1 Construction / Renovation Safety Program Prepared by: Environmental Health and Safety 11/3/ Commonwealth Avenue 85 E. Newton Street, M-470 Boston, Massachusetts Boston, Massachusetts (617) (617)
2 1. Purpose and Scope 1.1. The purpose of this program is to describe the process of developing project safety plans that identify potential hazards and the interim safety measures that minimize those hazards and disruptions during renovation or construction activities. It is intended to ensure an adequate level of safety when existing safety measures are disrupted due to work in an area. This plan applies to internal and external work Whenever possible this document will be provided in project bid packages. 2. References 2.1. Regulations Local Boston Fire Code Brookline Fire Code Cambridge Fire Code State Massachusetts State Building Code, CMR 780 Massachusetts Fire Prevention Regulations Massachusetts Department of Environmental Protection, 310 CMR 7.15 Asbestos Massachusetts Department of Environmental Protection, 310 CMR Hazardous Waste Federal Occupational Safety and Health Administration, 29 CFR 1910 Environmental Protection Agency, 40 CFR Part 745, Lead; Renovation, Repair, and Painting Program Guidelines and Standards National Fire Protection Association (NFPA) NFPA 101 (Life Safety Code) NFPA 10 (fire extinguishers) National Electric Code National Plumbing Code 2.2. Related Programs Asbestos Management Plan Fire Response Plan Laboratory Decommissioning Plan Control of Hazardous Energy (LOTO) Confined Space Entry Lead Management Plan Page 2 of 19
3 3. Definitions 3.1 Construction and demolition is defined as any physical change which involves the wrecking, taking out, removal, stripping of, or altering of a building structure or appurtenances. Appurtenances such as, but not limited to; HVAC equipment and components, piping, boilers, condensate tanks, lighting, and all building operations equipment. Boston University further defines construction as all new construction or any project that involves the removal of load bearing walls, partitions or smoke/fire walls and/or the erection of same or any work which compromises the Life Safety Code. In addition, any project which involves hazardous materials, or in the opinion of a representative of the EHS or the BU/BMC Construction Project Manager, has the potential for providing a hazard that could compromise safety, shall be considered a construction project requiring the implementation of one or more measures outlined this Program. Please Note: A Department of Environmental Protection (DEP) notification is required for demolition activities. Please see Appendix VII for its use and application. 3.2 Interim life safety measures (ILSM s) are administrative or physical systems to temporarily compensate for fire hazards posed by construction activities. ILSM s to be implemented during projects will be determined during the pre-construction planning meeting with EHS, the BU Project Manager and involved contractors or FMP trades personnel. Identified ILSM s apply to all personnel, including construction workers, and are assessed for implementation upon project development, and enforced through project completion. One or more ILSM s may be implemented as defined in this program. 4. Roles & Responsibilities Environmental Health and Safety (EHS) is responsible for determining the level of implementation of this plan. EHS will determine what safety measures including ILSM s will be used and to what degree and will determine if the potential for disruption in sensitive areas (patient care, research, etc) requires unique measures EHS will periodically inspect the project for proper implementation of the plan. Facilities Management and Planning (FMP) is responsible for identifying a Project Manager for activities performed by internal or external staff that constitute Construction Demolition as defined in Section 3.1. FMP will ensure all interim measures are in place for the duration of the project. FMP will distribute construction and design coordination meeting minutes identifying work being planned. Information Services and Technology (IS&T) is responsible for identifying a Project Manager for activities performed by internal or external staff that constitute Construction as defined in Section 3.1. IS&T will ensure all interim measures are in place for the duration of the project Page 3 of 19
4 BU Project Manager is responsible for ensuring the implementation of this plan and any other related BU policy or procedure. The Project Manager will report any variations or violations of the plan to EHS. A Project Manager is any BU employee, from any department, who is responsible for any renovation, cosmetic, construction, utility, or infrastructure improvement project. Contractors and BU Employees and Staff will comply with this plan, applicable regulations and standards, and other related BU policies and procedures. 5. Special Requirements 5.1. Equipment and Supplies Required As dictated by the development of the site specific safety plan under this plan Safety Requirements See Procedures, section 7 of this plan Training Contractor / Worker Training. Prior to commencing work on any construction project the Project Manager and the Principal in charge of each contracting firm on the project will read, acknowledge and sign the Contractors Agreement. They will also be responsible for ensuring that all project workers (in-house or contractors) have each been trained on the site specific safety plan Contractors and vendors will be provided appendix III which lists safety rules when working in laboratories and patient areas Monitoring Requirements Projects requiring negative air containment will be checked continuously by the General Contractor or BU FMP project manager. A magnehelic monitor or similar device installed directly adjacent to the entrance door of the project area. Monitor device readings shall be posted on a log sheet posted on the Board Personnel Protective Equipment (PPE) Will be reviewed and discussed at the preconstruction safety meeting. 6. Applicable Locations 6.1. This plan currently applies to renovation and construction projects at Boston University Page 4 of 19
5 6.2. This plan applies to all BU personnel and contractors performing work in any BU building or on BU property, including leased space. The level of implementation of this plan will be determined by EHS in cooperation with the BU Project Manager and will be administered by both EHS and the assigned BU Project Manager and Contractor representative, if applicable. 7. Procedures and Instructions 7.1. Construction and Design Coordination Meetings will be hosted by FMP and will include representatives of all areas that may be impacted by scheduled work Project Notification. BU Project Managers are responsible for notifying EHS before the start of any renovation or construction project. In addition, an EHS representative will attend scheduled FMP Construction meetings to assist in determining if a project requires a specific construction safety plan. As new projects are planned and discussed, the EHS representative will assess if a project requires a specific safety plan. The construction minutes will reflect if a project has been waived of a site specific plan or if a safety planning meeting has been scheduled Project Safety Planning. The BU Project Manager will request a safety planning meeting with EHS to review the scope of work and develop a site specific safety plan through the Preconstruction Risk Assessment. The safety plan including any identified ILSM s will be documented. The BU Project Manager will schedule the appropriate project contractor(s) and / or FMP staff conducting related project tasks for meeting attendance. These meetings may also be requested by EHS during the construction meeting Work Stoppage. EHS is authorized to stop work on any project which is not adhering to the agreed upon safety plan. Prior to shutdown, notification shall be made to FMP Leadership, the Project Manager, the Director of Campus and Clinical Safety, the Executive Director Research Compliance, and if necessary the Associate Vice President Research Compliance and the Assistant Vice President, Campus Construction. The BU Project Manager will modify the scope of work or project schedule to maintain compliance with the safety plan. Any modifications will be reviewed by EHS prior to resumption of construction activities. EHS has the authority to stop any work that is immediately dangerous to life and/or health. Notifications to those listed above will be made as soon as practical Inspections. An inspection of the construction area and surrounding areas may be conducted by EHS on a weekly basis depending on the scope of the project. The inspection will be documented utilizing the EHS Safety Information Management System (SIMS) should deficiencies be noted. All deficiencies will be reported to the Project Manager or designee for timely correction. Deficiencies that are immediately dangerous to life and/or health will be corrected immediately and reported directly to the BU FMP Project Manager, Director of Campus and Clinical Safety and FMP Leadership Page 5 of 19
6 7.6. Signage. The contractor will be responsible for posting proper warning notification (signage) at all entrances to the work site. The signage shall state: Construction Zone Authorized Personnel Only. The Project Manager or if directed by the Project Manager, the Contractor will install a construction safety board where all applicable permits, this risk assessment and other related safety information will be installed at the worksite entrance Permits. Obtaining and posting all required permits will be the responsibility of the contractor unless otherwise decided. Permits include but are not limited to: City Building Department, Local Fire Department, Department of Environmental Protection, Life Safety system impairments, use of torches, a copy of this safety plan, etc. Construction will not begin unless permits are on site. Copies of the permits will be posted at the job site and forwarded to the BU Project Manager and EHS, as requested. A Board will be used to post all applicable permits. It is ultimately the responsibility of the BU Project Manager that all necessary permits are obtained and posted Fire Watch. Whenever welding or cutting is anticipated, a paid local fire department detail is required. In other instances, such as, major fire alarm or fire sprinkler system impairment or malfunction, an internal qualified fire watch, other the local Fire Department personnel may be used if approved by the local Fire Department Flammables. Flammable products and materials will be properly stored in a flammable storage cabinet. A permit will be obtained through the BFD for the storage or use of flammables, per applicable BFD regulation. Only materials containing no or low Volatile Organic Compounds (VOC S) shall be used (painting materials, etc...) Compressed Gases. All compressed gases will require a BFD Permit, per applicable regulation. Flammable compressed gases are prohibited from storage inside buildings Laboratory Animal Housing Areas. All work that may involve disruption to normal operations in Laboratory Animal Housing Areas will require coordination with representatives from that area in order to minimize disruption to those operations Hazardous Materials. All hazardous materials must be considered, including hazardous materials within building materials such as asbestos and lead based paint. EHS Industrial Hygienists must be coordinated with through this plan to assess building materials that will be impacted by the project. Other hazardous materials must be considered especially when working in or around laboratories. For the purpose of this plan, hazardous materials include; certain building materials, chemicals, radioactive materials, chemotherapeutic, biological, and universal wastes. Chemical decontamination and hazardous waste disposal must be coordinated with EHS. Any radioactive decommissioning must be coordinated with Medical Physics and Radiation Safety Page 6 of 19
7 7.13. Contractor Parking. Contractors are permitted to park in authorized areas only. Parking is not allowed on sidewalks, fire lanes, or in front of fire hydrants. Vehicles parked in unauthorized areas will be towed at the owner s expense Dust Control. Every effort will be made to control dust and debris from the project area. Control measures include, but are not limited to barriers, negative air machines, dust control walk-off mats, sealing unused doors, damp mopping between tasks, High Efficiency Particulate Air (HEPA) vacuums with dust generating tools, and sealing air intakes as appropriate. Determination of these control measures will be discussed at the pre-construction safety meeting Interim life safety measures (ILSM s) will be considered for all renovation and construction projects, including demolition phases, to temporarily compensate for hazards posed by construction activities. ILSM s to be implemented during the project will be determined during the pre-construction planning meeting with EHS, the BU Project Manager and involved contractors. Identified ILSM s apply to all personnel, including construction workers, and are assessed for implementation upon project development, and enforced through project completion. One or more of the following ILSM s may be implemented for the duration of the project unless otherwise stated Egress. Any areas under construction and other affected areas must maintain exits at all times. Exit routes in affected areas may be inspected on a daily basis. This will be determined during the pre-construction safety meeting. The BU Project Manager, construction company representative, or EHS will conduct these inspections if egress is affected by the project. The Daily Egress Inspection Form shall be posted at the job site and signed daily, as determined during the planning meeting or requested by EHS. The inspection will ensure that the egress is free and unobstructed and smoke/fire doors are fully operational. Personnel in or around the area shall receive training if alternative exits must be designated Life Safety Systems. Temporary but equivalent fire systems will be used when systems are impaired. Fire systems include fire alarm, detection and suppression systems. Fire systems shall not be impaired for more than four hours. During the four (4) hour period, an authorized BU representative will be on standby at the impaired system control to initiate system reactivation in the event of building fire alarm system activation. The BUMC Control Center or BU Control Desk, and the designated BU Impairment Coordinator will be notified. Impairments longer than four (4) hours will require submittal of an Impairment Plan to the BU Impairment Coordinator for input and approval. A permit will be required for the impairment. Prior to requesting a permit for system impairment, EHS will also be consulted with the specifics of the method of impairment, equivalent measures, and duration. Impairments may require installation of a temporary, but equivalent, system. Temporary systems will be inspected and tested monthly by the appropriate licensed trade as necessary. The completion date of the tests will be documented Page 7 of 19
8 Fire Extinguishers. Additional fire-fighting equipment shall be provided as necessary and determined during the pre-construction safety meeting. Additional fire extinguishers will be provided by the contractor and will be maintained per the NFPA10 Standard. Maintenance shall include: Adequate number and type, placement for access, tamper seal, pull pin, gauge reading, label, weight, and nozzle/hose in place and undamaged. Construction personnel shall be properly trained on the use of firefighting equipment by the appropriate contractor representative. Extinguishers will be inspected monthly and serviced annually. Documentation will be provided on the extinguisher by use of a tag Construction Barrier. Temporary (hard) construction partitions that resist the passage of smoke will be noncombustible or made of limited-combustible material that will not contribute to the development or spread of fire. The need for barriers will be determined during the pre-construction safety meeting. The construction partition, including any doors or windows, must be maintained at all times until project completion. Use of additional dust barriers is considered a temporary enclosure, per fire department regulations. A permit is required for such use. Note: Polyethylene (Plastic) enclosures are not a substitute for a hard noncombustible construction partition Inspections. Increased surveillance of buildings, grounds, and equipment giving special attention to construction areas and storage, excavations, and field offices are conducted as necessary and determined during the pre-construction safety meeting. An inspection of the site will be conducted by EHS on a weekly basis, or as necessary. Deficiencies will be recorded and reported to the appropriate personnel for corrective action through the EHS SIMS Housekeeping. The storage, housekeeping, and debris-removal practices that reduce the buildings flammable and combustible fire load to the lowest feasible level is enforced as necessary and determined during the pre-construction safety meeting Training. Additional training to those that work in or around the project area on the use of fire-fighting equipment will be provided as necessary and determined during the pre-construction safety meeting. In addition, education to promote awareness of building deficiencies, construction hazards, and temporary measures implemented to maintain fire safety is conducted as necessary and determined during the pre-construction safety meeting. This notification shall be conducted by the BU Project Manager Fire Drills. A fire drill will be conducted as necessary and determined during the pre-construction safety meeting. Drills will be conducted by EHS Page 8 of 19
9 Forms The following forms are located in the appendices of this plan. Construction Notification Form Appendix I Preconstruction Risk Assessment Appendix II Safety Instructions for Contractors and Vendors Appendix III Daily Egress Inspection Form Appendix IV EHS Monitoring Form Appendix V Contractors Agreement Appendix VI Guidance for Notifying the MassDEP for Construction/Demolition Appendix VII 8. Records Management 8.1. A copy of the site-specific safety plan shall be posted at the job site. EHS will maintain all originals for the duration of the project and at least three (3) years after project completion. 9. SOP Revision History Version Section / Paragraph Changed Changes Made Effective Date V.1 N/A None, Original Version V.2 Entire Edits throughout based on March Meeting between EHS and FMP. V.3 Appendix 1 Added Appendix III Added items to Appendix II Added appendix IIV notification guidance to DEP 4/6/10 8/13/10 V.4 Sections 4, 7.1, 7.11 Added BU employees and staff responsibilities, FMP construction meetings, Lab animal housing areas requirements 9/21/ Page 9 of 19
10 Construction Notification Appendix I Date: Start Date: Completion Date: Project Number: Project: Location: Department: Scope of work: The Project Manager must request a meeting with EHS to complete the Preconstruction Risk Assessment Date Inspection Requested: Inspection Required Yes No Site Specific Planning Meeting Waived Yes No EHS Representative Signature Distribution: Safety ORC Radiation Safety (RSO) Laboratory Safety Cmt. Facilities Management Administration Return to Environmental Health and Safety Page 10 of 19
11 PRECONSRUCTION RISK ASSESSMENT Appendix II Date of Assessment: EHS Rep.: Location: Project Manager/ Project #: Yes No N/A 1. Dust control necessary? 2. Will construction affect exit routes around construction site? A. Is the Daily Egress Inspection Form needed? 3. Will any of the following systems be affected? A. Fire Alarm. If impaired, is a temporary but equivalent fire alarm system necessary? B. Sprinkler. If impaired, is a temporary but equivalent system necessary provided? C. Electrical D. Water E. Medical/Laboratory Gases F. HVAC G. Wall/ceiling cutting & patching 4. Is a local Fire Department Fire Watch required (welding, cutting, major F/A or sprinkler system impairment) 5. Will additional Fire Extinguishers be necessary? Are existing units sufficient? 6. Are temporary partitions to resist the passage of smoke/noncombustible/appropriately rated? 7. Are additional inspections of buildings, grounds, and equipment, construction areas and storage, excavations, and field offices necessary? 8. Will storage, housekeeping, and debris removal that reduce the buildings flammable and combustible fire load to the lowest feasible level be practiced? 9. Are construction personnel trained on the RACE fire plan and fire fighting equipment? Will access be unobstructed (fire extinguishers, pull stations, phones for emergency calls)? 10. Do additional fire drills need to be conducted? 11. Will temporary fire safety systems be inspected and tested monthly by the appropriate licensed trade? 12. Will affected personnel be educated on construction activities and the interim measures to promote awareness of building deficiencies and construction hazards? Yes NO N/A Page 11 of 19
12 13. Are any of the following safety/environmental hazards present? A. Asbestos B. Hazardous Materials (Chemicals, Radiation, Biohazard, Sharps, Chemotherapy) C. Flammable Products (stored in cabinet, BFD Permit) D. Compressed gases E. Confined Spaces F. Hot Work 14. Noise and Vibration Plan required/submitted? 15. Have all contractors been instructed on the NO SMOKING policy? 16. Will construction safety signs and Safety Board (Permit Posting) be posted? 17. Have the work stoppage rules been communicated? 18. Have all necessary permits been obtained and posted? 19. Have the parking rules been communicated? 20. Has Appendix III been distributed to Contractors/Vendors? Notes Project Specific Safety Measures: Page 12 of 19
13 HANDOUT FOR CONTRACTORS/VENDORS Appendix III Safety Instructions for Contractors / Vendors Working in Research Laboratories Boston University and Boston Medical Center expect all persons, including employees, visitors, vendors and contractors to fully comply with all Occupational Health and Safety and Environmental Protection regulations and standards. BU and BMC facilities include patient care, research and teaching facilities with a unique work environment, and have certain safety precautions that must be observed by everyone who enters these facilities. The following general rules are to be followed when working in any BU or BMC laboratory or patient care areas: Make prior arrangements with the Facility Project Manager for after-hours and weekend access to facilities and procedures to secure the worksite. Coordinate with the Facility Project Manager and the affected building occupants before planning any utilities interruption. Observe safety notices and warning signs posted on doors, benches, fume hoods, and cabinets. Introduce yourself to area personnel and explain the work you will be performing upon entry. Clarify with area personnel (laboratory, patient area) any necessary safety or biological safety precautions before entering or performing work in these areas. Inform the Facility Project Manager and occupants if odorous chemicals (e.g., adhesives, pesticides, paints, solvents, etc.) will be used. Provide the Facility Project Manager and EHS with MSDSs for all the chemicals used. MSDSs must be readily available at the project site. Do not remove any ceiling tiles, or open any access panels, without consulting with the Facility/Project Manager regarding potential asbestos or other hazards. Consult with Facility Project Manager regarding required safety procedures if the job requires removal of ceiling tiles. Work above ceilings in Boston Medical Center (BMC) locations; require an Above Ceiling Work Permit available from BMC Facilities. The Facility Project Manager will coordinate with laboratory personnel if ongoing experiments or sensitive equipment need to be covered, protected, or moved. Notify the Facility/Project Manager if work involves vibration or excessive noise before you perform work. Smoking is strictly prohibited in all BU and BMC buildings. No eating or drinking is permitted in any laboratory; discarding food containers, cups or wrappers in the laboratory waste container is prohibited. Do not discard any construction debris in waste containers located inside laboratories. Remove construction waste from labs, offices, hallways, and elevators Page 13 of 19
14 Do not stand or walk on any furniture or equipment. Do not turn fume hood fans off without first consulting with the Facility Project Manager and the laboratory supervisor. If a fume hood fan is shut down, notice must be posted at the affected fume hood(s). Do not block elevators, exits, corridors, hallways, emergency showers, eye washes, fire extinguishers, or other safety equipment. Report any accidents or damage in the work site to the Facility Project Manager and to the occupants immediately. Do not open windows or prop doors open. Do not leave unattended laboratory open or unlocked. Do not unplug or move any laboratory equipment or computers unless authorized by the Facility Project Manager and appropriate laboratory personnel. Clearly identify and secure all gas cylinders in an approved manner. Tying cylinders to railings is not approved! All unsecured cylinders will be disposed as hazardous waste at contractor's expense. Extension cords in use must be grounded and in good condition. Do not string extension cords across hallways or aisles. Cords must be disconnected at the end of the work shift. Non compliant cords will be removed by the Facility Project Manager or EHS. All hazardous waste generated from the project must be coordinated for disposal with EHS. Hazardous waste costs are the responsibility of the contractor. DO NOT dispose of the following in regular trash dumpsters: o Paint o Asbestos o Solvents o Compressed gas cylinders o Universal wastes (e.g. batteries, electronic components, etc.) o or other restricted wastes Environmental Health and Safety is authorized to stop all operations which are not compliant with health and safety or environmental regulations. For additional information contact the Environmental Health and Safety at (Medical Campus) or (Charles River Campus) Page 14 of 19
15 DAILY SAFETY and EGRESS INSPECTION Form to be used if deemed necessary by an EHS Appendix IV Project (name/number): LOCATION: DATE/TIME SIGNATURE DATE/TIME SIGNATURE Page 15 of 19
16 PROJECT MONITORING and SAFETY CHECKLIST Form to be used if deemed necessary by EHS Appendix V Note: EHS conducts regular inspections of projects. Deficiencies are entered in the EHS Web based Compliance Program. Date of Survey: Inspector: Location: Project number: EXITS 1. Are exits free and unobstructed? 2. Are phones/fire extinguishers/fire alarm pull boxes unobstructed? FIRE EQUIPMENT 3. Are fire alarms, detection, and suppression systems operational? Including temporary systems. YES NO N/A 4. Is additional fire fighting equipment provided, accessible, and maintained? FIRE SAFETY 5. Is the NO SMOKING policy enforced? 6. Are the work areas free from storage/debris from daily operations? 7. Are required temporary construction partitions compliant and maintained? GENERAL SAFETY 8. Is the power properly secured at the end of the shift? 9. Are hand/safety rails in place and good condition? 10. Are extension cords grounded and in good condition? 11. Are power tools and other equipment in good condition and secured when not in use? 12. Are "hot works" operations properly conducted? 13. Does scaffolding comply with OSHA requirement ( )? 14. Are construction areas, storage areas, excavations and field offices compliant and free of recognized hazards? 15. Are good housekeeping practices employed? 16. Dust Control Compliance 17. ILSM Compliance Page 16 of 19
17 18. Signage posted at entry(s) to the job site? 19. All Project Permits posted on site Board? COMMENTS: Page 17 of 19
18 Appendix VI PROJECT AGREEMENT I have read, understood, and will instruct all of my personnel on the provisions outlined in this plan. Print Name Signature Date Contractor Project Manager BU Project Manager EHS Representative BU In House FMP Staff THIS ENTIRE DOCUMENT WILL BE POSTED ON THE PROJECT CONSTRUCTION SAFETY BOARD Page 18 of 19
19 Appendix VII Guidance for Notifying MassDEP for Construction/Demolition The following are the requirements for notifying the MassDEP for Construction and Demolition activities. Construction and demolition is defined as any physical change which involves the wrecking, taking out, removal, stripping of, or altering to a structure. Boston University further defines construction as all new construction or any project that involves the removal of load bearing walls or smoke/fire walls and/or the erection of same or any work which compromises the Life Safety Code. In addition, any project which involves hazardous materials, or in the opinion of a representative of the EHS or the BU/BMC Construction Project Manager, has the potential for providing a hazard that could compromise safety, shall be considered a construction project requiring the implementation of one or more measures outlined in the Program. The DEP Construction/Demolition Notification Form AQ-06 is required when abating asbestos containing building materials. The form shall also be used under the following conditions and only after building materials identified to be disturbed have been tested and proven not to contain asbestos. When six (6) sq. ft. interior or twenty (20) sq. ft. exterior building materials will be altered, renovated or removed and/or any time more than three (3) different, non-asbestos building materials will be affected. The DEP Construction/Demolition Notification Form AQ-06 in not required for the following; When replacing floor tile or floor sheeting the notification is not required. Replacement of broken or stained ceiling tiles does not require notification. Replacing windows or door frames do not require notification unless the size of the affected building material is equal or greater than six (6) sq. ft. Questions regarding the use of the DEP Notification should be directed to EHS at (Medical Campus) or (Charles River Campus). The MassDEP encourages filing Construction/Demolition Notification Form AQ-06 online via edep! If you have not already done so, please register online with edep at Page 19 of 19
Beth Israel Deaconess Medical Center Environment of Care Manual
Beth Israel Deaconess Medical Center Environment of Care Manual Title: Interim Life Safety Measures (ILSM) Plan Policy #: EC39 Purpose: ILSM are fully adhered to in areas where the hospital/site occupants
More informationUNIVERSITY OF TOLEDO
UNIVERSITY OF TOLEDO SUBJECT: INTERIM LIFE SAFETY MEASURES AND INFECTION Procedure No: LS-08-008 CONTROL PROCEDURE STATEMENT Interim life safety and infection control measures will be implemented to protect
More informationGeneral Fire Code Requirements Within Commercial Tenant Spaces
FIRE DEPARTMENT in cooperation with Scope: General Fire Code Requirements Within Commercial Tenant Spaces This handout is designed to assist owners, architects, contractors and others in understanding
More informationALVERNIA UNIVERSITY OSHA REGULATION: 29 CFR 1910.252 WELDING, CUTTING, AND BRAZING ( HOT WORK ) SECTION: 3600
OSHA REGULATION: 9 CFR 90.5 WELDING, CUTTING, AND BRAZING ( HOT WORK ) A. POLICY. This procedure follows requirements set forth in 9 CFR 90.5.. This policy applies to all Hot Work operations being done
More informationSTCC Contractor/Vendor Rules and Regulations
STCC Contractor/Vendor Rules and Regulations STCC maintains specific rules and regulations that apply to all contractors and vendors who perform work or provide services. It is the responsibility of the
More informationLaboratory Safety and Environmental Health Assessment Program
Laboratory Safety and Environmental Health Assessment Program Principal Investigators and Faculty are vital to the success of safety and environmental compliance programs in Colorado School of Mines research
More informationENVIRONMENTAL HEALTH & SAFETY/RISK MANAGEMENT Contractor Management (including Sub-Contractors)
ENVIRONMENTAL HEALTH & SAFETY/RISK MANAGEMENT Contractor Management (including Sub-Contractors) Contractors have the responsibility to ensure the health and safety of their workers and that their work
More informationWORK RULES AND CONTRACTOR REQUIREMENTS FOR ALL UNIT OWNERS & UNIT OWNER CONTRACTORS PERFORMING WORK ON THE PREMISES AT HAWTHORNE PLACE CONDOMINIUMS
WORK RULES AND CONTRACTOR REQUIREMENTS FOR ALL UNIT OWNERS & UNIT OWNER CONTRACTORS PERFORMING WORK ON THE PREMISES AT HAWTHORNE PLACE CONDOMINIUMS 1) GENERAL GUIDELINES a) The following rules, regulations,
More informationFACILITY FIRE PREVENTION AND EMERGENCY PREPAREDNESS INSPECTION CHECKLIST
FACILITY FIRE PREVENTION AND EMERGENCY PREPAREDNESS INSPECTION CHECKLIST Date of Inspection: Conducted by: Location: Reviewed by: Date of Review: Comments or additional corrective action taken as a result
More information1.0 Purpose... 4. 2.0 Definitions...4. 3.0 Hot Work Operations. 5
HOT WORK PROGRAM Introduction The University of Kentucky recognizes a potential for fire from hot work operations. For that reason this program should be implemented in all departments at the University
More informationSafety and Health Office WORKPLACE SAFETY CHECKLIST
Location: Date: Inspected by: Safety and Health Office WORKPLACE SAFETY CHECKLIST WORK ENVIRONMENT Ventilation Removal of fumes and dust Temperature and humidity control Noise levels Vibration Lighting
More informationCore & Shell Construction. Rules and Regulations
Core & Shell Construction Rules and Regulations 1. Protection: During the construction Contractor shall endeavor to protect all areas of work from damage caused by workers, weather or equipment. 2. Permits
More informationFIRE SAFETY SELF-INSPECTION FORM FOR CULTURAL INSTITUTIONS. 1. All Floors (inspect from top floor to basement): Yes No
General Inspection FIRE SAFETY SELF-INSPECTION FORM FOR CULTURAL INSTITUTIONS 1. All Floors (inspect from top floor to basement): Yes are fire exits and directional signs properly illuminated? is the emergency
More informationSafety Inspection Checklist
Inspector(s): Building: Room Number (s): Department/Unit: Date Inspected: Supervisor: To customize your local inspection checklist, delete or add as required. Inspection Headings: 1. Administrative 8.
More informationFIRE SAFETY SELF-INSPECTION FORM FOR CULTURAL INSTITUTIONS
FIRE SAFETY SELF-INSPECTION FORM FOR CULTURAL INSTITUTIONS The attached self-inspection form is intended for staff use at regular, frequent intervals. It should not take the place of two other vital measures
More informationSAFETY SELF-INSPECTION PROGRAM
Palm Beach State College Florida s First Public Community College SAFETY SELF-INSPECTION PROGRAM PALM BEACH STATE COLLEGE SAFETY SELF-INSPECTION PROGRAM 1. INTRODUCTION An important element of any employee
More informationFire Alarm and Protection Impairment Policy and Procedures
1.0 Policy Statement The University of New Haven has developed a Fire Alarm and Protection Impairment Plan in accordance with the National Fire Protection Associations (NFPA) codes. Specific codes referenced
More informationDennis Fire Department Fire Prevention Mark Dellner Fire Chief
Dennis Fire Department Fire Prevention Mark Dellner Fire Chief FIRE SAFETY INSPECTION GUIDELINES FOR COMMERCIAL PROPERTIES (MA Fire Prevention Regulations 527 CMR, MGL Chapter 148) FIRE PREVENTION CHECKLIST-
More informationCONSTRUCTION FIRE SAFETY PLANNING GUIDELINES
CONSTRUCTION FIRE SAFETY PLANNING GUIDELINES Review the following information pertaining to Construction Fire Safety Planning: B.C. Building Code Sections 8.1 up to and including Subsection 8.2.3 B.C.
More informationHOT WORK PERMIT PROGRAM TRAINING. John Braun
HOT WORK PERMIT PROGRAM TRAINING John Braun 1.0 INTRODUCTION 1.2 Purpose The Hot Work Permit Program has been developed for University employees that work on or around hot work activities. This program
More informationOSHA & Restaurants: Top 10 Frequently Cited Violations from October 2008 September 2009 for SIC Code 5812 Eating and Drinking Places
OSHA & Restaurants: Top 10 Frequently Cited Violations from October 2008 September 2009 for SIC Code 5812 Eating and Drinking Places www.marsh.com Discussion Frequently Cited OSHA Regulations Current Penalty
More informationUAMS Representative: The person who is most directly responsible for aspects on location where renovation and construction will occur.
UAMS ADMINISTRATIVE GUIDE NUMBER: 11.2.08 DATE: 5/21/2002 REVISION: 10/03/2005, 09/18/2008, 10/05/2011, 07/10/2013 PAGE: 1 of 15 SECTION: CAMPUS OPERATIONS AREA: GENERAL SUBJECT: INTERIM LIFE SAFETY MEASURES
More informationFIRE AND LIFE SAFETY REQUIREMENTS FOR CONVENTIONS, TRADE SHOWS AND EXHIBITS
FIRE AND LIFE SAFETY REQUIREMENTS FOR CONVENTIONS, TRADE SHOWS AND EXHIBITS November 2011, Updated March 2012 COLORADO SPRINGS FIRE DEPARTMENT Division of the Fire Marshal If you have any questions or
More informationLEGAL REVIEW & UPDATE
LEGAL REVIEW & UPDATE There are lots of laws and regulations designed to protect workers, the general public, and the environment. However, not everyone follows the laws. Many people deliberately break
More informationContractor Name: Foremen/Superintendent on-site: email: phone: 24 Hr Phone# Email: Project Address: Floor(s)
FACILITIES & CONSTRUCTION MANAGEMENT SAFE WORK PLAN This document must be submitted with typed responses. Hand written forms will not be acceptable. All responses must be completed or filled in with N/A
More informationASBESTOS MANAGEMENT PROGRAM
ASBESTOS MANAGEMENT PROGRAM September 2015 Asbestos Management Program Table of Contents I. Purpose II. III. IV. Definitions Identification of Asbestos Asbestos Sampling V. Notification and Labeling VI.
More informationLABORATORY SAFETY INSPECTION CHECKLIST
LABORATORY SAFETY INSPECTION CHECKLIST As part of EH&S's laboratory safety survey program, we have compiled a list of the most common safety problems. This is not a list of every possible hazard, but can
More informationFIRE RISK ASSESSMENT
The Regulatory Reform (Fire Safety) Order 2005 FIRE RISK ASSESSMENT Employer or other responsible person Name of Premises Address Post Code Telephone N o Name of Assessor(s) Date of Assessment Date of
More informationCONSTRUCTION SAFETY POLICY
California Institute of Technology CONSTRUCTION SAFETY POLICY Caltech Environment, Health, and Safety Office 1200 E. California Blvd., M/C 25-6 Pasadena, CA 91125 Phone: 626.395.6727 Fax: 626.577.6028
More informationFIRE SAFETY ONLINE TRAINING
INTRODUCTION This Fire Safety Training module is designed to teach you preventive measures that will eliminate or minimize causes of fire or fire hazards in the workplace, and to teach you proper emergency
More informationNorth Carolina State University Emergency Facilities Closure Checklist- Part I
North Carolina State University Emergency Facilities Closure Checklist- Part I Unplanned or spontaneous events often disrupt daily operations on campus. In the event that an incident may interrupt your
More informationFIRE ALARM /FIRE PROTECTION OUTAGE/IMPAIRMENT RESPONSE GUIDELINE
Page 1 of 10 FIRE ALARM /FIRE PROTECTION OUTAGE/IMPAIRMENT RESPONSE GUIDELINE SYSTEM TESTING 1. Testing of the Fire Alarm and Fire Protection Systems 1.1. The Building Engineer, Electrician, Plumber (or
More informationFIRE AND LIFE SAFETY REQUIREMENTS FOR CONVENTIONS, TRADE SHOWS AND EXHIBITS November 2011
FIRE AND LIFE SAFETY REQUIREMENTS FOR CONVENTIONS, TRADE SHOWS AND EXHIBITS November 2011 COLORADO SPRINGS FIRE DEPARTMENT Division of the Fire Marshal If you have any questions or comments regarding the
More informationSafe Operating Procedure
Safe Operating Procedure (Revised 07/09) HOT WORK PERMIT OPERATIONS (For assistance, please contact EHS at (402) 472-4925, or visit our web site at http://ehs.unl.edu/) Authority In recognition of the
More informationTown of Bellingham Fire Department
Town of Bellingham Fire Department OFFICE OF THE Fire Prevention Division Captain Robidoux- jrobidoux@bellinghamma.org Lieutenant Bangma- jbangma@bellinghamma.org Fire Safety Inspection Guidelines for
More informationFire Risk Assessment Safety Checklist
Fire Risk Assessment Safety Checklist This checklist has been prepared to help you comply with The Regulatory Reform Fire Safety Order 2005 What is the Regulatory Reform (Fire Safety) Order 2005? The Regulatory
More informationLaboratory Audit Sheet Auditor s Name: Date of Inspection: / / Building Name: Room# Principal Investigator:
Laboratory Audit Sheet Auditor s Name: Date of Inspection: / / Building Name: Room# Principal Investigator: 1. 0 GENERAL HOUSKEEPING PRACTICES Y/N N/A C REGULATORY GUIDANCE COMMENTS 1.1 Walkways in and
More informationOSU INSTITUTE OF TECHNOLOGY POLICY & PROCEDURES
Hazardous Communications 5-001 FACILITY MANAGEMENT July 2014 INTRODUCTION AND GENERAL STATEMENT 1.01 OSU Institute of Technology (OSUIT) recognizes that its employees have both a right and need to know
More informationHSE Requirements for Contractors
PROJECT DEFINITION AND CONTACTS Project Title: Kodak is obligated to identify any known and potential Health, Safety, and Environmental (HSE) hazards to individuals who might be affected by them. This
More informationAn inventory of hazardous materials used in your workplace will prove useful.
Introduction Fire Protection is an organized approach designed to prevent fires. In the event of a fire, a fire protection program will help prevent or minimize personal injuries, losses, and harm to the
More informationHOT WORK PERMIT PROCEDURES
COLUMBIA UNIVERSITY ENVIRONMENTAL HEALTH & SAFETY HOT WORK PERMIT PROCEDURES COLUMBIA UNIVERSITY MEDICAL CENTER February 2010 1 TABLE OF CONTENTS A. PURPOSE 3 B. SCOPE 3 C. POLICIES AND PROCEDURES 3-4
More informationCOLUMBUS STATE COMMUNITY COLLEGE EMPLOYEE SAFETY MANUAL
COLUMBUS STATE COMMUNITY COLLEGE EMPLOYEE SAFETY MANUAL HAZARDOUS MATERIAL MANAGEMENT Effective October 15, 1995 Page 1 of 4 Updated August, 2008 Revised August, 2009 A. Columbus State Community College
More informationLOCKOUT/TAGOUT (LOTO) SAFETY PROGRAM
1 UNIVERSITY OF WEST FLORIDA LOCKOUT/TAGOUT (LOTO) SAFETY PROGRAM (EQUIPMENT HAZARD DE-ENERGIZING AND ISOLATION) DEPARTMENT OF ENVIRONMENTAL HEALTH AND SAFETY 11000University Parkway Pensacola, FL 32514
More informationDepartment: Manager: Safety Coordinator: Date:
SAFETY and staff, regardless of hiring status or job position 1 1. Can staff name their department safety coordinator? 2. Is the Department Safety Binder current? 3. Do slip/trip hazards exist? 4. How
More informationFIRE PREVENTION PLAN
FIRE PREVENTION PLAN 1 FIRE PREVENTION PLAN OSHA s Fire Prevention Plan regulation, found at 29 CFR 1910.38(b) and 29 CFR 1926.24, requires Northern Clearing, Inc. to have a written fire prevention plan
More informationTYPICAL FIRE SAFETY INSPECTION VIOLATIONS
TYPICAL FIRE SAFETY INSPECTION VIOLATIONS The following is a list of typical violations often found by inspectors and a generic solution. You can use this list to improve the safety of your facility, to
More informationLOUISVILLE FIRE PROTECTION DISTRICT 895 West Via Appia, Louisville, Colorado 80027 303-666-8809
LOUISVILLE FIRE PROTECTION DISTRICT 895 West Via Appia, Louisville, Colorado 80027 303-666-8809 Contractor s Checklist and Installation Guide TABLE OF CONTENTS Fire Protection Narrative........... 3 Fire
More informationNumber Northern Arizona University Facility Services Section Page. Effective April 1, 2011
Facility Services Section Page Recharge Services, Maintenance and Construction PURPOSE 1 of 6 The purpose of this policy is to set forth standards for chargeable services for maintenance and construction
More information1.1. EMERGENCY PROCEDURE On discovering a fire or being informed of an emergency;
Fire Action Plan FIRE ACTION PLAN SEStran aims to provide and maintain safe & healthy working conditions, equipment and systems of work for all our employees, and to provide such information, training
More informationFACILITY SAFETY SIGNAGE GUIDE: 10 SIGNS TO SPOT DURING A PLANT WALKTHROUGH
FACILITY SAFETY SIGNAGE GUIDE: 10 SIGNS TO SPOT DURING A PLANT WALKTHROUGH Safety signs are the primary way to communicate important warnings and messages to your employees, on-site contractors and other
More informationASBESTOS MANAGEMENT PROGRAM
ASBESTOS MANAGEMENT PROGRAM Prepared By: Triumvirate Environmental Program Approval Developed: August 2011 Updated: June 2015 Associate Vice President of Public Safety & Administrative Services Date Associate
More informationEMERGENCY ACTION, EVACUATION AND FIRE PREVENTION SAFETY PROGRAM
EMERGENCY ACTION, EVACUATION AND FIRE PREVENTION SAFETY PROGRAM REGULATORY STANDARD: OSHA - 29CFR1910.36-29CFR1910.38-29CFR1910.157-29CFR1910.165 NFPA-10 BASIS: The OSHA Emergency Action Planning and the
More informationMetropolitan Washington Airports Authority Office of Public Safety Fire & Rescue Department. Fire Code Enforcement Division
Metropolitan Washington Airports Authority Office of Public Safety Fire & Rescue Department Fire Code Enforcement Division Fire Protection System Impairment Requirements For Contractors and Service Personnel
More informationH-0123 Contractor Safety Program
H-0123 Contractor Safety Program SUBJECT: Contractor Safety H-0123 REVISION NO: 4 REFERENCES: 29 CFR190 29CFR1926 CP-04-201 Contract Labor CP-04-215 Contract Services CP-28-111 Badging P&P 40-19 CP-04-107
More informationAsbestos WHAT TO DO? Studies of people who were exposed to high levels of asbestos in factories and shipyards, are at increased risk of:
Asbestos WHAT TO DO? What Is Asbestos? Asbestos is mineral fiber. It can be positively identified only with a special type of microscope. There are several types of asbestos fibers. In the past, asbestos
More informationCANTON FIRE DEPARTMENT
CANTON FIRE DEPARTMENT Dean Floyd Fire Chief FIRE SAFETY INSPECTION GUIDELINES FOR COMMERCIAL PROPERTIES FIRE PREVENTION CHECKLIST- To review prior to your inspection. 1. Is the address of your property
More informationFire Safety Risk Assessment Checklist for Residential Care Premises
Checklist for Residential Care Premises Name of Premises: Address of Premises: Name of Responsible Person: What area / location does the assessment cover? Does the assessment cover the whole site YES or
More informationQuality Assurance Calendar Maintenance Responsible Party Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Generator fire up Generator 1 hour load test Generator 4 hour load test Fire extinguisher integrity checks Fire extinguisher certification Fire drills Fire door integrity Fire signage lighting Fire alarm
More informationAsbestos Work Permit Procedures
These procedures are to be followed by all persons required to perform the following work: Handling, installation or removal of non-friable manufactured products known to contain asbestos provided no sanding,
More informationRULES AND REGULATIONS CONTRACTOR WORK
RULES AND REGULATIONS CONTRACTOR WORK CARILLON 227 West Trade Street Suite 330 Charlotte, NC 28202 The following Rules and Regulations shall govern the operation of contractor work in the Building. For
More informationVERIFY HARD COPY AGAINST WEB SITE IMMEDIATELY PRIOR TO USE
Nuclear Safe Work Practice 6.7 Safety Signs/Tapes/Ropes/Chains and Tags 1.0 PURPOSE/SCOPE To provide consistent standards for using safety signs, tapes, ropes and chains (barriers) to communicate existing
More informationUniversity of Pittsburgh Safety Manual. EH&S Guideline Number: 01-007 ASBESTOS
Page 1 of 5 The inhalation of asbestos fibers in excess amounts can lead to chronic lung disease. Our knowledge of these health effects comes from studies of workers exposed routinely to high concentrations
More informationCommercial Fire Inspections
Commercial Fire Inspections Fire Department Inspection Requests and Procedures The following guidelines shall be used when calling for inspection requests: 1. All inspection requests shall be coordinated
More informationOSHA Compliance Checklist ASC
OSHA Compliance Checklist ASC Date Inspectors Facility OSHA is the agency responsible for establishing and enforcing standards that will make the workplace safe and healthful for the employees. The way
More informationThe Commonwealth of Massachusetts Executive Office of Public Safety Department of Fire Services
MITT ROMNEY GOVERNOR KERRY HEALEY LT. GOVERNOR EDWARD A. FLYNN SECRETARY The Commonwealth of Massachusetts Executive Office of Public Safety Department of Fire Services P.O. Box 1025 State Road Stow, Massachusetts
More informationFIRE AND LIFE SAFETY TRAINING
FIRE AND LIFE SAFETY TRAINING 1 Objectives General Information Emergency Evacuation Plans / Regulatory Requirements Notification Systems Emergency Exits and Fire Doors Electrical Safety Fire Prevention
More informationFIRE SAFETY HANDBOOK
29 CFR 1960.20, Alternate Standard For Fire Safety In Airport Traffic Control Towers (ATCTs) Fire Prevention Plan (FPP) Emergency Action Plan (EAP) FIRE SAFETY HANDBOOK DEPARTMENT OF TRANSPORTATION FEDERAL
More information1. Organization and Management of UNR Safety Programs
WRITTEN WORKPLACE SAFETY PLAN University of Nevada, Reno 1. Organization and Management of UNR Safety Programs Administrative Responsibilities Final responsibility for maintenance of campus safety and
More informationFLA S FIRE SAFETY INITIATIVE
Improving Workers Lives Worldwide FLA S FIRE SAFETY INITIATIVE Preventing fires and saving lives by empowering workers and factory managers SCENARIO 1 OCCURS AT FACTORY ABC, WHICH HAS NOT IMPLEMENTED NECESSARY
More informationSafety at Kaiser Permanente Los Angeles Medical Center Environmental Health & Safety Department
Safety at Kaiser Permanente Los Angeles Medical Center Environmental Health & Safety Department Environmental Health and Safety (EHS) The Los Angeles Medical Center (LAMC) is committed to providing a safe
More informationASBESTOS AWARENESS IN THE WORKPLACE. This easy-to-use Leader s Guide is provided to assist in conducting a successful presentation.
ASBESTOS AWARENESS IN THE WORKPLACE This easy-to-use Leader s Guide is provided to assist in conducting a successful presentation. Featured are: INTRODUCTION: A brief description of the program and the
More informationFACILITIES MANAGEMENT DEPARTMENT QUICK REFERENCE Guide to Services
FACILITIES MANAGEMENT DEPARTMENT QUICK REFERENCE Guide to Services After-Hours Service Calls Air Conditioning and Heating Bicycle Racks Building Conditions Inspections Contract Construction (handled by
More informationDepartment of Environmental Health and Safety & Emergency Management
Date: February 2014 Revision: 02 Page: 1 of 13 This Guideline is issued jointly by the Department of Environmental Health and Safety & (EHSEM) and Facilities Management to provide guidance and consistency
More informationName Of Occupancy Date. Yes No Describe
FIRE PREVENTION INSPECTION CHECKLIST For Class A Occupancy (For Assembly Buildings, Bars, Restaurants, Gyms, Churches, Arenas, Theatres or wherever people gather) Name Of Occupancy Date Physical Address
More informationSpray Booth Guideline
Department of Development Service 135 North D Street, Perris CA. 92570 Phone: (951) 443-1029 Fax: (951) 943-3293 PURPOSE The intent of this guideline is to provide the information necessary to ensure that
More informationTEMPORARY EMPLOYEES SAFETY PROCEDURES
TEMPORARY EMPLOYEES SAFETY PROCEDURES Temporary Agencies will ensure that any temporary employee sent to work at Modern will have received and understand the General Safety Rules. GENERAL SAFETY RULES
More informationInspection, Testing and Maintenance
Page 18 ABOUT CODE CORNER CCFS would like to remind you to check with your local Authority Having Jurisdiction (AHJ) for questions and opinions concerning your local Fire and Building Codes. The information
More informationWellesley College Asbestos Management Program
Wellesley College Asbestos Management Program Table of Contents Page Policy 2 Impacts of Asbestos Containing Materials (ACM)... 3 Compliance... 3 Objectives... 4 Operational Controls Standard Operating
More informationEnvironment of Care Fire Safety Management Plan 2014
Environment of Care Fire Safety Management Plan 2014 Updated 4.29.2014 PURPOSE The purpose of the Fire Safety Management Plan is to ensure that all facilities are designed, constructed, maintained, and
More informationSample Checklist for Permit Required Confined Spaces Program
Sample Checklist for Permit Required Confined Spaces Program 29 CFR 1910.146 - Permit Required Confined Spaces for General Industry Item Description Yes No N/A Section C (General Requirements) 1. (1) -
More informationASBESTOS CONTAINING MATERIALS OPERATIONS & MAINTENANCE PLAN 2015
ASBESTOS CONTAINING MATERIALS OPERATIONS & MAINTENANCE PLAN 2015 Prepared For: (School Name) PREPARED BY: DIOCESE OF JOLIET ENVIRONMENTAL OFFICE FOR ANY ENVIRONMENTAL RELATED EMERGENCY CONTACT: RICHARD
More informationBOSTON COLLEGE ENVIRONMENTAL HEALTH AND SAFETY LABORATORY GUIDE FOR RENOVATIONS, REMODELS, MOVES AND TERMINATIONS
BOSTON COLLEGE ENVIRONMENTAL HEALTH AND SAFETY LABORATORY GUIDE FOR RENOVATIONS, REMODELS, MOVES AND TERMINATIONS I. Policy for Termination of Laboratory Use of Hazardous Materials The Principal Investigator
More informationSAFETY AND HEALTH PROGRAM
PROGRAM NUMBER NO. PAGES 05-005 10 REVISION ISSUE DATE Revision 2 11/1/2005 SAFETY AND HEALTH PROGRAM Confined Space Entry 1.0 INTRODUCTION Confined Space Entry is a serious workplace hazard, capable of
More informationTAMPA ELECTRIC COMPANY ENERGY SUPPLY ASBESTOS AWARENESS PROGRAM
ASBESTOS AWARENESS PROGRAM TABLE OF CONTENTS TITLE PAGE # PURPOSE / INTRODUCTION 1 RESPONSIBILITY 2 EMPLOYEE TRAINING AND DOCUMENTATION 2-4 MEDICAL SURVEILLANCE 4 UNPLANNED DISTRUBANCE OF ASBESTOS CONTAINING
More informationInjury & Illness Prevention Program (IIPP)
Injury & Illness Prevention Program (IIPP) Adapted from Cal/OSHA Workplace Injury & Illness Prevention Model Program for Non-high Hazard Employers CS-1B, 1995 Revisions: 2/92, 4/93, 5/95, 3/00, 3/04, 3/06,
More informationPI s Name Date Bldg./Rm# CDC Biosafety Level 3 (BSL-3)
PI s Name Date Bldg./Rm# CDC Biosafety Level 3 (BSL-3) Yes No 1. Is access to the laboratory limited or restricted at the discretion of the laboratory director when experiments are in progress? Yes No
More informationInfection Control Risk Assessment : the Infection Preventionist s Role in Construction
Infection Control Risk Assessment : the Infection Preventionist s Role in Construction Key Concepts Use of ICRA is an important element in an infection prevention program Should be an integral part of
More informationAlaska. Occupational Safety and Health Standards. quick guide to. hazard communication for general industry. What you should know and not a word more!
Alaska Occupational Safety and Health Standards quick guide to hazard communication for general industry What you should know and not a word more! Table of Contents Overview of AKOSH Services 1 What is
More informationOffice of Research Facilities Development and Operations Contractor Safety Policy
Office of Research Facilities Development and Operations Contractor Safety Policy The National Institutes of Health (NIH) is committed to providing a safe environment for everyone who enters the NIH campus.
More informationAsbestos Abatement Management Program. Facilities Operations and Development Environmental Health & Safety
Asbestos Abatement Management Program Facilities Operations and Development Environmental Health & Safety November 7, 2012 INTRODUCTIONS David Kos (EHS) Director of Environmental Affairs David Kehl (EHS)
More informationCommercial Building Permit Application & Submittal Guidelines
Building Inspection Department 1625 13 th Street, Suite 106 Lubbock, Texas 79457 (806) 775-2087 (806) 775-2088 http://buildinsp.ci.lubbock.tx.us/ Commercial Building Permit Application & Submittal Guidelines
More informationMinnesota State Department of Public Safety
Minnesota State Department of Public Safety 444 Cedar Street, Suite 145, St. Paul, Minnesota 55101-5145 Phone: 651/215-0500 FAX: 651/215-0525 TTY: 651/282/6555 Internet: http://www.fire.state.mn.us Inspection
More informationFire Safety PROCEDURES January 2011
Fire Safety PROCEDURES January 2011 firesafety@uwo.ca Campus Phones EMERGENCY Dial 911 Fire Safety Service is the focal point for the coordinated administration of the University Fire Safety program and
More informationLoss Control TIPS Technical Information Paper Series
Loss Control TIPS Technical Information Paper Series Innovative Safety and Health Solutions SM The Safety Audit: A Management Tool A major soft drink bottler, concerned about ergonomics and lifting hazards,
More informationPLAN SUBMITTAL REQUIREMENTS FOR SPRAY BOOTHS AND SPRAYING ROOMS EXTINGUISHING SYSTEMS
January 1997 PLAN SUBMITTAL REQUIREMENTS FOR SPRAY BOOTHS AND SPRAYING ROOMS EXTINGUISHING SYSTEMS 1.0 PERMIT 1.1 After receipt of a Building Permit from the City of San Jose Building Department, submit
More informationSchool Science Lab Safety Guidelines
School Science Lab Safety Guidelines Occupational Safety & Health Bureau Montana Department of Labor & Industry Prepared for Montana Employers by the Occupational Safety & Health Bureau Department of Labor
More informationDESERT RESEARCH INSTITUTE MOLD ASSESSMENT AND REMEDIATEION PROCEDURE
1.0 Introduction DESERT RESEARCH INSTITUTE This Desert Research Institute (DRI) Mold Assessment and Remediation Procedure was established to assure that consistent and uniform information is provided to
More informationCSC-DIVISION 1-MASTER SECTIONS Description
CSC-DIVISION 1-MASTER SECTIONS Description 01 11 00 Summary of Work by Consultant 01 12 00 Multiple Contract Summary by Consultant 01 14 00 Work Restrictions see below 01 21 00 Allowances by Consultant
More informationWaste Management Log Book
Waste Management Log Book Web address: www.ehs.psu.edu Designated Accumulation Area: Building & Room Number Location in Room Supervisor: E-mail Individual designated to ensure procedures are followed:
More informationLead Exposure Management Plan
Lead Exposure Management Plan 1.0. Policy CSUF has developed the Lead Exposure Management Plan to reduce occupational and environmental exposure to lead, a potent neurotoxin and carcinogen that causes
More information