Project Specific Activities

Size: px
Start display at page:

Download "Project Specific Activities"

Transcription

1 Abbreviations CEQ DEIS DNR DTM EA EIS FHWA HPDP MPCA MEQB NEPA NPDES R/W Council on Environmental Quality draft Environmental Impact Statement Minnesota Department of Natural Resources digital terrain model Environmental Assessment Environmental Impact Statement Federal Highway Administration Mn/DOT s Highway Project Development Process handbook Minnesota Pollution Control Agency Minnesota Environmental Quality Board National Environmental Policy Act National Pollutant Discharge Elimination System right of way SEP-14 FHWA s Special Experimental Project 14 SHPO SOW USCOE WCA State Historic Preservation Officer Scope of Work United States Army Corps of Engineers Wetland Conservation Act Page 1

2 Project Specific Activities Preliminary Bridge Engineering TASK 0012 Bridge Estimate for Study Report Those tasks necessary to estimate the costs to do bridge repairs as contained in the preliminary repair recommendations. TASK 0014 Preliminary Repair Recommendations All tasks required to publish preliminary repair recommendations, as necessary for Study Report documentation, stating the work necessary to rehabilitate a bridge. Tasks are complete when the District approves the repair recommendation document. TASK 0017 Estimate For Study Report Without Preliminary Repair Recommendations Those tasks necessary to estimate the costs to do bridge repairs as contained in the final repair recommendations (Task 0018). TASK 0018 Final Repair Recommendations All tasks required to publish detailed recommendations, stating the bridge repair work necessary to rehabilitate a bridge. These recommendations include work found necessary from the condition survey. Tasks are complete when the District approves the repair recommendation document. TASK 0022 Hydraulics Those tasks necessary to make recommendations for the bridge design parameters related to waterway conditions. Required waterway opening, structure type, flood elevations, flow member elevation, flow velocities and scour potential, at bridge site are normally included. TASK 0030 Bridge Construction Foundation Review Those tasks necessary to make recommendations for the type and depth of foundation to be used in the design of the bridge. TASK 0031 Bridge Aesthetics Page 2

3 Those tasks necessary to determine or make recommendations for the type and extent of bridge aesthetic treatments. Mn/DOT has three levels of aesthetic investments: landmark, corridor, and routine. Work could include participating in and/or conducting meetings with various consultant, Mn/DOT, and city groups. TASK 0035 Preliminary Bridge Plan All tasks necessary to prepare a type, size, and location drawing for a bridge project. The drawing shows span arrangement, roadway cross section, and any other information necessary for guiding the detail design of the bridge. Receive bridge survey Submit depth of structure Receive grades Begin drawing Complete drawing Check drawing Conduct construction review Prepare for plan signing TASK 0040 District Letter And Preliminary Estimate Those tasks required to prepare and distribute the Preliminary Bridge Plan and the estimated cost for construction of the proposed bridge to those who need to coordinate other work with the bridge work. TASK 0045 FHWA Approval Those tasks necessary to obtain Federal Highway Administration approval of the Preliminary Bridge Plan as may be necessary for major bridge projects, interstate projects, and urban projects. TASK 0050 Bridge Design All design tasks necessary to complete bridge construction plans or design criteria or construction criteria for the project. TASK 0062 Partial Plan Delivery Those tasks necessary to accomplish the first submittal of work by the GEC showing the corner details of the bridge and direction proposed by the GEC for bridge design and plan preparation. TASK 0066 Final Draft Delivery Page 3

4 Those tasks necessary to prepare the submittal of the completed construction bridge plan. TASK 0068 Final Bridge Plan Review All tasks necessary to review submittals of the final construction bridge plan. TASK 0070 Consultant Final Tracings All tasks required to prepare the submittal of the reproducible tracings and all design computations for the bridge plan with all revisions as discussed in the final review meeting. TASK 0075 Tracing Backcheck All tasks required to review the tracings to ascertain that all revisions discussed at the plan review meetings are incorporated into the final bridge plan. TASK 0076 Bridge Specifications and Design Criteria Those tasks required to prepare the written special provisions and design criteria required for the bridge construction that supercede or supplement the Mn/DOT standard specifications and the information shown on the plan. TASK 0080 Bridge Construction Plan Review All tasks required for the review of the design-builder s bridge plan and special provisions, including all release for construction, final, and as-built versions. TASK 0090 Construction Estimate Those tasks required to prepare the engineer s estimate for the bridge plan, including necessary funding separations for cost sharing with other agencies. TASK 0095 Design-Build Bridge Concepts Those activities required to develop and/or verify bridge concepts that will be included in the design-build RFP. Verify bridge locations, widths and span lengths Determine preliminary beam type and superstructure depth Verify lateral and vertical clearances Verify retaining wall locations Determine retaining wall types (cut or fill) and approximate heights Page 4

5 Verify noise wall locations and heights Estimate bridge, retaining wall, and noise wall costs Deliverables could include documentation showing the following items: Bridge locations Lane, shoulder, and sidewalk widths Span lengths Preliminary beam type Beam and superstructure depth Minimum lateral and vertical clearances Retaining wall locations shown on preliminary geometric layout Wall types (cut or fill) and approximate heights Noise wall locations shown on preliminary geometric layout Noise wall heights Bridge, retaining wall, and noise wall costs Page 5

6 (1000) Design-Build Project Development TASK 1003 Project Scoping All tasks and work necessary to determine the project's scope. This activity is intended to get all functional groups to review the project location, either in person or through other means, to trigger a review so that the project's scope is more clearly defined from this point forward. This activity could involve developing several alternatives (including a "do nothing alternative) for the project that take into consideration existing roadway layouts, project goals, and public input. Gather and compile data related to the project Develop draft scoping sheet Visit project site(s) Conduct internal scope of work meeting Finalize project scoping sheet and distribute to project team Prepare preliminary analysis of data and hydraulic estimate TASK 1010 Project Management Those tasks necessary to manage or monitor the progress of a project during the Preconstruction Phase. This activity is performed over the entire preconstruction project schedule. TASK 1011 Consultant Selection The process involved in obtaining consultant services for a specific project, activity, or task within a project. Assess need for Consultant Determine scope of services Prepare and submit requisition for contracted services Develop Request for Proposals Review proposals and select Consultant TASK 1012 Aerial Photography All field and office tasks needed to plan for and produce aerial photography suitable for the Photogrammetric Base Map. District meetings requesting aerial photos are normally held in February. Because vegetation and snow prevent a clear view of the targets, flights for aerial photography suitable for producing the Photogrammetric Base Map can only be flown in the spring and fall. Index maps Page 6

7 and contact prints from flights are normally available within two to three months after the flights. Request photo limits Place targets Take aerial photos Prepare index map and contact prints TASK 1013 Consultant Management The process involved in managing the work done by a Consultant for a specific project, activity, or task. Meet with Consultant Review Consultant work progress Maintain communication with Consultant TASK 1015 Traffic Forecasts The forecasting of traffic necessary for Preliminary Design. Traffic forecasts on complex projects can be very lengthy and need to be scheduled early to prevent delaying other preliminary engineering activities. Review Mn/DOT s historically based traffic forecast for the project area Evaluate land use and demographic data for potential adjustments to previous forecasts Develop long range, generally 20 year, traffic forecast using existing traffic data Develop a project need and objectives statement that is based on public involvement, traffic studies, and analysis Evaluate crash studies and alternative levels of service Estimate service life of the project components. TASK 1016 ESAL Calculations The forecasting and calculating of traffic necessary for pavement design criteria and/or type selection. TASK 1018 Photogrammetric Base Map All tasks needed to provide photo control, base maps, and requested digital terrain model. Page 7

8 Photo control planning involves the analysis of specific control requirements for the project and ordering of photographic materials used in control and compilation. Photo control surveys involve surveying and computing the position of targeted control points and any supplemental control points needed. The survey crews also run field test profiles that will be used to figure the accuracy of compiled mapping. Complete photo control planning Conduct photo control surveying Establish survey control points Prepare field test profiles Prepare analytical triangulation Compile stereoscopic images Prepare base map including digital terrain models (as needed) TASK 1020 Preliminary Design Mapping All office and field tasks necessary to provide mapping to District Preliminary Design. Draw existing alignment on base map Add annotation (street names, basic utility features, etc.) to base map Place property lines on base map TASK 1021 Preliminary Design Surveys All field and office tasks necessary to obtain the survey information needed to prepare the Geometric Layout, consisting of land surveys, photogrammetric cross sections, exhibits, and map annotation. Existing alignment and existing right-of-way Planimetric map files DTM files in GEOPAK binary format - Triangular Irregular Network (TIN) Graphic file of obscured areas TASK 1030 Control Surveys All tasks necessary to furnish horizontal and vertical control for the project except photo control. Page 8

9 Conduct control surveys Traverse/GPS layout for horizontal control Tie sheets for horizontal control points Complete photo control Complete control list in format such as 80-column ASCII file format TASK 1032 Land Surveys All tasks necessary for the District Surveys Section to do the Land Survey (including section corners). Research existing information Schedule survey crew or Consultant Conduct survey Produce updated survey base map TASK 1040 Final Design Surveys All office and field survey tasks necessary to complete design activities (topography, cross-sections, drainage, utilities, etc.). Conduct survey including topography, cross-sections, drainage, and utilities Process field data Place property lines on Base Map Produce field input file TASK 1041 Bridge Surveys All survey tasks necessary to document bridge geometrics. Work could include any of the following: Conduct survey Prepare bridge survey report TASK 1050 Scoping Document All tasks necessary to prepare the document that provides information about the project including need, alternatives, and environmental impacts. In terms of the highway project development process, the Scoping Document is typically the first report prepared for projects thought to require an EIS, and it is distributed before the Public Scoping Meeting(s) so that comments on the project can be received and used to make a Scoping Decision. The Scoping Document serves the same purpose as a scoping EAW under the state process. The Scoping Document is required under MEQB rules for EIS projects. This Page 9

10 document identifies potentially significant issues relevant to the proposed project; defines the form, level of detail, content, alternatives, timetable for preparation, and preparers of the EIS; and is used to determine the permits for which information will be developed concurrently with the EIS. Visit project site Formulate alternatives Prepare scoping document Conduct review process among Mn/DOT, FHWA, and other external agencies Incorporate comments Obtain approval of document Publish the Scoping Document's Notice Of Availability in the MEQB Monitor. Distribute document TASK 1051 Public Scoping Meeting A meeting to share information about the proposed project at an early stage and to receive input from agencies and the general public to identify purpose and need, discuss the mode and project concept, narrow the number of alternatives that will be studied in greater depth in the environmental and project documents that follow, and discuss the consequences of the no-build alternative. The Public Scoping Meeting is required by the MEQB rules for EIS projects. The purpose of the Public Scoping Meeting is to present to the public and affected agencies the findings of the Scoping Document and to incorporate comments from the meeting into the Scoping Decision Document. The Public Scoping Meeting must be held during the 30-day comment period for the Scoping Document, but not less than 15 days after the Scoping Document is made available. Work could include any of the following: Prepare for meeting Begin public review and Scoping Document comment period Conduct meeting Prepare and distribute Scoping Meeting minutes End public review and Scoping Document comment period TASK 1052 Scoping Decision Document The tasks required to produce the Scoping Decision Document, which indicates the issues, and alternatives that will be examined in the EIS. The Highway Project Development Process Handbook 1, Part II, Section C, provides additional guidance for preparation of the Scoping Decision Document. Page 10

11 Revisit project site Refine alternatives Prepare scoping decision document Conduct review process Incorporate comments Obtain approval Distribute document Publish State EIS Preparation Notice in the MEQB Monitor TASK 1060 Draft Project Memorandum Those tasks necessary to produce the draft project memorandum, which is a Mn/DOT document used for certain Class II Actions (Categorical Exclusions) in order to obtain Mn/DOT and FHWA environmental clearances. It may also be used as a vehicle for coordination with outside agencies (and the public) that may have an interest in the project. Normally, it is prepared early in the process while still addressing the content requirements. Work could include any of the following: Prepare document Conduct review process Incorporate comments TASK 1070 Project Memorandum Those tasks necessary to complete the Project Memorandum (PM). The Project Memorandum is a Mn/DOT document used for Class II Actions (Categorical Exclusions) in order to obtain Mn/DOT and FHWA environmental and design clearances. The appropriate project design standard is documented and when critical design elements of the project s design standards are not met, design exceptions are noted and justified. It may also be used for coordination with other agencies and the public and guidance for final design. It is prepared as early as possible in the project development process, while still addressing the environmental requirements necessary for approval. Work could include any of the following: Revise Draft Project Memorandum Conduct internal Mn/DOT review process Conduct external agency review process Incorporate comments Obtain State Environmental Exception Determination and (when appropriate) Federal Categorical Exclusion Determination approval TASK 1080 Preliminary Geometric Layout Page 11

12 All tasks necessary to complete Preliminary Geometric Layouts, which are conceptual plans showing the horizontal and vertical location of the proposed roadway(s) in relation to the existing topography. Concept alignment and profile Approximate construction limits Anticipated typical sections TASK 1082 Wetlands All tasks involved with identifying and describing project related wetland impacts, preparing impact assessment sections for project documents, designing wetland impact avoidance, minimization, and replacement measures, and deciding whether to develop project-specific replacement or use the wetland bank. This activity also covers all tasks associated with identifying, delineating, and mitigating wetland impacts. Review files (i.e., NWI, USGS, SCS, County Soil Survey, DNR Protected Waters Maps, Mn/DOT and/or other aerial photos, existing boring logs, hydrologic studies, information on any county ditches) and project area Identify type of wetland impacts along project corridor (i.e., section, township, range, major watershed, wetland type Circular 39, wetland type Cowardin, dominant vegetation, total wetland size, impact area, topographic setting, if within the shoreland wetland protection zone the distance to the waterbody/watercourse) Delineate existing wetlands according to the United States Army Corps of Engineers Wetland Delineation Manual (January and determine impacts Prepare wetland impact sequencing section for project document Describe the impacts on the functions and values of wetlands for each alternative, including: *Vegetative diversity * Maintenance of hydrologic regime * Flood / Storm water attenuation * Water quality protection * Shoreline protection * Ground-water interaction * Wildlife habitat * Fishery habitat * Aesthetics/Recreation/Education/Cultural Commercial uses Hold interagency coordination meeting/field review Page 12

13 Mitigate impacts; design wetland impact avoidance, minimization and replacement measures Decide to develop project-specific replacement or use the state wetland bank Inplace field data collection (surveys, inspections, etc.) cannot be accurately gathered during the winter season (December to April). This activity does not cover the construction or maintenance monitoring work for the wetlands. TASK 1086 Economic Analysis All tasks needed to identify the positive economic gains from a project and compare them to the investment made in order to ensure that infrastructure investments strengthen the economy. Define alternatives, including base case Perform traffic modeling Estimate total costs Monetize travel time, vehicle operating costs, traffic crashes TASK 1090 Special Project Documents All tasks necessary to complete Special Project Documents, which are separate documents (other than DEIS, FEIS, Environmental Assessment, Project Path Report, Scoping Document, SDD, FONSI, Project Memorandum, or Study Report), which are prepared based on the specific needs of an individual project. Examples of types of special documents necessary would include Section 4(f) statements, noise reports (preliminary & final), air quality reports, hydraulic reports, aesthetic reports, wetlands findings, Interstate Access Reports, Environmental Assessment Worksheets, Value Engineering Reports, etc. Determine type of Special Project Document(s) required Noise Analysis (i.e., existing, no-build, and build conditions; new and old alignment; daytime and nighttime; with and without noise barriers) Air Analysis (i.e., no-build and build air quality analysis for one and ten years after construction using Mobile 5A emissions and CAL3QHC dispersion modeling (or current Air Quality air quality model approved by EPA) Value Engineering (projects with an anticipated construction cost in excess of $25 million will need a value engineering study in accordance with Federal-Aid Policy Guide dated September 8, 1998, Transmittal 24, Chapter 6, Value Engineering.) Prepare document(s) Conduct review process Incorporate comments Page 13

14 Obtain approval Distribute final document(s) Incorporate into EIS TASK 1100 Draft Environmental Impact Statement (DEIS) Those tasks necessary for the preparation of a DEIS, with all associated submittals and coordination required to comply with NEPA. The DEIS is a document that discusses the environmental impacts of a proposed Class I Action. It discusses all reasonable alternatives to the proposed action and summarizes the studies, reviews, consultations, and coordination required by law. The DEIS is a document required under MEQB rules for projects exceeding thresholds listed under FHWA regulations. The purpose of a DEIS is to provide information for governmental units, the proposer of the project, and other persons to evaluate proposed projects which have the potential for significant environmental effects, to consider alternatives to the proposed projects, and to explore methods for reducing adverse environmental effects. The documents shall be prepared in accordance with FHWA Regulations (as specified in 23CFR771 and FHWA Technical Advisory T6640.8A) and the Mn/DOT Highway Project Development Process, which can be found at Impact items that must be addressed in preparation of the DEIS are listed in Table 2, Part II, Section D of the Mn/DOT Highway Project Development Process (Handbook 2A). Prepare document Conduct review process Incorporate comments Obtain approval to prepare FEIS Distribute document after Public Hearing has been completed TASK 1110 Public Hearing on a DEIS All tasks necessary to prepare for, conduct, and document a public hearing; the purpose of which is to present to the public an explanation of a project, including alternatives under consideration, and receive public comments. A Public Hearing on a DEIS is required for an EIS project. It includes notices in the MEQB Monitor, Federal Register, and local newspapers; distribution of the DEIS; comment period; the public hearing; and preparation of a transcript. Page 14

15 The public involvement process could involve elected officials, affected Mn/DOT and other state, federal, and permitting agency staff, and the general public. There are different degrees of understanding of transportation and environmental concerns among these groups. Few, if any, participants will have any familiarity with the EIS process. Therefore, the public involvement task is primarily one of education. Prepare for hearing Conduct hearing Incorporate comments into Public Hearing Document Prepare Public Hearing transcripts and affidavits of publication Distribute Public Hearing documents TASK 1111 Public Hearing on an EA All tasks necessary to prepare for, conduct, and document a public hearing on an Environmental Assessment (EA); the purpose of which is to present to the public an explanation of a project, including alternatives under consideration, and receive public comments. A Public Hearing on Environmental Assessment projects is sometimes required. When a public hearing is not held, a Notice for an EA will be prepared (see Opportunity for Public Hearing (1130).) Since the EA also serves as a State EAW, MEQB rules must also be followed. Public Hearings on EA include notices in the MEQB Monitor and local newspapers, distribution of the EA, comment period, the public hearing, and preparation of a transcript. Prepare for hearing Conduct hearing Incorporate comments into Public Meeting Document Prepare Public Hearing transcripts and affidavits of publication Distribute Public Hearing documents TASK 1112 Public Hearing for Project Memorandum Projects All tasks necessary to prepare for, conduct, and document a public hearing, the purpose of which is to present to the public an explanation of a project, including alternatives under consideration and receive public comments. One or more public hearings, or the opportunities for hearing, are to be held at a convenient time and place for any Federal aid project that: Requires significant amounts of right of way Page 15

16 Substantially changes the layout or functions of connecting roadways or of the facility being improved Has a substantial adverse impact on abutting property Otherwise has a significant social, economic, environmental, or other effect, or FHWA determines that a public hearing is in the public interest. Prepare for hearing Conduct hearing Incorporate comments into Public Meeting Document Prepare Public Hearing transcripts and affidavits of publication Distribute Public Hearing documents TASK 1113 Public Information Meeting All tasks necessary to prepare for, conduct, and document an information meeting, the purpose of which is to present to the public and other governmental agencies an explanation of a project, including alternatives under consideration, and to receive comments. Public Information Meetings are used to inform and gather information from the public on project alternatives, impacts, schedule, cost, and other activities. There are no specific time requirements. Multiple Public Information Meetings may be used on a project. Arrange for meeting location Announce meeting Prepare for meeting Conduct meeting Incorporate comments into Public Meeting Document TASK 1120 Final Environmental Impact Statement (FEIS) All tasks necessary for the preparation and processing of the Final Environmental Impact Statement (FEIS) document as established by federal and state laws. The FEIS is a document required under MEQB rules for projects exceeding thresholds listed under FHWA regulations. The purpose of the FEIS is to respond to the substantive comments received on the DEIS consistent with the scoping decision. The FEIS discusses responsible opposing views related to scoped issues which were not adequately discussed in the DEIS, and Mn/DOT s response to those views. Page 16

17 Changes from the DEIS are generally, but not necessarily always, minor and consist of factual corrections and/or an explanation of why comments received on the DEIS do not warrant further response (this assumes that all issues were adequately presented and evaluated in the DEIS). In this case, the EIS would consist of the DEIS and an attachment containing the following: Errata sheets making any necessary corrections to the DEIS An explanation of how mitigation will be developed Summaries of all substantive comments of the DEIS and responses thereto. The FEIS is generally reviewed by Mn/DOT District, Central Office, and FHWA staff, and could involve meetings with any one or all groups to review comments. Prepare final document using DEIS Conduct review process Incorporate comments Obtain approval Distribute document TASK 1121 Adequacy Determination Those tasks needed to write the brief report known as the Mn/DOT Adequacy Determination, which is required by the MEQB rules and provides reasons explaining why the EIS is adequate. The Adequacy Determination can be made no earlier than 10 working days after FEIS Availability Notice appears in the MEQB Monitor. The Adequacy Determination is required under MEQB rules for EIS projects. The purpose of this document is to determine if the EIS adequately addresses potentially significant issues and alternatives raised in scoping, was prepared in compliance with State procedures, and provides responses to the substantive comments received during the DEIS review. The format and content is not extensive. A letter is prepared according to the requirements in the Mn/DOT/State Alternate Environmental Review Guidelines and MEQB rules (Ch ). Prepare draft document Obtain approval Distribute document Page 17

18 TASK 1122 Record of Decision Those tasks performed by the District to prepare a draft of the Record of Decision (ROD). The ROD is a federal document that states what decision was made, identifies all alternatives considered by the agency, and states whether all practical measures to minimize environmental harm will be adopted. Approval cannot occur until at least 30 days after the FEIS Notice of Availability appears in the Federal Register. The Record of Decision presents the basis for the FHWA (or other federal agency) environmental decision, summarizes any mitigation measures that will be incorporated in the project, and documents any required Section 4(f) approval. The ROD is required for EIS projects. TASK 1129 Environmental Assessment The process of writing the Environmental Assessment (EA), a federally required document, for those federally aided actions that are not Categorical Exclusions and where the potential significance of the environmental effects is not clearly established. The EA is also used as a State Environmental Assessment Worksheet (EAW) for those federally aided projects that are not exempt and which are not clearly mandated State EIS projects. When a public hearing for an EA project is not held, a notice of availability of the EA will be placed in the local newspapers. Since the EA also serves as a State EAW, MEQB rules must also be followed. A notice of availability for an EA includes notices in the MEQB Monitor and local newspapers, distribution of the EA, and comment period. An Environmental Assessment Worksheet is a State document required for projects where certain thresholds are crossed. Prepare document Conduct review process Incorporate comments Obtain approval Distribute document TASK 1130 Opportunity for Public Hearing All tasks necessary to prepare for an Opportunity for Public Hearing, an event which provides an alternate method for meeting the hearing requirements by providing for notification of an opportunity for the public to request a hearing. Page 18

19 When a public hearing for an EA project is not held, a notice of availability of the EA will be placed in local newspapers. Since the EA also serves as a State EAW, MEQB rules must be followed. Notice of availability for an EA includes notices in the MEQB Monitor and local newspapers, distribution of the EA, and comment period. Prepare opportunity notice Advertise opportunity Obtain waivers (if necessary) TASK 1131 EIS Need Decision Those tasks necessary for Mn/DOT to make an EIS Need Decision, which is a State requirement, and can be thought of as a Finding of Facts and Conclusions (FOF&C) and decision on the need for an EIS. The FOF&C summarizes the State environmental review process and includes summaries of the steps taken in reviewing a proposed project in accordance with environmental review procedures, public and agency written comments on the Environmental Assessment (EA) or Environmental Assessment Worksheet (EAW) and Mn/DOT s response, and the issues raised through public involvement, including public hearings, and Mn/DOT s response. It also includes the conclusions, based on findings, that the project has no potential for significant environmental impacts; that feasible mitigation will be provided; that all environmental review requirements have been met; and a decision on the need for an EIS. Typically, a negative declaration is made. It is required under MEQB rules. The EIS Need Decision includes preparation of a Findings of Fact and Conclusions and distribution of the decisions. TASK 1132 Finding of No Significant Impact The development of the Finding Of No Significant Impact (FONSI), which is a separate document written for the FHWA. The Environmental Assessment and Finding of Facts and Conclusions are attached to the FONSI and incorporate by reference any other appropriate information. The FONSI documents the finding that no EIS is needed, and the request for it is a product that includes the hearing transcript (if held), letters, responses, etc. The FHWA approves the FONSI package. Assemble EA, transcripts from Public Hearings, and Findings of Facts and Conclusions Distribute FONSI within Mn/DOT for review Page 19

20 Obtain Mn/DOT approval Submit FONSI package to FHWA Receive approval from FHWA TASK 1140 Final Geometric Layout All tasks necessary to complete the Final Geometric Layout, which is a conceptual plan showing the horizontal and vertical location of the proposed roadway in relation to existing topography. This task also includes preparation of geometric design criteria to be used by the design-builder. Alignment and profile Construction limits suitable for purchase of any additional R/W, if necessary, to construct the project. Such R/W may include, but is not limited to, drainage; NPDES permit requirements, and wetland mitigation. Cross-sections Road approach profiles and touchdown points Construction staging/detour plan TASK 1141 Preliminary Hydraulics Design The tasks needed to develop preliminary hydraulic recommendations from the District Hydraulics/Metro Water Resources Engineer. Inplace field data collection (surveys, inspection, etc.) cannot be accurately gathered during the winter season (December through April). Research files Identify permits Identify and review inplace drainage patterns and structures Identify new drainage patterns and design criteria Recommend preliminary construction limits Prepare cost estimates, cost splits (by agency if applicable), and recommendations TASK 1142 Municipal Approval of Final Layout All tasks needed to receive a Resolution from the municipality(s) approving the Final Geometric Layout. Minnesota Statute notes that highway improvements involving the following require municipal consent: Altering access; Increasing or reducing highway capacity; and Page 20

21 Acquiring permanent right of way. TASK 1150 Study Report All tasks necessary to document the major design features of the selected project alternative. Basic design criteria, exceptions to the standards, and environmental mitigation commitments are listed and described. These things, together with the Final Geometric Layout, serve as guidance for final design. The finished document is used for Mn/DOT and FHWA (federal funds - non MAP or MTP projects) approval of design/exceptions. Environmental commitments which have been made and which need to be incorporated into the construction plan are discussed. Prepare document Conduct review process Incorporate comments Obtain approval Distribute document TASK 1160 Final Design Mapping All office and field tasks necessary to provide final design mapping. TASK 1165 Signal Justification Report All tasks necessary to prepare a report that justifies traffic signal installations at intersections. Conduct turning movement counts/warrant analysis Conduct crash analysis Prepare document Obtain District/Metro Division Engineer approval TASK 1170 Pavement Type Selection All tasks associated with the preparation of the pavement type selection documentation. Perform preliminary soils survey and sampling Perform laboratory soils tests Prepare documentation Page 21

22 Determine proposed surface type Submit to CO Pavement Management Engineer Prepare pavement design and life-cycle cost analysis Obtain District concurrence TASK 1180 Soils Survey and Letter All field, lab, and office tasks necessary to provide roadway soils recommendations (including soils profile and cross-sections when appropriate) for use in developing final design plans and special provisions. Recommendations for resurfacing projects will require a shorter duration than reconstruction or new construction projects. This activity can coincide with or precede Road Plans (1250). Preliminary profile grades and cross-sections may be required. Conduct soils and pavement survey Perform materials tests Evaluate data Prepare Soils Letter TASK 1181 Soils Review and Approval The process of reviewing the District Soils Letter by both the Central Office Pavements and Geotechnical Sections which leads to the Soils Letter approval. Perform pavement review Perform Geotechnical review Approve letter TASK 1190 Foundation Recommendations All field, lab, and office tasks necessary to provide foundations recommendations for the structural elements of a project (i.e., bridges, retaining walls etc). Review preliminary design data Schedule field borings Bore holes Perform laboratory tests and analysis Prepare foundations recommendation Page 22

23 TASK 1195 Utility Coordination All tasks associated with utility identification and coordination. Identify utilities and assess project impacts on utilities Coordinate with affected utility(ies) Verify utility Develop utility plan information Coordinate with Central Office Utilities TASK 1200 Construction Limits All design tasks associated with the determination of construction limits for Right of Way purposes. TASK 1201 Project Cost Estimate All tasks associated with the preparation of preliminary project costs, including items such as design-builder design, construction, quality management, warranties. Assist with developing municipal, utility, and all other cost sharing agreement(s) associated with this project. As part of this task, develop a detailed opinion of probable construction costs for all work associated with this project and other agency cost participation. Cost sharing agreements could require a breakdown of costs; i.e., cost apportioned to affected city(ies), county(ies), utility(ies), or other party(ies), and Mn/DOT. TASK 1210 Title Order All tasks necessary to complete the initial title order, which includes a map that is sent to an attorney or abstractor for preparing Title Certificates, and the time necessary for the outside title attorney to complete the title investigation and resubmit completed titles. Order titles, prepare and submit unrecorded utility easements Prepare Attorney s Certificate of Title TASK 1220 Right of Way Package All tasks necessary to prepare the Right of Way acquisition package (including authorization map, Right of Way work map, building books, etc.). This activity also includes necessary survey data for preparation of Preliminary Plats. Spot titles on R/W base map Page 23

24 Complete R/W layout Conduct field title investigation and prepare building sketches Assemble and submit completed R/W package TASK 1225 Plats Preliminary and Final Plats and District Surveys The computation of Right of Way acquisition plats data, staking of boundary monumentation, and filing of final plats. Compute plat boundary Stake boundary monumentation Prepare final plats File final plats TASK 1230 Right of Way Preacquisition All necessary field and office tasks before the direct purchase offer. The legal descriptions, office abstract, purchase instruments, Commissioner s Orders and encumbering of funds must be completed prior to starting the Real Estate Purchase (Activity 1240). The relocation plan, replacement housing, and salvage value may or may not be complete when this activity is at 100%. Prepare legal descriptions Prepare office abstracts Prepare purchase instruments Complete Mn/DOT Commissioner s Orders Prepare acquisition maps Complete relocation plan Identify replacement housing Prepare salvage value TASK 1235 Valuation The preparation and certification of property valuations. This activity can be run concurrently with all or most of Activity The common practice is to start when Activity 1220 is 40% complete. TASK 1240 Real Estate Purchase All Right of Way tasks beginning with Direct Purchase offers and continuing through negotiations, which will culminate in acquisitions not requiring eminent domain. These tasks include relocation assistance, payments, and relocation review. Page 24

25 Relocation assistance, review, and payments are activities in conjunction and concurrent with other real estate purchase activities. 100% is not indicative of all parcels on a project, but only refers to those not in Eminent Domain (Activity 1241). Make direct purchase offers Record acquisition documents Make payment to owner TASK 1245 Jurisdictional Reassignment All the tasks necessary to complete the Jurisdictional Reassignment (turnback) of a segment of trunk highway. Prepare Memorandum of Understanding with local road authority Prepare Jurisdictional Reassignment Authorization Map Revise Control Section numbers Prepare Jurisdictional Reassignment Review Memorandum Conduct cultural resource management review Assemble Jurisdictional Reassignment Package TASK 1249 Final Hydraulics Design The tasks needed to complete final hydraulics design and review. TASK 1250 Road Design All the tasks necessary to prepare the desired level of road plans and roadway design criteria. TASK 1251 Signal Design All tasks necessary to prepare the desired level of traffic signal plans and design criteria. TASK 1252 Lighting Design All tasks necessary to prepare temporary or permanent lighting plans and design criteria. Page 25

26 TASK 1253 Time and Traffic All tasks necessary to prepare contract time (i.e., design-build contract completion date, intermediate completion date(s), number of working days), TASK 1254 Traffic Control All tasks necessary to complete the Traffic Control, Staging, and Maintenance of Traffic requirements and criteria for traffic handling during construction. This task includes the assessment of impacts that various forms of traffic control (i.e., detours, bypasses, and lane closures) may have on social, economic, and environmental interests. TASK 1255 Signing Design All work required to develop and design roadway signing plans and criteria. TASK 1256 Traffic Management Design All tasks necessary to complete the plans and design criteria for Traffic Management System (TMS) components, including electrical work for TMS (loop detectors, Changeable Message Signs (CMS), ramp meters, cameras, etc.) and some minor grading and ramp widening work. This task is often applicable in the Twin Cities metropolitan area, but may also be used in other urban areas, including but not limited to Duluth, St. Cloud, Mankato, and Rochester. TASK 1257 Landscaping Design Those tasks necessary for the design of plans and criteria for projects involving landscaping and site development; i.e., clearing and grubbing, soil preparation, minimal grading, tree transplanting, furnishing/installing/establishing trees, shrubs, groundcovers, vines, and turf. This activity also covers landscaping work for rest area projects. TASK 1258 Flasher Design All tasks necessary to prepare the signal flasher design criteria. TASK 1259 Hydraulics Letter The preparation of the memo that details the necessary hydraulic structure (bridge or culvert) along with hydraulic data for the surrounding area. Page 26

27 TASK 1260 Preliminary Bridge Design All tasks necessary to prepare a type, size, and location drawing for a bridge project and bridge design criteria for design-builders. The drawing could show span arrangement, roadway cross section, and any other information necessary for guiding the final design of the bridge. TASK 1270 Final Bridge Design All tasks necessary to complete construction plans for the bridge portion of the project. TASK 1280 Permits All tasks associated with preparing, processing, and securing permits on a project. Prepare permit documentation Submit documentation to permitting agency Obtain permit The type of permits to be applied for could include any of the following: Mn/DNR Protected Waters Permit COE Section 404 Nation Wide Permit COE Section 10/404 Permit Coast Guard Permit MPCA Section 401 Certification MPCA NPDES/SDS Permit Wetland Conservation Act Compliance Watershed District Permit County Ditch Permit Indirect Source Permit Mn/DNR Water Appropriation Permit Well Permits Endangered Species Surveys, Impacts and Mitigation Depredation of Migratory Birds or Active Migratory Bird Nests TASK 1290 Agreements Municipal All tasks associated with the preparation and processing of Municipal Agreements. Page 27

28 TASK 1291 Agreements Railroads All tasks associated with the preparation and processing of Railroad Agreements. Make initial contact with Railroad Company to determine potential impacts Prepare agreement submittal package Submit agreement to Railroad Obtain Railroad approval Route agreement within for final execution TASK 1292 Agreements Utility All tasks associated with the preparation and processing of Utilities Agreements. Review plans Get utility plans and estimates Write agreement TASK 1293 Agreements Other All tasks associated with the preparation and processing of Special Agreements, including the coordination with the party(ies) involved. TASK 1294 Agreements Signal All tasks associated with the preparation and processing of Signal Agreements. Coordinate with local agency Reconfirm pre-agreement contacts and negotiation Write agreement Submit agreement to agency Obtain agency approval Route agreement for final execution TASK 1295 Agreements Lighting All tasks associated with the preparation and processing of Lighting Agreements. Coordinate with local agency Write agreement Page 28

29 Submit agreement to agency Obtain agency approval Route agreement for final execution TASK 1296 Agreements Detour All tasks associated with the preparation and processing of Detour Agreements. Coordinate with local agency Write agreement Submit agreement to agency Obtain agency approval Route agreement for final execution (2000) Design-Build Project Management TASK 2010 Internal Supervision and Management During the course of the work order, maintain supervision and management of all activities. No management or supervisor activities will be shown under other tasks. TASK 2020 Project Management, Progress Meetings Take a lead role in the project management for this project and attend regular project development meetings with the Department and other affected interests. Attend up to meetings during this work order for items such as, but not limited to: Public meetings Permitting issues Right of way issues Utility issues RFQ development SOQ evaluation RFP development Technical proposal evaluation Progress reports will be developed in accordance with invoicing requirements and submitted to the Project Manager for review and approval at regular intervals of weeks. Progress reports and invoicing shall be done within the format of the tasks shown in each work order (i.e., all hours related to Project Management Page 29

30 or Progress Meetings shall be charged within Task Take minutes at meetings and submit the minutes to Mn/DOT s Project Manager within business days of each meeting. TASK 2030 Quality Management All items necessary to maintain quality management of performing the services of this work order, including quality control and quality assurance. No quality management will be shown in other tasks. To ensure quality, the GEC shall thoroughly and rigorously review all deliverables. Products that do not meet acceptable levels of quality must be corrected and/or revised. TASK 2040 Design-Build Project Website This task includes the development and ongoing design enhancement and maintenance of a design-build project website that the public could view from either Netscape or Microsoft Explorer web browsers. This task could also include work necessary for identifying and building links to other appropriate websites and information, including the Department s program website, This task could also include the creation of a secured access website that would be used by the project team for sharing project design files, text documents, or other project-related information that is not ready for public viewing. TASK 2050 Procurement Debriefing All tasks necessary to prepare, coordinate, conduct, and document debriefing meetings with the teams that were interested or involved in the project procurement. This could include teams that were not short-listed, short-listed but unsuccessful teams that were not chosen for the design-build contract, and the selected design-builder. The purpose of the meetings would be to solicit feedback from each team regarding the process, procurement documents, methodology, level of effort, and ideas for improving future projects. Page 30

31 (3000) Design-Build Contract Administration 1 General Requirements This section outlines a general list of the responsibilities and requirements for the GEC. This is broken into two subsections. Section 2.6 identifies the types of services that could be needed to administer the design and construction aspects of a design-build project, including design and construction quality management, inspection, materials testing and design-build contract administration. When examining the plans from the Design Builder, the GEC would use the following or similar criteria to check and review the plans: Review A comparative analysis for agreement with standard practice, agreement with similar structures, all with application of professional judgment. Mathematical analysis is not specifically required, but may be necessary where a discrepancy appears likely. Could include an analysis of the Design Builder s methods, assumptions, and calculations. Check Make a complete mathematical computation and resolve all differences that appear in the plans. All record keeping and documentation will be in accordance with standard Department procedures, formats, and content. 2 Personnel Training and Experience Requirements For the 5000 series tasks listed below, the GEC would be expected to provide a satisfactory number of qualified personnel as necessary to effectively carry out its responsibilities under each work order that included contract administration. Depending on the project, there may be work during nighttime hours, on weekends, and/or generally under tight time constraints. The number of personnel needed during any particular project may change as the project progresses (i.e., intense roadway and bridge/structure design in the early stages that tapers off to plan submittal review near the end of a project. The GEC may only use competent personnel who are qualified by experience and/or education as indicated. Minimum qualifications for some example positions are defined in this section. For any specific project work order, the Department may require that these minimum qualifications be altered in specific instances when the unique nature of the work requires specific or more specialized skills that are not shown below. Page 31

Appendix A Alternative Contracting General Engineering Consultant RFP. Appendix A

Appendix A Alternative Contracting General Engineering Consultant RFP. Appendix A Appendix A 1 1.0 Requirements and Minimum Qualifications This section outlines requirements and minimum qualifications for the GEC. It is anticipated that the GEC will be used to support and supplement

More information

Exhibit A Scope of Work

Exhibit A Scope of Work Exhibit A Scope of Work The agreement for S.P. 3116-142 (T.H. 169-Cross Range Expressway) includes final design plans for a 1.55 mile length of a 2 lane to 4 lane expansion project located 0.66 miles SW

More information

Major Construction Project Template (with EA) (Version 20130508) MnDOT - Gantt Chart Layout May-10-13 09:58. Final Design Project Baselined

Major Construction Project Template (with EA) (Version 20130508) MnDOT - Gantt Chart Layout May-10-13 09:58. Final Design Project Baselined 1 Major Construction Project Template (with EA) (Version 833 2 s 833 3 MS_100 Project Initiated 0 4 MS_110 Initial Design Project Baselined 0 5 MS_120 Layout Staff Approved 0 6 MS_130 Construction Limits

More information

Polk Commerce Centre CRA Spine Road Alignment Study

Polk Commerce Centre CRA Spine Road Alignment Study Polk Commerce Centre CRA Spine Road Alignment Study Florida Polytech Pace Road (LIMIT) Berkley Road Williams DRI Proposed Alignment Polk Commerce Centre CRA Boundary Braddock Road (LIMIT) Lake Myrtle Sports

More information

Work Breakdown Structure Element Dictionary. Final Design

Work Breakdown Structure Element Dictionary. Final Design Initiation FD 4.1 Initiation encompasses deliverables associated with the development, implementation and control of the project s schedule, budget and scope. The lead office develops these project parameters

More information

5.14 Floodplains and Drainage/Hydrology

5.14 Floodplains and Drainage/Hydrology I-70 East Final EIS 5.14 Floodplains and Drainage/Hydrology 5.14 Floodplains and Drainage/Hydrology This section discusses floodplain and drainage/hydrology resources and explains why they are important

More information

CHAPTER 12 Revised January 1, 2013 SIGNING AND SEALIN OF PROFESSIONAL SURVEY DELIVERABLES

CHAPTER 12 Revised January 1, 2013 SIGNING AND SEALIN OF PROFESSIONAL SURVEY DELIVERABLES CHAPTER 12 Revised January 1, 2013 SIGNING AND SEALIN OF PROFESSIONAL SURVEY DELIVERABLES Chapter Contents Sec. 12.01 Sec. 12.02 Sec. 12.03 Sec. 12.04 Sec. 12.05 Sec. 12.06 Introduction Business & Legal

More information

PROJECT TASKS & SCHEDULING GUIDE PROJECT DEVELOPMENT AND DELIVERY PROCESS

PROJECT TASKS & SCHEDULING GUIDE PROJECT DEVELOPMENT AND DELIVERY PROCESS PROJECT TASKS & SCHEDULING GUIDE PROJECT DEVELOPMENT AND DELIVERY PROCESS REVISED DECEMBER, 2015 TABLE OF CONTENTS INTRODUCTION...3 TASK SUMMARY (BY ID)........4 TASK SUMMARY (BY PHASE)..........8 TASK

More information

LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT CONSTRUCTION PLANS QUALITY CONTROL / QUALITY ASSURANCE MANUAL

LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT CONSTRUCTION PLANS QUALITY CONTROL / QUALITY ASSURANCE MANUAL LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT CONSTRUCTION PLANS QUALITY CONTROL / QUALITY ASSURANCE MANUAL August 2008 TABLE OF CONTENTS Section 1 - Introduction... 3 1.1 Defining Plan Quality...

More information

NCDOT MAPPING GUIDELINES FOR PLANNING AND DESIGN ACTIVITIES MAPPING PRODUCTS FOR ROADWAY DESIGN AND PDEA STEPS FOR REQUESTING MAPPING PRODUCTS

NCDOT MAPPING GUIDELINES FOR PLANNING AND DESIGN ACTIVITIES MAPPING PRODUCTS FOR ROADWAY DESIGN AND PDEA STEPS FOR REQUESTING MAPPING PRODUCTS NCDOT MAPPING GUIDELINES FOR PLANNING AND DESIGN ACTIVITIES MAPPING PRODUCTS FOR ROADWAY DESIGN AND PDEA STEPS FOR REQUESTING MAPPING PRODUCTS DESIGN TYPE DEFINITIONS YEARLY MAPPING NEEDS REQUEST DESCRIPTION

More information

Highway 23 Paynesville Richmond Soils Borings, Soils Tests, and Reporting

Highway 23 Paynesville Richmond Soils Borings, Soils Tests, and Reporting Highway 23 Paynesville Richmond Soils Borings, Soils Tests, and Reporting MnDOT Contract No. 1003249 General Project Overview This work is located along Trunk Highway (TH) 23, for State Project (SP) 7305-124.

More information

QUALITY ASSURANCE. and QUALITY CONTROL PROCESS GUIDE. for PROJECT MANAGERS

QUALITY ASSURANCE. and QUALITY CONTROL PROCESS GUIDE. for PROJECT MANAGERS QUALITY ASSURANCE and QUALITY CONTROL PROCESS GUIDE for PROJECT MANAGERS MDOT Trunkline Projects January 2005 TABLE OF CONTENTS Discussion.. 2 Scope Verification Meeting..... 3 Overview 3 Procedure...

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS Engineering Design Services for the Preliminary (Design) Engineering 1. Imlay City Road Imlay City Road at Wilder Road (signal modernization), Lapeer Township 2. Imlay City Road Imlay

More information

FHWA Minnesota Division Guidance for the Preparation of a FHWA INTERSTATE ACCESS REQUEST

FHWA Minnesota Division Guidance for the Preparation of a FHWA INTERSTATE ACCESS REQUEST FHWA Minnesota Division Guidance for the Preparation of a FHWA INTERSTATE ACCESS REQUEST August 2003 Background: The Federal Highway Administration (FHWA) has retained all approval rights to the control

More information

DESCRIPTION OF WORK:

DESCRIPTION OF WORK: DEPARTMENT OF PUBLIC WORKS COUNTY OF HENRICO P.O. BOX 27032 RICHMOND, VIRGINIA 23273 PERMIT NO. One (1) copy of application and four (4) copies of plans are hereby made to the Director of Public Works

More information

GENERAL. This manual addresses five local programs that are funded under the current Highway Act:

GENERAL. This manual addresses five local programs that are funded under the current Highway Act: OVERVIEW The Local Public Agency Manual published by the Missouri Department of Transportation (MoDOT) is intended to be used as a guide for cities and counties that sponsor projects utilizing federal

More information

5 ALTERNATIVE SOLUTIONS AND EVALUATION

5 ALTERNATIVE SOLUTIONS AND EVALUATION Page 23 5 ALTERNATIVE SOLUTIONS AND EVALUATION The process used for the assessment and evaluation of the alternatives follows the procedures of the Municipal Class EA, as described below: Identify a reasonable

More information

CHAPTER 7: QUALITY CONTROL/QUALITY ASSURANCE ***DRAFT***

CHAPTER 7: QUALITY CONTROL/QUALITY ASSURANCE ***DRAFT*** CHAPTER 7: QUALITY CONTROL/QUALITY ASSURANCE ***DRAFT*** CHAPTER 7: QUALITY CONTROL/QUALITY ASSURANCE... 1 SECTION 7.1 INTRODUCTION... 2 Subsection 7.1.1 Purpose... 2 Subsection 7.1.2 Scope... 2 Subsection

More information

P. ALTERNATE TECHNICAL CONCEPTS FOR CONSTRUCTION, STAGING AND TRAFFIC CONTROL

P. ALTERNATE TECHNICAL CONCEPTS FOR CONSTRUCTION, STAGING AND TRAFFIC CONTROL P. ALTERNATE TECHNICAL CONCEPTS FOR CONSTRUCTION, STAGING AND TRAFFIC CONTROL 1.0 Description. 1.1 This specification allows bidders the opportunity to include in their overall bid proposal, pricing for

More information

PROJECT MANAGEMENT HANDBOOK, PART 1 - ISSUES COMMON TO ALL PROJECT MANAGERS

PROJECT MANAGEMENT HANDBOOK, PART 1 - ISSUES COMMON TO ALL PROJECT MANAGERS CHAPTER 11 - Project Continuity Contents Introduction... 2 Phase Hand-Offs... 3 Project Feedback... 9 Project Management Team Approach... 10 Page 1 of 15 Introduction A primary objective of all Project

More information

AGENCY COORDINATION AND PUBLIC INVOLVEMENT

AGENCY COORDINATION AND PUBLIC INVOLVEMENT 5 AGENCY COORDINATION AND PUBLIC INVOLVEMENT 5.1 AGENCY COORDINATION As part of the planning process for the Oregon Avenue Final EA, DDOT conducted an agency coordination program. This coordination included

More information

Western Federal Lands Highway Division. Project Development Process Flow Chart

Western Federal Lands Highway Division. Project Development Process Flow Chart Western Federal Lands Highway Division Project Development Process Flow Chart Revised September 2007 PS&E Development at Various Stages of Design October 2007 WFLHD SUPPLEMENT 9.6.3-1 9.6.3 PS&E DEVELOPMENT

More information

Design-Build Manual. Office of Construction and Innovative Contracting (OCIC)

Design-Build Manual. Office of Construction and Innovative Contracting (OCIC) Design-Build Manual Office of Construction and Innovative Contracting (OCIC) THIS PAGE INTENTIONALLY BLANK FOR TWO-SIDED PRINTING Table of Contents List of Exhibits... 4 List of Forms... 5 Request for

More information

Utility Coordination Procedures for Hillsborough County Construction Projects within County Rights-of-Way

Utility Coordination Procedures for Hillsborough County Construction Projects within County Rights-of-Way Public Works Department Utility Coordination Procedures for Hillsborough County Construction Projects within County Rights-of-Way October 2015 HillsboroughCounty.org HILLSBOROUGH COUNTY Office of the County

More information

WESTFIELD-WASHINGTON ADVISORY PLAN COMMISSION December 7, 2015 1512-SPP-24 & 1512-ODP-24

WESTFIELD-WASHINGTON ADVISORY PLAN COMMISSION December 7, 2015 1512-SPP-24 & 1512-ODP-24 Petition Number: Subject Site Address: Petitioner: Request: East side of Oak Road, north of 151 st Street Langston Development Co. Primary Plat and Overall Development Plan amendment review for Mapleridge

More information

National Environmental Policy Act/ Clean Water Act Section 404 (NEPA/404) Merger Process and Agreement for Transportation Projects in Colorado

National Environmental Policy Act/ Clean Water Act Section 404 (NEPA/404) Merger Process and Agreement for Transportation Projects in Colorado Background In a May 12, 2003, letter from Mr. James L. Connaughton, Executive Office of the President, Council on Environmental Quality, to Mr. Norman Y. Minneta, Secretary of Transportation, Mr. Connaughton

More information

Work Type Definition and Submittal Requirements Work Type: Right-of-Way Surveys / Land Surveys

Work Type Definition and Submittal Requirements Work Type: Right-of-Way Surveys / Land Surveys The first section, Work Type Definition, provides a detailed explanation of the work type. The second section, Work Type Submittal Requirements, identifies the requirements a firm must meet to become pre-qualified

More information

Alternatives Presentation Meeting Middlebury WCRS(23)

Alternatives Presentation Meeting Middlebury WCRS(23) Alternatives Presentation Meeting Middlebury WCRS(23) Main Street (VT 30/TH 2 Bridge 102) and Merchants Row (TH 8 Bridge 2) over Vermont Railway June 4, 2013 Twilight Hall Auditorium, Middlebury College

More information

Preliminary Plan Application and Checklist

Preliminary Plan Application and Checklist ALL APPLICATIONS ARE DUE AT 12:00 NOON ON THE FILING DATE Office Use Only PRELIMINARY / REVISED PRELIMINARY PLAN $300.00 Fee Paid: $ Date Paid: ALL FIELDS HIGHLIGHTED IN RED ARE REQUIRED FIELDS Case No.:

More information

FHWA Colorado Division Control of Access to the Interstate and its Right-of-Way February 2005

FHWA Colorado Division Control of Access to the Interstate and its Right-of-Way February 2005 FHWA Colorado Division Control of Access to the Interstate and its Right-of-Way February 2005 Background: It is in the national interest to maintain the Interstate System to provide the highest level of

More information

SECTION 5 DRAFTING STANDARDS

SECTION 5 DRAFTING STANDARDS SECTION 5 DRAFTING STANDARDS 1 SECTION FIVE TABLE OF CONTENTS Description Page TABLE OF CONTENTS... 5-2 GENERAL... 5-3 DRAFTING STANDARDS... 5-5 DRAFTING MINIMUM REQUIREMENTS HANDOUT... 5-8 2 GENERAL 1.

More information

Colorado Off-System Bridge Program Description and Guidelines for Selecting Bridges for Rehabilitation or Replacement Funding

Colorado Off-System Bridge Program Description and Guidelines for Selecting Bridges for Rehabilitation or Replacement Funding C Colorado Off-System Bridge Program Description and Guidelines for Selecting Bridges for Rehabilitation or Replacement Funding These guidelines are intended to provide assistance in selecting OFF-SYSTEM

More information

05-15-98 CIVIL ENGINEERING ASSOCIATE, 7246

05-15-98 CIVIL ENGINEERING ASSOCIATE, 7246 CITY OF LOS ANGELES CIVIL SERVICE COMMISSION CLASS SPECIFICATION POSTED JUNE 1999 05-15-98 CIVIL ENGINEERING ASSOCIATE, 7246 Summary of Duties: Performs professional civil engineering work in researching,

More information

Design-Build Process for Project Managers

Design-Build Process for Project Managers Vermont Agency of Transportation Design-Build Process for Project Managers This document provides guidance on the preliminary engineering and procurement process and roles and responsibilities of key personnel

More information

Public Information & Public Scoping Meeting

Public Information & Public Scoping Meeting Public Information & Public Scoping Meeting William F. Cribari Memorial Bridge Route 136 over the Saugatuck River Review of Rehabilitation Study Report Public Scoping for the gathering and analysis of

More information

City of Valdosta Land Development Regulations. Table of Contents

City of Valdosta Land Development Regulations. Table of Contents TITLE 1 ADMINISTRATION Chapter 102 General Provisions 102-1 Title 102-2 Purpose 102-3 Authority 102-4 Jurisdiction 102-5 Application of Ordinance 102-6 Relationship to Existing Ordinances 102-7 Powers

More information

DESIGN-BUILD PROCUREMENT AND ADMINISTRATION GUIDE

DESIGN-BUILD PROCUREMENT AND ADMINISTRATION GUIDE ARIZONA DEPARTMENT OF TRANSPORTATION INTERMODAL TRANSPORTATION DIVISION DESIGN-BUILD PROCUREMENT AND ADMINISTRATION GUIDE 3rd Edition December 2007 Published by: ADOT Construction Group 206 S. 17 th Ave.,

More information

THE COMMONWEALTH OF MASSACHUSETTS MASSACHUSETTS HIGHWAY DEPARTMENT PROJECT INITIATION FORM (PIF)

THE COMMONWEALTH OF MASSACHUSETTS MASSACHUSETTS HIGHWAY DEPARTMENT PROJECT INITIATION FORM (PIF) THE COMMONWEALTH OF MASSACHUSETTS MASSACHUSETTS HIGHWAY DEPARTMENT PROJECT INITIATION FORM (PIF) To: From: Contact Information: Roland Bartl, Planning, Town of Acton, 472 Main St. Acton MA 01440; 978-264-9639;

More information

City of Auburn Americans with Disabilities Act (ADA) Transition Plan for Curb Ramps, Sidewalks, and Pedestrian Signals ADA TRANSITION PLAN

City of Auburn Americans with Disabilities Act (ADA) Transition Plan for Curb Ramps, Sidewalks, and Pedestrian Signals ADA TRANSITION PLAN Americans with Disabilities Act (ADA) Transition Plan for Curb Ramps, Sidewalks, and Pedestrian Signals ADA TRANSITION PLAN December 21, 2009 Public Works Department 171 N. Ross Street, Suite 200 Auburn,

More information

Clean Water Revolving Funds (SRF & SWQIF) Loan Application Instructions for Completing the Project Cost Worksheet

Clean Water Revolving Funds (SRF & SWQIF) Loan Application Instructions for Completing the Project Cost Worksheet Clean Water Revolving Funds (SRF & SWQIF) Loan Application Instructions for Completing the Project Cost Worksheet 1. Entering Cost Figures To complete the Project Cost Worksheet, enter costs incurred to

More information

Work Type Definition and Submittal Requirements Work Type: Construction Contract Administration & Management

Work Type Definition and Submittal Requirements Work Type: Construction Contract Administration & Management The first section, Work Type Definition, provides a detailed explanation of the work type. The second section, Work Type Submittal Requirements, identifies the requirements a firm must meet to become pre-qualified

More information

SERVICES THAT MAY ONLY BE PERFORMED BY A NEW JERSEY PROFESSIONAL LAND SURVEYOR

SERVICES THAT MAY ONLY BE PERFORMED BY A NEW JERSEY PROFESSIONAL LAND SURVEYOR SERVICES THAT MAY ONLY BE PERFORMED BY A NEW JERSEY PROFESSIONAL LAND SURVEYOR 1. ANY MAP OR PLAN THAT SHOWS: Property Lines. NJSA 45:8-28(e), NJAC 13:40-1.3, 13:40-5.1 Locations of Existing Buildings

More information

Note: All terms which are defined and which are used throughout this document appear in italicized text beginning with a CAPITAL letter.

Note: All terms which are defined and which are used throughout this document appear in italicized text beginning with a CAPITAL letter. SCHEDULE OF CONSULTANT S SERVICES Note: All terms which are defined and which are used throughout this document appear in italicized text beginning with a CAPITAL letter. Project (Insert name and description

More information

3.1 Historical Considerations

3.1 Historical Considerations 3. Recommended Scope of Bridge improvements 3.1 Historical Considerations In the fall of 2000, an outside consultant, Fraser Design, suggested that the existing 4 th St. Bridge is potentially eligible

More information

Harris County Flood Control District. Policy, Criteria, and Procedure Manual

Harris County Flood Control District. Policy, Criteria, and Procedure Manual Harris County Flood Control District Policy, Criteria, and Procedure Manual For Approval and Acceptance of Infrastructure General Review October 10, 2003 Draft Please Provide Written Comments to the HCFCD

More information

Chapter 4 ASSET INVENTORY AND CONDITION CHAPTER 4 ASSET INVENTORY AND CONDITION PAGE 33

Chapter 4 ASSET INVENTORY AND CONDITION CHAPTER 4 ASSET INVENTORY AND CONDITION PAGE 33 Chapter 4 ASSET INVENTORY AND CONDITION CHAPTER 4 ASSET INVENTORY AND CONDITION PAGE 33 This page intentionally left blank. PAGE 34 MINNESOTA GO MNDOT TRANSPORTATION ASSET MANAGEMENT PLAN ASSET INVENTORY

More information

LOCATION AND DESIGN DIVISION

LOCATION AND DESIGN DIVISION VIRGINIA DEPARTMENT OF TRANSPORTATION LOCATION AND DESIGN DIVISION INSTRUCTIONAL AND INFORMATIONAL MEMORANDUM GENERAL SUBJECT: DESIGN EXCEPTIONS / WAIVERS SPECIFIC SUBJECT: DESIGN EXCEPTION REQUEST FORM

More information

Land Use Series. Check List # 1I For Adoption of an Amendment to a Plan. December 22, 2010. Bringing Knowledge to Life!

Land Use Series. Check List # 1I For Adoption of an Amendment to a Plan. December 22, 2010. Bringing Knowledge to Life! Land Use Series Bringing Knowledge to Life! Thirty seven million acres is all the Michigan we will ever have. Former Governor William G. Milliken Michigan State University Extension Land Use Team http://ntweb11a.ais.msu.

More information

US 281 AT PREMONT PUBLIC HEARING. US 281 at Premont Public Hearing

US 281 AT PREMONT PUBLIC HEARING. US 281 at Premont Public Hearing US 281 AT PREMONT PUBLIC HEARING Hearing Purpose The purpose of tonight s Public Hearing is for the public to: Learn about the status of the proposed project Review the purpose and need for the project

More information

MEMORANDUM COMMUNITY AND ECONOMIC DEVELOPMENT DEPARTMENT

MEMORANDUM COMMUNITY AND ECONOMIC DEVELOPMENT DEPARTMENT #19 MEMORANDUM COMMUNITY AND ECONOMIC DEVELOPMENT DEPARTMENT TO: SUBJECT: John C. Phillips, City Manager Downtown Riverfront Park Preliminary Design (Armory Park) REVISED Scope of Services Schreiber Anderson

More information

REQUEST FOR PROPOSAL FOR PROFESSIONAL SERVICES (PS-0748-A) Appendix 1 Project Information. PS-0748-A Page 1 5/4/2016 Appendix 1

REQUEST FOR PROPOSAL FOR PROFESSIONAL SERVICES (PS-0748-A) Appendix 1 Project Information. PS-0748-A Page 1 5/4/2016 Appendix 1 REQUEST FOR PROPOSAL FOR PROFESSIONAL SERVICES (PS-0748-A) Project Information PS-0748-A Page 1 5/4/2016 Table of Contents Project Budget Worksheet Program Plan Project Location (Site Plan) Scope of Services

More information

I-25/ARAPAHOE INTERCHANGE RECONSTRUCTION PROJECT

I-25/ARAPAHOE INTERCHANGE RECONSTRUCTION PROJECT MANDATORY PRE-BID SIGN IN CDOT Carrie DeJiacomo, Program Engineer John Hall, Resident Engineer Telecia McCline, Project Manager Tammy Maurer, Assistant Project Manager David Evans/Hartwig Design Consultant

More information

Document Comparison. AIA Documents A134 2009 and A131CMc 2003

Document Comparison. AIA Documents A134 2009 and A131CMc 2003 Document Comparison AIA Documents A134 2009 and A131CMc 2003 AIA Document A134 2009 is in the right-hand column. Corresponding sections of AIA Document A131 CMc 2003 are in the left-hand column. Sections

More information

Welcome! Purpose of Tonight s Meeting. Informational Open House to discuss two City projects: Goal is to LISTEN TO YOU

Welcome! Purpose of Tonight s Meeting. Informational Open House to discuss two City projects: Goal is to LISTEN TO YOU Purpose of Tonight s Meeting Informational Open House to discuss two City projects: Fairchild Street Subway Phase I Engineering: Immediate need to replace subway Bowman Avenue Feasibility Study Future

More information

ROAD SURVEYING Section I. RECONNAISSANCE SURVEY PREPARATION AND SCOPE

ROAD SURVEYING Section I. RECONNAISSANCE SURVEY PREPARATION AND SCOPE CHAPTER 2 ROAD SURVEYING Section I. RECONNAISSANCE SURVEY PREPARATION AND SCOPE The reconnaissance survey is an extensive study of an entire area that might be used for a road or airfield. Its purpose

More information

must possible Check-in/check-out should be utilized for all draft documents must Only final documents

must possible Check-in/check-out should be utilized for all draft documents must Only final documents ODOT NEPA File Management and Documentation Guidance Prepared by Ohio Department of Transportation, Office of Services Last Updated: 3/23/16 ODOT must retain project files and general administrative files

More information

Surface Transportation Program (STP) Projects

Surface Transportation Program (STP) Projects Toledo Metropolitan Area Council of Governments American Reinvestment and Recovery Act (Economic Stimulus Program) Application Packet for: Surface Transportation Program (STP) Projects APPLICATIONS DUE

More information

City of Edgewood REQUEST FOR QUALIFICATIONS 2016 ON-CALL CONSULTANT SERVICES

City of Edgewood REQUEST FOR QUALIFICATIONS 2016 ON-CALL CONSULTANT SERVICES City of Edgewood REQUEST FOR QUALIFICATIONS 2016 ON-CALL CONSULTANT SERVICES I. PURPOSE OF REQUEST. The City of Edgewood is requesting statements of qualifications from professional consulting firms licensed

More information

Town of Elkton & Cecil Soil Conservation District Checklist for Joint Agency Review Stormwater Management / Erosion and Sediment Control

Town of Elkton & Cecil Soil Conservation District Checklist for Joint Agency Review Stormwater Management / Erosion and Sediment Control Town of Elkton & Cecil Soil Conservation District Checklist for Joint Agency Review Stormwater Management / Erosion and Sediment Control Project Name: Tax Map Parcel: Acreage: Plat: ADC Map & Grid Engineering

More information

City of Colleyville Community Development Department. Site/Landscape Plan Application Packet

City of Colleyville Community Development Department. Site/Landscape Plan Application Packet City of Colleyville Community Development Department Site/Landscape Plan Application Packet Development Application Fees City of Colleyville 100 Main Street Colleyville TX 76034 817.503.1050 Zoning Zoning

More information

MassDOT s Work Zone Transportation Management Procedures. By: Neil Boudreau, MassDOT and Michael Sutton, P.E., VHB

MassDOT s Work Zone Transportation Management Procedures. By: Neil Boudreau, MassDOT and Michael Sutton, P.E., VHB MassDOT s Work Zone Transportation Management Procedures By: Neil Boudreau, MassDOT and Michael Sutton, P.E., VHB What is the Work Zone Safety and Mobility Rule? 23 CFR 630 Subpart J, effective October

More information

Program guidance that details the eligibility, criteria and application process. Ferry Boat Program. Ohio Department of Transportation

Program guidance that details the eligibility, criteria and application process. Ferry Boat Program. Ohio Department of Transportation Program guidance that details the eligibility, criteria and application process. Ferry Boat Program Ohio Department of Transportation TABLE OF CONTENTS Program Overview Program Administration.........2

More information

ORDINANCE NO. 2013 -

ORDINANCE NO. 2013 - ORDINANCE NO. 2013 - AN ORDINANCE OF BREVARD COUNTY, FLORIDA AMENDING CHAPTER 62, LAND DEVELOPMENT REGULATIONS SECTION 62-2891, LOT DRAINAGE, AND CHAPTER 22 BUILDINGS AND BUILDING REGULATIONS, SECTION

More information

Sec. 22a-1a page 1 (4-97)

Sec. 22a-1a page 1 (4-97) Department of Environmental Protection Sec. 22a-1a page 1 (4-97) TABLE OF CONTENTS Connecticut Environmental Policy Act Definitions... 22a-1a- 1 Determination of sponsoring agency.... 22a-1a- 2 Determination

More information

SECTION 611 ACCEPTANCE PROCEDURES FOR TRAFFIC CONTROL SIGNALS AND DEVICES

SECTION 611 ACCEPTANCE PROCEDURES FOR TRAFFIC CONTROL SIGNALS AND DEVICES SECTION 611 ACCEPTANCE PROCEDURES FOR TRAFFIC CONTROL SIGNALS AND DEVICES 611-1 Description. This Section sets forth Contract acceptance procedures for installations of traffic control signals and devices

More information

Work Type Definition and Submittal Requirements

Work Type Definition and Submittal Requirements Work Type: Highway Materials Testing Geotechnical Laboratory Testing, Geotechnical Laboratory Testing, Standard Penetration (SPT) & Rock Coring, Cone Penetration Test, Solid Stem Auger Drilling, and Materials

More information

REQUEST FOR PROPOSALS CENTRAL NEW YORK ECONOMIC DEVELOPMENT REAL ESTATE SITE PROFILE DATA BASE SYRACUSE, NEW YORK MARCH 25, 2013

REQUEST FOR PROPOSALS CENTRAL NEW YORK ECONOMIC DEVELOPMENT REAL ESTATE SITE PROFILE DATA BASE SYRACUSE, NEW YORK MARCH 25, 2013 REQUEST FOR PROPOSALS CENTRAL NEW YORK ECONOMIC DEVELOPMENT REAL ESTATE SITE PROFILE DATA BASE SYRACUSE, NEW YORK MARCH 25, 2013 CENTRAL NEW YORK REGIONAL PLANNING AND DEVELOPMENT BOARD 126 NORTH SALINA

More information

CHAPTER 20 Project Development Cost Estimates Table of Contents

CHAPTER 20 Project Development Cost Estimates Table of Contents Chapter 20 Project Development Cost Estimates Table of Contents CHAPTER 20 Project Development Cost Estimates Table of Contents CHAPTER 20 Project Development Cost Estimates... 20-3 SECTION 1 Project Cost

More information

STATE OF NEVADA Department of Administration Division of Human Resource Management CLASS SPECIFICATION

STATE OF NEVADA Department of Administration Division of Human Resource Management CLASS SPECIFICATION STATE OF NEVADA Department of Administration Division of Human Resource Management CLASS SPECIFICATION TITLE GRADE EEO-4 CODE RIGHT-OF-WAY SUPERVISOR 39 A 7.412 SERIES CONCEPT Right-of-Way Agents appraise,

More information

CHAPTER 2 ENVIRONMENTAL CLASS OF ACTION DETERMINATION

CHAPTER 2 ENVIRONMENTAL CLASS OF ACTION DETERMINATION CHAPTER 2 ENVIRONMENTAL CLASS OF ACTION DETERMINATION TABLE OF CONTENTS 2-1 OVERVIEW...2-1 2-2 PROCEDURE...2-5 2-2.1 Determination of Federal Action...2-5 2-2.2 Categorical Exclusions...2-6 2-2.2.1 FHWA

More information

FHWA Emergency Relief (FHWA-ER) Training

FHWA Emergency Relief (FHWA-ER) Training FHWA Emergency Relief (FHWA-ER) Training Training Developed and Coordinated By Colorado Department of Transportation 2 Agenda FHWA Flowchart Policies, Purpose, Agency Roles Application Process Eligibility

More information

Chapter 7 PURPOSE AND NEED MDT ENVIRONMENTAL MANUAL

Chapter 7 PURPOSE AND NEED MDT ENVIRONMENTAL MANUAL Chapter 7 PURPOSE AND NEED MDT ENVIRONMENTAL MANUAL October 2010 Table of Contents Section Page 7.1 OVERVIEW... 7-1 7.2 LAWS, REGULATIONS AND GUIDANCE... 7-2 7.2.1 40 CFR 1500 through 1508 CEQ Regulations...

More information

Northern Middlesex Council of Governments

Northern Middlesex Council of Governments Northern Middlesex Council of Governments The Federal Energy Commission (FERC) is the agency charged with evaluating whether the proposed route should be approved Cooperating agencies generally include

More information

Agenda Item Executive Summary

Agenda Item Executive Summary Agenda Item Executive Summary Title: Willow Road STADI Project Engineering: Change Order #2: Initial Permit Submittals Presenter: Steven M. Saunders, Director of Public Works/Village Engineer Agenda Date:

More information

Chapter Forty-seven. RURAL TWO-LANE/MULTILANE STATE HIGHWAYS (New Construction/Reconstruction) BUREAU OF DESIGN AND ENVIRONMENT MANUAL

Chapter Forty-seven. RURAL TWO-LANE/MULTILANE STATE HIGHWAYS (New Construction/Reconstruction) BUREAU OF DESIGN AND ENVIRONMENT MANUAL Chapter Forty-seven RURAL TWO-LANE/MULTILANE STATE HIGHWAYS (New Construction/Reconstruction) BUREAU OF DESIGN AND ENVIRONMENT MANUAL Illinois RURAL TWO-LANE/MULTILANE STATE HIGHWAYS December 2009 2 Illinois

More information

PART II SCHEDULE. Scope of Services. Special Terms and Conditions. Virginia Railway Express

PART II SCHEDULE. Scope of Services. Special Terms and Conditions. Virginia Railway Express PART II SCHEDULE SECTION TITLE D E Scope of Services Special Terms and Conditions 11 SECTION D SCOPE OF SERVICES D.1 OVERVIEW A. The selected firm is referred to herein as either the Consultant or the

More information

CHAPTER 27 New Public Road Connections. Table of Contents

CHAPTER 27 New Public Road Connections. Table of Contents Chapter 27 New Public Road Connections Table of Contents CHAPTER 27 New Public Road Connections Table of Contents CHAPTER 27 New Public Road Connections... 27-3 ARTICLE 1 - General... 27-3 Responsibility...

More information

REQUEST FOR PROPOSAL to provide ON-CALL ENVIRONMENTAL CONSULTING SERVICES for the RIVERSIDE COUNTY TRANSPORTATION DEPARTMENT

REQUEST FOR PROPOSAL to provide ON-CALL ENVIRONMENTAL CONSULTING SERVICES for the RIVERSIDE COUNTY TRANSPORTATION DEPARTMENT REQUEST FOR PROPOSAL to provide ON-CALL ENVIRONMENTAL CONSULTING SERVICES for the RIVERSIDE COUNTY TRANSPORTATION DEPARTMENT Table of Contents I. Events Calendar. 1 II. Introduction.. 2 III. Inquires.

More information

108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised 03-24-10)

108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised 03-24-10) CRITICAL PATH METHOD SCHEDULE (Revised 03-24-10) The Standard Specifications are revised as follows: SECTION 108, BEGIN LINE 177, INSERT AS FOLLOWS: 108.04.1 Critical Path Method Schedule (a) General Requirements

More information

GREENSBORO - HIGH POINT ROAD (SR 1486 / 4121)

GREENSBORO - HIGH POINT ROAD (SR 1486 / 4121) NORTH CAROLINA DEPARTMENT OF TRANSPORTATION GREENSBORO - HIGH POINT ROAD (SR 1486 / 4121) FROM PROPOSED US 311 BYPASS TO HILLTOP ROAD (SR 1424) TIP PROJECT U-2412 WBS Element 34802 Federal Project Number

More information

Electronic Signature and Fee Payment Confirmation

Electronic Signature and Fee Payment Confirmation Jeff Levine, AICP, Director Planning & Urban Development Department Electronic Signature and Fee Payment Confirmation Notice: Your electronic signature is considered a legal signature per state law. By

More information

STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY FINDINGS OF FACT

STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY FINDINGS OF FACT STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY IN THE MATTER OF THE DECISION ON THE NEED FOR AN ENVIRONMENTAL IMPACT STATEMENT FOR THE PROPOSED ELKO NEW MARKET INTERCEPTOR, CSAH 2 SEGMENT SCOTT

More information

Appendix. Change Management Plan. Communication Plan. QA/QC Plan. Transition and Closure Plan C-1

Appendix. Change Management Plan. Communication Plan. QA/QC Plan. Transition and Closure Plan C-1 Appendix C Change Management Plan Communication Plan QA/QC Plan Transition and Closure Plan C-1 CHANGE MANAGEMENT PLAN Whether the effects of changes are positive or negative, managing change is an important

More information

PLANNED UNIT DEVELOPMENT & SIDEWALK WAIVER REQUEST STAFF REPORT Date: November 7, 2013

PLANNED UNIT DEVELOPMENT & SIDEWALK WAIVER REQUEST STAFF REPORT Date: November 7, 2013 PLANNED UNIT DEVELOPMENT & SIDEWALK WAIVER REQUEST STAFF REPORT Date: November 7, 2013 NAME LOCATION Audubon Properties, LLC. 4700 & 4960 Dauphin Island Parkway West side of Dauphin Island Parkway, 580

More information

Township of Georgian Bluffs POLICY USE OF UNOPENED ROAD ALLOWANCES

Township of Georgian Bluffs POLICY USE OF UNOPENED ROAD ALLOWANCES Township of Georgian Bluffs POLICY USE OF UNOPENED ROAD ALLOWANCES 1.0 Background An unopened road allowance as defined by the Municipal Act is a public highway that has not been opened and assumed for

More information

ARKANSAS STATE HIGHWAY AND TRANSPORTATION DEPARTMENT DESIGN-BUILD GUIDELINES AND PROCEDURES

ARKANSAS STATE HIGHWAY AND TRANSPORTATION DEPARTMENT DESIGN-BUILD GUIDELINES AND PROCEDURES ARKANSAS STATE HIGHWAY AND TRANSPORTATION DEPARTMENT DESIGN-BUILD GUIDELINES AND PROCEDURES Revision 1 September 2015 TABLE OF CONTENTS Section I. Introduction 6 PURPOSE 6 AUTHORITY 6 DEFINITIONS AND ACRONYMS

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS for PRELIMINARY ENGINEERING AND RIGHT-OF-WAY SERVICES for the COVELO SR 162 CORRIDOR MULTI-PURPOSE TRAIL in MENDOCINO COUNTY FOR: MENDOCINO COUNCIL OF GOVERNMENTS Phillip J. Dow,

More information

Draft Environmental Impact Statement. PORT OF OSWEGO AUTHORITY Lead Agency, State Environmental Quality Review Act

Draft Environmental Impact Statement. PORT OF OSWEGO AUTHORITY Lead Agency, State Environmental Quality Review Act CENTERSTATE NY INLAND PORT DRAFT SCOPING DOCUMENT FOR THE Draft Environmental Impact Statement PORT OF OSWEGO AUTHORITY Lead Agency, State Environmental Quality Review Act SEPTEMBER 30, 2015 INTRODUCTION

More information

TRANSPORTATION IMPACT ANALYSIS PROCEDURES MANUAL

TRANSPORTATION IMPACT ANALYSIS PROCEDURES MANUAL TRANSPORTATION IMPACT ANALYSIS PROCEDURES MANUAL INTRODUCTION The Town of Harrisburg is committed to establishing an interconnected, multimodal transportation system that increases mobility, safety, connectivity,

More information

TH 23 Access Management Study Richmond to Paynesville

TH 23 Access Management Study Richmond to Paynesville TH 23 Access Management Study Richmond to Paynesville Prepared For: Minnesota Department of Transportation District 8 Prepared By: Short Elliott Hendrickson Inc. July 2015 Table of Contents I. Introduction...

More information

3. The submittal shall include a proposed scope of work to confirm the provided project description;

3. The submittal shall include a proposed scope of work to confirm the provided project description; QIN Shoreline Master Program Project Summary The Shoreline Master Program (SMP) development process for the Quinault Indian Nation (QIN) includes the completion of inventory and analysis report with corresponding

More information

14-97. 14-97.002 Definitions. For the purposes of this rule chapter the following definitions shall apply unless the context clearly shows otherwise:

14-97. 14-97.002 Definitions. For the purposes of this rule chapter the following definitions shall apply unless the context clearly shows otherwise: 14-97 14-97.001 Purpose. This rule chapter sets forth an access control classification system and access management standards to implement the State Highway System Access Management Act of 1988. The implementation

More information

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0

More information

WORK ZONE SAFETY & MOBILITY GUIDANCE DOCUMENT

WORK ZONE SAFETY & MOBILITY GUIDANCE DOCUMENT WORK ZONE SAFETY & MOBILITY GUIDANCE DOCUMENT August 2007 Prepared by: Vermont Agency of Transportation The following document was drafted in response to updates made to the work zone regulations at 23

More information

Technical Memorandum No. 1: Environmental Approach and Decision Making Criteria

Technical Memorandum No. 1: Environmental Approach and Decision Making Criteria Memorandum TO: FROM: Michael Bergstrom and Robin Cole City of Bellevue Nancy Bird, AICP EDAW, Inc. DATE: July 23, 2008 RE: Technical Memorandum No. 1: Environmental Approach and Decision Making Criteria

More information

TOPOGRAPHICAL SURVEY REPORT - PART OF L.R No. 7413/11 Done on February 2015 at International Union for Conservation of Nature (IUCN) Eastern African

TOPOGRAPHICAL SURVEY REPORT - PART OF L.R No. 7413/11 Done on February 2015 at International Union for Conservation of Nature (IUCN) Eastern African TOPOGRAPHICAL SURVEY REPORT - PART OF L.R No. 7413/11 Done on February 2015 at International Union for Conservation of Nature (IUCN) Eastern African Regional Office 01 CHAPTER ONE Checklist Page 2 of 8

More information

Request for Proposals for Professional Civil Engineering Services. for the. Bridge Replacement Project. Placerville Drive Bridge at Hangtown Creek

Request for Proposals for Professional Civil Engineering Services. for the. Bridge Replacement Project. Placerville Drive Bridge at Hangtown Creek Request for Proposals for Professional Civil Engineering Services for the Bridge Replacement Project Placerville Drive Bridge at Hangtown Creek CITY PROJECT No. 41410 FEDERAL AID PROJECT No. BRLS 5015(024)

More information

FIBER-OPTIC CABLE PLAN CHECK

FIBER-OPTIC CABLE PLAN CHECK Engineering Division 201 North Broadway, Escondido, CA 92025 (760) 839-4651, FAX (760) 839-4597 FIBER-OPTIC CABLE PLAN CHECK To: Date: Project: Project No. Address: Check No. Attn: Via: The attached plans

More information

PUBLIC RIGHT-OF-WAY ACCESSIBILITY TRANSITION PLAN

PUBLIC RIGHT-OF-WAY ACCESSIBILITY TRANSITION PLAN PUBLIC RIGHT-OF-WAY ACCESSIBILITY TRANSITION PLAN FOR THE VILLAGE OF HUNTLEY, ILLINOIS 2015 Contents Introduction 1 Purpose 1 Officials Responsible for Implementation 2 Public Notice 2 Grievance Procedure

More information

Exhibit A Draft Scope of Work

Exhibit A Draft Scope of Work 1.0 General Statement of Scope of Work The Contractor will work with MnDOT as the Design Build Verification Consultant (DBVC) for the I-35W 4th Street South Design Build Project (Project). Contractor will

More information