Integrated analysis of wind turbine and wind farm

Size: px
Start display at page:

Download "Integrated analysis of wind turbine and wind farm"

Transcription

1 Integrated analysis of wind turbine and wind farm Ir. M.B. Zaaijer Dr. ir. G.J.W. van Bussel Tel Tel Section Wind Energy 1 Fax Faculty of Civil Engineering and Geosciences, Stevinweg 1, 2628 CN Delft, The Netherlands 1 The Section Wind Energy participates in DUWIND, the interdisciplinary wind energy institute of Delft University 1 Different design approaches 1.1 Traditional (robust) design In the traditional design process the problem of realising an offshore wind turbine is organised in two main clusters according to the parent technologies, i.e. wind energy technology (comprising wind turbine, tower, farm layout, grid connection design) and offshore technology (related to foundation, marine installation and submarine cables) (Figure 1). The treatment is denoted as robust since conventional design solutions are used (e.g. standard wind turbine with small modifications, stiff foundation) and traditional because of the direct application of experience from the normal scope of work of the parties involved. System Demonstration plant Political order / client Targets Prototype Study of environmental effects Limited risk Project manager Wind energy technology Offshore technology Subsystems Clusterleaders Elements Wind turbine (modified) Tower (onshore design) Farm layout Installation (turbine and tower) Grid connection design O&M (turbine and tower) Foundation design and construction Ancillary design Foundation installation Submarine cable laying Foundation and cable maintenance Engineers Figure 1 Traditional (robust) design approach 1

2 Good examples of a traditional design approach are the two early Danish wind farms at Vindeby and Tunø Knob (Table 1 in the next section). These two small wind farms have been realised with fairly standard wind turbines (450 to 500 kw turbines) mounted on gravity base foundations. Almost without exaggeration it can be said that these wind turbines were placed on small artificial islands in a fashion identical to an onshore operation. So it started with the "foundation preparation", which consists of seabed preparation, construction of the gravity base foundation and its installation at site. The subsequent standard operations for onshore wind turbine erection were more or less copied at sea. Thus, placement of tower, attachment of nacelle, assembly of the complete rotor (at land) transport to site (on a floating barge) and finally attachment at the main shaft in the nacelle were performed. The adaptation to operation in the offshore environment was limited to marinising the wind turbines. This means that extra efforts were made with respect to sealing of bearings, avoiding salt water or salt spray access to the cooling system of generator and gearbox, and corrosion protection. 1.2 Parallel design In a parallel design approach the implications that offshore conditions have on a wind farm are indeed recognised. Still they are considered individually in the main sub-systems as wind turbine, support structure, grid connection, etc (Figure 2). Thus the overall performance is limited to the sum of the separate optimisations of the sub-systems. System Demonstration plant or (near) commercial plant Order Targets Cost of energy Energy yield Life time & risk Customer Projectmanager Aspectsystems Costs O&M Marinisation Costs Strength & stiffness Installation Costs Reliability Wind turbine Support structure Grid connection & farm layout Subsystems Clusterleaders Elements Engineers Figure 2 Parallel design approach Two examples of early adaptation of a parallel design approach are the Nogersund project in the Swedish part of the Baltic Sea and the Lely wind farm in the Dutch IJsselmeer. The first case regards a single 220 kw machine on a fairly short distance from shore. The parallel design issue in this project can be seen in its installation procedure. The whole structure, including a standard wind turbine and a tripod foundation was assembled in a harbour surroundings, commissioned, transported to its offshore site and installed in one operation. So here a real offshore working method was adopted for the whole structure, and not for the offshore part (the tripod) alone. A second example of a parallel approach in realising an "offshore" wind farm can be recognised in the way wind park Lely was realised. A new issue at that time was the use of a steel monopiles as a foundation. This is a rather uncommon design solution for offshore 2

3 structures, but a logical extension of wind turbine technology practice (tubular towers) into offshore technology. The Lely wind turbines themselves are again slightly modified onshore machines. No attempt however was made to design the dynamics of wind turbine and offshore structure simultaneously. Installation and maintenance procedures are also modifications of the standard onshore practice. Another typical "parallel design" aspect of the project is the way the towers are fixed on the monopiles. On top of the pile a plug was grouted having a ring with standard bolts that fit to the bottom flange of the (standard) wind turbine tower. Table 1 below shows an overview of the offshore wind farms that have been realised up to the year Almost all these projects are realised along either the robust route or the parallel approach. The most advanced in terms of integrated design is probably the Utgrunden project. Table 1 First offshore wind farms, up to the year 2000 Location Year Installed Power (MW) Location Foundation details Nogersund, Baltic (Sw) 1991 (abandoned in 98) 1 x 0.22 = 0.22 Windworld (NEG Micon) in 7 m water, 250 m from shore Tripod on solid rock; Vindeby (Dk) x 0.45 = 4.95 Bonus in 3-5 m water, 1.5 km from shore Box caisson on sandy soil, Lely, Medemblik, IJsselmeer (Nl) x 0.5 = 5 NedWind (NEG Micon) in 5-10 m water, 750 m from shore Steel tower driven in sandy soil, corrosion lifetime 50 years, in fresh water. Tunø Knob (Dk) x 0.5 = 5 Vestas in 3-5 m water, 6 km from shore Box caisson on sandy soil Dronten, IJsselmeer (Nl) x 0.6 = 16.8 Nordtank (NEG Micon) in 5 m water, 20 m from shore Turbines located on monopiles a few meters from the dike, in fresh water Bockstigen Valar, Baltic (Sw) x 0.5 = 2.5 WindWorld (NEG Micon) in m water, 3 km from shore 2.25 meter steel monopiles secured by grouting in 10-m deep holes drilled in limestone rock. Middelgrunden (Dk) x 2 = 40 Bonus in 3-6 m water, 3 km from shore Concrete caissons resting on sea bed Utgrunden (Sw) x = 10 Tacke in 7-10 m water 8 km from shore First soft-soft monopile foundation (low eigenfrequency of support structure) Blyth Harbour (UK) x 2 = 4 Vestas in 8 m water, 800 m from shore The first North Sea wind farm, monopile foundation 1.3 Integrated design Design practice applied so far for the design of offshore wind farms fitted the objectives of demonstration plants. Such practice will however not be suitable to arrive at commercial, large-scale offshore wind farms to be erected in the coming decennium, and a highly integrated design approach had to be adopted. This refers not only to the interaction between the turbine and the support structure but also to an integrated treatment of all major wind farm parameters in all the design phases. Moving wind turbines further offshore will require major changes in the design, far beyond the obvious marinisation of the components open to the environment, if the optimum solution is to be used. Greater freedom in the design is also possible, regarding aspects such as the noise, visual impact and electrical aspects. A framework for an integrated design methodology recently developed for large, complex civil engineering projects can be applied as well for the design of future large-scale offshore wind farms. For this approach it is at first important to determine the client. Once the client is clearly identified his goals are known and can be translated into quantifiable criteria at the system level, the aspect-systems. Such quantifiable criteria facilitate the control of the design process in order to achieve the goals of the client (Figure 3). 3

4 System Delivery of substantial electricity Society / Political order Targets Profit Energyquality and quantity Life time & risk Customer Costs per kwh Location Dynamics Installation Availability Projectmanager Aspectsystems Wind turbine Support struct. & installation Grid connection & farm layout Operation & maintenance (O&M) Subsystems Clusterleaders Elements Engineers Figure 3 Integrated design approach An example of a set of such aspect-systems is: levelised (sometimes called lifetime) production costs adaptation to the actual site conditions, dynamics of the entire system, structural integrity of the design, installation and commissioning efforts availability of the offshore wind farm. From the aspect system level the total system is furthermore split into sub-systems and elements for efficient control of the design steps. Interactions between sub-systems have to be considered in a complete though manageable form as possible so that the selection of the final design solution is governed by overall criteria. Although a genuine integrated approach will most likely produce an innovative design solution, the evolutionary nature of technical progress and the commercial risks inherent to innovative solutions must be kept in mind. In particular it would be a serious mistake to interpret it as a justification for the application of unproven wind turbine design to the harsh offshore conditions 2 Examples of analysing aspect systems 2.1 Cost aspects LPC cost model The Levelised Production Cost (LPC) is the cost price of production per unit of energy, expressed in actualised nominal money. This means that the levelised production cost expresses the production cost in terms of current purchasing power, allowing comparison with other current costs of energy. The LPC is one of the main assessment criteria of a wind farm and recommended practises for its calculation are given by IEA. 4

5 The following expression is used to calculate the LPC: where: LPC T t t= 0 = T ( C R )( 1+ r) t= 0 E t t ( 1+ r) t t C t = total ongoing costs for year t, R t = total ongoing revenues for year t, E t = total energy production in year t, T = economic lifetime, r = real interest rate, defined by:, 1+ i 1+ r = 1+ v, with: i v = annual interest rate on debts, = annual inflation rate. In the LPC calculation the costs and energy production are weighted with the effect of interest and inflation on the cash flow during the lifetime of the wind farm. Common values to apply are a 20 year economic lifetime and 5% real interest rate. The strength of the LPC as an assessment criterion is the simplicity of the model for economic effects. However, this simplicity also implies that more complicated economic and market effects are not presented. Furthermore, the wind farm design with the lowest LPC is not necessarily the most desirable. The LPC has to be weighted against other targets and constrictions, such as energy yield per square kilometre, predictability and continuity of energy production and liquidity Cash flow The cost of energy of a wind farm can be decomposed into three major contributions, with a typical division over time. The largest contribution is the investment cost at the beginning of the wind farm life. The second largest contribution are operation and maintenance costs, that are distributed over the entire lifetime and finally the decommissioning costs contribute at the end of the wind farm s life. A straightforward expression of these contributions is obtained under the following assumptions: energy production starts after the construction period, annual O&M costs are constant in terms of purchasing power, annual energy production is constant. decommissioning takes place immediately after the last year of production. 5

6 The resulting LPC equals: C LPC = invest + T t T CO& M ( 1+ r) + C D ( 1+ r) T ' t = t' + 1 Cinvest ' CO& M C D ( 1+ r) = + + T t ae y E y ae y E y ( 1+ r) t = t' + 1 with: C invest = investment costs, C invest = investment costs including interest during construction, C O&M =annual operation and maintenance costs, C D = decommissioning costs, a = annuity factor, defined by: T ' a = t= 1 ( 1+ r) t r = r T '. The annuity factor in the contribution of investment costs reflects a constant annual amortisation in terms of purchasing power. The investment costs are slightly increased due to interest. The effect of interest causes a large reduction of the impact of decommissioning costs. Operation and maintenance costs are not affected by interest, because they are paid from the revenues of the same year Cost components In the wind farm design process the LPC must be broken down to a sufficient level of detail. The following main components can be identified as contributors to the costs of the wind farm: Design and acquisition Construction Turbine Support structure Electrical infrastructure Transportation and installation Project management Operation and maintenance Maintenance Retrofit of turbines Other recurring costs, such as social-, insurance- and administrative costs Decommissioning Decommissioning activities Revenues from salvaged materials and components The level of detail of the breakdown depends on the desired accuracy of the results. Assessment of this accuracy is difficult, but insight may be gained through parameter variations. 6

7 2.1.4 Energy yield and losses Several aspects contribute to the energy production of the wind farm. As for the cost components, the breakdown and modelling of energy production depends on the required accuracy. When the turbine has a technical availability of 100% for energy production its annual energy production, E, can be estimated from: where: E = P( V ) f ( ), i i V i P(V i ) = power of the turbine at wind speed Vi, f(v i ) = time per year in wind speed band with reference V i. The power of the turbine can be further specified by: P 3 ( Vi ) = ρ AVi ARotor η Rotor η Drive train ηgenerator ½, where: ρ A A Rotor η Rotor = air density, = surface of rotor plane, = aerodynamic rotor efficiency, η Drivetrain = drive train efficiency, η Generator = generator efficiency. The efficiencies are different for different wind speeds. Several aspects that relate to the design and operation of the wind farm reduce this technically achievable energy production per wind turbine. The four most common and important ones are: technical availability of the turbine, technical availability of the farm electrical infrastructure, reduced wind speed in wakes of upwind turbines, transformation and transmission losses in the farm electrical infrastructure. The technical availability of the turbine depends on the wind turbine design through failure behaviour and on wind farm operation through the O&M strategy. The technical availability of the farm electrical infrastructure affects single turbines, clusters of turbines or even the entire wind farm. The reduced wind speed in wakes is commonly expressed in an array efficiency that integrates the effect for the entire wind farm for different wind directions and wind speeds. Transformation and transmission losses differ for full load and partial load of the electrical infrastructure. Several additional issues could be considered for special types of wind farm design and operation. For instance the phased construction of the farm, with intermediate start-up of clusters of turbines could be beneficial for large wind farms. Intentional operation of the wind farm at less than maximum power may be profitable, because of better power control and use of the farm as a peak load plant. 7

8 2.2 RAMS aspects Introduction RAMS regards the complete issue of Reliability Availability, Maintainability and Serviceability in all phases of the design process. Commercial onshore wind turbines show very high availability levels nowadays. With a proper service organisation and by ensuring that regular maintenance and repair actions are quick and can be performed in a minimal time the operators of modern wind turbines achieve an availability level of 98% or sometimes even beyond. It must be stressed however that this is achieved through visiting a wind turbine about three to four times a year, either for regular service of for curing (repair) actions. In situations where both limited access and limited availability of maintenance equipment are at stake, such as for the offshore environment, this may easily lead to an unacceptable down time level. This makes it inevitable to assess the O&M demand of an offshore wind farm in conjunction with the other design parameters in order to achieve the required availability level against optimal cost expenditure. The latter being a trade-off between investment costs in order to increase the reliability and the cost and time of maintenance actions to boost the availability to a high level. A number of observations can be made when extrapolating the current onshore situation: The availability of wind farms at real offshore sites employing commercial wind turbines without significantly improved reliability and without optimised operation and maintenance solution may be unacceptably low, e.g. 70% or even less. Reliability of offshore wind energy converters and operation and maintenance solutions should be optimised with respect to the LPC rather than either to capital or to operation and maintenance costs. Operation and maintenance costs mainly related to the wind turbine can account for up to 30% and more of the energy costs The reliability dilemma Reliability as such is not a goal, it is a means to achieve a certain availability level necessary to comply with the primary goals of the wind farm. Without a thorough analysis it is also difficult to determine the availability level that can be reached for a future offshore wind farm. The reason is that achieved availability just as strongly depends upon the reliability of the system as upon the maintenance strategy that is applied for the system. Key factors in this are: the accessibility of the site, which is on its term determined by the weather conditions (wave height, wind speed and visibility) the availability of lifting equipment the ease of maintenance the required service level Reliability and O&M strategy together determine the wind farm availability ands thus its energy yield. Whenever an optimal trade-off is achieved between reliability and O&M strategy for one site this needs certainly not to be optimal for another case. One of the complicating factors is that harsher weather conditions will simultaneously lead to decreased availability and to increased gross energy yield for a given level of reliability under a given O&M strategy. Therefore the operation and maintenance (O&M) aspects of the complete offshore wind farm have to be analysed for each specific site in a comprehensive way in order to determine the optimal reliability level of the wind turbine. 8

9 2.2.3 O&M strategy Of the possible maintenance strategies there is a number that may turn out to be adequate for future offshore wind farms: Preventive and Corrective maintenance Opportunity based maintenance Condition based maintenance The first possibility is more or less a continuation of the onshore service and repair practice. It might be feasible under the assumption that the reliability of the wind turbines is improved significantly, and that the service demand is reduced to say one every 12 to 18 months. Opportunity based maintenance may come up as a good offshore practice. Preventive maintenance is only performed on the occasions that a failure has occurred. The repair and service actions are then combined and the number of (expensive) visits to the turbines is reduced. Such an approach is only possible when the wind turbine is designed for a very flexible servicing period. Condition based maintenance assumes a certain level of condition monitoring in the wind farm. The maintenance crew only carries out service or maintenance when the condition of components indicates the necessity of a visit. This is a rather ultimate form of reducing the number of visits, but requires an extra investment in monitoring systems. An extreme strategy to provide no maintenance at all is evidently the least demanding option with respect to the number if visits. Another advantage is that cranage operations can be done batchwise, which reduces costs significantly. The big disadvantage is loss of production capacity. Simulations showed that a reduction of the (total) failure rate to a value significantly lower then 0.2 failures/year would be necessary to obtain a reasonable availability without undertaking any corrective maintenance over a period of 3 to 5 years. This would mean a factor of about 10 with respect to the current reliability level. It is clear, in this light, that offshore wind farms that adopt such a maintenance strategy are not feasible options for the near future Installation and O&M hardware Since offshore work is between 5 to 10 times more expensive than on land, reduction of installation and maintenance effort is essential. For instance, gravity base support structures that can be floating fully equipped to their final destination offer reduced installation effort in comparison to lifted configurations. Another example of particular importance is the solution of the so-called cranage problem. Apart from wind turbines that are designed such that they can entirely rely on internal cranes or on add-up cranes a heavy crane is required about every five years. The day rate for general purpose equipment from the offshore oil and gas industry can be such that it is better to purchase cranage together with the installation of the farm and use it also for maintenance. A good proposal might be a permanently available modified jack-up platform for a large scale offshore wind farm (typically of the order of a few hundred megawatts). It can be used during installation and it would be a solution, which reduces the maintenance cost, ensures quick repair work leading to high availability and can serve as a permanent basis for maintenance crew. When the design of the wind turbine is sufficiently tuned it might be even possible to use such a jack up as a maintenance base where complete nacelles including blades can be overhauled and prepared for replacement of a failed turbine. 9

10 3 Integrated approach in the design process 3.1 Wind farm optimisation procedure with respect to primary targets A future offshore wind farm will comprise a large number (about 100) of offshore wind energy converters (i.e. wind turbine and support structure), a grid connection system and an integrated operation and maintenance strategy. Only as one entire system the offshore wind farm can provide a considerable amount of electric power in a reliable and cost-efficient way over its projected lifetime. Therefore a number of objectives for an optimum wind farm design can be stated: optimum distribution of investment and operation and maintenance (O&M) costs over the entire wind farm and over its lifetime design optimisation of sub-systems with respect to global goals, e.g. minimum energy price, wind farm availability, overall dynamics, etc high reliability system as a whole and of essential sub-systems e.g. grid connection system, wind turbines, etc adaptation to economy of scale, e.g. wind farms with about 100 units or more symbioses of experience from wind energy and offshore technology High investment costs for the fixed cost elements, i.e. support structures and grid connection, favour large, multi-megawatt converter units and large wind farms with a capacity of at least 100 to 200 MW. The latest commercial wind turbines in the so-called megawatt class, i.e. ratings between 1,5 MW and 2 MW, offer a good starting point for large OWECS. However, even greater turbines of 3 to 5 MW or even more might be promising for offshore sitting in the future. Under such conditions the cost breakdown between the major subsystems (wind turbine, support structure and grid connection) is nearly equally shared. Thus cost reduction has to consider all of these elements simultaneously and contradictory goals have to be balanced with respect to production costs and revenue over the entire life The following stepwise approach can be identified in a wind farm optimisation procedure: Project identification The entire process starts with the project identification: a potential site and an initial wind farm size, as well as identification of the stakeholders an operator and an initial statement of the project objectives Problem statement It defines the objectives of the design (e.g. delivery of a certain amount of electricity from offshore wind energy at a certain location and over a certain time span), the acceptable price (e.g. investment costs, costs of energy) and the demanded quality (e.g. power variation, grid influence, etc). The primary targets are thus clearly defined in this phase of the process. Overall realisation plan Based upon the characterisation of the design problem a feasibility study is carried out which obtains a functional description of a solution. The requirements are refined with respect to criteria as function, technology, construction and economics Preliminary or conceptual design The overall realisation plan forms the input to the conceptual design. The definition of main dimensions and site result in the preliminary design and the final requirements on function, technology, construction and economics Structural pre-design This design phase yields the solution for the problem of the client based on the concept and the site chosen at the end of the conceptual design phase. Again the design work of 10

11 the sub-systems is done in parallel. However, now the interactions between the subsystems are taken into account as complete as possible. For instance, between wind turbine and support structure design a number of iterations might be necessary until the design solution has converged. In a similar fashion reliability options and maintenance strategies are iterated mutually to comply with the primary targets and with the secondary goals defined in the conceptual design phase. Final structural design Next materials and components are chosen, dimensions are fixed, structure i.e. relations between sub-systems is generated and the final design is documented as result of the structural design. System description and detailed specification. In the last step of the design process detailed engineering or elaboration of the final design in the design reports, specifications and drawings for the realisation (i.e. construction, installation and commissioning) and for the exploitation are obtained. Further the use of resources and the data flow is planned. 3.2 Optimisation aspects of wind farms Identification of stakeholders The entire design process starts with the project identification, an identification of the stakeholders and the statement of the project objectives. Stakeholders for offshore projects can be utilities, public organisations, private companies, banks etc. Stakeholders will define some pre-conditions or demands that have to be considered in the project definition. These conditions will mainly regard the economical viability and/or the operational goals of the operational wind farm. Stakeholders can also be external parties that will become involved in the project in some phase. It is of a paramount important that the important external stakeholders are identified as well in the very early phases of the project Definition of primary targets Often the operator of the offshore wind farm, which can be a utility, a private company or public organisation) will also define some goals. One of the most important objectives is the primary target of the offshore wind farm. Is it e.g. a demonstration or a commercial plant; does it aim at the lowest energy costs, the maximum amount of profit, or a certain minimum amount of power. Are there limitations of short term and long term power variations, etc. etc. All these objectives will have a large impact on the optimum design. After approval of the primary targets of the stakeholders and the operator (which can be the same body (bodies)) these should be documented as a primary reference document for the further development of the design process Position of manufacturer and the offshore contractor. At the development of present onshore wind farms the position of the wind turbine manufacturer is a rather central one. Often wind turbine manufacturing companies are operating together with sister companies that perform the project development, and not seldom they operate the wind farms themselves and sell the electricity to a utility. With the development of future offshore wind farms the prominent position of the manufacturer will be quite different. A utility, a private company or a public organisation will perform the project co-ordination, and both wind turbine manufacturers and offshore construction- and operations companies will act as subcontractors. This may have major consequences to the way the wind turbine manufacturers organise their design and production process. In stead of a few standard products that can be sold to several projects, the client will demand dedicated design, in conformity with the primary targets of the stakeholders and the operator of the wind farm. 11

12 3.2.4 Wind farm site and lay-out selection Some of the choices for the wind farm layout may be restricted by external conditions or by the targets set for the wind farm. The optimisation of several of the other issues has interactions with other parts of the design. Most aspects of the wind farm site selection have a major interaction with the design of the electrical infrastructure. Evidently, distances between turbines, distance to shore and the definition of clusters affects cable lengths and routing of the cables. Indirectly, this may affect optimal voltage levels and the selection between AC and DC transmissions. The optimisation of the layout of the farm depends largely on the costs and losses of the electrical transmission balanced against the aerodynamic losses caused by wakes. The reduced average wind speed in the wake leads to power losses with respect to the undisturbed average wind speed. Since the ambient turbulence in the offshore environment is relatively mild mixing of the wake with the ambient wind is slower than onshore. With a small spacing the effect of wakes on turbine loading may also become important. The wake vortex, leading to increased turbulence, gives higher fatigue loading on downwind rotors. When the site is not fixed, its selection has a major interaction with the reliability of the turbine and the support structure design. The reliability of the turbine will become more important for remote and exposed sites, with worse accessibility. Due to variation in the loading environment, water depth and soil conditions, the support structure design is very dependent on site selection and different concepts may be selected at different sites. If soil conditions and water depth vary significantly within one site the support structure design may even vary within the farm. The four wind turbines of the Lely wind farm near Medemblik are stall controlled, constant speed machines. So there is a "forbidden" area of resonance frequencies for the monopiles. But soil conditions varied a lot so that there are three different monopiles for the four wind turbines. Site selection has a minor interaction with power performance of the turbine. For instance, different sites will have a different optimal rated wind speed Wind turbine and support structure selection The OWEC consists of many components for which different concepts can be selected. Several of these concept choices interact with other parts of the OWEC, or with other aspects of the wind farm. Some examples are given, although much more interactions could be identified. Exclusive interactions are often very straightforward, but very essential for the concept selection. For instance, the number of blades and the hub concept have an exclusive interaction since the teetering hub can only be combined with a two-bladed rotor. The jacket or tower and the foundation also have an exclusive interaction. The monopile only combines with the monotower and suction piles are virtually impossible as foundation for a monotower. The generator has a major interaction with the gearbox. The transfer ratio of the gearbox determines the rotational speed of the high-speed shaft in the generator, which is an important design parameter. The direct drive generator exemplifies this interaction. A related minor interaction exists between generator, optimum tip speed ratio and rotor diameter. The support structure interacts in many ways with turbine concepts. In the first place, the loading of the turbine on the tower top is a major interaction. This relates both to the magnitude and the characteristic excitation frequencies of the load spectrum. Important aspects of the turbine are in this case the number of blades, pitch or stall control and speed control. The operation of the rotor in downwind position has a major interaction with the support structure concept, because truss towers have less wake in the downstream airflow. 12

13 Required tower clearance for the blades gives a minor interaction between tower dimensions, blade flexibility and nacelle tilt and overhang. This interaction is most important for truss towers that have larger cross-sectional dimensions. The support structure interacts with operation and maintenance activities, because it has to provide access to the turbine and because it may provide facilities for lifting of larger components or a self-elevating nacelle Electrical infrastructure and Power control The main target of the design of the electrical infrastructure with respect to the cost of energy is the collection and transportation of electrical energy to shore with minimum costs and minimum electrical losses. There is a close interaction with the design of the electrical infrastructure in the turbine. For instance, voltage level and type of generator are important aspects for the design of the farm electrical infrastructure. A more involved interaction between the electrical infrastructure and the turbine is found in power control. The turbines have individual power control by constant or variable speed operation and by pitch or stall control. Variable speed control may also be implemented for clusters of turbines that are connected to a sub-grid operating at its own frequency. This saves inverters at the individual turbines. There may also be a central power control for the wind farm, for instance to reduce the total power output. This could be implemented to operate the wind farm as a peak load plant or to obtain better power quality. The central power control can regulate shut-down or power reduction of individual turbines or clusters. These types of integrated solutions of power control require careful consideration of the effect of the cluster or farm control on the dynamics of the OWEC. Particularly, cluster control affects short-term dynamic behaviour and stability and farm control affects long-term fatigue of the OWEC. The latter effect occurs, because the fatigue of the OWEC depends on the operational status of the turbine Assembly, transport, installation and decommissioning procedures Methods applied in current offshore wind energy projects build on the experience of offshore industry and onshore wind energy as separate disciplines. A consequence of this approach is an expensive installation method, particularly due to many lifting activities. In order to reduce costs of transportation and installation, procedures have to be developed that are tailored for offshore wind farms. This includes an integral approach of assembly, transportation and installation, but also parts of the OWEC design are involved. There is an exclusive interaction between the support structure concept and the installation procedures. For instance, gravity base foundations enable assembly of the entire OWEC in a dry-dock, after which it is towed to the site. This is not possible for a monopile foundation. Also, two-bladed and three-bladed rotors have different implications for transportation and installation. 13

14 A summary of procedures to be considered for the topside of the structure is given in Table 2 below: Table 2 Summary of possible procedures for installation of tower, nacelle and rotor Assembly Onshore (land or dock) Offshore Transportation Self-floating Self-floating with auxiliary floating elements (may be purpose built) On pontoon Installation Tower With large external crane, lifting tower top With smaller external crane lifting above mass centre With smaller external crane erecting tower with hinge connection at tower base Nacelle* With large external crane With internal crane at tower top Self-elevating along tower Hub / Blades* With large external crane With internal crane at tower top *The internal crane and self-elevating nacelle may be beneficial for maintainability An important difference between installation of a wind farm and installation of a conventional offshore structure is the large number of identical structures that need to be installed. The procedures for offshore activities must aim at an optimal use of equipment and short installation times per turbine. For large wind farms this includes the optimisation of (parallel) batched procedures to balance the costs of equipment and the duration of the total installation of the farm. Adaptations to existing equipment or even development of special purpose equipment may prove profitable, because of the repeated use. This equipment may also be used during maintenance or in the installation of other wind farms. The cost reduction is expected particularly for the many high lifting activities of components with relatively low masses. This might be performed with lighter vessels and in shorter times. Acknowledgements This paper is based to a large extend on notes for the lecture Integrated wind farm design, which is part of the course Technology of offshore wind energy, provided by DUWIND. However, much of the ideas presented here were developed during the Opti-OWECS project and the thesis work of Mr. M. Kühn, which is gratefully acknowledged. Documentation of both investigations can be found in the bibliography. 14

15 Bibliography [1] Barltrop, N.D.P., Adams, A.J., Dynamics of Fixed Marine Structures, Butterworth-Heinemann Ltd, Oxford, [2] Cockerill, T.T., Opti-OWECS Final Report Vol. 5: User Guide OWECS Cost Model, Institute for Wind Energy, Delft, [3] Cockerill, T.T.; Harrison, R.; Kühn, M.; Bussel, G.J.W. van, Opti-OWECS Final Report Vol. 3: Comparison of Cost of Offshore Wind Energy at European Sites, Institute for Wind Energy, Delft, [4] Ferguson, M.C., Structural and Economic Optimisation of OWEC Support Structure, In: Proceedings of the European Seminar on Offshore Windenergy in Mediterranean and Other European Seas, Held in La Maddalena, ENEA, Italy, April [5] Ferguson, M.C. (editor); Kühn, M.; Bussel, G.J.W. van; Bierbooms, W.A.A.M.; Cockerill, T.T.; Göransson, B.; Harland, L.A.; Vugts, J.H.; Hes, R., Opti-OWECS Final Report Vol. 4: A Typical Design Solution for an Offshore Wind Energy Conversion System, Institute for Wind Energy, Delft, [6] Hendriks, H.B., e.a., DOWEC Concept Study, Evaluation of Wind Turbine Concepts for Large Scale Offshore Application, In: Proceedings of the European Seminar on Offshore Windenergy in Mediterranean and Other European Seas, Held in Siracusa, ENEA, Italy, April [7] Kühn, M., Dynamics and Design Optimisation of Offshore Wind Wind Energy Conversion Systems, PhD thesis,, Delft, [8] Kühn, M.; Bierbooms, W.A.A.M.; Bussel, G.J.W. van; Ferguson, M.C.; Göransson, B.; Cockerill, T.T.; Harland, L.A.; Vugts, J.H., Opti-OWECS Final Report Vol. 1: Integrated Design Methodology for Offshore Wind Energy Conversion Systems, Institute for Wind Energy, Delft, [9] Kühn, M.; Bierbooms, W.A.A.M.; Bussel, G.J.W. van; Ferguson, M.C.; Göransson, B.; Cockerill, T.T.; Harrison, R.; Harland, L.A.; Vugts, J.H.; Wiecherink, R., Opti-OWECS Final Report Vol. 0: Structural and Economic Optimisation of Bottom-Mounted Offshore Wind Energy Converters, Executive Summary, Institute for Wind Energy, Delft, [10] Kühn, M. (editor); Bussel, G.J.W. van; Schöntag, C.; Cockerill, T.T.; Harrison, R.; Harland, L.A.; Vugts, J.H., Opti-OWECS Final Report Vol. 2: Methods Assisting the Design of Offshore Wind Energy Conversion Systems, Institute for Wind Energy, Delft, [11] Nitteberg, J. (editor); Boer, A.A. de; Simpson P.B., Expert Group Study on Recommended Practises for Wind Turbine Testing and Evaluation, 2. Estimation of Cost of Energy from Wind Energy Conversion Systems, IEA, [12] Zaaijer, M.B., e.a., Starting-point and Methodology of Cost Optimisation for the Conceptual Design of DOWEC, Section Wind Energy, Delft, March

INSTALLATION and LOGISTICS of OFFSHORE WIND FARMS

INSTALLATION and LOGISTICS of OFFSHORE WIND FARMS POWER Offshore Summer School 2006 INSTALLATION and LOGISTICS of OFFSHORE WIND FARMS Gerard van Bussel The Netherlands Offshore transport and installation vessels Semi Submersible Sheer leg crane Ship type

More information

Nordex SE. Capital Markets Day Products & Sales - Lars Bondo Krogsgaard

Nordex SE. Capital Markets Day Products & Sales - Lars Bondo Krogsgaard Nordex SE Capital Markets Day Products & Sales - Lars Bondo Krogsgaard Rostock, 13 October 2011 SUMMARY The situation in the wind industry has changed: Attractive medium-term growth prospects Overcapacity

More information

Offshore Wind Farm Layout Design A Systems Engineering Approach. B. J. Gribben, N. Williams, D. Ranford Frazer-Nash Consultancy

Offshore Wind Farm Layout Design A Systems Engineering Approach. B. J. Gribben, N. Williams, D. Ranford Frazer-Nash Consultancy Offshore Wind Farm Layout Design A Systems Engineering Approach B. J. Gribben, N. Williams, D. Ranford Frazer-Nash Consultancy 0 Paper presented at Ocean Power Fluid Machinery, October 2010 Offshore Wind

More information

Siemens D7 platform 6.0-MW and 7.0-MW direct drive wind turbines. The new standard for offshore. siemens.com/wind

Siemens D7 platform 6.0-MW and 7.0-MW direct drive wind turbines. The new standard for offshore. siemens.com/wind Siemens D7 platform 6.0-MW and 7.0-MW direct drive wind turbines The new standard for offshore siemens.com/wind The first SWT-6.0-154 prototype Siemens, the offshore leader Intelligent ways to drive down

More information

Case Study 5 Use of Wind Turbine Technology

Case Study 5 Use of Wind Turbine Technology Case Study 5 Use of Wind Turbine Technology 1. Context Hong Kong relies on an adequate and reliable electricity supply for its economic development. Our electricity needs are met by the two electricity

More information

Siemens D3 platform 3.0-MW, 3.2-MW, 3.3-MW, and 3.4-MW direct drive turbines. Reduced complexity, increased profitability. siemens.

Siemens D3 platform 3.0-MW, 3.2-MW, 3.3-MW, and 3.4-MW direct drive turbines. Reduced complexity, increased profitability. siemens. Siemens D3 platform 3.0-MW, 3.2-MW, 3.3-MW, and 3.4-MW direct drive turbines Reduced complexity, increased profitability siemens.com / wind As the major driver of innovation with more than 30 years of

More information

Title: IEC WT 01 vs. IEC 61400-22 Development of a new standard and innovations in certification of Wind Turbines. mike.woebbeking@gl-group.

Title: IEC WT 01 vs. IEC 61400-22 Development of a new standard and innovations in certification of Wind Turbines. mike.woebbeking@gl-group. Title: IEC WT 01 vs. IEC 61400-22 Development of a new standard and innovations in certification of Wind Turbines Author: Address: Mike Woebbeking Germanischer Lloyd Industrial Services GmbH, Business

More information

Opti-OWECS Final Report Vol. 5: User Guide OWECS Cost Model

Opti-OWECS Final Report Vol. 5: User Guide OWECS Cost Model Opti-OWECS Final Report Vol. 5: User Guide OWECS Cost Model T.T. Cockerill Renewable Energy Centre, University of Sunderland, UK Contract JOR3-CT95-0087 FINAL REPORT January 1996 to December 1997 Research

More information

Opti-OWECS Final Report Vol. 3: Comparison of Cost of Offshore Wind Energy at European Sites

Opti-OWECS Final Report Vol. 3: Comparison of Cost of Offshore Wind Energy at European Sites Opti-OWECS Final Report Vol. 3: Comparison of Cost of Offshore Wind Energy at European Sites T.T. Cockerill 1, R. Harrison 1, M. Kühn 2, G.J.W. van Bussel 2 1 Renewable Energy Centre, University of Sunderland,

More information

Brochure. Generators for wind power Proven generators reliable power

Brochure. Generators for wind power Proven generators reliable power Brochure Generators for wind power Proven generators reliable power We provide motors, generators and mechanical power transmission products, services and expertise to save energy and improve customers

More information

Scottish Enterprise. Offshore Wind Power: Priorities for Research and Development (R&D) and Innovation. Supporting a globally competitive Scotland

Scottish Enterprise. Offshore Wind Power: Priorities for Research and Development (R&D) and Innovation. Supporting a globally competitive Scotland Scottish Enterprise OPPORTUNITIES IN ENERGY Offshore Wind Power: Priorities for Research and Development (R&D) and Innovation Supporting a globally competitive Scotland Introduction Successful offshore

More information

The Reliance on Wind Energy Depends on Advancements in Blade Pitch Control

The Reliance on Wind Energy Depends on Advancements in Blade Pitch Control INSIGHT# 2010-23MPH JULY 6, 2010 The Reliance on Wind Energy Depends on Advancements in Blade Pitch Control By Sal Spada Overview Source: GWEC Many nations are in the process of making wind power an integral

More information

Tidal Energy. Wind Energy. Transmission & Distribution Network. Offshore Substation. Onshore Substation. Tidal Stream Energy.

Tidal Energy. Wind Energy. Transmission & Distribution Network. Offshore Substation. Onshore Substation. Tidal Stream Energy. Offshore Renewables Tidal Energy Transmission & Distribution Network Offshore Substation Wind Energy Onshore Substation Tidal Stream Energy Consumer Atkins in Offshore Renewables The offshore wind journey

More information

installation, operations & maintenance

installation, operations & maintenance installation, operations & maintenance Contents Introduction... 2 The offshore wind opportunity... 2 Innovation in offshore wind... 2 The cost of offshore wind projects... 2 Offshore wind foundation, turbine

More information

Offshore Work Packages

Offshore Work Packages Rampion Offshore Wind Farm Offshore Work Packages Meet The Buyer Naren Mistry, Engineering Manager 26 th Feb 2014 Rampion Offshore Project Scope Design, manufacture, transportation and Installation: Up

More information

GE Renewable Energy. GE s 3 MW Platform POWERFUL AND EFFICIENT. www.ge.com/wind

GE Renewable Energy. GE s 3 MW Platform POWERFUL AND EFFICIENT. www.ge.com/wind GE Renewable Energy GE s 3 MW Platform POWERFUL AND EFFICIENT www.ge.com/wind GE S 3 MW PLATFORM PITCH Since entering the wind industry in 2002, GE Renewable Energy has invested more CONTROLS than $2 billion

More information

Introduction BAM and Van Oord GBF - Concrete Centre Conference, December 2012

Introduction BAM and Van Oord GBF - Concrete Centre Conference, December 2012 Introduction BAM and Van Oord have teamed up to Design, Manufacture and install reinforced concrete gravity base foundations (GBFs) for the offshore wind industry. The concept for the GBF has been developed

More information

Design of Offshore Wind Farms Prepared by Flemming Jakobsen & Andrass Ziska Davidsen LICENGINEERING A/S

Design of Offshore Wind Farms Prepared by Flemming Jakobsen & Andrass Ziska Davidsen LICENGINEERING A/S Design of Offshore Wind Farms Prepared by Flemming Jakobsen & Andrass Ziska Davidsen Types of Foundations Overview of selected support structure and foundation types. From top left: 1. Monopile; 2. Tripod;

More information

MAXIMISING YOUR. Offshore wind assets ASSET OPERATION & MAINTENANCE SERVICES

MAXIMISING YOUR. Offshore wind assets ASSET OPERATION & MAINTENANCE SERVICES MAXIMISING YOUR Offshore wind assets ASSET OPERATION & MAINTENANCE SERVICES RES is one of the world s leading renewable energy companies active in the wind, wave, tidal, solar and biomass sectors Asset

More information

GE Power & Water Renewable Energy. Digital Wind Farm THE NEXT EVOLUTION OF WIND ENERGY. www.ge.com/wind

GE Power & Water Renewable Energy. Digital Wind Farm THE NEXT EVOLUTION OF WIND ENERGY. www.ge.com/wind GE Power & Water Renewable Energy Digital Wind Farm THE NEXT EVOLUTION OF WIND ENERGY www.ge.com/wind GE S DIGITAL WIND FARM PITCH Since entering the wind industry in 2002, GE Power & Water s Renewable

More information

Monobuckets and the competitiveness versus monopiles and jacket structures.

Monobuckets and the competitiveness versus monopiles and jacket structures. Monobuckets and the competitiveness versus monopiles and jacket structures. Lars Bo Ibsen, Aalborg University, Professor. Foundation concepts for offshore Wind Turbines The Universal Foundation Carbon

More information

Offshore Wind: some of the Engineering Challenges Ahead

Offshore Wind: some of the Engineering Challenges Ahead Offshore Wind: some of the Engineering Challenges Ahead David Infield CDT in Wind Energy Systems Institute of Energy and Environment University of Strathclyde International context (from IPCC report) Greenhouse

More information

Haliade 150-6MW Experiencia funcional con la nueva generación offshore

Haliade 150-6MW Experiencia funcional con la nueva generación offshore Haliade 150-6MW Experiencia funcional con la nueva generación offshore Bilbao Marine Energy week 2013 Daniel Castell, Offshore Wind Platform Director 17/04/2013 Alstom Group Three main activities in four

More information

V66 1.75 MW & V66 2.0 MW (OFFSHORE)

V66 1.75 MW & V66 2.0 MW (OFFSHORE) V66 1.75 MW & V66 2. MW (OFFSHORE) with OptiTip and OptiSpeed Offshore and onshore There are two versions of the V66 turbine: a 2. MW model for offshore sites, and a 1.75 MW model for inland locations.

More information

QUALITY OF WIND POWER. How does quality affect the cost of electricity generation from wind power?

QUALITY OF WIND POWER. How does quality affect the cost of electricity generation from wind power? QUALITY OF WIND POWER How does quality affect the cost of electricity generation from wind power? QUALITY OF WIND POWER Wind power is a cornerstone in the green transition of the power sector, and onshore

More information

V52-850 kw The turbine that goes anywhere

V52-850 kw The turbine that goes anywhere V2-8 kw The turbine that goes anywhere Versatile, efficient, dependable and popular The highly efficient operation and flexible configuration of the V2 make this turbine an excellent choice for all kinds

More information

Wind Turbine Technology Offshore

Wind Turbine Technology Offshore Wind Turbine Technology Offshore J R C Armstrong J A Consult * SYNOPSIS This paper looks at modern trends in onshore turbines, and the extent to which these turbines will be used offshore. The results

More information

COWI offshore wind marine engineering services

COWI offshore wind marine engineering services COWI offshore wind marine engineering services 2 COWI expertise COWI is a highly versatile and multidisciplinary company. We provide services within engineering, environment and economics and operate worldwide

More information

4. PROGRAMME OF WORK: PROJECT ACTIVITIES, TIMESCALE AND COSTS

4. PROGRAMME OF WORK: PROJECT ACTIVITIES, TIMESCALE AND COSTS The Application of Suction Caisson Foundations to Offshore Wind Turbines Extracts from a proposal to the DTI Participants: SLP Engineering Ltd, Shell Renewables Ltd, Enron Wind Overseas Development Ltd,

More information

V112-3.0 MW. Your best option for low cost energy production at low and medium wind sites. Federico Gonzalez Vives. Director Technology.

V112-3.0 MW. Your best option for low cost energy production at low and medium wind sites. Federico Gonzalez Vives. Director Technology. V112-3.0 MW Your best option for low cost energy production at low and medium wind sites Federico Gonzalez Vives. Director Technology. Vestas MED REOLTEC. Jornadas tecnicas 17 de junio de 2010 vestas.com

More information

Offshore Wind. IEEE Boston PES - November 16, 2010

Offshore Wind. IEEE Boston PES - November 16, 2010 Offshore Wind IEEE Boston PES - November 16, 2010 Offshore Wind A high-level overview of offshore wind project development identifying current technologies, challenges, risks and costs. Presented by: Brook

More information

Offshore Wind Turbine Support Structures

Offshore Wind Turbine Support Structures 1 Wind Power R&D Seminar Deep Sea Offshore Wind Royal Garden Hotel, Trondheim, Norway January 21, 2011 Effect of Foundation Modeling Methodology on the Dynamic Response of Offshore Wind Turbine Support

More information

GRAVITY BASE FOUNDATIONS

GRAVITY BASE FOUNDATIONS GRAVITY BASE FOUNDATIONS 2 Crown with reference to Marine All Activity Map Concrete gravity base foundations able to be floated and towed out to deeper water windfarms and installed without specialist

More information

Steel construction. Solutions for the renewable energy and offshore sectors. published by energyengineering magazine

Steel construction. Solutions for the renewable energy and offshore sectors. published by energyengineering magazine Steel construction Solutions for the renewable energy and offshore sectors published by energyengineering magazine SCI-Energy-Supplement.indd 1 25/10/2010 13:00:22 Introduction SCI is a world leader in

More information

Comparison of monopile, tripod, suction bucket and gravity base design for a 6 MW turbine

Comparison of monopile, tripod, suction bucket and gravity base design for a 6 MW turbine Comparison of monopile, tripod, suction bucket and gravity base design for a MW turbine Michiel B. Zaaijer Delft University of Technology, Section Wind Energy Stevinweg, 228 CN Delft, The Netherlands Tel.

More information

Offshore Deployment SYNOPSIS

Offshore Deployment SYNOPSIS Offshore Deployment P.R.Blott Technical Director, Mayflower Energy Limited, Middlesbrough, UK SYNOPSIS This paper presents an analysis of the reasons for deploying wind turbines in offshore locations by

More information

Who are we? *Based on an average annual domestic household electricity consumption of 4,700KWh (DECC).

Who are we? *Based on an average annual domestic household electricity consumption of 4,700KWh (DECC). Who are we? We re one of the world s leading power and gas companies. Here in the UK, we supply energy to more than 5 million customers, generate enough electricity for around 8 million homes and employ

More information

Offshore Windfarm Egmond aan Zee 4 years of Operation

Offshore Windfarm Egmond aan Zee 4 years of Operation Offshore Windfarm Egmond aan Zee 4 years of Operation CUEN Offshore Wind Energy Conference 28 June 2011, Cambridge Elke Delnooz Operations Support Manager www.noordzeewind.nl 1 Contents Project description

More information

E.ON Offshore Wind Energy Factbook

E.ON Offshore Wind Energy Factbook E.ON Offshore Wind Energy Factbook E.ON Climate & Renewables September 2012 Introduction 3 Offshore Wind Industry 5 Challenges of Offshore Wind 9 Technical Solutions 14 E.ON s Approach 37 Factsheets of

More information

Structural concepts for minimum facility platforms for Marginal field development in western offshore, India

Structural concepts for minimum facility platforms for Marginal field development in western offshore, India Structural concepts for minimum facility platforms for Marginal field development in western offshore, India A collaborative project By IIT Madras and IEOT,ONGC 24 April 2007 1 Outline Conventional Wellhead

More information

An insights report by the Energy Technologies Institute. Offshore Wind Floating Wind Technology

An insights report by the Energy Technologies Institute. Offshore Wind Floating Wind Technology An insights report by the Energy Technologies Institute Offshore Wind Floating Wind Technology 202 03 Contents Key headlines Introduction 04 Project findings 05 Floating offshore wind 06 The Floating Platform

More information

E.ON Offshore Wind Energy Factbook

E.ON Offshore Wind Energy Factbook E.ON Offshore Wind Energy Factbook E.ON Climate & Renewables December 2011 1 Picture taken at E.ON Offshore Project - Robin Rigg (United Kingdom, 2009) 2 Dear Reader, Offshore wind is one of the most fascinating

More information

Dansk Offshore Netværk, Lindø Industripark, 21. April 2015 The Road to Below 10 ct /kwh

Dansk Offshore Netværk, Lindø Industripark, 21. April 2015 The Road to Below 10 ct /kwh Dansk Offshore Netværk, Lindø Industripark, 21. April 2015 The Road to Below 10 ct /kwh, Head of Cost of Energy Siemens AG, Wind Power and Renewables Answers for energy. Introduction Siemens Wind Power

More information

Submarine Power Cables. State-of-the-art production facility, more than 100 years of experience and reference installations around the world.

Submarine Power Cables. State-of-the-art production facility, more than 100 years of experience and reference installations around the world. Submarine Power Cables State-of-the-art production facility, more than 100 years of experience and reference installations around the world. Reliable submarine power cables ABB is one of the world s most

More information

The installation and servicing

The installation and servicing European Forum for Renewable Energy Sources The installation and servicing of offshore wind farms Kaj Lindvig, CSO, A2SEA A/S 16 th September 2010 A2SEA Started 1 st July 2000 100% dedicated offshore wind

More information

Advantages of our solution

Advantages of our solution Introduction BAM and Van Oord have teamed up to design, manufacture and install reinforced concrete gravity base foundations (GBFs) for the offshore wind industry. The concept for the GBF has been developed

More information

Offshore Structures. Offshore Drilling Equipment

Offshore Structures. Offshore Drilling Equipment Offshore Structures Offshore Drilling Equipment The drill string is lowered through a conduit (riser). The drill string consists of a drill bit, drill collar and drill pipe. Drill pipe sections are added

More information

Ocean Energy: Cost of Energy and Cost Reduction Opportunities. May 2013

Ocean Energy: Cost of Energy and Cost Reduction Opportunities. May 2013 Ocean Energy: Cost of Energy and Cost Reduction Opportunities M May 2013 Table of Contents 1 Introduction... 3 2 Factors considered in cost calculation... 4 2.1 Lifetime levelised cost of energy calculation...

More information

O&M Cost Modelling, Technical Losses and Associated Uncertainties

O&M Cost Modelling, Technical Losses and Associated Uncertainties O&M Cost Modelling, Technical Losses and Associated Uncertainties A. Albers Deutsche WindGuard Consulting GmbH, Oldenburger Straße, D-31 Varel, Germany E-mail: a.albers@windguard.de, Tel: (++9) ()1/91-1,

More information

Critical Limitations of Wind Turbine Power Curve Warranties

Critical Limitations of Wind Turbine Power Curve Warranties Critical Limitations of Wind Turbine Power Curve Warranties A. Albers Deutsche WindGuard Consulting GmbH, Oldenburger Straße 65, D-26316 Varel, Germany E-mail: a.albers@windguard.de, Tel: (++49) (0)4451/9515-15,

More information

Nordex SE. Nordex goes Offshore

Nordex SE. Nordex goes Offshore Nordex SE Nordex goes Offshore Hannover, April 2011 Content 1. Offshore Wind Market 2. Nordex Offshore History & Future 3. Competition & Technical Development 4. The N150/6000 2 Strong growth prospects

More information

Cost Benefit Methodology for Optimal Design of Offshore Transmission Systems

Cost Benefit Methodology for Optimal Design of Offshore Transmission Systems Centre for Sustainable Electricity and Distributed Generation Cost Benefit Methodology for Optimal Design of Offshore Transmission Systems Predrag Djapic and Goran Strbac July 2008 FUNDED BY BERR URN 08/1144

More information

OCEAN LÍDER: Ocean Renewable Energy Leaders

OCEAN LÍDER: Ocean Renewable Energy Leaders OCEAN LÍDER: Ocean Renewable Energy Leaders Juan Amate López Offshore Projects Manager / Iberdrola I&C 7th October Removing barriers and building competences Ocean Líder : Harvesting the seas Road to Ocean

More information

CHAPTER 5 PHOTOVOLTAIC SYSTEM DESIGN

CHAPTER 5 PHOTOVOLTAIC SYSTEM DESIGN CHAPTER 5 PHOTOVOLTAIC SYSTEM DESIGN 5.1 Introduction So far in the development of this research, the focus has been to estimate the available insolation at a particular location on the earth s surface

More information

SITE SPECIFIC WIND TURBINE FOUNDATION CERTIFICATION

SITE SPECIFIC WIND TURBINE FOUNDATION CERTIFICATION SITE SPECIFIC WIND TURBINE FOUNDATION CERTIFICATION Mary Prabha, Nishikant Dash, Stefan Baars, GL Renewables Certification, 1st Floor, No.- 494, U.P Royal Building, 4th Cross, Sampige Road, Malleswaram,

More information

OWPST & Titan 200 & UK Offshore

OWPST & Titan 200 & UK Offshore OWPST & Titan 200 & UK Offshore A look at the Company, our Product and the Technology being applied in the UK Offshore Market Introduction Douglas Hines CEO/President Offshore Wind Power Systems of Texas

More information

Geotechnical Design Monopile Foundations for Offshore Wind Turbines

Geotechnical Design Monopile Foundations for Offshore Wind Turbines Geotechnical Design Monopile Foundations for Offshore Wind Turbines R.J.N.J. Luiken, Structural specialist Van Oord Dredging and Marine Contractors Copyright Van Oord 2012 1 Content Content - Company profile

More information

Development of 5-MW Offshore Wind Turbine and 2-MW Floating Offshore Wind Turbine Technology

Development of 5-MW Offshore Wind Turbine and 2-MW Floating Offshore Wind Turbine Technology Hitachi Review Vol. 63 (2014), No. 7 414 Featured Articles Development of 5-MW Offshore Wind Turbine and 2-MW Floating Offshore Wind Turbine Technology Mitsuru Saeki Ikuo Tobinaga Junichi Sugino Takashi

More information

Denmark - supplier of competitive offshore wind solutions

Denmark - supplier of competitive offshore wind solutions report from megavind December 2010 Denmark - supplier of competitive offshore wind solutions Megavind s Strategy for Offshore Wind Research, Development and Demonstration Content Abbreviations 2 Preface

More information

Siemens Wind Turbine SWT-2.3-108. The new productivity benchmark. www.siemens.com/wind

Siemens Wind Turbine SWT-2.3-108. The new productivity benchmark. www.siemens.com/wind Siemens Wind Turbine SWT-2.3-108 The new productivity benchmark www.siemens.com/wind The industry standard, redefined The Siemens 2.3-MW family has firmly established itself as the tried and tested workhorse

More information

PMG vs. DFIG the big generator technology debate

PMG vs. DFIG the big generator technology debate PMG The Switch challenges the industry on the superior total life cycle cost efficiency and reliability of PMG-FPC drive train solutions. gear DFIG PMG vs. DFIG the big generator technology debate In the

More information

User manual data files meteorological mast NoordzeeWind

User manual data files meteorological mast NoordzeeWind User manual data files meteorological mast NoordzeeWind Document code: NZW-16-S-4-R03 Version: 2.0 Date: 1 October 2007 Author: ing. HJ Kouwenhoven User manual data files meteorological mast NoordzeeWind

More information

Offshore Wind Energy Ready to Power a Sustainable Europe

Offshore Wind Energy Ready to Power a Sustainable Europe Offshore Wind Energy Ready to Power a Sustainable Europe Final Report Concerted Action on Offshore Wind Energy in Europe December 2001 Supported by the European Commission Report Ref.: Duwind 2001.006

More information

London Array Off-Shore Wind Farm

London Array Off-Shore Wind Farm London Array Off-Shore Wind Farm 1 Jamie R Mathlin Construction Manager Off-Shore Sub-Stations Project Commissioning Manager 27 Years Experience in the Power Industry Grid Trained Electrical Engineer 10

More information

THE COMPOSITE DISC - A NEW JOINT FOR HIGH POWER DRIVESHAFTS

THE COMPOSITE DISC - A NEW JOINT FOR HIGH POWER DRIVESHAFTS THE COMPOSITE DISC - A NEW JOINT FOR HIGH POWER DRIVESHAFTS Dr Andrew Pollard Principal Engineer GKN Technology UK INTRODUCTION There is a wide choice of flexible couplings for power transmission applications,

More information

Navires de travail pour la production d énergie en mer. Points communs et différences entre hydrocarbures et energie décarbonées

Navires de travail pour la production d énergie en mer. Points communs et différences entre hydrocarbures et energie décarbonées Navires de travail pour la production d énergie en mer Points communs et différences entre hydrocarbures et energie décarbonées Table of Contents 1. GeoSea company profile 2. Key References Oil & Gas 3.

More information

Advanced Electricity Storage Technologies Program. Smart Energy Storage (Trading as Ecoult) Final Public Report

Advanced Electricity Storage Technologies Program. Smart Energy Storage (Trading as Ecoult) Final Public Report Advanced Electricity Storage Technologies Program Smart Energy Storage (Trading as Ecoult) Final Public Report Introduction Ecoult, working with CSIRO as its principal subcontractor, was provided $1,825,440

More information

Overturning Stability of Offshore Wind Power Substructure with Bucket Foundation

Overturning Stability of Offshore Wind Power Substructure with Bucket Foundation Website: www.ijetae.com (ISSN 2250-2459, ISO 9001:2008 Certified Journal, Volume 5, Issue 10, October 2015) Overturning Stability of Offshore Wind Power Substructure with Bucket Foundation Young-Jun You

More information

HVDC Technology for Large Scale Offshore Wind Connections

HVDC Technology for Large Scale Offshore Wind Connections HVDC Technology for Large Scale Offshore Wind Connections Nandan Mahimkar, Gunnar Persson,Claes Westerlind, ABB AB, SE-771 80, Ludvika, Sweden, nandan.mahimkar@in.abb.com, gunnar.persson@se.abb.com,claes.westerlind@se.abb.com,

More information

Assessment of the Economic Benefits of Offshore Wind in the Mid-Atlantic

Assessment of the Economic Benefits of Offshore Wind in the Mid-Atlantic Assessment of the Economic Benefits of Offshore Wind in the Mid-Atlantic February 2012 Delivered to: Overview Impact Results New Jersey Tipping Point Discussion Economic Impact Results Review Summary results

More information

Outline. Introduction to Wind Energy. US Wind Energy Installations. ME 483 Alternative Energy Engineering II 1

Outline. Introduction to Wind Energy. US Wind Energy Installations. ME 483 Alternative Energy Engineering II 1 Wind Power Introduction February, Introduction to Wind Energy Larry Caretto Mechanical Engineering 48 Alternative Energy Engineering II February, Outline Current use of wind energy Advantages and disadvantages

More information

INNWIND.EU Offshore wind energy DTU Contributions to WP4.2 Technology, ecomony, trends and research. Henrik Bredmose Thomas Buhl

INNWIND.EU Offshore wind energy DTU Contributions to WP4.2 Technology, ecomony, trends and research. Henrik Bredmose Thomas Buhl INNWIND.EU Offshore wind energy DTU Contributions to WP4.2 Technology, ecomony, trends and research Henrik Bredmose Thomas Buhl DTU organization 2 DTU Wind Energy Technical University of Denmark Sections:

More information

The Delft Offshore Wind Turbine Concept (DOT)

The Delft Offshore Wind Turbine Concept (DOT) December 2009 The Delft Offshore Wind Turbine Concept (DOT) A hydraulic solution for offshore wind energy Antonio Jarquín Laguna Delft University of Technology Challenge the future Table of Contents Current

More information

Onshore Wind Services

Onshore Wind Services GE Renewable Energy Onshore Wind Services www.ge.com/wind PITCH TABLE OF CONTENTS: 3 Operate and Maintain 3 Asset and Park Management 5 Turbine Maintenance 8 Enhance and Optimize 8 Wind PowerUp * Services

More information

Wind Turbine Technology Overview

Wind Turbine Technology Overview Wind Turbine Technology Overview Course No: M01-009 Credit: 1 PDH Brian McCaffrey, P.E. Continuing Education and Development, Inc. 9 Greyridge Farm Court Stony Point, NY 10980 P: (877) 322-5800 F: (877)

More information

WIND TURBINE TECHNOLOGY

WIND TURBINE TECHNOLOGY Module 2.2-2 WIND TURBINE TECHNOLOGY Electrical System Gerhard J. Gerdes Workshop on Renewable Energies November 14-25, 2005 Nadi, Republic of the Fiji Islands Contents Module 2.2 Types of generator systems

More information

PMDD WIND TURBINE 1.5MW

PMDD WIND TURBINE 1.5MW 1.5MW PMDD WIND TURBINE Generator Stator Rotor Blade Wind Measurement Equipment Casted Hub Auxiliary Crane Pitch System Base Frame Generator PM Rotor GOLDWIND 1.5MW PERMANENT MAGNET DIRECT-DRIVE (PMDD)

More information

Figure 1: The existing 12 300 kw turbines with the Avedøre power plant, source [3].

Figure 1: The existing 12 300 kw turbines with the Avedøre power plant, source [3]. HVIDOVRE OFFSHORE WIND FARM Hans Christian Sørensen SPOK ApS / Hvidovre Vindmøllelaug I/S, Blegdamsvej 4, DK 2200, Copenhagen N, Denmark, E-mail: consult@spok.dk, Phone: +45 35360219/+45 28110219, Fax:

More information

Final Report Volume 0

Final Report Volume 0 Contract No. JOR3-CT95-0089 Page 1 of 16 COST OPTIMIZING OF LARGE-SCALE OFFSHORE WIND FARMS Final Report Volume 0 SK Power Company i/s by ELKRAFT A.m.b.A./SEAS A.m.b.A. Contract No. JOR3-CT95-0089 PUBLISHABLE

More information

Dynamics of Offshore Wind Turbines

Dynamics of Offshore Wind Turbines Proceedings of the Twenty-first (2011) International Offshore and Polar Engineering Conference Maui, Hawaii, USA, June 19-24, 2011 Copyright 2011 by the International Society of Offshore and Polar Engineers

More information

Offshore Windpark DanTysk. Cost-Effective Foundations Design to Installation

Offshore Windpark DanTysk. Cost-Effective Foundations Design to Installation Offshore Windpark DanTysk Cost-Effective Foundations Design to Installation. Kieler Branchenfokus: Kieler Winindustrie Windindustrie 2015.02.03 3.2.15 Vattenfall s Offshore Pipeline Onshore capacity: 720

More information

JEDI Capital Expenditure Update

JEDI Capital Expenditure Update JEDI Capital Expenditure Update U.S. Offshore Wind Market and Supply Chain Workshop Presented by Aaron Smith National Renewable Energy Laboratory Brent Cooper Ocean & Coastal Consultants, Inc. 2014 Navigant

More information

Life-Cycle Cost of a Floating Offshore Wind Farm

Life-Cycle Cost of a Floating Offshore Wind Farm Life-Cycle Cost of a Floating Offshore Wind Farm Laura Castro-Santos Abstract This chapter describes a general methodology in order to calculate the costs of a floating offshore wind farm. It is based

More information

Offshore wind potential in Europe and review of offshore resource modelling techniques

Offshore wind potential in Europe and review of offshore resource modelling techniques Offshore wind potential in Europe and review of offshore resource modelling techniques Rebecca Barthelmie, Sten Frandsen & Sara Pryor (Risø National Laboratory, Wind Energy Department), Colin Morgan (Garrad

More information

Simplified Design as Secret to higher Performance: Siemens Direct Drive Technology

Simplified Design as Secret to higher Performance: Siemens Direct Drive Technology Simplified Design as Secret to higher Performance: Siemens Direct Drive Technology Formatvorlage Gunnar Liehr, Head des Untertitelmasters of Sales Wind Power durch Region Klicken Central bearbeiten siemens.at/future-of-energy

More information

Project description. Power Electronics for Reliable and Energy efficient Renewable Energy Systems

Project description. Power Electronics for Reliable and Energy efficient Renewable Energy Systems Project description Title: Power Electronics for Reliable and Energy efficient Renewable Energy Systems OBJECTIVES Principal objective Provide competence and decision basis for enabling reliable and energy

More information

THE NEW GUIDELINE FOR THE CERTIFICATION OF WIND TURBINES, EDITION 2010

THE NEW GUIDELINE FOR THE CERTIFICATION OF WIND TURBINES, EDITION 2010 THE NEW GUIDELINE FOR THE CERTIFICATION OF WIND TURBINES, EDITION 2010 Mike Woebbeking Germanischer Lloyd Industrial Services GmbH, Renewables Certification (GL) Brooktorkai 18, 20457 Hamburg, GERMANY

More information

Forces on Large Steam Turbine Blades

Forces on Large Steam Turbine Blades Forces on Large Steam Turbine Blades RWE npower Mechanical and Electrical Engineering Power Industry INTRODUCTION RWE npower is a leading integrated UK energy company and is part of the RWE Group, one

More information

Insights into Tidal Stream energy

Insights into Tidal Stream energy An insights report by the Energy Technologies Institute Tidal Energy Insights into Tidal Stream energy 02 03 Energy Technologies Institute www.eti.co.uk Offshore Renewables Key headlines Our Marine technology

More information

CASE STUDY. History. National Renewable Energy Laboratory Testing Wind Turbine Power Generators using PULSE. United States of America

CASE STUDY. History. National Renewable Energy Laboratory Testing Wind Turbine Power Generators using PULSE. United States of America CASE STUDY National Renewable Energy Laboratory Testing Wind Turbine Power Generators using PULSE United States of America Industrial Products PULSE The National Renewable Energy Laboratory (NREL) is operated

More information

Wind Turbine Power Calculations

Wind Turbine Power Calculations Wind Turbine Power Calculations RWE npower renewables Mechanical and Electrical Engineering Power Industry INTRODUCTION RWE npower is a leading integrated UK energy company and is part of the RWE Group,

More information

EXPERT REMANUFACTURED WIND TURBINE

EXPERT REMANUFACTURED WIND TURBINE EXPERT REMANUFACTURED WIND TURBINE Repowering Solutions is a division of Jeraneas Group of companies. Our core business is the remanufacturing of wind turbines of different sizes; a work that we have been

More information

HV Submarine Cable Systems Design, Testing and Installation

HV Submarine Cable Systems Design, Testing and Installation HV Submarine Cable Systems Design, Testing and Installation CIGRE Ireland Technical Seminar 6 th October 2010 Robert Donaghy Senior Consultant Engineer, ESB International Presentation Overview Applications

More information

Manufactured by Seaforth Energy. The world s most proven 50 kw wind turbine

Manufactured by Seaforth Energy. The world s most proven 50 kw wind turbine Manufactured by Seaforth Energy The world s most proven 50 kw wind turbine The world s most proven 50 kw wind turbine The AOC 15/50 is the world s most proven 50 kw wind turbine. Manufactured by Seaforth

More information

Transient Wind Events and Their Effect on Drive-Train Loads INTERNATIONAL. siteurpublications

Transient Wind Events and Their Effect on Drive-Train Loads INTERNATIONAL. siteurpublications Transient Wind Events and Their Effect on Drive-Train Loads INTERNATIONAL April/May 2015 siteurpublications Volume 11 No. 3 Feature Although wind turbines have been around for decades, recent research

More information

ENERCON WIND TURBINES

ENERCON WIND TURBINES Sales ENERCON GmbH Dreekamp 5 2665 Aurich Germany Phone +49 494192 7 Fax +49 4941 92 71 9 vertrieb@enercon.de E-33 E-44 E-48 E-53 E-7 E-82 ENERCON WIND TURBINES PRODUCT OVERVIEW ENERCON GmbH Dreekamp 5

More information

An energy of the future coming from the sea

An energy of the future coming from the sea An energy of the future coming from the sea MAP showing the location of the Calvados offshore wind farm Why do we install off the coast of Calvados? Calvados offshore 75 PIONEER location of offshore wind

More information

Application and Design of the ebooster from BorgWarner

Application and Design of the ebooster from BorgWarner Application and Design of the ebooster from BorgWarner Knowledge Library Knowledge Library Application and Design of the ebooster from BorgWarner With an electrically assisted compressor, the ebooster,

More information

Brochure Introducing HVDC

Brochure Introducing HVDC Brochure Introducing HVDC ABB and HVDC The world s first commercial high-voltage direct current (HVDC) link, situated between the Swedish mainland and the island Gotland, was delivered by ABB already in

More information

Passion for Offshore. Wind Power & Renewables Division Market Unit Offshore

Passion for Offshore. Wind Power & Renewables Division Market Unit Offshore Wind Power & Renewables Division Market Unit Offshore Passion for Offshore - Frank Zimmermann, Head of Sales - 5 th British Chamber Conference on Renewable Energy, Hamburg, siemens.com/answers Siemens

More information