LAO PDR: SECOND ROAD MAINTENANCE PROJECT (RMP-2) Safeguards Policies, Social and Environmental Issues Summary (UPDATED for RMP-2 in June 2004)

Size: px
Start display at page:

Download "LAO PDR: SECOND ROAD MAINTENANCE PROJECT (RMP-2) Safeguards Policies, Social and Environmental Issues Summary (UPDATED for RMP-2 in June 2004)"

Transcription

1 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized A) INTRODUCTION LAO PDR: SECOND ROAD MAINTENANCE PROJECT (RMP-2) Safeguards Policies, Social and Environmental Issues Summary (UPDATED for RMP-2 in June 2004) The Government of Lao PDR (GOL) has been implementing the Road Maintenance Project (RMP) with support from the World Bank (WB). Arising from the success of the project, the Second Road Maintenance Project (RMP-2) has been proposed to expand the work nation-wide and to focus on the rehabilitation, periodic maintenance and routine maintenance of national and provincial roads in all 17 Provinces and one Special Zone of the country. During the preparation and appraisal of RMP-2 by a Bank mission, the management of the environmental and social impacts of the first RMP was reviewed with the objective of ensuring improved performance in these key areas in RMP-2. The main areas of concern observed during civil works undertaken in RMP1 included the following: the lack of supervisory budget for environmental and social impact monitoring; the limited capacity of the implementing units responsible for social and environmental performance (ESD and DTCPC); potential adverse impacts in sensitive areas; and compliance performance of contractors, especially in the areas of road safety, dust, disposal of wastes, location and treatment of borrow pits/quarries, and consultation with local communities. Other concerns noted are related to the post-maintenance phase of the project and include dust re-suspension, road safety, community participation, and encroachment of road right-of-way. To address these concerns, the Ministry of Communication, Transportation, Post and Construction (MCPCT), assisted by consultants, has conducted an initial environmental evaluation (IEE) for RMP-2 and prepared a Strategic Environmental Assessment (SEA) report presenting the findings of the IEE and a strategic plan to address key issues. The Environmental Guidelines for Road Projects (EGRP) prepared in 1999, which have been applied to RMP-1, have also been reviewed and updated (see Section C below). Although new adverse impacts are generally not expected to arise from most work undertaken in RMP-2, the Ministry is also proposing an additional precautionary measure in the form of a safeguard screening framework (see ESSF in Section C) that would be applied to all the civil work subprojects for RMP-2. The EGRP and the RCG have been reviewed and will become an integral part of the new screening procedure. Finally the Ethnic Minority Development Policy (EMDP) framework has been developed for RMP-2 (see Section B below), and this will be applied where appropriate. To ensure consistency of the Safeguard Policies to be applied in RMP-2, the Safeguard Policies proposed and publicly announced in late February 2004 have been updated as shown below. The updated Safeguard Policies for RMP-2 now comprise the ESSF, the updated EGRP, the RCG, and the EMDP. These documents will be publicly disclosed (both in English and Lao languages) before June 14, N:\LAO PDR\RMP2\Env and social\sea\appendix 1 sea part A\Final Safeguards Policies (updated) June5.doc 1

2 B) SOCIAL ASPECTS 1. Land Acquisition and Resettlement The Project is not expected to cause land acquisition nor resettlement. However, minor infrastructure or the use of some areas as deposits may result in unexpected low-level impacts/damages to parcels of land or buildings. Road maintenance activities may also require the temporary occupation of plots or may cause crops or income losses to settlers along the roads. 1.1 Resettlement and Compensation Guidelines In order to ensure that impacts are compensated in compliance with World Bank policy, Resettlement and Compensation Guidelines (RCG) specifying eligibility and entitlement principles have been prepared based on a Draft decree by the Prime Minister prepared by the national environmental protection agency (STEA). The RCG fully comply with OP/BP 4.12 and reflect Lao laws and regulations. The RCG text (see Attachment 1) will be translated in Lao and distributed as part of the Operations Manual to the local agencies responsible for the maintenance works. 1.2 Implementation The compensation of impacts will be implemented and managed by the Districts. The Environment and Social Division (ESD) of the Department of Roads will have a supervisory role and will ensure that the provisions contained in the Resettlement and Compensation Guidelines are implemented. 1.3 Public Information and Consultation MCTPC will ensure that all districts and villages are properly and timely informed of the road maintenance activities to be carried out. MCTPC will also ensure that the provisions of the RCG are effectively disclosed to the population living along the roads targeted by the project by means of a public information campaign. All communities along the roads targeted by the project will be consulted by means of ad hoc meetings regarding their priorities and needs in matters of road maintenance. 1.4 Complaints and Grievances Complaints and grievances at the local administrative level will be dealt with by an independent committee including leading members of the local communities. In case complaint and grievances issues are appealed they will be dealt with in the first instance by the district administration and in the second instance by the provincial authorities. Project affected persons will be exempted from all administrative and legal fees incurred in pursuant to the grievance redress procedures. 1.5 Voluntary Contributions Where local communities elect to make voluntary contribution of affected land without compensation, this should be acceptable only for marginal impacts (partial impact on land without causing any displacement or impact on structures, and with remaining assets viable for continued use) and only when benefits to affected people can be assured. The process of consultation with potential contributors should, be conducted in an open and transparent manner by district officials and decisions for 'voluntary' contributions should be based on the 'informed choice' of affected people. People who elect to make voluntary contributions must be informed of their rights to compensation, and the process and decisions must be documented by the district authorities N:\LAO PDR\RMP2\Env and social\sea\appendix 1 sea part A\Final Safeguards Policies (updated) June5.doc 2

3 2. Impact on Ethnic Minorities The project is not expected to generate adverse impacts on ethnic minorities living alongside the roads or in the vicinity of the project area. The experience from provinces during RMP1 generally reflects the fact that project impacts are not ethnic group-specific but relate to all communities in the project area. However, given the nationwide coverage of RMP-2 and in view of the large presence of ethnic minority communities in parts of the country where the project works will be undertaken, an Ethnic Minorities Development Policy (EMDP) framework has been prepared (see Attachment 2) as required by the Bank s OD Ethnic Minorities Development Policy Framework The broad objective of the EMDP is to ensure that ethnic minority communities do not suffer adverse effects during the project operations and that they receive culturally compatible social and economic benefits. As part of the framework, the EMDP includes mitigation measures and assistance aimed at institutional strengthening and capacity building of these communities. The framework also specifies community participation and consultation and grievance redress mechanisms that are developed in culturally appropriate ways. 2.2 Ethnic Minorities Action Plan In conformity with OD 4.20, the EMDP will guide the preparation of separate and free-standing Ethnic Minorities Action Plans (EMAP) as appropriate to meet the needs of the Bank s policy on Indigenous Peoples. C. ENVIRONMENTAL ASPECTS 1. Potential Negative Impacts and Safeguard Policies Road maintenance operations may potentially affect the environment in a number of ways. For example, environmental concerns can stem initially from poor road design and planning, mobilization of construction crews, construction camp maintenance, storage and handling of wastes and hazardous materials, location of borrow pits and quarry sites, associated earthworks, and drainage design. Poorly executed maintenance activities may create localized soil erosion problems affecting streams or other water bodies; lack of clear plans for environmental management will create opportunities for inappropriate disposal of solid waste materials and could lead to lack of controls of noise and dust which can create a nuisance for individuals and communities. Better maintained roads could lead to increased accessibility in remote areas thus increasing the potential for uncontrolled resource extraction and land conversion along the road sides. Concern over such issues are heightened in areas where roads pass through protected areas or other sites of a sensitive ecological nature such as wetlands, streams or forest areas. The alternative to road maintenance program is basically a no maintenance approach. This scenario also has adverse environmental implications. Lack of maintenance could generate unstable road bed conditions leading to localized erosion and drainage problems. In areas of high rainfall and geologic instability, these risks can be substantial. Road maintenance programs also provide an opportunity to address some basic design problems which can create drainage and erosion problems. 1.1 Environmental Category and Justification The RMP-2 is an expansion of the RMP1 and no new major environmental issues are anticipated. RMP1 experience has suggested that most of the potential impacts during maintenance works will N:\LAO PDR\RMP2\Env and social\sea\appendix 1 sea part A\Final Safeguards Policies (updated) June5.doc 3

4 be localized, temporary, and can be mitigated through the application of the EGRP and the RCG adopted in the RMP-1. The maintenance program will be on the existing roads and the incremental induced effects will be minimal. No new road construction will be undertaken under RMP-2 and the ESSD screening framework (Section C) will ensure that appropriate actions will be undertaken for the subprojects involving sensitive areas, land acquisition, or indigenous people. 1.2 Safeguards Arrangements under RMP-2 Based on the Strategic Environmental Assessment (SEA), maintenance activities to be funded under the project will be screened using the screening criteria specified in the ESSF by the subproject proponent in close consultation with DOR s environmental management unit (ESD). This is to ensure that the proposed maintenance activities will have no adverse effect on a number of environmental (and social) areas of concern such as protected areas or other sensitive sites which fall outside of protected status. To ensure appropriate safeguard measures are put in place, the EGRP (1999) has been updated (see Attachment 3) to facilitate effective application of the guidelines. Due consideration was given to improve consultation and information disclosure, ensure close supervision and monitoring of the contractor s performance, and address the impacts after maintenance operations. Specific guidelines and/or manuals, including monitoring/reporting requirements and specific criteria for maintenance operations in sensitive areas (ecologically and socially), will be developed. Training on safeguard operations for central and provincial staff and contractors will also be provided, This includes increasing awareness and capacity building for senior management. Results of the safeguard screening and application of the guidelines and frameworks will be included in the semi-annual report. The EGRP during the construction phase will form the basis of contractual obligations to be carried out by road maintenance crews. Contracts for maintenance will include specific clauses for environmental protection based on the guidelines. Supervision and monitoring of environmental performance will be carried out in the field by the project supervising engineer with assistance from ESD. Periodic audits will also be carried out during regular Bank supervision missions. The ESD of DOR will also prepare periodic (semi-annual) reports on the adherence to environmental measures under the project. 2. Institutional Capacity for Environmental Safeguards MCTPC recognizes the importance of environmental protection and has made basic commitments to addressing environmental concerns. In 2001, an Environmental and Social Division (ESD) was formally created in DOR to assist with project screening and to evaluate environmental risks of proposed projects. In 2003, a ministerial regulation on EA procedure was established and ESD is currently developing guidelines and procedures to facilitate effective execution of this regulation. Technical assistance has been provided to ESD and the national environmental agency (STEA) in the preparation of the guidelines related to the EIA process, including consultation and training. At national level, the Government is currently processing enactment of the Resettlement and Compensation Guidelines, including a policy to address issues related to ethnic minorities, to be part of the body of national regulations. Capacity enhancement at local level on the environmental and social safeguards work in all 17 provinces represents a substantial challenge in the new phase of the RPM2 program. There is also need to ensure that the environmental and social requirements are fully integrated into DOR s operational procedures. It is the responsibility of MCTPC (not only ESD) to ensure effective implementation of potential negative impacts at all stages (planning and pre-construction, N:\LAO PDR\RMP2\Env and social\sea\appendix 1 sea part A\Final Safeguards Policies (updated) June5.doc 4

5 construction, operations). To ensure effective implementation of safeguards for RMP-2, technical assistance will be provided to ESD and DCTPC to strengthen: (i) supervision and monitoring of safeguard compliance; (ii) consultation with local communities and authorities; (iii) mainstreaming of safeguards into DOR operations, and (iv) knowledge related to construction resource mapping, community inventory in the road right-of-way, and related social activities. 3. Public disclosure The updated Safeguard Policies as well as the SEA report will be disclosed (both in English and Laos) to the public in Vientiene (at MCTPC s office and the World Bank office) as well as in MCTCP s provincial offices (i.e. DTCPC offices) by June 14, D. ENVIRONMENTAL AND SOCIAL SAFEGUARDS FRAMEWORK (ESSF) Objectives. The ESSF aims to ensure that (a) the Project activities do not create or result in serious adverse impacts on the local community and environment, (b) the mitigation plan is carried out effectively, and (c) possible complaints from the local government authorities and community are minimized. The ESSF has been developed based on the lessons learned during supervision of RMP1 and it may be modified or revised when necessary with close consultation with the Bank. Strategies. To achieve these objectives, the following actions will be undertaken: All proposed subprojects will be screened by ESD through the screening process described below and the results will be documented and properly kept for review by the Bank. Appropriate mitigation measures will be included in the bidding document (BD) and contract document (CD); compliance with these measures will be monitored, and the results will be documented and properly kept for review by the Bank. ESD will supervise and monitor the overall activities and prepare a semi-annual report on the application of the EGRP and RCG guidelines and other frameworks and action plans during the planning, design, and construction phase of the project. ESD will also develop the reporting requirements and procedures to ensure compliance of the contractors; conduct public consultation and public awareness programs, and carry out periodic training for field engineers and contractors as appropriate. A semi-annual report on the implementation of the guidelines will be submitted to the Bank. Assumptions. The screening is based on the assumptions described below. If this is not the case, the Bank will be informed and consulted. The main civil works to be carried out under RMP2 will be limited to activities typically defined as routine and periodic maintenance (resurfacing and bridge repairs; flood repairs or emergency maintenance; regular upkeep of safety features and road signs, etc.) and small rehabilitation works to strengthen the road, repair structural defects, restore the road to its initial condition, make small changes or improvements to alignment, and small construction of drainage and footpaths. If large-scale rehabilitation works are involved, DOR will inform the Bank before proceeding with the contract. The works will be carried out within the existing right of way (ROW) and will not involve relocation and land acquisition. If land acquisition and relocation is needed, the Bank will be informed, and the Resettlement and Compensation Guidelines (RCG) will be applied. N:\LAO PDR\RMP2\Env and social\sea\appendix 1 sea part A\Final Safeguards Policies (updated) June5.doc 5

6 The project-related impacts are site specific; few of the effects are irreversible; and appropriate mitigation measures can be developed and implemented by the contractors and MCTPC. Screening procedures. The screening process is not intended to prohibit DOR from carrying out maintenance-related works in sensitive areas but is meant to ensure that proper mitigation measures are prepared and carried out effectively to avoid adverse impacts on the affected population, natural environment and cultural heritage. If the subproject is located in or near protected areas or other critical habitats or cultural property, an Initial Environmental Examination (IEE) for the subproject will be prepared and carried out in close cooperation with ESD and other concerned agencies and in consultation with the Bank. The civil works contracts for office building and construction of weigh stations will also be subject to this screening. The ESSF will be conducted by the subproject administrator (RAD, LAD, DTCPC, etc.) during the screening and preparation of the Annual Work Plan (AWP). Steps and actions for the screening are presented in Table 1. Key steps of the ESSF is shown in Figure 1. Table 1. Screening Process for Each Subproject Screening check list Yes Actions to be undertaken Involves land acquisition, relocation, indirect loss of access and assets, and has adverse impacts on ethnic minorities Scale of the civil works is larger than those identified for maintenance or involves new construction The project site is located near villages, residential, or other sensitive areas (schools and hospitals) and dust and road safety issues will significantly affect the human health/life Y Y Y Planning/Project engineer will consult ESD and apply RCG, EMDP. If the impacts are significant, ESD seeks Bank clearance before selection of the subproject. Extensive consultation with affected population is expected during the planning and implementation Consult ESD to apply appropriate guidelines. If the impacts are significant, ESD seeks Bank clearance before selection of the subproject. If new road construction is required, EA study will be required and Bank clearance will be necessary Planning/Project engineer will consult ESD and include appropriate mitigation measures during planning and design stages. DOR and ESD will establish criteria and technology appropriate for dust suppression in the sensitive areas. {preparation of action plan to mitigate impacts and consultation with local authority and communities will be necessary). Periodic monitoring of air quality, noise level, and opinions of local authority/community may be necessary. The issues and actions will be included in the EMP and recorded in the progress N:\LAO PDR\RMP2\Env and social\sea\appendix 1 sea part A\Final Safeguards Policies (updated) June5.doc 6

7 Screening check list Yes Actions to be undertaken report and/or the semi-annual report. The project site is located in or less than 50 m away from protected areas, areas of cultural heritages; or involves the use of large amounts of toxic chemicals or herbicides. Large amount of materials will be needed Fully comply with the assumptions specified above and a contractor will be hired to carry out the works *If No go to next step Y Y Y Planning/Project engineer will consult ESD to ensure that the mitigation measures are adequate to address the issues. Use of borrow pits and quarry sites and operation of asphalt plants in the sensitive areas must be prohibited. Specific requirements may be required to minimize the potential impacts. A standard clause should be included in all construction contract regarding the procedures to be followed in the event culturally significant sites are found. Planning/Design engineer will consult ESD with respect to locations and practices of material excavation. MCTPC (subproject administrator) prepares an action plan to mitigate potential impacts of the subproject in line with the EGRP and disclose the plan to the public (consultation with local authority and local community is encouraged). Endorsement of ESD will be necessary. MCTPC includes the environmental requirements in the bidding/contract document and ensures compliance of the contractors during the bidding process. Field engineers will closely monitor the contractor performance and document it in the supervision/progress report. Recommendations that are useful to increase efficiency and effectiveness of the mitigation plan should be provided. ESD will periodically review the supervision report, periodically inspect the contractor performance, conduct public consultation, and prepare a semi annual report to send to the Bank. N:\LAO PDR\RMP2\Env and social\sea\appendix 1 sea part A\Final Safeguards Policies (updated) June5.doc 7

8 Attachment 1. RESETTLEMENT AND COMPENSATION GUIDELINES (RCG) FOR RMP-2 PART I. INTRODUCTION 1. Background 1.1 Development projects, even when undertaken in the public interest, have social impacts and associated costs on individual persons, communities, and the environment. Said adverse social impacts may be any or a combination of the following: loss of abode, loss of fixed assets, loss of income and/or employment, displacement, separation of family members, disintegration of communities, etc. These impacts may be marginal or severe and/or irreparable. Yet, these adverse social impacts are often borne by projectaffected persons (APs) not by their own wish but involuntarily. 1.2 The resettlement efforts to mitigate adverse social impacts of development projects need to be carried out within an overall legal framework following clearly defined resettlement principles and operational procedures. Additionally, the Lao PDR's policy on poverty reduction needs to be integrated into resettlement efforts, with special attention to vulnerable groups. In view of the Government's efforts to give impetus to its development efforts and to deal with adverse social impacts and implementation problems, there is an urgent need for a national policy on involuntary resettlement and compensation with an aim to: (i) integrate social dimensions in development projects, (ii) address measures to mitigate adverse social impacts with a particular focus on vulnerable groups, and (iii) have a comprehensive approach to address social issues. 1.3 Although land acquisition and relocation are not expected in the Road Maintenance Program (RMP), as a safeguard measure, a Resettlement and Compensation Guidelines (RCG) was prepared and applied successfully in RMP-1. The RCG will be applied in RMP-2 and is considered as an integral part of the Environmental and Social Safeguards Framework (ESSF). 2. Definitions 2.1 Definitions of key terms are provided as follows: a) Compensation. Compensation means payment in cash or in kind for an asset to be acquired or affected. by a project at replacement cost. b) Cut-off Date. 'Cut-off date' is the date prior to which the occupation or use of the project area makes residents/users of the project area eligible to be categorized as affected persons. In many projects, the cut-off date coincides with the commencement of the census of affected persons within the project area

9 boundaries. Persons not covered in the census are not eligible for compensation and other entitlements. c) Entitlements. Range of measures comprising compensation, income rehabilitation assistance, transfer assistance, income substitution, and relocation, which are due to, affected people, depending on the type and degree of their losses. to restore their economic and social base. d) Implementing Agency (or Project Proponent/Project Authority/Executing Agency) is the divisions/offices/units of the Ministry of Communication, Transportation, Post and Construction (MCTPC) who is responsible for planning, design and implementation of a development project. e) Land Acquisition means the process whereby a person is compelled by a public agency to alienate all or part of the land a person owns or possesses, to the ownership and possession of that agency, for a public purpose in return for compensation. f) Project Affected Person (PAP/AP) includes any person or persons, household (sometimes referred to as project affected family), a firm, or a private or public institution who, in the context of acquisition, or repossession, of assets or change in land use, as of the cut-off date, on account of the execution of a development project, or any of its subcomponents or part, would have their: i) Standard of living adversely affected; ii) Right, title or interest in all or any part of a house, land (including residential, commercial, agricultural, plantations, forest and grazing land) or any other moveable or fixed assets acquired or possessed, in full or in part, permanently or temporarily adversely affected: or iii) Business, occupation, place of work, residence, habitat or access to forest or community resources adversely affected, with or without displacement. AP means persons or affected household and consists of all members of a household residing under one roof and operating as a single economic unit, who are adversely affected by a project or any of its components. For resettlement purposes, affected persons will be considered as members of affected households. g) Rehabilitation means assistance provided to APs seriously affected due to the loss of productive assets, incomes, employment or sources of living, to supplement payment of compensation for acquired assets in order to improve, or at least achieve full restoration of living standards and quality of life to preproject level. h) Relocation means the physical shifting of an AP from his/her pre-project place of residence, place of work or business premises.

10 i) Replacement Cost is the amount needed to replace an asset and is the value determined, as compensation for Agricultural and the pre-project or pre-displacement, whichever is higher, market value of land of equal productive potential or use located in the vicinity of the affected land, plus the cost of preparing the land to levels similar to those of the affected land, plus the cost of any registration and transfer taxes; ii) Land in urban areas, it is the pre-displacement market value of land of equal size and use, with similar or improved public infrastructure facilities and services and located in the vicinity of the affected land, plus the cost of any registration and transfer taxes, iii) Houses and other related structures based on current market prices of materials, transportation of material to construction site, cost of labor and contractor's fee, and cost of any registration and transfer taxes. In determining replacement cost, depreciation of the assets and value of salvaged building materials are not taken into account and no deductions are made for the value of benefits to be derived from the project, iv) Crops, trees and other perennials based on current market value; and v) Other assets (i.e. income, cultural, aesthetic) based on replacement cost or cost of mitigating measures. j) Resettlement refers to all measures taken by the Project Proponent to mitigate any and all adverse social impacts of a project on the APs, including compensation for lost assets and incomes and the provision of other entitlements, income restoration assistance, and relocation, as needed. k) Social Assessment (SA) or Social Impact Assessment (SIA). SA or SIA is a framework for incorporating social analysis and participatory process in project design and implementation. l) Vulnerable groups. These are distinct groups of people who might suffer disproportionately or face the risk of being marginalized from the effects of resettlement and specifically include: (i) female headed households with dependents, (ii) disabled household heads, (iii) households falling under the generally accepted indicator for poverty, (iv) elderly households with no means of support and landlessness, (v) households without security of tenure, and (vi) ethnic minorities.

11 PART II. SCOPE, ELIGIBILITY & LEGAL FRAMEWORK 3. Scope of the Policy The Policy would be applicable to all development projects carried out by public and private sector, regardless of funding sources, resulting in acquisition, of land and/or other assets, change in land use and restriction on access to community resources affecting community livelihood and income sources. 4. Eligibility. All people residing, cultivating or making a living within the area to be acquired for a project as of the formally recognized cut-off date should be considered as project affected persons (APs) for purposes of entitlements to compensation, resettlement and rehabilitation assistance in accordance with the policy, and lack of legal title to the land or structure affected by project should not bar any person for such entitlements/assistance. 5. Legal Framework. The Policy is based on the following laws and decrees that provides legal framework for resettlement: The Constitution of the Lao PDR The Land Law No. 01/97 SPS, dated 12 April The Forestry Law No. 01/96, dated 11 October The Water and Water Resources Law No. 02/96, dated 11 October The Environmental Protection Law No. 02/99 SPS, dated 3 April The Electricity Law No. 02/97 SPS, dated 12 April The Road Law No. 04/99 SPS, dated 03 April The Mineral Resources Law (April 1997). The Town Planning Law No. 03/99 SPS, dated 03 April Regulation 1266/95 of MCTPC on Valuation of Vehicles, Houses, Built Structures and Household Facilities for Government Employees and Personnel PART III OBJECTIVES 6. Objectives The objectives of the Policy include the following: Projects are designed so that resettlement is avoided or, if unavoidable, minimized by examining all design options available to the project and the losses incurred by affected people are redressed such that APs share project benefits, assisted to develop their economic, social and cultural potential in order to improve or at least restore their incomes and living standards to preproject levels and are not worse off than they would have been without the project.

12 Attention is paid to affected ethnic minority and other vulnerable groups, especially the poor, in order to enhance their future prospects and for poverty alleviation. The entire resettlement process is carried out through a meaningful involvement of project affected communities, and their existing social and cultural institutions are supported to the greatest extent feasible. Resettlement is envisioned and carried out as an integral part of the development project. PART IV. COMPENSATION AND ENTITLEMENTS. 7. Compensation Principles 7.1 APs will be provided with compensation for their lost assets affected in full or in part, at full replacement cost. 7.2 Where significantly large or entire land holding affected by a project, the general mechanism for compensation for affected agriculture, residential or commercial land will be through provision of "land for land" arrangements of equivalent size and productivity and at location acceptable to the AP. In case suitable land is not available, and at informed request of the AP cash compensation at current market value will be provided in addition to the assistance for relocation. However, when the portion of the land to be lost represents 20% or less of the total area of the landholding with remaining area viable for continued use, where the livelihood is not land-based, cash compensation a t full replacement value for the affected portion will be provided. In cases where only part of the land holding is affected but the remaining land becomes economically unviable, the AP will be entitled to surrender the entire holding and to compensation for entire holding at full replacement value, or land-for-land option. 7.3 If the house or structure is only partially being affected by the Project and the remaining structure is rendered unviable or in area less than the minimum house size under the prevailing standards, the AP will be entitled to surrender the entire structure and to compensation for the entire structure at full replacement cost without depreciation or deductions for salvaged material. 7.4 In case of APs affected by partial loss of structures and the remaining structures are viable for continued use, they will be entitled to assistance in cash or material for restoration of the remaining structure in addition to the compensation at replacement cost for affected portion. 7.5 APs whose land or assets are temporarily taken by the works under the project will be fully compensated for their net loss of income, damaged assets, crops and trees, as the case may be. Assets which are only temporarily affected or inoperable, will be compensated at 10% of the replacement cost of affected assets provided that such assets or properties are required by the project for a maximum of 6 months. In case the assets are required by the project for periods longer than six months, the amount of

13 compensation should be negotiated with the owner of said property, and the project shall insure that the land and structures are returned in its pre-project state. 7.6 Tenants, who have leased a house / structures for residential or other purposes and affected by the project, will be provided with a cash assistance equivalent to three months M1 allowance and, expenses to cover for other losses, and will be assisted in finding aiterne6 rental accommodation. 7.7 APs without any legal title or ownership right to the affected land and assets they occupy should be compensated for their lost assets at replacement cost. If needed such APs wig b provided additional assistance to ensure that they are able to improve their household income levels and are not worse-off due to the project. 7.8 All previous claims and unresolved issues related to tenure status and ownership of land art other assets on each sub-project or components will be resolved prior to initiating any new fart acquisition measures on the respective sub-project or component. 8. Other Assistance During Relocation and Transition Period 8.1 APs displaced and severely affected due to the loss of incomes and means of livelihood would be provided with a food allowance and suitable development assistance after displacement during the transition period until they are able to restore their incomes a livelihood standards or reach the targeted level of household incomes on a sustainable basis. 8.2 All displaced persons will be given a transport allowance or a assisted in transfer to the resettlement site or their choice of relocation, as the case may be. 8.3 In the case of loss of business, APs will be provided with a special allowance for the loss pf business-income during the transition period. 9. Economic Rehabilitation 9.1 All APs severely affected by the project due to the loss of productive assets (agricultural. commercial or industrial land), means of livelihood, incomes, employment or businesses, and access to community resources will be entitled to rehabilitation measures including income restoration programs, training to improve skills and other assistance for self-employment over and above their entitlements for compensation and other allowances, enabling them to attain, at a minimum, pre-project livelihood levels on sustainable basis. 9.2 These rehabilitation measures would specifically focus on vulnerable groups such as households without tenure security o r with weak tenure status, female-headed households, disabled-headed households, itinerant workers, households falling below the national poverty line or those severely affected by the project and are likely to fall below the poverty line, elderly households with no means of support and landless households.

14 Adequate assistance, in addition to compensation for affected assets and other allowances, should be provided such that t heir economic and social w ell-being c an b e improved and to enable such A Ps achieve household income targets set above the national poverty line. At least 30% of such rehabilitation assistance measures will be reserved for women. 9.3 For displaced persons whose land-based livelihood are affected due to the project, preference should be given to land-based resettlement strategies, or where land is not available, non-land-based options built around opportunities for employment or self employment in addition to cash compensation for lost assets. 10. Community Services and Resources 10.1 In cases community facilities and infrastructure such as schools, factories, water resources, roads, sewage system or electrical supply is damaged due to the project, the project developers will ensure that these would be restored or repaired as the case may be, at no cost to the community Any acquisition of, or restriction on access to resources owned or managed by affected community as a common property should be mitigated by arrangements ensuring access to improved or at least equivalent resources on a continuing basis, 11. Local Culture & Practices 11.1 Local cultural and religious properties, practices and beliefs should be respected and to the extent possible preserved Where local communities elect to make voluntary contribution of affected land without compensation in accordance with traditions practices, this should be acceptable only for marginal impacts (partial impact on land without causing any displacement or impact on structures, and with remaining assets viable for continued use) and only when direct benefits to affected people can be assured. The process of consultation with APs should, be conducted in an open and transparent manner by district officials of MCTPC and decisions for 'voluntary' contribution should be based on 'informed choice' of affected people. People who elect to make voluntary contributions must be informed of their rights to compensation, and the process and decisions must be documented by the provincial DCTPC. 12. Ethnic Group Issues 12.1 Where in a project cultural minorities are affected, the mitigation measures and social and economic benefits they receive to improve their status would be in harmony with their cultural preferences and would be decided in consultation with affected communities. The mitigation measures and assistance should also include institutions strengthening and capacity building of tribal elders, and community groups working on resettlement activities.

15 12.2 Community participation and consultation framework and grievance redress mechanism for ethnic minority groups should be developed in culturally appropriate ways, familiar to the affected community, in consultation with their leader-"s and in close collaboration with local officials. 13. Resettlement Linked to Project Resettlement transition period should be minimized and the acquisition of assets, compensation payment in full, resettlement and rehabilitation activities for a segment/section or phase (except where long-term rehabilitation measures such as vocations training or other measures recommended) should be completed prior to the initiation of construction work under the respective segment/section or phase thereof. PART V. RESETTLEMENT SITE DEVELOPMENT 14. Resettlement Site Development 14.1 All relocating persons should be provided with suitable housing or developed houselots, shop-lots as necessary, agricultural sites of sufficient size with productive potential and locations advantages better or at least equivalent to the old site. Replacement agricultural land, house/business plot will be as close as possible to the land that was lost and/or acceptable to the APs The replacement land for residential resettlement will be provided in fixed plot sizes according to the prevailing standards and planning practices. However, if the lost land of AP is in size larger than the plot sizes for relocation, a cash compensation to cover the difference of the area will be given to the AP All replacement land for agriculture, residential and businesses will be provided with secured tenure status and without any additional cost, sales taxes, fee, and surcharge to the APs at the time of transfer. Land titles for replacement land shall be issued in the joint names of husband and wife Attention should be paid to ensure that resettlement site development does not cause any adverse environmental impacts to the surrounding areas. All resettlement sites for relocation of displaced persons will be provided with adequate access to public facilities and services, income earning opportunities and market Where relocation is considered necessary, the 'host' community would also be entitled to compensation and other assistance similar to the project affected persons. Infrastructure and public services provided to the host community as necessary to improve, restore, or maintain accessibility would be the same level as provided for the displaced persons.

16 PART VI PUBLIC PARTICIPATION & CONSULTATION 15. Public Participation and Consultation The resettlement process should be carried out in a participatory manner, in which stakeholder concerns are taken into account at all stages of the project cycle, particularly during the planning and implementation phases of land acquisition, valuation and resettlement process. APs should be fully informed of the provisions of the policy, their entitlements to compensation for their lost assets, allowances and other assistance as provided for in the Policy. 16. Grievance Redress Mechanism 16.1 There should be effective mechanisms in place for hearing and grievance redress during the resettlement planning and implementation in a project The GoL PDR at the request of the Project authorities will establish a Grievance Redress Committee (GRC) for each district to address complaints and grievances pertaining to land acquisition, compensation and resettlement and to pre-empt all disagreements being referred to courts. The committee will consist of: i) District official ii) Village heads iii) Representative of the APs, other than the village head; iv) Village elders or representatives of MO; v) Project official Grievances related to any aspect of the project or sub-project will be handled through consultations conducted in a transparent manner and aimed at resolving matters through consensus at the project level before complainants forward these to higher level and ultimately to the court of law. The Project Authorities will document all complaints received in writing (or written when received verbally) from the APs APs will be exempted from all administrative and legal fees incurred i n pursuant t o the grievance redress procedures including cases of complaints taken to the court of law. PART VII. REPORTING-AND DOCUMENTATIONIT. 17. Reporting and Documentation The Project Proponents would carry out necessary studies and field investigations and prepare following required reports and documents for submission to the respective ministry and the Regulatory Agency for review and approval Initial Social Assessment (ISA) and Land Acquisition Assessment Project Proponents will carry out necessary field investigations for ISA, either as part of the IEE or as a standalone exercise, in order to identify relevant social issues, likely

17 impacts and the types of groups of people likely to be affected by the project. The report on ISA should be submitted by project proponents to the relevant ministry (in the case of private sector developer) and to the Regulatory Agency for review and approval prior to proceeding for further studies Social (Impact) Assessment In major projects with likely indirect and economic impacts on communities, within or in the vicinity of project areas, project proponents will conduct social assessment at the prefeasibility or feasibility stage of the project-preparation, as the case maybe, to address indirect social and economic impacts using appropriate mitigation measures with special attention paid to vulnerable groups, including ethnic minority groups. The report on social assessment should be prepared by Project Proponents for submission to the Regulatory Agency and the World Bank for review and approval to facilitate project process Resettlement Plans Land Acquisition and Compensation Report In case the impacts of the project are mostly marginal such that less than 200 persons (about families) are affected by the project either marginally or with limited displacement, a Land Acquisition and Compensation Report for each project, sub-project, or component will be prepared by Project Proponents and submitted to the Regulatory Agency and the World Bank for review and approval. Compensation, resettlement and rehabilitation activities will only commence after the Report is found acceptable to the Regulatory Agency and the World Bank Resettlement Action Plans (RAPs) In case the impacts of the project are severe, regardless of number of affected people or where more than 200 people (40-50 families) are affected by the Project, its component or sub-project; a Resettlement Action Plan (RAP) for each component or sub-project will be prepared in accordance with the provisions of this Policy. Project proponents will submit the required RAP to the World Bank for review and approval. Compensation, resettlement and rehabilitation activities will only commence after the Report is found acceptable to the Regulatory Agency and the World Bank Ethnic Minority Development Plans (EMDPs) a. Where in a project any ethnic minority groups are affected, particular attention should be paid to collect additional information focusing upon household ownership of economic and productive assets; economic information of community (e.g., brief information on economic and natural resources, production and livelihood systems, tenure systems); social information of community (e.g.. brief description of kinship, value system, types of social organizations of formal/informal groups, farming groups, etc.), especially those that can help the group in adjusting to potential impacts from the project; and potential impact of sub-project on the social and economic livelihood. The Resettlement Action Plans should include a separate section to address ethnic minority issues and suggested actions to ensure that the social and economic benefits they receive are in harmony with their cultural preferences.

18 b. Where the impacts on ethnic minority are likely to be significant, a standalone Ethnic Minority Development Action Plan (EMAP) will be prepared in line with the Ethnic Minorities Development Policy (EMDP) which has been developed for RMP-2. The EMAP will be submitted for approval by the World Bank. The description of resettlement measures and the types of development assistance proposed will ensure that the social and economic benefits proposed will be in harmony with their cultural preferences. PART VIII. MONITORING, SUPERVISION & EVALUATION 18. Resettlement Monitoring and Supervision 18.1 Adequate arrangements should be made for effective and timely supervision and internal monitoring of the implementation of the resettlement and rehabilitation measures In projects with major resettlement component, an experienced and independent external monitoring agency would be contracted by project authorities to periodically carry out external monitoring of the implementation of resettlement activities in accordance with the Resettlement Action Plans. Mechanisms should be put in place to involve the affected community in monitoring of resettlement implementation activities. The External Monitoring Agency will submit monitoring reports to the project authorities regularly. MCTPC will regularly provide a copy of the external monitoring reports to the Regulatory Agency and the World Bank In projects with major resettlement component, project authorities will make provision for post-evaluation of resettlement implementation activities, six months to one year after the completion of economic rehabilitation measures in the project, to check whether the economic rehabilitation objectives of the Policy and the Resettlement Action Plans have been achieved. If the evaluation indicates that the APs have not been able to achieve the stated objectives and income targets, project authorities will make arrangements for provision o f additional assistance to meet the stated objectives. PART IX. RESETTLEMENT COST AND BUDGETS 19. Resettlement Cost and Budget Each Resettlement Action Plan will include detailed cost estimates for compensation and other resettlement entitlements and relocation of APs, if that be the case, with a breakdown by category of APs; agricultural, residential and business land; houses, structures and other fixed assets affected; rehabilitation assistance, transport and other allowances; monitoring and evaluation; management and administration; phases of the project and by financial year. The cost estimates will make adequate provisions for contingencies.

19 Ethnic Minorities Development Policy Framework (EMDP) for RMP-2 World Bank Policy OP 4.0 Purpose is to ensure that indigenous people benefit from development projects, and (b) avoid or mitigate potentially adverse effects on indigenous people caused by Bank-assisted activities. The Bank's policy is that the strategy for addressing the issues pertaining to indigenous peoples must be based on the informed participation of the indigenous people themselves. The key step in project design is the preparation of a culturally appropriate development plan based on full consideration of the options preferred by the indigenous people affected by the project Remote or neglected areas where little previous experience is available often require additional research and pilot programs to fine-tune development proposals. As needed, the plan should include general education and training in management skills for indigenous people from the onset of the project. Studies should make all efforts to anticipate adverse trends likely to be induced by the project and develop the means to avoid or mitigate harm. The institutions responsible for government interaction with indigenous peoples should possess the social, technical, and legal skills needed for carrying out the proposed development activities. Implementation arrangements should be kept simple. They should normally involve RMP-2 Project Policy Framework All sub-projects located in areas that contain ethnic minority groups will identify the representatives of such minority groups and consult with them whether the subproject has the potential to provide benefits or adversely affect these groups If potential positive and negative effects are identified, the sub project will inform local communities of the nature of the subproject and record and incorporate into the design of the subproject the communities wishes in relation to obtaining benefits from the project and avoiding or mitigating any adverse impacts. If the project area is located in a very remote area where indigenous communities have restricted links with local government, the project manager will request the assistance of the ESD to manage the community consultation and participation process The project manager will distribute information and awareness raising material packages produced by ESD in relation to the potential impacts of the project on the well being of the community. These materials should preferably be in the language of the ethnic community The project manager will refer to the EMP for the project and associated guidelines and use this information to identify any potential adverse impacts arising from the project. This information will be included in the monitoring reports and be available for review. A national consultant will be appointed to the ESD with experience in social impact assessment and community participation to assist in monitoring subprojects and identify actions necessary for the subprojects in mitigating adverse impacts. The consultant will prepare regular reports on these

20 appropriate existing institutions, local organizations, and nongovernmental organizations (NGOs) with expertise in matters relating to indigenous peoples. Local patterns of social organization, religious beliefs, and resource use should be taken into account in the plan's design. Development activities should support production systems that are well adapted to the needs and environment of indigenous peoples, and should help production systems under stress to attain sustainable levels. Planning should encourage early handover of project management to local people. Where effective programs are already functioning, Bank support can take the form of incremental funding to strengthen them rather than the development of entirely new programs. For an investment project that affects indigenous peoples, the borrower should prepare an indigenous peoples development plan that is consistent with the Bank's policy. activities. The consultant will also be required to identify possible subprojects where a standalone Ethnic Minorities Development Plan may be required in view of serious impacts. The project manager of all environmentally and socially sensitive subprojects will coordinate with representatives of local communities to identify areas that are important in terms of providing livelihoods or are of socio-cultural and religious significance. The project manager will ensure that such areas are protected, and where necessary, will negotiate compensation for damage or reduced access to such areas. Where a subproject has the potential to influence or change the system of livelihood of an ethnic minority community, the project manager will coordinate with representatives of local communities to identify alternative sustainable production systems that are well adapted to the needs and environment of ethnic minority peoples. On completion of subprojects, they will be handed over to provincial authorities who will monitor the impacts of the project on ethnic minority peoples. The ESD will compile all monitoring reports and lobby donors and other funding agencies to support projects that mitigate the longer-term indirect impacts of improved access. When a subproject has the potential to seriously affect the livelihood or interests of ethnic minority communities, ESD in consultation with the World Bank may deem it necessary for the subproject to prepare an Ethnic Minorities Development Plan. The plan will be prepared according to guidelines*specified in the Bank s OD 4.20 on Indigenous People

Performance Standard 8:

Performance Standard 8: Overview of Performance Standards on Environmental and Social Sustainability 1. IFC s Sustainability Framework articulates the Corporation s strategic commitment to sustainable development, and is an integral

More information

V-1 Reference Material for Social Analysis

V-1 Reference Material for Social Analysis Manual for PIP Project Management (Version 3.0, August 2010) Section V Technical Approached in PIP Management Manual for PIP Project Management Section V Technical Approaches in PIP Management Section

More information

PR 5: Land Acquisition, Involuntary Resettlement and Economic Displacement

PR 5: Land Acquisition, Involuntary Resettlement and Economic Displacement 34 Environmental and Social Policy PR 5: Land Acquisition, Involuntary Resettlement and Economic Displacement Introduction 1. Involuntary resettlement refers both to physical displacement (relocation or

More information

Environmental & Social Assessment Procedures Basics

Environmental & Social Assessment Procedures Basics African Development Bank Group Environmental & Social Assessment Procedures Basics For public sector operations Compliance & Safeguards Division (ORQR.3) safeguards@afdb.org AFRICAN DEVELOPMENT BANK GROUP

More information

JAMAICA SOCIAL INVESTMENT FUND LAND ACQUISITION AND RESETTLEMENT POLICY FRAMEWORK

JAMAICA SOCIAL INVESTMENT FUND LAND ACQUISITION AND RESETTLEMENT POLICY FRAMEWORK Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized JAMAICA SOCIAL INVESTMENT FUND LAND ACQUISITION AND RESETTLEMENT POLICY FRAMEWORK I.

More information

Resettlement Policy Framework

Resettlement Policy Framework Wuhan Intelligent Transportation Demonstration Project, a subproject of the World Bank-funded Wuhan Urban Circle Transportation Integration Demonstration Project Resettlement Policy Framework Wuhan Municipal

More information

EBRD Performance Requirement 7

EBRD Performance Requirement 7 EBRD Performance Requirement 7 Indigenous Peoples Introduction 1. This Performance Requirement (PR) recognises that projects can create opportunities for Indigenous Peoples to participate in and benefit

More information

COMPONENT 2 - TKB DRAFT

COMPONENT 2 - TKB DRAFT 2015 Resettlement Policy Framework for the Turkey Geothermal Development Project COMPONENT 2 - TKB DRAFT Contents 1. Project Description & Background... 2 2. Principles & Objectives... 3 3. Process for

More information

Semi Annual Environmental Monitoring Report. July 2013 L2557/2558. SRI: Greater Colombo Wastewater Management Project

Semi Annual Environmental Monitoring Report. July 2013 L2557/2558. SRI: Greater Colombo Wastewater Management Project Semi Annual Environmental Monitoring Report July 2013 L2557/2558 SRI: Greater Colombo Wastewater Management Project This environmental monitoring report is a document of the borrower. The views expressed

More information

Environmental Assessment

Environmental Assessment OP 4.01 Page 1 of 5 Environmental Assessment Note: OP 4.01 replaces the policy elements of IFC s Environmental Analysis and Review of International Finance Corporation Projects (Washington, D.C.: IFC,

More information

VIE: Second Upper Secondary Education Development Project (USEDP II) - Ha Giang Province

VIE: Second Upper Secondary Education Development Project (USEDP II) - Ha Giang Province Due Diligence Report November 2014 VIE: Second Upper Secondary Education Development Project (USEDP II) - Ha Giang Province Quyet Tien Upper Secondary School Prepared by the Ministry of Education and Training,

More information

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized I. Basic Information Date prepared/updated: 03/11/2008 INTEGRATED SAFEGUARDS DATASHEET

More information

INDONESIA - LAW ON WATER RESOURCES,

INDONESIA - LAW ON WATER RESOURCES, Environment and Development Journal Law LEAD INDONESIA - LAW ON WATER RESOURCES, 2004 VOLUME 2/1 LEAD Journal (Law, Environment and Development Journal) is a peer-reviewed academic publication based in

More information

NEWMONT GHANA GOLD LTD. AHAFO SOUTH PROJECT COMPLETION AUDIT TERMS OF REFERENCE RESETTLEMENT ACTION PLAN

NEWMONT GHANA GOLD LTD. AHAFO SOUTH PROJECT COMPLETION AUDIT TERMS OF REFERENCE RESETTLEMENT ACTION PLAN NEWMONT GHANA GOLD LTD. AHAFO SOUTH PROJECT COMPLETION AUDIT TERMS OF REFERENCE RESETTLEMENT ACTION PLAN November 2009 BACKGROUND Newmont Ghana Gold Ltd. (NGGL) has developed gold reserves at the Ahafo

More information

Operational Directive

Operational Directive Page 1 of 9 Involuntary Resettlement Introduction 1. This directive describes Bank 1 policy and procedures on involuntary resettlement, as well as the conditions that borrowers are expected to meet in

More information

No. 132. Land Use and Building Act (132/1999, amendment 222/2003 included) Chapter 1. General provisions. Section 1 General objective of the Act

No. 132. Land Use and Building Act (132/1999, amendment 222/2003 included) Chapter 1. General provisions. Section 1 General objective of the Act NB: UNOFFICIAL TRANSLATION FINLAND No. 132 Land Use and Building Act (132/1999, amendment 222/2003 included) In accordance with the decision of Parliament the following is enacted: Chapter 1 General provisions

More information

ANNEX 7.1 Guide to Land Acquisition and Compensation (GLAC) LAND ACQUISITION

ANNEX 7.1 Guide to Land Acquisition and Compensation (GLAC) LAND ACQUISITION ANNEX 7.1 Guide to Land Acquisition and Compensation (GLAC) LAND ACQUISITION Overview Expropriation is a legal way to enable the government or a public legal entity to use immovable assets owned by natural

More information

PROCEDURES FOR ENVIRONMENTAL AND SOCIAL APPRAISAL AND MONITORING OF INVESTMENT PROJECTS

PROCEDURES FOR ENVIRONMENTAL AND SOCIAL APPRAISAL AND MONITORING OF INVESTMENT PROJECTS PROCEDURES FOR ENVIRONMENTAL AND SOCIAL APPRAISAL AND MONITORING OF INVESTMENT PROJECTS Approved 10 July 2015 CONTENTS 1. INTRODUCTION 1 2. OVERVIEW OF THE ENVIRONMENTAL AND SOCIAL APPRAISAL AND MONITORING

More information

SAMPLE MULTI-YEAR LEASE AGREEMENT

SAMPLE MULTI-YEAR LEASE AGREEMENT SAMPLE MULTI-YEAR LEASE AGREEMENT This Lease Agreement is entered into on this day of, 2009, by and between as lessor ( Lessor ), and, as lessee ( Lessee ), for the Lease of certain land bounded by in,

More information

Environmental Assessment

Environmental Assessment BP 4.01 January 1999 These procedures were prepared for use by World Bank staff and are not necessarily a complete treatment of the subject. Environmental Assessment (Archived August 2004) Note: OP and

More information

Water Services Act (119/2001)

Water Services Act (119/2001) NB: Unofficial translation Ministry of Agriculture and Forestry, Finland Water Services Act (119/2001) Chapter 1 General provisions Section 1 Objective (1) The objective of this Act is to ensure water

More information

Construction CONSTRUCTION

Construction CONSTRUCTION 135 R. English CONSTRUCTION Construction GOOD PRACTICE POINTERS Identify stakeholders most likely to be affected by construction. Notify local stakeholders of construction activities and changes to schedules.

More information

Regulations for the Resettlement Process Resulting from Economic Activities. Decree 31/2012 of 8 August

Regulations for the Resettlement Process Resulting from Economic Activities. Decree 31/2012 of 8 August Regulations for the Resettlement Process Resulting from Economic Activities Decree 31/2012 of 8 August REPUBLIC OF MOZAMBIQUE COUNCIL OF MINISTERS ----------- Decree 31/2012 of 8 August The growing demand

More information

Advisory Note: Due Diligence for Land Acquisition and Resettlement - New Manufacturing Facilities, Myanmar

Advisory Note: Due Diligence for Land Acquisition and Resettlement - New Manufacturing Facilities, Myanmar Overview Myanmar is at the early stage of a nation-building process. Given the underdeveloped infrastructure and weak rule of law companies which may be looking to invest in Myanmar will face many challenges,

More information

STATE OF NEVADA Department of Administration Division of Human Resource Management CLASS SPECIFICATION

STATE OF NEVADA Department of Administration Division of Human Resource Management CLASS SPECIFICATION STATE OF NEVADA Department of Administration Division of Human Resource Management CLASS SPECIFICATION TITLE GRADE EEO-4 CODE RIGHT-OF-WAY SUPERVISOR 39 A 7.412 SERIES CONCEPT Right-of-Way Agents appraise,

More information

2016 HOME REQUEST FOR PROPOSALS AFFORDABLE HOUSING ACQUISITION AND/OR REHABILITATION or NEW CONSTRUCTION

2016 HOME REQUEST FOR PROPOSALS AFFORDABLE HOUSING ACQUISITION AND/OR REHABILITATION or NEW CONSTRUCTION 2016 HOME REQUEST FOR PROPOSALS AFFORDABLE HOUSING ACQUISITION AND/OR REHABILITATION or NEW CONSTRUCTION The Eugene-Springfield HOME Consortium invites proposals from for-profit developers, non-profit

More information

Chapter 10. Acquisition of Real Property

Chapter 10. Acquisition of Real Property Chapter 10 Acquisition of Real Property Chapter 10: Acquisition of Real Property Table of Contents Page Property Management & Disposition... 10-1 Acquisition as a National Objective... 10-2 Uniform Relocation

More information

Sec. 22a-1a page 1 (4-97)

Sec. 22a-1a page 1 (4-97) Department of Environmental Protection Sec. 22a-1a page 1 (4-97) TABLE OF CONTENTS Connecticut Environmental Policy Act Definitions... 22a-1a- 1 Determination of sponsoring agency.... 22a-1a- 2 Determination

More information

RESETTLEMENT POLICY FRAMEWORK (RPF)

RESETTLEMENT POLICY FRAMEWORK (RPF) Public Disclosure Authorized Road Asset Management Project (RAMP) Works and Highways (MPWH) Republic of Yemen Road Maintenance Fund Implementation Unit(RMFIU) Ministry of Public Public Disclosure Authorized

More information

Data Protection Policy

Data Protection Policy 1 Data Protection Policy Version 1: June 2014 1 2 Contents 1. Introduction 3 2. Policy Statement 3 3. Purpose of the Data Protection Act 1998 3 4. The principles of the Data Protection Act 1998 4 5 The

More information

Performance Standard 8: Assessment and Management of Environmental and Social

Performance Standard 8: Assessment and Management of Environmental and Social Overview of Performance Standards on Environmental and Social Sustainability 1. IFC s Sustainability Framework articulates the Corporation s strategic commitment to sustainable development, and is an integral

More information

Performance Standard 8:

Performance Standard 8: Overview of Performance Standards on Environmental and Social Sustainability 1. IFC s Sustainability Framework articulates the Corporation s strategic commitment to sustainable development, and is an integral

More information

GREATER SYRACUSE PROPERTY DEVELOPMENT CORPORATION DISPOSITION OF REAL AND PERSONAL PROPERTY POLICY

GREATER SYRACUSE PROPERTY DEVELOPMENT CORPORATION DISPOSITION OF REAL AND PERSONAL PROPERTY POLICY GREATER SYRACUSE PROPERTY DEVELOPMENT CORPORATION DISPOSITION OF REAL AND PERSONAL PROPERTY POLICY SECTION 1. PURPOSE. This policy (the "Policy") sets forth guidelines for the Land Bank's disposal of real

More information

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized I. Basic Information Date prepared/updated: 12/17/2007 INTEGRATED SAFEGUARDS DATASHEET

More information

TERMS OF REFERENCE FOR SCOPING OF EIA STUDY

TERMS OF REFERENCE FOR SCOPING OF EIA STUDY TERMS OF REFERENCE FOR SCOPING OF EIA STUDY Ours project is a proposed large scale unit and categorized as 5(h)-B as per the EIA notification 2006 of MoEFCC, New Delhi and subsequent amendments. Looking

More information

Pre-Feasibility Study Bhopal Solid Waste Management. May 2015 Executive Summary

Pre-Feasibility Study Bhopal Solid Waste Management. May 2015 Executive Summary Pre-Feasibility Study Bhopal Solid Waste Management May 2015 Executive Summary Cities Development Initiative for Asia P a g e 2 A. Rationale i. The Project 1. Bhopal is the capital and second largest city

More information

Form letter RE-M to be mailed 30 days prior to beginning negotiations

Form letter RE-M to be mailed 30 days prior to beginning negotiations Local Let Real Estate Acquisition Checklist to monitor compliance with the Uniform Act and the Ohio Department of Transportation Real Estate Administration Policies and Procedures Manual The process of

More information

Real Estate Acquisition Guidelines For: WEST SACRAMENTO AREA FLOOD CONTROL AGENCY. Sacramento River Southport Early Implementation Project

Real Estate Acquisition Guidelines For: WEST SACRAMENTO AREA FLOOD CONTROL AGENCY. Sacramento River Southport Early Implementation Project Real Estate Acquisition Guidelines For: WEST SACRAMENTO AREA FLOOD CONTROL AGENCY Sacramento River Southport Early Implementation Project TABLE OF CONTENTS Introduction... 1 Before the Acquisition Process

More information

Grievance Management Guidance Note

Grievance Management Guidance Note May 2012 1 Grievance Management Guidance Note 1 EBRD S REQUIREMENTS 1.1 PERFORMANCE REQUIREMENT (PR) 10 INFORMATION DISCLOSURE AND STAKEHOLDER ENGAGEMENT Key Bank requirements relating to grievance management

More information

RELOCATION ASSISTANCE BUSINESSES, FARMS, AND NON-PROFIT ORGANIZATIONS

RELOCATION ASSISTANCE BUSINESSES, FARMS, AND NON-PROFIT ORGANIZATIONS RELOCATION ASSISTANCE BUSINESSES, FARMS, AND NON-PROFIT ORGANIZATIONS STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION HAYDON BURNS BUILDING 605 SUWANNEE STREET TALLAHASSEE, FLORIDA 32399-0450 October 1,

More information

Residential Rehabilitation Loan Program Guidelines

Residential Rehabilitation Loan Program Guidelines Residential Rehabilitation Loan Program Guidelines City of Middletown Department of Planning, Conservation and Development Community Development Division February 1999 Table of Contents Purpose 1 General

More information

Relocation Assistance

Relocation Assistance Harris County ~ Right of Way Division 10555 Northwest Freeway, Suite 210 Houston, Texas 77092 713-274-3722 Terry.gunn@hcpid.org Relocation Assistance CONTENTS Introduction 3 Qualification for Assistance

More information

Article 20. Nonconformities

Article 20. Nonconformities Article 20. Nonconformities 20.1 PURPOSE 20.2 GENERAL STANDARDS OF APPLICABILITY 20.3 NONCONFORMING USE 20.4 NONCONFORMING STRUCTURES 20.5 NONCONFORMING LOTS OF RECORD 20.6 NONCONFORMING SIGNS 20.1 PURPOSE

More information

EXHIBIT 17 INSURANCE COVERAGE REQUIREMENTS

EXHIBIT 17 INSURANCE COVERAGE REQUIREMENTS EXHIBIT 17 INSURANCE COVERAGE REQUIREMENTS 1. Builder s Risk Insurance During Construction At all times during the period from the Operating Commencement Date until the last Service Commencement Date and

More information

8.0 ENVIRONMENTAL PROTECTION MONITORING AND FOLLOW-UP

8.0 ENVIRONMENTAL PROTECTION MONITORING AND FOLLOW-UP 8.0 ENVIRONMENTAL PROTECTION MONITORING AND FOLLOW-UP 8.1 INTRODUCTION Mitigation measures, monitoring and other follow-up actions identified in Chapter 7 (Environmental Effects Assessment and Mitigation)

More information

Records Retention and Disposal Schedule. Property Management

Records Retention and Disposal Schedule. Property Management Records Retention and Disposal Schedule Property Management Version control Version Author Policy Approved By Approval Date Publication Date Review Due V 1.0 Information Governance Unit Philip Jones, Head

More information

These guidelines can help you in taking the first step and adopt a sustainability policy as well as plan your further sustainability communication.

These guidelines can help you in taking the first step and adopt a sustainability policy as well as plan your further sustainability communication. SUSTAINABILITY POLICY AND COMMUNICATION GUIDELINES Why communicate about sustainability? IFU encourages all our investments to be transparent and informative about business and sustainability performance

More information

Statement of Guidance: Outsourcing All Regulated Entities

Statement of Guidance: Outsourcing All Regulated Entities Statement of Guidance: Outsourcing All Regulated Entities 1. STATEMENT OF OBJECTIVES 1.1. 1.2. 1.3. 1.4. This Statement of Guidance ( Guidance ) is intended to provide guidance to regulated entities on

More information

CHAPTER E12 - ENVIRONMENTAL IMPACT ASSESSMENT ACT

CHAPTER E12 - ENVIRONMENTAL IMPACT ASSESSMENT ACT CHAPTER E12 - ENVIRONMENTAL IMPACT ASSESSMENT ACT ARRANGEMENT OF SECTIONS PART I General principles of environmental impact assessment SECTION 1.Goals and objectives of environmental impact assessment.

More information

ENVIRONMENTAL IMPACT ASSESSMENTS AND ENVIRONMENTAL IMPACT STATEMENTS

ENVIRONMENTAL IMPACT ASSESSMENTS AND ENVIRONMENTAL IMPACT STATEMENTS GOVERNMENT OF BERMUDA Department of Planning ENVIRONMENTAL IMPACT ASSESSMENTS AND Section 1: Introduction... 2 Section 2: What are Environmental Impact Assessments and Environmental Impact Statements and

More information

Salavanh Province SAL/PR/04: Sustainable Livestock Health Management System for Salavanh Province

Salavanh Province SAL/PR/04: Sustainable Livestock Health Management System for Salavanh Province Salavanh Province SAL/PR/04: Sustainable Livestock Health Management System for Salavanh Province Subproject Name Country Province Subproject code Number Subproject type Source of Funding/Amount ADB and

More information

HOME OWNERSHIP THE REAL COSTS

HOME OWNERSHIP THE REAL COSTS HOME OWNERSHIP THE REAL COSTS THE GOVERNMENT REQUIRES US TO PROVIDE YOU WITH THIS INFORMATION PURSUANT TO SECTION 121AA HOUSING ACT 1985 If you just compare the cost of a mortgage with the cost of your

More information

Principles for Responsible Investment in Farmland

Principles for Responsible Investment in Farmland Principles for Responsible Investment in Farmland September 2011 Preamble ln recent years, investment in farmland A has emerged as a new asset class for institutional investors. These Principles for Responsible

More information

REGULATION NO. 30. Loans for Rural Economic Development

REGULATION NO. 30. Loans for Rural Economic Development EASTERN ILLINI ELECTRIC COOPERATIVE REGULATION NO. 30 SUBJECT: Loans for Rural Economic Development OBJECTIVE: It is the objective of Eastern Illini Electric Cooperative (Cooperative) to provide an additional

More information

Global Environment Facility GEF OPERATIONAL PROGRAM #13 ON CONSERVATION AND SUSTAINABLE USE OF BIOLOGICAL DIVERSITY IMPORTANT TO AGRICULTURE

Global Environment Facility GEF OPERATIONAL PROGRAM #13 ON CONSERVATION AND SUSTAINABLE USE OF BIOLOGICAL DIVERSITY IMPORTANT TO AGRICULTURE Global Environment Facility GEF OPERATIONAL PROGRAM #13 ON CONSERVATION AND SUSTAINABLE USE OF BIOLOGICAL DIVERSITY IMPORTANT TO AGRICULTURE CONTENTS Introduction..1 Convention Guidance... 2 Agricultural

More information

Rural dwellings including bed and breakfast accommodation

Rural dwellings including bed and breakfast accommodation MORNINGTON PENINSULA SHIRE COUNCIL - INTERIM POLICY - JUNE 2011 Rural dwellings including bed and breakfast accommodation This policy applies to the use and development of land for a dwelling, including

More information

Property, Plant and Equipment

Property, Plant and Equipment STATUTORY BOARD FINANCIAL REPORTING STANDARD SB-FRS 16 Property, Plant and Equipment SB-FRS 16 Property, Plant and Equipment applies to Statutory Boards for annual periods beginning on or after 1 January

More information

Section 7. Terms of Reference

Section 7. Terms of Reference APPENDIX-A TERMS OF REFERENCE UNION-LEVEL TECHNICAL ASSISTANCE TO PROVIDE INSTITUTIONAL SUPPORT TO THE MYANMAR NATIONAL COMMUNITY DRIVEN DEVELOPMENT PROJECT I. INTRODUCTION IDA GRANT H814MM FY 2013-16

More information

CITY OF LUDINGTON RENTAL REHABILITATION PROGRAM PROGRAM GUIDELINES 2009 GENERAL

CITY OF LUDINGTON RENTAL REHABILITATION PROGRAM PROGRAM GUIDELINES 2009 GENERAL CITY OF LUDINGTON RENTAL REHABILITATION PROGRAM PROGRAM GUIDELINES 2009 GENERAL Program Purpose: To provide safe and affordable rental housing to low income tenants at or below 80% of Mason County s Area

More information

Submission to the Standing Committee on General Government regarding the review the Aggregate Resources Act, May 16, 2012

Submission to the Standing Committee on General Government regarding the review the Aggregate Resources Act, May 16, 2012 Submission to the Standing Committee on General Government regarding the review the Aggregate Resources Act, May 16, 2012 Dear Members of the Standing Committee, On behalf of our members and member groups

More information

Lao PDR Public-Private Partnership Policy

Lao PDR Public-Private Partnership Policy Lao PDR Public-Private Partnership Policy Supported by the Asian Development Bank GRANT-0309 LAO Governance and Capacity Development in Public Sector Management Program (Public Private Partnerships) Table

More information

THE NATURAL RESOURCES AND ENVIRONMENT ORDINANCE (CAP. 84 - LAWS OF SARAWAK, 1958 Ed.)

THE NATURAL RESOURCES AND ENVIRONMENT ORDINANCE (CAP. 84 - LAWS OF SARAWAK, 1958 Ed.) THE NATURAL RESOURCES AND ENVIRONMENT ORDINANCE (CAP. 84 - LAWS OF SARAWAK, 1958 Ed.) THE NATURAL RESOURCES AND ENVIRONMENT (PRESCRIBED ACTIVITIES) ORDER, 1994 (Made under section 11A(1)) (Incorporating

More information

When ODOT Needs Your Property

When ODOT Needs Your Property When ODOT Needs Your Property Foreword The State of Ohio is engaged in a continuous program of improving its transportation systems. Often this improvement process involves the purchase of land so that

More information

Guidelines for Financial Institutions Outsourcing of Business Activities, Functions, and Processes Date: July 2004

Guidelines for Financial Institutions Outsourcing of Business Activities, Functions, and Processes Date: July 2004 Guidelines for Financial Institutions Outsourcing of Business Activities, Functions, and Processes Date: July 2004 1. INTRODUCTION Financial institutions outsource business activities, functions and processes

More information

Draft Terms of Reference for appointment of Design and Supervision Consultants (DSC)

Draft Terms of Reference for appointment of Design and Supervision Consultants (DSC) Draft Terms of Reference for appointment of Design and Supervision Consultants (DSC) 1.0 BACKGROUND: 1. Introduction: Indian coasts of about 5700 kilometers are highly vulnerable to tropical cyclones and

More information

Environmental and Social Management System Arrangements

Environmental and Social Management System Arrangements Environmental and Social Management System Arrangements Project Number: 48015-002 Loan Number: LXXXX September 2015 Proposed Loan and Technical Assistance Grant Mongolia: Supporting the Credit Guarantee

More information

How To Write A Right Of Way Certificate

How To Write A Right Of Way Certificate CHAPTER 14 RIGHT OF WAY CERTIFICATION TABLE OF CONTENTS 14.01.00.00 INTRODUCTION 01.00 General 01.01 Definition 02.00 Projects Requiring R/W Certification 03.00 Projects Exempt From R/W Certification 04.00

More information

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized I. Basic Information Date prepared/updated: 01/04/2008 INTEGRATED SAFEGUARDS DATASHEET

More information

SECTION 1.0 STATUTORY AUTHORIZATION AND PURPOSE

SECTION 1.0 STATUTORY AUTHORIZATION AND PURPOSE A local law for Flood Damage Prevention as authorized by the New York State Constitution, Article IX, Section 2, and Environmental Conservation Law, Article 36 1.1 FINDINGS SECTION 1.0 STATUTORY AUTHORIZATION

More information

Part 700 Tribal Occupational Safety and Health Administration (TOSHA)

Part 700 Tribal Occupational Safety and Health Administration (TOSHA) Part 700 Tribal Occupational Safety and Health Administration (TOSHA) Section 701 Purpose and Definitions. (a) The purpose of Chapter 7 is to assure as far as possible safe and healthful working conditions

More information

Pre- FEASIBILITY REPORT

Pre- FEASIBILITY REPORT Pre- FEASIBILITY REPORT In Respect Of JHILIMINDA SAND BED OVER 20.30 ACRES OR 8.215 HA IN VILLAGE JHILIMINDA, ATTABIRA TAHASIL OF BARGARH DISTRICT, ODISHA (For the Financial Year-2015-16 to 2019-20) Prepared

More information

Contractor. Management

Contractor. Management Contractor Environment Health and Safety Management Best Practice (2007) A. INTRODUCTION Many construction Owners employ contract personnel for a wide range of activities, from administrative support to

More information

Bank on Human Rights. Key Human Rights Concerns and Recommendations regarding the World Bank s Proposed Social and Environmental Safeguards Framework

Bank on Human Rights. Key Human Rights Concerns and Recommendations regarding the World Bank s Proposed Social and Environmental Safeguards Framework Bank on Human Rights Key Human Rights Concerns and Recommendations regarding the World Bank s Proposed Social and Environmental Safeguards Framework March, 2015 I. Respect for human rights The World Bank

More information

Chapter 11 Housing Page 11-1

Chapter 11 Housing Page 11-1 Housing Page 11-1 11(1) Municipal Standards for Condominium Developments That the following minimum Municipal Standards for condominium developments be established: Minimum Municipal Standards Parking

More information

Your Rights and Benefits as a Displacee Under the Uniform Relocation Assistance Program (Business, Farm or Nonprofit Organization)

Your Rights and Benefits as a Displacee Under the Uniform Relocation Assistance Program (Business, Farm or Nonprofit Organization) Your Rights and Benefits as a Displacee Under the Uniform Relocation Assistance Program (Business, Farm or Nonprofit Organization) July 2013 www.hsr.ca.gov INTRODUCTION In building any large, modern transportation

More information

S.B.S. Resolution Nº 1928-2015 The Head of the Superintendency of Banks, Insurance Companies and Private Pension Fund Administrators

S.B.S. Resolution Nº 1928-2015 The Head of the Superintendency of Banks, Insurance Companies and Private Pension Fund Administrators Waiver of Responsibility The law and any other regulation translated into English are only referential. The official language for any legal purposes is Spanish as published in the Official Journal El Peruano.

More information

05-15-98 CIVIL ENGINEERING ASSOCIATE, 7246

05-15-98 CIVIL ENGINEERING ASSOCIATE, 7246 CITY OF LOS ANGELES CIVIL SERVICE COMMISSION CLASS SPECIFICATION POSTED JUNE 1999 05-15-98 CIVIL ENGINEERING ASSOCIATE, 7246 Summary of Duties: Performs professional civil engineering work in researching,

More information

LAW OF MONGOLIA ON CONCESSIONS CHAPTER ONE. GENERAL PROVISIONS

LAW OF MONGOLIA ON CONCESSIONS CHAPTER ONE. GENERAL PROVISIONS LAW OF MONGOLIA 28 January 2010 State Palace, Ulaanbaatar city Article 1. Purpose of the law ON CONCESSIONS CHAPTER ONE. GENERAL PROVISIONS 1.1. The purpose of this law is to regulate matters related to

More information

State Law in Virginia affecting Local Codes & Ordinances

State Law in Virginia affecting Local Codes & Ordinances State Law in Virginia affecting Local Codes & Ordinances Published as a public service by Page 1 of 15 INTRODUCTION State law changes in Virginia, impact many provisions in the ordinance codes of Virginia

More information

How To Account For Property, Plant And Equipment

How To Account For Property, Plant And Equipment International Accounting Standard 16 Property, Plant and Equipment Objective 1 The objective of this Standard is to prescribe the accounting treatment for property, plant and equipment so that users of

More information

Part of the Holyhead 2020 Regeneration Programme Working in Partnership with Welsh Government

Part of the Holyhead 2020 Regeneration Programme Working in Partnership with Welsh Government Holyhead Investment Fund Part of the Holyhead 2020 Regeneration Programme Working in Partnership with Welsh Government !!!!!!!!!!!"#$%"&'(!)*+,'-.!'-(!)*'+$&!/$'0&1!,&2&-&,'.*#-!/,#2,'33&! 45-(&(!+%!."&!6&$1"!2#)&,-3&-.7!'(3*-*1.&,&(!+%!*1$&!#4!'-2$&1&%!0#5-.%!

More information

SUPERVISORY AND REGULATORY GUIDELINES: PU48-0809 GUIDELINES ON MINIMUM STANDARDS FOR THE OUTSOURCING OF MATERIAL FUNCTIONS

SUPERVISORY AND REGULATORY GUIDELINES: PU48-0809 GUIDELINES ON MINIMUM STANDARDS FOR THE OUTSOURCING OF MATERIAL FUNCTIONS SUPERVISORY AND REGULATORY GUIDELINES: PU48-0809 ISSUED: 4 th May 2004 REVISED: 27 th August 2009 GUIDELINES ON MINIMUM STANDARDS FOR THE OUTSOURCING OF MATERIAL FUNCTIONS I. INTRODUCTION The Central Bank

More information

ENVIRONMENTAL MANAGEMENT STRATEGY

ENVIRONMENTAL MANAGEMENT STRATEGY Jos& M. Cabral 36 1 ENVIRONMENTAL MANAGEMENT STRATEGY FOR INFRASTRUCTURE AGENCIES IN DEVELOPING COUNTRIES Jose M. Cabral' INTRODUCTION This paper describes an environmental management strategy for agencies

More information

RELOCATION ASSISTANCE SERVICES SPECIFICATIONS (LUMP SUM)

RELOCATION ASSISTANCE SERVICES SPECIFICATIONS (LUMP SUM) RELOCATION ASSISTANCE SERVICES SPECIFICATIONS (LUMP SUM) A. PROJECT DESCRIPTION The Local Public Agency (LPA) will receive proposals for Relocation Assistance Services for: Project: CN: Location: The work

More information

DEPARTMENT OF FORESTRY DRAFT REVISED NATIONAL FOREST POLICY OF MALAWI

DEPARTMENT OF FORESTRY DRAFT REVISED NATIONAL FOREST POLICY OF MALAWI DEPARTMENT OF FORESTRY DRAFT REVISED NATIONAL FOREST POLICY OF MALAWI July, 2013 1. Foreword 2. Preface 3. Introduction 4. Policy linkages 5. Broad Policy Direction 6. Policy Priority Areas Provides the

More information

TERMS OF REFERENCE FOR THE RAPID EIA STUDY

TERMS OF REFERENCE FOR THE RAPID EIA STUDY TERMS OF REFERENCE FOR THE RAPID EIA STUDY 1 SUMMARY OF EIA METHODOLOGY STEP I : SCOPING OF THE ASSESSMENT Own with prevailing regulatory setting and criteria Identification of Environmental Assessment

More information

Land grabbing definition perpetrated in the BEE project

Land grabbing definition perpetrated in the BEE project Land grabbing definition perpetrated in the BEE project Bagamoyo EcoEnergy (BEE) believes that all Projects may do more harm than good unless safeguards are put in place to ensure equitable development.

More information

1) Stakeholder participation in ER-PIN planning and ERP design

1) Stakeholder participation in ER-PIN planning and ERP design Grading for ER-PIN Assessments: Color Qualification Analysis Green The indicator is clearly addressed and supported by country stakeholders and other sources of evidence; Reasons for attributed grade should

More information

Quick Summary of Final Tangible Property Regulations

Quick Summary of Final Tangible Property Regulations This summary is intended to provide a high-level overview only and should not be relied on for application to specific fact patterns and situations. Taxpayers should consult their tax advisors to determine

More information

5.0 ENVIRONMENTAL IMPACT ASSESSMENT METHODS

5.0 ENVIRONMENTAL IMPACT ASSESSMENT METHODS 5.0 ENVIRONMENTAL IMPACT ASSESSMENT METHODS The methods that are used to conduct the environmental impact assessment (EIA) of the Project are described in this section. The EIA uses a methodological framework

More information

SMALL BUSINESS LOAN ACT OF 2007 Ordinance 07-700-05

SMALL BUSINESS LOAN ACT OF 2007 Ordinance 07-700-05 SMALL BUSINESS LOAN ACT OF 2007 Ordinance 07-700-05 Article I. Purpose; Policy 1.01. Purpose. The purpose of the Small Business Loan Program is to effectively use Tribal resources to maximize the potential

More information

TCAP Guidance On Fees and Asset Management

TCAP Guidance On Fees and Asset Management TCAP Guidance On Fees and Asset Management As of September 18, 2009 I. INTRODUCTION This guidance addresses TCAP administrative, project compliance, and asset management costs that may occur during the

More information

4.1 PROPERTY, PLANT AND EQUIPMENT

4.1 PROPERTY, PLANT AND EQUIPMENT 4.1 PROPERTY, PLANT AND EQUIPMENT 4.1.1 Introduction 4.1.1.1 Authorities shall account for tangible fixed assets in accordance with IAS 16 Property, Plant and Equipment, except where interpretations or

More information

LAW ON INVESTMENT CHAPTER 1. General Provisions

LAW ON INVESTMENT CHAPTER 1. General Provisions NATIONAL ASSEMBLY No. 59-2005-QH11 SOCIALIST REPUBLIC OF VIETNAM Independence - Freedom - Happiness LAW ON INVESTMENT Pursuant to the 1992 Constitution of the Socialist Republic of Vietnam as amended by

More information

APPENDIX 7 : PHYSICAL CULTURAL RESOURCES MANAGEMENT PLAN

APPENDIX 7 : PHYSICAL CULTURAL RESOURCES MANAGEMENT PLAN APPENDIX 7 : PHYSICAL CULTURAL RESOURCES MANAGEMENT PLAN Contents 1.0 Introduction... 2 1.1 Definitions... 3 1.2 Purpose / Goals of the Plan... 3 1.3 Timing... 3 1.4 EMP Framework... 3 1.5 Plan Revision,

More information

LOAN. Program Guide SMALL BUSINESS. ECONOMIC DEVELOPMENT Phone: 916.478.3690 Fax: 916.691.3168 elkgrovecity.org/econdev

LOAN. Program Guide SMALL BUSINESS. ECONOMIC DEVELOPMENT Phone: 916.478.3690 Fax: 916.691.3168 elkgrovecity.org/econdev SMALL BUSINESS LOAN Program Guide Funded by City of Elk Grove with Community Development Block Grant (CDBG) Funds ECONOMIC DEVELOPMENT Phone: 916.478.3690 Fax: 916.691.3168 elkgrovecity.org/econdev Elk

More information

Environmental Law Enforcement in Zimbabwe. Farai Michael Nyahwa

Environmental Law Enforcement in Zimbabwe. Farai Michael Nyahwa Environmental Law Enforcement in Zimbabwe By Farai Michael Nyahwa Presentation Breakdown Institutional Arrangement for Environmental Law Enforcement in Zimbabwe Major Environmental Issues of Concern In

More information

Citizen s Guide to Property Acquisitions

Citizen s Guide to Property Acquisitions 3: SOME IMPORTANT DEFINITIONS Citizen s Guide to Property Acquisitions By Local Public Agencies in Mississippi 1 Citizen s Guide to Property Acquisitions By Local Public Agencies in Mississippi Contents

More information

Definition of Tower from the Bradley County Zoning Resolution

Definition of Tower from the Bradley County Zoning Resolution Definition of Tower from the Bradley County Zoning Resolution 43. TOWER. Any outdoor structure designed and constructed to support one (1) or more transmitting or receiving devices for telephone, radio

More information

Land Protection Planning for the National Wildlife Refuge System

Land Protection Planning for the National Wildlife Refuge System March 2012 Planning Information Brochure 1 Land Protection Planning for the National Wildlife Refuge System The following questions are often asked when the U.S. Fish and Wildlife Service (Service) begins

More information