How To Fix The Att Fd-6 Gap For Interregional Projects Outside Of Miso

Size: px
Start display at page:

Download "How To Fix The Att Fd-6 Gap For Interregional Projects Outside Of Miso"

Transcription

1 Potential Attachment FF-6 Tariff Gap Options Regional Expansion Criteria & Benefits Working Group (RECBWG) April 19, 2016

2 Overview Objective Review original intent of Attachment FF-6 Highlight tariff gap for interregional economic projects outside of MISO Discuss options to address gap Key Takeaways 2 of our JOAs allow for interregional projects to reside wholly in another RTO Attachment FF-6 only addresses projects terminating in MISO Attachment FF-6 gap for economic interregional projects located wholly outside of MISO. MISO is presenting 2 potential options: No tariff change and apply existing MEP cost allocation rules Modify Attachment FF-6 2

3 Attachment FF-6 Background MISO South transition period Transmission Expansion Planning Cost Allocation Transmission Projects Baseline Reliability Projects (BRPs) Market Efficiency Projects (MEPs) Multi-Value Projects (MVPs) Location Terminating in MISO North/Central and MISO South Terminating exclusively in one planning area 3

4 Background Why does the Att FF-6 gap only exist for economic beneficial interregional projects located wholly in another RTO? Reliability & Public Policy Interregional projects driven solely by reliability utilize the avoided cost of specific BRP projects when determining cost allocation, so those costs would be assigned to the original entity whose regional project was avoided. Public policy driven projects also utilize avoided cost. Those who would have paid the cost of the regional project would pay the cost of the interregional project. Economic Interregional projects that provide economic benefits utilize APC benefits, which are regionally cost shared both from a LRZ (80%) and a footprint wide postage stamp (20%) standpoint. There is no avoided project. 4

5 Option 1 No Tariff Change, Default to Existing Att FF MEP Cost Allocation Since Att FF-6 is silent on what to do with an interregional project that terminates solely outside of MISO, an option is to default to current Attachment FF procedures for economic projects. This however, implements a 20% postage stamp allocation of costs across the entire MISO footprint. Hypothetical Examples Interregional project provides economic benefits to MISO but is located wholly outside of MISO: Hypothetical Examples for Option 1 A B C Total Interregional Project Cost $100 million $100 million $100 million Total MISO Benefit 30% 30% 30% Analysis Results North/Central Benefit 100% 0% 50% Analysis Results South Benefit 0% 100% 50% MISO Cost Share $30 million $30 million $30 million MISO Regional Cost Allocation in Attachment FF LRZs 80% 80% 80% Postage Stamp Footprint Wide 20% 20% 20% Allocation of 80% to Benefitting LRZs LRZs in North/Central Cost $24 million $0 $12 million LRZs in South Cost $0 $24 million $12 million 20% Postage Stamp Allocation Footprint Wide $6 million $6 million $6 million 5

6 Option 2 - Modify Attachment FF-6 Introduces a benefit threshold to address a scenario where analysis shows that benefits span across North/Central and South. If at least 80% of MISO s benefit is to one particular region, then default to transition period language outlined in Attachment FF-6 Projects would be treated as if they terminate in the area benefiting by 80% or greater Hypothetical Examples Interregional project provides economic benefits to MISO but is located wholly outside of MISO. 80% of benefit resided in one MISO sub-region: Hypothetical Examples for Option 2 D E Total Interregional Project Cost $100 million $100 million Total MISO Benefit 30% 30% Analysis Results North/Central Benefit 80% of the 30% = 24% 20% of the 30% = 6% Analysis Results South Benefit 20% of the 30% = 6% 80% of the 30% = 24% MISO Cost Share $30 million $30 million MISO Cost Allocation for South Transition Period 100% to where project terminates North/Central Planning Area $30 million $0 South Planning Area $0 $30 million Allocation of 80% to Benefitting LRZs LRZs in North/Central Cost $24 million $0 LRZs in South Cost $0 $24 million 20% Postage Stamp North/Central Planning Area Cost $6 million $0 South Planning Area Cost $0 $6 million 6

7 Eric Thoms (651) Contacts Davey Lopez (317) Cathy Brewster (317)

8 Appendix 8

9 Regional Project Types and Cost Allocation Allocation Category Driver(s) Allocation to Beneficiaries Participant Funded ( Other ) Transmission Delivery Service Project Generation Interconnection Project Transmission Owner identified project that does not qualify for other cost allocation mechanisms. Can be driven by reliability, economics, public policy or some combination of the three. Transmission Service Request Interconnection Request Paid by requestor (local Pricing Zone) Generally paid for by Transmission Customer; Transmission Owner can elect to roll-in into local Pricing Zone rates Primarily paid for by requestor; 345 kv and above 10% postage stamp to load Baseline Reliability Project NERC Reliability Criteria 100% allocated to local Pricing Zone Market Efficiency Project Multi-Value Project Reduce market congestion when benefits are 1.25 in excess of costs Address energy policy laws and/or provide widespread benefits across footprint 345 kv and above: 80% distributed to Local Resource Zones commensurate with expected benefit, 20% postage stamp to load 100% postage stamp to load and exports other than what is exported to PJM 9

10 Interregional Planning and Cost Allocation Project Requirements Metrics Used Seam PJM Transmission Need Reliability Benefit to Cost Interconnection in both RTOs > $5 Million Avoided Cost Adjusted Production Cost Net Load Payments Economic >1.25 Public Policy Reliability >1.25 SERTP Economic >1.25 Public Policy >1.25 Reliability SPP Economic Public Policy 10

PJM Seams Update: Day-Ahead M2M Revisions to MISO- PJM Joint Operating Agreement

PJM Seams Update: Day-Ahead M2M Revisions to MISO- PJM Joint Operating Agreement PJM Seams Update: Day-Ahead M2M Revisions to MISO- PJM Joint Operating Agreement Asanga Perera Market-to-Market Lead Market Implementation Committee August 12, 2015 Purpose Overview This presentation provides

More information

Firm Flow Entitlement on M2M Flowgates Readers' Guide. Last Updated: February 01, 2016 Version: 4.0

Firm Flow Entitlement on M2M Flowgates Readers' Guide. Last Updated: February 01, 2016 Version: 4.0 Firm Flow Entitlement on M2M Flowgates Readers' Guide Last Updated: February 01, 2016 Version: 4.0 1 Table of Contents 1 DISCLAIMER...3 2 INTRODUCTION...3 3 GLOSSARY OF TERMS...3 4 FFE FILE...3 4.1 DESCRIPTION...

More information

PJM LMP Market Overview

PJM LMP Market Overview PJM LMP Market Overview Andrew Ott Senior Vice President, Markets June 10, 2010 PJM as Part of the Eastern Interconnection 6,038 substations KEY STATISTICS PJM member companies 600+ millions of people

More information

Electricity from the Power Plant To the Consumer

Electricity from the Power Plant To the Consumer Electric Transmission Lines Electricity from the Power Plant To the Consumer The Nature of Electricity Electricity must be used as it is generated. Unlike other commodities, there is very little ability

More information

INDEPENDENT SYSTEM OPERATORS (VI + Access Rules vs. ISO vs. ITSO)

INDEPENDENT SYSTEM OPERATORS (VI + Access Rules vs. ISO vs. ITSO) INDEPENDENT SYSTEM OPERATORS (VI + Access Rules vs. ISO vs. ITSO) Paul L. Joskow September 28, 2007 ALTERNATIVE SYSTEM OPERATOR MODELS System operator (SO) is vertically integrated utility (G+T) Functional

More information

FERC Order 1000 Transmission Planning and Cost Allocation. FRCC Board Briefing June 28, 2012

FERC Order 1000 Transmission Planning and Cost Allocation. FRCC Board Briefing June 28, 2012 FERC Order 1000 Transmission Planning and Cost Allocation FRCC Board Briefing June 28, 2012 Agenda Background Order 1000 Compliance Filings Regional Compliance Concepts Florida Sponsors Proposal Florida

More information

The Wind Coalition WIND ENERGY IS HERE TODAY AND IN AMERICA S FUTURE

The Wind Coalition WIND ENERGY IS HERE TODAY AND IN AMERICA S FUTURE The Wind Coalition 1 WIND ENERGY IS HERE TODAY AND IN AMERICA S FUTURE We will harness the sun and the winds and the soil to fuel our cars and run our factories. And we will transform our schools and colleges

More information

2012-2016 Strategic Plan

2012-2016 Strategic Plan 2012-2016 Strategic Plan A Message from John R. Bear, President and CEO J. Michael Evans, Chairman of the Board of Directors MISO prides itself on continually fostering a transparent, effective stakeholder

More information

Gas Electric System Interface Study. PPA Stakeholder Forum: MISO ENGCTF 6/03/2013 Eric Thoms (MISO)

Gas Electric System Interface Study. PPA Stakeholder Forum: MISO ENGCTF 6/03/2013 Eric Thoms (MISO) Gas Electric System Interface Study PPA Stakeholder Forum: MISO ENGCTF 6/03/2013 Eric Thoms (MISO) Table of Contents History Participating Planning Authorities (PPAs) / Study Region PPA Stakeholder Groups

More information

Key Take Away : There are 4 types of MISO transmission transactions : 1) Drive- In, 2) Drive-Within, 3) Drive-through, and 4) Drive-Out

Key Take Away : There are 4 types of MISO transmission transactions : 1) Drive- In, 2) Drive-Within, 3) Drive-through, and 4) Drive-Out 1 2 3 Key Take Away : There are 4 types of MISO transmission transactions : 1) Drive- In, 2) Drive-Within, 3) Drive-through, and 4) Drive-Out Speaker Notes: Drive-In refers to transactions that originate

More information

Generation and Transmission Interconnection Process

Generation and Transmission Interconnection Process PJM Manual 14A Generation and Transmission Interconnection Process Revision: 18 Effective Date: January 28, 2016 Prepared by Planning Division Generation Interconnection Department PJM 2016 Table of Contents

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Capacity Deliverability Across the ) Midwest Independent Transmission System ) Docket No. AD12-16-000 Operator, Inc./PJM Interconnection,

More information

AAPG 2011 Annual Convention & Exhibition April 10, 2011

AAPG 2011 Annual Convention & Exhibition April 10, 2011 Generator Transmission Grid Interconnection Guidelines AAPG 2011 Annual Convention & Exhibition April 10, 2011 Hala Ballouz, B.Sc., M.Sc. TAMU, P.E. President, Electric Power Engineers, Inc. Partner &

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Rock Island Clean Line LLC ) Docket No. ER12-365-000

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Rock Island Clean Line LLC ) Docket No. ER12-365-000 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Rock Island Clean Line LLC ) Docket No. ER12-365-000 ROCK ISLAND CLEAN LINE LLC S ANSWER TO COMMENTS OF INTERSTATE POWER AND LIGHT

More information

A Survey of Transmission Cost Allocation Methodologies for Regional Transmission Organizations

A Survey of Transmission Cost Allocation Methodologies for Regional Transmission Organizations A Survey of Transmission Cost Allocation Methodologies for Regional Transmission Organizations S. Fink, K. Porter, C. Mudd, and J. Rogers Exeter Associates, Inc. Columbia, Maryland NREL is a national laboratory

More information

Responsibility for Outage Coordination is designated by 4 key artifacts: 1. FERC Order 2000 FERC Order 2000 (Docket No. RM99-2-000; Order No.

Responsibility for Outage Coordination is designated by 4 key artifacts: 1. FERC Order 2000 FERC Order 2000 (Docket No. RM99-2-000; Order No. 1 2 3 4 Responsibility for Outage Coordination is designated by 4 key artifacts: 1. FERC Order 2000 FERC Order 2000 (Docket No. RM99-2-000; Order No. 2000) comments regarding Transmission and Generation

More information

COLORADO SPRINGS UTILITIES ATTACHMENT K TO OPEN ACCESS TRANSMISSION TARIFF

COLORADO SPRINGS UTILITIES ATTACHMENT K TO OPEN ACCESS TRANSMISSION TARIFF COLORADO SPRINGS UTILITIES ATTACHMENT K TO OPEN ACCESS TRANSMISSION TARIFF I. INTRODUCTION The City of Colorado Springs, Colorado ( City ) is a Colorado home-rule municipal corporation with a population

More information

Addressing Barriers to Renewable Energy Procurement. In association with the EPA Green Power Partnership

Addressing Barriers to Renewable Energy Procurement. In association with the EPA Green Power Partnership Addressing Barriers to Renewable Energy Procurement In association with the EPA Green Power Partnership September 19, 2012 CORPORATE GOALS Corporations are increasingly interested renewable energy. The

More information

THE FERC STANDARD MARKET DESIGN GIGANOPR: RESEARCH NEEDS

THE FERC STANDARD MARKET DESIGN GIGANOPR: RESEARCH NEEDS THE FERC STANDARD MARKET DESIGN GIGANOPR: RESEARCH NEEDS Presentation by George Gross University of Illinois at Urbana-Champaign Modernizing the National Electric Power Grid NSF Workshop November 18-19,

More information

Comments of Louisiana Energy Users Group and Texas Industrial Energy Consumers. MISO South Market Congestion Planning Study. September 18, 2015

Comments of Louisiana Energy Users Group and Texas Industrial Energy Consumers. MISO South Market Congestion Planning Study. September 18, 2015 Comments of Louisiana Energy Users Group and Texas Industrial Energy Consumers On MISO South Market Congestion Planning Study September 18, 2015 In response to the MISO Staff s September 11, 2015 request

More information

State Of California's Energy Bill

State Of California's Energy Bill 2750 Monroe Boulevard Valley Forge Corporate Center Audubon, PA 19403 James M. Burlew Counsel Telephone: (610) 666-4345 Fax (610) 666-8211 Email Address: james.burlew@pjm.com December 15, 2015 The Honorable

More information

Analysis and Selection of Analytical Tools to Assess National-Interest Transmission Bottlenecks Final Report

Analysis and Selection of Analytical Tools to Assess National-Interest Transmission Bottlenecks Final Report Analysis and Selection of Analytical Tools to Assess National-Interest Transmission Bottlenecks Final Report This work described in this report was coordinated by the Consortium for Electric Reliability

More information

NYISO Business Issues Committee Meeting Minutes DRAFT. October 6, 2010 10:00 a.m. 3:00 p.m.

NYISO Business Issues Committee Meeting Minutes DRAFT. October 6, 2010 10:00 a.m. 3:00 p.m. DRAFT NYISO Business Issues Committee October 6, 2010 10:00 a.m. 3:00 p.m. 1. Introductions, Meeting Objectives, and Chairman s Report Mr. Glenn Haake (Dynegy), the Chair of the Business Issues Committee

More information

TRANSMISSION GRID DEVELOPMENT & PORTFOLIO SERVICES December 22, 2014. Senior Vice President Trans Grid Development & Portfolio Services

TRANSMISSION GRID DEVELOPMENT & PORTFOLIO SERVICES December 22, 2014. Senior Vice President Trans Grid Development & Portfolio Services TRANSMISSION GRID DEVELOPMENT & PORTFOLIO SERVICES December 22, 2014 Senior Vice President Trans Grid Development & Portfolio Services The Senior Vice President Transmission Grid Development & Portfolio

More information

Competition in Transmission Planning and Development:

Competition in Transmission Planning and Development: Competition in Transmission Planning and Development: Current Status and International Experience Presented at EUCI Transmission Policy: A National Summit Washington, DC Prepared by Johannes Pfeifenberger

More information

Merchant Interconnectors

Merchant Interconnectors Merchant Interconnectors David Newbery EPRG Winter Research Seminar Cambridge 15 December 2006 http://www.electricitypolicy.org.uk Outline Strong pressure from EC to increase interconnection impeded by

More information

Performance Metrics. For Independent System Operators And Regional Transmission Organizations

Performance Metrics. For Independent System Operators And Regional Transmission Organizations Performance Metrics For Independent System Operators And Regional Transmission Organizations A Report to Congress In Response to Recommendations of the United States Government Accountability Office April

More information

The Benefits of Electric Transmission:

The Benefits of Electric Transmission: A WIRES Report on The Benefits of Electric Transmission: Identifying and Analyzing the Value of Investments The Brattle Group Judy W. Chang Johannes P. Pfeifenberger J. Michael Hagerty July 2013 www.wiresgroup.com

More information

Responsible for pipeline engineering and plant operations for DTI and Cove Point.

Responsible for pipeline engineering and plant operations for DTI and Cove Point. GAS TRANSMISSION DTI - Pipeline Vice President, Pipeline Responsible for pipeline operations for DTI and Cove Point. Vice President, Pipeline Engineering & Plant Managing Director, Pipeline Director, Gas

More information

124 FERC 61,317 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. Communication Protocols for Public Utilities ORDER NO.

124 FERC 61,317 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. Communication Protocols for Public Utilities ORDER NO. 124 FERC 61,317 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Joseph T. Kelliher, Chairman; Suedeen G. Kelly, Marc Spitzer, Philip D. Moeller, and Jon Wellinghoff.

More information

2015/2016 Planning Resource Auction Results. April 14, 2015

2015/2016 Planning Resource Auction Results. April 14, 2015 2015/2016 Planning Resource Auction Results April 14, 2015 Executive Summary MISO successfully completed its third annual Planning Resource Auction The MISO region has adequate resources to meet its Planning

More information

Retail Electric Rates in Deregulated and Regulated States: A Ten Year Comparison

Retail Electric Rates in Deregulated and Regulated States: A Ten Year Comparison Retail Electric Rates in Deregulated and Regulated States: A Ten Year Comparison Published March 2008 1875 Connecticut Avenue, NW Washington, D.C. 20009-5715 202/467-2900 www.appanet.org Retail Electric

More information

Clean Power Plan: MISO Analysis ADEQ/APSC Stakeholder Meeting

Clean Power Plan: MISO Analysis ADEQ/APSC Stakeholder Meeting Clean Power Plan: MISO Analysis ADEQ/APSC Stakeholder Meeting 8/28/2014 The generation fleet in MISO is being affected by timing, fuel prices and multiple phases of environmental regulations. MATS CSAPR

More information

Transmission Planning in the ERCOT Interconnection

Transmission Planning in the ERCOT Interconnection Transmission Planning in the ERCOT Interconnection Warren Lasher Manager, Long-Term Planning and Policy Department of Energy Electricity Advisory Committee The ERCOT Interconnection The ERCOT Region is

More information

Transmission Cost Allocation and Cost Recovery in the West

Transmission Cost Allocation and Cost Recovery in the West Transmission Cost Allocation and Cost Recovery in the West Presented at: Transmission Executive Forum WEST 2011 Strategies for Meeting the Transmission Needs in the West Presented by: Johannes Pfeifenberger

More information

Presentation for The National Commission for Energy State Regulation of Ukraine

Presentation for The National Commission for Energy State Regulation of Ukraine Presentation for The National Commission for Energy State Regulation of Ukraine Todd Keech Laura Walter PJM Interconnection June 17, 2014 What is PJM? 1 What is PJM? ISO RTO Map Part of Eastern Interconnection

More information

[ELECTRICITY PROCUREMENT PLAN] Prepared in accordance with the Illinois Power Agency and Illinois Public Utilities Acts September 29, 2014

[ELECTRICITY PROCUREMENT PLAN] Prepared in accordance with the Illinois Power Agency and Illinois Public Utilities Acts September 29, 2014 2015 Anthony Star Director [ELECTRICITY PROCUREMENT PLAN] Prepared in accordance with the Illinois Power Agency and Illinois Public Utilities Acts September 29, 2014 Illinois Power Agency 2015 Electricity

More information

New York State of the Market System - NYISO Success Project

New York State of the Market System - NYISO Success Project Auxiliary Market Products Additional Capacity Zones The NYISO and stakeholders are developing the rationale in 2010 for creating additional capacity zones, identified as a recommendation in the 2009 State

More information

Ms. Rae McQuade President & COO, North American Energy Standards Board

Ms. Rae McQuade President & COO, North American Energy Standards Board NORTH AMERICAN ENERGY STANDARDS BOARD 801 Travis, Suite 1675 Houston, Texas 77002 Phone: (713) 356-0060 Fax: (713) 356-0067 email: naesb@naesb.org Web Site Address: www.naesb.org The Honorable Kimberly

More information

Section 4: Integrating Public Policy Drivers

Section 4: Integrating Public Policy Drivers Public Policy Drivers Section : Integrating Public Policy Drivers PJM DE DC IL IN KY MD MI NJ NC OH PA TN VA WV Section.0: The Role of Public Policy in the RTEP Process Figure.1: Public Policy Drivers

More information

GIP. 3.2.3 Net Zero Interconnection Service.

GIP. 3.2.3 Net Zero Interconnection Service. GIP and GIA Energy Displacement Agreement shall mean an agreement between an Interconnection Customer with a commercially operating Generating Facility on the Transmission Provider s Transmission System

More information

May 3, 2011. 10:00 a.m. 3:30 p.m.

May 3, 2011. 10:00 a.m. 3:30 p.m. NYISO Business Issues Committee Meeting Minutes NYISO Business Issues Committee Meeting Minutes May 3, 2011 10:00 a.m. 3:30 p.m. 1. Introductions, Meeting Objectives, and Chairman s Report The chair of

More information

Project Screening Results

Project Screening Results Project Screening Results Updated Economic Issues List Issue Id Constraint Name Contingency M-1 Frederick Town AECI - Frederick Town AMMO 161 kv Line Lutesville - St Francois 345kV Line S-2 North East

More information

Market Solutions to Loop Flow

Market Solutions to Loop Flow Market Solutions to Loop Flow Robert Pike Director, Market Design New York Independent System Operator Business Issues Committee September 9, 2009 1 Agenda Background Recommendation Next Steps Solution

More information

Generator Interconnection and Deliverability Study Methodology Technical Paper

Generator Interconnection and Deliverability Study Methodology Technical Paper Generator Interconnection and Deliverability Study Methodology Technical Paper July 2, 2013 Generator Interconnection and Deliverability Study Methodology Table of Contents Introduction... 1 Section One:

More information

Economic Assessment of RTO Policy

Economic Assessment of RTO Policy Economic Assessment of RTO Policy Prepared for: Federal Energy Regulatory Commission Prepared by: ICF Consulting February 26, 2002 TABLE OF CONTENTS Page EXECUTIVE SUMMARY...V 1 INTRODUCTION...1 1.1 STUDY

More information

NEW JERSEY ELECTRICITY SUPPLIER LICENSE NUMBER PSEL 0016

NEW JERSEY ELECTRICITY SUPPLIER LICENSE NUMBER PSEL 0016 TERMS & CONDITIONS NEW JERSEY ELECTRICITY SUPPLIER LICENSE NUMBER PSEL 0016 Purchase of Electric Generation Service Constellation NewEnergy, Inc. ("Constellation") agrees to sell, and you agree to buy,

More information

TRANSMISSION OPERATIONS (August 5, 2010)

TRANSMISSION OPERATIONS (August 5, 2010) TRANSMISSION OPERATIONS (August 5, 2010) Managing Director Transmission Operations: Paul B. Johnson The Managing Director - Transmission Operations is responsible for the safe, reliable, costeffective,

More information

New Brunswick Electricity Business Rules

New Brunswick Electricity Business Rules New Brunswick Electricity Business Rules Table of Contents Chapter 1 Chapter 2 Chapter 3 Chapter 4 Administration and Participation Transmission Planning and Connections Reliable Operations Billing and

More information

New York s Transmission Challenges and Opportunities: An Overview

New York s Transmission Challenges and Opportunities: An Overview New York s Transmission Challenges and Opportunities: An Overview By: Dr. Matthew Cordaro 2012 is shaping up to be the year of the grid. Governor Cuomo has proposed an energy highway aimed at finding ways

More information

Administrative Services for the PJM Interconnection Operating Agreement

Administrative Services for the PJM Interconnection Operating Agreement PJM Manual 33: Administrative Services for the PJM Interconnection Operating Agreement Revision: 12 Effective Date: March 31, 2016 Prepared by Member Relations PJM 2016 PAGE iii lviii PJM 2008 Revision

More information

2014 Retail Electric Rates. in Deregulated and Regulated States

2014 Retail Electric Rates. in Deregulated and Regulated States 2014 Retail Electric Rates in Deregulated and Regulated States Published April 2015 2014 Retail Electric Rates in Deregulated and Regulated States Prepared by Paul Zummo, Manager, Policy Research and Analysis

More information

2016 Firewall Management Trends Report

2016 Firewall Management Trends Report 2016 Firewall Management Trends Report A survey of trends in firewall use and satisfaction with firewall management JANUARY 2016 Copyright 2016 Skybox Security, Inc. All rights reserved. Skybox is a trademark

More information

Appendix A. Glossary. For. 2016 Request For Proposals For Long-Term Renewable Generation Resources for Entergy Louisiana, LLC

Appendix A. Glossary. For. 2016 Request For Proposals For Long-Term Renewable Generation Resources for Entergy Louisiana, LLC Appendix A Glossary For 2016 Request For Proposals For Long-Term Renewable Generation Resources for Entergy Louisiana, LLC Entergy Services, Inc. June 8, 2016 Website means the internet website https://spofossil.entergy.com/entrfp/send/2016ellrenewablerfp/index.htm.

More information

HVDC Transmission Line Project for Moving ERCOT Wind Into SERC

HVDC Transmission Line Project for Moving ERCOT Wind Into SERC HVDC Transmission Line Project for Moving ERCOT Wind Into SERC ERCOT RPG Meeting August 13, 2010 Agenda Pattern Energy Group SERC and ERCOT Market Drivers Southern Cross Project Overview Project Development

More information

MINNESOTA POWER. Company Background: CapX2020 Transmission Plan

MINNESOTA POWER. Company Background: CapX2020 Transmission Plan TRANSMISSION PROJECTS: AT A GLANCE MINNESOTA POWER MINNESOTA POWER Company Background: Minnesota Power, a division of ALLETE, provides electricity in a 26,000 square mile electric service area located

More information

JOHN H. STOUT PRESIDENT, MARINER CONSULTING SERVICES, INC. 1303 LAKEWAY DRIVE TAYLOR LAKE VILLAGE, TEXAS 77586 713-252-0535

JOHN H. STOUT PRESIDENT, MARINER CONSULTING SERVICES, INC. 1303 LAKEWAY DRIVE TAYLOR LAKE VILLAGE, TEXAS 77586 713-252-0535 JOHN H. STOUT PRESIDENT, MARINER CONSULTING SERVICES, INC. 1303 LAKEWAY DRIVE TAYLOR LAKE VILLAGE, TEXAS 77586 713-252-0535 JSTOUT@MARINERCONSULT.COM WWW.MARINERCONSULT.COM OVER 36 YEARS OF EXPERIENCE

More information

Robust Adaptive Topology Control

Robust Adaptive Topology Control Robust Adaptive Topology Control Mladen Kezunovic, PI Texas A&M University Kory W. Hedman, Co-PI Arizona State University January 14-15, 2015 System Integration Robust Adaptive Topology Control (RATC)

More information

Retail Electric Rates

Retail Electric Rates Retail Electric Rates in Deregulated and Regulated States: Update Published April 2016 2451 Crystal Dr. Arlington, VA 22202 202.467.2900 www.publicpower.org Retail Electric Rates in Deregulated and Regulated

More information

Data Management Issues associated with the August 14, 2003 Blackout Investigation

Data Management Issues associated with the August 14, 2003 Blackout Investigation Material derived from PNNL-SA-40401 Originally presented June 8, 2004 Data Management Issues associated with the August 14, 2003 Blackout Investigation Jeff Dagle, PE Chief Electrical Engineer and Team

More information

2012 Proposed Projects. Project Title Project Description. Business Intelligence Products

2012 Proposed Projects. Project Title Project Description. Business Intelligence Products Business Intelligence Products etariff Public Website Module This project will add the etariff Public Website module to www.nyiso.com. This is a small effort with new enhancements for the MPs. It allows

More information

CONSTELLATION ENERGY TERMS AND CONDITIONS

CONSTELLATION ENERGY TERMS AND CONDITIONS CONSTELLATION ENERGY TERMS AND CONDITIONS Purchase of Electric Generation Service. Constellation NewEnergy, Inc. ( Constellation ) agrees to sell, and you agree to buy, your full requirements for residential

More information

Stakeholders in a Business

Stakeholders in a Business Name: Class: Date Taken: Total Possible Marks: Stakeholders in a Business Complete the following questions in the time allowed by your teacher QUICK DEFINITIONS Write a short, accurate definition for each

More information

Technical and Institutional Barriers to the Expansion of Wind and Solar Energy

Technical and Institutional Barriers to the Expansion of Wind and Solar Energy Technical and Institutional Barriers to the Expansion of Wind and Solar Energy Near term measures to foster development Prepared for Peter Fiekowsky, Citizen s Climate Lobby June 19, 2015 AUTHORS Patrick

More information

Business Intelligence Project Prioritization System

Business Intelligence Project Prioritization System A three-page excerpt from our 11-page Best Practice Guidebook: Business Intelligence Project Prioritization System Best Practice Guidebook growth team membership 1 Business Intelligence Project Prioritization

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Southwest Power Pool, Inc. ) ) Docket No. ER12-1179-000 MOTION FOR LEAVE TO INTERVENE AND PROTEST OF THE ELECTRIC POWER SUPPLY ASSOCIATION

More information

Transmission Service Reference Manual. April 29, 2015

Transmission Service Reference Manual. April 29, 2015 Transmission Service Reference Manual April 29, 2015 Revision History Revision History Date or Version Number April 29, 2015 Version 1.0 Author Shari Brown Change Description Initial creation of draft

More information

ISO/RTO PERFORMANCE METRICS. Commission Staff Report AD10-5-000

ISO/RTO PERFORMANCE METRICS. Commission Staff Report AD10-5-000 ISO/RTO PERFORMANCE METRICS Commission Staff Report AD10-5-000 Federal Energy Regulatory Commission October 21, 2010 Table of Contents Section Page I. Background... 5 II. Notice of Filing and Responsive

More information

Benjamin A. Stafford. February 12, 2010

Benjamin A. Stafford. February 12, 2010 Comparison of Smart Grid Clearinghouse Information Requests to United States Department of Energy Guidebook for ARRA Smart Grid Program Metrics and Benefits dated December 7, 2009. February 12, 2010 Benjamin

More information

Wind Power and Electricity Markets

Wind Power and Electricity Markets PO Box 2787 Reston, VA 20195 Phone: 703-860-5160 Fax: 703-860-3089 E-mail: info@uwig.org Web: www.uwig.org Wind Power and Electricity Markets A living summary of markets and market rules for wind energy

More information

Draft Advanced Voltage Control Technology Roadmap

Draft Advanced Voltage Control Technology Roadmap Draft Advanced Voltage Control Technology Roadmap Robert Entriken, Senior Project Manager John Wharton, Executive Director Friday, 20 May 2011 Agenda Future Statements Current Status Functional Gaps Next

More information

The fact is that 90% of business strategies are not implemented through operations as intended. Overview

The fact is that 90% of business strategies are not implemented through operations as intended. Overview Overview It is important to recognize that a company s network determines its supply chain efficiency and customer satisfaction. Designing an optimal supply chain network means the network must be able

More information

Governance. What s a Governance?

Governance. What s a Governance? Governance What s a Governance? Governance FERC - Federal Energy Regulatory Commission NERC - North American Electric Reliability Council. NPCC - Northeast Power Coordinating Council NYSRC - New York State

More information

Program Guide for Risk-based Compliance Monitoring and Enforcement Program. ERA-01 Rev. 1. NPCC Manager, Entity Risk Assessment

Program Guide for Risk-based Compliance Monitoring and Enforcement Program. ERA-01 Rev. 1. NPCC Manager, Entity Risk Assessment NPCC Entity Risk Assessment Program Guide for Risk-based Compliance Monitoring and Enforcement Program ERA-01 Rev. 1 Process Owner: NPCC Manager, Entity Risk Assessment Effective Date: 03/02/2015 Table

More information

Southwest Power Pool SPP REGIONAL COMPLIANCE WORKING GROUP (RCWG) CONFERENCE CALL. August 7, 2015 MINUTES

Southwest Power Pool SPP REGIONAL COMPLIANCE WORKING GROUP (RCWG) CONFERENCE CALL. August 7, 2015 MINUTES Southwest Power Pool SPP REGIONAL COMPLIANCE WORKING GROUP (RCWG) CONFERENCE CALL Agenda Item 1 Administrative Items August 7, 2015 MINUTES Chair Jennifer Flandermeyer called the meeting to order at 2:00

More information

Transmission Related Station Power Use at Substations

Transmission Related Station Power Use at Substations Transmission Related Station Power Use at Substations BUSINESS PRACTICE This Business Practice identifies the cost responsibility for energy consumption at substations by American Transmission Company

More information

Winter 2013-14 Energy Market Assessment Report to the Commission

Winter 2013-14 Energy Market Assessment Report to the Commission Winter 2013-14 Energy Market Assessment Report to the Commission Docket No. AD06-3-000 October 2013 Disclaimer: The matters presented in this staff report do not necessarily represent the views of the

More information

BUSINESS RULES GOVERNING CONTINGENCY RESERVE PROVIDED BY BATCH-LOAD DEMAND RESPONSE

BUSINESS RULES GOVERNING CONTINGENCY RESERVE PROVIDED BY BATCH-LOAD DEMAND RESPONSE BUSINESS RULES GOVERNING CONTINGENCY RESERVE PROVIDED BY BATCH-LOAD DEMAND RESPONSE This paper describes the issues associated with using Batch-Load Demand Response i resources to provide Contingency Reserve

More information

SHARED SERVICES OR OUTSOURCING?

SHARED SERVICES OR OUTSOURCING? SHARED SERVICES OR OUTSOURCING? Assessing Scope, Process Maturity and Organizational Design Kevin Lewis, ISG Director; CPA, CGMA www.isg-one.com INTRODUCTION As organizations grow in size and complexity,

More information

Addendum Combined Heat and Power Revisions to the CPUC GHG Calculator Revised Report

Addendum Combined Heat and Power Revisions to the CPUC GHG Calculator Revised Report Addendum Combined Heat and Power Revisions to the CPUC GHG Calculator Revised Report Prepared for: California Public Utilities Commission 505 Van Ness Avenue San Francisco, CA 94102 Under R.06-04-009 October

More information

Updated November 20, 2015. Director, System Planning

Updated November 20, 2015. Director, System Planning Updated November 20, 2015 Job Descriptions Job Title Reports To Job Description SYSTEM PLANNING & SERVICES VP Compliance Manages the system planning and services staff. The director is responsible for

More information

Section 1: Executive Summary

Section 1: Executive Summary Section 1: Executive Summary SECTION 1: EXECUTIVE SUMMARY 1.1 SECTION PURPOSE This report has been prepared for the Nevada Energy Assistance Corporation (NEAC), a 501(c)(3) non-profit agency; in support

More information

From Vision to Implementation: Integrated Strategic Planning

From Vision to Implementation: Integrated Strategic Planning A three-page excerpt from our 18-page Best Practice Guidebook: From Vision to Implementation: Integrated Strategic Planning 1 Best Practice Guidebook From Vision to Implementation: Integrated Strategic

More information

Transmission Leadership. Teresa Mogensen Vice President, Transmission

Transmission Leadership. Teresa Mogensen Vice President, Transmission Transmission Leadership Teresa Mogensen Vice President, Transmission 1 Safe Harbor This material contains forward-looking statements that are subject to certain risks, uncertainties ies and assumptions.

More information

Demand Response and Energy Efficiency in the Midwest ISO. A Primer

Demand Response and Energy Efficiency in the Midwest ISO. A Primer Demand Response and Energy Efficiency in the Midwest ISO A Primer John Moore Bruce Campbell Kevin Murray September 28, 2010 1 Agenda Types of Midwest ISO Demand Response (DR). Products DR is eligible to

More information

Price to Compare (PTC) Sample Calculation DISCLAIMER

Price to Compare (PTC) Sample Calculation DISCLAIMER Price to Compare (PTC) Sample Calculation DISCLAIMER Disclaimer This document does not include factors/adders such as surcharges and sales taxes applicable to PECO distribution service. The PTC contained

More information

Enterprise Calendar Request. Pennsylvania Interactive

Enterprise Calendar Request. Pennsylvania Interactive Enterprise Calendar Request Pennsylvania Interactive November 21, 2014 1 Version History The version numbering is as follows: The initial version is.01. Once the deliverable has been accepted, it becomes

More information

Job Descriptions. Job Title Reports To Job Description TRANSMISSION SERVICES Manager, Transmission Services. VP Compliance & Standards

Job Descriptions. Job Title Reports To Job Description TRANSMISSION SERVICES Manager, Transmission Services. VP Compliance & Standards Updated July 11, 2013 Job Descriptions Job Title Reports To Job Description TRANSMISSION SERVICES VP Compliance & Standards Develops strategy and business plans for efficient, safe, reliable, regulatorycompliant

More information

Generation Interconnection Feasibility Study Report-Web Version. PJM Generation Interconnection Request Queue Position Z1-055

Generation Interconnection Feasibility Study Report-Web Version. PJM Generation Interconnection Request Queue Position Z1-055 Generation Interconnection Feasibility Study Report-Web Version For PJM Generation Interconnection Request Queue Position Z1-055 South Bend Generation Project March 2014 PJM Interconnection 2014. All rights

More information

AN ACT IN THE COUNCIL OF THE DISTRICT OF COLUMBIA

AN ACT IN THE COUNCIL OF THE DISTRICT OF COLUMBIA AN ACT IN THE COUNCIL OF THE DISTRICT OF COLUMBIA To amend the Retail Electric Competition and Consumer Protection Act of 1999 to update the net metering provisions to ensure consistency across programs,

More information

Application and Network Performance Monitoring in a Virtualized Environment

Application and Network Performance Monitoring in a Virtualized Environment Application and Performance Monitoring in a Virtualized Environment As organizations implement virtualized environments, knowing how to monitor and maintain them becomes yet another challenge for today

More information

Resource Monitoring and Deliverability Tool Paper

Resource Monitoring and Deliverability Tool Paper Resource Monitoring and Deliverability Tool Paper NWPP MC Phase 3 Operations Integration Work Group 11/30/2014 Page 1 of 16 Table of Contents Executive Summary... 3 1. Purpose... 5 2. Existent Methods

More information

TRANSMISSION SERVICE TARIFF OF CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC FOR TRANSMISSION SERVICE TO FROM AND OVER CERTAIN INTERCONNECTIONS

TRANSMISSION SERVICE TARIFF OF CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC FOR TRANSMISSION SERVICE TO FROM AND OVER CERTAIN INTERCONNECTIONS TRANSMISSION SERVICE TARIFF OF CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC FOR TRANSMISSION SERVICE TO FROM AND OVER CERTAIN INTERCONNECTIONS FERC ELECTRIC TARIFF, SIXTH REVISED VOLUME NO. 1 TABLE OF CONTENTS

More information

ATTACHMENT RJL-2 MASTER STANDARD SERVICE OFFER ( SSO ) SUPPLY AGREEMENT BETWEEN THE DAYTON POWER AND LIGHT COMPANY AND

ATTACHMENT RJL-2 MASTER STANDARD SERVICE OFFER ( SSO ) SUPPLY AGREEMENT BETWEEN THE DAYTON POWER AND LIGHT COMPANY AND MASTER STANDARD SERVICE OFFER ( SSO ) SUPPLY AGREEMENT BETWEEN THE DAYTON POWER AND LIGHT COMPANY AND THE SSO SUPPLIER SET FORTH IN APPENDIX A HERETO TABLE OF CONTENTS ARTICLE 1: DEFINITIONS... 3 ARTICLE

More information

Comprehensive Economic Development Planning and Implementation for Somerset County, NJ. Somerset County Planning Board August 17, 2010

Comprehensive Economic Development Planning and Implementation for Somerset County, NJ. Somerset County Planning Board August 17, 2010 Comprehensive Economic Development Planning and Implementation for Somerset County Planning Board Comprehensive Economic Development FINDINGS Land Use Ordinances, Zoning Ordinances, and Master Plans are

More information

Consumer Cost Effectiveness of CO 2 Mitigation Policies in Restructured Electricity Markets. Jared Moore and Jay Apt.

Consumer Cost Effectiveness of CO 2 Mitigation Policies in Restructured Electricity Markets. Jared Moore and Jay Apt. Consumer Cost Effectiveness of CO 2 Mitigation Policies in Restructured Electricity Markets Jared Moore and Jay Apt Supporting Data Consumer Cost Effectiveness of CO 2 Mitigation Policies in Restructured

More information

Public Utilities and Their Reliability in Florida - History

Public Utilities and Their Reliability in Florida - History UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Remedying Undue Discrimination Through Open Access Transmission Service And Standard Electricity Market Design GridFlorida, LLC Docket No.

More information

Evaluability Assessment Template

Evaluability Assessment Template Evaluability Assessment Template Evaluability Assessment Template An Evaluability Assessment examines the extent to which a project or a programme can be evaluated in a reliable and credible fashion. An

More information

Workshop B. 11:15 a.m. to 12:30 p.m.

Workshop B. 11:15 a.m. to 12:30 p.m. Workshop B Advanced Energy Management Tools: Benefitting from the Competitive Electricity Marketplace Beyond the Fixed Rate & Key Issues to Understand when Comparing Electricity Quotes 11:15 a.m. to 12:30

More information