1 Meeting #9 December 4, 2008 Magic Valley Electrical Plan Community Advisory Committee
2 MVEP CAC Dec08.ppt Purpose of the Project To create a clear and documented electrical energy supply plan to serve the load needs of the Magic Valley from now through buildout The public process is the starting point of all electrical supply plans and any resulting transmission rights-of-way and substation siting requirements 2
3 MVEP CAC Dec08.ppt Meeting Purpose Present and gather final comments on the draft Magic Valley Electrical Plan Invite discussion, clarification, changes Finalize plans for implementation and local coordination 3
4 MVEP CAC Dec08.ppt Meeting Agenda 11:00 a.m. Welcome and Introductions Review CAC Meeting #8 Mike Preliminary Draft Plan Kent 11:10 a.m. Draft Magic Valley Electrical Plan 12:00 noon Lunch 12:45 p.m. Implementation Kent / Chris 1:15 p.m. Plan Integration & Coordination Kent / Dan / Mike 1:50 p.m. Process Evaluation / Next Steps / adjourn by 2 p.m. 4
5 MVEP CAC Dec08.ppt Review of Meeting #8 Discussed and reached consensus for the preferred and acceptable alternatives for each of the Magic Valley planning areas Discussed plan implementation Preliminary discussion on integrating plan into jurisdictional comprehensive plans 5
6 Draft Magic Valley Electrical Plan
7 MVEP CAC Dec08.ppt General Discussion The report is organized into: Executive Summary Introduction Background Committee Process Implementation Plan Conclusions/Results Appendixes We ve attempted to use non-technical terminology wherever possible so it s readable to people who weren t part of the Committee. 7
8 MVEP CAC Dec08.ppt Executive Summary This section will be completed last Description of area Description of project Description of committee process How detailed do you want the Executive Summary? 1 or 2 pages? More complete with some maps? What audience should the Executive Summary be written for? 8
9 MVEP CAC Dec08.ppt Introduction Area Description Description of Advisory Committee Anything else? 9
10 MVEP CAC Dec08.ppt Background Population and Electrical Load Projects Details for how the projections were made are in appendix Existing Magic Valley Electrical Supply System Transmission vs generation supply Transmission system description Existing Dependability (reliability) 10
11 MVEP CAC Dec08.ppt Committee Process and Input Description of committee process Alternative Energy Generating Technologies What was discussed in meetings Energy Efficiency Description of Idaho Power programs Description of Energy Efficiency programs in the Magic Valley Goals Document Mapping Exercise 11
12 12 MVEP CAC Dec08.ppt
13 13 MVEP CAC Dec08.ppt
14 14 MVEP CAC Dec08.ppt
15 15 MVEP CAC Dec08.ppt
16 16 MVEP CAC Dec08.ppt
17 17 MVEP CAC Dec08.ppt
18 18 MVEP CAC Dec08.ppt
19 19 MVEP CAC Dec08.ppt
20 20 MVEP CAC Dec08.ppt
21 MVEP CAC Dec08.ppt Committee Process and Input Committee Consensus on Alteratives 21
22 22 MVEP CAC Dec08.ppt
23 Overall Area: 230 kv & Source Substations Area 2: West Valley - South of Snake River MVEP CAC Dec08.ppt Total Score Total Score Group 1 Group 2 Group 3 Group 4 Group Group 1 Group 2 Group 3 Group 4 Group 5 Area 1: West Valley - North of Snake River Area 3: East Valley Total Score Group 1 Group 2 Group 3 Group 4 Group 5 Total Score Group 1 Group 2 Group 3 Group 4 Group 5
24 24 MVEP CAC Dec08.ppt
25 25 MVEP CAC Dec08.ppt
26 26 MVEP CAC Dec08.ppt
27 27 MVEP CAC Dec08.ppt
28 MVEP CAC Dec08.ppt Note, the report doesn t include a discussion about using the swath identified in previous slide. That was an oversight. 28
29 29 MVEP CAC Dec08.ppt
30 30 MVEP CAC Dec08.ppt
31 31 MVEP CAC Dec08.ppt
32 32 MVEP CAC Dec08.ppt
33 MVEP CAC Dec08.ppt Implemtation Plan 33
34 MVEP CAC Dec08.ppt Project Development How Does Idaho Power Determine what should happen next? Growth Rates (Customer and Load) Reliability Capacities (Transmission lines and Transformers) Budget Community Advisory Committee (not included in draft report but will be in final) 34
35 MVEP CAC Dec08.ppt Implementation 5 Years Build Kimberly Substation New 230:138 kv transformer at King Upgrade Filer Substation to 138 kv New 138 kv transmission line from Poleline to Filer Bring more capacity to the Buhl area New 138 kv transmission line to Buhl area Upgrade South Park Substation to 138 kv Bring new 138 kv line to South Park Substation (Southwest Twin Falls) from Russet Substation (Downtown Twin Falls) 35
36 MVEP CAC Dec08.ppt Implementation 10 Years Upgrade Golden Valley 69 kv loop (Cassia County) as loads dictate Add 230:138 kv transformer at Midpoint Upgrade Shoshone substation to 138 kv (connect to the new Midpoint Burmah 138 kv line) Upgrade Flat Top substation (East Jerome area) to 138 kv Build new 138 kv transmission line from Midpoint to Flat Top Build Switching Station between Twin Falls and Jerome 36
37 MVEP CAC Dec08.ppt Implementation 15 Years Upgrade Artesian Substation (Southeast of Hansen) to 138 kv Bring new 138 kv transmission line to Artesian Substation Extent 138 kv transmission line from Flat Top Substation to Hydra Substation Build Northeast Twin Falls Substation Build new Source Substation (Cedar Hill) south of Hansen 37
38 MVEP CAC Dec08.ppt Implementation 25 Years Upgrade Hagerman Substation to 138 kv Bring 138 kv transmission line to Hagerman Substation Connect Buhl and Filer Substations with a new 138 kv transmission line Connect South Park (Southwest Twin Falls) and Eastgate (South Twin Falls) Substations with a new 138 kv line 38
39 MVEP CAC Dec08.ppt Appendixes Appendix A List of Community Advisory Committee Members Appendix B Introduction and Technical Background Appendix C Committee Process and Input Appendix D Group Mapping Results & Alternative Scoring Matrix 39 Maps included here are printed in landscape format (sideways) so they are larger and more readable Appendix E Technical Analysis Appendix F ROW Analysis Appendix G Load Density Based on Zoning Appendix H n-1 Reliability Criteria Example
40 Plan Integration & Coordination
41 MVEP CAC Dec08.ppt Integration with Local Plans The goals: Local understanding and support Integration into local comprehensive plans Consideration of plan in local land use decisions Partnership for revisions over time The process: Presentations to local commissions Committee participation in presentations / process Determine roles, responsibilities and schedules 41
42 MVEP CAC Dec08.ppt Next Steps, Process Evaluation & Wrap Up Open discussion 42
Treasure Valley Electrical Plan
Treasure Valley Electrical Plan Community Advisory Committee January 25, 2006 Agenda 10 a.m. Welcome 10:10 a.m. Follow up DSM discussion 10:30 a.m. TVEP CAC process update 10:40 a.m. Transmission Presentation
More informationTreasure Valley Electrical Plan
Treasure Valley Electrical Plan Prepared by System Planning Department Idaho Power Company Boise, ID Table of Contents Table of Contents... i Executive Summary... 1 Introduction... 3 Technical Input...
More informationBRIDGE Group Meeting Date: 09.18.12
BRIDGE Group Meeting Date: Agenda 1. Capital Project Funding & Approval Process 2. DRAFT HEAPR List 3. Ccure Card Access System 4. SMART Asset Management Program Update 1. Capital Project Funding & Approval
More informationIdaho State Department of Education Certificated Staff Salaries Statewide Summary 2014-2015
Certificated Staff Salaries Statewide Summary 04-05 Activity Actual Employee Total FTE Employee Total Total Salaries Total Base Salary FTE Average Base Salary FTE Average Base Salary + 07 88 8,695,33 8,65,635
More informationTreasure Valley Electric Plan - Community Advisory Committee
Treasure Valley Electric Plan - Community Advisory Committee What is a transmission line and why are they necessary? A transmission line is used to conduct electricity between two points. Without high
More informationRecord Keeping FOR A SMALL BUSINESS
Record Keeping FOR A SMALL BUSINESS Welcome 1. Agenda 2. Ground Rules 3. Introductions RECORD KEEPING 2 Objectives Explain the concept of record keeping and its importance to small businesses Identify
More informationManagement Strategy Development Work Session
Management Strategy Development Work Session Healthy Watersheds Outcome Land Use Metrics and Methods Outcome Land Use Options Evaluation Outcome 10/30/2014 Agenda for today 10 10:30am Welcome and Review
More informationCOMMUNICATIONS MANAGEMENT PLAN <PROJECT NAME>
COMMUNICATIONS MANAGEMENT PLAN TEMPLATE This Project Communications Management Template is free for you to copy and use on your project and within your organization. We hope that you find this template
More informationDAKOTA COUNTY PHYSICAL DEVELOPMENT COMMITTEE OF THE WHOLE
DAKOTA COUNTY PHYSICAL DEVELOPMENT COMMITTEE OF THE WHOLE Meeting Minutes May 12, 2015 Dakota County Western Service Center Conference Room 106, 14955 Galaxie Avenue, Apple Valley, MN Call To Order And
More informationCall for Presentations by Singapore Actuarial Society General Insurance Conference 31 May/1 June 2012
Call for Presentations by Singapore Actuarial Society General Insurance Conference 31 May/1 June 2012 This is the fourth conference organised by the Singapore Actuarial Society. Dates for the conference
More informationIdaho Trauma Registry - ITR EMS Agency Codes
EMS Agency License Number EMS Agency Name 5601 Aberdeen / Springfield Fire District 8405 Ada Boi, Inc. 8407 Ada County Paramedics 8728 Air Idaho Rescue 8426 Air Saint Lukes Boise 8515 Air Saint Lukes Magic
More informationLMI Aerospace PROJECT MANAGEMENT PLAN ACCESS REQUEST PROCESS IMPROVEMENT FEBRUARY 7, 2012
PROJECT MANAGEMENT PLAN ACCESS REQUEST PROCESS IMPROVEMENT FEBRUARY 7, 2012 TABLE OF CONTENTS INTRODUCTION... 2 PROJECT MANAGEMENT APPROACH... 2 PROJECT SCOPE... 2 MILESTONE LIST... 2 SCHEDULE BASELINE
More informationWest London Dyke Flood Control Structure Master Plan Appendix A
West London Dyke Flood Control Structure Master Plan Appendix A Introduction The West London Dyke runs along the west bank of the North Branch of the Thames River from Oxford Street to the forks of the
More informationRecord Keeping FOR A SMALL BUSINESS
Record Keeping FOR A SMALL BUSINESS Welcome 1. Agenda 2. Ground Rules 3. Introductions Objectives Explain the concept of record keeping and its importance to small businesses Identify record keeping practices,
More informationTABLE OF CONTENTS. Executive Summary 1-3. Introduction 4-6. Illustrative Site Plan 7. East-West Streets 8. Cooper Street 9-10. Market Street 11-14
TABLE OF CONTENTS Executive Summary 1-3 Introduction 4-6 Illustrative Site Plan 7 East-West Streets 8 Cooper Street 9-10 Market Street 11-14 Federal Street 15-16 MLK Boulevard 17-20 North-South Streets
More informationCall for Papers by Singapore Actuarial Society General Insurance Conference 6-7 May 2009 A Firm Foundation for Taking Risk
Call for Papers by Singapore Actuarial Society General Insurance Conference 6-7 May 2009 A Firm Foundation for Taking Risk This is the first such conference organized by the Singapore Actuarial Society.
More informationTehachapi Renewable Transmission Project (TRTP)
SM Tehachapi Renewable Transmission Project (TRTP) February 2009 Why We Are Here Today Provide background on SCE s commitment to renewable energy Discuss the operational and economic importance of the
More informationPublic Hearing. City Council Study Session. February 11, 2013
Public Hearing City Council Study Session February 11, 2013 1 Staff Report Summarize the Overlay Conduct Public Hearing Council Discussion Schedule and Next Steps 2 2012-13 2007-2008 2013-2014 2013-2014
More informationCALIFORNIA AMERICAN WATER LOS ANGELES DISTRICT 2009 GENERAL RATE CASE CHAPTER: 1 INTRODUCTION AND SUMMARY OF APPLICATION
DISCUSSION OF INFORMATION PRESENTED IN THIS CHAPTER This chapter contains information regarding the operation of the Los Angeles District of California American Water as well as tables that summarize the
More informationMACOMB TOWNSHIP PLANNING COMMISSION MEETING MINUTES AND PUBLIC HEARING TUESDAY, May 5, 2009 PAGE 1 OF 8
PAGE 1 OF 8 LOCATION: PRESENT: ABSENT: ALSO PRESENT: MACOMB TOWNSHIP MEETING CHAMBERS 54111 BROUGHTON ROAD MACOMB, MI 48042 EDWARD GALLAGHER, CHAIRMAN DEAN AUSILIO, VICE CHAIRMAN MICHAEL D. KOEHS, SECRETARY
More informationCITY OF WINTER GARDEN
CITY OF WINTER GARDEN CITY COMMISSION REGULAR MEETING MINUTES A REGULAR MEETING of the Winter Garden City Commission was called to order by Mayor Rees at 6:30 p.m. at City Hall, 300 West Plant Street,
More informationPARKING AND HOUSING ISSUES NEAR COLLEGES AND
PARKING AND HOUSING ISSUES NEAR COLLEGES AND UNIVERSITIES Citizen Advisory Group Meeting I November 15, 2012 Overview Background Citizen Advisory Group Roles Identifying the Issues Case Studies Break Out
More informationThe Gateway Program and Hudson Tunnel Project
The Gateway Program and Hudson Tunnel Project Presented to: NJ State Senate Oversight Committee Stephen Gardner Executive Vice President NEC Business Development August 10, 2015 1 The Need for Gateway
More information1 Call meeting to order Jon Aubart, Chair. 2 Establish Quorum and Adopt Agenda Jon Aubart, Chair
Meeting Agenda Tuesday, November 6, 2012 at 4:00 p.m. 1 Call meeting to order 4 Approve Minutes from September 20, 2012 Meeting 5 Review Departmental Budget 6 Discuss and Take Action on Departmental Transition
More informationGreat River Energy Corridor Management Project
Great River Energy Corridor Management Project A subproject of GRE s Enterprise GIS Project Mike Siedschlag GIS Tech II United Services Group/ Great River Energy Topics GRE Transmission Facts Corridor
More informationSpecial Meeting Agenda July 26, 2011
Board of Supervisors Kim Dolbow Vann, District I Thomas A. Indrieri, District II Mark D. Marshall, District III Chairman Gary J. Evans, District IV, Vice chairman Denise J. Carter, District V COUNTY OF
More informationRural Residential Buildable Lands Inventory
The Dalles Periodic Review, May 2013 Rural Residential Lands Inventory Contents Introduction and Summary... 1 Concerns related to the 2007 Analysis... 2 Rural Residential Capacity Summary... 2 Methodology...
More informationAGENDA. CITY COUNCIL GOALS 2020 (Adopted by Resolution No. 9402 on December 20, 2005)
AGENDA REGULAR MEETING OF THE CITY COUNCIL City of Garland Council Chambers, City Hall 200 North Fifth Street, Garland, Texas 7:00 p.m. The City Council extends to each visitor a sincere welcome. We value
More informationMHSA Stakeholder Leadership Committee FY16 MHSA Annual Update Planning Meeting
MHSA Stakeholder Leadership Committee JUNE 22, 2015, 3:00PM -5:00PM S A N TA C L A R A C O U N T Y T R A I N I N G A N D C O N F E R E N C E C E N T E R AT C H A R C OT 2310 NORTH 1ST STREET, SU ITE 102,
More informationMillennium Pipeline Company, LLC Response to New York State Energy Highway RFI
Millennium Pipeline Company, LLC Response to New York State Energy Highway RFI www.millenniumpipeline.com One Blue Hill Plaza, 7th Floor Post Office Box 1565 Pearl River, N Y 10965 845.620.1300 Voice 845.620.1320
More informationSection 6 Traffic Analysis
Section 6 Traffic Analysis Traffic Operations of the Preferred Network Alternative After the Preferred Network was identified and confirmed by local policy makers and area residents, detailed traffic analysis
More informationNotice of Board of Managers Monthly Meeting
Notice of Board of Managers Monthly Meeting Monday, March 17, 2014 5:30 p.m. Meeting Location: Nine Mile Creek Watershed District Office 7710 Computer Avenue Suite 135 Edina, MN Agenda Enclosed Agenda
More informationSudbury to Hudson Transmission Reliability Project
Hudson Light & Power Sudbury to Hudson Transmission Reliability Project Sudbury, Massachusetts Board of Selectmen Presentation February 2, 2016 Revised on Page 12 to show Project Open House dates in Sudbury
More information5.14 Floodplains and Drainage/Hydrology
I-70 East Final EIS 5.14 Floodplains and Drainage/Hydrology 5.14 Floodplains and Drainage/Hydrology This section discusses floodplain and drainage/hydrology resources and explains why they are important
More informationSt. Vrain Watershed Master Plan Thursday, January 23 10:00 a.m. 12:15 p.m.
St. Vrain Watershed Master Plan Thursday, January 23 10:00 a.m. 12:15 p.m. City Council Study Session Room City of Longmont Civic Center, 350 Kimbark Street, Longmont Minutes 1. Introductions a. Jeff Crane
More informationPUBLIC UTILITY COMMISSION OF TEXAS (PUC) DOCKET NO. 37529
Application of Oncor lectric Delivery Company LLC to Obtain or Amend a Certificate of Convenience and Necessity for a Proposed CRZ 345 kv Transmission Line in Nolan, Taylor and Runnels Counties, Texas
More informationCity Council. Regular Session. 8:00 10:00 p.m.
Agenda City Council Regular Session MONDAY July 16, 2001 8:00 10:00 p.m. Council Chambers Page 1. Call to Order 2. Roll Call, Flag Salute (a) Proclaiming August 5, 2001 as National Kids Day in Bellevue
More informationPreliminary Plan for Expansion of the Regional Network of Floridan and Surficial Aquifer Monitor Wells for Northern Tampa Bay
DRAFT - August 24, 2000 Preliminary Plan for Expansion of the Regional Network of Floridan and Surficial Aquifer Monitor Wells for Northern Tampa Bay Introduction In 1999, the Southwest Florida Water Management
More informationVillage of Dexter. Request for Architectural Services for Facilities Assessment
Village of Dexter Request for Architectural Services for Facilities Assessment The Village of Dexter is requesting proposals for architectural services for a facility assessment involving Village Offices
More informationMINUTES OF MEETING OF BOARD OF TRUSTEES OF THE MUNICIPAL ELECTRIC UTILITY, CITY OF CEDAR FALLS, IOWA. February 12, 2014
MINUTES OF MEETING OF BOARD OF TRUSTEES OF THE MUNICIPAL ELECTRIC UTILITY, CITY OF CEDAR FALLS, IOWA February 12, 2014 The Board of Trustees of the Municipal Electric Utility of the City of Cedar Falls,
More informationAppendix C- Public Outreach
Appendix C- Public Outreach PUBLIC MEETING PUBLICITY A range of public outreach activities were undertaken in the summer and fall of 2008 to maximize public involvement in the Scoping Process. 1) Project
More informationEAST BETHEL PLANNING COMMISSION MEETING June 24, 2014
EAST BETHEL PLANNING COMMISSION MEETING June 24, 2014 The East Bethel Planning Commission met for a Regular Planning Commission Meeting on June 24, 2014 at 7:00 P.M for their regular meeting at City Hall.
More informationBoard Members Present: Chair Merv Bennett, Vice Chair Andy Pico, Board Members Don Knight, Jan Martin, Helen Collins, and Larry Bagley
Minutes Colorado Springs Utilities Board Special Meeting Governance Structure & Governance Process Review March 25, 2015, 1:00 p.m. - 3:00 p.m. Blue River Room 121 S. Tejon Street, 5 th Floor Board Members
More informationALAMEDA COUNTY COMMUNITY DEVELOPMENT AGENCY PLANNING DEPARTMENT
ALAMEDA COUNTY COMMUNITY DEVELOPMENT AGENCY PLANNING DEPARTMENT STAFF REPORT TO: CASTRO VALLEY MUNICIPAL ADVISORY COUNCIL HEARING DATE: October 26, 2015 GENERAL INFORMATION APPLICATION TYPE & NUMBER: Sign
More information2014 Summer Conference Pittsburgh, PA July 25-27
Friday Schedule: 9:00AM-5:00PM 3:00-6:00PM 6:00-7:00PM 7:15-9:00PM 2014 Summer Conference Pittsburgh, PA July 25-27 Democratic Campaign Staff Training YDA is hosting a campaign staff training with the
More informationComprehensive Plan Committee Kick-off Meeting A G E N D A
Comprehensive Plan Committee Kick-off Meeting A G E N D A Monday, June 1, 2015, 5:30-7:00 PM 530 Evans Street Sheppard Memorial Library, Room A Greenville, NC 27858 1. Welcome and introductions Merrill
More informationCourse Objective: To teach insurance agents how to communicate the terms of insurance contracts to their customers for comprehension.
COVER PAGE Name of Provider: Building Competent Insurance Agents Association Name of Course: Communicating Insurance to Consumers for Comprehension Targeted audience: General lines agents that are new
More informationSacramento Region Health Care Partnership. Notes and Stakeholder Input
Sacramento Region Health Care Partnership Notes and Stakeholder Input January 30, 2012 Compiled by The Abaris Group 1 Introduction At this convening on January 30, 2012, s team of consultants presented
More informationAGENDA ASTORIA CITY COUNCIL WORK SESSION / REGULAR SESSION
AGENDA ASTORIA CITY COUNCIL WORK SESSION / REGULAR SESSION October 19, 2015 6:00 p.m. 2 nd Floor Council Chambers 1095 Duane Street Astoria OR 97103 6:00 P.M. WORK SESSION 1. CALL TO ORDER 2. ROLL CALL
More informationSpecial Meeting Agenda. Thursday, May 7, 2015 6:30 p.m. Cedar Springs City Hall 66 S. Main St. Cedar Springs, Michigan
1. Call to Order and Pledge of Allegiance. Special Meeting Agenda Thursday, May 7, 2015 6:30 p.m. Cedar Springs City Hall 66 S. Main St. Cedar Springs, Michigan 2. ROLL CALL: Mr. Daniel Clark Mr. Perry
More informationTransmission Related Station Power Use at Substations
Transmission Related Station Power Use at Substations BUSINESS PRACTICE This Business Practice identifies the cost responsibility for energy consumption at substations by American Transmission Company
More informationIDAHO BROADBAND ACCESS STUDY COMMITTEE. October 5, 2015
IDAHO BROADBAND ACCESS STUDY COMMITTEE October 5, 2015 Overview 1 Cable ONE A Provider of Advanced Broadband Services 2 Cable is Not Just About TV Anymore 3 Cable ONE Fiber Reach 4 Government & Education
More informationBoard of Commissioners Meeting October 2, 2013. Chairman Davidson opened the meeting at 9:00 a.m. with all three Commissioners present.
Board of Commissioners Meeting Present: Commissioner Mark D. Davidson Commissioner Steve McClure Commissioner William D. Rosholt Chairman Davidson opened the meeting at 9:00 a.m. with all three Commissioners
More informationFinance Sub-Committee 30 November 2015
Agenda Item 8 88 Finance Sub-Committee 30 November 2015 Land at Ditchford Lakes Purpose of report The purpose of this report is to obtain Councillors agreement to enter into a 35-year lease of Council-owned
More informationEPCOR Distribution & Transmission Inc.
Decision 3478-D01-2015 Victoria E511S Substation Expansion February 17, 2015 Alberta Utilities Commission Decision 3478-D01-2015 Victoria E511S Substation Expansion Proceeding 3478 Application 1610934-1
More informationElectric system improvements near you South and West of Edmonton Area Transmission Development
Electric system improvements near you South and West of Edmonton Area Transmission Development SAUNDERS LAKE SUBSTATION AND TRANSMISSION LINES January 2014 Volume 2 PLEASE NOTE: We want to inform you that
More informationCHUGACH ELECTRIC ASSOCIATION, INC. Anchorage, Alaska. February 10, 2014
CHUGACH ELECTRIC ASSOCIATION, INC. Anchorage, Alaska February 10, 2014 QUESTIONS AND ANSWERS TO: Prospective Proposers FROM: Chugach Electric Association, Inc. 5601 Electron Drive Anchorage, Alaska SUBJECT:
More informationInternational Decade of Soils Workshop (IDOS)
International Decade of Soils Workshop (IDOS) March 14-16 2016 UCAR Foothills Campus in Boulder, CO Sponsored by the Carbon Cycle Interagency Working Group Workshop Organizers Melanie Mayes (ORNL), Kate
More informationMENDOCINO COUNTY BOARD OF SUPERVISORS SUMMARY/ACTION WORKSHOP MINUTES NOVEMBER 5, 2003
MENDOCINO COUNTY BOARD OF SUPERVISORS SUMMARY/ACTION WORKSHOP MINUTES NOVEMBER 5, 2003 BEFORE THE BOARD OF SUPERVISORS COUNTY OF MENDOCINO STATE OF CALIFORNIA The Mendocino County Board of Supervisors
More informationDRAFT POLICIES COUNTY OF HALIBURTON OFFICIAL PLAN UPDATE
SETTLEMENT AREAS Introduction Urban Serviced DRAFT POLICIES These urban areas have either full or partial primary urban services, mainly water, sewage and roads. Functionally, they tend to service larger
More informationBenefits of Inter-Departmental Project Management
Successful Collaboration Between Records Management WELCOME Information Technology Legal Subhead goes here. Remove Welcome and add Administration text box for presentation slides. We re not Adversaries,
More informationJ.D. Power Reports: Strong Network Quality Performance Is Key to Higher Customer Retention for Wireless Carriers
Kw J.D. Power Reports: Strong Network Quality Performance Is Key to Higher Customer Retention for Wireless Carriers Ranks Highest in Wireless Network Quality Performance in All Six Regions WESTLAKE VILLAGE,
More informationDecision-Making Structure and Process
MEMORANDUM Decision-Making Structure and Process This memo, which was adopted by the Oversight Team during their September 27, 2006 meeting, describes the decision-making structure and process for delivering
More informationBEFORE THE DEPARTMENT OF WATER RESOURCES OF THE STATE OF IDAHO
Travis L. Thompson, ISB #6168 Paul L. Arrington, ISB #7198 BARKER ROSHOLT & SIMPSON LLP 195 River Vista Place, Suite 204 Twin Falls, Idaho 83301-3029 Telephone: (208) 733-0700 Facsimile: (208) 735-2444
More informationCOMMUNICATIONS MANAGEMENT PLAN <PROJECT NAME>
COMMUNICATIONS MANAGEMENT PLAN TEMPLATE This Project Communications Management Template is free for you to copy and use on your project and within your organization. We hope that you find this template
More informationReady-for-Development Data Center Sites in Northeast Tennessee Valley
Ready-for-Development Data Center Sites in Northeast Tennessee Valley Three sites in the Northeast Tennessee Valley joined an elite group of locations identified by a recent Tennessee Valley Authority
More informationYour Views on NHS Continuing Healthcare. A consultation on proposed policy review for Mid Essex Clinical Commissioning Group
Your Views on NHS Continuing Healthcare A consultation on proposed policy review for Mid Essex Clinical Commissioning Group Monday 11th May - Sunday 5th July 2015 Contents 1. Introduction... 3 2. Who is
More informationOpen for Business Streamlined Permitting Orange County PERMITTING STANDARDS
CUSTOMER SERVICE Instill positive proactive attitude in the staff project review team, throughout the entire process, to help the customer make his or her project a reality. Provide Opportunity for Customer
More informationElectromagnetic Radiation
Environmental Protection Technical Advice note 2 Electromagnetic Radiation EP(S) Guidance notes for developers and consultants July 2003 Produced by: Environmental Protection (Specialist) Team ADVICE GUIDE
More informationEldorado-Ivanpah Transmission Project WELCOME To Southern California Edison Company s Eldorado-Ivanpah Transmission Project OPEN HOUSE
WELCOME To Southern California Edison Company s Eldorado-Ivanpah Transmission Project OPEN HOUSE 1 1 Welcome to The Eldorado-Ivanpah Transmission Project Open House How is the open house organized? This
More informationNotice of Meeting of the Governing Body of the City of Georgetown, Texas MAY 28, 2013
Notice of Meeting of the Governing Body of the City of Georgetown, Texas MAY 28, 2013 The Georgetown City Council will meet on MAY 28, 2013 at 3:00 P.M. at the Council Chambers at 101 E. 7th Street, Georgetown,
More informationWelcome to F&M Bank! In this Switch Kit, you will find the following forms:
Welcome to F&M Bank! At F&M Bank, we believe in personal relationships. Our staff is available to assist you in making your transition to F&M Bank an easy one. We have also provided you with tools in this
More informationPROJECT PLAN FOR. Project Name Here
PROJECT PLAN FOR Project Name Here Version # DatE Reviewed and Approved for submittal to Executive Sponsor , Project Manager Project Plan Approved for submittal to Executive Sponsor: , Project
More informationMedical Services Council
Thurston County Emergency Medical Services System Study A Report prepared for the Thurston County Emergency A Report prepared for the Thurston County Emergency Medical Services Council The Report Contents
More informationConsumer Advisory Board Meeting Mechanics. Agenda. A comprehensive meeting agenda will include the following core components:
Consumer Advisory Board Meeting Mechanics Agenda A comprehensive meeting agenda will include the following core components: 1. Welcome (This is where the chair will call the meeting to order and welcome
More informationCity of Friendswood FY 2010 Capital Improvements Program - Water & Sewer Projects 5-Year CIP
City of Friendswood FY 2010 Capital Improvements Program - Water & Sewer Projects 5-Year CIP PROJECT ESTIMATED COST ESTIMATED COUNCIL IDENTIFIED FUNDING SOURCES STRATEGIC COMPLETION INITIATIVES FM 2351/Beamer
More informationCOUNCIL CREEK REGIONAL TRAIL MASTER PLAN Committee Roles and Responsibilities
COUNCIL CREEK REGIONAL TRAIL MASTER PLAN Committee Roles and Responsibilities Three advisory committees will assist in developing the Council Creek Regional Trail Master Plan (Master Plan). The Project
More informationWalt Disney World Operating Hours* April 2016
4/1/16 4/2/16 Magic Magic 9am - 9am- 11am- 9am - 9am- 11am-,, Spectacular 9:15pm Spectacular 9:15pm Rivers of Light: 10am - 6pm Rivers of Light: 10am - 6pm Extra Magic Hours Magic Extra Magic Hours Last
More informationWard: Purley DELEGATED BUSINESS MEETING Lead Officer: Head of Planning Control week of 23/03/2009
Ward: Purley DELEGATED BUSINESS MEETING Lead Officer: Head of Planning Control week of 23/03/2009 Application No. 09/00389/LP - 51-61 Whytecliffe Road South, Purley, CR8 1. SUMMARY 1.1 This report concerns
More informationFireworks Go on Sale in Palmdale This Saturday. 44 nonprofit organizations to begin selling fireworks on Saturday, June 28th
FOR IMMEDIATE RELEASE CITY OF PALMDALE NEWS RELEASE CONTACT: John Mlynar PHONE: 661/267-5115 DATE: June 25, 2014 Fireworks Go on Sale in Palmdale This Saturday WHAT: 44 nonprofit organizations to begin
More informationChaffee County Public Health Director Susan Ellis presented the June 2010 monthly report.
Commissioners Meeting July 6, 2010 The regular meeting of the Board of Commissioners was held on Tuesday, July 6, 2010 in the Commissioners Meeting Room at the Courthouse. Board members present were Chairman
More informationYou may wish to encourage all of your guests to RSVP for your event so you know how many people to expect.
Viewing Party Guide for LPB - October Louisiana Public Square Funding the Future: Early Childhood Opportunities Wednesday, October 21, 2015 Airing: 7pm-8pm What is a Viewing Party and why you may want
More informationPrimary Questions: Deliverables: Target Audience:
Mobile Apps: Implications for 9-1-1 Tue, October 7 1:15PM 3:00PM Caribbean III Facilitated by Sandy Beitel, Jerry Schlesinger, Mike Vislocky & Dan Mongrain There has been a lot of discussion lately concerning
More informationNez Perce County. Sources for information reported on this page are on page v. Definitions of chart terminology can be found in the glossary.
glossary. Page I. County Characteristics Square Mileage: 86.7 Percent of Total Land Ownership Population Per Square Mile Private 77.% Federal 6.% State.% City & County.9% 98 99 6 Total,,7 7, 8, Per Sq
More informationSponsored by the Maryland Wood Energy Coalition
Don t Delay - Register Today! Biomass Boot Camp Overhills Mansion, 916 S. Rolling Road, Catonsville, MD Monday, February 23, 2015 (9:30 a.m. 4:30 p.m.) Sponsored by the Maryland Wood Energy Coalition In
More informationAPPENDICES G) DETAILED BACKBONE INFRASTRUCTURE CONSTRUCTION COST ESTIMATE SUMMARY
ALAMEDA POINT MASTER INFRASTRUCTURE PLAN March 31, 2014 APPENDICES G) DETAILED BACKBONE INFRASTRUCTURE CONSTRUCTION COST ESTIMATE SUMMARY Carlson, Barbee & Gibson, Inc. Backbone Infrastructure Engineer
More informationCITY OF WATERLOO, IOWA BOARDS AND COMMISSIONS DESCRIPTIONS/DUTIES
CITY OF WATERLOO, IOWA BOARDS AND COMMISSIONS DESCRIPTIONS/DUTIES The following is a list of the City of Waterloo Boards and Commissions with their respective descriptions, duties, applicable City Code,
More informationSection 1: Executive Summary
Section 1: Executive Summary SECTION 1: EXECUTIVE SUMMARY 1.1 SECTION PURPOSE This report has been prepared for the Nevada Energy Assistance Corporation (NEAC), a 501(c)(3) non-profit agency; in support
More informationSTATE PUBLIC TRANSPORTATION PARTNERSHIPS CONFERENCE. Westin Hotel Seattle, WA August 3-5, 2010
STATE PUBLIC TRANSPORTATION PARTNERSHIPS CONFERENCE Westin Hotel Seattle, WA August 3-5, 2010 2010 STATE PUBLIC TRANSPORTATION PARTNERSHIPS CONFERENCE SEATTLE, WA AUGUST 3-5, 2010 Welcome to Seattle, Washington,
More informationM I N U T E S 2015 BUDGET AND TAX LEVY PUBLIC HEARING DECEMBER 2, 2014 6:00 P.M. COUNCIL CHAMBERS
M I N U T E S 2015 BUDGET AND TAX LEVY PUBLIC HEARING DECEMBER 2, 2014 6:00 P.M. COUNCIL CHAMBERS MEMBERS PRESENT: MEMBERS ABSENT: OTHERS PRESENT: Mayor Stiehm, Council Members Boughton, Enright, Carolan,
More informationMinnesota e-health Initiative Conference Call Update on the HITECH Act Thursday, September 17, 2009, 4:00 p.m. to 4:45 p.m.
Minnesota e-health Initiative Conference Call Update on the HITECH Act Thursday, September 17, 2009, 4:00 p.m. to 4:45 p.m. Focus Today: Update on Medicaid Incentives & State Medicaid Director Letter Update
More informationNeed last-minute help with directions? Just call us at 309-691-7263. We look forward to welcoming you to our offices.
7620 N. University, Suite 203 Peoria, IL 61614-1297 Directions: Heiple Law Offices is located in the Pioneer Park area on Peoria's far north side, just South of the intersection of University Street and
More informationTown of Snowmass Village. PO Box 5010. Or Delivered To: 1 P a g e
The Town of Snowmass Village invites qualified consultants to submit a proposal to develop a Request Community for Connectivity Proposals Plan for the Town. Proposals must be submitted by 4:00 pm Friday
More informationApproval of Agenda The May 14, 2013 agenda approved as presented.
Nelson Township Board Meeting Tuesday, May 14, 2013 7:00 P.M. Held at the Nelson/Village of Sand Lake Municipal Hall 2 Maple Street Sand Lake, MI 49343 Call to Order Pledge of Allegiance Board Roll Call
More informationIT LEADERSHIP COUNCIL STRATEGIC PLAN. 2012 State of Idaho
IT LEADERSHIP COUNCIL STRATEGIC PLAN 2012 State of Idaho CONTENTS IT LEADERSHIP COUNCIL MISSION 3 MEMBERSHIP 3 BACKGROUND 4 STRATEGIC GOALS AND ALIGNMENT OF ACTIONS 9 2 P a g e IT LEADERSHIP COUNCIL MISSION
More informationWEBINARS ON WEBINARS: EDUCATION + ENTERTAINMENT
WEBINARS ON WEBINARS: EDUCATION + ENTERTAINMENT INTERMEDIATE We will be starting at 2:00 pm ET. Use the Question Pane in GoToWebinar to Ask Questions! 1 Use the hashtag #InboundLearning on Twitter 2 Question
More informationChairman Kent Carlson and Commissioners Barbarajean Brandt, Brandon Gustafson, Scott Hemink, John McGary, Gen McJilton and Pete Onstad
PAGE 1 CALL TO ORDER: Chairman Carlson called the meeting to order at 7:00 p.m. PRESENT: ABSENT: Chairman Kent Carlson and Commissioners Barbarajean Brandt, Brandon Gustafson, Scott Hemink, John McGary,
More informationNotice of Study Commencement and Invitation to Participate
REGION OF WATERLOO Wastewater Treatment Master Plan Class Environmental Assessment Notice of Study Commencement and Invitation to Participate Background The Regional Municipality of Waterloo is responsible
More informationDowntown South Salt Lake Redevelopment City of South Salt Lake
Project Information LOCAL PLANNING RESOURCE PROGRAM 2015 Downtown South Salt Lake Redevelopment City of South Salt Lake Overview of Objectives: Building a downtown city center could be the most significant
More informationTECHNICAL REVIEWERS' COMMENTS With Applicant's Response LRC-LXXIX (79) - C "Annual Lignite Energy Council Education Program"
TECHNICAL REVIEWERS' COMMENTS With Applicant's Response LRC-LXXIX (79) - C "Annual Lignite Energy Council Education Program" 1. OBJECTIVES The objectives or goals of the proposed project with respect to
More information