10.0 FLOOD RISK ASSESSMENT AND SURFACE WATER DRAINAGE STRATEGY This chapter of the Environmental Statement is based on a Flood Risk
|
|
- Vivian Stewart
- 7 years ago
- Views:
Transcription
1 10.0 FLOOD RISK ASSESSMENT AND SURFACE WATER DRAINAGE STRATEGY Introduction 10.1 This chapter of the is based on a Flood Risk Assessment (FRA) incorporating a Surface Water Drainage Strategy and Flood Risk Management Plan and Access Strategy (Access Strategy) produced by Odyssey Consulting Engineers to support the planning application. The purpose of the FRA is to: Provide a preliminary Surface Water Drainage Strategy identifying strategic proposals for the surface water drainage that will ensure current Government guidance is complied with, such as Planning Policy Statement 25 (PPS25) and Sustainable Drainage Systems guidance (SUDS); Undertake a FRA to confirm the sites suitability for development; Assess surface water run-off from the existing land use and compare this with the proposed development run-off; Review existing surface water systems; Review the impact (if any) of the proposed access location and construction makeup to flood risk both downstream and upstream of the site The Flood Risk Management Plan and Access Strategy demonstrates the Flood Risk Management procedures that will be in place (to be secured by condition) and concludes that there would be no risk to users of the proposed access road. Site Description 10.3 Chapter 2 of the FRA provides a site description. The development area is sited within arable land and has a level difference of 4 meters from east to west towards the River Soar. This represents a gradient of 1: The site is shown on the 1:50,000 British Geological Survey map no.169 Coventry. Data for the site and surrounding area suggests the underlying sub-strata is predominantly Till or Boulder Clay with some
2 Mercia Mudstone and Alluvium deposits associated with steams, rivers and other watercourses. Planning Policy 10.5 Planning Policy Statement 25 (PPS25) Development and Flood Risk requires a FRA to be undertaken on all development sites over 1 hectare in size whether in floodplain or not. In terms of fluvial flooding, the guidance categorises flood zones in three levels of risk as follows: Figure 18 - Table 4.1 of FRA Flood Zone 1. Little or no risk 2. Low to medium risk 3. High risk Annual Probability of Flooding <0.1% % >1.0% 10.6 Pursuant to PPS25 Annex D the proposed development of the AD plant will fall within the classification of Less Vulnerable and is considered appropriate in areas categorised by Flood Zones 1 or 2 and 3a This section of the document considers the requirements of the guidance and demonstrates that the proposed development lies within the acceptable flood risk parameters. Site Specific Information 10.8 Environment Agency (the Agency) Section 105 flood mapping and detailed flood modelling provided by the Agency illustrates that the proposed site is located within Flood Zone 1 with a small section of the undeveloped site located on the fringe of a section of Flood Zone 2. This is further confirmed by correspondence with the Agency, shown within Appendix C of the FRA The detailed flood mapping indicates that the proposed main access and egress is located mainly within Flood Zone 2 but with small sections
3 (as shown blue on drawing number /006 and comprising less than 40% of the access road) within Flood Zone The site is indicated on the British Geological Survey map no.169 Coventry as predominantly Till or Boulder Clay with some Mercia Mudstone and Alluvium deposits associated with streams, rivers and other watercourses. The geology of the site has been re-affirmed by a site specific intrusive investigation into the underlying sub-strata The three dimensional level survey completed has been used to establish terrain contour mapping for use in completing the FRA. Drawing /002 affixed within Appendix B of the FRA shows the existing site levels. It can be seen from the site topographic survey that the site falls at a steady gradient from a level of approximately 79.98m at the east corner to a level of 75.01m at the west corner. Flood Levels Modelled flood levels provided by the Agency for the upstream and downstream face of Stoney Bridge are as follows: Figure 19 - Table 4.1 of Access Strategy Environment Agency Modelled Flood Levels Return Period Description Node Label Upstream face Stoney Bridge Downstream face Stoney Bridge The above modelled flood levels within Table 4.1 do not include an allowance for climate change, therefore based on the Agency s recommendation 300mm should be added to these levels.
4 Figure 20 - Table 4.2 of Access Strategy Environment Agency Modelled Flood Levels, Including 300mm for Climate Change Return Period Description Node Label Upstream face Stoney Bridge Downstream face Stoney Bridge Based on the above, a review was undertaken based on the modelled flood levels and existing ground levels. OCE drawing within the Access Strategy illustrates a long section of the proposed road (at existing ground levels) plotted against the EA modelled flood levels, indicating the predicted depth of flood waters during the 1 in 100 year flood event plus 300mm for climate change. Existing Surface Water Drainage Scheme Based on local records, there are no existing surface water sewers in the vicinity of the site A walkover survey has confirmed that there is an existing overland flow path for surface water which does not infiltrate directly into the substrata. The overland flow path follows the existing ground profile of the site and flows east to west towards the River Soar. Drawing /004 within Appendix B of the FRA (contained within Appendix 5 of this statement) illustrates this overland flow path. Proposed Site Access As previously discussed, the proposed access for the development will be mainly within Flood Zone 2 but partly within Flood Zone 3 (less than 40% at the access road).
5 10.18 Initial discussions with the Agency raised an objection on flood risk grounds due to the then proposed access road being raised above existing levels and therefore having the potential of increasing flood risk to the up and downstream catchments Further correspondence provided by the Agency based on a revised access, shown within Appendix C of the Access Strategy, has lifted their previous objection of the proposed access road. This access will be provided at existing levels to ensure the floodplain is not impacted Within this correspondence the Agency have indicated that there is a potential that the access road will be subject to flooding anywhere from 0 days in a dry year to days of the year depending upon rainfall and local hydraulics. These durations are not based on site specific information but for the local area as a whole Following previous correspondence with the Agency it has been agreed that for this area vehicles can be safely operational during times of flood up to a flood depth of 300mm while floods in excess of this may have a risk to life if the access remains operational From reviewing the Agency s Upper Sour ISIS model, for a comparison of flood depths against duration, the access road will be under flood conditions for storms in excess of a 1 in 50 year return period, and only then if 300mm has been included for climate change. The duration that has been indicated from this review demonstrates that the access road will be subject to an unacceptable depth of flooding for an approximate duration of around 18 hours during the 1 in 50 year storm event During these 18 hours the main access gate will be locked and no deliveries made, a secondary access will be utilised for emergency use and exit from the site. This emergency access is an existing track that traverses the farmland from the junction of the B4114 / Fosse Way past the development on the northern side through Sutton Lodge Farm and
6 joining onto Frolesworth Road to the east of the development. Figure 6 within Appendix A of the FRA highlights this route. Preliminary Surface Water Drainage Strategy Current Planning Policy (PPS25) and Environment Agency guidance requires developments to employ Sustainable Drainage measures (SUDS) wherever feasible. Careful design of SUDS features can ensure that the site storm water drainage closely reflects the natural hydrology and hydrogeology of the site. Such systems can also improve the quality of water discharged from development prior to reaching the receiving watercourse Source control is a key element of SUDS and is now identified in Part H of the Building Regulations 2002 as taking preference over conventional drainage systems. Part H now states: Rainwater from a system provided pursuant to sub-paragraphs (1) or (2) shall discharge to one of the following, listed in order of priority: (a) an adequate soakaway or some other adequate infiltration system; or where that is not reasonably practicable, (b) a watercourse; or where that is not reasonably practicable, (c) a sewer Source control systems treat water close to the point of collection, in features such as soakaways, porous pavements, infiltration trenches, swales and basins. The use of these can have the benefit of discharging surface water back to ground rather than just temporarily attenuating peak flows before discharging it to the receiving watercourse As source control measures generally rely upon the infiltration of surface water to ground, it is a prerequisite that the ground conditions are appropriate for such. Published geology for the local area suggests the subsoil will have poor permeability, hence the use of groundwater recharge systems is likely to be low.
7 10.28 Next in the search sequence, defined by Part H, is discharge to a watercourse. The site has only one designated nearby watercourse approximately 130m to the west. It is clear that an existing overland flow path is available for the site to drain into the existing watercourse Last in the search sequence is discharge to a sewer. There are no known sewers within the vicinity of the proposed development. Further to this, there is an existing watercourse in close proximity to the development and, for sustainability, discharge to a sewer has not been considered further The search demonstrates that the potential to recharge the ground via the proposed attenuation pond and the existing watercourse is the most appropriate outfall via overland flow for extreme flood events Accordingly, initial drainage proposals have been developed employing a piped on-site network that discharges into the attenuation pond before discharging into the River Soar not exceeding greenfield run-off rates. Appraisal In establishing the permitted discharge from the development areas, an appraisal has been completed in accordance with IH 124. A copy of the existing calculations are contained in Appendix C of the FRA. Taking into account the indicative catchment area, the permitted discharges from the site will be as follows: Figure 21 - Table 4.4 of the FRA Storm Event 1 in 1 year 1 in 30 year 1 in 100 year Flow l/s
8 10.33 Preliminary proposals have been developed to demonstrate the proposed surface water management scheme. The proposals are indicated on drawing /005 affixed within Appendix B of the FRA, with post development calculations provided within Appendix D of the FRA. The calculations within Appendix D were calculated using WINDES (industry standard design package) to the design criteria within Table 4.3 (figure 20) The outline drainage scheme provides surface water drainage in the form of an attenuation pond before discharging into the River Soar via outflow pipe and headwall. Extreme storm events will utilise the existing overland flow path. Discharge rates will be limited to the existing greenfield run-off rates as detailed above. All surface water storage is catered for within the proposed pond The surface water network has been sized to accommodate storage for the 1 in 1, 1 in 30 and the 1 in 100 year plus 20% climate change whilst still maintaining greenfield discharge rates On the rare occasions when storm events exceed 1 in 30 years, existing overland flow path to the watercourse to the north west will be maintained. This is indicated schematically on drawing /005 shown within Appendix B of the FRA. Conclusions The proposed AD buildings are indicated on the Agency s Section 105 flood mapping as within Flood Zone 1. PPS25 states that Flood Zone 1 is appropriate for all uses of land. Agency. This has been confirmed by the The proposed access road is located mostly within land designated as Flood Zone 2 but with small sections (<40%) within Flood Zone 3. The Agency has lifted their previous objection of the proposed access road located within this zone.
9 10.39 Review of the Agency s Upper Sour ISIS model has indicated that the road will be subject to unacceptable depths of flooding for an approximate duration of around 18 hours during the 1 in 50 year storm event During these 18 hours the main access will be gated with no deliveries being made. During this closure there is a secondary access that will be utilised for emergency use. The emergency access is an existing lane that traverses the farmland from the junction of the B4114 / Fosse Way past the development on the northern side through Sutton Lodge Farm and joining onto Frolesworth Road to the east of the development. Figure 6 within Appendix A of the FRA highlights this route The risk of pollutants entering the groundwater is extremely small due to the employment of source control measures The preliminary storm water drainage scheme proposed has demonstrated that SUDS techniques can and will be utilised on this site in the form of an attenuation pond The proposal will limit the surface water discharge to replicate greenfield run-off and therefore will not increase flood risk. greenfield run-off is shown in Table 4.4. Existing The Flood Risk Management Plan and Access Strategy demonstrates: There is no significant flood risk to users of the main access road. Any risk would be fully addressed and mitigated by the detailed strategy which would be secured by appropriate planning conditions The closure of the site for up to 14 days would not create a significant impact on the facility. Closure of up to 30 days would have an economic impact on the plant but would not be long enough for the biological digestion process to be completely stopped. Based on the flood depth / duration hydrograph, the proposed access road will have
10 an average closed duration of around 18 hours during the 1 in 50 year storm event. This duration will have no effect on the operation of the AD facility The findings of the FRA demonstrate that the proposed development will fully comply with the requirements of PPS25. The proposed plant will be located within Flood Zone 1 and a safe means of access to serve the development will be provided in all circumstances. There are no flood risk or other hydrological constraints or impacts which indicate planning permission should be refused.
Taylor Wimpey UK Ltd. December 2007
Taylor Wimpey UK Ltd December 2007 QM Issue/revision Issue 1 Revision 1 Revision 2 Revision 3 Remarks Draft For Planning Date 3 August 2007 20 December 2007 Prepared by D Gooding P Barton Signature Checked
More informationFLOOD RISK AND SURFACE WATER DRAINAGE ASSESSMENT HILLHOUSE RESTORATION SITE, OFF JAMESON ROAD, THORNTON CLEVELEYS ON BEHALF OF NPL ESTATES
FLOOD RISK AND SURFACE WATER DRAINAGE ASSESSMENT HILLHOUSE RESTORATION SITE, OFF JAMESON ROAD, THORNTON CLEVELEYS ON BEHALF OF NPL ESTATES Integra Consulting Engineers Limited NS / 2543 Fountain House
More informationChapter 9: Water, Hydrology and Drainage Land West of Uttoxeter
Chapter 9: Water, Hydrology and Drainage Land West of Uttoxeter ENVIRONMENTAL STATEMENT: VOLUME 1 9.1 INTRODUCTION 9.1.1 This Chapter considers the effects of the Project on surface water and groundwater
More informationRecommendations for future developments
C Recommendations for future developments C.1 Reducing flood risk through site layout and design C.1.1 C.1.2 Flood risk should be considered at an early stage in deciding the layout and design of a site
More informationWEST LONDON PIPELINE AND STORAGE LIMITED AND UNITED KINGDOM OIL PIPELINES LIMITED
WEST LONDON PIPELINE AND STORAGE LIMITED AND UNITED KINGDOM OIL PIPELINES LIMITED WLPS BUNCEFIELD REBUILD Flood Risk Assessment Green Lane Hemel Hempstead Hertfordshire HP2 7HZ September 2009 Prepared
More informationFlood Risk Assessment and Drainage Impact Assessment: Planning Guidance for Developers
Flood Risk Assessment and Drainage Impact Assessment: Planning Guidance for Developers Development and Regeneration Services Glasgow City Council 229 George Street Glasgow G1 1QU May 2011 1. Introduction...-
More informationIntroduction. The vision of the West Yorkshire Combined Authority (WYCA) Flood Risk Partnership
WYCA SuDS Guidance Introduction As part of the government s continuing commitment to protect people and property from flood risk, the Department for Communities and Local Government and the Department
More informationFLOOD RISK ASSESSMENT AND DRAINAGE STRATEGY
FLOOD RISK ASSESSMENT AND DRAINAGE STRATEGY London Rd. WATERLOOVILE FOR McCarthy & Stone Ltd. July 2010 Such Salinger Peters Ltd 30558-1- Flood Risk Assessment & Drainage Strategy Contents Paragraph Page
More informationDesigned and produced by geo-graphicsdesign.com DP 300 3/02
Designed and produced by geo-graphicsdesign.com DP 300 3/02 Guidance for Developers and Regulators Purpose This booklet is produced on behalf of the North East Scotland Flooding Advisory Group and is intended
More informationEast Riding of Yorkshire Council
East Riding of Yorkshire Council Lead Local Flood Authority Interim Standing Advice Revision A - April 2015 1. Introduction From April 2015 the Lead Local Flood Authority (LLFA) became a statutory consultee
More informationSUSTAINABLE URBAN DRAINAGE SYSTEMS
overflow can lead into a permeable conveyance system to increase further the benefit and reduce the need for pipe systems. Pollutant removal rates have been shown to be high, with some pollutants being
More informationProposed Residential Development Land off Cody Road Waterbeach Cambridgeshire. Flood Risk Assessment
Land off Cody Road Waterbeach Cambridgeshire Cedar Barn, White Lodge, Walgrave, Northampton, NN6 9PY T: F: E: W: 01604 781811 01604 781999 mail@jppuk.net jppuk.net Proposed Residential Development Land
More informationGranville Road Estate, London Borough of Barnet. Flood Risk Assessment and Drainage Strategy August 2014. New Granville LLP
Granville Road Estate, London Borough of Barnet Flood Risk Assessment and Drainage Strategy August 2014 New Granville LLP Document History JOB NUMBER: 237 DOCUMENT REF: Granville Road FRA REVISIONS: Final
More informationLondon Borough of Waltham Forest LOCAL FLOOD RISK MANAGEMENT STRATEGY. Summary Document
LOCAL FLOOD RISK MANAGEMENT STRATEGY Summary Document October 2013 Local Flood Risk Management Strategy Summary 1 Introduction 2 Partner responsibilities 3 What do we know about flooding in the borough?
More informationLondon Road, Rayleigh Essex Flood Risk Assessment Addendum
FINAL Countryside Properties (UK) Limited Submitted by AECOM 6-8 Greencoat Place London SW1P 1PL London Road, Rayleigh Essex Flood Risk Assessment May 2015 i Limitations AECOM Infrastructure & Environment
More informationVital Earth Composting Facility Flood Risk and Drainage Statement
Vital Earth Flood Risk and Drainage Statement Final December 2011 Prepared for Vital Earth Ltd Revision Schedule Flood Risk and Drainage Statement December 2011 Rev Date Details Prepared by Reviewed by
More information1.2 This technical note provides a preliminary investigation into the Flood Risk and provides outline drainage strategies.
ODYSSEY MARKIDES TECHNICAL NOTE PROJECT : CHAILEY HOUSE, BLEWBURY JOB NO. : 14-216 NOTE TITLE : PRELIMINARY FLOODING AND DRAIANGE AUTHOR : STEVEN ROOTH APPROVED : ANDREAS MARKIDES DATE : 02/09/2014 1.0
More informationAnglian Water Services Limited. Sustainable drainage systems (SUDS) adoption manual
Anglian Water Services Limited i towards sustainable water stewardship Sustainable drainage systems (SUDS) adoption manual Anglian Water Services Limited 1 Tomorrow s forecast is more frequent, more violent
More informationDRAINAGE MANAGEMENT PLAN. HERTFORDSHIRE RESIDUAL WASTE TREATMENT PLANT Hertfordshire County Council
DRAINAGE MANAGEMENT PLAN HERTFORDSHIRE RESIDUAL WASTE TREATMENT PLANT Hertfordshire County Council EMPLOYER: Veolia Environmental Services (UK) Plc Veolia House 154A Pentonville Road London N1 9PE Copy
More informationAction plans for hotspot locations - Ash Study
Appendix 9 Action plans for hotspot locations - Ash Study Ash Vale North 1. Local evidence indicates the culvert could not discharge during December 2013 because the outlet was blocked on the western side
More informationEssex County Council Flood Investigation Report
Essex County Council Stock City of Chelmsford Rev Date Details Author Checked and Approved By 01 February 2015 Draft report for stakeholder consultation Ed Clarke Flood Investigation Engineer Lucy Shepherd
More informationUrban Flood Modelling
Urban Flood Modelling Adrian J Saul Pennine Water Group Department of Civil and Structural Engineering University of Sheffield a.j.saul@sheffield.ac.uk 1 Need for Integrated Urban Drainage within an integrated
More informationPollution Control NEW! NEW! Stormwater Attenuation Systems Sustainable Urban Drainage Solutions for Domestic & Commercial Applications. klargester.
Pollution Control NEW! NEW! Stormwater Attenuation Systems Sustainable Urban Drainage Solutions for Domestic & Commercial Applications klargester.com Stormwater Attenuation Systems Sustainable Urban Drainage
More informationSUSTAINABLE DRAINAGE IN LEEDS Supplementary Guidance No. 22 JULY 2004
SUSTAINABLE DRAINAGE IN LEEDS Supplementary Guidance No. 22 JULY 2004 BACKGROUND This guidance provides information for developers on the use of sustainable drainage techniques in new developments. It
More informationSustainable Drainage Systems (SUDS) A guide for developers
Sustainable Drainage Systems (SUDS) A guide for developers We are the Environment Agency. It s our job to look after your environment and make it a better place for you, and for future generations. Your
More information1 in 30 year 1 in 75 year 1 in 100 year 1 in 100 year plus climate change (+30%) 1 in 200 year
Appendix C1 Surface Water Modelling 1 Overview 1.1 The Drain London modelling was designed to analyse the impact of heavy rainfall events across each London borough by assessing flow paths, velocities
More informationENVIRONMENTAL STATEMENT: VOLUME 2 APPENDICES 11.1 TO 11.3
NORTH LONDON WASTE AUTHORITY NORTH LONDON HEAT AND POWER PROJECT ENVIRONMENTAL STATEMENT: VOLUME 2 APPENDICES 11.1 TO 11.3 AD06.02 NORTH LONDON WASTE AUTHORITY NORTH LONDON HEAT AND POWER PROJECT ENVIRONMENTAL
More informationFlood Risk Assessment and Drainage Statement
Trinity College, Cambridge Proposed Relocation of Felixstowe Rifle Range, Land north of Nicholas Road, Trimley St Mary, Felixstowe Quality Assurance Site name: Client name: Proposed Relocation of Felixstowe
More informationLittleport Co-located Schools
Littleport Co-located Schools February 2015 Morgan Sindall Littleport Co-located Schools 330763 BNI BSE 003 C P:\Cambridge\Murdoch\EST\PROJECTS\330763 Littleport Co-located Schools\12.0 Documents\12.2
More informationDECEMBER 2008 [ISSUE 2]
PROPOSED DEVELOPMENT WEST SUSSEX FLOOD RISK ASSESSMENT CLIENT: ARORA MANAGEMENT SERVICES LIMITED [ISSUE 2] Warrington Office Cinnamon House Cinnamon Park Crab Lane Fearnhead Warrington Cheshire WA2 0XP
More informationSurface Water Management: Interim Guidance for Developers
Surface Water Management: Interim Guidance for Developers www.shropshire.gov.uk Contents Executive Summary 1. Introduction...1 2. National Policy Context...2 Making Space for Water...2 Future Water...2
More informationBolton s Flood Risk Management Strategy
Bolton s Flood Risk Management Strategy www.bolton.gov.uk Public Summary Bolton s Flood Risk Management Strategy Public Summary Introduction Over 5.5 million properties in England and Wales are at risk
More informationAPPENDIX 9 INFRASTRUCTURE SERVICING REPORT
APPENDIX 9 INFRASTRUCTURE SERVICING REPORT Lot 50 Cockram Street, Mundijong Infrastructure Servicing Report Peet Ltd August 2012 LOT 50 COCKRAM STREET, MUNDIJONG-INFRASTRUCTURE SERVICING REPORT Project
More informationDevelopment at 2 St Albans Road, Kingston, London, KT25HQ
Development at SuDS Report. Prepared for: Report prepared by: Dave Alonso Divine Ideas (UK) ltd Date: August 2015 Project/Issue number: Appendices Attached: 1510/01/SuDS A, B & C Divine Ideas (UK) Ltd
More informationPlanning, Health and Environment Division
18 Planning, Health and Environment Division A Planning Guide to Sustainable Drainage Systems Introduction Working in co-operation with the Environment Agency, Severn Trent Water Ltd., the Highway Authority
More informationCatchment Scale Processes and River Restoration. Dr Jenny Mant Jenny@therrc.co.uk. The River Restoration Centre therrc.co.uk
Catchment Scale Processes and River Restoration Dr Jenny Mant Jenny@therrc.co.uk The River Restoration Centre therrc.co.uk 3 Main Catchment Elements Hydrology Energy associated with the flow of water affects
More informationFLOOD RISK ASSESSMENT
SEVERN ROAD RESOURCE RECOVERY CENTRE FLOOD RISK ASSESSMENT REF 402.0036.00374 September 2009 Severn Road Resource Recovery Centre Ref: 402-0036-00374 Viridor Waste Management i PPS25 Flood Risk Assessment
More informationCreating the environment for business
1. Introduction 1.1 Introduction to Water Cycle Strategies (WCS) 1.1.1 Background The water cycle describes the pathways and processes through which water moves through the natural and built environment,
More informationSTAFF REPORT TO COMMITTEE OF THE WHOLE
STAFF REPORT TO COMMITTEE OF THE WHOLE DATE: November 7 2012 TO: FROM: SUBJECT: ATTACHMENT(S): COMMITTEE OF THE WHOLE GINA LAYTE-LISTON, SUPERVISOR, WASTEWATER Stormwater Management Funding Strategy None
More informationAppendix C - Risk Assessment: Technical Details. Appendix C - Risk Assessment: Technical Details
Appendix C - Risk Assessment: Technical Details Page C1 C1 Surface Water Modelling 1. Introduction 1.1 BACKGROUND URS Scott Wilson has constructed 13 TUFLOW hydraulic models across the London Boroughs
More informationLondon Borough of Merton Local Flood Risk Management Strategy
Local Flood Risk Management Strategy Summary 2014-2020 Introduction In response to the severe flooding across large parts of England and Wales in summer 2007, the Government has recently enacted the Flood
More informationNewbiggin House Farm,
Newbiggin House Farm, Near Waberthwaite Flood Investigation Report 32 Flood Event 30/8/2012 Cumbria County Council Version Undertaken by Reviewed by Approved by Date Preliminary Colin Parkes Anthony Lane
More information11.2 The proposals to deal with the leachate within the closed Lodmoor North Landfill site are assessed in Chapter 10 Geology and Soils.
Chapter Eleven Water Quality, Drainage and Hydrogeology Introduction 11.1 This Chapter considers the impact of the Relief Road on the hydrology of the area and considers both surface and groundwater. Runoff
More informationGroundwater Flooding: a UK Perspective
Groundwater Flooding: a UK Perspective David Macdonald British Geological Survey Maclean Building Crowmarsh Gifford Wallingford OX10 8BB Tel 01491 838800 NERC All rights reserved Talk outline Definition
More informationURBAN DRAINAGE CRITERIA
URBAN DRAINAGE CRITERIA I. Introduction This division contains guidelines for drainage system design and establishes a policy for recognized and established engineering design of storm drain facilities
More information2 ND SEPTEMBER 2014. Report of the Bi-Borough Executive Director for Transport and Technical Services
London Borough of Hammersmith & Fulham COMMUNITY SAFETY, ENVIRONMENT & RESIDENTS SERVICES POLICY & ACCOUNTABILITY COMMITTEE 2 ND SEPTEMBER 2014 SURFACE WATER MANAGEMENT PLAN (SWMP) Report of the Bi-Borough
More informationCLACKAMAS COUNTY ZONING AND DEVELOPMENT ORDINANCE
1008 STORM DRAINAGE (3/24/05) 1008.01 PURPOSE To minimize the amount of stormwater runoff resulting from development utilizing nonstructural controls where possible, maintain and improve water quality,
More informationTravel Time. Computation of travel time and time of concentration. Factors affecting time of concentration. Surface roughness
3 Chapter 3 of Concentration and Travel Time Time of Concentration and Travel Time Travel time ( T t ) is the time it takes water to travel from one location to another in a watershed. T t is a component
More informationR enfrewshire Local Plan. Safe Environment. Page. Flooding & Sustainable Urban Drainage 163 Contaminated Land 175 Noise 177 Major-Accident Hazards 179
R enfrewshire Local Plan Safe Environment Page Flooding & Sustainable Urban Drainage 163 Contaminated Land 175 Noise 177 Major-Accident Hazards 179 16 Flooding and Sustainable Urban Drainage OVERVIEW Flooding
More informationSutton Harbour Holdings PLC. March 2007
Sutton Harbour Holdings PLC March 2007 Contents!! " # # $ % % &'(&'' ) ) ( * + ', *!$ -,!'! #. / $$ #% 00& ' 00&1 $ Executive Summary!! " WSP Development and Transportation has been engaged by Sutton
More information(http://www.molevalley.gov.uk/media/pdf/c/r/srfa_-_updated_jnauary_2012.pdf
Possible Submission about Water and Flooding (See maps 3a and 3b) From Mole Valley Local Development Framework: Strategic Flood Risk Assessment Update 2012 (http://www.molevalley.gov.uk/media/pdf/c/r/srfa_-_updated_jnauary_2012.pdf
More informationINFRASTRUCTURE, FLOOD PROTECTION AND REMEDIATION. Infrastructure Flood Protection Remediation Policies
INFRASTRUCTURE, FLOOD PROTECTION AND REMEDIATION Infrastructure Flood Protection Remediation Policies DRAFT POOLBEG PLANNING SCHEME 196 FIGURE 9.1: UTILITIES WAYLEAVES Electricity Cables 8m Wayleave for
More informationBUILDING SURVEYING 313021
BUILDING SURVEYING 313021 Session topic SUDS - Sustainable Urban Drainage Systems Session objectives To examine various Sustainable Urban Drainage Systems (SUDS) for managing rainwater run-off and discuss
More informationGuidance on the use of sustainable drainage systems (SUDS) and an overview of the adoption policy introduced by
Guidance on the use of sustainable drainage systems (SUDS) and an overview of the adoption policy introduced by Easy guide to Sustainable drainage systems 02 Contents Page Introduction 05 Purpose of this
More information5.14 Floodplains and Drainage/Hydrology
I-70 East Final EIS 5.14 Floodplains and Drainage/Hydrology 5.14 Floodplains and Drainage/Hydrology This section discusses floodplain and drainage/hydrology resources and explains why they are important
More informationLondon Borough Hillingdon. Ruislip Lido Improvement Programme Flood Risk Assessment September 2011. Halcrow Group Limited
London Borough Hillingdon Ruislip Lido Improvement Programme Flood Risk Assessment September 2011 Halcrow Group Limited London Borough Hillingdon Ruislip Lido Improvement Programme Flood Risk Assessment
More informationAPPROVAL AMENDMENT HISTORY
Prepared by: Aurecon South Africa (Pty) Ltd STORMWATER MANAGEMENT PLAN TOKAI ESTATE (DRAFT 1) Submission date: 11 January 2013 Contact Person: Francois du Toit T: +27 21 526 6950 F: +27 21 526 9500 E:
More informationProposed Construction of Basement Flood Risk Assessment. 35 Edwardes Square London W8 6HH
Proposed Construction of Basement Flood Risk Assessment 35 Edwardes Square London W8 6HH 1 Introduction This FRA has been carried out in accordance with the National Planning Policy Statement (NPPF), the
More informationIssue: 2 Adopted by Council: 20/02/07. Directorate of Environment and Regeneration Planning Services
Issue: 2 Adopted by Council: 20/02/07 Directorate of Environment and Regeneration Planning Services LOCAL PLANNIING GUIIDANCE NOTE NO..19:: SUSTAIINABLE DRAIINAGE SYSTEMS Background The provision of adequate
More informationWater and Flooding Position Statement
Derby City Local Plan, Part 1: Core Strategy Water and Flooding Position Statement August 2015 1. Introduction 1.1 This position statement provides an update to the Derby HMA Joint Water Issues Paper which
More informationStrategic Flood Risk Assessment Update 2015
Strategic Flood Risk Assessment Update 2015 On behalf of Contents Glossary... iv Executive Summary... 1 1 Introduction... 4 1.1 Overview... 4 1.2 Future Development in Lewisham Borough... 5 2 SFRA Approach...
More informationSample DEQ Plan Submitter s Checklist for Stormwater Management Plans
APPENDIX IV Version: February 2, 2015 Sample DEQ Plan Submitter s Checklist for Stormwater Management Plans Please fill in all blanks and please reference the plan sheets/pages where the information may
More informationCouncil Strategy DOC/15/86752
Council Strategy Council strategy title: Council strategy owner: Adopted by: Date adopted: July 2015 Document Reference no: Drainage Upgrade Strategy Director Infrastructure Services Bayside City Council
More information06 - NATIONAL PLUVIAL FLOOD MAPPING FOR ALL IRELAND THE MODELLING APPROACH
06 - NATIONAL PLUVIAL FLOOD MAPPING FOR ALL IRELAND THE MODELLING APPROACH Richard Kellagher 1, Mike Panzeri 1, Julien L Homme 1, Yannick Cesses 1, Ben Gouldby 1 John Martin 2, Oliver Nicholson 2, Mark
More informationStormwater management around the world Lessons from Novatech 2010 Dennis Corbett and Marion Urrutiaguer
Stormwater management around the world Lessons from Novatech 2010 Dennis Corbett and Marion Urrutiaguer Novatech 2010, the 7th international conference on sustainable techniques and strategies in urban
More informationAPPENDIX F. RESIDENTIAL WATER QUALITY PLAN: ALLOWABLE BMP OPTIONS
APPENDIX F. RESIDENTIAL WATER QUALITY PLAN: ALLOWABLE BMP OPTIONS The following section provides descriptions, advantages, limitations, and schematics of allowable best management practices (BMPs) for
More informationWelcome Welcome to the public exhibition for development at Bowman Field. This exhibition provides an overview of the proposals for the site.
Welcome Welcome to the public exhibition for development at Bowman Field. This exhibition provides an overview of the proposals for the site. Background & Planning Context The Site The site is an area
More informationReport Relating to Incidents of Flooding within the Dollar Catchment
Joint Position Statement Report Relating to Incidents of Flooding within the Dollar Catchment October 2012 Eric McQuarrie, Scottish Water Stuart Cullen, Clackmannanshire Council TABLE OF CONTENTS 1. INTRODUCTION...
More informationLondon Borough of Croydon Local Flood Risk Management Strategy
London Borough of Croydon Local Flood Risk Management Strategy Summary 2014-2020 Introduction In response to the severe flooding across large parts of England and Wales in summer 2007, the Government has
More informationURBAN STORMWATER GUIDELINES AND BEST MANAGEMENT PRACTICES FOR PROTECTION OF FISH AND FISH HABITAT DRAFT DISCUSSION DOCUMENT
URBAN STORMWATER GUIDELINES AND BEST MANAGEMENT PRACTICES FOR PROTECTION OF FISH AND FISH HABITAT DRAFT DISCUSSION DOCUMENT Contacts: Barry Chilibeck (666-3765) or Megan Sterling (666-2322) Revision 4
More informationChippenham Surface Water Management Plan Intermediate Assessment of Groundwater Flooding Susceptibility
Chippenham Surface Water Management Plan Intermediate Assessment of Groundwater Flooding Susceptibility Phase 1 & 2 November 2011 Prepared for Revision Schedule Surface Water Management Plan Intermediate
More informationFLOOD RISK RECENT TRENDS AND POLICY RESPONSES
FLOOD RISK RECENT TRENDS AND POLICY RESPONSES DEVELOPING WESTMINSTER S LOCAL PLAN Booklet No. 2 LDF Consultation - CMP Revision November 2013 INTRODUCTION CLLR ROBERT DAVIS Westminster is at risk of flooding
More informationORCHARD WAY / BROOM GROVE Knebworth
ORCHARD WAY / BROOM GROVE Knebworth Technical Assessment Report to support Section 19 Flood Investigation Project No: Date: Reviewed By: Approved By: 0469 October 2014 Tom Butler Neil Harding NHTB Consultancy
More informationFort Dodge Stormwater Master Planning. Prepared By: Ralph C. Stark, Jr., P.E., C.F.M. Joel N. Krause, P.E., C.F.M.
Fort Dodge Stormwater Master Planning Prepared By: Ralph C. Stark, Jr., P.E., C.F.M. Joel N. Krause, P.E., C.F.M. Project Location Project Background Flooding History Localized flooding and storm sewer
More informationLand Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department
Land Disturbance, Erosion Control and Stormwater Management Checklist Walworth County Land Conservation Department The following checklist is designed to assist the applicant in complying with the Walworth
More informationUPDATED FUNCTIONAL SERVICING and STORMWATER MANAGEMENT REPORT
TRAFALGAR ENGINEERING LTD. #1-481 Morden Road Oakville Ontario L6K 3W6 UPDATED FUNCTIONAL SERVICING and STORMWATER MANAGEMENT REPORT Fernbrook Homes (Bronte 15) Limited 3059/3047 Lakeshore Road West TOWN
More informationFlood Risk Assessment Breakspear House, Hemel Hempstead. Kier Property. October 08
Flood Risk Assessment Breakspear House, Hemel Hempstead. Kier Property October 08 Prepared by:... Approved by:... Simon Marcos Keith Searle Principal Engineer Associate Director Flood Risk Assessment Rev
More informationPervious Pavers. By: Rich Lahren. Hebron Brick & Block Supply
Pervious Pavers By: Rich Lahren Hebron Brick & Block Supply Stormwater Management and Control Issues Past emphasis was on flood control Today s emphasis is also on pollution More impermeable areas are
More information3.4 DRAINAGE PLAN. 3.4.1 Characteristics of Existing Drainages. 3.4.2 Master Drainage System. Section 3: Development Plan BUTTERFIELD SPECIFIC PLAN
3.4 DRAINAGE PLAN This section describes the existing onsite drainage characteristics and improvements proposed within this Specific Plan. Following this description, drainage plan development standards
More information4 Water supply description
4 Water supply description A description of the drinking-water system is equally applicable to large utilities with piped distribution systems, piped and non-piped community supplies, including handpumps
More informationHIGHWAYS. Drainage design on M25 motorway widening project (J16 - J23) Brijesh Vats
Drainage design on M25 motorway widening project (J16 - J23) 76 Brijesh Vats Drainage Engineer Highways & Transportation Abstract Drainage design on the M25 motorway comprises complex drainage networks
More informationScheduling Maintenance for Infiltration Basins and Trenches
Visual Inspection for Infiltration Practices Visual inspection is a rapid assessment procedure for qualitatively evaluating the functionality of a stormwater best management practice (BMP). Visual inspections
More informationEstimating Potential Reduction Flood Benefits of Restored Wetlands
Estimating Potential Reduction Flood Benefits of Restored Wetlands Kenneth W. Potter University of Wisconsin Introduction Throughout the summer of 1993 a recurring question was the impact of wetland drainage
More informationLand to the rear of the Black Bull Public House Flood Risk Assessment March 10, 2014 Version 1.0 Ref: RAB 148
Land to the rear of the Black Bull Public House Flood Risk Assessment March 10, 2014 Ref: RAB 148 Lindsey Phillips Turnbull Tweedale Ltd 61 Oaken Lanes Codsall South Staffordshire WV8 2AW R A B C O N S
More informationCITY OF CHARLOTTE STORM WATER SERVICES CREDIT APPLICATION INSTRUCTION MANUAL
CITY OF CHARLOTTE STORM WATER SERVICES CREDIT APPLICATION INSTRUCTION MANUAL March 2008 A note to recipients of the Charlotte-Mecklenburg Storm Water Services Credit Application Manual: This is the second
More informationInterlocking Concrete Pavement Institute (ICPI) Model Stormwater Ordinance for Permeable Interlocking Concrete Pavements August 2010
Interlocking Concrete Pavement Institute (ICPI) Model Stormwater Ordinance for Permeable Interlocking Concrete Pavements August 2010 Background What are permeable interlocking concrete pavements (PICP)?
More informationTo prevent increased stormwater runoff entering Council s drainage system and causing overloading of the system that in turn might cause flooding.
Background & Issues To provide guidelines and requirements for Developers, the Community and the Shire s Planning and Sustainability officers for connection to the Shire s Stormwater Drainage Disposal
More informationChapter 2 Spatial Portrait
15 November 2013 Dear Julie Fylde Local Plan to 2030 Part 1 Preferred Options Thank you for the opportunity to meet with you on 9 October in respect of the above mentioned document. As discussed at the
More informationProject Manager. Geoff Masotti, P.Eng. T. 905.940.6161 Ext. 254 T. 905.940.6161 416.987.6161
Rainbow Creek Master Plan Update Study The City of Vaughan june 2014 COLE ENGINEERING GROUP LTD. 70 Valleywood Drive Project Manager. Geoff Masotti, P.Eng. Markham, ON CANADA L3R 4T5 T. 905.940.6161 Ext.
More informationPost Construction Stormwater Management Checklist Program
Post Construction Stormwater Management Checklist Program Anahid Damerau, CPESC, CPSWQ Christopher Smith, P.E. Department of Environmental Protection Stormwater Section Watershed Management Program The
More informationStormwater Management Functional Servicing Report
Stormwater Management Functional Servicing Report Part of Lot 12, Concession 10 Township of Cavan Monaghan Ian Cameron Rural Subdivision Engage Project No. 14016 Engage Engineering Ltd. January 7, 2015
More informationA Developer s Guide: Watershed-Wise Development
A Developer s Guide: Watershed-Wise Development Environmental Protection What is a watershed? It does not matter how far away you build from a creek, lake, or the ocean, you are in a watershed. Another
More informationSTORMWATER MANAGEMENT CHECKLIST
STORMWATER MANAGEMENT CHECKLIST *This checklist must be completed and part of the Land Disturbing Permit submittal for review if the acreage disturbed is one (1) acre or more: I. SUPPORTING DATA Narrative
More informationSample Micro Hydro Initial Report
Sample Micro Hydro Initial Report Sample Micro Hydro Initial Report Introduction The Hydro Burn at Glen Water was visited by Richard Haworth of Glen Hydro to assess its suitability for a micro hydro installation.
More informationON-SITE STORMWATER DETENTION TANK SYSTEMS TECHNICAL GUIDE
ON-SITE STORMWATER DETENTION TANK SYSTEMS TECHNICAL GUIDE This page is intentionally left blank Contents 1 Introduction 1 11 Background 1 12 Requirements for Managing Peak Runoff at Source 1 13 On-site
More informationSite Deliverability Statement Development at: Beech Lane, Kislingbury. Persimmon Homes Midlands March 2015
Site Deliverability Statement Development at: Beech Lane, Kislingbury Persimmon Homes Midlands March 2015 Contents Site Deliverability Statement Development at: Beech Lane, Kislingbury 1.INTRODUCTION 1.1
More informationFlood Risk Management in Southwark
Flood Risk Management in Southwark 1 Presented to Borough & Bankside Community Council 25 th April 2012 By Flood and Drainage Team Agenda Item 11 IN BRIEF Background Legislation What have we done? What
More informationProduct 4 (Detailed Flood Risk) for: Sam Murray (Amey) Site: Land at Kingsnorth Reference: KSL151125 KR79 Date: 30 th November 2015.
Product 4 (Detailed Flood Risk) for: Sam Murray (Amey) Site: Land at Kingsnorth Reference: KSL151125 KR79 Date: 30 th November 2015 Contents Flood Map Confirmation Flood Map Extract Model Output Data Data
More informationPresentation on Flood Risk Management To Engineers Ireland 12 th February 2014. David Keane Cork County Council
Presentation on Flood Risk Management To Engineers Ireland 12 th February 2014 David Keane Cork County Council 1 Contents 1. The Power of Water 2. Defenses 3. Flooding & Flood Types 4. Flood Mitigation
More informationComputing Stormwater Runoff Rates and Volumes
New Jersey Stormwater Best Management Practices Manual February 2004 C H A P T E R 5 Computing Stormwater Runoff Rates and Volumes This chapter discusses the fundamentals of computing stormwater runoff
More information