Fremantle Port Inner Harbour and Channel Deepening - Reclamation at Rous Head and Offshore Placement of Dredged Material. Compliance Assessment Plan

Size: px
Start display at page:

Download "Fremantle Port Inner Harbour and Channel Deepening - Reclamation at Rous Head and Offshore Placement of Dredged Material. Compliance Assessment Plan"

Transcription

1 Fremantle Port Inner Harbour and Channel Deepening - Reclamation at Rous Head and Offshore Placement of Dredged Material Compliance Assessment Plan

2

3 P:\FremantlePorts\816_InnerHarbourDredgeMonitoring\003_CAPandCAR\Reports\Compliance Assessment Plan\Compliance Assessment Plan.docx Fremantle Ports Inner Harbour and Channel Deepening, Reclamation at Rous Head and Offshore Placement of Dredged Material Compliance Assessment Plan Prepared for Fremantle Ports Prepared by Oceanica Consulting Pty Ltd February 2010 Report No. 816_003/1

4 Client: Fremantle Ports Revisions history DISTRIBUTION REVIEW Version Author No. Copies & Recipients Format Date Reviewer Date A S. Scott R. DeRoach 1 x electronic 28/01/10 R. DeRoach 28/01/10 B S. Scott L. Banks M. Bailey 1 x electronic 29/01/10 L. Banks M. Bailey 8/02/10 29/01/10 C S. Scott R. DeRoach 1 x electronic 11/02/10 R. DeRoach 12/02/10 D S. Scott L. Banks 1 x electronic 12/02/10 L. Banks 15/02/10 Rev0 S. Scott OEPA L. Banks L. Stuart G. Valenti R. DeRoach M. Bailey 1 x electronic 15/02/10 OEPA 17/1/10 Rev1 Rev2 Rev3 S. Scott S. Scott S. Scott L. Banks L. Stuart G. Valenti R. DeRoach M. Bailey OEPA L. Banks L. Stuart G. Valenti R. DeRoach M. Bailey OEPA Fremantle Ports Oceanica 1 x electronic 17/02/10 L. Banks L. Stuart 17/02/10 19/02/10 1 x electronic 19/02/10 OEPA 19/02/10 1 x hard copy, 1 x electronic 3 x hard copy, 1 x electronic 2 x hard copy 24/02/10 Status This report is Draft until the author and director have signed it off for final release. A Draft report should not be used for any purpose other than to be reviewed with the intention of generating a Final version. Approved for final release: Author Director Disclaimer This report has been prepared on behalf of and for the exclusive use of Fremantle Ports, and is subject to and issued in accordance with the agreed terms and scope between Fremantle Ports and Oceanica Consulting Pty Ltd. Oceanica Consulting Pty Ltd accepts no liability or responsibility whatsoever for it in respect of any use of or reliance upon this report by any third party. Copying this report without the permission of Fremantle Ports or Oceanica Consulting Pty Ltd is not permitted. Cover Main image: View of Fremantle Port from the Swan River (Marianne Nyegaard); Minor images: Light logger deployed above seagrass, Cockburn Sound (Oceanica Consulting); Posidonia sinuosa with epiphytes, offshore of Rous Head (Oceanica Consulting). The Oceanica logo is a registered trade mark of Oceanica Consulting Pty Ltd which is protected by law. You may not use this trade mark without first obtaining the permission of Oceanica Consulting Pty Ltd. Copyright 2010 Oceanica Consulting Pty Ltd

5

6 Contents 1. Introduction Background Purpose and Scope Assessment and Reporting Audit table Frequency of compliance reporting Approach and timing of compliance assessments Retention of compliance assessments Reporting non-compliances and corrective measures Table of contents Public availability of reports References Oceanica: Fremantle Ports: Compliance Assessment Plan i

7 List of Tables Table 1.1 Key elements of the Project... 1 Table 2.1 Audit table... 5 Table 2.2 Approach and timing of compliance assessments... 9 List of Figures Figure 1.1 Proposed development areas and ecological protection areas Appendix A Ministerial Statement 801 List of Appendices ii Oceanica: Fremantle Ports: Compliance Assessment Plan

8 1. Introduction 1.1. Background The Fremantle Ports Inner Harbour and Channel Deepening Project (the Project ) involves the dredging of approximately 3.1 million m3 of consolidated and unconsolidated material and its disposal at an offshore spoil disposal area (Gage Roads) or its reuse in land reclamation at Rous Head. Dredging will be undertaken to deepen the Deep Water Channel and Inner Harbour Channel (Figure 1.1) to allow 14 m draft ships to utilise the Fremantle Inner Harbour. An area of seabed at Rous Head will also be reclaimed using dredged material. A combination of a Trailing Suction Hopper Dredge (TSHD) and a Cutter Suction Dredge (CSD) will be used. The key elements of the Project are provided in Table 1.1. A detailed description of the Proposal is provided in Section 2 of the Public Environmental Review document (SKM, 2008). For a description of water, mussel and sediment quality monitoring, please refer to the Water Quality Monitoring Program (WQMP, Oceanica, 2009). Table 1.1 Key elements of the Project Component Description Construction of a seawall around the reclamation area 20 weeks (prior to the dredging programme). This component of the works will be managed under the CEMP and therefore is only made reference to in the DSDMP and is not considered further. Duration of Dredging 26 weeks. Deepening of Fremantle Port Inner Harbour Dredging to a declared depth of RL m Low Water Mark Fremantle (LWMF); Removal of approximately 0.9 million m3 of dredged material. Deepening of the Entrance Channel Dredging to declared depths between RL m and RL m (LWMF); Removal of approximately 1.1 million m3 of dredged material. Deepening of Deep Water Channel Dredging to declared depths between RL m and RL m (LWMF) within an area up to 169 ha; Removal of approximately 1.1 million m3 of dredge material. Rous Head Reclamation Area Placement of approximately 1.6 million m3 dredged material for reclamation of an area of 27 ha of seabed (Stage 3); Construction of a protective seawall 1000 m long. Proposed Offshore Spoil Disposal area Placement of approximately 1.5 million m3 of dredged material within an area of approximately 150 ha (1.5 km2) located north of Gage Roads. Oceanica: Fremantle Ports: Compliance Assessment Plan 1

9 Figure 1.1 Proposed development areas and ecological protection areas. 2 Oceanica: Fremantle Ports: Compliance Assessment Plan

10 1.2. Purpose and Scope This compliance assessment plan is submitted in order to fulfil Ministerial Conditions 4.1 and 4.2 of Ministerial Statement 801 (Appendix A) as outlined below. Ministerial Condition 4.1 The proponent shall prepare and maintain a Compliance Assessment Plan to the satisfaction of the CEO. Ministerial Condition 4.2 The proponent shall submit to the CEO, the Compliance Assessment Plan required by Condition 4-1 within 6 months of the date of this Statement. The Compliance Assessment Plan shall indicate: 1. the frequency of compliance reporting 2. the approach and timing of compliance assessments 3. the retention of compliance assessments 4. reporting of non-conformances and corrective actions taken 5. the table of contents of compliance reports; and 6. public availability of compliance reports Oceanica: Fremantle Ports: Compliance Assessment Plan 3

11 2. Assessment and Reporting 2.1. Audit table An audit table has been prepared for Ministerial Statement 801. The audit table was partially populated by DEC with Fremantle Ports completing the table and preparing the audit program, in accordance with DEC Guidelines (DEC 2009a; DEC 2009b). The audit table contains each condition, procedure or commitment separated into audit elements for auditing purposes, and includes the following attributes: Audit code: Ministerial statement reference number Subject: The environmental subject/issue Action: What the proponent must do How: The way it must be done/performance Criteria Evidence: Information or data collected to verify compliance, i.e. report/letter/site inspection requirements Satisfy: Who will give approval Advice: Agencies whose advice must be considered as stipulated in the ministerial statement Phase: Project phase When: Specific timing and/or location Status: Notes about the fulfilment of compliance. Note that the table is only a summary of conditions in Statement 801 and that the Statement should be referred to directly for matters requiring additional clarification or information on procedural matters. 4 Oceanica: Fremantle Ports: Compliance Assessment Plan

12 Table 2.1 Audit Code 801:M :M :M2.2 Audit table Subject Action How Evidence Satisfy Advice Phase When Status Proposal Implementation Proponent Nomination and Contact Details Proponent Nomination and Contact Details The proponent shall implement the proposal as documented and described in schedule 1 of this statement subject to the conditions and procedures of this statement The proponent for the time being nominated by the Minister for Environment under sections 38(6) or 38(7) of the Environmental Protection Act 1986 is responsible for the implementation of the proposal The proponent shall notify the Chief Executive Officer of the Department of Environment and Conservation (CEO) of any change of the name and address of the proponent for the serving of notices or other correspondence within 30 days of such change. Project implemented as described in Statement Proponent nominated to implement the proposal Written advice Annual Compliance Assessment Report Proponent details as listed on Ministerial Statement 801 Letter to CEO notifying of change of contact name and address Min for Env Min for Env Overall For the life of the Proposal Overall For the life of the Proposal CEO Overall Within 30 days of such change. 801:M3.1 Time Limit of Authorisation The authorisation to implement the proposal provided for in this statement shall lapse and be void five years after the date of this statement if the proposal to which this statement relates is not substantially commenced Written advice Compliance Assessment Reports, written notification Min for Env Overall Commenced by 18 th August :M3.2 Time Limit of Authorisation 801:M :M :M :M :M :M4.6 Compliance Reporting Compliance Reporting Compliance Reporting Compliance Reporting Compliance Reporting Compliance Reporting The proponent shall provide the CEO with written evidence which demonstrates that the proposal has substantially commenced on or before the expiration of five years from the date of this statement The Proponent shall prepare and maintain a Compliance Assessment Plan to the satisfaction of the CEO The Proponent shall submit to the CEO, the Compliance Assessment Plan required by Condition 4.1 within 6 months of the date of this Statement The Proponent shall assess compliance with conditions in accordance with the Compliance Assessment Plan required by Condition 4.1 The Proponent shall retain reports of all compliance assessments described in the Compliance Assessment Plan required by Condition 4.1 and shall make those reports available when requested by the CEO The Proponent shall advise the CEO of any noncompliance as soon as practicable The Proponent shall submit to the CEO a Compliance Assessment Report annually from the date of issue of this Statement addressing the previous twelve month period or other period as agreed by the CEO. The date of the first Compliance Assessment Report shall be 15 months from the date of this Statement, with each subsequent report 12 months from the date of the previous Report Written advice Letter to CEO of OEPA outlining substantial commencement DEC Overall Within one month of commencement Prepare Compliance Assessment Plan Compliance Assessment Plan CEO For the life of the Proposal The Compliance Assessment Plan shall indicate: 1. the frequency of compliance reporting; 2. the approach and timing of compliance assessments; 3. the retention of compliance assessments; 4. reporting of non-compliances and corrective actions taken; 5. the table of contents of Compliance Assessment Reports; and 6. public availability of compliance reports. Follow Compliance Assessment Plan when assessing compliance Compliance Assessment Reports will be placed on Fremantle Ports website A letter describing the non-compliance will be sent to the CEO of OEPA The Compliance Assessment Report shall: 1. be endorsed by the Proponent s Chief Executive Officer or a person, approved in writing by the Department of Environment and Conservation, delegated to sign on the Chief Executive Officer s behalf; 2. include a statement as to whether the Proponent has complied with the conditions; 3. identify all non-compliances and describe corrective and preventative actions taken; 4. be made publicly available in accordance with the approved Compliance Assessment Plan; and 5. Compliance Assessment Plan CEO Design Compliance Assessment Reports CEO Overall Annually Reports on website Letter to CEO of OEPA Annual Compliance Assessment Reports CEO CEO CEO Within 6 months of the date of this Statement. That is by 18 February 2010 Overall When requested of the CEO Overall Overall Within 72 hours of a non-compliance being identified (subsequent to processing of data) Annually with the first report due 15 months from the date of issue of this Statement. That is on 18 November Oceanica: Fremantle Ports: Compliance Assessment Plan 5

13 Audit Code 801:M :M :M :M :M :M :M6.1 Subject Action How Evidence Satisfy Advice Phase When Status Marine Ecology Benthic Primary Producer Habitat Marine Ecology Benthic Primary Producer Habitat Marine Ecology Benthic Primary Producer Habitat Marine Ecology Benthic Primary Producer Habitat Marine Ecology Benthic Primary Producer Habitat Marine Ecology Benthic Primary Producer Habitat Marine Water Quality and Sediment Quality Prior to dredging activities the proponent shall prepare maps showing the: 1. Gage Roads Benthic Primary Producer Habitat Management Unit; 2. location and extent of the benthic primary producer habitat types; 3. boundaries of the direct disturbance area and predicted levels of impact, including coordinates; 4. boundaries of the indirect disturbance area and predicted levels of indirect impact, including coordinates; 5. the spatially defined offshore spoil disposal ground, including coordinates; and 6. boundary of the Rous Head reclamation area, including coordinates The proponent shall ensure that there are no direct or indirect losses of coral or macroalgal Benthic Primary Producer Habitat within the Gage Roads management unit (referred to in condition 5-1) caused by this dredging campaign and that losses of seagrass BPPH within this management unit caused by the dredging campaign do not exceed 50 hectares The proponent shall monitor and record the loss of Benthic Primary Producer Habitat (seagrass, macroalgae, coral) within the Gage Roads management unit referred to in condition 5-1 for the duration of the dredging campaign and for six months following the dredging campaign if impacts are within predicted levels, or for up to 5 years if impacts exceed predictions, to the requirements of the Department of Environment and Conservation Two months following the conclusion of monitoring of each program referred to in condition 5-3 the proponent is to report to the CEO of the Department of Environment and Conservation the total cumulative loss of each Benthic Primary Producer Habitat type (seagrass, macroalgae, and coral) in the Gage Roads management unit referred to in condition 5-1. The report is to include a map showing area and losses of benthic primary producer habitat type The proponent shall annually survey the footprint (as per coordinates) of the offshore spoil ground for two years after completion of the disposal activities and after any severe storm event within the two year period exceeding a one in five year ARI for the purposes of demonstrating that the dredging spoil has remained within the footprint of the approved dredge spoil disposal ground The future use of the offshore disposal site for disposal outside the approved coordinates is not permitted under this assessment and therefore requires an additional consideration under the EP Act To achieve the Environmental Quality Objectives (EQOs) established for the marine environment by the Environmental Protection Authority in Perth Coastal Waters Environmental Values and Objectives, specifically for the high Ecological Protection Area adjacent to the reclamation return water discharge zone, the proponent shall prepare and implement a Water Quality Monitoring Program as a component of the Dredge Spoil Disposal Management Plan (DSDMP) to the satisfaction of the CEO of the Department of Environment and Conservation indicate any proposed changes to the Compliance Assessment Plan required by Condition 4.1 Prepare maps listed under Action column Measurement of baseline coral, macroalgal and seagrass BPPH extent (801: M5.1) and comparative post-dredging BPPH survey to ensure that there are no losses of coral or macroalgal BPPH and no more than 50 ha of seagrass BPPH Measurement of baseline coral, macroalgal and seagrass BPPH extent (801: M5.1) and comparative post-dredging BPPH survey/s to ensure that there are no losses of coral or macroalgal BPPH and no more than 50 ha of seagrass BPPH Calculate cumulative habitat losses based on monitoring results. Prepare a report with these losses as well as a map showing area and losses of BPPH. Annually survey footprint of offshore disposal ground for two years after completion of disposal. Survey after any severe storm event exceeding a one in five year annual recurrence interval within the two year period. No offshore disposal will occur to the site described in MS801 other than that approved under this assessment. Implement the Water Quality Monitoring Program. Maps to be provided to OEPA within the first Compliance Assessment Report. Compliance Assessment Report including habitat loss calculations Compliance Assessment Report including habitat loss calculations; Monitoring results provided to the CEO of OEPA as outlined in M5.4 Compliance Assessment Report including a map and cumulative habitat loss calculations for each BPPH type; Report provided to the CEO of OEPA Provide survey details to OEPA within annual compliance report Records of volume dumped will be provided to the DEC in the annual reports Results of the Water Quality Monitoring Program will be provided in annual Compliance Assessment Reports. Fortnightly WQMP data reports to be submitted to the OEPA. Min for Env Min for Env Design Overall CEO Overall CEO Overall Min for Env Min for Env Overall CEO Overall Overall Annually Maps prepared prior to dredging activities, to be provided together with comparative maps from BPPH monitoring surveys referred to in 801:M5.2, 801:M5.3 and 801:M5.4. Maps to be provided within the first Compliance Assessment Report. Two months following the completion of the proposal Throughout the dredging campaign and for six months following the dredging campaign if impacts are within predicted levels, or for up to 5 years if impacts exceed predictions Two months following the conclusion of monitoring of each program referred to in condition 5-3 Annually for two years after completion of the disposal activities and after any severe storm event within the two year period exceeding a one in five year ARI Compliance assessment reports to be submitted annually through the dredging campaign. Fortnightly WQMP data reports to be submitted to the OEPA 6 Oceanica: Fremantle Ports: Compliance Assessment Plan

14 Audit Code 801:M :M :M6.4 Subject Action How Evidence Satisfy Advice Phase When Status Marine Water Quality and Sediment Quality Marine Water Quality and Sediment Quality Marine Water Quality and Sediment Quality Prior to dredging activities causing sediment dispersion into the marine environment the proponent shall prepare a map defining the levels of Ecological Protection that will apply for the duration of the dredging campaign including: 1. The boundary of the Rous Head reclamation area and adjacent seabed where the level of ecological protection is reduced to moderate for the duration of the project implementation 2. The boundary of the Rous Head reclamation area and adjacent seabed where a high level of ecological protection will be met after completion of the dredging campaign 3. Identify environmental quality indicators and associated trigger levels, based on the guidelines and recommended approaches in the Australian and New Zealand Guideline for Fresh and Marine Water Quality (ANZECC & ARMCANZ, 2000) and the Environmental Quality Criteria Reference Document for Cockburn Sound ( ) (EPA, 2005), for assessing the performance of the discharges in meeting the EQOs for the moderate ecological protection areas and at the boundary of the high Ecological Protection Area, both during and after completion of the dredging campaign 4. Design and employ protocols and schedules for reporting performance against the EQOs using the environmental quality trigger levels for discharges 5. Specify appropriate management and mitigation measures to be applied if monitoring demonstrates that the environmental quality trigger levels are exceeded at any point during the dredging and reclamation program, or if they are exceeded for a high level of ecological protection adjacent to Rous Head after completion of the dredging campaign If the Water Quality Monitoring Program required in condition 6-1 demonstrates that the environmental quality trigger levels (as determined in condition 6.2) are not met, the proponent shall immediately report to the CEO of the Department of Environment and Conservation with the remedial management and/or preventative actions to be implemented Monitoring shall be conducted for the duration of the dredging and disposal program and for six months following completion of the program, or until it has been demonstrated that the High Ecological Protection values have re-established adjacent to Rous Head. The results of monitoring shall be reported to the CEO of the Department of Environment and Conservation Prepare Water Quality Monitoring Program (WQMP) to include: map defining levels of ecological protection as described in action column; environmental quality indicators and associated trigger levels; protocols and schedules for reporting performance against the EQOs; and management and mitigation measures Provide report to the CEO of the OEPA with the remedial management and/or preventative actions to be implemented following the exceedance of trigger levels The Compliance Assessment Report shall include the initial predictions of the proponent as described in the Public Environmental Review and proponent s response to submissions, and an analysis of how, and to what extent the results of monitoring varied from the predictions WQMP Min for Env Design Report to the CEO of the OEPA CEO Overall Compliance Assessment Report submitted to the CEO of the OEPA. CEO Overall Submit WQMP prior to dredging activities causing sediment dispersion into the marine environment Within 72 hours of an exceedance of environmental quality trigger levels (subsequent to processing of data). Within two months of completion of the monitoring and analysis Oceanica: Fremantle Ports: Compliance Assessment Plan 7

15 2.2. Frequency of compliance reporting The first compliance report shall be submitted 15 months from the date of Ministerial Statement 801, that is 18 November Each subsequent report shall be submitted 12 months from the date of the previous report Approach and timing of compliance assessments Fremantle Ports shall on an annual basis assess compliance with all conditions of Ministerial Statement 801 as outlined in the Audit Table provided as Table 2.1. The approach shall include an assessment of compliance with all commitments outlined in the Water Quality Monitoring Program approved by the Office of the Environment Protection Authority. The approach and timing to compliance assessments is outlined in Table 2.2. Table 2.2 Approach and timing of compliance assessments Audit Code (refer to audit table) Assessment Timing M4.6 Compliance Assessment Report Annually with the first due 18 November 2010 M6.1 Water Quality Monitoring Programme data reports Fortnightly 2.4. Retention of compliance assessments Fremantle Ports will retain all compliance assessment reports for the life of the project and make them publically available when requested by the CEO of DEC Reporting non-compliances and corrective measures Fremantle Ports will provide notification to the Proposal Implementation and Monitoring Section (PIMS) of the Office of the Environment Protection Authority via an to the PIMS mailbox within 72 hours of a non-compliance being identified. A report including any corrective actions identified will be provided to the PIMS via both (pims@epa.wa.gov.au) and in hard copy, once an investigation into the non-compliance is completed. The Compliance Assessment Report for Ministerial Statement 801 will include where required, reference to the submission of any investigation reports provided to PIMS as detailed above Table of contents The table of contents to be included in each annual compliance report would include at a minimum the following; Introduction Purpose Project status Marine ecology Benthic primary producer habitat Marine water quality and sediment quality Compliance summary 2.7. Public availability of reports Fremantle Ports will make the annual compliance reports publically available under their website for the life of the project. Oceanica: Fremantle Ports: Compliance Assessment Plan 9

16 3. References DEC, 2009a. Compliance Monitoring and Reporting Guidelines for Proponents, Preparing an Audit Table, Department of Environment and Conservation, Government of Western Australia, May DEC, 2009b. Compliance Monitoring and Reporting Guidelines for Proponents - Preparing a Compliance Assessment Plan, Department of Environment and Conservation, Government of Western Australia. Oceanica, 2010, Fremantle Port Inner Harbour and Channel Deepening Reclamation at Rous Head and Offshore Placement of Dredged Material: Water Quality Monitoring Program, Prepared for Fremantle Ports by Oceanica Consulting Pty Ltd, Report no. 816_006/1, Perth, Western Australia, January Sinclair Knight and Merz (SKM), Fremantle Port Inner Harbour and Channel Deepening, Reclamation and Rous Head and Offshore Placement of Dredged Material Public Environmental Review Document, Prepared for Fremantle Ports by SKM, Perth, Western Australia, Oceanica: Fremantle Ports: Compliance Assessment Plan

17 Appendix A Ministerial Statement 801

18 STATUS OF THIS DOCUMENT This document has been produced by the Office of the Appeals Convenor as an electronic version of the original Statement for the proposal listed below as signed by the Minister and held by this Office. Whilst every effort is made to ensure its accuracy, no warranty is given as to the accuracy or completeness of this document. The State of Western Australia and its agents and employees disclaim liability, whether in negligence or otherwise, for any loss or damage resulting from reliance on the accuracy or completeness of this document. Copyright in this document is reserved to the Crown in right of the State of Western Australia. Reproduction except in accordance with copyright law is prohibited. Published on 18 August 2009 Statement No 801 STATEMENT THAT A PROPOSAL MAY BE IMPLEMENTED (PURSUANT TO THE PROVISIONS OF THE ENVIRONMENTAL PROTECTION ACT 1986) FREMANTLE PORTS INNER HARBOUR AND CHANNEL DEEPENING, RECLAMATION AT ROUS HEAD AND OFFSHORE PLACEMENT OF DREDGED MATERIAL Proposal: The proposal is to deepen the Fremantle Inner Harbour, Entrance Channel and the Deep Water Channel by dredging approximately 3.1 million cubic metres to provide for further reclamation at Rous Head of approximately 27 hectares and for offshore disposal. The proposal is further documented in schedule 1 of this statement. Proponent: Fremantle Ports Proponent Address: 1 Cliff Street, Fremantle, WA 6160 Assessment Number: 1621 Report of the Environmental Protection Authority: Report 1330 The proposal referred to in the above report of the Environmental Protection Authority may be implemented. The implementation of that proposal is subject to the following conditions and procedures: 1 Proposal Implementation 1-1 The proponent shall implement the proposal as documented and described in schedule 1 of this statement subject to the conditions and procedures of this statement. Published on:

19 2 Proponent Nomination and Contact Details 2-1 The proponent for the time being nominated by the Minister for Environment under sections 38(6) or 38(7) of the Environmental Protection Act 1986 is responsible for the implementation of the proposal. 2-2 The proponent shall notify the Chief Executive Officer of the Department of Environment and Conservation (CEO) of any change of the name and address of the proponent for the serving of notices or other correspondence within 30 days of such change. 3 Time Limit of Authorisation 3-1 The authorisation to implement the proposal provided for in this statement shall lapse and be void five years after the date of this statement if the proposal to which this statement relates is not substantially commenced. 3-2 The proponent shall provide the CEO with written evidence which demonstrates that the proposal has substantially commenced on or before the expiration of five years from the date of this statement. 4 Compliance Reporting 4.1 The Proponent shall prepare and maintain a Compliance Assessment Plan to the satisfaction of the CEO. 4.2 The Proponent shall submit to the CEO, the Compliance Assessment Plan required by Condition 4.1 within 6 months of the date of this Statement. The Compliance Assessment Plan shall indicate: 1. the frequency of compliance reporting; 2. the approach and timing of compliance assessments; 3. the retention of compliance assessments; 4. reporting of non-compliances and corrective actions taken; 5. the table of contents of Compliance Assessment Reports; and 6. public availability of compliance reports. 4.3 The Proponent shall assess compliance with conditions in accordance with the Compliance Assessment Plan required by Condition The Proponent shall retain reports of all compliance assessments described in the Compliance Assessment Plan required by Condition 4.1 and shall make those reports available when requested by the CEO. 4.5 The Proponent shall advise the CEO of any non-compliance as soon as practicable. 4.6 The Proponent shall submit to the CEO a Compliance Assessment Report annually from the date of issue of this Statement addressing the previous twelve month period or other period as agreed by the CEO. The date of the first Compliance Assessment 2

20 Report shall be 15 months from the date of this Statement, with each subsequent report 12 months from the date of the previous Report. The Compliance Assessment Report shall: 1. be endorsed by the Proponent s Chief Executive Officer or a person, approved in writing by the Department of Environment and Conservation, delegated to sign on the Chief Executive Officer s behalf; 2. include a statement as to whether the Proponent has complied with the conditions; 3. identify all non-compliances and describe corrective and preventative actions taken; 4. be made publicly available in accordance with the approved Compliance Assessment Plan; and 5. indicate any proposed changes to the Compliance Assessment Plan required by Condition Marine Ecology Benthic Primary Producer Habitat 5-1 Prior to dredging activities the proponent shall prepare maps showing the: 1. Gage Roads Benthic Primary Producer Habitat Management Unit; 2. location and extent of the benthic primary producer habitat types; 3. boundaries of the direct disturbance area and predicted levels of impact, including coordinates; 4. boundaries of the indirect disturbance area and predicted levels of indirect impact, including coordinates; 5. the spatially defined offshore spoil disposal ground, including coordinates; and 6. boundary of the Rous Head reclamation area, including coordinates. 5-2 The proponent shall ensure that there are no direct or indirect losses of coral or macroalgal Benthic Primary Producer Habitat within the Gage Roads management unit (referred to in condition 5-1) caused by this dredging campaign and that losses of seagrass BPPH within this management unit caused by the dredging campaign do not exceed 50 hectares. 5-3 The proponent shall monitor and record the loss of Benthic Primary Producer Habitat (seagrass, macroalgae, coral) within the Gage Roads management unit referred to in condition 5-1 for the duration of the dredging campaign and for six months following the dredging campaign if impacts are within predicted levels, or for up to 5 years if impacts exceed predictions, to the requirements of the Department of Environment and Conservation. 5-4 Two months following the conclusion of monitoring of each program referred to in condition 5-3 the proponent is to report to the CEO of the Department of Environment and Conservation the total cumulative loss of each Benthic Primary Producer Habitat type (seagrass, macroalgae, and coral) in the Gage Roads 3

21 management unit referred to in condition 5-1. The report is to include a map showing area and losses of benthic primary producer habitat type. 5-5 The proponent shall annually survey the footprint (as per coordinates) of the offshore spoil ground for two years after completion of the disposal activities and after any severe storm event within the two year period exceeding a one in five year ARI for the purposes of demonstrating that the dredging spoil has remained within the footprint of the approved dredge spoil disposal ground. 5-6 The future use of the offshore disposal site for disposal outside the approved coordinates is not permitted under this assessment and therefore requires an additional consideration under the EP Act. 6 Marine Water Quality and Sediment Quality 6-1 To achieve the Environmental Quality Objectives (EQOs) established for the marine environment by the Environmental Protection Authority in Perth Coastal Waters Environmental Values and Objectives, specifically for the high Ecological Protection Area adjacent to the reclamation return water discharge zone, the proponent shall prepare and implement a Water Quality Monitoring Program as a component of the Dredge Spoil Disposal Management Plan (DSDMP) to the satisfaction of the CEO of the Department of Environment and Conservation. 6-2 Prior to dredging activities causing sediment dispersion into the marine environment the proponent shall prepare a map defining the levels of Ecological Protection that will apply for the duration of the dredging campaign including: 1. The boundary of the Rous Head reclamation area and adjacent seabed where the level of ecological protection is reduced to moderate for the duration of the project implementation. 2. The boundary of the Rous Head reclamation area and adjacent seabed where a high level of ecological protection will be met after completion of the dredging campaign. 3. Identify environmental quality indicators and associated trigger levels, based on the guidelines and recommended approaches in the Australian and New Zealand Guideline for Fresh and Marine Water Quality (ANZECC & ARMCANZ, 2000) and the Environmental Quality Criteria Reference Document for Cockburn Sound ( ) (EPA, 2005), for assessing the performance of the discharges in meeting the EQOs for the moderate ecological protection areas and at the boundary of the high Ecological Protection Area, both during and after completion of the dredging campaign. 4. Design and employ protocols and schedules for reporting performance against the EQOs using the environmental quality trigger levels for discharges. 5. Specify appropriate management and mitigation measures to be applied if monitoring demonstrates that the environmental quality trigger levels are exceeded at any point during the dredging and reclamation program, or if they are exceeded for a high level of ecological protection adjacent to Rous Head after completion of the dredging campaign. 4

22 6-3 If the Water Quality Monitoring Program required in condition 6-1 demonstrates that the environmental quality trigger levels (as determined in condition 6.2) are not met, the proponent shall immediately report to the CEO of the Department of Environment and Conservation with the remedial management and/or preventative actions to be implemented. 6-4 Monitoring shall be conducted for the duration of the dredging and disposal program and for six months following completion of the program, or until it has been demonstrated that the High Ecological Protection values have re-established adjacent to Rous Head. The results of monitoring shall be reported to the CEO of the Department of Environment and Conservation. The report shall include the initial predictions of the proponent as described in the Public Environmental Review and proponent s response to submissions, and an analysis of how, and to what extent the results of monitoring varied from the predictions. Notes 1. Where a condition states on advice of the Environmental Protection Authority, the Environmental Protection Authority will provide that advice to the Department of Environment and Conservation for the preparation of written notice to the proponent. 2. The Environmental Protection Authority may seek advice from other agencies or organisations, as required, in order to provide its advice to the Department of Environment and Conservation. 3. The Minister for Environment will determine any dispute between the proponent and the Environmental Protection Authority or the Department of Environment and Conservation over the fulfilment of the requirements of the conditions. Donna Faragher JP MLC MINISTER FOR ENVIRONMENT; YOUTH 5

23 Schedule 1 Table 1: BPPH assessment The table below is a summary of the project s predicted footprint from dredging from direct (dredged area and spoil placement) and indirect (sediment plume dispersion and settlement). The proponent has modelled the zone of effect for indirect impacts as a result of sediment plumes across two timing scenarios (November and January). BPPH Loss Calculations Total Size of Management Unit (ha) Types of Benthic Primary Producer Habitat Historical Area of Total BPPH (ha) BPPH Management Unit (MU) Gage Roads Deep Water Channel Category E Category D November January Coastal Unit Category C Dominant seagrass with macroalgae and coral Macroalgae on limestone pavement, occasional seagrass Dominant seagrass with macroalgae on limestone pavement Current Area of Total BPPH (ha) EPA Category and Loss Threshold (2004b) Potential Permanent Seagrass Loss due to Project (ha and %) Estimated Historic Seagrass Loss (ha and %) Potential Total Cumulative Seagrass Loss (Historical + this Project) (ha and %) Potential Permanent Macroalgal Loss due to Project (ha and %) Estimated Historic Macroalgal Loss (ha and %) Potential Total Cumulative Macroalgal Loss (Historical + this Project) (ha and %) Potential Permanent Direct Coral Loss due to Project (ha and %) Estimated Historic Coral Loss (ha and %) Potential Total Cumulative Coral Loss (Historical + this Project) (ha and %) E 10% D 5% C 2% % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % The Proposal (Assessment No. 1621) The main characteristics of the proposal are summarised in Table 2 below. A detailed description of the proposal is provided in Section 2 of the project referral document, Fremantle Ports Inner harbour and Channel Deepening, Reclamation at Rous Head and Offshore Placement of Dredged Material (PER, 2009). 6

24 Table 2: Summary of key proposal characteristics Element Description General Construction of a sea wall 1000 m long Reclamation Approx 27 ha at Rous Head Dredging Inner Harbour, from a depth of RL m to a depth of RL m Low Water Mark Fremantle (LWMF) Entrance Channel from depths of RL to 13.4 m to depths between RL m (LWMF) and RL m (LWMF) to provide adequate depth for turning ships Deep Water Channel to a depth of RL m (LWMF) on straight sections and RL m (LWMF) on bends, within an area of approx 169ha Relocation of dredged materials From the Inner Harbour (approx 0.9 Mm3) and the inner section of Entrance Channel (approx 1.1 Mm3) to Rous Head from the Deep Water Channel (approx 1.1 Mm3) to a proposed spoil ground located at Gage Roads (placement of approx 1.45 Mm3 within an area of approx 150ha) Timing Dredging campaign to commence in November for weeks. Key M metres M3 cubic metres Figures 1. Fremantle Ports project location 2. Fremantle Ports project location Satellite 3. Fremantle Ports project location Inner Harbour dredging and reclamation 4. Fremantle Ports project location Rous Head extension 7

25 8

26 9

27 10

28

29

ANNUAL COMPLIANCE ASSESSMENT REPORT. Brockman Railway Infrastructure Project (Ministerial Statement 923) Revision history:

ANNUAL COMPLIANCE ASSESSMENT REPORT. Brockman Railway Infrastructure Project (Ministerial Statement 923) Revision history: ANNUAL COMPLIANCE ASSESSMENT REPORT Brockman Railway Infrastructure Project (Ministerial Statement 923) 2014 2015 Revision history: Revision Prepared Reviewed Approved Dated Issued Description A G. Firth

More information

Pluto LNG Project Ministerial Statement 757 Compliance Report 22 December 2008

Pluto LNG Project Ministerial Statement 757 Compliance Report 22 December 2008 Pluto LNG Project Ministerial Statement 757 Compliance Report 22 December 2008 1. INTRODUCTION This al Compliance Report demonstrates compliance with conditions outlined in Ministerial Statement 757 for

More information

CHAPTER 24: ENVIRONMENTAL MANAGEMENT

CHAPTER 24: ENVIRONMENTAL MANAGEMENT Central Eyre Iron Project Environmental Impact Statement CHAPTER 24: ENVIRONMENTAL MANAGEMENT CHAPTER 24 ENVIRONMENTAL MANAGEMENT COPYRIGHT Copyright Iron Road Limited, 2015 All rights reserved This document

More information

Works Approval Conditions 1 General

Works Approval Conditions 1 General Works Approval Conditions 1 General 1.1 Interpretation 1.1.1 In the Works Approval, definitions from the Environmental Protection Act 1986 apply unless the contrary intention appears. 1.1.2 In the Works

More information

Guideline: Works that interfere with water in a watercourse watercourse diversions. September 2014

Guideline: Works that interfere with water in a watercourse watercourse diversions. September 2014 Guideline: Works that interfere with water in a watercourse watercourse diversions September 2014 This publication has been compiled by the Department of Natural Resources and Mines. State of Queensland,

More information

Cliff Head Oil Field Development- 20 km south of Dongara, Shire of Irwin Roc Oil (WA) Limited

Cliff Head Oil Field Development- 20 km south of Dongara, Shire of Irwin Roc Oil (WA) Limited Cliff Head Oil Field Development- 20 km south of Dongara, Shire of Irwin Roc Oil (WA) Limited Report and recommendations of the Environmental Protection Authority Environmental Protection Authority Perth,

More information

Environmental Guidelines for Preparation of an Environmental Management Plan

Environmental Guidelines for Preparation of an Environmental Management Plan 2013 Environmental Guidelines for Preparation of an Environmental Management Plan Environmental Management Division Environmental Protection Agency 3/13/2013 ENVIRONMENTAL GUIDELINES FOR PREPARATION OF

More information

Chatham Rock Phosphate Marine Consent Application. P Kennedy - Environmental Impact Assessment Evidence Summary

Chatham Rock Phosphate Marine Consent Application. P Kennedy - Environmental Impact Assessment Evidence Summary Chatham Rock Phosphate Marine Consent Application P Kennedy - Environmental Impact Assessment Evidence Summary My evidence and this summary cover the following matters: Seabed and sediment Discharge and

More information

Memorandum of Understanding between the NSW Ministry of Health and Sydney Water Corporation

Memorandum of Understanding between the NSW Ministry of Health and Sydney Water Corporation Page 1 of 11 Memorandum of Understanding between the NSW Ministry of Health and Sydney Water Corporation This work is copyright. It may be reproduced in whole or in part for study or training purposes

More information

Health, Safety and Environment Management System

Health, Safety and Environment Management System Health, Safety and Environment Management System For Bridgeport Energy Ltd Level 7, 111 Pacific Highway North Sydney 2011 June, 2010 DOCUMENT CONTROL Title: Document Number: Health, Safety and Environmental

More information

Guide. Minister s Guide to Auditing for Building Surveyors. April 2014

Guide. Minister s Guide to Auditing for Building Surveyors. April 2014 Guide Minister s Guide to Auditing for Building Surveyors April 2014 Guide Minister s Guide to Auditing for Building Surveyors April 2014 Department of Planning, Transport and Infrastructure 136 North

More information

Australian Transport Council. National Standard for the Administration of Marine Safety SECTION 4 SURVEYS OF VESSELS

Australian Transport Council. National Standard for the Administration of Marine Safety SECTION 4 SURVEYS OF VESSELS Australian Transport Council National Standard for the Administration of Marine Safety SECTION 4 SURVEYS OF VESSELS Edition 1 Draft for comment issued 20 December 2005 Endorsed by the Australian Transport

More information

Environmental damage: extending the Environmental Liability Directive into marine waters

Environmental damage: extending the Environmental Liability Directive into marine waters www.gov.uk/defra Environmental damage: extending the Environmental Liability Directive into marine waters Consultation on amending the Environmental Damage (Prevention and Remediation) Regulations 2009

More information

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS PROPOSED PHASE 2 EXPANSION OF THE TRANSNET IRON ORE HANDLING FACILITY, SALDANHA

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS PROPOSED PHASE 2 EXPANSION OF THE TRANSNET IRON ORE HANDLING FACILITY, SALDANHA ENVIRONMENTAL IMPACT ASSESSMENT PROCESS PROPOSED PHASE 2 EXPANSION OF THE TRANSNET IRON ORE HANDLING FACILITY, SALDANHA BACKGROUND INFORMATION DOCUMENT 1 BACKGROUND Transnet Limited s (Transnet) existing

More information

VET (WA) Ministerial Corporation Purchase of Training Services Process Terms and Conditions

VET (WA) Ministerial Corporation Purchase of Training Services Process Terms and Conditions VET (WA) Ministerial Corporation Purchase of Training Services Process Terms and Conditions NOVEMBER 2013 EDITION TABLE OF CONTENTS 2. RESPONDENT S PARTICIPATION IN THE PROCUREMENT PROCESS 7 3. GENERAL...

More information

Final Project Report

Final Project Report CURTIN UNIVERSITY OF TECHNOLOGY Department of Applied Geology Western Australia School of Mines Applied Sedimentology, Coastal and Marine Geoscience Group GERALDTON EMBAYMENTS COASTAL SEDIMENT BUDGET STUDY

More information

Marine Protection Rules Marine Protection Rules Part 102 Certificates of Insurance Amendment 2014

Marine Protection Rules Marine Protection Rules Part 102 Certificates of Insurance Amendment 2014 Marine Protection Rules Marine Protection Rules Part 102 Certificates of Insurance Amendment 2014 Invitation to comment May 2014 Ensuring our transport system helps New Zealand thrive Contents Invitation

More information

LICENCE NUMBER: L8272/2008/2 FILE NUMBER: 2013/000545

LICENCE NUMBER: L8272/2008/2 FILE NUMBER: 2013/000545 WESTERN AUSTRALIA DEPARTMENT OF ENVIRONMENT REGULATION Environmental Protection Act 1986 Licensee: Nationwide Oil Pty Ltd Registered Office: Level 4, 441 St Kilda Road MELBOURNE VIC 3004 ACN: 066 383 364

More information

Import Health Standard

Import Health Standard Import Health Standard Ballast Water from All Countries 17 May 2016 Issued under the Biosecurity Act 1993 TITLE Import Health Standard: Ballast Water from All Countries COMMENCEMENT This Import Health

More information

CHAPTER E12 - ENVIRONMENTAL IMPACT ASSESSMENT ACT

CHAPTER E12 - ENVIRONMENTAL IMPACT ASSESSMENT ACT CHAPTER E12 - ENVIRONMENTAL IMPACT ASSESSMENT ACT ARRANGEMENT OF SECTIONS PART I General principles of environmental impact assessment SECTION 1.Goals and objectives of environmental impact assessment.

More information

Quality Management System Manual ISO9001:2008

Quality Management System Manual ISO9001:2008 Quality Management System Manual ISO9001:2008 Controlled Copy Rev. 3 Page 1 of 21 7/1/13 Table of Contents Company Profile...5 Past...5 Present...5 Mission...5 Vision...5 Locations...6 1 Scope...6 1.1

More information

Guide to agrichemical use in Resource Management Plans Northland Region as at October 2011

Guide to agrichemical use in Resource Management Plans Northland Region as at October 2011 Guide to agrichemical use in Resource Management Plans Northland Region as at October 2011 Northland Regional Air Quality Plan Note: This guide is intended to assist users and applicators understanding

More information

GUIDE TO IMPLEMENTING A REGULATORY FOOD SAFETY AUDITOR SYSTEM

GUIDE TO IMPLEMENTING A REGULATORY FOOD SAFETY AUDITOR SYSTEM GUIDE TO IMPLEMENTING A REGULATORY FOOD SAFETY AUDITOR SYSTEM FEBRUARY 2016 2 Contents Introduction... 4 Scope and objectives... 5 Scope... 5 Objectives... 5 Responsibilities... 5 The role of the licensee

More information

Maritime and Coastguard Agency LogMARINE INFORMATION NOTE

Maritime and Coastguard Agency LogMARINE INFORMATION NOTE Maritime and Coastguard Agency LogMARINE INFORMATION NOTE MIN 499 (M+F) Wreck Removal: Liability and Compulsory Insurance for the locating, marking and removing of wrecks Notice to all ship owners, operators,

More information

SOUTH COOGEE TRANSPORT MANAGEMENT PLAN

SOUTH COOGEE TRANSPORT MANAGEMENT PLAN SOUTH COOGEE TRANSPORT MANAGEMENT PLAN On behalf of : DEPARTMENT FOR PLANNING & INFRASTRUCTURE Prepared by: ENV Australia A.C.N. 091 839 520 Mezzanine Level, Central Park 152-158 St Georges Terrace Perth

More information

Diploma of Legal Services

Diploma of Legal Services Diploma of Legal Services BSB52215 Course Guidelines General Information This document provides an overview of the Diploma of Legal Services (BSB52215) qualification offered via the Queensland Law Society

More information

Project Management. Advice on the provision of Local Decontamination Units (LDUs) Decontamination Services

Project Management. Advice on the provision of Local Decontamination Units (LDUs) Decontamination Services Advice on the provision of Local Decontamination Units (LDUs) Decontamination Services January 2010 Contents Project Management Page Local Decontamination Units (LDUs) Construction Project Management...3

More information

Corporate Standard. Contractor Management

Corporate Standard. Contractor Management Corporate Standard Contents Purpose... 2 Scope... 2 Definitions... 2 Background... 3 Specific Requirements... 4 Responsibilities... 11 Review Date... 11 References... 11 Date Issued July 2010 Management

More information

Wellington Inner City Improvements National War Memorial Park (Pukeahu) Certification Review

Wellington Inner City Improvements National War Memorial Park (Pukeahu) Certification Review Wellington Inner City Improvements National War Memorial Park (Pukeahu) Air Quality (Dust) Certification Review 22 November 2012 [CAQMP1 TR] Prepared in association with: Document produced by: Apecx PO

More information

Precision Hydrographic Services. Company Profile. Company Profile. We do it once, we do it right.

Precision Hydrographic Services. Company Profile. Company Profile. We do it once, we do it right. Precision Hydrographic Services Company Profile 2015 Company Profile We do it once, we do it right. About Us Overview Precision Hydrographic Services (PHS) commenced in 2008 and specialise in the acquisition,

More information

FINAL REPORT (DEVELOPMENT AWARD)

FINAL REPORT (DEVELOPMENT AWARD) FINAL REPORT (DEVELOPMENT AWARD) AWARD CODE and TITLE 2009/315.29 FRDC People Development Program: Aquatic animal health training scheme fish kill investigation AWARD RECIPIENT: Dr Shane Roberts and Mr

More information

Value Extended Warranty and Premium Extended Warranty. Terms and Conditions

Value Extended Warranty and Premium Extended Warranty. Terms and Conditions Value Extended Warranty and Premium Extended Warranty Terms and Conditions Your Value Extended Warranty and Premium Extended Warranty (referred to herein as the Plan or Plans ) are governed by these Terms

More information

GUIDANCE NOTE 1.1.1 Building Control (Amendment) Regulations 2014 Procurement Implications for Contracting Authorities

GUIDANCE NOTE 1.1.1 Building Control (Amendment) Regulations 2014 Procurement Implications for Contracting Authorities GUIDANCE NOTE 1.1.1 Building Control (Amendment) Regulations 2014 Procurement Implications for Contracting Authorities Office of Government Procurement Building Control (Amendment) Regulations 2014 Procurement

More information

in this issue A newsletter from the Consumer Protection Division of the Department of Commerce CPD activities for 2012

in this issue A newsletter from the Consumer Protection Division of the Department of Commerce CPD activities for 2012 No.03 Autumn 2012 settlement news A newsletter from the Consumer Protection Division of the Department of Commerce Are you on track Office for Distribution your CPD? List in this issue New policy to counter

More information

Guideline for preparing an Environmental and Social Management Plan

Guideline for preparing an Environmental and Social Management Plan Guideline for preparing an Environmental and Social Management Plan NZ Transport Agency www.nzta.govt.nz Version 1: April 2014 ISBN 978-0-478-41934-4 (online) Copyright information This publication is

More information

Recommendations Relating to the Application of Requirements Governing Seafarers Hours of Work and Rest

Recommendations Relating to the Application of Requirements Governing Seafarers Hours of Work and Rest Oil Companies International Marine Forum s Relating to the Application of Requirements Governing Seafarers Hours of Work and Rest January 2012 The OCIMF mission is to be the foremost authority on the safe

More information

www.epa.nsw.gov.au August 2014

www.epa.nsw.gov.au August 2014 Report on the Findings of the NSW Environment Protection Authority s Review of Snowy Hydro Limited Cloud Seeding Program: 2013 Annual Compliance Report August 2014 www.epa.nsw.gov.au State of NSW, Environment

More information

Drinking Water Quality Management Plan Review and Audit Guideline

Drinking Water Quality Management Plan Review and Audit Guideline Drinking Water Quality Management Plan Review and Audit Guideline This publication has been compiled by Queensland Water Supply Regulator, Department of Energy and Water Supply. State of Queensland, 2013.

More information

The key points of the 2013 Annual Compliance Report are described fully in the following sections of this report:

The key points of the 2013 Annual Compliance Report are described fully in the following sections of this report: Introduction Snowy Hydro Limited (Snowy Hydro) relies on precipitation falling over the catchments of the Snowy Mountains to supply water for the production of hydro-electricity. Cloud seeding over this

More information

WA Pollution Licensing and environmental impact assessment

WA Pollution Licensing and environmental impact assessment Marine Pollution An introduction to Marine Pollution Fact Sheet 20 Updated December 2010 Western Australia has the longest and most remote coastline in Australia. It is home to a wide range of marine ecosystems.

More information

Entrepreneurs Programme - Business Growth Grants

Entrepreneurs Programme - Business Growth Grants Entrepreneurs Programme - Business Growth Grants Version: 15 July 2015 Contents 1 Purpose of this guide... 4 2 Programme overview... 4 2.1 Business Management overview... 4 3 Business Growth Grant... 5

More information

GUIDANCE DOCUMENT FOR DEVELOPMENT OF SITE MANAGEMENT PLANS FOR OCEAN DREDGED MATERIAL DISPOSAL SITES. February 1996

GUIDANCE DOCUMENT FOR DEVELOPMENT OF SITE MANAGEMENT PLANS FOR OCEAN DREDGED MATERIAL DISPOSAL SITES. February 1996 GUIDANCE DOCUMENT FOR DEVELOPMENT OF SITE MANAGEMENT PLANS FOR OCEAN DREDGED MATERIAL DISPOSAL SITES February 1996 Developed by: US Environmental Protection Agency US Army Corps of Engineers 1 PURPOSE

More information

Clearing and Settlement Procedures. New Zealand Clearing Limited. Clearing and Settlement Procedures

Clearing and Settlement Procedures. New Zealand Clearing Limited. Clearing and Settlement Procedures Clearing and Settlement Procedures New Zealand Clearing Limited Clearing and Settlement Procedures 30 November 2011 Contents Section A: Interpretation and Construction 6 Section 1: Introduction and General

More information

STATE RECORDS COMMISSION. SRC Standard 6 OUTSOURCING. A Recordkeeping Standard for State Organizations

STATE RECORDS COMMISSION. SRC Standard 6 OUTSOURCING. A Recordkeeping Standard for State Organizations STATE RECORDS COMMISSION SRC Standard 6 OUTSOURCING A Recordkeeping Standard for State Organizations State Records Commission of WA Perth, Western Australia February 2002 Table of Contents Definitions

More information

Environmental guidelines for preparation of an Environment Management Plan

Environmental guidelines for preparation of an Environment Management Plan Environmental guidelines for preparation of an Environment Management Plan Environment Protection Authority MAY 2013 Australian Capital Territory, Canberra 2013 This work is copyright. Apart from any use

More information

SUBDIVISION AND DEVELOPMENT REGULATION

SUBDIVISION AND DEVELOPMENT REGULATION Province of Alberta MUNICIPAL GOVERNMENT ACT SUBDIVISION AND DEVELOPMENT REGULATION Alberta Regulation 43/2002 With amendments up to and including Alberta Regulation 119/2014 Office Consolidation Published

More information

Compliance. Group Standard

Compliance. Group Standard Group Standard Compliance Serco is committed to good governance practices and the management of risks supported by a robust business compliance process SMS-GS-G2 Compliance July 2014 v1.0 Serco Public

More information

Incident Reporting Requirements

Incident Reporting Requirements Incident Reporting Requirements Directive PNG014 February 2016 Revision 1.0 Governing Legislation: Acts: The Oil and Gas Conservation Act The Pipelines Act, 1998 Regulations: The Oil and Gas Conservation

More information

Customer Service Charter Guidelines

Customer Service Charter Guidelines Customer Service Charter Guidelines August 2006 Customer Service Charter Guidelines August 2006 1 Contents 1 What are the Customer Service Charter Guidelines? 2 2 What is a Customer Service Charter? 2

More information

Reef Health Incident Response System

Reef Health Incident Response System Reef Health Incident Response System 2011 Commonwealth of Australia 2007 Published by the Great Barrier Reef Marine Park Authority Reef Health Incident Response System. 2011 ISSN 2200-2057 (pdf) This work

More information

REGISTER OF DELEGATIONS COUNCIL TO CEO Environmental Protection Act 1994

REGISTER OF DELEGATIONS COUNCIL TO CEO Environmental Protection Act 1994 1 Chief Executive Officer Power, as an affected person, to make written comments to the chief executive about a TOR notice. 2 Chief Executive Officer Power to make a written submission about a submitted

More information

Unofficial Consolidation

Unofficial Consolidation CENTRAL BANK (SUPERVISION AND ENFORCEMENT) ACT 2013 (SECTION 48) (LENDING TO SMALL AND MEDIUM-SIZED ENTERPRISES) REGULATIONS 2015 (S.I. No. 585 of 2015) Unofficial Consolidation This document is an unofficial

More information

APPLICATION KIT AND GUIDELINES FOR ORGANISATIONS SEEKING TO UNDERTAKE WORKS WITHIN ROAD RESERVE LOW COMPLEXITY WORKS.

APPLICATION KIT AND GUIDELINES FOR ORGANISATIONS SEEKING TO UNDERTAKE WORKS WITHIN ROAD RESERVE LOW COMPLEXITY WORKS. Document No: 16-02-12A Issue Date: 09 December 2014 APPLICATION KIT AND GUIDELINES FOR ORGANISATIONS SEEKING TO UNDERTAKE WORKS WITHIN ROAD RESERVE LOW COMPLEXITY WORKS (An approved Traffic Management

More information

CALDER PARK PROJECT STAGE 1. EPBC Act Approval Compliance Report (EPBC 2012/6439)

CALDER PARK PROJECT STAGE 1. EPBC Act Approval Compliance Report (EPBC 2012/6439) CALDER PARK PROJECT STAGE 1 EPBC Act Approval Compliance Report (EPBC 2012/6439) Prepared for: METRO TRAINS MELBOURNE Level 28, 80 Collins Street, Melbourne, VIC 3000 Prepared by: Kellogg Brown & Root

More information

Planning Act 2008: Guidance on Changes to Development Consent Orders. December 2015 Department for Communities and Local Government

Planning Act 2008: Guidance on Changes to Development Consent Orders. December 2015 Department for Communities and Local Government Planning Act 2008: Guidance on Changes to Development Consent Orders December 2015 Department for Communities and Local Government Crown copyright, 2015 Copyright in the typographical arrangement rests

More information

NORTHERN TERRITORY ELECTRICITY RING-FENCING CODE

NORTHERN TERRITORY ELECTRICITY RING-FENCING CODE NORTHERN TERRITORY ELECTRICITY RING-FENCING CODE JULY 2001 Table of Provisions Clause Page 1. Authority...2 2. Application...2 3. Objectives...2 4. Ring-Fencing Minimum Obligations...2 5. Compliance with

More information

International Financial Reporting Standards (IFRS)

International Financial Reporting Standards (IFRS) FACT SHEET September 2011 IAS 24 Related Party Disclosures (This fact sheet is based on the standard as at 1 January 2011.) Important note: This fact sheet is based on the requirements of the International

More information

Procedure. Work Health and Safety Contractor Management. Document number: PRO-00808. Rev no. Description Process Owner Approved for issue

Procedure. Work Health and Safety Contractor Management. Document number: PRO-00808. Rev no. Description Process Owner Approved for issue Procedure Work Health and Safety Contractor Management Document number: PRO-00808 This document is the property of Seqwater. It must not be copied or reproduced in any way whatsoever without the authority

More information

How To Prepare A Configuration Change Change Request For The Tfnsw Cmaac

How To Prepare A Configuration Change Change Request For The Tfnsw Cmaac Guide TfNSW Configuration Management and Asset Assurance Committee Submissions Guide Important Warning This document is one of a set of standards developed solely and specifically for use on public transport

More information

Rachel Silverstein, Ph.D. Executive Director and Waterkeeper

Rachel Silverstein, Ph.D. Executive Director and Waterkeeper Dredging-Related Sediment Impacts on Coral Reefs near the Port of Miami Channel Rachel Silverstein, Ph.D. Executive Director and Waterkeeper As the Panama canal undergoes an expansion, shallow ports along

More information

Appendix A1. Register of legal and other requirements

Appendix A1. Register of legal and other requirements Appendix A1 Register of legal and other requirements 1 Table 1 Legal register Act Activity / General Environmental Planning and Assessment Act 1979 All Comply with the terms Minister for Planning and Infrastructure

More information

London STOCK EXCHANGE

London STOCK EXCHANGE London STOCK EXCHANGE 16 March 2006 For the attention of the Nominated Advisers/ Finance Directors/ Company Secretaries, all AIM Companies 10 Paternoster Square London EC4M 7LS Telephone 020 7797 1000

More information

2011 No. 1824 TOWN AND COUNTRY PLANNING. The Town and Country Planning (Environmental Impact Assessment) Regulations 2011

2011 No. 1824 TOWN AND COUNTRY PLANNING. The Town and Country Planning (Environmental Impact Assessment) Regulations 2011 STATUTORY INSTRUMENTS 2011 No. 1824 TOWN AND COUNTRY PLANNING The Town and Country Planning (Environmental Impact Assessment) Regulations 2011 Made - - - - 19th July 2011 Laid before Parliament 26th July

More information

ATTACHMENT F ONSHORE PIPELINES DECOMMISSIONING GUIDELINE 1. INTRODUCTION

ATTACHMENT F ONSHORE PIPELINES DECOMMISSIONING GUIDELINE 1. INTRODUCTION ATTACHMENT F ONSHORE PIPELINES DECOMMISSIONING GUIDELINE 1. INTRODUCTION After concession is expired or at the end of its economic life, pipeline network and all associated structures are due for decommissioning

More information

Essential Standards for Registration

Essential Standards for Registration Essential Standards for Registration State and Territory Registering Bodies Australian Capital Territory New South Wales Northern Territory Queensland South Australia Tasmania Victoria Western Australia

More information

TABLE OF CONTENTS. City of Mitcham Page 1 of 9

TABLE OF CONTENTS. City of Mitcham Page 1 of 9 Building Audit Inspections Development Control Policy Endorsing Body Council Responsible Department: Development & Compliance Policy Folder No: FF/2012/2017 Policy Record No: 12.092262 Template Folder

More information

Crown Land Management

Crown Land Management Crown Land Management An introduction to Crown Land Management Fact Sheet 12 Updated December 2010 Approximately 93% of Western Australia s land area is Crown land (that is, not private land). The majority

More information

NHS Standard Contract 2015/16 General Conditions

NHS Standard Contract 2015/16 General Conditions NHS Standard Contract 2015/16 Draft for consultation December 2014 NHS Standard Contract 2015/16 Draft for consultation Version number: 1 First published: December 2014 Updated: Prepared by: NA NHS Standard

More information

Home Owners (Owner Builder) Warranty Inspection Agreement

Home Owners (Owner Builder) Warranty Inspection Agreement Home Owners (Owner Builder) Warranty Inspection Agreement To AS 4349.0-2007 Inspection of Buildings General Requirements And Section 95 of the NSW Home Building Act 1989 Part 3 of the WA Home Building

More information

MLD: Domestic Maritime Transport Project

MLD: Domestic Maritime Transport Project Environmental Monitoring Report Project Number: 37265 December 2010 MLD: Prepared by Japan Port Consultants Co., Ltd. Malé, Maldives For Ministry of Finance and Treasury Ministry of Transport and Communication

More information

MARITIME OPERATOR SAFETY SYSTEM: MARITIME RULE PARTS 19 AND 44

MARITIME OPERATOR SAFETY SYSTEM: MARITIME RULE PARTS 19 AND 44 Office of the Minister of Transport Chair Cabinet Economic Growth and Infrastructure Committee MARITIME OPERATOR SAFETY SYSTEM: MARITIME RULE PARTS 19 AND 44 Proposal 1. The purpose of this paper is to

More information

Permitting of Development and Infrastructure Projects in Abu Dhabi

Permitting of Development and Infrastructure Projects in Abu Dhabi Table of Contents 1.0 Purpose... 4 1.1 What Is a Objection Certificate for Development and Infrastructure Projects?... 4 1.2 Why Is an NOC Required?... 4 2.0 Scope... 4 2.1 What Development and Infrastructure

More information

WA Health Exit Survey Policy

WA Health Exit Survey Policy WA Health Exit Survey Policy health.wa.gov.au Effective: 10 August 2015 Title: WA HEALTH EXIT SURVEY POLICY 1. POLICY STATEMENT A person s employment journey commences with recruitment and ends when they

More information

Superseded by T MU AM 04001 PL v2.0

Superseded by T MU AM 04001 PL v2.0 Plan T MU AM 04001 PL TfNSW Configuration Management Plan Important Warning This document is one of a set of standards developed solely and specifically for use on the rail network owned or managed by

More information

Executive Summary. The functional groupings of LSD s operations are:

Executive Summary. The functional groupings of LSD s operations are: Executive Summary Land Systems Division (LSD) is a Division within the (DMO) that is responsible for acquisition and sustainment of designated land systems for the Australian Defence Force (ADF). LSD provides

More information

Dutch Labour Standards Foundation The Standard for reliability. Information set about Standard NEN 4400 and the Labour Standards Register

Dutch Labour Standards Foundation The Standard for reliability. Information set about Standard NEN 4400 and the Labour Standards Register Dutch Labour Standards Foundation The Standard for reliability Information set about Standard NEN 4400 and the Labour Standards Register Key terms: NEN 4400-1, NEN 4400-2, temporary staffing sector, contracting

More information

ARTWORK COMMISSION AGREEMENT

ARTWORK COMMISSION AGREEMENT ARTWORK COMMISSION AGREEMENT THIS AGREEMENT is made the day of in the year BETWEEN the Minister for Works of Level 6, 16 Parkland Road, Osborne Park, WA 6017 being the body corporate created under Section

More information

WORKPLACE HEALTH AND SAFETY AUDITING GUIDELINES

WORKPLACE HEALTH AND SAFETY AUDITING GUIDELINES WHS UNIT WORKPLACE HEALTH AND SAFETY AUDITING GUIDELINES Contents 1 Purpose... 1 2 Scope... 1 3 Definitions... 1 4 Responsibilities... 1 4.1 WHS Unit... 1 4.2 Auditor(s)... 1 4.3 Managers of Faculties

More information

TITLE 5.1 AND TITLE 5.2 FLAG STATE INSPECTION AND CERTIFICATION AND PORT STATE INSPECTION

TITLE 5.1 AND TITLE 5.2 FLAG STATE INSPECTION AND CERTIFICATION AND PORT STATE INSPECTION SECTION 9 TITLE 5.1 AND TITLE 5.2 FLAG STATE INSPECTION AND CERTIFICATION AND PORT STATE INSPECTION Introduction 10.1 This section seeks your views on the Maritime and Coastguard Agency s proposals for

More information

U & D COAL LIMITED A.C.N. 165 894 806 BOARD CHARTER

U & D COAL LIMITED A.C.N. 165 894 806 BOARD CHARTER U & D COAL LIMITED A.C.N. 165 894 806 BOARD CHARTER As at 31 March 2014 BOARD CHARTER Contents 1. Role of the Board... 4 2. Responsibilities of the Board... 4 2.1 Board responsibilities... 4 2.2 Executive

More information

Minerals Regulatory Guidelines MG5. Guidelines for miners: tailings and tailings storage facilities in South Australia

Minerals Regulatory Guidelines MG5. Guidelines for miners: tailings and tailings storage facilities in South Australia Minerals Regulatory Guidelines MG5 Guidelines for miners: tailings and tailings storage facilities in South Australia Mineral Resources Group Division of Minerals and Energy Resources Primary Industries

More information

Rail Network Configuration Management

Rail Network Configuration Management Division / Business Unit: Function: Document Type: Enterprise Services Engineering Procedure Rail Network Configuration Management Applicability ARTC Network Wide SMS Publication Requirement Internal /

More information

INDONESIA - LAW ON WATER RESOURCES,

INDONESIA - LAW ON WATER RESOURCES, Environment and Development Journal Law LEAD INDONESIA - LAW ON WATER RESOURCES, 2004 VOLUME 2/1 LEAD Journal (Law, Environment and Development Journal) is a peer-reviewed academic publication based in

More information

Construction & Demolition Waste Management in Green Star Discussion Paper

Construction & Demolition Waste Management in Green Star Discussion Paper Construction & Demolition Waste Management in Green Star Discussion Paper 1 Construction & Demolition Waste Management in Green Star - Discussion Paper Construction & Demolition Waste Management in Green

More information

AusPat Email Notification User Guide

AusPat Email Notification User Guide AusPat Email Notification User Guide March 2014 Contents Disclaimer... 3 Introduction... 4 Subscribing to the Notification Service... 5 Via the IP Australia Website... 5 Via AusPat Landing Page... 6 Via

More information

Audit report VET Quality Framework Initial registration as a national VET regulator (NVR) registered training organisation

Audit report VET Quality Framework Initial registration as a national VET regulator (NVR) registered training organisation Audit report VET Quality Framework Initial registration as a national VET regulator (NVR) registered training organisation ORGANISATION DETAILS Organisation s legal name Trading name/s R-Training Pty Ltd

More information

Power and Water Corporation Report for Bathymetric and Benthic Survey of the Proposed East Point Outfall

Power and Water Corporation Report for Bathymetric and Benthic Survey of the Proposed East Point Outfall Power and Water Corporation Report for Bathymetric and Benthic Survey of the Proposed East Point Outfall Part Two Bathymetric Report January 2009 Photo: East Point at high tide Contents 1. Hydrosurvey

More information

Audit report VET Quality Framework Continuing registration as a national VET regulator (NVR) registered training organisation

Audit report VET Quality Framework Continuing registration as a national VET regulator (NVR) registered training organisation Audit report VET Quality Framework Continuing registration as a national VET regulator (NVR) registered training organisation ORGANISATION DETAILS Organisation s legal name Kreate Pty Ltd Trading name/s

More information

CSX Public Safety, Health, and Environmental Management System

CSX Public Safety, Health, and Environmental Management System CSX Public Safety, Health, and Environmental Management System As one of the nation s leading suppliers of rail and intermodal transportation, CSX Transportation (CSX) is committed to minimizing the impact

More information

2012 No. 637 TOWN AND COUNTRY PLANNING, ENGLAND. The Neighbourhood Planning (General) Regulations 2012

2012 No. 637 TOWN AND COUNTRY PLANNING, ENGLAND. The Neighbourhood Planning (General) Regulations 2012 STATUTORY INSTRUMENTS 2012 No. 637 TOWN AND COUNTRY PLANNING, ENGLAND The Neighbourhood Planning (General) Regulations 2012 Made - - - - 1st March 2012 Laid before Parliament 6th March 2012 Coming into

More information

Operational Audit and. Asset Management System Review. Shire of Coolgardie

Operational Audit and. Asset Management System Review. Shire of Coolgardie Shire of Coolgardie Operational Audit and Asset Management System Shire of Review Dowerin 2011 (Water Services Operating Licence) Water Services Operating Licence (Sewerage and Non-Potable Water) DRAFT

More information

Health and Safety Policy and Procedures

Health and Safety Policy and Procedures Health and Safety Policy and Procedures Health & Safety Policy & Procedures Contents s REVISION AND AMENDMENT RECORD : Summary of Change Whole Policy 4.0 05 Nov 08 Complete re-issue Whole Policy 4.1 10

More information

NATIONAL PRIORITIES FOR INTRODUCED MARINE PEST RESEARCH AND DEVELOPMENT 2013 2023

NATIONAL PRIORITIES FOR INTRODUCED MARINE PEST RESEARCH AND DEVELOPMENT 2013 2023 NATIONAL PRIORITIES FOR INTRODUCED MARINE PEST RESEARCH AND DEVELOPMENT 2013 2023 Developed by the Marine Pest Sectoral Committee, 2013 Commonwealth of Australia Ownership of intellectual property rights

More information

Risk and Audit Committee Terms of Reference. 16 June 2016

Risk and Audit Committee Terms of Reference. 16 June 2016 Risk and Audit Committee Terms of Reference 16 June 2016 Risk and Audit Committee Terms of Reference BHP Billiton Limited and BHP Billiton Plc Approved by the Boards of BHP Billiton Limited and BHP Billiton

More information

GUIDELINE NO. 22 REGULATORY AUDITS OF ENERGY BUSINESSES

GUIDELINE NO. 22 REGULATORY AUDITS OF ENERGY BUSINESSES Level 37, 2 Lonsdale Street Melbourne 3000, Australia Telephone.+61 3 9302 1300 +61 1300 664 969 Facsimile +61 3 9302 1303 GUIDELINE NO. 22 REGULATORY AUDITS OF ENERGY BUSINESSES ENERGY INDUSTRIES JANUARY

More information

AUTHORISATION JAMES PAGET UNIVERSITY HOSPITALS NHS FOUNDATION TRUST

AUTHORISATION JAMES PAGET UNIVERSITY HOSPITALS NHS FOUNDATION TRUST AUTHORISATION of JAMES PAGET UNIVERSITY HOSPITALS NHS FOUNDATION TRUST (pursuant to Section 6 of the Health and Social Care (Community Health and Standards) Act 2003) Signature:... 1 August 2006 1 TABLE

More information

Registered and Accredited Individual Non-government Schools (NSW) Manual

Registered and Accredited Individual Non-government Schools (NSW) Manual Registered and Accredited Individual Non-government Schools (NSW) Manual October 2014 (incorporating changes from 2004 to 2014) Please note: Amendments to the Manual are noted, as they take effect, in

More information

GENERAL SPECIFICATION

GENERAL SPECIFICATION R64 - PAVEMENT MARKING August 1996 GENERAL SPECIFICATION G10 CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN Date JUNE 2012 Department 1 DOT Spec R64 of Infrastructure, Energy and Resources Index DEPARTMENT

More information

Office of the Auditor General Western Australia. Audit Practice Statement

Office of the Auditor General Western Australia. Audit Practice Statement Office of the Auditor General Western Australia Audit Practice Statement Office of the Auditor General Western Australia 7th Floor Albert Facey House 469 Wellington Street Perth Mailing Address Perth BC

More information