POSITIVE SCOPING STUDY DEMONSTRATES POTENTIAL OF SALAMANCA PROJECT

Size: px
Start display at page:

Download "POSITIVE SCOPING STUDY DEMONSTRATES POTENTIAL OF SALAMANCA PROJECT"

Transcription

1 Highlights: POSITIVE SCOPING STUDY DEMONSTRATES POTENTIAL OF SALAMANCA PROJECT Positive Scoping Study confirms technical and economic viability of the Salamanca Project; Initial mine life of 11 years, including 7 years steady state operation, with strong potential to increase; Steady state annual production of 3.2 million pounds U 3 O 8, with average annual production of 2.6 million pounds U 3 O 8 over the life of mine; Life of mine average operating costs of US$25.65 per pound of U 3 O 8 ; Upfront capital cost of US$83.6 million to deliver initial production. A further US$95.0 million, incurred in the second year of production and largely funded from operating cashflow, to achieve steady state operation; and Pre-Feasibility Study to commence immediately, targeting completion in mid Berkeley Resources Limited ( Berkeley or the Company ) is pleased to announce that the Scoping Study for the Company s flagship Salamanca Project (the Project ) in Spain has confirmed the technical and economic viability of the Project. Using only the current Mineral Resource Estimates for Retortillo and Alameda, which total 33.9 million pounds U 3 O 8 (35.9 million tonnes at 429 ppm; 200 ppm U 3 O 8 cut-off grade), as a base case scenario, the Project can support an average annual production of 3.2 million pounds of U 3 O 8 during the seven years of steady state operation and 2.6 million pounds of U 3 O 8 over a minimum eleven year mine life. There is strong potential to increase the production profile and mine life through the exploitation of additional resources held by the Company (totalling 27.1 million pounds U 3 O 8 ) and with ongoing exploration work. The Scoping Study is based on open pit mining, heap leaching, a centralised process plant at Retortillo, and a remote ion exchange operation at Alameda, with loaded resin trucked to the centralised plant for final extraction and purification. The Company currently favours a contractor mining scenario. The average annual ore processing rate during steady state operation is 5.5 million tonnes. Operating cost estimates average US$25.65 per pound U 3 O 8 over the life of mine. The initial capital cost (nominally ± 30% accuracy) for the Project is estimated at US$83.6 million. This cost is inclusive of all mine, processing, infrastructure and indirect costs required to develop and commence production at Retortillo. A further US$95.0 million of capital, incurred in the second year of production and largely funded from operating cashflow, is required to develop Alameda and achieve steady state operation. The Project s capital cost reflects the excellent existing infrastructure, use of heap leaching as the preferred processing route, and the favoured mining contractor scenario (no mining fleet capital expenditure). Berkeley Resources Limited ASX/AIM:BKY T: F: E: W: Level 9, BGC Centre, 28 The Esplanade PERTH 6000 ABN:

2 Berkeley will award and commence the Pre-Feasibility Study ( PFS ) immediately and anticipates completion of the PFS in mid The Company will undertake a more detailed mine scheduling and materials movement optimisation study, metallurgical testwork program and infrastructure assessment during the PFS phase, with the aim of identifying opportunities to further enhance the Project economics through capital and operating cost reductions. Resource infill and exploration drilling programs aimed at upgrading the resource classification and increasing the overall resource base are also underway. The Directors are encouraged by the positive results of the Scoping Study which clearly demonstrate the potential of the integrated Salamanca Project to support a significant scale, long life uranium mining operation. Accordingly, the Company will continue to focus on pursuing the ongoing exploration, appraisal and development of the Project in order to fulfil its strategic objective of becoming the next European uranium producer. Enquiries: Robert Behets Berkeley Resources

3 ASX RELEASE 29 November 2012 ASX:BKY Introduction Following the agreement with ENUSA in July 2012, Berkeley Resources Limited ( Berkeley or the Company ) has focussed on the advancement of its wholly owned flagship Salamanca Project ( the Project ), which comprises the Retortillo, Alameda and Gambuta deposits plus a number of other Satellite deposits located in western Spain (Figure 1), through the development phase. The results of a Preliminary Feasibility Study ( PFS ) completed in early 2012 confirmed the technical and economic viability of a stand-alone project exploiting Retortillo, whilst Alameda formed part of a separate Feasibility Study completed in The Company has now completed an initial assessment of the integrated development of Retortillo and Alameda and is pleased to report the results of this Scoping Study ( the Study ). The Study has been managed by Berkeley with input from a number of industry recognised specialist consultants covering the key disciplines. The Study has incorporated all of the information generated from the previous studies conducted on Retortillo and Alameda, as well as new, more recently completed drilling and metallurgical testwork data. Figure 1: Location of the Salamanca Project, Spain

4 Scoping Study Parameters The Scoping Study was completed using the following parameters: Life of Mine ( LOM ) minimum 11 years, including 7 years of steady state operation Average Production 3.2 million pounds U 3 O 8 per annum during steady state operation Strip Ratio 1:2.0 (ore to waste) average LOM Ore Processing Rate 5,500,000 tonnes per annum during steady state operation Mining Cut-off Grade 98 parts per million (ppm) U 3 O 8 Metallurgical Recovery 85% Uranium Price US$65 per pound U 3 O 8 Exchange Rate US$/ 1.25 The key considerations for the Study were preferred mining and processing route, scale, throughput rate, mine life, as well as development of the associated infrastructure taking due cognisance of community and environmental impacts. The Study, which has been based solely on the Mineral Resource Estimates ( MRE ) for Retortillo and Alameda, demonstrates the Project has a minimum mine life of eleven years (including 7 years of steady state operation). Given the significant additional Mineral Resources and exploration upside associated with Gambuta and other Satellite deposits within the Salamanca Province, the potential exists to increase the mine life and accordingly, the Study is considered as a base case scenario. The basic conceptual approach to the development of Retortillo and Alameda contemplated in the Study includes: Open pit mining (transfer mining to facilitate continuous rehabilitation) Heap leaching using on-off leach pads Centralised solvent extraction ( SX ) and ammonium diuranate ( ADU ) precipitation plant, located at Retortillo Remote ion exchange ( IX ) operation at Alameda, with loaded resin trucked to the centralised plant for final extraction and purification Mineral Resources The Study has been based solely on the MRE s for Retortillo and Alameda (Table 1). The MRE s were prepared by Berkeley and are reported in accordance with the JORC Code (2004). Updated MRE s for Retortillo and Alameda, based on a combination of chemical assays and e-grades (down-hole gamma logging data presented as equivalent U 3 O 8 grades or eu 3 O 8 ) from historical drilling, supplemented by additional diamond and reverse circulation ( RC ) drilling by Berkeley with both chemical assays and e-grades, were reported in July These MRE s were developed by a team of in-house and consulting geologists who undertook a rigorous program to verify the historical data and create a validated database containing all historical and recent data. The MRE at Retortillo was based on data from approximately 20,000 metres of historical drilling and 42,000 metres of drilling undertaken by Berkeley whilst the Alameda MRE was based on data from 41,000 metres of historical drilling and 10,000 metres of drilling undertaken by Berkeley. The drilling is a combination of diamond and RC drilling.

5 ASX RELEASE 29 November 2012 ASX:BKY Table 1 - Summary of Mineral Resource Estimates used as basis of the Study Retortillo and Alameda Mineral Resource Estimates July 2012 Reported at a lower cut-off grade of 200 ppm U3O8 Category Retortillo Alameda Tonnage (million tonnes) Grade (U3O8 ppm) Indicated Inferred Sub Total Indicated Sub Total Indicated Inferred Combined Inferred Total Contained U3O8 (million pounds) Retortillo and Alameda are both vein type deposits hosted in meta-sedimentary sequences adjacent to granitic intrusives. At Alameda, the uranium mineralisation occurs in a complex network of moderately to steeply dipping brittle structures (veins, faults, fractures and along bedding contacts) as a result of a low temperature hydrothermal event. The mineralised zones commonly have sharp boundaries, separating mineralised structures from poorly mineralised host rock. At Retortillo, the mineralised envelope is generally sub-horizontal and the mineralisation is contained within a stockwork of veins. The uranium mineralisation appears to be associated with the presence of sulphides within the partially weathered zone and the base of mineralisation is associated with the base of partial weathering which locally deepens along structures. Figure 2: Grade Tonnage Curves Whilst the Retortillo and Alameda MRE s are reported at a 200 ppm U3O8 lower cut-off grade, the grade tonnage curves (Figure 2) highlight the significant impact that the cut-off grade used has on the resource estimate. At a 100 ppm U3O8 lower cut-off grade, which approximates the mining cut-off grade derived from the pit optimisations undertaken in the Study, the resource estimates for Retortillo and Alameda total 18.2 million pounds and 25.4 million pounds contained U3O8 respectively. This represents increases of 42% and 20% in contained uranium at Retortillo and Alameda respectively when compared with the MRE at the 200 ppm lower cut-off grade.

6 Although the Study has been based solely on the Retortillo and Alameda MRE s, the Company has a 100% interest in additional Inferred Resources totalling 27.1 million pounds of contained U 3 O 8 (28.5 million tonnes averaging 431 ppm U 3 O 8, refer ASX June 2012 Quarterly Report) at Gambuta and other Satellite deposits, which are in close proximity to Retortillo and Alameda. These additional resources have not been considered in the current Study and their inclusion in subsequent studies has the potential to increase the mine life and/or production scale of the Project. The Company is also planning drilling programs with the objective of testing the numerous exploration targets within the Project area. Mining The mining of both ore and waste is a conventional open pit operation. Diesel-powered truck and shovel operations, in combination with an effective drill and blast plan has been considered for both deposits. As part of the Study, a series of Whittle optimisations were completed on the Retortillo and Alameda MRE s. Materials classified in the Indicated and Inferred categories were used in the optimisation process. Pit designs, waste dump designs and life of mine ( LOM ) mining schedules were then completed to determine the optimal long term mine plan. The mining schedule is expected to be conducted over a period of 11 years. Initial mining activity is at Retortillo, with the first of seven years of steady state operation being achieved in Year 3, with the commencement of mining at Alameda. The mine schedule averages 5.5 million tonnes per annum of combined mine production during steady state operation (Retortillo million tonnes per annum; Alameda million tonnes per annum). At its peak, the mining schedule contemplates the movement of a combined 16.9 million tonnes per annum (both waste and ore). Strip ratios for the Project are low with the average LOM strip ratio being 1:2.0 ore to waste (Retortillo 1:2.6; Alameda 1:1.6). The open pits are shallow with the maximum depths being 90 metres at Retortillo and 135 metres at Alameda. The mined grade averages 291 ppm U 3 O 8 and 322 ppm U 3 O 8 at Retortillo and Alameda respectively over the LOM. The basic mining fleet will comprise standard truck and shovel equipment, in the form of 7m 3 to 12m 3 hydraulic excavators (Komatsu PC 1250 or ) and a fleet of 100 tonne capacity (CAT 777 or similar) rigid dump trucks. Mine support equipment will include track mounted dozers, graders, water trucks and front end loaders, the latter used predominantly to feed the crusher. The graders will provide the majority of pit and road clean-up and support to the excavators, whilst the dozers will carry out floor level control and waste dump maintenance. The mining method utilised will be transfer mining which will allow the open pits to be continuously backfilled, minimising waste dump volumes and waste rehandling, whilst also facilitating a continuous rehabilitation program that minimises environmental impact. Typical mining bench heights of six metres will be employed at both deposits. Blast hole drilling will be carried out in fresh rock using diesel powered top-hammer rock drills, whilst the Tertiary cover and weathered materials will be loaded without blasting. The mining cost estimates assume a contractor mining scenario.

7 ASX RELEASE 29 November 2012 ASX:BKY Processing The results of extensive metallurgical testwork previously carried out on an approximately 5 tonne representative sample of the Alameda deposit at the SGS laboratories in Perth (including tank leach and heap leach scenarios) and the recent metallurgical testwork program undertaken on a 5.5 tonne bulk sample, representative of the Retortillo deposit, at Mintek s mineral processing facility in Johannesburg (heap leach scenario, refer ASX September 2012 Quarterly Report) have been used to select the preferred process route and design the flowsheet. The process flowsheet comprises crushing, agglomeration, stacking and heap leaching using on-off leach pads, followed by uranium recovery and purification by direct solvent extraction ( SX ), ammonium diuranate ( ADU ) precipitation and calcination at a centralised plant, located at Retortillo (Figure 3). Pregnant liquor solution ( PLS ) from the heap leach process at Alameda will be passed through an ion exchange ( IX ) adsorption column, with the loaded resin trucked to the centralised plant for final extraction and purification. Heap leach technology has been selected as the preferred leaching option due to the high efficiency shown during testwork, with high recoveries (ranging from 85% to 95% across both deposits and comparable to the tank leaching testwork results) and good leach kinetics. The uranium recoveries were achieved at relatively coarse crush sizes of 40mm for Retortillo and 20mm for Alameda. In addition, the spent ore from the on-off heap leach pads ( ripios ) can be backfilled to the open pits, removing the requirement for a tailings storage facility. Figure 3: Process Flow Sheet

8 Two stage crushing of run of mine ( ROM ) ore will be undertaken at Retortillo (target product size of 40mm) while three stage crushing is contemplated at Alameda, to deliver a finer product (20mm) to optimise the uranium recovery during heap leaching. The primary stage of crushing will use a jaw crusher, while cone crushers will be used for the secondary and tertiary stages. Crushed ore will be agglomerated before stacking. The crushed ore will be fed directly into a conventional drum where spray bars will dose the ore with sulphuric acid and raffinate to produce agglomerated ore. No polymer addition is required during the agglomeration process. The agglomerates are conveyed via overland conveyors to the heap leach pad. The heap leach comprises an on-off pad subdivided into cells to define areas for stacking, leaching, rinsing and reclaiming. The heap leach facility is complete with ponds for makeup water, barren, immediate leach solution, PLS, storm water and all associated pumping and reagent storage facilities. The pad design includes a triple insulation system including two high density polyethylene ( HDPE ) sheets and a clay layer. The agglomerated material is stacked in 6 metre lifts and irrigated with sulphuric acid using drip emitters. The testwork has indicated a commercial leach cycle of 140 days. The ripios will be backfilled into lined (HDPE and clay) and isolated areas previously mined within the pits. Acid consumption for the heap leach will range from 18 kg/t to 22 kg/t, inclusive of the addition of approximately 8 kg/t to 10 kg/t of acid in the agglomeration process. There is potential to reduce the total acid consumption through further optimisation of the acid addition in agglomeration. An external chemical oxidant is not required in the process. At Retortillo, the heap leach PLS will contain approximately 400 mg/l of U 3 O 8 which will feed directly into the SX facility. The Alameda heap leach PLS will be loaded onto resin in an IX adsorption column and the loaded resin transported a distance of approximately 50 kilometres by road to the centralised plant at Retortillo. Once the resin has been stripped, the eluate containing uranium will be combined with the Retortillo PLS and fed into the SX plant for further processing. The SX facility will be designed with four extraction steps and three stages of scrub to produce a raffinate of <1mg/l U 3 O 8. Regenerated resin will be returned to Alameda for re-use. The purified enriched uranium solution from the SX plant is treated to precipitate the uranium using anhydrous ammonia. The solution is heated to a temperature of degrees and ammonia is injected into the solution, raising the ph to around 7 and precipitating the uranium as ADU. The ADU slurry from the precipitation is pumped into a thickener for dewatering. The underflow is then further dewatered using centrifuges. The centrifuge cake is finally calcined to produce U 3 O 8 which is drummed and prepared for shipping. Analytical data of the PLS obtained during the testwork programs indicate that there are no impurities at levels that could adversely impact the quality of the yellowcake to be produced. Annual production averages 3.2 million pounds of U 3 O 8 during the seven years of steady state operation, and 2.6 million pounds of U 3 O 8 over the entire eleven year mine life. Infrastructure The total power requirements for the Project are low at an estimated 3.7 MW and 3.5 MW of installed power for Retortillo and Alameda respectively. Power will be supplied from the distribution grid available in the area at a cost of US$0.10 per kilowatt hour excluding capital.

9 ASX RELEASE 29 November 2012 ASX:BKY Water is available from both adjacent water courses and on-site sources derived from bores. Both Retortillo and Alameda are readily accessible from the existing public road network, with only the deviation of 4.5 kilometres of an existing road being required at Retortillo and the upgrade of 6 kilometres of an existing road necessary at Alameda. Given the Project sites proximity to the city of Salamanca and local villages, on-site accommodation facilities are not required. Figure 4: Project Infrastructure Capital Costs The initial capital cost for the mine, processing facilities and associated infrastructure for Retortillo is estimated at US$83.6 million. This cost is inclusive of all infrastructure and indirect costs required to develop and commence production at Retortillo. The capital cost for the mine, processing facilities and associated infrastructure for Alameda is estimated at US$95.0 million. This cost, which will be incurred in the second year of production, includes all infrastructure and indirect costs required for the Project to achieve a steady state production profile averaging 3.2 million pounds of U3O8 per annum. The indirect costs include the first fill of reagents, ECPM (engineering, procurement and construction management) costs and a 15% contingency. No allowance has been made for the acquisition of mining fleet (included in operating costs), as it is envisaged that this activity will be outsourced to a specialist mining contractor.

10 The engineering studies conducted to date, to support a capital cost estimate for the Project, allow for a level of accuracy of nominally +/- 30%. A summary of major capital costs is shown in Tables 2 and 3. Table 2 Summary of Retortillo Capital Costs (nominally ± 30% accuracy) Description Cost (US$m) Pre-Strip 3.1 Processing: ROM Pad 0.2 Crushing 3.2 Agglomeration 2.5 Heap Leach 8.9 Water Treatment Plant 5.2 SX 7.2 Refinery 8.9 Reagents and Utilities 5.2 Infrastructure: Power Supply 3.7 Road Diversion 1.4 Temporary/Waste Dumps, Water Dams 10.2 Security 0.4 Land Acquisition 4.6 G & A 2.1 Indirect Costs 16.8 Mining Fleet (included in Opex) 0 Total 83.6 Table 3 Summary of Alameda Capital Costs (nominally ± 30% accuracy) Description Cost (US$m) Pre-Strip 6.1 Processing: ROM Pad 2.4 Crushing 7.3 Agglomeration 3.9 Heap Leach 17.9 Water Treatment Plant 4.9 IX 5.2 Reagents and Utilities 2.7 Infrastructure: Power Supply 1.1 Road Diversion 2.0 Temporary/Waste Dumps, Water Dams 15.3 Security 0.4 Land Acquisition 6.1 G & A 2.1 Indirect Costs 17.6 Mining Fleet (included in Opex) 0 Total 95.0 An additional US$12.4 million of capital is required to develop a second major pit at Retortillo in the fifth year of production. Rehabilitation and Closure costs for the Project are estimated at US$120 million over the LOM. Operating Costs The average LOM operating cost has been estimated at US$25.65 per pound of U 3 O 8 produced. The operating costs (C1 cash costs) are defined as the direct operating costs including contract mining, processing, ripios management, water treatment and general and administration. The operating costs were estimated in conjunction with the Scoping Study process design criteria, block flow diagram, mechanical equipment lists, metallurgical testwork results for reagents, in-country labour cost data, in-country reagent and fuel supply prices, and benchmarked local mining contractor rates. Key operating cost data is summarised in Table 4.

11 Table 4 - Summary of LOM Operating Costs (nominally ± 30% accuracy) Description Cost (US$/lb U 3 O 8 ) Retortillo Alameda Mining Processing (including ripios backfill) General and Administration Subtotal by Area Total Operating Costs Marketing and transport costs of US$0.98/lb U 3 O 8 are in addition to the operating costs. A number of potential opportunities to reduce operating costs have been identified, including ripios management, reagent consumption, mining design and mine scheduling. Trade-off and optimisation studies focussed on these key operating cost drivers will be undertaken during the next phase of the Project. Waste Management and Rehabilitation Waste has been characterised and classified into four types: Oxide waste ( inert waste ) - an inert waste that can be handled as a typical mining waste; Acid Rock Drainage ( ARD ) - potential acid generator due to a marginal sulphide content; Natural Occurring Radioactive Materials ( NORM ) - rock containing very low residual uranium below the mining cut-off grade; and Ripios - spent ore from the on-off heap leach pads which can be considered equivalent to ARD and/or NORM waste due to its similar physical and chemical characteristics. As noted earlier, open pit mining will be undertaken using the transfer mining method to allow continuous backfilling of the pits with waste, thus minimising waste dump volumes and waste rehandling, whilst also allowing for a continuous rehabilitation program that minimises the environmental impact. Inert waste will be managed using standard industry procedures, placing the material on permanent waste dumps or backfilling the material directly into mined areas within the pits. Ripios, ARD and NORM waste will be placed onto temporary dumps designed with the required isolation system (HDPE and clay) during the initial years of operation and subsequently backfilled into lined and isolated areas within the mined pits (once sufficient space is available). The backfilling of ripios is prioritised over ARD and NORM. At the end of the mine life, the whole volume of ripios, ARD and NORM waste will be fully encapsulated within the mined pits, and the surface rehabilitated as per the existing profile and vegetation. Community and Employment Berkeley has worked closely with all stakeholders, including local communities and relevant government authorities, in all aspects of work conducted on the Project to date. As part of this strategy, the Company has already signed co-operation agreements with the three municipalities proximal to Retortillo. These agreements are an important step in progressing through the permitting phase to production. As part of the agreements, the municipalities undertake to actively and promptly contribute throughout the necessary administrative procedures required for the Project to achieve both licensing and permitting. Berkeley in turn commits to contribute to the economic and social development of the municipalities.

12 Similar agreements are being negotiated with the relevant municipalities proximal to Alameda. The workforces required for the construction and operational phases of the Project will be sourced from the local communities whenever possible, in combination with a small number of highly skilled professionals who will be recruited from elsewhere in Spain or abroad. There is over thirty years of uranium mining experience within the region that hosts the Project. Permitting The permitting of Retortillo and Alameda are independent processes, with the process for Retortillo already well advanced. In October 2011, Berkeley initiated the licensing and permitting process for the development of Retortillo with the submission of an application for the conversion of the Pedreras Investigation Permit (Exploration Permit) into an Exploitation Concession (Mining Permit). The submission included a Scoping Environmental Impact Assessment and was subjected to a consultation period. All comments received from the consultation period were addressed and/or incorporated into the Environmental Impact Assessment ( EIA ) submitted in March Along with the EIA, the Company also submitted other key documents for the permitting process in March, including the Exploitation Plan, the Restoration and Closure Plans, the Authorisation for the Use of Rural Land for Industrial Purposes, and the Initial Authorisation for the Process Plant as a Radioactive Facility. The application was approved for public information in May and the 30 day Public Information Period was completed in mid September. The public comments were received in late September and the Company submitted its responses to these comments in late October. The Company s responses will be subject to clearance and direction from the relevant authorities before they are incorporated into the Declaration of Environmental Impact. Ancillary permits, such as those associated with water and roads, are also currently being advanced. The permitting process for Alameda will follow same procedure as for Retortillo however, reporting to Central Administration instead of Regional Government. The process has commenced with the Company submitting the Scoping Environmental Impact Assessment to the relevant authorities in November. Pre-Feasibility Study and Drilling Berkeley will award and commence the PFS immediately and anticipates it being completed in mid During the PFS phase, the Company will undertake a more detailed mine scheduling and materials movement optimisation study, metallurgical testwork program and infrastructure assessment aimed at identifying opportunities to further enhance the Project economics through capital and operating cost reductions. Resource infill and exploration drilling programs aimed at upgrading the resource classification and increasing the overall resource base are also underway. The drilling programs comprise both diamond and RC drilling, with the diamond drilling planned to give a better geological understanding of the structural controls influencing the local distribution of uranium mineralisation, as well as to supply drill core for further metallurgical testwork.

13 Further optimisation of the mine schedule and materials movement will be undertaken with a view to accelerating the ramp up to steady state operation, and to minimising materials handling and rehandling. Waste dump positioning will be detailed to reduce haulage costs. The planned metallurgical testwork program will include additional column leach work which will generate more detailed information relating to the geotechnical characterisation of the heap, solution tenor and downstream precipitation options. The findings from this testwork program will be used to finalise the design of the process flowsheet and its associated infrastructure. All required infrastructure for the Project will be further assessed and optimal site layout plans generated. The opportunity to use local supply and rates will be investigated to further enhance the Project s capital efficiency. Competent Persons Statement The information in this announcement that relates to Exploration Results and Mineral Resources is based on information compiled by Craig Gwatkin, who is a Member of The Australian Institute of Mining and Metallurgy and is an employee of Berkeley Resources Limited. Mr. Gwatkin has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2004 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves. Mr. Gwatkin consents to the inclusion in the report of the matters based on his information in the form and context in which it appears. Forward Looking Statement Statements regarding plans with respect to the Company s mineral properties are forward-looking statements. There can be no assurance that the Company s plans for development of its mineral properties will proceed as currently expected. There can also be no assurance that the Company will be able to confirm the presence of additional mineral deposits, that any mineralisation will prove to be economic or that a mine will successfully be developed on any of the Company s mineral properties.

Update on Heap Leach potential of the Murchison gold project

Update on Heap Leach potential of the Murchison gold project 3 July 2012 Australian-based Kentor Gold Limited (ASX: KGL) is entering the ranks of operating gold mining companies in 2012. The Company is progressing a pipeline of advanced projects in Australia and

More information

ALCYONE REPORTS JORC SILVER RESOURCES

ALCYONE REPORTS JORC SILVER RESOURCES ASX ANNOUNCEMENT & MEDIA RELEASE 29 March 2010 ALCYONE REPORTS JORC SILVER RESOURCES +15Moz RESOURCE INVENTORY UNDERPINS PROGRAM TARGETING RESUMPTION OF SILVER PRODUCTION AT TEXAS PROJECT LATER THIS YEAR

More information

Paladin Energy. Development & Expansion of the Langer Heinrich Operation in Namibia. June 2009

Paladin Energy. Development & Expansion of the Langer Heinrich Operation in Namibia. June 2009 Paladin Energy Development & Expansion of the Langer Heinrich Operation in Namibia June 2009 1 Disclaimer This presentation includes certain statements that may be deemed forward-looking statements. All

More information

AFRICAN GOLD GROUP, INC. DEFINITIVE FEASIBILITY STUDY FOR KOBADA GOLD PROJECT GENERATES ROBUST ECONOMIC OUTCOME

AFRICAN GOLD GROUP, INC. DEFINITIVE FEASIBILITY STUDY FOR KOBADA GOLD PROJECT GENERATES ROBUST ECONOMIC OUTCOME African Gold Group, Inc. TSX-V: AGG Yonge & Richmond Centre 151 Yonge Street, 11th Floor. Toronto Canada M5C 2W7 Tel: +1 647 775 8538 website : www.africangoldgroup.com AFRICAN GOLD GROUP, INC. DEFINITIVE

More information

ANNUAL FINANCIAL REPORT 30 JUNE 2013

ANNUAL FINANCIAL REPORT 30 JUNE 2013 ANNUAL FINANCIAL REPORT 30 JUNE ABN 40 052 468 569 CORPORATE DIRECTORY Directors Mr Ian Middlemas Non-Executive Chairman Dr James Ross Deputy Chairman Mr Robert Behets Non-Executive Director Company Secretary

More information

For personal use only

For personal use only Korab Resources Limited Gold Operations Update November 2012 Andrej K. Karpinski Executive Chairman Korab Projects BOBRIKOVO MELROSE 1 Korab Gold Projects Other Korab Projects Robust Undervalued Gold Portfolio

More information

Positioned for Production: Exploring for Growth

Positioned for Production: Exploring for Growth ASX Code: AYN Positioned for Production: Exploring for Growth Andrew King, Managing Director May 2010 Pg 1 Disclaimer and Key Information Disclaimer This presentation has been prepared by the Directors

More information

Mako Project, Eastern Senegal Completion of Scoping Study

Mako Project, Eastern Senegal Completion of Scoping Study Toro Gold Ltd Trafalgar Court Admiral Park, Guernsey. GY1 3EL. News Release: 18 th April 2013, Guernsey Mako Project, Eastern Senegal Completion of Scoping Study Toro Gold Ltd ( Toro Gold or the Company

More information

ANNUAL GENERAL MEETING 2015. 30 November 2015

ANNUAL GENERAL MEETING 2015. 30 November 2015 ANNUAL GENERAL MEETING 2015 30 November 2015 Disclaimer Competent Person Statement This presentation may contain some references to forecasts, estimates, assumptions and other forward-looking statements.

More information

Cannon Big Pit Given the Green Light

Cannon Big Pit Given the Green Light ASX Release Tuesday 3 November 2015 Cannon Big Pit Given the Green Light Southern Gold maintains 50% profit share on Cannon Metals X estimate open pit recovered gold +270% to ~50koz Significant cash flow

More information

Armadale Capital Plc Armadale or the Company Robust Project Demonstrated by Mpokoto Feasibility Study HIGHLIGHTS

Armadale Capital Plc Armadale or the Company Robust Project Demonstrated by Mpokoto Feasibility Study HIGHLIGHTS Armadale Capital Plc / Index: AIM / Epic: ACP / Sector: Investment Company 8 February 2016 Armadale Capital Plc ( Armadale or the Company ) Robust Project Demonstrated by Mpokoto Feasibility Study Armadale,

More information

Savannah North Scoping Study Looking into the future 3 February 2016

Savannah North Scoping Study Looking into the future 3 February 2016 Savannah North Scoping Study Looking into the future 3 February 2016 ASX: PAN Disclaimer Cautionary Statements This presentation includes information extracted from Panoramic Resources Limited ASX announcement

More information

BAUXITE RESOURCES LIMITED

BAUXITE RESOURCES LIMITED BAUXITE RESOURCES LIMITED POSITIVE EXPORT DSO BAUXITE SCOPING STUDY RESULTS RECEIVED FOR 100% BRL FORTUNA PROJECT Highlights Existing Mineral Resource and rail logistic chain can support a Direct Shipping

More information

Developing Europe s largest uranium project

Developing Europe s largest uranium project Developing Europe s largest uranium project Delivering sustainable jobs and fuelling Europe s clean energy future Sydney/ Melbourne Institutional Roadshow January 2016 A HIGH IMPACT CLEAN ENERGY INVESTMENT

More information

TURKEY CREEK PIT OPTIMISATION STUDY ADDS 2 YEARS MINE LIFE TO THE LITTLE EVA PROJECT AT CLONCURRY

TURKEY CREEK PIT OPTIMISATION STUDY ADDS 2 YEARS MINE LIFE TO THE LITTLE EVA PROJECT AT CLONCURRY 10 August 2015 ASX: AOH, FSE: A2O TURKEY CREEK PIT OPTIMISATION STUDY ADDS 2 YEARS MINE LIFE TO THE LITTLE EVA PROJECT AT CLONCURRY Estimated oxide and sulphide resources within the optimum pit is 17.3

More information

Queensland Mining Corporation L I M I T E D. Maiden JORC Resources Estimate for Horseshoe Copper Deposit, Duck Creek, South Cloncurry District

Queensland Mining Corporation L I M I T E D. Maiden JORC Resources Estimate for Horseshoe Copper Deposit, Duck Creek, South Cloncurry District ASX Release 12 October 2012 Maiden JORC Resources Estimate for Horseshoe Copper Deposit, Duck Creek, South Cloncurry District Total mineral resource at Duck Creek Project area of 960,000t @ 1.47% Cu (0.2%

More information

De Grey Mining Ltd. Wingina Deeps Drilling Commenced (Turner River Project) Highlights. Turner River Unlocking Shareholder Value

De Grey Mining Ltd. Wingina Deeps Drilling Commenced (Turner River Project) Highlights. Turner River Unlocking Shareholder Value De Grey Mining Ltd ASX RELEASE 5 July 2016 ASX Code DEG ABN 65 094 206 292 Wingina Deeps Drilling Commenced (Turner River Project) Highlights Diamond drilling programme of approximately 1,500m has COMPANY

More information

14 SEPTEMBER 2016 N E W D E V E L O P M E N T S T R A T E G Y A T C L E V E L A N D

14 SEPTEMBER 2016 N E W D E V E L O P M E N T S T R A T E G Y A T C L E V E L A N D 14 SEPTEMBER 2016 N E W D E V E L O P M E N T S T R A T E G Y A T C L E V E L A N D Elementos Limited (ASX: ELT) ( Elementos or the Company ) is pleased to announce the implementation of an enhanced development

More information

QUARTERLY REPORT HIGHLIGHTS. Three Months Ending: 30 September 2012 BUTCHERBIRD MANGANESE:

QUARTERLY REPORT HIGHLIGHTS. Three Months Ending: 30 September 2012 BUTCHERBIRD MANGANESE: QUARTERLY REPORT Three Months Ending: 30 September 2012 ASX CODE: MZM ISSUED SHARES: 67.66M 52 WEEK HIGH: $0.80 52 WEEK LOW: $0.16 CASH ON HAND: $6.13M CONTACT: JUSTIN BROWN Managing Director +61 8 6315

More information

ENCOURAGING PRELIMINARY METALLURGICAL TESTWORK FOR OXIDE HEAP LEACHING AT THE SOUTH HOUNDÉ PROJECT

ENCOURAGING PRELIMINARY METALLURGICAL TESTWORK FOR OXIDE HEAP LEACHING AT THE SOUTH HOUNDÉ PROJECT NEWS RELEASE JANUARY 30, 2014 ENCOURAGING PRELIMINARY METALLURGICAL TESTWORK FOR OXIDE HEAP LEACHING AT THE SOUTH HOUNDÉ PROJECT VANCOUVER, CANADA. Sarama Resources Ltd. ( Sarama or the Company ) is pleased

More information

BUILDING A COPPER COMPANY IN BRAZIL. PDAC Feb - 2014 - TORONTO

BUILDING A COPPER COMPANY IN BRAZIL. PDAC Feb - 2014 - TORONTO BUILDING A COPPER COMPANY IN BRAZIL PDAC Feb - 2014 - TORONTO CORPORATE & GOALS Shares on Issue 1.355B Significant Shareholders Share Price ~Au$0.07* Glencore 15% Market Cap ~Au$95m* BlackRock 5% Cash

More information

Sorby Hills Silver Lead Project

Sorby Hills Silver Lead Project ASX RELEASE Sorby Hills Silver Lead Project Major Milestone Achieved with Environmental Approval As announced on 3 April, the WA Minister for Environment has approved the development of the Sorby Hills

More information

For personal use only

For personal use only ABN 52 077 110 304 31 July 2013 JUNE 2013 QUARTERLY ACTIVITIES REPORT HIGHLIGHTS Record production of 4,422 tonnes of copper in concentrate achieved in June 2013 Record production of 11,116 tonnes of copper

More information

Appendix A Use of Supporting Studies in Process for NI 43-101 Documentation

Appendix A Use of Supporting Studies in Process for NI 43-101 Documentation Appendix A Use of Supporting Studies in Process for NI 43-101 Documentation Foreword Appendix A serves as support documentation within the Best Practice Guidelines for Mineral Processing (BPGMP). It supplements

More information

Keras Resources plc ( Keras or the Company ) Moving Towards First Production in Q2 2016 at Grants Patch Gold Tribute Project, Australia

Keras Resources plc ( Keras or the Company ) Moving Towards First Production in Q2 2016 at Grants Patch Gold Tribute Project, Australia Keras Resources plc / Index: AIM / Epic: KRS / Sector: Mining 14 January 2016 Keras Resources plc ( Keras or the Company ) Moving Towards First Production in Q2 2016 at Grants Patch Gold Tribute Project,

More information

Resources Rising Stars

Resources Rising Stars ASX Code: AYN Resources Rising Stars Andrew King, Managing Director September 2010 Pg 1 Disclaimer and Key Information Disclaimer This presentation has been prepared by the Directors of Alcyone Resources

More information

Quarterly Report December 2015

Quarterly Report December 2015 NEWS RELEASE 29 January 2016 AIM/ASX BKY Overview Quarterly Report December 2015 The Zona 7 deposit has transformed the economics of the Salamanca project and has led to the company aiming to be one of

More information

UPDATE ON SRIG - ALTONA TRANSACTION AGREED WORK AND DRILLING PROGRAMME COMMENCES

UPDATE ON SRIG - ALTONA TRANSACTION AGREED WORK AND DRILLING PROGRAMME COMMENCES 6 October 2015 SX: OH, FSE: 2O UPDTE ON SRIG - LTON TRNSCTION GREED WORK ND DRILLING PROGRMME COMMENCES greed Work Programme ltona Mining Limited s ( ltona or the Company ) and Sichuan Railway Investment

More information

NORTON TAKES UP OPTION TO MINE AND TREAT ORE FROM CASTLE HILL STAGE 1

NORTON TAKES UP OPTION TO MINE AND TREAT ORE FROM CASTLE HILL STAGE 1 ` Dated: 5 th August 2014 NORTON TAKES UP OPTION TO MINE AND TREAT ORE FROM CASTLE HILL STAGE 1 ASX: PXG, PXGOA HIGHLIGHTS Development of Castle Hill Stage 1 with Norton Gold Fields potentially adds a

More information

Mining Indaba Presentation. Capetown, South Africa 8 th 10 th February 2016

Mining Indaba Presentation. Capetown, South Africa 8 th 10 th February 2016 Mining Indaba Presentation Capetown, South Africa 8 th 10 th February 2016 www.birimiangold.com 1 Disclaimer This presentation has been prepared by Birimian Gold Limited (BGS) for general information purposes

More information

AIM: KEFI 6 March 2014. KEFI Minerals Plc. ( KEFI or the Company ) SAUDI ARABIAN EXPLORATION AND DEVELOPMENT UPDATE

AIM: KEFI 6 March 2014. KEFI Minerals Plc. ( KEFI or the Company ) SAUDI ARABIAN EXPLORATION AND DEVELOPMENT UPDATE KEFI Minerals Plc Doğu Akdeniz Mineralleri San. Tic. Ltd. Şti. Cemal Gürsel Cad. Yalı Apt. No:304 K:4 D:9 Karşıyaka İZMİR Tel: +90 232 381 9431 Fax: +90 232 381 9071 Email: info@kefi-minerals.com AIM:

More information

ANNUAL GENERAL MEETING. Investor Presentation 24 November 2015

ANNUAL GENERAL MEETING. Investor Presentation 24 November 2015 ANNUAL GENERAL MEETING Investor Presentation 24 November 2015 Corporate Structure ASX Code: OVR Shares on Issue 205.4 million Top 20 133.0 million (64.8%) Market Capitalisation $1.23 million (share price

More information

NEWS RELEASE. Toronto and Swiss Stock Exchanges Symbol IMZ, Frankfurt Symbol MIW

NEWS RELEASE. Toronto and Swiss Stock Exchanges Symbol IMZ, Frankfurt Symbol MIW NEWS RELEASE February 11, 2008 Toronto and Swiss Stock Exchanges Symbol IMZ, Frankfurt Symbol MIW INTERNATIONAL MINERALS ANNOUNCES 6.2 MILLION OUNCES OF MEASURED AND INDICATED GOLD RESOURCES AND RESULTS

More information

Interim Financial Report for the half-year ended 31 December 2011

Interim Financial Report for the half-year ended 31 December 2011 Interim Financial Report for the half-year ended 31 December 2011 Note: The information contained herein should be read in conjunction with the most recent annual report. Aura Energy Limited Level 4, 66

More information

News release. No. 7/2015 KATANGA MINING ANNOUNCES 2015 SECOND QUARTER RESULTS

News release. No. 7/2015 KATANGA MINING ANNOUNCES 2015 SECOND QUARTER RESULTS No. 7/2015 News release KATANGA MINING ANNOUNCES 2015 SECOND QUARTER RESULTS BAAR, SWITZERLAND, August 12, 2015 Katanga Mining Limited (TSX: KAT) ("Katanga" or the "Company") today announces its financial

More information

For personal use only

For personal use only DECEMBER 2011 Issued 31 January 2012 HIGHLIGHTS INDIAN IRON ORE MINING PROJECT Significant on-site work completed and installation of phase one processing infrastructure underway at Kurnool iron beneficiation

More information

Corporate Presentation February 2016

Corporate Presentation February 2016 Corporate Presentation February 2016 A HIGH IMPACT CLEAN ENERGY INVESTMENT THAT S GOOD FOR THE ENVIRONMENT, THE COMMUNITY AND SHAREHOLDERS. RENEWABLES ALONE CANNOT DELIVER OUR CLEAN ENERGY FUTURE THE UK

More information

ALCYONE TO RAISE $5M TO UNDERPIN TRANSITION TO SILVER PRODUCTION AT TEXAS PROJECT

ALCYONE TO RAISE $5M TO UNDERPIN TRANSITION TO SILVER PRODUCTION AT TEXAS PROJECT ASX ANNOUNCEMENT & MEDIA RELEASE 25 November 2010 ALCYONE TO RAISE $5M TO UNDERPIN TRANSITION TO SILVER PRODUCTION AT TEXAS PROJECT ENTITLEMENT OFFER TO FUND FURTHER EXPLORATION, ACQUISITION OF LONG-LEAD

More information

QUARTERLY ACTIVITIES REPORT FOR PERIOD ENDED 30 SEPTEMBER 2015

QUARTERLY ACTIVITIES REPORT FOR PERIOD ENDED 30 SEPTEMBER 2015 ASX RELEASE ASX:AWV 30 October 2015 QUARTERLY ACTIVITIES REPORT FOR PERIOD ENDED 30 SEPTEMBER 2015 HIGHLIGHTS Pit optimisation and final mine design completed Metallurgical test work completed Engineering

More information

For personal use only

For personal use only Investigator Resources Limited Date: 7 th February 2012 up to 2.25% Ag at the new Paris prospect in South Australia First assays received for new drilling on Paris Line 7 with all three holes assayed returning

More information

Ferrex plc ( Ferrex or the Company ) Acquisition of Gold Mining Company in Australia and Strategic Review

Ferrex plc ( Ferrex or the Company ) Acquisition of Gold Mining Company in Australia and Strategic Review Ferrex plc / Index: AIM / Epic: FRX / Sector: Mining 17 November 2015 Ferrex plc ( Ferrex or the Company ) Acquisition of Gold Mining Company in Australia and Strategic Review Ferrex plc, the AIM quoted

More information

International approaches to mining projects: Due Diligence, Scoping, Pre-Feasibility, Feasibility Studies

International approaches to mining projects: Due Diligence, Scoping, Pre-Feasibility, Feasibility Studies International approaches to mining projects: Due Diligence, Scoping, Pre-Feasibility, Feasibility Studies Sergei Sabanov, PhD, CEng MIMMM Date:10 December 2013 Location: Almaty, Kazakhstan SRK Consulting

More information

Guidelines for the Estimation and Reporting of Australian Black Coal Resources and Reserves

Guidelines for the Estimation and Reporting of Australian Black Coal Resources and Reserves Guidelines for the Estimation and Reporting of Australian Black Coal Resources and Reserves 2001 Edition (as referred to in the Joint Ore Reserves Committee Code ( The JORC Code ) 1999 edition) Prepared

More information

For personal use only

For personal use only ASX Release 28 January 2016 QUARTERLY ACTIVITIES REPORT For the quarter ended 31 December 2015 Level 1, 672 Murray Street West Perth WA 6005 Locked Bag 8 West Perth WA 6872 t. +61 8 9322 1182 f. +61 8

More information

Developing Power Projects in Southern Africa. Annual General Meeting Presentation 20 th November 2015

Developing Power Projects in Southern Africa. Annual General Meeting Presentation 20 th November 2015 Developing Power Projects in Southern Africa Annual General Meeting Presentation 20 th November 2015 2015 Company Highlights AFR now participating in the development of three large-scale power projects

More information

Cummins Range Rare Earths Project

Cummins Range Rare Earths Project Cummins Range Rare Earths Project December 2011 DISCLAIMER The information contained in this presentation is not financial product advice. The presentation is for information purposes and is of a general

More information

DAMANG MINE: SWINGING BACK TO PROFITABILITY ALFRED BAKU EVP & Head of West Africa NG Mining Summit, Cape Town, June 2015

DAMANG MINE: SWINGING BACK TO PROFITABILITY ALFRED BAKU EVP & Head of West Africa NG Mining Summit, Cape Town, June 2015 DAMANG MINE: SWINGING BACK TO PROFITABILITY ALFRED BAKU EVP & Head of West Africa NG Mining Summit, Cape Town, June 2015 CONTENT GLOBAL OPERATIONS WHERE WE VE COME FROM REVERSING THE TREND TRANSFORMATION

More information

Exploration and Development Activity

Exploration and Development Activity For the period ending 30 June 2008 Exploration and Development Activity Over the last year, exploration and development work at the Company s Nullagine Gold Project in Western Australia s eastern Pilbara

More information

NOTE FOR MINING AND OIL & GAS COMPANIES - JU N E 2 0 0 9

NOTE FOR MINING AND OIL & GAS COMPANIES - JU N E 2 0 0 9 NOTE FOR MINING AND OIL & GAS COMPANIES - JU N E 2 0 0 9 A G U I D E T O A I M U K TA X B E N E F I T S 2 AIM Note for Mining, Oil and Gas Companies Contents Introduction 1 Companies to which this Note

More information

Developing Power Projects in Southern Africa. Cape Town Presentation 8 th February 2016

Developing Power Projects in Southern Africa. Cape Town Presentation 8 th February 2016 Developing Power Projects in Southern Africa Cape Town Presentation 8 th February 2016 Company Highlights AFR now participating in the development of three large-scale power projects in Botswana Completion

More information

NEW DRILLING RESULTS FROM THE CLONCURRY PROJECT

NEW DRILLING RESULTS FROM THE CLONCURRY PROJECT 8 October 2015 ASX: AOH, FSE: A2O NEW DRILLING RESULTS FROM THE CLONCURRY PROJECT Excellent results from previously un-assayed drill core. Best intersection of 29.1 metres at 1.41% copper, 0.11g/t gold.

More information

Sangan Iron Ore Mines(SIOM)

Sangan Iron Ore Mines(SIOM) Sangan Iron Ore Mines(SIOM) Abstract Iran has a long history and tradition activities in Mining and related industries. It has the ninth largest minerals reserves in the world. Iran has about 4 billions

More information

Quarterly Activities Report

Quarterly Activities Report ASX Release Thursday 28 January 215 Quarterly Activities Report ASX Code: SAU Issued Shares: 36.53M Directors Greg Boulton AM (Chair) Simon Mitchell (MD) Michael Billing David Turvey Head Office Southern

More information

GEOLOGICAL REINTERPETATION LEADS TO MAJOR DRILL PROGRAM AT JUPITER

GEOLOGICAL REINTERPETATION LEADS TO MAJOR DRILL PROGRAM AT JUPITER GEOLOGICAL REINTERPETATION LEADS TO MAJOR DRILL PROGRAM AT JUPITER Dacian Gold Ltd ( Dacian or the Company ) (ASX:DCN) is pleased to announce that it has completed a major geological review and reinterpretation

More information

For personal use only

For personal use only dmin1138 27 January 2016 Key Points Corporate and Operational Update Savannah - decision made to preserve the value of the remaining Savannah orebody and to move the operation onto care and maintenance

More information

North Atlantic and Rio Tinto Joint Venture Potash Project in Saskatchewan, Canada. Resource Summary

North Atlantic and Rio Tinto Joint Venture Potash Project in Saskatchewan, Canada. Resource Summary North Atlantic and Rio Tinto Joint Venture Potash Project in Saskatchewan, Canada Resource Summary The Canadian Potash Project is located in the central Saskatchewan Potash district that represents nearly

More information

For personal use only

For personal use only ASX Release 27 September 2012 OPTION TO ACQUIRE 560,000oz PEAK HILL GOLD PROJECT RESOURCE AND INVESTMENT NL (ASX: RNI) (RNI or the Company) has reached agreement with Montezuma Mining Company Limited for

More information

Wonawinta Silver Project to be acquired; Mount Boppy development cost and risk cut back

Wonawinta Silver Project to be acquired; Mount Boppy development cost and risk cut back Southern Cross Goldfields Ltd ASX Announcement 5 September 2014 Wonawinta Silver Project to be acquired; Mount Boppy development cost and risk cut back Wonawinta Silver Project (60 M oz) to be acquired

More information

Investing in an Underground Coal Mine in Indonesia

Investing in an Underground Coal Mine in Indonesia Coal Supplying Key Resources into expanding Asian markets Investing in an Underground Coal Mine in Indonesia Disclaimer Forward Looking Statements This presentation includes certain forward looking Statements.

More information

QUARTERLY ACTIVITIES REPORT FOR PERIOD ENDED 31 DECEMBER 2015

QUARTERLY ACTIVITIES REPORT FOR PERIOD ENDED 31 DECEMBER 2015 ASX RELEASE ASX:AWV 29 January 2015 QUARTERLY ACTIVITIES REPORT FOR PERIOD ENDED 31 DECEMBER 2015 HIGHLIGHTS Review of updated pit optimisation undertaken Metallurgical testwork report received confirming

More information

D e c e m b e r 2 0 1 5 Q u a r t e r l y A c t i v i t y R e p o r t

D e c e m b e r 2 0 1 5 Q u a r t e r l y A c t i v i t y R e p o r t 29 January 2016 ASX Release ASX Code: CXX D e c e m b e r 2 0 1 5 Q u a r t e r l y A c t i v i t y R e p o r t Highlights Final stage Pilot Plant progressing well Definitive Feasibility Study on track

More information

Report for the Quarter Ended 30 September 2015

Report for the Quarter Ended 30 September 2015 Report for the Quarter Ended 30 September 2015 ASX: KIS Market Capitalisation $18.2 million Shares on Issue 165.3 million 52 Week High 16.5 cents 52 Week Low 8.9 cents Share Price Board of Directors Johann

More information

Detour Gold Provides New Life of Mine Plan for Detour Lake

Detour Gold Provides New Life of Mine Plan for Detour Lake January 25, 2016 NEWS RELEASE Detour Gold Provides New Life of Mine Plan for Detour Lake Detour Gold Corporation (TSX: DGC) ( Detour Gold or the Company ) is pleased to announce a new life of mine plan

More information

For personal use only

For personal use only 29 January 2016 ASX Announcement December 2015 Quarterly Activities Report Summary New Satimola Limited Sale and Purchase Agreement Signed Financing to Acquire Satimola Limited Secured Revised Consulting

More information

For personal use only

For personal use only Mawson Iron Project PERTH 21 ST NOVEMBER 2015 Dr Gavin England General Manager DISCLAIMER AND COMPETENT PERSONS STATEMENT Slogan XXXX URBANISATION & INDUSTRIALISATION Chinese urbanisation and industrialisation

More information

HIGH GRADE GOLD DRILL RESULTS MT EGERTON PROJECT

HIGH GRADE GOLD DRILL RESULTS MT EGERTON PROJECT July 7 th, 2015 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 HIGH GRADE GOLD DRILL RESULTS MT EGERTON PROJECT RC Drilling has returned shallow high grades at the Gaffney

More information

HIGH GRADE DRILL RESULTS CONTINUE AT THE KYLYLAHTI MINE

HIGH GRADE DRILL RESULTS CONTINUE AT THE KYLYLAHTI MINE 22 August 2013 ASX: AOH, FSE: A2O HIGH GRADE DRILL RESULTS CONTINUE AT THE KYLYLAHTI MINE Upper part of Wombat zone returns excellent drilling intersections: - 29.0m at 4.7% copper - 37.6m at 3.2% copper

More information

Developing the Tanlouka Gold Project. AGM Presentation 18th November 2015

Developing the Tanlouka Gold Project. AGM Presentation 18th November 2015 Developing the Tanlouka Gold Project AGM Presentation 18th November 2015 1 Executive Summary West African Resources Ltd is an ASX and TSXV listed gold development company focussed on Burkina Faso Largest

More information

Quarterly Report Highlights. Ulysses Gold Project, Western Australia. Viking Gold Project, Western Australia

Quarterly Report Highlights. Ulysses Gold Project, Western Australia. Viking Gold Project, Western Australia ASX Announcement Quarterly Activities Report For the Quarter Ended 31 December 2015 29 January 2016 Genesis Minerals Limited ASX Code: GMD Issued Capital 446 million shares 27.2 million options Current

More information

Funds from the placement will be used for working capital requirements, including the completion of the Productora Pre-feasibility Study (PFS).

Funds from the placement will be used for working capital requirements, including the completion of the Productora Pre-feasibility Study (PFS). ASX ANNOUNCEMENT Monday 1 st February 2016 Hot Chili to Raise A$1.6m via Placement to Strategic Shareholders Hot Chili Limited (ASX Code: HCH) is pleased to announce that it has received commitments from

More information

For personal use only

For personal use only EXCELLENT RESULTS FROM EARLY METALLURGICAL TEST WORK ON YANGIBANA SAMPLES Hastings Rare Metals Limited ASX Code: HAS Level 25, 31 Market Street Sydney NSW 2000 PO Box Q128 Queen Victoria Building NSW 1225

More information

September 2015 Quarterly Activities Report

September 2015 Quarterly Activities Report ASX RELEASE 31 OCT 2015 September 2015 Quarterly Activities Report Expansion of Premier JV Gold Mine to 40,000ozpa production rate on track and future production growth plans advanced Highlights Production

More information

Australian Stock Exchange Limited Company Announcements NO. OF PAGES : (5) Level 10, 20 Bond Street SYDNEY NSW 2000

Australian Stock Exchange Limited Company Announcements NO. OF PAGES : (5) Level 10, 20 Bond Street SYDNEY NSW 2000 6 November 2006 Australian Stock Exchange Limited Company Announcements NO. OF PAGES : (5) Level 10, 20 Bond Street SYDNEY NSW 2000 TROPICANA JV (IGO 30%) PROJECT UPDATE KEY POINTS: New significant drill

More information

For personal use only

For personal use only 27 January 2016 Savannah North Scoping Study Positive results demonstrate robust, long life, Ni-Cu-Co Project Highlights Mining Inventory of 6.07Mt @ 1.26%Ni, 0.64% Cu and 0.09% Co for 76,500t Ni, 38,600t

More information

The final quarter of 2015 recorded 7,924 ounces of gold production, giving a year-end total of 32,629 ounces.

The final quarter of 2015 recorded 7,924 ounces of gold production, giving a year-end total of 32,629 ounces. Fourth quarter update on gold operations at Palito and Sao Chico, declaration of commercial production at Sao Chico and extension of loan repayment terms Serabi Gold plc (AIM:SRB, TSX:SBI), the Brazilian

More information

ABN Financial Statements. for the Half-year ended 31 December 2008

ABN Financial Statements. for the Half-year ended 31 December 2008 ABN 92 114 187 978 Financial Statements for the Half-year ended 31 December 2008 Overland Resources Limited CORPORATE DIRECTORY Directors Mr Michael Haynes (Chairman) Mr Hugh Bresser (Managing Director)

More information

Pathway to Production

Pathway to Production Charging forward with Lithium Pathway to Production 8th Lithium Supply & Markets Conference 24 26 May 2016 Las Vegas Disclaimer This presentation has been prepared by Altura Mining Limited ( Altura or

More information

RED 5 Limited The next gold producer

RED 5 Limited The next gold producer The next gold producer May 2011 Company highlights Target production Sept 2011 quarter at Siana Gold project Construction 0% complete, all plant equipment in country Forecast cash costs sub $400 per ounce,

More information

Press Release 29 th January 2016

Press Release 29 th January 2016 Press Release 29 th January 2016 DECEMBER 2015 QUARTERLY REPORT West African Resources Limited (ASX: WAF) is pleased to report activities on its 100%-owned gold and copper-gold projects in Burkina Faso,

More information

Continental Gold Announces a Positive Preliminary Economic Assessment for the Buriticá Project

Continental Gold Announces a Positive Preliminary Economic Assessment for the Buriticá Project Continental Gold Announces a Positive Preliminary Economic Assessment for the Buriticá Project Toronto, Ontario, November 17, 2014 - Continental Gold Limited (TSX:CNL; OTCQX:CGOOF) ("Continental" or the

More information

A Battery Technology focused Graphite Company

A Battery Technology focused Graphite Company February 2016 Taking Graphite to New Levels A Battery Technology focused Graphite Company ASX: MTA www.metalsofafrica.com.au Disclaimer & Competent Person Statement Statements and material contained in

More information

QUARTERLY REPORT FOR THE PERIOD TO 31 MAY 2012

QUARTERLY REPORT FOR THE PERIOD TO 31 MAY 2012 QUARTERLY REPORT FOR THE PERIOD TO 31 MAY 2012 Metals Finance Limited (ASX: MFC) is pleased to provide its Quarterly Activities Report for the three month period ending 31 May 2012. HIGHLIGHTS Separate

More information

Metallurgy Test Work Confirms Commercial Potential of Kambale Graphite Deposit

Metallurgy Test Work Confirms Commercial Potential of Kambale Graphite Deposit 3 rd September 2012 ASX Announcement Metallurgy Test Work Confirms Commercial Potential of Kambale Graphite Deposit Castle Minerals Limited (ASX: CDT), the Ghana gold explorer, is pleased to announce that

More information

Candelaria and Ojos del Salado Chile

Candelaria and Ojos del Salado Chile TSX : LUN OMX : LUMI 2016 Candelaria Key Facts Open Pit and Underground Mine Copper, gold, and silver 2016 estimate 124,000-128,000 tonnes copper Cash costs of $1.45 per lb copper after by-product credits

More information

C o r p o r a t e P r e s e n t a t i o n A u g u s t 2 0 1 5

C o r p o r a t e P r e s e n t a t i o n A u g u s t 2 0 1 5 C o r p o r a t e P r e s e n t a t i o n A u g u s t 2 0 1 5 Forward Looking Statements This presentation includes certain estimates, projections and forward looking statements within the meaning of Section

More information

Q4 & FY2015 OPERATING HIGHLIGHTS. January 29, 2016

Q4 & FY2015 OPERATING HIGHLIGHTS. January 29, 2016 Q4 & FY2015 OPERATING HIGHLIGHTS January 29, 2016 1 FORWARD-LOOKING STATEMENTS This presentation contains certain statements that constitute forward-looking information within the meaning of applicable

More information

Accounting for stripping costs in the production phase costs of waste removal and the associated benefit

Accounting for stripping costs in the production phase costs of waste removal and the associated benefit IFRIC Meeting Agenda reference 2A Staff Paper Date March 2010 Project Topic xtractive Activities Accounting for stripping costs in the production phase costs of waste removal and the associated benefit

More information

TIGER RESOURCES LTD ACN 077 110 304

TIGER RESOURCES LTD ACN 077 110 304 TIGER RESOURCES LTD ACN 077 110 304 1st Floor, 8 Parliament Place, West Perth WA 6005 PO Box 1618, West Perth WA 6872 Tel: (08) 9481-7833 Fax: (08) 9481-7835 Email: tiger@tigerez.com Website: www.tigerez.com

More information

Investment && projects

Investment && projects Investment & projects We assigned US$ 3.34 billion to our investment portfolio in. We are the company that invests the most in Chile. Between and 2019 we will transfer over US$ 20.0 billion into our investment

More information

PALADIN ENERGY LTD ACN 061 681 098

PALADIN ENERGY LTD ACN 061 681 098 PALADIN ENERGY LTD ACN 061 681 098 7 February 2014 ASX Market Announcements Australian Securities Exchange 20 Bridge Street SYDNEY NSW 2000 By Electronic Lodgement Dear Sir/Madam Suspension of Production

More information

December, 2015 Quarterly Report First Graphite makes strong progress in strategy to be major supplier of high-grade graphite and graphene in 2016

December, 2015 Quarterly Report First Graphite makes strong progress in strategy to be major supplier of high-grade graphite and graphene in 2016 29 January 2016 First Graphite Limited ACN 007 870 760 ABN 50 007 870 760 Registered Office Suite 3 9 Hampden Road Nedlands WA 6009 Tel +61 1300 660 448 Fax +61 1300 855 044 Directors Warwick Grigor Craig

More information

ST GEORGE ACQUIRES NICKEL SULPHIDE PROJECTS

ST GEORGE ACQUIRES NICKEL SULPHIDE PROJECTS ASX / MEDIA RELEASE 18 September 2015 HIGHLIGHTS: ST GEORGE ACQUIRES NICKEL SULPHIDE PROJECTS St George acquires 100% of the Hawaii and Mt Alexander North nickel sulphide exploration projects from BHP

More information

Establishing the feasibility of your proposed mining venture

Establishing the feasibility of your proposed mining venture RUPPRECHT, S. Establishing the feasibility of your proposed mining venture. International Platinum Conference Platinum Adding Value, The South African Institute of Mining and Metallurgy, 2004. Establishing

More information

What s Down the Track? Kalgoorlie CCI

What s Down the Track? Kalgoorlie CCI What s Down the Track? Kalgoorlie CCI 27 th October 2011 Disclaimer This presentation has been prepared by Toro Energy Limited ( Toro ). The information contained in this presentation is a professional

More information

COMPANY PRESENTATION. Cape Town 2016

COMPANY PRESENTATION. Cape Town 2016 COMPANY PRESENTATION Cape Town 2016 DISCLAIMER The purpose of this presentation is to provide general information about OreCorp Limited (Company). It is not recommended that any person makes any investment

More information

KATANGA MINING ANNOUNCES 2013 YEAR END RESULTS AND COMMITMENT OF GLENCORE TO EXTEND AND INCREASE LOAN FACILITIES

KATANGA MINING ANNOUNCES 2013 YEAR END RESULTS AND COMMITMENT OF GLENCORE TO EXTEND AND INCREASE LOAN FACILITIES No. 3/2014 News release KATANGA MINING ANNOUNCES 2013 YEAR END RESULTS AND COMMITMENT OF GLENCORE TO EXTEND AND INCREASE LOAN FACILITIES ZUG, SWITZERLAND, March 3, 2014 Katanga Mining Limited (TSX: KAT)

More information

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS PROPOSED PHASE 2 EXPANSION OF THE TRANSNET IRON ORE HANDLING FACILITY, SALDANHA

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS PROPOSED PHASE 2 EXPANSION OF THE TRANSNET IRON ORE HANDLING FACILITY, SALDANHA ENVIRONMENTAL IMPACT ASSESSMENT PROCESS PROPOSED PHASE 2 EXPANSION OF THE TRANSNET IRON ORE HANDLING FACILITY, SALDANHA BACKGROUND INFORMATION DOCUMENT 1 BACKGROUND Transnet Limited s (Transnet) existing

More information

For personal use only

For personal use only 10 May 2011 ASX: GRR Grange Resources Limited Australia s leading magnetite producer Successful Completion of Southdown Project PFS Grange Resources Limited ( Grange or the Company ) is pleased to announce

More information