Compliance Date Approaches for Installation of Fire Sprinkler Systems

Size: px
Start display at page:

Download "Compliance Date Approaches for Installation of Fire Sprinkler Systems"

Transcription

1 Compliance Date Approaches for Installation of Fire Sprinkler Systems By Frank Monikowski It has been nearly three years since the Centers for Medicare and Medicaid Services (CMS) announced amended federal regulations that require long-term care facilities such as nursing homes to install a comprehensive sprinkler system in order to continue serving Medicare and Medicaid beneficiaries. The regulation from CMS, an agency in the U.S. Department of Health and Human Services, provided a fiveyear phase-in period (until August 2013) for long-term care facilities to be fully compliant with the fire sprinkler rule. The regulation CFR (a)(8)(i) -- requires the sprinkler system to be installed in accordance with the 1999 edition of NFPA 13: Standard for the Installation of Sprinkler Systems. CMS concurrently adopted 42 CFR (a)(8)(ii) pertaining to the inspection, testing and maintenance of sprinkler systems. That regulation specifies that inspection, testing and maintenance activities be performed in accordance with the 1998 edition of NFPA 25: Standard for the Inspection, Testing and Maintenance of Water-Based Fire Protection Systems. Approximately three million elderly and disabled Americans reside in the nation s 16,000 nursing homes. The fire sprinkler regulations are intended to help promote fire safety and protect nursing home residents. This paper examines some of the events that led to the adoption of the fire sprinkler regulations, provides practical suggestions on how to proceed with the compliance effort, and describes the sprinkler retrofit and design/build construction processes. The history of fire sprinklers in nursing homes Many years back, the NFPA 13 standard allowed healthcare facilities to omit fire sprinklers in certain areas. Additionally, NFPA 101: Life Safety Code allowed fire sprinklers to be omitted from specified areas of certain occupancies. In nursing homes, sprinklers were not typically required in resident closets and bathrooms. In older facilities built under previous fire codes, smoke detectors or fire sprinklers were often required only in hallways or higher risk areas such as storage and mechanical equipment rooms. In some cases, these fire protection devices were not required at all. Consequently, many existing nursing home structures have partial sprinkler coverage or no fire sprinklers at all, which can make these facilities more vulnerable in the event of a fire. The issuance of the sprinkler regulations followed the tragic 2003 fires that swept through nursing homes in Connecticut and Tennessee. These homes did not have full sprinkler protection. The fires killed a total of 31 residents and injured many others. The states of Connecticut, Alabama and Tennessee subsequently put mandates in place that required nonsprinklered facilities to immediately add fire sprinklers. However, even in these states, some of the facilities considered to be sprinklered at the time the mandates were put in place may not comply today with the full sprinkler protection requirement outlined in the CMS regulation. 1

2 The 2006 editions of NFPA 101 and NFPA 5000: Building Construction and Safety Code added provisions requiring existing nursing facilities to be retrofitted with fire sprinklers. Adoption and enforcement of these standards has not been universal, which underscores the importance of the CMS regulation. The CMS press release that announced the new regulation back in June 2008 said the following: CMS is taking further action to protect the lives of our beneficiaries through a more comprehensive and effective approach to fire safety. In the past, certain older facilities were exempt from having an automatic sprinkler system, but we now will hold all 16,000 nursing homes in the nation to this standard. According to that CMS release, there had never been a multiple-fatality fire in a facility with a sprinkler system that meets the requirements of the new rule. A good time to take action We are now more than halfway through the five-year phase-in period that long-term care facilities were given to be fully compliant with the new rule. With the compliance deadline on the horizon, this is an opportune time to take steps to get full fire sprinkler coverage in place in accordance with the requirements of the regulation. A good first step in this process is an evaluation of your current sprinkler system, preferably performed by a trained professional. This evaluation can be completed by a professional fire protection engineer or a highly qualified sprinkler contractor. It is advisable to work with a firm that has NICET-certified design technicians on staff. The initial evaluation can demonstrate to a CMS representative that you are committed to due-diligence and working to get the desired results by engaging experienced professionals. The addition of fire sprinklers could have an impact on water demand and existing pipe sizes -- another reason for hiring an experienced professional to conduct a sprinkler system survey. A copy of the original installation drawings will assist tremendously in this process. If they are not available, a sprinkler professional can do a walking review of the existing system and produce appropriate drawings. In addition, a determination will need to be made regarding the adequacy of the existing water supply and what corrective actions, if any, will be required to retrofit a new sprinkler system into the existing facility. The value of an experienced contractor Whether extending an existing sprinkler system or providing a new system throughout a facility, it is highly recommended that you find an experienced contactor that specializes in this type of work. Contractors experienced in sprinkler retrofits understand the importance of minimizing facility disruptions, limiting inconvenience to residents and staff, and being efficient about cleanup. They can also offer aesthetic and concealment options to fit your budget. Two general methods are used when providing a new sprinkler system in a facility. One is the traditional method, where an architect and/or an engineer is hired to do a survey and provide 2

3 bid documents for soliciting a quote from various contractors. This process, known as designbid-build, can be quite time consuming and some believe it delivers less overall value to the building owner. The design and development of the bid documents can be expensive in and of itself, sometimes consuming as much as 25% of the total project. The other sprinkler system method, which we will discuss in greater detail, is design-build. With this approach, a single contract is used for design and construction. Design-build has been used for years by many quality general contractors around the country, and can be executed by skilled fire sprinkler contractors as well. It is a good fit for the type of work required when retrofitting a fire sprinkler system into an existing healthcare facility. Design-build becomes more widely used Design-build now represents nearly 50% of all general contracting work that is performed in the United States, according to the Design Build Institute of America (DBIA). DBIA released information from the Construction Industry Institute (CII) on design-build performance that estimates this process can speed the completion of a project by an average of 33%. As an example, DBIA cited the federal government s decision to proceed with design-build methodology immediately after the 9/11 terrorist attacks on the Pentagon. DBIA reported that original estimates indicated it would have taken three years to complete the demolition and rebuilding process using design-bid-build methodology. Design-build was ultimately used, and DBIA reports that demolition and rebuilding was completed in one year [66% less time] and at a dramatically lower cost. The pricing and retrofit process begins with a survey of the existing facility and the completion of an onsite flow test. Alternatively, you can obtain recent test information from the local water purveyor. Next, a sit-down meeting is held where the fire sprinkler contractor typically meets with facilities personnel who will be most directly involved in the sprinkler retrofit project. Sprinkler layout and concealment options are usually discussed, along with installation scheduling and the daily routines of residents and staff. The relocation of residents to temporary holding areas during the retrofit project should be given strong consideration. Others affected by the installation and any ancillary systems and any special requirements should also be discussed. The meeting can also address ceiling work, access panels, new alarms and panels, painting, soffiting, cleanup, and other renovation work considerations. At this point, the interview process should end and a schedule developed for future meetings. Based on the interview process, and after determining the adequacy of the water supply, the fire sprinkler contractor will prepare budgetary pricing. Once that is complete, the contractor generally provides a presentation at the facility. This presentation should include the Guaranteed Maximum Price [GMP] for the project, along with an outline specifying a list of services and products to be provided, any exclusions, and a more detailed scheduling and project management plan. The GMP should also include an estimate on any items that will need to be subcontracted to an outside vendor. The final price can then be adjusted after all quotations are received and the subcontractor selected. 3

4 By now, the owner or facility manager should be in position to make a commitment to a contractor. If not satisfied with the presentation, there should either be an open discussion with the contractor or the meeting should end. If that happens, attention can be directed toward soliciting another contractor that may offer a better solution. Generally speaking, when retrofitting fire sprinklers in your facility, it is critical to make a good decision in the selection of a contractor. You can be best served by a contractor that has years of retrofit experience, its own design technicians with NICET certification, highly skilled construction and project management, and the necessary staffing to get your installation completed efficiently and with minimal disruption. That is how we approach retrofit work at SimplexGrinnell. It is worth noting that a contractor capable of handling both fire alarm and sprinkler work can provide more uniformity in installation, coordination and commissioning -- and potentially a more competitive price. After a commitment is made to a contractor via a written agreement, the contractor will proceed with a design layout. Once the layout is complete, drawings are submitted for approval to the AHJ [Authority Having Jurisdiction] and the building owner. Simultaneously, the drawings are submitted to solicit any subcontracting quotes that may be required. Subcontracting quotes could be needed for items such as electrical wiring for new fire alarm devices or fire pumps, painting, ceiling work or other minor general contracting activities, underground piping installation, excavation for the installation, or cleaning activities. Once bids are received, they can be reviewed by the contractor and the facility administrator or designated party to also participate in the selection process if desired. Once all the drawings are approved and the subcontracting process complete, the contractor s project manager provides a detailed construction schedule and a final price is submitted. This schedule will include all subcontractors, what areas need to be worked during off hours -- such as kitchen and dining areas -- and daily, weekly and monthly projections. The scheduling is critical, and buy-in and cooperation will be needed from all affected parties. An experienced sprinkler foreman and project manager can work to ensure a smooth flow of required daily operations. Preparing for the unexpected and being able to shift to other areas when an emergency arises are paramount in maintaining the schedule and providing a smooth transition for residents and facility staff. Neat and clean workmanship will assist in getting residents back in their rooms comfortably and safely. The proper equipment, whether for hole drilling or covering of furnishings, can also help simplify the process and the daily cleanup. Finally, when all installation is complete, a training session with facility maintenance and key administrative personnel should be conducted. This training should include daily, weekly, and monthly sprinkler requirements, an explanation of the functional operation of the systems, and a binder with operation and maintenance manuals, together with a copy of NFPA 25, the standard for maintaining water-based fire protection systems. Testing, inspection and maintenance of fire sprinkler systems To properly maintain a fire sprinkler system, it is critical to follow the requirements and 4

5 responsibilities outlined in NFPA 25: Standard for the Inspection, Testing, and Maintenance of Water-Based Fire Protection Systems. The importance of proper inspection, testing and maintenance is described in the standard itself: History has shown that the performance reliability of a water-based fire protection system under fire-related conditions increases where comprehensive inspection, testing, and maintenance procedures are enforced. The standard lays out the responsibilities of building owners in maintaining their sprinkler systems, the basic requirements for properly inspecting and testing sprinkler systems and their components, and the steps that should be taken when system deficiencies and impairments are found. There are experienced and respected companies (such as SimplexGrinnell) that can help nursing homes in fulfilling the NFPA 25 inspection, testing and maintenance requirements and in keeping their systems compliant and in good working order. Frank Monikowski is the Fire Sprinkler Marketing Manager for SimplexGrinnell, a full-service sprinkler and fire alarm contractor that also provides integrated security, emergency communications, sound and communications, and nurse call systems and services. 5

F.Y.I. Who Designs Fire Sprinkler Systems?

F.Y.I. Who Designs Fire Sprinkler Systems? F.Y.I. Who Designs Fire Sprinkler Systems? This pamphlet was prepared by the Engineering Department of the National Fire Sprinkler Association,Inc. (NFSA). Established in 1914, the NFSA is a non-profit

More information

Rhode Island State Fire Marshal Fire Protection Systems Narrative Reports. What is a Narrative Report?

Rhode Island State Fire Marshal Fire Protection Systems Narrative Reports. What is a Narrative Report? RHODE ISLAND DIVISION OF STATE FIRE MARSHAL 1951 Smith Street, North Providence, RI 02911 Telephone: (401) 383-7717 Fax: (401) 383-8879 John E. Chartier, EFO, CFI State Fire Marshal Rhode Island State

More information

FORM APPROVED OMB NO. 0938-0391 (X3) DATE SURVEY AND PLAN OF CORRECTION IDENTIFICATION NUMBER: 15G531 08/07/2014 ID PREFIX TAG K010000

FORM APPROVED OMB NO. 0938-0391 (X3) DATE SURVEY AND PLAN OF CORRECTION IDENTIFICATION NUMBER: 15G531 08/07/2014 ID PREFIX TAG K010000 CENTERS FOR MEDICARE & MEDICA SERVICES STATEMENT OF DEFICIENCIES (X1) PROVER/SUPPLIER/CLIA (X2) MULTIPLE CONSTRUCTION (X3) SURVEY AND PLAN OF CORRECTION ENTIFICATION NUMBER: 15G531 08/07/24 NAME OF PROVER

More information

AMERICAN SOCIETY OF CERTIFIED ENGINEERING TECHNICIANS

AMERICAN SOCIETY OF CERTIFIED ENGINEERING TECHNICIANS GREEN TAG/RED TAG AMERICAN SOCIETY OF CERTIFIED ENGINEERING TECHNICIANS ORLANDO CHAPTER ORLANDO, FL February 7, 2013 2012 FLORIDA STATUTES 633.082 Inspection of fire control systems, fire hydrants, and

More information

COMMONWEALTH OF MASSACHUSETTS STATE BUILDING CODE 780 CMR, 6 th Edition FIRE PROTECTION SYSTEMS CHAPTER 9

COMMONWEALTH OF MASSACHUSETTS STATE BUILDING CODE 780 CMR, 6 th Edition FIRE PROTECTION SYSTEMS CHAPTER 9 COMMONWEALTH OF MASSACHUSETTS STATE BUILDING CODE 780 CMR, 6 th Edition FIRE PROTECTION SYSTEMS CHAPTER 9 GUIDELINES FOR THE PREPARATION OF FIRE PROTECTION SYSTEM NARRATIVE REPORTS 780 CMR 903.1.1 State

More information

1.0 General. Inspection, Testing, and Maintenance 1 of 8

1.0 General. Inspection, Testing, and Maintenance 1 of 8 1.0 General 1.1 Scope This specifications covers the minimum requirements for the inspection, testing, and maintenance of the existing Notifier fire alarm systems at Bergen Community College (BCC) campus

More information

UNIVERSITY OF TOLEDO

UNIVERSITY OF TOLEDO UNIVERSITY OF TOLEDO SUBJECT: INTERIM LIFE SAFETY MEASURES AND INFECTION Procedure No: LS-08-008 CONTROL PROCEDURE STATEMENT Interim life safety and infection control measures will be implemented to protect

More information

ELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1

ELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1 KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1 PART 1 - GENERAL 1.01 RELATED DOCUMENTS: SECTION 16050 A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division-1

More information

Fire Alarm and Protection Impairment Policy and Procedures

Fire Alarm and Protection Impairment Policy and Procedures 1.0 Policy Statement The University of New Haven has developed a Fire Alarm and Protection Impairment Plan in accordance with the National Fire Protection Associations (NFPA) codes. Specific codes referenced

More information

DEPARTMENT OF CONSUMER AND INDUSTRY SERVICES DIRECTOR'S OFFICE

DEPARTMENT OF CONSUMER AND INDUSTRY SERVICES DIRECTOR'S OFFICE DEPARTMENT OF CONSUMER AND INDUSTRY SERVICES DIRECTOR'S OFFICE CERTIFICATION OF FIRMS FOR FIRE ALARM SYSTEMS AND FIRE SUPPRESSION SYSTEMS IN STATE-REGULATED FACILITIES (By authority conferred on the state

More information

OVERVIEW SCOPE DEFINITIONS

OVERVIEW SCOPE DEFINITIONS Procedure No 400.10 Subject: Fire Protection Impairment Program Reference: NFPA (see bottom of page 5) Effective Date: March 2008 Distribution All Employees Review Date: April 2008 Purpose: To establish

More information

OBOA 2009 Huntsville, ON Overview of ULC Standards Affecting Building Occupancy Alan Cavers Area Manager Fire & Security Systems Group

OBOA 2009 Huntsville, ON Overview of ULC Standards Affecting Building Occupancy Alan Cavers Area Manager Fire & Security Systems Group OBOA 2009 Huntsville, ON Overview of ULC Standards Affecting Building Occupancy Alan Cavers Area Manager Fire & Security Systems Group Course Title: Rev Date Agenda Introduction to Underwriters Laboratories

More information

NATIONAL INSTITUTE FOR CERTIFICATION IN ENGINEERING TECHNOLOGIES. Level III Content Outline

NATIONAL INSTITUTE FOR CERTIFICATION IN ENGINEERING TECHNOLOGIES. Level III Content Outline Fire Alarm Systems Level III Content Outline The skills and knowledge listed under each task are suggestive of those involved in that task, but are not intended to constitute an exhaustive listing. 3.1

More information

NATIONAL INSTITUTE FOR CERTIFICATION IN ENGINEERING TECHNOLOGIES www.nicet.org 888-476-4238. Fire Alarm Systems

NATIONAL INSTITUTE FOR CERTIFICATION IN ENGINEERING TECHNOLOGIES www.nicet.org 888-476-4238. Fire Alarm Systems Fire Alarm Systems Level IV Content Outline Standard Model/CBT The skills and knowledge listed under each task are suggestive of those involved in that task, but are not intended to constitute an exhaustive

More information

FISCAL YEAR 2013 / WORK PLAN

FISCAL YEAR 2013 / WORK PLAN work plan City of Eugene Central Services Department Facility Management Division FISCAL YEAR 2013 / WORK PLAN City of Eugene Central Services Department Facility Management Division 210 Cheshire Avenue

More information

Austin Independent School District Police Department Policy and Procedure Manual

Austin Independent School District Police Department Policy and Procedure Manual Policy 8.07 Austin Independent School District Police Department Policy and Procedure Manual Life Safety Systems I. POLICY The proper operations of the AISD Life Safety Systems (LSS) are essential for

More information

FIRE ALARM SYSTEM PLAN SUBMITTAL CHECKLIST

FIRE ALARM SYSTEM PLAN SUBMITTAL CHECKLIST FIRE ALARM SYSTEM PLAN SUBMITTAL CHECKLIST All fire alarm system plan submittals must include this Fire Alarm System Plan Submittal Checklist. PLAN APPROVAL - No work shall be performed until plans are

More information

POSITION STATEMENT THE ENGINEER AND THE ENGINEERING TECHNICIAN DESIGNING FIRE PROTECTION SYSTEMS. July 28, 2008

POSITION STATEMENT THE ENGINEER AND THE ENGINEERING TECHNICIAN DESIGNING FIRE PROTECTION SYSTEMS. July 28, 2008 SOCIETY OF FIRE PROTECTION ENGINEERS (SFPE) NATIONAL SOCIETY OF PROFESSIONAL ENGINEERS (NSPE) NATIONAL INSTITUTE FOR CERTIFICATION IN ENGINEERING TECHNOLOGIES (NICET) POSITION STATEMENT THE ENGINEER AND

More information

FREDERICK COUNTY INTERAGENCY INTERNAL AUDIT AUTHORITY FREDERICK COUNTY PUBLIC SCHOOLS CONSTRUCTION MANAGEMENT PHASE II

FREDERICK COUNTY INTERAGENCY INTERNAL AUDIT AUTHORITY FREDERICK COUNTY PUBLIC SCHOOLS CONSTRUCTION MANAGEMENT PHASE II FREDERICK COUNTY INTERAGENCY INTERNAL AUDIT AUTHORITY FREDERICK COUNTY PUBLIC SCHOOLS CONSTRUCTION MANAGEMENT PHASE II Report #12-03 September 21, 2011 Frederick County Internal Audit Division TABLE OF

More information

ACG Commissioning Guideline

ACG Commissioning Guideline ACG Commissioning Guideline Appendix A Sample Commissioning Specification NOTES TO APPENDIX A This appendix contains a sample Request for Proposal (RFP) for Commissioning Services as would be issued by

More information

C. Conform to requirements of Americans with Disabilities Act (ADA).

C. Conform to requirements of Americans with Disabilities Act (ADA). SECTION 28 31 00 - FIRE ALARM AND DETECTION SYSTEMS PART 1 - GENERAL 1.1 SECTION INCLUDES A. Fire alarm and detection systems 1.2 REFERENCES A. NFPA 70 - National Electrical Code B. NFPA 72 - National

More information

Request for Proposal No. RFP02658. Project Construction Management Services. for. Capital Levy BTA IV Project: Ingraham High School Classroom Addition

Request for Proposal No. RFP02658. Project Construction Management Services. for. Capital Levy BTA IV Project: Ingraham High School Classroom Addition Seattle Public Schools Contracting Services 2445 Third Avenue South Seattle, WA 98134 Telephone: (206) 252-0566 Fax: (206) 743-3018 contractingservices@seattleschools.org Request for Proposal No. RFP02658

More information

ANNUAL FIRE PROTECTION SUMMARY INFORMATION REPORTING GUIDE Revised: May 2011

ANNUAL FIRE PROTECTION SUMMARY INFORMATION REPORTING GUIDE Revised: May 2011 ANNUAL FIRE PROTECTION SUMMARY INFORMATION REPORTING GUIDE Revised: May 2011 Organizations responsible for maintaining property under stewardship of DOE and the Administrator, NNSA, will seek concurrence

More information

Copyright 2011 S&S Sprinklers All Rights Reserved. Family Honesty Integrity Spiritual Growth Fairness Teamwork

Copyright 2011 S&S Sprinklers All Rights Reserved. Family Honesty Integrity Spiritual Growth Fairness Teamwork Copyright 2011 S&S Sprinklers All Rights Reserved Family Honesty Integrity Spiritual Growth Fairness Teamwork AUTOMATIC SPRINKLERS Wet, Dry, Pre-Action & Deluge Sprinkler Systems Foam Systems Standpipes

More information

Fire Alarm Systems Certification

Fire Alarm Systems Certification Fire Alarm Systems Certification The skills and knowledge listed under each task are suggestive of those involved in that task, but are not intended to constitute an exhaustive listing. 2.1 Submittal Preparation

More information

Inspection and Testing of Water-Based Systems

Inspection and Testing of Water-Based Systems Inspection and Testing of Water-Based Systems Standard Model/Computer-Based Testing Level III Content Outline The candidate for NICET certification at Level III in the Inspection and Testing of Water-Based

More information

University Design Standard. Fire Alarm Systems

University Design Standard. Fire Alarm Systems University Design Standard Fire Alarm Systems 1.0 Overview This document provides Virginia Tech s standards for the design and installation of fire alarm systems and equipment in new construction, retrofit

More information

Texas Commission on Environmental Quality Page 1 Chapter 293 - Water Districts

Texas Commission on Environmental Quality Page 1 Chapter 293 - Water Districts Texas Commission on Environmental Quality Page 1 SUBCHAPTER F: DISTRICT ACTIONS RELATED TO CONSTRUCTION PROJECTS AND PURCHASE OF FACILITIES 293.62-293.70 Effective November 13, 2014 293.62. Construction

More information

INSPECTION AND TESTING OF FIRE ALARM SYSTEMS

INSPECTION AND TESTING OF FIRE ALARM SYSTEMS Page 1 January 2, 2009 INSPECTION AND TESTING OF FIRE ALARM SYSTEMS Introduction Early warning plays a key role in a healthcare facility s ability to safely evacuate its residents during a fire emergency.

More information

Centers for Medicare and Medicaid Services Emergency Preparedness Regulations, Standards and Guidance

Centers for Medicare and Medicaid Services Emergency Preparedness Regulations, Standards and Guidance Centers for Medicare and Medicaid Services Emergency Preparedness Regulations, Standards and Guidance 483.70 Physical Environment State Operation Manual Guidance to Surveyors for Long Term Care Facilities

More information

Core & Shell Construction. Rules and Regulations

Core & Shell Construction. Rules and Regulations Core & Shell Construction Rules and Regulations 1. Protection: During the construction Contractor shall endeavor to protect all areas of work from damage caused by workers, weather or equipment. 2. Permits

More information

CHAPTER 69A-46 FIRE PROTECTION SYSTEM CONTRACTORS AND SYSTEMS

CHAPTER 69A-46 FIRE PROTECTION SYSTEM CONTRACTORS AND SYSTEMS CHAPTER 69A-46 FIRE PROTECTION SYSTEM CONTRACTORS AND SYSTEMS 69A-46.001 69A-46.010 69A-46.015 69A-46.016 69A-46.0165 69A-46.017 69A-46.025 69A-46.030 69A-46.035 69A-46.040 69A-46.041 Scope Submission

More information

Fraternity and Sorority House Fire Safety

Fraternity and Sorority House Fire Safety Fraternity and Sorority House Fire Safety Buddy Dewar Director of Regional Operations National Fire Sprinkler Association 850-222-2070 How To Manage Greek Housing Fire Sprinkler Retrofit Brief Overview.

More information

Fire Code Inspector II

Fire Code Inspector II Class specifications are intended to present a descriptive list of the range of duties performed by employees in the class. Specifications are not intended to reflect all duties performed within the job.

More information

Replacement of Heat System Components

Replacement of Heat System Components STATEMENT OF WORK FOR Replacement of Heat System Components At Warehouse Takoraudantie 4 08/17/2013 REV 8-24-13 Project 2013-021 Page 1 of 6 1.0 INTRODUCTION 1.1 Overview: The U.S. Embassy Helsinki has

More information

9770 CULVER BOULEVARD CULVER CITY, CA 90232-0507 www.culvercity.org. Incidental improvements: improvements that do not qualify as minor or

9770 CULVER BOULEVARD CULVER CITY, CA 90232-0507 www.culvercity.org. Incidental improvements: improvements that do not qualify as minor or 9770 CULVER BOULEVARD CULVER CITY, CA 90232-0507 www.culvercity.org Construction Permitting Guidelines for Businesses Moving into Existing Buildings in Culver City If your business is moving into an existing

More information

Invitation to Bid FIRE ALARM & DETECTION SYSTEM

Invitation to Bid FIRE ALARM & DETECTION SYSTEM Invitation to Bid FIRE ALARM & DETECTION SYSTEM Responses to an Invitation to Bid will be received by the Purchasing Supervisor, Sumner County Board of Education, 1500 Airport Road, Gallatin, TN 37066

More information

bgw architectural process

bgw architectural process bgw architectural process your solution based on solid, proven expertise The Phase I-V Timeline takes the Building God s Way (BGW) process from preliminary design through completion of construction and

More information

INSPECTION, TESTING AND MAINTENANCE OF FIRE PROTECTION SYSTEMS AND EQUIPMENT

INSPECTION, TESTING AND MAINTENANCE OF FIRE PROTECTION SYSTEMS AND EQUIPMENT CITY OF SPRING LAKE PARK Code Enforcement Department 1301 81 st Avenue NE Spring Lake Park MN 55432 Business Phone 763-784-6491 Fax 763-792-7257 INSPECTION, TESTING AND MAINTENANCE OF FIRE PROTECTION SYSTEMS

More information

PART 70 - ADMINISTRATION AND MANAGEMENT

PART 70 - ADMINISTRATION AND MANAGEMENT CHAPTER 70-4 INTERNAL AND EXTERNAL REVIEWS 70-4.1 INTRODUCTION................ (70-4) 1 70-4.2 REVIEWING ORGANIZATIONS.......... (70-4) 1 70-4.3 MANAGEMENT CONTROL............. (70-4) 3 70-4.4 GUIDELINES

More information

Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents

Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents Administration of Project: Local Higher Education Project Name Shideler Hall Renovation Response Deadline 12/20/13

More information

FIRE SPRINKLER SYSTEM DESIGN, ENGINEERING EXEMPTION POLICY FOR (Effective April 1, 2006)

FIRE SPRINKLER SYSTEM DESIGN, ENGINEERING EXEMPTION POLICY FOR (Effective April 1, 2006) State of Tennessee Department of Commerce and Insurance Board of Architectural and Engineering Examiners 500 James Robertson Parkway Nashville, TN 37243 1142 800 256 5758 615 741 3221 (Nashville Area)

More information

Inspection, Testing and Maintenance

Inspection, Testing and Maintenance Page 18 ABOUT CODE CORNER CCFS would like to remind you to check with your local Authority Having Jurisdiction (AHJ) for questions and opinions concerning your local Fire and Building Codes. The information

More information

Construction Management and project process

Construction Management and project process Construction Management and project process Presented by: Vourvoutsiotis Apostolos GSO University of Applied Science Nürnberg 06.04.2000 Table of Contents Construction Management and project process Construction

More information

Covance Construction Management Staffing Plan Chandler, Arizona

Covance Construction Management Staffing Plan Chandler, Arizona INTRODUCTION: This Construction Management (CM) Staffing Plan has been prepared for Covance to identify the critical organizational structure necessary to successfully complete the Chandler project according

More information

THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME A PART OF THIS SOLICITATION. Amend Invitation to Bid 14-MC-2194 as follows:

THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME A PART OF THIS SOLICITATION. Amend Invitation to Bid 14-MC-2194 as follows: Denver Public Schools Purchasing Department 1617 S. Acoma St. Denver, Colorado 80223 INVITATION TO BID 14-MC-2194 ADDENDUM NUMBER ONE January 24, 2014 THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM

More information

FIRE ALARM /FIRE PROTECTION OUTAGE/IMPAIRMENT RESPONSE GUIDELINE

FIRE ALARM /FIRE PROTECTION OUTAGE/IMPAIRMENT RESPONSE GUIDELINE Page 1 of 10 FIRE ALARM /FIRE PROTECTION OUTAGE/IMPAIRMENT RESPONSE GUIDELINE SYSTEM TESTING 1. Testing of the Fire Alarm and Fire Protection Systems 1.1. The Building Engineer, Electrician, Plumber (or

More information

Maintaining Fire Protection Systems

Maintaining Fire Protection Systems Maintaining Fire Protection Systems Fire continues to be a major threat to your business and your personal safety. Each year several thousand people are injured or killed by fires and billions of dollars

More information

GENERAL INFORMATION. REQUIRED SERVICES: are described in the enclosure consisting of 4 pages, dated 3/29/12 OR: are described as follows:

GENERAL INFORMATION. REQUIRED SERVICES: are described in the enclosure consisting of 4 pages, dated 3/29/12 OR: are described as follows: These documents consist of three parts (Part A - Request for Proposals; Part B - Proposal Form; Part C - Contract Award, Notice to Proceed & Invoice Summary), -- plus the current edition dated February

More information

Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents

Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents Administration of Project: Local Higher Education Project Name RH-Renovations Summer 2013 Response Deadline 1/03/13

More information

Commissioning Hospital Construction

Commissioning Hospital Construction Commissioning Hospital Construction Kenneth E. Toombs Toombs & Associates Engineering Specialists, Inc. Synopsis Not only does hospital construction warrant the commissioning process, but it also requires

More information

Sample Company SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES

Sample Company SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES A. The Owner will contract separately and directly for the majority of the commissioning work

More information

CODE ENFORCEMENT AND CERTIFICATION OF INSPECTORS FOR PUBLIC SCHOOLS, CHARTER SCHOOLS AND JUNIOR COLLEGES

CODE ENFORCEMENT AND CERTIFICATION OF INSPECTORS FOR PUBLIC SCHOOLS, CHARTER SCHOOLS AND JUNIOR COLLEGES DEPARTMENT OF PUBLIC SAFETY CODE ENFORCEMENT AND CERTIFICATION OF INSPECTORS FOR PUBLIC SCHOOLS, CHARTER SCHOOLS AND JUNIOR COLLEGES 8 CCR 1507-30 [Editor s Notes follow the text of the rules at the end

More information

Choosing an Assisted Living Facility: Comparing Apples to Apples!

Choosing an Assisted Living Facility: Comparing Apples to Apples! Choosing an Assisted Living Facility: Comparing Apples to Apples! A Report Provided by Wisconsin Association of Homes and Services for the Aging 204 South Hamilton Street Madison WI 53703 (608) 255-7060

More information

c. As mandated by law, facilities must obtain and maintain valid zoning permits as well as permits for intended use.

c. As mandated by law, facilities must obtain and maintain valid zoning permits as well as permits for intended use. Walmart Standards for Suppliers Section 7. Health and Safety 7. Health and Safety Suppliers must provide workers with a safe and healthy work environment. Suppliers must take proactive measures to prevent

More information

INSURANCE REQUIREMENTS (A) This insert applies to the following State Contracts:

INSURANCE REQUIREMENTS (A) This insert applies to the following State Contracts: INSURANCE REQUIREMENTS (A) This insert applies to the following State Contracts: General Conditions of the Construction Contract Design/Bid/Build (SC-6.23), or Contractors Agreement Design/Bid/Build (SC-6.21),

More information

PROJECT AND CONSTRUCTION MANAGEMENT SERVICES FOR KUWAIT PORT AUTHORITY FOR PROJECTS AT SHUAIBA PORT

PROJECT AND CONSTRUCTION MANAGEMENT SERVICES FOR KUWAIT PORT AUTHORITY FOR PROJECTS AT SHUAIBA PORT PROJECT AND CONSTRUCTION MANAGEMENT SERVICES FOR KUWAIT PORT AUTHORITY FOR PROJECTS AT SHUAIBA PORT - INTRODUCTION 1.1. General. Kuwait Ports Authority (KPA) through the Ministry Of Finance (MOF) wishes

More information

APPLICATION FOR ADULT DAYCARE CENTERS PROFESSIONAL AND GENERAL LIABILITY INSURANCE

APPLICATION FOR ADULT DAYCARE CENTERS PROFESSIONAL AND GENERAL LIABILITY INSURANCE APPLICATION FOR ADULT DAYCARE CENTERS PROFESSIONAL AND GENERAL LIABILITY INSURANCE APPLICANT S INSTRUCTIONS: 1. Answer all questions. If the answer requires detail, please attach a separate sheet. 2. Application

More information

FIRE SUPPRESSION CONTRACTORS GENERAL LIABILITY APPLICATION

FIRE SUPPRESSION CONTRACTORS GENERAL LIABILITY APPLICATION x x FIRE SUPPRESSION CONTRACTORS GENERAL LIABILITY APPLICATION 1. First Named Insured: 2. Street Address: Mailing Address (if different than above): Additional Locations (if any): a. b. c. If additional

More information

1. GENERAL. Attachment 1 Page 1 of 7

1. GENERAL. Attachment 1 Page 1 of 7 STATEMENT OF WORK Fire Alarm and Fire Suppression Systems Testing, Inspection, Maintenance, and Repair SOUTH TEXAS VETERANS HEALTH CARE SYSTEM - KERRVILLE 1. GENERAL 1.1 General: This is a non-personal

More information

Report of the New York State Governor s Task Force on. Campus Fire Safety

Report of the New York State Governor s Task Force on. Campus Fire Safety Report of the New York State Governor s Task Force on Campus Fire Safety July 2000 Table of Contents Task Force Members / ii Task Force Letter to Governor George E. Pataki / iii I. Executive Summary A

More information

Rio Hondo Community College District Measure A General Obligation Bonds Fund Performance Audit Year Ended June 30, 2015 With Report of Independent

Rio Hondo Community College District Measure A General Obligation Bonds Fund Performance Audit Year Ended June 30, 2015 With Report of Independent Year Ended June 30, 2015 With Report of Independent Auditors Year Ended June 30, 2015 With Report of Independent Auditors Table of Contents PAGE REPORT OF INDEPENDENT AUDITORS 1 PERFORMANCE AUDIT Objectives

More information

ALBERTA FIRE CODE SAFETY EQUIPMENT MAINTENANCE REQUIREMENTS

ALBERTA FIRE CODE SAFETY EQUIPMENT MAINTENANCE REQUIREMENTS ALBERTA FIRE CODE SAFETY EQUIPMENT MAINTENANCE REQUIREMENTS In this document are the fire safety equipment maintenance requirements that are found in Division B of the Alberta Fire Code (AFC 2006) for

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 903 CONSTRUCTION QC/QA PROGRAM

San Antonio Water System Standard Specifications for Construction ITEM NO. 903 CONSTRUCTION QC/QA PROGRAM ITEM NO. 903 CONSTRUCTION QC/QA PROGRAM 903.1 DESCRIPTION: This item shall govern the preparation and implementation of the Contractor s Construction Quality Control/Quality Assurance (QC/QA) Program for

More information

MINNESOTA HEALTH CARE ENGINEERS IN ASSISTED LIVING FACILITIES

MINNESOTA HEALTH CARE ENGINEERS IN ASSISTED LIVING FACILITIES MINNESOTA HEALTH CARE ENGINEERS FIRE/LIFE SAFETY IN ASSISTED LIVING FACILITIES September 13, 2012 MINNESOTA HEALTH CARE ENGINEERS FIRE/LIFE SAFETY IN ASSISTED LIVING FACILITIES WELCOME Exits Restrooms

More information

1 OF 7. there will be few "surprises" as the work progresses.

1 OF 7. there will be few surprises as the work progresses. 1 OF 7 FP-G1.94 GUIDELINES FOR SUCCESSFUL SUPERVISION OF SCHOOL DISTRICT CAPITAL CONSTRUCTION PROJECTS There is no doubt that the successful completion of any capital construction project is the result

More information

RHODE ISLAND DIVISION OF STATE FIRE MARSHAL

RHODE ISLAND DIVISION OF STATE FIRE MARSHAL RHODE ISLAND DIVISION OF STATE FIRE MARSHAL Smoke Alarm and Carbon Monoxide Brochure JOHN E. CHARTIER STATE FIRE MARSHAL 118 PARADE STREET PROVIDENCE, RI 02909 DAYS 401-462-4200 24 Hr. 401-222-2331 FAX#

More information

PROCUREMENT PRACTICES AT PUBLIC HOUSING AGENCIES

PROCUREMENT PRACTICES AT PUBLIC HOUSING AGENCIES PROCUREMENT PRACTICES AT PUBLIC HOUSING AGENCIES Table of Contents Procurement Regulations and Agency 3 Procurement Policies and Procedures 3 Roles and Responsibilities 4 Board of Commissioners 4 Sample

More information

KITCHEN AND BATH REMODELING BUILDING PERMIT REQUIREMENTS

KITCHEN AND BATH REMODELING BUILDING PERMIT REQUIREMENTS St. Louis County Department of Public Works Division of Code Enforcement KITCHEN AND BATH REMODELING BUILDING PERMIT REQUIREMENTS This guideline is intended to provide the homeowner/contractor with the

More information

REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES. PASSENGER SCREENING CHECKPOINT CONSOLIDATION PROJECT PROJECT No.

REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES. PASSENGER SCREENING CHECKPOINT CONSOLIDATION PROJECT PROJECT No. REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES PASSENGER SCREENING CHECKPOINT CONSOLIDATION PROJECT PROJECT No. FY15-805-67 Manchester-Boston Regional Airport is soliciting Proposals from qualified

More information

RURAL UTILITIES SERVICE

RURAL UTILITIES SERVICE Rural Development United States Department of Agriculture RURAL UTILITIES SERVICE RUS Bulletin 1738-2 Rural Broadband Access Loan and Loan Guarantee Advance and Construction Procedures Guide Page 1 According

More information

OCCUPATIONAL GROUP: Facilities Support. CLASS FAMILY: Facility Management CLASS FAMILY DESCRIPTION:

OCCUPATIONAL GROUP: Facilities Support. CLASS FAMILY: Facility Management CLASS FAMILY DESCRIPTION: OCCUPATIONAL GROUP: Facilities Support CLASS FAMILY: Facility Management CLASS FAMILY DESCRIPTION: This family of positions includes those whose purpose is to oversee the operations of or the construction

More information

H O M E F I R E S P R I N K L E R S S A V E L I V E S, M O N E Y A N D W A T E R A G U I D E F O R W A T E R P U R V E Y O R S

H O M E F I R E S P R I N K L E R S S A V E L I V E S, M O N E Y A N D W A T E R A G U I D E F O R W A T E R P U R V E Y O R S H O M E F I R E S P R I N K L E R S S A V E L I V E S, M O N E Y A N D W A T E R A G U I D E F O R W A T E R P U R V E Y O R S HomeFireSprinkler.org F I R E T H E L A R G E ST S I N G L E C AU S E O F

More information

MERCER ISLAND FIRE DEPARTMENT FIRE COMMERCIAL SPRINKLER STANDARDS

MERCER ISLAND FIRE DEPARTMENT FIRE COMMERCIAL SPRINKLER STANDARDS MERCER ISLAND FIRE DEPARTMENT FIRE COMMERCIAL SPRINKLER STANDARDS COMMERCIAL FIRE SPRINKLER SYSTEMS Page 1-5 SCOPE: Fire sprinkler systems in the City of Mercer Island shall meet the criteria as set forth

More information

REQUEST FOR QUALIFICATIONS CONSULTANT ARCHITECTURAL SERVICES FOR VARIOUS TOWN BUILDINGS FOR THE PUBLIC WORKS DEPARTMENT, TOWN OF GROTON, CT

REQUEST FOR QUALIFICATIONS CONSULTANT ARCHITECTURAL SERVICES FOR VARIOUS TOWN BUILDINGS FOR THE PUBLIC WORKS DEPARTMENT, TOWN OF GROTON, CT REQUEST FOR QUALIFICATIONS CONSULTANT ARCHITECTURAL SERVICES FOR VARIOUS TOWN BUILDINGS FOR THE PUBLIC WORKS DEPARTMENT, TOWN OF GROTON, CT Statements of Qualification for the selection of on-call architectural

More information

The purpose of the policy is to establish guidelines for the administration of the School Planning and the School Construction programs.

The purpose of the policy is to establish guidelines for the administration of the School Planning and the School Construction programs. SCHOOL PLANNING/SCHOOL CONSTRUCTION PROGRAMS Effective: August 14, 2014 I. Policy Statement The Board of Education is responsible for providing safe, engaging and supportive educational and work environments

More information

FIRE SUPPRESSION CONTRACTORS GENERAL LIABILITY APPLICATION

FIRE SUPPRESSION CONTRACTORS GENERAL LIABILITY APPLICATION QSR www.qsr-insurance.com 212 Christopher Way, Suite 12 Eatontown, New Jersey 07724 P: (732) 223-6666 F: (732) 223-9072 Producer: Producer Is: Wholesaler Retailer Address: Telephone: Fax: Excess & Surplus

More information

Basement Finishing 101: The Essential Guide to Finishing Your Basement

Basement Finishing 101: The Essential Guide to Finishing Your Basement Are you tired of walking into a dark, disorganized basement? Do you wish that you had more finished space in your home? Do you want to finish your basement, but don t know where to begin? Do you want to

More information

FIRE ALARM SYSTEM RECORD OF COMPLETION

FIRE ALARM SYSTEM RECORD OF COMPLETION FUNDAMENTALS OF FIRE ALARM SYSTEMS 72 33 FIRE ALARM SYSTEM RECORD OF COMPLETION To be completed by the system installation contractor at the time of system acceptance and approval. 1. PROTECTED PROPERTY

More information

Overview 1) Grantee s procurement requirements must be in conformance with the appropriate applicable Federal, State, and local laws.

Overview 1) Grantee s procurement requirements must be in conformance with the appropriate applicable Federal, State, and local laws. The award of Federal funds does not exempt the Grantee organization from compliance with State, and local requirements. When similar requirements exist at all levels, the rule of thumb is that the most

More information

527 CMR: BOARD OF FIRE PREVENTION REGULATIONS

527 CMR: BOARD OF FIRE PREVENTION REGULATIONS 527 CMR 31.00: CARBON MONOXIDE ALARMS Section 31.01: Purpose and Scope 31.02: Definitions 31.03: General Installation Provisions 31.04: Specific Installation Provisions 31.05: Carbon Monoxide Protection:

More information

bout your HOUSE Hiring a contractor

bout your HOUSE Hiring a contractor A bout your HOUSE Hiring a contractor CE 26 a At some time, most homeowners will hire someone for repairs or renovations. Even a homeowner experienced in home repairs may have to hire a contractor or renovator

More information

FIRE ALARM SYSTEM RECORD OF COMPLETION

FIRE ALARM SYSTEM RECORD OF COMPLETION FIRE ALARM SYSTEM RECORD OF COMPLETION To be completed by the system installation contractor at the time of system acceptance and approval. 1. Protected Property Information Name of property: Description

More information

SACRAMENTO VALLEY FIRE MARSHALS ASSOCIATION

SACRAMENTO VALLEY FIRE MARSHALS ASSOCIATION SACRAMENTO VALLEY FIRE MARSHALS ASSOCIATION Sacramento Valley Fire Marshals Association Standards Article No: 10 Section: CFC 1003.1 Standard No: 13 Title: Centrifugal Fire Pumps Date: April 24, 2002 Revised:

More information

Construction Services Procedure

Construction Services Procedure Construction Services Procedure Table of Contents.1 General Information... 2.2 Process Overview... 2.3 Who Needs to Know This Procedure... 2.4 Roles and Responsibilities... 2.5 Types of Construction Contracts...

More information

Nursing Home Checklist

Nursing Home Checklist Nursing Home Checklist Name of nursing home: Date of visit: Address: City, State and Zip: Telephone number: Email: Contact person: Note: Not all of the following are facility requirements, but markers

More information

ALVERNIA UNIVERSITY OSHA REGULATION: 29 CFR 1910.252 WELDING, CUTTING, AND BRAZING ( HOT WORK ) SECTION: 3600

ALVERNIA UNIVERSITY OSHA REGULATION: 29 CFR 1910.252 WELDING, CUTTING, AND BRAZING ( HOT WORK ) SECTION: 3600 OSHA REGULATION: 9 CFR 90.5 WELDING, CUTTING, AND BRAZING ( HOT WORK ) A. POLICY. This procedure follows requirements set forth in 9 CFR 90.5.. This policy applies to all Hot Work operations being done

More information

U.S. Department of Health and Human Services. Centers for Medicare & Medicaid Services Region II

U.S. Department of Health and Human Services. Centers for Medicare & Medicaid Services Region II U.S. Department of Health and Human Services Centers for Medicare & Medicaid Services Region II FINAL REPORT New Jersey EPSDT Review Report Dental Services March 2008 Site Visit Executive Summary The Early

More information

MEDICARE DRUG INTEGRITY CONTRACTORS IDENTIFICATION

MEDICARE DRUG INTEGRITY CONTRACTORS IDENTIFICATION Department of Health and Human Services OFFICE OF INSPECTOR GENERAL MEDICARE DRUG INTEGRITY CONTRACTORS IDENTIFICATION OF POTENTIAL PART D FRAUD AND ABUSE Daniel R. Levinson Inspector General October 2009

More information

Experts in Life Safety and Security Systems since 1977

Experts in Life Safety and Security Systems since 1977 Experts in Life Safety and Security Systems since 1977 Bass-United. Your Go-To Team For Life Safety and Security Solutions. Bass-United began in 1977 with one man and his passion for life safety and technology.

More information

Columbia University Medical Center. Policies and Procedures for Shutdowns and Modifications to Fire Alarm Systems and Fire Suppression Systems

Columbia University Medical Center. Policies and Procedures for Shutdowns and Modifications to Fire Alarm Systems and Fire Suppression Systems Columbia University Medical Center Policies and Procedures for Shutdowns and Modifications to Fire Alarm Systems and Fire Suppression Systems 1. Modifications to Fire Alarm or Fire Suppression System A.

More information

OSHA Regulation and the Growing Popularity of Employee Leasing Programs. Including Temporary Worker Services and Professional Employer Organizations

OSHA Regulation and the Growing Popularity of Employee Leasing Programs. Including Temporary Worker Services and Professional Employer Organizations OSHA Regulation and the Growing Popularity of Employee Leasing Programs Including Temporary Worker Services and Professional Employer Organizations Jeffry Carter RMS Regulatory Services John D. Surma Of

More information

PROPOSED FIRE INSPECTION SYSTEM THIRD PARTY REPORTING

PROPOSED FIRE INSPECTION SYSTEM THIRD PARTY REPORTING 2013 Officers President Richard King BOMA SW Florida (954) 927-6119 Vice President Lacey Willard BOMA Gtr Tampa Bay (813) 273-8412 Treasurer Rick Beaver BOMA Jacksonville (904) 504-9405 Secretary Chris

More information

Health Care Facilities

Health Care Facilities Health Care Facilities CHAPTER 25 Joseph M. Jardin A large Illinois hospital undergoing a sprinkler retrofit quickly discovered the benefits of upgrading its system when sprinklers confined a fire caused

More information

Florida Healthcare Engineering Association

Florida Healthcare Engineering Association Life Safety Accreditation Challenges A PRESENTATION FOR Florida Healthcare Engineering Association Dean Samet, Director of Regulatory Compliance dsamet@ssr-inc.com, cell 615-388-0332 Copyright 2011 Smith

More information

MULTI- PURPOSE HALL. College Station, Texas January 17, 2015

MULTI- PURPOSE HALL. College Station, Texas January 17, 2015 BID SOLICITATION FOR CONSTRUCTION PROJECT MANAGEMENT MULTI- PURPOSE HALL College Station, Texas January 17, 2015 A. PURPOSE Islamic Community of Bryan- College Sation, Texas (ICBCS) solicits bids for Project

More information

Tennessee s Facility Management Outsourcing State of Tennessee Department of General Services

Tennessee s Facility Management Outsourcing State of Tennessee Department of General Services State of Tennessee Department of General Services Robert E. Oglesby Commissioner of General Services 312 Rosa L. Parks Avenue 22 nd Floor Nashville, Tennessee 37243 Bob.Oglesby@tn.gov Summary The Tennessee

More information

WORK RULES AND CONTRACTOR REQUIREMENTS FOR ALL UNIT OWNERS & UNIT OWNER CONTRACTORS PERFORMING WORK ON THE PREMISES AT HAWTHORNE PLACE CONDOMINIUMS

WORK RULES AND CONTRACTOR REQUIREMENTS FOR ALL UNIT OWNERS & UNIT OWNER CONTRACTORS PERFORMING WORK ON THE PREMISES AT HAWTHORNE PLACE CONDOMINIUMS WORK RULES AND CONTRACTOR REQUIREMENTS FOR ALL UNIT OWNERS & UNIT OWNER CONTRACTORS PERFORMING WORK ON THE PREMISES AT HAWTHORNE PLACE CONDOMINIUMS 1) GENERAL GUIDELINES a) The following rules, regulations,

More information