1 Alternative Construction Delivery Methods By: Jody Becker and Tim Murphy 1

2 1. Introduction One of the key purposes of any contract is to allocate risks and benefits between the parties to the contract. In the construction context, various project delivery methods have been developed to deal with the different ways, owners, developers, contractors, consultants and public entities view and accept risk. For the construction solicitor the objective then is to ensure that the form of contract and its drafting properly allocate the risks associated with the project to the party who has accepted and has been (or will be) compensated for bearing the risk. In determining who should assume any particular risk in a project the commercial parties need to understand what those risks are and who is most able to control, manage, avoid or mitigate those risks. Their solicitors then are assigned the task of taking the commercial deal and drafting language to ensure that the risk allocation is properly reflected in the documents. The solicitors are also responsible for ensuring that their individual clients do not inadvertently accept risk for which they are not being compensated or in relation to which they are not in control. Project delivery methods have evolved to deal with the many ways in which contracting parties wish to allocate their risk, from the traditional stipulated price/ general contract to the development of alternative financing and procurement methods including P3 models. Each delivery method has its advantages and disadvantages, and it is the role of the construction solicitor to ensure that his or her clients are protected to the greatest extent possible against the risks that they have chosen to accept. 2

3 2. Stipulated Price/ General Contracts In considering alternative delivery methods, it is useful to look briefly at how a traditional project is structured. The traditional stipulated price or general contract project structure relies upon the owner first contracting with the consultant, who is responsible for the project s design, including detailed drawings and specifications, preparation of the bid package or Request for Proposals (where appropriate) and, in some part, for the supervision and administration and certification of the work performed under the construction contract. The consultant s contract is most often a fixed price and date certain contract. Through the consulting agreement, the owner gains the benefit of the consultant s experience and expertise. Once the design has been completed and the work offered for tender or proposal, the owner will retain the general contractor, who is wholly responsible for the construction of the project in accordance with the consultant s design. The contractor under this procurement method accepts Owner Consultant General Contractor Subconsultant Subconsultant Subcontractor Subcontractor Subsubconsultant Subsubconsultant Subsubcontractor Subsubcontractor Figure 1 - Traditional project delivery 3

4 the responsibility and risks for the construction means and methods and for the performance of the various subcontractors that it retains. This structure is commonly referred to as a Design-Bid-Build project since each of these phases is undertaken separately. Throughout each component of the project, each of the parties will subcontract with various other consultants, trades and suppliers in order to fulfil their obligations. The consultant will often subcontract portions of its scope of work to consulting engineers and architects, including environmental, structural, electrical and geotechnical specialists, who will work collectively to complete the design tasks for which the consultant was retained. In addition, the contractor will retain subcontractors and suppliers of various specializations who will supply labour and materials to the project. The owner reduces its risk by entering into single contracts for each of the design and construction of the project and has a single point of contact in respect of each of these obligations. The consultant and the contractor mitigate their own risks by assigning portions of their scope to subcontractors and assume other risks in relation to the management and supervision of their trades. The advantages of the stipulated price contract are several. The traditional project structure is the one with which most people are familiar, and most owners, consultants and contractors understand their roles and obligations under this structure. The completion of the design in advance of the bidding process allows for greater certainty for the contractor in fixing the price and for the owner in budgeting and financing the project. As well, standard form contracts have been created to simplify these types of projects and add further certainty and familiarity to the process. 4

5 However, the separation of the design and construction phases also has the disadvantage of slowing the progress of the overall project. The contractor and the consultant do not work together on the design of the project, which can give rise to conflicts when the design is being interpreted during construction. In addition, where the consultant also acts as the owner s representative on site, and interpreter of its own design documents an inherent conflict of interest arises. The consultant will have a bias in favour of its own interpretation of the contract documents rather than that of the contractor. Finally, the owner may assume greater risk in this model if it has not adequately accounted for and allocated the risk as between the consultant and contractor. 3. Construction Management The construction management framework is similar in many respects to a traditional construction contract. The difference comes by way of the introduction of the construction manager, who takes the place of the general contractor and has a modified role. In a Owner Construction Manager Consultant Contractor Contractor Subconsultant Subconsultant Subcontractor Subcontractor Figure 2 - construction manager Not-at-Risk 5

6 pure construction management structure, the owner again contracts with a consultant to prepare a design and contract documents. Simultaneously, or subsequent to the completion of the design the owner will also contract with a construction manager as its agent for the management of the project. The construction manager s role is predominantly one of advisor and administrator. In addition to assisting the owner with tendering and the selection of the various contractors who will complete the work, the construction manager will also administer the trade contracts (a role assumed by the contractor in a traditional project). The construction manager may be responsible for creating the project schedule and may assist the owner in developing the project budget. The owner relies on the technical knowledge of the construction manager. Depending on the expertise and experience of the owner, the construction manager may perform many of these functions with minimal oversight from the owner. The retention of the construction manager in the early stages of the project allows the construction manager to assist the owner in its interactions with the consultant regarding the design of the project. In addition, a construction manager can begin to engage trades and suppliers for some aspects of the project before the design is completely finalized. The key difference between a traditional project and a construction management project is that the owner retains privity with the trade contractors and therefore retains the risk for ensuring their contractual obligations are fulfilled. The construction manager acts as the owner s agent and is typically paid for the cost of its work together with an agreed fee. This structure means less risk for the construction manager, particularly in relation to defects and deficiencies within the subcontracted work. Generally the construction manager is only liable for these deficiencies if they arose from the construction manager s failure to properly supervise or coordinate the project. For this reason, this structure is also commonly known as construction 6

7 manager Not-at-Risk. However, as the owner s agent, the construction manager must operate within the confines of the authority the owner has bestowed upon it. Where the construction manager exceeds its authority, the owner will hold the construction manager liable. This structure also has the effect of increasing the owner s exposure to contractual risk arising from the contractual complexity of the project. As the owner essentially takes on the role of the general contractor, the owner assumes the risks of the contractual relationships with the trades. In addition, the owner often provides an indemnity to the construction manager in relation to any claims made by the subcontractors with whom the construction manager contracted as agent. Conversely, under this structure, the construction manager would rarely indemnify the owner for claims beyond those arising from the construction manager s failure to properly manage the project. The advantage of this structure is that the owner and the construction manager as its agent are, for the most part, aligned in their interests. However, because the construction manager is not directly responsible for the subcontractor costs, there may be little incentive for the construction manager to seek out all possible cost savings. A common variant of the construction management delivery system is referred to as construction manager At-Risk. As can be inferred from its name, the difference here is the nature of the relationship between the owner and the construction manager and the way in which the project s risk is apportioned between them. While a construction manager At-Risk continues to act as the owner s advisor on technical matters, the owner contracts only with the construction manager who contracts directly with the trades and suppliers. Under this model, the construction manager s role is expanded and resembles the role of a general contractor in a traditionally delivered project. Specifically, the construction manager assumes two types of risk: the obligation to manage the project and act as the owner s representative; and, the obligation to 7

8 Owner Construction Manager Consultant Contractor Contractor Subconsultant Subconsultant Subcontractor Subcontractor Figure 3 - Construction Manager At-Risk perform own force s work and prevent subcontractor default. The owner gains the benefit of having a single point of contractual interaction with the construction manager and lessens its exposure to risk. Construction Manager vs. General Contractor For owners without expertise or experience in the construction industry, the involvement of a construction manager is usually a benefit. It will be the construction manager s obligation, whether At-Risk or not, to guide the owner through the construction process from the very early stages of a project. Some of the major advantages to using the construction management project delivery system are as follows: (i) Expertise The construction manager will be selected for its expertise in relation to technical matters on complex projects. As the construction manager will often be engaged early in the 8

9 design phase, it can also provide advice and industrial expertise to the owner in relation to the performance and obligations of the consultant. If provided with access to the preliminary design, the construction manager can assist the owner and the consultant in avoiding the risk that the design has constructability issues or will significantly increase the owner s costs. (ii) Fast-tracking Construction management can be used to fast-track a project to completion. As a result of the construction manager being involved in a project from its inception, it may be possible for portions of the work, such as excavation or foundation work, to be tendered and commenced before the consultant s design is finalized. This effectively allows the work to proceed while the balance of the design is being completed. However, the risk in this approach is in respect of the integration of the ongoing design with the work that has already been performed. The consultant will not have the ability to amend the initial stages of the design, where the work has already been performed. (iii) Control With the assistance of a construction manager, the owner is able to exert a significant degree of control over both the project s budget and schedule. Budgetary control can be augmented by the construction manager s ability to advise the owner at the design stage of any potential cost or constructability issues and to resolve them prior to the design being finalized. Similarly, the owner and construction manager have significant flexibility to schedule the subcontracted work as needed and as construction advances. 9

10 (iv) Cost Where the construction manager is Not-at-Risk, the owner maintains the risk for the subcontractors and for their completion of their work. However, as a result of the owner retaining this risk, it should expect some cost savings as a result. There are also disadvantages to using construction management: (v) Complexity While a construction manager can be of great assistance in engaging and managing the various trades and suppliers, there may be an increase in the level contractual complexity over that on a project delivered under a stipulated price general contract. Despite the involvement of the construction manager in the management of the trades, the owner retains the ultimate risk in relation to the payment of trades and addressing their individual concerns. The owner also bears the risk of subcontractor default. While some of the complexity can be handled by having a construction manager who is actively involved in managing communications with the trades, the owner is still legally bound to each of the contracting parties and subject to the complexity that that entails. (vi) Cost As discussed above, the total cost for a construction management project will often turn out to be less than that of a similar project delivered traditionally (depending, of course, upon whether the risks the owner assumes will occur). This benefit however, comes with the caveat that whereas in a traditional project it is often possible to have price certainty as of the bid stage, in a construction management project such price certainty will be rare. Since the 10

11 construction manager and the owner are responsible for engaging and negotiating individually with each trade and supplier, it will be nearly impossible to definitively ascertain the total price until all of the trade and supply contracts have been negotiated. In addition, the owner may not be aware of what the construction manager s reimbursable expenses will be at the outset of the project and will have to ensure that these expenses are managed appropriately. (vii) Risk Much of the risk that in a traditional project is borne by the general contractor will be borne by the owner in a contract management project. While each of the individual trades and suppliers will continue to be responsible for the completion of their tasks, the owner will be at risk for the completion of the project generally. The owner will typically be responsible for procuring necessary insurance for the project and may also be responsible for providing other project security in the form of bonds or subcontractor default insurance. Furthermore, since the owner is filling the role traditionally held by the general contractor and, as a result, will be retaining the services of multiple service providers on the site, the owner will incur the added responsibility of being the constructor under the Occupational Health and Safety Act. This means that the obligations of compliance will rest directly with the owner. Employing a construction manager At-Risk can mitigate some of these disadvantages, though that benefit is tempered by a reduction in the advantages that are enjoyed. While the risk apportionment using a construction manager At-Risk is similar to that in the traditional delivery system and it may not be possible to contract in advance with the 11

12 construction manager for a guaranteed maximum price. As such, the cost savings that are possible when the construction manager is Not-at-Risk will not be available. 4. Design-Build Under the design-build approach, the owner typically seeks competitive bids based upon a set of project performance requirements or specifications. The owner then retains a single entity who is responsible for both design and construction. This approach has several advantages over more conventional approaches. From a practical perspective, the design and construction companies will be integrated from the very early stages of the project. This integration will provide the opportunity for considerable interaction and discourse between the architect or engineer and the contractor during the design phase of the project. As a result, the project may be expedited. The contractor will be able to commence construction with the understanding of how the design has progressed and how it is proceeding with the potential to save both time and cost. There is also often a reduction in the number and severity of conflicts between the design and construction entities since they will be, in essence, on the same team. While these potential benefits also exist under the construction management delivery system, the increased integration between the designer and contractor under a design-build contract will serve in many cases to augment these advantages. From a risk-allocation point of view, the owner benefits by being able to off-load the design risk as well as the on-time, on-budget and performance requirements to a single entity. This structure also offers many of the same cost saving features found in construction management projects, particularly those with the construction manager At-Risk. 12

13 Due to the intersection of the design and construction teams, the project developer can expect cost savings through a more efficient delivery of the project. In addition, since the project is delivered by a single entity with whom the owner negotiates at the outset of the project, it will be possible for the owner and the design-builder to agree upon a fixed price contract for the entire project. This, in turn, may lead to advantages for the owner when negotiating with the project s financiers, who will be more receptive to a project with a lower risk of unanticipated costs. However, while the potential for cost certainty in the early stages is an advantage, this is tempered by the risks that preliminary specifications can impose on a project. The owner will have less involvement in the overall and detailed design of the project and may only comment on whether the design meets with the general specifications to which the designbuilder bid. As well, the design-builder will often be the judge of the quality of its work. It may also be difficult to accurately price a project before the design has been fully completed. For this reason, cash allowances are often built in to design-build contracts. From the design-builder s point of view, this delivery method adds the obvious increase in risk for the design. Unlike traditional projects where design risk remains with the consultant, under this structure the design-builder will be held liable for an overall failure of the design as well as the defects in construction. Design-builders will also need to ensure that the owner s expectations regarding the finished product, including any specific performance, fitness for purpose or design objects are clear before entering into the contract. For these reasons, design-build contracts are particularly well suited to so-called turnkey projects those where the owner contracts for a finished product and awaits complete delivery. This is especially true of projects that can be executed from standardized designs that 13

14 require little or no modification and can be built to established and proven performance levels. Using this model on such projects will reduce the pricing risk which will provide greater certainty for the owner in relation to the finished product. 5. Engineering, Procurement and Construction Contracts a Form of Design - Build Engineering, procurement and construction (EPC) contracts are structured very similarly to the turnkey design-build contract. EPC contracts are commonly used in the construction of larger-scale project-financed infrastructure and energy projects. To take the example of a wind farm project, the project entity, which contracts with the government authority under a power purchase agreement (a PPA ) to supply power, will then enter into an EPC contract. This contract will govern various elements of the construction of the wind farm from manufacture of the blades and towers and assembly of the nacelles and hubs and construction of the balance of the plant comprising civil and electrical works. Obviously, other contractual approaches can be taken to construct a wind farm, such as having a separate supply contract for the wind turbines, a separate design agreement and a construction contract with or without a further project management agreement. The choice of contracting approach will depend on a number of factors including the time available, the lenders requirements and the identity of the contractor(s). The major advantage of the EPC contract over the other possible approaches is that it provides for a single point of responsibility and a single point of contact between the project developer and the contractor. As opposed to a more traditional delivery method and the construction management systems described above, EPC delivery systems rely on a single entity that contracts with the owner to design, build and procure the key elements of the project. 14

15 This structure is generally preferred by project developers and their lenders because of the project finance structure. This non-recourse (or more often limited recourse) structure means that lenders will be looking for the following key terms: Owner EPC Entity / Design-Builder Consultant Contractor Contractor Subconsultant Subconsultant Subcontractor Subcontractor Figure 4 - EPC / Design-Build a fixed completion date; a fixed completion price; no or limited technology risk; performance guarantees; liquidated damanges for both delay and performance; security from the contractor and/or its parent 15

16 large caps on liability (ideally, there would be no caps on liablity, however, given the nature of EPC contracting and the risks to the contractors involved there are almost always caps on liability); and restrictions on the ability of the contractor to claim extensions of time and additional costs. An EPC contract delivers all of these requirements in one integrated contract. These provisions are crucial to ensuring the bankability or financeability of a project One key risk allocation in the EPC contract that distinguishes it from a standard construction contract is the requirement to comply with a performance standard and a performance specification. The project developer will be looking to the EPC contractor to deliver a project to it and to the operator that performs up to the requisite power production standards. Obviously, the performance specification and the performance criteria overlap and a delicate balance must be struck between the two to ensure an effective risk allocation to the contractor. Part of the EPC contractor responsibility will include obtaining compliance certificates in respect of turbine performance and EPC contractors will need to be aware of this and related compliance risks when entering these contracts. In addition, the obligation to meet a fixed completion date may be a difficult challenge if turbines and/or other crucial project components are not readily available. Turbine or solar panel supply contracts may have to be separately negotiated aspects of the EPC contract as backlogs in availability of these items are common. Another key provision in EPC contracts relates to commissioning and testing regimes. The testing regime under the EPC contract must be set so that it also matches the 16

17 testing and commissioning requirements under the PPA. In addition, technical compliance requirements, such as meeting electricity safety standards, are generally the obligation of the EPC contractor, which increases contractor risk. As a result of the significant risk transfer and the highly technical nature of the subject matter of EPC contracts, many contractors will not undertake them. Any contractor considering an EPC contract should ensure it understands the risks and ensure that its counsel has reviewed the proposed contract in detail. 5. P3 Projects The advent of public-private partnerships (P3) has altered the risk allocation in public infrastructure projects between parties in both the public and private sectors. While there is a vast array of models for P3 or alternative financing and procurement (AFP) projects, at a basic level all these projects will involve parties from both the public and private sectors and a realignment of project risks (and potential rewards) between the stakeholders. In a typical P3 arrangement the private sector assumes risk that would normally be borne by the public sector on a traditionally delivered project. In the continuum of project delivery methods, a P3 contract shares similarities with the EPC model with owner-like project management and financing obligations added. The P3 delivery method was developed in the United Kingdom on the basis that they could provide demonstrable value for money and increased accountability compared to either privatization or traditionally procured government infrastructure projects. The advantages for the public sector in entering into a P3 arrangement are several. Generally speaking, the aim of these delivery models is to develop and manage all project costs in an integrated fashion over the 17

18 entire project life (construction, lifecycle and operations) in order to achieve optimal cost allocation. In addition, through the various risk allocations set out in these models, the private sector is able to minimize their exposure to cost-overruns, increased financing costs and delay costs. By placing the burden for these risks on the private sector, the public sector achieves its goal of completing large infrastructure project on time and on budget. In addition, the public sector may be unable or unwilling to allocate funds to develop a project, or may wish to defer the substantial capital cost of an infrastructure project. Under certain circumstances the private sector may be better able to secure financing for the initial development of an infrastructure project. By enabling the private sector to pick up the front-end costs of development and spread the cost to the public sector over the life of the project, P3 arrangements can increase the capacity of cash-strapped governments to embark on several projects simultaneously. P3s are increasingly seen as a cost-effective alternative to traditionally delivered projects due to the possibility of more creative financing and delivery solutions generated by the private sector entities who bid them in a competitive process. There are a wide range of contractual structures used in P3 projects. For most analysts, true P3s require two key factors: private sector financing and integrated design and lifecycle obligations. However, as these projects tend to be very large and complex, categorizing them is difficult. It is nevertheless possible to describe some of the typical structures, while noting that many projects will in reality use a structure that falls between, or combines two or more of the following: 18

19 (i) Build-Finance In build-finance projects, the private sector assumes responsibility both for financing and building the project. The build-finance developer is responsible for securing sufficient financing and for working with the contractor to arrive at a viable construction price in order to put forward a competitive bid. Typically, the developer will be a special purpose entity (SPE) who will contract directly with the lenders for the financing of the project and with the contractor for its construction. The SPE is usually a corporate alter ego of the contractor. Only once construction is finalized and certified by both the private lenders and the public sector as complete, will the public sector entity pay for and take ownership of the project. The build-finance delivery model is the most similar to traditional (non-p3) project delivery. The major differences are that the project is financed by private sector lenders and the borrower is a private sector SPE. While the benefits are the potential for cost savings and risk transfer away from the public sector, one major criticism of this model is that is that the public sector can borrow funds at more economical rates. Particular jurisdictions deal with this concern in different ways and proponents of the delivery system assert that the competitive process, together with the implementation of a transparent risk-transfer model ensures an overall benefit for the ultimate financiers, the taxpayers. (ii) Design-Build-Maintain (DBM) Another permutation of the P3 model is the design-build-maintain project. In this scenario the private sector assumes responsibility for the design and construction of the project. After construction is complete, the public sector takes ownership, but the private sector entity continues to maintain the constructed facility under an ongoing maintenance agreement. 19

20 (iii) Design-Build-Finance-Maintain (DBFM) In a design-build-finance-maintain project, in addition to design and construction of the facility, the private sector is responsible for the financing the project. As in the designbuild-maintain model, once construction is complete, ownership of the facility goes to the public sector but the facility is maintained privately under an ongoing maintenance agreement. (iv) Design-Build-Finance-Operate (DBFO) In another variation, the design-build-finance-operate model sees the private sector, after having designed and built the facility with private financing, continue to operate and maintain it for the duration of the concession period, which may be 30 years or more. Only after the agreement has expired does ownership of the facility revert to the public sector. (a) Risk allocation overall In a P3 project, the risk assumed by the private sector participants will generally extend beyond that of a conventional construction project. In a P3 arrangement where the project is financed by a private sector SPE, the risks associated with financial obligations will fall on that entity. However, in order for lenders to loan funds to what is typically a minimally capitalized SPE, sufficient security is required, including such things as assignment of contracts, parent company guarantees, insurance and bonding. Given the complexity of these projects and their economic scale, the transfer of these financial obligations is a risk that only large well positioned developers and contractors can accept. Smaller developers and contractors are not typically parties to these types of transactions. 20

21 In addition, depending on the P3 project model implemented, the responsibilities of the private sector participants will often extend well beyond the construction phase of a project into maintenance or operation of the facility. The extended duration of these projects gives rise to additional risk for the developer participants. (b) Risk transfer to the contractor With respect to construction risk, the contractor will be responsible for the usual risks associated with any project. These obligations will include defects and deficiencies in construction, scheduling issues, site health and safety, labour, materials and construction equipment. However, since P3 projects tend to projects of a significant size (i.e. hundreds of millions of dollars), there is an increased risk on the contractor to accurately price the scope of the work. A mistake in pricing could have serious impact on even the most robust contractor. Additionally, the contractor may become responsible for bearing additional risk that arises as a result of the unique nature of the P3 arrangement. The contractor will often be asked to take on risks related to site conditions, resource availability, equipment procurement and installation, permits and approvals, labour, changes in law and force majeure, which risks under a traditional project would have remained with the owner. Moreover, since the private sector s involvement in the project will often last much longer than the construction period, as in a P3 with a maintenance or an operational concession period, the risks relating to the ongoing private sector involvement will need to be apportioned among the private sector participants. It will be the objective of the solicitors involved in structuring the project to align these risks with the party most able to manage and mitigate them. Some of the risk will fall to the contractor, even though its direct involvement in 21

22 the project might otherwise end with the facility s successful construction. While the contractor will sometimes remain involved in the project during the concession period, in a maintenance capacity or otherwise, the contractor typically retains all risks associated with construction warranty obligations and latent defect issues. The contractor s involvement may also be protracted where the contractor has an interest in the SPE. Lenders will want to ensure that very few to none of the risks transferred to the SPE through the P3 agreement are stranded in the SPE. Obviously, as risks are dropped down from the SPE to the construction company and the operator or service-provider, there exists a requirement that the transferred risks be covered appropriately between the operator and the constructor. This is addressed by way of an interface agreement between the key contracting entities within the project structure. The interface agreement and the respective dropdown agreements will also include an equivalent project relief provision, which contractors should understand. The EPR principle is simple in concept and may be challenging in practice: the construction contractor and service provider are only entitled to relief under their respective agreements to the extent that the SPE obtains any relief under the main project agreement. (c) Contractor as consortium lead/participant The risks and responsibilities assumed by the contractor will vary depending on the role that it plays in the consortium of private sector participants engaged for the project. Where the contractor assumes the dual role of developer/ contractor or that of lead member of the consortium, it will be exposed to additional risk and carry additional responsibilities. The contractor, acting as consortium lead, will often take primary responsibility for negotiating the terms of the arrangement between the consortium and the public sector entity. 22

23 Among other things, this will entail negotiating with consortium team members, including equity contributors and service or operations subcontractors. The contractor may also be involved in retaining the various professional advisors including consortium counsel, financial model auditors, tax advisors, accounting advisors, lender counsel and lender technical and insurance advisors. Further, the consortium lead will often be responsible for developing term sheets and negotiating final credit and equity contribution agreements with the project s financiers. One issue that contactors and their counsel will need to pay particular attention to occurs when a contractor has an equity stake in the consortium. Here, there is the potential for a difference in interests between the contractor as contractor and as equity participant. The equity in the deal will want to ensure that as many risks are passed onto the contractors as possible so that obligations of damage repair, for example, or liquidated damages are met by the responsible contractor and not by equity injections. (d) Subcontractors Due to the strict timelines and technical expertise required in many P3 projects, highly specialized subcontractors will often be required. For these large scale projects, particular subcontracts including those for the mechanical and electrical work which may be a significant percentage of the overall cost of the project, with subcontract values of $50 million or more. As such, the expertise and experience of these subcontractors or suppliers will be essential for the successful and timely completion of the project. It will therefore be of critical importance to ensure that the construction contract and subcontracts have a mechanism to address the withdrawal or default of such key parties. The contractor will also often look for substantial 23

24 security from these subcontractors, in the form of bonding, insurance, indemnities and liability for liquidated damages arising from their delay. (e) Design risk Except where the public sector takes responsibility for the design of the project, as in the build-finance model, the design risk will also fall to the private sector participants. The proponent will assume responsibility for the constructability, completeness and coordination of the design, as well as any conflicts or interferences in the design documents. Depending on the structure of the consortium, the design risk might be allocated to an architect/engineer, or shared more widely amongst the participants. However, regardless of who is responsible for design risks, a project that calls for an ongoing maintenance or operational component, will increase the risk assumed by the design professionals, particularly as it relates to fitness for purpose requirements. A poorly designed project might, for example, perform acceptably but have exorbitant maintenance costs, placing disproportionate burden on the party charged with ongoing maintenance. Ensuring that the risks associated with the ongoing consequences of the project s design are assigned to the appropriate party will ensure that the parties in the position most able to offset the risk are those who have the incentive to do so. (f) Key differences in role of architect/consultant Under the P3 model, the public sector will transfer to the private sector not only the risk of the design of the project but also the administrative oversight of the project, the role typically assumed by the consultant. The project consortium will be responsible for retaining on behalf of the owner a consultant or independent certifier who will act as the owner s representative during the course of the project and who will provide to the owner reports and 24

25 evaluations on the work being performed. The independent certifier will also advise the owner with respect to whether the project is on schedule and whether any significant problems have arisen during construction. In addition, the independent certifier may have a role to play in the resolution of disputes between the consortium and the government sponsor of the project. However, because these projects are typically financed privately, the owner s independent certifier will not be the payment certifier for the project. The consortium will be required by its lenders to retain an independent third party valuator. This valuator, or technical advisor will be retained in the early development of the project and will also undertake responsibility for thorough due diligence and oversight to ensure problems are identified and resolved. The lenders technical advisor will be responsible for ensuring that the work performed is in accordance with the contract documents, for certifying payments and for confirming the achievement of particular project milestones, including substantial performance of the work. Conclusion The varying ways in which risk can be transferred to a construction contractor is limited only by the creativity of counsel and the relative bargaining power of the contractor and owner or developer. However, in certain areas such as P3-based public infrastructure procurement and energy development certain contractual models have evolved which include significant new risk for the unwary contractor. Understanding the basic structure and getting good advice before you sign on the dotted line are crucial elements of ensuring that the project is priced accurately and that only the appropriate risks are assumed. 25

STRUCTURING AND MANAGING CONSTRUCTION RISKS IN PUBLIC PRIVATE PARTNERSHIPS

STRUCTURING AND MANAGING CONSTRUCTION RISKS IN PUBLIC PRIVATE PARTNERSHIPS STRUCTURING AND MANAGING CONSTRUCTION RISKS IN PUBLIC PRIVATE PARTNERSHIPS BY: TIMOTHY J. MURPHY PARTNER MCMILLAN LLP - 2 - STRUCTURING AND MANAGING CONSTRUCTION RISKS IN PUBLIC PRIVATE PARTNERSHIPS Introduction

More information

The FIDIC Suite of Contracts

The FIDIC Suite of Contracts Less well know FIDIC contracts are also available such as the Turquoise Book for Dredging and Reclamation Works published in January 2006 and the White Book model services agreement published in October

More information

Client Contracts: Business Risk, Professional Liability & Insurance Coverage

Client Contracts: Business Risk, Professional Liability & Insurance Coverage Hanover Architects & Engineers Advantage Client Contracts: Business Risk, Professional Liability & Insurance Coverage Many client-drafted contracts endeavor to transfer unreasonable risk to the design

More information

photos.com Cost, Quality and Accountability Public Tendering versus Self-Performance for Municipal Infrastructure Delivery in Canada

photos.com Cost, Quality and Accountability Public Tendering versus Self-Performance for Municipal Infrastructure Delivery in Canada photos.com Cost, Quality and Accountability Public Tendering versus Self-Performance for Municipal Infrastructure Delivery in Canada For more than 200 years and with few exceptions, Canada s municipal

More information

DESIGN IS GOOD BUSINESS

DESIGN IS GOOD BUSINESS COMPENSATING YOUR ARCHITECT The creature comforts are one thing, but for a house to become a home it s got to be elevated to the point that it s about raising one s spirits as well. SAMUEL MOCKBEE Building

More information

Developing a Public-Private Partnership Framework: Policies and PPP Units

Developing a Public-Private Partnership Framework: Policies and PPP Units Note 4 May 2012 Developing a Public-Private Partnership Framework: Policies and PPP Units This note is the fourth in a series of notes on developing a comprehensive policy, legal, and institution framework

More information

CONTRACTOR DEFAULT & SURETY PERFORMANCE:

CONTRACTOR DEFAULT & SURETY PERFORMANCE: CONTRACTOR DEFAULT & SURETY PERFORMANCE: A PRACTICAL GUIDE FOR UNDERSTANDING AND NAVIGATING A BOND DEFAULT SITUATION TEXAS CITY ATTORNEYS ASSOCIATION SUMMER CONFERENCE JUNE 9-11, 2010 SOUTH PADRE ISLAND,

More information

Head of Lease Terms - Ten Steps to a Successful negotiation

Head of Lease Terms - Ten Steps to a Successful negotiation Imperial College ThinkSpace Leasing Terminology Head of lease terms The principal terms upon which the lease will be drafted are detailed within a single document, entitles the Heads of Lease Terms. These

More information

Consolidated I&T Data Centre - P3 Canada Fund

Consolidated I&T Data Centre - P3 Canada Fund STAFF REPORT ACTION REQUIRED Consolidated I&T Data Centre - P3 Canada Fund Date: January 16, 2012 To: From: Wards: Reference Number: Government Management Committee Deputy City Manager & Chief Financial

More information

Terms and Conditions of Offer and Contract (Works & Services) Conditions of Offer

Terms and Conditions of Offer and Contract (Works & Services) Conditions of Offer Conditions of Offer A1 The offer documents comprise the offer form, letter of invitation to offer (if any), these Conditions of Offer and Conditions of Contract (Works & Services), the Working with Queensland

More information

ICE Legal Notes Series

ICE Legal Notes Series ICE Legal Notes Series Legal Notes Reviewing the work of another Engineer and replacing another Engineer Institution of Civil Engineers www.ice.org.uk Published by the Institution of Civil Engineers (ICE).

More information

PROCUREMENT GUIDE: CHP FINANCING

PROCUREMENT GUIDE: CHP FINANCING PROCUREMENT GUIDE: CHP FINANCING 1. Overview The decision of whether and how to finance a CHP system is a critical step in the development of a CHP project. CHP systems require an initial investment to

More information

Risk Management in the Development of a Penta-P Project

Risk Management in the Development of a Penta-P Project Risk Management in the Development of a Penta-P Project Bill Van Meter Regional Transportation District Denver, CO Julie Skeen Jacobs Engineering Denver, CO Damian Carey Jacobs Engineering Denver, CO Don

More information

BONDS C&L Preview. Introduction. What is a bond? Types of bonds. On default bond. On demand bond

BONDS C&L Preview. Introduction. What is a bond? Types of bonds. On default bond. On demand bond BONDS C&L Preview Third Edition September 2012 Introduction There are three collateral arrangements that can be used to secure the performance of the obligations undertaken by you. This issue focuses on

More information

West Virginia Housing Development Fund. Debt Management Policy

West Virginia Housing Development Fund. Debt Management Policy West Virginia Housing Development Fund Debt Management Policy Approved March 8, 2011 Table of Contents Debt Management Policy... 1 Variable Rate Debt and Interest Rate Swap Management Plan... 5 Variable

More information

Kingdom of the Netherlands

Kingdom of the Netherlands Kingdom of the Netherlands GENERAL GOVERNMENT PURCHASING CONDITIONS 2014 (ARIV 2014) Adopted by order of the Prime Minister, Minister of General Affairs, of 26 March 2014, no. 3132081 I General Article

More information

Australian Constructors Association. Bonding Issues Faced by Construction Companies in Australia

Australian Constructors Association. Bonding Issues Faced by Construction Companies in Australia Bonding Issues Faced by Construction Companies in Australia October 2009 This report contains 17 pages 6277500_6 Contents 1 Introduction and Summary 1 2 Purpose of Performance Guarantees and Bonds 3 3

More information

6.0 Procurement procedure 1 Infrastructure

6.0 Procurement procedure 1 Infrastructure Page 6-1 6.0 Procurement procedure 1 Infrastructure 6.1 Overview Introduction Procurement procedure 1 Infrastructure consists of four parts: guidelines for understanding the strategic context for the procurement

More information

Guidelines for Financial Institutions Outsourcing of Business Activities, Functions, and Processes Date: July 2004

Guidelines for Financial Institutions Outsourcing of Business Activities, Functions, and Processes Date: July 2004 Guidelines for Financial Institutions Outsourcing of Business Activities, Functions, and Processes Date: July 2004 1. INTRODUCTION Financial institutions outsource business activities, functions and processes

More information

Auditor General Procurement Processes Review - Bid Bonds/Performance Bonds

Auditor General Procurement Processes Review - Bid Bonds/Performance Bonds STAFF REPORT June 22, 2005 To: From: Subject: Administration Committee Deputy City Manager and Chief Financial Officer Auditor General Procurement Processes Review - Bid Bonds/Performance Bonds Purpose:

More information

The programming, design

The programming, design Understanding Project Delivery for the Design and Construction of Public Buildings architecture The programming, design and construction of important public buildings require the coordinated efforts of

More information

Overcoming financing challenges for Hydro Power Projects Francois Viljoen, Director, Cresco Project Finance, South Africa

Overcoming financing challenges for Hydro Power Projects Francois Viljoen, Director, Cresco Project Finance, South Africa Overcoming financing challenges for Hydro Power Projects Francois Viljoen, Director, Cresco Project Finance, South Africa Contents Features of Project Finance Challenges posed by Project Finance Risk assessment

More information

Feasibility. A guide to feasibility planning for junior mining companies

Feasibility. A guide to feasibility planning for junior mining companies Financial institutions Energy Infrastructure, mining and commodities Transport Technology and innovation Life sciences and healthcare Feasibility A guide to feasibility planning for junior mining companies

More information

Single Project Professional Indemnity Insurance Proposal Form. Note: This is a proposal form for a claims made policy

Single Project Professional Indemnity Insurance Proposal Form. Note: This is a proposal form for a claims made policy Single Project Professional Indemnity Insurance Proposal Form Note: This is a proposal form for a claims made policy Please provide any necessary explanations or additional details by attaching separate

More information

Guidance on the template contract for social impact bonds and payment by results

Guidance on the template contract for social impact bonds and payment by results Guidance on the template contract for social impact bonds and payment by results Introduction These guidance notes have been prepared to assist users of the Cabinet Office template contract. The guidance

More information

Guide on drawing up contracts for large industrial works

Guide on drawing up contracts for large industrial works Guide on drawing up contracts for large industrial works Topic: Construction, installation of plant, engineering Source: United Nations Economic Commission for Europe Palais des Nations Genève, Switzerland

More information

CONTRACT MANAGEMENT POLICY

CONTRACT MANAGEMENT POLICY CONTRACT MANAGEMENT POLICY Section Finance Approval Date 25/08/2014 Approved by Directorate Next Review Aug 2016 Responsibility Chief Operating Officer Key Evaluation Question 6 PURPOSE The purpose of

More information

Bonding P3 Projects. Frequently Asked Questions about P3s and Bonding

Bonding P3 Projects. Frequently Asked Questions about P3s and Bonding Bonding P3 Projects Government entities in the United States have understood the importance of surety bonds and have required bonds for over a century to provide performance and payment assurance for the

More information

Part E: Contract management

Part E: Contract management Overview Part A: Strategic assessment Part B1: Business case developing the business case Part B2: Business case procurement options Part B3: Business case funding and financing options Part C: Project

More information

Document A101. Standard Form of Agreement Between Owner and Contractor where the basis of

Document A101. Standard Form of Agreement Between Owner and Contractor where the basis of TM Document A101 2007 Instructions Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum GENERAL INFORMATION Purpose. AIA Document A101 2007 is intended

More information

(1) risks should be allocated to the party that is in the position to control them and

(1) risks should be allocated to the party that is in the position to control them and Risk allocation in the FIDIC Conditions of Contract (1999) for Construction (Red Book) and the FIDIC Conditions of Contract (1999) for EPC/Turnkey Projects (Silver Book) from the perspective of a German

More information

CONCODE Guide to contract strategies for construction projects in the NHS STATUS IN WALES ARCHIVED

CONCODE Guide to contract strategies for construction projects in the NHS STATUS IN WALES ARCHIVED CONCODE Guide to contract strategies for construction projects in the NHS 1995 STATUS IN WALES ARCHIVED For queries on the status of this document contact info@whe.wales.nhs.uk or telephone 029 2031 5512

More information

EPC CONTRACTS IN THE POWER SECTOR

EPC CONTRACTS IN THE POWER SECTOR Asia Pacific Projects Update EPC CONTRACTS IN THE POWER SECTOR INTRODUCTION Engineering, procurement and construction (EPC) contracts are the most common form of contract used to undertake construction

More information

CSA CONSTRUCTION, INC. 2314 McAllister Road Houston, Texas 77092 SUBCONTRACTOR AGREEMENT

CSA CONSTRUCTION, INC. 2314 McAllister Road Houston, Texas 77092 SUBCONTRACTOR AGREEMENT CSA CONSTRUCTION, INC. 2314 McAllister Road Houston, Texas 77092 SUBCONTRACTOR AGREEMENT THIS AGREEMENT made this day of Month, Year, by and between CSA CONSTRUCTION, INC., a Texas corporation whose principal

More information

ENERGY PERFORMANCE CONTRACT

ENERGY PERFORMANCE CONTRACT DATED DAY OF ENERGY PERFORMANCE CONTRACT THE CUSTOMER SPECIFIED IN THE FORMAL INSTRUMENT OF AGREEMENT -AND- THE ESCO SPECIFIED IN THE FORMAL INSTRUMENT OF AGREEMENT [This document is a DRAFT provided only

More information

https://www.ofgem.gov.uk/publications-and-updates/ofto-build-providing-additional-flexibility-through-extendedframework

https://www.ofgem.gov.uk/publications-and-updates/ofto-build-providing-additional-flexibility-through-extendedframework All interested parties Direct Dial: 020 7901 1849 Email: transmissioncompetition@ofgem.gov.uk Date: 17 November 2015 Dear Colleague EPC Contract Principles for OFTO Build Tenders This letter provides guidance

More information

School Construction Projects

School Construction Projects The process of educating young people seems to be continually developing. New insights regarding how students most effectively receive retain and gain understanding of information and principles affect

More information

CONTRACT CONDITIONS FOR LOGISTICS (2014)

CONTRACT CONDITIONS FOR LOGISTICS (2014) CONTRACT CONDITIONS FOR LOGISTICS (2014) The Company provides all items and services on the following Conditions which can be varied only in writing by an Officer of the Company. The Company is a member

More information

effectively structuring and managing design-build projects 2. factors involved in selecting the form of contract design-bid-build / stipulated price

effectively structuring and managing design-build projects 2. factors involved in selecting the form of contract design-bid-build / stipulated price construction November 25, 2009 effectively structuring and managing design-build projects 1. introduction While design-build has become a particularly popular method of project delivery over the past several

More information

ON-TIME AND ON-BUDGET: KEY ISSUES IN NEGOTIATING CONSTRUCTION CONTRACTS

ON-TIME AND ON-BUDGET: KEY ISSUES IN NEGOTIATING CONSTRUCTION CONTRACTS ON-TIME AND ON-BUDGET: KEY ISSUES IN NEGOTIATING CONSTRUCTION CONTRACTS ACC REAL ESTATE COMMITTEE PRESENTATION SEPTEMBER 17, 2009 SEAN T. BOULGER, ESQ. WILMER CUTLER PICKERING HALE AND DORR LLP I. Introduction

More information

Information Note 02/13 18 February 2013

Information Note 02/13 18 February 2013 Procurement Procurement Policy Note Procurement Policy Note Supplier Financial Risk Issues Information Note 02/13 18 February 2013 Issue 1. This note provides advice on issues frequently raised by suppliers

More information

Memorandum Potentially Affected AIA Contract Documents AIA Document A105 2007 AIA Document B105 2007 Important Information

Memorandum Potentially Affected AIA Contract Documents AIA Document A105 2007 AIA Document B105 2007 Important Information Memorandum Important information related to requirements of state or local laws to include additional provisions in residential construction contracts Potentially Affected AIA Contract Documents AIA Document

More information

MDB Harmonised Particular Conditions

MDB Harmonised Particular Conditions FIDIC Plant and Design-Build Contract MDB Harmonised Particular Conditions 1. Introduction There is a need for FIDIC to provide sample Particular Conditions that render the General Conditions of the 1st

More information

LEX HELIUS: THE LAW OF SOLAR ENERGY Solar Energy System Design, Engineering, Construction, and Installation Agreements

LEX HELIUS: THE LAW OF SOLAR ENERGY Solar Energy System Design, Engineering, Construction, and Installation Agreements LEX HELIUS: THE LAW OF SOLAR ENERGY Solar Energy System Design, Engineering, Construction, and Installation Agreements Alan R. Merkle Stoel Rives LLP 600 University Street, Suite 3600 Seattle, WA 98101-4109

More information

Unofficial Consolidation

Unofficial Consolidation CENTRAL BANK (SUPERVISION AND ENFORCEMENT) ACT 2013 (SECTION 48) (LENDING TO SMALL AND MEDIUM-SIZED ENTERPRISES) REGULATIONS 2015 (S.I. No. 585 of 2015) Unofficial Consolidation This document is an unofficial

More information

ONTARIO P3s - COST DOES NOT EQUAL VALUE Focus on $8 billion excess cost for P3s in Ontario ignores the value to taxpayers

ONTARIO P3s - COST DOES NOT EQUAL VALUE Focus on $8 billion excess cost for P3s in Ontario ignores the value to taxpayers SPECIAL REPORT TD Economics ONTARIO P3s - COST DOES NOT EQUAL VALUE Focus on $8 billion excess cost for P3s in Ontario ignores the value to taxpayers Highlights The Ontario Auditor General s recent report

More information

A P3 is Just Another Method to Finance and to Deliver a Public Works Project.

A P3 is Just Another Method to Finance and to Deliver a Public Works Project. Federal Highway Administration Docket FHWA 2014-0006 Draft Toll Concession Public-Private Partnership (P3) Model Contract Guide Addendum Comments from the American Subcontractors Association (ASA), Surety

More information

INSTITUTE OF TRANSLATION AND INTERPRETING

INSTITUTE OF TRANSLATION AND INTERPRETING INSTITUTE OF TRANSLATION AND INTERPRETING CODE OF PROFESSIONAL CONDUCT 1 CONTENTS 1. INTRODUCTION 2. THE PURPOSE OF THE CODE 3. PRINCIPLES OF PRACTICE 4. PROFESSIONAL VALUES 5. AMENDMENTS 6. PRINCIPLE

More information

Briefing document: Understanding the Royal Institute of British Architects (RIBA) Building Contracts. 5 November 2014

Briefing document: Understanding the Royal Institute of British Architects (RIBA) Building Contracts. 5 November 2014 Briefing document: Understanding the Royal Institute of British Architects (RIBA) Building Contracts 5 vember 2014 Table of Contents Part 1 Introduction Part 2 Why new contracts? The reason for the publication

More information

BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT. Notice No... 2011

BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT. Notice No... 2011 BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT Notice No.... 2011 NOTICE IN TERMS OF THE COUNCIL FOR THE BUILT ENVIRONMENT ACT, 2000 (ACT NO. 43 OF 2000) The Council for the Built Environment has under

More information

The Role of Construction Managers. FIDIC offers two contributions on the question of the role of a construction manager in a construction contract:

The Role of Construction Managers. FIDIC offers two contributions on the question of the role of a construction manager in a construction contract: The Role of Construction Managers FIDIC offers two contributions on the question of the role of a construction manager in a construction contract: A. Notes on the use of FIDIC in the Middle East B. A Communication

More information

Outsourcing: key legal issues and contractual protections

Outsourcing: key legal issues and contractual protections Page 1 Outsourcing: key legal issues and contractual protections Paul Jones May 2009 Introduction As the economic climate becomes more challenging, organisations in all sectors are looking to drive efficiencies

More information

Contract Management Handbook. A Guide to contract management at the University

Contract Management Handbook. A Guide to contract management at the University Contract Management Handbook A Guide to contract management at the University July 2012 CONTENTS 1. INTRODUCTION... 4 2. PURPOSE... 4 2.1 Using this Handbook... 5 3. CONTRACT MANAGEMENT FRAMEWORK... 5

More information

P3 Value for Money Assessment and Project Report. Evan Thomas Water and Wastewater Treatment Facility Project

P3 Value for Money Assessment and Project Report. Evan Thomas Water and Wastewater Treatment Facility Project P3 Value for Money Assessment and Project Report Evan Thomas Water and Wastewater Treatment Facility Project July 2013 Table of Contents 1. Summary: Using a P3 for a Water Treatment Plant - did it work?

More information

Checklist 26: How Owners Can Avoid Litigation on Construction Projects

Checklist 26: How Owners Can Avoid Litigation on Construction Projects Checklist 26: How Owners Can Avoid Litigation on Construction Projects While it is impossible to completely avoid litigation on construction projects, certain steps can be taken to minimize the potential

More information

ISA 620, Using the Work of an Auditor s Expert. Proposed ISA 500 (Redrafted), Considering the Relevance and Reliability of Audit Evidence

ISA 620, Using the Work of an Auditor s Expert. Proposed ISA 500 (Redrafted), Considering the Relevance and Reliability of Audit Evidence International Auditing and Assurance Standards Board Exposure Draft October 2007 Comments are requested by February 15, 2008 Proposed Revised and Redrafted International Standard on Auditing ISA 620, Using

More information

REQUEST FOR PROPOSAL TO PROVIDE CONSTRUCTION MANAGEMENT AND GENERAL CONTRACTOR SERVICES SPRINGVILLE CITY NEW AQUATICS AND ACTIVITIES CENTER

REQUEST FOR PROPOSAL TO PROVIDE CONSTRUCTION MANAGEMENT AND GENERAL CONTRACTOR SERVICES SPRINGVILLE CITY NEW AQUATICS AND ACTIVITIES CENTER RFP #2016-02 REQUEST FOR PROPOSAL TO PROVIDE CONSTRUCTION MANAGEMENT AND GENERAL CONTRACTOR SERVICES FOR SPRINGVILLE CITY NEW AQUATICS AND ACTIVITIES CENTER RELEASE DATE: January 29, 2016 DUE DATE: February

More information

A Guidance Note to. Conditions of Contract for Consultancy Services (2005)

A Guidance Note to. Conditions of Contract for Consultancy Services (2005) A Guidance Note to Conditions of Contract for Consultancy Services (2005) This Guidance Note is based on a document prepared by the Auckland Region Contract Group, and verified by ACENZ, in February 2005.

More information

MAY I HAVE THIS DANCE? TO WRAP OR NOT

MAY I HAVE THIS DANCE? TO WRAP OR NOT MAY I HAVE THIS DANCE? TO WRAP OR NOT Grace V.B. Garcia, Esquire Morrison Mahoney LLP 250 Summer Street Boston, MA 02110 P: 617.737.8822 F: 617.342.4914 ggarcia@morrisonmahoney.com Grace V.B. Garcia is

More information

Client Alert. Global Information Technology & Communications Privacy, Data Protection and Information Management

Client Alert. Global Information Technology & Communications Privacy, Data Protection and Information Management Global Information Technology & Communications Privacy, Data Protection and Information Management Client Alert Umbrellas for Clouds: Risk Mitigation Strategies for SaaS Transactions www.bakermckenzie.com

More information

Nominated Subcontractors on International Projects: Approaches to Risk Allocation

Nominated Subcontractors on International Projects: Approaches to Risk Allocation Nominated Subcontractors on International Projects: Approaches to Risk Allocation September 5, 2005 (he following outline was used in a presentation to the Overseas Construction Association of Japan, Inc.

More information

EPC Contracts in the oil and gas sector

EPC Contracts in the oil and gas sector Investing in Infrastructure International Best Legal Practice in Project and Construction Agreements January 2016 Damian McNair Partner, Legal M: +61 421 899 231 E: damian.mcnair@au.pwc.com EPC Contracts

More information

ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES

ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES CAPITAL GRANTS PROGRAM / BUILDING GRANTS ASSISTANCE SCHEME Background Non government schools accepting the

More information

Document Commentary. AIA Document C191 2009, Standard Form Multi-Party Agreement for Integrated Project Delivery

Document Commentary. AIA Document C191 2009, Standard Form Multi-Party Agreement for Integrated Project Delivery Document AIA Document C191 2009, Standard Form Multi-Party Agreement for Integrated Project Delivery INTRODUCTION Current practice in the construction industry promotes inefficiency when the key project

More information

APPENDIX D CONTRACTUAL AGREEMENT (Sample) THE GOVERNMENT OF SASKATCHEWAN as represented by the Minister of Energy and Resources

APPENDIX D CONTRACTUAL AGREEMENT (Sample) THE GOVERNMENT OF SASKATCHEWAN as represented by the Minister of Energy and Resources APPENDIX D CONTRACTUAL AGREEMENT (Sample) THIS AGREEMENT made in duplicate, BETWEEN: THE GOVERNMENT OF SASKATCHEWAN as represented by the Minister of Energy and Resources (Hereinafter referred to as the

More information

TRANSFERRING RISKS IN CONSTRUCTION CONTRACTS

TRANSFERRING RISKS IN CONSTRUCTION CONTRACTS TRANSFERRING RISKS IN CONSTRUCTION CONTRACTS Bryan S. Shapiro, QC I. INTRODUCTION Risk and conflict are inherent characteristics of the construction industry. Conflict usually results from the allocation

More information

Construction Contract

Construction Contract Construction Contract Case Number: Date: Borrower Name(s): Phone #: Phone #: THIS IS A MODEL DOCUMENT FOR USE IN RENOVATION OR CONSTRUCTION LOAN TRANSACTIONS. THIS FORM IS PROVIDED AS AN EXAMPLE AND IS

More information

GUIDELINE NO. 6 PENSION PLAN PRUDENT INVESTMENT PRACTICES GUIDELINE

GUIDELINE NO. 6 PENSION PLAN PRUDENT INVESTMENT PRACTICES GUIDELINE GUIDELINE NO. 6 PENSION PLAN PRUDENT INVESTMENT PRACTICES GUIDELINE November 15, 2011 TABLE OF CONTENTS CONTEXT FOR THE GUIDELINE... 3 Prudent Investment Practices... 3 Self-Assessment Questionnaire...

More information

Outsourcing. Definitions. Outsourcing Strategy. Potential Advantages of an Outsourced Service. Procurement Process

Outsourcing. Definitions. Outsourcing Strategy. Potential Advantages of an Outsourced Service. Procurement Process CIPS takes the view that the outsourcing of services to specialist providers can often lead to better quality of services and increased value for money. Purchasing and supply management professionals should

More information

SUPERVISORY AND REGULATORY GUIDELINES: PU48-0809 GUIDELINES ON MINIMUM STANDARDS FOR THE OUTSOURCING OF MATERIAL FUNCTIONS

SUPERVISORY AND REGULATORY GUIDELINES: PU48-0809 GUIDELINES ON MINIMUM STANDARDS FOR THE OUTSOURCING OF MATERIAL FUNCTIONS SUPERVISORY AND REGULATORY GUIDELINES: PU48-0809 ISSUED: 4 th May 2004 REVISED: 27 th August 2009 GUIDELINES ON MINIMUM STANDARDS FOR THE OUTSOURCING OF MATERIAL FUNCTIONS I. INTRODUCTION The Central Bank

More information

STANDARD FORM OF AGREEMENT BETWEEN OWNER AND DESIGN- BUILDER - LUMP SUM

STANDARD FORM OF AGREEMENT BETWEEN OWNER AND DESIGN- BUILDER - LUMP SUM DC STANDARD FORM OF AGREEMENT BETWEEN OWNER AND DESIGN- BUILDER - LUMP SUM Document No. 525 Second Edition, 2010 Design-Build Institute of America Washington, Design-Build Institute of America - Contract

More information

Procurement Routes. Curtin University of Technology

Procurement Routes. Curtin University of Technology Procurement Routes An Overview Curtin University of Technology Overview of Principal Routes Traditional / conventional design led Design and construct Management (Fee) Traditional Client appoints consultants

More information

An Owner s Guide To Construction Management Assuring Project Success Under Any Delivery Method

An Owner s Guide To Construction Management Assuring Project Success Under Any Delivery Method An Owner s Guide To Construction Management Assuring Project Success Under Any Delivery Method Reprinted with the permission of Construction Management Association of America, Inc. Copyright 2007 All Rights

More information

Best Practice in Design of Public-Private Partnerships (PPPs) for Social Infrastructure, particularly in Health Care and Education

Best Practice in Design of Public-Private Partnerships (PPPs) for Social Infrastructure, particularly in Health Care and Education EMAIL contact@fosterinfrastructure.com WEB www.fosterinfrastructure.com Best Practice in Design of Public-Private Partnerships (PPPs) for Social Infrastructure, particularly in Health Care and Education

More information

NEC Users Group Workshop Defined Cost

NEC Users Group Workshop Defined Cost NEC Users Group Workshop Defined Cost Ian.Heaphy@turntown.com; July 2014 Turner & Townsend plc July 14 making the difference Introduction Practicalities in assessing of Defined Cost & Disallowed Cost Assumption

More information

A Guide to Small Works. A brief explanation

A Guide to Small Works. A brief explanation A Guide to Small Works A brief explanation A Guide to House Extensions/Small Works - a brief explanation Small works are an ongoing, cherished part of DDC's activity and restricted only by distance. Here

More information

EXPLANATORY MEMORANDUM TO THE CONTRACTS FOR DIFFERENCE (ELECTRICITY SUPPLIER OBLIGATIONS) REGULATIONS 2014. 2014 No. [XXXX]

EXPLANATORY MEMORANDUM TO THE CONTRACTS FOR DIFFERENCE (ELECTRICITY SUPPLIER OBLIGATIONS) REGULATIONS 2014. 2014 No. [XXXX] EXPLANATORY MEMORANDUM TO THE CONTRACTS FOR DIFFERENCE (ELECTRICITY SUPPLIER OBLIGATIONS) REGULATIONS 2014 2014 No. [XXXX] 1. This explanatory memorandum has been prepared by the Department for Energy

More information

General Purchasing Conditions. R e v i s i o n 02 dated August 24, 2 0 0 7

General Purchasing Conditions. R e v i s i o n 02 dated August 24, 2 0 0 7 General Purchasing Conditions 1 1. Scope 1.1 These general purchasing conditions apply to all business transactions of the Trierenberg Holding AG and all its associated companies (from now on TBG ) with

More information

PUBLIC PRIVATE PARTNERSHIP HANDBOOK

PUBLIC PRIVATE PARTNERSHIP HANDBOOK PUBLIC PRIVATE PARTNERSHIP HANDBOOK VERSION 2 March 2012 1 CONTENTS Section 1: Introduction to Public Private Partnerships... 3 1.1 What is Public Private Partnership?... 4 1.2 Typical PPP Delivery Models...

More information

CONSTRUCTION RISK MANAGEMENT. TABLE of CONTENTS:

CONSTRUCTION RISK MANAGEMENT. TABLE of CONTENTS: CONSTRUCTION RISK MANAGEMENT TABLE of CONTENTS: 1. Introduction 2 2. Project Start Up Risk Exposure Analysis 3 3. Insurance 5 4. Additional Advice 8 5. Bonding 9 6. Subcontractor Default Insurance 11 1

More information

TERMS & CONDITIONS CONTRACTOR SERVICES

TERMS & CONDITIONS CONTRACTOR SERVICES TERMS & CONDITIONS CONTRACTOR SERVICES Hahn Electrical Contracting Pty Ltd EC003930 ACN 009 434 904 ABN 23 364 787 165 Hahn Electrical Contracting Pty Ltd Terms& Conditions Contracting EC 003930 ABN 23

More information

Claims College School of Construction LEVEL 1

Claims College School of Construction LEVEL 1 Claims College School of Construction LEVEL 1 Construction Defect Liability Theories and Defenses Objectives At the end of this course, you will be able to: Describe the theories of liability and defenses

More information

The New Standard Construction Contracts: NZS3910, 3916 and 3917

The New Standard Construction Contracts: NZS3910, 3916 and 3917 The New Standard Construction Contracts: NZS3910, 3916 and 3917 Brian Clayton, Partner FEBRUARY 2014 3258689.3 Chapman Tripp Introduction Standards New Zealand has recently completed the first review of

More information

NUCLEAR SUPPLY CHAIN SYMPOSIUM

NUCLEAR SUPPLY CHAIN SYMPOSIUM NUCLEAR SUPPLY CHAIN SYMPOSIUM Canadian Contracting Models Darryl J. Brown Gowling Lafleur Henderson LLP November 10, 2015 Suite 1600 1 First Canadian Place 100 King Street West Toronto, Ontario Canada

More information

Trelleborg Sealing Solutions Germany GmbH Handwerkstr. 5-7, 70565 Stuttgart. General Conditions of Purchase for Components

Trelleborg Sealing Solutions Germany GmbH Handwerkstr. 5-7, 70565 Stuttgart. General Conditions of Purchase for Components Trelleborg Sealing Solutions Germany GmbH Handwerkstr. 5-7, 70565 Stuttgart General Conditions of Purchase for Components 1. Basic Provisions 1.1 The General Conditions of Purchase of Trelleborg Sealing

More information

Capital Procurement Checklist - Overview

Capital Procurement Checklist - Overview Checklist - Overview The Ministry of Finance has recently implemented a capital procurement checklist to support the Asset Management Framework (CAMF) and related provincial policies for capital projects.

More information

STANDARD FORM OF AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR (Where Contractor and Subcontractor Share Risk of Owner Payment)

STANDARD FORM OF AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR (Where Contractor and Subcontractor Share Risk of Owner Payment) State License #CGC048773 STANDARD FORM OF AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR (Where Contractor and Subcontractor Share Risk of Owner Payment) This Agreement is made this day of, 200, by and

More information

Statement of Guidance: Outsourcing All Regulated Entities

Statement of Guidance: Outsourcing All Regulated Entities Statement of Guidance: Outsourcing All Regulated Entities 1. STATEMENT OF OBJECTIVES 1.1. 1.2. 1.3. 1.4. This Statement of Guidance ( Guidance ) is intended to provide guidance to regulated entities on

More information

Appendix D. Minimum Requirements For Developmental Resources. For

Appendix D. Minimum Requirements For Developmental Resources. For z Appendix D Minimum For Developmental Resources For 2016 Request For Proposals For Long-Term Renewable Generation Resources For Entergy Louisiana, LLC Entergy Services, Inc. June 8, 2016 MINIMUM REQUIREMENTS

More information

CONSTRUCTION PROJECT MANAGER TERMS OF REFERENCE CENTRAL BANK OF LESOTHO PROPOSED EXTENSION BUILDING AND DISASTER RECOVERY SITE CONSTRUCTION PROJECTS

CONSTRUCTION PROJECT MANAGER TERMS OF REFERENCE CENTRAL BANK OF LESOTHO PROPOSED EXTENSION BUILDING AND DISASTER RECOVERY SITE CONSTRUCTION PROJECTS CONSTRUCTION PROJECT MANAGER TERMS OF REFERENCE CENTRAL BANK OF LESOTHO PROPOSED EXTENSION BUILDING AND DISASTER RECOVERY SITE CONSTRUCTION PROJECTS 1. GENERAL PROVISIONS. 1.2 DEFINITIONS Where the words

More information

EPCM Contracts: Project delivery through engineering, procurement and construction management contracts

EPCM Contracts: Project delivery through engineering, procurement and construction management contracts Investing in Infrastructure International Best Legal Practice in Project and Construction Agreements January 2016 Damian McNair Partner, Legal M: +61 421 899 231 E: damian.mcnair@au.pwc.com EPCM Contracts:

More information

Public Health Services - The Cost of Doing Data Centre Project in Ontario, Canada

Public Health Services - The Cost of Doing Data Centre Project in Ontario, Canada VALUE FOR MONEY ASSESSMENT MINISTRY OF GOVERNMENT SERVICES NEW DATA CENTRE - PAGE 1 - - PAGE 2 - - PAGE 3 - - PAGE 4 - Table of Contents Summary...6 Project description...8 Competitive selection process

More information

TUPE 2006 Detailed Analysis

TUPE 2006 Detailed Analysis that activity is central or ancillary. Under existing case law this can include an organised group of one person! TUPE 2006 Detailed Analysis The TUPE 2006 Regulations completely replace the 1981 Regulations

More information

Important Information about Real Estate Investment Trusts (REITs)

Important Information about Real Estate Investment Trusts (REITs) Robert W. Baird & Co. Incorporated Important Information about Real Estate Investment Trusts (REITs) Baird has prepared this document to help you understand the characteristics and risks associated with

More information

PPP Models. Ownership of capital assets Responsibility for investment Assumption of risks, and Duration of contract.

PPP Models. Ownership of capital assets Responsibility for investment Assumption of risks, and Duration of contract. PPP Models The PPP models vary from short-term simple management contracts (with or without investment requirements) to long-term and very complex BOT form, to divestiture. These models vary mainly by:

More information

Community and Renewable Energy Scheme Project Development Toolkit

Community and Renewable Energy Scheme Project Development Toolkit Community and Renewable Energy Scheme Project Development Toolkit Balance Sheet Equity Investment Community Bond Issues Community Vehicle Crowd Funding Debentures a form of bond Debt Debt Service Cover

More information

AIA Document A141 TM - 2004 Standard From of Agreement Between Owner and Design- Builder

AIA Document A141 TM - 2004 Standard From of Agreement Between Owner and Design- Builder AIA Document A141 TM - 2004 Standard From of Agreement Between Owner and Design- Builder AGREEMENT made as of the day of in the year of (In words, indicate day, month and year) BETWEEN the Owner: (Name,

More information

INLAND REVENUE BOARD MALAYSIA CONSTRUCTION CONTRACTS

INLAND REVENUE BOARD MALAYSIA CONSTRUCTION CONTRACTS INLAND REVENUE BOARD MALAYSIA CONSTRUCTION CONTRACTS PUBLIC RULING NO. 2/2009 Translation from the original Bahasa Malaysia text DATE OF ISSUE : 22 MAY 2009 CONSTRUCTION CONTRACTS INLAND REVENUE BOARD

More information

CHAPTER 23. Contract Management and Administration

CHAPTER 23. Contract Management and Administration Date Issued: June 12, 2009 Date Last Revised: September 28, 2015 CHAPTER 23. Contract Management and Administration Table of Contents CHAPTER 23. Contract Management and Administration... 23-1 23.1 Policy...

More information

DOCUMENT. General Purchase Conditions

DOCUMENT. General Purchase Conditions 1. Scope 1.1 These general purchase conditions (hereinafter the GPC ) shall apply to all kinds of materials, articles, products and services related to them, (hereinafter Products ), offered, sold or supplied

More information