmar Winkler

Best-Practice Software Engineering: Software Processes to Support Project Success. Dietmar Winkler Best-Practice Software Engineering: Software Processes to Support Project Success Dietmar Winkler Vienna University of Technology Institute of Software Technology and Interactive Systems Dietmar.Winkler@qse.ifs.tuwien.ac.at

More information

Software Estimation Experiences at Xerox

Software Estimation Experiences at Xerox 15th lntemational Forum on COCOMO and Software Cost Modeling Software Estimation Experiences at Xerox Dr. Peter Hantos OfJice Systems Group, Xerox No, but it is certainly not victimless... CROW By Bill

More information

2 Evaluation of the Cost Estimation Models: Case Study of Task Manager Application. Equations

2 Evaluation of the Cost Estimation Models: Case Study of Task Manager Application. Equations I.J.Modern Education and Computer Science, 2013, 8, 1-7 Published Online October 2013 in MECS (http://www.mecs-press.org/) DOI: 10.5815/ijmecs.2013.08.01 Evaluation of the Cost Estimation Models: Case

More information

Software project cost estimation using AI techniques

Software project cost estimation using AI techniques Software project cost estimation using AI techniques Rodríguez Montequín, V.; Villanueva Balsera, J.; Alba González, C.; Martínez Huerta, G. Project Management Area University of Oviedo C/Independencia

More information

Usability metrics for software components

Usability metrics for software components Usability metrics for software components Manuel F. Bertoa and Antonio Vallecillo Dpto. Lenguajes y Ciencias de la Computación. Universidad de Málaga. {bertoa,av}@lcc.uma.es Abstract. The need to select

More information

E-COCOMO: The Extended COst Constructive MOdel for Cleanroom Software Engineering

E-COCOMO: The Extended COst Constructive MOdel for Cleanroom Software Engineering Database Systems Journal vol. IV, no. 4/2013 3 E-COCOMO: The Extended COst Constructive MOdel for Cleanroom Software Engineering Hitesh KUMAR SHARMA University of Petroleum and Energy Studies, India hkshitesh@gmail.com

More information

PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING

PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING 03-23-05 Christine Green, PMI PMBOK and Estimating EDS, Delivery

More information

ICS 121 Lecture Notes Spring Quarter 96

ICS 121 Lecture Notes Spring Quarter 96 Software Management Cost Estimation Managing People Management Poor managment is the downfall of many software projects Ð Delivered software was late, unreliable, cost several times the original estimates

More information

ANALOG-BASED COST ESTIMATION FOR MANAGING INCONSISTENCY IN SOFTWARE DEVELOPMENT

ANALOG-BASED COST ESTIMATION FOR MANAGING INCONSISTENCY IN SOFTWARE DEVELOPMENT ANALOG-BASED COST ESTIMATION FOR MANAGING INCONSISTENCY IN SOFTWARE DEVELOPMENT JOSH MARY ANUKULA 1*, Dr. S. MARUTHU PERUMAL 2*, Dr. S. MARUTHU PERUMAL 3* 1. II- M.Tech, SE, G.I.E.T, RAJAHMUNDRY. 2. PROFESSOR,

More information

Contents. Today Project Management. Project Management. Last Time - Software Development Processes. What is Project Management?

Contents. Today Project Management. Project Management. Last Time - Software Development Processes. What is Project Management? Contents Introduction Software Development Processes Project Management Requirements Engineering Software Construction Group processes Quality Assurance Software Management and Evolution Last Time - Software

More information

Software Metrics. Lord Kelvin, a physicist. George Miller, a psychologist

Software Metrics. Lord Kelvin, a physicist. George Miller, a psychologist Software Metrics 1. Lord Kelvin, a physicist 2. George Miller, a psychologist Software Metrics Product vs. process Most metrics are indirect: No way to measure property directly or Final product does not

More information

Web Development: Estimating Quick-to-Market Software

Web Development: Estimating Quick-to-Market Software Web Development: Estimating Quick-to-Market Software Donald J. Reifer 15 th International Forum on COCOMO and Software Estimation 10/25/00 Copyright 2000, RCI 1 Setting the Stage Business and government

More information

Software Process Improvement Framework for Software Outsourcing Based On CMMI Master of Science Thesis in Software Engineering and Management

Software Process Improvement Framework for Software Outsourcing Based On CMMI Master of Science Thesis in Software Engineering and Management Software Process Improvement Framework for Software Outsourcing Based On CMMI Master of Science Thesis in Software Engineering and Management ZAHOOR UL ISLAM XIANZHONG ZHOU University of Gothenburg Chalmers

More information

MoP Glossary of Terms - English

MoP Glossary of Terms - English English Term aggregated risk English Definition The overall level of risk to the portfolio when all the risks are viewed as a totality rather than individually. This could include the outputs of particular

More information

Software Engineering. Introduction. Software Costs. Software is Expensive [Boehm] ... Columbus set sail for India. He ended up in the Bahamas...

Software Engineering. Introduction. Software Costs. Software is Expensive [Boehm] ... Columbus set sail for India. He ended up in the Bahamas... Software Engineering Introduction... Columbus set sail for India. He ended up in the Bahamas... The economies of ALL developed nations are dependent on software More and more systems are software controlled

More information

Project Management. Lecture 3. Software Engineering CUGS. Spring 2012 (slides made by David Broman) Kristian Sandahl

Project Management. Lecture 3. Software Engineering CUGS. Spring 2012 (slides made by David Broman) Kristian Sandahl Project Lecture 3 Software Engineering CUGS Spring 2012 (slides made by David Broman) Kristian Sandahl Department of Computer and Information Science Linköping University, Sweden A Software Life-cycle

More information

Project Management. Lecture 3. Software Engineering CUGS. Spring 2011 (slides made by David Broman)

Project Management. Lecture 3. Software Engineering CUGS. Spring 2011 (slides made by David Broman) Lecture 3 Software Engineering CUGS Spring 2011 (slides made by David Broman) Kristian Sandahl Department of Computer and Information Science Linköping University, Sweden A Software Life-cycle Model Which

More information

11.1 What is Project Management? Object-Oriented Software Engineering Practical Software Development using UML and Java. What is Project Management?

11.1 What is Project Management? Object-Oriented Software Engineering Practical Software Development using UML and Java. What is Project Management? 11.1 What is Project Management? Object-Oriented Software Engineering Practical Software Development using UML and Java Chapter 11: Managing the Software Process Project management encompasses all the

More information

IT2403-SOFTWARE PROJECT MANAGEMENT 2 MARKS QUESTIONS

IT2403-SOFTWARE PROJECT MANAGEMENT 2 MARKS QUESTIONS IT2403-SOFTWARE PROJECT MANAGEMENT 2 MARKS QUESTIONS 1. Define software project management. Software Project Management has key ideas about the planning, monitoring, and control of software projects 2.

More information

Pragmatic Peer Review Project Contextual Software Cost Estimation A Novel Approach

Pragmatic Peer Review Project Contextual Software Cost Estimation A Novel Approach www.ijcsi.org 692 Pragmatic Peer Review Project Contextual Software Cost Estimation A Novel Approach Manoj Kumar Panda HEAD OF THE DEPT,CE,IT & MCA NUVA COLLEGE OF ENGINEERING & TECH NAGPUR, MAHARASHTRA,INDIA

More information

Software Engineering. Reading. Effort estimation CS / COE 1530. Finish chapter 3 Start chapter 5

Software Engineering. Reading. Effort estimation CS / COE 1530. Finish chapter 3 Start chapter 5 Software Engineering CS / COE 1530 Lecture 5 Project Management (finish) & Design CS 1530 Software Engineering Fall 2004 Reading Finish chapter 3 Start chapter 5 CS 1530 Software Engineering Fall 2004

More information

Software Development: Tools and Processes. Lecture - 16: Estimation

Software Development: Tools and Processes. Lecture - 16: Estimation Software Development: Tools and Processes Lecture - 16: Estimation Estimating methods analogy method direct estimating method Delphi technique PERT-type rolling window Constructivist Cost Model (CoCoMo)

More information

Appendix B Data Quality Dimensions

Appendix B Data Quality Dimensions Appendix B Data Quality Dimensions Purpose Dimensions of data quality are fundamental to understanding how to improve data. This appendix summarizes, in chronological order of publication, three foundational

More information

A Study on RE Process Models for Offshore Software Development

A Study on RE Process Models for Offshore Software Development J. Basic. Appl. Sci. Res., 4(4)114-119, 2014 2014, TextRoad Publication ISSN 2090-4304 Journal of Basic and Applied Scientific Research www.textroad.com A Study on RE Process Models for Offshore Software

More information

Using Productivity Measure and Function Points to Improve the Software Development Process

Using Productivity Measure and Function Points to Improve the Software Development Process Using Productivity Measure and Function Points to Improve the Software Development Process Eduardo Alves de Oliveira and Ricardo Choren Noya Computer Engineering Section, Military Engineering Institute,

More information

Function Point: how to transform them in effort? This is the problem!

Function Point: how to transform them in effort? This is the problem! Function Point: how to transform them in effort? This is the problem! Gianfranco Lanza Abstract The need to estimate the effort and, consequently, the cost of a software project is one of the most important

More information

Studying the Impact of Global Software Development Characteristics on Project Goals: A Causal Model

Studying the Impact of Global Software Development Characteristics on Project Goals: A Causal Model Studying the Impact of Global Software Development Characteristics on Project Goals: A Causal Model *Ansgar Lamersdorf University of Kaiserslautern a_lamers@informatik.uni-kl.de Jürgen Münch Fraunhofer

More information

Efficient Indicators to Evaluate the Status of Software Development Effort Estimation inside the Organizations

Efficient Indicators to Evaluate the Status of Software Development Effort Estimation inside the Organizations Efficient Indicators to Evaluate the Status of Software Development Effort Estimation inside the Organizations Elham Khatibi Department of Information System Universiti Teknologi Malaysia (UTM) Skudai

More information

AN ENHANCED MODEL TO ESTIMATE EFFORT, PERFORMANCE AND COST OF THE SOFTWARE PROJECTS

AN ENHANCED MODEL TO ESTIMATE EFFORT, PERFORMANCE AND COST OF THE SOFTWARE PROJECTS M PAULINE et. al.: AN ENHANCED MODEL TO ESTIMATE EFFORT, PERFORMANCE AND COST OF THE SOFTWARE PROJECTS AN ENHANCED MODEL TO ESTIMATE EFFORT, PERFORMANCE AND COST OF THE SOFTWARE PROJECTS M. Pauline 1,

More information

TG 47-01. TRANSITIONAL GUIDELINES FOR ISO/IEC 17021-1:2015, ISO 9001:2015 and ISO 14001:2015 CERTIFICATION BODIES

TG 47-01. TRANSITIONAL GUIDELINES FOR ISO/IEC 17021-1:2015, ISO 9001:2015 and ISO 14001:2015 CERTIFICATION BODIES TRANSITIONAL GUIDELINES FOR ISO/IEC 17021-1:2015, ISO 9001:2015 and ISO 14001:2015 CERTIFICATION BODIES Approved By: Senior Manager: Mpho Phaloane Created By: Field Manager: John Ndalamo Date of Approval:

More information

Requirements Management in Distributed Projects

Requirements Management in Distributed Projects Journal of Universal Knowledge Management, vol. 1, no. 2 (2006), 69-76 submitted: 15/5/06, accepted: 15/6/06, appeared: 28/9/06 J.UKM Requirements Management in Distributed Projects Darja Šmite (Riga Information

More information

Chemuturi Consultants Do it well or not at all Productivity for Software Estimators Murali Chemuturi

Chemuturi Consultants Do it well or not at all Productivity for Software Estimators Murali Chemuturi Productivity for Software Estimators Murali Chemuturi 1 Introduction Software estimation, namely, software size, effort, cost and schedule (duration) are often causing animated discussions among the fraternity

More information

Requirements Engineering: Elicitation Techniques

Requirements Engineering: Elicitation Techniques 2008:PR003 Requirements Engineering: Elicitation Techniques Sai Ganesh. Gunda Source:http://www.marcocioffi.com/archives/2005/04/requirements-engineering/ MASTER S THESIS Software Engineering, 2008 Department

More information

How To Manage Project Management

How To Manage Project Management CS/SWE 321 Sections -001 & -003 Software Project Management Copyright 2014 Hassan Gomaa All rights reserved. No part of this document may be reproduced in any form or by any means, without the prior written

More information

Manual Guide of The Induction Program for New Employees in the Federal Government

Manual Guide of The Induction Program for New Employees in the Federal Government United Arab Emirates Federal Authority For Government Human Resources Manual Guide of The Induction Program for New Employees in the Federal Government Building a Productive Institutional Culture @FAHR_UAE

More information

CALCULATING THE COSTS OF MANUAL REWRITES

CALCULATING THE COSTS OF MANUAL REWRITES CALCULATING THE COSTS OF MANUAL REWRITES Know before you go. 2 You ve got an old legacy application and you re faced with the dilemma.. Should I rewrite from scratch? Should I keep trying to maintain it?

More information

Agile Based Software Development Model : Benefits & Challenges

Agile Based Software Development Model : Benefits & Challenges Agile Based Software Development Model : Benefits & Challenges Tajinder Kumar Assistant Professor, IT Department JMIT Radaur, Haryana Vipul Gupta Assistant Professor, IT Department JMIT Radaur, Haryana

More information

Article 3, Dealing with Reuse, explains how to quantify the impact of software reuse and commercial components/libraries on your estimate.

Article 3, Dealing with Reuse, explains how to quantify the impact of software reuse and commercial components/libraries on your estimate. Estimating Software Costs This article describes the cost estimation lifecycle and a process to estimate project volume. Author: William Roetzheim Co-Founder, Cost Xpert Group, Inc. Estimating Software

More information

Module 11. Software Project Planning. Version 2 CSE IIT, Kharagpur

Module 11. Software Project Planning. Version 2 CSE IIT, Kharagpur Module 11 Software Project Planning Lesson 28 COCOMO Model Specific Instructional Objectives At the end of this lesson the student would be able to: Differentiate among organic, semidetached and embedded

More information

Hathaichanok Suwanjang and Nakornthip Prompoon

Hathaichanok Suwanjang and Nakornthip Prompoon Framework for Developing a Software Cost Estimation Model for Software Based on a Relational Matrix of Project Profile and Software Cost Using an Analogy Estimation Method Hathaichanok Suwanjang and Nakornthip

More information

CS 458 - Homework 4 p. 1. CS 458 - Homework 4. To become more familiar with top-down effort estimation models, especially COCOMO 81 and COCOMO II.

CS 458 - Homework 4 p. 1. CS 458 - Homework 4. To become more familiar with top-down effort estimation models, especially COCOMO 81 and COCOMO II. CS 458 - Homework 4 p. 1 Deadline Due by 11:59 pm on Friday, October 31, 2014 How to submit CS 458 - Homework 4 Submit these homework files using ~st10/458submit on nrs-labs, with a homework number of

More information

Center for Effective Organizations

Center for Effective Organizations Center for Effective Organizations HR METRICS AND ANALYTICS USES AND IMPACTS CEO PUBLICATION G 04-8 (460) EDWARD E. LAWLER III ALEC LEVENSON JOHN BOUDREAU Center for Effective Organizations Marshall School

More information

SE351a: Software Project & Process Management

SE351a: Software Project & Process Management SE351a: Software Project & Process Management W8: Software Project Planning 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa SE351 Roadmap Introduction to Software Project Management Project Management

More information

Introduction to Systems Analysis and Design

Introduction to Systems Analysis and Design Introduction to Systems Analysis and Design What is a System? A system is a set of interrelated components that function together to achieve a common goal. The components of a system are called subsystems.

More information

High-Performance Scorecards. Best practices to build a winning formula every time

High-Performance Scorecards. Best practices to build a winning formula every time High-Performance Scorecards Best practices to build a winning formula every time Will your team win or lose? Scorecards drive financial decision making For decades, your organization has used the predictive

More information

Evaluation and Integration of Risk Management in CMMI and ISO/IEC 15504

Evaluation and Integration of Risk Management in CMMI and ISO/IEC 15504 Evaluation and Integration of Risk Management in CMMI and ISO/IEC 15504 Dipak Surie, Email : ens03dse@cs.umu.se Computing Science Department Umea University, Umea, Sweden Abstract. During software development,

More information

COCOMO II Model Definition Manual

COCOMO II Model Definition Manual COCOMO II Model Definition Manual Acknowledgments COCOMO II is an effort to update the well-known COCOMO (Constructive Cost Model) software cost estimation model originally published in Software Engineering

More information

Applying COCOMO II - A case study Darko Milicic

Applying COCOMO II - A case study Darko Milicic Master Thesis Software Engineering Thesis no: MSE-2004-19 August 2004 Applying COCOMO II - A case study Darko Milicic School of Engineering Blekinge Institute of Technology Box 520 SE 372 25 Ronneby Sweden

More information

Managing Uncertainty in Globally Distributed Software Development Projects

Managing Uncertainty in Globally Distributed Software Development Projects LATVIJAS UNIVERSITĀTES RAKSTI. 2008, 733. sēj.: DATORZINĀTNE UN INFORMĀCIJAS TEHNOLOĢIJAS 9. 23. lpp. Managing Uncertainty in Globally Distributed Software Development Projects Darja Šmite, Juris Borzovs

More information

Agile Inspired Risk Mitigation Techniques for Software Development Projects

Agile Inspired Risk Mitigation Techniques for Software Development Projects Agile Inspired Risk Mitigation Techniques for Software Development Projects Presented at GTISLIG, Toronto November 15 th 2007 Michael Bica, Sogard Inc. 1 Roadmap I. Risks Heuristics Risks & Estimation

More information

Introduction to Software Engineering. 9. Project Management

Introduction to Software Engineering. 9. Project Management Introduction to Software Engineering 9. Project Management Roadmap > Risk management > Scoping and estimation > Planning and scheduling > Dealing with delays > Staffing, directing, teamwork 2 Literature

More information

Architecture of a Software Configuration Management System for Globally Distributed Software Development Teams

Architecture of a Software Configuration Management System for Globally Distributed Software Development Teams Architecture of a Software Configuration Management System for Globally Distributed Software Development Teams Muhammad Wasim Bhatti Engineering Management Department CASE, Center for Advanced Studies

More information

Lecture 14: Cost Estimation

Lecture 14: Cost Estimation Overview Project management activities Project costing Project scheduling and staffing Project monitoring and review General cost estimation rules Algorithmic Cost Modeling Function point model COCOMO

More information

Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire. P3M3 Project Management Self-Assessment

Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire. P3M3 Project Management Self-Assessment Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire P3M3 Project Management Self-Assessment Contents Introduction 3 User Guidance 4 P3M3 Self-Assessment Questionnaire

More information

IMPROVED SIZE AND EFFORT ESTIMATION MODELS FOR SOFTWARE MAINTENANCE. Vu Nguyen

IMPROVED SIZE AND EFFORT ESTIMATION MODELS FOR SOFTWARE MAINTENANCE. Vu Nguyen IMPROVED SIZE AND EFFORT ESTIMATION MODELS FOR SOFTWARE MAINTENANCE by Vu Nguyen A Dissertation Presented to the FACULTY OF THE USC GRADUATE SCHOOL UNIVERSITY OF SOUTHERN CALIFORNIA In Partial Fulfillment

More information

The COCOMO II Estimating Model Suite

The COCOMO II Estimating Model Suite The COCOMO II Estimating Model Suite Barry Boehm, Chris Abts, Jongmoon Baik, Winsor Brown, Sunita Chulani, Cyrus Fakharzadeh, Ellis Horowitz and Donald Reifer Center for Software Engineering University

More information

University of Calgary Schulich School of Engineering Department of Electrical and Computer Engineering

University of Calgary Schulich School of Engineering Department of Electrical and Computer Engineering University of Calgary Schulich School of Engineering Department of Electrical and Computer Engineering Research Area: Software Engineering Thesis Topics proposed by Dr. Dietmar Pfahl, Assistant Professor

More information

Amplification of the COCOMO II regarding Offshore Software Projects

Amplification of the COCOMO II regarding Offshore Software Projects Amplification of the COCOMO II regarding Offshore Software Projects Stefanie Betz 1, Juho Mäkiö 2 1 University of Karlsruhe, Institute AIFB, Hertzstrasse 16 76187 Karlsruhe, Germany Betz@aifb.uni-karlsruhe.de

More information

Software Development Process

Software Development Process Software Development Process A software development process, also known as software development lifecycle, is a structure imposed on the development of a software product. Similar terms include software

More information

TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT. Hazar Hamad Hussain *

TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT. Hazar Hamad Hussain * TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT Hazar Hamad Hussain * 1. Introduction The definition of Project as a temporary endeavor... refers that project has to be done within a limited

More information

Quality Management in Purchasing

Quality Management in Purchasing Saimaa University of Applied Sciences Faculty of Business Administration, Lappeenranta Degree Programme in International Business Olga Anisimova Quality Management in Purchasing Thesis 2014 Abstract Olga

More information