1 Use of ALARP in Naviair Sten Bertram Winther Head of Project Facilitation October 2013
2 Agenda Sten Bertram Winther, Naviair ALARP ALARP in operation ALARP in system development Conclusion
3 Naviair IFR Operations En-Route
4 Airspace
5 Airspace FL285 UTA, Upper Control Area FL95 CTA, Control Area 1500ft GDR TMA CTR TMA CTR
6 Naviair
7 Naviair Technical Sites Sindal ATC ILS VOR/DME Aalborg Radar Siri RAMME Bovbjerg Karup Tinghøj Tirstrup Vejrradar Voice kommunikation Data kommunikation Tyra Børsmose LEMME VESTA Esbjerg VAMDU Rømø Skrydstrup Billund Kolding ODIN TRANO Lerbjerg KORSA Slots Bjergby Kulsbjerg NORA (nedlægges) BELLA Roskilde CODAN København Sturup Stevns RØNNE 6 stk. ALSIE Skrøbelev
8 Safety Public Perception 80 % af alle flyulykker sker inden for få minutter under flyvningen især inden for de første tre minutter samt de sidste seks at langt de fleste flyulykker sker risikoen for, at du omkommer i en fly ulykke er en til 11 millioner scorer SAS syv ud af syv stjerner Norwegian, Ryanair og EasyJet fik fem ud af syv
9 Safety Freedom from unacceptable risk
10 Protection Safety space Bankruptcy Catastrophe Production
11 Definition: Functional System ATC ATCOs Maintenance Procedures People Engineers ATM Equipment Network TWR Building VCS
12 Processes and outcomes Causes and consequences of operational errors are not linear in their magnitude
13 Severity ALARP As Low As Reasonably Practicable AFARP EC 1035/2011 Probability - hazard/year Hazard Probability Hazard Risk Severity Often 3E+00 or more Several times during the lifetime of the system 3E+00 to 2E-01 Probably during the lifetime of the system 2E-01 to 1E-02 Probably not 1E-02 to 3E-05 Unlikely to occur Less than 3E-05 I II III IV V Accident 1 A A AA A AA A A A A C Serious incident 2 A A B C D Major incident 3 A B C D D Significant incident 4 B C D D D No immediate effect 5 C D D D D Naviair Management System
14 Hazard hazard means any condition, event, or circumstance which could induce an accident EC 1035:2011;
15 Hazard
16 Effect, EC 1035/2011 Common Requirements COST???
17 Probability, BL 7-25 Bestemmelser om risikovurdering og risikoreduktion i lufttrafikstyring (2003) 1/year 2/10year 1/100year 3/ year <3/ year 4 years 13 years 65 years 100 years years
18 Risk Perception Future Trends Development Mirror Past
19 Risk Perception Future Trends Enviroment, socilogy, trafic, technical. Development Enviroment, socilogy, trafic, technical. Mirror Past
20 Risk High Risk Unacceptable region Tolerable region ALARP Acceptable region Low risk Regulation System req Acceptable risk
21 Bow-tie Model People Preventive Hazard Safety nets Effect Procedure Equipment SW Barriere System Surroundings
22 Safety Requirements Safety Targets Bow-tie Model Causes Mitigations PSSA Preliminary System Safety Assessment D1 E1 Hazard Mitigations FHA Functional Hazard Assessment Effect Effect A SC5 D2 E2 H Effect B SC4 D3 E3 Effect C SC3 E Ph Safety Objective Pe Effect D SC2 Effect E SC1 SSA System Safety Assessment
23 Decision-making-proces Accept of Hazard or Severity or Likelihood or Risk? Model or evaluation or gut feeling! Who is the decision maker! Decision-makers wants: Objectives Cost Alternatives Evidence Benefit Logic Is this provided by the Risk management process?
24 Safety Assessment ATM System Hazard Effect Safety Requirement Ph Pe FTA RBD FMEA FMECA SWAL.. Safety Objective Quantitative model Semi-quantitative model Semi-precriptive model Fixed-precriptive model Safety Target
25 Risk Identify hazard Identify the effect Assess the likelihood Find the risk Do something! Evaluate the risk Accept the risk Not OK OK
26 Perspective System Developer Perspective Fault External Event System Failure Service User Perspective Hazard Incident Accident Potential Consequences Causes of Failures
27 ALARP in operation
28 ALARP in system development Safety objectives/requirements Radar Safety requirements Radar Display System
29 Examples Security, Not the same RCM Cost: CPH 98 Mkr Mkr 2010 Use of different RCM, eg. Canada - Iceland Denmark Implementation of software mitigations, CPDLC Controller Pilot Data Link Communication Unknown enviroment Ash cloud 2010 Network dependence TDC MPLS failure SAS Dash 8
30 WAM, Wide Area Multilateration
31 Next call.
32 Conclusion Correlations between mitigations effect of mitigations Barrier erosion Is cost (mitigations effect) identifiable Quantitative Qualitative argumentation Define apportionment and assumptions Benefit (success case) Design to avoid instead to control faults Resilient Design Complex systems Design As Simple As Reasonably Practicable Barriere erosion Poor design?
33 Questions.
Information to VFR pilots
Information to VFR pilots Information to VFR pilots This publication has been prepared by Naviair with the purpose of focusing on flight safety and clarifies topics, which are important to know for VFR
More informationControlling Risks Risk Assessment
Controlling Risks Risk Assessment Hazard/Risk Assessment Having identified the hazards, one must assess the risks by considering the severity and likelihood of bad outcomes. If the risks are not sufficiently
More informationFunctional Hazard Assessment (FHA) Report for Unmanned Aircraft Systems
Distribution: EUROCONTROL Ebeni Holger Matthiesen Hayley Burdett Unmanned Aircraft System (UAS) Safety Case Development Chris Machin Joanne Stoker Don Harris Alan Simpson Functional Hazard Assessment (FHA)
More informationSafety Risk Impact Analysis of an ATC Runway Incursion Alert System. Sybert Stroeve, Henk Blom, Bert Bakker
Safety Risk Impact Analysis of an ATC Runway Incursion Alert System Sybert Stroeve, Henk Blom, Bert Bakker EUROCONTROL Safety R&D Seminar, Barcelona, Spain, 25-27 October 2006 Contents Motivation Example
More informationWHICH AIR TRAFFIC CONTROLLER TO CONTACT
WHICH AIR TRAFFIC CONTROLLER TO CONTACT 1. Introduction This article is written in order to explain to all beginners in the IVAO network the basics for any pilot to contact the correct air traffic controller.
More informationRISK MANAGEMENT FOR INFRASTRUCTURE
RISK MANAGEMENT FOR INFRASTRUCTURE CONTENTS 1.0 PURPOSE & SCOPE 2.0 DEFINITIONS 3.0 FLOWCHART 4.0 PROCEDURAL TEXT 5.0 REFERENCES 6.0 ATTACHMENTS This document is the property of Thiess Infraco and all
More informationRisk Assessment and Management. Allen L. Burgenson Manager, Regulatory Affairs Lonza Walkersville Inc.
Risk Assessment and Management Allen L. Burgenson Manager, Regulatory Affairs Lonza Walkersville Inc. Standard Disclaimer Standard Disclaimer: This presentation is the opinion of the presenter, and does
More information3.0 Risk Assessment and Analysis Techniques and Tools
3.0 Risk Assessment and Analysis Techniques and Tools Risks are determined in terms of the likelihood that an uncontrolled event will occur and the consequences of that event occurring. Risk = Likelihood
More informationRisk Assessment for Medical Devices. Linda Braddon, Ph.D. Bring your medical device to market faster 1
Risk Assessment for Medical Devices Linda Braddon, Ph.D. Bring your medical device to market faster 1 My Perspective Work with start up medical device companies Goal: Making great ideas into profitable
More informationThe SPE Foundation through member donations and a contribution from Offshore Europe
Primary funding is provided by The SPE Foundation through member donations and a contribution from Offshore Europe The Society is grateful to those companies that allow their professionals to serve as
More informationCastor Demo Simulations
Castor Demo Simulations Presentation for SESAM Stefan Nygren Stockholm, Jan 25, 2007 Castor Demo The real challenge is not to make UAV s fly, but to qualify them for operating in controlled airspace. Castor
More informationThe International Scenario
National ADS-B Implementation Programme 1 The International Scenario The ADS-B implementation programme is carried out in an European context ü Related to SESAR Implementation Package 1 (IP1) 2008 2013
More informationISO 26262 Introduction
ISO 26262 Introduction Prof. Christian Madritsch 2012 Table of Contents Structure of ISO 26262 Management of Functional Safety Product Development System Level Product Development Hardware Level Product
More informationGuidance note. Risk Assessment. Core concepts. N-04300-GN0165 Revision 4 December 2012
Guidance note N-04300-GN0165 Revision 4 December 2012 Risk Assessment Core concepts The operator of an offshore facility must conduct a detailed and systematic formal safety assessment, which includes
More informationchapter 9 conduct a climate change
CONDUCT A CLIMATE RESILIENCY STUDY The following chapters recommend how to reach CRC Milestone Two, Conduct a Climate Resiliency Study. 2 MILESTONE Chapter 8: Conduct a Climate Change Vulnerability Assessment
More informationDo you know exactly how the communication with an aerodrome controller in a foreign country should look like? No? If not, this list might help you.
Dear IVAO-Pilots, Do you know exactly how the communication with an aerodrome controller in a foreign country should look like? No? If not, this list might help you. As a controller I experienced pilots
More informationProviding Safety and Reliability with PBN Guy Greider HUGHES PROPRIETARY
Providing Safety and Reliability with PBN Guy Greider Layout plan for integrated fully supported low level PBN airspace Providing Safety and Reliability with PBN Helicopter Accident Rate Vertical Flight
More informationCertificate of Compliance
No. 0V151007.CFMTW07 Brushless Dc motor FL42BLS01(CE), FL16, FL20, FL22, FL24, FL28, FL32, FL33, FL36, FL42, FL45 EN 61000-6-3:2007+A1:2011, EN 61000-6-1:2007, EN 55014-2:1997+A1:2001+A2:2008, No. 0V151007.CFMTW08
More informationPerformance management Identification of metrics
WKSP/ASBU/NAIROBI/2013-PPT/10 Performance management Identification of metrics Air Navigation Bureau WORKSHOP ON ASBU FRAMEWORK: ALIGNMENT OF REGIONAL AND NATIONAL PERFORMANCE PLANS, PLANNING, 14 October
More informationUniversity of Paderborn Software Engineering Group II-25. Dr. Holger Giese. University of Paderborn Software Engineering Group. External facilities
II.2 Life Cycle and Safety Safety Life Cycle: The necessary activities involving safety-related systems, occurring during a period of time that starts at the concept phase of a project and finishes when
More informationGuidance for Industry: Quality Risk Management
Guidance for Industry: Quality Risk Management Version 1.0 Drug Office Department of Health Contents 1. Introduction... 3 2. Purpose of this document... 3 3. Scope... 3 4. What is risk?... 4 5. Integrating
More informationTÜV FS Engineer Certification Course www.silsupport.com www.tuv.com. Being able to demonstrate competency is now an IEC 61508 requirement:
CC & technical support services TÜV FS Engineer Certification Course www.silsupport.com www.tuv.com Being able to demonstrate competency is now an IEC 61508 requirement: CAPITALISE ON EXPERT KNOWLEDGE
More informationAirspace classification change
Airspace classification change With effect from 06 March 2014 the airspace classification and configuration of the Channel Islands Airspace will be changed: The Channel Islands Control Zone (CTR) will
More informationSpace Applications and Technologies Expo Rome, Italy February 4 6, 2010
Space Applications and Technologies Expo Rome, Italy February 4 6, 2010 Overview of the EUROCONTROL UAS Integration Activity Anders Hallgren EUROCONTROL Manager ATM Procedures 1 European Organisation for
More informationOccupational safety risk management in Australian mining
IN-DEPTH REVIEW Occupational Medicine 2004;54:311 315 doi:10.1093/occmed/kqh074 Occupational safety risk management in Australian mining J. Joy Abstract Key words In the past 15 years, there has been a
More informationTÜV Rheinland Functional Safety Engineer Certificate (Process Hazard & Risk Analysis)
TÜV Rheinland Functional Safety Engineer Certificate (Process Hazard & Risk Analysis) Controlling risks within major hazard enterprises requires a robust process safety management (PSM) system and the
More informationAnvendelse af vejrradar til forudsigelse af kraftig regn
Anvendelse af vejrradar til forudsigelse af kraftig regn (Baltrad.eu) Michael R. Rasmussen Dept. of Civil Engineering Aalborg University, Denmark mr@civil.aau.dk Michael R. Rasmussen Dept. of Civil Engineering,
More informationTraining program for S2 (TWR) rating
Training program for S2 (TWR) rating Introduction This is the official Vatsim Scandinavia training program for students training for the TWR (S2) Rating. Each mentor is expected to take his student through
More informationSFJCCAD2 Promote business continuity management
Overview This unit is about providing advice and assistance on business continuity management, including general advice for the business and voluntary sectors, and specific advice and assistance to individual
More informationNova Scotia EMO. Hazard Risk Vulnerability Assessment (HRVA) Model. Guidelines for Use. October, 2010
Nova Scotia EMO Hazard Risk Vulnerability Assessment (HRVA) Model Guidelines for Use October, 2010 EMO NS Hazard Risk Vulnerability Assessment Model Page 1 of 10 Table of Contents 1. Background 2. Definitions
More informationUK AIRSPACE Introduction
UK AIRSPACE Introduction The UK has now adopted the ICAO system for naming of airspace types from A to G. However in the UK there is at present no Class C airspace. Classes A to E are called Controlled
More informationSafety Management Systems (SMS) guidance for organisations
Safety and Airspace Regulation Group Safety Management Systems (SMS) guidance for organisations CAP 795 Published by the Civil Aviation Authority, 2014 Civil Aviation Authority, CAA House, 45-59 Kingsway,
More informationEuropean ADS-B Regulation
ADS-B Workshop SP/22 European ADS-B Regulation John Law Surveillance Programmes Manager EUROCONTROL Regulators Workshop Jakarta Aug 2010 European Regulation The European Organisation for the Safety of
More informationTRAINING IN SAFETY MANAGEMENT SYSTEMS
TRAINING IN SAFETY MANAGEMENT SYSTEMS ARAB CIVIL AVIATION CONFERENCE Amman, Jordania 19-23 July 2009 1 Welcome to Safety Management System Workshop 2 Speakers: CHRISTER PRAHL ATM Safety Expert Electronic
More informationCurriculum for The Master of Science in Technology in Risk and Safety Management
The Faculty of Engineering and Science The Board of Studies for Civil Engineering Curriculum for The Master of Science in Technology in Risk and Safety Management Aalborg University 2014 Version 2, november
More informationSAFE SOFTWARE FOR SPACE APPLICATIONS: BUILDING ON THE DO-178 EXPERIENCE. Cheryl A. Dorsey Digital Flight / Solutions cadorsey@df-solutions.
SAFE SOFTWARE FOR SPACE APPLICATIONS: BUILDING ON THE DO-178 EXPERIENCE Cheryl A. Dorsey Digital Flight / Solutions cadorsey@df-solutions.com DIGITAL FLIGHT / SOLUTIONS Presentation Outline DO-178 Overview
More informationRISK ASSESSMENT AND USE OF RISK ACCEPTANCE CRITERIA FOR THE REGULATION OF DANGEROUS SUBSTANCES
RISK ASSESSMENT AND USE OF RISK ACCEPTANCE CRITERIA FOR THE REGULATION OF DANGEROUS SUBSTANCES Eivind Okstad and Per Hokstad SINTEF Industrial Management, Dept. of Safety and Reliability, N-7465 Trondheim,
More informationLONDON SOUTHEND AIRPORT CLASS D CONTROLLED AIRSPACE GUIDE
CLASS D CONTROLLED AIRSPACE GUIDE Introduction From the 2 nd of April 2015 London Southend Airport (LSA) will be implementing Class D (CAS). This airspace is made up of a Control Zone (CTR) and Control
More informationICAO Standard Phraseology A Quick Reference Guide for Commercial Air Transport Pilots
ICAO Standard Phraseology A Quick Reference Guide for Commercial Air Transport Pilots Communication error is the biggest causal factor in both level busts and runway incursions in Europe. This document
More informationRAM Analyses do we expect too little?
RAM Analyses do we expect too little? ESRA Seminar Praktisk bruk av RAM og produksjonstilgjengelighetsanalyser Siegfried Eisinger, DNV GL January 2015 1 SAFER, SMARTER, GREENER RAMS Definitions [EN 50126]
More informationRISK 2014. Case Study: Safety in Design Process Development. Engineering Management Systems Engineering Management Systems
RISK 2014 1 Case Study: Safety in Design Process Development Mike Hurd, representing 2 Contact details 3 Engineering.Systems.Management @gmail.com Mike Hurd 0432 858 958 This is what it is all about 4
More informationBest Practice In A Change Management System
Quality & Compliance Associates, LLC Best Practice In A Change Management System President Quality & Compliance Associates, LLC Change Control and Its Role in a Continuous Improvement Environment 3 Benefits
More informationPhase A Aleutian Islands Risk Assessment. Options and Recommended Risk Matrix Approach. April 27, 2010
Phase A Aleutian Islands Risk Assessment Options and Recommended Risk Matrix Approach April 27, 2010 Agenda for Risk Matrix Discussion Introductions Where we are in AIRA Phase A Risk Matrix Background
More informationSafety Management Challenges for Aviation Cyber Physical Systems
Safety Management Challenges for Aviation Cyber Physical Systems Prof. R. John Hansman & Roland Weibel MIT International Center for Air Transportation rjhans@mit.edu, weibel@mit.edu Challenges Target Level
More informationAdapting to air traffic growth in Europe
Comment volerons-nous en 2050?/ Flying in 2050 Conference Session VII Air Traffic Management Adapting to air traffic growth in Europe Pierre ANDRIBET EUROCONTROL SESAR and Research Deputy Director Comment
More informationThe use of statistical problem solving methods for Risk Assessment
The use of statistical problem solving methods for Risk Assessment Citti P., Delogu M., Giorgetti A. University of Florence. DMTI, Department of Mechanics and Industrial Technology Via Santa Marta, 3 50121
More informationCHAPTER 7. AIRSPACE 7.1 AFFECTED ENVIRONMENT
CHAPTER 7. AIRSPACE 7.1 AFFECTED ENVIRONMENT 7.1.1 Definition of Resource Airspace management is defined as directing, controlling, and handling flight operations in the volume of air that overlies the
More informationMIL AIP DENMARK TACTICAL AIR STAFF DENMARK FLIGHT INFORMATION
Address: Herningvej 30 DK-7470 Karup J D E N M A R K Telephone: +45 7284 1221 AFTN: EKMCYOYX E-mail: ftk-fli@mil.dk www.flv.dk/milais MIL AIP DENMARK TACTICAL AIR STAFF DENMARK FLIGHT INFORMATION Amendment
More informationSafety and Security Driven Design. Unmanned Aircraft-National Airspace System Integration Case Study
2 nd uropean STAMP Workshop, 2014 Safety and Security Driven Design. Unmanned Aircraft-National Airspace System Integration Case Study Kip Johnson Prof. Nancy eveson See accompanying abstract: Johnson,
More informationIntroduction to Safety Cases
Introduction to Safety Cases Tim Kelly E-mail: tim.kelly@cs.york.ac.uk High Integrity Systems Engineering Group Department of Computer Science Historical Context Overview Definitions Role of Argument &
More informationCRES - a Scientific Platform for Sharing Climate Change Related Knowledge in Denmark
CRES - a Scientific Platform for Sharing Climate Change Related Knowledge in Denmark Jens Hesselbjerg Christensen Danish Meteorological Institute http://cres-centre.net Outline Something about communicating
More informationImproved Utilization of Self-Inspection Programs within the GMP Environment A Quality Risk Management Approach
Improved Utilization of Self-Inspection Programs within the GMP Environment A Quality Risk Management Approach Barbara Jeroncic Self-inspection is a well-established and vital part of the pharmaceutical
More informationFuld Skolerapport for Søhusskolen, i Odense kommune, for skoleår 2013/2014 for klassetrin(ene) 9. med reference Tilsvarende klassetrin i kommunen
Side 1 af 41 Side 2 af 41 Side 3 af 41 Side 4 af 41 Side 5 af 41 Side 6 af 41 Side 7 af 41 Side 8 af 41 Side 9 af 41 Side 10 af 41 Side 11 af 41 Side 12 af 41 Side 13 af 41 Side 14 af 41 Side 15 af 41
More informationFuld Skolerapport for Hunderupskolen, i Odense kommune, for skoleår 2013/2014 for klassetrin(ene) 7. med reference Tilsvarende klassetrin i kommunen
Side 1 af 43 Side 2 af 43 Side 3 af 43 Side 4 af 43 Side 5 af 43 Side 6 af 43 Side 7 af 43 Side 8 af 43 Side 9 af 43 Side 10 af 43 Side 11 af 43 Side 12 af 43 Side 13 af 43 Side 14 af 43 Side 15 af 43
More informationAn Integrated Operational Risk Management Framework for Power Generation
An Integrated Operational Risk Management Framework for Power Generation Ir Stephen W.K. Pang Acting Plant Risk Manager Generation Business Group CLP Power Hong Kong Limited Introduction Excellent risk
More informationDesigning an Effective Risk Matrix
Designing an Effective Risk Matrix HENRY OZOG INTRODUCTION Risk assessment is an effective means of identifying process safety risks and determining the most cost-effective means to reduce risk. Many organizations
More informationFERC Engineering Guidelines Risk-Informed Decision Making
FERC Engineering Guidelines Risk-Informed Decision Making Chapter R1 Introduction to Risk-Informed Decision Making Chapter R1, Risk-Informed Decision Making Table of Contents Chapter R1 Introduction to
More informationAsset integrity process safety management Involving the workforce
Shell Global Solutions Asset integrity process safety management Involving the workforce Task Force ZERO Annual Safety Conference Esbjerg, Denmark, March 2010 Diederick Bax, Shell Global Solutions International
More informationQUALITY RISK MANAGEMENT (QRM): A REVIEW
Lotlikar et al Journal of Drug Delivery & Therapeutics; 2013, 3(2), 149-154 149 Available online at http://jddtonline.info REVIEW ARTICLE QUALITY RISK MANAGEMENT (QRM): A REVIEW Lotlikar MV Head Corporate
More informationSafety and Airspace Regulation Group
Safety and Airspace Regulation Group 27 April 2016 Policy Statement Policy for ATS Provision Within Controlled Airspace by Units not Notified as the Controlling 1 Introduction 1.1 The purpose of this policy
More informationOperational Risk Analysis of Predator/Reaper Flight Operations in a Corridor between Cannon AFB and Melrose Range (R-5104A)
Operational Risk Analysis of Predator/Reaper Flight Operations in a Corridor between Cannon AFB and Melrose Range (R-5104A) Executive Summary This assessment was prepared to support the 27 th Operations
More informationIRM CERTIFICATE AND DIPLOMA OUTLINE SYLLABUS
IRM CERTIFICATE AND DIPLOMA OUTLINE SYLLABUS 1 Module 1: Principles of Risk and Risk Management Module aims The aim of this module is to provide an introduction to the principles and concepts of risk and
More informationFAA-P-8740-52 AFS-820-2000
S1 Introduction You fly in actual instrument weather conditions and make enough approaches to keep "current," take your flight review from a good instructor, know the "Normal" and "Emergency" procedure
More informationFlyntGroup.com. Enterprise Risk Management and Business Impact Analysis: Understanding, Treating and Monitoring Risk
Enterprise Risk Management and Business Impact Analysis: Understanding, Treating and Monitoring Risk 2012 The Flynt Group, Inc., All Rights Reserved FlyntGroup.com Enterprise Risk Management and Business
More information4. Critical success factors/objectives of the activity/proposal/project being risk assessed
ARTC Risk Management Work Instruction 2: 1. Conduct Risk Assessment Workshop This Work Instruction provides general guidelines for conducting a generic Risk Assessment workshop. The instructions supplement
More informationFault Tree Analysis (FTA) and Event Tree Analysis (ETA)
Fault Tree Analysis (FTA) and Event Tree Analysis (ETA) It is easy to get confused between these two techniques. Indeed, the two are in fact complimentary (and are often used together) but focus on opposite
More informationDefining and operationalizing the barrier concept
The human contribution Sondre Øie Introduction Sondre Øie - Human Factors & risk management consultant at DNV Topics & focus in this presentation - What is a barrier? - Operationalization - The human contribution
More informationasuresign Aero (NATEP Grant MA005)
asuresign Aero (NATEP Grant MA005) WP2 Workshop: Identification of Needs for Tool Support in Meeting Aircraft Avionics Systems, Hardware & Software Certification Standards Dr Chris Harper Systems & Safety
More informationMemorandum Date: February 5, 2014
Federal Aviation Administration Memorandum Date: February 5, 2014 To: From: Subject: Memo No.: See Distribution List David W. Hempe, Manager, Aircraft Engineering Division, AIR-100 James D. Seipel, Manager,
More informationENR 5 NAVIGATIONAL WARNINGS
MIL AIP DENMARK ENR 5.1-1 12 FEB 2009 ENR 5 NAVIGATIONAL WARNINGS ENR 5.1 PROHIBITED, RESTRICTED AND DANGER AREAS 1. GENERAL All airspace within which the operation of airspace may, for one reason or another
More informationAdvanced Data Link Infrastructure Solution for Next Generation of Air Traffic Management
Advanced Data Link Infrastructure Solution for Next Generation of Air Traffic Management The Air Navigation Service Providers (ANSPs) are primarily responsible for operational Communication (Data and Voice)
More informationRulemaking Directorate. Preliminary Regulatory Impact Assessment Explanatory Note 2012/2013
Rulemaking Directorate Preliminary Regulatory Impact Assessment Explanatory Note 2012/2013 1 What is the purpose of the Pre-RIA?... 2 2 What is new?... 2 3 Rulemaking procedure and workflow... 3 4 Description
More informationA Risk Management Standard
A Risk Management Standard Introduction This Risk Management Standard is the result of work by a team drawn from the major risk management organisations in the UK, including the Institute of Risk management
More informationFMEA and FTA Analysis
FMEA and FTA Analysis Why it is Coming to Your Hospital and Your Laboratory Tina A. Krenc Director, R&D Phase Systems Abbott Laboratories 1 Agenda Background on requirements for risk management Tools to
More informationInternational Diploma in Risk Management Syllabus
International Diploma in Risk Management Syllabus Module 1: Principles of Risk and Risk Management The aim of this module is to provide an introduction to the principles and concepts of risk and risk management.
More informationRisk Management and the Impact of EN ISO 14971:2012 Annex Z
Risk Management and the Impact of EN ISO 14971:2012 Annex Z BSI 2014 Medical Device Mini-Roadshow Ibim Tariah Ph.D Technical Director, Healthcare Solutions Copyright 2014 BSI. All rights reserved. 1 Risk
More informationADVISORY CIRCULAR ON SAFETY RISK ASSESSMENT AND MITIGATION
Page 1 of 14 1. PURPOSE This Advisory Circular (AC) provides guidance to service providers on safety risk assessment and mitigation. 2. REFERENCES Civil Aviation (SMS) Regulations Other related Tanzania
More informationA RISK ASSESSMENT STANDARD FOR EQUIPMENT FOR USE IN POTENTIALLY EXPLOSIVE ATMOSPHERES: THE RASE PROJECT
A RISK ASSESSMENT STANDARD FOR EQUIPMENT FOR USE IN POTENTIALLY EXPLOSIVE ATMOSPHERES: THE RASE PROJECT Dr. R.L. Rogers, Dr.-Ing. B. Broeckmann Inburex GmbH, 59067 Hamm, Germany N. Maddison Inburex (UK)
More informationTOWARDS A MORE SECURE ATC VOICE COMMUNICATIONS SYSTEM
TOWARDS A MORE SECURE ATC VOICE COMMUNICATIONS SYSTEM Tim H. Stelkens-Kobsch, Dr. Andreas Hasselberg, Dr. Thorsten Mühlhausen, Dr. Nils Carstengerdes, Michael Finke and Constantijn Neeteson, German Aerospace
More informationRisktec Training Catalogue 2016
Risktec Training Catalogue 2016 Asset Integrity Risk Management The purpose of the course is to provide an in-depth understanding of the ways to manage major incident risk throughout the asset lifecycle,
More informationENTERPRISE RISK MANAGEMENT FRAMEWORK
ENTERPRISE RISK MANAGEMENT FRAMEWORK COVENANT HEALTH LEGAL & RISK MANAGEMENT CONTENTS 1.0 PURPOSE OF THE DOCUMENT... 3 2.0 INTRODUCTION AND OVERVIEW... 4 3.0 GOVERNANCE STRUCTURE AND ACCOUNTABILITY...
More informationStockholm Control Requirements
Stockholm Control Requirements Information and learning objectives VACCSCA By Martin Loxbo Reworked by Daniel Edvardsson Study Questions by Håkan Schulz September 2010 Version 2 1 Introduction Controllers
More informationQuality Risk Management Tools Quality Risk Management Tool Selection When to Select FMEA: QRM Tool Selection Matrix
Quality Risk Management Tools Quality Risk Management Tool Selection When to Select FMEA: QRM Tool Selection Matrix 26 Quality Risk Management Tools The ICH Q9 guideline, Quality Risk Management, provides
More informationThe Total Economic Value. Its application to the Single European Sky 2nd Reference Period
The Total Economic Value Its application to the Single European Sky 2nd Reference Period 1. The idea of Total Economic Value. The Total Economic Value (TEV) is a term introduced officially into the Single
More informationThe need for Safety Intelligence based on European safety data analysis
The need for Safety Intelligence based on European safety data analysis Rachel Daeschler Head of Safety Intelligence and Performance OPTICS Workshop, 29 April 2015 Content Introduction to EASA Safety Intelligence
More informationAnnex to Decision 2013/008/R
Annex to Decision 2013/008/R Annex to Decision 2012/007/R of the Executive Director of the Agency of 19 April 2012, on Acceptable means of compliance and guidance material to Commission Regulation (EU)
More informationWind Turbine Risk. Dr Phillip Bratby
Wind Turbine Risk Dr Phillip Bratby Introduction The Government has very little to say about the safety of wind turbines and the risks they pose to people. The Companion Guide to PPS22 (Planning Policy
More informationProcess Safety Management Training
IHS OPERATIONAL EXCELLENCE & RISK MANAGEMENT Process Safety Management Training Leverage state-of-the-art resources and practical knowhow to learn about proven management system concepts and techniques.
More information140.01.3 REQUIREMENTS OF SAFETY MANAGEMENT SYSTEM
SA-CATS 140 Safety management system List of technical standards 140.01.3 REQUIREMENTS OF SAFETY MANAGEMENT SYSTEM 1. Minimum standards for the safety management system 140.01.3 REQUIREMENTS OF A SAFETY
More informationA System-safety process for by-wire automotive systems
A System-safety process for by-wire automotive systems Steer-by-wire and other by-wire systems (as defined in this article) offer many passive and active safety advantages. To help ensure these advantages
More informationGREEN PAPER. on the insurance of natural and man-made disasters
EUROPEAN COMMISSION Strasbourg, 16.4.2013 COM(2013) 213 final GREEN PAPER on the insurance of natural and man-made disasters Comments from the Danish Financial Supervisory Authority EN EN (1) (1) What
More informationChicago Center Fire Contingency Planning and Security Review
Chicago Center Fire Contingency Planning and Security Review Background In the early morning hours of September 26, 2014, the Federal Aviation Administration s (FAA) Chicago Air Route Traffic Control Center
More informationChange Impact analysis
1 Change Impact analysis and the safety standard IEC 61508:2010 series Author and presenter: Thor Myklebust SINTEF ICT Authors: Tor Stålhane, IDI NTNU Geir Hanssen, SINTEF ICT Børge Haugset, SINTEF ICT
More informationFrom patchwork to network:
From patchwork to network: Implementing the Single European Sky July 2011 The ATM crunch: after the liberalization of air traffic in 1990s There was an unprecedented increase of delays Why? Ageing technologies
More information3rd Nordic Conference of Computational Linguistics NODALIDA 1981 149
149 H a i m e Ruus I n s t i t u t f o r n o r d i s k f i l o l o g i K ø b e n h a v n s U n i v e r s i t e t O R D B Ø G E R F O R F R E M T I D E N I m i d t e n a f d e t t y v e n d e å r h u n
More information4 Keys to Driving Results from Project Governance
THOUGHT LEADERSHIP WHITE PAPER In partnership with Agile or Waterfall? 4 Keys to Driving Results from Project Governance You can t swing a project manager these days without hitting the debate of Agile
More informationAssessment of changes to functional systems in ATM/ANS and the oversight thereof
Assessment of changes to functional systems in ATM/ANS and the oversight thereof Entry Point North Seminar: The changing landscape of ATM Safety Malmo, 26 th -27 th May 2015 Jose L Garcia-Chico Gomez ATM/ANS
More informationOPERATIONAL RISK ASSESSMENT FOR AIRSPACE PLANNING
OPERATIONAL RISK ASSESSMENT FOR AIRSPACE PLANNING Karim Mehadhebi Direction des Services de la Navigation Aérienne karim.mehadhebi@aviation-civile.gouv.fr Toulouse, France Abstract ICAO policy requires
More information