1 PT02_PDP1 Acquisition and Fitting of a Dynamic Position (DP) vessel equipped with marine surveying equipment Nuno Lourenço (nuno.lourenco@ipma.pt)

2 Topics: The framework The Project: 1st Phase The New Vessel The Project: 2nd Phase

3 The Framework: EEA Financial Mechanism Programme Area 1: Integrated Marine and Inland Water Management Programme: Integrated Marine and Coastal Management Objective: Achieve Good environmental status in European marine and coastal areas Expected Outcomes: Integrated management of marine resources Improved monitoring of marine waters Increased capacity for assessing and predicting environmental status in marine waters Increased awareness of and education in integrated marine management Predefined Projects: 1) Acquisition and fitting of a DP Vessel equipped with marine surveying equipment. 2) Preparation of integrated geographic information for marine and coastal water management.

4 The Framework: DRIVERS (in the scope of IPMA mission): Exploration of the deep and ultra-deep (NOS ) Habitat mapping, VME s, genetic resources Exploration of non living Rainbow resources Menez Gwen Lucky Strike Sedlo D. J. Castro Knowledge based managment of MPA s Monitoring and Ensurance of GES in all marine water (MSFD) Evaluation of living resources

5 The Framework: Existing Capacity (or a tribute to NI Noruega) 1978 Norway financed acquisition of NI Noruega (trawling vessel, with focus on fisheries research); During a 37 years comission the NI Noruega, has served well the Portuguese Government and the Marine R&D community, collecting multidisciplinary data with enphasis on fisheries; Since its recovery in 2012 she has sailed between 130 and 155 days per year executing 100% of the Data Collection Framework (DCF) fisheries program; In 2014 she was used to a 3D high resolution MCS survey in the Tagus Delta. However...

6 The Framework: The need of a new vessel Before 2012 After 2012 Despite its maintenance and upgrade since 2012 NI Noruega is largely an: Outdated Vessel With Limited operational range With Limited depth range With Limited versatility; One on one (one cruise one project)

7 The Project Budget ~12.9 M (11M EEA, 1.9 M National Budget) Project Promoter IPMA; Donor Project Partner: IMR (Norway) Two main development phases: 1st phase: Acquisition of a vessel (international tender) 2nd phase: Refitting of a vessel and fitting of scientific equipment (whinches, cranes and hull mounted eq.). International tender The new vessel: concept of operations Multipurpose vessel with two main operating modes: halieutic research (trawling) and ROV operations (DP and USBL); plus geophysical and geotechnical op s Oceanic vessel fit to operate in both coastal and oceanic waters with high authonomy and high performance; Decks adaptable to contentorized infrastructures (e.g ROV LUSO and portable laboratories); Fit with multi-purpose lab spaces; High Capacity for multidisciplinary teams and technical personnel.

8 The Project: Phase 1 Timeline: Vessel Acquisition March 2015 IMR and Vera Navis Evaluation reports Final classification August 2015 Contract awarded Account court October 2015 Ship in Lisbon Out 2014 Tech Specs of ship and equipment Jannuary 2015 Tender closure November 2014 International Tender Fev 2013 On site inspections May 2015 Fisheries convertion Feasability study October 2015 Account court Visa

9 The Project: Winning Proposal Original Vessel: Salmaid Boom and Mooring Vessel Photo Hays Ships

10 The Refit (2013): Photo Hays Ships

11 The Refit (2013): Workspaces

12 The Refit (2013): Accomodation and Social spaces

13 Kommandor Calum Following the Refit : Survey Vessel Project 1 st Phase: International Tender: Winning proposal

14 The Project: Changing Paradigm Key Concepts : Multipurpose Versatile managment of working space Adaptable to mission Multidisciplinary From shallow (coastal) to ultra-deep (open ocean) From subsurface to water column High autonomy High hotel capacity Low acquisition cost and low running costs one to many (one cruise -multiproject, multidisciplinar, multitask) Kommandor Calum: Arrival in Lisbon

15 The new vessel: Main Characteristics: Year 1986 refit 2012 Length: 75; Beam: 15 m; Draft: 4.5 m Container capacity: 3x20 or 4 x10 Iso containers. Endurance: 40 days Two four stroke engines and one independent azimuthal 4x400 KW Generator + 1 emergency generator Speed: 13/10 knts (Peak/transit) Seismic compressors Loyds Class 100A1 10 T A Frame and a 30 T crane aft Moon Pool (1.2x1.2m) EMRI DP system (one azimuthal, one tunnel, one main) Accomodations: 45 pax (15 crew 30 Scientific and Technical ) Sci facilities: Dry Lab, Wet lab, processing room, conference room Gym, sauna, cinema (dark room), lounge Workshop

16 Project: Phase 2 Timeline: Vessel Transformation August 2016 Ship conversion April 2016 Out 2015 Ship s Arrival in Lisbon December 2015 End of Modifications Plan Closure of International tender February 2016 Modification plans Approval by Loyds And DGRM End of statutary certification July 2016 Account court and contracting December 2016 Project Completed

17 Project: Phase 2 Vessel Transformation Ongoing: Refit for Fisheries Research

18 Project: Phase 2 Vessel Transformation

19 THE N.I. MAR PORTUGAL A new platform for Ocean Research in Portugal to the service of the National and International Scientific Communities

20 PT02_PDP1 Acquisition and Fitting of a Dynamic Position (DP) vessel equipped with marine surveying equipment Nuno Lourenço (nuno.lourenco@ipma.pt)

GOLIATH DPIII OFFSHORE SUPPORT VESSEL. Vessel Specification - December 2011

GOLIATH DPIII OFFSHORE SUPPORT VESSEL. Vessel Specification - December 2011 Vessel Specification - December 2011 GOLIATH DPIII OFFSHORE SUPPORT VESSEL This technical specification sheet is subject to change without notice.whilst every effort has been made to ensure that accuracy

More information

Contents. 1. PROFILE p2. 2. SERVICES 2.1 Offshore Support Services p 4 Offshore support p 6 ROV operations p 8

Contents. 1. PROFILE p2. 2. SERVICES 2.1 Offshore Support Services p 4 Offshore support p 6 ROV operations p 8 OCTOBER 2013 22 Contents 1. PROFILE p2 2. SERVICES 2.1 Offshore Support Services p 4 Offshore support p 6 ROV operations p 8 2.2 Hydrographic & Geophysical services p 10 Bathymetric surveys p 12 High resolution

More information

MERMAID FLEET PROFILE SUBSEA SERVICES

MERMAID FLEET PROFILE SUBSEA SERVICES 010 Mermaid Maritime Public Company Limited MERMAID ENDURER (Built in 2010) The DSV Mermaid Endurer is a Norwegian purpose-built DP2 dive support and light construction vessel, specially designed for operations

More information

Case Study 10 R/V WESTERN FLYER Chronic Cracking in an Aluminum SWATH Research Vessel

Case Study 10 R/V WESTERN FLYER Chronic Cracking in an Aluminum SWATH Research Vessel Case Study 10 R/V WESTERN FLYER Chronic Cracking in an Aluminum SWATH Research Vessel Vessel Particulars LOA: 117-3 5/8 Breadth: 53-0 Depth: 25-0 Draft: 12-0 Gross Tonnage: 499 Displacement: 419 LT Complement:

More information

About us. Remontowa reliability, quality & experience At Your Service. Worldwide

About us. Remontowa reliability, quality & experience At Your Service. Worldwide About us COMPANY KEY DATA Company established in November 2003 Employment 70 persons. 12 service engineers, IT specialists y Quality management system complaisant with ISO 9001:2000 y OHSAS 18001:2007

More information

M/Y NAIA RV PEGASO. (ex. PEGASO) Isle of Man CLASSIFICATION: 14 knots (cruising) 3516C 2350 KW ( Total 4700 KW) GUESTS: 12 in 6 CONSTRUCTION:

M/Y NAIA RV PEGASO. (ex. PEGASO) Isle of Man CLASSIFICATION: 14 knots (cruising) 3516C 2350 KW ( Total 4700 KW) GUESTS: 12 in 6 CONSTRUCTION: M/Y NAIA (ex. PEGASO) TYPE: MY BUILT: 2011 BUILDER: Freire Shipyard SPEED: 16 knots (max) CLASSIFICATION: Lloyds ENGINES: 2 x Caterpillar 3516C 2350 KW ( Total 4700 KW) 14 knots (cruising) CONSTRUCTION:

More information

RESEARCH SHIP ELLEN KHUZWAYO

RESEARCH SHIP ELLEN KHUZWAYO RESEARCH SHIP ELLEN KHUZWAYO BACKGROUND: Ellen Khuzwayo, was built according to a Norwegian design by FAROCEAN Marine in Cape Town and commissioned in 2007, she is the newest addition to the Department

More information

Esa Jokioinen Rolls Royce Marine 10.9.2014 MUNIN Workshop at SMM. Trusted to deliver excellence

Esa Jokioinen Rolls Royce Marine 10.9.2014 MUNIN Workshop at SMM. Trusted to deliver excellence Esa Jokioinen Rolls Royce Marine 10.9.2014 MUNIN Workshop at SMM 2014 Rolls-Royce plc The information in this document is the property of Rolls-Royce plc and may not be copied or communicated to a third

More information

Proven expertise and total reliability to support globally recognised oil and gas clients

Proven expertise and total reliability to support globally recognised oil and gas clients Oil & Gas Services B ibby HydroMap works closely with clients from the oil and gas industry to provide a variety of services relevant to all construction and monitoring phases. Our flexiblity and range

More information

Kongsberg Maritime Torfinn Kildal, President

Kongsberg Maritime Torfinn Kildal, President Kongsberg Maritime Torfinn Kildal, President WORLD CLASS through people, technology and dedication Kongsberg Maritime Business Model & Strategic Direction Offshore & Merchant Marine Yachting & Fishery

More information

Marine biological diversity beyond areas of national jurisdiction. Legal and policy framework

Marine biological diversity beyond areas of national jurisdiction. Legal and policy framework Marine biological diversity beyond areas of national jurisdiction Legal and policy framework 1. The United Nations Convention on the Law of the Sea (UNCLOS) provides the legal framework within which all

More information

Invitation for Tender: Sea Bed Survey Services (Geophysical, Bathymetric and Geotechnical)

Invitation for Tender: Sea Bed Survey Services (Geophysical, Bathymetric and Geotechnical) Invitation for Tender: Sea Bed Survey Services (Geophysical, Bathymetric and Geotechnical) 1. Introduction Moni Pulo Limited (Petroleum Development) invites interested and reputable contractors with relevant

More information

Ocean Class AGOR Program Acquisition Status. Prepared by PEO Ships, PMS325Q For UNOLS Annual meeting 13 October 2009

Ocean Class AGOR Program Acquisition Status. Prepared by PEO Ships, PMS325Q For UNOLS Annual meeting 13 October 2009 Program Acquisition Status Prepared by PEO Ships, PMS325Q For UNOLS Annual meeting 13 October 2009 Agenda History/Status of Acquisition Efforts History of Specification Development Acquisition Schedule

More information

Roadmap for Remote Controlled Ships

Roadmap for Remote Controlled Ships Roadmap for Remote Controlled Ships Esa Jokioinen, Head of Blue Ocean Team, E&T, Marine MUNIN Workshop Professional Insight on Unmanned Ships Norshipping, 3.6.2015 2015 Rolls-Royce plc The information

More information

Ocean Engineering, Surveying and Mapping Services

Ocean Engineering, Surveying and Mapping Services Ocean Engineering, Surveying and Mapping Services FUGRO PELAGOS, INC. Fugro collects and interprets data related to the earth s surface and the soils and rocks beneath. It provides advice based on the

More information

Marine industry careers

Marine industry careers Marine industry careers Québec s marine transport industry: an economic driving force The St. Lawrence River permits large volumes of raw materials and manufactured products (imports and exports) to be

More information

Cruise Report. OSU R/V Oceanus OC1405B. Cascadia Initiative Leg 2 May 28 to June 1 Newport, OR Newport OR. Matt Fowler Chief Scientist

Cruise Report. OSU R/V Oceanus OC1405B. Cascadia Initiative Leg 2 May 28 to June 1 Newport, OR Newport OR. Matt Fowler Chief Scientist Cruise Report OSU R/V Oceanus OC1405B Cascadia Initiative Leg 2 May 28 to June 1 Newport, OR Newport OR Matt Fowler Chief Scientist Captain and Crew: R/V Oceanus: Captain: Jeff Crews Chief Engineer: Jonathan

More information

AUSTAL 69.10M / 226 8

AUSTAL 69.10M / 226 8 AUSTAL 69.10M / 226 8 WELCOME ON-BOARD Built by the Australian shipyard Austal in 2003 as a small luxury cruise ship for Polynesia service, Saluzi was transformed into a megayacht. Boasting a brand new

More information

Press Release. PIRIOU launches the ALMAK, a Maritime Training Vessel of 44 meters

Press Release. PIRIOU launches the ALMAK, a Maritime Training Vessel of 44 meters Press Release PIRIOU launches the ALMAK, a Maritime Training Vessel of 44 meters Concarneau, 27 September, 2013 The Almak, Maritime Training Vessel (MTV) of 44 meters, was officially delivered today by

More information

E-navigation, process, results, status and delivery

E-navigation, process, results, status and delivery E-navigation, process, results, status and delivery Chile, October 2013 John Erik Hagen, Regional Director NCA Coordinator of IMO Correspondence Group on e-navigation Shipping moves into the digital world

More information

Instrumentation for Monitoring around Marine Renewable Energy Devices

Instrumentation for Monitoring around Marine Renewable Energy Devices Instrumentation for Monitoring around Marine Renewable Energy Devices 1 Introduction As marine renewable energy has developed, a set of consistent challenges has emerged following attempts to understand

More information

VICTORIA D. 103' (31.60m) CNB

VICTORIA D. 103' (31.60m) CNB VICTORIA D 103' (31.60m) CNB LOA: Beam: Min Draft: Max Draft: Speed: 103' 9" (31.60m) 24' 7" (7.49m) Min 12' 6" (3.80m) Cruising 10 knots Max 12 knots Year: Builder: Type: Price: Location: Mfg 1994 Model

More information

Horizon Survey and Geotechnical Companies

Horizon Survey and Geotechnical Companies Oil & Gas Directory Middle East - 2013 147 Horizon Survey and Geotechnical Companies Corporate P r ofile OUR PEDIGREE Horizon provides comprehensive survey and geotechnical services to the offshore industry

More information

Onboard-NAPA News. Jan Schauman, Onboard-Napa Ltd

Onboard-NAPA News. Jan Schauman, Onboard-Napa Ltd 1 (6), Onboard-Napa Ltd 1. Introduction This paper will briefly look into the new development that has been done within Onboard-NAPA as well as our SPS (Ship Performance Solutions) product lines since

More information

OFFSHORE WIND Peter Robert

OFFSHORE WIND Peter Robert OFFSHORE WIND Peter Robert Business Development Manager Offshore Wind Damen Shipyards Group Phone: +31 (0)183 655177 Mobile: +31 (0)6 22856004 E-mail: peter.robert@damen.com ABOUT DAMEN FOUNDER: KOMMER

More information

Permanent Reservoir Monitoring (PRM) System Installation: The Installers Perspective

Permanent Reservoir Monitoring (PRM) System Installation: The Installers Perspective Permanent Reservoir Monitoring (PRM) System Installation: The Installers Perspective Introduction Global Marine Systems Limited (Global Marine) has a vast wealth of knowledge in designing planning and

More information

Real Estate Investment: Main Tax Issues

Real Estate Investment: Main Tax Issues Real Estate Investment: Main Tax Issues 1 All the lawyers know what s happening on the case and work really well as a team. It sets them apart from others in the market. Client reference from Chambers

More information

SCICEX boat-to-archive route map and data management template Biological and Chemical Samples

SCICEX boat-to-archive route map and data management template Biological and Chemical Samples SCICEX boat-to-archive route map and data management template Biological and Chemical Samples R. Sambrotto & B. Smethie SCICEX SAC Feb. 14-15, 2013 SCICEX data management can be thought of in four parts:

More information

Report of Investigation into the fatal accident happened on board m.v. Najran at Kwai Chung Container Terminal on 15 May 2008

Report of Investigation into the fatal accident happened on board m.v. Najran at Kwai Chung Container Terminal on 15 May 2008 Report of Investigation into the fatal accident happened on board m.v. Najran at Kwai Chung Container Terminal on 15 May 2008 Purpose of Investigation This incident is investigated, and published in accordance

More information

The BEAMS Program College of Charleston & University of Washington

The BEAMS Program College of Charleston & University of Washington The BEAMS Program College of Charleston & University of Washington Development of the Marine Survey Workforce Leslie R. Sautter, Ph.D. Scott Harris, Ph.D. Dept. of Geology and Environmental Geosciences

More information

CMEMS user requirements and user uptake strategy

CMEMS user requirements and user uptake strategy CMEMS Service Evolution & User Uptake Workshop CMEMS user requirements and user uptake strategy Dominique Obaton Mercator Océan CMEMS Service Evolution & User Uptake Workshop The Copernicus Marine service

More information

SANTA TERESA RESEARCH CENTRE

SANTA TERESA RESEARCH CENTRE SANTA TERESA RESEARCH CENTRE THE CENTRE Address ENEA S. Teresa Marine Environment Centre 19036 Pozzuolo di Lerici (La Spezia) C.P. 224 19100 La Spezia Tel. +39-0187-9781, fax +39-0187-978213 Director Eng.

More information

JOIDES Resolution Playing Cards

JOIDES Resolution Playing Cards JOIDES Resolution Playing Cards Age: all These JOIDES Resolution playing cards depict images from the JOIDES Resolution drill ship, and can be used in a variety of different ways. There are four groups

More information

Implementing a Ship Energy Efficiency Management Plan (SEEMP) Guidance for shipowners and operators

Implementing a Ship Energy Efficiency Management Plan (SEEMP) Guidance for shipowners and operators Implementing a Ship Energy Efficiency Management Plan (SEEMP) Guidance for shipowners and operators Lloyd s Register, its affiliates and subsidiaries and their respective officers, employees or agents

More information

USNS Maury (T-AGS 66) Moon Pool Launch & Recovery System (MLARS)

USNS Maury (T-AGS 66) Moon Pool Launch & Recovery System (MLARS) USNS Maury (T-AGS 66) Moon Pool Launch & Recovery System (MLARS) Mr. Willis Proper Assistant Program Manager PEO Ships (PMS325) 17 May 2016 Mr. Scott CR Henry Concept Design Manager CSRA, LLC Operating

More information

Part 0 - Classification and Surveys Classification and Surveys I-0 2016-01

Part 0 - Classification and Surveys Classification and Surveys I-0 2016-01 Code Edition I - Ship Technology Part 0 - Classification and Surveys Classification and Surveys I-0 2016-01 Part 1 - Seagoing Ships Chapter 1 - Hull Structures I-1-1 2016-01 Chapter 1 - Hull Structures

More information

Request for Quote: Remotely Operated Vehicle May 16, 2014

Request for Quote: Remotely Operated Vehicle May 16, 2014 RFQ: Remotely Operated Vehicle Request for Quote: Remotely Operated Vehicle May 16, 2014 1.0 INTRODUCTION Industrial Economics, Incorporated (IEc) is seeking a qualified subcontractor(s) to provide a Remotely

More information

MPA Baseline Program. Annual Progress Report. North Coast Region

MPA Baseline Program. Annual Progress Report. North Coast Region MPA Baseline Program Annual Progress Report Principal Investigators - please use this form to submit your MPA Baseline Program project annual report, including an update on activities completed over the

More information

ROV Data Collection Results

ROV Data Collection Results ROV Data Collection Results Data is processed and displayed din seconds through the ROV communications channels The operator can view the results while the ROV isinposition in anddetermine determine ifadditionaldata

More information

Presentation to: Federal Renewable Ocean Energy Working Group Oregon Military Department (OMD) Marine Renewable Energy

Presentation to: Federal Renewable Ocean Energy Working Group Oregon Military Department (OMD) Marine Renewable Energy Presentation to: Federal Renewable Ocean Energy Working Group Oregon Military Department (OMD) Marine Renewable Energy Energy Independence Energy Security Disaster Resilience Camp Rilea Energy The Model

More information

Second Mares Conference Abstract Submission Guidelines

Second Mares Conference Abstract Submission Guidelines Second Mares Conference 1. Introduction 2 2. Abstract Submission & Conference Proceedings 2 3. Conference Programme 2 4. How to submit an abstract? 3 5. Oral Presentation Guidelines 4 6. Exhibition Guidelines

More information

Perspektiv fra en faglig ansatt

Perspektiv fra en faglig ansatt Perspektiv fra en faglig ansatt Geir Johnsen, NTNU Strategiske partnerskap og allianser hva får vi ut av dem case NORUS Forskning Hands On Undervisning Fremtidige partnerskap og allianser SiU funded NORUS

More information

Possible management measures and potential fisheries displacement analysis Upper Loch Fyne and Loch Goil

Possible management measures and potential fisheries displacement analysis Upper Loch Fyne and Loch Goil Purpose v1.0 Page 1 Possible Marine Protected Areas (pmpas) Analysis of possible fisheries management measures The purpose of this paper is to set out possible management measures of the pmpa and provide

More information

How To Develop A Waterborne

How To Develop A Waterborne Waterborne TP and Vessels for the Future Initiative in H2020 Luciano Manzon WATERBORNE Secretary, SEARDI Chairman the RDI Group of SEA Europe 27 November Santiago de Compostela ETP WATERBORNE All the Stakeholders

More information

Performance On Innovative Mechanical Connections In Precast Building Structures Under Seismic Conditions. 1º Year Meeting

Performance On Innovative Mechanical Connections In Precast Building Structures Under Seismic Conditions. 1º Year Meeting Performance On Innovative Mechanical Connections In Precast Building Structures Under Seismic Conditions 1º Year Meeting LOEMCO LABORATORY 1º year meeting Summary: Work package number 1 Design exercise

More information

Total Subsea Services

Total Subsea Services Total Subsea Services Customer Support FMC Customer Support provides service and strategic life of field planning and solutions designed to deliver immediate and long-term satisfaction to operators worldwide.

More information

Safe carriage of oil in extreme environments

Safe carriage of oil in extreme environments Safe carriage of oil in extreme environments Stena Aframax. 117,100 DWT. Swedish-Finnish Ice Class 1A Super Stena Panamax. 74,999 DWT. Swedish-Finnish Ice Class 1A Stena P-MAX. 49,900 DWT. Swedish-Finnish

More information

NATIONAL SINGLE WINDOW PROTOTYPE AN ELECTRONIC SOLUTION FOR SIMPLIFYING ADMINISTRATIVE PROCEDURES

NATIONAL SINGLE WINDOW PROTOTYPE AN ELECTRONIC SOLUTION FOR SIMPLIFYING ADMINISTRATIVE PROCEDURES NATIONAL SINGLE WINDOW PROTOTYPE AN ELECTRONIC SOLUTION FOR SIMPLIFYING ADMINISTRATIVE PROCEDURES BACKGROUND A longstanding problem in the shipping industry is the complexity and time involved in submitting

More information

Crowley LNG. Puget Sound Harbor Safety Committee June 3 rd, 2015. Matthew Sievert Director Business Development LNG

Crowley LNG. Puget Sound Harbor Safety Committee June 3 rd, 2015. Matthew Sievert Director Business Development LNG Crowley LNG Puget Sound Harbor Safety Committee June 3 rd, 2015 Matthew Sievert Director Business Development LNG Company Profile Crowley was founded in 1892. Largest US Jones Act Co. Focusing on Marine

More information

SIMON STEVIN. 24,350kw Diesel-Electric Propulsion 19,500m 3 Capacity of Rock Storage Dynamic Positioning System DP-2

SIMON STEVIN. 24,350kw Diesel-Electric Propulsion 19,500m 3 Capacity of Rock Storage Dynamic Positioning System DP-2 SIMON STEVIN The world s largest FALL PIPE & ROCK DUMPING Vessel 24,350kw Diesel-Electric Propulsion 19,500m 3 Capacity of Rock Storage Dynamic Positioning System DP-2 The world s largest fall pipe & rock

More information

A leading British OEM of integrity in the Shipping, Naval, Offshore Oil & Gas, Fire Safety and Energy Markets.

A leading British OEM of integrity in the Shipping, Naval, Offshore Oil & Gas, Fire Safety and Energy Markets. A leading British OEM of integrity in the Shipping, Naval, Offshore Oil & Gas, Fire Safety and Energy Markets. T: +44 207 629 8475 F: +44 207 629 8477 info@coltraco.co.uk www.coltraco.com Coltraco Limited

More information

Multi-Modal Logistics Hub (MMLH) in Yanbu

Multi-Modal Logistics Hub (MMLH) in Yanbu Multi-Modal Logistics Hub (MMLH) in Yanbu 2nd RCYCI Forum program 5 January 2016 Agenda Multi-Modal Logistics Hub (MMLH) study outcome in 2014 Education and employment requirements in MMLH Current status

More information

Marine Stewardship Council

Marine Stewardship Council Marine Stewardship Council MSC Fishery Standard Principles and Criteria for Sustainable Fishing Version 1.1 1 st May 2010 Committees responsible for this Standard This standard is intended to be used on

More information

Our recent customers Siemens / Statoil and Bard Offshore have experienced this. References on request.

Our recent customers Siemens / Statoil and Bard Offshore have experienced this. References on request. SweOffshore Fabriksgatan 10 SE-412 50 Gothenburg, Sweden +46(0)31 788 78 00 commercial@sweoffshore.com www.sweoffshore.com SweOffshore Accommodation concept, Supporting our Customers in achieving the most

More information

Baltic Marine Environment Protection Commission

Baltic Marine Environment Protection Commission Baltic Marine Environment Protection Commission Response Working Group Stockholm, Sweden, 15-17 March 2016 RESPONSE 21-2016 Document title BONUS SWERA - Sunken Wreck Environmental Risk Assessment Code

More information

FORCE 16 INTERCEPTOR. UNION FORCE MARINE GROUP Jean-Marc Gregori, President ITALY: + 39 328 10 97 440 - FRANCE: + 33 619 976711 JMG@UFMGroup.

FORCE 16 INTERCEPTOR. UNION FORCE MARINE GROUP Jean-Marc Gregori, President ITALY: + 39 328 10 97 440 - FRANCE: + 33 619 976711 JMG@UFMGroup. The FORCE 16 INTERCEPTOR is designed for high-speed (up to 90 knots), extraordinary maneuverability, and exceptional sea keeping. It is ideal for coastal operations and severe conditions up to sea state

More information

JARPA II* Research Fleet Departs for the Antarctic

JARPA II* Research Fleet Departs for the Antarctic THE INSTITUTE OF CETACEAN RESEARCH 4-5 TOYOMI-CHO, CHUO-KU, TOKYO 104-0055 JAPAN PHONE: +81-3-3536-6521 FAX: +81-3536-6522 MEDIA RELEASE 7 November 2005 JARPA II* Research Fleet Departs for the Antarctic

More information

Capacity building for Maritime Domain Awareness in East Africa

Capacity building for Maritime Domain Awareness in East Africa 1 US Naval Forces Africa Capacity building for Maritime Domain Awareness in East Africa Kirsty McLean + 39 081 568 8104 +39 335 179 6404 Kirsty.mclean@eu.navy.mil Overview 2 What is NAVAF and what do we

More information

FLEET LIST OFFSHORE SUPPORT VESSELS

FLEET LIST OFFSHORE SUPPORT VESSELS FLEET LIST OFFSHORE SUPPORT VESSELS maersksupplyservice.com Reliable, Safe and Efficient Maersk Supply Service is proud to serve the offshore industry with a fleet of around 65 vessels, manned by more

More information

Driven by history... With a pedigree dating back several hundred years, Balk Shipyard is now in the capable hands of the seventh generation of the

Driven by history... With a pedigree dating back several hundred years, Balk Shipyard is now in the capable hands of the seventh generation of the Driven by history... With a pedigree dating back several hundred years, Balk Shipyard is now in the capable hands of the seventh generation of the family. Today we offer you genuinely state-of-the-art

More information

AMOS SFI. Group System. Product Description

AMOS SFI. Group System. Product Description AMOS SFI Group System Product Description 1. INTRODUCTION 1 2. BACKGROUND, PURPOSE AND ADVANTAGES 1 2.1 Background 1 2.2 Purpose and Advantages 1 2.3 Scope 2 3. THE PROBLEMS SFI CAN SOLVE 2 3.1 Controlling

More information

maersksupplyservice.com S-TYPE ANCHOR HANDLING TUG SUPPLY VESSEL Visit our web site at: maersksupplyservice.com

maersksupplyservice.com S-TYPE ANCHOR HANDLING TUG SUPPLY VESSEL Visit our web site at: maersksupplyservice.com maersksupplyservice.com S-TYPE ANCHOR HANDLING TUG SPLY VESSEL Visit our web site at: maersksupplyservice.com Maersk Supply Service serves the offshore industry world wide with more than 60 vessels manned

More information

Commercial Seaglaze - The Professionals Choice. Marine Windows Doors Hatches

Commercial Seaglaze - The Professionals Choice. Marine Windows Doors Hatches Commercial Seaglaze - The Professionals Choice Marine Windows Doors Hatches Why Us? Second Generation Family Business We know the reliability of your supply chain is key to delivering your vessels on time

More information

The MUNIN project An overview

The MUNIN project An overview The MUNIN project An overview MUNIN Final Event June 10 th 2015, Hamburg, Germany Dipl.-Wirtsch.-Ing. Univ. Hans-Christoph Burmeister MUNIN Project Coordinator Fraunhofer CML http://www.unmanned-ship.org

More information

Florida Institute of Oceanography

Florida Institute of Oceanography Florida Institute of Oceanography Dr. William T. Hogarth, Interim Director, FIO & Dr. Jyotika I. Virmani, Associate Director, FIO National Water Quality Monitoring Council New Orleans, LA May 3-5, 2011

More information

MATERIAL TRANSFER AGREEMENT RESPONSIBILITY TERM

MATERIAL TRANSFER AGREEMENT RESPONSIBILITY TERM Request #: (To be filled by EMEPC) The recipient MATERIAL TRANSFER AGREEMENT RESPONSIBILITY TERM The Task Group for the Extension of the Continental Shelf (EMEPC) was established by Resolution of the Council

More information

Inland Waterway Infrastructure - Mekong River cruise promoting factor. Tokyo September 2010

Inland Waterway Infrastructure - Mekong River cruise promoting factor. Tokyo September 2010 Inland Waterway Infrastructure - Mekong River cruise promoting factor Tokyo September 2010 Mekong river system Mekong river system Land and resources: Parts of China, Myanmar and Viet Nam, nearly 1/3 of

More information

Keep Your Head Above Water

Keep Your Head Above Water Grade 8 Activity Keep Your Head Above Water Do things that float behave differently in salt and fresh water? What lets them float, and when do they sink? Concepts Water has physical properties of density

More information

National Transportation Safety Board

National Transportation Safety Board National Transportation Safety Board Marine Accident Brief Fire On Board Motor Yacht Ocean Alexander 85E06 Accident no. Vessel name Accident type Location DCA13LM029 Ocean Alexander 85E06 Fire Date July

More information

Improving Hydrographic Rate of Effort

Improving Hydrographic Rate of Effort Improving Hydrographic Rate of Effort Presented by Scott Elson Australia s Surveying Responsibility Source: http://www.hydro.gov.au/business-publications/hydroscheme-2010-2012.pdf Company Proprietary 2

More information

13. FPSO Operational Problems Don Smith, OGP

13. FPSO Operational Problems Don Smith, OGP OGP Marine Risks Workshop Proceedings 13. FPSO Operational Problems Don Smith, OGP FPSO Operational Problems Don Smith OGP Analysis of Accident Statistics for Floating Monohull and Fixed Installations

More information

Blohm+Voss at SMM 2016 Customer service and innovative solutions from a single source

Blohm+Voss at SMM 2016 Customer service and innovative solutions from a single source Blohm+Voss at SMM 2016 Customer service and innovative solutions from a single source Hamburg, August 5, 2016 For Blohm+Voss, the focus is on the customer. Be it refits, servicing and maintenance of ships

More information

The Advance of New ROV Conveyed Geotechnical Acquisition Tools - Going Where No Man Has Gone Before. Subsea UK Expo February 2014

The Advance of New ROV Conveyed Geotechnical Acquisition Tools - Going Where No Man Has Gone Before. Subsea UK Expo February 2014 The Advance of New ROV Conveyed Geotechnical Acquisition Tools - Going Where No Man Has Gone Before Subsea UK Expo February 2014 UTEC Geomarine Snapshot Founded Newcastle 2009 Subsea geotechnical engineering

More information

Any Ocean, Anywhere, Anytime. www.shadowmarine.com

Any Ocean, Anywhere, Anytime. www.shadowmarine.com Any Ocean, Anywhere, Anytime www.shadowmarine.com CONCEPT If you had no limitations, what would you change about your next voyage? What would you take with you? A Shadow Marine yacht support vessel or

More information

il Castorone la più avanzata nave posatubi al mondo: acquisti e logistica Paolo Daleffe Armando Favi

il Castorone la più avanzata nave posatubi al mondo: acquisti e logistica Paolo Daleffe Armando Favi il Castorone la più avanzata nave posatubi al mondo: acquisti e logistica Paolo Daleffe Armando Favi Castorone concentration of technologies and efficiency, Castorone is designed for high productivity

More information

Cruise planning worksheet. Scheduling information. Equipment requirements. Date of cruise planning meeting 2013-05-20, Monday R/V Melville

Cruise planning worksheet. Scheduling information. Equipment requirements. Date of cruise planning meeting 2013-05-20, Monday R/V Melville Cruise planning worksheet Date of cruise planning meeting 2013-05-20, Monday Ship R/V Melville Chief Scientist Craig Merrill Cruise Name MV1307 Scheduling information Start port Load start date (begin

More information

THE FUTURE OF THE OCEAN ECONOMY: AN OECD/IFP FORESIGHT PROJECT

THE FUTURE OF THE OCEAN ECONOMY: AN OECD/IFP FORESIGHT PROJECT THE FUTURE OF THE OCEAN ECONOMY: EXPLORING THE PROSPECTS FOR EMERGING OCEAN INDUSTRIES TO 2030 AN OECD/IFP FORESIGHT PROJECT BARRIE STEVENS OECD/DSTI Verftskonferansen 2013 Alesund, Norway, 5 th November

More information

APPLICATION FORM YACHT LIABILITY INSURANCE POLICY

APPLICATION FORM YACHT LIABILITY INSURANCE POLICY APPLICATION FORM YACHT LIABILITY INSURANCE POLICY APPLICATION FORM Yacht liability insurance policy 1. Contact details Please provide us with the name and contact details of the person/company to be insured.

More information

Real Estate Investment: Main Tax Issues

Real Estate Investment: Main Tax Issues Real Estate Investment: Main Tax Issues 1 All the lawyers know what s happening on the case and work really well as a team. It sets them apart from others in the market. Client reference from Chambers

More information

Block Vote Projects Approved by the OGCIO in 2013-14 (from 1.4.2013 to 31.3.2014)

Block Vote Projects Approved by the OGCIO in 2013-14 (from 1.4.2013 to 31.3.2014) 1 Agriculture, Fisheries and Conservation Replacement of Endangered Species Licensing and Enforcement 7.7 2013-14 1st Quarter 2014-15 3rd Quarter 2 Architectural Services 3 Chief Secretary for Administration's

More information

Data Data Everywhere, We are now in the Big Data era

Data Data Everywhere, We are now in the Big Data era Data Data Everywhere, We are now in the Big Data era Mike Liddell 13 th March 2014 UUVs @ OI 2014 Contents Menu Background Big Data What is Generating our Big Data Physical Management of Big Data Optimisation

More information

DOLPHIN GROUP INTELLIGENT, FAST AND FRIENDLY COMPANY PRESENTATION SEG 2012 NOVEMBER 2012

DOLPHIN GROUP INTELLIGENT, FAST AND FRIENDLY COMPANY PRESENTATION SEG 2012 NOVEMBER 2012 DOLPHIN GROUP INTELLIGENT, FAST AND FRIENDLY COMPANY PRESENTATION SEG 2012 NOVEMBER 2012 Disclaimer This presentation includes and is based, inter alia, on forward-looking information and statements that

More information

Shallow Water Swath Bathymetry from Small Platforms. Advances in Seafloor Mapping Sonar, 30 Dec 2009 Systems Engineering & Assessment Ltd.

Shallow Water Swath Bathymetry from Small Platforms. Advances in Seafloor Mapping Sonar, 30 Dec 2009 Systems Engineering & Assessment Ltd. Shallow Water Swath Bathymetry from Small Platforms Advances in Seafloor Mapping Sonar, 30 Dec 2009 Systems Engineering & Assessment Ltd. Presentation Requirements, applications and challenges SWATHplus

More information

GOVERNMENT OF PAKISTAN MINISTRY OF PORTS AND SHIPPING

GOVERNMENT OF PAKISTAN MINISTRY OF PORTS AND SHIPPING GOVERNMENT OF PAKISTAN MINISTRY OF PORTS AND SHIPPING Mission Statement As more than 95 per cent of the total freight trade of Pakistan is seaborne, the overall objective of the Ministry of Ports and Shipping

More information

PETROBRAS R&D CENTER (CENPES)

PETROBRAS R&D CENTER (CENPES) PETROBRAS R&D CENTER (CENPES) Luciano Pereira dos Reis CENPES / PDP /GR SIBGRAPI 2009: Workshop on Applications of Graphics for the Petroleum Industry TECHNOLOGICAL PROGRAMS New Exploratory Frontiers Basin

More information

Cable Care. ABB Power Cables Service Products

Cable Care. ABB Power Cables Service Products Cable Care ABB Power Cables Service Products 2 ABB Power Cables Service Products ABB Power Cables Minimize revenue losses in case of a fault High preparedness with ABB Cable Care ensures efficient repair

More information

MARINE SCIENCE CO-ORDINATION COMMITTEE UPDATE REPORT FROM THE WORKING GROUPS FOR PERIOD MARCH AUGUST 2014 CONTENTS SCIENCE ALIGNMENT...

MARINE SCIENCE CO-ORDINATION COMMITTEE UPDATE REPORT FROM THE WORKING GROUPS FOR PERIOD MARCH AUGUST 2014 CONTENTS SCIENCE ALIGNMENT... MARINE SCIENCE CO-ORDINATION COMMITTEE UPDATE REPORT FROM THE WORKING GROUPS FOR PERIOD MARCH AUGUST 2014 CONTENTS SCIENCE ALIGNMENT... 1 1.1 Eco-system Models Alignment Sub Group... 1 1.2 Science Alignment

More information

THE NEXT REVOLT 18 BATTERY COASTAL TRAFFIC REVOLT IN BRIEF

THE NEXT REVOLT 18 BATTERY COASTAL TRAFFIC REVOLT IN BRIEF 18 BATTERY COASTAL TRAFFIC THE NEXT REVOLT Could present-day technology improve the cost and effectiveness of shortsea shipping while enhancing safety and environmental performance? Yes, it could! Taking

More information

POOLLC PLATFORM HOGAN SUBMARINE CABLE REPAIR PROJECT MARCH & APRIL 2008 SANTA BARBARA CHANNEL

POOLLC PLATFORM HOGAN SUBMARINE CABLE REPAIR PROJECT MARCH & APRIL 2008 SANTA BARBARA CHANNEL POOLLC PLATFORM HOGAN SUBMARINE CABLE REPAIR PROJECT MARCH & APRIL 2008 SANTA BARBARA CHANNEL PRESENTED BY MARK STEFFY LONGITUDE 123, INC. PRESENTATION OVERVIEW: The California offshore oilfield marine

More information

CALIFORNIA OCEAN PROTECTION COUNCIL. Staff Recommendation March 11, 2011 STATEWIDE SCIENCE INTEGRATION AND MARINE PROTECTED AREA MONITORING PROGRAMS

CALIFORNIA OCEAN PROTECTION COUNCIL. Staff Recommendation March 11, 2011 STATEWIDE SCIENCE INTEGRATION AND MARINE PROTECTED AREA MONITORING PROGRAMS CALIFORNIA OCEAN PROTECTION COUNCIL Staff Recommendation March 11, 2011 STATEWIDE SCIENCE INTEGRATION AND MARINE PROTECTED AREA MONITORING PROGRAMS File No.: 08-123-02 File No.: 06-090-02 Project Managers:

More information

Bergen Group -positioned for growth

Bergen Group -positioned for growth Bergen Group -positioned for growth CFO Ståle Rene SR-Markets oljeseminar, Stavanger 5. juni 2012 QUALITY THROUGH SERVICE AND INNOVATION Bergen Group is an innovative supplier of products, services & solutions

More information

13º Encontro Sociedade Brasileira de Geofísica 2013 Rio de Janeiro, 26-29 29 August Earthquake Mitigation in the Lisbon and Lower Tagus Valley area, Portugal 1 J. Carvalho, R. Dias, C. Pinto, T. Cunha,

More information

FLEET LIST OFFSHORE SUPPORT VESSELS

FLEET LIST OFFSHORE SUPPORT VESSELS FLEET LIST OFFSHORE SUPPORT VESSELS Safe, Reliable and Efficient Maersk Supply Service is proud to serve the offshore industry with a fleet of around 60 vessels, manned by more than 1,800 highly professional

More information

ANNEX 5 RESOLUTION MEPC.127(53) Adopted on 22 July 2005 GUIDELINES FOR BALLAST WATER MANAGEMENT AND DEVELOPMENT OF BALLAST WATER MANAGEMENT PLANS (G4)

ANNEX 5 RESOLUTION MEPC.127(53) Adopted on 22 July 2005 GUIDELINES FOR BALLAST WATER MANAGEMENT AND DEVELOPMENT OF BALLAST WATER MANAGEMENT PLANS (G4) RESOLUTION MEPC.127(53) Adopted on 22 July 2005 GUIDELINES FOR BALLAST WATER MANAGEMENT AND DEVELOPMENT OF BALLAST WATER MANAGEMENT PLANS (G4) THE MARINE ENVIRONMENT PROTECTION COMMITTEE, RECALLING Article

More information

NEW DIGITAL TERRAIN MODELING (DTM) TOOLS FOR CABLE ROUTE PLANNING by Dr. Jose M. Andres Makai Ocean Engineering Inc.

NEW DIGITAL TERRAIN MODELING (DTM) TOOLS FOR CABLE ROUTE PLANNING by Dr. Jose M. Andres Makai Ocean Engineering Inc. NEW DIGITAL TERRAIN MODELING (DTM) TOOLS FOR CABLE ROUTE PLANNING by Dr. Jose M. Andres Makai Ocean Engineering Inc. EXISTING CABLE ROUTE PLANNING TOOLS In recent years, methods used for submarine cable

More information

Within the Ministry of Petroleum Resources, technical issues of policy nature, regulatory control of the industry, revenues, royalties and fiscal

Within the Ministry of Petroleum Resources, technical issues of policy nature, regulatory control of the industry, revenues, royalties and fiscal Nigeria s practice and experience in its domestic licensing regimes and views on the implementation of Article 82 with regard to its offshore oil and gas activities By Adesina Adegbie International Workshop

More information

Appendix A. The Marine Life Protection Act (MLPA)

Appendix A. The Marine Life Protection Act (MLPA) Appendix A. The Marine Life Protection Act (MLPA) THE PEOPLE OF THE STATE OF CALIFORNIA DO ENACT AS FOLLOWS: SECTION 1. Chapter 10.5 (commencing with Section 2850) is added to Division 3 of the Fish and

More information

lng conversion (General)

lng conversion (General) lng conversion (General) 1 Wärtsilä 10.4.2013 Jens Häggblom Content DF conversion portfolio and references Reasons for conversion DF conversion in practice LNG storage, process and bunkering system (Wärtsilä

More information

Maintenance and Disposition. Ocean and Marine Technology Functional Files. Function Number 1800

Maintenance and Disposition. Ocean and Marine Technology Functional Files. Function Number 1800 Maintenance and Disposition Ocean and Marine Technology Functional Files Function Number 1800 Function number 1800 deal with program related to ocean and marine technology promotion, evaluation, and information.

More information

CROSSING THE OSLOFJORD - AN EARLY STRATEGIC ANALYSIS - Technical challenges and consideration of Feasible solutions

CROSSING THE OSLOFJORD - AN EARLY STRATEGIC ANALYSIS - Technical challenges and consideration of Feasible solutions CROSSING THE OSLOFJORD - AN EARLY STRATEGIC ANALYSIS - Technical challenges and consideration of Feasible solutions Ove Solheim MSc - Norwegian Public Roads Administration ABSTRACT Feasibility studies

More information